RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 1 of 31 Project: RENAISSANCE HIGH SCHOOL FOR THE ARTS MODERNIZATION AND ADDITION DSA File No.: 19-H15 DSA Application No.: 03-116401 LBUSD Project No.: 9076-1112-681 GBA Project No.: 1401 DSA ADDENDUM NO. 1 Date: May 9, 2016 Owner: Long Beach Unified School District 2425 Webster Ave. Long Beach, CA 90810 Architect: Ghataode Bannon Architects LLP 760 W. 16th Street - Unit B Costa Mesa, CA 92627 (714) 665-8030 The clarifications, modifications, changes, additions, and/or deletions contained herein shall be incorporated within the construction documents for the project. Such information shall take precedence over that previously published. CHANGES TO THE SPECIFICATIONS: Item No. 1.1 Specification Reference: 00 01 10 TABLE OF CONTENTS Description: Replace the Table of Contents with the attached revised Table of Contents showing added sections 07 22 16 ROOF BOARD INSULATION, 07 22 19 ROOF INSULATION COVER BOARD, 22 11 29 PLUMBING SPECIALTIES, and 28 13 53.10 VIDEO INTERCOM SYSTEM

Upload: others

Post on 10-Jul-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 1 of 31

Project: RENAISSANCE HIGH SCHOOL FOR THE ARTS MODERNIZATION AND ADDITION DSA File No.: 19-H15 DSA Application No.: 03-116401 LBUSD Project No.: 9076-1112-681 GBA Project No.: 1401 DSA ADDENDUM NO. 1 Date: May 9, 2016 Owner: Long Beach Unified School District 2425 Webster Ave. Long Beach, CA 90810 Architect: Ghataode Bannon Architects LLP 760 W. 16th Street - Unit B Costa Mesa, CA 92627 (714) 665-8030 The clarifications, modifications, changes, additions, and/or deletions contained herein shall be incorporated within the construction documents for the project. Such information shall take precedence over that previously published. CHANGES TO THE SPECIFICATIONS: Item No. 1.1 Specification Reference: 00 01 10 TABLE OF CONTENTS Description: Replace the Table of Contents with the attached revised Table of

Contents showing added sections 07 22 16 ROOF BOARD INSULATION, 07 22 19 ROOF INSULATION COVER BOARD, 22 11 29 PLUMBING SPECIALTIES, and 28 13 53.10 VIDEO INTERCOM SYSTEM

TNishihira
Text Box
NOTE: THIS ADDENDUM IS CONSIDERED TO BE INCORPORATED INTO THE BID. YOU ARE NOT REQUIRED TO ACKNOWLEDGE THIS ON PAGE 14 OF THE BID DOCUMENTS YOU WILL TURN IN TO THE DISTRICT.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 2 of 31

Item No. 1.2 Specification Reference: 01 11 00 SUMMARY OF WORK Description: Replace specification section 01 11 00 SUMMARY OF WORK with

the attached revised section 01 11 00. Item No. 1.3 Specification Reference: 01 12 16 PHASING OF THE WORK Description: Replace specification section 01 12 16 PHASING OF THE

WORK with the attached revised section 01 12 16. Revise duration of Phase 2 Construction to 640 calendar days.

Item No. 1.4 Specification Reference: 01 25 00 SUBSTITUTION PROCEDURES Description: Delete specification section 01 25 00 SUBSTITUTION PROCEDURES

from the project.. Item No. 1.5 Specification Reference: 01 26 00 CONTRACT MODIFICATION PROCEDURES Description: Delete specification section 01 26 00 CONTRACT MODIFICATION

PROCEDURES from the project. Item No. 1.6 Specification Reference: 01 29 73 SCHEDULE OF VALUES PROCEDURES Description: Replace specification section 01 29 73 SCHEDULE OF VALUES

PROCEDURES with the attached revised section 01 29 73. Item No. 1.7 Specification Reference: 01 29 76 PROGRESS PAYMENT PROCEDURES Description: Replace specification section 01 29 76 PROGRESS PAYMENT

PROCEDURES with the attached revised section 01 29 76. Item No. 1.8 Specification Reference: 01 31 13 PROJECT COORDINATION Description: Replace specification section 03 31 13 PROJECT COORDINATION

with the attached revised section 03 31 13 to reflect the following change:

Add the following subsection 01 31 13.3.01.A.1: "1. Contractor shall be familiar with and refer to the provided

Existing Record Drawings when bidding, coordinating, and constructing the Work. It is the contractor's responsibility to be

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 3 of 31

familiar with the existing conditions depicted within said Existing Record Drawings and shall coordinate the demolition and new construction work accordingly."

Item No. 1.9 Specification Reference: 01 31 19 PROJECT MEETINGS Description: Replace specification section 01 31 19 PROJECT MEETINGS with

the attached revised section 01 31 19. Item No. 1.10 Specification Reference: 01 32 13 CONSTRUCTION SCHEDULE Description: Replace specification section 01 32 13 CONSTRUCTION SCHEDULE

with the attached revised section 01 32 13. Item No. 1.11 Specification Reference: 01 33 00 SUBMITTAL PROCEDURES Description: Replace specification section 01 33 00 SUBMITTAL PROCEDURES

with the attached revised section 01 33 00. Item No. 1.12 Specification Reference: 01 45 24 ENVIRONMENTAL IMPORT/EXPORT MATERIALS

TESTING Description: Replace specification section 01 45 24 ENVIRONMENTAL

IMPORT/EXPORT MATERIALS TESTING with the following attached new sections:

01 45 24 ENVIRONMENTAL IMPORT MATERIALS TESTING 01 45 25 ENVIRONMENTAL EXPORT MATERIALS TESTING Item No. 1.13 Specification Reference: 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY

CONTROLS Description: Replace specification section 01 50 00 CONSTRUCTION FACILITIES

AND TEMPORARY CONTROLS with the attached revised section 01 50 00.

Item No. 1.14 Specification Reference: 01 71 23 FIELD ENGINEERING Description: Replace specification section 01 71 23 FIELD ENGINEERING with

the attached revised section 01 71 23.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 4 of 31

Item No. 1.15 Specification Reference: 01 73 00 EXECUTION Description: Replace specification section 01 73 00 EXECUTION with the

attached revised section 01 73 00. Item No. 1.16 Specification Reference: 01 77 00 CLOSEOUT PROCEDURES Description: Replace specification section 01 77 00 CLOSEOUT PROCEDURES

with the attached new specification section 01 77 00 CONTRACT CLOSEOUT.

Item No. 1.17 Specification Reference: 02 41 19 SELECTIVE DEMOLITION Description: Replace specification section 02 41 19 SELECTIVE DEMOLITION

with the attached revised section 02 41 19 to reflect the following change:

Revise subsection 02 41 19.1.9.C to read as follows: "C. Notify Architect of discrepancies between existing

conditions, Drawings, and Existing Record Drawings before proceeding with selective demolition. In regards to showing existing conditions, the Drawings and Existing Record Drawings shall be considered complementary and additive to one another. What is shown in one shall reasonably interpreted as to be shown on the other."

Item No. 1.18 Specification Reference: 07 22 16 ROOF BOARD INSULATION Description: Add specification section 07 22 16 ROOF BOARD INSULATION to

the project. Item No. 1.19 Specification Reference: 07 22 19 ROOF INSULATION COVER BOARD Description: Add attached specification section 07 22 19 ROOF INSULATION

COVER BOARD to the project. Item No. 1.20 Specification Reference: 07 52 16 SBS MODIFIED BITUMINOUS MEMBRANE

ROOFING Description: Replace specification section 07 52 16 SBS MODIFIED

BITUMINOUS MEMBRANE ROOFING with the attached revised section 07 52 16.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 5 of 31

Item No. 1.21 Specification Reference: 07 62 00 SHEET METAL FLASHING AND TRIM Description: Replace specification section 07 62 00 SHEET METAL FLASHING

AND TRIM with the attached revised section 07 62 00. Item No. 1.22 Specification Reference: 08 71 00 DOOR HARDWARE Description: Add Door Hardware Groups HW-86 through HW-91 as written in

the attached revised specification section 08 71 00 DOOR HARDWARE.

Item No. 1.23 Specification Reference: 09 06 00 SCHEDULES FOR FINISHES Description: Replace specification section 09 06 00 SCHEDULES FOR FINISHES

with the attached revised section 09 06 00. Item No. 1.24 Specification Reference: 09 30 13 CERAMIC TILING Description: Replace specification section 09 30 13 CERAMIC TILING with the

attached revised section 09 30 13. Item No. 1.25 Specification Reference: 09 64 66.20 WOOD THEATER FLOORING Description: Replace specification section 09 64 66.20 WOOD THEATER

FLOORING with the attached revised section 09 64 66.20. Item No. 1.26 Specification Reference: 09 65 13 RESILIENT BASE AND ACCESSORIES Description: Replace specification section 09 65 13 RESILIENT BASE AND

ACCESSORIES with the attached revised section 09 65 13. Item No. 1.27 Specification Reference: 09 65 16 HYBRID RESILIENT SHEET FLOORING - CARPET Description: Replace specification section 09 65 16 HYBRID RESILIENT SHEET

FLOORING - CARPET with the attached revised section 09 65 16. Item No. 1.28 Specification Reference: 11 40 00 FOOD SERVICE EQUIPMENT Description: Replace specification section 11 40 00 FOOD SERVICE EQUIPMENT

with the attached revised section 11 40 00.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 6 of 31

Item No. 1.29 Specification Reference: 22 05 13 COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT Description: Revise specification section 22 05 13 to include subsection 22 05

13.1.4 WARRANTY as written in the attached revised specification section 22 05 13.

Item No. 1.30 Specification Reference: 22 05 19 METERS AND GAGES FOR PLUMBING PIPING Description: Replace specification section 22 05 19 METERS AND GAGES FOR

PLUMBING PIPING with the attached revised section 22 05 19. Item No. 1.31 Specification Reference: 22 05 23 GENERAL-DUTY VALVES FOR PLUMBING PIPING Description: Replace specification section 22 05 23 GENERAL-DUTY VALVES

FOR PLUMBING PIPING with the attached revised section 22 05 23. Item No. 1.32 Specification Reference: 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING

PIPING AND EQUIPMENT Description: Replace specification section 22 05 29 HANGERS AND SUPPORTS

FOR PLUMBING PIPING AND EQUIPMENT with the attached revised section 22 05 29.

Item No. 1.33 Specification Reference: 22 05 48 NOISE, VIBRATION AND SEISMIC CONTROL OF PLUMBING PIPING AND EQUIPMENT Description: Revise specification subsection 22 05 48.1.5 SUBMITTALS as

written in the attached revised section 22 05 48. Item No. 1.34 Specification Reference: 22 11 29 PLUMBING SPECIALTIES Description: Add the new attached specification section 22 11 29 PLUMBING

SPECIALTIES to the project. Item No. 1.35 Specification Reference: 23 23 00 REFRIGERANT PIPING Description: Replace specification section 23 23 00 REFRIGERANT PIPING with

the attached revised section 23 23 00.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 7 of 31

Item No. 1.36 Specification Reference: 23 34 23 HVAC POWER VENTILATORS Description: Revise specification subsection 23 34 23.2.1.F as written in the

attached revised section 23 34 23. Item No. 1.37 Specification Reference: 23 52 33 WATER-TUBE BOILERS Description: Revise specification subsection 23 52 33.2.2.E as written in the

attached revised section 23 52 33. Item No. 1.38 Specification Reference: 23 74 00 PACKAGED ROOFTOP OUTDOOR HVAC EQUIPMENT Description: Revise specification subsection 23 74 00.2.1.E.1.c and add

subsection 23 74 00.2.2.V as written in the attached revised section 23 74 00.

Item No. 1.39 Specification Reference: 27 50 00 DIGITAL INTERCOM/CLOCK & BELL SYSTEM Description: Replace specification section 27 50 00 DIGITAL INTERCOM with

attached section 27 50 00. Item No. 1.40 Specification Reference: 28 13 53.10 VIDEO INTERCOM SYSTEM Description: Add the new attached specification section 28 13 53.10 VIDEO

INTERCOM SYSTEM to the project. Item No. 1.41 Specification Reference: 28 23 00 DIGITAL VIDEO SURVEILLANCE SYSTEM Description: Replace specification section 28 23 00 DIGITAL VIDEO

SURVEILLANCE with attached section 28 23 00. Item No. 1.42 Specification Reference: 32 31 19 DECORATIVE METAL FENCES AND GATES Description: Replace specification section 32 31 19 DECORATIVE METAL

FENCES AND GATES with attached section 32 31 19.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 8 of 31

CHANGES TO THE DRAWINGS: Item No. 1.43 Drawing Reference: G001.1 SHEET INDEX VOLUME 1 OF 2 G002.2 SHEET INDEX VOLUME 1 OF 2 807726_0.01 NEW METER & SERVICE FINAL DESIGN DRAWING Description: Incorporate attached SCE Electric Utility New Meter & Service Final

Design Drawing Sheet 807726_0.01 into the project and revise Sheet Index sheets as shown clouded on attached revised sheets G001.2 and G002.2

Item No. 1.44 Drawing Reference: A010 OVERALL SITE PLAN Description: Revise Gate 5 and fence configuration as shown clouded on the

attached revised sheet A010. Item No. 1.45 Drawing Reference: A018 SITE DETAILS Description: Plan 17/A018 TRASH ENCLOSURE PLAN: Revise steel beam to

CMU wall detail reference to 2/S522 as shown clouded on the attached revised sheet A018.

Item No. 1.46 Drawing Reference: A019 SITE DETAILS Description: 9/A019 STAIR GUARDRAIL ELEVATION: Revise guardrail height

and post/rail spacing as shown clouded on the attached revised sheet A019.

10/A019 ENLARGED PLAN: Add reference to Detail 21/A017

HANDRAIL ATTACHMENT AT CONC as shown clouded on the attached revised sheet A019.

17/A019 ENLARGED PLAN: Add reference to Detail 21/A017 as

shown clouded on the attached revised sheet A019. 18/A019 STAIR GUARDRAIL ELEVATIONS: Revise guardrail height

and post/rail spacing as shown clouded on the attached revised sheet A019.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 9 of 31

20/A019 STAIR OPENING GUARDRAIL DETAIL: Revise guardrail height and rail spacing as shown clouded on the attached revised sheet A019.

24/A019 STAIR GUARDRAIL ELEVATIONS: Revise guardrail height

and post/rail spacing as shown clouded on the attached revised sheet A019.

25/A019 STAIR GUARDRAIL DETAIL: Revise to show base plate

mounting of the guardrail post as shown clouded on the attached revised sheet A019.

27/A019 ENLARGED PLAN: Add reference to Detail 21/A017 as

shown clouded on the attached revised sheet A019. Item No. 1.47 Drawing Reference: A021 FENCE DETAILS Description: Add detail 10 HANDRAIL BRACKET as shown clouded on the

attached revised sheet A021. Item No. 1.48 Drawing Reference: AD101.1 BLDG 100 DEMOLITION FLOOR PLAN Description: Remove existing toilet partitions, ceiling tiles, and projector

mounts in bldg. 100 and revise sheet AD101.1 as shown clouded on the attached revised sheet AD101.1.

Item No. 1.49 Drawing Reference: AD102.1 BLDG 200 FIRST FLOOR DEMO PLAN Description: Add detail references to enlarged plans at Stairs #1 and #2 as

shown clouded on the attached revised sheet AD102.1. Item No. 1.50 Drawing Reference: AD102.2 BLDG 200 SECOND FLOOR DEMO PLAN Description: Add detail references to enlarged plans at Stairs #1 and #2 as

shown clouded on the attached revised sheet AD102.2. Item No. 1.51 Drawing Reference: AD106.1 BLDG 600 DEMOLITION FLOOR PLAN Description: Incorporate attached new sheet AD106.1 into the project.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 10 of 31

Item No. 1.52 Drawing Reference: A101.1 BLDG 100 FLOOR PLAN Description: Revise name of Room 112 to be Student Toilet and add Doors

100A-1, 111-2, 115-1, 115-2, 116-1, 116-2, 118-1, 118-2, 120-1, 121-1, 121-2 to the scope of work as shown clouded on the attached revised sheet A101.1.

Item No. 1.53 Drawing Reference: A102.1 BLDG 200 FIRST FLOOR PLAN Description: Add detail references to enlarged plans at Stairs #1 and #2 as

shown and revise sheet A102.1 as shown clouded on attached revised sheet A102.1.

Item No. 1.54 Drawing Reference: A102.2 BLDG 200 SECOND FLOOR PLAN Description: Add detail references to enlarged plans at Stairs #1 and #2 as

shown clouded on the attached revised sheet A102.2. Item No. 1.55 Drawing Reference: A106.1 BLDG 600 FLOOR PLAN Description: Incorporate attached new sheet A106.1 into the project. Item No. 1.56 Drawing Reference: A107.1 BLDG 700 FIRST FLOOR PLAN Description: Revise portion of double wall at Door 715-3 to provide 4” metal

studs as shown clouded on the attached revised sheet A107.1. Move Grid 5, the columns at Grid 5 and the canopy column and

revise dimensions as shown clouded on the attached revised sheet A107.1.

Item No. 1.57 Drawing Reference: A107.2 BLDG 700 SECOND FLOOR PLAN Description: Revise cricket and roof drainage configuration in the Mechanical

Well (708) as shown clouded on the attached revised sheet A107.2. Move Grid 5, the columns at Grid 5 and the canopy column and

revise dimensions as shown clouded on the attached revised sheet A107.2.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 11 of 31

Item No. 1.58 Drawing Reference: A107.3 BLDG 700 ROOF PLAN Description: Revise dimensions at Grid 5 as shown clouded on the attached

revised sheet A107.3. Item No. 1.59 Drawing Reference: A111.1 BLDG 100 REFLECTED CEILING PLAN Description: 1. Replace existing acoustical tile ceiling panels and provide

LCD projector mounts in classrooms 116, 118, 120, and 121.

2. Replace existing acoustical tile ceiling panels in the administration office areas as shown and revise sheet A111.1 as shown clouded on attached revised sheets A111.1

Item No. 1.60 Drawing Reference: A114.1 BLDG 400 REFLECTED CEILING PLAN Description: Revise graphic for ceiling hatching in Engineering (433) and

Corridor (441) to match the ceiling legend for 12”x12” glue-up acoustical tiles as shown clouded on the attached revised sheet A114.1.

Item No. 1.61 Drawing Reference: A116.1 BLDG 600 REFLECTED CEILING PLAN Description: Incorporate attached new sheet A116.1 into the project. Item No. 1.62 Drawing Reference: A117.1 BLDG 700 FIRST FLOOR REFLECTED CEILING PLAN Description: Move Grid 5, the columns at Grid 5 and the canopy column as

shown clouded on the attached revised sheet A117.1. Item No. 1.63 Drawing Reference: A117.2 BLDG 700 SECOND FLOOR REFLECTED CEILING

PLAN Description: Move Grid 5, the columns at Grid 5 and the canopy column as

shown clouded on the attached revised sheet A117.2. Item No. 1.64 Drawing Reference: A118.1 BLDG 800 REFLECTED CEILING PLAN Description: Revise to remove partial height walls from the Reflected Ceiling

Plan at the shower stalls in rooms 802, 805, 812 and 815 as shown clouded on the attached revised sheet A118.1.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 12 of 31

Item No. 1.65 Drawing Reference: A207.2 BLDG 700 EXTERIOR ELEVATIONS Description: Move Grid 5 and the canopy column as shown clouded on the

attached revised sheet A207.2. Item No. 1.66 Drawing Reference: A308.1 BLDG 800 BUILDING SECTIONS Description: 13/A308.1 BLDG 800 BUILDING SECTION: Revise walls in rooms

802 and 812 to be partial height walls as shown clouded on the attached revised sheet A308.1.

Item No. 1.67 Drawing Reference: A402.3 BLDG 200 ENLARGED PLANS AND INTERIOR

ELEVATIONS Description: Add information for interior stairs #1 and #2 Incorporate attached new sheet A402.3 into the project. Item No. 1.68 Drawing Reference: A407.4 BLDG 700 ENLARGED PLANS Description: 20/A407.4 BLDG 700 ENLARGED REFLECTED CEILING PLAN – 1. WEST CANOPY: Move Grid 5, the columns at Grid 5 and the

canopy column and revise the gap between the storefront and the canopy as shown clouded on the attached revised sheet A407.4.

2. Revise Enlarged Bridge and Canopy Plan 3 on sheet A407.4 as

follows and as shown clouded on attached revised sheet A407.4: a. Add top of structural conc. deck elevations b. Revise topping slab elevations as shown c. Add Annotation Legend Item No. 1.69 Drawing Reference: A408.1 BLDG 800 ENLARGED PLANS Description: 2/A408.1 BLDG 800 ENLARGED PLAN: Revise walls at the shower

stalls to be partial height walls with posts as shown clouded on the attached revised sheet A408.1.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 13 of 31

3/A408.1 BLDG 800 ENLARGED PLAN: Add posts in the partial height walls at the shower stalls posts as shown clouded on the attached revised sheet A408.1.

11/A408.1 BLDG 800 INTERIOR ELEVATIONS: Revise walls at

shower stalls to be partial height as shown clouded on the attached revised sheet A408.1.

12/A408.1 BLDG 800 INTERIOR ELEVATIONS: Revise walls at the

shower stalls to be partial height walls as shown clouded on the attached revised sheet A408.1.

Item No. 1.70 Drawing Reference: A422.1 BLDG 200 INTERIOR ELEVATIONS Description: Revise sheet A422.1 as shown clouded on the attached revised

sheet A422.1 Item No. 1.71 Drawing Reference: A422.2 BLDG 200 INTERIOR ELEVATIONS Description: Revise sheet A422.2 as shown clouded on the attached revised

sheet A422.2 Item No. 1.72 Drawing Reference: A422.4 BLDG 200 INTERIOR ELEVATIONS Description: Revise sheet A422.4 as shown clouded on the attached revised

sheet A422.4 Item No. 1.73 Drawing Reference: A511 WALL DETAILS Description: Revise WALL NOTES (ACOUSTICAL)-A as follows: Revise Note 5 to read: “NOT USED” Add Notes 10 thru 14 to read: “10. ALL DOORS IN ACOUSTICAL WALLS SHALL MAINTAIN THE

ACOUSTICAL RATING AS NOTED IN THE DOOR SCHEDULE ON SHEET A602.”

“11. ALL DUCT PENETRATIONS IN ACOUSTICAL WALLS SHALL

CONFORM WITH DETAIL 1/A630.”

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 14 of 31

“12. ALL PIPE, CONDUIT AND /OR CABLE PENETRATIONS IN

ACOUSTICAL WALLS SHALL CONFORM WITH DETAIL 3/A630.” “13. ALL RECESSED BOXES IN ACOUSTICAL WALLS SHALL

CONFORM WITH DETAIL 4/A630.” “14. ALL DUCTS WITHIN THEATER (709), VESTIBULE (709.1) AND

TECH GALLERY (710) SHALL CONFORM WITH THE GENERAL NOTES 6, 8, 10 & 11 ON SHEET M107.2.”

As shown clouded on the attached revised sheet A511. Item No. 1.74 Drawing Reference: A512 WALL TYPE DETAILS Description: Revise details 5 and 20 as follows: Add sound insulation in the

cavity between the steel floor deck flute and the metal plate at acoustical walls as shown clouded on the attached revised sheet A512.

Item No. 1.75 Drawing Reference: A514 ROOF DETAILS Description: Revise details 2, 5, 6, 7 and 13 to provide termination bars at the

termination of the flashing plies as shown clouded on the attached revised sheet A514.

Revise detail 21 to show flashing plies up and over the parapet

wall on the right side of the wall, just like on the left side, as shown clouded on the attached revised sheet A514.

Item No. 1.76 Drawing Reference: A515 ROOF DETAILS Description: 2/A515 MECH PLATFORM WITH (N) OPENING: Revise to provide

termination bars at the termination of the flashing plies as shown clouded on the attached revised sheet A515.

7/A515 MECH PLATFORM (E) OPENING: Revise to provide

termination bars at the termination of the flashing plies as shown clouded on the attached revised sheet A515.

19/A515 CLOSURE DETAIL AT CANOPY: Revise the detail as

shown clouded on the attached revised sheet A515.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 15 of 31

24/A515 CLOSURE DETAIL AT CANOPY: Revise the detail as

shown clouded on the attached revised sheet A515. Item No. 1.77 Drawing Reference: A516 MISC. DETAILS Description: Revise details 25A, 25B, 25C AND 25D as follows: Add automatic

door bottom at all acoustical doors, add solid grout under the threshold at all acoustical doors as shown clouded on the attached revised sheet A516.

Revise detail 10 to provide termination bars at the termination of

the flashing plies as shown clouded on the attached revised sheet A516.

Add detail 12/A516 PARTIAL HEIGHT WALL as shown clouded on

the attached revised sheet A516. Item No. 1.78 Drawing Reference: A541 SIGNAGE DETAILS Description: Revise detail 11 as follows: Revise spec reference in Note #2 to be

10 14 23 as shown clouded on the attached revised sheet A541. Item No. 1.79 Drawing Reference: A573 ELEVATOR DETAILS Description: Revise elevator and landing drawings 16, 17, and 20 on sheet A573

as shown clouded on attached revised sheet A573. 13/A573 ELEVATOR SIGNAGE: Revise size of star to be 3” high as

shown clouded on the attached revised sheet A573. Item No. 1.80 Drawing Reference: A576 DETAILS Description: Revise details 26 and 28 on sheet A576 as shown clouded on

attached revised sheet A576 to indicate that top of structural concrete filled decks underneath topping slabs shall slope to drains. See sheet A407.4 for elevations.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 16 of 31

Item No. 1.81 Drawing Reference: A601 DOOR SCHEDULE Description: Add Door 111 in the Building 100 Door Schedule as shown

clouded on the attached revised sheet A601. Add reference in the Building 100 Door Schedule to new Sheet

A603 for additional Building 100 doors as shown clouded on the attached revised sheet A601.

Delete Door Schedule Note 8 as shown clouded on the attached

revised sheet A601. Item No. 1.82 Drawing Reference: A602 DOOR SCHEDULE Description: Revise schedule information for acoustical doors 709-1, 709-2,

709-3, 709.1-1, 709.1-2, 709.1-3, 715-3, 710-1 and 712-1 as shown clouded on the attached revised sheet A602.

Add Comment Legend notes 7 and 8 as shown clouded on the

attached revised sheet A602. Delete Door Schedule Note 8 as shown clouded on the attached

revised sheet A602. Item No. 1.83 Drawing Reference: A603 DOOR SCHEDULE Description: Incorporate new attached sheet A603 into the project. Item No. 1.84 Drawing Reference: A621 FINISH SCHEDULE Description: Revise Building 100 finishes and add Building 600 finishes to the

Room Finish Schedule on sheet A621 as shown clouded on attached revised sheet A621.

Item No. 1.85 Drawing Reference: A630 MISC ACOUSTICAL DETAILS Description: Revise detail 1 to clarify the graphic for the solid grout in the HM

frame as shown clouded on the attached revised sheet A630.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 17 of 31

Item No. 1.86 Drawing Reference: M004 SCHEDULES Description: Revise information for EF-7.3 as shown clouded on attached

revised sheet M004. Item No. 1.87 Drawing Reference: MD102.2 BLDG 200 – SECOND FLOOR MECHANICAL DEMOLITION PLAN Description: Add the following note to sheet MD102.2: "ALL DEMOLITION WORK NOTED ABV. IS TO ADDITIONALLY

APPLY TO ATTIC SPACE ABOVE SECOND FLLOR." Item No. 1.88 Drawing Reference: M101.1BLDG 100 – FIRST FLOOR MECHANICAL PLAN M102.0BLDG 200 – BASEMENT MECHANICAL PLAN M102.1BLDG 200 – FIRST FLOOR MECHANICAL PLAN M102.1P BLDG 200 – FIRST FLOOR MECHANICAL PIPING PLAN M102.2BLDG 200 – SECOND FLOOR MECHANICAL PLAN M102.3BLDG 200 – ATTIC MECHANICAL PLAN M102.3P BLDG 200 – ATTIC MECHANICAL PIPING PLAN M104.2BLDG 400 – MECHANICAL ROOF PLAN Description: Revise General Note ‘5’ on sheets M101.1, M102.0, M102.1,

M102.1P, M102.2, M102.3, and M102.3P as shown clouded on the attached revised respective sheets.

Item No. 1.89 Drawing Reference: M104.1BLDG 400 – FIRST FLOOR MECHANICAL PLAN Description: Revise General Note ‘5’ and Keynotes ’20’ and ‘21’ as shown

clouded on the attached revised sheet M104.1. Item No. 1.90 Drawing Reference: M107.1BLDG 700 – FIRST FLOOR MECHANICAL PLAN Description: Make the following changes and revise sheet M107.1 as shown

clouded on the attached revised sheet M107.1 1. Revise General Note ‘4’. 2. Revise Key Notes ‘6’, ‘10’, ‘12’ and ‘18’. 3. Revise section reference sheet numbers. 4. Revise ductwork and louver within Elevator Equipment 735. 5. Remove transfer duct to Elevator Equipment 735.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 18 of 31

6. Revise General Note ‘3’. Item No. 1.91 Drawing Reference: M107.2BLDG 700 – SECOND FLOOR MECHANICAL PLAN Description: Make the following changes and revise sheet M107.2 as shown

clouded on the attached revised sheet M107.2 1. Revise General Note ‘4’. 2. Revise ductwork at Theater and Library 720. 3. Revise section reference sheet numbers. Item No. 1.92 Drawing Reference: M107.1P BLDG 700 – FIRST FLOOR MECHANICAL PIPING PLAN M107.2P BLDG 700 – SECOND FLOOR MECHANICAL PIPING PLAN Description: Revise General Note ‘3’ on sheets M107.1P and M107.2P as shown

clouded on the attached revised respective sheets. Item No. 1.93 Drawing Reference: M502 DETAILS Description: Revise details 6 and 9 on sheet M502 as shown clouded on

attached revised sheet M502. Item No. 1.94 Drawing Reference: M508 DETAILS Description: Revise fan motor location in detail 2 on sheet M508 as shown

clouded on the attached revised sheet M508. Item No. 1.95 Drawing Reference: M509 MECHANICAL SECTIONS & ENLARGED PLANS Description: Revise ductwork routing on sheet M509 as shown clouded on the

attached revised sheet M509. Item No. 1.96 Drawing Reference: M510 MECHANICAL SECTIONS & ENLARGED PLANS Description: Revise section drawing 3 on sheet M510 as shown clouded on the

attached revised sheet M510. Item No. 1.97 Drawing Reference: P001 LEGEND, SCHEDULE AND NOTES Description: Revise DD-1 Deck Drain on Plumbing Fixture Schedule as shown

clouded on attached revised sheet P001

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 19 of 31

Item No. 1.98 Drawing Reference: PD102.0 BLDG 200-BASEMENT PLUMBING DEMOLITION PLAN Description: Revise sheet PD102.0 as shown clouded on the attached revised sheet PD102.0. Item No. 1.99 Drawing Reference: P101.1 BLDG 100 – FIRST FLOOR PLUMBING PLAN Description: Revise sheet P101.1 as shown clouded on the attached revised sheet P101.1 Item No. 1.100 Drawing Reference: P102.0 BLDG 200 – BASEMENT PLUMBING PLAN Description: Add replacement of all remaining domestic water piping, sanitary Vents and sewer piping and revise sheet P102.0 as shown clouded

on the attached revised sheet P102.0 Item No. 1.101 Drawing Reference: P102.1 BLDG 200 – FIRST FLOOR PLUMBING PLAN Description: Revise condensate piping, replace new water and waste piping

and revise sheet P102.1 as shown clouded on the attached revised sheet P102.1

Item No. 1.102 Drawing Reference: P301 BLDG 200 – ENLARGED PLUMBING PLAN Description: Revise water, waste and sanitary vent piping as shown clouded on

the attached revised sheet P301. Item No. 1.103 Drawing Reference: P303 BLDG 700 – ENLARGED PLUMBING PLAN Description: Revise water, waste and sanitary vent piping as shown clouded on

the attached revised sheet P303. Item No. 1.104 Drawing Reference: P502 DETAILS Description: Add detail 10 on sheet P502 as shown clouded on attached

revised sheet P502. Item No. 1.105 Drawing Reference: E010D DEMO SITE ELECTRICAL PLAN Description: Revise Plan Notes and revise plan note call outs on site plan.

Indicate that the existing power company service is to remain until

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 20 of 31

the new service is fully functional and all buildings are backfed. Add General Demolition Notes 14 and 15 as shown and revise sheet E010D as shown clouded on attached revised sheet E101D.

Item No. 1.106 Drawing Reference: E010 SITE ELECTRICAL PLAN Description: Revise Plan Notes. Remove existing cameras from site plan. Revise

camera locations and quantity. Re-number CCTV cameras and change cameras from “existing” to “new”. Add Note at feeders running between Buildings 200 and 600 to verify depth of new trenching required to avoid existing utilities in the area. Revise all Feeders named “HDB4” to be “HB41” per Single Line Diagram. Revise all Feeders named “HDB8” to be “HB81” per Single Line Diagram. Revise Site Utility Construction Note 20 to include conduits between pullboxes. Extend site signal conduits from pullbox to Building 600 signal head-end equipment. Revise routing of primary feeder per SCE plan as shown and revise sheet E010 shown clouded on attached revised sheet E010.

Item No. 1.107 Drawing Reference: E011 SITE LIGHTING PLAN Description: Revise circuiting to flag pole lights as shown and revise sheet E011

as shown clouded on attached revised sheet E011. Item No. 1.108 Drawing Reference: ED101.1.0 BUILDING 100 – ELECTRICAL DEMOLITION PLAN Description: Add Plan Notes 10 and 11. Revise plan note call-outs throughout

building. Add demo note in Telecom Room 125. Revise Plan Note “9” to be Plan Note “3” in Corridor (existing lighting to be replaced) as shown and revise sheet ED101.1.0 as shown clouded on attached revise sheet ED101.1.0.

Item No. 1.109 Drawing Reference: E101.1.1 BUILDING 100 – POWER PLAN Description: Provide new power for ceiling mounted projectors and teacher’s

stations in classrooms. Provide floor outlet for mobile cart at Gallery. Provide new receptacles in Admin area as shown and revise sheet E101.1.1 as shown clouded on attached revised sheet E101.1.1.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 21 of 31

Item No. 1.110 Drawing Reference: E101.1.2 BUILDING 100 – SIGNAL PLAN Description: Provide new wireless access point in Career Center room 114.

Revise exterior cctv camera quantity and locations. Add data drops at projectors in 5 classrooms. Add AV components in 5 classrooms. Provide new telephone cabling. Provide new data cabling throughout and new data outlets. Add plan notes 12 through 16 as shown and revise sheet E101.1.2 as shown clouded on attached revise sheet E101.1.2.

Item No. 1.111 Drawing Reference: ED102.1.0 BUILDING 200 – ELECTRICAL DEMOLITION PLAN Description: Revise General Demolition Note 14A to indicate all existing

lighting to be disconnected and removed, U.O.N.. Revise sheet ED102.1.0 as shown clouded on attached revised sheet ED102.1.0

Item No. 1.112 Drawing Reference: E102.1.1 BUILDING 200 – 1ST FLOOR POWER PLAN Description: Revise homerun at electric water heater to be to Panel HB22 as

shown and revise sheet E102.1.1 as shown clouded on attached revised sheet E102.1.1.

Item No. 1.113 Drawing Reference: E102.1.2 BUILDING 200 – 1ST FLOOR SIGNAL PLAN Description: Revise plan notes 6 and 7. Delete four exterior CCTV cameras as

shown. Revise sheet E102.1.2 as shown clouded on attached revised sheet E102.1.2.

Item No. 1.114 Drawing Reference: ED104.1.0 BUILDING 400 – ELECTRICAL DEMOLITION PLAN Description: Revise Plan Note 13 call-out at Room 457 to Note 5. Add notes 14

and 15 to clarify areas where existing power is to remain or stay. Revise lighting to be removed in Office 454 and Storage 455 as shown. Revise sheet ED104.1.0 as shown clouded on attached revised sheet ED104.1.0.

Item No. 1.115 Drawing Reference: E104.1.1 BUILDING 400 – POWER PLAN Description: Revise Panel “HDB4” to be “HB41” per Single Line Diagram. Add

future provisions for air curtains at Vestibule 409. Provide new power at Office 411. Add wire ticks at Edit 440 and Dining 401 as

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 22 of 31

shown. Revise sheet E104.1.1 as shown clouded on attached revised sheet E104.1.1.

Item No. 1.116 Drawing Reference: E104.1.2 BUILDING 400 – SIGNAL PLAN Description: Provide new wireless access point in ASB Lab room 407. Delete

one CCTV camera at building Northeast corner. Add data outlet in office 411. Move CCTV camera #14 and rename as #10. Move CCTV camera #15 and rename as #07. Provide new door buzzer and video intercom system with video cameras at both OMS entry doors as shown and revise sheet E104.1.2 as shown clouded on attached revised sheet E104.1.2.

Item No. 1.117 Drawing Reference: E104.1.3 BUILDING 400 – LIGHTING PLAN Description: Shift 2’ x 4’ fixtures at Office/Conference 422 to match ceiling grid

and provide new downlights and exit sign. Shift light fixtures and switch at ASB Lab. Revise lighting layout and circuiting at Dining as shown. Revise sheet E104.1.3 as shown clouded on attached revised sheet E104.1.3.

Item No. 1.118 Drawing Reference: E104.1.4 BUILDING 400 – ENLARGED KITCHEN ELECTRICAL

PLAN Description: Add receptacle for future warmer by roll-up door. Revise floor

outlet locations at Dining. Revise rethermalizing unit receptacle locations as well as power requirements to Item 23. Provide power to hood lights. Provide controls and conduit to hood exhaust and MAU. Relocate one prep sink receptacle and delete one. Relocate disposer. Relocate reach-in freezer receptacle. Add receptacles in Vestibule 403 for future equipment as shown. Revise sheet E104.1.4 as shown clouded on attached revised sheet E104.1.4.

Item No. 1.119 Drawing Reference: ED106.1.0 BUILDING 600 – ELECTRICAL DEMOLITION PLAN Description: Revise conduit at BMS to include cabling. Add Plan Notes 10 and

11 as shown. Revise sheet ED106.1.0 as shown clouded on attached revised sheet ED106.1.0.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 23 of 31

Item No. 1.120 Drawing Reference: E106.1.1 BUILDING 600 – POWER PLAN Description: Provide new power for ceiling mounted projectors and teacher’s

stations in classrooms as shown. Revise sheet E106.1.1 as shown clouded on attached revised sheet E106.1.1.

Item No. 1.121 Drawing Reference: E106.1.2 BUILDING 600 – SIGNAL PLAN Description: Move CCTV camera #13 and rename as #06. Move CCTV camera

#09 and rename as #05. Add classroom AV devices in 7 classrooms. Provide new telephone cabling. Add plan notes 7 through 11 as shown. Revise sheet E106.1.2 as shown clouded on attached revised sheet E106.1.2.

Item No. 1.122 Drawing Reference: E107.1.1 BUILDING 700 – 1st FLOOR POWER PLAN Description: Revise Motor Equipment Schedule for EF7-3. Delete provisions to

one smoke fire damper as shown. Revise sheet E107.1.1 as shown clouded on attached revised sheet E107.1.1.

Item No. 1.123 Drawing Reference: E107.1.2 BUILDING 700 – 1st FLOOR SIGNAL PLAN Description: Move CCTV camera #11 and rename as #03. Move dual data

outlet, and add data drop at projector as shown. Revise sheet E107.1.2 as shown clouded on attached revised sheet E107.1.2.

Item No. 1.124 Drawing Reference: E107.2.1 BUILDING 700 – 2nd FLOOR POWER PLAN Description: Relocate and add provisions for electronic catalogs in Library as

shown. Revise sheet E107.2.1 as shown clouded on attached revised sheet E107.2.1.

Item No. 1.125 Drawing Reference: E107.2.2 BUILDING 700 – 2nd FLOOR SIGNAL PLAN Description: Provide new wireless access point above Theater 709. Add data

devices in Library room floor boxes.Relocate and add provisions for electronic catalogs in Library as shown. Revise sheet E107.2.2 as shown clouded on attached revised sheet E107.2.2.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 24 of 31

Item No. 1.126 Drawing Reference: E108.1.1 BUILDING 800 – POWER PLAN Description: Revise provisions for water heater as shown and revise sheet

E108.1.1 as shown clouded on the attached revised revised . Revise sheet E108.1.1 as shown clouded on attached revised sheet E108.1.1.

Item No. 1.127 Drawing Reference: E108.1.2 BUILDING 800 – SIGNAL PLAN Description: Remove CCTV cameras #12 and #13 as shown. Revise sheet

E108.1.2 as shown clouded on attached revised sheet E108.1.2. Item No. 1.128 Drawing Reference: E201 SINGLE LINE DIAGRAM Description: Add existing Transformer TE and existing Panel EA to Single Line

Diagram. Revise incoming primary feeder to be (1) 5”C. Add transformer slab box size as shown. Revise sheet E201 as shown clouded on attached revised sheet E201.

Item No. 1.129 Drawing Reference: E202 TRANSFORMER SCHEDULE, NOTES AND DETAILS Description: revise Feeder “HB8” to be “HB81” per Single Line Diagram. Revise

Feeder “HB4” to be “HB41” per Single Line Diagram. Revise Feeders TB2, TB7 and TB4 to have 3#250KCMIL (not 4#250KCMIL) as shown. Revise sheet E202 as shown clouded on attached revised sheet E202.

Item No. 1.130 Drawing Reference: E203 ENLARGED ELECTRICAL ROOMS Description: Revise utility yard detail to clarify SCE requirements. Detail 6; Add

note to demo existing jack-panels in MDF Room. Revise telco MPOE call-out. Revise Telecom room detail #6 as shown. Revise sheet E203 as shown clouded on attached revised sheet E203.

Item No. 1.131 Drawing Reference: E204 ENLARGED ELECTRICAL ROOMS Description: Revise IDF Rack Elevation Note E, Ethernet switches are now

Contractor-Furnished.Adjust layout of Building 400 Electrical Room as shown. Revise sheet E204 as shown clouded on attached revised sheet E204.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 25 of 31

Item No. 1.132 Drawing Reference: E209 PANEL SCHEDULES Description: Revise Panels EA, DPE and EHB1 as shown. Revise sheet E209 as

shown clouded on attached revised sheet E209. Item No. 1.133 Drawing Reference: E211 PANEL SCHEDULES Description: Add 400A-3P main circuit breaker at Panel “HB41” and increase

bus size to 400A as shown. Revise sheet E211 as shown clouded on attached revised sheet E211.

Item No. 1.134 Drawing Reference: E212 PANEL SCHEDULES Description: Revise Panel Schedules LP4K1 and B2 and add Specific Panel

Schedule Note “R1” as shown. Revise sheet E212 as shown clouded on attached revised sheet E212.

Item No. 1.135 Drawing Reference: E214 PANEL SCHEDULES Description: Add projectors at Panel DA as shown. Revise sheet E214 as

shown clouded on attached revised sheet E214. Item No. 1.136 Drawing Reference: E215 PANEL SCHEDULES Description: Revise Circuit HB81-25 to be a 30A/1P for an electric water heater

as shown. Revise sheet E215 as shown clouded on attached revised sheet E215.

Item No. 1.137 Drawing Reference: EFA001 FIRE ALARM SYMBOLS LEGEND Description: Add “Intelliquad” combination smoke/carbon monoxide detector

to Symbols Legend as shown. Revise sheet EFA001 as shown clouded on attached revised sheet EFA001.

Item No. 1.138 Drawing Reference: EFA004 FIRE ALARM RISER DIAGRAM Description: Revise two smoke detectors to be combination smoke/carbon

monoxide detectors as shown. Revise sheet EFA004 as shown clouded on attached revised sheet EFA004.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 26 of 31

Item No. 1.139 Drawing Reference: EFA005 FIRE ALARM RISER CALCS Description: Add combination smoke/carbon monoxide detector to FACP

battery calculation as shown. Revise sheet EFA005 as shown clouded on attached revised sheet EFA005.

Item No. 1.140 Drawing Reference: EFA104.1 BUILDING 400 - FIRE ALARM PLAN Description: Revise smoke detectors to be combination smoke/carbon

monoxide detectors as shown. Revise sheet EFA104.1 as shown clouded on attached revised sheet EFA104.1.

Item No. 1.141 Drawing Reference: EFA107.1 BUILDING 700 – FIRST FLOOR FIRE ALARM PLAN Description: Relocate provisions for one smoke/fire damper as shown. Revise

sheet EFA107.1 as shown clouded on attached revised sheet EFA107.1.

Item No. 1.142 Drawing Reference: SCS001 LOW VOLTAGE SYSTEMS BLOCK DIAGRAMS Description: Add General Note to keep OMS Building systems functioning

during construction as shown. Revise sheet SCS001 as shown clouded on attached revised sheet SCS001.

Item No. 1.143 Drawing Reference: SCS002 LOW VOLTAGE SYSTEMS BLOCK DIAGRAMS Description: Revise Plan Note to Building 600 on PA/Clock Block Diagram.

Detail 1: revise transition point note. Detail 2: revise Key Note 8. Add General Note to keep OMS Building systems functioning during construction as shown. Revise sheet SCS002 as shown clouded on attached revised sheet SCS002.

Item No. 1.144 Drawing Reference: SCS003 LOW VOLTAGE SYSTEMS BLOCK DIAGRAMS Description: Add General Note to keep OMS Building systems functioning

during construction. Local Area LAN system block diagram #1, revise plan notes and diagram. Telephone system block diagram #2, revise plan notes and diagram as shown. Revise sheet SCS003 as shown clouded on attached revised sheet SCS003.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 27 of 31

Item No. 1.145 Drawing Reference: SCS004 FACEPLATE DETAILS Description: Remove ceiling data symbol at Detail 5 and provide new Detail 13

for ceiling data drops. All ceiling data drops to projectors to now have two data drops as shown. Revise sheet SCS004 as shown clouded on attached revised sheet SCS004.

Item No. 1.146 Drawing Reference: SCS008 CCTV SURVEILLANCE SYSTEM DETAILS Description: Detail 1, revised camera schedule. Revise Surveillance System

General Note #1 and 34. Detail 2, revise camera block diagram and plan notes as shown. Revise sheet SCS008 as shown clouded on attached revised sheet SCS008.

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 28 of 31

ATTACHMENTS: Specifications (8 1/2" x 11"): 00 01 10 TABLE OF CONTENTS 01 11 00 SUMMARY OF WORK 01 12 16 PHASING OF THE WORK 01 29 73 SCHEDULE OF VALUES PROCEDURES 01 29 76 PROGRESS PAYMENT PROCEDURES 01 31 13 PROJECT COORDINATION 01 31 19 PROJECT MEETINGS 01 32 13 CONSTRUCTION SCHEDULE 01 33 00 SUBMITTAL PROCEDURES 01 45 24 ENVIRONMENTAL IMPORT MATERIALS TESTING 01 45 25 ENVIRONMENTAL EXPORT MATERIALS TESTING 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS 01 71 23 FIELD ENGINEERING 01 73 00 EXECUTION 01 77 00 CONTRACT CLOSEOUT 02 41 19 SELECTIVE DEMOLITION 07 22 16 ROOF BOARD INSULATION 07 22 19 ROOF INSULATION COVER BOARD 07 52 16 SBS MODIFIED BITUMINOUS MEMBRANE ROOFING 07 62 00 SHEET METAL FLASHING AND TRIM 08 71 00 DOOR HARDWARE 09 06 00 SCHEDULES FOR FINISHES 09 30 13 CERAMIC TILING 09 64 66.20 WOOD THEATER FLOORING 09 65 13 RESILIENT BASE AND ACCESSORIES 09 65 16 HYBRID RESILIENT SHEET FLOORING - CARPET 11 40 00 FOOD SERVICE EQUIPMENT 22 05 13 COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT 22 05 19 METERS AND GAGES FOR PLUMBING PIPING 22 05 23 GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 48 NOISE, VIBRATION & SEISMIC CONTROL OF PLUMBING PIPING & EQUIPMENT 22 11 29 PLUMBING SPECIALTIES 23 23 00 REFRIGERANT PIPING 23 34 23 HVAC POWER VENTILATORS 23 52 33 WATER-TUBE BOILERS 23 74 00 PACKAGED ROOFTOP OUTDOOR HVAC EQUIPMENT 27 50 00 DIGITAL INTERCOM/CLOCK & BELL SYSTEM

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 29 of 31

ATTACHMENTS: (continued) 28 13 53.10 VIDEO INTERCOM SYSTEM 28 23 00 DIGITAL VIDEO SURVEILLANCE SYSTEM Sheets (30" x 42"): G001.1 SHEET INDEX VOLUME 1 OF 2 G002.2 SHEET INDEX VOLUME 1 OF 2 A010 OVERALL SITE PLAN A018 SITE DETAILS A019 SITE DETAILS A021 FENCE DETAILS AD101.1 BLDG 100 DEMOLITION FLOOR PLAN AD102.1 BLDG 200 FIRST FLOOR DEMO PLAN AD102.2 BLDG 200 SECOND FLOOR DEMO PLAN AD106.1 BLDG 600 DEMOLITION FLOOR PLAN A101.1 BLDG 100 FLOOR PLAN A102.1 BLDG 200 FIRST FLOOR PLAN A102.2 BLDG 200 SECOND FLOOR PLAN A106.1 BLDG 600 FLOOR PLAN A107.1 BLDG 700 FIRST FLOOR PLAN A107.2 BLDG 700 SECOND FLOOR PLAN A107.3 BLDG 700 ROOF PLAN A111.1 BLDG 100 REFLECTED CEILING PLAN A116.1 BLDG 600 REFLECTED CEILING PLAN A114.1 BLDG 400 REFLECTED CEILING PLAN A117.1 BLDG 700 FIRST FLOOR REFLECTED CEILING PLAN A117.2 BLDG 700 SECOND FLOOR REFLECTED CEILING PLAN A117.2 BLDG 700 SECOND FLOOR REFLECTED CEILING PLAN A118.1 BLDG 800 REFLECTED CEILING PLAN A308.1 BLDG 800 BUILDING SECTIONS A402.3 BLDG 300 ENLARGED PLANS AND INTERIOR ELEVATIONS A407.4 BLDG 700 ENLARGED PLANS+ A408.1 BLDG 800 ENLARGED PLANS AND INTERIOR ELEVATIONS A422.1 BLDG 200 INTERIOR ELEVATIONS A422.2 BLDG 200 INTERIOR ELEVATIONS A422.4 BLDG 200 INTERIOR ELEVATIONS A511 WALL DETAILS A512 WALL TYPE DETAILS A514 ROOF DETAILS A515 ROOF DETAILS+

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 30 of 31

ATTACHMENTS: (continued) A516 MISC DETAILS A541 SIGNAGE DETAILS A573 ELEVATOR DETAILS A576 DETAILS A601 DOOR SCHEDULE A602 DOOR SCHEDULE A603 DOOR SCHEDULE A621 FINISH SCHEDULE A630 MISC ACOUSTICAL DETAILS M004 SCHEDULES MD102.2 BLDG 200 – SECOND FLOOR MECHANICAL DEMOLITION PLAN M101.1 BLDG 100 – FIRST FLOOR MECHANICAL PLAN M102.0 BLDG 200 – BASEMENT MECHANICAL PLAN M102.1 BLDG 200 – FIRST FLOOR MECHANICAL PLAN M102.1P BLDG 200 – FIRST FLOOR MECHANICAL PIPING PLAN M102.2 BLDG 200 – SECOND FLOOR MECHANICAL PLAN M102.3 BLDG 200 – ATTIC MECHANICAL PLAN M102.3P BLDG 200 – ATTIC MECHANICAL PIPING PLAN M104.1 BLDG 400 – FIRST FLOOR MECHANICAL PLAN M107.1 BLDG 700 – FIRST FLOOR MECHANICAL PLAN M107.1P BLDG 700 – FIRST FLOOR MECHANICAL PIPING PLAN M107.2 BLDG 700 – SECOND FLOOR MECHANICAL PLAN M107.2P BLDG 700 – SECOND FLOOR MECHANICAL PIPING PLAN M502 DETAILS M508 DETAILS M509 MECHANICAL SECTIONS & ENLARGED PLANS M510 MECHANICAL SECTIONS & ENLARGED PLANS P001 LEGEND, SCHEDULE AND NOTES PD102.0 BLDG 200-BASEMENT PLUMBING DEMOLITION PLAN P101.1 BLDG 100 – FIRST FLOOR PLUMBING PLAN P102.0 BLDG 200 – BASEMENT PLUMBING PLAN P102.1 BLDG 200 – FIRST FLOOR PLUMBING PLAN P301 BLDG 200 – ENLARGED PLUMBING PLAN P303 BLDG 700 – ENLARGED PLUMBING PLAN P502 DETAILS E010D DEMOLITION SITE ELECTRICAL PLAN E010 SITE ELECTRICAL PLAN E011 SITE LIGHTING PLAN ED101.1.0 BUILDING 100 – ELECTRICAL DEMOLITION PLAN E101.1.1 BUILDING 100 – POWER PLAN

RENAISSANCE HIGH SCHOOL FOR THE ARTS DSA ADDENDUM NO. 1 MODERNIZATION AND ADDITION 9076-1112-681 MAY 9, 2016 Page 31 of 31

ATTACHMENTS: (continued) E101.1.2 BUILDING 100 – SIGNAL PLAN ED102.0.0 BUILDING 200 – BASEMENT ELECTRICAL DEMOLITION PLAN E102.1.1 BUILDING 200 – 1ST FLOOR POWER PLAN E102.1.2 BUILDING 200 – 1ST FLOOR SIGNAL PLAN ED104.1.0 BUILDING 400 – ELECTRICAL DEMOLITION PLAN E104.1.1 BUILDING 400 - POWER PLAN E104.1.2 BUILDING 400 – SIGNAL PLAN E104.1.3 BUILDING 400 – LIGHTING PLAN E104.1.4 BUILDING 400 – ENLARGED KITCHEN ELECTRICAL PLAN ED106.1.0 BUILDING 600 – ELECTRICAL DEMOLITION PLAN E106.1.1 BUILDING 600 – POWER PLAN E106.1.2 BUILDING 600 – SIGNAL PLAN E107.1.1 BUILDING 700 – 1st FLOOR POWER PLAN E107.1.2 BUILDING 700 – 1st FLOOR SIGNAL PLAN E107.2.1 BUILDING 700 – 2nd FLOOR POWER PLAN E107.2.2 BUILDING 700 – 2nd FLOOR SIGNAL PLAN E108.1.1 BUILDING 800 – POWER PLAN E108.1.2 BUILDING 800 – SIGNAL PLAN E201 SINGLE LINE DIAGRAM E202 TRANSFORMER SCHEDULE, NOTES, AND DETAILS E203 ENLARGED ELECTRICAL ROOMS E204 ENLARGED ELECTRICAL ROOMS E209 PANEL SCHEDULES E211 PANEL SCHEDULES E212 PANEL SCHEDULES E214 PANEL SCHEDULES E215 PANEL SCHEDULES EFA001 FIRE ALARM SYMBOLS LEGEND EFA004 FIRE ALARM RISER DIAGRAM EFA005 FIRE ALARM RISER CALCS EFA104.1 BUILDING 400 - FIRE ALARM PLAN EFA107.1 BUILDING 700 – FIRST FLOOR FIRE ALARM PLAN SCS001 LOW VOLTAGE SYSTEMS BLOCK DIAGRAMS SCS002 LOW VOLTAGE SYSTEMS BLOCK DIAGRAMS SCS003 LOW VOLTAGE SYSTEMS BLOCK DIAGRAMS SCS004 FACEPLATE DETAILS SCS008 CCTV SURVEILLANCE SYSTEM DETAILS 807726_0.01 NEW METER & SERVICE FINAL DESIGN DRAWING END OF DSA ADDENDUM NO. 1