project progress report april 12, 2010 - anchorage, alaska · stakeholder survey result 52...

16
Project Progress Report April 12, 2010 Seong Dae Kim, Ph.D. Gary Kretchik, PMP Donghwoon Kwon University of Alaska Anchorage

Upload: others

Post on 20-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Project Progress ReportApril 12, 2010

Seong Dae Kim, Ph.D.Gary Kretchik, PMPDonghwoon KwonUniversity of Alaska Anchorage

Page 2: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Background

The motivation for this project is to identify and rank the freight movement problem areas in the Anchorage area.

Project Management Department Slide 2 of 20

Page 3: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Scope of Work The study consisted of three deliverable modules

which progressively feed into one another. Database development using subjective and

objective criteria. End result is a comprehensive prioritization list of

freight infrastructure projects.

Project Management Department Slide 3 of 20

Page 4: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Subjective Inputs Defined as those inputs which have no numerical value, it is the

most difficult to quantify. Stakeholder values are the main component of inputs. On-line survey was used to gain stakeholder input.

Project Management Department Slide 4 of 20

Page 5: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Project Management Department Slide 5 of 20

Page 6: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Objective Inputs

Crash Data Traffic Volumes

Project Management Department Slide 6 of 20

Page 7: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Project Flowchart

Project Management Department

Anchorage Freight movement Survey

Export Data to Excel Spreadsheet

Data Entered to Charts

Update Data on Map and

Website

Slide 7 of 20

Page 8: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Project Management Department

Draft Online Stakeholder Survey

Slide 8 of 20

Page 9: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Project Management Department

EXAPMLE Table before ranking

EXAMPLE Table after ranking

Slide 9 of 20

Page 10: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Personnel change Dr. Ra’s leave for this semester Graduation and relocation of Harrison Yeoh Personnel change was inevitable and it caused delay of the project progress. New members

Seong Dae Kim, Ph.D. Lead the project

Gary Kretchik, PMP Analyze the survey result Prepare final report and presentation Review the website and the ranking system

Donghwoon Kwon Input survey result into database Design ranking system model Develop website to show the prioritization on the map

Project Management Department Slide 10 of 20

Page 11: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Works completed Collection of crash data Literature search Stakeholder surveys using Survey Monkey

Project Management Department Slide 11 of 20

Page 12: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Works to be completed Analyze the survey result Input survey result into database Design ranking system model Develop website with map Review the website and the ranking system model Prepare final report & presentation and update in

response to feedback

Project Management Department Slide 12 of 20

Page 13: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides

the transportation service of truckload 52.2% of responders are not a freight driver 29.5% of responders drive single-trailer tractor

Project Management Department Slide 13 of 20

Page 14: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Stakeholder survey result (cont’d)

Area Problem? Type of problemOcean Dock Road and Terminal Road intersection 34.1% road congestion (54.2%)Industrial Area circulation and access area 34.2% turning radius (36.8%)School Bus storage area 13.9% road congestion (36.8%)3rd Avenue and Ingra/Gambell area 54.3% road congestion (50.0%)Ocean Dock alignment near the Port entrance 31.4% road congestion (84.6%)3rd Avenue: Post Road and Reeve Blvd 45.5% road congestion (50.0%Lake Otis Parkway and Tudor Road 71.9% road congestion (84.6%)Dowling Road: New Seward Hwy to Lake Otis Pkwy 51.6% turning radius (77.8%)International Airport Road and Postmark Drive 3.2% merge lanes (50.0%Ocean Dock Railroad Crossings 43.3% road congestion and poor signage (43.8%)C Street and 5th/6th Avenue Intersection 43.3% road congestion (72.2%)Lake Otis Parkway: Debarr Road to Northern Lights Blvd 40.0% road congestion (53.3%)West Northern Lights Blvd and Wisconsin Street intersection 16.7% road congestion (37.5%)C Street/Potter/64th Ave intersections 33.3% road congestion (50.0%)North C Street and Ocean Dock road Intersection (i.e. Multiple RR Crossings) 40.0% road congestion (41.7%)Ocean Dock road access and crossing from Port to Terminal Road 26.7% road congestion (55.6%)C Street and International Airport Road intersection 17.2% road congestion (50.0%)New Seward Hwy and O’Malley Interchange 41.4% turning radius (53.3%)C Street: Tudor Road to 36th Avenue Northbound 31.0% road congestion and turning radius (50.0%)Postmark Drive and Point Woronzof/West Northern Lights Blvd Intersection 10.3% road congestion (40.0%)

Project Management Department Slide 14 of 20

Page 15: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Stakeholder survey result (cont’d) Most problem types are road congestion and turning radius. Some of the candidate areas need more attention than other areas. The respondents are not necessarily truck drivers Need more clear definitions

E.g. Freight driver vs. commercial vehicle driver Causal relationship of problem types

Problem types in the questions are not exclusive. Some problem types are the caused by other problem types

E.g. ‘Road congestion’ can be caused by ‘merge lanes,’ ‘turning radius,’ etc. Need more information as to what is specifically wrong with each

problem they perceive.

Project Management Department Slide 15 of 20

Page 16: Project Progress Report April 12, 2010 - Anchorage, Alaska · Stakeholder survey result 52 responses by March 24, 2010 42.3% of responders said that their company provides the transportation

Project Management Department Slide 16 of 20