project: talley road phase i non-tolled (bc03)

1
Limits: Potranco Road (FM 1957) to Wiseman Blvd. Contractor: Texas Sterling Construction Engineer: CP&Y, Inc. Construction Cost: $22,305,572.62 Construction NTP: 11/11/19 Contract Completion Date: 07/05/22 Projected Completion Date: 04/25/22 Scope: Expand from an existing two-lane rural roadway to a four-lane urban roadway consisting of two 12-foot travel lanes in each direction, a median, curb, and sidewalk. Status: 40% Paid Out, 41% Time used Monthly Activity: Installing 16” D.I. Watermain on Talley Road Installing 24” RCP on Talley Road. Installing 4X4 SBC Boxes Installing culvert boxes Installing CMP 30” pipe and structure Placing and building forms for bridge deck. Updated: March 09, 2021 ALAMO REGIONAL MOBILITY AUTHORITY COUNTY OF BEXAR Project: Talley Road Phase I – Non-Tolled (BC03)

Upload: others

Post on 08-May-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project: Talley Road Phase I Non-Tolled (BC03)

Limits: Potranco Road (FM 1957) to Wiseman Blvd.

Contractor: Texas Sterling Construction

Engineer: CP&Y, Inc.

Construction Cost: $22,305,572.62

Construction NTP: 11/11/19

Contract Completion Date: 07/05/22

Projected Completion Date: 04/25/22

Scope: Expand from an existing two-lane ruralroadway to a four-lane urban roadway consistingof two 12-foot travel lanes in each direction, amedian, curb, and sidewalk.

Status: 40% Paid Out, 41% Time used

Monthly Activity:

• Installing 16” D.I. Watermain on Talley Road

• Installing 24” RCP on Talley Road.

• Installing 4X4 SBC Boxes

• Installing culvert boxes

• Installing CMP 30” pipe and structure

• Placing and building forms for bridge deck.

Updated: March 09, 2021

ALAMO REGIONAL MOBILITY AUTHORITYCOUNTY OF BEXAR

Project: Talley Road Phase I – Non-Tolled (BC03)