Page 1: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Project Scheduling: Adding the Time

Dimension

Chapter 7

Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved.McGraw-Hill/Irwin

Page 2: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Chapter Learning Objectives

• Employ project scheduling concepts to engage team commitment and manage stakeholder expectations.

• Graphically illustrate the various project scheduling formats available and describe the key features of each.

• Given a network schedule, identify the critical path and float using visual and mathematical approaches.

• Facilitate a team session to create a project schedule.

• Discuss the application of project scheduling software and describe the advantages and challenges associated with its use.

• Apply the PERT approach to develop three-point time estimates and predict likelihoods for various project completion times.

When you have mastered the material in this chapter, you should be able to:

7-2

Page 3: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Project Scheduling: Adding the Time Dimension

“Time is a versatile performer. It flies, marches on, heals all wounds,

runs out, and will tell.”

Franklin P. Jones

7-3

Page 4: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.2

Key Contributions Stemming from the Project Schedule

7-4

Page 5: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Box 7.1

Project Scheduling: Two Real Life Scenarios

Scenario 1: Schedule Goals Make a Difference in Landscaping

Peter Roberts operates a successful landscaping company in the southeastern United States. As his company grew, Peter noted an increasing tendency for major landscaping jobs to run beyond scheduled due dates. He knew it was possible to complete the work within the time frames he had promised his customers, but he was less and less able to spend time on every job site now that he had more employees and several projects running simultaneously.

After taking a course on project management, Peter decided to try posting, at each job site, a simple horizontal bar chart (see Exhibit 7.3). Peter also reviewed the schedule with each crew chief at the beginning and middle of each project. As time went by, he involved the crew chiefs and team members in decisions about the schedule.

Within just a few weeks, projects began to come in on time, consistently.

7-5

Page 6: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.3

Gantt Chart for Installing a Garden Irrigation System

7-6

Page 7: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Box 7.1

Project Scheduling: Two Real Life Scenarios

Scenario 2: Schedule Leads to Cooperation in Tool Design

Brad Clemson, an industrial engineering manager at a Fortune 500 company, was experiencing schedule delays in the large machine-tool design process he managed. Designers produced tool drawings, which were then passed to industrial engineers who created the shop drawings used in fabrication and assembly. Both sets of drawings were critical. Schedules were chaotic, and there was considerable finger-pointing between the two groups. Designers were unable to give time estimates for their work, and often produced drawings out of sequence for the needs of the industrial engineering group.

continued

7-7

Page 8: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Box 7.1

Project Scheduling: Two Real Life Scenarios

Scenario 2: Schedule Leads to Cooperation in Tool Design

Brad’s solution was to get both groups to cooperate in developing a network-type schedule that incorporated (and made visible) the necessary precedence relationships among the various drawing tasks. He also assisted both groups in establishing standard methods for estimating realistic drawing development times; these factored in drawing complexity, tool type, and other relevant attributes. Team members created the schedules by hand on large sheets of paper and posted them on the wall in a common area. The most time-critical activities were highlighted in red. A simplified version of one of these schedules is shown in Exhibit 7.4.

7-8

Page 9: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.4

Scenario 2: Time-Based Network for Tool Design Project (Simplified Version)

Within four months of implementing this new system, schedule performance had improved dramatically, the quality of work had increased, cross-functional conflict was diminished, and people were generally more satisfied with their work.

7-9

Page 10: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Schedule Display Formats

Activity-on-arrow (AOA): A type of network schedule display used to show when activities will occur during a project and also to make clear the sequential relationships between activities.

• Activity information (including a description of the activity and its estimated duration) appears on connecting arrows or arcs

• Nodes (represented by boxes, circles, or other two-dimensional shapes) indicate the beginning and ending points of activities.

• AOA networks in some configurations require what are known as dummy activities – dummy activities are used to show precedence, but have no time associated with them. 7-10

Page 11: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Schedule Display Formats

Activity-on-node (AON): A type of network schedule display used to show when activities will occur during a project and also to make clear the sequential relationships between activities.

• Activity information (including a description of the activity and its estimated duration) appears inside nodes (represented by boxes, circles, or other two-dimensional shapes)

• Arrows between nodes indicate the sequential relationships among activities to be performed in the project.

7-11

Page 12: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.5

Activity-on-Node and Activity-on-Arrow Schedule Displays

7-12

Page 13: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Concepts for Project Scheduling

• Schedule Display Formats• Activity-on-node• Activity-on-arrow

• Level of Detail• A high-level milestone schedule is used for big-

picture thinking about project plans & progress.• Milestone: An event in a project designating the point

at which a related set of activities has been completed, or at which a set of activities may begin.

• A highly detailed schedule will depict the sequence and timing of individual tasks.

• Types of Network Logic• Types of Precedence Relationships

7-13

Page 14: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.6

Dam Construction Megaproject (Program) with Subprojects

7-14

Page 15: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Types of Network Logic

Soft logic: A sequential relationship between activities that can be arranged in a number of ways, depending on the project manager or team’s preferences, resources available, or other circumstances.

Hard logic: A mandatory sequential relationship in which an activity must absolutely be completed before a successor activity may begin.

• In creating the initial schedule, adhere to hard logic first to avoid building false dependencies based on initial assumptions about resource availability of other circumstances that later may prove to be incorrect.

7-15

Page 16: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Types of Precedence RelationshipsFinish-to-start: A sequential relationship between tasks whereby the second task in the sequence cannot start until the first task in the sequence has finished, either immediately after the first task has finished or after a specified lag.•Lag or Delay: A specified amount of waiting time designated between sequential activities in a finish-to-start relationship.

Finish-to-finish: A sequential relationship between tasks whereby the second task in the sequence cannot finish until a specified time after the first task in the sequence has finished.

Start-to-finish: A sequential relationship between tasks whereby the second task in the sequence cannot finish until a specified time after the first task has started.

Start-to-start: A sequential relationship between tasks whereby the second task in the sequence cannot start until a specified time after the first task has started. This type of sequential relationship is often used for fast-tracking schedules. 7-16

Page 17: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.7

Finish-to-Start Relationship without Lag and with Lag: Skydiving Example

7-17

Page 18: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.8Start-to-Start Relationship with Overlapping Tasks: Party Invitation Example

7-18

Page 19: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Displaying and Interpreting Project Schedules

• Activity-on-Node Diagram

• Activity-on-Arrow Diagram

• Gantt Chart

• Schedule Graph (Time-Based Network)

The diagrams on the next several frames illustrate the application of these project schedule displays for a project to create a call center in India.

7-19

Page 20: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.9

AON (Activity-on-Node) Schedule for the Indian Call Center Project

7-20

Page 21: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.10

Activity-on-Arrow Diagram for the Indian Call Center Project

7-21

Page 22: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.12

Gantt Chart for the Indian Call Center Project

7-22

Page 23: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Critical Path and Float

• Critical path: The longest duration path of activities in a network schedule, which determines the anticipated total amount of calendar time a project will consume.

• Float or Slack: A metric used in project scheduling to indicate the length of time that a task not on the critical path can be delayed without jeopardizing the schedule.

7-23

Page 24: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.11

Path Analysis for Indian Call Center Project

7-24

Page 25: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Early-Start, Late-Start and Float• Early start schedule: A network schedule in

which every activity is set to begin at its earliest possible start time.

• Late-start schedule: A schedule in which all project activities are delayed to their latest possible start times.

• Float or slack: The length of time that a task not on the critical path can be delayed without jeopardizing the schedule.

• Free float: The amount of time an activity can be delayed from its early start time without delaying the early start of any activity that immediately follows it.

• Total float: The amount of time by which an activity can be delayed from its early start time without delaying the project beyond its anticipated end date.

7-25

Page 26: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.13

Early-Start Schedule Graph (Time-Based Network) for the Indian Call Center Project

7-26

Page 27: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.14

Late-Start Schedule Graph (Time-Based Network) for the Indian Call Center Project

7-27

Page 28: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.15

MS Project Output for the Indian Call Center Project: Network View

7-28

Page 29: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.16

MS Project Output for the Indian Call Center Project: Gantt View

7-29

Page 30: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Critical Path Algorithm• A mathematical algorithm used for assessing

the location of the critical path, free float, and total float on a network schedule. It involves:

1. Making a forward pass through the network to determine the earliest possible start and finish times for each activity

2. Making a backward pass to determine the latest possible start and finish times for each activity.

This method was developed and used by Du Pont in the 1950s to bring order and substantial time compression to projects involving the closure of chemical plants during routine maintenance procedures.

7-30

Page 31: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.17

Critical Path Algorithm

7-31

Page 32: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.17

Critical Path Algorithm

continued

7-32

Page 33: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.17

Critical Path Algorithm

continued

7-33

Page 34: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.17

Critical Path Algorithm

7-34

Page 35: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.18

Critical Path Algorithm Calculations for the Indian Call Center Project

7-35

Page 36: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.19

Team-Based Process for Creating the Project Schedule

continued7-36

Page 37: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.19

Team-Based Process for Creating the Project Schedule

7-37

Page 38: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.19

Team-Based Process for Creating the Project Schedule

7-38

Page 39: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.20

A Project Team Collaborating to Develop a Schedule

7-39

Page 40: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.21

Precedence Table for the Financial System Upgrade

7-40

Page 41: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.21

Network Diagram for the Financial System Upgrade Built from the Precedence Table

7-41

Page 42: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.21

Precedence Table and Network Diagram for the Financial System Upgrade

7-42

Page 43: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.22

Tips for Developing Network Schedules

Use Beginning and Ending Milestone Nodes If There is More Than One Activity at the Start or End of the Network. Begin every project with a single starting node and end every project with a single finish node. In some networks, there is a single beginning and a single ending task. If there is not, the team should create start and finish milestones to tie things together in the beginning and end.

Incorrect Form Correct Form

7-43

Page 44: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Place Task Information in One Place. For AON networks, all task information should be inside the node. The exception to this rule is when there is a designated lag between two tasks to show some sort of waiting time. For AOA networks, all task information should be above or below the task arrow.

Exhibit 7.22Tips for Developing Network Schedules

Incorrect Form for AON Network Correct Form for AON Network

7-44

Page 45: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.22Tips for Developing Network Schedules

Avoid Cycles or Loops. Eliminate instances where a set of connecting arrows would result in repeating a sequence of tasks that are meant to be performed only once.

Schedule Loop Example: A → B → C → D → A This Project Will Never Be Finished!

7-45

Page 46: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.22Tips for Developing Network Schedules

Be Sure All Tasks Lead to the End. Every activity should connect with others leading to the end of the project. Nothing should be hanging without a place to go.

Task C Does Not Lead to Any Other Activity or to the End of the Project.

7-46

Page 47: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.22

Tips for Developing Network Schedules

Be Consistent with Line Styles. Lines in an AON network should all be the same type, generally solid and not dashed. Dashed lines are reserved for use in specifying dummy activities in AOA networks and showing float in time-based networks.

Recognize that Some Tasks are Ongoing. A task that occurs during the entire life of a project and ends when the project is complete (e.g., monitoring performance or regular reporting to the sponsor) can be shown as a single task connected to the start node on one end and the finish node at the other end. These are known as hammock tasks.

7-47

Page 48: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.22

Tips for Developing Network Schedules

Be Sure All Tasks Lead to the End. Consider the example shown below. In this case, the line connecting “Assess user requirements” with “Test Web site” would be redundant because the relationship is already shown with the sequence Assess user requirements → Develop Web site → Test Web site.

7-48

Page 49: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Incorporating Probabilistic Concepts into Schedules: PERT

• Program Evaluation and Review Technique (PERT) or Three-point Estimates is a method for calculating probabilistic task time estimates first used by the U.S. military and based on three time estimates given for each task:

• an “optimistic” time estimate t(o), • a “pessimistic” time estimate t(p), • and a “most likely” time estimate t(m).

• Based on the Beta distribution, PERT uses the following equation to calculate an expected time estimate:

t(e) = t(o) + 4 t(m) + t(p)

6 7-49

Page 50: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.23

Beta Distribution Example for Commute Times

7-50

Page 51: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.24

Commuting Example with Three-Point Time Estimates

7-51

Page 52: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.25

Normal Distribution for Total Commute Time (Including Car, Carpool, Walk)

7-52

Page 53: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.26

Probability of a 53-Minute Commute Time

7-53

Page 54: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.27

Z-Table Cumulative Single Tail Probabilities (Area Under the Normal Curve)

7-54

Page 55: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Chapter Summary• Scheduling is a critical part of project planning. • Before a team develops a schedule, members must

understand the project’s purpose, agree on goals, select the best course of action, create a comprehensive WBS, assess project uncertainties, and estimate activity times.

• Schedules can be formal or informal, broad-brush or detailed, manually- or computer-generated.

• Several formats are available: AON networks, AOA networks, Gantt charts, and time-based networks.

• Project schedules are best created in a team environment. The result is better decision-making about sequencing, and a higher likelihood of commitment to time based goals. continued

7-55

Page 56: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Chapter Summary• Key concepts for project network schedules include

critical path, total float, and free float. • Anyone using project scheduling software should

make certain he or she understands these concepts before “going digital.”

• PERT is an extension of basic network scheduling methods that incorporates three point time estimates and allows for probability estimates of possible project completion times.

• Individuals who understand these concepts can apply them to varying degrees for improving time estimation accuracy, answering questions about possible scenarios, or managing client expectations.

7-56

Page 57: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Appendix 7A and 7B

Chapter 7

7-57

Page 58: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7:1A

Replacing Heat Exchange Equipment at the Cameron Co. AON Diagram

7-58

Page 59: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7:2A

Replacing Heat Exchange Equipment at the Cameron Co. AON Diagram

7-59

Page 60: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.1B

Network Diagram for Preparing the University Stadium for Graduation (Time Units in Days)

7-60

Page 61: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.2B

Percent of Normal Curve for a Low-Probability Outcome

7-61

Page 62: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exhibit 7.3B

Comparative Probabilities for Three Paths (Likelihood of Finishing within 25 Days)

7-62

Page 63: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Team Activities and Discussion Questions

and Exercises

Chapter 7

7-63

Page 64: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Team Activity 7- 2

High-Level Mind Map WBS for Transportation of Olympic Athletes to Competitive Venues

7-64

Page 65: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exercise 7-10

What errors do you see in the AON diagram below?

7-65

Page 66: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exercise 7 - 13

High Level Project Network for Development of New Performance Evaluation System

7-66

Page 67: Project Scheduling: Adding the Time Dimension Chapter 7 Copyright © 2010 by the McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin

Exercise 7 - 16

Network for Commercial Jet Design Project

7-67