project/activity percent complete
TRANSCRIPT
Project/Activity Percent Complete:
What Are We Measuring?
Presented By:
This manual was created for online viewing. State specific information in this manual is used for illustration and is an example only.
mail: P.O. Box 509 Eau Claire, WI 54702-0509 • telephone: 866-352-9539 • fax: 715-833-3953email: [email protected] • website: www.lorman.com • seminar id: 401185
Saleh MubarakSaleh A. Mubarak, Ph. D.
Take advantage of this special offer for $50 off of a Lorman
live webinar!
C O N V E N I E N T:Lorman offers a wide variety of live webinars covering current issues affecting numerous industries. Learn the latest on legal compliance, cost savings and strategies, and business trends.
E X P E R I E N C E D :Learn about today’s hot topics presented by our expert speakers who represent prominent firms and have years of industry experience and knowledge.
C U R R E N T :In today’s business world, staying current of the ever-changing regulations is absolutely necessary in order to advance in your field. Earn continuing education credits, educate your entire team and ask questions of the speakers. For a complete listing of upcoming live webinars visit www.lorman.com.
SPECIAL OFFER
$50 OFFYOUR NEXT Discount Code Y1719669This offer can not be used in combination with other discounts.
LIVE WEBINAR
Project/Activity Percent Complete:
What Are We Measuring?
©2017 Lorman Education Services. All Rights Reserved.
All Rights Reserved. Lorman programs are copyrighted and may not be recorded or transcribed in whole or part without its express prior written permission. Your attendance at a Lorman seminar constitutes your agreement not to record or transcribe all or any part of it.
Full terms and conditions available at www.lorman.com/terms.php.
This publication is designed to provide general information on the topic presented. It is sold with the understanding that the publisher is not engaged in rendering any legal or professional services. The opinions or viewpoints expressed by faculty members do not necessarily reflect those of Lorman Education Services. These materials were
prepared by the faculty who are solely responsible for the correctness and appropriateness of the content. Although this manual is prepared by professionals, the content and information provided should not be used as a substitute for professional services, and such content and information does not constitute legal or other professional
advice. If legal or other professional advice is required, the services of a professional should be sought. Lorman Education Services is in no way responsible or liable for any advice or information provided by the faculty.
This disclosure may be required by the Circular 230 regulations of the U.S. Treasury and the Internal Revenue Service. We inform you that any federal tax advice contained in this written communication (including any attachments) is not intended to be used, and cannot be used, for the purpose of (i) avoiding federal tax penalties imposed by
the federal government or (ii) promoting, marketing or recommending to another party any tax related matters addressed herein.
mail: P.O. Box 509 Eau Claire, WI 54702-0509 • telephone: 866-352-9539 • fax: 715-833-3953email: [email protected] • website: www.lorman.com • seminar id: 401185
Prepared By:Saleh Mubarak
Saleh A. Mubarak, Ph. D.
Learn What You Want, When You Want From Our Entire
Course Library
UNLIMITED ACCESS
ON-THE-GO LEARNING
We Offer Accredited Training Including CLE, CPE, HRCI, ENG and Many More
A L L - A C C E S S P A S SLORMAN EDUCATION SERVICES
Learn at Your Own Pace From Your Computer,
Tablet or Mobile Device
lorman.com/pass
GET CERTIFIED
Want to learn more? Contact a Lorman
All-Access Pass Specialist:
[email protected] or call 1-877-296-2169
© 2017 Lorman Education Services. All Rights Reserved.Lorman programs are copyrighted and may not be recorded or transcribed in whole or part without its express prior written permission. Your attendance at a Lorman program constitutes your agreement not to record or transcribe all or any part of it. This publication is designed to provide general information on the topic presented. It is sold with the understanding that the publisher is not engaged in rendering any legal or professional services. Although this manual is prepared by professionals, it should not be used as a substitute for professional services. If legal or other professional advice is required, the services of a professional should be sought.
This disclosure may be required by the Circular 230 regulations of the United States Treasury and the Internal Revenue Service. We inform you that any federal tax advice contained in this written communication (including any attachments) is not intended to be used, and cannot be used, for the purpose of (i) avoiding federal tax penaltiesimposed by the federal government or (ii) promoting, marketing or recommending to another party any tax related matters addressed herein.
The opinions or viewpoints expressed by the faculty members do not necessarily reflect those of Lorman Education Services. These materials were prepared by the faculty members who are solely responsible for their correctness and appropriateness.
Learn to identify the specific percent complete types and how to use them consistently.
Percent complete (for activities and projects) is one of the most confusing and misunderstood pieces of information in the field of project management and project control. There are many types of percent complete; each has a definition and measures something specific. Percent complete may measure physical work, units completed, cost, time, manhours, or other parameters. It could reflect the baseline or actual performance. Being ignorant in this matter makes you vulnerable to misinformation and misrepresentation. It is of vital importance for the project management team, representing all parties, to identify the specific percent complete types used, understand them well, and be consistent in using them throughout the project and across the organization.This material sheds the light on this topic in a simple and practical manner. It provides invaluable information to those involved in the management of construction projects.
CourseDescription
4
LearningObjectives
At the end of the this course, participants will be able to:
1. You will be able to describe the different methods for measuring work progress.
2. You will be able to recognize the use and importance of percent complete.
3. You will be able to discuss methods to measure work progress.
4. You will be able to explain the definition of percent complete.
Activity, Project, or Program?
What we do, falls under one of these…
or, in between them!
Percent Complete, Dr. Mubarak 7
Task / Activity
ProjectProgramWork
Package
5
Example
Program: Summer Olympic 2020 in Tokyo
Project: Constructing a new building to house athletes
Work Package: Foundation or Roof assembly
Activity: One spread footing
Task/Step: Setting the formwork for the spread footing
Percent Complete, Dr. Mubarak 8
Definition of Percent Complete
Percent Complete: An estimate, expressed as a percent of the
amount of work that has been completed on an activity or a work
breakdown structure component.
(PMI PMBOK, 6th ed., 2017)
Schedule Percent Complete: The proportion of an activity or all
the project’s activities that has been completed.
(AACE® International RP No. 10S‐90, Cost Engineering Terminology, Nov 2014)
Percent Complete, Dr. Mubarak 9
6
Definition of Percent Complete
Percent Complete: A completion percentage of the
work in an activity / work package / project, based on a
chosen method of measuring work progress
A work package can be as small as concrete column
(formwork + rebar + concrete placement + other), as
big as the concrete shell of an entire building shell, or
somewhere in between such as the foundation.
Percent Complete, Dr. Mubarak 10
Definition of Percent Complete
Elements in a work package / assembly are usually
logically related. Elements in a WBS element or a
segment of the project can be grouped / linked by logic,
location, or other criteria. For example the foundation
or an entire floor of the building.
Pre‐manufactured modular units are not considered
work packages because they are delivered already
assembled
Percent Complete, Dr. Mubarak 11
7
Percent Complete, Dr. MubarakSlide No.
12
160000
100000
Tam
pa
Off
ice
Bld
g
110000
Foun
dati
on/
Subs
truc
ture
120000
Bui
ldin
g sh
ell
130000
Ext
erio
r cl
osur
e
140000
Inte
rior
fi
nish
es
150000
Mec
hani
cal
/ E
lect
rica
l
Site
Wor
k
121000
Col
umns
122000
Shea
r W
alls
123000
Ele
vate
d
Slab
s
124000
Bea
ms/
G
ird
ers
125000
CIP
Sta
irs
123100
Pos
t-te
nsio
ned
Sl
abs
123200
Flat
Sla
bs
123300
Waf
fle
Slab
s
123400
One
-way
Sl
ab a
nd
beam
123110Fa
lsew
ork
123120
Reb
ar
123130
Pos
t-te
nsio
n ca
ble
123140
Con
cret
e
123111
Soff
it a
nd
edge
s
123112
Scaf
fold
(t
able
s)
123113
Shor
es
123114
Res
hore
s
Level 0
Level 1
Level 2
Level 3
Level 4
Level 5
Work Breakdown Structure, WBS
Work Breakdown Structure, WBS
Percent Complete, Dr. Mubarak 13
Level
0
1
2
3 to 6
8
Use of Percent CompleteActivity % Complete Project % Complete
1. To estimate progress payments
2. To update activities’ remaining
duration in schedule updates
Subsequently, recalculate upcoming
activities’ dates and project
completion date
3. As a component for calculating
work package / project percent
complete
More important than project %
complete
1. Often used to report to the
client or the upper management
(just to get an idea)
2. To calculate the overhead cost
3. Can be used for approximate
financial arrangements
4. Rarely, if ever, used to authorize
progress payments or make
decisions on a project
Percent Complete, Dr. Mubarak 14
Methods to Measure Work Progress
1. Units completed
Physical percent complete
2. Start/finish
3. Supervisor Opinion
4. Cost/Budget Ratio:
a. Actual
b. Baseline
5. Man‐hour Ratio:
a. Actual
b. Baseline
6. Duration Ratio:
a. Actual
b. Baseline
7. Incremental milestones
8. Weighted or Equivalent
Units
9. The “Workday” Unit Method
Percent Complete, Dr. Mubarak 15
9
Units Completed Method
Percent Complete = Units Completed / Total Units
Example: In an activity of installing 4,000 concrete blocks, 1,200 have been
installed:
Percent complete = (1,200 / 4,000) * 100 = 30%
Assumptions:
Work is assumed to be linear throughout the activity
A “unit is a unit”, i.e. all units take the same effort / time
This method works great for activities with small identical
repetitive components such as laying bricks or CMU (concrete
masonry units), painting, installing tile or carpet, excavation,
fishing electric wire, etc.
16Percent Complete, Dr. Mubarak
Units Completed Method
In some cases, total units may be different from the estimated
quantity.
For example, assume:
Original estimated amount of excavation = 45,000 CY
Actual excavated amount = 18,500 CY
Estimated amount to complete = 30,300 CY
Total amount at completion (Adjusted Total Amount) = 18,500 + 30,300 =
48,800 CY
Percent Complete (Actual) = 18,500 / 48,800 = 37.91%
Most likely, there will be a change order in this case
17Percent Complete, Dr. Mubarak
10
Physical Percent Complete
Physical Percent Complete is almost the same as Units
Completed method. The main difference is:
In the Units Completed method, “units” are discrete (usually
countable) while in the physical percent completion, units may not
be discrete but can be measured or estimated, e.g. gallons of water,
concrete placed, land area cleared.
In general, the two methods use the same calculations and can
be considered the same
In both cases, there is an assumption of “uniformity / similarity” of
units
Percent Complete, Dr. Mubarak 18
Start/Finish Method
This method works best for small activities or those with or
short duration
The project manager can assign one of three stages:
have not started yet (0%),
started by not yet finished: An arbitrary amount, say 40% or
50%, or
finished (100%).
When these activities become so small, we can look at
them as “almost events” with either 0% or 100% complete.
19Percent Complete, Dr. Mubarak
11
Supervisor’s Opinion Method
The most subjective method. It is used when no other
method can suitably apply.
For example, an “engine tune up”, a repair, restoration, or
“dewatering” operation.
It relies totally on the judgment of the foreman or
superintendent.
The scheduler has to be careful not to overuse this
method.
20Percent Complete, Dr. Mubarak
Cost or Man‐hour Method
This method applies to those activities that are continuous and
uniform throughout the entire or part of the duration of a project.
For example, Safety Inspection, supervision, and other project‐
management type activities.
Actual Cost/Budget or Man‐hours Ratio:
• % complete = Actual cost to date / Estimate cost at completion
• % complete = Actual MH to date / Estimate MH at completion
Baseline Cost/Budget or Man‐hours Ratio:
• % complete = Budgeted (planned) cost to date / Baseline Budget
• % complete = Budgeted (planned) MH to date / Baseline MH Budget
21Percent Complete, Dr. Mubarak
12
Cost or Manhour Method
This method can be applied to calculate percent complete of an
activity, work package, or the entire project.
Baseline ratio represents what percent complete is supposed to
be at this point.
A comparison between actual and baseline % complete is good for
project control purposes
Example: Project overhead expenses are estimated to be $252,000 for
a project with a duration of 18 month ($14,000/month). After two
months, actual spending was $30,700.
Actual percent complete = $30,700/252,000 = 12.2%
Baseline percent complete = $28,000/252,000 = 11.1%
22Percent Complete, Dr. Mubarak
Duration Ratio
This method is suitable for tracking time; how much
passed as a percentage of the total duration.
Actual Duration:
% Complete = Actual Duration / At Completion Duration
At Completion Duration = Actual Duration + Remaining
Duration
Baseline Duration:
% Complete = Planned duration to date / Total BL Duration
Planned duration to date = Data Date – BL Start Date
Comparing actual and baseline percent complete tell us if
the project is ahead, on, or behind schedule.
23
13
19 days
Duration Ratio: Example
Project percent complete:
Actual Duration % Complete = 16 / 33 = 48%
Baseline Duration % Complete = 19 / 32 = 59%
24
16 days33 days
32 days
Importance of Accurate RD
Updating remaining duration is extremely important
Assume an “Excavation” activity with 8 days of original
duration (OD)
Four days after starting, only 30% was completed
AD = 4, Percent Complete = 30%
You need to update remaining duration (RD), say 9 days
If you failed to do so, you may be showing the wrong
dates for the successors and project completion date
25Percent Complete, Dr. Mubarak
14
Importance of Accurate RD
Percent complete must use the updated “At
Completion Duration” in calculations
At Completion Duration = Actual Duration + Remaining Duration
Except in baseline percent complete
Strange Percent Complete Numbers: Explanation?
26Percent Complete, Dr. Mubarak
Variances
Typically, we will find differences between the “As
Planned” and the “As built” in terms of percent
complete to cost, man‐hours, and duration
Do not rush to judgement
The cause of the variance may be in the performance or
baseline. It may be the fault of the contractor, the owner,
another party, or nobody’s!
Some variances are tolerated and some are not.
27Percent Complete, Dr. Mubarak
15
Incremental Milestones Method
This method is more suitable to large and complex or multi‐
stage activities including work packages / assemblies.
Each stage is given a “weight” that is approximately equal to
its percentage share of effort out of the total activity. Then
each stage is treated as “all or nothing”.
Example: a contractor is installing 25 doors:
Four doors have not yet started,
Eight doors have the frame erected, say 30% complete,
Six doors are hung, say 50% complete,
Four doors have been painted, say 75% complete, and
Three doors completed.
28Percent Complete, Dr. Mubarak
Incremental Milestones Method
29Percent Complete, Dr. Mubarak
Must add up to 100%
16
Weighted or Equivalent Units Method
This method is used for large and complicated activities that are
usually composed of several consecutive / overlapping sub‐
activities. The method follow the following steps:
Assign a weight to each sub‐activity so that total weights = 100%
Multiply each sub‐activity’s weight by the quantity of the total
activity. This is the “equivalent weight” in units for each sub‐activity.
Find out individual sub‐activities’ percent complete using one of the
previously discussed methods.
Multiply each sub‐activity’s percent complete by its “equivalent
weight”. This is “earned quantity”.
Add “earned quantities” for all activities and divide by total quantity.
This is the percent complete for the total activity.
30Percent Complete, Dr. Mubarak
Weighted or Equivalent Units Method
31Percent Complete, Dr. Mubarak
Equivalent MBF = Assigned weight * Total MBF = 0.08 * 3.50 = 0.28Earned MBF = (Completed Quantity/Total Quantity)* Equivalent MBF
= (8 / 12) * 0.28 = 0.19Total Activity % Complete = Earned MBF / Total MBF = 1.97 / 3.50 = 56.3%
17
Primavera P6 “Steps”
Percent Complete, Dr. Mubarak 32
Why a Complex Activity?
It is natural that some work components are complex,
so what should we do?
Consider the work package as an activity and then use
one of these methods to measure its progress, or
Consider each of the components as a stand‐alone
activity and then use WBS or P6 “Level of Effort”
(Hammock) activity to look at the work package?
Percent Complete, Dr. Mubarak 33
18
The “Work‐Day” Unit Method
percent complete = 20/39 = 51.3%
Activity IPA Original Duration
Actual Duration
Remaining Duration
A - 7 7 0 B A 12 9 3 C A 6 4 2 D B, C 5 0 5 E D 9 0 9
Total 39 20 19
34
Data date
A
B
C
D
E
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
The “Work‐Day” Unite Method
This method assumes a “day” is a day’s worth no matter what
activity or other considerations.
What is the percent complete?
Waiting period: a lag or part of the duration?
Are we reporting baseline or actual?
35
Data Date
Percent Complete, Dr. Mubarak
A
B
C
2 4 6 80
(2 / 6)*100 = 33%
19
Comparison Among All Methods
These methods do not measure the same thing and certain
methods may be more appropriate to the situation than other
methods.
Suitability of methods differ according to:
Nature of activity
Purpose of the percent complete
Things in reality are not are as well‐defined as we like to have, in
order to decide on which method to use.
36Percent Complete, Dr. Mubarak
Comparison Among All Methods
In most of these methods there is an element of subjectivity
(Supervisor’s Opinion method may be blended with other
method)
However, to reduce the element of subjectivity, make the activity
smaller, simpler, more homogeneous, and shorter duration
Even if the activity is made of similar units (e.g. CMU), some
factors may result in varying productivity such as location
(height) of installed units, learning curves, and weather
conditions.
Rule of duration confidence!
37Percent Complete, Dr. Mubarak
20
Percent Complete Example
Assume a work package with three activities:
The first two activities are (A and B) identical. Each one requires the
installation of an interior hollow‐core wood door which cost $200
each (including hardware). Installation of these doors requires one
laborer for 2 hours for each door.
The third activity, C, requires the installing of hand‐carved
decorative exterior door that costs $2,200 and takes three laborers
for 3 hours.
A man‐hour costs $40. Activities A
and B are to be performed
simultaneously, and then activity C.
Percent Complete, Dr. Mubarak 38
1 2 3 4 5 hours
A
B
C
Percent Complete Example
Total cost of activities A and B =
$200 + 1 laborer * 2 hours * $40/hr = $ 280 each
Total cost of activity C =
$2,200 + 3 laborers * 3 hours * $40/hr = $2,560
Total cost for project = 2 * $280 + $2,560= $3,120
Total man‐hours for project = 2 + 2 + 3*3 = 13 man‐hours
Total duration for project = 2 + 3 = 5 hours
Percent Complete, Dr. Mubarak 39
21
Percent Complete Example: Update
Activities A and B are now complete but the doors actually cost the
contractor $230 and took an extra hour for installation, i.e. 3 man‐
hours (one laborer for 3 hours); each
Activity C has not yet started (no change is expected for cost or
duration)
What is the percent complete of this work package?
Percent Complete, Dr. Mubarak 40
Data date
1 2 3 4 5 6 hours
C
A
B
Calculation of Percent Complete
1. Units completed:
Assume “a door is a door”
Percent Complete = Units completed/Total units
= 2 door / 3 door = 66.7%
Percent Complete, Dr. Mubarak 41
22
Calculation of Percent Complete
2. Cost / Budget ratio:
Actual:
Actual cost for activities A or B
= $230 + 1 laborer * 3 hours * $40 = $350 each
Cost at Completion for work package = 2*350 + 2,560 = $3,260
Percent Complete = Actual Cost / Cost at Completion
= $700 / $3,260 = 21.5%
Baseline:
Percent Complete = Planned Cost / Original Budget
= $560 / $3,120 = 17.9%
Percent Complete, Dr. Mubarak 42
Calculation of Percent Complete
3. Man‐hour ratio:
Actual:
Actual man‐hours for activities A or B = 3 + 3 = 6
Total man‐hours at Completion for work package = 6+9 = 15
Percent Complete = 6 / 15 = 40%
Baseline:
Percent Complete = 4 / 13 = 30.8%
Percent Complete, Dr. Mubarak 43
23
Calculation of Percent Complete
4. Duration:
Actual:
Percent Complete = 3 / 6 = 50%
Baseline:
Percent Complete = 2 / 5 = 40%
Percent Complete, Dr. Mubarak 44
1 2 3 4 5 hours
A
B
C
Data date
1 2 3 4 5 6 hours
A
B
C
Calculation of Percent Complete
5. Workday Unit (work-day or work-
hour unit):
Actual:
Percent Complete = 6 / 9 = 66.7%
Baseline:
Percent Complete = 4 / 7 = 57.1%
Percent Complete, Dr. Mubarak 45
1 2 3 4 5 hours
A
B
C
Data date
1 2 3 4 5 6 hours
A
B
C
24
Calculation of Percent Complete
6. Supervisor’s opinion:
The foreman "believes" the work package is about 55%
complete!
Percent Complete, Dr. Mubarak 46
Are You Confused Yet?
So, what is the true percent complete: 66.7%, 57.1%,
50%, 40%, 30.8%, 21.5%, or 17.9%, or 55%?
Which one should I use?
None of the previously discussed methods is wrong
but none of them can be considered the right method.
Most importantly:
Know exactly what each percent complete means
Pick one or two types to use
Be consistent with the chosen ones throughout the project
47Percent Complete, Dr. Mubarak
25
More Examples
To emphasize the previous example, think of:
A contractor has two tasks of excavation: 10,000 CY of
sand @ $3.00/CY and 10,000 CY of rock @ $25/CY. He
finished excavating the sand, so what’s his percent
complete?
Think of excavation as:
A work package, or
An activity
Is it just a cubic yard anyway?
Percent Complete, Dr. Mubarak 48
More Examples
A contractor has to demolish two identical buildings:
one in an open space and one in confined space next to
occupied buildings. He completed the demotion of the
first one , so what’s his percent complete?
You got the point, right?
Percent Complete, Dr. Mubarak 49
26
Primavera P6 Types of % Complete
Activity % Complete (15) Project % Complete (12)
Percent Complete, Dr. Mubarak 50
Types of Percent Complete in P6
Percent Complete, Dr. Mubarak 51
27
P6’s “Units % Complete”
Oracle Primavera P6 gives an option for calculating
percent complete:
Units here mean units of the resource; e.g. man‐hours
P6 has equation to calculate percent complete of both
Duration and Units, but the user needs to input the
Physical percent complete
Percent Complete, Dr. Mubarak 52
P6’s “Units % Complete”
For example, in an update for an activity:
50% of the duration passed,
We consumed 70% of the resources (units),
But we achieved only 33% physical completion
Percent Complete, Dr. Mubarak 53
28
Remaining Duration and Percent Complete
If work progress in an activity did not go as planned,
and the Percent Complete type was “Physical”, the user
needs to input both remaining duration and actual
percent complete.
Expected completion is an option that calculates
remaining duration
Percent Complete, Dr. Mubarak 54
P6: Past in the Future?
Oracle Primavera P6 allows you to mark future dates as
actual
This may lead to awkward percent
complete (but it shows as 0 in P6)
Percent Complete = AD / ACD
AD = Data Date – Actual Start
AD = ‐1 in this case
Percent Complete, Dr. Mubarak 55
Data
Date
1 2 1 2 3 4
29
Software Issues
When your computer software gives you choices of different
percent complete types, try to understand what each type means
When rolling up / grouping activities, make sure what does the
group activity’s percent complete represents
When your schedule is neither cost loaded nor resource loaded,
have you ever wondered how does P6 give you the project %
complete?
56Percent Complete, Dr. Mubarak
Human Judgement
Software programs may offer some automated
processes in updating projects.
Schedulers have to be careful in using such processes by:
1. Knowing the rules of such process
2. Making decisions on exceptions to the rules
3. Reviewing the output and making sure it is correct
Personally, I refrain from using such automated
processes
Percent Complete, Dr. Mubarak 57
30
Judgement Errors
People who are not familiar with the nature of the
construction industry (mostly owners):
Don’t rush to judgement! What you see may not be what it
really is
Guessing percent complete by what you see, may carry a large
error if you don’t know the steps
Schedulers who know the software rules but lack the
knowledge in scheduling concepts and construction, may
also lack the educated common sense judgement whether
to accept computer output, and how to interpret it.
Percent Complete, Dr. Mubarak 58
It Could be a Deliberate Bias!
Since Progress Payments (periodic payments from
owner to contractor) depend largely on activities’
percent complete, there may always be a tug‐of‐war
game between owners and contractors, even if the
contract is lump‐sum
This is one of several ways contractors try to get early
money
Inaccuracies in the schedule may backfire if/when the
schedule is analyzed in a claim dispute case
Percent Complete, Dr. Mubarak 59
31
Progress Payments
While contractors incur expenses on a daily basis,
owners make payments to contractors usually on a
monthly basis.
This payment is based on
Actual quantities / percent complete claimed by the
contractor and verified by the owner,
Unit price as mentioned in the Schedule of Values.
There are other issues such as retainage, penalties,
purchased but not installed materials, …
Percent Complete, Dr. Mubarak 60
Schedule of Values
Schedule of Values: A detailed statement furnished by
a construction contractor, builder, or others,
apportioning the contract value into work packages. It
is used as the basis for submitting and reviewing
progress payments
It is part of the contract documents but may get
modified or supplemented by a change order
Percent Complete, Dr. Mubarak 61
32
Activity Cost Distribution
Activity cost may not be distributed evenly (linearly)
over the duration of the activity. It is a user‐defined
item.
So, if the activity is 25%, “Actual Cost” may be higher
than 25% of total cost
This distribution may not be compatible with progress
payments unless the contract / owner approves it
Percent Complete, Dr. Mubarak 62
Activity Cost Distribution in P6
Percent Complete, Dr. Mubarak 63
33
Percent Complete and Progress Payments
Knowing the type of percent complete and its accuracy
is extremely important for the accuracy of progress
payments
Contractors tend to exaggerate in activity percent
complete, especially in high‐cost activities and those in
the early stage of the project
Percent Complete, Dr. Mubarak 64
Final Recommendation
All data must be based on scientific principles and
rules, and must be consistent
Measurement tools and indicators need to be clear to
all project parties and spelled out in the contract
Documentation is equally important
Accuracy and fairness are ultimately good for everyone
Percent Complete, Dr. Mubarak 65
34