Page 1: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Project Quality Management

Page 2: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design
Page 3: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

TOTAL QUALITY MANAGEMENT

BY

Engr. Dr. Attaullah Shah PhD (Civil Engg.) , MSc ( Str Engg.) , MBA , MA ( Eco) , MSc Envir design

BSc Civil Engg (Gold Medal) , Post Grad Dip in computer ( Gold medal)

Project Director Allama Iqbal Open University

Islaamabad [email protected]

[email protected]

Cell: +92-333-5729809

Tel:+92-51-9057212

Fax:+92-51-9250100

Page 4: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

What is quality? All those features of a product (or services)

which are required by the customer.

In this context, quality may include a number of Different attributes, such as:

Availability- can it be delivered when I want it? Reliability- will it work first time every time Responsibilities- will the supplier be reasonably

flexible

Page 5: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Competence- do the necessary skills and knowledge exist to perform the service?

Communication- can I contact the supplier easily and do they speak my language?

Credibility- do they inspire confidence?

Security- are their systems and procedures secure.

Page 6: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Why is quality important?

The effectiveness of quality managementhas been shown to be one of the mostimportant characteristics of successfulcompanies. In recent years quality hasbecome the key in determining manyorganizations’ position in respect of theircompetitive advantage. Improved quality canincrease revenue and reduce costs, since:

Page 7: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Better quality improves the perceived image of a product or service and makes customers more likely to buy it.

Higher demand should result in higher sales volume and higher profits.

Higher quality in manufacturing should result in lower unit costs, with economies of scale in production and selling.

Higher quality in manufacturing should result in lower waste and defective rates, which will reduce production cost.

The volume of customer complaints should fall, and warranty claims should be lower. This will reduce costs.

Better quality in production should result in shorter processing times and less capital equipment requirements.

Page 8: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

The cost of quality

A report into ‘ The effectiveness of the corporate overhead in British business ‘ by Develin & Partners (1989), estimates that the average cost of waste and mistakes in the UK represents 20% of controllable corporate overhead.

This includes the cost of ensuring and assuring quality, as well as the loss incurred when quality is not achieved. Quality costs can be classified as prevention cost, appraisal cost, internal failure cost and external failure cost.

Page 9: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Quality control

Quality control is the traditional approach

concerned with ensuring that actual quality,

as measured, meets the target or

benchmark standards that have been set. It

is concerned with maintaining quality

standards, rather than improving them and

involves:

Page 10: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Establishing quality standards for a product or service.

Establishing procedures and processes that ought to ensure that these quality standards are met in a suitably high number of cases (in other words, quality acceptance standards are established)

Monitoring actual quality

Taking control action in cases where actual quality falls below the standard.

Procedures for inspecting and checking the quality of bought – in material’s and production output.

Page 11: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

QUALITY ASSURANCEQuality assurance is the term used where a supplier

guarantees the quality of goods supplied and allows the customer access while the goods are being manufactured.

This is usually done through supplier quality assurance (SQA) officers, who control the specification of the goods supplied. Quality assurance may:

Page 12: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

save purchasers quality control and production costs as items can be passed unchecked straight to production. This can give large savings in cost and time inflow production, and can facilitate Just- in- Time (Jit) production.

help companies to identify and remove the causes for poor quality goods before production instead of waiting for the end result

be particularly useful where extensive sub-contracting work is carried out, such as in the motor industry.

Page 13: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

TOTAL QUALITY MANAGEMENT (TQM)

Origins, Evolution & key elements

Page 14: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

WHAT IS QUALITY?

Quality is “fitness for use”

(Joseph Juran)

Quality is “conformance to requirements”

(Philip B. Crosby)

Quality of a product or services is its ability to satisfy the needs and expectations of the customer

Page 15: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

WHAT IS QUALITY

FEDEX - “PERFORMANCE TO THE STANDARD EXPECTED BY THE CUSTOMER”

GENERAL SERVICES ADMINISTRATION - “MEETING THE CUSTOMER’S NEED THE FIRST TIME AND EVERY TIME”

BOEING - “PROVIDING CUSTOMERS WITH PRODUCTS AND SERVICES THAT CONSISTENTLY MEET THEIR NEEDS AND EXPECTATIONS”

Page 16: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

WHAT IS QUALITY

US DEPARTMENT OF DEFENSE - “DOING THE RIGHT THING RIGHT THE FIRST TIME, ALWAYS STRIVING FOR IMPROVEMENT, AND ALWAYS SATISFYING THE CUSTOMER”.

QUALITY CAN BE DEFINED IN TERMS OF THE AGENT. WHO IS THE JUDGE OF QUALITY?

Page 17: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

WHAT IS QUALITY QUALITY INVOLVES MEETING OR

EXCEEDING CUSTOMER EXPECTATIONS.

QUALITY APPLIES TO PRODUCTS, SERVICES, PEOPLE, PROCESSES, AND ENVIRONMENTS.

QUALITY IS AN EVER-CHANGING STATE (I.E., WHAT IS CONSIDERED QUALITY TODAY MAY NOT BE GOOD ENOUGH TO BE CONSIDERED QUALITY TOMORROW).

Page 18: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

SIX BASIC CONCEPTS OF TQM1. A COMMITTED AND INVOLVED

MANAGEMENT TO PROVIDE LONG-TERM TOP-TO-BOTTOM ORGANIZATION SUPPORT

2. AN UNWAVERING FOCUS ON THE COSTOMER, BOTH INTERNALLY AND EXTERNALLY.

3. EFFECTIVE INVOLVEMENT AND UTILIZATION OF THE ENTIRE WORK FORCE.

Page 19: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

SIX BASIC CONCEPTS OF TQM4. CONTINUOUS IMPROVEMENT OF

THE BUSINESS AND PRODUCTION PROCESS.

5. TREATING SUPPLIERS AS PARTNERS.

6. ESTABLISH PERFORMANCE MEASURES FOR THE PROCESSES.

Page 20: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

THE TOTAL QUALITY APPROACH TOTAL QUALITY IS AN APPROACH TO

DOING BUSINESS THAT ATTEMPTS TO MAXIMIZE THE COMPETITIVENESS OF AN ORGANIZATION THROUGH THE CONTINUAL IMPROVEMENT OF THE QUALITY OF ITS PRODUCTS, SERVICES, PEOPLE, PROCESSES AND ENVIRONMENTS.

Page 21: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

THE TOTAL QUALITY APPROACH

Customer focus

Page 22: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

THE TOTAL QUALITY APPROACHCHARACTERISTICS OF THE TOTAL QUALITY STRATEGICALLY BASED CUSTOMER FOCUS (INTERNAL AND

EXTERNAL) OBSESSION WITH QUALITY SCIENTIFIC APPROACH TO DECISION

MAKING AND PROBLEM SOLVING LONG-TERM COMMITMENT

Page 23: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

THE TOTAL QUALITY APPROACHTEAMWORK CONTINUAL PROCESS IMPROVEMENT EDUCATION AND TRAINING FREEDOM THROUGH CONTROL UNITY OF PURPOSE EMPLOYEE INVOLVEMENT AND

EMPOWERMENT

Page 24: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Evolution of Quality Management

Inspection

Quality Control

Quality Assurance

TQM

Salvage, sorting, grading, blending, corrective actions, identify sources of non-conformance

Develop quality manual, process performance data, self-inspection, product testing, basic quality planning, use of basic statistics, paperwork control.

Quality systems development, advanced quality planning, comprehensive quality manuals, use of quality costs, involvement of non-production operations, failure mode and effects analysis, SPC.

Policy deployment, involve supplier & customers, involve all operations, process management, performance measurement, teamwork, employee involvement.

Page 25: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Deming’s view of a production as a system

Consumer Research

Design & redesign

Receipt & test of materials

Suppliers, materials & equipment

Production, assembly, inspection

Distribution Consumers

Test of processes, machines, methods, cost

Page 26: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Improve Quality

Productivity improves

Provide jobs and more jobs

Deming’s Chain Reaction

Cost decreases because of less rework, fewer mistakes, fewer delays, snags, better use of machine time and materials

Stay in business

Capture the market with better quality and lower price

Page 27: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

PLAN

CHECK

DOACT

The Deming Cycle or PDCA Cycle

Plan a change to the process. Predict the effect this change will have and plan how the effects will be measured

Implement the change on a small scale and measure the effects

Adopt the change as a permanent modification to the process, or abandon it.

Study the results to learn what effect the change had, if any.

Page 28: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

W. Edwards Deming’s 14 Points

Create constancy of purpose towards improvement of product and services.

Adopt the new philosophy. We can no longer live with commonly accepted levels of delays, mistakes, defective workmanship.

Cease dependence on mass inspection. Require, instead, statistical evidence that quality is built in.

End the practice of awarding business on the basis of price tag.

1)

2)

3)

4)

Page 29: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

W. Edwards Deming’s 14 Points

Find problems. It is management’s job to work continually on the system.

Institute modern methods of training on the job.

Institute modern methods of supervision of production workers. The responsibility of foremen must be changed from numbers to quality.

Drive out fear that everyone may work effectively for the company.

5)

6)

7)

8)

Page 30: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Break down barriers between departments.

Eliminate numerical goals, posters and slogans for the workforce asking for new levels of productivity without providing methods.

Eliminate work standards that prescribe numerical quotas.

Remove barriers that stand between the hourly worker and his right to pride of workmanship.

9)

10)

11)

12)

W. Edwards Deming’s 14 Points

Page 31: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Institute a vigorous programme of education and retraining.

Create a structure in top management that will push everyday on the above 13 points.

13)

14)

W. Edwards Deming’s 14 Points

Page 32: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Deming’s System of Profound Knowledge

Appreciation for system

Knowledge about variation

Theory about knowledge

Knowledge of psychology

Page 33: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Joseph M. Juran and the Cost Of Quality

2 types of costs:

Unavoidable Costs: preventing defects (inspection, sampling, sorting, QC)

Avoidable Costs: defects and product failures (scrapped materials, labour for re-work, complaint processing, losses from unhappy customers

“Gold in the Mine”

Page 34: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

What is TQM?

Constant drive for continuous

improvement and learning.

Concern for employee

involvement and development

Management by Fact

Result FocusPassion to deliver customer value /

excellence

Organisation response ability

Actions not just words

(implementation)Process

Management

Partnership perspective (internal / external)

Page 35: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Learning

LEARNING AND TQM

Process Improvement

Quality Improvement

Customer Satisfaction

Shareholder Satisfaction

Employee Satisfaction

Page 36: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

BASIC PRINCIPLES OF TQM

Approach Management Led

Scope Company Wide

Scale Everyone is responsible for Quality

Philosophy Prevention not Detection

Standard Right First Time

Control Cost of Quality

Theme On going Improvement

Page 37: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

FOUR KEY PRINCIPLESFOUR KEY PRINCIPLES

•Measure quality so you can affect it

•Focus on a moving customer

•Involve every employee

•Think long term - Act short term

Page 38: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

THE CASE FOR QUALITY

1 Success of competitors who take quality seriously

2 Rising expectations of customers

3 Quality differentiates companies from the competition

4 Narrowing of supplier bases by quality conscious companies

.

Page 39: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

5 Growing evidence that growth in market share comes from sustained quality.

6 Cost advantages

7 High cost of catastrophic failure

8 Inspection poor substitute for right first time

THE CASE FOR QUALITY

Page 40: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

TQM IN CONSTRUCTION INDUSTRY

IMPLEMENTATION OF TQM RESULTED IN IMPROVED CUSTOMER SATISFACTION, REDUCED CYCLE TIMES, DOCUMENTED COST SAVINGS, AND MORE SATISFIED AND PRODUCTIVE WORK FORCES.

A TQM PROCESS IMPLEMENTED BY TEXAS INSTRUMENT (USA) HAS FOLLOWING OUTCOMES:

Page 41: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

THE TQM IN CONSTRUCTION INDUSTRY REWORK REDUCED FROM 11% TO

LESS THAN 1% OF PROJECT IMPROVED SAFTY AND HEALTH REDUCED WORKERS’

COMPENSATION INSURANCE, AND COMPLETION ON SCHEDULE.

Page 42: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

IS QUALITY A SOUND INVESTMENT?Year Company Stock Growth (Oct 94)1988 Motorola 373.0%1988 Westinghouse (CNFD) - 49.6%1989 Xerox (BPS) 75.9%1990 General Motors 1.6%1990 Federal Express 10.6%1990 IBM (IBM Rochester) - 34.9%1991 Selectron 526.9%1992 AT&T (UCS) 32.2%1992 AT&T (TSBU) 32.2%1992 Texas Instruments (DS&E) 106.8%1993 Zyta 8.4%1994 Eastman Chemical 18.5%

Total Stock Value £23016 (91.8% growth)Standard & Poor 500 Stock value £15911 (32.6% growth)Source: US Dept. of Commerce Study 1995

Page 43: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Project Quality management Project Quality Management processes include

all the activities of the performing organization that determine quality policies, objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken.

It implements the quality management system through the policy, procedures, and processes of quality planning, quality assurance, and quality control, with continuous process improvement activities conducted throughout, as appropriate.

Page 44: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design
Page 45: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Project Quality Management processes Quality Planning – identifying which quality standards

are relevant to the project and determining how to satisfy them.

Perform Quality Assurance – applying the planned, systematic quality activities to ensure that the project employs all processes needed to meet requirements.

8.3 Perform Quality Control – monitoring specific project results to determine whether they comply with relevant quality standards and identifying ways to

eliminate causes of unsatisfactory performance

Page 46: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Project Management and TQM Modern quality management complements project management.

For example, both disciplines recognize the importance of: Customer satisfaction. Understanding, evaluating, defining, and

managing expectations so that customer requirements are met. This requires a combination of conformance to requirements (the project must produce what it said it would produce) and fitness for use (the product or service must satisfy real needs).

Prevention over inspection. The cost of preventing mistakes is generally much less than the cost of correcting them, as revealed by inspection.

Management responsibility. Success requires the participation of all members of the team, but it remains the responsibility of management to provide the resources needed to succeed.

Continuous improvement. The plan-do-check-act cycle is the basis for quality improvement

Page 47: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Quality Planning: Tools and Techniques Cost-Benefit Analysis: Quality planning must consider cost-

benefits tradeoffs. The primary benefit of meeting quality requirements is less rework, which means higher productivity, lower costs, and increased stakeholder satisfaction.

Benchmarking involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.

Design of Experiments (DOE) is a statistical method that helps identify which factors may influence specific variables of a product or process under development or in production.

Cost of Quality (COQ) are the total costs incurred by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirements, and failing to meet requirements (rework).

Page 48: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Additional Quality Planning Tools Other quality planning tools are also often

used to help better define the situation and help plan effective quality management activities.

Page 49: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Quality Planning: Outputs Quality Management Plan describes how the project management team

will implement the performing organization’s quality policy. The quality management plan provides input to the overall project management plan and must address quality control (QC), quality assurance (QA),and continuous process improvement for the project.

Quality Metrics A metric is an operational definition that describes, in very specific terms, what something is and how the quality control process measures it. A measurement is an actual value.

Quality Checklists A checklist is a structured tool, usually component-specific, used to verify that a set of required steps has been performed. Checklists may be simple or complex.

Quality Baseline The quality baseline records the quality objectives of the project.

Project Management Plan (Updates) The project management plan will be updated through the inclusion of a subsidiary quality management plan

Page 50: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Assurance Quality assurance (QA) is the application of planned,

systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

Continuous process improvement provides an iterative means for improving the quality of all processes.

Continuous process improvement reduces waste and non-value-added activities, which allows processes to operate at increased levels of efficiency and effectiveness.

Page 51: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Assurance: Inputs, Tools & Techniques, and Outputs

Page 52: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Assurance: Tools and Techniques

Quality Planning Tools and Techniques The quality planning tools and technique.

Quality Audits A quality audit is a structured, independent review to determine

whether project activities comply with organizational and project policies, processes, and procedures.

The objective of a quality audit is to identify inefficient and ineffective policies, processes, and procedures in use on the project.

Quality audits may be scheduled or at random, and may be carried out by properly trained in-house auditors or by third parties, external to the performing organization.

Page 53: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Process AnalysisProcess analysis follows the steps outlined in

the process improvement plan to identify needed improvements from an organizational and technical standpoint.

Page 54: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Assurance: Outputs Requested Changes

Quality improvement includes taking action to increase the effectiveness and efficiency of the policies, processes, and procedures of the performing organization, which should provide added benefits to the stakeholders of all projects.

Recommended Corrective Actions Quality improvement includes recommending actions to increase the

effectiveness and efficiency of the performing organization.

Organizational Process Assets (Updates) Updated quality standards provide validation of the effectiveness and efficiency of

the performing organization’s quality standards and processes to meet requirements.

Project Management Plan (Updates)

Page 55: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Control Performing quality control (QC) involves monitoring specific project

results to determine whether they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.

Quality standards include project processes and product goals.

QC is often performed by a quality control department or similarly titled organizational unit.

The project management team should have a working knowledge of statistical quality control, especially sampling and probability, to help evaluate QC outputs.

Page 56: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Among other subjects, the team may find it useful to know the differences between the following pairs of terms:

Prevention (keeping errors out of the process) and inspection (keeping errors out of the hands of the customer).

Attribute sampling (the result conforms, or it does not) and variables sampling (the result is rated on a continuous scale that measures the degree of conformity).

Special causes (unusual events) and common causes (normal process variation).

Common causes are also called random causes. Tolerances (the result is acceptable if it falls within the range

specified by the tolerance) and control limits (the process is in control if the result falls within the control limits).

Page 57: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Control: Inputs, Tools & Techniques, and Outputs

Page 58: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Control: Tools and Techniques

Cause and Effect Diagram Cause and effect diagrams, also called Ishikawa diagrams or

fishbone diagrams, illustrate how various factors might be linked to potential problems or effects.

Page 59: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Control Charts A control chart's purpose is to determine whether or not a

process is stable or has predictable performance. Control charts may serve as a data gathering tool to show when

a process is subject to special cause variation, which creates an out-of-control condition.

Control charts also illustrate how a process behaves over time When a process is outside acceptable limits, the process should

be adjusted. The upper control limit and lower control limit are usually set at

+/- 3 sigma (i.e., standard deviation). Control charts can be used for both project and product life cycle

processes. An example of project use of control charts is determining whether cost variances or schedule variances are outside of acceptable limits (for example, +/- 10 percent).

Page 60: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design
Page 61: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Flowcharting Flowcharting helps to analyze how problems occur. A flowchart is a

graphical representation of a process. There are many styles, but all process flowcharts show activities, decision points, and the order of processing.

Flowcharts show how various elements of a system interrelate.

What and where quality problems might occur and, thus, can help develop approaches for dealing with them.

Page 62: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design
Page 63: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Histogram A histogram is a bar chart showing a distribution of variables. Each

column represents an attribute or characteristic of a problem/situation.

The height of each column represents the relative frequency of the characteristic. This tool helps identify the cause of problems in a process by the shape and width of the distribution.

Page 64: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Run Chart A run chart shows the history and pattern of variation. A run

chart is a line graph that shows data points plotted in the order in which they occur.

Run charts show trends in a process over time, variation over time, or declines or improvements in a process over time.

Trend analysis is performed using run charts. Trend analysis involves using mathematical techniques to forecast future outcomes based on historical results. Trend analysis is often used to monitor:

Technical performance. How many errors or defects have been identified, how many remain uncorrected?

•ost and schedule performance. How many activities per period were

completed with significant variances?

Page 65: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Scatter Diagram A scatter diagram shows the pattern of relationship between two

variables. This tool allows the quality team to study and identify the possible

relationship between changes observed in two variables. Dependent variables versus independent variables are plotted.

The closer the points are to a diagonal line, the more closely they are related.

Statistical Sampling Statistical sampling involves choosing part of a population of interest for

inspection (for example, selecting ten engineering drawings at random from a list of seventy five).

Appropriate sampling can often reduce the cost of quality control. There is a substantial body of knowledge on statistical sampling; in some application areas, it may be necessary for the project management team to be familiar with a variety of sampling techniques.

Page 66: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Inspection An inspection is the examination of a work product to

determine whether it conforms to standards. Generally, the results of an inspection include measurements. Inspections can be conducted at any level. For example, the

results of a single activity can be inspected, or the final product of the project can be inspected. Inspections are also called reviews, peer reviews, audits, and walkthroughs. In some application areas, these terms have narrow and specific meanings. Inspections are also used to validate defect repairs.

Page 67: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Defect Repair Review Defect repair review is an action taken by the

quality control department or similarly titled organization to ensure that product defects are repaired and brought into compliance with requirements or specifications.

Page 68: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Perform Quality Control: Outputs Quality control measurements represent the results of QC activities that are fed

back to QA. Validated Defect Repair

The repaired items are re inspected and will be either accepted or rejected before notification of the decision is provided

Quality Baseline (Updates) Recommended Corrective Actions Recommended Preventive Actions Requested Changes Recommended Defect Repair Organization Process Assets (Updates)

Completed checklists. Lessons learned documentation

Validated Deliverables Project Management Plan (Updates)

Page 69: Project Quality Management. TOTAL QUALITY MANAGEMENT BY Engr. Dr. Attaullah Shah PhD (Civil Engg.), MSc ( Str Engg.), MBA, MA ( Eco), MSc Envir design

Quality is a Journey, not a Destination