projects: nh-3-001(027)161 (pcn-21667), nh-6 … 37...003 202 0350 removal of temporary bypass ea 3....
TRANSCRIPT
SpecNo.
Amount
Description UnitApprox.Quantity
Unit Price
$$$$$ 000 $$$$$ 00
PROPOSAL FORMNorth Dakota Department of Transportation
037Page 5 of 11
11/15/2017
JobNovember 17, 2017BID OPENING:
CodeNo.
Bidder must type or neatly print unit prices in numerals, make extensions for each item, and total. Do not carry unit prices further than three (3) decimal places.
ItemNo.
Projects: NH-3-001(027)161 (PCN-21667), NH-6-002(122)295 (PCN-21341), and NH-6-002(123)295 (PCN-21346)
Rev: BID ITEMS
CONTRACT BOND 1.001 103 0100 L SUM
REMOVE AGGREGATE BASE & SURFACING 1,625.002 202 0021 TON
REMOVAL OF TEMPORARY BYPASS 3.003 202 0350 EA
COMMON EXCAVATION-TYPE C 383.004 203 0103 CY
TOPSOIL 1,122.005 203 0109 CY
TOPSOIL-IMPORTED 112.006 203 0119 CY
BORROW-EXCAVATION 5,515.007 203 0140 CY
WATER 170.008 216 0100 M GAL
SHOULDER PREPARATION 8801.009 230 0125 MILE
SUBGRADE PREPARATION-TYPE A-SHOULDERS 40.010 230 0302 STA
SEEDING CLASS II 5001.011 251 0200 ACRE
TEMPORARY COVER CROP 800.012 251 2000 ACRE
STRAW MULCH 3002.013 253 0101 ACRE
FIBER ROLLS 12IN 5,625.014 261 0112 LF
REMOVE FIBER ROLLS 12IN 1,880.015 261 0113 LF
SALVAGED BASE COURSE 348.016 302 0100 TON
SpecNo.
Amount
Description UnitApprox.Quantity
Unit Price
$$$$$ 000 $$$$$ 00
PROPOSAL FORMNorth Dakota Department of Transportation
037Page 6 of 11
11/15/2017
JobNovember 17, 2017BID OPENING:
CodeNo.
Bidder must type or neatly print unit prices in numerals, make extensions for each item, and total. Do not carry unit prices further than three (3) decimal places.
ItemNo.
Projects: NH-3-001(027)161 (PCN-21667), NH-6-002(122)295 (PCN-21341), and NH-6-002(123)295 (PCN-21346)
Rev: BID ITEMS
AGGREGATE BASE COURSE CL 5 1,356.017 302 0120 TON
TACK COAT 2,385.018 401 0050 GAL
PRIME COAT 875.019 401 0060 GAL
FOG SEAL 663.020 401 0070 GAL
MILLING PAVEMENT SURFACE 106,691.021 411 0105 SY
RELAYING MILLED MATERIAL 10,438.022 411 0132 TON
SUPERPAVE FAA 45 4,956.023 430 0045 TON
CORED SAMPLE 21.024 430 1000 EA
PG 58-28 ASPHALT CEMENT 400297.025 430 5828 TON
CONCRETE OVERLAY 14,695.026 550 0355 CY
CONCRETE PLACEMENT - DOWELED 71,934.027 550 0365 SY
PCC PAVEMENT GRINDING 41,495.028 570 0210 SY
DOWELED CONTRACTION JOINT ASSEMBLY 342.029 570 0240 LF
8IN CONCRETE PAVEMENT REPAIR-FULL DEPTH-DOWELED 1,367.030 570 0713 SY
TRANSVERSE PCC JOINT CLEANING & SEALING 54,050.031 570 0963 LF
LONGITUDINAL PCC JOINT CLEANING & SEALING 26,611.032 570 0965 LF
SpecNo.
Amount
Description UnitApprox.Quantity
Unit Price
$$$$$ 000 $$$$$ 00
PROPOSAL FORMNorth Dakota Department of Transportation
037Page 7 of 11
11/15/2017
JobNovember 17, 2017BID OPENING:
CodeNo.
Bidder must type or neatly print unit prices in numerals, make extensions for each item, and total. Do not carry unit prices further than three (3) decimal places.
ItemNo.
Projects: NH-3-001(027)161 (PCN-21667), NH-6-002(122)295 (PCN-21341), and NH-6-002(123)295 (PCN-21346)
Rev: BID ITEMS
RANDOM PCC CRACK CLEANING & SEALING 2,975.033 570 0966 LF
SPALL REPAIR-PARTIAL DEPTH 2,090.034 570 1512 SF
MOBILIZATION 1.035 702 0100 L SUM
FLAGGING 1,240.036 704 0100 MHR
TRAFFIC CONTROL SIGNS 11,287.037 704 1000 UNIT
ATTENUATION DEVICE-TYPE B-55 2.038 704 1041 EA
TYPE I BARRICADE 30.039 704 1050 EA
TYPE III BARRICADE 169.040 704 1052 EA
DELINEATOR DRUMS 97.041 704 1060 EA
TUBULAR MARKERS 167.042 704 1067 EA
FLEXIBLE DELINEATORS 504.043 704 1072 EA
STACKABLE VERTICAL PANELS 11.044 704 1080 EA
SEQUENCING ARROW PANEL-TYPE C 4.045 704 1087 EA
SEQUENCING ARROW PANEL-TYPE C-CROSSOVER 2.046 704 1088 EA
PILOT CAR 100.047 704 1185 HR
OBLITERATION OF PAVEMENT MARKING 4,963.048 704 1500 SF
SpecNo.
Amount
Description UnitApprox.Quantity
Unit Price
$$$$$ 000 $$$$$ 00
PROPOSAL FORMNorth Dakota Department of Transportation
037Page 8 of 11
11/15/2017
JobNovember 17, 2017BID OPENING:
CodeNo.
Bidder must type or neatly print unit prices in numerals, make extensions for each item, and total. Do not carry unit prices further than three (3) decimal places.
ItemNo.
Projects: NH-3-001(027)161 (PCN-21667), NH-6-002(122)295 (PCN-21341), and NH-6-002(123)295 (PCN-21346)
Rev: BID ITEMS
PRECAST CONCRETE MED BARRIER-STATE FURNISHED 80.049 704 3510 EA
FIELD OFFICE 1.050 706 0400 EA
AGGREGATE LABORATORY 1.051 706 0500 EA
BITUMINOUS LABORATORY 1.052 706 0550 EA
CONTRACTOR'S LABORATORY 1.053 706 0600 EA
GEOSYNTHETIC MATERIAL TYPE R1 3,278.054 709 0151 SY
PIPE PVC 18IN 704.055 714 7036 LF
FLAT SHEET FOR SIGNS-TYPE IV REFL SHEETING 14.056 754 0112 SF
STEEL GALV POSTS-TELESCOPING PERFORATED TUBE 215.057 754 0206 LF
RESET SIGN PANEL 4.058 754 0592 EA
RUMBLE STRIPS - CONCRETE SHOULDER 6389.059 760 0001 MILE
RUMBLE STRIPS - ASPHALT SHOULDER 8801.060 760 0005 MILE
RUMBLE STRIPS - ASPHALT CENTERLINE 940.061 760 0007 MILE
RUMBLE STRIPS - INTERSECTION 1.062 760 0010 SET
PVMT MK PAINTED-MESSAGE 52.063 762 0103 SF
EPOXY PVMT MK 4IN LINE-GROOVED 13,213.064 762 0110 LF
SpecNo.
Amount
Description UnitApprox.Quantity
Unit Price
$$$$$ 000 $$$$$ 00
PROPOSAL FORMNorth Dakota Department of Transportation
037Page 9 of 11
11/15/2017
JobNovember 17, 2017BID OPENING:
CodeNo.
Bidder must type or neatly print unit prices in numerals, make extensions for each item, and total. Do not carry unit prices further than three (3) decimal places.
ItemNo.
Projects: NH-3-001(027)161 (PCN-21667), NH-6-002(122)295 (PCN-21341), and NH-6-002(123)295 (PCN-21346)
Rev: BID ITEMS
EPOXY PVMT MK MESSAGE 96.065 762 0112 SF
EPOXY PVMT MK 4IN LINE 154,069.066 762 0113 LF
EPOXY PVMT MK 8IN LINE 2,270.067 762 0115 LF
EPOXY PVMT MK 24IN LINE 65.068 762 0117 LF
RAISED PAVEMENT MARKERS 21,309.069 762 0200 EA
SHORT TERM 4IN LINE-TYPE NR 32,587.070 762 0430 LF
PVMT MK PAINTED 4IN LINE 12,321.071 762 1104 LF
MAILBOX-ALL TYPES 3.072 766 0100 EA
FLASHING BEACON-POST MOUNTED 2.073 772 2110 EA
REVISE FLASHING BEACON SYSTEM 1.074 772 2935 EA
TOTAL SUM BID
Revised 11/14/2017 NOTES
11/14/2017 4:09:25 PM R:\project\60002295.122\design\006NT_001_notes.docm
STATE PROJECT NO. SECTION NO.
SHEET NO.
ND NH-6-002(122)295 6 1
This document was originally issued and sealed by Sara A. Cahlin,
Registration Number PE-8397,
on 11/13/2017 and the original document
is stored at the North Dakota Department of Transportation.
107-P01 MAINTAINING TRAFFIC –DROP-OFFS: If, at the end of the work-day, drop-offs greater than 2 inches and less than 18 inches or slopes steeper than 4:1 exist between the edge of a traffic lane and the outside edge of the proposed roadway, perform one of the following actions:
Construct a traversable wedge in the area of the drop-off or steep slope; or Close the lane adjacent to the drop-off or steep slope and provide 24-hour
flagging or pilot car operations.
When constructing a wedge, construct a wedge composed of aggregate or earthen materials with a 4:1 or flatter slope along the entire length of the area. Compact materials using Type C compaction, as specified in 203.04 E.4, “Compaction Control Type C”.
Install stackable vertical panels that meet the requirements of Section 704.03 H, “Stackable Vertical Panels”, along the edge of the driving lane closest to the wedge.
The Engineer will measure stackable vertical panels as specified in Section 704.05, “Method of Measurement” and will pay for panels as specified in Section 704.06, “Basis of Payment”.
The Engineer will not measure material used to construct the wedge. Include the cost of materials, equipment, labor, and incidentals required for this operation in the price bid for “Aggregate Base CL 5.
If a 4:1 or flatter wedge is not installed, provide 24 hour flagging or pilot car operations and associated traffic control at no additional cost to the Department.
The requirements of Section 704.04 O, “Traffic Control for Uneven Pavement” apply to drop-offs created by milling or the placement of hot mix asphalt.
202-P01 MEDIAN APPROACH REMOVAL: Remove the median crossing adjacent to the
west crossover. Engineer will measure the removal as “Removal of Temporary Bypass”.
202-P02 REMOVAL OF TEMPORARY BYPASS: Obtain approval from the Engineer before
removing a temporary bypass. Restore the area impacted by the construction, and removal of the crossovers to its original condition; shape the median slopes to a 6:1 slope, seed and mulch. Include all costs associated with the removal of the asphalt surfacing, aggregate, geosynthetic material, topsoil on the crossover and pipe in the contract unit price for “Removal of Temporary Bypass”.
203-P01 SHRINKAGE: 25 percent additional volume is included for shrinkage in earth
embankment. 230-P01 SUBGRADE PREPARATION: Complete subgrade preparation – type A shoulders to
a depth of 12 inches.
261-P01 PERMANENT FIBER ROLLS: If fiber rolls are to remain on the project, use fiber rolls that are composed of netting that meets either of the following:
· Plastic or natural fiber photodegradable netting that has a life expectancy
between 12 to 24 months. If the photodegradable netting is plastic, the netting color must be either clear or green. Black plastic netting will not be allowed.
· 100 percent biodegradable jute netting that has a life expectancy between 6 to
12 months. 411-P01 MAINLINE MILLING: The last paragraph of Section 411.04 “Construction
Requirements” only applies to the intersection with ND 1; the 5 day limitation will not apply to milling operations on US 2. Provide milling and paving equipment capable of following a string line.
411-P02 SURFACE TOLERANCE: Construct the finished surface of the milling to within 0.04
feet of the proposed elevation. 411-P03 MILLING SECTION: Remove the existing bituminous material at the beginning and
end of milling sections, project termini, and at intersection to form a straight vertical edge to allow placement of the full depth of surfacing.
The loaded trucks are limited to running on 1 mile of the milled surface at a time. The Contractor is allowed to use the leave out locations listed in Note 550-P04 to stay within the 1 mile limitation. Include the cost of labor, materials and equipment in the price bid for “Milling Pavement Surface”.
411-P04 RELAYING MILLED MATERIAL: This work consists of placing, shaping, and
compacting material on the roadway shoulders using a road widening/shouldering machine. Use one of the following materials:
- Asphalt millings from the project; - Class 4 aggregate meeting the requirements of Section 816; or - Class 5 aggregate meeting the requirements of Section 816.
Use the same type of material throughout the project. If asphalt millings are used, the following additional requirements apply:
- Produce material with a maximum particle size of 1.5 inches;
Such payment is full compensation for furnishing all materials, equipment, labor, and incidentals to complete the work as specified.
Provide 1627 ton of milled material for project NH-6-002(123)295.
411-P05 MILLED MATERIAL: Approximately 5500 ton of hot
bituminous pavement (HBP) material will be stockpiled with a front-end loader at the NDDOT Maintenance Yard located at 205 Main Street South, Pekin, ND 58361. Process the HBP material so that the maximum particle size does not exceed
Revised 11/14/2017 NOTES
11/14/2017 4:09:25 PM R:\project\60002295.122\design\006NT_001_notes.docm
STATE PROJECT NO. SECTION NO.
SHEET NO.
ND NH-6-002(122)295 6 2
This document was originally issued and sealed by Sara A. Cahlin,
Registration Number PE-8397,
on 11/13/2017 and the original document
is stored at the North Dakota Department of Transportation.
1-1/2”. Notify the NDDOT Section Yard 72 hours prior to delivery of any HBP material. Include the cost of labor and equipment to remove, process, haul, and stockpile the HBP material in the price bid for “Milling Pavement Surface”.
550-P01 DOWEL BARS: Include the cost of cleaning, drilling, epoxy, and dowel bars where
the new concrete pavement abuts the existing concrete in the price bid for “Concrete Placement - Doweled”.
550-P02 CONCRETE PAVEMENT: Place the concrete on a clean surface, free of loose or
adhering foreign material. Air blast the milled surface no more than 30 minutes before placing concrete. Loaded trucks are allowed to run on the milled surface and back up to the concrete paving operation as long as loaded trucks aren’t tracking foreign material onto the milled surface.
550-P03 CONCRETE PAVEMENT: The Department will waive the requirement to place the
reinforcing steel, tie bars and dowel bar assemblies a minimum of 2,000 feet ahead of the paving operation as stated in Sections 550.04 E.1 and 550.04 G.2 and allow the use of the roadway as a haul road at the Contractors request, provided the following conditions are met:
Repair all damaged areas Construct the finished surface to the specific surface tolerance prior to the
placement of reinforcing steel, tie bars and dowel bar assemblies. Place the reinforcing steel and tie bars on approved supports securely,
properly and accurately in advance of the paving operation. 550-P04 LEAVE OUT: Leave out consists of paving half an intersection at a side street and
allowing traffic to cross US 2 on the unpaved portion. The portion left out will not be paved until the concrete overlay has attained a flexural strength of 450 psi or a compressive strength of 3,000 psi. Leave out location are:
Sta. 15611+75 – Airport Entrance Sta. 15892+18 – 42nd St NE Sta. 15981+30 – Private Drive Access Sta. 16041+52 – 113th Ave NE Sta. 16081+90 – Private Drive Access
Leave outs may be added or eliminated at the request of the contractor and at the discretion of the engineer. Include the cost for this work in the price bid for “Concrete Placement – Doweled”.
550-P05 CONCRETE PAVEMENT: Included in the quantity for “CONCRETE OVERLAY” is
an additional 5% for irregularities.
550-P06 CONCRETE PAVEMET: Contractor has the option of utilizing dowel bar basket clips and nails at shown in Section 20 sheet 6. If this option is utilized the contractor must:
Furnish a MIT-Scan-T2 non-destructive testing device having the ability to locate dowel bars. Perform all tests in the presents of the Engineer unless otherwise approved. Locate the entire span of the dowel bar basket and verify the anchoring of the dowel bar basket by locating the upstream and downstream edges of the dowel bar baskets. Testing requirements are as follows: Verify the adequacy of the dowel bar anchoring by scanning seven random doweled contraction joint in each lot.
704-100 TRAFFIC CONTROL SUPERVISOR: Provide a Traffic Control Supervisor. 704-200 PRECAST CONCRETE MEDIAN BARRIERS – STATE FURNISHED: Obtain 36
barriers from Devils Lake District. Return barriers to Devils Lake District. Obtain 44 barriers from Grand Forks District. Return barriers to Grand Forks District. Some 4 inch x 4 inch boards are available at the return location. Provide any additional 4 inch x 4 inch boards necessary to stack barriers. The boards will become property of the Department. Include the cost for boards in the contract unit price for "Precast Concrete Median Barrier - State Furnished".
704-301 SEQUENCING ARROW PANEL – TYPE C – CROSSOVER: Provide solar powered
arrow panels that meet the requirements of the MUTCD and ITE and that are capable of operating for 20 days without a solar charge. Include all costs for materials, equipment, labor, and incidentals in the contract unit price for "Sequencing Arrow Panel – Type C – Crossover".
704-511 OBLITERATION OF PAVEMENT MARKINGS: Mask pavement markings designated
for obliteration as specified in Section 704.04 N.1, "Masking". 704-P01 TRAFFIC CONTROL FOR BITUMINOUS PAVEMENT: Provide traffic control
consisting of median crossings and road closure. Maintain a minimum 12 feet wide lane for traffic at all times.
Complete necessary pavement marking and rumble strip
installation operations prior to removing traffic control crossovers.
Phase 1: Construct median cross overs. A total of 4 lane
closures have been provided to allow work at two separate locations. Remove existing median approach.
Phase 2: Perform work on mainline concrete overlay and cross road overlay.
Revised 11/14/2017 NOTES
11/14/2017 4:09:25 PM R:\project\60002295.122\design\006NT_001_notes.docm
STATE PROJECT NO. SECTION NO.
SHEET NO.
ND NH-6-002(122)295 6 3
This document was originally issued and sealed by Sara A. Cahlin,
Registration Number PE-8397,
on 11/13/2017 and the original document
is stored at the North Dakota Department of Transportation.
Phase 3: Removal of median cross overs. A total of 4 lane closures have been provided to allow work at two separate locations.
Traffic control device quantities are based on the phasing described above and the
following list. Provide additional devices at no cost to the Department. Standard D-704-15 layout A – For ND 1 intersection paving Standard D-704-22 layouts K and L – For trucks hauling Standard D-704-26 layouts CC, EE, and GG – For paving Standard D-704-34 – For single lane closure Standard D-704-38 – For east median crossover Standard D-704-39 – For west median crossover
Place flaggers and traffic control devices as shown on Standard D-704-15, layout A at the intersection of US 2 and ND 1 when paving in the intersection.
704-P02 CLOSING AND MAINTAINING ACCESS: Maintain access to private drives and local
roads at all times with the use of leave outs or work with the local entity to temporarily close access. Notify the local entity one week prior to any closure.
704-P03 TRAFFIC CONTROL AT ND 1: Temporarily widen the west edge of the ND 1
approach with milled material, during Phase 1 of the intersection paving. Remove the extra material once the intersection is complete.
Placement of the milled material is measured as “Relaying Milled Material”. Removal of the milled material is measured as “Remove Aggregate Base &
Surfacing”. 704-P01 FLASHING BEACON: Provide solar powered flashing beacons that meet the
requirements of the MUTCD and ITE. Provide beacons that are visible for a distance of 0.25 miles (1,320 feet) and are capable of operating for 20 days without a solar charge. Include all costs for materials, equipment, labor, and incidentals in the contract unit price for "Flashing Beacon – Post Mounted".
706-P01 FIELD OFFICE: Provide a field office which meets the following requirements:
1. The field office shall be a minimum of 450 square feet. 2. Indoor bathroom facilities.
3. Air conditioner (20,000 BTU minimum) 4. Lighting (lumens required 110 foot-candles) 5. Minimum of 3 phone jacks (NDDOT to pay for phone service) 6. Heat, electric, sewer, and water hookups to be furnished by contractor to pay utility bills. 7. Cabinet space of a minimum of 32 cubic feet.
8. Counter space of a minimum of 40 square feet.
9. The floor is to be free of protrusions so that it will accommodate NDDOT furnished office equipment. 10. Photocopy/printer machine capable of 11x17 photocopies and toner to last the duration of the project (NDDOT will furnish paper). Other features to include digital coping & scanning (fax capabilities can be included but not necessary). Copier/printer machine shall have operating software compatible with that used by NDDOT. 11. The location of the field office shall be on, or as close to the project as possible and approved by the Engineer. Any rental fees shall be paid by Contractor. 12. The field office shall be available for occupancy at the start of the project and remain available to project completion. 13.The following services will be furnished and paid for by the NDDOT and requested through the Work Management System:
a. Telephone b. Broadband internet service including State Network access
All requirements of the Field Office are subject to approval by the Engineer. Payment for the Field Office shall be under the bid item “Field Office”. Schedule for Payments:
· 25% when set up on site · 50% when 30% of work is completed · 75% when 60% of work is completed · 100% when project is complete
ESTIMATE OF QUANTITIESSTATE PROJECT NO. SECTION
NO.SHEETNO.
ND 8
NH-6-002(122)295 1
REVISED 11/13/2017
SPEC CODE ITEM DESCRIPTION UNIT MAINLINE TOTAL ---- ---- ---------------- ---- ------------ -----
103 0100 CONTRACT BOND L SUM 0.815 0.815
202 0021 REMOVE AGGREGATE BASE & SURFACING TON 1,625 1,625
202 0350 REMOVAL OF TEMPORARY BYPASS EA 3 3
203 0103 COMMON EXCAVATION-TYPE C CY 383 383
203 0109 TOPSOIL CY 1,122 1,122
203 0119 TOPSOIL-IMPORTED CY 112 112
203 0140 BORROW-EXCAVATION CY 5,515 5,515
216 0100 WATER M GAL 170 170
230 0302 SUBGRADE PREPARATION-TYPE A-SHOULDERS STA 40 40
251 0200 SEEDING CLASS II ACRE 1.5 1.5
251 2000 TEMPORARY COVER CROP ACRE 0.8 0.8
253 0101 STRAW MULCH ACRE 2.3 2.3
261 0112 FIBER ROLLS 12IN LF 5,625 5,625
261 0113 REMOVE FIBER ROLLS 12IN LF 1,880 1,880
302 0100 SALVAGED BASE COURSE TON 348 348
302 0120 AGGREGATE BASE COURSE CL 5 TON 1,306 1,306
401 0050 TACK COAT GAL 616 616
401 0060 PRIME COAT GAL 875 875
411 0105 MILLING PAVEMENT SURFACE SY 106,433 106,433
411 0132 RELAYING MILLED MATERIAL TON 8,811 8,811
430 0045 SUPERPAVE FAA 45 TON 1,325 1,325
430 5828 PG 58-28 ASPHALT CEMENT TON 79.4 79.4
550 0355 CONCRETE OVERLAY CY 14,695 14,695
550 0365 CONCRETE PLACEMENT - DOWELED SY 71,934 71,934
702 0100 MOBILIZATION L SUM 0.815 0.815
704 0100 FLAGGING MHR 800 800
704 1000 TRAFFIC CONTROL SIGNS UNIT 8,773 8,773
704 1041 ATTENUATION DEVICE-TYPE B-55 EA 2 2
704 1052 TYPE III BARRICADE EA 119 119
704 1060 DELINEATOR DRUMS EA 97 97
704 1067 TUBULAR MARKERS EA 107 107
704 1072 FLEXIBLE DELINEATORS EA 504 504
704 1080 STACKABLE VERTICAL PANELS EA 11 11
ESTIMATE NUMBER: 17659 RUN DATE: 11/13/2017 TIME: 14:36:21
Approach Leave
Paving Direction
Basket Support Wire
Wrap-around Type Clip
Min. 2" Dowel Bar Basket Assembly
Basket Clips
Inset A
Inset A
Basket Support Wire
Paving Direction
assembly.
3. Provide a minimum of 10 clips per dowel bar basket
support wire.
2. Install basket clip on the leave side of the basket
1. Provide wrap-around clips with a minimum 2" nail.
Note:
8397
1/14/2017
20
STATE PROJECT NO.
ND
NO.
SHEET
NO.
SECTION
11/14/2017 scahlin R:\project\60002295.122\design\020GD_006_Dowel Bar .dgn4:20:47 PM
of Transportation
North Dakota Department
document is stored at the
on and the original
PE- ,
Registration Number
issued and sealed by
This document was originally
NH-6-002(122)295 6
Basket Clip Detail
Milling and PCC Overlay
Sheet Added11/14/2017
ND 1 E 0.5 Mi. & 5.5 Mi E ND 1 to W Jct ND 35 (EB)
Sara A. Cahlin,
Spec Code Description Quantity
202 0021 Surfacing & Base AggregateRemove 967TON
203 0109 Topsoil 568CY
203 0104 Excavation -Borrow 3126CY
203 0302 A-Shoulders Prep-TypeSubgrade 20STA
709 0151 R1 Type MaterialGeosynthetic 1639SY
714 7036 18IN PVCPipe 324LF
1470
1475
1480
1485
1490
1495
1500
1505
1510
1515
1520
1525
1530
1535
1540
1545
1470
1475
1480
1485
1490
1495
1500
1505
1510
1515
1520
1525
1530
1535
1540
1545
STATE PROJECT NO.
ND
NO.
SHEET
NO.
SECTION
11/13/2017 scahlin R:\project\60002295.122\design\060PP_001_Wxover_1.dgn11:44:51 AM
of Transportation
North Dakota Department
document is stored at the
on and the original
PE- ,
Registration Number
issued and sealed by
This document was originally
60
NH-6-002(122)295 1
Plan & Profile 9+20 to 14+80
Milling and PCC Overlay
ND 1 E 0.5 Mi & 5.5 Mi E ND 1 to W Jct ND 35 (EB)
8397
Sara A. Cahlin,
Revised 11/13/17
11/13/17
50120-24
RC
PF
FN
EN
DS I
N
SR
CP
50122INVERT
50119
1506.07
+24RCPF PP CATTAIL MUCK
50052TFO
1 RCFES S. end cattail muck (poor)
24" X Ð RCP (poor)
15593+77 - 83' RT to S end
50049TFO
50045TFO
50055-TFO
50046TFO
50115
1506.92
+18
CS
PF
PP
BE
NT
AN
D
MU
CK
2 CSFES bent and muck (poor)
18" X 68' CSP (poor)
15594+37 - 1' LT
50051TFO
MIDCO50048
TFO
50054TFO
50177-SGN
Sign
50043TFO
50047TFO
50044TFO
50050TFO
50116
1507.46
-18CSPF FF
50042TFO
50167-SGN
Culverts Ð
50174-SGN
Sign50180
SGN
50041TFO
50176+SGN
50121TOP
50040TFO
Tel Mkr
50238+UEC
50171+SGN
Sign50179
-SGN
50053UMT
Tel Mkr
50178+SGN
50164SGN
50181SGN
50175SGN
50173+SGN
50166+SGN
50242-UEC
50243+UEC
Brush
Lg bushes
Brush
50253UEC
50172-SGN
50250UEC
50168SGN
50251UEC
MUNICIPAL50244
UEC
50252UEC
50247UEC
50241UEC
50245UEC
MU
NICIP
AL
50248UEC 50249
UEC
50246UEC
Asph
Asph
Asph
50170SGN
50169SGN
Conc
50239UEC
for the OH line Xing near Sta 15591+80 is 41.9'
The centerline East bound Vertical clearance
50240UEC
SRCP
Sign
Sign
8595+00
8600+00
15580
+00
15585
+00
15590
+00
15595
+00
R/W Mon
Begin 15577
+92.13
R-60-W
T-153-N
Sec 27
R-60-W
T-153-N
Sec 34
RTK 53
LAKOTA
#6 I
Pn
Sec line
#5 Rebar
Sta 8595+94.56 ND 1
Sta 15600+71.04 US 2 =
Station Equation:
US 2
Proposed
Existing
1,512.87
1,512.82
1,512.71
1,511.81
1,509.83
1,509.22
1,511.20
1,512.48
1,513.09
1,513.16
1,512.59
1,512.68
1,512.77
1,512.86
1,512.96
Spec Code Description Quantity
202 0021 Surfacing & Base AggregateRemove 658TON
203 0103 C Excavation-TypeCommon 373CY
203 0109 Topsoil 554CY
203 0104 Excavation -Borrow 2389CY
203 0302 A-Shoulders Prep-TypeSubgrade 20STA
709 0151 R1 Type MaterialGeosynthetic 1639SY
714 7036 18IN PVCPipe 380LF
1490
1495
1500
1505
1510
1515
1520
1525
1530
1535
1540
1545
1550
1555
1560
1565
1490
1495
1500
1505
1510
1515
1520
1525
1530
1535
1540
1545
1550
1555
1560
1565
STATE PROJECT NO.
ND
NO.
SHEET
NO.
SECTION
11/13/2017 scahlin R:\project\60002295.122\design\060PP_015_exover_1.dgn1:22:41 PM
of Transportation
North Dakota Department
document is stored at the
on and the original
PE- ,
Registration Number
issued and sealed by
This document was originally
60
NH-6-002(122)295 15
Plan & Profile 1+80 to 7+60
Milling and PCC Overlay
ND 1 E 0.5 Mi & 5.5 Mi E ND 1 to W Jct ND 35 (EB)
8397
Sara A. Cahlin,
Revised 11/13/17
11/13/17
1 RCFES S. end (good)
24" X 88' RCP (good)
16117+36 - 83' RT to S end
1516.6121894
-30RCPF FF
2 RCFES (fair)30" X 170' RCP (fair)16106+39 - 84' RT to S end16106+27 - 87' LT to N end
21891-30RCPF GN
21890 1516.72+30RCPF GG
21896
1516.76
-24CSPF FF
21895
1516.85+24CSPF FF
2 CSFES (fair)
24" X 70' CSP (fair)
16112+09 - 110' RT to E end
16111+38 - 117' RT to W end
50677TFO2
21893+30RCPF FN
50674TFO2
50476TFO
POLAR
50475TFO
50474TFO
50670TFO2
50673TFO1
50473TFO
50472TFO
50480TFO
50676TFO1
50481UMT
Tel Mkr
50671TFO1
21892STEEL PIPE -2.52I
NV
SRCP
50675TFO1
2 CSFES (good)24" X 43'
CSP (good)16094+4
2 - 128' LT
50482TFO
1519.53+24CSPF GG
50471UMT
Tel Mkr
50477TFO
50469POLAR
Tel Mkr50468!TB
50467TB
Tel boxFO
50465+TB
50466TB
50663+TFO POLAR
Wire
50470TFOPOLAR
Wire
50669TFO2
50664TFO
50668TFO1
50666TFO2
50662TFO250665-TFO50661
TFO2
50478TFO
50667TFO1
Asph
50479TFO
Gr
Conc
Gr
Lg trees
50543SGN
50542SGN
Yard Lht
Asp
hAsph
Conc
Lg Evgrs
Asph
Lg trees
178.98'
16095
+00
PC 16098
+11.71
16100
+00
16105
+00
16110
+00
16115
+00
PT 16116
+08.30
PI 16107
+14.17
Curve CAP8
R = 7,639.49T = 902.46L = 1,796.59
R Mkr 305
R Mkr 305
R/W Mon
R/W MonR/W Mon
R/W Mon
R/W Mon
Mons
2-R/W
Mons
2-R/W
Mons
2-R/W
PI = 16107+14.17
E 2546430.88
N 381350.53
R-58-WT-152-NSec 6
#5
Rebar
T-ironRec Sec
Cor
MICHIGAN114th A
ve N
E
(Adh Tan)
Twp line Xing
Twp line
Twp line
1,490
1,500
1,510
1,520
1,530
Proposed
Existing
-+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 10+00 11+00
1,400
1,410
1,528.20
1,528.09
1,527.73
1,526.89
1,525.13
1,522.88
1,523.06
1,524.66
1,524.80
1,524.21
1,523.82
1,523.50
1,527.73
1,527.24
1,526.75
1,526.26
1,525.77
1,525.29