By: Ali Y. YousefBy: Ali Y. Yousef 1

Project

• A project is a temporary endeavor designed to produce a unique product, service or result with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables), undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value.

2

Project Success Criteria

• On time• On budget• Meeting the goals that have been agreed

upon

3

Iron Triangle

4

The Typical PMs Role Overall responsibility for the successful

planning, execution, monitoring, control and closure of a project.

Primary point of contact with project sponsors

Key tasks Plans Meets Communicates

Project Management == Leadership5

10 Qualities of a PM

1. Inspires a Shared Vision

2. Good Communicator

3. Integrity & Honesty

4. Interest & Enthusiasm

5. Empathy & Understanding

6. Competence & Skill

7. Ability to Delegate Tasks

8. Cool Under Pressure

9. Team-Building Skills

10. Problem Solving Skills

6

What does a PM do?

• Development process divides development into phases and activities

• To execute it efficiently, must allocate resources, manage them, monitor progress, take corrective actions, …

• These are all part of the PM process• Hence, PM process is an essential part of

executing a project

7

PM Process Phases

• There are three broad phases– Before: Initiating and Planning– During

• Monitoring and control• Communication facilitation

– After: termination analysis• Planning is a key activity that produces a

plan, which forms the basis of monitoring

8

Project Manager

• Project managers need both leadership and management skills, with a ability for problem solving.

• Project managers are there to plan and manage the work – NOT to do it!

• Ultimately responsible for the Project’s Success

• Plan and Act• Focus on the project’s end

9

Project management

• is the application of knowledge, skills and techniques to execute projects effectively and efficiently. It’s a strategic competency for organizations, enabling them to tie project results to business goals — and thus, better compete in their markets.

• is the process and activity of planning, organizing, motivating, and controlling resources, procedures and protocols to achieve specific goals in daily problems.

10

Project Mgmt Process Groups• Initiating – Defines and authorizes the project • Planning – Describes how the project will be

managed • Executing – Helps the project groups work

together to complete the work • Monitoring and Controlling – Checks the

progress of the project and corrects problems.

• Closing – Formally closes each phase or the project and receives approval of the project work for the phase or project.

11

Project Mgmt knowledge Areas

12

• an area of project management defined by its knowledge requirements and described in terms of its associated process, practices, inputs, outputs, tools and techniques

1. Project Integration Management

2. Project Scope Management

3. Project Time Management

4. Project Cost Management

5. Project Quality Management

6. Project Human Resource Management

7. Project Communications Management

8. Project Risk Management

9. Project Procurement Management

PM Knowledge Areas & Process Groups

PM Process Groups / Knowledge Area Processes

Initiating Process Group

Planning Process Group Executing Process Group Monitoring & Controlling Process Group

Closing Process Group

Project Management Integration

Develop Project Charter Develop Prelim Project Scope Statement

Develop Project Management Plan

Direct and Manage Project Execution

Monitor and Control Project WorkIntegrated Change Control

Close Project

Project Scope Management

Scope PlanningScope DefinitionCreate WBS

Scope VerificationScope Control

Project Time Management

Activity Definition & SequencingResource EstimatingDuration EstimatingSchedule Development

Schedule Control

Project Cost Management

Cost EstimatingCost Budgeting

Cost Control

Project Quality Management

Quality Planning Perform Quality Assurance Perform Quality Control

Project HR Management

Human Resources Planning Acquire Project TeamDevelop Project Team

Manage Project Team

Project Communications Management

Communications Planning Information Distribution Performance ReportingManage Stakeholders

Project Risk Management

Risk Management PlanningRisk IdentificationQualitative / Quantitative Risk AnalysisRisk Response Planning

Risk Monitoring and Control

Project Procurement Management

Plan Purchases and AcquisitionsPlan Contracting

Request Seller ResponsesSelect Sellers

Contract Administration Contract Closure

13

Project Integration Management• effective integration of the processes required to

accomplish project objectives• processes include

1. project charter development

2. preliminary project scope statement development

3. project management plan development

4. project execution

5. monitoring and control of project work

6. Integrated Change Control

7. Close Project

5

Project Scope Management

• defines and controls what is and is not included in the project

• processes include

1. scope planning

2. scope definition

3. creation of a Work Breakdown Schedule

4. scope verification

5. scope control

15

Project Time Management• includes processes required for the timely

completion of a project• processes include

1. defining activities

2. sequencing activities

3. estimating resource activities

4. estimating duration of activities

5. developing the project schedule

6. controlling the project schedule

16

Project Cost Management

• planning, estimating, budgeting and controlling costs to ensure the project can be completed within the approved budget

• processes include

1. cost estimating

2. cost budgeting

3. cost control

17

Project Quality Management

• all activities that determine quality policies, objectives and responsibilities for the project to satisfy the needs for which it was undertaken

• processes include

1. quality planning

2. performing quality assurance

3. performing quality control

18

Project Human Resource Management

• processes that organize and manage the project team

• processes include:

1. human resource planning

2. acquiring the project team

3. developing the project team

4. managing the project team

19

Project Communications Management

• activities to ensure project information is timely and appropriately generated, collected, distributed, stored, retrieved and disposed of

• processes include

1. communications planning

2. information distribution

3. performance reporting

4. managing stakeholders

20

Project Risk Management

• processes to increase the probability and impact of positive events and decrease the probability and impact of negative events

• updated throughout the project• processes include

1. risk management planning

2. risk identification

3. qualitative risk analysis

4. quantitative risk analysis

5. risk response planning

6. risk monitoring and control21

Project Procurement Management• processes to purchase/acquire the products, services

or results needed to perform the project work• includes contract management and change control

processes to administer contracts or purchase orders• processes include:

1. planning purchases and acquisitions

2. contract planning

3. requesting seller responses

4. selecting sellers

5. contract administration

6. contract closure

22

PM Knowledge Areas & Process Groups

PM Process Groups / Knowledge Area Processes

Initiating Process Group

Planning Process Group Executing Process Group Monitoring & Controlling Process Group

Closing Process Group

Project Management Integration

Develop Project Charter Develop Prelim Project Scope Statement

Develop Project Management Plan

Direct and Manage Project Execution

Monitor and Control Project WorkIntegrated Change Control

Close Project

Project Scope Management

Scope PlanningScope DefinitionCreate WBS

Scope VerificationScope Control

Project Time Management

Activity Definition & SequencingResource EstimatingDuration EstimatingSchedule Development

Schedule Control

Project Cost Management

Cost EstimatingCost Budgeting

Cost Control

Project Quality Management

Quality Planning Perform Quality Assurance Perform Quality Control

Project HR Management

Human Resources Planning Acquire Project TeamDevelop Project Team

Manage Project Team

Project Communications Management

Communications Planning Information Distribution Performance ReportingManage Stakeholders

Project Risk Management

Risk Management PlanningRisk IdentificationQualitative / Quantitative Risk AnalysisRisk Response Planning

Risk Monitoring and Control

Project Procurement Management

Plan Purchases and AcquisitionsPlan Contracting

Request Seller ResponsesSelect Sellers

Contract Administration Contract Closure

23

Time Management

24

• The process of converting a general or outline plan for a project into a time-based graphic presentation using information on available resources and time constraints.

What is Scheduling?

25

Project Management Process

Next Launch the Plang Recruit and organize project

teamg Establish team operating

rulesg Level project resourcesg Assign work

Then Monitor & Control Progress

g Establish progress reporting system

g Set up change control processg Define problem escalation

processg Monitor progress vs. plang Revise project plan

Finally Close Out Projectg Obtain client acceptanceg Install project deliverablesg Complete project

documentationg Complete post-implementation

auditg Issue final project report

Then Develop Detailed Plan

g Identify project activitiesg Estimate activity durationg Determine resource

requirementsg Construct / analyze project

networkg Prepare project schedule

Start with Define the Project

g State need, problem or opportunity

g Define project objectivesg Identify success criteriag List assumptions, risks and

obstaclesg Define project scope and work

breakdown structureFeedbackWe are here

26

Elements of Developing a Project Plan

ClientSOW

WorkBreakdown Structure

ActivityDefinition

ResourcePlanning

ResourcePool

ActivitySequencing

ActivityDuration

Estimating

CostEstimating

ScheduleDevelopment

WorkPackages

Project PlanDevelopment

27

· To obtain the best detailed schedule, you must first have:– A Work Breakdown Structure (WBS). – A list of activities derived from each Work

Package. – A list of activities timing.– Staffing and resources required, or available, for each activity.

Preparing a Schedule

28

Create a work breakdown structure (WBS) “The Work Breakdown Structure (WBS) is the foundation for defining the project’s work as it relates to the objectives and establishes a structure for managing the work to its completion. The WBS defines: the project’s work in terms of activities that create deliverables.

First: Identify the project’s statement of work and main

tasks.

Second: Start by listing the major pieces (summary

tasks) of the project, and then map out the minor pieces within each major

piece.

Third: Continue to break down each piece until you

have sufficient level of detail (activities) to support your

plan. 29

Estimate Activities Duration

• Expert Judgment• Analogous estimating• Parametric estimating• Three-point estimating• Reverse Analysis

Start with estimate the time it will take to

complete each activity: Hourly, Daily, Weekly.

Then identify the Early start, Early Finish, Late

Start and Late Finish for each activity.

30

1. Identify the predecessor and the successor for each

activity.

2. Sequence the activities by determining the

dependencies relations among activities (FS, SS,

FF, SF).

Create DependenciesA dependency occurs when the start or finish of one activity depends

upon the start or finish of another

31

Assign Resources

• Manpower• Equipment• Material

1. Estimate the resources for each

activity:

2. Level the resources: resource assignments drive the duration for

each activity, the duration shortens or

lengthens as resources are added or removed

from an activity.

32

33

34

REPRESENTING & SCHEDULING PROJECT PLANS

The Most commonly used methods are :-

GANTT CHART

NETWORK DIAGRAMS (PERT/ CPM)

35

GANTT CHART• A graphical representation of a Project that shows

each task as a horizontal bar whose length is proportional to its time for completion.

• A GANTT Chart is a horizontal bar chart that illustrates a Project schedule.

• In the GANTT Chart Time is displayed on the horizontal axis and the Tasks/ Activities are arranged vertically from top to bottom, in order of their start dates.

• A detailed GANTT Chart for a large project might be quite complex and hard to understand. To simplify the chart Project manager can combine related activities into one Task.

36

GANTT CHART

A graphical representation of a Project that shows each task as a horizontal bar whose length s proportional to its time for completion.

GANTT CHART do not show how tasks must be ordered (precedence) but simply show when a task should begin and should end

GANTT Chart is often more useful to for depicting relatively simple projects or sub projects of a large project, the activities of a single worker, or for monitoring the progress of activities compared to scheduled completion dates..

37

GANTT CHART

38

NETWORK DIAGRAM Is a graphical depiction of Project tasks and their

inter-relationships.

The distinguishing feature of a Network Diagram is that the ordering of Tasks is shown by connecting with its predecessor and successor tasks. tasks.

Network Diagramming is a Critical Path Scheduling Technique used for controlling resources.

CRITICAL PATH SCHEDULING

A scheduling technique whose order and duration of a sequence of task activities directly affect the Completion Date of a Project

39

NETWORK DIAGRAM

You would use a Network Diagram when Project Tasks:-

Are well defined and have clear beginning and end point

Can be worked on independently of other tasks

Are ordered

Serve the purpose of project

40

PROGRAM EVALUATION REVIEW TECHNIQUE (PERT)

• One of the most difficult and most error prone activities when constructing a Project Schedule is the determination of the TIME DURATION for each task within a Work Breakdown Structure (WBS), specially when there is a high degree of complexity and uncertainty about a task.

• PERT is a technique used to calculate the Expected Time for a tasks.

• PERT is a technique that uses Optimistic time (O), Pessimistic time (P) and Realistic Time (R) estimates to calculate the EXPECTED TIME (ET) or a particular task.

41

PROGRAM EVALUATION REVIEW TECHNIQUE (PERT)

• PERT is a technique that uses Optimistic time (o), Pessimistic time (p) and Realistic Time (r) estimates to calculate the EXPECTED TIME (ET) or a particular task.

• The Optimistic time (o) and Pessimistic time (p) reflects the minimum and maximum possible periods of time for an activity to be completed.

• The Realistic time (r) or the Most likely time , reflects the Project manager’s “Best Guess” of the amount of time required for a task completion.

42

PROGRAM EVALUATION REVIEW TECHNIQUE (PERT)

CALCULATING EXPECTED COMPLETION TIME (ET)

o + 4r + p ET = ------------------- 6

Because the expected Completion time should be closer to the realistic time (r), it is typically weighed Four times more than the Optimistic time (o) and the Pessimistic time (p). Once you add these values together , it must be divided by 6 to determine the Expected Time for a task.

43

HOW TO CONSTRUCT A NETWORK DIAGRAM (PERT / CPM)

DEVELOPING A NETWORK DOAGRAM IS A FOUR STEP PROCESS:-

1. Identify each Project Activity to be completed

2. Determine Time estimates and calculate Expected Completion Time for each Activity

3. For each Activity, identify the immediate predecessor Activities

4. Enter the Activities with connecting arrows based on Dependencies and calculate Start and End times based on Duration and Resources.

44

PERT CHART SYMBOLSSLACK TIME:-

The Slack Time available for any Task is equal to the difference between the Earliest completion Time (ECT) and the Latest Completion Time (LCT)

SLACK TIME = (LCT – ECT)

CRITICAL PATH:- Is a sequence of Dependent Tasks that have the Largest sum of

Estimated Time (ET). IT is the Path that has no Slack Time built in.

• The Critical Path on PERT chart is shown with thick Dark line.

• To find the Critical Path begin with identifying all alternative paths that exist from Event 1 to the Final Event.

45

46

GANTT CHART vs PERT CHART

47

GANTT CHART vs PERT CHART• GANTT chart visually shows the duration of Tasks

whereas a PERT chart visually shows the sequence dependencies between tasks.

• GANTT visually shows the Time overlap of Tasks whereas a Network does not show time overlap but does show which tasks could be done in parallel.

• Some form of GANTT chart can visually show Slack Time available within an Earliest Start and Latest finish time..

• Most Project Managers find PERT very helpful for scheduling, monitoring and controlling Projects.

• PERT is recommended for Large Projects with high intertask dependencies and the GANTT chart for simpler Projects.

• Most Project Management Case Tools nowadays (eg. MS-Project ) allow the best feature of PERT to be incorporated into GANTT Charts. 48

Earned Value Management • Earned Value, EV or BCWP• Planned Value, PV or BCWS (after leveling!)• Actual Cost of Work Performed, AC or ACWP• Schedule Variance: SV = EV - PV (negative $=trouble)• Cost Variance: CV = EV - AC (negative $=trouble)• Schedule Performance Index: SPI = EV/PV (<1=trouble)

• (My favorite – you get this one free! Stay on schedule & you’ll stay on budget.)

• Cost Performance Index: CPI = EV/AC (<1=trouble) CV (%) = CV/EV SV (%) = SV/PV

49

Cost Management

50

What is Cost and Project Cost Management?

• Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange

• Costs are usually measured in monetary units like dollars

• Project cost management includes the processes required to ensure that the project is completed within an approved budget

51

Cost Management Plan

• A cost management plan is a document that describes how the organization will manage cost variance on the project

• A large percentage of total project costs are often labor costs, so project managers must develop and track estimates for labor

52

Project Cost Management Processes

• Cost estimating: developing an approximation or estimate of the costs of the resources needed to complete a project

• Cost budgeting: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance

• Cost control: controlling changes to the project budget

53

Basic Principles of Cost Management

• Most members of an executive board better understand and are more interested in financial terms than project terms, so project managers must speak their language– Profits are revenues minus expenditures– Profit margin is the ratio of revenues to profits– Life cycle costing considers the total cost of

ownership, or development plus support costs, for a project

– Cash flow analysis determines the estimated annual costs and benefits for a project and the resulting annual cash flow 54

Basic Principles of Cost Management• Tangible costs or benefits are those costs or

benefits that an organization can easily measure in dollars

• Intangible costs or benefits are costs or benefits that are difficult to measure in monetary terms

• Direct costs are costs that can be directly related to producing the products and services of the project

• Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project

• Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs

55

Basic Principles of Cost Management (continued)

• Learning curve theory states that when many items are produced repetitively, the unit cost of those items decreases in a regular pattern as more units are produced

• Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict– Contingency reserves allow for future

situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline

– Management reserves allow for future situations that are unpredictable (sometimes called unknown unknowns)

56

Types of Cost Estimates

57

Cost Estimation Tools and Techniques• Basic tools and techniques for cost estimates

– Analogous or top-down estimates: use the actual cost of a previous, similar project as the basis for estimating the cost of the current project

– Bottom-up estimates: involve estimating individual work items or activities and summing them to get a project total

– Parametric modeling: uses project characteristics (parameters) in a mathematical model to estimate project costs

– Three-Points Estimates – PERT: uses Program Evaluation and Review Technique 58

Cost Budgeting

• Cost budgeting involves allocating the project cost estimate to individual work items over time

• The WBS is a required input to the cost budgeting process since it defines the work items

• An important goal is to produce a cost baseline– A time-phased budget that project managers

use to measure and monitor cost performance

59

Cost Control

• Project cost control includes:– Monitoring cost performance– Ensuring that only appropriate project

changes are included in a revised cost baseline

– Informing project stakeholders of authorized changes to the project that will affect costs

• Many organizations around the globe have problems with cost control

60

Earned Value Management (EVM)

• EVM is a project performance measurement technique that integrates scope, time, and cost data

• Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals

• You must enter actual information periodically to use EVM

• More and more organizations around the world are using EVM to help control project costs

61

Earned Value Management Terms• The planned value (PV), formerly called the

budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period

• Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period

• The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed

• EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date 62

Earned Value: Example

On Day X:• PLANNED VALUE (Budgeted cost of the work

scheduled, BCWS) = 18 + 10 + 16 + 6 = 50• EARNED VALUE (Budgeted cost of the work

performed, BCWP) = 18 + 8 + 14 + 0 = 40

• ACTUAL COST (of the work performed , ACWP) = 45 (from your project tracking - not evident in above

chart) 63

18

8

14

Today

Earned Value: Example

64

Co

st (

Pe

rso

n-H

our

s)

Time (Date)

Planned Value: what your plan called for sending on the tasks planned to be completed by this date.

Today

Earned Value: value (cost) of what you have accomplished to date, per the base plan.

Actual Cost: what you have actually spent to this point in time.

Budgeted (Planned) Spending

Actual Spending

Earned Value

Earned Value: Example

65

Co

st (

Pe

rso

n-H

our

s)

Time (Date)

Today

Budgeted (Planned) Spending

Actual Spending

Earned Value Behind Schedule

Over Budget

Variance• Any schedule or cost deviation from a specific plan.• Used within an organization to verify the budget and

schedule for a project• Frequently used as a key component of plan reviews and

performance measurement• Must compare scheduling and budget variance at the

same time– Schedule variance: deviations from work planned – not

a measure of changes in cost– Cost variance: deviations from the

budget – not a measure of work scheduled vs. work completed• Example: applying more $$/people to a task may

maintain the schedule, but it adds to cost… schedule on track… over budget on expenses (cost)66

Performance Indices

• Cost Performance Index– CPI = BCWP/ACWP

• Schedule Performance Index– SPI = BCWP/BCWS

• Analysis– CPI > 1.0 exceptional performance– CPI < 1.0 poor performance– Similar for SPI

67

Earned Value & Variance: Example

On Day X:• PLANNED VALUE (BCWS) = 18 + 10 + 16 + 6 = 50• EARNED VALUE (BCWP) = 18 + 8 + 14 + 0 = 40• ACTUAL COST (ACWP) = 45 (from your project tracking)Therefore:• Schedule Variance = BCWP – BCWS = 40 - 50 = -10 (behind

schedule)• Schedule Performance Index = 40 / 50 = 0.8, or 80% of plan • Cost Variance = BCWP - ACWP = 40 - 45 = -5• Cost Performance Index = 40/45 = .89, or you’re getting an

89¢ return on every $1.00 (or, person-hour) spent on this project 68

18

8

14

The need for project management is becoming increasingly apparent in the world today. Speed, quality, and cost control are taking on increased significance in business, government, and non-profit sectors. Project management allows managers to plan and manage strategic initiatives that generate new revenue in expanding sectors of the market. Project management tools decrease time to market, control expenses, ensure quality products, and enhance profitability. Project management helps to sell products and services by positively differentiating them from their competitors. Project management is one of the most important management techniques for ensuring the success of an organization.

WHY PROJECT MANAGEMENT IS NECESSARY IN TODAY'S WORLD

69

• That's it! Now, you're ready to present your management plan and to use it to track and manage your project.

70

Ali Y. Yousef - Project Support Specialist. B.Eng., PMP ® @ CBCL LimitedLocation: Halifax, NS Canada Industry: Mechanical Engineering

Previous Companies: SBM Offshore, Halifax - CanadaGulf House of Trade and Contacting Co., Doha - QatarEl Concorde Ltd. Amman - Jordan

Professional MembershipJordanian Association Engineers (JAE)American Society of Mechanical Engineers (ASME)Canadian Council of Professional Engineers (CCPE)Project Management Institute (PMI ID No.2316875)

Email:[email protected]

71