Projects OPR
2 June 2016 DECOMMISSIONING
The Case for Metrics
Win Thornton
VP Decommissioning
BP
15 Nov 2016 1
Agenda….the Case for Metrics
• Industry Standards for Guidance
• Types of Metrics for
Decommissioning
• Example Class 5 Cost Metrics
• Example Class 4 Cost Metrics
• Next steps in the use of Metrics in
Decommissioning
2
OGUK Work Breakdown Structure WBS
3
AACE Estimate Classification (18R-97)
4
What type of metrics for Decommissioning?
Performance (like Insight)
• Cost per asset component - £XX/well P&A
• Cost per unit measure - £YY/Te
• Some concern on need for anonymity to protect commercial data
Activity
• Time per well P&A – X.X days
• Cycle time for module removal: rig, lift and backload – Y.Y days
• Limited concern on anonymity, easier to share data, requires more granularity of data
Scope
• Number of B Annuli that need remediation – 1 out of 4
• Number of DPZ requiring barrier – 2 DPZ 80% of well stock
• Number of padeyes existing and suitable for use – 60%of padeyes suitable
Probabilistic vs Deterministic
• Probabilistic data set with P10/P50/P90 to illustrate uncertainty and variability. Identify drivers to
improve performance
• Need to segregate performance/activity from scope metrics to understand drivers 5
Example Class 5 Cost Metrics
OGUK WBS Scope Data Source Basis of Estimate Metric/NORM Estimate % % Insight
Operator Project
Management
Compay Project Team (6% PMT & 1%
Studies)7% £20,000,000 7%
Facility Running/Owner
CostsP&A 50% wells preCOP 80% final year OPEX £40,000,000 14%
Wells Abandonment 20 wells region well inventoryP&A 50% wells preCOP with exisitng
rig. No refurb req'd£4MM/well £80,000,000 29% 29% 31%
Facilities/Pipelines Making
Safe50% prep time SIMOPS with P&A 5% of removal costs £5,500,000 2%
Topsides Preparation50% prep time SIMOPS with P&A;
modules have all lifting aids in place5% of removal costs £5,500,000 2%
Topsides Removalreverse installation of modules and
backload to HLV for transit£3,500/Te £70,000,000 25%
Substructure Removal 18,000 Tederogation of jacket footings and
single lift of top section to shore£4,000/Te £40,000,000 14%
Topsides & Substructure
Onshore Recycling30,000 Te
assumed weight removed
w/derogation
backload to disposal site, demo &
recycle£150/Te £4,500,000 2%
Subsea Infrastructure20" 3rd party gas;
16" 3rd party oilPipeline database Obligation to clean & disconnect £5MM/pipeline £10,000,000 4%
Site Remediation 0 M3 region inventory No drill cuttings or debris £0 0%
Monitoringtwo inspections (1@5 yrs & 1@10yrs)
as part of industry program£1MM/inspection £2,000,000 1%
£277,500,000 100% 100% 100%Totals
22% 36%
50% 33%
20,000 Te
Photo & OSPAR database
6
Example Class 5 Cost Metrics
OGUK WBS Scope Data Source Basis of Estimate Metric/NORM Estimate % % Insight
Operator Project
Management
Compay Project Team (6% PMT & 1%
Studies)7% £20,000,000 7%
Facility Running/Owner
CostsP&A 50% wells preCOP 80% final year OPEX £40,000,000 14%
Wells Abandonment 20 wells region well inventoryP&A 50% wells preCOP with exisitng
rig. No refurb req'd£4MM/well £80,000,000 29% 29% 31%
Facilities/Pipelines Making
Safe50% prep time SIMOPS with P&A 5% of removal costs £5,500,000 2%
Topsides Preparation50% prep time SIMOPS with P&A;
modules have all lifting aids in place5% of removal costs £5,500,000 2%
Topsides Removalreverse installation of modules and
backload to HLV for transit£3,500/Te £70,000,000 25%
Substructure Removal 18,000 Tederogation of jacket footings and
single lift of top section to shore£4,000/Te £40,000,000 14%
Topsides & Substructure
Onshore Recycling30,000 Te
assumed weight removed
w/derogation
backload to disposal site, demo &
recycle£150/Te £4,500,000 2%
Subsea Infrastructure20" 3rd party gas;
16" 3rd party oilPipeline database Obligation to clean & disconnect £5MM/pipeline £10,000,000 4%
Site Remediation 0 M3 region inventory No drill cuttings or debris £0 0%
Monitoringtwo inspections (1@5 yrs & 1@10yrs)
as part of industry program£1MM/inspection £2,000,000 1%
£277,500,000 100% 100% 100%Totals
22% 36%
50% 33%
20,000 Te
Photo & OSPAR database
7
Example Class 4 Cost Metrics – Topsides Removal
8
Original Strucural Analysis & Results at Hand
Structural Integrity Monitored & Suitable for Decom
All Modules Inspected
All Module Seperation & Prepartion Doable for Reverse Installation
All Padeyes Present & Usable
Weight Control Up to Date and Verified
HLV Barge
Mob/Demob HLV 1 6 day £750,000 £/day £4,500,000 6
Charter Barge 3 45 day £15,000 £/day £2,025,000 135
Charter Tug 3 21 day £35,000 £/day £2,205,000 63
Engineering & PM Lump Sum 1 Lump Sum £ £5,000,000
Setup HLV 1 5 day £750,000 £/day £3,750,000 5
Remove Modules HLV 22 2 day £750,000 £/day £33,000,000 44
Backload to CB HLV 22 1 day £750,000 £/day £16,500,000 22
Transit & Offload HLV 1 5 day £750,000 £/day £3,750,000 5
Weather Spread 10% 82 % £830,000 £/day £6,806,000
Contingency Spread 10% 82 % £830,000 £/day £6,806,000
£84,342,000 82 198
Time (days)Task Resource Quanity Duration Unit Costs Unit Total Costs
£84,342,000 £4,217
£70,000,000 £3,500
£14,342,000 21%
Example Class 4 Cost Metrics – Topsides Removal
9
Original Strucural Analysis & Results at Hand
Structural Integrity Monitored & Suitable for Decom
All Modules Inspected
All Module Seperation & Prepartion Doable for Reverse Installation
All Padeyes Present & Usable
Weight Control Up to Date and Verified
HLV Barge
Mob/Demob HLV 1 6 day £750,000 £/day £4,500,000 6
Charter Barge 3 45 day £15,000 £/day £2,025,000 135
Charter Tug 3 21 day £35,000 £/day £2,205,000 63
Engineering & PM Lump Sum 1 Lump Sum £ £5,000,000
Setup HLV 1 5 day £750,000 £/day £3,750,000 5
Remove Modules HLV 22 2 day £750,000 £/day £33,000,000 44
Backload to CB HLV 22 1 day £750,000 £/day £16,500,000 22
Transit & Offload HLV 1 5 day £750,000 £/day £3,750,000 5
Weather Spread 10% 82 % £830,000 £/day £6,806,000
Contingency Spread 10% 82 % £830,000 £/day £6,806,000
£84,342,000 82 198
Time (days)Task Resource Quanity Duration Unit Costs Unit Total Costs
£84,342,000 £4,217
£70,000,000 £3,500
£14,342,000 21%
Scope Reduction
What does good look
like?
Next steps for decommissioning metrics