Project ‐ Quarterly Progress Report
Promoter’s Name : RAMKY WAVOO DEVELOPERS PVT.LTD.
Project Name : GRAND CORRIDOR
Project Registration No : No.TN/02/Building/0037/2019
Quarter Ending : JANUARY 2020.
A. Sales
Sl.
No.
Description No. Total Area
1. Plots/Flats Booked size wise (As given in Carpet Area
Statement while registering)
49 5684.362 Sq.m
2. Parking Slots 49
3. UDS Registered in Sq.m. 3 143.349
B. Construction
C. Details of Clearances
1. Completion Certificate No. ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (only CC No. in Text Format)
2. Compliance Report, if any (Kindly Specify) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)
3. Annual Audit Report of Special Account in Form 7 ‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)
D. Latest Photo with Date (Atleast from 2 angles) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)
Note: Report the above particulars under “Registered Projects” in www.tnrera.in
Sl.No. Description Block/Tower
No. Status
1
Compound Wall &
Foundation
ABC
Compound Wall :- 100 % of work has been completed,
Foundation :-
Pile Foundation Work 40 % has been Completed,
Balance Work In Progress
![Page 2: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/2.jpg)
Reg. No.TN/02/Building/0037/2019
PROJECT STATUS REPORT
JANUARY 20
![Page 3: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/3.jpg)
Views
![Page 4: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/4.jpg)
TYPE Area in Sq.ft No of Apt’s
No. of Apt’s Booked
A BLOCK
3 BHK /2T 1359-1436 566
3 BHK/3T 1491-1606 5615
TOTAL 11221
Project Details
Car park Details No. of Lots Booked
Total No. of Car Park Provided - A BLOCK
126 Nos
Covered Car Park 126 14
![Page 5: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/5.jpg)
TYPE Area in Sq.ftNo of
Apt’s
No. of Apt’s Booked
B BLOCK
3 BHK /2T 1343 - 1418 563
3 BHK/3T 1528 - 1558 565
TOTAL 112 8
Project Details
Car park Details No. of Lots Booked
Total No. of Car Park Provided – B BLOCK
126 Nos
Covered Car Park 126 9
![Page 6: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/6.jpg)
TYPE Area in Sq.ft No of Apt’s
No. of Apt’s Booked
C BLOCK
2 BHK /2T 1051 - 1159 132 20
TOTAL 132 20
Project Details
Car park Details No. of Lots Booked
Total No. of Car Park Provided – C BLOCK132 Nos
Covered Car Park 34 11
Open Car Park 98 6
Total No. of Car park Provided for Club House / Visitors 19 Nos 17
![Page 7: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/7.jpg)
Project Status,.
Compound Wall -100 % Completed
Pile foundation Works 40 % Completed, Balance Work in Progress
![Page 8: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/8.jpg)
Project Status,.
Compound Wall -100 % Completed
Pile foundation Works 40 % Completed, Balance Work in Progress
![Page 9: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/9.jpg)
Project Status,.
Compound Wall -100 % Completed
Pile foundation Works 40 % Completed, Balance Work in Progress
![Page 10: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/10.jpg)
Project Status,.
Compound Wall -100 % Completed
Pile foundation Works 40 % Completed, Balance Work in Progress
![Page 11: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/11.jpg)
Project Status,.
Compound Wall -100 % Completed
Pile foundation Works 40 % Completed, Balance Work in Progress
![Page 12: Project Quarterly Progress Report Promoter s Name : RAMKY ... · Compound Wall & Foundation ABC Compound Wall :-100 % of work has been completed, Foundation : - Pile Foundation Work](https://reader035.vdocument.in/reader035/viewer/2022062916/5ebc0f2f096cdb3c38792dbe/html5/thumbnails/12.jpg)
Project Status,.
Compound Wall -100 % Completed
Pile foundation Works 40 % Completed, Balance Work in Progress