project timetable feasib

3
Activities/Tasks Predeces sor Activity Start Date Finish Date Duration A. Feasibility Study None September 1 2015 November 30 2015 91 Days B. Pulling up of Equity A December 1 2015 December 31 2015 31 Days C. Registration B January 1 2016 January 15 2016 15 Days D. Renovation B January 1 2016 March 31 2016 91 Days E. Equipment & Supplies D April 1 2016 April 30 2016 30 Days F. Orders and Receipts of Console Gaming Equipment D April 1 2016 April 30 2016 30 Days G. Installation of Gaming Equipment and Other Supplies D April 1 2016 April 30 2016 30 Days H. Hiring and Training of Personnel G May 1 2016 May 31 2016 31 Days I. Start of Operations H June 1 2016 Project Schedule Business purpose or objectives are set to be accomplished. Realization of these objectives can be obtained through proper planning and scheduling of specific business activities to be undertaker. The proportion of a project schedule is very important. And to concretize the various process/sequences, the proponents involved are a GANTT chart that will control and monitor the process. Areas of consideration: Feasibility Study Duration: From September 1 2015 to November 30 2015

Upload: william-andrew-gutiera-bulaquena

Post on 02-Feb-2016

10 views

Category:

Documents


0 download

DESCRIPTION

Timetable sample of Feasib

TRANSCRIPT

Page 1: Project Timetable Feasib

Activities/Tasks Predecessor Activity

Start Date Finish Date Duration

A. Feasibility Study None September 1 2015

November 30 2015

91 Days

B. Pulling up of Equity A December 1 2015

December 31 2015

31 Days

C. Registration B January 1 2016 January 15 2016 15 DaysD. Renovation B January 1 2016 March 31 2016 91 DaysE. Equipment & Supplies D April 1 2016 April 30 2016 30 DaysF. Orders and Receipts of

Console Gaming Equipment

D April 1 2016 April 30 2016 30 Days

G. Installation of Gaming Equipment and Other Supplies

D April 1 2016 April 30 2016 30 Days

H. Hiring and Training of Personnel

G May 1 2016 May 31 2016 31 Days

I. Start of Operations H June 1 2016

Project Schedule

Business purpose or objectives are set to be accomplished. Realization of these objectives can be obtained through proper planning and scheduling of specific business activities to be undertaker. The proportion of a project schedule is very important. And to concretize the various process/sequences, the proponents involved are a GANTT chart that will control and monitor the process.

Areas of consideration: Feasibility Study

Duration: From September 1 2015 to November 30 2015

The feasibility study will be completed within this period to which the researchers conducted a comprehensive study like interviews and surveys. The also involves an analysis of market, technical and financial feasibility of the business.

Areas of consideration: Putting up of equity

Duration: From December 1 2015 to December 31 2015

Collection of cash contribution from the proponents for the capitalization of the business will take place within this period. Capitalization ranges from P500,000 to P700,000, thus requiring more time to put up the required capitalization.

Page 2: Project Timetable Feasib

Areas of consideration: Registration

Duration: From January 1 - 15 2016

Areas of consideration: Renovation

Duration: From January 1 2016 to March 31 2016

Aldecoa Drive, Brgy. Daro, Dumaguete City is the best location for our business because university and other schools are near the place and it is very accessible to the public. Furthermore, the place is surrounded by a number a boarding houses for students. The building, intended as its business locale is family owned.

Areas of consideration: Equipment and Supplies

Duration: From April 1-30 2016

The owner will have to canvas the console gaming equipment, furniture and other supplies for the Gaming Cafe which aims to get the lowest price but with high quality. The one who will give the better offer is the first priority.

Areas of consideration: Orders and receipts of computer equipment and other supplies

Duration: From April 1-30 2016

Orders of gaming equipments and other supplies should be listed for the purpose of monitoring. Receipts should be issued to determine the mode of payment.

Areas of consideration: Installation of computer equipment and other supplies

Duration: From April 1-30 2016

Delivery and installation of the console gaming equipments and other supplies/equipments to be used by the business for giving a quality service should be done during this period.

Areas of consideration: Hiring and training of personnel

Duration: From May 1 – 31 2016

During this period, the partners will train its employees/workers for the different jobs assigned.

Areas of consideration: Start of the Operation

Duration: June 2016

The business will start during this period. Its goal is to give quality service at the most affordable price possible.