project progress report...fulton square report no. report #17 june 24, 2016 1.0 executive summary...
TRANSCRIPT
32 Market Avenue SW, Suite 200 ♦ Grand Rapids, MI 49503
Ph: 616. 464. 1740 ♦ Fx: 616. 464. 1742 ♦ www.OrionBuilt.com
Project Progress Report
Report No: 17
Report Period: June 20th thru June 24th, 2016
Fulton Square
Distribution:
Roger Rehkopf, John Wheeler,
Gary Postma, Ryan Wheeler,
John Boonstra, Corey Bixby,
Deb Filipiak
Project Manager: DuWayne Johnson
Superintendent: Kyle Marchand
Report Date: June 24th, 2016
Fulton Square Report No. Report #17 June 24, 2016
Contents
1.0 Executive Summary .......................................................................................................... 2
2.0 Summary of Work ........................................................................................................... 2-3
2.0 Work Completed & Two Week Look-Ahead ....................................................... 2
2.1 Schedule Impacts ................................................................................................ 3
2.2 Issues/Potential Delays/Potential Change Orders .............................................. 3
3.0 Health & Safety Report .................................................................................................... 3
4.0 Resources & Labor Report .............................................................................................. 4
5.0 Weather .......................................................................................................................... 4
6.0 Open RFI Log ................................................................................................................... 4
7.0 On Schedule? .................................................................................................................. 5
Notes ..................................................................................................................................... 5
Project Photos ....................................................................................................................... 6-7
Appendix
Fulton Square Report No. Report #17 June 24, 2016
1.0 Executive Summary
With two rain days this week, progress was a bit slower than normal. However, trades were
able to stay on schedule and continue significant work on Building A. Consumers Energy was
onsite to run primary power and set transformer for Building A.
2.0 Summary of Work The following work has been completed since the last report:
• Fair & Square Carpentry
o Completed roof truss installation and roof sheathing
o Completed wood top plate for all Steel Building B
o Completed South stairs in Building A
o Started floor truss hanger installation on Building B.
o Started Stair #3 for Building B
• Consolidated Electric
o Continued Electrical Box out for Building A 2nd and 3rd Level Units.
• Tekton Masonry
o Completed masonry work above Mailroom Building A.
• Custom Steel
o Completed installation of structural steel for Building B.
o Completed installation fo brick relief angle on perimeter of Building B.
o Steel inspection performed and passed.
• J Stevens Roofing
o Started installation of Building A Roof
• MPH Plumbing
o Continued plumbing rough-in for Building A 2nd Floor.
Two Week Look-Ahead:
• J Stevens Roofing
o Complete Building A Roof
• Custom Steel
o Deliver and install brick relief angle/tube steel for Masonry stair towers
• Fair & Square
o Complete installation of floor truss hangers Building B.
o 2nd Floor trusses and sheathing Building B.
o Delivery and installation of 2nd Floor wall panels Building B.
• Consolidated Electric
o Continue electrical Rough-In Building A 3rd Floor due 7/8/16
• MPH Plumbing
o Continue plumbing rough-In Building A 3rd Floor due 7/8/16
• Progressive HVAC
o Start Building A mechanical rough-in 3rd Floor due 7/8/16
• Brigade Fire Protection
o Start Building A FP rough-in 3rd Floor due 7/8/16
Fulton Square Report No. Report #17 June 24, 2016
2.1 Schedule Impacts
The Project has lost # days since last report.
Item Description/Activity
Schedule
Start
Actual
Start
Delay
Days
1
2
3
4
5
6
7
8
Total lost days this report 0.00
Total lost days last report 0.00
Total lost days to date 0.00
2.2 Issues / Potential Delays / Potential Change Orders
Item Description Category
1 Bulletin #5 Issued for pricing from subcontractors Change Orders
2
3
4
5
6
7
8
3.0 Health & Safety Report / OSHA Visit
Item Accident / Incident Date Time Lost
1
2
3
4
5
Fulton Square Report No. Report #17 June 24, 2016
4.0 Resources & Labor Report
Item Trade / Designation
1 Orion Construction 40 hours
2 ThornApple Excavation 0 hours
3 B & B Concrete 0 hours
4 Custom Steel 19 hours
5 Tekton Masonry 72 hours
6 M.P.H. Plumbing 42 hours
7 Fair & Square 522 hours
8 Consolidated Electric 72 hours
9 Progressive HVAC 0 hours
10 J Stevens Roofing 50 hours
11 Brigade Fire Protection 3 hours
12
hours
Total hours this report 748 hours
Total hours last report 7,070.0 hours
TOTAL HOURS 7,818.0 hours
5.0 Weather
Day Date Description of Weather Event Low Temp Hi Temp Precipitation
Mon 6/20 Sunny-Humid 72 90
Tue 6/21 Overcast 62 86
Wed 6/22 Overcast 56 89
Thu 6/23 Overcast 59 85
Fri 6/24 Sunny 57 86
Sat
6.0 Open RFI
Item Description
1 RFI #21- Kitchen Electrical (In Progress)
2 RFI #22- Balcony Electrical Boxes (In Progress)
3
4
5
6
Fulton Square Report No. Report #17 June 24, 2016
7.0 On Schedule?
Anticipated Completion Date: December 22, 2016
Item Milestone Description Due Date
1 Building Permit Received 2/17/16
2 Project Actual Start Date 2/18/16
3 Project Date of Substantial Completion
4 Date of Occupancy
5 Weekly Subcontractor Meeting (date & time) Tues 11am
6 Bi-Weekly Owner/Architect/Contractor Meeting (date & time) Tues 11:30
7
8
9
10
11
12
13
14
15
NOTES:
Fulton Square Report No. Report #17 June 24, 2016
Project Photographs
Stairs in Building A Framing
Building A Framing above Water Room
West Elevation Framing Tyvek Completed
Stairs in Building B Framing
South Elevation Framing Completed
East Elevation Framing Tyvek Completed
Fulton Square Report No. Report #17 June 24, 2016
Project Photographs
MEP rough-ins Continue
Steel Relief angled welded in place
Roof Sheathing Completed
Wood top plate for steel completed
Building B Floor Truss Hanger installation
Roofing Installation Progress
Updated On: June 24, 2016
REQUEST FOR INFORMATION LOGID Current
Status
Priority Request Description Requested By Approval Authority Date Requested Date Response
Required
Date Response
Received
Notes
001 In Progress High Location of storm water leads Orion/ Thornapple Civil Engineer 03/08/16 03/10/16
No storm leads located along Carlton Ave as indicated on
drawings.
002 Closed Critical Foundation Dimension Issues Orion/ B&B Concrete Architect 03/14/16 03/14/16 03/17/16 USE ARCH DRAWING DIMENSIONS
003 Closed Medium First Floor Demising Wall Columns Orion/Standale Lumber Architect 03/15/16 03/21/16 03/25/16 Use Collumns Spec'd. Collumns will stick out in closets
004 Closed Medium Connection Details Orion/Standale Lumber Structural Engineer 03/15/16 03/21/16 03/25/16 See attached Sketchs within response
005 Closed Medium Multiple Framing Questions- Standale Panalization Pacakage Orion/Standale Lumber Structural Engineer 03/25/16 04/06/16 03/28/15 See RFI response for multiple answers
006 Closed Medium Foundation Details for Building A East walls Orion/ B&B Concrete Architect 03/30/16 04/06/16 03/31/16 Reissued Changed in Bulletin #1 Porch Sizes Reduced
007 Closed Medium Misc. Structural Steel Detail Questions Orion/Ludtke Architect 04/13/16 04/19/16 04/13/16
008 Closed Low Selection of Electrical cover plate colors Orion/ Consolidated Architect 04/29/16 05/16/16 04/29/16
009 Closed Medium Footing Schedule does not include F5.5 Footing Orion/B&B Concrete Structural Engineer 05/03/16 05/10/16 05/03/16 Updated Footing Schedule
010 Closed High Stair S2 wall schedule and MECH Room Wall Schedule Orion/ Tekton Masonry Architect 05/06/16 05/10/16 05/12/16
011 Closed Medium Brick Relief Angle Steel Exterior Fastening Orion/ Tekton Masonry Architect 05/06/16 05/13/16 05/12/16
012 Closed Medium Building A Interior Footing Details Orion/ B&B Concrete Structural Engineer 05/09/16 05/16/16 05/09/16 Updated Footing Detail w/ sketch
013 Closed Medium CMU Block Damproofing and Insulation Alternative Orion/ Tekton Masonry Architect 05/19/16 05/27/16 05/19/16 Approved Alternate CMU Block Insulation
014 Closed Medium Electronic strike on storefront doors Orion/Double O Architect 05/25/16 05/30/16 05/31/16 Provided door to place electric strike
015 Closed High Building A Framing Fastening Requirements Orion/ Fair & Square Structural Engineer 05/31/16 06/03/16 06/02/16 Provided fastening requirements and clarification
016 Closed Medium Patio Door Alternate Orion/ Double O Architect 06/06/16 06/13/16 06/06/16 Patio Door Alternate from Jeld-Wen Approved
017 Closed High Building B 2nd Floor Header Issue Orion/ Standale Lumber Architect 06/06/16 06/10/16 06/06/16 Cut Down header and fasten as directed in RFI Response
018 Closed Medium Unit Type G Header Issue Orion/ Standale Lumber Architect 06/06/16 06/10/16 06/06/16 Adjusted From H4 to H1 Header
019 Closed Medium Reflected Ceiling Plan 1st Floor Building A Orion Architect 06/08/16 06/15/16 06/15/16 Changed Framing in Bulletin #5
020 Closed Medium Kitchen Cabinets & Appliance Conflict Orion/ Lumbermans Architect 06/10/16 06/17/16 06/15/16 Changed Kitchen Layouts in Bulletin #5
021 In Progress Medium Kitchen Island Electrical Orion/ Consolidated Architect 06/20/16 06/24/16 Working on Potential Solutions
022 In Progress Medium Balcony Electrical and Framing Conflict Orion/ Consolidated Architect 06/20/16 06/24/16 Potential solution provided, Electrican confirming
Concept Design
Orion Construction
Fulton Square
General Contractor:
Project Name:
Architect:
32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503
(616) 464-1740 Office | (616) 464-1742 Fax Page 1 of 1
SUBMITTAL LOG UPDATED: June 24, 2016
0004 Concrete B&B Concrete 03 3000 Steel Reinforcement Drawings 3/4/2016 3/1/2016 3/3/2016 3/9/2016 3/10/2016 3/11/2016 REVIEWED W/COMMENTS NONE CLOSED
0008 Concrete B&B Concrete 03 3000 Mix Designs 03/07/16 3/5/2016 3/7/2016 3/11/2016 3/7/2016 3/7/2016 REVIEWED NONE CLOSED
0032 Masonry Tekton 04 20 00 Unit Block Masonry 4/15/16 4/26/2016 4/26/2016 5/4/2016 4/27/2016 4/28/2016 APPROVED NONE CLOSED
0015 Steel Ludtke Steel 05 Structural Steel Shop Drawings 03/22/16 3/23/2016 3/24/2016 4/4/2016 4/4/2016 4/4/2016 APPROVED AS NOTED NONE CLOSED
0015 Steel Ludtke Steel 05 Misc Steel Shop Drawings 03/22/16 3/23/2016 3/24/2016 4/4/2016 4/4/2016 4/4/2016 APPROVED AS NOTED MAKE CORRECTIONS NOTED CLOSED
0024 Carpentry Standale Lumber 06 17 53 Fabricated Wood Trusses Bld B 4/1/16 4/11/2016 4/11/2016 4/25/2016 4/13/2016 4/13/2016 RETURNED NONE CLOSED
0025 Carpentry Standale Lumber 06 17 53 Fabricated Roof Trusses Bld B 4/1/16 4/12/2016 4/12/2016 4/25/2016 4/13/2016 4/13/2016 RETURNED NONE CLOSED
0031 Carpentry Standale Lumber 06 17 53 Fabricated Roof Trusses Bld A 04/25/16 4/25/2016 4/26/2016 5/4/2016 5/6/2016 5/9/2016 REVIEWED W/COMMENTS NONE CLOSED
0033 Carpentry Standale Lumber 06 10 00 Wall Panels Bld A 4/6/16 4/6/2016 4/26/2016 5/4/2016 5/6/2016 5/9/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED
0034 Carpentry Standale Lumber 06 10 00 Wall Panels Bld B 4/6/16 4/6/2016 4/26/2016 5/4/2016 5/6/2016 5/9/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED
0016 Caulking Custom Caulking 07 90 00 Joint Protection 03/15/16 3/24/2016 3/25/2016 4/4/2016 4/1/2016 4/1/2016 RETURNED NONE CLOSED
0022 Concrete B&B Concrete 07 00 00 Elevator Pit Waterproofing 04/01/16 4/6/2016 4/6/2016 4/7/2016 4/7/2016 4/7/2016 APPROVED NONE CLOSED
0030 Insulation Randl Interiors 07 21 00 Thermal Insultation 04/18/16 4/18/2016 4/26/2016 5/3/2016 5/6/2016 5/9/2016 APPROVED NONE CLOSED
0028 Fireproofing Randl Interiors 07 81 00 Applied Fireproofing 04/18/16 4/18/2016 4/26/2016 5/3/2016 5/6/2016 5/9/2016 APPROVED AS NOTED NONE CLOSED
0027 EIFS Randl Interiors 07 24 00 Direct Exterior Finish System 04/18/16 4/18/2016 4/26/2016 5/3/2016 5/6/2016 5/9/2016 APPROVED AS NOTED NONE CLOSED
0002 Carpentry Double O Supply 088000 Insulated Glass 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0002 Carpentry Double O Supply Tubelite Entrances 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0002 Carpentry Double O Supply 087100 Aluminum Door Hardware 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0002 Carpentry Double O Supply Fire Rated Glass 2/23/16 2/23/16 2/23/2016 3/4/2016 2/24/2016 3/3/2016 RETURNED NONE CLOSED
0019 Carpentry Double O Supply 084113 Vinyl Windows and Patio Doors 2/23/16 3/8/2016 3/30/2016 4/8/2016 4/4/2016 4/4/2016 APPROVED AS NOTED MAKE CORRECTIONS NOTED CLOSED
0021 Carpentry Double O Supply 083100 Aluminum Doors & Storefront Windows 03/15/16 3/29/2016 3/30/2016 4/12/2016 4/5/2016 4/12/2016 REVIEWED W/COMMENTS NONE CLOSED
0021 Carpentry Double O Supply 083100 Aluminum Doors & Storefront Windows UPDATED COMMENTS 4/26/2016 NONE CLOSED
0026 Carpentry AOA 08113 1400 Hollow Metal and Wood Doors 4/1/16 4/18/2016 4/18/2016 4/25/2016 4/22/2016 5/11/2016 APPROVED AS NOTED NONE CLOSED
Division 05 Metals
Division 06 Wood, Plastics & Composites
Division 07 Thermal & Moisture Protection
Division 08 Openings
Fulton Sqaure
Division 03 Concrete
Division 02 Existing Conditions
Item No.Due From
A/E/ORequired Action
Due From
SubStatus
Ball in
Court Company
Rec'd From
Sub
Sent to
A/E/O
Revision
No.Spec #
Division 04 Masonry
Returned to
SubTrade Required Submittal Item
Rec'd from
A/E/O
32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503
(616) 464-1740 Office | (616) 464-1742 Fax
www.OrionBuilt.com
0038 Metal Panel Reliable Sheet 08 00 00 ACM Panels and Metal Coping 5/1/16 5/11/2016 5/11/2016 5/25/2016 5/26/2016 5/26/2016 REVIEWED W/COMMENTS APPROVAL CLOSED
0020 Painting DeMaat Bros. 099000 Paint 03/15/16 3/29/2016 3/30/2016 4/12/2016 4/4/2016 4/4/2016 APPROVED NONE CLOSED
0029 Gypboard Randl Interiors 09 2116-5113 Gypsum Board and ACT Ceiling 04/18/16 4/18/2016 4/22/2016 5/3/2016 5/26/2016 5/27/2016 REVIEWED W/COMMENTS NONE CLOSED
Carpet DeGraaf Interiors 09 68 00 Carpeting 06/01/16 6/15/2016 ORION
Interiors DeGraaf Interiors 09 72 00 Wall Coverings 06/01/16 6/15/2016 ORION
0007 Mailboxes Klosterman 10 55 00 Postal Specialties 03/10/16 3/4/2016 3/4/2016 3/16/2016 3/7/2016 3/31/2016 REVIEWED W/COMMENTS NONE CLOSED
0009 Bath Acessories Product Resources 10 28 00 Toilet Room Accessories 3/15/16 3/9/2016 3/9/2016 3/18/2016 3/21/2016 3/22/2016 APPROVED AS NOTED NONE CLOSED
0010 Bike Racks Product Resources 10 00 00 Bike Racks 3/15/16 3/9/2016 3/9/2016 3/18/2016 3/11/2016 3/11/2016 REVIEWED W/COMMENTS NONE CLOSED
0014 Signage Handicap Signs 10 00 00 Parking Lot Signage 03/15/16 3/16/2016 3/18/2016 3/25/2016 3/23/2016 3/31/2016 APPROVED AS NOTED NONE CLOSED
0006 Appliances General Electric 11 31 00 Residential Appliances 03/01/16 03/01/16 03/04/16 03/14/16 03/11/16 03/29/16 REVIEWED W/COMMENTS REVIEW CLOSED
0012 Casework Lumbermans 12 35 30 Casework Shop Drawings 03/15/16 3/16/2016 3/18/2016 3/23/2016 3/29/2016 3/29/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED
0013 Casework Lumbermans 12 35 30- 2.5 Countertop Shop Drawing 03/15/16 3/16/2016 3/18/2016 3/23/2016 3/29/2016 3/29/2016 REVIEWED W/COMMENTS MAKE CORRECTIONS NOTED CLOSED
0023 Elevator Kone 14 21 00 Electric Traction Elevator 04/01/16 4/6/2016 4/7/2016 4/18/2016 4/15/2016 4/15/2016 REVIEWED W/COMMENTS NONE CLOSED
042 Fire Protection Brigade 21 13 11 Building A Wet Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED
042 Fire Protection Brigade 21 13 11 Building B Wet Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED
042 Fire Protection Brigade 21 13 16 Building A Dry Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED
042 Fire Protection Brigade 21 13 16 Building B Dry Fire Protection 05/20/16 6/20/2016 6/20/2016 6/27/2016 6/21/2016 6/21/2016 RETURNED NONE CLOSED
0003 Plumbing M.P.H. 22 4000 WC-1 and WC-2 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 4000 Lav-1, Lav-2, and Lav-3 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 01 Plumbing M.P.H. 22 4000 Tub-1 and Tub-2 2/23/16 2/23/16 03/15/16 3/22/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 01 Plumbing M.P.H. 22 4000 SH-1, SH-2, and SH-3 2/23/16 2/23/16 03/15/16 3/22/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 4000 S-1, S-2, S-3 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 4000 SS-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 3300 EWC-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 0000 WB-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 0000 IM-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 3300 EWH-1 and EWH-2 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 0000 Expansion Tank 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 0000 SP-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 1119 TS-1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
0003 Plumbing M.P.H. 22 0000 OI- 1 2/23/16 2/23/16 2/23/16 3/9/2016 3/9/2016 3/29/2016 APPROVED AS NOTED NONE CLOSED
043 Plumbing M.P.H. 22 00 00 Submeters 2/23/16 6/20/2016 06/22/16 6/26/2016 FORWARDED TO A/E APPROVAL A/E
0037 Mechanical Progressive 23 00 00 Multiple (HVAC Package) 4/10/2016 4/21/2016 5/11/2016 5/25/2016 5/26/2016 5/26/2016 APPROVED AS NOTED NONE NONE
Division 09 Finishes
Division 10 Specialties
Division 22 Plumbing
Division 12 Furnishings
Division 14 Conveying Equipment
Division 11 Equipment
Division 23 HVAC
Division 21 Fire Protection
32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503
(616) 464-1740 Office | (616) 464-1742 Fax
www.OrionBuilt.com
0011 Electrician Consolidated 26 00 00Electrical Distribution (panelboards,
Meters, Load Centers)3/10/16 3/15/2016 3/16/2016 3/23/2016 4/15/2016 4/15/2016 REVIEWED W/COMMENTS NONE CLOSED
0017 Electrician Consolidated 26 09 26 Lighting Controls 3/10/16 3/29/2016 3/29/2016 4/8/2016 4/4/2016 4/4/2016 APPROVED AS NOTED NONE CLOSED
0018 Electrician Consolidated 26 29 51 Lighting Fixtures 3/10/16 3/29/2016 3/29/2016 4/8/2016 4/4/2016 4/4/2016 REVIEWED W/COMMENTS NONE CLOSED
0018 01 Electrician Consolidated 26 29 51 Missing Lighting Fixture 04/07/16 4/11/2016 4/11/2016 4/15/2016 4/12/2016 4/12/2016 REVIEWED NONE CLOSED
0039 Electrician Consolidated 27 05 28 Building A Tele-Low Voltage 05/01/16 5/17/2016 5/17/2016 5/31/2016 5/18/2016 5/19/2016 APPROVED NONE CLOSED
0040 Electrician Consolidated 27 05 28 Building B Tele- Low Voltage 05/01/16 5/17/2016 5/17/2016 5/31/2016 5/18/2016 5/19/2016 APPROVED NONE CLOSED
0035 Electrician Consolidated 28 31 00 Building A Fire Alarm System 05/01/16 5/11/2016 5/11/2016 5/25/2016 5/18/2016 5/19/2016 REJECTED-RESUBMIT NONE CLOSED
0035 R01 Electrician Consolidated 28 31 00 Building A Fire Alarm System 5/19/2016 5/25/2016 6/1/2016 6/1/2016 REJECTED-RESUBMIT NONE CLOSED
0035 R02 Electrician Consolidated 28 31 00 Building A Fire Alarm System 6/1/2016 6/7/2016 6/1/2016 6/2/2016 APPROVED NONE CLOSED
0036 Electrician Consolidated 28 31 00 Building B Fire Alarm System 05/01/16 5/11/2016 5/11/2016 5/25/2016 5/18/2016 5/19/2016 REJECTED-RESUBMIT NONE CLOSED
0036 R01 Electrician Consolidated 28 31 00 Building B Fire Alarm System 5/19/2016 5/25/2016 6/1/2016 6/1/2016 REJECTED-RESUBMIT NONE CLOSED
0036 R02 Electrician Consolidated 28 31 00 Building B Fire Alarm System 6/1/2016 6/7/2016 6/1/2016 6/2/2016 APPROVED NONE CLOSED
0001 Excavation Thornapple 310000 WCU, Geotextile, IB Pipe, etc.. 1/28/16 2/1/2016 2/1/2016 2/4/2016 2/5/2016 2/18/2016 APPROVED AS NOTED NONE CLOSED
0041 Fencing Fence Consultant 31 00 00 Wood Privacy Fence 06/09/16 6/9/2016 6/6/2016 6/14/2016 FORWARDED TO A/E APPROVAL A/E
Division 31 Site Improvements
Division 28 Electronic Safety and Security
Division 26 Electrical
Division 27 Communications
32 Market Avenue SW, Suite 200 | Grand Rapids, MI 49503
(616) 464-1740 Office | (616) 464-1742 Fax
www.OrionBuilt.com