The Project Academy Series: Feb 22 nd and 26th, 2016 Project Transitions: People, Process and Technology California Department of Child Support Services

Upload: trantram

Post on 01-Feb-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

The Project Academy Series:

Feb 22nd and 26th, 2016

Project Transitions:

People, Process and Technology

California

Department of Child Support Services

Page 2: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Anthony Blue:

Branch Chief, IT Infrastructure, DCSS

Catherine Lanzaro:

Branch Chief, IT Applications, DCSS

Suzie McBride:

Section Manager, Enterprise Operational Data, FTB

2

Welcome and Introductions

Page 3: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Objectives

CCSAS Project Background

Business Process / Operational Transitions

Staff Transitions

Technology Transitions

Measures for Success

Questions

3

Agenda

Page 4: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Learn the Three Types of Transitions

Business Process / Operational Transitions

Staff Transitions

Technology Transitions

Understand Transition Tools

Learn How to Measure Success

4

Objectives

Page 5: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Venture outside your comfort zone. The rewards are worth it!

– Rapunzel,Tangled

5

Transition Ice Breaker

Page 6: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

6

Benefits of

Transition

Personal Growth

Flexibility

Improvement

The Snowball Effect

Strength Progress

Opportunities

Fresh Start

Routine

Page 7: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

7

Page 8: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

CCSAS Project Background

California Child Support Automation

System (CCSAS)

Transition Activities/Approach

Managing the Transition

Business Process / Operational Transitions

Transition Planning

Staff Transitions

Technology Transitions

8

Page 9: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Managing the Transition

Define Your Team

Ensure Any Sub-Teams Are Chartered

Manage Communications

Stakeholder

External Interactions

Internal

Quality Management

Change Control

Risks

Issues

Transition In / Out

9

Page 10: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Transition: Are you In or Out?

Every Transition Has Two Primary Efforts

’Transition Out’ which is the turning over of

an already built system, artifacts, and

responsibilities

’Transition In’ which is the definition and

implementation of ongoing/future systems,

artifacts, and responsibilities

10

Page 11: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Transition: In or Out? (cont.)

The ‘Transition Out’ effort consists of

itemizing and making available the

requested ‘as is’ application code,

hardware products, software products,

tools, data, and documentation

The ‘Transition In’ effort is comprised of

evaluating the ‘as is’ artifacts and then

defining and implementing the ‘to be’

system

11

Page 12: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Transition Planning

Business Processes

Objectives

Transitioned Services

Helpdesk

End User Support

Visual

12

Business Process / Operational Transitions

Page 13: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Transition Planning: Business Processes

13

Account Management

Problem Management (Operations)

Change Management (Operations)

Recovery Management

On-line/Batch Processing Management

Performance and Capacity Management

Operations Monitoring

Help Desk Management

Security Management

Service Level Management

CSE and ECSS Production Support

Change Management (CCSAS)

System Configuration Management

Application Development/Testing

Requirements Management

Systems Management

(Database Support, Environments Architecture)

Performance and Capacity Management

Knowledge Management

Problem Resolution Management

Disaster Recovery

Page 14: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Transition Planning: Objectives

To avoid negative impacts to the business during

system transition

To transition management of system support

operations (helpdesk, LCSA support,

configuration management, etc.) responsibilities

to DCSS

To migrate system hardware from contracted

Data Center to State Data Center

To transition management of software

development and maintenance responsibilities

from contractor to DCSS 14

Page 15: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Transition Planning: Transitioned Services

15

Services Currently Provided by the Business Partner

Managed Services DCSS Provided Services (CSE Specific)

eBHC Project Office – Tech ArchAIX System Admin

- Performance Monitoring (I/O, CPU, Memory)

- Coordinate hardware changes

- Coordinate OS Upgrades/patch

- Application Software installation, upgrades and

patches

- System tuning (Kernel, network)

- Forecasting and Capacity Planning

- System Monitoring (File System, Disk Capacity)

- Problem Identification and Resolution

Backup and Recovery

Batch Operation

- Level 1 Support

- Level 2 Support

Batch Scheduling

- Tivoli Workload Scheduler

Change and Problem Management

Data Center HIDS/NIDS

- Security Monitoring 24x7x365

- Security Controls Policy

Data Center Facility Manager

Database Support

- Monitoring (Uptime)

- Backup and Recovery

- Perform upgrades and patches (Prod)

- Provide 24x7x365 Support

Disaster Recovery

Hardware Support

- Hands and Eyes

- Hardware upgrades

- Monitoring (Uptime)

- OS Upgrades and patches

- Problem Identification and Resolution

- SAN Hardware Support

- Tape and Media Support

ID Management – UNIX and Windows

- Create/Delete User IDs

- Reset/Unlock User Accounts (Prod)

Infrastructure Architect

Infrastructure Security Architect

Intel System Admin

- Performance Monitoring (I/O, CPU, Memory)

- Coordinate hardware changes

- Coordinate OS Upgrades/patch

- Application Software installation, upgrades and patches

- System tuning (Kernel, network)

- Forecasting and Capacity Planning

- System Monitoring (File System, Disk Capacity)

- Problem Identification and Resolution

Middleware Support – Application Software

- Installation and Configuration

- WebSphere, HTTP Server, Wily,

Pitney Bowes, Adobe, MQ, Hyperion

Network/Firewall

- Define and Apply Rules

- Document Operation and Authorization

Process

Offsite Tape Management

Operations

- Monitor Systems (Uptime, Daily Matrix)

- Business Hour Support Time

- On Call Incident Management

- Restart Processes

- Document Issues/Resolutions

Performance Architect

Storage Area Network (SAN)

- Disk Allocation

- Forecasting and Capacity Planning

- Define Backup and Restores Procedures

- Performance Tuning

- Upgrade and Patches

AIX System Admin

- Authorize Hardware changes

- Authorize OS Upgrades/patch

Backup and Recovery

- Define Procedures

Batch Operation

- Level 3 Support

Batch Scheduling

- Develop Batch Schedule

Database Support

- Manage Databases

- Perform upgrade and patches (Non-Prod)

- Provide 24x7x365 Support

Disaster Recovery

- Approve DR Plan

- Participate in planning DR exercise

- Perform DR Task

ID Management

- Reset/Unlock Non-Production User

Accounts

Infrastructure Architect

Infrastructure Security Architect

Intel System Admin

- Authorize Hardware changes

- Authorize OS Upgrades/patch

LCSA Support

- E-mail, Anti-Virus, Client Software, TCM

- Network Support

- Security

- Windows Admin/Domain

- Hardware/Software Installation

- Software Distribution Packaging

Middleware Support

- Coordinate Application Software Updates

Network/Firewall

- Authorize and coordinate network changes

Performance Architect

Storage Area Network

- Authorize Disk Allocation

AIX System Admin

- Performance Monitoring (I/O, CPU, Memory)

- Authorize and Coordinate hardware changes

- Authorize and Coordinate OS Upgrades/patch

- Application Software installation, upgrades and patches

- System tuning (Kernel, network)

- Forecasting and Capacity Planning

- System Monitoring (File System, Disk Capacity)

- Problem Identification and Resolution

Backup and Recovery

- Define Procedures

Batch Operation

- Level 3 Support

Batch Scheduling

- Tivoli Workload Scheduler

- Develop Batch Schedule

Change and Problem Management

Database Support

- Manage databases

- Perform upgrades and patches

- Provide 24x7x365 Support

Disaster Recovery

- Approve DR Plan

- Participate in planning DR exercise

- Perform DR Task

ID Management – UNIX and Windows

- Create/Delete User IDs

- Reset/Unlock User Accounts

Infrastructure Architect

Infrastructure Security Architect

- CSE Application

Intel System Admin

- Performance Monitoring (I/O, CPU, Memory)

- Authorize and Coordinate hardware changes

- Authorize and Coordinate OS Upgrades/patch

- Application Software installation, upgrades and patches

- System tuning (Kernel, network)

- Forecasting and Capacity Planning

- System Monitoring (File System, Disk Capacity)

- Problem Identification and Resolution

LCSA Support

- E-mail, Anti-Virus, Client Software, TCM

- Network Support

- Security

- Windows Admin/Domain

- Hardware/Software Installation

- Software Distribution Packaging

Middleware Support – Application Software

- Installation and Configuration

- WebSphere, HTTP Server, Wily,

Pitney Bowes, Adobe, MQ, Hyperion

Network/Firewall

- Define Rules

- Document Operation and Authorization Process

- Authorize and coordinate network changes

Performance Architect

Storage Area Network (SAN)

- Disk Allocation

- Forecasting and Capacity Planning

- Performance Tuning

- Authorize and coordinate upgrades and patches

Backup and Recovery

Batch Operation

- Level 1 Support

- Level 2 Support

Data Center HIDS/NIDS

- Security Monitoring 24x7x365

- Security Controls Policy

Database Support

- Monitoring (Uptime)

- Backup and Recovery

Data Center Facility Manager

Disaster Recovery

Hardware Support

- Hands and Eyes

- Hardware upgrades

- Monitoring (Uptime)

- OS Upgrades and patches

- Problem Identification and Resolution

- SAN Hardware Support

- Tape and Media Support

Infrastructure Security Architect

Network/Firewall

- Apply Rules

- Document Operation and Authorization

Process

Offsite Tape Management

Operations

- Monitor Systems (Uptime, Daily Matrix)

- Business Hour Support Time

- On Call Incident Management

- Restart Processes

- Document Issues/Resolutions

Performance Architect

Storage Area Network (SAN)

- Backup and Recovery

- Upgrade and Patches

* Note: Blue Highlighted Text indicate this service can be provided by DCSS or Managed Services

Page 16: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Help Desk: End User Support

Help Desk Plan (call and incident process)

Help Desk Integration

Service Level Management

Incident Tracking and Management

Staffing Model

16

Page 17: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Help Desk: Visual

17

DCSS CSE Help Desk

Help Desk – Boulder, CO.CSE Help Desk Agent

- Level 1 System Support

CSE Help Desk Manager

CSE Help Desk Team Lead

CSE Problem Process Coordinator

CSE Problem Resolver

CSE Problem Resolver Group Leader

Customer Satisfaction Manager

- Surveys

Facility

- 800 Number

- CentreVu

- ManageNow

- eESM

- Scripts

- Status Board

- Problem Interface Flow

- Enterprise Systems Management Reporting Technology

CSE Help Desk Agent

- Level 2 System Support

- Level 3 System Support

Service Entitlement Failure State Contact

State Liaison

Project Office

CSE Help Desk Agent

- Level 1 System Support

- Level 2 System Support

- Level 3 System Support

CSE Help Desk Manager

CSE Help Desk Team Lead

CSE Problem Process Coordinator

CSE Problem Resolver

CSE Problem Resolver Group Leader

Customer Satisfaction Manager

- Surveys

Facility

- 800 Number

- CentreVu

- ClearQuest (Replacement for ManageNow)

- eESM

- Scripts

- Status Board

- Problem Interface Flow

- Enterprise Systems Management Reporting Technology

Service Entitlement Failure State Contact

State Liaison

BP CSE Help Desk

* Note: Red Highlighted Text indicate application will not migrate to DCSS.

Page 18: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Knowledge Management

Organizational Change Management

Class Exercise

Break

18

Staff Transitions

Page 19: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Definition: Knowledge

Management is the process

of capturing, distributing, and

effectively using knowledge

20 year old concept/term

Has not been mastered,

close, but not yet

Be purposeful in your KM

efforts

19

Knowledge Management (KM)

Page 20: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Why Start?

When to Start?

How to Start?

20

Knowledge Management (KM)

Page 21: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

What Format?

PowerPoint

One on One Training Program

Meetings

Documentation

Cross Team Training

Training Guide or Wiki

Video or Audio Recordings

21

Knowledge Management (KM)

Page 22: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

KM in Action – Enterprise Data to Revenue

22

Overview

Approach

Roles

Format

Handouts

KM

IDP

KM

IDP

Transition

Page 23: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

OCM is an approach to transitioning an

organization, its groups and individuals from

their current state to a new state

It’s all about managing the most important part

of change…the People!

Links:

http://www.cio.ca.gov/opd/itla/itla-21.html

http://www.cio.ca.gov/opd/project_academy.html

23

Organizational Change Management

Page 25: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #1: Keep Calm

25

Page 26: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

CCSAS Migration

26

Page 27: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

EDR Transition

27

Page 28: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #2: Know Technical Requirements

28

CCSAS Migration EDR Transition

Re-Host the System to a State

Facility

Inventory, Assess EDR Solution,

Roles, Processes and Tools

Plan Future State Organization Plan Future State Organization

Assume Ownership of Processes Assume Ownership of Persistent

Processes

Implement by End of Contact Execute Transition Of Ownership of

System by End of Warranty Period

Page 29: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #3: Engage Your Teams

29

CCSAS Migration EDR Transition

Organized into Sub

Teams:

•Hardware

•Software

•Network

•Special Projects

Organized Leads by

Subdivisions and Area:

•Overall PM/Scope

•Tools

•Process

•Solution

Page 31: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #4: Target Your Communications

31

Communication Plans

Use Your Project Resources

Forums, Newsletters

Knowledge Management Program

Organizational Change Management Team

Vendor Relationships

Technical Contacts

Page 32: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #5: Roadmaps Are Your Friend

Road Map Your Activities w/ Stakeholders

32

Page 33: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

33

Tip #5: Roadmaps (Cont.)

Page 34: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

34

Tip #5: Roadmaps (Cont.)

Page 35: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #6: Execute Quick Wins

Executed Quick Wins (CCSAS)

Transitioned Project Office Early

Transitioned Central Scan Early

Transitioned Call Center Early

Executed Contract with IBM to

“Transition Out” of their

hosting center for one time

efforts

35

Page 36: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Executed Quick Wins (EDR):

Transitioned Design Stage 1 to FTB Sept.

2014

Utilized State Credit Resources for Skill Sets

already in House

36

Tip #6: Execute Quick Wins (Cont.)

Page 38: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #8: Manage Technology Risks

38

Dashboards

Sponsorship

Examples

Page 39: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tip #9: Practice Technology Cutovers

CCSAS Migration:

Production Validation Teams

Dry Runs

Establish Expectations Early

Stay Calm, expect the unexpected

(Small Things)

39

Page 41: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Technology Transition Challenges

Good Idea?

41

Bad Idea?

Page 42: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tools and Templates by Type

Processes

Business Process Implementation Plans

Project Planning:

Roadmaps

Sponsor Dashboards

Services Planning:

Migration Visual

42

Page 43: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Tools and Templates by Type

Cutover Planning

Wave Execution Checkpoints - ORARs

Wave Kick Off / Entry Criteria Checklists

Cutover Validation

Testing Activities

Timeline Example

Knowledge Management

Tools / Templates

Organizational Change Management

43

Page 44: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Business Process/Operational

Transitions

Have clear objectives and

sponsor agreement

Business processes are well

understood for transition

in / out

Services to the business

continue uninterrupted

44

Measures for Success

Page 45: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Staffing Transitions

Increase or consistency in staff

productivity, product and service quality,

and deliverable consistency

Intellectual and knowledge-based

assets have been captured

Knowledge gaps are minimal

Created an environment where the

people are truly happy, know what to do

and how to do it 45

Measures for Success (cont.)

Page 46: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

Technology Transitions – Survival Tips

46

Measures for Success (cont.)

Page 47: Project Transitions: People, Process and Technology · PDF file... s P artne r M anag e d S e rv ic e s D C S S P ro v ... c h i te c t In te l S y s te m A d mi n - P e rfo ... h

47

Questions