Project Networks
Two Approaches• Activity-on-Arrow (AOA): Uses an arrow to depict an
activity • Activity-on-Node (AON): Uses a node to depict an
activity
![Page 2: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/2.jpg)
Activity on Arrow (AOR)Activities are
shown by ArrowLength of Arrow may show relative time to
complete tasks
Nodes show where activities end and begin in
sequence.The starting node for an
activity is the activity’s “i-node,” the
ending node is the “j-node.
Task A Task B Task C
Task DTask
E
Each project has a starting “i-node” and
ending “j-node”
![Page 3: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/3.jpg)
Activity on Arrow (AOR)
Task A Task B Task C
Task DTask
E
![Page 4: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/4.jpg)
Activity on Node (AON)
Start
Task A
Task B
Task E
Task C
Task D
End
![Page 5: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/5.jpg)
Activity on Node (AON)Activities are show in nodes or
boxes
Start
Task A
Task B
Task E
Task C
Task D
End
Project Has a Start and an
End
Task C is a predecessor to Task E and a
successor to Task A
Arrow show dependencies. Task D can’t start until both
Task A and B have completed
![Page 6: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/6.jpg)
Project Networks
BTask
CTask
DTask
ETask
FTask
ATask
![Page 7: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/7.jpg)
• Networks typically flow from left to right.• An activity cannot begin until all of its
preceding activities are complete.• Arrows indicate precedence and can cross
over each other.• Identify each activity with a unique
identifier; this identifier must increment (1.2.3, A,B,C, etc.) as the network proceeds.
• Looping is not allowed.• Conditional statements are not allowed.• Use start and stop nodes.
Project Networks Rules
![Page 8: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/8.jpg)
• Terminology:
A
C
B D
Constructing a Project Network
• Parallel (concurrent) activities: Activities that can occur independently and, if desired, at the same time.• Merge activity: an activity that has two or more preceding activities on which it depends.
• Activity: an element of theproject that requires time.
Time
![Page 9: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/9.jpg)
• Terminology B
D
A C
Constructing a Project Network (cont’d)
• Burst activity: an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it).
• Milestone: a point in time when an activity is started or completed. It does not consume time.
Q
![Page 10: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/10.jpg)
Project Networks
BTask
CTask
DTask
ETask
FTask
ATask
![Page 11: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/11.jpg)
Project Networks
BTask
CTask
DTask
ETask FTask
ATask
![Page 12: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/12.jpg)
= Early StartES
Time-Related Task Properties
= Early FinishEF = Late StartLS = Late FinishLF = Slack or FloatSL
= Duration
DRATask
![Page 13: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/13.jpg)
Tasks
ES EF
LS LF
SLA
DR
![Page 14: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/14.jpg)
A
4
Project Networks
C
3
B
8
D
2
E
3
F
10
Critical PathES ID EFSLLS DR LF
![Page 15: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/15.jpg)
Longest Path through the project network (not the path with the most number of tasks, but the one that takes the longest).
=Any delay of a task on the critical path will delay the entire project. PM needs to watch=Tasks with zero slack=
Critical Path
![Page 16: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/16.jpg)
A
4
Project Networks
C
3
B
8
D
2
E
3
F
10
A-B-D-F 4+8+2+10 = 24A-C-E-F 4+3+3+10 = 20
ES ID EFSLLS DR LF
![Page 17: Project networks](https://reader036.vdocument.in/reader036/viewer/2022070515/587b7e0e1a28ab9d448b4a57/html5/thumbnails/17.jpg)
A
4
Project Networks
C
3
B
8
D
2
E
3
F
10
A-B-D-F 4+8+2+10 = 24A-C-E-F 4+3+3+10 = 20
ES ID EFSLLS DR LF