project : tpi and monitoring of physical & financial
TRANSCRIPT
![Page 1: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/1.jpg)
To, Fichtner Consulting Engineers (India) Pvt. LTD.
Executive Engineer 9th Floor, Menon Eternity,
Basti, Uttar Pradesh 165, St. Mary’s Road, Alwarpet
Chennai – 600 018, India
Phone +91 44 4593 2600
Fax +91 44 4593 2809
Internet www.fichtner.co.in
Kind Attn:
Mr. Rehan Farooqui Our reference FCE-6220163-TPI-RPT-CIVIL-290
Contact person B.R.Lakshmi Narasimhan
Direct dialing +91 44 4593 2612
E-mail [email protected]
Date 11.10.2021
PROJECT : TPI and Monitoring of Physical & Financial Progress for Various Rural Water Supply Projects
CLIENT : State Water and Sanitation Mission, Government of Uttar Pradesh
Dear Sir,
Please find enclosed the following document(s) issued as indicated below.
Thanking you and assuring you of our best attention.
Very truly yours,
for FICHTNER Consulting Engineers (I) Pvt. Ltd.,
Sunil Kumar Giri M J Arulmozhikannan
Project Manager Team Leader-Basti Cluster
Encl. : As attached
In
R Issued for Review and comments C Issued for Construction
Issued for Information
T Issued for Tender purposes D Issued for Distribution
Purpose Code
A Issued for Approval AB Issued as “As Built”
P Preliminary In
DOCUMENT TRANSMITTAL
1 0
TitleRev
FCE-6220163-TPI-RPT-
CIVIL-290Soft Copy
DOC/DRG No.S. No. SOFT COPY
Third Party Inspection (TPI) for Orwara
Water Supply Scheme, Block: Saughat ,
Dist: Basti
HARD
COPY
Hard Copy
PURPOSE
CODE
Registered Office: FICHTNER Consulting Engineers (India) Pvt. Ltd.,
Menon Eternity, 9th Floor, 165, St. Mary’s Road, Alwarpet, Chennai – 600 018, India
CIN: U74210TN1987PTC014366
![Page 2: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/2.jpg)
S. No. Particulars
1 Name of District
2 Name of Block
3 Name of Panchayat
4 Name of Village
5 Name of Scheme
6 Name of Work
7 Name of TKC
8TKCs Agreement No.
& Date
9 Bill No. & Date
10 Amount of Bill (In Rs.)Total
AmountWithout GST
11
Type of Bill (Supply/
Laying/Construction/ot
her)
12 Date of Bill Received
13 Date of Inspection
14
14.1Name & Designation of
UPJN RepresentativeJunior Engineer
14.2Name & Designation of
TPIA RepresentativeQA/QC Engineer
14.3Name & Designation of
TKC RepresentativeSite Engineer
I
Mr. Sushil Anand
Mr. Raj Kumar Singh
Details of Inspecting Persons
M/s Anand Construction Company & M/s Amar Pratap
Singh (J.V.)
Name of Document
TPI for Monitoring and Supervision of various Rural Water Supply Projects under Jal Jeevan Mission
Inspection of Orwara- Rectrofitting work under Water Supply Scheme.
Bill Inspection Report
16.08.2021
Saughat
Orwara
Orwara
Orwara Water supply scheme
Water supply (scheme)
A. GENERAL DETAILS
BILL 642(L)
40 /E.E./ 2020-2021 Date- 20.10.2020
M/s Anand Construction Company & M/s Amar Pratap Singh (J.V.)
Basti
Information
Dismentling and Valve chamber work
06.09.2021
265,440 237,000
B. Details of documents
1/6
![Page 3: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/3.jpg)
1
2
3
4
5
II
1
2
3
4
5
6
7
8
9
10
11
III
1
2
3
4
5
6
7
8
9
10
11
IV
1
2
3
4
5
6
7
8
9
10
V
1
Water Quality Test Report
Not applicable under Current RA Bill
Over Head Tank
Payment terms & Conditions/breakup
Slump Test Report
Cube Test Report
Steel Test Report (MTC)
Steel Test Report (MTC)
Not applicable under Current RA Bill
Aggregate (Fine & Coarse) Test Report
Slump Test Report
Cube Test Report
Soil Test Report
Steel Test Report (MTC)
Provided
Certification from TKC that all these items are not claimed previously. Not Provided
Provided
Provided
Provided
Silt Content Test Report for sand
Geo Electric Resistivity Tomography Report
Bore Well
Water Quality Test Report
Silt Content Test Report for sand
Pipe Test Report (MTC)
Staff Quarter
Design Mix
Slump Test Report
Cube Test Report
Soil Test Report
Brick test report
Cement Test Report (MTC)
Aggregate (Fine & Coarse)Test Report
Silt Content Test Report for sand
Pipe Test Report (MTC)
BOQ & Price Schedule
RA Bill
Previous claimed bill ( if any)
Brick Test Report
Cement Test Report (MTC)
Pump house
Design Mix
Cement Test Report (MTC)
Aggregate (Fine & Coarse) Test Report
Soil Test Report
Design Mix
Water Tightness Test Report
Water Quality Test Report
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
2/6
![Page 4: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/4.jpg)
2
3
4
5
6
VI
1
2
3
4
VII
1
2
3
VIII
1
2
3
C. Work status details (Write down all items claimed in the RA bill)
C.B. item No.
33
36
107
108
Pipe (DI/ HDPE)Test Report (MTC)
FHTC
Valves Test Report (MTC)
Specials (Bends/ Tees/ Reducers) Material Test Report (MTC)
Campus Development Works
Boundary wall Works
Main Gate, Wigat Gate
Approach Road
Applicable
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Provided
Provided
Provided
Provided
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Not applicable under Current RA Bill
Pipe (GI/MDPE) Test Report (MTC)
Specials (Saddle, Ferrules, Tap) Material Test Report (MTC)
Household Service Connection List
Compressor Test Report
Yield Test Report - OP Unit
Verticality Test Report
Strata Chart
Distribution System
Field Hydro Test Report
Water Test Laboratory
Description of itemsObservation on quality of work as per site inspection (Defects/ General
Observations / Remedial Measures)
During site visit, on sampling basis, it is observed that 1.Reinstatement
of CC road surface is carried out and found to be acceptable.
2.Photograph is attached for reference
Reinstatement of above dismantled road surface with old and new materials including supply of all materials, labour, T&P etc. required for
proper completion of the work.
interlocking
Supply and fixing in position including supply of jointing materials such as nuts-boalt, rubber insertion whitelead,valves and specials
required etc. complete of the following size of C.I.D./F. Sluice valves, scourvalves,20mm dia scewed down type air valve and fire hydrant
containing 80mm dia sluice valve and itsaccesories as per latest I.S. specification including F.O.R. destination, all taxes and insurance
etc.complete for proper completion of work.
Sluice valve Sluice valves are installed and currently in working condition
3/6
![Page 5: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/5.jpg)
109
110
111
112
113
114
115
116
117
122
34
43
4
Sluice valves are installed and currently in working condition
80 mm dia Sluice valve Sluice valves are installed and currently in working condition
50 mm dia Scour valve Sluice valves are installed and currently in working condition
15 mm dia Air valve Sluice valves are installed and currently in working condition
Fire Hydrent Sluice valves are installed and currently in working condition
Provides all material and labours
T&P required for the proper repair
Boundary wall Gate as per
instruction of E.I.C.
During site visit, on sampling basis, it is observed that
1. Durring the inspection of site, where are break of boundary wall gate repair as per required
area of the wall and also maintain finishing surface wall.
2. Photograpph is attached for refrence
Electronic type dozer of6LPH capacity
with 200 litre with accessories.
During site visit, on sampling basis, it is observed that
1.Electronic type dozer & its Pvc Tank of 200 L capacity accessories work already completed &
in functioining condition. As per the visual inspection work is already installed and currently in
working condition.
2. Photograpph is attached for refrence
During site visit, on sampling basis,it is observed that 1.Road
crossing work is carried out before the engageemnet of Tpi. Based on observation it is found to be
completed.
2.Photograph is attached for reference
Reinstatement & completeion of road
crossing with old and new materials
including supply of all materials, labour,
T&P etc. required for proper completion
of the work.
125 mm dia Sluice valve Sluice valves are installed and currently in working condition
100 mm dia Sluice valve
(i) Air valve chamber Sluice valves are installed and currently in working condition
(i) Fire Hydrent chamber Sluice valves are installed and currently in working condition
Supply of all materials, labour, T&P etc.complete for construction of following chamber as per departmen type design.
Sluice valve chamber (masonary Type) Sluice valves chamber already installed and currently working condition
4/6
![Page 6: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/6.jpg)
Bill
Verification
Status
a) Work has been completed with All Households in the village provided with FHTC
b) Work is in Progress with All households in the village are being targeted with FHTC
c) Work found ok based on sample checking
d) Work is satisfactory with minor deviations
e) Work is unsatisfactory with major incompletions
f) Work is highly unsatisfactory with major works undone
g) Bill returned due to unavailability of major documents
h) Bill is irrelevant
Status
Name Contractor Mr. Rehan Faroqui
Designation Executive Engineer - Jal Nigam
Signature
c) Work found ok based on sample checking
Reason
D. Status
E. Other observations
As the TPI was asked to conduct the inspection after completion of the work by TKC, therefore the above observations are specifically for the
overall works executed on sample basis and not for individual items which were not visible. The TKC may be directed from your end to take
corrective measure at the earliest.
Rectification of above mentioned defects and submission of pending documents and reports may be ensured before release of payment to
Contractor.
Also, adherence of Payment terms and conditions as per contract agreement done between UPJN and TKC may be referred before
releasing the payment.
Verified with
Observations
Returned with
Observations
1. Considering climate condition, it is advised to store material including reinforcement in proper manner
2. Advised to follow all safety procedure during construction. How ever silt contant test, slump test must be provided before releasing of payment by clint.
Team Leaderof TPIA Inspecting Engineer (QA/QC )of
TPIA
Mr.M J
Arulmozhikannan Mr. Raj Kumar Singh
Third Party Inspection Agency (TPIA)
5/6
![Page 7: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/7.jpg)
1) All photographs shall be Geo Tagged photos with Location, Date and Time
2) Photos shall be enclosed for each component claimed in the bill.
3) Photos shall be enclosed for all the Defects/ Observations mentioned under B. Work Status Details
4) Description shall be written under each photograph indicating the comment/observation/ status of work
SNAPSHOTS OF SITE OBSERVATION
6/6
![Page 8: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/8.jpg)
![Page 9: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/9.jpg)
![Page 10: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/10.jpg)
![Page 11: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/11.jpg)
![Page 12: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/12.jpg)
![Page 13: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/13.jpg)
![Page 14: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/14.jpg)
1
Fig-1 Inspection of Gate.
Fig-2 Installation of sluice chamber
![Page 15: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/15.jpg)
2
Fig-3 Inspection of Electronic type dozer of6LPH
Fig-4 Inspection of chamber
![Page 16: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/16.jpg)
3
Fig-3 Inspection of clamber.
Fig-3 Inspection of BOE.
![Page 17: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/17.jpg)
![Page 18: PROJECT : TPI and Monitoring of Physical & Financial](https://reader034.vdocument.in/reader034/viewer/2022042219/625a000e3f42ce456d5d39b7/html5/thumbnails/18.jpg)