project of the month: desert steel erection speed-up · the contractual deadline for completed...

5
subscribe contact us advertise industry jobs events FAQ Welcome Patty | Your Account | logout » share: more » print email Slide Show Photo: SME Steel Contractors/Michael Moore ----- Advertising ----- Text size: A A comment Project of the Month: Desert Steel Erection Speed-Up 08/13/2009 By Scott Lewis Doubling up in Las Vegas usually means doubling the size of your bet. At the new terminal at McCarran International Airport, the steel erector’s detailing subcontractors doubled the number of staff working on the project. That and other measures other measures paid off big. Terminal 3 is expected to open in mid-2012 and will cost approximately $2.4 billion. It will span 1.9 million square feet, and include 14 gates and a multistory parking garage. The Terminal’s frame, 300 ft wide and a half mile long, rose from the desert floor this summer. General contractor Perini Building Co., Framingham, Mass. is obligated to project milestones in order to avoid financial penalties. According to Derek Bamberry, project manager with steel fabricator and erector SME Steel, “Perini wanted to accelerate the steel erection and concrete work to gain some time” on the project. The contractual deadline for completed steel erection is October, 2009. To gain some breathing room on the overall project, Perini laid out a five-month erection schedule for SME, which is based in West Jordan, Utah, beginning in March and ending in August. Given the scale of the project, that is “not a lot of time to fabricate the steel, which involves over 200,000 shop drawings,” says Bamberry. One of our biggest problems was getting drawings approved by all the project members. SME submitted drawings to Perini. The chain of approval then ran from owner’s representative Bechtel Infrastructure, to architect PGA and engineer Walter P. Moore and then back to Bechtel for final review. All the approvals needed doubled the typical approval time to 60 days. “Because of the compressed schedule, our detailers doubled the number of people they had on this project, with 60 to 70 detailers working at the peak,” Bamberry said. The 17,000 steel components were fabricated in five shops. SME used their plants in Utah and Idaho, while their fabrication partner, Hirschfeld Steel Group LP, San Angelo, Texas, parcelled out its work to their three plants in Texas. The plants delivered 15 to 20 truckloads of steel each week to each of the four erection teams. Each fabricator worked with a separate detailer — SME used Steel Systems Engineering, Sherman Oaks, Calif., while Hirschfeld used Pro Draft Inc., Surrey, B.C. By carefully insuring that elements were delivered according to erection sequence, the project team avoided storing steel at the site until it was needed by each crane crew. Good logistics coordination, and having lots of room available for steel shakedown and handling, also contributed. The slowdown that hit casino and commercial construction in Las Vegas worked to SME’s advantage as well. “Lots of other projects in Las Vegas were put on hold,” says Bamberry “Seven or eight hundred local ironworkers were on the out of work list. At our peak we employed 165 ironworkers, with 120 our normal staffing for four crews.” Ironworkers Local 433 organizer Darrell Fagg backed that up. “The work on CityCenter project was slowing down at that time, so the Terminal 3 job came along at a perfect time.” Erection topped out June 3rd, when the photos you see in the slide show were taken. Bamberry estimates that erection will be completed this month, well ahead of the October deadline. “We expect to beat our original internal schedule by six weeks.” ----- Advertising ----- This week's content Archive Subscribe to ENR Order back issues Manage Subscription Most Viewed on ENR.com Italians Finalize Design for World's Longest Suspension Bridge An Unprecedented 11 Partners Propel Integrated Project Delivery at Sutter's New California Hospital Hot-Rod Trencher Still Draws the Crowds Most Commented On Structural Engineers Need Separate Licensing A Cautionary Digital Tale of Virtual Design and Construction Video SUBSCRIBE TODAY & receive immediate web access Search our site: INFRASTRUCTURE BLDGS BIZ MGMT POLICY EQUIPMENT PEOPLE MULTIMEDIA OPINION TECH EDUCATION ECONOMICS TOP LISTS REGIONS TRANSPORTATION ENVIRONMENT POWER & INDUSTRIAL WATER & DAMS REBUILDING JAPAN GULF OIL SPILL

Upload: ngominh

Post on 11-Apr-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

subscribe contact us advertise industry jobs events FAQ Welcome Patty | Your Account | logout »

share: more » print email

Slide Show

Photo: SME Steel Contractors/Michael Moore

----- Advertising -----

Text size: A A

comment

Project of the Month: Desert Steel Erection Speed-Up08/13/2009

By Scott Lewis

Doubling up in Las Vegas usually means doubling the size of your bet. At the new terminal at McCarran InternationalAirport, the steel erector’s detailing subcontractors doubled the number of staff working on the project. That and othermeasures other measures paid off big.

Terminal 3 is expected to open in mid-2012 and will costapproximately $2.4 billion. It will span 1.9 million squarefeet, and include 14 gates and a multistory parkinggarage.

The Terminal’s frame, 300 ft wide and a half mile long,rose from the desert floor this summer. General contractorPerini Building Co., Framingham, Mass. is obligated toproject milestones in order to avoid financial penalties.According to Derek Bamberry, project manager with steelfabricator and erector SME Steel, “Perini wanted toaccelerate the steel erection and concrete work to gainsome time” on the project.

The contractual deadline for completed steel erection isOctober, 2009. To gain some breathing room on theoverall project, Perini laid out a five-month erectionschedule for SME, which is based in West Jordan, Utah,beginning in March and ending in August. Given the scaleof the project, that is “not a lot of time to fabricate thesteel, which involves over 200,000 shop drawings,” saysBamberry.

One of our biggest problems was getting drawingsapproved by all the project members. SME submitteddrawings to Perini. The chain of approval then ran fromowner’s representative Bechtel Infrastructure, to architectPGA and engineer Walter P. Moore and then back toBechtel for final review. All the approvals needed doubledthe typical approval time to 60 days.

“Because of the compressed schedule, our detailersdoubled the number of people they had on this project,with 60 to 70 detailers working at the peak,” Bamberrysaid.

The 17,000 steel components were fabricated in fiveshops. SME used their plants in Utah and Idaho, whiletheir fabrication partner, Hirschfeld Steel Group LP, SanAngelo, Texas, parcelled out its work to their three plantsin Texas. The plants delivered 15 to 20 truckloads of steel

each week to each of the four erection teams. Each fabricator worked with a separate detailer — SME used SteelSystems Engineering, Sherman Oaks, Calif., while Hirschfeld used Pro Draft Inc., Surrey, B.C.

By carefully insuring that elements were delivered according to erection sequence, the project team avoided storingsteel at the site until it was needed by each crane crew. Good logistics coordination, and having lots of room availablefor steel shakedown and handling, also contributed.

The slowdown that hit casino and commercial construction in Las Vegas worked to SME’s advantage as well. “Lots ofother projects in Las Vegas were put on hold,” says Bamberry “Seven or eight hundred local ironworkers were on theout of work list. At our peak we employed 165 ironworkers, with 120 our normal staffing for four crews.”

Ironworkers Local 433 organizer Darrell Fagg backed that up. “The work on CityCenter project was slowing down atthat time, so the Terminal 3 job came along at a perfect time.”

Erection topped out June 3rd, when the photos you see in the slide show were taken. Bamberry estimates that erectionwill be completed this month, well ahead of the October deadline. “We expect to beat our original internal schedule bysix weeks.”

----- Advertising -----

This week's content

Archive

Subscribe to ENR

Order back issues

Manage Subscription

Most Viewed on ENR.comItalians Finalize Design for World's Longest SuspensionBridge

An Unprecedented 11 Partners Propel IntegratedProject Delivery at Sutter's New California Hospital

Hot-Rod Trencher Still Draws the Crowds

Most Commented OnStructural Engineers Need Separate Licensing

A Cautionary Digital Tale of Virtual Design andConstruction

Video

SUBSCRIBE TODAY& receive immediate web access

Search our site:

INFRASTRUCTURE BLDGS BIZ MGMT POLICY EQUIPMENT PEOPLE MULTIMEDIA OPINION TECH EDUCATION ECONOMICS TOP LISTS REGIONS

TRANSPORTATION ENVIRONMENT POWER & INDUSTRIAL WATER & DAMS REBUILDING JAPAN GULF OIL SPILL

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Project of the Month: McCarran Airport Terminal 3

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Las Vegas Airport Terminal 3 – 18,000 tons of structural steel.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Four raising gangs hoisted more than 16,000 pieces of steel intoplace.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Five beams being hoisted in mid-air.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Architecturally exposed structural steel painted gray and white.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Eighty truckloads of steel from five fabrication shops arrived on siteevery week.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

The project had the pick of Las Vegas’s best ironworkers.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Safety standards for ironworkers were rigidly enforced.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Topping out portrait of erection crew, members of Las VegasIronworkers Local 433.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window

Photo: SME Steel Contractors/Michael Moore

Desert Steel Erection Speed-Up

Rendering of completed terminal.

View Related Story

1 2 3 4 5 6 7 8 9 10

Close window