Page 1: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

PROJECT PLANNING ACTIVITIES

“This is a nice pieceof Rez! What canwe build here?”

by: Capital Projects Management Department2018

From the:Economic & Community Development Unit

Navajo Nation Department of Justice2009

Page 2: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

After the community decides to proceed with a Construction Project, what needs to happen first – before we can even think about getting a contractor to build, the Project?

Hmm?

Page 3: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

Hey! Where you gonna

put us?

Page 4: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

Project Planning Activities (PPAs)!

Page 5: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

Who should do “PPAs”?

Page 6: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

PPAs should be performed primarily by Chapters,with the technical assistance of the CapitalProjects Management Department, the fundingagency that provided funds for your chapterProject, and/or some limited assistance from theLead Agency.

Page 7: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

Why are PPAsso important?

Page 8: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

Because all necessary PPAs mustbe completed before actualProcurement for a constructioncontract can be started!

Page 9: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

• REMEMBER THAT COMPLETION OFPPAs TAKES !

• Do not expect that the entire amount of funding available can be spent on the actual construction of the Project.

• Upon completion of design, the architect or engineer will have a better understanding of the costs and how the project will fit into your budget.

• You may need to scale down the original concepts and plans for the Project, given the funding limitations.

Page 10: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

What are PPAs?

Project Planning Activities!

Page 11: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

1. Secure land free and clear via land withdrawal or other method, factoring in utilities, access roads and additional acreage to be used if necessary.

“Naw, we can’t build it there, Gramma Bullygoatwill never sign the consent form.”

Page 12: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

2. Secure a comprehensive legal description of the sitefor the facility, including any existing land use rightsof other parties such as rights-of-way or othereasements, if any.

Page 13: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

3. Obtain land survey information, withcomprehensive site data. May need to contract with someone for this.

Page 14: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

4. Obtain evaluation of existing site conditions, anyand all site development requirements, subsoilinvestigation & test results, including soil andwater retention & drainage, fill requirements, anderosion control. May need to contract withsomeone for this.

Page 15: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

5. Determine building & site material requirements and all required quality construction standards, quality assurance and quality control requirements. May need to contract with someone for this.

Hey guys! Are you sure this building is gonna stand up to

these Reservation Winds? Remember what happened at

McDonalds!

Page 16: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

6. Take into account any desired aestheticconsiderations for the building. Is the designcompatible with existing facilities, if any?

7. Make a description of planned and potentialuses for the proposed facility, the conceptualcriteria for project, and a schematic design anddrawing.

“Don’t forget about me!”

Page 17: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

8. Determine needs for furniture, fixtures, and any special equipment.

9. Determine electrical, HVAC, plumbing/fresh & waste water/septic system requirements.May need to contract with or hire someone for these.

Page 18: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

10. Determine the cost for all phases of the project; available and projected funding; budget estimates including available funding.

11. Determine schedules,milestones, critical dates.Again, may need to contract with, or hire someone for these tasks.

Page 19: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

12. Determine what special codes, regulations,ordinances, statutes, and permittingrequirements apply to the project.Child daycare? Food Service? Don’t forget it should be handicapped accessible.

Page 20: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

13. Determine the availability and location of all utilities, any additional land use necessary for utilities infrastructure, and what parties will have responsibility for the costs of utilities.

Page 21: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

14. Determine necessary turnouts, access roads, parking and landscaping requirements.

Are we there yet?

Page 22: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

16. Determine what existing contracts, if any, are to be utilized . . . . .

15. Determine any future expansion requirements.

Page 23: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

17. Do your best “due diligence” to find out if there are other applicable requirements or considerations that must be taken into account for the project.

Page 24: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

Good News!Some of the requirements on the list will not apply to your project if your project if your project does not involve new land disturbance. Use your best judgment to determine which items on the list apply to your project; and if in doubt, ask!

Remember:• all items on the list must be fully completed before

procurement for construction can begin• CPMD will determine the “project delivery method” to use

for your project” (this is part of procurement)• chapters and programs must consult with CPMD before

publishing any solicitation for a project

Page 25: PROJECT PLANNING ACTIVITIEScpmd.nndcd.org/uploads/FileLinks/6db72b8bcc8849da99cf7... · 2018. 6. 22. · 1. Secure land free and clear via land withdrawal or other method, factoring

For further assistance or any questions regarding PPAs, please contact your CPMD, or the funding agency that provided funds for the Project.