Climate Survey Actions
Project Summary Sheet – January 2014
ContentsProject Name: North Turramurra Recreation Area (NTRA)Site Address: Curagul Road, North TurramurraWard: Wahroonga
Project Officer: Phillip Beninati, Strategic Projects - Contracts
Project DescriptionProject Stages: Page 4Current Works: Page 5Photographs and Plans: Pages 6 - 21Project Timeline: Page 22
North Turramurra Recreation Area
1 of 22
Climate Survey Actions Project Stages
Completed Works– Catchment Dam 100% Complete– Sewer Treatment Plant 100% Complete– New Hole 14 along Curagul Road 100% Complete– Preliminary Civil Works - Landfill remediation & stabilisation 100% Complete
Current Works Stage 1 and Stage 2– Bulk Earthworks Stage 1 construct six new golf holes 90% complete– Finishing Works Stage 1 construct six new golf holes 50% complete– Bulk Earthworks Stage 2 construct five new golf holes 80% complete – Finishing Works Stage 2 construct five new golf holes &
two practice greens 20% complete
Future Works– Stage 3 – Refurbishment of seven existing golf holes. Design Complete– Stage 4 – Playing fields Design Complete– Stage 5 – Sports precinct clubhouse amenities & carparks Concept design stage
4 of 22
Climate Survey Actions Current Works
Current works under construction include:
• Civil works – Slope ‘A’ works - stabilising earth berm & construction of a Gabion Basket Retaining Wall
Structure.– Slope ‘B’ works - construct a Gabion Basket Retaining Wall Structure, drainage & landfill
capping.– Slope ‘C’ works - construct a Semi contiguous concrete pile retaining wall & drainage at the toe
of Slope C.– Remediate the former North Turramurra Landfill site closed 1986.
• Bulk Earthworks – Construct the general landform of the new golf holes – Cut and fill operation requiring importation of significant volumes of imported landfill capping
sandstone, shale, clay, sand, gravel & topsoil. – Improved capping & drainage over landfill to reduce the flow of leachate & improve stability of
landfill slopes.
• Finishing Works – Shape, and place growing medium to landscape ,turf & grow in new golf holes.– Construct creek & wetland to convey stormwater flows– Final covering of suitable clean soil & a growing medium for planting turf, native grasses, &
selected shrubs & trees.5 of 22
Climate Survey Actions 4th Tee complex and Wetland
January 2014 - 4th Tee complex and wetland pond, sandstone wall, bridges & creek receive growing medium ready for planting
8 of 22
Climate Survey Actions Golf Course Finishing Works Stage 1
Irrigation January 2014 First mow January 2014
Early civil works January 2013
9 of 229/24
Climate Survey Actions Golf Hole 2 - Typical Tee Profile
Landfill cover material 600mm Megaflow Drainage Sandstone 500mm
Gravel 100mm Growing medium 250mm
Climate Survey Actions Green 2 treatment over landfill
High tensile geo-grid underlay Compactable clay base 11 of 22
Climate Survey Actions Slope C – April 2012 – December 2013
18 of 22
Landslips undermine Slope C and road access to leachate pumping station
Climate Survey Actions Stage 4 - Sports Fields
Detailed planning for sports fields, amenities, car parks, playground & walkways
Review of Environmental Factors, Geotechnical Investigation, Develop Scope of Work, Bill of Quantities and Budget Estimate for synthetic fields.
20 of 22
Climate Survey Actions Project Timeline
• Preliminary works: Completed May 2013• Civil Works Stage 1: Practical Completion September 2013• Civil Works Stage 2: March/early April 2014• Golf Finishing Works Stage 1: Under construction, five new golf holes over
former landfill, due for completion early 2014• Golf Finishing Works Stage 2: Contract awarded construction to follow Civil
works Stage 2, due for completion late 2014• Stage 3: Design plans for the refurbishment of seven existing golf holes.
Progressive construction works are anticipated to be completed mid to late 2015
• Stage 4: Design plans for the construction of multi-purpose playing fields and amenities. Construction works are anticipated to be completed mid-2015
• Stage 5: Consultation and construction of the clubhouse/community room and car parking is in the early stages of design. Construction works anticipated to be completed late early 2016
22 of 22