Manasota Basin
Projects
April 2010
Table of ContentsBasinBookReport-FY2010 v2.3 Production March 23.rpt.......................................................................................................................... 1
Z010 - Boards & Executive Services - Manasota Basin.................................................................................................... 1
Z030 - Planning - Manasota Basin.................................................................................................................................... 2
Z050 - Information Resources - Manasota Basin.............................................................................................................. 3
Z060 - Communications - Manasota Basin....................................................................................................................... 4
Z090 - Community Affairs - Manasota Basin..................................................................................................................... 5
Z300 - Resouce Data and Restoration Department - Manasota Basin............................................................................. 6
Z500 - Resource Projects - Manasota Basin..................................................................................................................... 7
Z600 - Operations - Manasota Basin................................................................................................................................ 8
Z700 - Land Resources - Manasota Basin........................................................................................................................ 9
Z910 - Commissions - Manasota Basin............................................................................................................................ 10
Z930 - Contingencies - Manasota Basin........................................................................................................................... 11
S005 - Myakka River......................................................................................................................................................... 12
S019 - Edward W. Chance Reserve................................................................................................................................. 13
S024 - Upper Myakka River Watershed............................................................................................................................ 14
S030 - RV Griffin Reserve................................................................................................................................................. 15
S031 - Myakka Prairie....................................................................................................................................................... 16
S032 - Little Manatee River............................................................................................................................................... 17
S041 - Myakkahatchee Creek........................................................................................................................................... 18
S042 - Tampa Bay Estuarine Ecosystem.......................................................................................................................... 19
S099 - Save Our Rivers Administration............................................................................................................................. 20
SA05 - Deer Prairie Creek................................................................................................................................................. 22
SA19 - Lake Manatee Lower Watershed Upland Restoration #1...................................................................................... 23
SA31 - Myakka State Forest Hydrologic Rstr.................................................................................................................... 25
SB05 - Myakka River Deer Prairie Creek Preserve Wetland Restoration......................................................................... 27
SB19 - Edward W. Chance Reserve Hydrologic Rstr....................................................................................................... 28
SB31 - Myakka River State Park-Myakka Prairie Tract Wetland Restoration................................................................... 30
W020 - SWIM Plan Implementation - Tampa Bay............................................................................................................. 31
W027 - Tampa Bay Estuary Program............................................................................................................................... 33
W028 - Bay Soundings...................................................................................................................................................... 36
W030 - Tampa Bay Watch Field Trip Program................................................................................................................. 38
W226 - City of Anna Maria-Implementation of BMPs........................................................................................................ 40
W312 - Tampa Bay Habitat Restoration............................................................................................................................ 43
W316 - Cockroach Bay (Phases C-D-E-F)........................................................................................................................ 45
W331 - Biennial Seagrass Mapping of Tampa Bay, Sarasota Bay, Charlotte Harbor...................................................... 48
W348 - Terra Ceia Isles Habitat Restoration..................................................................................................................... 51
W358 - Tom Bennett Park................................................................................................................................................. 54
W364 - Palmetto Estuary.................................................................................................................................................. 56
W394 - FELTS Preserve Restoration................................................................................................................................ 58
W501 - SWIM Plan Implementation - Charlotte Harbor.................................................................................................... 60
W506 - CHEC Charlotte Harbor/Lemon Bay SWIM Watershed Education....................................................................... 62
W509 - Alligator Creek In-Stream Restoration.................................................................................................................. 65
W521 - Charlotte Harbor Water Quality Monitoring........................................................................................................... 67
W526 - Charlotte Harbor National Estuary Program......................................................................................................... 69
W528 - Myakka River Water Quality Monitoring............................................................................................................... 71
W552 - Sarasota County Pollutant Model Development................................................................................................... 73
W558 - Venice Hatchett Creek Stormwater Facility.......................................................................................................... 75
W559 - Assessment of 2008 Seagrass Maps in Charlotte Harbor And Lemon Bay......................................................... 77
W601 - SWIM Plan Implementation - Sarasota Bay......................................................................................................... 79
W602 - Neal Preserve Environmental Restoration............................................................................................................ 81
W603 - Ungarelli Preserve................................................................................................................................................ 83
W604 - Phillippi Creek In-stream Restoration................................................................................................................... 85
W611 - Sarasota Bay Spoil Island Restoration Project..................................................................................................... 87
W612 - Sarasota Bay Estuary Program............................................................................................................................ 89
W613 - Sarasota-Catfish Creek SW Facility-Phase II....................................................................................................... 91
W616 - Sarasota Bay Habitat Restoration........................................................................................................................ 94
W617 - Sarasota Imp. BMPs Coastal Basin Beach Road................................................................................................. 96
W619 - Perico Preserve Environmental Restoration......................................................................................................... 98
W620 - Pelican Cove Stormwater Retrofit......................................................................................................................... 100
W621 - Little Sarasota Bay Water Quality Management Plan........................................................................................... 102
W622 - Sarasota Bay Water Quality Management Plan................................................................................................... 104
W623 - Holmes Beach Stormwater Retrofit...................................................................................................................... 106
W624 - Red Bug Slough Restoration................................................................................................................................ 108
W625 - Runaway Bay - Sarasota Bay Coast Line Restoration......................................................................................... 110
W626 - Blackburn Point Park Addition.............................................................................................................................. 112
W627 - Bradenton Beach Stormwater Retrofits................................................................................................................ 114
B074 - Manatee - WMPlan Braden River.......................................................................................................................... 116
B099 - Quality of Water Improvement Program - Manasota Basin................................................................................... 119
B131 - Hotel/Motel/Restaurant Water Conservation Program (Water CHAMP/PRO)....................................................... 121
B246 - Water Conservation/FYN Regional Builder/Developer Specialist.......................................................................... 124
B274 - Salt Water Intrusion Monitoring Network............................................................................................................... 127
B277 - Florida Water Star.................................................................................................................................................. 129
B310 - Manatee - Maintenance of Watershed Parameters and Models........................................................................... 132
B315 - Sarasota - Maintenance of Watershed Parameters and Models........................................................................... 134
B620 - Mapping and GIS................................................................................................................................................... 136
B630 - Field Operations 021............................................................................................................................................. 138
B733 - FYN Manatee County............................................................................................................................................ 139
B735 - FYN Sarasota County............................................................................................................................................ 141
P259 - Youth Water Resources Education........................................................................................................................ 143
P268 - Public Education.................................................................................................................................................... 146
F032 - Peace River Regional Reservoir Expansion.......................................................................................................... 150
F033 - Peace River Facility Expansion............................................................................................................................. 153
H008 - Lake Hancock Lake Level Modification................................................................................................................. 156
H009 - Lake Hancock Outfall Structure P-11 Modification................................................................................................ 160
H015 - FARMS Back-Plug Program.................................................................................................................................. 162
H017 - Facilitating Agricultural Resource Management Systems Program...................................................................... 164
H024 - Upper Peace River Resource Development.......................................................................................................... 166
H048 - Myakka River Watershed Initiative........................................................................................................................ 170
H050 - PR/MRWSA Reg Integ Loop Sys Phase 1 Interconnect....................................................................................... 173
H051 - PR/MRWSA Reg Integ Loop Sys Phase 2 Interconnect....................................................................................... 175
H052 - PR/MRWSA Reg Integ Loop Sys Phase 3A Interconnect..................................................................................... 177
H059 - City of Bradenton Reservoir Expansion................................................................................................................. 179
H062 - CF Industries Aquifer Recharge and Recovery Project......................................................................................... 181
H069 - PR/MRWSA Reg Loop System Ph 1A.................................................................................................................. 183
H079 - PRMRWSA Brackish Groundwater Development................................................................................................. 185
H086 - Manatee County Regional 10 MG Reclaimed Water Storage Tank Project.......................................................... 187
H087 - City of Punta Gorda Reverse Osmosis Facility..................................................................................................... 189
H088 - Pilot Treatment Study and Intermediate Well for Dona Bay Water Supply Project............................................... 191
H089 - Flatford Swamp Hydrologic RestorationImplementation...................................................................................... 193
H093 - Manatee County Regional 10 MG RW Storage SW-2........................................................................................... 195
K114 - Bradenton - ASR Program..................................................................................................................................... 197
K120 - North Port - Water ASR - Phase V........................................................................................................................ 200
K253 - Manatee - Imp. BMPs Wares Creek...................................................................................................................... 203
K269 - Sarasota Co. - N. Sarasota Co. Reclaimed Water ASRs...................................................................................... 206
K883 - North Port WMPlan Big Slough............................................................................................................................. 208
L007 - Manatee - WMPlan Buffalo Canal/Frog Creek....................................................................................................... 210
L010 - Manatee - WMPlan Gamble Creek........................................................................................................................ 213
L210 - Implementation of BMPs - Phillippi Creek/Celery Fields........................................................................................ 216
L230 - Longboat Key Backup Potable Water Supply Interconnect................................................................................... 218
L512 - (Completed) Manatee County Shallow Well Rebate Program............................................................................... 220
L604 - Manatee - WMPlan Little Manatee River............................................................................................................... 222
L608 - Palmetto Reclaimed Water ASR............................................................................................................................ 225
L610 - Sarasota County - Watershed Plan: Lemon Bay................................................................................................... 227
L611 - Sarasota County - Watershed Plan: Roberts Bay.................................................................................................. 229
L613 - Sarasota Imp. BMPs South Pelican Drive.............................................................................................................. 231
L614 - Sarasota Imp. BMPs Matheny Creek..................................................................................................................... 233
L615 - Sarasota Imp. BMPs Alligator Creek...................................................................................................................... 235
L624 - Venice Imp. BMPs Hatchett Creek-Venice............................................................................................................ 237
L627 - City of North Port Water Conservation and Retrofit Project................................................................................... 239
L693 - Water Exhibits in the Glazer Children's Museum of Tampa................................................................................... 241
L854 - Bradenton/Manatee Co./Palmetto Reuse Interconnect Study............................................................................... 243
L867 - Sarasota County GIS Dataset Development.......................................................................................................... 245
L874 - Aqua Utilities Reuse Transmission - Eastern Lakewood Ranch............................................................................ 247
L949 - Manatee County Water Conservation Program..................................................................................................... 249
N084 - City of North Port Reuse Storage Tank and High Service Pump Station.............................................................. 251
N107 - Braden River Soil Moisture Sensor Rebate Program............................................................................................ 253
N115 - Manatee County Indoor Water Conservation Project............................................................................................ 255
N139 - Low Impact Development Manual......................................................................................................................... 257
N188 - City of Bradenton NAVD88 Vertical Control Densification..................................................................................... 259
N218 - Englewood Reclaimed Water Supply Project........................................................................................................ 261
N231 - Manatee County Toilet Rebate Project - Phase IV................................................................................................ 263
L019 - Sarasota - Update W. Para. & County maintained models.................................................................................... 265
L238 - SEC Southern Coastal Watershed Education........................................................................................................ 268
L520 - Around the Bend Nature Tours Manatee/Sarasota................................................................................................ 271
L618 - Sarasota - Watershed Management Plan: Coastal Fringe..................................................................................... 273
N014 - The Florida Aquarium Watershed Education Initiative.......................................................................................... 275
N151 - Manatee County NAVD88 Vertical Control Densification...................................................................................... 277
N255 - Beach Water Quality Project................................................................................................................................. 279
N263 - Manatee County - Watershed Evaluation.............................................................................................................. 281
N275 - Sarasota County - Watershed Evaluation............................................................................................................ 283
N276 - Low Impact Design Implementation at Venice East Blvd...................................................................................... 285
N277 - City of North Port Reclaimed Water Transmission Expansion Phase I................................................................. 287
N306 - Sarasota County - Englewood CRA Stormwater Retrofit...................................................................................... 289
N325 - Manatee County Toilet Rebate Program Phase V................................................................................................ 292
L015 - Sarasota County Surface Water Monitoring Program............................................................................................ 294
L200 - Bradenton - Wares Creek Bridge Replacement..................................................................................................... 296
N281 - Nokomis Drainage Improvement and Stormwater Treatment............................................................................... 299
N181 - Science Curriculum Enhancement Program......................................................................................................... 300
N206 - G.WIZ Water Wonders Workshop......................................................................................................................... 302
N215 - Anna Maria Island - Watershed Evaluation........................................................................................................... 304
N268 - Watershed Education Classroom.......................................................................................................................... 306
N273 - Sarasota County Park Facility Construction.......................................................................................................... 308
N294 - Sarasota County Outdoor Conservation Kits......................................................................................................... 310
N297 - PRMRWSA Water Supply Construction & Operations Educational Video............................................................ 312
N310 - Venice Greenhouse Rain Harvest System............................................................................................................ 313
N082 - City of North Port Myakkahatchee Creek Water Treatment Plant RBF/RO Reliability Project.............................. 314
N266 - City of North Port - Como Waterway Water Control Structure.............................................................................. 316
M110 - Manatee - FEMA Map Modernization................................................................................................................... 318
M115 - Sarasota - FEMA Map Modernization................................................................................................................... 320
M118 - FEMA Map Modernization Management Support................................................................................................. 323
Z010
Boards & Executive Services - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
N/ACooperator(s)
Project Manager KAVOURAS, LOU
Task Manager(s)
Status Ongoing
DescriptionThe Boards and Executive Services Department provides administrative support to the Basin Board. These support
activities include noticing, scheduling and preparing the agenda and minutes for regular and special meetings and
workshops. Other functions include preparing meeting and travel arrangements and correspondence for Board
members. The Deputy Executive Director for Outreach, Planning and Board Services is the primary staff liaison for
members. The Deputy also assists with the conduct of meetings, works with the Governor's staff to ensure the legal
constitution of Boards, coordinates with appropriate staff to ensure follow up on meeting issues, conducts new
member orientation and ensures compliance with the Sunshine Laws. In addition, the Deputy and staff coordinate
Board field trips, including planning, scheduling, meals, logistics and arranging for staff support. This budget item also
provides funds for equipment and facility rental, legal advertisements for meeting notices, miscellaneous office
supplies and printing and Board member travel reimbursements (e.g., meals, conference registration, mileage, etc.).
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 1
Z030
Planning - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager DAVIES, DIANNE
Task Manager(s)
Status Ongoing
DescriptionPlanning is an Executive support function responsible for long-range comprehensive planning and near-term strategic
planning. Department staff administer the Comprehensive Watershed Management initiative; provide Basin Board
support; and assist the Basin Board with development of resource management priorities.
BenefitsPlanning Department staff support the Basin Board through the following tasks. Project Management Database project
worksheets that are used in the Budget Notebook for each Basin Board meeting are reviewed to ensure accuracy and
completeness. Planning staff work with project managers to identify any significant issues and resolve any
discrepancies. Staff take the lead in preparing for joint Governing and Basin Board Planning Workshops and for the
Basin Board's Annual Planning Workshop. Basin Board meetings are attended and presentations are made to the
Board on an as-needed basis. Staff often coordinate responses to issues raised during meetings. Staff respond to
Board Member questions and requests via oral and written communications. Staff assist Basin Board members by
creating and providing presentations on Basin-specific issues. At the Board's request, research is conducted and
special issues are presented during Board meetings. Department staff assist the Community Affairs Coordinators with
Cooperative Funding kick-off meetings held for local governments and other potential cooperators. Assistance is
provided for new Board member orientations.
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 2
Z050
Information Resources - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager LEWIS, JIM
Task Manager(s)
Status Ongoing
DescriptionVideo production and conferencing staff provides audio-visual, archive tape, and video teleconferencing support for
Basin Board and Governing Board meetings, including staff presentations. Audio-visual staff provides support for
annual Basin Board planning workshops, and the semiannual Governing Board/Basin Board planning workshops, as
well as other non-regularly scheduled workshops not held in a District office, as needed. Based on the time devoted to
these activities, including travel, the appropriate salary percentage is allocated to each Basin Board.
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 3
Z060
Communications - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
N/ACooperator(s)
Project Manager MOLLIGAN, MICHAEL
Task Manager(s)
Status Ongoing
DescriptionThe Communications Department is an Executive support function responsible for a broad range of activities that
support the District's mission, Governing and Basin boards, and other departments. Departmental functions include
projects funded by the Governing and Basin boards, such as public information and media coordination; youth and
public education programs and initiatives in coordination with local governments and other community organizations;
promotion of sound water conservation practices; presentation of projects to the Basin boards in the budget adoption
process; and graphics support for Basin Board presentations. Communications Department staff support the Basin
Board through the following tasks. Basin Board meetings are attended on an as-needed basis to make presentations,
answer questions, and participate in budget discussions. Reponses are prepared to answer Board Member questions
and requests via oral and written communications. Educational materials are developed, reviewed, updated, promoted,
and distributed. Assistance is provided to cooperators to develop education projects that support the District's mission.
Education and grant programs are promoted at schools and to cooperators. Support is provided to the Basin Board
Education Committee. Media contact summaries and articles are disseminated. The District's web site is maintained.
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 4
Z090
Community Affairs - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager RATHKE, DAVID
Task Manager(s)
Status Ongoing
DescriptionBasin Board funds budgeted are for the administration and coordination of the Cooperative Funding program, including
conducting cooperator workshops, processing applications, communicating with applicants and participating in project
ranking. Basin Board funds are budgeted for the Community Affairs Coordinator (CAC) to attend and participate in
Basin Board meetings and new Board member orientations and briefings and for the CAC's responses to Board
member information requests, as well as other "as needed" services to the Basin Board.
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 5
Z300
Resouce Data and Restoration Department - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager DEHAVEN, ERIC
Task Manager(s)
Status Ongoing
DescriptionThe Resource Data and Restoration Department is involved in the collection, management, and analysis of water
resource data and the development and implementation of restoration projects to improve resource conditions. The
Department includes five sections comprised of professional and technical staff with oversight from an administrative
section. The FARMS Section is involved in the implementation of innovative agricultural water conservation and
alternative supply projects that are designed to reduce ground water withdrawals and improve water quality within the
Southern Water Use Caution Area (SWUCA). The Water Quality Monitoring Program (Section) performs water quality
sampling and analysis for a number of long-term ground and surface-water monitoring efforts, as well as specific,
short-term projects that investigate water quality issues. The Geohydrologic Data Section supports the Regional
Observation Monitor Well Program (ROMP) and the Quality of Water Improvement Program (QWIP), which provide
hydrogeologic data and well construction services. The Chemistry Laboratory Section conducts the water quality
analysis for District-related projects (Cooperative Funding and initiatives) and programs (regulation). Finally, the
Surface Water Improvement and Management (SWIM) Section is responsible for implementing the SWIM legislation
which requires that the water management districts prepare and maintain a priority list of water bodies requiring
management action for restoration or preservation; write management plans consistent with the rules established by
the Department of Environmental Protection; and implement the plans.
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 6
Z500
Resource Projects - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
N/ACooperator(s)
Project Manager HAMMOND, MARK
Task Manager(s)
Status Ongoing
DescriptionThe Resource Projects Department addresses issues related to water supply, flood protection, water quality, and
natural systems and consists of the Conservation Projects, Ecologic Evaluation,
Engineering, Environmental, Hydrologic Evaluation, and Water Supply and Resource Development sections. The
District's goal for water supply is to ensure an adequate supply of the water resource to provide for all existing and
future reasonable and beneficial uses while protecting and maintaining water resources and related natural systems.
The Department's efforts involve activities associated with the regional water supply planning, alternative water
supplies, conservation, and reclaimed water strategic initiatives. The District's goal for flood protection is to minimize
flood damage to protect people, property, infrastructure and investment. The Department's efforts primarily involve
activities associated with the floodplain management strategic initiative and support for the flood and emergency
response initiative. The District's goal for natural systems is to preserve, protect, and restore natural systems in order
to support their natural hydrologic and ecologic functions. The Department's efforts involve minimum flows and levels
and wetland system restoration. The District's goal for water quality is to protect and improve water quality to sustain
the environment, economy and quality of life. The Department's efforts involve diagnostic, monitoring and
implementing water quality improvement projects. The funds budgeted here are for coordinating the Water Supply
and Resource Development Program, Water Resource Assessment Projects, Minimum Flows and Levels Program,
Watershed Management Program, FEMA Map Modernization, and Cooperative Funding Programs, as-requested
attendance at citizen meetings, and those unforeseen basin analyses which occur during the year. The Department
works on ongoing projects and reviews, evaluates, and ranks each Fiscal Year's Cooperative Funding projects related
to water supply, water quality, natural systems, and flood protection. Staff makes recommendations regarding these
projects, and other items proposed in each year's budget. Staff also works to address any budget issues identified at
Basin Board meetings. The funds budgeted here are for staff time related to coordinating those activities that do not
relate to specific budgeted projects. These include the staff time of the Director, managers and several staff.
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 7
Z600
Operations - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager HOLTKAMP, MIKE
Task Manager(s)
Status Ongoing
DescriptionThe Operations Department consists of six sections including Administration, Field Operations, Aquatic Plant
Management, Hydrologic Data, Structure Operations and Mapping and GIS. The Administration section provides
support for departmental management, planning, budgeting, and clerical functions. The Field Operations section is
responsible for maintenance and restoration of all District-owned lands including fence construction, mowing, culvert
installations, road and bridge maintenance and construction, fire line maintenance, prescribed burn support, erosion
control, and well site preparation/restoration. The Aquatic Plant Management section is responsible for aquatic and
ditch bank vegetation management operations on District flood control systems, the control of exotic aquatic plants on
natural waters throughout the District, and the control of aquatic vegetation around water control structures and lake
level gauges. Additionally, the Aquatic Plant Management section controls/eradicates infestations of upland invasive
species including Brazilian pepper, Australian pine, cogongrass and tropical soda apple on all District-owned
conservation lands. The Hydrologic Data section is responsible for designing, installing, and maintaining data
collection sites in support of the District's resource monitoring and technical analysis, as well as data analysis and
database management. The Structure Operations section inspects, operates, maintains, and repairs all District-owned
flood and water conservation structures as well as salinity barriers throughout the District. This section also directs and
operates the District's Emergency Operations Center (EOC), which is part of a state and nationwide storm tracking
and emergency response network.The Mapping and GIS section is responsible for providing and maintaining all
mapping and Geographical Information System database support. Included in this project are administrative salary
allocations associated with overseeing field operations and maintenance, aquatic plant management, emergency
operations, Supervisory Control and Data Acquisition (SCADA), and structure operations programs throughout the
Basin, as applicable. Funds expended have been to prepare for Basin Board meetings as required or provide data to
Board members, local agencies or the public.
Status As Of: May 12, 2009
Ongoing project details are shown in the project description.
021 - Manasota Basin 8
Z700
Land Resources - Manasota Basin
Project Type On-Going Activities
AORs Strategic Initiatives
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager SUTTON, ERIC
MILLER, WILL, WALSH, TOM, LOVE, KEVIN, BLASCHKA, STEVENTask Manager(s)
Status Ongoing
DescriptionThe Land Resources Department consists of five sections, including Administration, Land Acquisition, Land
Management, Survey, and Land Use and Protection. The Administration section provides support for departmental
management, planning, budgeting and clerical functions. The Land Acquisition section acquires lands as set forth in
the District's Florida Forever Workplan. These lands are acquired for various functions including flood control, water
storage and management, conservation and protection of water resources, aquifer recharge and recovery, water
resource development, and preservation of wetlands, streams, lakes, and other natural systems. The Land
Management section is responsible for the management and protection of natural and cultural resources on District
lands. Major functions include natural systems restoration, prescribed burning, forest management, exotic species
control, and monitoring. The Survey section is responsible for providing land surveying assistance in support of various
projects and programs within the District. The Land Use and Protection section is responsible for land use activities on
District lands including development of recreational trails and facilities, monitoring of public and private uses,
management of the security officer program and maintaining visitor safety. Included in this project are activities on
District-managed lands purchased with funds other than Florida Forever, Preservation 2000 and Save Our Rivers such
as surveying costs (salaries and equipment rental), miscellaneous land use requests (salaries), resource protection
(utilities and maintenance) and structural flood control projects.
Status As Of: March 13, 2007
As of this date, this project will not show an update. Ongoing project details are shown in the project description.
021 - Manasota Basin 9
Z910
Commissions - Manasota Basin
Project Type Prop. App.&Tax Coll.
AORs Strategic InitiativesManagement Services Management Services
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager PILCHER, LINDA
CACIOPPO, MIKE, LINSBECK, CATHYTask Manager(s)
Status Ongoing
DescriptionThese funds pay the commissions due to the counties within the Basin for tax collection and property appraisals.
Status As Of: March 01, 2010
During the five months ended February 28, 2010, $225,815 was remitted in commissions to Property Appraisers and Tax
Collectors. Property Appraiser and Tax Collector commissions are statutorily prescribed and are based on property tax
levies and collections, respectively. Amounts collected in excess of the underlying Property Appraiser and Tax Collector
budgets are returned to the Basin as excess fees. Excess fees not recorded as accounts receivable as of September 30,
2009 are reflected as current FY2010 revenue.
021 - Manasota Basin 10
Z930
Contingencies - Manasota Basin
Project Type Reserves
AORs Strategic InitiativesManagement Services Management Services
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager PILCHER, LINDA
CACIOPPO, MIKE, LINSBECK, CATHYTask Manager(s)
Status Ongoing
DescriptionFunds are budgeted for contingencies to be used at the Board's discretion. The goal is to set aside an amount equal to
approximately 5 percent (2.5 percent minimum target) of the ad valorem based budget (ad valorem taxes plus interest
plus balance forward multiplied by 5 percent).
Status As Of: March 01, 2010
To date, the Basin Board has not allocated any of its contingency funds.
021 - Manasota Basin 11
S005
Myakka River
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager LOVE, KEVIN
NELSON, BRIAN, HAGBERG, JEFFREY, SOWDERS, GINA, MILLER, WILL, GREEN,
STEPHANIE
Task Manager(s)
Status Ongoing
DescriptionA majority of the lands within the Myakka River Save Our Rivers project were jointly purchased with the State of
Florida's Conservation and Recreation Lands (CARL) program (Myakka State Forest). Lands within the project area
are characterized by a variety of natural lands and lands altered by development including mesic pine flatwoods, oak
hammocks, shell mounds, prairie hammock and improved pasture. The project area includes portions of the Myakka
River and its floodplain forests. Lands included within the Myakka State Forest are managed by the State of Florida's
Division of Forestry (DOF). The DOF has made the following recreational improvements/ amenities available on the
property: 13 miles of marked shared use trails for bicycling, horseback riding and hiking, and primitive camping.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2010 budget consists of salaries and operational costs for public use management, resource monitoring,
resource protection, road and bridge maintenance, exotic plant control, recreation equipment, 175 acres of firelane
maintenance, 220 acres of chopping, 75 acres of road mowing; and contractual services for 465 hours of security.
Costs for these activities are reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
010 General Fund (Districtwide) 0 0
021 Manasota Basin 118,844 106,835
Funding Funding
2010 FY 2011 FY
Status As Of: February 16, 2010
Land Resources staff conducted one controlled burn along the Schewe/city of North Port interface, totaling 114 acres.
The Myakka State Forest inholding Conservation Easement (21-708-108) is being reviewed for possible amendment for
a non-profit youth equestrian camp.
021 - Manasota Basin 12
S019
Edward W. Chance Reserve
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) Peace River, Manasota
Cooperator(s)
Project Manager LOVE, KEVIN
NELSON, BRIAN, HAGBERG, JEFFREY, SOWDERS, GINA, MILLER, WILL, GREEN,
STEPHANIE, VANGELDER, WILL
Task Manager(s)
Status Ongoing
DescriptionIn 2007, the former Lake Manatee Reserve, was dedicated and renamed as the Edward W. Chance Reserve, in honor
of departed Governing Board member, Ed Chance. The Reserve extends over a large area which includes narrow
floodplain forests and native pine lands surrounded by vast areas of rangeland, improved pastures, croplands, and
citrus groves. Lands purchased within this project protect an existing regional water resource, protect floodplains, and
restore adjoining wetlands in the headwaters. Hiking is available on the property and horseback riding is allowed by a
special use permit. Management units include the Rutland Ranch and Gilley Creek Tracts.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2010 budget consists of salaries and operational costs for public use management, resource monitoring,
resource protection, road and bridge maintenance, exotic plant control, recreation equipment, 226 acres of firelane
maintenance, 70 acres of hydro-ax maintenance, 149 acres of road mowing, two culverts, and 25 days of prescribed
burning; and contractual services for 41 acres of recreational mowing and 435 hours of security. Costs for these
activities are reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
010 General Fund (Districtwide) 0 0
021 Manasota Basin 199,287 155,591
Funding Funding
2010 FY 2011 FY
Status As Of: February 16, 2010
Aquatic Plant Management Section staff treated 216 acres with scattered infestations of the invasive species
cogongrass. Prescribed burns on the Edward W. Chance Reserve at Gilley Creek property totalled 770 acres while 68
acres were burned on the Edward W. Chance Reserve at Coker Prairie property.
021 - Manasota Basin 13
S024
Upper Myakka River Watershed
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager LOVE, KEVIN
NELSON, BRIAN, HAGBERG, JEFFREY, SOWDERS, GINA, MILLER, WILL, GREEN,
STEPHANIE, VANGELDER, WILL
Task Manager(s)
Status Ongoing
DescriptionThe Upper Myakka River Watershed project is located in Manatee County and includes forested floodplain swamps
and marshes along the upper portions of the Myakka River watershed. The headwater swamps function as retention
and detention areas for local drainage. Wetland forests and adjoining uplands provide treatment of surface runoff.
Access to the property is limited since the project lands are often flooded, which is not conducive to recreational trail
development. However, the property contains narrow flatwoods roads and jeep trails that can be used for hikers during
dry weather.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2010 budget consists of salaries and operational costs for public use management, resource monitoring,
resource protection, road and bridge maintenance, exotic plant control, recreation equipment, 20 acres of firelane
maintenance, 13 acres of road mowing, and 4 days of prescribed burning; and contractual services for 18 acres of
recreational mowing and 435 hours of security.
Costs for these activities are reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
010 General Fund (Districtwide) 0 0
021 Manasota Basin 41,648 40,577
Funding Funding
2010 FY 2011 FY
Status As Of: February 17, 2010
No significant activities this period.
021 - Manasota Basin 14
S030
RV Griffin Reserve
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementWater Supply Regional Water Supply PlanningNatural Systems Natural Systems Conservation and Restoration
Basin(s) Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager LANE, CHUCK
NELSON, BRIAN, HAGBERG, JEFFREY, LANE, CHUCK, MILLER, WILL, GREEN, STEPHANIE,
ELLIOTT, PAUL
Task Manager(s)
Status Ongoing
DescriptionThe RV Griffin Reserve is located in DeSoto and Sarasota Counties and includes lands supporting and surrounding
the existing facilities at the Peace River/Manasota Regional Water Supply Authority treatment plant. Lands in the
project area include mixed hardwood forests along the river; however, the majority of the lands consist of pine
flatwoods, rangelands, pastures and pine plantations. The project supports and protects present potable water
supplies. Land management has recently been delegated to the Water Supply Authority. Recreational
activities/amenities include 21 miles of shared-use trails available for bicycling, horseback riding and hiking. A
3,804-acre conservation easement is known as the Lewis Longino Preserve.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2010 budget consists of contract coordination and monitoring for management of the land by the Peace
River/Manasota Regional Water Supply Authority.
Costs for these activities are reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
010 General Fund (Districtwide) 0 0
020 Peace River Basin 2,629 12,799
021 Manasota Basin 2,212 1,535
Funding Funding
2010 FY 2011 FY
Status As Of: January 28, 2010
Staff is communicating with the National Wild Turkey Federation and the Florida Fish and Wildlife Conservation
Commission to coordinate a special youth recreation opportunity on the Reserve. Annual inspection was conducted on
the Lewis Longino Conservation Easement, no violations were observed.
021 - Manasota Basin 15
S031
Myakka Prairie
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Florida State ParksCooperator(s)
Project Manager MILLER, WILL
SOWDERS, GINA, LOVE, KEVIN, GREEN, STEPHANIETask Manager(s)
Status Ongoing
DescriptionLands within the Myakka Prairie project are characterized by the region's flat topography and include landscapes of
extensive shrub and brushlands, pine flatwoods and pastures. Numerous isolated freshwater marshes dot the site's
flatlands. The project provides surface water detention and natural water quality treatment of overland sheet flow. The
Myakka Prairie is adjacent to lands within the Myakka River State Park and is managed by the State¿s Division of
Recreation and Parks. Recreational development/amenities on the property made available by the Division of
Recreation and Parks include several miles of hiking, bicycling and horseback riding trails. District land management
activities primarily consist of exotic species control.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2009 FY2010 budgets includes salaries for Land Resources to coordinate management responsibilities with
the Division of Recreation and Parks and to monitor the management agreement. Costs for these activities are 100
percent reimbursed through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
021 Manasota Basin 3,332 3,396
Funding Funding
2010 FY 2011 FY
Status As Of: February 17, 2010
No significant activities this period.
021 - Manasota Basin 16
S032
Little Manatee River
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Manasota
Hillsborough CountyCooperator(s)
Project Manager LOVE, KEVIN
NELSON, BRIAN, HAGBERG, JEFFREY, SOWDERS, GINA, MILLER, WILL, KRUK, COLLEEN,
VANGELDER, WILL
Task Manager(s)
Status Ongoing
DescriptionThe Little Manatee River project, located in Hillsborough and Manatee Counties, contains parcels of land along the
Little Manatee riverine corridor from downstream estuarine waters, to the river's headwaters. Dense forest dominates
the land along the river's floodplain with the adjoining uplands being comprised of a mixture of pine flatwoods, mixed
hardwoods and shrub and brushlands. The District has entered into an interlocal agreement with Hillsborough County
wherein the County has lead responsibility for lands jointly purchased by Hillsborough County and the District.
Recreational improvements/amenities made available by the County include: canoe landing sites adjacent to five
primitive campsites along the river; fishing; and hiking trails. District land management activities consist of road
stabilization, prescribed burning, natural systems restoration, mowing and recreational development/maintenance.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2010 budget consists of salaries and operational costs for public use management, resource monitoring,
resource protection, road and bridge maintenance, 50 acres of firelane maintenance, 20 acres of chopping, 42 acres
of hydro-ax restoration and maintenance, 25 acres of road mowing, eight days of prescribed burning; and contractual
services for 18 acres of recreational mowing and 435 hours of security.
Costs for these activities are reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
011 Alafia River Basin 46,323 16,600
021 Manasota Basin 92,070 95,995
Project Funds Not Budgeted by the
District
Hillsborough County 0 0
Funding Funding
2010 FY 2011 FY
Status As Of: January 28, 2010
Land use staff working with Hillsborough County to amend management agreement which wills streamline
reimbursement payments.
021 - Manasota Basin 17
S041
Myakkahatchee Creek
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager MILLER, WILL
SOWDERS, GINA, LOVE, KEVIN, GREEN, STEPHANIETask Manager(s)
Status Ongoing
DescriptionThe Myakkahatchee Creek project area consists of oak/cabbage palm hammock dominated banks along the southern
portions of the creek, isolated marshes and improved pastures within the upland portions and mixed natural lands
scattered throughout. The main surface water feature, Myakkahatchee Creek, is a 21.5-mile long tributary creek of the
Myakka River. Lands are managed by Sarasota County.
BenefitsSince the lands within the project were purchased in less-than-fee simple, no land management activities are required.
Costs
The FY2010 budget consists of annual conservation easement monitoring, contract monitoring and 50%
reimbursement of land management costs to Sarasota County for their management of jointly owned lands within the
project.
Costs for this activity are reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
010 General Fund (Districtwide) 0 0
021 Manasota Basin 40,016 37,266
Funding Funding
2010 FY 2011 FY
Status As Of: February 25, 2010
No significant activities this period.
021 - Manasota Basin 18
S042
Tampa Bay Estuarine Ecosystem
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Pinellas-Anclote River, Manasota
Florida State Parks, Hillsborough CountyCooperator(s)
Project Manager MILLER, WILL
HAGBERG, JEFFREY, SOWDERS, GINA, KRUK, COLLEEN, LOVE, KEVIN, VANGELDER, WILLTask Manager(s)
Status Ongoing
DescriptionThe Tampa Bay Estuarine Ecosystem project furthers the Tampa Bay Surface Water Improvement and Management
(SWIM) plan. Approximately half the project consists of mangroves and salt marsh which dominate the northern
project area along Bishop Harbor and the western area associated with the tidal bays of Moses Hole, Clambar Bay
and Williams Bayou. The natural upland and wetland habitats within the project area provide natural water quality
treatment of overland flows before reaching the receiving waters of Tampa Bay. A majority of lands within the Tampa
Bay Estuarine Ecosystem project were jointly purchased with the State or local governments. Under an agreement
with the State, the Department of Environmental Protection's Division Recreation and Parks is the lead land manager
for the Terra Ceia tract. Hillsborough County manages the Bullfrog Creek and Port Redwing tracts, and Pinellas
County manages the Clam Bayou tract.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2010 budget consists of salaries and operational costs for public use management, resource monitoring,
resource protection, road and bridge maintenance, recreation equipment, nine acres of road mowing, two days of
prescribed burning; and contractual services for 271 acres of recreational mowing. Costs for these activities are
reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
011 Alafia River Basin 20,992 16,341
016 Pinellas-Anclote River Basin 0 0
021 Manasota Basin 18,960 18,195
Project Funds Not Budgeted by the
District
Hillsborough County 0 0
Funding Funding
2010 FY 2011 FY
Status As Of: February 17, 2010
No significant activities this period.
021 - Manasota Basin 19
S099
Save Our Rivers Administration
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) General Fund (District), Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers,
Pinellas-Anclote River, Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager SUTTON, ERIC
NELSON, BRIAN, HAGBERG, JEFFREY, MILLER, WILL, WALSH, TOM, LOVE, KEVINTask Manager(s)
Status Ongoing
DescriptionThe Save Our Rivers Administration project contains monies for those items not attributable to one unique project
during the budget cycle. Examples are studies affecting all conservation lands, preparation of resource evaluation
reports, heavy equipment used solely on conservation lands, overtime, staff time, vehicle charges and equipment
rental.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
In addition to salaries and central garage charges, the FY2009 budget includes funds for tree removal in cases where
trees fall from District property onto adjoining owners' property in the Coastal, Hillsborough and Pinellas-Anclote
Basins; and aerial flights to view exotic species in the Hillsborough, Manasota and Peace Basins. The FY2010 budget
includes salaries, central garage charges, tree removal in cases where trees fall from District property onto adjoining
owners' property in the Coastal and Hillsborough Basins, and aerial flights to view exotics speciec in the General Fund.
Costs for these activities are 100 percent reimbursed through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
010 General Fund (Districtwide) 1,302,606 937,997
011 Alafia River Basin 4,483 7,549
013 Hillsborough River Basin 9,483 12,549
015 Coastal Rivers Basin 9,483 15,641
016 Pinellas-Anclote River Basin 4,275 7,932
019 Withlacoochee River Basin 9,483 7,932
020 Peace River Basin 7,683 7,549
021 Manasota Basin 7,683 7,549
Funding Funding
2010 FY 2011 FY
Status As Of: March 12, 2009
With the exception of the District fund, the Save Our Rivers (SOR) Administration project is used primarily to budget
monies for SOR, Preservation 2000 and Florida Forever (reimbursable) projects. Generally, funds are not charged to this
project, but transferred to other reimbursable projects within the Basin. An example is overtime. Staff knows at budget
time that overtime will be required within the basins for work on SOR projects, but does not know for which projects, so
monies will be budgeted in S099. When overtime is used later in the year, the monies will show as being spent for the
actual project the staff member worked on (i.e., S009- Starkey, S016 - Weekiwachee Preserve, etc.). In the District funds
021 - Manasota Basin 20
S099
Save Our Rivers Administration
monies are primarily used for SOR program administration, purchase of equipment and contractual services.
021 - Manasota Basin 21
SA05
Deer Prairie Creek
Project Type SOR
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
NoneCooperator(s)
Project Manager LOVE, KEVIN
NELSON, BRIAN, HAGBERG, JEFFREY, SOWDERS, GINA, MILLER, WILL, GREEN,
STEPHANIE, FOX, AUGUST
Task Manager(s)
Status Ongoing
DescriptionAll lands within the project are jointly owned by the District and Sarasota County. Lands within the project area are
characterized by a variety of natural lands and lands altered by development including mesic pine flatwoods, oak
hammocks, shell mounds, prairie hammock and improved pasture. The project area includes portions of the Myakka
River and its floodplain forests. Lands within Deer Prairie Creek are jointly managed by the District and Sarasota
County. The District is lead manager for prescribed burning, natural systems restoration, exotics control and timber
management. The County is lead manager for land use and management plan development, public recreation,
education and land use requests, wildfire response, resource monitoring, cattle grazing and security.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
The FY2010 budget consists of salaries and operational costs for resource monitoring, resource protection, road and
bridge maintenance, exotic plant control, 304 acres of firelane maintenance, 200 acres of chopping, 100 acres of
hydro-ax restoration and maintenance, 172 acres of road mowing, and 15 days of prescribed burning.
Costs for these activities are reimbursable through the state's Water Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
021 Manasota Basin 159,940 132,468
Funding Funding
2010 FY 2011 FY
Status As Of: February 17, 2010
Annual cooperators meeting held on December 8, 2009, Sarasota County management is consistent with the
interagency agreement. Aquatic Plant Management Section staff treated 47 acres infested with Brazilian pepper and 12
acres infested with Old World climbing fern.
021 - Manasota Basin 22
SA19
Lake Manatee Lower Watershed Upland Restoration #1
Project Type SOR
AORs Strategic InitiativesNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager VANGELDER, WILL
Task Manager(s)
Status Ongoing
DescriptionIn 1991 the Governing Board authorized the acquisition of lands within the Lake Manatee Lower Watershed project in
Manatee County. The Lake Manatee Lower Watershed extends over a large area that includes narrow floodplain
forests and native pinelands surrounded by vast areas of rangeland, improved pastures, croplands, and citrus groves.
Lands purchased within this project protect an existing regional water resource, protect floodplains, and restore
adjoining wetlands in the headwaters. To date 7,932 acres have been acquired in fee simple within the project, with an
additional 11,046 approved for future fee simple acquisition. In 2002, 149 wetland acres were restored via the Florida
Department of Transportation (FDOT) mitigation program. In FY2005 through FY2010, approximately 324 acres of
former farm field are proposed for restoration back to upland vegetation communities, including scrub, scrubby
flatwoods and dry prairie. The site is the largest contiguous altered site on the tract and ranked as a high priority for
restoration. In FY2005, site work began in preparation for re-vegetation of a 25-acre portion of the site to serve as a
pilot project to test planting methods. A grower was contracted to propagate plant materials for the project, including
palmettos, and three species of scrub oaks, totaling 18,500 plants. The re-vegetation of this site will expand a five-acre
remnant scrub patch that currently supports a family of scrub-jays. This pilot phase of the project was completed in
July 2006. Subsequent monitoring has indicated that the pilot results have exceeded target levels.
BenefitsPursuant to Section 373.1391(1)(a), Florida Statutes, lands within the project are managed and maintained in such a
way as to ensure a balance between public access, general public recreational purposes, and restoration and
protection of their natural state and condition.
Costs
Funds were included in the FY2008 budget to conduct phase 2 of the project, which included plant material and
planting labor to re-vegetate approximately 46 acres of the site. Plant species, stocking rates and planting methods will
be similar to those proving successful on the pilot phase. Future restoration efforts on the remainder of the site will be
conducted in annual stages over an approximately four-year period.Funds in the FY2009 and FY2010 budgets are for
salaires and central garage charges. Costs for these activities are 100 percent reimbursed through the Water
Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
021 Manasota Basin 11,869 18,385
Funding Funding
2010 FY 2011 FY
Critical Project Milestones ActualProjected Amended
Phase 1RFB 9/1/04 9/1/04
Install Plants 7/31/06 7/31/06
Award Contract 12/1/07 12/1/04
Phase 2RFB 10/1/07 11/1/07
Award Contract 12/1/07 9/1/07
Install Plants 7/31/09
021 - Manasota Basin 23
SA19
Lake Manatee Lower Watershed Upland Restoration #1
Phase 3RFB 10/1/08 10/15/08
Award Contract 12/1/08 4/21/08
Install Plants 7/31/10
Phase 4RFB 10/1/09
Award Contract 12/1/09
Install Plants 7/31/11
Status As Of: February 28, 2010
No significant activities this period.
021 - Manasota Basin 24
SA31
Myakka State Forest Hydrologic Rstr
Project Type SOR
AORs Strategic InitiativesNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager RHINESMITH, PHILIP
Task Manager(s)
Status Ongoing
DescriptionThe District's Governing Board approved the Hydrologic and Wetlands Restoration of District-owned Lands initiative at
their January 2004 meeting. The initiative focuses on 2 goals which are: A) recovering the functions of water storage
and conveyance in impacted wetlands and streams; and B) recapturing the benefits of water quality and wildlife habitat
formerly provided by the impacted system in its undisturbed state. To accomplish this goal, the District retained the
engineering and environmental services of PBS&J consultants to complete a feasibility study and alternatives analysis.
The Myakka State Forest Hydrologic Restoration project is located in the Myakka State Forest in Sarasota County.
The property is currently managed as a passive recreational facility by the Department of Agriculture and Consumer
Services-Division of Forestry. The surface water impacts are to two separate creek systems both of which contribute
surface water flows to Lemon Bay. These include Ainger Creek and Oyster Creek. Based on the results of the post
restoration surface water modeling accomplished during the first phase of the project, a total of 557 acres of wetlands
will be restored.
BenefitsThe project will restore the functions of water storage and conveyance of Oyster Creek, Ainger Creek and numerous
isolated herbaceous wetlands, and recapture the benefits of water quality and wildlife habitat formerly provided by the
impacted system in its undisturbed state.
Costs
The design and permitting for the project will be completed in FY2010 at acost of $75,082 and construction in
FY2010-11 at an estimated cost of $295,925. The funding table below includes District staff time, travel and central
garage charges. These activities are reimbursed at 100 percent from the state's Water Management Lands Trust
Fund.
District Budgeted - Outside Revenue
(SOR)
021 Manasota Basin 9,279 0
Funding Funding
2010 FY 2011 FY
Critical Project Milestones ActualProjected Amended
1. Project DesignFeasibility and Analysis Report Complete 8/31/07 1/1/08
Design Complete 10/31/08 3/15/10
1A. Permit Exemption FDEPPhase 1 Removal of Salinity Barrier 8/13/09 11/25/09
1A. Permit Exemption FDEPComplete Remoal of Salinity Barrier 10/31/09 12/4/09
2. PermittingPermitting Commence 12/31/08 3/15/10
Permitting Complete 1/31/09 4/15/10
3. ConstructionConstruction Commence 2/28/09 5/15/10
021 - Manasota Basin 25
SA31
Myakka State Forest Hydrologic Rstr
Construction Complete 5/31/09 8/15/10
Status As Of: February 15, 2010
The consultant completed the final restoration plan which identified three distinct areas where minor modifications to the
ditch network will result in rehydration of degraded wetlands. These include: removal of a tidal salinity barrier to restore
natural tidal fluctuation to the lower portions of Ainger Creek; installation of a berm on the south side of the forest to
restore normal flows through Oyster Creek; and installation of a series of ditch plugs in the ditches connecting wetlands
in the south-eastern portions of the forest. District staff presented the restoration plan to the "Myakka State Forest
Liaison Committee" at their 04/22/2008 meeting with a favorable response. ACTION TO DATE: On-time. The District
selected King Engineering to finish the surface water modeling for the project and complete the design, permitting and
construction services. The model verification will require more time to complete than originally budgeted. There are
however certain elements of the project that can be accomplished by permit exemption. Part of the construction plan is to
remove a salinity barrier that interrupts flows of Ainger Creek. The District applied for and received de minimis
exemptions from the Florida Department of Environmental Protection (FDEP) for minor activities such as this. The
exemption allowed District crews to begin construction and accomplish a portion of the project. The District's contractor,
American Construction, completed the removal of the salinity barrier on December 4, 2009
021 - Manasota Basin 26
SB05
Myakka River Deer Prairie Creek Preserve Wetland Restoration
Project Type SOR
AORs Strategic InitiativesNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager RHINESMITH, PHILIP
GREEN, STEPHANIETask Manager(s)
Status Proposed
DescriptionThe Myakka River Deer Prairie Creek Tract was acquired by the District from 2001-05 in several parcels. The Myakka
River borders the project to the west and is listed as an Outstanding Florida Water (OFW). The Florida Fish and
Wildlife Conservation Commission listed portions of the site as having Strategic Habitat for wading birds. FWC also list
the site as having priority wetlands Habitat for the American alligator, black bear and bald eagle. Additionally, FWC has
identified an eagle next within 1-mile of the project. The wetland restoration project includes the hydrologic restoration
of the Tracts altered wetland systems. Past agricultural practices of previous landowners have altered the site's
hydrology increasing the discharge from the wetlands. The restoration will provide increased hydroperiods in the
isolated wetlands and increase the habitat value of the wetlands. The FY2011 funds will be for design and permitting.
Construction and construction management will be budgeted for in FY2012-13.
BenefitsThe restoration will provide enhancement to the site's wetlands and increased habitat value for fish and wildlife.
Costs
The FY2011 funding will be for the feasibility, design, and permitting costs for the project. Costs for construction will be
budgeted in FY2012-13.
District Budgeted - Outside Revenue
(SOR)
021 Manasota Basin 227,099 0
Funding Funding
2010 FY 2011 FY
Critical Project Milestones ActualProjected Amended
1. Project DevelopmentRequest for Proposal Issued 10/29/10
Project Awarded 12/15/10
2. Design and PermittingBegin Design 2/15/11
End Design 6/16/11
Permit Application FDEP/USACE 7/20/11
Status As Of:
021 - Manasota Basin 27
SB19
Edward W. Chance Reserve Hydrologic Rstr
Project Type SOR
AORs Strategic InitiativesNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager RHINESMITH, PHILIP
Task Manager(s)
Status Ongoing
DescriptionThe District's Governing Board approved the Hydrologic and Wetlands Restoration of District-Owned Lands initiative at
their January 2004 meeting. The project focuses on 2 goals which are: A) recovering the functions of water storage
and conveyance in impacted wetlands and streams; and B) recapturing the benefits of water quality and wildlife habitat
formerly provided by the impacted system in its undisturbed state. To accomplish this goal, the District will retain the
engineering and environmental services of PBS&J to complete a feasibility and alternatives analysis for the site. The
restoration site is located in the District's Edward W. Chance Reserve (formerly known as the Rutland Ranch). The
property is currently managed by the District for passive recreation and natural resource protection. There are many
isolated wetlands throughout the project area. The impacts to wetland systems are a result of linear ditches
constructed to facilitate drainage off-site thereby improving lands for row crops.
BenefitsThe project will recover the functions of water storage and conveyance of Gilley Creek and numerous isolated
herbaceous wetlands and recapture the benefits of water quality and wildlife habitat formerly provided by the impacted
system in its undisturbed state.
Costs
The design and permitting for the project will be completed in FY2010 at a cost of $75,439 and construction in
FY2010-11 for an additional $236,475. The total project cost is $311,914. The funding table below includes District
staff time, travel and central garage charges. These activities are reimbursed at 100 percent from the state's Water
Management Lands Trust Fund.
District Budgeted - Outside Revenue
(SOR)
021 Manasota Basin 10,199 0
Funding Funding
2010 FY 2011 FY
Critical Project Milestones ActualProjected Amended
1. DesignFesibility and Analysis Report Complete 8/31/06 2/21/08
Design Complete 10/31/09 3/15/10
1A Construction Under ExemptionAg Ditch Ponds and Fill Begin 9/15/09
Ag Ditch Ponds and Fill Complete 11/15/09
2. PermittingPermitting Commence 12/31/09 4/15/10
Permitting Complete 1/30/10 5/15/10
3. ConstructionConstruction Commence 2/28/10 6/15/10
Construction Complete 6/1/10 9/15/10
Status As Of: December 07, 2009
The consultant completed the final restoration plan which identified three distinct areas where minor modifications to the
021 - Manasota Basin 28
SB19
Edward W. Chance Reserve Hydrologic Rstr
ditch network will result in rehydration of degraded wetlands. ACTION TO DATE: On-time. King Engineering, the
District's environmental consultant on the project is working on the model verification of the site hydrology. This is proving
to be more time consuming than originally anticipated. There are however certain elements of the project that can be
accomplished by permit exemption. Part of the construction plan is to fill several upland agricultural ditches that are no
longer contributing surface water to Gilley Creek. Instead of incorporating this into the ERP, the District was able to apply
for and receive a de minimis exemptions from the Florida Department of Environmental Protection (FDEP) for minor
activities which included the filling of 2.4 miles of agricultural ditches. The District received a Nationwide 27 Permit from
the Army Corps of Engineers. One of the conditions of the NW 27 was for the District to create two mitigation ponds to
compensate for the loss of foraging habitat that the ag ditches provided for wood storks, a federally listed species.
District crews completed the construction in November 2009. The two mitigation ponds were planted in February 2010.
021 - Manasota Basin 29
SB31
Myakka River State Park-Myakka Prairie Tract Wetland Restoration
Project Type SOR
AORs Strategic InitiativesNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Cooperator(s)
Project Manager ZAJAC, CHRIS
RHINESMITH, PHILIPTask Manager(s)
Status Proposed
DescriptionThe Myakka River State Park-Myakka Prairie Tract is located just south of the Myakka River State Park. The
restoration includes the filling of ditches which interconnect the site's isolated wetlands. The ditches alter the
hydroperiods in individual wetlands thereby reducing their hydroperiod. The project is supported by the Florida
Department of Environmental Protection who are responsible for the management of the State Park.
BenefitsThe restoration project will provide enhancement to the site's wetlands and increase habitat value for fish and wildlife.
Costs
The total project cost is $125,000 and will be used to hire a consultant for design and permitting. Funds for
construction will be budgeted in FY2012-13.
Additional Information
The Myakka Prairie Tract is approximately 8,275 acres and was purchased by the District in 1994 using Preservation
2000 funds. The Florida Fish and Wildlife Conservation Commission (FWC) has listed the property as having priority
wetlands habitat for the Florida Sandhill Crane, Black Bear and American Alligator. The FWC has also identified
strategic habitat for wading birds and two bird rookeries on site.
District Budgeted - Outside Revenue
(SOR)
021 Manasota Basin 129,331 0
Funding Funding
2010 FY 2011 FY
Critical Project Milestones ActualProjected Amended
1. Project DevelopmentRequest for Proposal Issued 10/20/10
Consultant Selection 12/15/10
2. Design and PermittingDesign Begin 3/16/11
Design Completed 7/20/11
Permit Applications FDEP/USACE 9/14/11
Status As Of:
021 - Manasota Basin 30
W020
SWIM Plan Implementation - Tampa Bay
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Pinellas-Anclote River, Manasota
Tampa Bay Estuary ProgramCooperator(s)
Project Manager KAUFMAN, KRIS
Task Manager(s)
Status Ongoing
DescriptionThis project provides for the implementation, periodic review, and update of the Tampa Bay Surface Water
Improvement and Management (SWIM) Plan. The plan was originally prepared in 1988 and updated in 1992 and
1999. Development and update of the SWIM plan is completed in coordination with involved stakeholders and
governmental agencies and includes: an assessment of implementation progress, development of new projects
(rationale and justification), and determination of pertinent Pollutant Load Reduction Goals (PLRG). Additionally, this
project provides for the implementation of projects identified in the Tampa Bay SWIM Plan; including water quality
assessments necessary for SWIM plan implementation, periodic Tampa Bay Estuary Program (TBEP) Technical
Advisory Committee meetings, contract development, invoicing, project presentations, site visits and other relevant
tasks.
BenefitsA SWIM Plan must be developed and approved before state SWIM funds can be spent on restoration, protection or
management activities.
Costs
The FY2010 ongoing costs for the Tampa Bay SWIM Plan Implementation are funded 25 percent from the
Pinellas-Anclote River, 25 percent from the Manasota, 25 percent from the Hillsborough River, and 25 percent from
the Alafia River Basin Boards. District funds shown in the table include staff salaries.
Additional Information
In 1987, the Florida Legislature established the Surface Water Improvement and Management (SWIM) Act having
recognized that water quality and habitat in surface waters throughout the state have degraded or were in danger of
being degraded. The Act requires the five water management districts to maintain a priority list of water bodies of
regional or statewide significance within their boundaries, and develop plans and programs for the improvement of
those water bodies. Tampa Bay was identified by the Legislature in the SWIM Act as the highest priority on the
District's SWIM priority list. To date, ten SWIM water bodies in the District have had plans developed and approved by
the state. Several plans have been updated one or more times as required by the Act.
021 - Manasota Basin 31
W020
SWIM Plan Implementation - Tampa Bay
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 119,733 0 74,687 21,518 23,528
013 Hillsborough River Basin 121,002 0 74,686 22,350 23,966
014 Northwest Hillsborough Basin 74,686 0 74,686 0 0
016 Pinellas-Anclote River Basin 121,174 0 76,128 21,518 23,528
021 Manasota Basin 120,220 0 75,504 21,518 23,198
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 218,160 0 218,160 0 0
State Trust Funds (SWIM) - Prior 2006 236,306 0 236,306 0 0
WMLTF (SWIM) - Prior Year Funds 44,220 0 0 0 44,220
$1,055,501 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesTampa Bay SWIM Plan Update 2/8/99 2/8/99
Next Update of SWIM Plan 12/31/06 12/31/07
2. Critical Project MilestonesUSF Stable Isotope Analysis Purchase Order Opened 8/25/05 8/25/05
Coordination Meeting for Isotopic Investigation of OTB Pollutants 4/15/07 4/15/07
Expiration of Purchase Order 12/31/07 12/31/07
3. Critical Project MilestonesDesign and implementation of Tampa Bay Shallow Water Sampling 1/31/08 2/29/08 2/25/08
3. Critical Project MilestonesCompletion of first year of Tampa Bay Shallow Water Sampling 12/31/08 12/31/08
Completion of second year of Tampa Bay Shallow Water Sampling 12/31/09 12/31/09
Status As Of: March 02, 2010
Coordination and implementation of the Tampa Bay Shallow Water Quality Evaluation is complete. The final monthly
sampling event was held December 2009. The data is currently being reivewed for QA/QC purposes and will be made
available for analysis. Evaluations of TBEP's existing monitoring programs and discussions of other cooperative
implementation opportunities will continue to be reviewed through participation in the TAC and subcommittee meetings.
021 - Manasota Basin 32
W027
Tampa Bay Estuary Program
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Pinellas-Anclote River, Manasota
Tampa Bay Estuary ProgramCooperator(s)
Project Manager GARCIA, LIZANNE
SEACHRIST, JENNETTE, CRAW, VERONICATask Manager(s)
Status Ongoing
DescriptionThis proposed project provides funding for the Tampa Bay Estuary Program (TBEP) as outlined in the Interlocal
Agreement which established the TBEP as a independent special district in 1998. The District participates in three
main areas. First the District's SWIM program, funded by the basin boards and State, carries out the projects that will
address water quality and habitat restoration within the bay. Second, the basin boards and State have contributed
funding to the TBEP since 1990 to carry out the administration and implement projects identified in the TBEP
Comprehensive Conservation and Management Plan. And finally, the District provides staff to sit on the technical,
management and policy (Governing Board Member) boards and the Nitrogen Management Consortium of the
program. The District's annual budget includes funding support to the TBEP and District staff salaries, travel and
central garage to administer the project, which includes attending board meetings and other workshops and invoicing.
BenefitsThis project's support of the Tampa Bay Estuary Program creates an opportunity for a cohesive effort between the
District, TBEP and other state and local agencies to implement resource management decisions and restoration
activities. Additionally, this project provides for leveraging funding between the partners.
Costs
The District has provided funding to the TBEP on an annual basis since 1990. The District's annual funding
commitment to the TBEP is $138,335. Prior to FY2011, the District share was split between State SWIM funds (50%)
and the Basin Boards (50%). In FY2011, the District's proposed funding will be funded 100% by the Basin Boards. The
FY2011 proposed funding is split 25 percent ($34583.75) from the Pinellas-Anclote River, 25 percent ($34583.75)
from the Manasota, 25 percent ($34583.75) from the Hillsborough River, and 25 percent ($34583.75) from the Alafia
River Basin Boards. District funds are used to implement projects outlined in the Annual Workplan. District funds
shown in the table include staff salaries.
Additional Information
TBEP Background: In 1987, the Florida Legislature established the Surface Water Improvement and Management
Program (SWIM) Act having recognized that water quality and habitat in surface waters through out the state have
degraded or are in danger of being degraded. The Act requires the District maintain a priority list of waterbodies of
regional or statewide significance within their boundaries. The Act listed Tampa Bay as the District's number one
priority. Subsequently, in 1990, the United States Environmental Protection Agency identified Tampa Bay as an
estuary of Federal Significance and included it in the National Estuary Program. As a result of this designation, the
Tampa Bay National Estuary Program (TBNEP) was established in 1991 (with the District as a founding partner) to
assist the region in developing a comprehensive plan for the restoration and protection of Tampa Bay. The TBNEP
developed the first Comprehensive Conservation and Management Plan (CCMP) for Tampa Bay in 1996 which
included measurable goals for restoring seagrasses and related targets for reducing nitrogen discharges to the bay.
The parties unanimously adopted a "hold the line" target on nitrogen discharges that capped the load at a level that
would ensure adequate water clarity and light to sustain seagrass recovery. In August 1996, the NEP's governmental
partners joined with key industries in the Tampa Bay region to create a unique public/private partnership known as the
Tampa Bay Nitrogen Management Consortium (Consortium) for the express purpose of developing a Consortium
Action Plan to meet the "hold the line" target. The original Consortium Action Plan consisted of more than 100 projects
which collectively reduced or precluded nitrogen discharges to the bay by an estimated 134 tons/year between 1995
and 1999. In 1998, local government and agency partners in the TBNEP executed the Tampa Bay Estuary Program
Interlocal Agreement reinforcing their commitment to the NEP and its purpose (at which time the NEP became the
Tampa Bay Estuary Program or TBEP). Parties to the Interlocal Agreement include the U.S. Environmental Protection
Agency (EPA), Florida Department of Environmental Protection (FDEP), the District, Hillsborough, Manatee and
Pinellas counties and the cites of St. Petersburg, Tampa and Clearwater. The Interlocal Agreement requires that
parties provide annual funding to the TBEP, develop an agency action plan and to participate as a member of the
Consortium. Later in 1998, the public and private entities in the Consortium executed the "Resolution of the Nitrogen
021 - Manasota Basin 33
W027
Tampa Bay Estuary Program
Management Consortium Adopting the 1995-1999 Nitrogen Management Action Plan and Committing to its
Implementation" (1998 Resolution). This resolution was presented to the five Basin Boards that represented Tampa
Bay (Alafia River, Northwest Hillsborough, Hillsborough River, Pinellas-Anclote River, and Manasota) and the
Governing Board at their meetings in June 1998 and the Governing Board approved this resolution and the District's
Action Plan June 23, 1998. Tampa Bay Total Maximum Daily Load (TMDL) Status: In 1998, pursuant to the federal
Clean Water Act, FDEP submitted a TMDL for nitrogen for Tampa Bay to the EPA. The TMDL is based on the annual
average total nitrogen loading to major bay segments estimated by the TBEP. These loadings are seen as the
maximum loadings that can occur and still meet the seagrass restoration goals. EPA approved the submitted TMDL
June 18, 1998. In 1999, the Florida Legislature passed the Florida Watershed Restoration Act which established the
state's TMDL process. This Act allows for stakeholders to show that existing or proposed pollution control programs
will provide "Reasonable Assurance" (RA) that impaired water bodies will meet their designated uses. If FDEP accepts
the documentation for RA, then the water body will not be included on the Verified List for Impaired Waters and will not
require the development ofa TMDL. Subsequently, the TBEP and the Consortium developed and submitted a RA
document to the FDEP in 2002, based on the Consortium Action Plan. The document provided the FDEP with a
complete description of the Tampa Bay Nitrogen Management Strategy. The TBEP also provided FDEP with a copy of
the 1998 Resolution that committed both private and public partners to the projects identified in their action plans. The
FDEP accepted the 2002 RA document submitted by the TBEP and the Consortium as adequate to address nutrient
impairment in Tampa Bay segments, and removed Tampa Bay segments from the State's 303(d) list for 2002-2007.
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 129,769 0 57,684 35,588 36,497
013 Hillsborough River Basin 129,769 0 57,684 35,588 36,497
014 Northwest Hillsborough Basin 57,684 0 57,684 0 0
016 Pinellas-Anclote River Basin 129,769 0 57,684 35,588 36,497
021 Manasota Basin 129,768 0 57,683 35,588 36,497
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 288,408 0 288,408 0 0
WMLTF (SWIM) - Prior Year Funds 7,648 0 0 0 7,648
Project Funds Not Budgeted by the
District
Local Government Partners 1,393,325 0 1,106,660 0 286,665
US EPA 2,602,983 0 1,994,733 0 608,250
$4,869,123 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2010 Annual Workplan Critical Project MilestonesFY2010 Draft Agreement to Management Services 10/1/09 10/27/09
FY2010 Agreement fully executed 11/12/09 1/14/10
FY2010 First 1/2 payment 12/31/09 2/1/10 2/1/10
FY2010 Second 1/2 payment 3/1/10
FY2010 End of Contract 9/30/10
Status As Of: February 15, 2010
FY2010 Annual Work Plan: The work plan was fully executed on January 14, 2010 and the first installment has been
021 - Manasota Basin 34
W027
Tampa Bay Estuary Program
processed. TBEP Nitrogen Management Consortium (Consortium): In December 2007, 40+ public and private
participants in the Tampa Bay Nitrogen Management Consortium proactively committed to develop an equitable process
to propose TN load allocations to all sources consistent with the TMDL. The RA Document was completed and the FDEP
approved the technical changes to the document. TN allocations have been assigned to all 189 point and nonpoint
sources within the Tampa Bay watershed. The Consortium understands that the proposed allocations will be
incorporated into NPDES and MS4 permits. Compliance will be calculated annually for point sources and every 5 yrs as
part of the RA Plan updates for non-point sources. The NMC has received declarations of commitment from all members
except Cities of Palmetto and Gulfport (pending), Cities of Tampa and Bradenton (unknown) and City of Lakeland (not
forwarded for signature). At this time it does not appear that the NMC is requiring the District, DEP or Florida Department
of Agriculture and Consumer Services (DACS) to submit a declaration letter because we don't have allocated loads in the
document. However, the District will be asked to contribute contribute $6,000 for the next RA update, which could be
included in the FY2011 budget. This is consistent with our contribution of $5,000 several years ago to begin the RA
Update process. Numeric Nutrient Criteria: The TBEP and Consortium have requested that USEPA accept and
recognize the Consortium's TN loads as Interim Estuarine Numeric Nutrient Loading Targets in the January 2010 draft
documentation for freshwaters in the Tampa Bay watershed. The estuarine criteria should be out July 2010 (well in
advance of the January 2011 official proposal). For Tampa Bay, the downstream protective load identified by the
SPARROW model is 1,421 tons/yr TN. But the RA Document identified a target load of 3,714 tons/yr TN. The model is
predicting levels more than two times as restrictive as the RA is proposing. The NMC disagrees with the assumption by
EPA that ALL estuaries are impaired and is arguing that the model is overly protective. The NMC recommends a 5 year
assessment period instead of the proposed 3 years. The NMC discussed also submitting formal comments to EPA on
the portions of the rule they agree with. The NMC will be developing formal comments on the rule to be submitted to EPA
during the formal public comment period. That letter will be circulated to members. The NMC would like to track which
members are planning on attending the EPA public workshops and if they are planning on speaking. The next meeting of
the NMC is February 26, 2010.
021 - Manasota Basin 35
W028
Bay Soundings
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Pinellas-Anclote River, Manasota
Tampa Bay Regional Planning CouncilCooperator(s)
Project Manager HARROUN, AMY
Task Manager(s)
Status Proposed
DescriptionThis Surface Water Improvement and Management (SWIM) project consists of a full-color, 16-page, quarterly
environmental journal that provides important information on issues affecting Tampa Bay, its watershed and the
natural resources of the Tampa Bay region. The Bay Soundings publication supports the Tampa Bay SWIM plan and
is consistent with the Tampa Bay Estuary Program goals. Through the education efforts of Bay Soundings, residents in
the Tampa Bay area learn about the restoration and preservation of SWIM water bodies. This free publication is
distributed throughout Pasco, Pinellas, Hillsborough and Manatee counties to government and non-government
agencies, local attractions, private businesses, environmental clubs, schools, libraries, elected officials and sponsors.
District staff sits on the editorial board and provides story ideas featuring District projects that meet the editorial focus
of the publication. Bay Soundings' web site is www.tbsoundings.com.
BenefitsBay Soundings enhances the District's educational outreach efforts on Tampa Bay by helping to increase the readers'
knowledge of local environmental issues. Each edition of this publication features one or more topics pertaining to
District projects or areas of responsibility. SWIM water bodies are often featured in the publication's articles.
Costs
The total cost for the FY2011 project is $45,000 with the District requested to contribute $22,500 (Alafia River $2,250;
Hillsborough River $7,875; Pinellas-Anclote River $7,425; Manasota $4,950). The publication's circulation has
increased from 25,000 to 30,000 copies distributed each issue. In addition the web site is reporting 35,000 hits per
month. The cost benefit for all four copies of an annual subscription is $.75. Adding web site hits brings the cost
to $.04 per impression.
Additional Information
The total cost of the FY2010 project is $45,000 with the District contributing $22,500 (Alafia River $2,250; Hillsborough
River $7,875; Pinellas-Anclote River $7,425; Manasota $4,950). No state SWIM funds were available to be applied to
this project. The publication's circulation of 25,000 copies per printing (four times a year), brings the cost benefit ratio
to $.90 per resident.
021 - Manasota Basin 36
W028
Bay Soundings
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 8,165 0 3,665 2,250 2,250
013 Hillsborough River Basin 25,828 0 10,078 7,875 7,875
014 Northwest Hillsborough Basin 5,040 0 5,040 0 0
016 Pinellas-Anclote River Basin 31,801 0 16,951 7,425 7,425
021 Manasota Basin 19,978 0 10,078 4,950 4,950
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 45,806 0 45,806 0 0
Project Funds Not Budgeted by the
District
Tampa Bay Regional Planning Council 22,500 0 0 0 22,500
$159,118 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2008Winter issue 2/20/08 2/20/08
Spring issue 5/20/08 5/20/08
Summer issue 8/20/08 7/29/08
Fall issue 11/20/08 10/17/08
FY2009PO opened 10/1/08 10/20/08
Winter issue 2/20/09 2/5/09
Spring issue 5/20/09 5/18/09
Summer issue 8/20/09 8/20/09
Fall issue 11/20/09 11/20/09
FY2010PO opened 10/1/09 10/1/09
Winter issue 2/20/10 2/20/10
Spring issue 5/20/10
Summer issue 8/20/10
Fall issue 11/20/10
Status As Of: March 09, 2010
ACTION TO DATE: On time. The District was featured in an article called, "What's up with water?" The article focused
on the current conditions of the water resources in the Tampa Bay region and discussed the status of the C.W. "Bill"
Young Reservoir and answered frequently asked questions about the drought. The article also included information on
the District's Skip A Week campaign. The "Get Outside" campaign was also featured in an article and promoted the
District's Recreation Guide.
021 - Manasota Basin 37
W030
Tampa Bay Watch Field Trip Program
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Pinellas-Anclote River, Manasota
Tampa Bay WatchCooperator(s)
Project Manager HULL, MARY MARGARET
Task Manager(s)
Status Proposed
DescriptionThis Surface Water Improvement and Management (SWIM) project proposes to educate elementary, middle and high
school students about estuarine science and empowers them to act as stewards of the Tampa Bay estuary by
combining classroom curriculum with 300 hands-on field experiences in and around Tampa Bay Watch's Marine
Science Center. Proposed programming includes students and teachers in Hillsborough and Manatee counties as well
as serving schools throughout Pinellas County. In FY2011, the program continues to include the educational field
experiences, classroom presentations, teacher training, coastal plantings, oyster reef enhancement efforts and coastal
cleanups, while adding a pilot comprehensive program evaluation of student learning with no cost increases. The
proposed program evaluation will assess the efficacy of understanding and retention of estuarine science and
environmental literacy as well as awareness and behavioral changes due to exposure and progressive experiences
linked with the programming. Overall efforts will provide restoration of approximately eight acres of coastal and
near-shore habitat, build and install 300 new oyster domes and construct approximately 600 linear feet of new oyster
shell bars. The program's effectiveness is measured with student pre/posttests, journal work and teacher surveys.
BenefitsThis project proposes to implement an environmental education initiative in Tampa Bay. Tampa Bay was identified as
the highest priority on the District's SWIM priority list in 1988. The program's goals are to educate students and
teachers about the importance of estuarine habitats and restoration efforts and to empower them to become lifelong
stewards of Tampa Bay. The cooperator continues to look for ways to innovate the program and implement
improvements. A three year comprehensive pilot study is proposed with three to five participating middle schools to
track students' progression and learning from sixth through eighth grade. With expansion of the programs (in FY2009)
into Hillsborough and Manatee counties and the addition of Bay Grasses in Classes, this project features a more
comprehensive environmental education restoration initiative, reaching a proposed 12,600 students and adults during
FY2011. A 32% gain in student knowledge has been documented through pre/posttest analyses.
Costs
The total proposed costs of the FY2011 program is $307,170, with the District requested to contribute $147,850 (Alafia
River $14,785; Hillsborough River $36,963; Pinellas-Anclote River $88,710; Manasota $7,392). The dollar amount
allocated for each contributing Basin Board is determined by the participating schools within each basin. District funds
will be used for program implementation, 300 field trips, three teacher training workshops, aquatic supplies, equipment
and field guides. The program is projected to reach 12,600 students and adults at a cost to the District of $11.73 per
person, 28% lower than other comparable youth education projects. The cost per participant contact hour is $2.05,
31% lower than the youth education average. The budget lines below include costs for staff to manage the project.
Additional Information
The FY2010 total project cost was $307,500, with the District contributing $147,850 (Alafia River $29,570;
Hillsborough River $29,570; Pinellas-Anclote River $73,925; Manasota $14,785). The dollar amount allocated for each
contributing Basin Board is determined by the participating schools within each basin. District funds will be used for
program implementation, 300 field trips, three teacher training workshops, aquatic supplies, and equipment and field
guides. The program is reaching 12,600 students and adults at a cost to the District of $11.73 per person. Cooperator
has reduced the District's cost per person by 8% from FY2009 ($12.80) to FY2011 ($11.73) by increasing reach and
reducing each field trip costs by $20. The District has supported this project since FY2007.
021 - Manasota Basin 38
W030
Tampa Bay Watch Field Trip Program
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 59,370 0 15,015 14,785 29,570
013 Hillsborough River Basin 74,040 0 7,507 36,963 29,570
014 Northwest Hillsborough Basin 7,507 0 7,507 0 0
016 Pinellas-Anclote River Basin 279,384 0 114,499 90,481 74,404
021 Manasota Basin 29,685 0 7,508 7,392 14,785
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 152,033 0 152,033 0 0
WMLTF (SWIM) - Prior Year Funds 479 0 0 0 479
Project Funds Not Budgeted by the
District
Tampa Bay Watch 495,340 0 335,690 0 159,650
$1,097,838 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2009 Budgeted FundsPurchase order opened 10/27/08 10/31/08
Field trips and teacher training completed 8/30/09 8/30/09
Final report and invoice due to District 9/30/09 9/30/09
FY2010 Budgeted FundsInitiate purchase order 10/1/09 12/4/09
Field trips and teacher training completed 8/31/10
Final report and invoice due to District 9/30/10
Status As Of: February 19, 2010
ACTION TO DATE: On time. Cooperator completed field trips (82 on-site Estuary EDventrues, 47 off-site Bay Grasses In
Classes field trips), 1 community ecotour, 9 outreach sessions and 1 community saltmarsh planting within the first
quarter (October through December). Teacher workshops will occur during the fourth quarter of grant cycle. One issue of
student newsletters has been completed and the second will be distributed in March. Summer camps have been
scheduled.
021 - Manasota Basin 39
W226
City of Anna Maria-Implementation of BMPs
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
City of Anna MariaCooperator(s)
Project Manager PRESTON, MATT
PRATER, CORRINATask Manager(s)
Status Ongoing
DescriptionThe City of Anna Maria has submitted this multi-phase cooperative funding project to implement water quality and
flood protection best management practices (BMPs) in the Lower Tampa Bay Watershed, part of Tampa Bay and
Sarasota Bay, SWIM waterbodies. The project will impact four areas within the City totaling approximately 124 acres:
1) North Bay/Tarpon Basin, 2) North Shore/Jacaranda Basin, 3) South Drive/South Bay Area, and 4)
Crescent/Gulf/Willow Basin. All four basins outfall into the internal canals of Anna Maria, which in turn discharge into
Lower Tampa Bay. With FY2007 funding the work on the Implementation of BMPs (Phase 1) includes the following
tasks: design, development of construction documents, construction permitting, bidding and contractor selection,
construction of the BMPs and construction engineering and inspection for the Crescent/Gulf/Willow improvement area.
The BMPs will address level of service (LOS) deficiencies. The flood protection and water quality improvements
include 10-ft wide shallow dry retention swales with ditch blocks, various diameter HDPE/RCP pipe, inlet/control
structures and BMP baffle structures (one at each basin outfall location). The swales will provide treatment of
stormwater runoff through percolation and evaporation while the baffle structures will provide treatment through
sedimentation, filtration and skimming. The City submitted a request for FY2008 and FY2009 funding to complete the
implementation of BMPs in the final three areas.
BenefitsThe City of Anna Maria has initiated a program to provide capital improvement projects that will improve both the water
quality and flood protection LOS provided by the City's surface water management system. The overall effect of the
improvements will be a reduction in pollutant loadings to the internal man-made canal system (classified as
Outstanding Florida Waters), Anna Maria Sound, Sarasota Bay, and Tampa Bay. The anticipated increase in flood
protection LOS will be through an increase in storage and conveyance capacity. The stormwater filtration devices
being proposed will provide suspended solids removal from stormwater runoff that previously discharged directly into
the canal/bay system.
Costs
The total budget amount for this project is $1.47 million with the Distict and the City of Anna Maria each contributing
half. The FY2009 project cost is $225,600, with the City and the District each contributing half ($112,800). The District
share is split between the Manasota Basin Board ($56,400) and State SWIM ($56,400). The probable construction
costs for this project are based on the BMP alternative analysis developed by the cooperator. The District funding
amounts shown in the table below include staff salary, travel and central garage.
Additional Information
Since 1950, approximately 50 percent of Tampa Bay's natural shoreline and approximately 40 percent of Sarasota
Bay's intertidal wetland habitat has been lost due to development and reduction in water quality. This resulted in a
decline in the aesthetic, recreational, and commercial value of the bay, as well as loss of habitat for native plants and
animals. The SWIM Plans for Tampa Bay and Sarasota Bay outline goals to restore habitat throughout the bay areas
and reduce pollutant loads entering the bays. The improvements will be made in City owned alleys and right of ways.
The funding should complete the following tasks for Phase 2 (North Bay/Tarpon Basin, North Shore/Jacaranda Basin,
and South Drive/South Bay improvement areas): design, development of construction documents, construction
permitting, bidding and contractor selection, construction of the BMPs and construction engineering and inspection.
021 - Manasota Basin 40
W226
City of Anna Maria-Implementation of BMPs
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 380,717 0 375,585 2,820 2,312
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 375,582 0 375,582 0 0
WMLTF (SWIM) - Prior Year Funds 2,311 0 0 0 2,311
Project Funds Not Budgeted by the
District
City of Anna Maria 734,800 0 734,800 0 0
$1,493,410 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Phase I - Contract Development & ExecutionNotice to Proceed 10/1/06 10/1/06
Draft Agreement sent to Management Services 11/30/06 11/30/06
City Approval of Contract 12/15/06 12/15/06
Contract Executed by District 12/27/06 12/27/06
2. Phase I - Critical Project MilestonesProject Conceptual Design Complete 6/30/07 6/30/07
Design and Survey Complete 12/1/07 11/28/07
Acquire Project Permits 1/30/08 6/12/08
Commence Construction 3/31/08 6/15/08
Preparation of Construction Documents Complete 7/30/08 12/28/07
Public Bid for Project Construction 9/30/08 12/14/07
Project Construction Complete 7/30/10 5/29/09
As-built Record Drawings 9/30/10
Final Project Report with Evaluation of Improvements 9/30/10 11/5/09
Approval of Maintenance Plan 10/31/10
3. Phase I - Close OutContract Termination 12/31/10
4. Phase II - Contract Development & ExecutionDraft Agreement 8/9/07 8/9/07
Draft Agreement to Management Services 9/4/07 9/4/07
Agreement to City 9/20/07 9/20/07
City Approval of Contract 9/28/07 10/11/07
District Approval of Contract 10/1/07 1/14/08
Agreement Back to Contracts for Funding Adjustments 12/11/07 12/11/07
Revised Agreement Back to City for Approval 12/31/07 1/15/08
City Approval of Revised Contract 1/15/08 1/9/08
Executed Contract and Notice to Proceed to City 1/31/08 1/14/08
5. Phase II - Critical Project MilestoneDesign and Survey Complete 10/17/08 3/31/09 4/30/09
Commence Construction 12/31/08 10/30/09 10/26/09
Approval of Maintenance Plan 4/17/10
Project Construction Complete 9/30/11
As-built Record Drawings 11/30/11
Final Project Report With Evaluation 11/30/11
021 - Manasota Basin 41
W226
City of Anna Maria-Implementation of BMPs
Contract Termination 12/31/11
Status As Of: January 04, 2010
Phase I construction is complete and Phase II design is complete and the ERP application has been approved and
construction is underway.
021 - Manasota Basin 42
W312
Tampa Bay Habitat Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Pinellas-Anclote River, Manasota
Cooperator(s)
Project Manager HENNINGSEN, BRANDT
Task Manager(s)
Status Ongoing
DescriptionTampa Bay, in 1987, was identified by the Legislature in the Surface Water Improvement and Management (SWIM)
Act of as the top priority on the District's SWIM priority list. This project provides funds for general support to SWIM
habitat restoration efforts for Tampa Bay. Funds are provided for equipment rental, equipment repair/maintenance,
advertising/public notices, parts and supplies, etc. Limited project construction expenses are also budgeted under this
activity code. Additionally, this project includes funds for exotic plant maintenance at the habitat restoration sites.
Lastly, funds for this project allow planning of future projects, and facilitate SWIM involvement with various
environmental committees and task forces (e.g., various committees of the Tampa Bay Estuary Program, etc.)
BenefitsThis project is important for meeting management goals of SWIM and the Tampa Bay Estuary Program (TBEP).
Coordination and planning of existing and future projects is a critical component of long term success of both
programs. If funds are not allocated, then SWIM's ability to successfully perform their habitat restoration projects for
Tampa Bay will be compromised. Accordingly, the District will not be meeting its (and the TBEP's) goals to restore
important habitats (and improve water quality) for the bay, habitats which have suffered great losses because of land
development and other human uses of the resource.
Costs
The FY2011 costs are funded 25 percent from the Pinellas-Anclote River, 25 percent from the Manasota, 25 percent
from the Hillsborough River, and 25 percent from the Alafia River Basin Boards. State SWIM funds will not
be available during FY2011. District funds shown in the table include staff salaries. District funds shown in the table
include staff salaries, travel and central garage.
Additional Information
Tampa Bay is the District's top priority Surface Water Improvement and Management (SWIM) program waterbody, is
a category I (most in need of restoration) under the State's Unified Watershed Assessment and Watershed
Restoration Priorities, and is considered an "estuary of national significance" with the designation of the Tampa Bay
(National) Estuary Program. Since 1950, about 50 percent of the bay's natural shoreline and 40 percent of its
seagrass acreage were lost as a result of physical destruction and water quality impairment. This resulted in a decline
in the aesthetic, recreational, and commercial value of the bay, as well as a loss of habitat for native plants and
animals.
021 - Manasota Basin 43
W312
Tampa Bay Habitat Restoration
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 188,321 0 153,539 18,528 16,254
013 Hillsborough River Basin 185,697 0 150,915 18,528 16,254
014 Northwest Hillsborough Basin 154,098 0 154,098 0 0
016 Pinellas-Anclote River Basin 209,624 0 174,842 18,528 16,254
021 Manasota Basin 195,248 0 160,466 18,528 16,254
District Budgeted - Outside Revenue
Ecosystem Trust Fund - Tampa-Allen's
Ck (SWIM)
1,500,000 0 1,500,000 0 0
State Trust Funds (SWIM) 269,888 0 269,888 0 0
State Trust Funds (SWIM) - Prior 2006 784,492 0 784,492 0 0
WMLTF (SWIM) - Prior Year Funds 15,012 0 0 0 15,012
$3,502,380 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: February 26, 2010
Due to inclement weather, the Busch Gardens Volunteer Marsh Planting Event originally scheduled for Saturday,
January 9, 2010, had to be postponed and has been rescheduled for Saturday, March 6, 2010; an anticipated 125
volunteers will install 10,000 marsh grass plugs at the Terra Ceia Ecosystem Project. In addition, SWIM and Tampa Bay
Watch have begun planning the largest volunteer planting event in the history of Tampa Bay (scheduled for Saturday,
April 10, 2010); an anticipated 350 volunteers will attempt to set a Tampa Bay (possibly world) record for the greatest
number of plants ever installed during a single volunteer event: 35,000 marsh grass plugs installed at a sector of the
Terra Ceia Ecosystem Restoration Project. SWIM has been notified that the Terra Ceia Ecosystem Restoration Project
will be recognized during the upcoming 18th Annual Future of the Region Awards ceremony conducted by the Tampa
Bay Regional Planning Council (TBRPC, March 19, 2010); SWIM staff are optimistic that the Terra Ceia project will be
awarded the Environmental Project of the Year for 2009. Brandt Henningsen and Janie Hagberg provided an invited
presentation to the Natural Resources and Environmental Impact Review Subcommittees of the TBRPC concerning an
update of the Clam Bayou (Phase 3) Ecosystem Restoration and Stormwater Treatment Project. On February 19, 2010,
B. Henningsen and Mike Dalsis provided a requested tour of Tampa Bay restoration projects for faculty and students
from the University of London (England). At the request of the federal Environmental Protection Agency (EPA), SWIM
staff are coordinating with EPA scientists who will be conducting a scientific study of various ecological parameters of
differing aged SWIM restoration projects for Tampa Bay. SWIM staff continued to coordinate with the Land Resources
Department for the planning of the upcoming District Volunteer Appreciation Day (March 27, 2010); SWIM will be
recognizing the 616 volunteers distributed among 14 groups for their contributions to the restoration of the bay during
nine volunteer events of 2009 (note: 2009 SWIM volunteers donated 2696 hours of service, installing at least 29,630
marsh plants and picking up 20,200 pounds of illegally deposited debris at/from four SWIM restoration sites). Lastly,
SWIM staff continued to coordinate with one Eagle Scout candidate (Boy Scouts of America) to perform his Eagle
Project at a SWIM restoration site (Terra Ceia).
021 - Manasota Basin 44
W316
Cockroach Bay (Phases C-D-E-F)
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Pinellas-Anclote River, Manasota
Hillsborough CountyCooperator(s)
Project Manager HENNINGSEN, BRANDT
HENNINGSEN, BRANDTTask Manager(s)
Status Ongoing
DescriptionThis 500 acre SWIM initiative project is an ecosystem restoration effort located in southeastern Tampa Bay on
property owned by Hillsborough County. The 651 acre property was purchased in 1991 for $2.1 million by the County's
Environmental Lands Acquisition and Protection Program (ELAPP), purchase, in part, contingent upon the District
(SWIM) assuming primary responsibility for wetland restoration of the tract; of the 651 acres, approximately 500 acres
are the primary target for restoration, with enhancement appropriate for the remaining 151. Since 1991, the project has
evolved into a much larger ecosystem project, encompassing a mosaic of habitats typically found in coastal areas of
the bay: uplands as well as freshwater and estuarine wetlands; stormwater treatment of regional agricultural runoff is
also a component of the restoration. While the County is the primary cooperator for this project, the effort also involves
15 other cooperators, collectively known as the "Cockroach Bay Restoration Alliance" (COBRA). Over the past six
decades, the property had been used for agriculture and mining activities. It has suffered from a number of
environmental problems including wetland and upland habitat loss/degradation, exotic plant infestation, adverse
hydrological alterations, and exposure to polluted runoff from an upstream agricultural watershed. Currently, 425 acres
of the 500 acre project have been completed.
BenefitsThis project has been and will continue to be important in meeting management goals of SWIM and the Tampa Bay
Estuary Program (TBEP), including several phases providing low salinity habitats and improvements to water quality
via stormwater treatment. Improved habitat values and the addition of habitat acreages will provide opportunities for
many differing species of coastal wildlife,inclusive of commercial and sportfishing species, bird populations, a host of
invertebrate species (crabs, shrimp, oysters, etc.), reptiles/amphibians, and small mammals. In addition, the site is part
of the State's and County's Cockroach Bay Aquatic and Park Preserves, (increasingly) popular destinations for the
public to visit for nature activities (canoeing/kayaking, fishing, bird watching, camping, hiking, etc.).
Costs
While early funding for this project originated as early as 1991, figures given here represent funds encumbered under
the 1996 cooperative agreement with the County. This project has been implemented by phases, contingent upon
available funds. Project updates given here cover four ongoing phases: Phases C (southeastern Leisey Shell Pit and
braided tidal creek), D (northeastern Leisey Shell Pit), E (uplands), F (freshwater wetlands). Grants for this
project have totaled $1.6 million. Aside from grants, mitigation funds from the FDOT have been used to help complete
the project. The FY2005 budget includes $500,000 for State Appropriation and approximately $420,000 of Basin and
State SWIM funds for construction of on-going phases. The FY2004 through FY2009 budgets included a total of
$257,781 of incoming revenue from the Gardinier Trust Fund; in addition, FY2006 and FY2007 included a total
of $200,000 of Basin and State SWIM funds. During FY2009, an additional $1,000,000 of incoming revenue was
awarded to the project from the Tampa Port Authority. District funds shown in the table include staff salaries, travel
and central garage.
Additional Information
Tampa Bay is the District's top priority Surface Water Improvement and Management (SWIM) program waterbody, is
a category I (most in need of restoration) under the State's Unified Watershed Assessment and Watershed
Restoration Priorities, and is considered an "estuary of national significance" with the designation of the Tampa Bay
Estuary Program. Since 1950, about 50 percent of the bay's natural shoreline and 40 percent of its seagrass acreage
were lost as a result of physical destruction and water quality impairment. This resulted in a decline in the aesthetic,
recreational, and commercial value of the bay, as well as a loss of habitat for native plants and animals. Adjacent to
the County's property lies Cockroach Bay, often touted as the "Crown Jewel" of Tampa Bay; it is one of the few
relatively pristine coastal ecosystems left in Tampa Bay. Despite these adverse watershed and estuarine impacts,
Cockroach Bay still maintains relatively abundant sea grass beds and recreational and commercially important
fisheries resources.
021 - Manasota Basin 45
W316
Cockroach Bay (Phases C-D-E-F)
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 634,279 0 624,022 6,010 4,247
013 Hillsborough River Basin 1,744 0 0 1,744 0
016 Pinellas-Anclote River Basin 1,161 0 0 1,161 0
021 Manasota Basin 1,744 0 0 1,744 0
District Budgeted - Outside Revenue
DEP/EPC Gardinier - (SWIM) 168,370 0 168,370 0 0
Ecosystem Trust Fund - Cockroach Bay
(SWIM)
500,000 0 500,000 0 0
Gardinier - Cockroach Bay (W316) 200,000 0 200,000 0 0
State Trust Funds (SWIM) 150,169 0 150,169 0 0
State Trust Funds (SWIM) - Prior 2006 860,777 0 860,777 0 0
WMLTF (SWIM) - Prior Year Funds 4,247 0 0 0 4,247
$2,522,491 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesCompletion of USACE Feasibility Report (by USACE) 6/30/01 3/31/02 3/15/02
Completion of construction of freshwater wetlands 4/30/04 4/15/04
Planting of freshwater wetlands 8/15/04 8/2/04
Start construction of braided tidal creek by OPS 1/15/05 1/26/05
Complete construction of braided tidal creek by OPS 7/15/05 9/15/05 9/23/05
Planting of braided tidal creek 8/31/05 10/1/05 10/8/05
Begin Sediment Survey of NE Leisey Shell Pit 12/1/05 12/15/05 12/13/05
Complete Sediment Survey of NE Leisey Shell Pit 3/15/06 3/1/06
Restoration of E. Leisey Shell PitsComplete in-house draft 30% restoration plan 6/30/08
Secure consulting firm to assist with rest. plans 8/31/08
Complete 100% restoration plan set 12/31/08
Prepare/submit permit applications for E. Leisey Pits 3/31/09
Draft RFB for Leisey Shell Pit Rest. Construction 4/30/09
Release RFB for Leisey Shell Pit construction 6/26/09
Award const. contract Leisey Shell Pit Rest. 8/30/09
Begin construction of Leisey Shell Pit Project 10/1/09
Complete const. Leisey Shell Pit project 3/31/10
Status As Of: February 26, 2010
As previously described, the Tampa Port Authority (TPA) and the District (SWIM) have entered into a cooperative
agreement detailing the TPA's proposal to Hillsborough County to perform mitigation and restoration at the County's
Cockroach site ("Leisey Shell Pits" area). The TPA has received permission from the County to perform 10.88 ac of
wetland mitigation at the Cockroach site. In return for use of the Cockroach site for the Port's mitigation, the TPA will
provide $1.1 million for the restoration of up to 75 acres of wetlands and the completion/maintenance of the upland
systems (i.e., 75 acres of wetland restoration for 10.88 acres of wetland mitigation plus remaining upland work); of those
funds, $1.0 million will be earmarked for wetland (and possibly upland) restoration, and $100,000 will specifically be
021 - Manasota Basin 46
W316
Cockroach Bay (Phases C-D-E-F)
earmarked for upland restoration and site management. The TPA will be responsible for the design, permitting, bidding,
construction, and monitoring of the project. In essence, this effort should complete the overall Cockroach Bay Ecosystem
Restoration Project. No SWIM/District funds will be used for any mitigation expenses, only restoration components over
and above mitigation aspects. Project design has been finalized and permit applications submitted for processing.
Permits have been received from all agencies excepting the Hillsborough County Environmental Protection Commission
(HCEPC); environmental concerns raised by the HCEPC currently are still being addressed by the TPA and their
consultant. Construction bids are now anticipated to be released by the TPA during spring/summer 2010, followed by
construction. Lastly, a no-cost time extension is being routed for execution by the Florida Department of Environmental
Protection and HCEPC to allow grant funds from the Gardinier Trust Fund, now not needed for the north side of the
Cockroach Bay system, to be used for habitat restoration on the south side of Cockroach Bay proper (i.e., "Rock Ponds"
property). ACTION TO DATE: On-time; Tampa Port Authority securing permits/preparing construction RFB but
permitting delays may influence the timeline.
021 - Manasota Basin 47
W331
Biennial Seagrass Mapping of Tampa Bay, Sarasota Bay, Charlotte
HarborProject Type SWIM
AORs Strategic InitiativesWater Quality Water Quality MonitoringNatural Systems Natural Systems Identification and Monitoring
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Pinellas-Anclote River, Peace River,
Manasota
Charlotte Harbor National Estuary Program, Pinellas County, Sarasota Bay Estuary Program,
Tampa Bay Estuary Program
Cooperator(s)
Project Manager KAUFMAN, KRIS
Task Manager(s)
Status Ongoing
DescriptionThis SWIM initiative project involves mapping and monitoring seagrass within four SWIM priority waterbodies: Tampa
Bay, Sarasota Bay, Lemon Bay, and Charlotte Harbor. Funds requested in the FY2011 budget of $175,000 will be for
the 2012 phase of mapping. It is anticipated that the funds needed for the 2012 effort will be budgeted in FY2011 and
FY2012. In addition to SWIM waterbodies, contractual services for the St. Joseph Sound/Clearwater Harbor Biennial
GIS Mapping of Seagrass (See K150) are completed under a single agreement to benefit from economy of scale.
Specifically, the District's consultant will provide digital aerial photography, photointerpretation, and GIS-based
mapping in order to generate calculations of seagrass acreage and distribution within each of the named waterbodies.
The project is conducted every two years to monitor the long-term health of these vital resources. Funds budgeted in
FY2009 and FY2010 are for the 2009 - 2010 effort. The digital format utilized in 2004 and 2006 allowed for more
detailed GIS analysis to be conducted beyond creation of the original seagrass map product and will allow for efficient
transfer of the imagery to fill agency and public requests. A new task started during the 2007-2008 effort was to scan
historical photography from previous seagrass mapping efforts in the 1990s and early 2000s at high resolution. The
intent is to continue this effort in 2010 and complete the georeferencing needed to and create digital GIS imagery
layers that will then be uploaded to the District's GIS system. SWIM is utilizing a pre-qualified firm procured under the
Mapping & GIS Section's RFP 006-07 as the consultant for the 2009 - 2010 phase of mapping. District funds shown in
the table include staff salaries.
BenefitsThe mapping of seagrasses within each estuary allows the District, the Estuary Programs, and other entities to monitor
the health and distribution of seagrasses. Seagrass health is used as an indicator of water quality conditions. Thus,
this project can assist with water resource management decision making, specifically in evaluating the effectiveness of
water quality improvement projects.
Costs
The project costs for mapping SWIM waterbodies in 2012 is estimated at $350,000. The FY2011 proposed funding is
$175,000 with five basin boards contributing. The project costs for mapping SWIM waterbodies in 2009 - 2010 is
$350,000. Costs associated with this effort are included in the FY2009 and FY2010 budgets. The FY2009 budget was
$175,000, with 50 percent from State SWIM and 50 percent from five basin boards (Alafia River, Hillsborough River,
Pinellas-Anclote River, Manasota, and Peace River). The FY2010 budget is $175,000, with the five basin boards
contributing. At their April 2009 meetings, the basin boards approved amending their FY2009 budgets to include
reallocated State SWIM funds to cover 50 percent of the District's proposed FY2010 costs ($87,500). The remaining
funds ($87,500) are included in the five basin boards FY2010 budgets. District funds shown in the table include staff
salaries.
Additional Information
The next phase of mapping will begin in December 2009. Seagrass mapping for SWIM waterbodies (W331) and St.
Joseph Sound Clearwater Harbor (K150) will be completed under one agreement at a total estimated cost of
$350,000. Seagrass meadows serve as nurseries for a variety of commercially and recreational important species of
fin fish and shellfish, and they are highly dependent upon the maintenance of good water quality. The project meets
the goals and objectives of the Tampa Bay, Sarasota Bay, and Charlotte Harbor SWIM Plans, the Tampa Bay Estuary
Program, Sarasota Bay Estuary Program, and Charlotte Harbor National Estuary Program. The 2008 effort is ongoing,
with the most recent completed mapping results from 2006. Between 2004 and 2006, seagrass coverage in Tampa
Bay increased by approximately 4.7%. In Sarasota Bay, which has a more highly urbanized watershed than Tampa
Bay, seagrass increased 7% in coverage from 2004 to 2006. From 2004 to 2006, Charlotte Harbor seagrass coverage
increased by 1%. The only SWIM waterbody to experience a loss in coverage between 2004 and 2006 was Lemon
Bay with a 1% decrease.
021 - Manasota Basin 48
W331
Biennial Seagrass Mapping of Tampa Bay, Sarasota Bay, Charlotte
Harbor
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 110,883 0 52,954 37,925 20,004
013 Hillsborough River Basin 110,883 0 52,954 37,925 20,004
014 Northwest Hillsborough Basin 52,954 0 52,954 0 0
016 Pinellas-Anclote River Basin 110,883 0 52,954 37,925 20,004
020 Peace River Basin 197,177 0 137,777 39,396 20,004
021 Manasota Basin 201,328 0 133,833 47,491 20,004
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 371,912 0 371,912 0 0
State Trust Funds (SWIM) - Prior 2006 253,404 0 165,904 0 0
WMLTF (SWIM) - Prior Year Funds 12,520 0 0 0 12,520
$1,421,944 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesRequest for Proposals 6/15/03 7/11/03
Begin Review of Proposals 8/15/03 9/22/03
Draft Agreement to Management Services 10/31/03 12/17/03
Contract Executed 11/15/03 1/16/04
Photography Shot for 2003/2004 1/31/04 1/17/04
Final Report for 2003/2004 12/31/04 12/31/04
First Amendment to the 2003/2004 Agreement 12/1/05 12/13/05
Consultant Notice to Proceed 12/1/05 12/13/05
Acquisition of Aerial Photography 1/31/06 2/15/06 2/10/06
Final Deliverables for 2005/2006 12/31/06 12/31/06
Agreement Expiration Date 12/31/06 12/31/06
2. Critical Project MilestonesProcessing of Technical Specifications and Purchase Order 10/30/07 11/30/07
Purchase Order with scope of work Opened 11/30/07 11/30/07
Work Order #1 Opened 12/13/07 12/13/07
Consultant imagery acquisition 1/30/08 2/15/08 2/15/08
Consultant ortho-imagery production 3/31/08 3/31/08
Consultant photointerpretation 10/31/08 10/31/08
Consultant GIS validation 11/30/08 11/30/08
Consultant draft final deliverables 12/31/08 12/31/08
3. Critical Project MilestonesWork Order 1 under 2010 P.O. Executed 12/1/09 12/15/10
2010 Work Order 1: Imagery Acquired 2/15/10 1/12/10
Work Order 2 under 2010 P.O. Executed 3/1/10
2010 Work Order 2: GIS Mapping 12/31/10
Status As Of: March 02, 2010
The 2010 purchase order is open and the first work order for the 2010 effort were executed December 2009. Imagery for
021 - Manasota Basin 49
W331
Biennial Seagrass Mapping of Tampa Bay, Sarasota Bay, Charlotte
Harborall waterbodies was captured by January 12, 2010. Imagery is being processed by the Consultant and will be reviewed by
District staff for final approval. The second work order for photointerpretation and GIS based mapping is expected to be
executed in March 2010.
021 - Manasota Basin 50
W348
Terra Ceia Isles Habitat Restoration
Project Type SWIM
AORs Strategic InitiativesNatural Systems Natural Systems Conservation and RestorationWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
Florida Department of Environmental ProtectionCooperator(s)
Project Manager HENNINGSEN, BRANDT
DALSIS, MIKETask Manager(s)
Status Proposed
DescriptionThe Terra Ceia Aquatic and Park Preserves habitat enhancement and restoration project, a SWIM initiative, is located
in the southeastern reaches of Tampa Bay (Manatee County). This large, multi-phased project is being cooperatively
implemented with the Florida Department of Environmental Protection (FDEP). Currently, the project involves 2,308
acres of publicly owned land (Terra Ceia Isles and the Peanut Lake parcel, with an additional 2,900 acres included in
the District's five year acquisition plan. Accordingly, this project has the potential of encompassing at least 5,200 acres
and will require multiple years of funding, planning, and implementation. Project updates focus primarily on just the
1,745 acre Terra Ceia Isles parcel, although updates will be given on progress within Peanut Lake lands and
concerning additional land purchases and potential future phases. It is anticipated that the majority of this project will
be performed by private contractors.
BenefitsThis project will be important in meeting management plan goals of SWIM and the Tampa Bay Estuary Program
(TBEP). The current project involves the enhancement, restoration, and management of an estimated 700 acres of
various habitats typical of coastal ecosystems (i.e., habitat mosaics): estuarine and freshwater wetlands, transitional
habitats, and uplands. Salinity gradients and low salinity habitats will be emphasized to improve fisheries production.
Accordingly, the project will provide valuable habitats for Tampa Bay fisheries and other coastal species. Portions of
this are true restoration in that sections of the site historically were bay bottom and intertidal wetlands that were filled to
create a proposed finger-fill subdivision. In addition, strides to meet bay water quality goals of both SWIM and TBEP
will be addressed via improved stormwater treatment. Improved habitat values and the addition of habitat acreages will
provide opportunities for many differing species of coastal wildlife, inclusive of commercial and sportfishing species,
bird populations, a host of invertebrate species (crabs, shrimp, oysters, etc.), and small mammals.
Costs
Total cost estimate for Terra Ceia Isles is $9,400,000 and is being budgeted over multiple fiscal years. Note: exotic
plant control funds (S042) have annually been budgeted under Land Resources Department using Save Our Rivers
dollars; these funds have been included here to give a more complete picture of the restoration effort. Proposed
FY2011 funds ($500,000) are for construction of additional project phases and will include staff salaries, travel, and
central garage. Traditionally, District funds are split 50/50 between the Manasota Basin Board and State SWIM Fund,
but during FY2011, State funds will not be available. Future phases associated with additional land acquisition will
require future funding.
Additional Information
Tampa Bay is the District's top priority Surface Water Improvement and Management (SWIM) program waterbody, is
a category I (most in need of restoration) under the State's Unified Watershed Assessment and Watershed
Restoration Priorities, and is considered an "estuary of national significance" with the designation of the Tampa Bay
(National) Estuary Program. Since 1950, about 50 percent of the bay's natural shoreline and 40 percent of its
seagrass acreage were lost as a result of physical destruction and water quality impairment. This resulted in a decline
in the aesthetic, recreational, and commercial value of the bay, as well as a loss of habitat for native plants and
animals.
021 - Manasota Basin 51
W348
Terra Ceia Isles Habitat Restoration
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,715,726 0 1,181,691 523,766 10,269
041 Florida Forever/SOR/P2000 216,189 0 216,189 0 0
District Budgeted - Outside Revenue
Ecosystem Trust - Terra Ceia Habitat
Rstr (SWIM)
2,312,500 0 2,312,500 0 0
Nat'l Fish & Wildlife - Terra Ceia
(SWIM)
300,000 0 300,000 0 0
NOAA - Terra Ceia 2,000,000 0 2,000,000 0 0
State Trust Funds (SWIM) 330,866 0 330,866 0 0
State Trust Funds (SWIM) - Prior 2006 1,276,234 0 1,276,234 0 0
WMLTF (SWIM) - Prior Year Funds 10,269 0 0 0 10,269
$8,161,784 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project Milestones30% wetland design plans 9/30/02 9/30/04 12/1/04
Draft Phase 3 upland restoration RFB 8/1/04 4/15/04
Release Phase 3 upland restoration contract 9/1/04 8/13/04
Award Phase 3 upland restoration contract 11/1/04 12/2/04
Complete 60% wetland design plans 4/30/05 8/1/05 8/9/05
Submit Environmental Permit Applications 12/31/05 2/1/06
Complete 100% wetland design plans 12/31/05 12/22/05
Draft wetland construction RFB 12/31/05 12/22/05
Release Wetland Construction RFB 1/31/06 1/13/06
Negotiate/process/execute const. contract 6/15/06 9/4/06
Complete Phase 3 upland restoration 7/31/06 9/30/06 9/29/06
Complete Phase 1 wetland construction 6/15/08 12/31/08 12/15/08
Status As Of: March 16, 2010
Due to inclement weather, the Busch Gardens Volunteer Marsh Planting Event originally scheduled for
Saturdays,December 5, 2009, and then January 9, 2010, had to be postponed and was rescheduled for Saturday, March
6, 2010 (in coordination with Tampa Bay Watch); 80 Busch Gardens and public volunteers install 8,500 marsh grass
plugs at the Terra Ceia project. In addition, SWIM and Tampa Bay Watch have begun planning the largest volunteer
planting event in the history of Tampa Bay (scheduled for fall 2010); an anticipated 350 volunteers will attempt to set a
Tampa Bay (possibly world) record for the greatest number of plants ever installed during a single volunteer event:
35,000 marsh grass plugs installed at a sector of the Terra Ceia project. SWIM has been notified that the Terra Ceia
Ecosystem Restoration Project will be recognized during the upcoming 18th Annual Future of the Region Awards
ceremony conducted by the Tampa Bay Regional Planning Council (TBRPC, March 19, 2010); SWIM staff are optimistic
that the Terra Ceia project will be awarded the Environmental Project of the Year for 2009. USGS and USF staff
continued the Frog Creek Hydrodynamic Modeling Study, evaluating if proposed 1-3 creek offline intertidal lagoons would
deleteriously affect the existing salinity regime of the creek. Study results are anticipated later this year and will be used
to help determine whether 1-3 lagoons will be constructed for the creek or if the areas will be restored as coastal
uplands. As noted in previous updates, the 2008-2009 drought impacted upland restoration efforts for a 24 acre site
("airplane site") cleared of its original Brazilian pepper and Australian pine forests, resulting in poor survivorship of
installed grass seed, pine trees, and saw palmetto. New grass seed has now been sown, and grass is sprouting
throughout the area; additional pine trees and saw palmetto currently are being installed throughout the tract. Quarterly
maintenance by Tampa Contracting Services (TCS) has continued for the 217 acre Phase 3 upland restoration project;
021 - Manasota Basin 52
W348
Terra Ceia Isles Habitat Restoration
persistent guinea grass problems are being addressed by TCS. Maintenance of the 64 acre Phase 4 Upland Restoration
also continued by a private contractor (Rick Richards, Inc.), with the maintenance contract drawing to a close during early
2010. A new contractor (Environmental Aquatic Control, Inc.) completed their second quarter of maintenance of the
Phase 5 upland restoration project (i.e., a redressing of upland Phases 1 and 2 to get non-native plants back under
control, inclusive of a partial replant of native plants that had been killed over the years due to drought, flooding, and/or
non-native plant competition); new Phase 5 plants are doing well, especially with the abundant fall/winter rains. One
section of relic (i.e., farm) road (aka "Drunkard Lane") immediately adjacent to a wetlands was graded, sod laid, and
grass seed sown to stabilize the area, with the FDEP intending to close the road to traffic and re-routing traffic along a
new upland route; FDEP has not closed the road and grass seed has not been able to successfully stablize the path (due
to vehicular traffic) although sodded areas are thriving (no traffic). SWIM has suggested FDEP establish a new path
using geoweb and/or crushed granite; FDEP is considering the recommendation. SWIM completed stabilization of a
second section of Drunkard Lane with crushed granite, addressing FDEP concerns over potential turbidity issues that
could result from stormwater runoff. FDEP has completed their plans for the revamped Bishop Harbor Boat ramp but are
still in permitting. SWIM received bids for the final phase (Phase 6) of upland restoration for the Terra Ceia Isle site, and
a purchase order commissioning the work is being processed. In addition, right-of-way issues with the Florida
Department of Transportation have been resolved for the Phase 6 upland project, thereby giving the District and our
contractor convenient access to a sector of the Phase 6 project. ACTION TO DATE: On-time; Phase 5 upland
restoration contract awarded; construction commenced during May 2009. Phase 6 upland restoration about to
commence.
021 - Manasota Basin 53
W358
Tom Bennett Park
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager POWERS, STEPHANIE
Task Manager(s)
Status Ongoing
DescriptionThis project is in response to a request from Manatee County to restore and enhance approximately 75 acres of
intertidal and freshwater wetland and upland habitat along the Manatee River. Tom Bennett Park is a 180-acre site that
was purchased in 2003 by Manatee County and the Florida Communities Trust. The project plan targets the
restoration of degraded salt marsh habitat and associated coastal maritime forest on adjacent hummocks through
minor regrading, nuisance and exotic species eradication, and supplemental plantings. The creation of freshwater,
ephemeral wetlands throughout the property is also anticipated. The County will be the lead agency for the project.
The District will provide project management oversight of design and construction progress.
BenefitsUpon completion, the project will provide significant benefits to habitat and water quality. The County also plans to
provide passive recreational and educational opportunities to the public.
Costs
The total project cost is approximately $4.4 million, which includes $3.9 million for land acquisition. The County
contributed $1.5 million for the land purchase and has budgeted $260,000 for design and construction. The District's
FY2010 contribution is to be $60,000. At their April 2009 meeting, the Manasota Basin Board approved amending its
FY2009 budget to include reallocated State SWIM funds to cover 50 percent ($30,000) of the FY2010 costs. The
remaining costs ($30,000) are funded by the Manasota Basin Board. The County is requesting $200,000 for FY2011,
which will be awarded upon Board approval. District funds shown in the table include staff salaries.
Additional Information
Since 1950, approximately 50 percent of the bay's natural shoreline has been lost due to development and reduction
in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the bay, as well as a
loss of habitat for native plants and animals. The SWIM Plan for Tampa Bay outlines goals to restore habitat
throughout the bay area and reduce pollutant loads entering Tampa Bay. The objectives of this project are consistent
with these goals.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 34,213 0 0 2,328 31,885
District Budgeted - Outside Revenue
WMLTF (SWIM) - Prior Year Funds 31,885 0 0 0 31,885
Project Funds Not Budgeted by the
District
Manatee County 260,000 0 0 0 260,000
$326,098 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 54
W358
Tom Bennett Park
Critical Project Milestones ActualProjected Amended
Contract Development and ExecutionReceive Scope of Work from Cooperator 9/16/09
Draft Agreement to Management Services 10/1/09
Agreement Returned from Management Services 10/22/09
Agreement Sent to Cooperator 10/29/09
Signed Agreement Returned from Cooperator 11/30/09
Agreement Fully Executed 12/15/09
Contract ExpirationProject Close Out 12/31/11
Status As Of: February 26, 2010
The scope of work was received from the cooperator on December 4, 2009. An agreement is being routed to
Management Services for review.
021 - Manasota Basin 55
W364
Palmetto Estuary
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
PalmettoCooperator(s)
Project Manager DALSIS, MIKE
HAGBERG, JANIETask Manager(s)
Status Proposed
DescriptionThis project is a District initiated cooperative project. Over the past ten years the City of Palmetto purchased 11.75
acres of various coastal habitats near the mouth of the Manatee River. The parcel contains various estuarine habitats
that transition to coastal uplands. The restoration project expaned to include an addtional 18 acre park referred to as
"Wayside Park" adjacent to the south and east of the 11.75 acres acquired by the City of Palmetto. This is a
multi-phase project with the 30 acre Phase 1 restoration completed in 2000. The proposed Phase 2 is an extension of
Phase 1 and will restore an additional 7.86 acres of coastal habitat adjacent and to the north of Phase I. Habitat values
of the parcel have been severely compromised due to dredge and fill impacts, illegal dumping, untreated stormwater,
and dominance of most of the uplands by non-native vegetation (i.e., Brazilian pepper, Australian pine, melaleuca).
Based on field investigations, portions of the site will require only non-native plant removal/native plant enhancement,
while others will require excavation/regrading to create new/restored open water and intertidal habitats. The City of
Palmetto is interested in partnering with the District on Phase 2 of this coastal restoration project which is envisioned
to enhance coastal uplands and restore intertidal and open water wetlands. The project site will become a component
of the Palmetto Estuary Nature Park to the south.
BenefitsThis project has been and will continue to be important in meeting management goals of SWIM and the Tampa Bay
Estuary Program (TBEP), including multiple phases providing low salinity habitats that create valuable nursery grounds
for breeding. Improved habitat values and the addition of habitat acreages will provide opportunities for many differing
species of coastal wildlife, inclusive of commercial and sportfishing species, bird populations, a host of invertebrate
species (crabs, shrimp, oysters, etc.), reptiles, amphibians, and small mammals. In addition, the site will become a
part of the "Palmetto Estuary Nature Park", an increasingly popular destination for the public to visit for nature activities
(canoeing/kayaking, fishing, bird watching, etc.).
Costs
The total estimated project cost for the proposed Phase 2 project is $100,000 which is being funded by the Manasota
Basin Board. District funds shown in table include staff salaries, travel, and central garage charges.
Additional Information
Tampa Bay is the District's top priority Surface Water Improvement and Management (SWIM) program waterbody, is
a category I (most in need of restoration) under the State's Unified Watershed Assessment and Watershed
Restoration Priorities, and is considered an "estuary of national significance" with the designation of the Tampa Bay
Estuary Program. Since 1950, about 50 percent of the bay's natural shoreline and 40 percent of its seagrass acreage
were lost as a result of physical destruction and water quality impairment. This resulted in a decline in the aesthetic,
recreational, and commercial value of the bay, as well as a loss of habitat for native plants and animals. The 2000
Phase 1 project was the 2001 Environmental Project of the Year as honored by the Future of the Region Awards
program of the Tampa Bay Regional Planning Council.
021 - Manasota Basin 56
W364
Palmetto Estuary
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 188,245 0 81,834 104,246 2,165
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 81,833 0 81,833 0 0
WMLTF (SWIM) - Prior Year Funds 2,165 0 0 0 2,165
Project Funds Not Budgeted by the
District
City of Palmetto 375,000 0 375,000 0 0
$647,243 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: January 04, 2010
This project represents Phase 2 of a two part series of cooperative projects with the City of Palmetto; the award winning
Phase 1 project was completed in 2000. Phase 2 proposed funding is envisioned to cover permitting and construction
costs associated with this coastal ecosystem restoration project. Received 100% plans signed and sealed from
environmental consultant to join Phase 2 with the completed Phase 1 project, and the revised notice general permit for
submittal to the FDEP. The Cooperative Agreement is currently being drafted with the City of Palmetto.
021 - Manasota Basin 57
W394
FELTS Preserve Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Manatee County Audubon SocietyCooperator(s)
Project Manager PRATER, CORRINA
NORTON, NANCYTask Manager(s)
Status Ongoing
DescriptionThis project will restore important habitat and improve water quality functions on the FELTS Preserve which drains into
Terra Ceia Bay about two miles away and ultimately discharges into Tampa Bay, a District SWIM waterbody. The
FELTS Preserve, owned by Manatee County Audubon, is located at 4600 24th Avenue, East Palmetto in north
Manatee County within the Manatee River Watershed. This project will result in restoration/creation/enhancement of
5.5 acres of freshwater wetlands, plus restoration of 8.5 acres of adjacent uplands located within the 28.5 acre
preserve through backfilling ditches, removal of exotic vegetation and planting of native vegetation. Much of the project
site has been altered over time, primarily through ditching and draining to create improved pasture for agricultural
purposes. The site is important because the general area is rapidly being converted from agricultural to residential
development and much of the habitat has been fragmented by construction of roads. Natural sheet flow has been
diverted through development and ditching. Vegetative diversity is relatively low in the existing water features due to
the establishment of monocultures by invasive and exotic plants. A mosaic of diverse habitat types is proposed,
including emergent marsh, existing hardwood swamp and hammock and ponded features.
BenefitsBest management practices will be implemented through planting of emergent and submergent plant species and the
management and control of invasive exotics. Water quality benefits will be achieved and monitored as the enhanced
site will provide for pollutant filtration and nutrient uptake through the creation of the proposed littoral shelves, as well
as buffering against erosion. The project location will also offer exceptional habitat value through the creation of
feeding platforms for wading birds.
Costs
The total cost of the project is $196,900. In FY2006, the District contributed $29,500 shared evenly by SWIM and the
Manasota Basin Board. The FY2006 application requested $40,400 but the manatee Audubon was unable to acquire
that amount for a match. Earthmoving was accomplished by grants from U.S. Fish & Wildlife Service and National
Fish & Wildlife Foundation at a cost of $23,070. The FY2008 project cost was $32,600, with the Manatee Audubon
and the District each contributing half ($16,300). The District's share was split between the Manasota Basin Board
($8,150) and State SWIM ($8,150). The FY2009 project cost was $28,700, with Manatee Audubon and the District
each requested to contribute half ($14,350). The District share was split between the Manasota Basin Board ($7,175)
and State SWIM ($7,175). The FY2010 project cost is $18,000 with Manatee Audubon and the District each
contributing half ($9,000). Total funding in the table below includes staff salary, travel and central garage.
Additional Information
A professional management plan has been completed by Ed Freeman, then with the Nature Conservancy when
contracted by Manatee Audubon. The Mana-Teens, Native Plant Society, Manatee River Garden Club and others
have helped to inventory plants on site, control exotic plants by manual removal and minimal chemical means, and
performed additional habitat improvement primarily on the uplands. Five and one-half wetland acres have been
planted and eight and one-half acres of pasture was restored in FY2008. Chemical and mechanical control for
invasive exotic plants has been implemented on approximately 17.5 acres and a monthly maintenance program is
underway. Audubon is re-creating littoral areas around the enhanced ponds by planting some 14,200 plants. Manatee
Audubon will guarantee survival of 85% of planted material. In FY2009, Manatee Audubon will do a littoral shelf
planting of 3 acres, install 90 plants in a 17-acre upland area and continue with exotic control.
021 - Manasota Basin 58
W394
FELTS Preserve Restoration
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 55,979 0 43,868 2,226 9,885
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 43,868 0 43,868 0 0
WMLTF (SWIM) - Prior Year Funds 885 0 0 0 885
Project Funds Not Budgeted by the
District
Manatee County Audubon Society 47,150 0 38,150 0 9,000
National Fish and Wildlife Foundation 10,000 0 10,000 0 0
Other 58,600 0 49,600 0 9,000
USFWS 12,000 0 12,000 0 0
$228,482 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Consultant Agreement Development and ExecutionScope of Work Developed 8/24/09 8/18/09
Scope sent to finance for Purchase Order 8/31/09 12/2/09
2. Project TasksPlantings 8/28/10
Maintenance 9/5/10
3. Close OutFinal Report and Invoice 9/6/10
3. Contract TerminationProject Completion 9/27/10
Status As Of: February 15, 2010
The purchase order for the approved FY2010 scope has been submitted for review. The Manatee County Audobon
Society submitted invoices for FY09 and they have been reviewed and have been submitted for payment. A portion of the
invoices were not eligible for reimbursement due to the date of the work done and the scope not covering the work
performed. The Manatee County Audobon Society did not request funding for FY2011.
021 - Manasota Basin 59
W501
SWIM Plan Implementation - Charlotte Harbor
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Peace River, Manasota
Charlotte Harbor National Estuary ProgramCooperator(s)
Project Manager GARCIA, LIZANNE
KAUFMAN, KRISTask Manager(s)
Status Ongoing
DescriptionThis project provides for the administration and implementation of projects as outlined in the SWIM Plan for Charlotte
Harbor. The FY2009 budget will include staff salaries and administrative costs to implement projects in the SWIM
Plan. Administration and implementation includes assessment of implementation progress, a review and refinement of
the Pollutant Load Reduction Goal (PLRG) for the waterbody, periodic SWIM Advisory Committee meetings, new
project development (rationale and justification), development of relevant contracts and Requests for Proposals,
invoicing, project related presentations, field visits, and miscellaneous duties as they arise. Included in the FY2006
budget was $50,000 for a historical benthic habitat mapping and change analysis of Charlotte Harbor. The project will
be similar to the effort completed for Tampa Bay in determining historical seagrass coverage from 1950s aerial
photography. This benthic habitat map will allow the District and the Charlotte Harbor National Estuary Program
(CHNEP) to refine goals being set for this system.
BenefitsThis project's support of the Charlotte Harbor SWIM Plan creates an opportunity for a cohesive effort between the
District, the CHNEP, and other state and local agencies to better implement resource management decisions and
restoration activities. Historically, SWIM projects have been eligible for state matching funds with the state funding 50
percent of the project costs and the District funding the remaining 50 percent. In FY2011, SWIM projects will be funded
100 percent by Basin Funds, specifically, the Peace River and/or Manasota Basin Boards, depending on the project
location within the Charlotte Harbor watershed.
Costs
The FY2009 and FY2010 ongoing costs for the Charlotte Harbor SWIM Plan Implementation were funded 12.5
percent from the Manasota Basin, 37.5 percent from the Peace River Basin, and 50 percent from the State SWIM
Program and include staff salary, travel and central garage. In FY2011, ongoing costs for the Charlotte Harbor SWIM
Implementation will be funded 25 percent from the Manasota Basin and 75 percent from the Peace River Basin. There
are no State SWIM Program funds available in FY2011.
Additional Information
In 1987, the Florida Legislature established the Surface Water Improvement and Management (SWIM) Act having
recognized that water quality and habitat in surface waters throughout the state have degraded or were in danger of
being degraded. The Act requires the five water management districts to maintain a priority list of water bodies of
regional or statewide significance within their boundaries, and develop plans and programs for the improvement of
those water bodies. To date, ten SWIM water bodies in the District have had plans developed and approved by the
state. Several plans have been updated one or more times as required by the Act. The Charlotte Harbor SWIM Plan
was first approved in 1993 and last updated in November 2000. Since the first plan, the District has initiated a number
of restoration and diagnostic assessment projects. Included within these are: 1) implementation of a water quality
monitoring program, 2) development of a pollutant loading model, 3) investigation of a resource-based pollutant load
reduction goal, 4) assessment of toxin levels, 5) identification of cumulative impacts to freshwater inflow reductions, 6)
seagrass mapping efforts, 7) various habitat restoration projects, and 8) involvement in numerous public outreach and
education activities.
021 - Manasota Basin 60
W501
SWIM Plan Implementation - Charlotte Harbor
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 96,733 0 88,816 7,058 859
021 Manasota Basin 37,281 0 29,606 6,899 776
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 66,027 0 66,027 0 0
State Trust Funds (SWIM) - Prior 2006 76,230 0 76,230 0 0
WMLTF (SWIM) - Prior Year Funds 1,634 0 0 0 1,634
$277,905 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. SWIM Plan Critical Project MilestonesNext Update of SWIM Plan 6/1/07 12/31/10
Status As Of: February 15, 2010
SWIM Plan Update:The last update of the SWIM Plan for Charlotte Harbor became effective in 2000. District staff
continue to work with the Charlotte Harbor National Estuary Program, the Florida Department of Environmental
Protection and local governments to implement projects in the 2000 Plan. The CHNEP completed the Comprehensive
Conservation and Management Plan in 2008 and are working on several key projects that will be useful in updating the
SWIM Plan. These include the establishment of seagrass targets, the calculation of nutrient loads and development of
numeric nutrient criteria. These are expected to be complete by mid 2010 and will be useful in the update to the District
SWIM Plan. District staff have completed the outline for the Charlotte Harbor SWIM Plan and have drafted the
Management Issues chapter of the document. Additionally, District staff have been in contact with FDEP regarding the
review and approval process for the Plan.
021 - Manasota Basin 61
W506
CHEC Charlotte Harbor/Lemon Bay SWIM Watershed Education
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply ConservationNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) Peace River, Manasota
Charlotte Harbor Environmental CenterCooperator(s)
Project Manager STERNBERGER, VIRGINIA
Task Manager(s)
Status Proposed
DescriptionThis Surface Water Improvement and Management project with the Charlotte Harbor Environmental Center provides
public involvement and water quality education opportunities to 4,300 residents in the Charlotte Harbor/Lemon Bay
watersheds. The program's goal is to foster a sense of stewardship and encourage actions that benefit the watershed
through focused education/outreach programs. The FY2011 program components include a volunteer water quality
monitoring program, estuary wading trips, water school workshop for local residents, community events, speaking
programs, estuary boat trips, hiking trips, develop and implement an Adopt-A-Pond program, reprint and distribution of
"Keep it Clean" Lemon Bay booklets, and reprint and distribution of "Watershed" Lemon Bay DVDs. Effectiveness will
be measured by number of participants, number of materials distributed, pre- and posttests and surveys.
BenefitsThe Peace River discharges into Charlotte Harbor, a SWIM priority water body and a designated "estuary of national
significance." The project fosters a sense of stewardship for the Peace River, Charlotte Harbor, Lemon Bay and
related freshwater resources through focused education opportunities for public participation and schools. The
program provides an opportunity for comparison of different areas within the Charlotte Harbor and Lemon Bay
watersheds. These programs are consistent with the District's watershed management and watershed education
initiatives. Education was named as a priority by the Manasota and Peace River basin boards. CHEC has the expertise
and experience to provide quality education in a variety of methods leading to increased knowledge and behavior
modificiation among participants.
Costs
The total proposed cost of the FY2011 project is $79,171, with the District requested to contribute $39,215 (Peace
River Basin Board $31,372, Manasota Basin Board $7,843). District funds will pay for materials and program
expenses. Each basin's share is based on anticipated work within that basin. The program is projected to reach 4,300
residents at a cost to the District of $9.12 per person. Although the cost per person is relatively high, the cost per
contact hour is 38 percent lower than average reflecting the hands-on and long-term nature of the program. The
budget lines below include costs for staff to manage the project.
Additional Information
The total cost of the FY2010 project was $89,446, with the District contributing $39,250. The District's share was split
between the Peace River Basin Board ($16,283), the Manasota Basin Board ($3,342) and State SWIM (19,625).
District funding was used for materials and program expenses. Each basin's share was based on work completed
within that basin. The program reached 4,230 residents at a cost to the District of $9 per person. The District has
supported this project since FY2000.
021 - Manasota Basin 62
W506
CHEC Charlotte Harbor/Lemon Bay SWIM Watershed Education
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 139,711 0 92,056 31,372 16,283
021 Manasota Basin 55,281 0 41,823 9,369 4,089
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 78,877 0 78,877 0 0
State Trust Funds (SWIM) - Prior 2006 76,737 0 76,737 0 0
WMLTF (SWIM) - Prior Year Funds 20,371 0 0 0 20,371
Project Funds Not Budgeted by the
District
Charlotte Harbor Environmental Center 211,115 0 136,159 39,956 35,000
$582,092 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2008 Budgeted FundsInitiate purchase order 10/1/07 10/31/07 10/31/07
First task report due 12/31/07 12/11/07
Second task report due 3/31/08 3/31/08
Third task report due 6/30/08 6/16/08
Fourth task report due 9/16/08 9/29/08 9/29/08
Project close 11/14/08 3/31/09 3/31/09
FY2009 Budgeted FundsInitiate purchase order 10/1/08 12/4/08 12/4/08
First task report 12/31/08 12/29/08
Second task report 3/31/09 3/31/09
Third task report due 6/30/09 6/30/09
Fourth task report due 9/30/09 9/30/09
Project close 11/20/09 11/20/09
FY2010 Budgeted FundsInitiate purchase order 10/12/09 11/24/09 11/24/09
First task report due 12/31/09 1/5/10 1/5/10
Second task report 3/31/10 2/11/10
Third task report 6/30/10
Fourth task report 9/15/10
Project close 9/30/10
FY2011 Budgeted FundsInitiate purchase order 10/1/10
First task report 12/31/10
Second task report 3/31/11
Third task report 6/30/11
Fourth task report 9/30/11
Project close 11/18/11
Status As Of: February 18, 2010
ACTION TO DATE: On time. To date, the following tasks have been completed on the FY2010 scope of work: one
volunteer water quality monitoring (VWQM) workshop (16 participants), four VWQM speaking sessions (26 participants),
four Journey through the Estuary boat trips (40 participants), two land-based hiking trips (23 participants), three wading
021 - Manasota Basin 63
W506
CHEC Charlotte Harbor/Lemon Bay SWIM Watershed Education
trips (39 participants), three speaking engagements (68 participants) and reprinted 1,000 copies of the Lemon Bay DVD.
021 - Manasota Basin 64
W509
Alligator Creek In-Stream Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Minimum Flows and Level Establishment and MonitoringFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
PECK, MICHAELTask Manager(s)
Status Proposed
DescriptionSarasota County is developing the Lemon Bay North Watershed Management Plan (L610) to protect and improve
water quality and restore natural systems throughout the watershed. The Lemon Bay Plan has identified several
in-stream restoration projects along Alligator Creek and nearby areas to address unstable conveyance systems that
are currently degrading water quality and impacting natural systems. The goal of this project is to achieve improved
water quality and increase natural habitat along Alligator Creek through the combined use of the following methods at
several project locations: (1) Stream bank re-sloping and restoration through removal of exotic vegetation and
replanting appropriate native wetland species of vegetation; (2) Incorporating the low impact design technique of
bioswales along the top of stream banks to reduce the velocity of overland flow of stormwater and protect natural
systems; and (3) Installation of weirs in select locations to provide increased residence time for wetland treatment
processes. The County began preliminary evaluations for several project locations in late FY2009. For FY2010 the
County has initiated preliminary designs and permitting for several proposed project elements with some construction
anticipated in late FY2010. District funds are requested for construction.
BenefitsThis project will improve surface water quality by reducing sedimentation and erosion by re-sloping the banks and
planting appropriate native vegetation. The installation of weirs at several locations will increase residence time and
thereby provide additional in-stream water quality treatment.
Costs
Current estimated project construction costs are estimated at $1,250,000 (not including staff salaries and travel
charges) but will be further refined during project design. For FY2009 Sarasota County has dedicated $200,000 to
fund preliminary design and permitting. For FY2010 the District budgeted $150,000 for the project. The District's
FY2010 share is split between the Manasota Basin Board ($75,000) and State SWIM ($75,000) with an equal match
from Sarasota County. For FY2011 the Manasota Basin Board is requested to fund $300,000 in construction costs.
Sarasota County's FY2011 funding contribution is expected to be $300,000. District funds shown in the table include
staff salaries, travel and central garage. If approved for future funding, the District's total contribution would be spread
over several fiscal years.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 382,520 0 0 303,806 78,714
District Budgeted - Outside Revenue
WMLTF (SWIM) - Prior Year Funds 78,713 0 0 0 78,713
Project Funds Not Budgeted by the
District
Sarasota County 800,000 150,000 200,000 300,000 150,000
$1,261,233 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 65
W509
Alligator Creek In-Stream Restoration
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionDevelop Draft Agreement with Sarasota County 10/30/09 3/31/10
Agreement to Contracts Administration 11/25/09 4/5/10
Execution of Agreement by Sarasota County 12/21/09 4/30/10
Execution of Agreement by SWFWMD 1/4/10 5/10/10
Notice to Proceed 1/5/10 5/10/10
2. Design & PermittingSubmit ERP Application 5/25/10
90% Plans Completed 7/30/10
ERP Permit Issued 9/15/10
3. ConstructionBegin Construction 2/1/10 9/30/10
End Construction 11/30/11
Status As Of: February 21, 2010
Sarasota County has selected an engineering consultant and has initiated preliminary evaluations and preliminary design
for instream restoration/improvements at several localities within the Alligator Creek basin. County and District staff have
visited all the proposed sites in late October - November 2009. Evaluation of preliminary design concepts is complete but
required more time than originally anticipated. Review of land ownership required modifications for several of the
proposed elements. Final Design and Permitting has begun and is anticipated to be complete by June 2010. Permit
review and issuance of permits is expected to take several months. The construction phase of the project is not
anticipated to begin until October 2010. The agreement between the District and Sarasota County is under internal
review. The agreement will cover the construction of the approved and permitted projects.
021 - Manasota Basin 66
W521
Charlotte Harbor Water Quality Monitoring
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Monitoring
Basin(s) Peace River, Manasota
Charlotte County, Florida Fish and Wildlife Conservation CommissionCooperator(s)
Project Manager SZAFRANIEC, MARY
KAUFMAN, KRISTask Manager(s)
Status Ongoing
DescriptionThis project is an ongoing SWIM Initiative to monitor water quality in Charlotte Harbor, a SWIM priority waterbody and
designated estuary of national significance. The purpose of the water quality monitoring is to establish a long-term
database of water quality conditions within the estuary to provide essential data for planning and management
purposes, such as implementation of the Charlotte Harbor SWIM Plan. The District began collecting and analyzing
monthly water quality samples from Charlotte Harbor in 1993. In 2000, the District worked with staff from Charlotte
County (County) and the Florida Fish and Wildlife Conservation Commission (FFWCC) to develop an implementation
plan for long-term water quality monitoring. As a result of these discussions, the District, County, and FFWCC agreed
to cooperatively monitor water quality in Charlotte Harbor. The District and the FFWCC are responsible for collection of
25 samples per month. The County is responsible for analyzing each sample for 11 water quality parameters, including
nutrients, color and turbidity. The District is responsible for estuarine water quality data compilation, quality
assurance/quality control, updates to a District approved database and upload of the data to the State's STOrage and
RETrieval (STORET) database. Internet publication of the data for this project are completed under W547.
BenefitsThe project created a multi-agency cooperative effort that provides a long-term water quality dataset to assist in
establishing the health of the Charlotte Harbor study area and provide information on changes in water quality.
Costs
The FY2010 project budget is $38,250. The proposed FY2011 project budget is $38,250, of which Peace River Basin
Board is funding $28,688 and Manasota Basin Boards is funding $9,562. District funds shown in the table include staff
salaries.
Additional Information
Charlotte Harbor is generally viewed as one of the most productive estuarine systems in southwest Florida. Although it
is appropriately considered a healthy system, problems exist in the areas of hydrologic alterations, water quality
degradation, and habitat loss. The SWIM Plan for Charlotte Harbor focus on management strategies for the Peace
and Myakka Rivers, in addition to Charlotte Harbor proper, to reduce point and non-point source pollution and to
preserve and restore habitat. The objectives of this project are consistent with these strategies. This coordinated effort
involves two separate agreements: 1) an agreement between the District and the County outlining responsibilities of
both parties but does not involve the transfer of funds, and 2) an agreement between the District and the FFWCC
outlining sampling services and reimbursement rates for water quality monitoring.
021 - Manasota Basin 67
W521
Charlotte Harbor Water Quality Monitoring
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 220,663 0 154,711 42,037 23,915
021 Manasota Basin 77,674 0 51,572 17,123 8,979
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 90,165 0 90,165 0 0
State Trust Funds (SWIM) - Prior 2006 193,296 0 174,171 0 0
WMLTF (SWIM) - Prior Year Funds 3,768 0 0 0 3,768
$585,566 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesDraft Agreement to Contracts 12/31/00 11/21/00
Basin Board Approval of Agreement 4/30/01 12/13/00
Governing Board Approval of Agreement 4/30/01 12/19/00
Contract Executed 5/1/01 5/7/01
First Water Quality Monitoring Event 5/12/01 5/12/01
Notice to Proceed 6/1/01 5/9/01
FFWCC First Amendment to Contracts Management 3/26/04 4/2/04
FFWCC First Amendment Fully Executed 5/31/04 9/27/04
Charlotte County First Amendment Fully Executed 3/30/05 3/30/05
FFWCC Second Amendment to Contract Fully Executed 5/22/07 5/22/07
Charlotte County Second Amendment Fully Executed 3/26/08 4/28/08
1. Critical Project MilestonesFFWCC Third Amendment Initiation 8/31/10
FFWCC Second Amendment Expires 11/30/10
Charlotte County Third Amendment Initiation 12/28/10
Charlotte County Second Amendment Expires 3/31/11
Status As Of: March 08, 2010
A second amendment to the original agreement was executed in May 2007 with the FFWCC. A second amendment to
the original with Charlotte County was executed on April 28, 2008. These amendments allow for an additional three-year
"No Cost Time Extension" extending each party's committment to the project through March 31, 2011. Currently, the
Charlotte Harbor Environmental Center (CHEC) is presenting the results of these efforts on its website,
http://www.checflorida.org, allowing the public to view results in terms of both status and trends in water quality. CHEC
submitted the second and third quarterly reports, and the final report and invoices. For FY2010, $10,000 of the remaining
funds from project W547 is being used for data management under a separate purchase order with Benchmark Labs as
part of this project.
021 - Manasota Basin 68
W526
Charlotte Harbor National Estuary Program
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Peace River, Manasota
Cooperator(s)
Project Manager GARCIA, LIZANNE
POWERS, STEPHANIE, KAUFMAN, KRIS, GARCIA, LIZANNETask Manager(s)
Status Ongoing
DescriptionThis proposed project provides for the funding of the Annual Workplan for the Charlotte Harbor National Estuary
Program (CHNEP). The District participates in three main areas. First the District's SWIM program, usually funded by
the basin boards and State, carries out the projects that will address water quality and habitat restoration within the
Harbor. Second, the District has contributed annual funding to the CHNEP since 1997 to carry out the administration
and implement of projects identified in the CHNEP Comprehensive Conservation and Management Plan. And finally,
the District provides staff to sit on the technical, management and policy (Governing or Basin Board member)
committees of the program. The District's annual budget includes funding support to the CHNEP and District staff
salaries, travel and central garage to administer the project, which includes attending board meetings and other
workshops and invoicing.
BenefitsThis project support of the CHNEP creates an opportunity for a cohesive effort between the District, CHNEP and other
state and local agencies to implement resource management decisions and restoration activities. Additionally, this
project provides for leveraging funding between the partners. Projects contained within the CHNEP Annual Workplan
address management issues concerning hydrologic alterations, water quality degradation, and habitat loss within the
Peace and Myakka River watersheds and the Charlotte Harbor estuary.
Costs
The District has provided funding to the CHNEP on an annual basis since 1997. The District's annual funding
commitment for the CHNEP is $110,000. Prior to FY2011, the District share was split between the Manasota Basin
Board (12.5%) and the Peace River Basin Board (37.5%) and State SWIM funds (50%). In FY2011, the District's
proposed share of $110,000 will be funded 25% ($27,500) by the Mansota Basin Board and 75% ($82,500) by the
Peace River Basin Board. District funds are used to implement projects outlined in the Annual Workplan. District funds
shown in the table include staff salaries.
Additional Information
In 1987, the Florida Legislature established the Surface Water Improvement and Management (SWIM) Act, having
recognized that water quality and habitat in surface waters through out the state have degraded or were in danger of
being degraded. The Act requires the District to maintain a priority list of waterbodies of regional or statewide
significance within their boundaries. Charlotte Harbor is designated as a priority waterbody. Charlotte Harbor was
identified by the United States Environmental Protection Agency (USEPA) in 1995 as an estuary of Federal
Significance and subsequently included in the National Estuary Program. As a result of this designation, the Charlotte
Harbor National Estuary Program was established to assist the region in developing a comprehensive plan for the
restoration and protection of Charlotte Harbor. Partners in the CHNEP include the Southwest Florida and South
Florida Water Management Districts, USEPA, Florida Department of Environmental Protection, other state and federal
agencies, and local governments from the watershed. The goals and strategies for the Harbor are identified in the
Comprehensive Conservation and Management Plan (CCMP) for Charlotte Harbor which provides guidance to each
entity on their contribution to restore the Harbor. Since 1993, the District has completed several habitat restoration
projects and diagnostic assessments, including seagrass mapping, water quality monitoring, and development of a
pollutant load reduction goal for the Harbor.
021 - Manasota Basin 69
W526
Charlotte Harbor National Estuary Program
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 493,350 0 364,032 85,592 43,726
021 Manasota Basin 167,933 0 121,343 30,425 16,165
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 239,574 0 239,574 0 0
State Trust Funds (SWIM) - Prior 2006 368,701 0 368,701 0 0
WMLTF (SWIM) - Prior Year Funds 59,891 0 0 0 59,891
Project Funds Not Budgeted by the
District
CHNEP 1,307,725 0 1,197,725 0 110,000
$2,637,174 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2007 Annual Workplan Critical Project MilestonesFY2007 Contract with CHNEP Executed 4/1/07 6/11/07
FY2007 Contract Close Out 12/31/09
FY2008 Annual Workplan Critical Project MilestonesFY2008 Contract with CHNEP Executed 12/1/07 8/26/08
FY2008 Contract Close Out 12/31/10
FY2009 Annual Workplan Critical Project MilestonesFY2009 Contract with CHNEP Executed 12/1/08 12/18/09
FY2009 Contract Close Out 12/31/11
FY2010 Annual Workplan Critical Project MilestonesFY2010 Contract with CHNEP Executed 2/1/10 2/23/10
FY2010 Contract Closeout 12/31/12
Status As Of: February 17, 2010
FY2007 Contract: The FY2007 Agreement was executed on 6/11/2007 and expires 12/31/2009. All projects have been
completed except the pre-development mapping project which spans the FY2007 and FY2008 contracts. The CHNEP
has indicated that they would not submit invoices for this project until completion of the project and the District has
accepted the final deliverable. The District has reviewed interim deliverables for this project and found them to be
acceptable. A draft G-2 has been submitted to encumber the remaining $20,000 under this agreement. FY2008 Contract:
The FY2008 agreement was executed in 08/2008 and expires 12/31/2010. Projects include refinement of water quality
targets and pre-development vegetation mapping in the CHNEP watershed. District staff have reviewed draft
deliverables for the water quality targets report and participated in meetings for this project. As stated above, the
pre-development vegetation map project is progressing and is expected to be complete by 12/31/2010. FY2009 Contract:
The FY2009 agreement was executed on December 13, 2009 and expires 12/31/2011. Projects include fisheries
monitoring in Lemon Bay, additional work by Mote Marine Laboratory to evaluate light attenuation by algae attached to
seagrass (epiphytes), setting seagrass targets and finalizing the water quality targets necessary to maintain seagrass
health. District staff have been participating in the development of the scope of work and subsequent development of
seagrass targets. A final draft report for water quality targets is expected by mid-February. FY2010 Contract: The
FY2010 agreement is routing for District review. Projects include an update of the triennial status and trends for water
quality throughout the CHarlotte Harbor watershed, staff support and the development of estuaring nutrient criteria.
Management Conference: The Management and Policy Committees met in February 2010. Items on the agenda of
interest to the District included updates on numberic nutrient criteria development, water quality targets and climate
change.
021 - Manasota Basin 70
W528
Myakka River Water Quality Monitoring
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Monitoring
Basin(s) Manasota
Cooperator(s)
Project Manager KAUFMAN, KRIS
WOLDEN, CATHERINETask Manager(s)
Status Ongoing
DescriptionThis project is an ongoing SWIM Initiative to monitor the water quality of the Myakka River. In 1996, a SWIM
watershed assessment project for Charlotte Harbor found that in order to make sound management decisions, water
quality monitoring was needed in the Peace and Myakka river basins. The District participated in a multi-agency
cooperative effort to monitor the Myakka River in 1999. It was determined a long term effort was needed to
characterize water quality conditions and pollutant loadings in the river system. The current project began in 2000 and
funding for this project will be used to continue the monthly water quality monitoring program at six United States
Geological Service (USGS) stream stations on the Myakka River. The data from this project will be used in conjunction
with streamflow measurements provided by an existing USGS program to estimate monthly pollutant loading at the six
gauge sites (See W554 & W547). Partners in this project include the Charlotte Harbor National Estuary Program and
the Charlotte Harbor Environmental Center (CHEC). Currently, CHEC is presenting results of this effort on its website,
www.checflorida.org (See W547).
BenefitsThis data will be used to develop future water quality improvement projects as needed. The project's data is regularly
used to create publications such as, "Water Quality Conditions and Pollutant Loads and Yields in the Peace and
Myakka River Basins" (See W554). Ongoing projects such as the Myakka River Watershed Initiative will benefit from
use of the ongoing long term data set.
Costs
The proposed FY2011 costs for this project are funded from the Manasota Basin Board. The funds are for the
District's Water Quality Monitoring Program (WQMP) staff to collect samples and the District Laboratory to analyze the
samples. District funds shown in the table include staff salaries.
Additional Information
The Myakka River discharges into Charlotte Harbor, a SWIM priority waterbody and a Charlotte Harbor National
Estuary Program (CHNEP) designated "estuary of national significance." Charlotte Harbor is generally viewed as one
of the most productive estuarine systems in Southwest Florida. Although it is appropriately considered a healthy
system, problems exist in the areas of hydrologic alterations, water quality degradation, and habitat loss. The SWIM
Plan for Charlotte Harbor focus on management strategies for the Peace and Myakka Rivers, in addition to Charlotte
Harbor proper, to reduce point and non-point source pollution and to preserve and restore habitat. The objectives of
this project are consistent with these strategies. The District began water quality monitoring projects along the Peace
and Myakka Rivers in 2000 (See W527). Since 2001, the District has also supported sampling in the tidal portions of
the Peace and Myakka Rivers by the Florida Fish and Wildlife Conservation Commission (FFWCC) (See W521).
021 - Manasota Basin 71
W528
Myakka River Water Quality Monitoring
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 172,836 0 89,206 57,877 25,753
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 45,032 0 45,032 0 0
State Trust Funds (SWIM) - Prior 2006 66,262 0 66,262 0 0
WMLTF (SWIM) - Prior Year Funds 25,753 0 0 0 25,753
$309,883 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesFirst Sampling Event 10/5/00 10/5/00
1. Critical Project MilestonesFY2008 Monthly Sampling Completed 9/30/08 9/30/08
FY2009 Monthly Sampling Completed 9/30/09 9/30/09
FY2010 Monthly Sampling Completed 9/30/10
Status As Of: March 02, 2010
Water quality sampling is ongoing. Samples have been collected from October 2000 through February 2010. Field data
has been submitted to the laboratory for inclusion into their database through June 2009.
021 - Manasota Basin 72
W552
Sarasota County Pollutant Model Development
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
GARCIA, LIZANNETask Manager(s)
Status Ongoing
DescriptionThis project involves developing a pollutant loading model to be used to assess pollutant loading to Sarasota County
surface waters. This project includes the following activities: inventory existing land uses and best management
practices (BMP) facilities by watershed sub-basin and incorporate information within GIS feature classes; inventory
hydrologic input data by watershed sub-basin for model documentation; characterize wet season and dry season
runoff volume input data by watershed sub-basin for model verification; develop models by watershed through
expanding input data with the above criteria; process model results for tabulating wet season and dry season pollutant
loading summary; create model/mapping geodatabase for future County application needs; and perform field sampling
within each bay watershed for use in model validation. The model is expected to discern the portion of water clarity
conditions (chlorophyll, color, and suspended solids) that are caused by human activities rather than those caused by
weather or climatic events.
BenefitsThe pollutant load model will generate monthly loads based on daily rainfall data enabling a correlation to be made
between the monthly loads and the ongoing monthly bay water quality data that can then be used to propose
alternative chlorophyll criteria to the Florida DEP for Sarasota County bays. In addition, this model will provide the
detail and reliability needed for local support of legitimate TMDL program load reductions. Also, as more sampling data
is incorporated, the model will become more reliable to justify (via a cost-benefit analysis) the appropriate project in the
proper location that will provide an improvement in water quality.
Costs
The original total project cost was $1,725,814, with the District's share $862,907 and the County's share $862,907,
funded over two fiscal years FY2006 and FY2007. The District budgeted $431,907 in FY2006 with the Manasota Basin
Board providing $215,954 and the State SWIM fund providing $215,953. Sarasota County provided $431,907 for
FY2006. Funding for FY2007 included $431,000 from the District with the Manasota Basin Board providing $215,500
and the State SWIM fund providing $215,500. For FY2007 Sarasota County was to provide $431,000. However, on
March 2, 2007 the County indicated it wished to withdraw the request for FY2007 funding. The revised total project
cost is now $863,814. FY2007 funds budgeted by the District will be released to the basin's budget. The current
agreement funded with FY2006 funds will complete the current project scope. The District funding amounts listed in
the table include staff salaries, travel and central garage charges.
Additional Information
Potential model outputs and design features will be reviewed by the Technical Advisory Committee of the Sarasota
Bay Estuary Program. The model will guide the County's and District's management activities associated with water
quality for the systems noted above. The proposed pollutant loading model can be used in conjunction with outputs
from the existing hydrologic and hydraulic stormwater model to produce event specific pollutant loads.
021 - Manasota Basin 73
W552
Sarasota County Pollutant Model Development
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 447,618 0 442,795 4,823 0
District Budgeted - Outside Revenue
Ecosystem Trust Fund - Sarasota Pollut
(SWIM)
200,000 0 200,000 0 0
State Trust Funds (SWIM) 242,793 0 242,793 0 0
Project Funds Not Budgeted by the
District
Sarasota County 431,907 0 431,907 0 0
$1,322,318 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionContract Executed 5/15/06 5/31/06
Notice to Proceed Sent 5/31/06 5/31/06
First Ammendment Approved - Time Extension 6/15/07 6/6/07
2. Critical Project MilestonesDraft Verification Monitoring Plan 12/10/06 2/10/07 1/30/07
Draft Model Design Memorandum 1/10/07 7/15/07 7/15/07
Final Verification Monitoring Plan 3/30/07 7/30/07 7/30/07
Final Model Design Memorandum 4/30/07 9/30/08 10/30/08
Draft Model Operation Manual 10/30/07 1/30/09 1/30/09
Final Functional Model 11/30/07 6/15/09 6/15/09
Final Model Operation Manual/Final Report 12/15/07 5/25/09 6/15/09
No-Cost Time Extension Approved 1/10/09 3/30/09 1/30/09
No-Cost Time Extension Approved 2/5/10 2/12/10
2. Critical Project MilestonesContract Expiration 8/31/11
Status As Of: March 19, 2010
Final model calibration including review of hydrology and water quality modules is complete. The SIMPLE model
installation files have been made available for model runs. Final calibration of the water quality module was completed in
early 2009; however, data reviews noted inconsistencies in the values reported. Further inspection revealed stormwater
samples collected were not flow-weighted, therefore they are not suitable for use to develop EMCs (Event Mean
Concentrations) for pollutants of interest. Established literature values for EMCs were used for model simulations and
calibration. Currently, the model is fully operational. Project team members met for model discussions and reviews, in
particular the absence of flow-weighted samples. Additional time for final model calibration and testing was deemed
necessary. Likewise, additional time was needed to subsequently draft the final project report. Sarasota County has
requested a no-cost time extension to the agreement. The District concurred with the request and has approved an
amendment to the agreement to extend the contract termination date to August 31, 2011. Additional time will allow the
County (through its consultant) to conduct new storm sampling to develop data suitable for incorporation into the model.
The new sampling will be conducted over a series of storm events at no additional project cost. Project team members
have selected sampling localities and will be viewing the sampling installations in late March 2010.
021 - Manasota Basin 74
W558
Venice Hatchett Creek Stormwater Facility
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Emergency Flood ResponseNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
City of VeniceCooperator(s)
Project Manager NORTON, NANCY
Task Manager(s)
Status Ongoing
DescriptionThis multi-year funded project was originally funded in FY2008 by the City of Venice, which is the lead agency for
implementing the stormwater retrofit and habitat restoration goals of this effort. The project is associated with the
implementation of Best Management Practices (BMPs) for the City's Hatchett Creek Basin Master Plan and the
Sarasota County unified local mitigation strategy. This project includes the following tasks: land acquisition, design,
development of construction documents, construction permitting, bidding and contractor selection, and construction
engineering and inspection during construction of the BMPs. In 2007, the City purchased a 1.33 acre parcel at 1155
US 41 Bypass South, to be converted to a stormwater pond to provide additional storage and water quality treatment
for a 16.6 acre drainage area. The BMP will address water quality improvements, stormwater management level of
service deficiencies and natural systems restoration along approximately 200 linear feet of intertidal shoreline of
Hatchett Creek.
BenefitsCompletion of this project improves stormwater quality prior to discharging into Hatchett Creek, restores approximately
200 linear feet of intertidal shoreline, and will provide an increased stormwater management level of service on East
Venice Avenue and neighboring areas.
Costs
The total project cost is $1,850,000, and the requested District share is $300,000 ($150,000 from the Manasota Basin
Board and $150,000 from State SWIM), of which $150,000 was requested in FY2008 for design and construction and
$150,000 in FY2009 for construction. The City of Venice purchased a 1.33 acre parcel in 2007 for $1,250,000 and the
District funds match the City funding for design and construction. District funds shown in the table include staff
salaries.
Additional Information
This project is located within the geographic boundaries of the Charlotte Harbor National Estuary Program and the
Charlotte Harbor SWIM Plan. Charlotte Harbor is generally viewed as one of the most productive estuarine systems in
Southwest Florida. Although it is appropriately considered a healthy system, problems exist in the areas of hydrologic
alterations, water quality degradation, and habitat loss. The SWIM Plan for Charlotte Harbor focus on management
strategies for the Peace and Myakka Rivers, in addition to Charlotte Harbor proper, to reduce point and non-point
source pollution and to preserve and restore habitat. Charlotte Harbor is a District priority Surface Water Improvement
and Management (SWIM) program waterbody and is considered an "estuary of national significance" with the
establishment of the Charlotte Harbor National Estuary Program (CHNEP). Water quality data and seagrass mapping
efforts suggest that Charlotte Harbor's water quality is not degrading, and its fisheries' habitats are mostly stable.
However, data collected since its SWIM designation in 1993 indicate the system experiences annual algae blooms
that appear to be related to elevated nutrient concentrations. The Hatchett Creek Stormwater Facility project is
consistent with the water quality improvement goals of the District's SWIM Plan for Charlotte Harbor and the Charlotte
Harbor National Estuary Program's CCMP. The City will manage the project and the District project manager must
approve any agreements to accomplish project tasks.
021 - Manasota Basin 75
W558
Venice Hatchett Creek Stormwater Facility
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 155,799 0 151,702 3,052 1,045
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 151,701 0 151,701 0 0
WMLTF (SWIM) - Prior Year Funds 1,045 0 0 0 1,045
Project Funds Not Budgeted by the
District
City of Venice 1,650,000 0 1,650,000 0 0
$1,958,545 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Contract Development and ExecutionDraft Agreement sent to Management Services 1/29/08 2/7/08
Draft Agreement returned from Management Services 2/20/08 3/11/08
Agreement sent to Cooperator 2/27/08 3/12/08
Signed Agreement returned from Cooperator 3/27/08 4/11/08
Agreement fully executed 4/10/08 4/21/08
Notice to Proceed 4/15/08 4/25/08
Critical Project MilestonesComplete Design and Permitting 4/25/09 3/20/09
Bidding and Contractor Selection 7/25/09 9/1/09 9/27/09
Building Demolition 9/25/09 1/9/09
Commence Construction 11/25/09 12/31/09 2/23/10
Complete Construction 8/25/10
Contract Close-Out 10/25/10
Construction Contract Termination 12/25/10
Agreement Expiration 3/25/11
Status As Of: February 24, 2010
The City of Venice completed building demolition for the project site in January 2009, 8 months ahead of schedule. The
City completed design and received an environmental resource permit (ERP) from SWFWMD for the proposed work
March 20, 2008. Due to escalating construction costs, the City requested and has received additional funding from
FEMA. On May 27, 2009 the City provided 100% plans to the District and is currently finalizing the specifications and bid
documents for this project. The cooperator requested approximately 40 days of additional time to extend milestones for
bidding and contractor selection and for commence construction due to delays associated with acquiring FEMA funding.
The City has combined design of this project, Hatchett Creek Stormwater Facility, with design of L624, Implementation of
BMP's Hatchett Creek. The City opened bids November 17, 2009. Bid responses required a public meeting to determine
bid award recommendation. ACTION TO DATE: The City issued a notice to proceed to the Contractor on February 23,
2010. The construction contract allows 210 days to complete construction which is within the project timeframe.
021 - Manasota Basin 76
W559
Assessment of 2008 Seagrass Maps in Charlotte Harbor And Lemon
BayProject Type SWIM
AORs Strategic InitiativesNatural Systems Natural Systems Identification and Monitoring
Basin(s) Peace River, Manasota
Charlotte Harbor Environmental CenterCooperator(s)
Project Manager KAUFMAN, KRIS
Task Manager(s)
Status Ongoing
DescriptionThis FY2009 SWIM cooperative funding project will assess the accuracy of mapping classifications used in the
District's ongoing Biennial Seagrass Mapping Project (See W331). This effort will supplement the District's well
established accuracy assessment of the maps. While the District assesses the project's ability to correctly identify the
presence of seagrass, the cooperative funding project will conduct a more in-depth evaluation of the mapping
categories: patchy seagrass, continuous seagrass, and tidal flat. Estimates of inter-annual change in seagrass habitat
based on aerial photos finds little change between habitat classes during the past nearly 20 years of study. However, a
recent analysis of more localized data from the Florida DEP seagrass transect data (CHEC 2006) found decreases in
abundance and distribution of seagrasses around Charlotte Harbor and Lemon Bay. Furthermore, of the quadrats
sampled by DEP that occurred in tidal flat polygons, most did contain some seagrass, some up to 25% coverage. The
following tasks regarding the 2008 seagrass maps produced by the District for the Charlotte Harbor and Lemon Bay
segments are proposed for this project: 1. assess map accuracy by defining spatial variability of seagrass abundance
in classified polygons using variation in percent cover by seagrass in square-meter quadrats; 2. quantify seagrass
abundance in classified polygons using percent cover by seagrass in square-meter quadrats; 3. describe abundance
and distribution of seagrass at its deepest depth of occurrence to verify map estimates of deep edge/maximum depth
of distribution of seagrass species. The public will be able to access all data via www.checflorida.org.
BenefitsThis project will provide the District and end users of District seagrass maps with new highly detailed information on
the accuracy of classifying seagrass as patchy or continuous. The District, county governments, and Estuary Programs
will be able to use the data in ongoing water quality/water clarity target setting and other resource protection projects.
Costs
The FY2009 project cost is $40,000, with CHEC and the District each contributing half ($20,000). The District share is
split between Peace River and Manastoa Basin Boards ($5,000 each) and State SWIM ($10,000).
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 6,111 0 5,402 0 709
021 Manasota Basin 6,111 0 5,402 0 709
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 10,802 0 10,802 0 0
WMLTF (SWIM) - Prior Year Funds 1,418 0 0 0 1,418
Project Funds Not Budgeted by the
District
Charlotte Harbor Environmental Center 20,000 0 20,000 0 0
$44,442 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 77
W559
Assessment of 2008 Seagrass Maps in Charlotte Harbor And Lemon
Bay
Critical Project Milestones ActualProjected Amended
1. Contract Development and ExecutionFinalize scope of work and process purchase order 10/1/08 12/31/08 1/21/09
Notice to Proceed 10/5/08 1/21/09
Purchase Order Termination 9/30/09 12/31/09
2. Critical MilestoneProject Kick Off Meeting 10/15/08 1/9/09 1/9/09
Field Work Commenced 4/15/09 1/26/09 1/26/09
First Progress Report 6/15/09 1/30/09 3/27/09
2. Critical MilestoneSecond Progress Report 2/27/09 6/5/09 6/5/09
Third Progress Report 3/27/09 6/5/09 6/5/09
Draft Final Report 5/29/09 8/24/09
Final Report 6/26/09 9/21/09
Status As Of: March 02, 2010
The project scope of work was finalized and submitted on December 31, 2008. A purchase order with attached scope
was opened. District and CHEC staff held a project meeting January 9, 2009 to discuss project scheduling and project
design. Field work for the District's classification accuracy assessment was completed April 2009. District and cooperator
staff met June 4, 2009 to discuss project progress and final report formatting. The purchase order and associated scope
of work were revised for time extensions of project milestones. After discussions with CHEC staff and contracted staff, it
was agreed that tasks left uncompleted under the purchase order at this time cannot be finished due to the time
sensative nature of the proposed work. Deliverables for completed tasks have been recieved and paid for by the District.
The District project manager, Finance Department, and CHEC determined the purchase order should be closed with the
remaining balance of the project funds be balanced foward.
021 - Manasota Basin 78
W601
SWIM Plan Implementation - Sarasota Bay
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota County, Manatee County, Sarasota Bay Estuary ProgramCooperator(s)
Project Manager GARCIA, LIZANNE
POWERS, STEPHANIE, KAUFMAN, KRISTask Manager(s)
Status Ongoing
DescriptionThis project provides for the administration and implementation of projects as outlined in the SWIM Plan for Sarasota
Bay. Administration and implementation includes assessment of implementation progress, a review and refinement of
the Pollutant Load Reduction Goal (PLRG) for the waterbody, periodic SWIM Advisory Committee meetings, new
project development (rationale and justification), development of relevant contracts and Requests for Proposals,
invoicing, project related presentations, field visits, and miscellaneous duties as they arise.
BenefitsThis project's support of the Sarasota Bay SWIM Plan creates an opportunity for a cohesive effort between the District,
and other state and local agencies to better implement resource management decisions and restoration activities.
Historically, SWIM projects have been eligible for state matching funds with the state funding 50 percent of the project
costs and the District funding the remaining 50 percent. In FY2011, all projects within the Sarasota Bay SWIM
watershed will be funded 100 percent by the Manasota Basin Board as no State SWIM funds will be available.
Costs
The FY2009 and FY2010 ongoing costs for the Sarasota Bay SWIM Plan Implementation were funded 50 percent
from the Manasota Basin and 50 percent from the State SWIM Program and include staff salary, travel and central
garage. In FY2011, ongoing costs for the Sarasota Bay SWIM Implementation will be funded 100 percent from the
Manasota Basin. There are no State SWIM Program funds available in FY2011.
Additional Information
In 1987, the Florida Legislature established the Surface Water Improvement and Management (SWIM) Act having
recognized that water quality and habitat in surface waters throughout the state have degraded or were in danger of
being degraded. The Act requires the five water management districts to maintain a priority list of water bodies of
regional or statewide significance within their boundaries, and develop plans and programs for the improvement of
those water bodies. To date, ten SWIM water bodies in the District have had plans developed and approved by the
state. Several plans have been updated one or more times as required by the Act. The Sarasota Bay SWIM Plan was
first approved in 1997 and last updated in 2002. Since the first plan, the District has initiated a number of restoration
and diagnostic assessment projects. Included within these are: 1) investigation of toxic loading sources to the Bay, 2)
seagrass mapping 3) habitat restoration, 4) development of stormawater master plans 5) various habitat restoration
projects, 6) construction of artificial reefs and oyster reefs and 7) involvement in numerous public outreach and
education activities.
021 - Manasota Basin 79
W601
SWIM Plan Implementation - Sarasota Bay
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 275,935 0 263,022 8,666 4,247
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 24,218 0 24,218 0 0
State Trust Funds (SWIM) - Prior 2006 358,202 0 358,202 0 0
WMLTF (SWIM) - Prior Year Funds 4,247 0 0 0 4,247
$662,602 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesLast Update of Plan 6/7/97 6/7/97
Initiate Update of Plan 4/1/02 4/1/02
Obtain FDEP Approval of Plan Update 9/2/02 12/20/02
Initiate Next Update of Plan 1/1/09 1/1/12
Status As Of: December 21, 2009
The last update for the SWIM Plan for Sarasota Bay became effective in December 2002. District staff continue to work
with local governments and the Sarasota Bay Estuary Program (SBEP) to implement projects identified in the 2002 Plan.
Status of activities implemented with the SBEP are provided under project number W612. Additionally, Sarasota County
is working on projects to establish water clarity and other resource management targets for the segments of Sarasota
Bay. Currently the District is cooperating in this effort through the Lemon Bay and Roberts Bay Watershed Plans (L610
and L611). For FY2009, Sarasota County submitted cooperative funding applications for Sarasota Bay (W621) and Little
Sarasota Bay (W622) Water Quality Management Plans which will be key in updating the SWIM Plan. These two
projects are scheduled to be complete in 2012. The SBEP has begun its update of the Comprehensive Conservation and
Management Plan (CCMP) for the Bay and this plan should include water quality targets. District staff will participate in
this process and this and the above mentioned projects will be useful in the future update to the SWIM Plan and the
SBEP's CCMP. The next update of the SWIM plan is contingent upon the progress of these projects. Updates for these
projects are included under the individual project numbers. This will be the last update under this write-up until a revised
timeline is developed for the SWIM plan based on the progress of the pending projects.
021 - Manasota Basin 80
W602
Neal Preserve Environmental Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager POWERS, STEPHANIE
Task Manager(s)
Status Ongoing
DescriptionThis project is in response to a cooperative funding request from Manatee County to restore and enhance habitat on
119 acres of intertidal wetlands and uplands in west central Manatee County. The land was purchased in July 2005 by
Manatee County for $9 million. The proposed restoration will target the creation and enhancement of open water,
intertidal habitats, and coastal uplands. Exotic plants such as Australian Pine and Brazilian Pepper will be removed
and replaced with both planted and naturally recruiting native species. Under the current agreement, the County is
responsible for managing the construction contract and will be responsible for the long-term operation and
maintenance of the site. The District is providing project management overview of construction progress.
BenefitsUpon completion, the project will provide significant benefits to habitat through the removal of exotic plant species and
replanting of native vegetation. Hydrologic alterations will also improve the habitat and water quality of the site and
provide limited stormwater treatment of waters entering Tampa Bay and Sarasota Bay. Because the project site drains
to both Tampa Bay and to Sarasota Bay, this project will benefit both systems.
Costs
The total project cost is $9,650,000. The District's contribution is $500,000, which is being split 50/50 between the
Manasota Basin Board ($250,000) and State funds ($250,000). Manatee County is matching the District's contribution
with $9 million used for the land purchase. District funds will be used for the construction phase of the project. District
funds shown in the table include staff salaries.
Additional Information
Since 1950, approximately 50 percent of Tampa Bay's natural shoreline and approximately 40 percent of Sarasota
Bay's intertidal wetland habitat has been lost due to development and reduction in water quality. This resulted in a
decline in the aesthetic, recreational, and commercial value of the bay, as well as a loss of habitat for native plants
and animals. The SWIM Plans for Tampa Bay and Sarasota Bay outline goals to restore habitat throughout the bay
areas and reduce pollutant loads entering the bays. The objectives of this project are consistent with these goals.
021 - Manasota Basin 81
W602
Neal Preserve Environmental Restoration
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 334,792 0 330,751 2,696 1,345
District Budgeted - Outside Revenue
Ecosystem Trust Fund - Sarasota Bay
Rstr (SWIM)
250,000 0 250,000 0 0
State Trust Funds (SWIM) 80,749 0 80,749 0 0
WMLTF (SWIM) - Prior Year Funds 1,345 0 0 0 1,345
Project Funds Not Budgeted by the
District
Manatee County 9,000,000 0 9,000,000 0 0
$9,666,886 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development and ExecutionDraft Agreement to Management Services 5/14/07 7/5/07
Draft Agreement returned from Management Services 6/4/07 8/22/07
Agreement to Cooperator 6/8/07 8/24/07
Signed Agreement from Cooperator 7/9/07 10/23/07
Agreement Fully Executed 7/26/07 10/31/07
Notice to Proceed 8/1/07 11/6/07
2. Project TasksCompletion of Design and Permitting 10/31/08 7/31/10
Construction Complete 12/31/09 7/31/11
3. Agreement Expiration DatesContract Expiration 12/31/08 12/31/11
Status As Of: March 02, 2010
The County put this project on hold for an extended period of time. An amendment to the original agreement was drafted
to extend the expiration date and is currently in Management Services for review.
021 - Manasota Basin 82
W603
Ungarelli Preserve
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager POWERS, STEPHANIE
Task Manager(s)
Status Ongoing
DescriptionThis project is in response to a request from Manatee County to restore and enhance approximately 10 acres of
intertidal wetland and upland habitat along the Manatee River. The Ungarelli Preserve is a 35-acre site that was
purchased in 2008 by Manatee County. The proposed plan targets the restoration of degraded salt marsh habitat and
associated coastal maritime forest on adjacent hummocks through nuisance and exotic species eradication and
supplemental native plantings. The County will be the lead agency for the project. The District will provide project
management oversight of design and construction progress.
BenefitsUpon completion, the project will provide significant benefits to habitat and water quality. The County also plans to
provide passive recreational and educational opportunities to the public.
Costs
The total project cost is approximately $250,000, which includes $150,000 for land acquisition. The District's FY2010
contribution is $50,000. At their April 2009 meeting, the Manasota Basin Board approved amending its FY2009 budget
to include reallocated State SWIM funds to cover 50 percent ($25,000) of the FY2010 costs. The remaining costs
($25,000) are funded by the Manasota Basin Board. The County fully funded the land purchase in 2008 and will use
the land as a match to District funding. District funds shown in the table include staff salaries.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plans for Sarasota Bay outline goals to
restore habitat throughout the bay areas and reduce pollutant loads entering the bays. The objectives of this project
are consistent with these goals.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 29,213 0 0 2,328 26,885
District Budgeted - Outside Revenue
Ecosystem Trust Fund - SWIM Prior
Year Funds
25,000 0 0 0 25,000
WMLTF (SWIM) - Prior Year Funds 1,885 0 0 0 1,885
Project Funds Not Budgeted by the
District
Manatee County 150,000 0 0 100,000 50,000
$206,098 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 83
W603
Ungarelli Preserve
Critical Project Milestones ActualProjected Amended
Contract Development and ExecutionReceive Scope of Work from Cooperator 9/16/09 10/29/09
Draft Agreement to Management Services 10/1/09
Agreement Returned from Management Services 10/22/09
Agreement Sent to Cooperator 10/29/09
Signed Agreement Returned from Cooperator 11/30/09
Agreement Fully Executed 12/15/09
Contract ExpirationProject Close Out 12/31/11
Status As Of: March 02, 2010
An agreement has been drafted and is currently routing for Management Services approval.
021 - Manasota Basin 84
W604
Phillippi Creek In-stream Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Minimum Flows and Level Establishment and MonitoringFlood Protection Emergency Flood Response
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
PECK, MICHAELTask Manager(s)
Status Proposed
DescriptionSarasota County is developing the Roberts Bay North Watershed Management Plan (see L611), to protect and
improve water quality and restore natural systems throughout the watershed. This plan has identified several in-stream
restoration projects along Phillippi Creek (and nearby areas) to address unstable systems that are currently degrading
water quality and impacting natural systems. The goal of this project is to achieve measurable, improved water quality
and increase natural habitat along Phillippi Creek through the combined use of the following methods at five project
locations: 1) stream bank resloping and removal of exotic vegetation and replanting appropriate native species of
vegetation, 2) incorporating the low impact design technique of bioswales along the top of stream banks to reduce the
velocity of overland flow of stormwater and protect natural systems, 3) creating wetland treatment systems to restore
habitat at the confluence of stream branches, 4) constructing sediment sumps to reduce the amount of nutrient
transport associated with unstable systems, and 5) installation of weirs in select locations to provide increased
residence time for wetland treatment processes. The County began preliminary evaluations for several project
locations in late FY2009. For FY2010 the County has initiated preliminary designs and permitting for several proposed
project elements with some construction anticipated in late FY2010. District funds are requested for construction.
Current estimated construction costs are around $1,800,000 but will be further refined during design. Sarasota County
anticipates requesting additional funding to complete construction.
BenefitsUpon implementation, this project will improve surface water quality by reducing sedimentation and erosion through
bank re-sloping and stabilization with appropriate native vegetation. The installation of weirs at several locations will
increase residence time and thereby provide additional in-stream water quality treatment.
Costs
The total project cost is estimated at $1,350,000 (not including staff salaries and travel charges) but will be further
refined during project design. For FY2009 Sarasota County allocated $200,000 for the design and permitting of
the project. For FY2010 Sarasota County requested the District contribute $600,000 with the County contributing an
equal match. Due to FY2010 budget constraints, the District budgeted $150,000 for the project. The District's FY2010
share is split between the Manasota Basin Board ($75,000) and State SWIM ($75,000). For FY2011, the District's
Manasota Basin is requested to fund $400,000 for project construction with an equal match of $400,000 from
Sarasota County. District funds shown in the table include staff salaries and travel charges. If approved for
future funding, the District's total contribution would be spread over several fiscal years.
Additional Information
In 1987, the Florida Legislature established the Surface Water Improvement and Management (SWIM) Act having
recognized that water quality and habitat in surface waters throughout the state have degraded or were in danger of
being degraded. The Act requires the five water management districts to maintain a priority list of water bodies of
regional or statewide significance within their boundaries, and develop plans and programs for the improvement of
those water bodies. To date, ten SWIM water bodies in the District have had plans developed and approved by the
state. Several plans have been updated one or more times as required by the Act. The Sarasota Bay SWIM Plan was
first approved in 1997 and last updated in 2002. Since the first plan, the District has initiated a number of restoration
and diagnostic assessment projects. Included within these are: 1) investigation of toxic loading sources to the Bay, 2)
seagrass mapping 3) habitat restoration, 4) development of stormwater master plans, 5) various habitat restoration
projects, 6) construction of artificial reefs and oyster reefs, and 7) involvement in numerous public outreach and
education activities.
021 - Manasota Basin 85
W604
Phillippi Creek In-stream Restoration
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 481,657 0 0 403,662 77,995
District Budgeted - Outside Revenue
WMLTF (SWIM) - Prior Year Funds 77,994 0 0 0 77,994
Project Funds Not Budgeted by the
District
Sarasota County 800,000 50,000 200,000 400,000 150,000
$1,359,651 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionDevelop Draft Agreement with Sarasota County 10/16/09 3/31/10
Agreement to Contract Administration 11/13/09 4/12/10
Execution of Agreement by Sarasota County 12/11/09 5/31/10
Execution of Agreement by SWFWMD 12/18/09 6/4/10
Issue Notice to Proceed 12/30/09 6/4/10
2. Project ConstructionBegin Construction 10/1/10 12/1/10
End Construction 11/30/11 12/30/11
Status As Of: February 21, 2010
Sarasota County has selected an engineering consultant for evaluations and to complete design and permitting for
instream restoration/improvements at several localities within the Phillippi Creek basin. County and District staff visited all
the proposed sites in late October - November 2009. Evaluations of preliminary design concepts are complete but
required more time than originally anticipated. Review of land ownership required modifications for several of the
proposed elements. Final Design and Permitting has begun and is anticipated to be complete by June 2010. Permit
review and issuance of permits is expected to take several months. The construction phase of the project is not
anticipated to begin until October / November 2010. The agreement between the District and Sarasota County is under
internal review. The agreement will cover the construction of the approved and permitted projects.
021 - Manasota Basin 86
W611
Sarasota Bay Spoil Island Restoration Project
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota County Watershed Management, Sarasota CountyCooperator(s)
Project Manager GARCIA, LIZANNE
Task Manager(s)
Status Ongoing
DescriptionThis project originally proposed to restore degraded habitat on three groups of islands in Sarasota Bay, a SWIM
priority water body. The islands were Bird Colony Islands, Jim Neville Marine Preserve and Palmer Point Park. These
islands have been impacted by spoil deposition from the dredging of the Intracoastal Waterway, and have been
colonized by exotic vegetation consisting mostly of Australian pines and Brazilian peppers. The project proposes to
restore habitat through the removal of exotic vegetation, excavation of tidal channels and excess spoil, planting of
native vegetation and shoreline stabilization. The project at Bird Colony Islands was primarily focused on shoreline
stabilization while the other two projects focused more on comprehensive coastal ecosystem restoration. Due to the
significant construction cost estimate for the Jim Neville Marine Preserve and a shortfall in expected federal funding
the cooperative funding agreement was amended to remove the Jim Neville Preserve Marine Preserve site from this
project. The County is responsible for design and construction of the projects. District funding from prior fiscal years
(FY) has been used for construction of the Bird Colony Islands Project. Funding in FY2009 will be used for
construction of the Palmer Point Park project.
BenefitsThese projects focus on intertidal hydrologic restoration, removal of exotic vegetation, and re-vegetation with native
plants to increase and improve wildlife habitat. This habitat restoration project is consistent with and specifically
identified in the the Sarasota Bay SWIM Plan, 2002.
Costs
The total project cost is approximately $2.6 million. The District share totals $945,000 with $402,500 from the
Manasota Basin Board, $322,500 from State SWIM and $220,000 in State Appropriations. The county's share totals
$1,608,453, with $637,953 from the county, $300,000 from the West Coast Inland Navigation District, $520,500 from a
Jacksonville Community Foundation Grant and $150,000 from the United State Army Corps of Engineers. FY2009
project funding is $750,000, with the District contributing $325,000 and the County contributing $425,000. The
District's share is split 50/50 between the Manasota Basin Board and State SWIM ($162,500). District funds shown in
the table include staff salaries.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plans for Sarasota Bay outline goals to
restore habitat throughout the bay areas and reduce pollutant loads entering the bays. The objectives of this project
are consistent with these goals.
021 - Manasota Basin 87
W611
Sarasota Bay Spoil Island Restoration Project
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 490,126 0 485,877 3,293 956
District Budgeted - Outside Revenue
Ecosystem Trust Fund - Sarasota Bay
Impl (SWIM)
120,000 0 120,000 0 0
Ecosystem Trust Fund - Sarasota Spoil
(SWIM)
100,000 0 100,000 0 0
State Trust Funds (SWIM) 344,808 0 344,808 0 0
State Trust Funds (SWIM) - Prior 2006 61,606 0 61,606 0 0
WMLTF (SWIM) - Prior Year Funds 956 0 0 0 956
Project Funds Not Budgeted by the
District
Jacksonville Community Foundation 520,500 0 520,500 0 0
Sarasota County 637,953 0 637,953 0 0
USACE 150,000 0 150,000 0 0
West Coast Inland Navagation District 300,000 0 300,000 0 0
$2,725,949 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development and ExecutionDraft agreement sent to Management Services 2/18/05 2/18/05
Draft agreement returned from Management Services 3/11/05 3/11/05
Agreement sent to Cooperator 3/18/05 3/18/05
Signed agreement returned from Cooperator 4/15/05 4/15/05
Agreement fully executed 4/29/05 4/29/05
Notice to Proceed 5/6/05 5/3/05
2. Project TasksCompletion of Design and Permitting for Bird Colony Island 10/31/05 10/31/05
Construction complete for Bird Colony Island 3/30/08 2/22/08
Completion of Design and Permitting for Palmer Point Park 9/30/08 1/1/10 12/18/09
Construction complete for Palmer Point Park 5/30/09 11/30/10
3. Agreement Expiration DateContract Expiration 12/31/11
Status As Of: February 17, 2010
Construction at Bird Colony Island commenced in late 2007 and was completed on 2/22/08. The County submitted an
Environmental Resource Permit Application for the Palmer Point Park project on 5/16/08. The Department of
Environmental Protection is reviewing the permit and has issued Sarasota County two Requests for Additional
Information (RAI). Since the last update, the County and DEP are continuing to negotiate on the information required in
the RAI. This has delayed the date by which the County had hoped to complete design. The County has received the
permit from FDEP for the project and is preparing to advertise the request for bids. Construction is anticipated to begin in
June 2010. An amendment has been executed by both parties to encumber the FY2009 funds, revise the project
completion schedule for Palmer Point and change the District's project manager. The Project Milestones section of this
write-up has been revised to show these changes. The County received its environmental permits in December 2009 at
which time they provided the District with copies of the 100 percent plans. Comments have been provided to the County
on the 100 percent plans and the District is awaiting the County's response. A Request for Bids for Construction is
anticipated to occur in Spring 2010 upon approval of 100 percent plans.
021 - Manasota Basin 88
W612
Sarasota Bay Estuary Program
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota Bay Estuary ProgramCooperator(s)
Project Manager GARCIA, LIZANNE
Task Manager(s)
Status Ongoing
DescriptionThis proposed project provides funding for the Sarasota Bay Estuary Program (SBEP) as outlined in the Interlocal
Agreement which established the SBEP as a independent special district in 2005. The District participates in three
main areas. First the District's SWIM program carries out the projects that will address water quality and habitat
restoration within the bay. Second, the District, through the Manasota basin board and State have contributed annual
funding to the SBEP since 1990 to carry out the administration and implement of projects identified in the SBEP
Comprehensive Conservation and Management Plan. And finally, the District provides staff to sit on the technical,
management and policy (Governing Board member) committees of the program. The District's annual budget includes
funding support to the SBEP and District staff salaries, travel and central garage to administer the project, which
includes attending board meetings and other workshops and invoicing.
BenefitsThis project's support of the Sarasota Bay Estuary Program creates an opportunity for a cohesive effort between the
District, SBEP and other state and local agencies to implement resource management decisions and restoration
activities. Additionally, this project provides for leveraging funding between the partners.
Costs
The District has provided funding to the SBEP on an annual basis since 1990. The District's annual funding
commitment for the SBEP is $133,000. Prior to FY2011, the District share was split between the Manasota Basin
Board (50%, $66,500) and State SWIM (50%, $66,500) funds. In FY2011, the District's proposed share of $133,000
will be funded 100 percent by the Manasota Basin Board. District funds are used to implement projects outlined in the
Annual Workplan. District funds in the table include staff salaries, travel and central garage.
Additional Information
In 1987, the Florida Legislature established the Surface Water Improvement and Management Program. (SWIM) Act
having recognized that water quality and habitat in surface waters through out the state have degraded or in danger of
being degraded. The Act requires the District maintain a priority list of waterbodies of regional or statewide
significance within their boundaries. Sarasota Bay is designated as a priority waterbody. Sarasota Bay was identified
by the United States Environmental Protection Agency in 1989 as an estuary of Federal Significance and subsequently
included in the National Estuary Program. As a result of this designation, the Sarasota Bay National Estuary Program
was established in 1989 to assist the region in developing a comprehensive plan for the restoration and protection of
Sarasota Bay. In 2004, the "National" designation was dropped from the program name as a result of the execution of
an interlocal agreement between the program partners. The Interlocal Agreement commits the partners to an annual
funding commitment. Partners in the SBEP include the District, USEPA, Florida Department of Environmental
Protection, Sarasota and Manatee counties, the cities of Sarasota and Bradenton, and the town of Longboat Key. The
goals and strategies for the Bay are identified in the Comprehensive Conservation and Management Plan (CCMP) for
Sarasota Bay which provides the guidance for each entity on their contribution to restore the Bay. Since 1998, the
District and other partners have completed several habitat restoration projects and diagnostic assessments, including
seagrass mapping, assessment of atmospheric deposition and identification of toxic load sources in the Bay.
021 - Manasota Basin 89
W612
Sarasota Bay Estuary Program
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 537,090 0 328,684 138,012 70,394
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 275,482 0 275,482 0 0
State Trust Funds (SWIM) - Prior 2006 79,800 0 79,800 0 0
WMLTF (SWIM) - Prior Year Funds 70,393 0 0 0 70,393
Project Funds Not Budgeted by the
District
Local Government Partners 1,331,400 0 1,005,400 163,000 163,000
US EPA 3,686,750 0 2,486,750 600,000 600,000
$5,980,915 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2010 Annual Workplan Critical Project MilestonesFY2010 Draft Agreement to Management Services 10/1/09 10/26/09
FY2010 Agreement fully executed 11/12/09 1/11/10
FY2010 first payment (1/2 total) 12/31/09 2/1/10
FY2010 Second/final payment 3/1/10
FY2010 End of contract 9/30/10 9/30/10
Status As Of: February 12, 2010
FY2010 Annual Workplan: The FY2010 workplan was fully executed on January 11, 2010. The first invoice has been
received and being processed. Management Conference: The SBEP Boards and Technical Committees continue to
work with its partners to develop a mechanism for establishing numeric nutrient criteria for the Bay in advance of the
effort being conducted by EPA. This is consistent with work the Tampa Bay and Charlotte Harbor Estuary Programs are
conducting.
021 - Manasota Basin 90
W613
Sarasota-Catfish Creek SW Facility-Phase II
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementWater Supply Alternative Water SupplyNatural Systems Minimum Flows and Level Establishment and Monitoring
Basin(s) Manasota
Sarasota County Watershed Management, Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
THORNTON, SHELLEYTask Manager(s)
Status Ongoing
DescriptionThis FY2005 project is to implement Best Management Practices (BMPs) for the Catfish Creek Watershed which
drains into Sarasota Bay, a District SWIM water body. The Catfish Creek watershed covers an area of approximately
6.22 square miles and is located in Sarasota County. Implementation of BMPs includes design, development of
construction documents, construction permitting, land acquisition, bidding, contractor selection, construction of the
BMPs and construction engineering and inspection. Current plans call for the construction of one stormwater treatment
pond totaling 23.75 acres. The County's prior funding includes the property purchased by the County for the project.
With FY2005 funds and additional funds provided in FY2008 and FY2009, work on the Implementation of BMPs will be
completed in 2010 and includes the following tasks: construction of the BMPs and construction engineering and
inspection.
BenefitsThe combined pond acreage will be sufficiently large that stormwater runoff from approximately 810 acres of
watershed will receive adequate treatment to meet design criteria for existing stormwater regulations and will improve
water quality by increasing residence time.
Costs
The total current projected project cost is $9,903,703, which includes land costs to date of $1,788,129. The District's
share in FY2005 was $2,500,000 split 40/60 between the Manasota Basin Board ($1,000,000) and State SWIM
($1,500,000). Sarasota County's share in prior years was $6,229,949 in addition to a FDEP grant for
$504,413. Sarasota County contributed $275,000 to the project in FY2008 with the District providing a matching
contribution shared evenly between the Manasota Basin Board ($137,500) and State SWIM ($137,500). The
County requested the final $275,000 in FY2009 (shared evenly between the Manasota Basin Board ($137,500) and
State SWIM ($137,500)) and contributed an equal amount. The total District funding reflected in the table below
includes staff salary, travel and central garage costs.
021 - Manasota Basin 91
W613
Sarasota-Catfish Creek SW Facility-Phase II
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,302,000 0 1,296,903 2,363 2,734
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 291,165 0 291,165 0 0
State Trust Funds (SWIM) - Prior 2006 1,500,000 0 1,500,000 0 0
WMLTF (SWIM) - Prior Year Funds 2,734 0 0 0 2,734
Project Funds Not Budgeted by the
District
Florida Department of Environmental
Protection
504,413 0 504,413 0 0
Sarasota County 6,779,949 0 6,779,949 0 0
$10,380,261 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionDraft Agreement for Construction to Management Services 11/19/04 12/19/04
Agreement returned from Management Services 12/9/04 1/7/05
Agreement returned from Executive Review 12/17/04 1/14/05
Agreement to Sarasota County 12/27/04 1/19/05
Execution by District 1/31/05 1/31/05
Sarasota County Approval of Agreement 2/8/05 4/26/05 4/26/05
Draft SWIM Agreement for Construction to Management Services 7/26/05 8/17/05
Agreement returned from Management Services 8/12/05 9/19/05
Agreement returned from Executive Review 9/1/05 9/21/05
Agreement to Sarasota County 9/4/05 9/23/05
Sarasota County Approval of Agreement 11/30/05 11/8/05 11/8/05
Execution by District 12/15/05 12/2/05
Notice to Proceed 1/31/07 12/2/05
2. Contract Development & ExecutionPrepare Amendment for FY2008 Funding 8/28/07 8/28/07
Amendment to County for Approval 11/30/07 1/15/08 1/4/08
Amendment Approved by County 3/1/08 3/11/08 3/18/08
Amendment Approved by District 5/22/08 3/25/08
Notice to Proceed 5/26/08 9/30/08 9/10/08
2. Critical Project MilestonesPermits Issued 3/11/04 7/3/07
Construction Begins 4/30/08 2/28/09 10/1/08
Construction Substantially Completed 1/31/10 9/30/09 12/15/09
As-Builts Received and Approved 4/30/10
Maintenance Plan Received 4/30/10
Final Project Report 4/30/10
3. Close OutContract Termination 5/31/10
Status As Of: March 19, 2010
The Catfish Creek stormwater facility project continues in the final construction phase with Oklawaha Farms Inc., as the
primary contractor. Construction is complete. The County submitted a permit modification to transfer the constructed
021 - Manasota Basin 92
W613
Sarasota-Catfish Creek SW Facility-Phase II
facility from Construction Status to Operational Status. Operational Status was granted on February 10, 2010. Pending
receipt of final invoices for reimbursement, the contract is anticipated to close out by late April 2010.
ACTIONS-TO-DATE: On schedule. Reasonably good weather and site management have kept operations running.
021 - Manasota Basin 93
W616
Sarasota Bay Habitat Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota Bay Estuary ProgramCooperator(s)
Project Manager POWERS, STEPHANIE
Task Manager(s)
Status Ongoing
DescriptionThis proposed project is in repsonse to a cooperative funding request from the Sarasota Bay Estuary Program (SBEP)
for the restoration and enhancement of several coastal dune/coastal hammock systems in the Sarasota Bay
watershed. The SBEP has developed a comprehensive plan for restoring intertidal and submerged aquatic habitats at
20 locations throughout Sarasota Bay. This project will help to fund restoration and management plans for several of
the locations in addition to exotic plant species removal and control.
BenefitsThis project provides improved natural systems through habitat enhancement and creation.
Costs
The total estimated project budget is $720,000. The current FY2009 project cost is $240,000, with the SBEP and the
District each contributing half ($120,000). The District share is split between the Manasota Basin Board ($60,000) and
State SWIM ($60,000). The FY2009 funds will be used to implement restoration projects for Sarasota Bay. The
FY2010 proposed project cost is $240,000, with the SBEP contributing half ($120,000) and requesting half ($120,000)
from the District. At their April 2009 meeting, the Manasota Basin Board approved amending its FY2009 budget to
include reallocated State SWIM funds to cover 50 percent of the District's proposed FY2010 costs ($60,000). The
remaining funds ($60,000) are included in the Manasota Basin Board's FY2010 proposed budget. District funds shown
in the table include staff salaries.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plans for Sarasota Bay outline goals to
restore habitat throughout the bay areas and reduce pollutant loads entering the bays. The objectives of this project
are consistent with these goals.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 187,992 0 122,302 4,050 61,640
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 122,301 0 122,301 0 0
State Trust Funds (SWIM) - Prior 2006 60,000 0 0 0 0
WMLTF (SWIM) - Prior Year Funds 1,640 0 0 0 1,640
Project Funds Not Budgeted by the
District
Sarasota Bay Estuary Program 365,000 0 245,000 0 120,000
$736,933 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 94
W616
Sarasota Bay Habitat Restoration
Critical Project Milestones ActualProjected Amended
1. Contract Development and ExecutionDraft agreement Sent to Management Services 9/12/07 1/3/08
Agreement Returned from Management Services 10/3/07 2/20/08
Agreement Sent to Cooperator 10/10/07 2/28/08
Signed Agreement Returned from Cooperator 11/7/07 4/1/08 3/24/08
Agreement Fully Executed 11/21/07 4/15/08 4/7/08
Notice To Proceed 11/27/07 4/30/08 4/9/08
1. Contract Development and ExecutionFirst Amendment to Original Agreement 4/1/09
Status As Of: March 02, 2010
Additional projects are being chosen for implementation under this agreement with SBEP. As they are chosen, District
staff will evaluate the projects and objectives to ensure they coincide with District and SWIM Program goals.
021 - Manasota Basin 95
W617
Sarasota Imp. BMPs Coastal Basin Beach Road
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota County Watershed Management, Sarasota CountyCooperator(s)
Project Manager PRESTON, MATT
Task Manager(s)
Status Ongoing
DescriptionIn response to a cooperative funding request from Sarasota County, this regional initiative conforms with, and furthers,
the implementation of the Sarasota Bay's CCMP, SWFWMD's Southern Coastal Watershed CWM Plan, and Sarasota
County's Comprehensive Plan. The project is designed to improve water quality standards and reduce street flooding
on Beach Road located in the Sarasota Bay Coastal basin. The water quality in the drainage piping system along
Beach Road near Siesta Key Public Beach does not meet water quality standards and has impacted the Public Beach
through a ditch outfall system to the Gulf of Mexico. This project entails the design and construction of a stormwater
treatment system to protect the public health and safety to meet recreational water quality standards. A feasibility study
report was completed in January 2006. The design includes construction of a linear estuarine lagoon system for
stormwater biological treatment, removal of the existing outfall ditch crossing the public beach and rerouting the
treated stormwater discharge to the Grand Canal. Alternate ideas for a stormwater vault system will be considered. A
stormwater pump station will be planned with an in-line UV treatment system to kill bacteria. The project is expected to
improve water quality by increasing the residence time in the new lagoon system. This FY2010 request is being made
for construction cost funding.
BenefitsThe project will be designed to take stormwater runoff that presently discharges across Siesta Key Beach and redirect
it through a water quality treatment marsh and discharge to a residential canal system that connects with Sarasota
Bay. The primary benefits of the project would be reduced flooding on Beach Road with water quality improvement
from biological contamination and natural systems enhancement.
Costs
The total project cost is $2,227,000. The County had a feasibility study completed in January 2006 at a cost of $77,000
and budgeted $200,000 for design in FY2007, leaving a balance of $1,950,000 estimated to be required for the
construction of the project. Sarasota County contributed $487,500 to the project in FY2008 while the District provided
a matching contribution shared evenly between the Manasota Basin Board ($243,750) and State SWIM ($243,750).
The County requested the remaining funding in FY2009, with the County and the District each contributing half
($487,500). Since the County could not commit to spending all of the funding in FY2009, they contributed half of the
requested amount or $243,750 in FY2009 and the District contributed $243,750 split evening between the Manasota
Basin Board ($121,875) and State SWIM ($121,875). The County will contribute $243,750 for FY2010 and is
requesting FY2010 funding of $243,750 from the District. At their April 8, 2009 meeting, the Manasota Basin Board
approved amending its FY2009 budget to include reallocated State SWIM funds to cover 50 percent of the District's
proposed FY2010 costs ($121,875). The remaining funds ($121,875) are included in the Manasota Basin Board's
FY2010 proposed budget. District funds shown in the table include staff salaries.
Additional Information
This regional initiative conforms with, and furthers, the implementation of the Sarasota Bay's CCMP, SWFWMD's
Southern Coastal Watershed CWM Plan, and Sarasota County's Comprehensive Plan.
021 - Manasota Basin 96
W617
Sarasota Imp. BMPs Coastal Basin Beach Road
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 495,215 0 369,877 1,079 124,259
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 369,875 0 369,875 0 0
State Trust Funds (SWIM) - Prior 2006 121,875 0 0 0 0
WMLTF (SWIM) - Prior Year Funds 2,383 0 0 0 2,383
Project Funds Not Budgeted by the
District
Sarasota County 1,252,000 0 1,008,250 0 243,750
$2,241,348 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Implementation of BMPs for Coastal Basin Beach RoadDraft Contract and Scope of Work 9/30/07 7/25/07
Contract Executed by the County 11/30/07 12/18/07 12/18/07
Application for FY2009 Funding 12/10/07 12/7/07
Contract Executed by the District 12/31/07 3/6/08
Notice to Proceed 1/15/08 3/12/08
Commence Design and Permitting 3/30/08 3/30/08
Complete Design and Permitting 3/30/09 12/1/08
Commence Construction 4/30/10
Complete Construction 4/30/11
Final Report and As-Builts 12/31/11
Final Report and As-Builts 12/31/11
Contract Termination 3/31/12
Status As Of: January 04, 2010
The contract was fully executed on 03/06/2008 and originals returned to the County with a Notice to Proceed on
3/11/2008. The original design has been completed and the ERP has been issued, however, there is significant
opposition to the proposed project among citizens living near the proposed stormwater system outfall on Grande Canal.
The County has been and is seeking to address this through both public education and investigation into alternate outfall
locations. The consultant is currently preparing calculations to compare existing nutrient loadings at the proposed outfall
with post-developed nutrient loadings. An alternative design plan with a Gulf outfall location is also being prepared in
order to compare construction costs.
021 - Manasota Basin 97
W619
Perico Preserve Environmental Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager POWERS, STEPHANIE
Task Manager(s)
Status Ongoing
DescriptionThis project is in response to a FY2009 cooperative funding request from Manatee County to restore and enhance
approximately 57 acres of intertidal wetlands and uplands in west central Manatee County. The land was purchases in
June 2007 by Manatee County for $6 million. The proposed restoration will target the creation and enhancement of
open water, intertidal, and coastal upland habitats. Exotic plants such as Australian Pine and Brazilian Pepper will be
removed and replaced with both planted and naturally recruiting native species. The funding request for FY2009 is to
complete an existing resource investigation and restoration project design.
BenefitsUpon completion, the project will provide significant benefits to habitat through the removal of exotic species and
replanting of native vegetation. Improved hydrologic conditions will also improve the habitat and water quality of the site
and provide limited stormwater treatment of waters entering both Tampa Bay and Sarasota Bay. Because the project
site drains to both Tampa Bay and Sarasota Bay, this project will benefit both systems.
Costs
The total project cost is $9,250,000. The FY2009 project cost is $450,000, which is being split 50/50 between
Manasota Basin Board ($225,000) and State SWIM funds ($225,000). Manatee County is matching the District's
contribution with the $6 million used for land purchase. District funds for FY2009 will be used for the Design and
Permitting phase of the project.The remaining funds for construction would be budgeted in future years and contingent
upon Basin approval. District funds shown in the table include staff salaries.
Additional Information
Since 1950, approximately 50 percent of Tampa Bay's natural shoreline and approximately 40 percent of Sarasota
Bay's intertidal wetland habitat has been lost due to development and reduction in water quality. This resulted in a
decline in the aesthetic, recreational, and commercial value of the bay, as well as a loss of habitat for native plants
and animals. The SWIM Plans for Tampa Bay and Sarasota Bay outline goals to restore habitat throughout the bay
areas and reduce pollutant loads entering the bays. The objectives of this project are consistent with these goals.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 231,752 0 228,142 2,654 956
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 228,141 0 228,141 0 0
WMLTF (SWIM) - Prior Year Funds 956 0 0 0 956
Project Funds Not Budgeted by the
District
Manatee County 6,000,000 0 6,000,000 0 0
$6,460,849 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 98
W619
Perico Preserve Environmental Restoration
Critical Project Milestones ActualProjected Amended
1. Contract Development and ExecutionDraft agreement sent to Management Services 10/31/08 3/16/09 5/13/09
Draft agreement returned from Management Services 11/21/08 9/14/09
Agreement Sent to Cooperator 11/28/08 9/17/09
Signed Agreement returned from Cooperator 12/26/08 10/26/09
Agreement fully executed 1/16/09 11/2/09
Notice to Proceed 1/23/09 11/4/09
2. Project TasksDesign and Permitting Complete 12/31/09 5/30/10
Construction Complete 12/30/10
3. Agreement Expiration DateContract Expiration 6/30/11
Status As Of: March 02, 2010
An agreement with Manatee County was executed on November 2, 2009. A project kickoff meeting will now be
scheduled with County project staff.
021 - Manasota Basin 99
W620
Pelican Cove Stormwater Retrofit
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
Pelican Cove, Sarasota CountyCooperator(s)
Project Manager NORTON, NANCY
Task Manager(s)
Status Proposed
DescriptionThis project is in response to a FY2009 cooperative funding request from Pelican Cove Condominium Association.
Pelican Cove is a Sarasota County Neighborhood Environment Stewardship Team (NEST) community which has
begun to retrofit stormwater BMPs in the 1970's property. This project involves the design and construction of berms to
redirect the flow of stormwater runoff into detention areas and swales designed to reduce the amount of flow and
pollutants entering Little Sarasota Bay by as much as 80% to 90%. The project will provide treatment for stormwater
from approximately 20 acres of Pelican Cove Condominiums. Maintenance will be provided by Pelican Cove
Condominium Association which has a staff of over 40 grounds and maintenance employees. Additional funding is
requested in FY2011 to provide longer stormwater retention times by diverting some of the stormwater runoff to an
existing stormwater pond.
BenefitsThe stormwater treatment system will redirect stormwater runoff from approximately 20 acres of the site, reducing
nutrients and sediments that currently flow untreated to Little Sarasota Bay.
Costs
The FY2009 project cost estimate is $35,000, with the Pelican Cove Condominium Association and the District each
contributing half ($17,500). The District share is split between the Manasota Basin Board ($8,750) and State SWIM
($8,750). In FY2011, the the Association requested additional funding, increasing the project budget by $10,000, with
the Pelican Cove Condominium Association and the District each contributing half ($5,000). The District portion is
funded by the Manasota Basin Board. District funds shown in the table includes staff salaries.
Additional Information
Since 1950, approximately 50 percent of Tampa Bay's natural shoreline and approximately 40 percent of Sarasota
Bay's intertidal wetland habitat has been lost due to development and reduction in water quality. This resulted in a
decline in the aesthetic, recreational, and commercial value of the bay, as well as a loss of habitat for native plants
and animals. The SWIM Plans for Tampa Bay and Sarasota Bay outline goals to restore habitat throughout the bay
areas and reduce pollutant loads entering the bays. The objectives of this project are consistent with these goals.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 18,961 0 8,905 9,006 1,050
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 8,905 0 8,905 0 0
WMLTF (SWIM) - Prior Year Funds 1,049 0 0 0 1,049
Project Funds Not Budgeted by the
District
Pelican Cove Condominiums 22,500 0 17,500 5,000 0
$51,415 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 100
W620
Pelican Cove Stormwater Retrofit
Critical Project Milestones ActualProjected Amended
Contract Development and ExecutionDraft Agreement Sent to Management Services 9/2/08 9/9/08
Draft Agreement Returned from Management Services 9/23/08 12/18/08
Agreement Sent to Cooperator 9/30/08 12/18/08 4/30/09
Signed Agreement Returned from Cooperator 10/28/08 5/12/09
Agreement Fully Executed 11/11/08 5/22/09
Notice to Proceed 11/17/08 6/8/09
Critical Project MilestonesComplete Project Design and Permitting 12/31/09 4/8/10
Complete Construction 12/31/10
Agreement Expiration 12/31/12
Status As Of: February 23, 2010
The Pelican Cove Condominium Association provided a Scope of Work in August 2008 and a preliminary draft
Agreement for the project was sent to both Sarasota County and the Association in September 2008. The final
agreement was forwarded to Sarasota County for signatures in December 2008. In lieu of entering into the tri-party
agreement, the County Water Resource Manager stated that the County ordinance, Stormwater Conveyance
Maintenance, provides for the County to enforce maintenance of private stormwater drainage systems. The revised
Agreement between Pelican Cove and the District was executed May 22, 2009 and Notice to Proceed was issued June
8, 2009. After Pelican Cove contracted with a consultant to design the project, another opportunity to treat more
stormwater flow was identified. The Association requested a extension of four months to complete design so they can
increase treatment volume and submitted a FY2011 cooperative funding request for an additional $5,000.
021 - Manasota Basin 101
W621
Little Sarasota Bay Water Quality Management Plan
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota County, Sarasota County Watershed ManagementCooperator(s)
Project Manager GARCIA, LIZANNE
Task Manager(s)
Status Proposed
DescriptionThis proposed project will develop a water quality management plan for Little Sarasota Bay that includes the Little
Sarasota Bay, Elligraw Bayou, Holiday Bayou, Clower Creek, Catfish Creek, North Creek, South Creek and direct
runoff to the bay from Siesta Key and Casey Key. The plan will focus on water resource issues such as restoration of
historic or more natural hydrologic regimes in the basin, and improvements to water quality and habitat. Through this
plan, the County and District will work with the Sarasota Bay Estuary Program and its partners to develop water quality
and habitat restoration goals and identify projects that will assist in meeting these goals. The plan will include short
term and long term projects for improvements that may include wastewater reuse, stormwater reuse, smart growth,
revised land development standards, sediment control, wetland or floodplain restoration, flood level abatement, aquifer
protection, and restoration of natural flow regimes. The County will post deliverables and reports on the Sarasota
County Water Atlas website. Additionally, the plan will identify the monitoring needed to evaluate the progress made
toward meeting the established goals.
BenefitsDevelopment of this plan will assist the District in its update of the SWIM Plan for Sarasota Bay by developing pollutant
load reduction goals and specific projects to meet those goals. Implementation of the plan by Sarasota County and
others will result in protecting and restoring water quality and natural systems within the watershed of Little Sarasota
Bay.
Costs
The total estimated cost for the development of the Water Quality Management Plan is $600,000. This multi-year
funded project is expected to be funded over three fiscal years beginning in FY2009. The FY2009 and FY2010 total
costs were $400,000 with the District and Sarasota each contributing one-half ($200,000). The District's FY2009 and
FY2010 share is split evenly between the Manasota Basin Board ($100,000) and State SWIM funds ($100,000). In
FY2011, Sarasota has requested and the Manasota Basin Board has included $100,000 in its proposed FY2011
budget to match $100,000 proposed by the County. FY2009 funds are for compiling and evaluating all existing studies,
models and data, identifying pollutant sources and development of a data collection plan. FY2010 funds are for
modeling watershed pollutant loads and evaluating alternatives, and proposed FY2011 funds are for completing and
draft and final plan. District funds shown in the table include staff salaries, travel and central garage.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plans for Sarasota Bay outline goals to
restore habitat throughout the bay areas and reduce pollutant loads entering the bays. The objectives of this project
are consistent with these goals.
021 - Manasota Basin 102
W621
Little Sarasota Bay Water Quality Management Plan
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 218,062 0 29,821 107,267 80,974
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 29,820 0 29,820 0 0
State Trust Funds (SWIM) - Prior 2006 75,000 0 0 0 0
WMLTF (SWIM) - Prior Year Funds 5,974 0 0 0 5,974
Project Funds Not Budgeted by the
District
Sarasota County 300,000 0 50,000 100,000 150,000
$628,856 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Cooperator Contract Development and ExecutionDraft Agreement sent to Management Services 10/1/08 1/29/09
Agreement Returned from Management Services 10/15/08 2/16/09
Agreement sent to Cooperator 10/15/08 2/25/09
Signed Agreement Returned from Cooperator 10/29/08 3/13/09 3/20/09
Agreement Fully Executed 11/7/08 3/16/09 3/27/09
2. Project TasksConsultant Selction, Negotiation and Contract Execution 11/17/09 2/28/10
Compile and evaluate existing data, identify projects, outline final report 6/1/11
Final Report 6/29/12
3. Cooperative Agreement ExpirationAgreement Expiration 12/31/12
Status As Of: January 11, 2010
The cooperative funding agreement was fully executed in March 2009. A kick-off meeting with the County was held May
5, 2009. At the meeting, the selection of a consultant to conduct the study and a timeline was discussed. The County
issued the Request for Professional Services for this project in November 2009 and a ranking meeting was held on
January 7, 2010 to develop the ranked list for presentation to the County Commission.
021 - Manasota Basin 103
W622
Sarasota Bay Water Quality Management Plan
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota County, Sarasota County Watershed ManagementCooperator(s)
Project Manager GARCIA, LIZANNE
Task Manager(s)
Status Proposed
DescriptionThis proposed project will develop a water quality management plan for Sarasota Bay that includes the watersheds
within Sarasota County for Sarasota Bay, Hudson Bayou, Whitaker Bayou, Lido Key, and direct runoff to the bay. The
plan will focus on water resource issues such as restoration of historic or more natural hydrologic regimes in the basin,
and improvements to water quality and habitat. Through this plan, the County and District will work with the Sarasota
Bay Estuary Program and its partners to develop water quality and habitat restoration goals and identify projects that
will assist in meeting these goals. The plan will include short term and long term projects for improvements that may
include wastewater reuse, stormwater reuse, smart growth, revised land development standards, sediment control,
wetland or floodplain restoration, flood level abatement, aquifer protection, and restoration of natural flow regimes. The
County will post deliverables and reports on the Sarasota County Water Atlas website. Additionally, the plan will
identify the monitoring needed to evaluate the progress made toward meeting the established goals.
BenefitsDevelopment of this plan will assist the District in its update of the SWIM Plan for Sarasota Bay by developing pollutant
load reduction goals and specific projects to meet those goals. Implementation of the plan by Sarasota County and
others will result in protecting and restoring water quality and natural systems within the watershed of Sarasota Bay.
Costs
The total estimated cost for the development of the Water Quality Management Plan is $600,000. This multi-year
funded project is expected to be funded over three fiscal years beginning in FY2009. The FY2009 and FY2010 total
costs were $400,000 with the District and Sarasota each contributing one-half ($200,000). The District's FY2009 and
FY2010 share is split evenly between the Manasota Basin Board ($100,000) and State SWIM funds ($100,000). In
FY2011, Sarasota has requested and the Manasota Basin Board has included $100,000 in its proposed FY2011
budget to match $100,000 proposed by the County. FY2009 funds are for compiling and evaluating all existing studies,
models and data, identifying pollutant sources and development of a data collection plan. FY2010 funds are for
modeling watershed pollutant loads and evaluating alternatives, and proposed FY2011 funds are for completing and
draft and final plan. District funds shown in the table include staff salaries, travel and central garage.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plans for Sarasota Bay outline goals to
restore habitat throughout the bay areas and reduce pollutant loads entering the bays. The objectives of this project
are consistent with these goals.
021 - Manasota Basin 104
W622
Sarasota Bay Water Quality Management Plan
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 218,062 0 29,821 107,267 80,974
District Budgeted - Outside Revenue
State Trust Funds (SWIM) 29,820 0 29,820 0 0
State Trust Funds (SWIM) - Prior 2006 75,000 0 0 0 0
WMLTF (SWIM) - Prior Year Funds 5,974 0 0 0 5,974
Project Funds Not Budgeted by the
District
Sarasota County 300,000 0 50,000 100,000 150,000
$628,856 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Cooperator Contract Development and ExecutionDraft Agreement sent to Management Services 10/1/08 1/29/09
Agreement Returned from Management Services 10/15/08 2/16/09
Agreement sent to Cooperator 10/15/08 2/25/09
Signed Agreement Returned from Cooperator 10/29/08 3/13/09
Agreement Fully Executed 11/7/08 3/16/09
2. Project TasksConsultant selection, negotiation and Contract execution 3/31/10
Compile evaluate existing data, identify projects 6/1/11
Final Report 6/29/12
3. Cooperative Agreement ExpirationAgreement Expiration 12/31/12
Status As Of: December 21, 2009
The agreement was fully executed in March 2009. A kick-off meeting with the County was held May 5, 2009. At the
meeting, the selection of a consultant to conduct the study and a timeline was discussed. The District and County staff
have prepared a Request for Professional Services and it is expected to be advertised before year end. Approval by the
Board of County Commissioners to enter into a consultant agreement is expected by March 2010.
021 - Manasota Basin 105
W623
Holmes Beach Stormwater Retrofit
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) Manasota
Holmes BeachCooperator(s)
Project Manager PRESTON, MATT
Task Manager(s)
Status Proposed
DescriptionThis project is in response to a cooperative funding request from the City of Holmes Beach. The project will impact two
drainage basins within the City of Holmes Beach totaling approximately 107 acres. Both basins have a total of 16
outfall locations that discharge into the finger canals within the City, which discharge into Sarasota Bay. The objective
of this project is to reduce pollutants being received by Sarasota Bay by improving the water quality discharge to the
bay and reduce flooding within the basins. The project includes the construction of a new retention area at the
southwest intersection of 62nd Street and Flotilla Drive. Additional improvements will include reconstruction of the city
owned land to accommodate shallow grassed swales and installation of new baffle box structures at each outfall
location. The swales provide treatment of stormwater through percolation and evaporation. Treated stormwater will
discharge into the bay through the new baffle structures which provide additional treatment through sedimentation,
filtration and skimming.
BenefitsThis project will improve the water quality and flood protection by removing pollutants and increasing storage and
conveyance capacity. The stormwater filtration devices being proposed will provide suspended solids removal from
stormwater runoff that previously discharged directly into the canal/bay system. The project is anticipated to reduce
TSS by 80%.
Costs
The total project budget is $515,000, of which the City and the District are funding half ($257,500). The FY2010 project
cost is $164,460 with the City and the District each contributing half ($82,230). The District's FY2010 share is split
between the Manasota Basin Board ($41,115) and State SWIM ($41,115). The FY2011 project cost is $350,540 with
the City and the District each contributing half ($175,270). The District's FY2011 share would be funded by the
Manasota Basin Board. District funds shown in the table include staff salaries.
Additional Information
The State of Florida has designated Sarasota Bay as an OFW. In 1997, a Sarasota Bay Surface Water Improvement
and Management (SWIM) Plan was created to outline a series of research and/or restoration projects that will allow
for the preservation and continued restoration of the health of Sarasota Bay. The goals of the SWIM plan include
improvement of water transparency in Sarasota Bay to decrease the quantity and increase the quality of stormwater
runoff to Sarasota Bay, to restore shoreline habitats in Sarasota Bay and to continue monitoring programs in Sarasota
Bay. This project will help to accomplish those objectives and increase the overall health, welfare and safety of the
residents living within these basins.
021 - Manasota Basin 106
W623
Holmes Beach Stormwater Retrofit
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 477,227 255,500 0 178,228 43,499
District Budgeted - Outside Revenue
Ecosystem Trust Fund - SWIM Prior
Year Funds
41,115 0 0 0 41,115
WMLTF (SWIM) - Prior Year Funds 2,383 0 0 0 2,383
Project Funds Not Budgeted by the
District
City of Holmes Beach 257,500 0 0 175,270 82,230
$778,225 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Design and Permitting Completion 8/31/10
Commence Construction 11/30/10
Complete Construction 12/31/11
As-Built Drawings and Final Report 4/30/12
Status As Of: January 04, 2010
The cooperative funding agreement is currently being routed for approval.
021 - Manasota Basin 107
W624
Red Bug Slough Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager PRESTON, MATT
Task Manager(s)
Status Proposed
DescriptionThis project is in response to a cooperative funding request from Sarasota County. Sarasota County and SWFWMD
are jointly developing the Roberts Bay North Watershed Management Plan which has identified the Red Bug Slough
Restoration project to improve water quality and restore habitat in the watershed. This project was also identified in the
2002 Sarasota Bay SWIM Plan to improve the quality of stormwater runoff to Sarasota Bay. Red Bug Slough is a
tributary to Philippi Creek, which eventually discharges to Roberts Bay, and is part of the larger Sarasota Bay system.
The Red Bug Slough basin is 600 acres and includes a series of four interconnected lakes: West Clark Lake, East
Clark Lake, Mirror Lake and Red Bug Slough Lake. There are four proposed restoration components identified for
design that will partially restore a historical wetland, enhance native plant communities, and improve the quality of
water entering Phillippi Creek and ultimately Sarasota Bay.
BenefitsThe project will create additional storage within the watershed and, thereby, provide an improved level of service for
flooding. The project will also provide improved water quality treatment by increasing residence times and providing
additional biological treatment through restoration of historical marshes and creation of new wetland systems within
Red Bug Sough. This will improve the quality of water entering Phillippi Creek and ultimately Sarasota Bay, and will
have a positive impact on waterbodies on the TMDL verified list for the Sarasota Bay Group 3 segments, including
Roberts Bay for nutrients and Chl (a); and Phillippi Creek for coliform bacteria.
Costs
The total project budget is $1,000,000, of which the County and the District are funding half ($500,000). Sarasota
County has budgeted $250,000 for FY2010 and $250,000 for FY2011. The District budgeted $400,000 for FY2010.
The District's FY2010 share is split between the Manasota Basin Board ($200,000) and State SWIM ($200,000). The
proposed FY2011 budget includes $100,000, which would be funded by the Manasota Basin Board. District funds
shown in the table include staff salaries.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plans for Sarasota Bay outline goals to
restore habitat throughout the bay areas and reduce pollutant loads entering the bays. The objectives of this project
are consistent with these goals.
021 - Manasota Basin 108
W624
Red Bug Slough Restoration
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 305,342 0 0 102,958 202,384
District Budgeted - Outside Revenue
Ecosystem Trust Fund - SWIM Prior
Year Funds
200,000 0 0 0 200,000
WMLTF (SWIM) - Prior Year Funds 2,383 0 0 0 2,383
Project Funds Not Budgeted by the
District
Sarasota County 500,000 0 0 250,000 250,000
$1,007,725 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Design and Permitting Completion 12/31/10
Commence Construction 5/31/11
Complete Construction 5/31/13
As-Builts and Final Project Report 12/31/13
Status As Of: January 04, 2010
The cooperative funding agreement is currently being routed.
021 - Manasota Basin 109
W625
Runaway Bay - Sarasota Bay Coast Line Restoration
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and RestorationFlood Protection Emergency Flood Response
Basin(s) Manasota
Runaway Bay Condominium AssociationCooperator(s)
Project Manager NORTON, NANCY
Task Manager(s)
Status Ongoing
DescriptionThis project is in response to a FY2010 Cooperative Funding request from Runaway Bay Condominium Association.
Runaway Bay is a waterfront condominium association located between Gulf Drive North and Sarasota Bay. The
objective of this project is to restore approximately 900 linear feet of shoreline. This project will also reduce pollutants
being received by Sarasota Bay. Through the years, this shoreline has experienced serious erosion which has
negatively impacted the habitat and wetland function. Best Management Practices will be implemented to remove
non-permitted structures and sea walls, restore the shoreline and improve water quality. Runaway Bay will be
responsible for ongoing maintenance once the project is completed.
BenefitsImplementation of restoration practices on the Runaway Bay Condominium's 900 linear feet of Sarasota Bay shoreline
will restore shoreline habitat and improve water quality.
Costs
The total project budget is $80,000, with Runaway Bay Condominium Association and the District each contributing
half ($40,000). The District's share is split between the Manasota Basin Board ($20,000) and State SWIM ($20,000).
District funds shown in the table include staff salaries.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plan for Sarasota Bay outlines goals to
restore habitat throughout the bay area and reduce pollutant loads entering the bay. The objectives of this project are
consistent with these goals.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 24,575 0 0 3,059 21,516
District Budgeted - Outside Revenue
WMLTF (SWIM) - Prior Year Funds 21,516 0 0 0 21,516
Project Funds Not Budgeted by the
District
Runaway Bay Condominium
Association
139,000 0 99,000 0 40,000
$185,091 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 110
W625
Runaway Bay - Sarasota Bay Coast Line Restoration
Critical Project Milestones ActualProjected Amended
Contract Development and ExecutionDraft Agreement to Management Services 12/31/09 1/20/10
Draft Agreement Returned from Management Services 2/26/10
Signed Agreement Returned from Cooperator 3/10/10
Agreement Sent to Cooperator 3/10/10
Agreement Fully Executed 3/12/10
Notice to Proceed 3/19/10
Status As Of: February 24, 2010
The revised agreement is routing.
021 - Manasota Basin 111
W626
Blackburn Point Park Addition
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
PECK, MICHAELTask Manager(s)
Status Proposed
DescriptionSarasota County purchased Blackburn Point Park Addition to meet the needs of the County's Comprehensive Plan
objectives for public water access, open space, and recreational opportunities. Blackburn Point Park Addition is a
10.94 acre parcel located at 477 Blackburn Point Road in Osprey, Florida and is the primary landward access to
Casey Key. The eastern portion of the park will provide boat launch access to Blackburn Bay and the western portion
will provide boat launch access to Little Sarasota Bay. Both enbayments are designated SWIM water bodies. Park
development will include construction of a public boat ramp, pavilions, walkways, nature trails, restrooms, playground,
fishing piers, parking for cars and boat trailers, wetlands, stormwater system, and landscape buffers. Stormwater
management is challenging in this area because of its proximity to bay waters and will require treatment of 1.5 times
the volume; however, attenuation is not required. The cooperative funding project will enhance stormwater treatment in
the park by adding Low Impact Development (LID) techniques where feasible, including permeable pavers, porous
concrete, and biofiltration.
BenefitsThe project will be designed to enhance stormwater treatment through implementation of Low Impact Development
(LID) techniques. Water quality treatment will be enhanced through a series of LID techniques that will be compatible
with the park setting and require less structural components.
Costs
The estimated total project cost for implementation of Low Intensity Development (LID) elements for stormwater
treatment at Blackburn Point Park Addition is $540,000. For FY2010 the District has budgeted $100,000 for the project
with an equal match from Sarasota County. The District's FY 2010 share is split between the Manasota Basin Board
($50,000) and State SWIM ($50,000). For FY2011, the Manasota Basin Board is requested to fund $170,000 for
construction of LID elements with an equal match from Sarasota County. District funds shown in the table include
staff salaries, travel and central garage. If approved for future funding, the District's total contribution would be spread
over several fiscal years.
Additional Information
Economic feasibility and permittability: All aspects of the final design will require extensive permitting. The District will
require an Environmental Resource Permit and may require a Water Use Permit. The District may claim jurisdiction
over any wetlands or other surface waters that may be found on site and the Army Corps of Engineers will be copied
for concurrent review. The Florida Department of Environmental Protection (DEP) will require water and sewer permits
and will be coordinated with Sarasota County and the Health Department. A Generic Permit for Stormwater Discharge
from Large and Small Construction Activities is required in accordance with DEP regulations. Several public
workshops regarding the park's development have been held and the input was utilized in the creation of the concept
plan to date. The Sarasota County Development Review Committee provided comments on the concept plan on April
7, 2008 and will review the project development plans. A Scope of Services is being prepared.
021 - Manasota Basin 112
W626
Blackburn Point Park Addition
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 226,764 0 0 173,769 52,995
District Budgeted - Outside Revenue
WMLTF (SWIM) - Prior Year Funds 52,994 0 0 0 52,994
Project Funds Not Budgeted by the
District
Sarasota County 270,000 0 0 170,000 100,000
$549,758 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionDevelop Draft Agreement with Sarasota County 10/20/09 3/1/10 3/1/10
Agreement to Contracts Administration 10/30/09 3/30/10
Execution of Agreement by Sarasota County 12/15/09 5/10/10
Agreement Executed by SWFWMD 12/21/09 5/20/10
Notice to Proceed 12/30/09 5/21/10
2. ConstructionConstruction Start 1/25/10 10/30/10
Construction Complete 10/30/11
Status As Of: March 19, 2010
The agreement between the District and Sarasota County for the project is under development and should be complete
by late March 2010. New provisions developed for CFI agreements were pending approval. Final details for the project's
scope of work will be reviewed with Sarasota County staff in late March 2010. Project design has continued on schedule,
and should be ready for submittal for permit review by early summer. It is anticipated the draft agreement will be
undergoing review by both parties in April 2010, with full execution by both parties in early May 2010. The agreement is
for the construction of approved project elements which include several Low Impact Development features to be used as
part of the design for stormwater treatment.
021 - Manasota Basin 113
W627
Bradenton Beach Stormwater Retrofits
Project Type SWIM
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and RestorationFlood Protection Emergency Flood Response
Basin(s) Manasota
Bradenton BeachCooperator(s)
Project Manager NORTON, NANCY
Task Manager(s)
Status Proposed
DescriptionThis project is in response to the FY2010 Cooperative Funding request by the City of Bradenton Beach to design,
permit and construct stormwater retrofit Best Management Practices within five sub basins that discharge to Sarasota
Bay. The sub basins are delineated as; Avenue A between 24th Street and 25th Street comprising 17.5 acres, Gulf
Drive Basin at Runaway Bay and Avenue B comprising 24.2 acres, Bay Drive South from 3rd Street South to 5th
Street South draining 11.09 acres, First Street North to Bridge Street comprising 11.11 acres and Bay Drive North
between 12th Street North and 10th Street North comprising 6.5 acres. The objectives of the project include improving
water quality, providing shoreline stabilization, enhancing shoreline functions, and reducing flooding. Best
Management Practices will be implemented to stabilize the shoreline and protect existing mangroves. Project limits
include reconstruction of the city owned land for the construction of shallow grassed swales with outfall pipes. The
swales will provide treatment of stormwater through percolation and evaporation. The baffle structures will be installed
at outfall locations to provide additional treatment. The shoreline will be repaired and restored to enhance the quality
and function of the existing wetlands habitat. The City of Bradenton Beach will be responsible for ongoing maintenance
and will perform monitoring at each outfall location to establish the treatment effectiveness.
BenefitsThe project is anticipated to reduce total suspended solids (TSS) by approximately 15,000 pounds per year (80%
reduction) with implementation of the BMP's proposed in this project.
Costs
The total estimated project cost is $3,120,650. In FY2010, the total budget is $200,000, with the City of Bradenton
Beach and the District each contributing half ($100,000). The District's share was split between the Manasota Basin
Board ($50,000) and State SWIM ($50,000). The FY2011 total budget amount is $200,000, with the City of Bradenton
Beach and the District each contributing half ($100,000). The District's share is being funded entirely by the Manasota
Basin Board. Additional funds for design and construction will be budgeted in future fiscal years. District funds shown
in the table include staff salaries.
Additional Information
Since 1950, approximately 40 percent of Sarasota Bay's intertidal wetland habitat has been lost due to development
and reduction in water quality. This resulted in a decline in the aesthetic, recreational, and commercial value of the
bay, as well as a loss of habitat for native plants and animals. The SWIM Plan for Sarasota Bay outlines goals to
restore habitat throughout the bay area and reduce pollutant loads entering the bay. The objectives of this project are
consistent with these goals.
021 - Manasota Basin 114
W627
Bradenton Beach Stormwater Retrofits
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,432,975 1,275,575 0 104,951 52,449
District Budgeted - Outside Revenue
WMLTF (SWIM) - Prior Year Funds 52,448 0 0 0 52,448
Project Funds Not Budgeted by the
District
City of Bradenton Beach 1,645,075 1,275,575 169,500 100,000 100,000
$3,130,498 Total:
Prior
Funding Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Contract Development and ExecutionDraft Agreement to Management Services 12/17/09 12/17/09
Draft Agreement Returned from Management Services 1/8/10 2/11/10
Agreement Sent to Cooperator 1/15/10 2/11/10
Signed Agreement Returned from Cooperator 2/15/10
Agreement Fully Executed 2/26/10
Notice to Proceed 3/5/10
Status As Of: December 28, 2009
The agreement is routing.
021 - Manasota Basin 115
B074
Manatee - WMPlan Braden River
Project Type Basin Initiatives
AORs Strategic InitiativesFlood Protection Floodplain ManagementWater Supply Alternative Water SupplyNatural Systems Minimum Flows and Level Establishment and Monitoring
Basin(s) Manasota
City of Bradenton, Manatee County, Sarasota CountyCooperator(s)
Project Manager NGUYEN, NAM
Task Manager(s)
Status Ongoing
DescriptionThis multi-year funded project is to perform the 1) Topographic Information, 2) Watershed Evaluation, and 3)
Watershed Management Plan elements of the District's Watershed Management Program (WMP) for the BRADEN
RIVER Watershed beginning at the Bill Evers Reservoir dam and progressing upstream in southwestern Manatee
County. The watershed occupies approximately 59.0 square miles within southern Manatee County and ultimately
discharges into Manatee River and Tampa Bay, a SWIM waterbody. The WMP will address watershed issues of rapid
growth, flood damage, and water supply. Residential development is occurring in the upper portions of the watershed
where Federal Emergency Management Agency (FEMA) flood level information is suspect. In addition, competition for
the surface water resource has increased as a result of residential development within the watershed. Surface water
runoff is currently used as a potable supply for the City of Bradenton via the Bill Evers Reservoir. In the future, surface
water use will be expanded through the use of stormwater as a non-potable source for irrigation of new residential
developments.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies and 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain management and water quality management .
Costs
The current budget amount for this project is $1.279 million, of which the District's share is $654,000 funded by the
Manasota Basin. Manatee County is contributing $379,700, Sarasota County is contributing $89,200, and the City of
Bradenton is contributing $156,100. FY2009 funding includes $200,000 with the Manasota Basin funding $114,500
and revenue of $69,800 from Manatee County and $15,700 from Sarasota County. Previously approved FY2005
funding included $110,000 with the Manasota Basin funded $55,000 and revenue of $31,600 from Manatee County,
$7,500 from Sarasota County, and $15,900 from the City of Bradenton. Previously approved FY2004 funding included
$280,500 with revenue of $157,300 from Manatee County, $33,000 from Sarasota County, and $90,200 from the City
of Bradenton. Previously approved FY2003 funding included $484,500 with the Manasota Basin funded $280,500 and
revenue of $121,000 from Manatee County, $33,000 from Sarasota County, and $50,000 from the City of Bradenton.
Previously approved FY2002 funding included $204,000 with the Manasota Basin funded $204,000. When each
element is completed the project budget may require refinement based on the information gathered. The District
funding amounts shown in the table include staff salaries.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. A cooperative funding revenue
agreement with Manatee County, Sarasota County, and the City of Bradenton has been executed as a multi-year
funded project. District staff is managing the project and has entered into a consultant services agreement to
accomplish project tasks. As part of the project, a surface water capacity assessment will be performed concurrently
with the Watershed Management Plan to evaluate surface water management policies and their effect on existing
users, water quantity, and water quality. Future cooperative funding requests and agreements will be required for
establishment of LOS, the analysis of BMP alternatives, the Implementation of BMPs, and Maintenance of Watershed
Parameters and Models.
021 - Manasota Basin 116
B074
Manatee - WMPlan Braden River
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 849,627 0 0 830,839 8,652 10,136
District Budgeted - Outside Revenue
Bradenton - WMPlan Braden River
(B074)
156,100 0 0 156,100 0 0
Manatee - WMPlan Braden River
(B074)
379,683 0 0 379,683 0 0
Sarasota - WMPlan Braden River
(B074)
89,217 0 0 89,217 0 0
$1,474,627 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesRecognition of District, Basin Board, City & County on reports 12/17/02
2. Cooperative AgreementCoop Agreement Executed by Manatee County 5/30/02 12/17/02
Coop Executed by Sarasota County 5/30/02 3/11/03
Coop Executed by City of Bradenton 5/30/02 3/17/03
Coop Executed by the District 7/30/02 4/23/03
Execute Amendment #1 to Cooperative Agmt 1/30/05 1/27/05
Execute Expired Coop. Agreement 2003REV0020-A 1/31/07 3/7/07
Execute Expired Coop. Agreement 2003REV0020-B 1/31/08 7/9/08
Execute new Coop. Agrmt. (2003REV0020-C) 2/26/10
Cooperative Agmt Close-out 9/30/10
3. Consultant Services AgreementExecute new Consultant Agrmt. (03CONC00015-B) 6/15/09 6/15/09
3. Consultant Services AgreementExecuted Consultant Agmt 7/20/03 7/21/03
Notice to Proceed 7/20/03 7/21/03
Commence Element 1, Digital Topographic Information 7/21/03 7/21/03
Commence Element 2, Watershed Evaluation 7/21/03 7/21/03
Complete Element 1, Digital Topographic Information 5/11/04 9/21/04 7/1/05
Execute Amendment #1 to Consultant Agmt 12/29/04 12/29/04
Complete Element 2, Watershed Evaluation 1/21/05 7/21/06
Commence Element 3, Watershed Management Plan 1/21/05 9/30/06 12/15/04
Execute Expired Consultant Agmt (03CONC00015-A) 9/21/06 8/29/06
Execute Amendment #1 to Expired Consultant Agmt (03CONC00015-A) 1/31/08 1/28/08
Complete Element 3, Watershed Management Plan 6/30/10
Consultant Agmt Close-out 6/30/10
Status As Of: February 22, 2010
A Request for Proposals was advertised on October 4, 2002 to perform the Braden River Watershed Management
Program from which 8 responses were received. Singhofen and Associates (SAI) was chosen as the top consultant and
board recommendation to negotiate and enter into a contract with SAI. The Cooperative Funding Agreement between the
District, the City of Bradenton, and Manatee and Sarasota Counties was executed on April 23, 2003. The First
Amendment to the Revenue Agreement to include additional FY2005 funds was executed on January 27, 2005.
Likewise, the amendment to the Consultant Services Agreement with Singhofen and Associates (SAI) was executed and
021 - Manasota Basin 117
B074
Manatee - WMPlan Braden River
was effective as of December 1, 2004. The consultant services agreement has been amended to extend the contract
termination date and revise the project schedule. The cooperative agreement has, likewise, been amended to extend the
contract termination date to December 31, 2007. SAI's Work Order #2 was executed on February 11, 2004. Work Order
#2 tasks include a detailed watershed reconnaissance, the development of a Digital Terrain Model that represents the
current watershed conditions, and a subbasin and watershed connectivity inventory in GIS database format. SAI has
completed all the deliverables for Work Order #2, which includes recent color orthophotographs, digital topographic
information, GIS geodatabase of field reconnaissance/secondary survey data to date (40% effort), and supporting
documentation for the selection of storm events for model calibration and verification. Work Order #3 with SAI, to
complete the Watershed Evaluation element and begin development of the Watershed Management Plan, has been
executed. Notice to Proceed on Work Order #3 was effective as of December 15, 2004. Work Order #4 for the Phase 1
survey effort was executed on March 28, 2006. All task and deliverables under Work Order #4 are completed. SAI has
completed the draft final Watershed Evaluation report under Work Order #3 and additional staff comments are being
addressed. Work Order #5 for the surface water resource assessment has been executed and is currently in progress.
The consultant team has prepared a spreadsheet water budget to quantify the amount of water entering the Bill Evers
Reservoir (Ward Lake) and will serve as an input to the water quality model that is currently being calibrated. This model
and associated write-up have been transmitted to the District and local cooperators for review and comments. The draft
report on the water quality modeling effort is still being completed by the sub-consultant. The consultant is currently
developing a refined schedule and budget to complete remaining tasks. Both schedule and budget are contingent upon
collecting field measurements for remaining cross sections and hydraulic features. Two additional work orders will be
developed to complete the project--first for the remaining survey/field measurements and the second to complete the
Watershed Management Plan. SAI has selected a survey firm and is currently developing the detail scope of work,
including how the information will be delivered. Both the consultant services agreement and the cooperative agreement
for this project will need to be amended because it does not appear that the project will be completed by the end of
December 2007. The surface water resource assessment final reports (quantity & quality) are being reviewed by District
staff and cooperators. Work Order #6 is currently being developed to complete the remaining survey/field measurements
(Phase 2). The cooperative agreement and consultant services agreement have been finalized for execution, to extend
from December 31, 2007 to December 31, 2008. The surface water resource assessment (SWRA) final reports (quantity
& quality) review comments from District staff and cooperators are being addressed by the consultants. Work Order #6 is
currently being executed by the department's director and work will begin soon by the consultant to complete the
remaining survey/field measurements (Phase 2). The cooperative agreement is being routed to the cooperators for
execution to extend from December 31, 2007 to January 31, 2009. The consultant services agreement has been
executed by the District on January 28, 2008. The consultant has developed a refined schedule and budget to complete
remaining tasks. Two additional work orders will be developed to complete the project--first for the public notification,
limited public meetings with large property owners or consultant firms, and watershed parameterization and the second
to finish out the Watershed Management Plan. An additional funding of $220,000 has been requested for FY2009 to
complete the project. This cost is associated with the increased survey costs, significantly more structures in watershed
than anticipated and costs to cover public involvement not in original scope. District staff is currently developing a letter
asking the cooperators for their participation in contributing to the requested additional funding. The consultants are near
completion with the SWRA final reports, addressing comments from the District and the cooperators. Work Order #6 -
Phase 2 of the survey/field measurements has been executed and the consultant has been given notice to proceed, May
28, 2008. The cooperative agreement to extend the expiration date from December 31, 2007 to January 31, 2209 is
currently with Manatee County. The requested additional funding for FY2009 to complete the project has been refined
from $220,000 to $200,000. This additional amount will be shared among Manatee County, Sarasota County and the
District. City of Bradenton is unable to contribute and their portion of contribution will be splitted among the remaining 3
sources. The cooperative agreement to extend the expiration date to January 31, 2009 has been executed on July 9,
2008. The SWRA water quality report has been finalized. The water quantity portion is being updated by the consultant.
The consultant is near completion with WO#6, Phase 2 of the survey. Work Order #7, deliverable 1 was submitted to the
District on July 14, 2008. The District provided comments to the consultant on December 9, 2008. The consultant is
currently evaluating the inclusion of the hydraulic features for some of the 192 small ponds, where construction drawings
do exist. The consultant will provide to the District a GIS layer summarizing the findings. A new cooperative agreement,
extending the termination date to September 30, 2010, has been sent to the cooperators for signatures. Likewise, a new
consultant agreement, extending the termination date to June 30, 2010, has been sent to SAI for signature. The SWRA
final reports - Quantity & Quality have been sent to the cooperators. The final deliverable for survey phase 2, WO#6 has
been submitted to the District on May 14, 2009. The new cooperative agreement is still being routed for signatures. It's
currently with Sarasota County. The new consultant agreement with SAI has been executed on 6/15/09. The last
deliverable for WO#7 has been submitted to the District and the District has completed the review. SAI is addressing the
District's comments at the moment and a GoTo meeting will be set up to discuss the results. SAI and the District will
begin coordination for WO#8 to finish the remaining tasks of the project. Current Status: The new cooperative agreement
is being routed to the City of Bradenton for signature.SAI has submitted WO#8, Deliverable on 12/23/09. District staff is
reviewing the deliverable.
021 - Manasota Basin 118
B099
Quality of Water Improvement Program - Manasota Basin
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Pinellas-Anclote River, Peace River,
Manasota
Cooperator(s)
Project Manager STOVER, KEVIN
Task Manager(s)
Status Ongoing
DescriptionPursuant to F.S. Ch. 373.206, any abandoned artesian well having a detrimental impact on the District's water
resources must be properly plugged. The District's Quality of Water Improvement Program (QWIP) provides funding
assistance to landowners to come into compliance with the statute. To increase landowner cooperation and the
number of abandoned artesian wells plugged annually, without increasing staff levels, the District's Governing Board
has allocated matching funds to augment the Alafia River, Hillsborough River, Northwest Hillsborough,
Pinellas-Anclote River, Peace River, and Manasota Basins QWIP budget to maintain the Funding Assistance Initiative
since January 1, 1994. The Funding Assistance Initiative was designed to reimburse landowners up to 100 percent of
the cost to have their abandoned artesian wells plugged, with a maximum District reimbursement of $5,000 per well
and $15,000 annually per landowner. This incentive has increased landowner cooperation and the number of wells
plugged annually. Under the 50/50 cost sharing program, QWIP plugged an average of 50 wells per year. Under the
Funding Assistance Initiative, the QWIP has reimbursed an average of approximately 200 wells per year.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 2,798,889 0 76,810 1,417,063 645,675 659,341
011 Alafia River Basin 633,615 0 29,850 603,765 0 0
013 Hillsborough River Basin 225,358 0 10,000 215,358 0 0
014 Northwest Hillsborough Basin 136,618 0 0 136,618 0 0
016 Pinellas-Anclote River Basin 112,449 0 0 112,449 0 0
020 Peace River Basin 1,052,108 0 36,960 1,015,148 0 0
021 Manasota Basin 1,704,233 0 0 1,684,233 10,000 10,000
$6,663,270 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: March 01, 2010
Since the last update 22 wells have been plugged in the Manasota Basin for a total of 2,989 wells plugged in the basin
since the program's inception. There are 15 additional wells that have been inspected and approved for plugging. Wells
plugged since last update are as follows: Sarasota County - (1) Inn on the Beach - six inch well casing to 41 feet - total
well depth 391 feet - plugging for an obstructed well no longer in use with poor WQ - District Reimbursement $4,658; (2)
Walgreens - four inch well casing to 42 feet - total well depth 100 feet - plugging for a well no longer in use - District
Reimbursement $893; (3) Steven Stenten - four inch well casing to 40 feet - total well depth 82 feet - plugging for a well
no longer in use with poor WQ - District Reimbursement $850; (4) Church of the Holy Spirit - four inch well casing to 42
feet with a total well depth unknown - plugging for a well no longer in use - District Reimbursement $383; (5) John Filak -
four inch well casing to 55 feet - total well depth 113 feet - plugging for a well no longer in use - District Reimbursement
$964; (6) Donald Grosse - four inch well casing to 45 feet with a total depth of 94 ft. - plugging for a well no longer in use
- District Reimbursement $860; (7) Gerald Horton - four inch well casing to 98 feet with a total well depth 130 feet -
021 - Manasota Basin 119
B099
Quality of Water Improvement Program - Manasota Basin
plugging for a well no longer in use - District Reimbursement $1,057; (8) Sarasota Co. Sch Bd. - six inch well casing to
46 feet - total well depth 139 feet - plugging for a, obstructed well no longer in use with poor WQ - District
Reimbursement $2,632; (9) Jonathan Hedge - four inch well casing to 40 feet with a total well depth of 110 feet -
plugging for a well no longer in use - District Reimbursement $948; (10) Suzanne Myers - four inch well casing to 58 feet
- total well depth 78 feet - plugging for an obstructed well no longer in use with poor WQ - District Reimbursement $852;
(11) City of Venice - six inch well casing to unknown depth - total well depth 335 feet - plugging for an obstructed well no
longer in use with poor WQ - District Reimbursement $3,600; (12) Carlos Juarez - four inch well casing to 63 feet with a
total well depth of 137 feet - plugging for a well no longer in use - District reimbursement $1,096: (13) SCHD/Healy - four
inch well casing to 60 feet - with a total well depth of 71 feet - plugging for a well no longer in use due to contamination in
area - District reimbursement $734: (14) Larry Loeber - four inch well casing to 40 feet - total well depth 96 feet -
plugging for a well no longer in use - District Reimbursement $871; (15) John Bilotta - four inch well casing to unknown
depth with a total depth of 105 ft - plugging for an obstructed well no longer in use - District Reimbursement $1,173; (16)
Jerry Armstrong - four inch well casing to 75 feet - total well depth 139 feet - plugging for a well no longer in use - District
Reimbursement $1,107; (17) Bobby Purdy - four inch well casing to 45 feet - total well depth 110 feet - plugging for a well
no longer in use - District Reimbursement $948; Manatee County: (1) Mantee Co.- six inch well casing to 20 feet - total
well depth 459 feet - plugging for a well no longer in use with poor WQ - District Reimbursement $3,938; (2) Manatee Co.
- six inch well casing to unknown depth with a total well depth of 160 feet - plugging for an obstructed well no longer in
use - District Reimbursement $1,793; (3) M-J Road, LLC - four inch well casing to 80 feet - total well depth unknown -
plugging for a well no longer in use - District Reimbursement $783; (4) Rising Tide Dev. - four inch well casing to
unknown depth with a total well depth 84 feet - plugging for a well no longer in use - District Reimbursement $700; (5)
John Harlee - four inch well casing to unknown depth - total well depth 102 feet - plugging for a well no longer in use -
District Reimbursement $904; (6)
021 - Manasota Basin 120
B131
Hotel/Motel/Restaurant Water Conservation Program (Water
CHAMP/PRO)Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Conservation
Basin(s) General Fund (District), Alafia River, Hillsborough River, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager ROE, MELISSA
ALTMAN, MELISSATask Manager(s)
Status Proposed
DescriptionThis Basin Initiative (BI) project provides education to hotel/motel management and guests with the goal of reducing
water use. The District provides printed materials to all participating properties to assist owners/managers in
determining ways to save water through their properties' operational processes, including, but not limited to, a towel
and linen reuse program. To build on the success of Water CHAMP, the District created the Water Program for
Restaurant Outreach (Water PRO) to promote water conservation in restaurants. The CHAMP coordinator will
promote the program through the Florida Restaurant and Lodging Association, partnerships with utility companies,
direct mail and site visits to association members and independent restaurants. Materials include a button for wait staff
to wear declaring that the restaurant serves water only upon request, information tabletop displays, children's coloring
sheets, coasters and bathroom mirror cling stickers promoting water conservation to be placed on bathroom
mirrors. Both Water CHAMP and PRO are measured for effectiveness by number of participating properties. In
addition, Water CHAMP has proven its success by conducting two water audits on participating properties in 2003 and
2008.
BenefitsWater CHAMP provides the tools and education needed to help hotel/motel staff and guests learn to conserve water.
This program measures the effectiveness of this education effort via actual water savings. The first evaluation of water
savings was conducted by the City of Tampa and Pinellas County Utilities in 2002 and showed that participants saved
an average of 20 gallons of water per occupied room per day. A five-year follow-up water audit was conducted in
cooperation with 16 utility companies to determine the current level of water savings. The audit compared water
consumption of 115 Water CHAMP participants before the program's implementation in 2002 to the amount used
in 2007. The Districtwide audit showed that participants saved an average of 17 gallons of water per occupied room
per day. The slight adjustment in water savings from the first audit to the five-year follow-up audit is attributed to a
larger representative sample of the entire District. Based on the audit results and occupancy rates it is projected
that more than 185 million gallons of water was saved by participating properties in 2009. In addition to water savings,
this program has successfully prompted a change in water-use behavior as well as increased knowledge
and awareness of the need for water conservation to protect the water resources.
Costs
The total proposed cost for the FY2011 program is $74,742 (District $1,677; Alafia River $4,756; Hillsborough River
$16,441; Coastal Rivers $6,173; Pinellas-Anclote River $17,451; Withlacoochee River $5,331; Peace River $12,116;
Manasota $10,797.) This reflects an overall decrease of 10.6%, primarily in printing costs. District funds will be used
for CHAMP/PRO properties in the Green Swamp Basin. Funds will be used to pay for CHAMP/PRO coordinator
(District temporary employee) salary, travel, printed materials and costs to educate the audience and promote the
programs through advertising, workshops, tradeshows, professional memberships, etc. The dollar amount allocated
per basin is based on anticipated work within that basin. Based on the average number of guests exposed to the
program, the estimated per person cost for the program is less than $.01. As the program grows, the cost per person
decreases. The cost benefit for the project, using the total cost amortized over five years, is $0.47 per thousand
gallons of water.
Additional Information
The total cost of the FY2010 program is $83,692 (District - $7,768; Alafia River - $3,941; Hillsborough River - $13,274;
Coastal Rivers - $6,866; Pinellas-Anclote - $16,613; Withlacoochee River - $6,107; Peace River - $15,113; Manasota
- $14,010.) The District has supported this project since FY2002. Survey results show a 98 percent approval rating
from hotel/motel guests.
021 - Manasota Basin 121
B131
Hotel/Motel/Restaurant Water Conservation Program (Water
CHAMP/PRO)
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 23,150 0 0 7,909 7,194 8,047
011 Alafia River Basin 29,309 0 0 20,324 4,889 4,096
013 Hillsborough River Basin 71,428 0 0 40,522 16,907 13,999
014 Northwest Hillsborough Basin 22,245 0 0 22,245 0 0
015 Coastal Rivers Basin 36,939 0 0 23,395 6,351 7,193
016 Pinellas-Anclote River Basin 240,764 0 0 203,736 17,982 19,046
019 Withlacoochee River Basin 34,191 0 0 21,993 5,486 6,712
020 Peace River Basin 119,267 0 0 89,469 12,493 17,305
021 Manasota Basin 112,558 0 0 86,596 11,107 14,855
District Budgeted - Outside Revenue
Tampa - Water CHAMP (B131) 5,000 0 0 0 0 5,000
$694,851 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Program begins in Pinellas 6/10/02 6/10/02
Program begins in Hillsborough 6/1/03 6/1/03
Program begins in Citrus and Hernando 9/15/04 11/10/04 11/10/04
Program begins in Manasota 10/1/04 10/1/04
Program begins in Peace River 10/1/05 10/1/05
Pilot continuing education program in Pinellas 9/1/06 8/1/08
300th property signs up 6/29/07 6/29/07
Education pilot program evaluation complete 1/31/08 4/1/10
Water PRO developed 5/15/08 5/15/08
400th property signs up 6/26/08 6/26/08
Districtwide water audit 12/31/08 10/31/08 10/31/08
Pilot restaurant conservation kit in Hillsborough 3/16/09 7/31/09 7/28/09
200th restaurant signs up 9/1/09 5/15/09
Restaurant conservation kit evaluation complete 11/1/09 6/30/10
300th restaurant signs up 12/31/09 6/30/10
Status As Of: February 23, 2010
Water CHAMP: ACTION TO DATE: On time. (1) Currently, Water CHAMP has 453 participants, representing more than
49 percent of all the hotels and 68 percent of all available rooms in the District. (2) The "Sleep Well at a Water-Saving
Hotel/Motel" directories have been updated and distributed to all five Florida welcome centers, the Tampa International
Airport's Travelers AID office, Sarasota Convention and Visitors Bureau, Tampa Bay Beaches Chamber of Commerce in
St. Pete Beach, and the Citrus County Convention and Visitors Bureau. District staff is also working with other local
tourist centers to display and distribute the Water CHAMP hotel directories. (3) Basin updates are as follows:
Pinellas-Anclote River Basin has approximately 322 properties; 136 are CHAMP properties. District staff cooperated with
Progress Energy to complete a housekeeping manual for hotels that emphasizes conserving water and energy. The
manual will be distributed during workshops in the Pinellas-Anclote, Coastal Rivers and Withlacoochee River basins. In
partnership with Progress Energy, "Do Not Disturb, We are Conserving Our Energy" door hangers were purchased from
Project Planet Corporation and are being distributed to hotels/motels within the Pinellas-Anclote River, Withlacoochee
River and Coastal Rivers basins. Hillsborough River and Alafia River basins have approximately 186 properties; 127 are
CHAMP properties. Coastal Rivers and Withlacoochee River basins have approximately 89 properties; 58 are CHAMP
properties. Manasota Basin has approximately 186 properties; 72 are CHAMP properties. Peace River Basin has
approximately 144 properties; 60 are CHAMP properties. (4) The following city and county government cable channels
021 - Manasota Basin 122
B131
Hotel/Motel/Restaurant Water Conservation Program (Water
CHAMP/PRO)are running commercials promoting Water CHAMP and Water PRO: the cities of Lakeland, St. Petersburg, Oldsmar and
New Port Richey, and the counties of Polk, Pinellas and Manatee. Water PRO: Water PRO, an extension of the Water
CHAMP program that promotes water conservation in restaurants, began in May 2008. The CHAMP coordinator
promotes the program through the Florida Restaurant and Lodging Association, partnerships with utility companies,
direct mail and site visits to association members and independent restaurants. In cooperation with the City of Tampa
and Hillsborough County, District staff created a children's restaurant conservation kit to be distributed in Hillsborough
County. Each kit includes a children's activity book, crayons and a child's tattoo. While Hillsborough County purchased
the kits ($1 each) directly from the vendor, in 2009 the City of Tampa reimbursed the District $5,000 for 5,000 kits.
Currently, there are 256 restaurants participating in Water PRO.
021 - Manasota Basin 123
B246
Water Conservation/FYN Regional Builder/Developer Specialist
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Coastal Rivers, Pinellas-Anclote River, Withlacoochee River,
Peace River, Manasota
Cooperator(s)
Project Manager DURELL, SYLVIA
Task Manager(s)
Status Proposed
DescriptionThe Water Conservation/FYN Regional Builder/Developer specialist, a Basin Initiative project, will promote
implementation of indoor and outdoor water conservation to the members of the building industry, government
employees and green building groups. The specialist will train and provide expert advice to landscape
professionals involved in the District's Florida Water StarSM programs. In addition, the specialist will act as liaison for
government employee trainings. Effectiveness will be measured by the number of professional landscapers and
irrigation system installers who incorporate the FWSG criteria in their projects. Education will be accomplished
through one-on-one outreach, trainings and promotion of the programs' benefits at meetings of industry groups and
local governments. The program's goal is to educate 15 builders, 15 landscape professionals and 15 irrigation
specialists in FY2011.
BenefitsIf funded, the program will continue to educate builders, developers, and landscape and irrigation professionals on the
water conservation and water quality protection benefits of environmental landscaping best management practices.
The specialist will also continue to support FYN coordinators with outreach to builders and developers in their
individual counties. In addition to educating on landscape best management practices, the specialist is involved
in indoor water conservation education through the FWSG program.
Costs
The total proposed cost of the FY2011 program is $77,500 (Alafia River $5,425; Hillsborough River $18,600; Coastal
Rivers $6,975; Pinellas-Anclote River $17,825; Withlacoochee River $5,425; Peace River $11,625; Manasota
$11,625). This reflects no change from FY2010. Funding is requested to provide for project coordination, program
expenses and travel expenses for outreach to all basins. The dollar amount allocated for each contributing basin is
based on population. The budget lines below include costs for staff to manage the project.
Additional Information
The total cost of the FY2010 program was $77,500 (Alafia River $5,425; Hillsborough River $18,600; Coastal Rivers
$6,975; Pinellas-Anclote River $17,825; Withlacoochee River $5,425; Peace River $11,625; Manasota $11,625).
FY2010 was the third year of funding for this outreach. Education is based on the Florida Water Star criteria and
landscape best management practices, which reference the nine Florida-Friendly LandscapingTM principles of the
University of Florida/Institute of Food and Agricultural Sciences.
021 - Manasota Basin 124
B246
Water Conservation/FYN Regional Builder/Developer Specialist
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 31,944 0 0 17,900 7,033 7,011
013 Hillsborough River Basin 80,606 0 0 38,559 21,012 21,035
014 Northwest Hillsborough Basin 21,134 0 0 21,134 0 0
015 Coastal Rivers Basin 40,174 0 0 22,966 8,583 8,625
016 Pinellas-Anclote River Basin 100,526 0 0 63,225 18,629 18,672
019 Withlacoochee River Basin 36,878 0 0 22,834 7,033 7,011
020 Peace River Basin 72,389 0 0 45,878 13,233 13,278
021 Manasota Basin 66,604 0 0 40,105 13,233 13,266
$450,255 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2008Purchase order created 3/1/08 3/3/08
First task report 3/31/08 3/31/08
Second task report 4/30/08 4/30/08
Third task report 5/31/08 5/31/08
Fourth task report 6/30/08 6/30/08
Fifth task report 7/31/08 7/31/08
Sixth task report 8/31/08 8/31/08
Seventh task report 9/30/08 9/30/08
Eighth task report 10/31/08 10/31/08
Ninth task report 11/30/08 11/28/08
Tenth task report 12/31/08 12/31/08
Eleventh task report 1/30/09 1/30/09
Twelfth task report 2/27/09 2/27/09
Project ends 2/28/10 2/28/09
FY2009Purchase order created 3/1/09 3/13/09 3/13/09
First task report 3/31/09 3/31/09
Second task report 4/30/09 4/30/09
Third task report 5/29/09 5/29/09
Fourth task report 6/30/09 6/30/09
Fifth task report 7/31/09 7/31/09
Sixth task report 8/31/09 8/31/09
Seventh task report 9/30/09 9/30/09
FY2010Purchase order created 10/1/09 12/3/09 12/3/09
Purchase order extended 10/12/09 10/12/09
First task report 11/5/09 11/5/09
Second task report 12/4/09 12/4/09
Third task report 1/5/10 1/5/10
Fourth task report 2/5/10 2/5/10
Fifth task report 3/5/10
Sixth task report 4/5/10
Seventh task report 5/5/10
Eighth task report 6/4/10
Ninth task report 7/5/10
021 - Manasota Basin 125
B246
Water Conservation/FYN Regional Builder/Developer Specialist
Tenth task report 8/5/10
Eleventh task report 9/6/10
Twelfth task report 10/5/10
Status As Of: February 18, 2010
ACTION TO DATE: On time. Among other efforts, Angela Maraj, the water conservation/FYN regional builder/developer
specialist, (1) is working with SJRWMD staff to revise content of a full-day training for landscape professionals, which
she will present in this District (2) is coordinating the District's part of the Landscape Challenge event planned for
3/12/2010 in Pasco County with FNGLA and Pay It Forward Farm. A team from the District's facilities section will
compete. (3) created a plan for a demonstration landscape at FWSG model home for a community in Dade City and
attended the certification event for the community (4) referred a builder for Ryland Homes to the Hillsborough County
Extension office after he requested landscape best management practices training for his landscape contractor (5) made
a presentation to Sustainable Sarasota and Florida House, which garnered interest in FWS being incorporated into their
Neighborhood Stabilization projects and, (6) presented information on FWS to Sarasota County government who
requested certifiers training for staff in preparation of including FWS guidelines in their ordinances.
021 - Manasota Basin 126
B274
Salt Water Intrusion Monitoring Network
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and Improvement
Basin(s) Alafia River, Manasota
Cooperator(s)
Project Manager KRAFT, CAROL
STARKS, ROBERTATask Manager(s)
Status Ongoing
DescriptionThe Salt Water Intrusion Monitoring Network (SWIMN) was developed in an effort to work closely with Water Use
Permit (WUP) holders along the coastal areas of the Southern Water Use Caution Area (SWUCA), who have wells
that are identified through groundwater modeling efforts to be most at risk for salt-water intrusion. A water quality
baseline for the wells is established through a sampling assessment of current chloride, sulfate, dissolved solids, and
electrical conductivity concentrations. After the baseline assessment, the wells are sampled by the permittees for
electrical conductivity at regular intervals, using District supplied conductivity meters. This provides an early warning
for WUP holders to plan for alternative supplies, alternative use of the land, or to take advantage of the District's
backplugging, Facilitating Agricultural Resource Management Systems (FARMS) program, and Cooperative Funding
Initiative to attempt to mitigate the problem.
BenefitsThis project monitors ground-water quality data and works closely with WUP holders to help determine the degree of
salt water intrusion experienced by the permittee in an effort to help mitigate potential impacts.
Costs
The FY2009 project cost is $33,000, with the District's General Fund contributing half ($16,500). The remaining funds
will be split between the Alafia River Basin (20 percent; $5,600) and Manasota Basin (30 percent; $10,900). This
project is expected to be ongoing. District funds shown in the table include staff salaries and overhead costs.
Additional Information
The SWIMN was established in order to track water quality in WUP well sites along the coastal areas of the SWUCA
that were predicted through modeling efforts to be at risk for salt water intrusion. Approximately 190 WUP wells have
been identified by District modeling efforts to be at varying degrees of risk of salt water intrusion. These wells have
been prioritized according to their degree of risk. Sampling of the wells predicted to be at the greatest risk has already
been conducted. The remaining wells will be sampled and WUP holders that agree to participate will be supplied with
training and equipment (conductivity meters) to periodically check water quality in their wells. All data collected is
analyzed for local trends, and WUP holders are informed of negative trends in their water quality. If it is determined
that a WUP holder is experiencing salt-water intrusion to the degree that ground water in the wells is no longer
suitable for its intended use, the permittee can explore management actions available though the District, in an
attempt to mitigate the problem.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 83,330 0 0 33,266 22,317 27,747
011 Alafia River Basin 32,146 0 0 11,153 10,636 10,357
021 Manasota Basin 56,507 0 0 22,115 17,003 17,389
$171,983 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Kick-Off Meeting 8/28/08 8/28/08
021 - Manasota Basin 127
B274
Salt Water Intrusion Monitoring Network
Complete Baseline Sampling of Candidate Wells 9/30/09
Provide conductivity meter training and support to select well owners 9/30/09
Status As Of: February 23, 2010
Reviews of associated WUPs and subsequent sampling of wells are currently ongoing. Staff is also currently evaluating
operation and training for conductivity meters for associated WUP holders. Conductivity meter training and subsequent
result reporting has been established with two WUP holders. A project status meeting was held on Feb. 23, 2010 with
internal staff from Hydrologic Evaluation, Regulation, FARMS, and the WQMP.
021 - Manasota Basin 128
B277
Florida Water Star
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) General Fund (District), Alafia River, Hillsborough River, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager DURELL, SYLVIA
Task Manager(s)
Status Proposed
DescriptionThe Florida Water StarSM (FWS) program was originated by the St. Johns River Water Management District
(SJRWMD). SJRWMD's original program, now known as FWS Silver, was used as a base for this District to create a
higher-tier version, Florida Water Star Gold (FWSG). The Silver and Gold levels are certification programs for new
home construction that provide incentives to builders and developers and encourage indoor and outdoor water
efficiency and water quality protection. They are designed to increase the knowledge level of the building industry
about water efficient building practices and to provide educational resources and incentives to make these practices
common to the marketplace. Only FWSG is promoted to builders and developers in this District. It reflects a closer
alignment to the University of Florida/Institute of Food and Agricultural Sciences' Florida Friendly LandscapingTM
principles and landscape best management practices through criteria that will reduce impacts to water quality. The
FWSG rating system is integrated into the landscape evaluation component of the Florida Green Building Coalition's
certification program and has consistency with national green building programs such as the Leadership in Energy and
Environmental Design (LEED) by the U.S. Green Building Council and Energy Star® from the Environmental
Protection Agency. As of the second quarter of FY2010, 22 properties have been certified FWS Gold and 14
companies have signed contracts to potentially build 300 homes to the program criteria. If funded, this will be the third
year of the FWS Gold program. In FY2010, staff began piloting FWS Commercial and Homeowner Retrofit programs
and efforts will continue on these programs in FY2011.
BenefitsThe program's objectives are to increase the knowledge level of efficient indoor and outdoor water use and to provide
educational resources and incentives to promote water conservation practices. Up to 50 percent of all household water
is used outside the home and inefficient or incorrectly installed irrigation can waste thousands of gallons of water each
month. Indoors, inefficient shower fixtures use an average of five gallons per minute. A leaking toilet can waste more
than 200 gallons in a single day. The FWS program criteria provide guidelines to follow that will positively impact water
resources when the program is successfully implemented. Because of the program's high profile and the involvement
of the water management districts, it is of high interest to the target audience. By providing an incentive for builders,
developers and homeowners that encourages them to incorporate best management practices, the District realizes
water savings and water quality protection. Changes in behavior occur when a builder signs a contract with the District
to build houses according to the FWSG criteria, and agrees thereafter to include water conserving elements into future
projects. Owners of new or retrofitted FWS properties receive the benefits of the indoor and outdoor water-conserving
elements of the program and can promote the certification as a marketing edge at time of resale. The program's close
partnership with the Florida Green Building Coalition (FGBC) resulted in FWSG outdoor water conservation criteria
being incorporated into the FGBC standards.
Costs
The total proposed cost of the FY2011 program is $93,365, with the District requested to contribute $48,100 and the
Basin Boards to contribute $45,265 (Alafia River $3,388; Hillsborough River $11,563; Coastal Rivers $4,350;
Pinellas-Anclote River $11,094; Withlacoochee River $3,388; Peace River $7,236; Manasota $7,246). Overall program
costs have decreased slightly since FY2010. The dollar amount allocated per contributing basin is based on
population. Funding will provide for salary and travel for a project coordinator to manage the program, support for
education outreach and contractual services related to the delivery of the program. The budget lines below include
costs for staff to manage the project.
Additional Information
The total cost of the FY2010 program was $94,500, with the District contributing $47,250 and the Basin Boards
contributing $47,250 (Alafia River $3,500; Hillsborough River $12,000; Coastal Rivers $4,500; Pinellas-Anclote River
$11,500; Withlacoochee River $3,500; Peace River $7,500; Manasota $7,500). This was the second year of funding
for the FWS program. FWS programs support the Governor's Climate Change Initiative by promoting public
021 - Manasota Basin 129
B277
Florida Water Star
protection, wise use and management of natural resources. A residential FWS program (Bronze) and programs for
commercial buildings and communities are being developed and piloted by SJRWMD, with input from SFWMD and
this District.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 154,076 0 0 52,340 50,512 51,224
011 Alafia River Basin 14,548 0 0 4,561 4,995 4,992
013 Hillsborough River Basin 36,535 0 0 8,561 13,974 14,000
014 Northwest Hillsborough Basin 5,061 0 0 5,061 0 0
015 Coastal Rivers Basin 17,477 0 0 5,561 5,957 5,959
016 Pinellas-Anclote River Basin 39,500 0 0 14,061 12,701 12,738
019 Withlacoochee River Basin 15,545 0 0 5,561 4,995 4,989
020 Peace River Basin 29,366 0 0 10,061 9,654 9,651
021 Manasota Basin 26,784 0 0 9,061 8,853 8,870
$338,892 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2009Request for quotes issued 10/15/08 10/15/08
Purchase order/scope of work created 11/15/08 11/12/08
First task report 11/30/08 11/30/08
Second task report 12/30/08 12/30/08
FWS/FWSG certifier training 1/16/09 1/16/09
Third task report 1/30/09 1/30/09
Fourth task report 2/27/09 2/27/09
First home kick-off event 3/25/09 3/25/09
Fifth task report 3/31/09 3/31/09
Second house certified 4/17/09 4/17/09
Sixth task report 4/30/09 5/4/09 5/4/09
Seventh task report 5/29/09 5/29/09
Eighth task report 6/30/09 6/30/09
Ninth task report 7/31/09 7/31/09
Third house certified 8/18/09 8/18/09
Tenth task report 8/31/09 8/31/09
Eleventh task report 9/30/09 9/30/09
Twelfth task report 10/30/09 11/5/09 11/5/09
Project complete 10/31/09 12/15/09 12/15/09
FY2010First task report 12/4/09 12/4/09
Second task report 1/5/10 1/5/10
Third task report 2/5/10 2/5/10
Fourth task report 3/5/10
Fifth task report 4/5/10
Sixth task report 5/5/10
Seventh task report 6/4/10
Eighth task report 7/5/10
021 - Manasota Basin 130
B277
Florida Water Star
Ninth task report 8/5/10
Tenth task report 9/6/10
Eleventh task report 10/5/10
Status As Of: February 18, 2010
On 3/25/2009, a model home in the Glencairn Cottages community in Dunedin (Pinellas County) was the first house to
be certified as FWSG in the District and the state. Since then, twenty-two homes have been certified. As of the end of
FY2009, 14 companies have signed intent agreements with the District with a potential of 305 homes being built under
the program. Through the partnership with the affordable housing builder, Florida Home Partnership, Inc. (FHP), 13
homes have been certified in FHP's Wimauma community and one has been certified in a Dade City community. FHP
expects that 100 homes will eventually be certified in Wimauma and at least 40 in Dade City. Builders with certified
projects were recognized in February at Alafia River, Pinellas-Anclote River, Manasota and Withlacoochee River Basin
Board meetings. Two certification events were held in February, both of which were the first in their counties. The first
Pasco County home certified is the FHP model home at the Sunset Hills community in Dade City. The event attracted
approximately 65 people. A congratulatory letter from the office of Senator Bill Nelson was sent to FHP and copied to the
District. The second event was for a single home in Hernando County. Approximately 20 people attended. The first FWS
commercial project in the District is nearing completion in Lakeland.
021 - Manasota Basin 131
B310
Manatee - Maintenance of Watershed Parameters and Models
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
Cooperator(s)
Project Manager NGUYEN, NAM
MCCLUNG, GORDON, WEVER, DONNA, BROWN, GWEN, HAMMOND, MARKTask Manager(s)
Status Proposed
DescriptionThis is a basin initiative to fund the Maintenance of Watershed Parameters and Models element of the District's
Watershed Management Program (WMP) in Manatee County. This process will be applied to watersheds where the
parameters and model(s) were developed or updated based on the District's Guidelines and Specifications (G&S) and
where parameters from Environmental Resource Permitting (ERP) submittals can be converted to the District's GIS
system until a model is developed. Funding will be required each year to continue maintenance. With proposed
funding the work of capturing watershed parameter changes resulting from approved ERPs, and updates to
topographic, soils and land use information will continue throughout the District. The funding will also support the peer
review and public outreach process on the preliminary floodplain results, and presenting the results to Governing
Board for approval.
BenefitsA WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality and
natural systems, while achieving flood protection. The information developed assists local governments with their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. In addition, the information provides the District with the best available
information to evaluate adverse impacts and mitigation of floodplain impacts for proposed ERPs. The most up to date
information about the watershed will be available through the continuous maintenance of watershed parameters in the
GIS database: as ERP permits are approved, new information is provided to the District through aerial topographic
mapping and the public review and comment period. If a watershed model has not been developed, the maintenance
of parameters in the GIS processes the information in a format that will save time and funding when the watershed is
modeled.
Costs
For FY2011 the funding distribution for Manatee county is as follows: Governing Board $67,635 and Manasota Basin
Board $67,635. There is no revenue from Manatee County. Previously approved FY2010 funding included $67,635
from Governing Board and $67,635 from Manasota Basin Board. The budget is based on the projected number of
approved ERP permits and the average development area within each Basin. Local government matching funds are
equally matched by Governing Board and Basin Board funds. The Governing Board is also providing funds specifically
to address public meetings and unforeseen issues with projecting the floodplains to be used in the FEMA mapping
process. The projected annual funding amount for Manatee County ranges from $200,000 to $250,000. The District
funding amounts shown in the table includes staff salaries.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the District's Strategic Priorities.
After the Topographic Information, Watershed Evaluation and Management Plan elements are completed; the
watershed parameters and models require continuous maintenance to simulate the watershed's characteristics as the
land form changes. The watershed's parameters change with the continued growth experienced in the District. If
continued maintenance of the models is not performed, the watershed parameters and model will no longer represent
the system. This limits their value in the areas of ERP and flood protection programs. A revenue agreement will be
developed with each community contributing funds towards maintenance. The District will manage the project and
enter into purchase orders and agreements to accomplish project tasks. Future funding will be required each fiscal
year to continue maintenance of watershed parameters and models. In the future those local governments with the
technical abilities to perform the maintenance activities will be encouraged to manage this effort. The District will
provide funding assistance to communities that can and those that cannot provide matching funds. Matching funds will
be requested from the Federal Emergency Management Agency (FEMA) for this basin initiative. Failure to provide
ongoing maintenance will diminish the return on the investment the District has made in their respective Watershed
021 - Manasota Basin 132
B310
Manatee - Maintenance of Watershed Parameters and Models
Management Plans.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 136,039 0 0 0 67,635 68,404
021 Manasota Basin 135,270 0 0 0 67,635 67,635
$271,309 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of:
021 - Manasota Basin 133
B315
Sarasota - Maintenance of Watershed Parameters and Models
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) General Fund (District), Manasota
Cooperator(s)
Project Manager TURNER, DAWN
MCCLUNG, GORDON, WEVER, DONNATask Manager(s)
Status Ongoing
DescriptionThis is a basin initiative to fund the Maintenance of Watershed Parameters and Models element of the District's
Watershed Management Program (WMP) in Sarasota County. This process will be applied to watersheds where the
parameters and model(s) were developed or updated based on the District's Guidelines and Specifications (G&S) and
where parameters from Environmental Resource Permitting (ERP) submittals can be converted to the District's GIS
system until a model is developed. Funding will be required each year to continue maintenance. With proposed
funding the work of capturing watershed parameter changes resulting from approved ERPs, and updates to
topographic, soils and land use information will continue throughout the District. The funding will also support the peer
review and public outreach process on the preliminary floodplain results, and presenting the results to Governing
Board for approval.
BenefitsA WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality and
natural systems, while achieving flood protection. The information developed assists local governments with their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. The information also provides the District with the best available information to
evaluate adverse impacts and mitigation of floodplain impacts for proposed ERPs. In addition, as ERP permits are
approved, new information is provided to the District through aerial topographic mapping and the public review and
comment period. If a watershed model has not been developed, the maintenance of parameters in the GIS processes
will allow the ERP information to be captured in a format that will save time and funding when the watershed is
modeled. As a result, the most up to date information about the watershed will be available in the District's GIS
database.
Costs
For FY2010 the funding distribution for Sarasota county is as follows: Governing Board $64,420; and Manasota Basin
$64,420. The budget is based on the projected number of approved ERP permits and the average development area
within each Basin. The Governing Board is also providing funds specifically to address public meetings and
unforeseen issues with projecting the floodplains to be used in the FEMA mapping process. Future funding represents
an annual cost to continue maintenance.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the District's Strategic Priorities.
After the Topographic Information, Watershed Evaluation and Management Plan elements are completed; the
watershed parameters and models require continuous maintenance to simulate the watershed's characteristics as the
land form changes. The watershed's parameters change with the continued growth experienced in the District. If
continued maintenance of the models is not performed, the watershed parameters and model will no longer represent
the system. This limits their value in supporting the District's Resource Regulation and flood protection programs.
A revenue agreement will be developed with each community contributing funds towards maintenance. The District
will manage the project and enter into purchase orders and agreements to accomplish project tasks. Future funding
will be required each fiscal year to continue maintenance of watershed parameters and models. In the future those
local governments with the technical abilities to perform the maintenance activities will be encouraged to manage this
effort. The District will provide funding assistance to communities that can manage maintenance; and accept
cooperative funding from those that cannot. Matching funds will also be requested from the Federal Emergency
Management Agency (FEMA) for this basin initiative. Failure to provide ongoing maintenance will diminish the return
on the investment the District has made in their respective Watershed Management Plans.
021 - Manasota Basin 134
B315
Sarasota - Maintenance of Watershed Parameters and Models
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 194,029 64,420 0 0 64,420 65,189
021 Manasota Basin 198,196 64,420 0 0 64,420 69,356
$392,225 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: February 18, 2010
Sarasota Co. Maintenance: Previously performed under B206. B315 funds will be used to update Watershed
Management Plans for the Hudson Bayou, Whitaker Bayou, Roberts Bay, Alligator Creek, Island of Venice, and Big
Slough watersheds. Project funds may also being used to perform Peer and Public review of the models, and generate
Digital Flood Insurance Rate Maps (DFIRMS). The County has requested that the their certified watershed models be
presented to the public for review and comment prior to use in the generation of DFIRMs. The County has also
requested that the District prepare the materials needed to present the model results at the public meetings. B315 and
B300 funds may be used to cover these costs.
021 - Manasota Basin 135
B620
Mapping and GIS
Project Type Basin Initiatives
AORs Strategic InitiativesFlood Protection Floodplain ManagementNatural Systems Natural Systems Identification and MonitoringWater Supply Regional Water Supply PlanningWater Quality Water Quality Monitoring
Basin(s) General Fund (District), Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers,
Pinellas-Anclote River, Withlacoochee River, Peace River, Manasota
N/ACooperator(s)
Project Manager DICKS, STEVE
DICKS, STEVETask Manager(s)
Status Ongoing
DescriptionThis is a continuing initiative with the goal of providing Geographic Information System (GIS), aerial photo
interpretation and photogrammetric mapping services to support Governing and Basin Board activities. GIS support
includes the input, management, analysis and distribution of spatial data, the design and implementation of databases,
software training and map production. Aerial photo interpretation includes land use and cover mapping in support of
land acquisition, Surface Water Improvement and Management (SWIM), engineering, planning and environmental
studies. Photogrammetric support includes the mapping of topographic information, collection of aerial photographs
and satellite imagery and the production of digital orthophotographs. This program also supports the distribution of
data to the public and routine maintenance activities. The annual budget includes administrative costs for salaries,
travel, training, plotting and photographic supplies, maps and other data purchases, etc.
BenefitsMapping and GIS has been a continuing activity since 1987 and is required to support the District's GIS, digital
orthophoto, aerial mapping and other data collection, maintenance and management activities. The District's GIS
database is an integral component of planning, engineering, regulatory, and land acquisition and management
activities. In a rapidly growing area such as the District, continued maintenance and expansion is needed for the GIS
database to meet new demands and is required to protect the historical investment in the system. The data are
currently accessed by over 450 District staff using the ArcGIS software, and serves as the foundation for the Water
Management and Land Resources Information Systems. Additionally, the data collected by the Mapping and GIS
Section are viewable and downloadable from the District's Internet web site.
Costs
In addition to plotting/printing supplies, office supplies and travel/training the FY2010 funding include: Adminstrative
Assistant Contractor ($30,633 - Governing Board), GIS Programming Contractor ($220,000 - Governing Board),
Parcel Updates $48,000 - Governing Board). Funds for the GIS Programming Contractor are transferred to the
Information Resources Department at the beginning of the fiscal year.
021 - Manasota Basin 136
B620
Mapping and GIS
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 2,315,566 0 (415,481) 866,780 917,800 946,467
011 Alafia River Basin 94,879 0 0 37,509 30,125 27,245
013 Hillsborough River Basin 95,354 0 0 37,984 30,125 27,245
014 Northwest Hillsborough Basin 36,559 0 0 36,559 0 0
015 Coastal Rivers Basin 94,879 0 0 37,509 30,125 27,245
016 Pinellas-Anclote River Basin 96,779 0 0 39,409 30,125 27,245
019 Withlacoochee River Basin 96,779 0 0 39,409 30,125 27,245
020 Peace River Basin 99,154 0 0 41,784 30,125 27,245
021 Manasota Basin 102,739 0 0 40,829 30,125 31,785
$3,032,688 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
The following are major activities for FY2010Transfer GIS Contractor Funds to IRD and Fill Position 10/30/09
Issue work order for parcel update. 12/30/09
Status As Of: February 08, 2010
Mapping and GIS is an ongoing support activity and to date there were no unforeseen expenditures or activities in
FY2010. The section will continue supporting ad hoc requests for GIS data as well as conducting routine data
maintenance activities. Significant activities recently completed or underway include:
Mapping and GIS is reviewing it's aerial imagery data management processes and will be removing the majority of the
data from the Oracle database over the next 12 months. This will reduce the load on the Oracle server and improve the
ability to back up and restore the data in the event of equipment failure.
Staff are currently working with cooperators on developing FY2011 project budgets.
Mapping and GIS is working with other District staff to develop a database that will serve as the official repository for all
waterbody names in our region. The database will be integrated with the federal Geographic Names Information System
(GNIS) were applicable.
ACCELERATE FLORIDA ACTION-TO-DATE: The GIS Programming Contract Funds ($220,000) have been transferred
to the Information Resources Department and have been encumbered to a private firm to provide onsite GIS
programming Services.
021 - Manasota Basin 137
B630
Field Operations 021
Project Type Basin Initiatives
AORs Strategic InitiativesNatural Systems Minimum Flows and Level Establishment and Monitoring
Basin(s) General Fund (District), Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers,
Pinellas-Anclote River, Withlacoochee River, Peace River, Manasota
N/ACooperator(s)
Project Manager HAGBERG, JEFFREY
HINKLE, RANDY, BAILEY, TIMTask Manager(s)
Status Ongoing
DescriptionAnnual field maintenance activities for this basin are generally for maintenance of well sites which include mowing,
painting, tree trimming, fence installation and repair. Various types of well sites include groundwater sampling wells,
data collection wells, and rainfall wells/gauges. Additional requirements at well sites includes erosion and access road
stabilization and maintenance. These maintenance areas are District owned, but were not acquired using Save Our
Rivers (SOR), P2000, and Forever Florida funds. In the Manasota Basin, costs are primarily for maintenance activities
at 24 well sites.
BenefitsKeeping well sites maintained for Hydrologic Data and Resource Data crews to collect data easily and in a safe
manner. In addition, maintenance requirements at well sites include materials for road stabilization and fencing repairs.
Costs
The budget includes salaries, central garage charges, rental equipment, parts, supplies, landfill disposal fees, land
maintenance materials (limerock, shell, rock, fill), and fencing repairs.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 5,622,889 0 127,000 4,322,913 546,138 626,838
011 Alafia River Basin 547,677 0 0 392,078 77,041 78,558
013 Hillsborough River Basin 4,494,453 0 600,000 3,078,181 419,777 396,495
014 Northwest Hillsborough Basin 251,043 0 0 251,043 0 0
015 Coastal Rivers Basin 502,846 0 0 373,365 67,657 61,824
016 Pinellas-Anclote River Basin 1,173,395 0 0 804,231 198,553 170,611
019 Withlacoochee River Basin 1,422,089 0 107,000 970,067 146,981 198,041
020 Peace River Basin 2,032,201 0 347,000 1,395,157 144,155 145,889
021 Manasota Basin 327,743 0 0 252,137 35,821 39,785
$16,374,336 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: February 18, 2010
Field Operations crews have mowed and maintained well and data collection sites as needed during this reporting
period.
021 - Manasota Basin 138
B733
FYN Manatee County
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Manatee County Cooperative Extension ServiceCooperator(s)
Project Manager DURELL, SYLVIA
Task Manager(s)
Status Proposed
DescriptionFYN Manatee County has been moved from the Cooperative Funding (L510) budget category to Basin Initiative
(B733). The move reflects the value of Florida-Friendly LandscapingTM education to water resources and the integral
role FYN plays in this education. The level of county support is expected to be maintained. This Florida Yards &
Neighborhoods (FYN) project will provide education on Florida-Friendly Landscaping to homeowners, students,
builders, landscape professionals and participants in Florida Water StarSM projects. In addition, the FYN coordinator
will continue specific outreach efforts to homeowners association boards and residents. Effectiveness will be
measured by the number of participants in workshops, one-on-one interactions, and school visits; potential exposure
to newspaper articles and electronic media; and distribution of education materials.
BenefitsIn past years, approximately 24,485 people have received education annually either on a one-on-one basis, at
workshops, classes and exhibits or through distribution of education materials. In addition, several million people have
been exposed each year to education through mass media outlets, such as newspaper articles and county
government television programming. Education increases knowledge and promotes behavior change related to
conservation of water and protection of water quality and natural systems.
Costs
The total proposed cost of the FY2010 program is $110,000, with the District requested to contribute
$50,000 (Manasota). Program costs have remained stable since FY2009. District funds are being requested to
support the salary and benefits for the coordinator. The program is expected to reach 24,000 Manatee County
residents at a cost to the District of approximately $2.08 per person. The budget lines below include costs for staff to
manage the project.
Additional Information
The total cost of the FY2010 program was $110,000, with the District contributing $50,000 (Manasota). The
District has funded this program since 2007. Education is based on the nine Florida-Friendly Landscaping principles
that were created by the University of Florida/Institute of Food and Agricultural Sciences (UF/IFAS) for the Florida
Yards & Neighborhoods Program: Right Plant, Right Place, Water Efficiently, Fertilize Appropriately, Mulch, Attract
Wildlife, Manage Yard Pests Responsibly, Recycle, Reduce Stormwater Runoff and Protect the Waterfront. The
following outreach was accomplished in FY2009: 3,477 individual contacts; 67 programs reaching 974 people; 467
building/green industries/FWSG contacts; 39 realtor contacts; 4 programs reaching 102 youth, 14,917 pieces of
educational literature distributed; 28 newsletter articles published online; 25,996 web site visitors; 9 yard recognitions;
7 exhibits attracting 3,500 people and 2,005 hours contributed by volunteers. Total reached: 23,485 (not including
media and web page contacts).
021 - Manasota Basin 139
B733
FYN Manatee County
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 52,412 0 0 0 52,412 0
Project Funds Not Budgeted by the
District
Manatee County 357,400 0 0 237,400 60,000 60,000
$409,812 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2008Purchase order created 10/1/07 10/18/07
First task report 1/31/08 1/31/08
Second advisory committee meeting 4/14/08 4/14/08
Second task report 4/30/08 4/17/08
Third advisory committee 7/21/08 7/21/08
Third task report 7/31/08 7/31/08
Fourth advisory committee meeting 9/18/08 10/15/08 10/15/08
Fourth task report 9/30/08 10/15/08 10/15/08
Project complete 9/30/08 9/30/08
FY2009Purchase order created 10/1/08 11/1/08 10/27/08
First task report 1/30/09 1/30/09
Second advisory committee meeting 4/14/09 4/30/09
Second task report 4/30/09 4/30/09
Third advisory committee meeting 7/14/09 7/14/09
Third task report 7/31/09 7/31/09
Project complete 9/30/09 9/30/09
Fourth task report 10/31/09 12/31/09
FY2010Purchase order created 10/12/09 11/16/09 11/16/09
First advisory committee meeting 1/28/10 1/28/10
First task report 1/29/10 1/29/10
Second advisory committee meeting 3/11/10
Second task report 4/30/10
Third advisory committee 6/10/10
Third task report 7/30/10
Fourth advisory committee meeting 9/16/10
Project complete 9/30/10
Fourth task report 10/29/10
Status As Of: February 17, 2010
ACTION TO DATE: On time. The following outreach was accomplished by the Manatee County FYN coordinator,
Michelle Atkinson, in the first task period of FY2010: 758 individual contacts; 11 programs reaching 4,328 people; 179
building/green industries/FWSG contacts; 14 programs reaching 336 youth, 2,122 pieces of educational literature
distributed; 1 newsletter articles published online; 5 newspaper articles published with a potential readership of 174,829;
34,256 web site visitors; 2 yard recognitions; 2 exhibits attracting 147 people and 60 hours contributed by 21 volunteers.
Also in this task period, Atkinson worked with Manatee County Planning and Building Departments to ensure that all
future Manatee County-owned projects include certified Florida-Friendly Landscapes. She also submitted a
recommendation that the FYN principles be referenced in the Manatee County Land Development Code. Atkinson is
coordinating the Florida-Friendly Family Festival at the Manatee Fairgrounds on March 6. The event, which will run from
9 a.m. to 3 p.m., will feature workshops on water conservation and Florida-Friendly Landscaping.
021 - Manasota Basin 140
B735
FYN Sarasota County
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota County Extension ServiceCooperator(s)
Project Manager DURELL, SYLVIA
Task Manager(s)
Status Proposed
DescriptionFYN Sarasota County has been moved from the Cooperative Funding (N143) budget category to Basin Initiative
(B735). The move reflects the value of Florida-Friendly LandscapingTM education to water resources and the integral
role FYN plays in this education. The level of county support is expected to be maintained. This Florida Yards &
Neighborhoods (FYN) project will provide education on Florida-Friendly Landscaping primarily to homeowners but will
also include outreach to local government employees, staff/associates in big box stores and garden centers, members
of garden clubs and plant societies, and participants in Florida Water StarSM projects. Effectiveness will be measured
by the number of participants in workshops, one-on-one interactions and school visits; potential exposure to
newspaper articles and electronic media; and distribution of printed education materials. Effectiveness will be
measured by the number of participants in workshops, one-on-one interactions and school visits; potential exposure to
newspaper articles and electronic media; and distribution of printed education materials.
BenefitsThis program's outreach to homeowners and students expands the very successful homeowners/community
association FYN program in Sarasota County. Education increases knowledge and promotes behavior change related
to conservation of water and protection of water quality and natural systems. Education increases knowledge and
promotes behavior change related to conservation of water and protection of water quality and natural systems.
Costs
The total proposed cost of the FY2011 program is $115,600, with the District requested to contribute $50,000
(Manasota). Program costs remain the same as in FY2010. District funds are being requested to support salary,
benefits and professional training for the coordinator. The Sarasota Bay Estuary Program has committed $10,000
toward program materials. The program is expected to reach 28,000 county residents at a cost to the District of
approximately $1.79 per person. The budget lines below include costs for staff to manage the project.
Additional Information
The total cost of the FY2010 program is $115,600, with the District contributing $50,000 (Manasota). The Sarasota
Bay Estuary Program provided $10,000 toward program materials. Education is based on the nine Florida-Friendly
Landscaping principles that were created by the University of Florida/Institute of Food and Agricultural Sciences
(UF/IFAS) for the Florida Yards & Neighborhoods program: Right Plant, Right Place, Water Efficiently, Fertilize
Appropriately, Mulch, Attract Wildlife, Manage Yard Pests Responsibly, Recycle, Reduce Stormwater Runoff and
Protect the Waterfront.
021 - Manasota Basin 141
B735
FYN Sarasota County
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 51,608 0 0 0 51,608 0
Project Funds Not Budgeted by the
District
Sarasota Bay Estuary Program 20,000 0 0 0 10,000 10,000
Sarasota County 108,600 0 0 0 55,000 53,600
$180,208 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2010Purchase order created 10/12/09 10/7/09
First advisory committee meeting 1/21/10 1/21/10
First task report 1/29/10 1/29/10
Second advisory committee meeting 4/14/10
Second task report 4/30/10
Third advisory committee meeting 7/15/10
Third task report 7/30/10
Fourth advisory committee meeting 10/15/10
Fourth task report 10/29/10
Status As Of: February 17, 2010
ACTION TO DATE: On time. The following outreach was accomplished by Sarasota County FYN coordinator, Angela
Antonucci, in the first task period of FY2010: 9 workshops/educational events with 114 attendees; 259 contacts via
telephone, email and office visits; 1 newsletter article; 1888 web site visitors; 15 media promotions potentially reaching
147,000 viewers per event and 4,420 pieces of educational materials distributed. Approximately 250 hours were donated
by 16 volunteers. Eight individual yards, the landscapes of a commercial site, Children's World Uniform Supply, and two
homeowners associations, Edmundite Residences and Golden Gate Point, received Florida-Friendly Yard recognitions
and certifications.
021 - Manasota Basin 142
P259
Youth Water Resources Education
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality MonitoringWater Supply ConservationNatural Systems Natural Systems Identification and MonitoringFlood Protection Floodplain Management
Basin(s) General Fund (District), Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers,
Pinellas-Anclote River, Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager HULL, MARY MARGARET
UNSER, SALLY, TORRUSIO, MARY, KUSHMER, KAYLIETask Manager(s)
Status Proposed
DescriptionThis Basin Initiative proposes to provide funding for a variety of water resources education programs to county school
districts, private schools, homeschool groups and nonformal educators. Program components will consist of school
board agreements, teacher training workshops, grants for classroom projects, field trip program support, Envirothon
support and educational resources for students and educators. Agreements with the majority of school districts
throughout the District continue to be proposed for annual completion, which would provide baseline water resources
education programs to students and teachers. Teacher training efforts will ensure that teachers understand and are
able to teach students about relevant basin issues. Proposed training sessions provide background information,
materials, experiences and opportunities to explore topics of importance in the basin. Teacher workshops will be
conducted by District staff and/or educators who have been trained by District staff. Participants evaluate the
effectiveness of teacher workshops, providing another method of improving performance. Workshops will include
information about the District and the basins, as well as basic hydrology and water management issues. The Splash!
school grant program proposes to provide funds to teachers for classroom water education projects centered on
current basin issues. Classroom projects will be designed to increase knowledge and understanding of the impacts of
human activities on the water resources in their basin and to effect behavior change in regard to water resources
conservation and protection. Grant projects proposed must fall into one of six categories: watersheds, water
conservation and supply, water quality, flood protection/drought education, alternative water sources or natural
systems. Proposed projects must also support the District's Strategic Plan. Measurable outcomes include
documentation and evaluation of individual mini-grants including pre- and post-assessment scores, sample student
work generated from the project, video or photographic documentation, and final reports by teachers and
representative students. Grant recipients are required to participate in annual sharing days, which provide an
opportunity for mini-grant participants to showcase their projects and provide model programs for other teachers who
would like to implement water projects in their classrooms. The District will provide a variety of educational resources
to educators and students including student newsletters with accompanying teacher's guides, water-testing equipment,
surface and groundwater models, and others. The District also will provide kits and boxes specific to water
conservation (the grades K-3 Water Conservation Kit) and watersheds (the grades K-3 Watershed Resource Box and
the grades 4-8 Watershed Education Resources Box) that teach students about the importance of water conservation
and healthy watersheds, while meeting Sunshine State Standards and preparing students for the Florida
Comprehensive Assessment Test. Each of these resources includes a big book, several smaller books, a teacher's
guide and other tools and materials used for role-playing and demonstrations. Each county has received kits and
boxes for circulation, and these materials are available through the Splash! school grant program.
BenefitsThe proposed Youth Water Resources Education project will continue to help the District meet its mission by providing
students, teachers and families with classroom materials and opportunities for hands-on learning experiences that
equip them to make informed decisions about water resources. Throughout coordination of the District's youth
education program, strong partnerships have been developed throughout public school districts, private schools,
homeschool networks, science centers, museums and organizations, colleges and universities, state departments,
local governments, girl and boy scout groups, boys and girls clubs, environmental education providers as well as
numerous non-formal educational centers.
Costs
The proposed FY2011 budget for youth education totals $906,000. Funding is shared among the basins as follows:
Alafia River $58,900; Hillsborough River $189,650; Coastal Rivers $59,200; Pinellas-Anclote River $256,250;
Withlacoochee River $59,200; Peace River $195,550; Manasota $87,250. The District is proposing to provide $12,000
in additional funding support. Budget lines below include costs for staff to manage the projects. This program directly
021 - Manasota Basin 143
P259
Youth Water Resources Education
reached 371,536 students and teachers in FY2009 through programs, outreach, teacher workshops and school
grants. An additional 525,000 students and teachers received District youth education publications and curriculum
tools during FY2009. Because most, if not all, of those involved in youth education programs also receive publications,
a conservative estimate puts District outreach (371,536) at 45 percent of the students and teachers in the District
(817,644) at a cost of $2.44 per person, which is 17% lower than the average of other District-funded youth education
projects implemented by cooperators.
Additional Information
The FY2010 budget for youth education was $906,000. Funding was shared among the basins as follows: Alafia River
$58,900; Hillsborough River $189,650; Coastal Rivers $59,200; Pinellas-Anclote River $256,250; Withlacoochee River
$59,200; Peace River $195,550; Manasota $87,250. Staff reached a total of 537,670 students and teachers in FY2009
through programs, school grants and outreach. A total of 209 school grants were completed, impacting more than
114,150 students. Water resources education program agreements with 13 separate school boards impacted more
than 53,000 students and teachers. The 19 teacher workshops involved 417 teachers who will reach more than
42,000 students per year. More than 843,000 pieces of youth education materials were distributed to students and
teachers throughout the District. In FY2010, the Youth Education Section continued its three-year program evaluation
to determine successful program elements, to identify ways to improve impact and to develop effective ways to impart
behavior change. The comprehensive evaluation conducted by an outside evaluator will conclude in FY2011.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 411,259 0 0 263,732 88,632 58,895
011 Alafia River Basin 638,046 0 0 497,245 71,357 69,444
013 Hillsborough River Basin 1,470,542 0 0 1,052,090 207,124 211,328
014 Northwest Hillsborough Basin 488,873 0 0 488,873 0 0
015 Coastal Rivers Basin 639,518 0 0 495,019 73,384 71,115
016 Pinellas-Anclote River Basin 2,937,108 0 0 2,385,704 276,972 274,432
019 Withlacoochee River Basin 630,138 0 0 488,806 71,761 69,571
020 Peace River Basin 1,729,430 0 0 1,296,442 217,924 215,064
021 Manasota Basin 887,622 0 0 672,899 112,487 102,236
District Budgeted - Outside Revenue
Hillsborough - Youth & Water Rstr Edu
(P259)
50,000 0 0 0 0 50,000
$9,882,536 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2009 Budgeted FundsProgram commence for school board agreements 8/1/08 8/1/08
Mini-grants selected 10/15/08 10/10/08
Mini-grant projects complete 5/30/09 5/29/09
School board agreement program complete 7/30/09 7/30/09
Final reports submitted to District 8/30/09 8/30/09
FY2010 Budgeted FundsProgram commence for school board agreements 8/3/09 8/28/09 8/28/09
Mini-grants selected 10/16/09 10/16/09
Mini-grant projects complete 5/29/10
School board agreement program complete 7/30/10
Final reports submitted to District 8/31/10
021 - Manasota Basin 144
P259
Youth Water Resources Education
Status As Of: February 19, 2010
ACTION TO DATE: On time. Outreach: (1) On Jan. 12, Youth Education staff judged science projects at the Oneco
Elementary School Science Fair in Manatee County. (2) Staff presented information about watersheds, groundwater and
conservation to students and families on Jan. 20 at Rushe Middle School's Science Night in Pasco County. (3) Staff
provided water cycle and conservation presentations on Jan. 21 to approximately 85 students at Jesse Keen Elementary
in Polk County. (4) Also on Jan. 21, members of the Youth Education Section participated in the Kinnan Elementary
Science Fair in Manatee County. Staff provided educational materials and demonstrated a watershed model to parents
and students. (5) Staff participated in Bauder Elementary's Science Night on Jan. 28, reaching 300 Pinellas County
students with water education resources and information. (6) During the month of February, staff provided 13
presentations at 3 schools, reaching 344 students and teachers. (7) Youth Education staff judged Hernando County
Science & Engineering Fair projects on Feb. 18. Teacher Training: (1) A Great Water Odyssey teacher training took
place at Lakewood Ranch High School on Jan. 4, reaching 20 Manatee County elementary teachers. The Great Water
Odyssey is a multidisciplinary technology-based computer program designed to increase third, fourth and fifth-grade
students' understanding of the importance of protecting and conserving Florida's water. (2) On Jan. 22, the SJRWMD
and SWFWMD co-sponsored a Great Water Odyssey workshop at the Silver River Museum in Marion County for 40
elementary teachers. (3) Lakeland Christian School hosted a Great Water Odyssey workshop on Jan. 23 for 12 Polk
County elementary teachers. (4) A two-day Project WET workshop on Feb. 9 and 16 educated 20 elementary and middle
school teachers about water resources at the District's Sawgrass Lake Park in Pinellas County. (5) Orange Lakes Resort
hosted a Project WET workshop on Feb. 20, which included 3 Polk County elementary teachers. Publications: 82,569
youth education publications have been distributed in this calendar year. More than 218,765 youth publications have
been distributed in fiscal year 2010.
021 - Manasota Basin 145
P268
Public Education
Project Type Basin Initiatives
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Hillsborough River, Coastal Rivers, Pinellas-Anclote River, Withlacoochee River,
Peace River, Manasota
Cooperator(s)
Project Manager PUTNAM, BETH
STERNBERGER, VIRGINIA, DURELL, SYLVIA, ROE, MELISSATask Manager(s)
Status Proposed
DescriptionThis Basin Initiative provides funding for a variety of projects designed to inform and educate the public about the
importance of managing and protecting the water resources. All programs align directly with one or more of the
District's areas of responsibilities, with the District's Strategic Plan and with Basin Board priorities. The District's broad
range of public education programs and materials reflect the variety of backgrounds and interests of the District's
residents and visitors. Some of the projects are implemented Districtwide with support from all the Basin Boards, while
some are basin-specific and supported only by the Basin Board(s) that will benefit from the project(s). Districtwide
programs include media messaging, educational material development, surveys and other research/evaluation
measures, Florida-Friendly LandscapingTM education, and translation services for Spanish materials. Basin-specific
programs reflect differing priorities as well as unique opportunities. Examples are Community Education Grants,
watershed education programs, exhibits and signage, special events and partnerships with local environmental
education centers, nonprofits and others.
BenefitsThe programs listed benefit the District through an increase in awareness and understanding of water management
and water resource issues, as well as an increase in behaviors that conserve and protect the District's water resources
and watersheds.
Costs
Funding for public education is budgeted within the basins for FY2011 as follows: Alafia River -- $52,223; Hillsborough
River -- $195,417; Coastal Rivers -- $62,056; Pinellas-Anclote River -- $184,035; Withlacoochee River -- $66,096;
Peace River -- $129,099; Manasota -- $95,289. In addition, the Governing Board contributes $933,212 to
support public education efforts, $525,000 of which is allocated to media messaging. Basin Board and General Fund
contributions in FY2011 for media messaging total $902,010. The cost/benefit of those reached via media messaging
is measured in impressions and is projected to cost the District less than eight hundredths of a cent per impression.
P268 funds support a variety of education and outreach efforts Districtwide. Based on the total number of people
reached through the public education materials and programs in FY2009 (1.8 million people), the cost/benefit ratio for
the remaining amount budgeted for public education in FY2011 is projected to be approximately $0.45 per person.
Budget lines below include costs for staff to manage the projects.
Additional Information
Funding for public education was budgeted within the basins for FY2010 as follows: Alafia River - $59,493;
Hillsborough River - $228,648; Coastal Rivers - $67,517; Pinellas-Anclote River - $257,106; Withlacoochee River -
$87,079; Peace River - $154,423; Manasota - $102,715. In addition the Governing Board contributed $942,490 to
support public education efforts, $525,000 of which was for media messaging. Funds support a variety of educational
and outreach efforts Districtwide. Budget lines below include costs for staff to manage the projects. Based on the total
number of people reached through the public education materials and programs in FY2008 (2,099,000+), the cost for
FY2009 is projected to be approximately $0.48 per person. This cost/benefit ratio does not include those reached via
media messaging, which is measured in impressions, and is projected to cost the District less than six hundredths of a
cent per impression. Budget lines below include costs for staff to manage the projects.
021 - Manasota Basin 146
P268
Public Education
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 6,163,431 0 755,000 3,529,039 936,902 942,490
011 Alafia River Basin 690,199 0 6,600 543,683 65,314 74,602
013 Hillsborough River Basin 1,873,597 0 38,365 1,353,877 221,079 260,276
014 Northwest Hillsborough Basin 600,036 0 8,400 591,636 0 0
015 Coastal Rivers Basin 724,425 0 11,989 556,220 74,436 81,780
016 Pinellas-Anclote River Basin 3,260,901 0 28,200 2,726,433 211,955 294,313
019 Withlacoochee River Basin 919,486 0 0 740,344 78,450 100,692
020 Peace River Basin 1,538,669 0 0 1,211,927 146,916 179,826
021 Manasota Basin 1,133,181 0 0 896,162 112,804 124,215
$16,903,925 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Barrier and Benefit SurveySurvey instrument one written 5/1/08 6/19/08
Survey one results 5/30/08 7/20/08 7/18/08
Survey instrument two written 6/20/08 9/15/08 10/24/08
Survey two results 7/18/08 11/20/08 12/18/08
Survey instrument three written 8/8/08 1/15/09 1/15/09
Survey three results 8/29/08 4/30/09 4/30/09
CBSM education intervention plans complete 9/26/08 4/30/09 6/16/09
FY2009 Community Education Grant ActivitiesApplication deadline 8/22/08 8/22/08
Basin Board Education Committee input 11/21/08 11/21/08
Announcement of allocations to CE Grant recipients 1/23/09 1/12/09 1/12/09
Basin Boards informed of grant allocations 2/13/09 1/22/09 2/22/09
Grant-recipient required workshops 2/27/09 2/27/09
End of projects' work period 7/31/09 7/31/09
Final reports due 7/31/09 8/31/09 8/31/09
Requests for reimbursements 8/31/09 8/31/09 8/31/09
FY2009 Media MessagingFall media buy 10/14/08 10/14/08
Spring plan developed 11/30/08 11/30/08
Fall media buy final report 12/30/08 12/30/08
Winter media buy 1/5/09 1/5/09
Spring media buy 3/1/09 3/1/09
Summer media buy plan 4/28/09 4/28/09
Summer media buy 5/17/09 5/15/09
Media buy final report 6/1/09 7/31/09 7/31/09
FY2010 Community Education Grant ActivitiesApplication deadline 8/21/09 8/21/09
Basin Board Education Committee input 11/20/09 11/20/09
Announcement of allocations to CE Grant recipients 1/22/10 1/11/10 1/11/10
Basin Boards informed of grant allocations 2/12/10 2/12/10
Grant-recipient required workshops 2/23/10 2/25/10 2/25/10
End of projects' work period 7/31/10
Requests for reimbursements 8/31/10
Final reports due 8/31/10
021 - Manasota Basin 147
P268
Public Education
FY2010 Media MessagingWinter media buy plan 10/30/09 11/6/09 11/6/09
Winter media buy 1/4/10 11/30/09 11/30/09
Winter media buy final report 4/30/10
FY2010 Media ResearchPO Opened 10/1/09 10/1/09
Post test 4/5/10
Focus Groups 8/30/10
Final Report 9/27/10
Pretest Survey 11/22/10 11/22/10
Pilot Irrigation ProjectFinish focus group research 9/30/07 9/30/07
Take test meter readings of pilot neighborhoods 9/30/07 10/24/07
Finish survey research 2/28/08 5/1/08 6/9/08
Develop pilot project plans 5/31/08 9/30/08 10/6/08
Begin pilot project in designated neighborhoods 7/1/08 12/1/08 12/1/08
Take meter read #1 7/31/08 12/30/08 12/30/08
Take meter read #2 8/31/08 1/31/09 2/9/09
Take meter read #3 9/30/08 3/20/09 4/10/09
Evaluate pilot program based on meter readings 10/15/08 10/15/10
Begin phase two with needed revisions 1/1/09 7/1/09 7/1/09
Take meter read #1 1/31/09 7/31/09 7/31/09
Take meter read #2 2/28/09 8/31/09 9/15/09
Take meter read #3 3/30/09 9/30/09 12/10/09
Pilot end date 3/31/09 9/30/10
WWIPPConduct campaign with pretest 7/31/09 9/30/09 10/1/09
Evaluate program impact with posttest 6/30/10
Final report and fact sheet due 8/31/10
Status As Of: March 09, 2010
Community Education Grants (CEG): The FY2010 Community Education Grant program received 70 applications
Districtwide, requesting $319,992. Staff has approved funding for 35 projects, totaling $144,052. In February, Basin
Boards were informed of funded projects and grant implementation workshops for grantees were held. The Hillsborough
County Extension's 2010 Tree and Landscape Short Course, held on February 19, educated more than 420 landscape
professionals on Florida-Friendly Landscaping principles, and best management practices. The grant implementation
period runs from March through July 2010. Florida-Friendly Landscaping Education: (1) A Hernando County half-day
workshop focusing on SB 2080 and Florida-Friendly Landscaping was held on February 26. (2) In the first task period,
the Pinellas HOA FYN coordinator, Doris Heitzmann, conducted 11 site visits; made 8 presentations to a total of 155
people and had 412 individual contacts. The Hillsborough/Polk HOA FYN coordinator, Lisa Strange, conducted 8 site
visits; made 9 presentations to a total of 247 people and had contact with 928 individuals. "Get Outside!" Campaign:
Since FY2007, the Communications, Land Resources and Community and Legislative Affairs departments have been
working together to let people know that District lands are available for recreation and to encourage more people to visit
District lands. In September 2009 the District launched the "Get Outside!" campaign to promote the recreational
opportunities available to the public on District-owned lands. Since the campaign began, 18,000 copies of the Recreation
Guide to the Southwest Florida Water Management District Lands have been distributed. There have also been 35,000
visits to revised WaterMatters.org/recreation web site, with 15,000 of those unique visitors. Staff distributed a news
release encouraging residents to get outside for Florida Hiking Trails Month in February, which resulted in articles in the
Sumter County Times, Citrus County Chronicle, Pasco Shopper, Tampa Bay Newspapers in Pinellas County and the
Greater Tampa Chamber of Commerce's eVIEW newsletter. As part of the campaign, the District is hosting three
community events to showcase District lands with the hope that those attending come back with family and friends to
enjoy these properties on their own. The first event was held at Starkey Wilderness Preserve -- Serenova Tract in Pasco
County on Nov. 7, 2009. The second "Get Outside!" community event was held at the Green Swamp Wilderness
Preserve -- Hampton Tract on Feb. 27, 2010. Despite cold and rainy conditions, 130 people attended along with 29
volunteers, including members of Boy Scout Troop 72, members of American Disability Adventures and a group of
students from Tenoroc High School. As a result of increased effort to enhance diversity at the event, members from both
the Dade City Farmworkers Self-Help group and Boys and Girls Club attended. Ninety-five attendees signed the pledge
to come back to visit Hampton. Ninety-five attendees signed the pledge to come back to visit Hampton. Staff is currently
021 - Manasota Basin 148
P268
Public Education
planning the next "Get Outside!" event at Deep Creek in DeSoto County on April 10, 2010. The event will feature similar
activities and displays as previous events. Media Messaging: The District's FY2010 media messaging campaign began
in November 2009 and ran through February 14, 2010. Two advertisements were created to reach the target audiences.
One of the ads focused on the negative consequences of over-watering lawns in the winter. The other ad explained how
to turn off an irrigation timer to skip a week of watering. This integrated campaign promoted the "Skip a Week" concept
through television, print, radio, billboard, Internet and magazine advertisements as well as utility bill stuffers and at
special events. New this year, the message was promoted on 30 wrapped buses in Hillsborough County, on banners and
signs at county extension offices, and at nine Lowe's stores. A posttest public survey is being conducted to evaluate the
effectiveness of the campaign. Research: (1) The Irrigation Literacy Evaluation, Phase II: Water-Wise Irrigation
Practices and Perceptions Campaign. University of Florida has reviewed survey data it collected within Pinellas County
during Phase I. Homeowners will be provided with information on day-of-week restrictions and seasonal irrigation
scheduling guidelines via a fact sheet, laminated irrigation system run-time card to attach to their time clock and web site
link. To measure irrigation savings, billing data will be obtained for all participating homes and compared to an equal
number of randomly selected non-participant households of similar value and parcel size. Survey packets created to
promote program participation that include an informed consent form, homeowner letter explaining the program and
initial criteria questionnaire have been submitted to District staff for review. (2) The pretest phase of the FY2010 media
research plan has been completed. Significant responses include the following: a.) six out of ten households surveyed
report having irrigation systems, b.) 86 percent of households with irrigation systems report having someone in the
household who knows how to turn off the system, and c.) nearly half of those surveyed felt they needed to water their
lawns every week year-round to keep them healthy. The posttest, which is a Districtwide telephone survey conducted
directly after the campaign in early March, will focus on the last point to see if there is any change in respondents'
attitudes regarding irrigation needs during the winter. Results will be available in late April. Watershed/Water Quality
Education: The District's watershed education efforts focus on specific behaviors, such as reducing fertilizer and
pesticide use, maintaining septic systems, conserving water, disposing of trash appropriately and picking up and
disposing of pet waste. The District continues to partner with the Tampa Bay Estuary Program to implement the
"Pooches for the Planet" program in Pinellas County. The program's goal is to reduce water quality impacts by increasing
the number of pet owners who pick up dog waste and dispose of it properly. Nearly 400 adoption kits containing valuable
coupons and educational materials about how dog waste impacts water quality have been distributed at the Pinellas
County animal shelter and the Humane Society since November. Two Pinellas County neighborhoods, Crescent Lake
and Greater Pinellas Point, have received pet waste stations and bags to encourage residents to dispose of pet waste
properly. Residents in these neighborhoods also received educational materials including door hangers and a newsletter
article reinforcing the message of proper disposal. Special Events: The District participates in special events throughout
the year as a part of its outreach efforts. At some events, the District supplies a restroom trailer that includes signage
that promotes the District's message as well as airing the District's radio ads on its sound systems. Twenty-one events
were scheduled in FY2010. Seven of these events include the restroom trailer. During January and February, the
following attendance numbers were reported: 200 people visited the District's booth at the Tampa Bay Black Heritage
Festival and approximately 6,500 visited the District's restroom trailer. A total of 2,812 visited the District's booth at the
Florida State Fair with 60,000 visiting the trailer. Due to poor weather conditions, less than 20 people visited the District's
booth at the African American Heritage Celebration.
021 - Manasota Basin 149
F032
Peace River Regional Reservoir Expansion
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager GOODWIN, AUDRIE
RAMOY, ALISON, ARMSTRONG, BRIANTask Manager(s)
Status Ongoing
DescriptionThe Peace River Regional Reservoir Expansion is an alternative water supply project that will expand the surface
water storage capacity of the Peace River Manasota Regional Water Supply Authority's water supply facilities by
constructing a six (6) billion gallon reservoir. The total cost to construct the reservoir is approximately $77 million.
BenefitsIn combination with project F033, which expands the Authority's water treatment plant capacity from 24 to 48 mgd, this
project will enable the Authority to supply up to their permitted amount of 32.7 mgd on an annual average basis.
Costs
The total estimated project cost is $77,049,654. The District's share is $38,630,837which includes District ad valorem
funding of $29,053,918 and SB444 funding of $9,576,919. The District ad valorem cost may be reduced depending on
future funding received from the State, as described in Senate Bill 444. It is anticipated that, of the District's projected
total funding contribution of $29,053,918, the District Governing Board will contribute $14,526,959, the Manasota
Basin Board will contribute $10,604,680, and the Peace River Basin Board will contribute $3,922,279. Since the low
bid for the project was 21% higher than the engineer's estimate, the Authority requested additional funding. As a result
the Peace River and Manasota Basin Boards, and the Governing Board approved an additional $3,703,704 in FY2008,
$7,812,582 in FY 2009, and $644,694 in FY2010. The FY2010 request of $644,694 is divided between the Peace
River ($600,777) and Manasota ($43,917) Basin Boards and completes the funding commitments of both Basin
Boards and Governing Board.
Additional Information
The Peace River facility is located in DeSoto County and provides potable water to residents of Charlotte, DeSoto and
Sarasota Counties. As configured in 2005, the Facility includes a surface water withdrawal from the Peace River, a
625 million gallon reservoir (85 acres), a 24 mgd surface water treatment plant, and 21 Aquifer Storage and Recovery
(ASR) wells with a total storage capacity of approximately 6 billion gallons. Because the Peace River experiences
significant periods of low flow, it is important for the Authority to have sufficient capacity to store excess flows during
wet periods for use during dry periods when river flows are insufficient to meet demands. Withdrawals from the Peace
River are prohibited when flows, as measured at the Arcadia gage, are less than 84 mgd (130 cubic feet per second
(cfs)). The Authority's customers have identified an additional demand of 15 mgd beyond the 18 mgd that is currently
provided by the Authority's Facility, for a total 2015 demand of 33 mgd. Because of the uncertainty associated with
permitting new ASR wells due to mobilization of arsenic in the aquifer, the Authority proposed removing the ASR
component of the Peace River Facility Expansion Project (F033). As a result, the Authority needed additional storage
capacity and requested amending this project to increase reservoir capacity from two (2) to six (6) billion gallons. In
October 2005, the Peace River and Manasota Basin Boards and the Governing Board approved increasing the size of
the reservoir and deleting the additional ASR wells from the Facility Expansion project. The combination of this project
and the Peace River Facility Expansion (F033) will allow the Authority to deliver a permitted capacity of 32.7 mgd to its
customers at a total cost of $167,192,854. The project is a critical component of the District's SWUCA water supply
plan by providing users in the coastal areas, where there is the greatest threat of saltwater intrusion, with supplies
other than ground water. Of the total project cost ($77 million), approximately 90 percent ($69.5 million) is expected to
be needed for construction, and the remainder for design, permitting, and administration.
021 - Manasota Basin 150
F032
Peace River Regional Reservoir Expansion
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 14,566,470 0 1,852,024 12,708,873 0 5,573
020 Peace River Basin 3,922,279 0 500,046 2,821,456 0 600,777
021 Manasota Basin 10,605,030 0 1,351,983 9,209,130 0 43,917
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
9,576,920 0 1,464,277 8,112,643 0 0
Project Funds Not Budgeted by the
District
PR/MRWSA 38,418,817 0 0 38,418,817 0 0
$77,089,516 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Design Commence 2/1/03 2/5/03
Draft Agreement returned from Contract Administration 5/1/03 6/6/07
Peace River Basin Board Approval of Agreement 6/2/03 6/13/03
Manasota Basin Board Approval of Agreement 6/2/03 6/18/03
Governing Board Approval of Agreement 6/2/03 6/24/03
Contract Executed 8/1/03 12/18/03
Notice to Proceed 8/1/03 12/18/03
Basis of Design Report 9/30/05 11/9/05
Execute Amended Agreement 12/31/05 3/28/06
Detailed Plans and Specifications 9/30/06 9/30/06
Permitting 9/30/06 5/7/07
Bidding 11/15/06 6/8/07
Award Construction Contract 11/30/06 7/25/07
50% Construction Completion 11/30/07 8/31/08
Completion of Construction 10/31/08 3/31/10 11/30/09
Contract Termination 10/1/16
Status As Of: February 24, 2010
Final design for the Regional Reservoir Expansion was completed in 2007 and the Environmental Resource Permit
(ERP)s for mitigation and reservoirs were issued respectively by April 2007 and October 2007. The Authority Board
approved the reservoir construction contract at its July 25, 2007 meeting and issued a limited notice to proceed to the
Contractor to begin initial work and permitting. In addition, the Army Corps of Engineers issued the companion permit to
the ERP on May 18, 2007. The District agreed to convey a perpetual exclusive easement and a perpetual nonexclusive
easement to the Authority by September 2007. The District will also convey a conservation easement to the DEP over
the mitigation area to satisfy permit requirements established by DEP. District and Authority staff agreed on public use
issues associated with the Reservoir Expansion project. DEP approved the commencement of construction in December
2007. The dedication ceremony was held on May 15, 2009, with FDEP Secretary Mike Sole and SWFWMD Executive
Director Dave Moore in attendance. The project reached the substantial completion milestone on June 25, 2009; five
days ahead of the updated schedule. Final Completion of Construction was granted in November 2009. By late-February
2010, the Authority stored 6 billion gallons of water, or up to the capacity of the new reservoir. All field work and punch list
items are complete, and all claim item issues have been resolved. The final reconciliatory change order, which resolves
any quantity overages/underages, was approved by the Peace River Manasota Regional Water Supply Authority Board in
November 2009. ACTION-TO-DATE: Ahead of Schedule/Complete. At the request of the Office of Governor Charlie
Crist, the District has been communicating regularly with the cooperator concerning the Governor's Accelerate Florida
initiative to stimulate Florida's economy. An information request was sent to the cooperator on October 15, 2008. District
021 - Manasota Basin 151
F032
Peace River Regional Reservoir Expansion
staff followed up in October 2008 and November 2009 regarding the cooperator's efforts to accelerate the project. The
cooperator responded, "PRMRWSA and their construction subcontractors have agreed and executed contracts with
early completion incentives. The District has allocated $7,812,582 in FY2009 funding toward this project to assist
meeting this accelerated schedule. This project met its accelerated schedule milestone in November 2009."
021 - Manasota Basin 152
F033
Peace River Facility Expansion
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager GOODWIN, AUDRIE
RAMOY, ALISON, ARMSTRONG, BRIANTask Manager(s)
Status Proposed
DescriptionThe Peace River Facility Expansion is an alternative water supply project that involves expansion of the Peace River
Manasota Regional Water Supply Authority's water treatment facilities. Whereas, F032 is for the design and
construction of a six billion gallon reservoir, this project is for the design and construction associated with expanding
the surface water treatment plant capacity from 24 to 48 mgd. Additionally, this project will construct five miles of a
20-inch pipeline from the Authority's facilities to extended areas of DeSoto County to supply up to 5.5 mgd to the
county.
BenefitsIn combination with F032, this project will enable the Authority to supply up to their permitted quantity of 32.7 mgd on
an annual average basis from the Peace River.
Costs
The total estimated project cost is $90,143,200. The District share is $44,027,800 which includes District ad valorem
funding of $28,109,508 and SB444 funding of $15,918,292. The District's ad valorem cost may be reduced depending
on future funding received from the state, as described in Senate Bill 444. It is anticipated that, of the District's
projected total funding contribution of $28,109,508, the District Governing Board will contribute $14,412,930, the
Manasota Basin Board will contribute $10,521,438, and the Peace River Basin Board will contribute $3,175,140. Since
the bid was approximately $17 million over the original engineer's estimate of probable cost, the Authority requested
additional funding. As a result the District awarded an additional $3,756,693 in 2008 Water Protection and
Sustainability Trust Funds, $8,205,398 in FY2009 District funding and $2,165,568 in FY2010 District funding toward
the project. The project has a FY2011 request of $716,354 and represents funding from the Peace Basin Board that
will maintain the contract percentages. The future funding identified for the project are contingent upon approval of
such amounts by the District Basin and Governing Boards in the annual Budget(s). The funding table below includes
lapsed 2008 Governing Board funds of $997,525.
Additional Information
The project originally included the construction of 24 Aquifer Storage and Recovery (ASR) wells for storage of excess
river flows. However, because of the uncertainty involved in permitting ASR wells due to mobilization of arsenic in the
aquifer, the Authority has deferred the ASR component of this project. The Authority provides public drinking water to
residents of Charlotte, DeSoto and Sarasota counties. As configured in 2005, the facility includes a surface water
withdrawal from the Peace River, a 625 million gallon reservoir (85 acres), a 24 mgd surface water treatment plant,
and 21 ASR wells capable of storing up to a total of six billion gallons. Because of the Peace River's seasonal flow
pattern, characterized by significant periods of low flow that are insufficient for providing potable supply, the Peace
River facility must possess the necessary capacity to capture, treat, and store high flows from the river when they
occur so that sufficient reserves are available to meet customer demand during low flow periods. The Authority's water
use permit allows them to supply up to 32.7 mgd on an annual average basis from the Peace River and prohibits
withdrawals when river flow, as measured at the Arcadia gage, is less than 130 cubic feet per second (cfs). The
reservoir and ASR wells provide water during the dry season when withdrawal from the river is prohibited to assure the
environmental health of the downstream estuary. This project also includes the design and construction of a potable
water transmission pipeline known as the DeSoto County Water Transmission Main, which extends from the Peace
River Facility south across the Peace River, then south along Hwy 17, to the Wal-Mart Distribution Facility. This supply
line is to serve potable water customers that DeSoto County Utilities has identified. The combination of this project and
the Peace River Reservoir Expansion (F032) will result in approximately 24 mgd of additional supply at a total cost of
$167,192,854. The project is a critical component of the District's SWUCA water supply plan by providing users in the
coastal areas, where there is the greatest threat of saltwater intrusion, with supplies other than ground water. Of the
total project cost ($90.1 million), approximately $84.7 million is expected to be needed for construction, and the
remainder for design, permitting, and administration.
021 - Manasota Basin 153
F033
Peace River Facility Expansion
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 15,653,935 0 163 15,647,493 706 5,573
020 Peace River Basin 3,857,438 0 44 2,700,172 716,544 440,678
021 Manasota Basin 10,351,071 0 121 8,625,544 516 1,724,890
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
15,918,289 0 0 15,918,289 0 0
Project Funds Not Budgeted by the
District
EPA Grant 9,000,000 0 0 9,000,000 0 0
PR/MRWSA 37,115,403 0 0 37,115,403 0 0
$91,896,136 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Transmission Line Design Commence 9/1/02 10/1/03
Consultant Selection 1/1/03 1/1/03
Transmission Line Design Complete 3/1/03 5/1/03
Draft Agreement to Contract Administration 4/1/03 6/9/03
Draft Agreement returned from Contract Administration 5/1/03
Transmission Line Construction Commence 6/1/03 7/30/04
Peace River Basin Board Approval of Agreement 6/2/03 6/13/03
Manasota Basin Board Approval of Agreement 6/2/03 6/18/03
Governing Board Approval of Agreement 6/2/03 6/24/03
Contract Executed 8/1/03 10/13/04
Notice to Proceed 8/1/03 10/15/04
Transmission Line Construction Complete 3/1/04 9/7/05
Construction Complete 10/31/06 1/1/06
Bidding 11/15/06 2/8/07
Award Construction Contract 11/30/06 3/19/07
Plans and Specifications 9/30/07 11/30/06
50% Completion 11/30/07 2/4/08
100% Completion 3/31/10
Contract Closeout 10/1/16
Status As Of: February 24, 2010
In February 2007, the Authority received one bid for Contract 2 for major components of the Facility Expansion. The bid
was approximately $17 million over the original engineer's estimate of probable cost. After receiving the bid, Authority
staff and the contractor negotiated a revised project cost $14 million below the original bid price. The Authority's Board
approved the revised cost and authorized staff to enter into an agreement with the contractor. Construction of the Facility
Expansion Project occured through three separate contracts. The first contract focused on site preparation. The second
contract was for construction of a maintenance building, dewatering facility, filters, storage tanks, thickeners, and
chemical feed and disinfection stations. The third contract was for construction of an operations center.
ACTION-TO-DATE: On-time/Ahead of Schedule Construction on the facility is considered 99.9 percent complete. The
project appears to be on schedule for the March 2010 Final Completion of Construction deadline. As of February,
021 - Manasota Basin 154
F033
Peace River Facility Expansion
construction of the three new finished water storage tanks (2 million gallons of storage capacity each) and site work was
completed. Current activities include addressing final punch list items. At the request of the Office of Governor Charlie
Crist, the District has been communicating regularly with the cooperator concerning the Governor's Accelerate Florida
initiative to stimulate Florida's economy. An information request was sent to the cooperator on October 15, 2008. District
staff followed up in October 2008 and November 2009 regarding the cooperator's efforts to accelerate the project. The
cooperator responded, "PRMRWSA and their construction subcontractors have agreed and executed contracts with
early completion incentives. The District has allocated $8,205,398 in FY2009 funding and $2,165,568 in FY2010 funding
toward this project to assist meeting this accelerated schedule. This project met its accelerated schedule milestone - the
new facilities have been used to treat over 3.5 billion gallons of water."
021 - Manasota Basin 155
H008
Lake Hancock Lake Level Modification
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Regional Water Supply PlanningNatural Systems Minimum Flows and Levels Recovery
Basin(s) General Fund (District), Alafia River, Peace River, Manasota
Cooperator(s)
Project Manager DOWNING, HARRY
SMITH, RANDY, LETASI, SCOTT, BLASCHKA, STEVEN, HILL, CHERYLTask Manager(s)
Status Ongoing
DescriptionThe Lake Hancock Lake Level Modification Project is part of the proposed strategy for achieving minimum flows and
levels recovery for the upper Peace River established by the District. The goal of the Lake Level Modification Project is
to store water by raising the control elevation of the existing outflow structure on Lake Hancock and to slowly release
the water during the dry season to help meet the minimum flow requirements in the upper Peace River between
Bartow and Zolfo Springs. Historically, Lake Hancock fluctuated more than a foot higher than it has during the past
several decades. The project proposes to increase the normal operating level from 98.7 feet to 100.0 feet National
Geodetic Vertical Datum (NGVD) by modifying the P-11 outfall structure. See H009 (Lake Hancock Outfall Structure
P-11 Modification) for a description of that project. This proposed project will further the District's recent efforts to
restore minimum flows in the upper Peace River, which is a major component of the District's SWUCA Recovery Plan.
As such, it is funded as a Water Supply and Resource Development (WSRD) project.
BenefitsRaising the normal operating water level of Lake Hancock to 100.0 feet NGVD will provide the storage to increase the
number of days the upper Peace River will meet minimum flows from 70 to 87 percent. It was also determined that
raising of the operating level along with other District projects will help restore wetland function for several hundred
acres of contiguous lands to Lake Hancock.
Costs
This is a multi-year funded project. Funding for this project is shared by the Governing Board (50 percent), Peace
River Basin Board (25 percent), Alafia River Basin Board (12.5 percent) and Manasota Basin Board (12.5 percent).
Basin Board funding percentages are based on Alafia, Manasota, and Peace Basin impacts to the loss of flows from
the upper Peace River Watershed from ground-water withdrawals. As of 2008, the District has budgeted $5,554,000 of
which $1,350,000 is from state appropriations and Ecosystem Trust Fund. For continued funding of future project
steps, District staff is requesting $500,000 in FY2009 for implementing the project, broken down as follows: District
$250,000 Peace River Basin Board $125,000, Manasota and Alafia River Boards each $62,500. The funding is for
design, permitting, and construction of project area mitigation and replacement of the P-11 Structure necessary to
raise the operating level of the Lake to 100 feet NGVD. Land costs are not included. In additional to H008, a
$2,500,000 was funded in FY2003 and another $2,500,000 in FY2009 through field operations (Project H009) for the
replacement of the P-11 structure.
Additional Information
This project is being conducted in 3 Steps: Step (1) provided the preliminary evaluations and incremental probable
costs for raising the normal high operating levels of Lake Hancock to 99.5, 100.0, and the target 100.5 feet from the
current level of 98.7 feet. Step (1) is complete with a recommended target level up to 100.0 feet. The results of Step 1
were presented to the boards with a staff recommendation for moving forward with Step (2) of the project in October
2004. Step (2) involves the generation of the detailed information necessary to submit a complete Conceptual
Environmental Resource Permit (ERP) Application, and to specifically identify impacts to private lands for acquisition
and other mitigation needs (environmental, facilities, etc). Major components of the Conceptual ERP include: pre and
post condition analysis; private property, dwelling, environmental, and infrastructure mitigation; outfall structure
operation characteristics; and an anticipated fluctuation schedule for the Lake. Step (3) is the implementation of the
mitigation components as specified in the Conceptual ERP. Costs for design, ERPs, and construction for
environmental and infrastructure mitigation requirements have not been determined. The Project will be coordinated
with H014 which will look at improving water quality released from the lake.
021 - Manasota Basin 156
H008
Lake Hancock Lake Level Modification
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 6,692,402 1,287,000 (9,254) 2,400,805 1,505,588 1,508,263
011 Alafia River Basin 1,683,886 321,750 0 604,683 378,140 379,313
020 Peace River Basin 3,556,022 643,500 0 1,218,917 856,846 836,759
021 Manasota Basin 1,680,798 321,750 0 601,595 378,140 379,313
District Budgeted - Outside Revenue
Ecosystem Trust Fund - Lk Hancock Lk
Level
1,050,000 0 0 1,050,000 0 0
State Approp - WRAP - Prior Year
Funds
250,000 0 0 250,000 0 0
Water Protection & Sust T.F. (Surface
Wtr Rstr)
300,000 0 0 300,000 0 0
$15,213,108 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Step (1) Preliminary Evaluation1. Preliminary Identification of Potentially Affected Parcels 10/30/02 10/30/02
2. Advertise Request for Proposals 12/20/02 12/20/02
3. Select and Approve Consulting Firm 12/30/02 12/30/02
4. Develop Project Scope of Work 12/30/02 2/27/03
5. Begin Contract Negotiations 2/27/03 3/15/03
6. Enter into Contract 5/23/03 5/14/03
7. Provide Preliminary Results 4/28/04 6/15/04
8. Board Action for Step (2) 9/27/04 10/26/04
2. Step(2) Preliminary Design and Conceptual Permitting1. Amend Contract with BCI, Inc. for Conceptual Permitting 11/3/04 11/3/04
2. Permitting of NCLF Phase III Expansion 3/29/05 3/29/05
3. NCLF Evaluation for Project Effects 3/31/05 12/20/05
4. Develop Project Mitigation Strategies 6/30/05 12/30/05
5. Approve Mitigation Strategies 8/30/05 7/25/06
6. Submit CERP Application 10/14/05 8/31/06
7. Obtain CERP 3/31/06 6/14/07
8. Board Authorization of Project 9/25/07 9/25/07
9. USACE Notice of Intent 9/26/07 12/12/07
3. Step (3) P-11 Design and Construction1. Post P-11 Request For Proposals 3/31/08 2/8/08
2. Select P-11 Engineering Firm 6/30/08 6/6/08
3. Execute Agreement - P-11 Engineering Firm 8/31/08 10/8/08
4. Notice to Proceed - P-11 Engineering Firm 9/15/08 10/29/08
5. 30% P-11 Design Completion (Conceptual) 3/8/09 3/20/09 3/20/09
6. 60% P-11 Design Completion 7/8/09 10/1/09 7/20/09
7. Submit P-11 Environmental Resource Permit 8/1/09 10/30/09 1/29/10
8. 90% P-11 Design Completion 10/8/09 11/30/09 11/24/09
9. Final P-11 Design Completion 1/8/10 3/5/10
10. Post P-11 Request For Bids 2/15/10 4/7/10
11. Select P-11 Lowest Responsive Bidder 5/15/10 7/15/10
12. Execute Agreement - P-11 Construction Contractor 6/30/10 8/16/10
13. Notice to Proceed - P-11 Construction Contractor 7/1/10 9/1/10
14. P-11 Construction Commences 8/1/10 10/4/10
021 - Manasota Basin 157
H008
Lake Hancock Lake Level Modification
15. P-11 Construction Completion 12/31/11
3. Step (3) Cemetery Drainage Improvements1. Complete Design Alternative Analysis 3/31/10
2. Submit Environmental Resource Permit 10/29/10
3. Complete Design Plans & Specifications 11/30/10
4. Begin Construction 2/28/11
5. Complete Construction 8/31/11
3. Step (3) Jacque Lee Lane & HWY 5401. Complete Design Alternative Analysis 8/2/10
2. Submit Environmental Resource Permit 11/30/10
3. Complete Design Plans & Specifications 12/31/10
4. Begin Construction 4/22/11
5. Complete Construction 12/30/11
3. Step (3) Lake Lena Run1. Complete Design Alternative Analysis 8/31/10
2. Submit Environmental Resource Permit 10/29/10
3. Complete Design Plans & Specifications 12/31/10
4. Begin Construction 5/31/11
5. Complete Construction 12/30/11
3. Step (3) OFP Flow Way1. Complete Design Alternative Analysis 8/31/10
2. Complete Design Plans & Specifications 12/31/10
3. Begin Construction 4/29/11
4. Complete Construction 9/30/11
3. Step (3) Parkway Pond Modification1. Submittal of FDOT Permits 11/19/07 3/31/10
2. Complete Design 5/31/10
3. Submit Environmental Resource Permit to FDEP 6/30/10
4. Begin Construction 8/30/10
5. Complete Construction 12/31/10
3. Step (3) River Lake Stormwater Pond1. Complete Design 11/30/08 3/30/09
2. Submit Environmental Resource Permit 1/1/09 3/17/10
3. Begin Construction 2/15/09 8/18/10
4. Complete Construction 4/15/09 11/17/10
Status As Of: February 15, 2010
Status History: The Preliminary Evaluation Report (Step 1) for Lake Hancock by BCI, Inc., is complete and was
approved by the Governing Board in October 2004 for initiating preliminary design and conceptual permitting to raise the
lake operating level from 98.7 to 100.0 feet (Step 2). With the approval of the Governing Board (October 26, 2004),
District staff amended the contract and entered into a Work Order with BCI Engineers and Scientists, Inc. to begin Step
(2) of the project on November 3, 2004. The Governing Board at their January 24, 2006 meeting authorized staff to
submit a conceptual ERP application to the FDEP and the United States Army Corps of Engineers to raise the control
elevation up to 100 feet NGVD to help meet the low flow requirements of the upper Peace River, upon reaching
agreement through a Memorandum of Agreement (MOA) with Polk County. The Board authorized staff to develop a
MOA with Polk County for the Lake Level Modification Project. With the approval of the MOA by the District at the July
2006 meeting, a Conceptual ERP application was submitted to FDEP on August 31, 2006 for permitting. A Conceptual
ERP was received from FDEP on June 14, 2007. The USACE Public Notice of Intent to permit was completed in
December 2007 and approval was later received in April 2008. District staff have met with affected property owners in
August and September, 2007 to discuss (1) project effects, (2) whether their property would be needed to implement the
project, and (3) Board meetings and schedules. Current Status: Land Resources is currently negotiating with private land
owners and purchasing their properties when successful negotiations are achieved. District staff is currently working on
FDOT permits for Highway 540 and the Polk Parkway, and has contracted with BCI, Engineers and Scientists, Inc. to
implement (Step 3), the design, permitting, and development of construction documents for mitigation required upstream
of the P-11 Structure. The District has contracted the engineering consulting firm DMK & Associates to design the new
Lake Hancock Outfall Structure (P-11). DMK has completed the P-11 90% design plans and specifications. An
application to FDEP for an ERP to construct the new P-11 structure was submitted on January 29, 2010.
ACTION-TO-DATE: On-time, this project already has an accelerated schedule and District staff will continue to make
021 - Manasota Basin 158
H008
Lake Hancock Lake Level Modification
sure the project tasks are being completed on schedule.
021 - Manasota Basin 159
H009
Lake Hancock Outfall Structure P-11 Modification
Project Type WS&R Dev.
AORs Strategic InitiativesFlood Protection Floodplain ManagementNatural Systems Minimum Flows and Levels Recovery
Basin(s) General Fund (District), Alafia River, Peace River, Manasota
Cooperator(s)
Project Manager LETASI, SCOTT
LETASI, SCOTT, GANUN, JIM, BARTLETT, MIKETask Manager(s)
Status Ongoing
DescriptionFunding under Project H009 is provided for the replacement of the Lake Hancock P-11 Water Control Structure. This
project is directly related to Project H008, Lake Hancock Lake Level Modification. Project H009 is contingent on the
successful completion of Project H008 in 3 steps: Step (1) provide the preliminary evaluations and incremental
probable costs for raising the normal high operating levels of Lake Hancock to 99.5, 100.0, and the target 100.5 feet
from the current level of 98.7 feet. Step (1) is complete with a recommended target level up to 100.0 feet. The results
of Step 1 were presented to the boards with a staff recommendation for moving forward with Step (2) of the project in
October 2004. Step (2) involves the generation of the detailed information necessary to submit a complete Conceptual
Environmental Resource Permit (ERP) Application, and to specifically identify impacts to private lands for acquisition
and other mitigation needs (environmental, facilities, etc). Major components of the Conceptual ERP include: pre and
post condition analysis; private property, dwelling, environmental, and infrastructure mitigation; outfall structure
operation characteristics; and an anticipated fluctuation schedule for the Lake. Step (3) is the implementation of the
mitigation components as specified in the Conceptual ERP. Costs for design, ERPs, and construction for
environmental and infrastructure mitigation requirements have not been determined. Once these steps have been
completed, construction documents will be completed for the replacement of Structure P-11 and the District will post a
request for bids. Funding for this project is shared by the Governing Board (50 percent), Peace River Basin Board (25
percent), Alafia River Basin Board (12.5 percent) and Manasota Basin Board (12.5 percent). Basin Board funding
percentages are based on Alafia, Manasota, and Peace Basin impacts to the loss of flows in the Upper Peace River
Watershed from ground-water withdrawals.
BenefitsRaising the normal operating water level of Lake Hancock to 100.0 feet NGVD will provide the storage to meet
approximately 50% of the Minimum Flows and Levels Requirements of the upper Peace River. It was also determined
that raising of the operating level along with other District projects will help restore wetland function for several hundred
acres of contiguous lands to Lake Hancock. Project H009 will involve the actual replacement of the present control
structure to achieve these goals.
Costs
The probable cost are projected to be a total of $5,000,000 for this structural replacement project. This cost does not
include any land acquisition costs. Funds encumbered under Project H009 were approved in FY2003 in the amount of
$2,500,000 and an additional $2,500,000 was approved in the FY2009 for implementing the structure replacement
project. The FY2009 funds are from the West Central Florida Water Restoration Action Plan FY2009 State funds. The
FY2003 and FY2009 funds do not include any land acquisition cost.
021 - Manasota Basin 160
H009
Lake Hancock Outfall Structure P-11 Modification
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 1,252,473 0 0 1,250,000 0 2,473
011 Alafia River Basin 313,325 0 0 312,500 0 825
020 Peace River Basin 625,825 0 0 625,000 0 825
021 Manasota Basin 313,325 0 0 312,500 0 825
District Budgeted - Outside Revenue
State Approp - WRAP - Prior Year
Funds
2,500,000 0 0 2,500,000 0 0
$5,004,948 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: February 15, 2010
Status History: See Project H008 for a detailed history on the project. Milestones and updates will be provided for this
project once the P-11 design has been completed. As described in the project description steps 1 and 2 have been
completed. Current Status: The engineering consulting firm DMK & Associates has been contracted to design the new
Lake Hancock Outfall Structure (P-11). Project Milestones will be followed as part of project H008 until the request for
bidders on the construction has been posted. The design process detailed in H008 has been accelerated so that
construction of the new P-11 structure (H009) can start as soon as possible.
021 - Manasota Basin 161
H015
FARMS Back-Plug Program
Project Type WS&R Dev.
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Alafia River, Peace River, Manasota
Cooperator(s)
Project Manager BRUMBAUGH, DAVID
Task Manager(s)
Status Ongoing
DescriptionPunta Gorda's in-stream drinking water reservoir is sustained by Class I surface water bodies comprised of the Shell
and Prairie Creek watersheds. In 2000, the City of Punta Gorda contacted FDEP and the District with concerns for
declining water quality trends observed in the reservoir. Investigations indicated that irrigation pumping from deep
wells was a primary source adversely impacting the watersheds through degraded agricultural runoff, ultimately
leading to a decline in water quality of the Punta Gorda reservoir downstream. In 2002, the Back-Plug Program was
initiated primarily to improve water quality in the watershed systems of the SWUCA. The back-plug program was
included in the Facilitating Agricultural Resources Management Systems (FARMS) Program in 2005.
BenefitsWell back-plugs may become a procedure recommended for agricultural growers wanting to significantly improve crop
yields by decreasing highly mineralized sources of groundwater used for irrigation, and to mitigate potential impacts to
public surface water supplies.
Costs
Qualifying landowners are reimbursed up to a maximum of $6,500 per well for back-plug procedures, with final
amounts of reimbursement determined by borehole dimensions of the back-plugged interval. The Shell, Prairie, and
Joshua Creek (SPJC) watersheds are considered priority areas for this program.
Additional Information
A brochure and webpage is available from SWFWMD summarizing the FARMS Back-Plug Program.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 740,493 0 (30,000) 697,122 28,075 45,296
011 Alafia River Basin 67,062 0 0 51,612 4,673 10,777
020 Peace River Basin 744,691 0 0 704,769 16,855 23,067
021 Manasota Basin 50,945 0 0 32,933 6,557 11,455
$1,603,191 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: February 26, 2010
A total of 64 wells have been back-plugged in the SWUCA overall to date, with 47 of these wells located in the SPJC
priority watersheds. Analytical results for samples collected from the 47 back-plugged wells in the SPJC area indicated
conductivity, total dissolved solids (TDS) and chloride were decreased by 47%, 48% and 66%, respectively, with
pumping yields reduced by 23% as a result of back-plugging procedures. For the 17 wells in the SWUCA (outside of the
SPJC area), seven wells were back-plugged in the Peace River watershed, six in the Alafia River watershed, two in the
Manatee River watershed, one in the Myakka River watershed, and one in the Horse Creek watershed. Analytical results
for all back-plugged wells combined in the SWUCA indicated conductivity, TDS and chloride were decreased by 46%,
46% and 62%, respectively. Combined SWUCA pumping yields were reduced by 24% as a result of back-plugging
procedures. Routine monitoring results of select back-plugged wells so far have indicated sustained improvements to the
021 - Manasota Basin 162
H015
FARMS Back-Plug Program
quality of groundwater used for irrigation purposes.
021 - Manasota Basin 163
H017
Facilitating Agricultural Resource Management Systems Program
Project Type WS&R Dev.
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Alternative Water Supply
Basin(s) General Fund (District), Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers,
Pinellas-Anclote River, Withlacoochee River, Peace River, Manasota
Cooperator(s)
Project Manager ORENDORFF, BILL
Task Manager(s)
Status Ongoing
DescriptionThe Facilitating Agricultural Resource Management Systems (FARMS) Program is an agricultural Best Management
Practice (BMP) cost-share reimbursement program. The program is a public/private partnership developed by the
District and the Florida Department of Agriculture and Consumer Services (FDACS). The purpose of the FARMS
initiative is to provide an incentive to the agricultural community, within the District, to implement agricultural BMPs that
will provide resource benefits that include water quality improvement; reduced Upper Floridian aquifer withdrawals;
and/or conserve, restore, or augment the area's water resources and ecology. FARMS is intended to assist in the
implementation of the District's Regional Water Supply Plan.
BenefitsThe goal for the FARMS Program is to offset 40 mgd of ground water within the District by 2025. Ground water use
reductions not only benefit the Upper Floridan aquifer but also can improve surface water quality in areas where
ground water is highly mineralized. According to the District's Water Management Information System (WMIS), there
are 6,395 permitted agricultural permits in the District, with a combined permitted annual average daily ground water
quantity of 699,485,000 gpd. Since actual use of permitted quantities is dependent on hydrologic conditions, one of the
main goals of the FARMS program is to provide cost-share that helps reduce ground water use, regardless of
hydrologic conditions. Therefore, FARMS projects not only offset ground water use with surface water but also try to
increase the overall efficiency of irrigation water use. Each project's performance is tracked to determine its
effectiveness. To date, total ground water offset accomplished through the FARMS Program by District funding has
cost $1.40 per 1000 gallons.
Costs
From the inception of the FARMS Program through FY2007 a total of $10,837,563 has been spent on FARMS
projects with $4,700,599, or 43.4 percent coming from the farming participants and $6,136,964, or 56.6 percent, from
public funding through the FARMS budget. Public funding sources for total project reimbursement is as follows: basin
boards - 6.9 percent, Governing Board - 10.3 percent, State Appropriations - 27.5 percent, and FDACS - 11.8 percent.
Additional Information
FARMS also funds a limited amount of non-project related outreach activities and data collection efforts in support of
the Program. These include: IFAS Flatwood Citrus BMP Implementation. The District will provide $50,000 to this
project for three years for a total of $150,000. This is an outreach effort by IFAS that furthers the goals of FARMS
Program in the SPJC watersheds, in addition to growers within Manatee, Hardee, Sarasota, DeSoto, and Charlotte
Counties IFAS Row Crop BMP Implementation. The District will provide $50,000 to this project for two years, and
$55,000 in the final year for a total of $155,000. This is also an outreach effort by IFAS that furthers the goals of
FARMS Program in Hillsborough, Manatee, Hardee, Sarasota, DeSoto, and Charlotte Counties. Finally for the Upper
Myakka Surface-Water Quality Monitoring Network - funding for the deployment of data sondes at seven USGS gage
sites in the UMRW has been approved. The network will assist in better understanding agricultural impacts on Flatford
Swamp and in determining the effectiveness of FARMS projects.
021 - Manasota Basin 164
H017
Facilitating Agricultural Resource Management Systems Program
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 4,377,110 0 (2,184,533) 4,350,237 1,320,778 890,628
011 Alafia River Basin 416,352 0 (98,450) 330,001 102,705 82,096
013 Hillsborough River Basin 697,292 0 (47,490) 142,123 524,667 77,992
015 Coastal Rivers Basin 2,393 0 0 0 2,393 0
019 Withlacoochee River Basin 173,308 0 (15,224) 118,300 22,698 47,534
020 Peace River Basin 1,916,310 0 (1,245,990) 2,154,299 522,698 485,303
021 Manasota Basin 1,659,040 0 241,243 1,299,199 53,431 65,167
District Budgeted - Outside Revenue
DACS - FARMS (H017) 1,450,911 0 33,495 1,417,416 0 0
Ecosystem Trust Fund - FARMS 1,770,594 0 (3,229,406) 5,000,000 0 0
State Approp - WRAP - Prior Year
Funds
166,853 0 (1,233,147) 1,400,000 0 0
Project Funds Not Budgeted by the
District
Applicant Contribution 3,086,014 0 0 3,086,014 0 0
$15,716,177 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: February 26, 2010
The FARMS Program has 85 active Board Approved projects in six of the District's nine Basins. Projected offset from the
board approved projects is 14,022,635 gallons per day (gpd). Peace River Basin The Peace River Basin has 53 board
approved active FARMS projects with a projected offset of 8,896,685 gpd. Of the 53 projects in this Basin, 34 are
operational with average groundwater offsets of approximately 4,401,416 gpd. Eleven projects are under construction in
this basin, and eight more are in the contracting process. The Peace River Basin Board includes the Shell, Prairie, and
Joshua Creek (SPJC) watershed, which is one of two priority areas designated for the FARMS Program. Thirty eight of
the 53 projects, including twenty four of the operational projects, are within the SPJC Priority area. Manasota Basin The
Manasota Basin has seventeen board approved projects with a projected offset of 4,236,555 gpd. Of the seventeen
projects in the Manasota Basin, eight are now operational, with groundwater offsets of approximately 2,238,921 gpd. One
project is under construction, and eight are in the contracting process. The Manasota Basin includes the other FARMS
priority area, the Upper Myakka River Watershed. Nine of the seventeen projects are in the Upper Myakka River
Watershed Priority area, including six of the operational projects. Hillsborough River Basin The Hilllsborough River
Basin has three board approved FARMS Projects with projected offsets of 175,650 gpd. Two projects are now
operational, with an average groundwater offset of 150,979 gpd. The other project is in the contracting process. Green
Swamp Basin FARMS has two projects in the basin. The one operational project is offsetting approximately 33,700 gpd
of groundwater and the other project is in the contracting process. Alafia River Basin The Alafia Basin has eight board
approved projects with projected offsets of 627,250 gpd. Four projects are operational with groundwater offsets of
approximately 675,659 gpd. One project is under construction and three are in the contracting phase. Withlacoochee
River Basin. The Withlacoochee River Basin has three board approved projects with projected offsets of 29,095 gpd.
One project is under construction and the other two are in the contracting process. FARMS is also providing partial
funding for four regional projects. These projects are being coordinated through the Florida Department of Agriculture
and Consumer Services. Three of them will help implement BMP programs for citrus growers and row crop farmers, and
the other is the Mini-FARMS program that is described in greater detail under project number H529.
021 - Manasota Basin 165
H024
Upper Peace River Resource Development
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water SupplyNatural Systems Minimum Flows and Levels Recovery
Basin(s) Alafia River, Peace River, Manasota
Cooperator(s)
Project Manager TURNER, DAWN
MORRIS, LISANN, HERD, KENTask Manager(s)
Status Ongoing
DescriptionThis project involves the identification and evaluation of potential water resource development projects in the upper
Peace River watershed above Zolfo Springs. The vehicle to accomplish this is the District's Watershed Management
Program (WMP). The project includes performing the 1) Topographic Information, 2) Watershed Evaluation, and 3)
Watershed Management Plan elements of the WMP. Work on the Topographic Information, Watershed Evaluation,
and Watershed Management Plan tasks for the area contributing flow to the river between the confluence with the
Peace Creek Canal and the Highway 640 bridge crossing in Homeland are nearing completion. FY2007 funds are
being used to perform Watershed Evaluation tasks for the area contributing flow to the river between the Highway 640
bridge crossing in Homeland and Zolfo Springs. These tasks include the collection of hydrologic and hydraulic
information for both the existing condition and the committed future condition reflected in approved reclamation plans.
FY2008 funds were used to evaluate a potential surface water storage area adjacent to the river. FY2009 and FY2010
funds will be used to further evaluate potential surface water storage facilities, and perform Topographic Information,
Watershed Evaluation, and Watershed Management Plan tasks. Future funding will be needed to complete the
Topographic Information, Watershed Evaluation, and Watershed Management Plan tasks for the area between
Homeland and Zolfo Springs. Preferred Best Management Practices (BMPs) will be further developed through the
Implementation of BMPs process under separate activity codes, and will require additional funding.
BenefitsThe water resource development projects that are ultimately selected for implementation will enhance low flows, water
quality, and natural systems within the upper Peace River.
Costs
The anticipated project cost is $3,150,000. For FY2010, $250,000 of project funding is appropriated in the following
Basin budgets: Governing Board ($125,000), Peace River Basin ($62,500), Alafia River Basin ($31,250), and the
Manasota Basin ($31,250). FY2010 funds will be used to complete Topographic Information, Watershed Evaluation,
and Watershed Management Plan tasks. For FY2009, $250,000 is appropriated in the following budgets: Governing
Board ($125,000), Peace River Basin ($62,500), Alafia River Basin ($31,250), and the Manasota Basin ($31,250).
$41,142 of the FY2009 funds will be used to obtain LiDAR for an area within the river floodplain that was inundated
when the original LiDAR data was obtained. The remaining FY2009 funds are being used for the technical evaluation
of suitable water storage areas adjacent to the Peace River, and to optimize design opportunities for MFL recovery.
For FY2008, $250,000 was appropriated in the following budgets: Governing Board ($125,000), Peace River Basin
($62,500), Alafia River Basin ($31,250), and the Manasota Basin ($31,250). $200,000 was used for an evaluation of a
potential surface water storage area. The remaining $50,000 of FY2008 funds was liquidated. For FY2007, $250,000
was appropriated in the following budgets: Governing Board ($125,000), Peace River Basin ($62,500), Alafia River
Basin ($31,250), and the Manasota Basin ($31,250). In FY2007, $250,000 in revenue will be received from state
appropriations and distributed as follows: Governing Board ($125,000), Peace River Basin ($62,500), Alafia River
Basin ($31,250), and the Manasota Basin ($31,250). When each element is completed the project budget and scope
may require refinement based upon the information gathered. The District funding amounts shown in the table include
staff salaries.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. In 2002, the District completed
the technical work necessary for establishing minimum flows in the upper Peace River, and the first draft of the Peace
River Cumulative Impacts Analysis Report. The Upper Peace River Watershed has been heavily impacted by mining,
development activities, and groundwater withdrawals. Proposed minimum "low" flows are currently not being met at
the Bartow and Ft. Meade gage sites. The District has developed the Southern Water Use Caution Area (SWUCA)
021 - Manasota Basin 166
H024
Upper Peace River Resource Development
Recovery Strategy that proposes concepts for development of water resource projects. Two of the concepts are
storage of wet season rainfall in surface water reservoirs for later release during periods of low or no flow; and the
hydraulic optimization of areas impacted by mining, including the reconnection of closed basin areas. Two projects,
the Upper Peace River Minimum Flow Enhancement project (H004), and the Old Lands Phosphate project (H011),
were initiated in FY2003 to accomplish similar goals. The Upper Peace River Minimum Flow Enhancement project
included funding for a feasibility analysis, and design and permitting of a surface water reservoir on reclaimed mine
land. The District evaluated a reservoir site located on the east side of the Peace River just south of County Highway
640, and began the land acquisition process. The property owner rejected the District's offer for purchase, which
terminated the efforts for this site. As part of the Old Lands Phosphate project, District staff identified other potential
reservoir locations, and areas that no longer contribute runoff to the river as a result of mining activities that could be
hydraulically reconnected. Both of these projects are consistent with the Upper Peace River Resource Development
project. Projects H004 and H011 were discontinued as individual projects, and incorporated into the Upper Peace
River Resource Development project. Alternative reservoir sites are being evaluated, and District staff are collecting
available information from property owners, mine companies, FDEP Bureau of Mine Reclamation, and others. FY2004
funds were used to complete elements of a Watershed Evaluation to identify the connectivity of the Upper Peace
River system from the confluence of Saddle Creek and Peace Creek, south to Zolfo Springs. Work Order #1 tasks
focused on the identification of system connectivity through phosphate lands located between the confluence of
Saddle Creek and Peace Creek, and Zolfo Springs. The First Amendment was executed to expand the scope of work
to complete the Watershed Evaluation tasks for the area above County Highway 640 at Homeland, and encumber
FY2005 funds. The Second Amendment was executed to prepare a Watershed Management Plan for the area that
contributes flow to the River between the confluence of Saddle Creek and the Peace Creek Canal, and Homeland;
and encumber FY2006 funds. The Watershed Management Plan element will include a water resource assessment
and an alternative analysis that will include a cost/benefit evaluation of potential water resource development projects.
A Third Amendment was executed to extend the contract expiration date from December 31, 2008 to December 31,
2009. A second Agreement was developed to encumber FY2007 funds to perform Watershed Management Program
elements for the area contributing flow to the river between the Highway 640 bridge crossing at Homeland, and Zolfo
Springs. Future funding will be needed to complete the Watershed Management Plan for the area between Homeland
and Zolfo Springs. When each task is completed the project budget will be refined based on the information
developed. The District is cooperating with FEMA to modernize the flood insurance rate maps (FIRMs) in Polk County.
Information developed with this project will be used to update the FIRMs representing this watershed.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 2,471,813 1,125,000 0 1,216,530 0 130,283
011 Alafia River Basin 571,580 281,250 0 256,469 0 33,861
020 Peace River Basin 1,127,579 562,500 0 499,968 0 65,111
021 Manasota Basin 582,787 281,250 0 267,376 0 34,161
District Budgeted - Outside Revenue
Ecosystem Trust Fund - Upper Peace
Rvr Rstr
250,000 0 0 250,000 0 0
Water Protection & Sust T.F. (Surface
Wtr Rstr)
250,000 0 0 250,000 0 0
$5,253,759 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Original AgreementDraft Original Agreement to Management Services 7/26/04 8/24/04
Draft Original Agreement returned from Management Services 8/26/04 8/25/04
Execute Original Agreement (First Agreement) 9/17/04 9/30/04
Notice to Proceed - Work Order #1 9/24/04 10/22/04
021 - Manasota Basin 167
H024
Upper Peace River Resource Development
Submittal of Final Report related to Work Order #1 4/22/05 4/22/05
Execute Contract Amendment 1 to the First Agreement 9/21/05 9/21/05
Recognition of the SWFWMD, Peace, Alafia & Manasota Basin Bds. will be
provided on all reports
10/31/05 12/31/10
Notice to Proceed - Work Order #2 for geotechnical testing 11/30/05 1/9/06
Notice to Proceed - Work Order #3 (Watershed Evaluation) 11/30/05 11/17/05
Submittal of Final Report related to Work Order #2 2/28/06 4/19/06
Notice to Proceed - Work Order #4 (Feasibility of Alternatives) 5/19/06 5/19/06
Execute Contract Amendment 2 6/2/06 7/24/06
Submittal of Final Report related to Work Order #3 6/17/06 10/3/06
Notice to Proceed - Work Order #5 for geotechnical testing 7/28/06 7/28/06
Contract Expiration - Original Agreement 7/29/06 12/31/10
Submittal of Final Report related to Work Order #5 9/28/06 3/27/07
Notice to Proceed - Work Order #6 Watershed Mgt. Plan 10/31/06 10/25/06
Submittal of Final Report related to Task 2.2.7.1 of Work Order #4 12/22/06 2/21/07
Submittal of Final Report related to Task 2.2.7.3 of Work Order #4 12/22/06 12/31/10
Submittal of Final Report related to Task 2.2.7.2 of Work Order #4 12/22/06 12/31/10
Notice to Proceed - Work Order #7 (Summary Report) 7/20/07 7/20/07
Submittal of Final Report related to Work Order #7 8/31/07 8/31/07
Notice to Proceed - Work Order #8 (Sinkhole Survey) 10/31/07 12/14/07
Submittal of Final Deliverables related to Work Order #8 1/31/08 6/10/08
Notice to Proceed - Work Order #9 (Survey) 5/31/08 5/15/09
Submittal of Final Report related to Work Order #6 11/30/08 12/31/10
1. Original AgreementFinal Deliverables WO#9 (Survey) 8/31/08 10/24/08
Notice to Proceed - Work Order #10 (Additional Field Reconnaissance) 11/10/08 11/10/08
Final Deliverables WO#10 (Additional Field Reconnaissance) 3/10/09 12/31/10 9/2/09
2. Second AgreementDraft Second Agreement to Management Services 12/1/06 5/29/07
Draft Second Agreement returned from Management Services 1/1/07 6/7/07
Execute Second Agreement - Zolfo Springs 1/31/07 7/11/07
Notice to Proceed - Zolfo Springs Work Order #1 2/9/07 7/20/07
Submittal of Final Report - Zolfo Springs WO #1 2/9/08 12/31/10
Contract Expiration - Second Agreement (Zolfo Springs) 1/31/09 12/31/10
Status As Of: February 18, 2010
An Agreement was executed with HDR to further evaluate CS-11 as a potential surface water reservoir to enhance low
flows in the upper Peace River. Tasks involved probable design criteria and conceptual cost estimates on rehabilitation
of CS-11 to a reservoir along with assisting staff with negotiations on the possible purchase of the property from the
current owner. The evaluation will build upon the feasibility assessment performed by Ardaman and Associates as part of
the Surface Water Resource Assessment Inventory and Approach Development task. Ardaman and Associates will
continue to develop the Upper Peace River Watershed Management Plan. Hydrologic and hydraulic data collected as
part of the Upper Peace River Resource Development project is also being used in the development of the Peace River
Integrated Model (P687). The Agreement (#04CON00047) with Ardaman was executed on September 30, 2004. Project
tasks focus on the area above Homeland. As part of the Watershed Management Plan, Ardaman conducted
geotechnical testing and surface water modeling to evaluate potential reservoir sites. The Ardaman evaluations indicate
CS-11 could be modified to function as a surface water reservoir. The tasks associated with Work Orders #1, #2, #3, #5,
#7, #8, & #9 have been completed, and associated final deliverables have been approved. Tasks related to Work Orders
#4, #6, & #10 are on-going. A draft of the first of 3 reports related to Work Order #4 was received on January 26, 2007.
Staff reviewed the draft, and provided comments to the consultant on January 30, 2007. Data collection for Work Order
#6 has been completed. The final report related to Work Order #6 was due on November 30, 2008. However a time
extension was granted until December 31, 2009. Work Order #7 was issued on July 20, 2007 for the preparation of a
summary report to consolidate recent geotechnical and engineering evaluation information regarding the feasibility of
using CS-11 as a water storage area for MFL recovery. The water discharged back into the river will need to be of
sufficient quantity to overcome the influence of sinkholes in and adjacent to the streambed in order to meet MFLs in the
upper river. A draft summary report was received in August 2007. Comments were provided to the consultant. Final
version of the WO#7 summary report received May 27, 2009. Work Order #8 was executed on December 14, 2007 to
survey sinkhole areas to determine if low flows can be redirected around the sinkhole features, and to identify the
021 - Manasota Basin 168
H024
Upper Peace River Resource Development
hydraulic control elevation in the streambed that may be backing water up into these features. An evaluation of the
survey data will be conducted as part of the SWUCA Recovery - Upper Peace Karst Berms (H064) project. Please refer
to the PIMS entry for H064 for further information on that project. Work Order #9 was developed to collect survey data for
several cross-sections and bridge crossings within the upper Peace River and two of its tributaries, Bear Branch and Six
Mile Creek. Notice to Proceed was issued on May 15, 2008. Notice to Proceed for Work Order #10 was issued on
November 10, 2008. Work Order #10 includes the collection of additional survey information within the City of Bartow for
areas that discharge to the Peace River. This work has been completed. The Fourth Amendment to Agreement
04CON00062 was executed to add $243,500 in FEMA funds for tasks related to the delineation of the 100 year
floodplain for the Upper Peace River above Homeland, and to perform peer and public reivew of the model results.
Notice to Proceed for Work Order #11 was issued on January 28, 2010 to perform the floodplain analysis and delineation
tasks using the FEMA funds. A second consultant services agreement (#07CC0000062) was developed to focus on the
area contributing flow to the river between Homeland and Zolfo Springs. The Second Agreement was executed on July
11, 2007. Work Order #1 was issued against the Second Agreement on July 20, 2007; and involvesthe completion of
Watershed Evaluation tasks for the area between Homeland and Zolfo Springs. Status History: The first contract,
(#04CON00047), currently encumbers $150,000 of FY2004 funds, $500,000 of FY2005 funds, and $500,000 of FY2006
funds. The Second Agreement, (#07CC0000062), encumbers $500,000 of FY2007 funds. $200,000 in FY2008 funding
was used to retain HDR to further evaluation the use of CS-11. The remaining $50,000 in FY2008 funds was liquidated.
$250,000 was budgetted in FY2009. $360,000 of H004 Upper Peace River Minimum Flow Enhancement project funds
were transferred to this project to retain a consultant to perform detailed geotechnical analyses, obtain topographic
information, prepare cost/benefit analyses, prepare preliminary and final design plans, and obtain permits needed to
construct a reservoir. The H004 funds were previously Board encumbered. The amount shown in the Prior Funding
column of the funding table has been revised to reflect the funds transferred from the H004 project. Tasks associated
with the Ardaman Work Orders #1, #2, #3, #5, #7, #8, & #9 have been completed, and associated final deliverables have
been approved. Tasks related to Ardaman Work Orders #4, #6, #10, and #11 are on-going. As of this writing, the
following has been expended: $786,237 has been invoiced and paid in accordance with the Original Agreement with
Ardaman; $404,159 has been invoiced, and $292,362 has been paid in accordance with the Second Agreement with
Ardaman; and $41,142 has been expended to obtain additional LiDAR data. Of the $250,000 in FY2009 funding, $15,000
will be used to retain a consultant to provide technical support in responding to questions on the conceptual design for
CS-11; $41,142 will be used to obtain topographic information for an area that was inundated when the LiDAR data was
obtained. An additional $3,350 was added to the HDR contract to finish technical support for CS-11 land negotiations and
$10,000 was added as contigency in case any new issues arise.
021 - Manasota Basin 169
H048
Myakka River Watershed Initiative
Project Type WS&R Dev.
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementWater Supply Alternative Water SupplyNatural Systems Natural Systems Conservation and Restoration
Basin(s) General Fund (District), Peace River, Manasota
Cooperator(s)
Project Manager MORRIS, LISANN
SZAFRANIEC, MARY, RIALS, MARK, STARKS, ROBERTA, SMITH, RANDY, ARNOLD, DAVETask Manager(s)
Status Ongoing
DescriptionThe Myakka River Watershed is approximately 600 square miles in size and spans about 66 miles from Myakka Head
to its outfall in Charlotte Harbor. It includes portions of several counties including Hardee, Desoto and Charlotte with
the majority of the watershed located in Manatee and Sarasota counties. The 34-mile segment of the Myakka River in
Sarasota county has been designated a Wild and Scenic River by the State of Florida and, together with the estuarine
portions of the river, it is designated an Outstanding Florida Water by the Florida Department of Environmental
Protection. The river is the second largest source of freshwater inflow for Charlotte Harbor, which is generally viewed
as one of the most productive estuaries in Southwest Florida and is a SWIM waterbody. This Initiative is a
comprehensive project that will illustrate the effects of land use conversions and alterations and evaluate best
management practices (BMPs) for restoration alternatives. The objective of this initiative is to restore water quality,
natural system, and floodplain impacts in the watershed in ways that can also provide a benefit to water supplies in the
Southern Water Use Caution Area (SWUCA). The Topographic Information, Watershed Evaluation, and Watershed
Management Plan elements of the District's Watershed Management Program (WMP) are included in this initiative.
This effort will build upon existing data and analyses as well as the Sarasota County Lower Myakka Watershed
Management Plan, K487, and the City of North Port Big Slough Watershed Management Plan, K883. Evaluation will
also be performed on existing and proposed activities within the watershed to address long-term water resource
issues.
BenefitsThe Initiative will determine how alternations have affected these systems, evaluate potential water resource impacts
from future land use changes, and provide alternatives to better manage the water resource within the Myakka River
watershed.
Costs
The estimated cost for the WMP of the Initiative is approximately $4.9 million. Costs for FY2011 are only staff salaries,
and water quality monitoring lab costs. Funding History: At its February 21, 2006 meeting, the Governing Board
transfered funds ($500,000) from the Water Supply and Resource Development reserves to hire consultants to obtain
digital topographic information using LiDAR in eastern Manatee County ($380,000) and to initiate the water budget
analysis for the Upper Myakka watershed ($120,000). The FY2007 funding ($2 million) continued the Upper Myakka
water budget, the Watershed Evaluation for the entire watershed, and initiate the Watershed Management Plan
element within the Upper Myakka. The $2 million FY2007 budget was funded as follows: $575,000 from the Governing
Board, $517,500 from the Manasota Basin Board, $57,500 from the Peace River Basin Board, and $850,000 from
state appropriations. In FY2008, $1.77 million was budgeted to complete the Watershed Evaluation element, continue
the Watershed Management Plan element, complete the Independent quality assurance review of existing parameters
and models previously developed for the Myakka River in unincorporated Sarasota County (K487) and the Big Slough
tributary (K883). The FY008 funding was divided as follows: $635,000 from the Governing Board, $571,500 from the
Manasota Basin Board, $63,500 from the Peace River Basin Board, and $500,000 from the State Funding. The
funding distribution is Governing Board (50%), Manasota Basin Board (45%) and Peace River Basin Board (5%).
Contracting for independent, peer review of the Water Budget for the Upper Myakka and the purchase of the
necessary software licenses for the MikeSHE model were accomplished with FY2008 funds. The remaining $765,000
in funding is being used to complete the Watershed Management Plan through the Alternatives Analysis. Because this
project was able to secure State Funding for FY2009 in the amount of $1,000,000, additional funds were not needed
leverage Ad valorum funding budgeted in previous fiscal years was used to match the state grant. When each element
is completed, the project budget and scope may require refinement based on the information gathered. The District
funding amounts shown in the table include staff salaries. Future funding will be required for implementation of
selected BMPs.
021 - Manasota Basin 170
H048
Myakka River Watershed Initiative
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP is one of the Comprehensive Watershed Management (CWM)
initiative strategies and one of the District's Strategic Priorities. Funding was requested to continue the Watershed
Management Plan including: GIS data base development, watershed parameterization, computer modeling, floodplain
analysis, floodplain delineation, and alternative analysis of BMPs within the Upper Myakka. Since all task under the
Watershed Management Plan will not be completed within, the necessary funding to complete the project has be
distributed between to FY2009. Objectives of the Initiative include: 1) ensuring an adequate supply of the water
resource, 2) providing flood protection, 3) protecting and enhancing water quality and preventing the further
degradation of the water resource, and 4) preserving, protecting and restoring natural systems. There is a significant
amount of research, study and other data available for the watershed from the District and other Myakka stakeholders
that can and will be used during the course of the project. Stakeholder involvement and contribution of available
information will be important for the Initiative's ultimate success.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 1,860,778 0 500,000 1,298,784 30,800 31,194
020 Peace River Basin 168,916 0 0 161,094 2,903 4,919
021 Manasota Basin 1,228,621 0 0 1,168,157 28,280 32,184
District Budgeted - Outside Revenue
Ecosystem Trust Fund - Myakka Rvr
W/S Init
2,350,000 0 0 2,350,000 0 0
$5,608,315 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Aerial Mapping ServicesExecute Work Order for Aerial Topographic Mapping 2/24/06 2/24/06
Complete Aerial Topographic Mapping 10/31/06 1/30/06 3/22/07
3. WMP Consulting ServicesExecute Consultant Services Agreement 11/13/06 12/4/06
Complete Work Order #1 5/8/07 5/8/07
Complete Work Order #5 9/27/07 6/16/08
Complete Work Order #4 12/3/07 1/18/08
Complete Work Order #3 4/1/08 5/17/08
Complete Work Order #2 5/22/08 5/14/08
3. WMP Consulting ServicesComplete Work Order #6 3/3/08 3/31/08
Complete Work Order #8 4/2/08 4/1/09
Complete Work Order #7 5/15/08 8/1/08
Execute Amendment 1 5/22/09 5/22/09
3.WMP Consulting ServicesExecute Work Order #9 9/9/08 9/9/08
Execute Work Order #10 1/31/09 3/31/09 4/10/09
Complete Work Order #9 4/30/09 9/30/09 9/30/09
4. WMP Consulting ServicesSAI Agreement Termination 10/31/10 1/10/11
WMP Consulting ServicesExecute Work Order #13-Jones Edmunds 4/24/09 7/10/09
021 - Manasota Basin 171
H048
Myakka River Watershed Initiative
Execute Work Order #12-Singhofen 4/24/09 7/10/09
Complete Work Order #11 8/31/09 9/30/09 10/2/09
Execute Work Order #15 10/26/09 10/26/09
Execute Work Order #16 11/17/09 11/17/09
Complete Work Order #10 2/10/10
WMP Consulting Services-DewberryExecute Work Order #14 4/24/09 8/17/09
Status As Of: February 22, 2010
Status History: At the February 21, 2006 Governing Board Meeting, a transfer of funds ($500,000) from the Water
Supply and Resource Development reserves was approved to hire consultants to obtain LiDAR in eastern Manatee
County ($380,000) and to initiate the water budget analysis for the Upper Myakka watershed ($120,000). The notice to
proceed for the LiDAR work order was executed on February 24, 2006. The Request for Proposals to perform the
Watershed Management Program elements was posted on May 19, 2006. Oral presentations of the three respondents
were given on July 25, 2006. Singhofen & Associates, Inc. (SAI) was selected and approved on August 8, 2006. The SAI
agreement was executed on December 4, 2006. Copies of the executed agreement were transmitted to Manatee
County, City of North Port, Sarasota County, and PRMRWSA. A kick-off meeting was held with the Myakka River
stakeholders on February 14, 2007, to present the project and collect information from staff with projects, knowledge,
and/or data within the watershed. Work began on June 12, 2007, to develop the Upper Myakka River water budget
model. The digital topographic information element was the first item completed geospatially referencing existing survey
data throughout the watershed, historic land use mapping, and identification of model-specific features for the
geodatabase. Imagery (late 1940s and early 1950s) is being utilized for historic land use mapping in the water budget
analysis. Coordination efforts were prevalant with the H063 PRMRWSA Source Feasibility study in early 2008. The
kick-off meeting for the the peer review of the Upper Myakka Water Budget Model was held March 20, 2008. The
Myakka website can now be accessed on watermatters.org. The Upper Myakka Water Budget was presented to the
Watershed Summit sponsored by the Charlotte Harbor National Estuary Program. The MRWI was presented to the
Florida State conference of Agricultural and Biological Engineers in early June 2008. The peer review document was
received in early July 2008 and comments addressed. In an effort to accelerate the project, staff was able to initiate
water quality monitoring for a major portion of the Class 3 constituents, along with coordination efforts with potential
users and updates to the GIS database as a result of state funding from FY2009. These efforts can begin now instead of
waiting for additional funding in the next fiscal year. This requires an amendment to the current Singhofen & Associates
agreement increasing the funding amount by $276,000 to cover the updated database efforts and increased coordination
efforts. The District's Chemistry Lab and Water Quality Monitoring Program sections are managing the water quality
monitoring element. The consultant was delayed because of waiting to utilze the recent Sarasota County Lidar before
proceeding. The consultant team presented removal scenarios of excess water from Flatford swamp and screening for
potential uses at a meeting April 30, 2009. Watershed Evaluation work orders were delayed as coordination efforts are
worked through at the District. Consultant has completed a preliminary alternatives analysis in the Tatum Sawgrass area
of the watershed. The consultant has started development of the hydraulic event modeling for the river as well as several
tributary sub-watersheds that will assist with future permitting of best management practices to address alterations within
the study area. A presentation was given to FDEP's Myakka River Coordinating Council on January 22, 2010.Current
Status: Consultant presented preliminary alternatives to District staff for Flatford Swamp hydrologic restoration on
February 18, 2010. Additional meetings with potential water users are scheduled for March 2010.
021 - Manasota Basin 172
H050
PR/MRWSA Reg Integ Loop Sys Phase 1 Interconnect
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager FERGUSON, JOHN
ARMSTRONG, BRIANTask Manager(s)
Status Proposed
DescriptionThe Regional Integrated Loop System project provides a regional water transfer and delivery system for existing and
future water sources within the Authority's service area The Regional Integrated Loop System is a series of
transmission pipelines that will be developed to regionally transfer and deliver water from existing and future
alternative supplies to demand centers within the Peace River/Manasota Regional Water Supply Authority's (Authority)
four county region. The Phase I Interconnect project will provide regional loop transmission capacity to the City of
Punta Gorda, and service to Charlotte and DeSoto Counties along the U.S. 17 corridor. This project was previously
considered for SWFWMD co-funding, but in the spring of 2007 was suspended in favor of the Phase 1A interconnect
project (H069). The Phase 1 project is being reconsidered by the Authority to establish rotational capacity with the City
of Punta Gorda's Shell Creek Water Treatment Facility (SCWTF.) The Phase 1 project includes a total of 6 miles of
24-inch diameter transmission main extending the Authority's 20-inch regional transmission line along U.S. 17 to the
SCWTF. Also included will be high service pumping, storage and chemical adjustment facilities.
BenefitsDevelopment of this transmission system will assist in achieving the regional resource management and water supply
goals within the four county area including: maximizing use of surface water for public supply; providing rotational
capacity and the ability to blend and rest sources; providing reserve capacity for emergency transfers; providing
alternatives to the development of groundwater in the Southern Water Use Caution Area (SWUCA); and optimizing
financial investments in water supply infrastructure on a regional basis. The use of alternative sources via maximizing
surface water for public supply is consistent with the District's Regional Water Supply Plan (SWFWMD, December
2006), the SWUCA recovery strategy, and the provisions of Senate Bill 444.
Costs
The total estimated project cost is $11,500,000; with the requested District's share being $5,250,000 and the
Authority's share being $6,250,000. District funding will be shared by the Governing Board ($2,625,000), and the
Peace River ($708,750) and Manasota ($1,916,250) Basin Boards. The FY2011 funding request is for $3,749,625 and
is divided as follows: Governing Board ($1,874,813), Manasota Basin Board ($1,368,613) and the Peace River Basin
Board ($506,199). These funds are needed for the construction of the pipeline, and no District funding is currently
encumbered for the project. The prior District and WPSTF funds shown in the table below were transferred to other
projects after this project was suspended in 2007, and are not encumbered. Prior Authority funding of $1,000,000
shown below represents completed design work for this project, and is not eligible for reimbursement. The future
funds identified for the project ($1,500,375 remaining District share) are contingent upon approval of such amounts by
the District Basin and Governing Boards in the annual budgets.
Additional Information
The project design was completed in 2007, permitting and property acquisition efforts can be finished with minimal
delay. This project could provide the City of Punta Gorda access to regional supplies during the dry season, and
provide the Region with increased reliability and access to seasonally available supplies from Shell Creek. Water
delivered from the interconnect would provide an additional blending source at the SCWTF. Completion of both Phase
1 and Phase 1A will establish rotational capacity between the SCWTF and the Peace River WTF. Additional capacity
from the project to DeSoto County would create delivery options to customers in Sun River.
021 - Manasota Basin 173
H050
PR/MRWSA Reg Integ Loop Sys Phase 1 Interconnect
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 3,700,945 750,187 0 1,073,027 1,877,731 0
020 Peace River Basin 1,001,319 202,551 0 290,215 508,553 0
021 Manasota Basin 2,701,780 547,637 0 783,337 1,370,806 0
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
0 0 (562,000) 562,000 0 0
Project Funds Not Budgeted by the
District
PRMRWSA 6,250,000 1,500,375 0 1,000,000 3,749,625 0
$13,654,044 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: February 26, 2010
On January 14th, the Authority Board directed staff to expedite development of the Phase 1 project in order to take
advantage of currently low construction costs. Negotiations are underway to develop a funding package in coordination
with the City of Punta Gorda and DeSoto County. Design of the project was previously completed, although some
modifications will be required to accommodate the recent widening of US-17. The Authority's target date for bidding the
project for construction is early Fall 2010.
021 - Manasota Basin 174
H051
PR/MRWSA Reg Integ Loop Sys Phase 2 Interconnect
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager FERGUSON, JOHN
ARMSTRONG, BRIANTask Manager(s)
Status Proposed
DescriptionThe Regional Integrated Loop System project is a series of transmission pipelines that will be developed to regionally
transfer and deliver water from existing and future alternative supplies to demand centers within the Peace River
Manasota Regional Water Supply Authority's four county region. The Phase II Interconnect project is a component of
the Regional Integrated Loop System that will provide needed regional transmission capacity between the Peace River
Facility and the City of North Port. The transmission line will be a 36-to-42 inch diameter pipeline extending
approximately 7 miles from the Peace River Facility, generally along the existing 36-inch regional transmission main
(RTM) corridor to Serris Boulevard, where it will interconnect with the City of North Port's transmission/distribution
system. In addition to serving the City of North Port, Phase II provides back-up capacity to the existing 36-inch RTM,
and comprises a critical segment for the extension of future regional transmission capacity to the City of North Port's
Myakkahatchee Creek Water Treatment Facility, the Englewood Water District treatment facilities, and the Carlton
Water Treatment Facility.
BenefitsThe initial segment of the Phase 2 Interconnect will allow the City of North Port to receive additional water from the
Authority's ongoing expansion project. The City currently requires this project to transmit the quantities of water they
are contracted to purchase from the Authority in FY2012. Development of additional segments will further integrate
regional resources; maximize surface water for public supply; provide rotational capacity and the ability to rest sources;
provide for reserve capacity for emergency transfers; provide alternatives to the development of groundwater in the
Southern Water Use Caution Area (SWUCA); and better match supply, demand and financial investment on a regional
basis. The use of alternative sources with the maximization of surface water for public supply is consistent with the
District's Regional Water Supply Plan.
Costs
The total estimated cost for the H051 Phase 2 Interconnect is $15,400,000. The requested District share is $7,700,000
divided between the Governing Board, $3,850,000 (50%); Manasota Basin, $2,810,00 (36.5%); and the Peace River
Basin, $1,039,500 (13.5%). District funding in FY2010 is: General Fund $1,500,000; Manasota $500,000; Peace River
$200,000; for a total of $2,200,000. Funding requested for FY2011 is: General Fund $1,750,000, Manasota
$1,277,500, Peace River $472,500, for a total of $3,500,000. Funds will be used for design and construction of the
pipeline. The future funds identified for the project are contingent upon approval of such amounts by the District
Governing Board and Basin Boards in the annual budgets. The Funding table below shows funds that were budgeted
in "FY2007" and "FY2008" and "Cumulative Transfers". Those funds lapsed at the end of their fiscal years, as the
project was not pursued at those times. A negative adjustment is made under "prior funding" to show the actual total
funding. The long-term project cost of all additional Phase 2 components for joining the Englewood Water District, City
of Venice, and the Carlton WTP has been estimated at $82,400,000.
Additional Information
The Loop Feasibility/Routing Study was authorized by the Authority in May 2005 and the report was issued in June
2006. The Feasibility/Routing Study identified the preferred loop pipeline routing, environmental impacts, major
connection points, preliminary pipe sizing, proposed schedule of project phasing, and time frames for construction.
The Study's recommended Phase 2 route connects the Peace River Water Treatment Plant with the Myakkahatchee
Creek Water Treatment Plant and then branches into two segments. The one segment loops northwest to Sarasota
County's Carlton Water Treatment Facility, and the other segment runs southwest and connects to the public water
systems of the Englewood Water District and the City of Venice. In August 2007, the Authority Board approved the
first work order for Phase 2 of the Regional Loop System and issued a notice to proceed. In December 2007, the
Authority's consultant released a preliminary design report for the Phase 2. In May 2008, the Authority chose to
postpone the project in favor of an alternate connection between North Port's system near the Snover Waterway and
the existing regional line connecting the Carlton and Peace River WTPs. As a result, the District reallocated the
FY2007 and FY2008 funds towards other projects. After much discussion between the City of North Port, Sarasota
County, and the Authority over shared capacities, the Snover Waterway connection was considered insufficient to
021 - Manasota Basin 175
H051
PR/MRWSA Reg Integ Loop Sys Phase 2 Interconnect
meet all the partners' combined needs. In November 2008, the Authority revised a shorter version the Phase 2 project,
which calls for a segment between the Peace River WTP and the North Port's Serris Blvd connection. The pipeline
would be the length needed to deliver an increased capacity to the City, but would retain the greater transmission
capacity needed for future extensions. In February 2009, The Authority's consultant released a technical
memorandum which updated the cost estimate from the 2007 Preliminary Design report. The cost for a 36-inch
diameter, 5.5 mile long pipeline with a transmission capacity of 13.5 mgd was updated from $12,000,000 to
$15,400,000. The project is scheduled for completion by September 2012. The City is currently exceeding their 1.192
mgd annual average capacity entitlement in the existing pipeline from the Peace River Facility. The City will require an
additional 1.758 mgd transmission capacity by 2011, and a total of 3.20 mgd transmission capacity by 2014. The City
of North Port, Charlotte County, and the Authority entered into a three party temporary interlocal agreement for the
capacity use of existing water main. The City and County approved the agreement on May 26, 2009, and the Authority
board approved the agreement on June 3, 2009. This agreement will allow the City of North Port additional capacity
until September 30, 2012, which is the scheduled completion date for the Phase 2 interconnect. Also on May 26,
2009, The City of North Port approved the interlocal agreement for the Phase 2 interconnect. The agreement was
approved at the Authority Board meeting on June 3, 2009. The Authority executed Work Order No. 2 with King
Engineering Associates (King) on September 2, 2009 for the project coordination, BODR, final design, permitting, and
bidding award services of the Phase 2 Interconnect. King was initially contracted in June 2007 for the project. The
Authority held a project kick-off meeting on October 22, 2009.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 4,455,061 600,000 (3,200) 3,200 2,353,276 1,501,785
020 Peace River Basin 1,041,760 367,000 (2,001) 2,001 473,900 200,860
021 Manasota Basin 3,848,227 1,033,000 (2,001) 2,001 2,313,314 501,913
Project Funds Not Budgeted by the
District
PRMRWSA 7,700,000 2,000,000 0 600,000 2,900,000 2,200,000
$17,045,048 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Final Basis of Design Report 4/15/10
Construction Bidding Award 3/31/11
Commence Construction 4/1/11
Complete Construction 5/25/12
Status As Of: January 12, 2010
Authority and District staff have prepared a draft Cooperative Funding Agreement. The District is conducting a review of
the document. The Authority submitted their FY2011 Cooperative Funding Request for $3,500,000. Final design work is
ongoing. Soil surveys have been completed along the proposed route. The consultant is coordinating with the engineers
that installed the existing pccp pipeline along the right-of-way to determine safe installation protocols.
021 - Manasota Basin 176
H052
PR/MRWSA Reg Integ Loop Sys Phase 3A Interconnect
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager FERGUSON, JOHN
GOODWIN, AUDRIE, ARMSTRONG, BRIANTask Manager(s)
Status Proposed
DescriptionThe Regional Integrated Loop System Program is a series of transmission pipelines that will be developed to regionally
transfer and deliver water from existing and future alternative supplies to demand centers within the Peace River
Manasota Regional Water Supply Authority's (Authority) four county region. This project, Phase 3A, is for the
construction of a pipeline from Sarasota County's Carlton Water Treatment Facility westward across the Myakka
River, northward along Cow Pen Slough, where it will connect to an existing County utility line. Eventually the
interconnect will extend northward into Manatee County once all phases have been completed.
BenefitsDevelopment of this project will further integrate regional resources; maximize surface water for public supply; provide
rotational capacity and the ability to rest sources; provide for reserve capacity for emergency transfers; provide
alternatives to the development of groundwater in the Southern Water Use Caution Area; and better match supply,
demand and financial investment on a regional basis.
Costs
The total estimated cost for the Phase 3A project is $42,570,000, with the requested District's share being
$21,285,000. District funding will be divided by the Governing Board, $10,642,500 (50%); the Peace River Basin
Board, $2,873,475 (13.5%); and the Manasota Basin Board, $7,769,025 (36.5%.) District funding will be used for the
design and construction of the pipeline, and for additional storage and pumping at the Carlton WTP. Total funding
budgeted to date (FY2007 through FY2010) is $18,935,904; split between the Governing Board ($10,642,500), the
Peace River Basin Board ($1,709,750), and the Manasota Basin Board ($6,583,654). The District Governing Board
share was completed in the FY2010 budget. The remaining Basin Board FY2011 funding requested to complete Basin
shares are: Peace River Basin Board ($1,163,725), and the Manasota Basin Board ($1,185,371) for a total of
$2,349,096. The future funds are contingent upon approval of such amounts by the Basin Boards in the annual
budgets. The total actual project cost is currently running approximately $14,000,000 under budget, and it is likely that
enough District funding was allocated in prior years to complete the project.
Additional Information
This project would provide potable water service to areas of northern Sarasota County and Manatee County. Phase
3A is the initial segment in the overall Integrated Regional Loop System Phase 3. Subsequent interconnect
expansions (Loop System Phases 3B, 4A and 4B) will connect to the surface water treatment facility on Lake Manatee
and a treatment plant on University Parkway, and will allow regional water delivery service to communities in Sarasota
and Manatee Counties. Total cost for the entire Phase 3 & 4 program is estimated to be $146,207,442. On April 2008,
District staff received the Preliminary Engineering Basis of Design Report for Phases 3A and 3B. The
Feasibility/Routing Study identified the preferred loop pipeline routing, environmental impacts, major connection
points, preliminary pipe sizing, proposed schedule of project phasing, and time frames for construction. Major
components of Phase 3A include above ground storage, a pumping station and approximately nine miles of 48-inch
diameter transmission pipeline. The pipeline route is generally from the Carlton Water Treatment Plant westward
across the Myakka River following an established utility corridor; west along Laurel Road, north along Knights Trail
Road, and parallel along Cow Pen Slough to a point near the Central County Landfill and State Road 681.
Components co-located at the Carlton Water Treatment Plant would include a pumping station with a 10 mgd capacity
and above-ground storage. It is anticipated that a portion of the project's storage component, a 5 million gallon above
ground storage tank, will be acquired from Sarasota County by the Authority. The transmission capacity of the pipeline
will have a minimum design capacity of 37 mgd. Future upgrades to the pumping station will be needed to reach that
capacity. Phase 3A will provide an additional water delivery point to Sarasota County and the potential for an inter-tie
between the Authority's RTS and the City of Venice water system. The Cooperative Funding Agreement between the
District and the Authority for Phase 3A was executed on November 10, 2008. The Agreement is back-dated to July 25,
2007 and will remain in effect through November 1, 2011. The Interlocal Agreement between the Authority and
Sarasota County was signed by the County on March 32, 2009 and by the Authority on April 1, 2009. The Authority
submitted RAI responses for the FDEP ERP for the pipeline and the FDEP Myakka River Wild & Scenic River Permit
021 - Manasota Basin 177
H052
PR/MRWSA Reg Integ Loop Sys Phase 3A Interconnect
on May 8, 2009. Also on May 8, 2009, permit applications were submitted for the FDEP drinking water permit for the
pipeline and pump station, and for Sarasota County's Site & Development Permit. On June 3, 2009, the Authority
board approved a work order for final design services of a new 5 million gallon storage tank to be located at the
Carlton WTP. The FDEP Myakka Wild and Scenic River permit was acquired on August 5, 2010. The FDEP drinking
water construction permit was acquired on August 24, 2009. The FDOT utility permit was received on July 2nd, 2009.
The USACOE permits were issued on July 30, 2009. A FDEP environmental resource permit was issued October 10,
2009. The project design is complete. The Authority selected the low bid contractor at their Board meeting on
December 17, 2009, at a cost of $18,385,256. The construction costs were much lower than anticipated.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 10,657,494 0 (3,000) 6,563,406 3,276 4,093,812
020 Peace River Basin 1,862,046 0 (2,001) 1,714,599 146,836 2,612
021 Manasota Basin 6,594,777 0 (2,001) 4,470,747 2,814 2,123,217
Project Funds Not Budgeted by the
District
PR/MRWSA 21,285,000 0 0 12,729,517 0 8,555,483
$40,399,317 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Preliminary Design / Basis of Design - Phase 3 7/31/08 3/31/08
Final Design - Phase 3A 3/31/09 10/20/09
Permitting / Property Aquisition - Phase 3A 4/30/09 10/15/09
Construction - Phase 3A 5/31/10
Status As Of: February 17, 2010
Project is running under buget and close to anticipated time schedule. The Authority intends to request a task schedule
update for construction and completion deadlines. The Authority issued a Notice to Proceed with construction on
February 15, 2010. District staff have requested to the Authority that FY2011 funding request be adjusted, as additional
Distict funding may only be needed from the Peace River Basin. Accelerate Florida Update: Notice was sent to
PRMRWSA regarding the Accelerate Florida Initiative. Project construction has commenced.
021 - Manasota Basin 178
H059
City of Bradenton Reservoir Expansion
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Manasota
City of BradentonCooperator(s)
Project Manager MORRIS, LISANN
Task Manager(s)
Status Proposed
DescriptionThis is an ongoing Cooperative Funding project requested by the City of Bradenton to develop an alternative water
supply project that will provide additional storage capacity at the Bill Evers Reservoir and capture excess flow from the
Braden River during the wet season's high flow periods. The project is for the design, permitting and construction of an
upland, offstream storage facility on City-owned property adjacent to the City's water supply reservoir. The proposed
facility will be made of earthen dike construction and includes a raw water intake at the existing reservoir plus pumping
and piping for filling the new storage facility; systems to provide turnover and prevent stratification and stagnation of
water in the new storage facility; and equipment and piping for withdrawing water from the new storage facility.
BenefitsThis project is also consistent with the SWUCA Recovery Plan and the District's Regional Water Supply Plan in
providing supply from an alternative source (surface water). The project will help the City meet their future demands
and has the potential to reduce demand on the Upper Floridian aquifer.
Costs
The total estimated cost for the H059 Raw Water Storage is $17,372,000. The requested District share is $8,686,000
divided between the General fund $4,343,000 (50%); Manasota Basin 4,343,000 (50%). Water Protection and
Sustainablility Trust Funds (WPST) in the amount of $43,541 were transferred into the project. These WPST funds will
be split evenly between the District and City decreasing construction costs accordingly. Funding requested for FY2011
is: General fund $1,003,000, Manasota $1,003,000, for a total of $2,006,000. Funds will be used for construction of the
facility. When each phase (such as design\permitting) is completed the project budget and scope and schedule may
require refinement based on the information gathered. The future funds identified for the project are contingent upon
approval of such amounts by the District Governing Board and Manasota Basin Board in their annual budgets.
Additional Information
At their March 2006 meeting, the Governing Board established a policy regarding Cooperative Funding for potable
water supply projects submitted by local governments in areas served by a water supply authority (WSA). Funding
criteria is dependent on whether or not the local government is a member\customer of the WSA. The City of
Bradenton is located in the service area of the Peace River/Manasota Regional Water Supply Authority (Authority), but
is not a member of the Authority. The City must coordinate their water supply needs with the Authority so that they are
consistent with regional plans. Affirmative written documentation from the Authority supporting the project must
accompany the City's application. The Authority supplied a written statement in early May 2006 indicating coordination
with the City and consistency of the project with the Authority's regional plan.The City plans to increase the size of the
reservoir storage area from 580 to 755 million gallons because of the uncertainty of arsenic mobilization and ASR.
Without ASR, the projection for raw water supply capacity must increase to 2.62 MGD to meet demands through
2025. In their cooperative funding application, the City stated that if ASR proves to be a viable option for treated water
storage, the City will have excess water available to participate in a regional water supply effort.
021 - Manasota Basin 179
H059
City of Bradenton Reservoir Expansion
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 4,033,002 1,332,500 0 687,329 1,006,609 1,006,564
021 Manasota Basin 4,077,133 1,332,500 43,541 687,178 1,006,970 1,006,944
Project Funds Not Budgeted by the
District
City of Bradenton 6,000,000 0 0 2,172,000 2,006,000 1,822,000
$14,110,135 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Draft Agreement to Management Services 11/30/06 1/17/07
Draft Agreement Returned from Management Services 12/31/06 2/17/07 2/7/07
Contract Execution 1/15/07 3/30/07 3/21/07
Topographic Survey 8/31/07 9/25/07 9/4/07
Preliminary Design 10/31/07 11/1/07
Geotechnical Evaluation 2/28/08 3/31/09 4/30/09
Final Design 9/30/08 4/30/11
Construction Permitting 5/31/09 5/31/11
Bidding and Contractor Selection 4/1/10 8/31/11
Observation and Geotech Services During Construction 8/2/10 3/31/13
Construction of Proposed Facilities 8/2/10 3/31/13
Engineering Services During Construction 8/2/10 3/31/13
Status As Of: February 22, 2010
Status History: Cooperative funding agreement was executed on March 21, 2007. The kick-off meeting was held May 2,
2007 in Bradenton. The consultant completed the survey and preliminary geotechnical exploration tasks. The Preliminary
Design & Engineering Report is complete. The City submitted its FY2009 Cooperative funding application with an
updated reservoir size increased to 755 MG to offset the uncertainty of the arsenic mobilization in ASR. City anticipates
ASR arsenic mobilization issues will not be remedied before the reservoir expansion is complete. Activities completed
during the first quarter of 2008 include, kick-off meeting for final design phase, and preliminary permitting meetings with
regulatory staff. A meeting was held on March 19, 2009 to discuss the FY2010 cooperative funding application, schedule
and project status for the "Accelerate Florida Initiative". The design geotechnical investigation report is complete. Letter
was received requesting line item revisions for tasks with total project cost not to change. The second permitting meeting
was held on July 8, 2009. FDEP requested wetland delineations be checked in the field by both parties before review of
ERP begins. Consultant has completed the dam break analysis and continues work on final design. A permitting meeting
with Manatee County was held Nov. 6, 2009. Current Status: Delays have occurred because of negotiations with the
FDEP consultant for permitting review and the MOU development between FDEP and the City. The City has the second
amendment to add FY2010 funds and increase the project cost for approval.
021 - Manasota Basin 180
H062
CF Industries Aquifer Recharge and Recovery Project
Project Type WS&R Dev.
AORs Strategic InitiativesWater Quality Water Quality MonitoringWater Supply Alternative Water Supply
Basin(s) General Fund (District), Alafia River, Peace River, Manasota
CF IndustriesCooperator(s)
Project Manager KELLEY, MIKE
Task Manager(s)
Status Withdrawn
DescriptionCF Industries is developing an Aquifer Recharge and Recovery Project (ARRP) on a portion of its South Pasture mine
in Hardee County. The project will store mine stormwater in an existing sand-clay mix area; naturally treat the water
through two reclaimed wetland cells constructed in an adjacent sand-clay mix area; filter the water through a sand
tailings filter basin; and then recharge an estimated 2 to 4 mgd of the naturally treated water into the Floridan aquifer.
The goal of the natural treatment system is to treat the water to primary and secondary drinking water standards so
that it can be recharged into the Upper Floridan aquifer to increase water levels and provide additional water to help
meet local and regional water demands. Project components include design and construction of the treatment
wetlands and sand filtration basin; construction of intake control structures to and from the mine, reservoir and
treatment systems; and, construction of an injection well and two monitor wells. The project will be conducted in two
phases: Phase 1 includes design, permitting, and construction of the wetlands treatment system and sand filtration
basin; and, Phase II includes construction and testing of the recharge well. CF Industries' original FY2009
Cooperative Funding request was modified to postpone construction and testing of the recharge well until at least
FY2010. Total District funding now being requested for FY2009 is $400,675 and will be used for construction of a
stormwater collection and discharge system. This will increase the District's previous total funding committment from
$2,250,000 to $2,605,729.
BenefitsThis is an innovative alternative water supply project that could provide significant benefits to the Southern Water Use
Caution Area (SWUCA) by maintaining or increasing Upper Floridan aquifer levels. Utilizing excess surface waters
and safely injecting those waters into the aquifer is one of several strategies the District is pursuing as part of its
SWUCA Recovery Strategy. The information collected from this project will be used to demonstrate the full-scale
feasibility of this type of treatment technology and can be applied to future natural treatment and aquifer recharge
projects in the area. This project was identified in the District's most recent update of the Regional Water Supply Plan
as a water supply development option under the Heartland Water Alliance planning area.
Costs
The total cost of the project including reclamation funds from CF Industries is $7,042,314, with the District funding up
to 50 percent of eligible costs to a maximum of $2,605,729. District funding will be shared by the Governing Board (50
percent), Peace River Basin Board (25 percent), Alafia River Basin Board (12.5 percent), and Manasota Basin Board
(12.5 percent). CF Industries' original FY2009 Cooperative Funding Initiative request was for $1,148,445 to complete
the project. However, based on discussions with District staff, CF Industries has postponed construction and testing of
their recharge well until at least 2010, reducing their FY2009 funding request to $400,675. The FY2009 Governing and
Basin Boards shares are, Peace River Basin Board: $100,169; Manasota & Alafia River Basin Boards: $50,084 each;
Governing Board: $200,338. Due to delays CF Industries did not request FY2010 funding.
Additional Information
The project consists of constructing the major components required to operate the ARRP, which will include the
design and construction of the treatment wetlands and sand filtration basin, intake control structures to and from the
mine, reservoir and treatment systems, and the construction of an injection well and two monitor wells. In anticipation
of receiving formal approvals and variances from the required regulatory agencies, CF Industries commenced
construction of the project in March 2007. It is expected to take approximately two years to complete the installation of
the necessary infrastructure. Another two years will be required to thoroughly test the system. Project costs for the first
fiscal year, FY2007, are estimated at $1,751,620, with the District's approved share not-to-exceed $875,810 (Peace
River Basin Board: $218,953; Manasota & Alafia River Basin Boards: $109,476 each; Governing Board: $437,905).
These funds were transferred from the Water Supply and Resource Development Reserves to each of the
participating boards. Project approved funds for FY2008 were $1,074,138, with the District's funded share
not-to-exceed $395,789(Peace River Basin Board: $97,927; Manasota & Alafia River Basin Boards: $49,474 each;
Governing Board: $198,914).
021 - Manasota Basin 181
H062
CF Industries Aquifer Recharge and Recovery Project
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 757,694 0 347,588 404,864 0 5,242
011 Alafia River Basin 213,632 0 109,476 103,108 0 1,048
020 Peace River Basin 421,712 0 218,985 201,679 0 1,048
021 Manasota Basin 211,569 0 109,476 101,045 0 1,048
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
193,814 0 0 193,814 0 0
Project Funds Not Budgeted by the
District
CF Industries 4,436,585 0 0 3,591,908 0 844,677
$6,235,006 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Phase IGoverning Board Approval 11/30/06 11/30/06
Basin Board Approvals 12/15/06 12/15/06
FDEP Underground Inj. Permit Application 1/1/07 1/1/07
Effective Date 1/2/07
CF Industries Sitework/Wetland Const. Commence 3/15/07
Wetland Berm, Pump, Filter Construction Commence 4/1/07
FDEP Reclamation Modification Application 11/1/07 11/1/07
Execute Contract 4/15/08
FDEP Underground Inj. Permit Issued 1/1/09
FDEP Reclamation Modification Issued 1/1/09
CF Industries Sitework/Wetland Construct. Complete 1/1/09
Wetland Berm, Pump, Filter Construction Complete 7/1/09
Phase IIRecharge/Monitor Wells Construction Commence 10/1/09
Recharge/Monitor Wells Construction Complete 4/1/10
Status As Of: February 03, 2010
A meeting was held with Craig Kovach of CF Ind. to discuss the District's continuing involvement in this project. CF
Industries has decided to withdraw their coop funding request and proceed with the project without District funds. The
draft cooperative funding agreement documents were not returned from CF Industries. Telephone and email
communications have been made with Craig Kovach and Gary Blitch of CF Ind. The major issues in the draft agreement
were non-profit through sale, termination without cause, an additional monitor well, annual report content, and
performance standards. The FDEP UIC permit for well construction and testing has been issued. CF Ind. is in the
process of permitting their expansion of the mine. On site, the wetland treatment cell 1 is complete and growing in well;
cell 2 is being herbicided and planted with native plant species. A small holding pond near the sand filtration basin is
being permitted through the Corps of Engineers.
021 - Manasota Basin 182
H069
PR/MRWSA Reg Loop System Ph 1A
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager FERGUSON, JOHN
GOODWIN, AUDRIE, ARMSTRONG, BRIANTask Manager(s)
Status Ongoing
DescriptionThe Regional Integrated Loop System project is a series of transmission pipelines that will be developed to regionally
transfer and deliver water from existing and future alternative supplies to demand centers within the Peace River
Manasota Regional Water Supply Authority's four county region. This project will connect the water supply systems of
the Authority, Charlotte County and the City of Punta Gorda so that the additional water from the recently expanded
facility on Shell Creek can be shared regionally. Construction of the interconnect consists of approximately 12 miles of
a 24 inch diameter line interconnecting the Shell Creek facility to the Peace River facility, and includes a sub-aqueous
crossing of the lower Peace River. The project will have a minimum design capacity of 6 million gallons a day.
BenefitsDevelopment of this project will integrate regional resources; maximize surface water for public supply; provide
rotational capacity and the ability to rest sources; provide for reserve capacity for emergency transfers; provide
alternatives to the development of groundwater in the Southern Water Use Caution Area (SWUCA); and better match
supply, demand, and financial investment on a regional basis.
Costs
The total estimated cost for the Phase 1A project is $19,015,000, with the requested District's share being
$12,007,500. The District funding is divided between the Governing Board, $6,003,750 (50%); the Manasota Basin
Board, $4,382,738 (36.5%); and the Peace River Basin Board, $1,621,012 (13.5%). Ad Valorum shares were
budgeted in FY2008, and funding received from the West Central Florida Water Restoration Action Plan (WRAP) was
applied in FY2009. $5,000,000 in WRAP funding was budgeted in FY2009 in place of Ad Valorum funding. When the
availablity of the WRAP funding was evident, the District's FY2008 project budget was reduced from a total of
$7,407,410 to $7,007,500. This reduction is not represented in the funding table below. The actual FY2008 shares
were: Governing Board $3,503,750, Manasota Basin $2,557,738, Peace River Basin $946,012.
Additional Information
The Phase 1A pipeline was designed as an alternative to two separately proposed pipelines, the Authority's Integrated
Regional Loop system Phase 1 (H050) and Charlotte County's Emergency Interconnect (L636). The original Phase 1
route was designed to interconnect the Peace River and Shell Creek water treatment plants via an extension of the
DeSoto County Regional Transmission System southward along US-17. Charlotte County was also planning to
construct an emergency interconnect consisting of a sub-aqueous crossing of the Peace River, to interconnect the
water supply systems of Charlotte County and Punta Gorda. Discussions were initiated in 2006 to combine the
projects and achieve the benefits of both pipelines. The revised and expanded pipeline (H069), was approved by both
Charlotte County and the Authority Board in June 2006. This expanded pipeline is designed to bidirectionally transfer
up to 6 MGD between the Authority, Charlotte County, and Punta Gorda. The pipeline will deliver water to four key
delivery points in Charlotte County Utility's (CCU) distribution system, and has the potential to tie into CCU's system
south of the Peace River. Water provided by Punta Gorda to CCU can offset the County's demand on the Peace River
facility, making additional water available to other Authority customers and increasing reliability in the regional system.
The PRMRWSA Board awarded the design consultant contract for Phase 1A in September 2007, and issued a notice
to proceed on October 17, 2007. The Preliminary Engineering Report was received in February 2008. In June 2008,
the Authority presented a draft of the Basis of Design Report to the District. The Cooperative Funding Agreement
between the District and Authority was executed in September 2008. The contract period is back-dated to July 25,
2007 and remain in effect through February 2012. In February 2009, the Authority submitted a draft amendment to
their interlocal agreement with Charlotte County and the City of Punta Gorda to reflect the current project. The
amendment includes the sale transfer of the interconnect's northern segment. Charlotte County has already installed
and put into service this 3000' long segment, which runs from the DeSoto/Charlotte County border southward to a
connection by a new shopping center. The Authority intends to purchase this segment and anticipates the cost to be
eligible for funding. South of the Peace River, an approximately 2 mile segment will utilize the City of Punta Gorda's
existing 30" transmission main. The amendment allows for the shared capacity of this segment. A regional pumping
station and 0.5 mg storage will be located between the Peace River crossing and the Punta Gorda segment. The
021 - Manasota Basin 183
H069
PR/MRWSA Reg Loop System Ph 1A
Authority approved a list of eleven pre-qualified construction contractors on October 7, 2009. The final Basis of Design
Report was received on December 3, 2009.
At the Charlotte County BOCC meeting on October 13, 2009, The County Board denied the formal Authority request to
construct the interconnect within the County, resulting in a project postponement. Opinions expressed by some Board
members were that the County would not have fair ownership of the pipeline, and the project benefited other Authority
members that weren't contributing the project. On December 14, 2009, the District informed the Authority that it
intended to reallocate the $5 million in WRAP funding to other projects unless a decision was made to move forward
with the project by February 1, 2010. A mediation settlement agreement between Charlotte County and the Authority
was approved in January 2010 prior to the deadline. The parties amended their water supply contract by agreeing to
segment the hydraulic allocations along pipeline. The Authority claims they will retain a hydraulic capacity share equal
or greater to the percentage of District funding, as required by the funding agreement.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 3,720,996 0 0 3,713,609 3,276 4,111
020 Peace River Basin 1,008,159 0 0 1,004,779 1,371 2,009
021 Manasota Basin 2,714,840 0 0 2,707,788 2,814 4,238
District Budgeted - Outside Revenue
State Approp - WRAP - Prior Year
Funds
5,000,000 0 0 5,000,000 0 0
Project Funds Not Budgeted by the
District
PRMRWSA 7,007,500 0 0 7,007,500 0 0
$19,451,495 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Preliminary Design/Basis of Design 7/31/07 6/1/08
Final Design 6/30/09 12/3/09
Permitting / Property Aquisition 7/31/09
Construction, substantial completion 8/1/11
Contract Expires 2/1/12
Status As Of: February 15, 2010
The project has resumed after a three month postponement, but is now behind schedule. The project could potentially be
completed before the contract expiration (February 1, 2012) but scheduled task dates must be revised. The Authority
expects to advertise bidding for the Construction contract to the prequalified contractors in March 2010, and award a
contract in May 2010. The project build period is expected to last 16 months. The Authority was concerned about the
potential loss of WRAP funds during the FY2011 Cooperative Funding Application deadline (December 4, 2009), and
submitted a funding request in case the WRAP funds were transferred to other projects. The District has informed the
Authority that all District funding for the project is encumbered, and the FY2011 funding request can be withdrawn.
021 - Manasota Basin 184
H079
PRMRWSA Brackish Groundwater Development
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) General Fund (District), Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager MORRIS, LISANN
FERGUSON, JOHNTask Manager(s)
Status Proposed
DescriptionThis alternative water supply project is proposed to provide 3 mgd of brackish groundwater by 2018. The new capacity
is needed to meet regional reliability targets and growing regional needs. The first step in the process will be to
evaluate the RV Griffin Reserve and Peace River Facility Site for brackish groundwater development and concentrate
disposal options. This project is the first phase of the Regional Resource Development Program described below.
BenefitsThe 3 mgd of alternative water supplies will be used towards meeting up to 26 mgd that will be developed as part of
the Regional Resource Development Program. Completion of this project will assist in achieving the regional resource
management and water supply goals within the four county area (Manatee, Sarasota, DeSoto and Charlotte) including:
maximizing use of surface water for public supply; providing rotational capacity and the ability to blend and rest
sources; providing reserve capacity for emergency transfers; providing alternatives to the development of groundwater
in the Southern Water Use Caution Area (SWUCA); and optimizing financial investments in water supply infrastructure
on a regional basis.
Costs
The total estimated cost to develop the 3 mgd is $36,000,000. The requested District share is $9,000,000 (50%) from
the Governing Board, $6,570,000 (36.5%) from the Manasota Basin Board and $2,430,000 (13.5%) from the Peace
River Basin Board. In FY2009 $600,000 was allocated to the project from the West-Central Florida Water Restoration
Action Plan (WRAP)Fund. The FY2011 funding request is for $625,000, and is divided as follows: Governing Board
($312,500), Manasota Basin Board ($228,125), and the Peace River Basin Board ($84,375). Funding will be used for
preliminary design activities associated with a brackish groundwater source on RV Griffin Reserve property and
injection well exploration. The future funds identified for the project are contingent upon approval of such amounts by
the District Basin and Governing Boards in the annual budgets.
Additional Information
The Peace River Manasota Regional Water Supply Authority (Authority) is comprised of Charlotte, DeSoto, Manatee
and Sarasota counties. In accordance with its Master Water Supply Contract, the Authority is obligated to timely
develop and deliver new water supply sources and facilities to meet the needs of its customers. The Regional
Resource Development Program will result in the development of up to 26 mgd average daily capacity of alternative
water supplies. New supplies will be a mix of brackish groundwater development at or near existing production
facilities, and surface water development projects in one or more of the following resource areas: Shell/Prairie Creek
basin, Cow-Pen Slough/Dona Bay, Upper Myakka/Flatford areas.To date, the Authority has executed Memoranda of
Understanding (MOUs) with DeSoto County, Sarasota County, the City of Punta Gorda and the Englewood Water
District to investigate potential partnerships in developing these and other proposed sources. Costs associated with
potential future phases will be determined as these partnerships develop.
021 - Manasota Basin 185
H079
PRMRWSA Brackish Groundwater Development
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 42,126,821 41,787,499 0 11,381 319,689 8,252
020 Peace River Basin 11,797,322 11,700,499 0 3,643 90,627 2,553
021 Manasota Basin 30,329,289 30,087,000 0 8,550 229,693 4,046
District Budgeted - Outside Revenue
State Approp - WRAP - Prior Year
Funds
600,000 0 0 600,000 0 0
Project Funds Not Budgeted by the
District
PR\MRWSA 78,300,000 75,500,000 0 50,000 1,250,000 1,500,000
$163,153,432 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Execute Cooperative Funding Agreement 6/25/10
Status As Of: February 23, 2010
Status History: On November 5, 2008, the options from the H063 Feasibility Study were formally presented to the
Authority board. These options include: 1)three potential reservoir sites in the Upper Myakka Basin and a new surface
water treatment facility, yielding 10 mgd;2) three potential reservoir sites by Shell and Prairie creeks and expansion of the
existing facility on Shell Creek, for an additional 12 to 20 mgd;3) the Dona Bay option of diverting water from Cow Pen
Slough to a reservoir on the Venice Minerals site, then transmitting stored water to a surface water treatment expansion
at the Carlton plant, yielding an additional 5 to 15 mgd; and the development of new or existing brackish groundwater
wells to yield an estimated 5 mgd. $600,000 in WRAP funds has been budgeted by the District for the development of
the selected project. A funding agreement between the District and Authority was executed in December 2008 to secure
these funds. A meeting was held with the Authority on May 1, 2009. With the current funding, they are looking to do some
brackish groundwater exploration after a consultant is chosen for the next phase. Memorandums of Understanding
(MOU) are being developed for water supply projects with potential partners to assist with the development and
scheduling of future water sources. At the June 3, 2009 PRMRWSA Board Meeting MOUs with the City of Punta Gorda
and DeSoto County were approved. The Punta Gorda project is a 5 to 8 mgd brackish water groundwater supply. The
DeSoto County project is an up to 5 mgd brackish groundwater supply. At the July 2009 meeting, MOUs were executed
with the Sarasota County and the City of Englewood. The next step then in the process is to develop a contract for the
specific project providing details of items such as operation, ownership etc. Current Status: As discussions continue on
the development of agreements through the various MOUs, the Authority intends to move forward with a preliminary
design/investigation for brackish water on RV Griffin. Results should determine whether a disposal well for RO
concentrate is feasible in the area. Notice to proceed to the successful bidder is not anticipated until June 2010.
021 - Manasota Basin 186
H086
Manatee County Regional 10 MG Reclaimed Water Storage Tank
ProjectProject Type WS&R Dev.
AORs Strategic InitiativesWater Quality ConservationWater Supply Alternative Water Supply
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project will construct the first of four 10 Million Gallon (MG) reclaimed water storage tanks in support of the
Manatee County Agricultural Reuse System (MARS). MARS is a regional system that consists of the over 21 miles of
transmission lines that interconnect Manatee County's three regional Wastewater Treatment Facilities (WWTF). The
MARS system supplies reclaimed water for irrigation of agricultural, residential, and recreational customers, thereby
decreasing dependence on potable groundwater. New residential developments, some with golf courses, have been
replacing agricultural demand and many are planned or under construction along the transmission route. These
developments are potential customers of the MARS System. The MARS system is designed to distribute over 30 mgd.
Currently the County relies on one 3 MG tank at the Spencer Parrish Pumping Station and one .75 MG tank at it's
North Wastewater Reclamation Facility to meet peak demand. Wastewater plant peak flows are processed during the
daytime and used primarily at night. This condition requires the county system to have sufficient tank storage to meet
the nightime peak demand. The addition of this 10 MG tank, and three more planned 10 MG tanks, will better enable
the County's regional system to provide for the nightly peak demand events, without comprimising pressure and water
quality. This tank will be located at the County's Southwest Wastewater Reclamation Facility.
BenefitsThis 10 MG reclaimed water storage tank will better enable the County to accommodate its customer base as it
evolves from purely agriculture to a mix including residential. The storage will assist the county in providing reclaimed
water for irrigation purposes throughout its system to its customers during nightly peak demand events, without
comprimising pressure and water quality.
Costs
The total project construction costs are estimated to be $4,500,000. The District's share is $2,250,000 or fifty percent,
of which the county is requesting $1,125,000 from the Governing Board and $1,125,000 from the Manasota Basin
Board in FY2010. The cost benefit cannot be calculated, since the project addresses system storage and efficiency,
and offsets will be associated with future related transmission projects.
Additional Information
The proposed 10 MG Reclaim Water Storage Tank is an enhancement to the existing Manatee County Agricultural
Reclaim System (MARS). This system reduces demand for public potable water for irrigation, improves overall
utilization of existing SWFWMD water resources and provides on demand high quality irrigation water for our urban
and agricultural customers. MARS is an integral part of Manatee County water conservation program. The County's
overall program includes existing metering and loss reduction programs, water conservation rate structures, urban
and agricultural reclaim water irrigation supply, public education, SWUCA based level of service for water supply at
110 gpfcpd, land development codes requiring non-potable sources for irrigation in new developments, water supply
protection ordinances and the use of aquifer storage and recovery for potable and potentially reclaim waters.
021 - Manasota Basin 187
H086
Manatee County Regional 10 MG Reclaimed Water Storage Tank
Project
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 1,128,144 0 0 0 1,581 1,126,563
021 Manasota Basin 1,128,144 0 0 0 1,581 1,126,563
Project Funds Not Budgeted by the
District
Manatee County 2,250,000 0 0 0 0 2,250,000
$4,506,288 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Bid Ground Storage Tank 2/26/10
Execute CFI Agreement 3/11/10
Start Construction 5/31/10
Complete Construction 11/30/11
Status As Of: February 19, 2010
The CFI agreement has been drafted by District staff and reviewed by Manatee County. The agreement has been
processed through the District's Contract Management Section and is with Manatee County for signature.
021 - Manasota Basin 188
H087
City of Punta Gorda Reverse Osmosis Facility
Project Type WS&R Dev.
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Alternative Water SupplyNatural Systems Minimum Flows and Level Establishment and Monitoring
Basin(s) General Fund (District), Peace River, Manasota
City of Punta GordaCooperator(s)
Project Manager FERGUSON, JOHN
MORRIS, LISANNTask Manager(s)
Status Proposed
DescriptionThe City has requested funding assistance for a 2 mgd Reverse Osmosis (RO) system to treat brackish groundwater
for blending with their existing treated surface water facility. The RO system is necessary to meet total dissolved solids
and ASR remediation requirements stipulated by the Department of Environment Protection. This project is continuing
to evolve as additional information is provided by the City of Punta Gorda, Peace River Regional Water Supply
Authority (Authority) and the District's ongoing MFL establishment for Shell Creek. Initially the project was evaluated as
a potable water supply project that would share water between the City and Authority, benefiting both the Peace and
Manasota Basin Boards. As a result of the recent decline in demand and the availability of excess regional water, the
Authority has decided not to participate in the development of this project. As a result, funding from the Manasota
Basin Board has been removed and the FY 2010 funding will be balanced forward into the Basin's budget. For the time
being, budgeted funds from the Governing Board will remain in the project until a determination is made on the benefit
of expanding the RO system to assist with meeting the proposed MFL on Shell Creek. If it is determined that the RO
expansion will not benefit the MFL recovery strategy, Governing Boards funds will be balanced forward into General
Fund and the project will be reevaluated as a local cooperative funding project solely funded by the Peace River Basin
Board.
BenefitsConstruction of the 2 mgd RO facility will provide a blending source to reduce levels of TDS and allow the City to
continue operating their existing surface water facility within the SWUCA. Additionally the RO facility would assist the
City with the required remediation of their ASR system. Staff is currently evaluating an expansion of the system to
potentially serve as a future recovery strategy for the proposed MFL on Shell Creek.
Costs
The City estimated the total project cost for the 2 mgd RO facility at $36,700,000. The total District eligible cost
through construction is estimated at $35,700,000, with $17,850,000 in funding requested. The District budgeted
$1,770,000 in FY2010 funding divided as: Governing Board $1,000,000, Manasota Basin Board $500,000, and the
Peace River Basin Board $270,000. The City's FY2011 funding request is for $2,000,000. There are outstanding
questions that will determine whether funding should be provided solely by the Peace River Basin as a CFI project, or
if the project qualifies for regional funding as a MFL recovery strategy.
Additional Information
The City of Punta Gorda's Shell Creek facility currently consists of a conventional treatment plant with 10 mgd
capacity, an in-stream reservoir on Shell Creek and an ASR storage system. Because the level of total dissolved
solids (TDS) in Shell Creek are often elevated, the facility utilizes stored treated water from their ASR system to blend
with raw surface water to reduce TDS levels. Even with ASR blending the City does not meet current DEP
requirements for TDS and is operating under a variance allowing an exceedance until June 15, 2011, after which time
additional treatment or another source must be developed. To increase the quality and availability of supply, the City
has reviewed several project options; including various RO treatment and off-stream reservoir scenarios. These
options were published in their January 2009 Water Supply Mater Plan Update, and the 2 mgd Brackish Groundwater
RO Project was the recommended option. Additionally, the City is required to cease operation of their existing ASR
wells, and has expressed interest in converting them into a brackish water supply. Withdrawal and treatment of water
from these wells would serve as the remediation required by the DEP.
021 - Manasota Basin 189
H087
City of Punta Gorda Reverse Osmosis Facility
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 7,933,861 6,925,000 0 0 4,167 1,004,694
020 Peace River Basin 4,144,746 1,869,750 0 0 2,002,389 272,607
021 Manasota Basin 5,791,274 5,285,250 0 0 2,261 503,763
Project Funds Not Budgeted by the
District
City of Punta Gorda 17,850,000 6,950,000 0 1,000,000 7,900,000 2,000,000
$35,719,881 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Preliminary Design Report 3/31/10
Final Design and Permiting 10/31/11
Complete Construction 9/30/12
Status As Of: March 10, 2010
The Preliminary Design Report (PDR) is ongoing and scheduled for completion in March 2010. The PDR will provide an
update of detailed costs and time table. The Authority has decided not to participate in the development of this project.
As a result, funding from the Manasota Basin Board has been removed. A determination is being made on the benefit of
expanding the RO system to assist with meeting the proposed MFL on Shell Creek. If it is determined that the RO
expansion will not benefit the MFL recovery strategy, Governing Boards funds will be balanced forward into General
Fund and the project will be reevaluated as a local cooperative funding project solely funded by the Peace River Basin
Board.
021 - Manasota Basin 190
H088
Pilot Treatment Study and Intermediate Well for Dona Bay Water
Supply ProjectProject Type WS&R Dev.
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Alternative Water SupplyNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) General Fund (District), Peace River, Manasota
Sarasota CountyCooperator(s)
Project Manager MORRIS, LISANN
HEYL, MIKETask Manager(s)
Status Proposed
DescriptionThis project includes construction and testing of an intermediate test well and a pilot treatment study to determine the
most technical and economical options for treating surface and groundwater proposed as part of Dona Bay water
supply project. The overall objective of the Dona Bay water supply project project is to decrease excess freshwater
flows to Dona Bay and provide an alternative source of water within the Southern Water Use Caution Area. This
project will provide the necessary information to determine the feasibility of moving forward with treatment options for
implementation and construction of the Dona Bay Water Supply project.
BenefitsThe Pilot Treatment Study and Intermediate test well will provide technical and economic information on how to best
treat surface water and groundwater sources at a common water treatment facility. Actual bench-scale testing of
treatment technologies will benefit future regional water supplies and assist in determining the feasiblity of moving
forward with the second phase of the Dona Bay Water Supply project.
Costs
The total estimated cost for this project is $2,299,000, and the District is requested to fund 50 percent ($1,149,500).
The District funding will be divided between the Governing Board (50 percent) and the Manasota Basin Board (50
percent). The funding approved in FY2010 includes $500,000 from the Governing Board and $250,000 from the
Manasota Basin Board, for a total of $750,000 in District funding. The request for FY2011 for the pilot treatment
study\intermediate test well includes $74,750 from the Governing Board and $324,750 from the Manasota Basin
Board, for a total of $399,500 in District funding. The requested FY2011 funds will complete the District's share of
funding for this task of the Dona Bay Water Supply project. The future funds identified for the project are contingent
upon approval of such amounts by the District Governing Board and the Manasota Basin Board in their annual
budgets.
Additional Information
The Dona Bay Watershed Management Plan (DBWMP) was finalized in June 2007 (L493). This project is a portion of
the first phase in an overall plan to reduce excess freshwater flows directed into Dona Bay by the Cow Pen Canal that
was constructed in the late 1960s. Excess freshwater flows have decreased the seasonal salinity concentrations
necessary for estuarine dependent flora and fauna. The plan is to divert, store and transport excess freshwater flows
from Cow Pen Slough prior to discharge into the Dona Bay Estuary, which could provide an alternative water supply in
the SWUCA as well as environmental benefits to the bay. Water from Cow Pen Slough would ultimately be
transported to Sarasota County's Carlton Facility for treatment and distribution. Potential water supply capacity is
estimated in 3, 5, 10, and 15 mgd phases and Sarasota County has already begun design and permitting for other
elements of the larger Dona Bay Water Supply Project such as: West Pinelands restoration, the new weir in Cow Pen
Slough, phased modifications of the Venice Minerals mine to a reservoir, and the conveyance from the new weir to
Venice Minerals. The PRMRWSA provided a letter indicating regional interest in the Pilot Treatment Study Task
making it eligible for Governing Board and Peace River Basin Board funding. Sarasota County and the PRMRWSA
entered into a Memorandum of Understanding in July2009 and are now working through Dona Bay Project agreement
issues.
021 - Manasota Basin 191
H088
Pilot Treatment Study and Intermediate Well for Dona Bay Water
Supply Project
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 6,499,947 5,911,180 0 0 74,750 514,017
020 Peace River Basin 6,950 0 0 0 2,006 4,944
021 Manasota Basin 6,495,523 5,911,180 0 0 324,750 259,593
Project Funds Not Budgeted by the
District
Sarasota County 5,742,386 0 0 1,200,000 2,742,386 1,800,000
$18,744,806 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Initiate Pilot Treatment Study 6/25/10
MOU agreement with Authority 7/27/10
Status As Of: February 24, 2010
Staff continues to monitor the progress between Sarasota County and the Authority as they work through the MOU to
jointly move forward with the Dona Bay Water Supply project. A meeting was held August 21, 2009 to get an update on
environmental benefits information and to discuss the possibility of proceeding with the Water Quality Pilot Treatment
task as soon as possible. The County forwarded the draft Request for Professional Services on December 11, 2009 for
review on the Pilot Treatment Study component for this project. Comments from the District were submitted on
December 22, 2009. Pilot treatment study was advertised by the County on January 20, 2010. Submittals from
prospective consultants are due February 25, 2010. Both the Authority and District will participate in some fashion in the
review of the submittals. The Authority provided a letter indicating regional interest in the Pilot Treatment Study Task
making it eligible for Governing Board and Peace River Basin Board funding.Current Status: Because two challenges
were received on the Request for Services (RFS) for the Pilot Treatment Study released by the County, advertising for
consultant services is delayed until after the Sarasota County Commission meets on March 16, 2010. Once the County
makes a decision on their procurement process the RFS will be re-advertised. District staff is developing the cooperative
funding agreement for the Pilot Treatment Study and Intermediate Well.
021 - Manasota Basin 192
H089
Flatford Swamp Hydrologic Restoration\Implementation
Project Type WS&R Dev.
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Alternative Water SupplyNatural Systems Natural Systems Conservation and RestorationFlood Protection Floodplain Management
Basin(s) General Fund (District), Manasota
Cooperator(s)
Project Manager MORRIS, LISANN
SZAFRANIEC, MARY, STARKS, ROBERTA, ARNOLD, DAVETask Manager(s)
Status Proposed
DescriptionHydrologic alternations and excess runnoff has adversely impacted Flatford Swamp in the upper Myakka watershed.
This project will remove excess flows from Flatford Swamp and some portions of the surrounding area to improve the
natural systems. This project will include design/permitting and construction of the alternatives identified from the
results of the evaluation from the Myakka River Watershed Initiative (H048). Also included will be training for District
staff on use of the Upper Myakka Water Budget Model (developed under H048) which will be utilized to track
performance of the proposed BMPs after construction. The FY2010 funding is anticipated to initiate studies with
potential partners to explore the feasibility of taking the excess water effecting the swamp. Also the Upper Myakka
Water Budget model developed under H048 will be updated to 2010 Mike SHE software.
BenefitsThe Flatford Swamp hydrologic restoration alternative will work to re-establish hydro-periods close to historic levels
estimated by the Upper Myakka Water Budget model and for natural systems restoration. Depending on the potential
end user for the excess water removed from the Flatford Swamp area the benefits could range from a recovery
strategy for a MFL, groundwater use offset, and to recharge the Floridan aquifer near the MIA.
Costs
The estimated cost for the H089 Flatford Swamp Hydrologic Restoration ranges from $70,000,000 to $120,000,000
from early conceptual estimates. District funding in FY2010 is divided as follows: General Fund $400,000; Manasota
$400,000. For FY2010 the plan is to initiate feasibility studies with potential users and to perform an initial evaluation of
natural systems restoration opportunities. The restoration alternatives matrix of Flatford Swamp options (H048) is
expected to be completed in early 2010 when total costs for the next phase will be more defined. Funding requested
for FY2011 is: General Fund $250,000, Manasota $250,000 for a total of $500,000. Funds will be used to refine the
alternative analysis and to meet with potential users and respond to questions raised on the proposed conceptual
design.
Additional Information
Work from the Myakka River Watershed Initiative has shown there is no "one" best management practice that will
mitigate problems within the Flatford Swamp. The plan is to address the issues with a multi-prong adaptive
management approach. With the amount of excess water that in the past has effected the swamp, a workhorse
project is needed to successfully bring hydroperiods within the swamp back to a more historic level. The analysis of
the hydrologic restoration alternatives for the "workhorse" has been divided into three parts: 1)Withdrawal scenarios
from the Flatford Swamp either by diverting flow before it reaches the swamp or removal from the swamp, 2)Storage
for excess water depending on where the end user of the excess water is located, 3)transmission and water quality
treatment to potential water users.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 33,499,490 30,000,000 0 0 3,019,521 479,969
021 Manasota Basin 33,496,324 30,000,000 0 0 3,019,012 477,312
$66,995,814 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 193
H089
Flatford Swamp Hydrologic Restoration\Implementation
Critical Project Milestones ActualProjected Amended
WMP Consultant Services-Prelim. DesignDevelop Contract Amendment 3/31/10
Status As Of: February 22, 2010
Work continues on H048 to refine preferred alternatives for hydrologic restoration before moving these options into
preliminary design. Anticipate an agreement being developed by June 2010.
021 - Manasota Basin 194
H093
Manatee County Regional 10 MG RW Storage SW-2
Project Type WS&R Dev.
AORs Strategic InitiativesWater Supply Alternative Water SupplyWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Proposed
DescriptionThis project will design and construct the second of four 10 Million Gallon (MG) reclaimed water storage tanks in
support of the Manatee County Agricultural Reuse System (MARS). MARS is a regional system that consists of the
over 21 miles of transmission lines that interconnect Manatee County's three regional Wastewater Treatment Facilities
(WWTF). The MARS system supplies reclaimed water for irrigation of agricultural, residential, and recreational
customers, thereby decreasing dependence on potable groundwater. New residential developments, some with golf
courses, have been replacing agricultural demand and many are planned or under construction along the transmission
route. These developments are potential customers of the MARS System. The MARS system is designed to distribute
over 30 mgd. Currently the County relies on one 3 MG tank at the Spencer Parrish Pumping Station and one .75 MG
tank at it's North Wastewater Reclamation Facility to meet peak demand. Wastewater plant peak flows are processed
during the daytime and used primarily at night. This condition requires the county system to have sufficient tank
storage to meet the nightime peak demand. The District and County are in the process of constructing the first 10MG
reclaimed water ground storage tank (H086) at the Southwest Wastewater Reclamation Facility with FY2010 funding.
The addition of this second 10 MG tank, and two more planned 10 MG tanks, will better enable the County's regional
system to provide for the nightly peak demand events, without comprimising pressure and water quality. This tank will
also be located at the County's Southwest Wastewater Reclamation Facility.
BenefitsThis 10 MG reclaimed water storage tank will better enable the County to accommodate its customer base as it
evolves from purely agriculture to a mix of customers, including residential. The storage will assist the county in
providing reclaimed water for irrigation purposes throughout its system to its customers during nightly peak demand
events, without comprimising pressure and water quality.
Costs
The total project design and construction costs are estimated to be $5,000,000. The District's share is $2,500,000 or
fifty percent, of which the county is requesting $625,000 from the Governing Board and $625,000 from the Manasota
Basin Board in FY2011 and will request $625,000 from the Governing Board and $625,000 from the Manasota Basin
Board in FY2012. The cost benefit cannot be calculated, since the project addresses system storage and efficiency,
and offsets will be associated with future related transmission projects. The total project cost includes $500,000 for
design and $4,500,000 for construction. Future funds identified for the project are contingent upon the approval by the
District in their annual budgets.
Additional Information
The proposed second 10 MG Reclaim Water Storage Tank is an enhancement to the existing Manatee County
Agricultural Reclaim System (MARS). This system reduces demand for public potable water for irrigation, improves
overall utilization of existing SWFWMD water resources and provides on demand high quality irrigation water for our
urban and agricultural customers. MARS is an integral part of Manatee County water conservation program. The
County's overall program includes existing metering and loss reduction programs, water conservation rate structures,
urban and agricultural reclaim water irrigation supply, public education, SWUCA based level of service for water
supply at 110 gpfcpd, land development codes requiring non-potable sources for irrigation in new developments, water
supply protection ordinances and the use of aquifer storage and recovery for potable and potentially reclaimed waters.
021 - Manasota Basin 195
H093
Manatee County Regional 10 MG RW Storage SW-2
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 1,251,510 625,000 0 0 626,510 0
021 Manasota Basin 1,251,510 625,000 0 0 626,510 0
Project Funds Not Budgeted by the
District
Manatee County 2,500,000 1,250,000 0 0 1,250,000 0
$5,003,020 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of:
021 - Manasota Basin 196
K114
Bradenton - ASR Program
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) Manasota
City of BradentonCooperator(s)
Project Manager ELLISON, DON
Task Manager(s)
Status Ongoing
DescriptionThis project is to permit and construct up to three additional monitoring wells, and perform two additional cycle tests at
the City of Bradenton's Downtown aquifer storage and recovery (ASR) site. The project is a continuation of the City's
Downtown ASR project that is located at the High Service Pump Station (HSPS) in Downtown Bradenton and will
provide 1.5 mgd of potable water during the 100-day dry season. The wells will be constructed to address FDEP
monitoring requirements for sites mobilizing arsenic in the subsurface. These wells are estimated to be about 550 feet
deep and completed into the aquifer storage zone, and will be located within several hundred feet of the ASR well. The
wells are being required by the FDEP. Funding requested for the project includes engineering fees for the required
Area of Review analysis, an update to the Well Inventory, and additional storage zone monitoring wells required by
FDEP. Funding is also being requested to modify FDEP permit No.133098-074-UC/MN for construction of the
additional monitoring wells; for the design, bid, award, construction and testing of up to three additional monitoring
wells; and for the extension of Cycle Testing to include Cycles 7 and 8.
BenefitsThis project is expected to provide 1.5 mgd potable supply during a typical 100 day dry season which is needed to help
the city provide a more reliable source of water during periods of low flow in Braden River. The information from this
project will also support the Districts efforts to find methods to minimize arsenic mobilization in the aquifer during ASR
activities.
Costs
The total cost for all prior and ongoing project work is $2,684,250 ($1,342,125 each) and is contained in two separate
contracts. The first contract was completed in October 2005 and covered the construction and testing of an ASR well
and monitoring well for a total amount of $1,625,000 ($812,500 each). The second contract was initiated in FY 2007
and covers the construction of up to three new monitoring wells and continuation of cycle testing through FY2010 for a
total amount of $1,059,250 ($529,625 each). With the allocation of $101,650 from the Water Protection Sustainability
Trust Fund Program, the City's and District's equal shares of the second contract have been reduced to $478,800
each. The District's budget as it appears below does not reflect the $655,000 that was funded in FY2000 and prior
years, nor the $529,625 that was transferred into the project in FY2006 from project L513, the City's reservoir ASR
site.
Additional Information
The existing ASR well (1.5 mgd injection/recovery capacity) and piping was constructed in 2003 with cooperative
funding from the District. The City has completed 6 cycle tests as required by Florida Department of Environmental
Protection (FDEP) permit No.133098-074-UC/MN. Cycle test results have identified arsenic mobilization in the
subsurface and further plans for cycle testing is on hold until a new approach to control the arsenic mobilization
problem within acceptable Drinking Water Standards is developed. Continuation of cycles tests 7 and 8 is on hold until
the City identifies an acceptable approach, the additional monitoring wells at this point are to identify the extent of
arsenic contamination in the aquifer. The City has one storage zone monitoring well offsite with arsenic exceeding the
Drinking Water Standard of 10 ppb.
021 - Manasota Basin 197
K114
Bradenton - ASR Program
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 778,773 0 448,350 305,251 18,868 6,304
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
101,650 0 101,650 0 0 0
Project Funds Not Budgeted by the
District
City of Bradenton 687,125 0 0 687,125 0 0
$1,567,548 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesDistrict Recognition/Signage: YES 10/1/00 10/1/00
2. First Contract for ASR well Construction and Cycles 1-6Preparation of Plans and Specs 10/1/00 10/30/02 10/30/02
Permitting 9/1/01 9/30/02 9/30/02
Well Construction 1/1/02 11/20/03 11/20/03
ASR Cycle Testing Through Cycle 6 2/1/02 12/20/04 10/1/05
First Contract Amendment 2/25/02 5/3/02
Final Report 3/28/02 7/20/05 10/1/05
Project Complete 5/27/02 9/20/05 10/1/05
Contract Termination 10/1/02 10/1/05 10/1/05
3. Second Contract (Pending) for Montioring Wells and Additional Cycle TestsTask 1 Cycle 6a Recovery and Design Equipment Upgrades 6/30/06 6/30/06
Task 2 SZMW-3 Design, Permitting 10/30/06 12/30/09
Request Basin Board Transfer of Funds 12/30/06 12/30/06
Contract Execution 1/30/07 1/24/07
Task 3 SZMW-3 Construction 10/30/07 12/30/09
Task 4 Cycle Test 7 10/30/08 12/20/07
Task 5 Feasibility Study Update 10/30/08
Task 6 SZMW-4 & SZMW-5 Design, Permitting, Construction 5/30/09
Task 7 SZMW-4 and SZMW-5 Construction 10/30/09
Task 8 Cycle Tests 8 and 9 10/30/10
Task 9 Final Report, Application for Operations Permit 10/30/11
Second ContractContract Completion Date 12/30/11
Status As Of: January 11, 2010
The scope of work for the first contract to construct and test an ASR well at the Downtown Booster Station site has been
completed and all submittals have been received. Arsenic concentrations exceeding the drinking water standard (DWS)
were observed in the monitoring well 200 feet away at the end of the cycle test 6. This new data indicates that the arsenic
standard would be exceeded at the property line 75 feet away. In response to the arsenic mobilization issue at this site
the City, FDEP, and District have been developing strategies to address the issue. Part of the strategy developed was to
install additional monitoring wells and to continue cycle testing to demonstrate that the arsenic issue is limited in extent
and not posing a threat to the aquifer. The strategy was, at the time consistent with guidance received from the FDEP
indicating that as long as the arsenic concentrations were below the DWS at the property boundary, the site would be
eligible for an operational permit. The City submitted a request for FY2007 funding through the District's Cooperative
Funding Program to proceed with this additional work. Because of the urgent need to address the arsenic mobilization
issue, the City made a request to the Manasota Basin Board at it's April 2006 meeting to transfer $550,000 in FY2006
021 - Manasota Basin 198
K114
Bradenton - ASR Program
funds from the City's ASR project at the Evers Reservoir (L513) for use in this project. The request was approved by the
Basin Board at it's April meeting and the City has thus withdrawn their FY2007 cooperative funding application. The
District and City have executed the contract for this additional testing. Since that time the FDEP has changed their
position on permitting ASR facilities with the arsenic issue and is now indicating that any site with arsenic anywhere that
exceeds the DWS would not be permitted for operational use. The only option at this time is to explore pre-treatment of
the injection water to produce compatible water qualities between the injectant and the native water in the aquifer.
Recognizing this requirement, the District approached the City with a request to participate in a pre-treatment study to
remove dissolved oxygen and other oxidants from the injection water which are suspected of being the primary causes of
the arsenic mobilization. The property line monitoring well(s) will still be necessary, but it is contingent on the
implementation of the pre-treatment option. The scope of work for the pre-treatment option has been developed by the
City and bids have been awarded for construction under a separate contract. The City has completed construction of the
pre-treatment system and started cycle testing with de-oxygenated water on December 2, 2008. Equipment problem
arose after two weeks of operation and was shut down for repair in January. Repairs have been completed and the full
scale cycle test injecting 140 mg of de-oxygenated water began in August 2009. As of december 2009 the city has
injected approximately 95 million gallons of degassed water. The city will continue injection through February and start
recovery in May or June 2010.
021 - Manasota Basin 199
K120
North Port - Water ASR - Phase V
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) Manasota
City of North Port - Public Utilities, City of North PortCooperator(s)
Project Manager KELLEY, MIKE
Task Manager(s)
Status Ongoing
DescriptionThis project consists of an Aquifer Storage and Recovery (ASR) Program in the City of North Port to create an
alternative water supply by treating excess wet season flows from Myakkahatchee Creek and storing it in the
mineralized Floridan aquifer. The location is downtown North Port at the water treatment plant. The goal of the project
is to develop a 1.5 million gallon per day dry season supply. FY2008 funding is for Phase V of the project which is for
the installation and testing of a degasification system and for the injection and recovery of treated water, cycle test 4.
Longer duration cycle tests will follow. These cycle tests should determine the effectiveness of removing dissolved
oxygen from injected water on arsenic mobilization in the aquifer and recovered water. Phase V will finish this project.
BenefitsThe goal of this ASR project is to develop a 1.5 million gallons per day (mgd) dry season supply (equivalent to an
annual average of 410,000 mgd). ASR is an effective method of optimizing the supply of water available from the
Myakkahatchee Creek. Combined with the City's allocation from the Peace River/Manasota Regional Water Supply
Authority (PR/MRWSA), this ASR project has the potential to enable the City of North Port to meet its needs until
approximately 2014.
Costs
The FY2010 funding request for $60,000 is to continue FDEP required sampling and testing of water quality in the
monitor wells through 2009 and 2010 while this project is on stand by. This project will continue when we have
favorable, recovery water quality results from the cycle testing at the Bradenton ASR site. The estimated total cost to
conduct Phase V of the project is $619,000 and will be shared by the Manasota Basin Board and the City of North Port
on a 50/50 cost-share basis ($309,500 each). The Basin's contribution will be provided as follows: $75,000 previously
approved in the Basin's FY2007 budget; $126,000 that is in the FY2008 budget; and the remaining $108,500 is in the
FY2009 and future budget years. Funding for FY2009 is combined with approved funding for FY2008 to expand Phase
V of the project to monitor and finish cycle test 4, and run additional longer cycle tests at the City's ASR site. The total
cost of the project is approximately $2,000,000 including prior phases I-IV and funding through FY2010. The Manasota
Basin Board and the City of North Port each contributed about $1,000,000.
Additional Information
Phase I determined ASR was the most effective method of optimizing the supply of water available from North Port
Utility's only local source, the Myakkahatchee Creek. The objective of Phase I was to determine the feasibility of ASR
at the North Port water treatment facility, and compare its merits and disadvantages with those of other forms of water
storage, primarily aboveground facilities. During Phase II, the City's consultant designed the ASR well system and
acquired construction and water use permits from the FDEP and the District. They also applied for a Class V injection
well permit from the FDEP. Phase III included construction and testing of the ASR well and monitor wells, and project
report writing. Phase III was initiated July 2001 and is complete. Line item adjustments have been made to Phase III to
change the focus of this ASR project from treated raw water to fully treated potable water ASR. Cycle tests one and
two were included in Phase III. Phase IV of the City's pilot ASR Program includes engineering services, hydrogeologic
field work, data collection and analysis, laboratory analytical services and completion report to accommodate the third
cycle test as required by the FDEP UIC permit for the project. The third cycle test was not included, as it was not
anticipated to be required by the FDEP at the time the Phase III agreement was finalized. The Phase III agreement is
being extended to 12/31/2005 to allow sufficient time to complete all activities related to finalization of the second cycle
test. Completion of the cycle test was hampered for a couple of reasons. First, the start of the injection portion of the
test was delayed due to a lack of water when the city was providing emergency water supplies to the PR/MRWSA
after Hurricane Charley hit the area in August 2004. The second major reason was the fact that the recovery portion of
the test was halted prematurely when the recovered water, which was directly discharged into Myakkahatchee Creek,
exceeded the standard for arsenic concentration of 50 micrograms/liter (ug/L). The DEP was contacted and the
second cycle test is considered complete. A third cycle test began 8/2/2005 and injected a million gallons per day of
treated water for 75 days which was to remain in storage 30 days. Recovery is delayed due to the construction of a lift
station to pump recovered water to the wastewater treatment plant because initial recovered water is anticipated to
021 - Manasota Basin 200
K120
North Port - Water ASR - Phase V
exceed the 50 ug/L arsenic limit. When recovered water quality is below 50 ug/L arsenic the discharge will be to
Myakkahatchee Creek. The recovered water during Cycle Test 3 was all discharged into the sanitary sewer system.
The arsenic levels remained above the maximum contaminate level (10 ug/l) in the recovered water. The FDEP
construction and testing permit is complete for Cycle Tests 4 through 6.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 974,918 0 0 904,049 5,467 65,402
Project Funds Not Budgeted by the
District
City of North Port 1,013,752 0 0 953,752 0 60,000
$1,988,670 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. PHASE IBoard Approval of Contract 11/24/98 11/24/98
Execute Contract 1/11/99 1/11/99
Feasibility Report Completed 10/28/99 10/28/99
Contract Termination 12/31/99 12/31/99
2. PHASE IIBoard Approval of Contract 4/25/00 4/25/00
Board Approval of Contract 6/19/00 6/19/00
Contract Termination 6/19/01 6/19/01
3. PHASE IIIBasin Board Approval of Agreement 5/16/01 5/16/01
Governing Board Approval of Agreement 5/31/01 5/31/01
Contract Executed 7/20/01 8/8/01
FDEP Permitting (Construction and Testing) 7/31/01 7/31/01
Well Construction and Testing Completed 8/15/02 3/1/03
ASR Cycle Testing Completed 11/15/03 9/30/05
Final Report 12/31/03 12/31/05 12/31/05
Contract Termination 12/31/03 12/31/05 12/31/05
4. PHASE IVBasin Board Approval of Agreement 12/15/03
Governing Board Approval of Agreement 12/15/03
Contract Executed 9/1/04 9/27/04
Final Report 12/31/05 12/31/07 12/14/07
Contract Termination 12/31/05 12/31/07 12/31/07
FDEP Permit Required ASR Cycle 3 Testing Completed 8/15/06 12/15/06 12/15/06
5. PHASE VCooperative Funding Agreement 3/1/08 3/1/08
Status As Of: February 03, 2010
A teleconference was held December 17, 2009 with the City of North Port Utilities and Entrix, their consultants. We
discussed the design drawings and documents of the ASR de-gasification equipment and the test of the new hydrogen
sulfide addition to ASR at DeLand, FL. We also addressed the contract amendment to add Jerry Manning as
co-manager, an end date extension and the budget change for more monitoring. The contract amendment is being
drafted. Also, we planned for the North Port requested delay until 2014 for the start of testing the ASR pre-treatement
system. The North Port the cooperative funding agreement, Phase V, for FY2010 is in effect. No new 2011 funds are
021 - Manasota Basin 201
K120
North Port - Water ASR - Phase V
requested. Our existing funding for monitoring and testing will cover the requested delays. Groundwater sampling and
testing from monitor wells are ongoing. The water quality has returned to ambient conditions and the ASR well flow has
been shut off. The consultant is working on the coordination, design review and engineering of the degasification
equipment. ACTION-TO-DATE: Delayed. The project has been delayed as noted in the status above. An information
request concerning the Accelerate Florida Program was mailed to the cooperator on October 15, 2008. District follow-up
email on January 12, 2009 prompted an email from Jennifer Desrosiers, North Port Business Manager, January 29,
2009. She sent a spreadsheet of preliminary action plans for projects with District funding. She stated that she was eager
to accelerate North Port projects. Specific to this ASR project she says "This project is being monitored pursuant to our
SWFWMD contract and we are awaiting the results of the pre-treatment study being conducted at the Bradenton ASR
project site to remove dissolved oxygen and other oxidants from the injection water to mitigate the arsenic problem."
021 - Manasota Basin 202
K253
Manatee - Imp. BMPs Wares Creek
Project Type Cooperative Funding
AORs Strategic InitiativesFlood Protection Floodplain Management
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager FRIES, GEORGE
Task Manager(s)
Status Ongoing
DescriptionThis is a multi-year funded project to perform the Implementation of Best Management Practices (BMPs) element of
the District's Watershed Management Program (WMP) for the Wares Creek Watershed. Implementation of BMPs
includes the following tasks: design, development of construction documents, construction permitting, land acquisition,
bidding and contractor selection, construction of the BMPs and construction engineering and inspection. Wares Creek
is an intermediate-scale system that conveys stormwater from a 6.23 square mile watershed that flows from the
unincorporated areas of Manatee County north through the City of Bradenton before discharging to the Manatee River.
The Wares Creek Flood Protection Project is a joint effort between Manatee County (County) and the United States
Army Corps of Engineers (USACE), as authorized by the U.S. Congress in the Water Resources Development Act of
1996, to reduce flood damage within the Cedar Hammock (Wares Creek) Drainage Basin located in west central
Manatee County. The USACE has proposed channel widening and bank stabilization of Wares Creek to reduce flood
levels to within-bank for a storm event of a 10-year magnitude. Wares Creek channel improvements will begin at the
confluence of Wares Creek with the Manatee River and end at the 44th Avenue West crossing (Cortez Road).
BenefitsThe project will provide additional capacity within the stream banks and, thereby, provide an improved level of service.
These improvements will address structure flooding along Wares Creek by providing flood protection for homes
currently inundated and damaged during the 10-year flood event. Based on an analysis prepared by the USACE, the
project will provide a positive benefit/cost ratio.
Costs
The total projected cost for this project is $55.2 million of which the District's share is $14,254,000. The County will
contribute $14,254,000. Additional funding of $2,150,000 will be provided by the Florida DEP and $24.5 million will be
provided by the US Army Corps of Engineers. Funding for this project has been provided in the Manasota Basin Board
budgets for FY2000 ($346,000); FY2001 ($862,000); FY2002 ($431,000); FY2004 ($892,500); FY2005 ($500,000);
FY2006 ($3,000,000); FY2007 ($2,000,000); and FY2008 ($2,885,036) for a total funding commitment through
FY2008 of $10,916,536. Future funding of $3,337,464 will be required to complete the District's obligation to fund the
project. The future funds identified for the project are contingent upon approval of such amounts by the District
Governing Board and Basin Board in the annual budget(s). When each element is completed the project budget and
scope may require refinement based on the information gathered. The District funding amounts shown in the table
include staff salaries.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of BMPs, and 5) Maintenance of Watershed Parameters and Models.
Implementing elements of the WMP with local governments is one of the District's Strategic Priorities. The WMP
provides a method to evaluate the capacity of a watershed to protect, enhance and restore water quality and natural
systems while achieving flood protection. This project involves the Implementation of BMPs. The total project cost
(construction plus easement acquisition) was estimated to be $13.4 million in 1996 and in 2005 was estimated at
$55.2 million of which $24.5 million is the responsibility of the USACE while the remaining $30.7 million is the
responsibility of the local sponsor, Manatee County. In FY2000 the Basin Board agreed to participate with Manatee
County in the project by providing one-half of the County's required share of 5% of the total project cost. The Basin
Board budgeted $346,000 in FY2000 and a cooperative funding agreement was executed. A second cooperative
funding agreement was developed in FY2001 for the Wares Creek Project for rights-of-way and easement
acquisitions necessary to construct the creek enhancements. In FY2001 the Basin Board provided funding of
$862,000; in FY2002: $431,000; and in FY2004: $892,500. In FY2005 the County requested additional funding of
$500,000 for right-of-way and easement acquisition because of the steady increase in land values in Manatee County
since the original estimate was developed in 1996. The Board budgeted the additional funds and the agreement was
amended to incorporate these funds. For FY2006 the County requested that the project scope be amended to
incorporate the additional construction work needed to extend the project to the Manatee River and to provide
021 - Manasota Basin 203
K253
Manatee - Imp. BMPs Wares Creek
additional funding for easement acquisitions and project construction. The Basin Board, at its April 2005 meeting,
agreed to this change in scope and scale of the project. Furthermore, the Basin Board, at its August 2005 meeting
budgeted $3,000,000 for FY2006 for this project. For FY2007 the county sought additional funding of $2,000,000 to
be applied towards the land acquisition and easement expenses and the non-federal share of construction including
dredging of the lower Wares Creek between the Manatee Avenue Bridge and the Manatee River. A new cooperative
funding expenditure agreement has been developed to incorporate the change in scope and the additional funds. The
District is also co-funding project L200 with the City of Bradenton which will replace 4 bridges across Wares Creek
within the city limits and will provide additional flow capacity within the stream banks.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 13,481,465 2,517,464 0 10,957,527 3,276 3,198
Project Funds Not Budgeted by the
District
Florida DEP (Bradenton) 500,000 0 0 500,000 0 0
Florida DEP (Manatee County) 1,650,000 0 0 1,650,000 0 0
Manatee County 14,254,000 0 0 12,916,536 0 1,337,464
U.S. Army Corps of Engineers 24,507,500 0 0 24,507,500 0 0
$54,392,965 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesDistrict signage will be provided on all construction signs. 12/1/02
2. 5% ConstructionDistrict Agreement Execution 5/31/00 5/31/00
USACE Execution of the Memorandum of Agreement 1/31/01
Permitted Construction Drawings 3/15/01
Begin Construction 12/1/02
Contract Termination 3/31/05 3/31/06
3. Rights-of-Way AcquisitionsDraft Agreement to Management Services 12/15/00 1/18/01
Survey Work Began 12/18/00 12/18/00
Draft Agreement Returned from Management Services 1/31/01 3/12/01
Basin Board Approval of Agreement 2/21/01 2/21/01
Governing Board Approval of Agreement 2/26/01 2/26/01
Contract Executed 4/15/01 8/23/01
Notice to Proceed 9/5/01 10/2/01
4. FY 2005 FundingDraft Agreement to Management Services 6/30/04 6/30/04
Draft Agreement Returned from Management Services 7/15/04 7/15/04
Contract Executed 8/15/04 10/28/04
Notice to Proceed 8/16/04 11/1/04
Project Complete 12/30/04 12/31/06
Contract Termination 12/31/04 12/31/06
5. New Agreement (FY 2006/2007/2008 funding)Contract Executed 3/31/07 3/6/08
Notice to Proceed 3/31/07 3/7/08
Funds Encumbered 4/15/07 3/24/08
021 - Manasota Basin 204
K253
Manatee - Imp. BMPs Wares Creek
Project Complete 12/31/12
Contract Termination 12/31/12
Status As Of: February 17, 2010
Status History: County staff appeared before the Manasota Basin Board at the April 2005 meeting and requested an
amendment to the cooperative funding agreement to permit the County to use the Land Acquisition and Easement
funding for construction as well as easement acquisition. As discussed by County staff, the cost of the entire project was
estimated, at that time, to exceed $55,000,000. County staff made a presentation to the Basin Board at its July 2007
meeting to discuss project status, economics and direction. County staff is continuing the acquisition of land and
easements necessary for the project. The County has submitted three requests for reimbursement for land and
easement acquisition which have been approved. The County attorney's staff is working on the Project Partnership
Agreement (PPA) between the County and the ACOE. The Board of County Commissioners (BCC) has authorized staff
to begin eminent domain proceedings against Bradenton Tropic Palms Mobile Home Park. The County has taken
possession of the former City Hall site (now in private ownership) located at Manatee Avenue and Wares Creek for use
as a temporary spoil storage site. An amendment to the Cooperative Funding Agreement, revising the project budget and
providing funding for the acquisition of the former Bradenton City Hall property for dewatering of the dredged materials,
was drafted and is with the County waiting on action by the BCC which is scheduled for March 2010. ACTION-TO-DATE:
Delayed. The FDEP has issued the required permit. The County and the ACOE are planning to dispose of the dewatered
dredged material at the County landfill. The cost and funding for this disposal have not been decided upon at this time.
Land acquisition for the most southerly (upstream) phase of the work has begun now that the FDEP permit is in place.
The USACE and the FDEP are negotiating conditions of the PPA. These negotiations were expected to be completed by
July 2009 but are now projected to be completed by March 2010. Bidding and Contractor selection are expected in the
spring of 2010 with construction commencing in September 2010.
021 - Manasota Basin 205
K269
Sarasota Co. - N. Sarasota Co. Reclaimed Water ASRs
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Reclaimed Water
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project consists of the design, permitting, and construction of three 1.2 mgd reclaimed water aquifer storage and
recovery (ASR) wells with ultra-violet (UV) disinfection. These ASRs will be constructed at the County's Central County
Wastewater Treatment Facility (WWTF). The ASRs will provide wet weather storage for the County's Northern
Regional Reuse System, consisting of four interconnected county WWTFs's and a interconnection with the City of
Sarasota's Reuse System.
BenefitsThe project will provide storage of approximately 1,200,000 gpd for 120 days or 144 million gallons per year for each of
three proposed ASR wells for a total of 432 million gallons per year stored. This will yield a flow of approximately
888,000 gpd of reclaimed water to offset existing ground-water withdrawals and potable service and better serve
existing reclaimed water users such as Palmer Ranch, Manor Care of Boynton Beach, Plaza Oaks, Silver Oak, and the
Hamptons Development.
Costs
The total project cost is estimated to be $6,443,546, and the District's share is requested to be 50 percent, or
$3,221,773. The Manasota Basin has funded $2,011,743 so far, between FY2000 and FY2007, and the WPSTF
provided $164,864 in FY2006/7, for a total of $2,176,607 already budgeted for the project. The Manasota Basin will
fund $1,127,598 in future years. The cost, amortized at 8 percent over 30 years, is $1.75 per thousand gallons of
traditional water offset. Any additional funds are for staff time. The future funds identified for the project are contingent
upon approval of such amounts by the District Governing and Basin Boards in the annual budget(s).
Additional Information
This is a multi-year project that will expand Sarasota County's reclaimed water system by providing wet weather
storage for the interconnected reclaimed water systems of the Sarasota County and City of Sarasota. This regional
system has five wastewater treatment plants with a permitted capacity of 18.5 mgd and a reuse flow of 5.4 mgd that
are now interconnected. This wet weather storage will increase the system's efficiency. Cost history: The original
project was submitted to the SWFWMD in 1998 and was approved for multi-year funding beginning in FY2000 and
ending in FY2005 with a total cost of $3,030,000. Following a lengthy hearing resulting in DEP issuing a permit to
proceed with construction of the first of three ASR wells, a first amendment was approved in 2006, which increased
the total cost and apportioned the District's share as follows: Cost Breakout: FY2000 = $100,000 FY2001 = $550,000
FY2002 = $390,000 FY2003 = $405,000 FY2006 = $311,607 ($286,743 ad valorem $24,864 WPSTF) FY2007 =
$420,000 ($280,000 ad valorem $140,000 WPSTF) FY2010 = $350,000 FY2011 = $350,000 and FY2012 = $427,598.
The County has updated the costs, revised the timeline and also determined that split flow UV disinfection is needed
for this project to ensure that water quality can consistently meet drinking water standards prior to injection into the
aquifer. An added benefit of installing UV disinfection is documented effectiveness in treating water borne pathogens
that are not amenable to chlorine disinfection. The cost of the UV disinfection system for each well is estimated at
$580,000. Of the total project cost of $6,443,546, approximately 83 percent ($5,320,247) is expected to be needed for
construction, and the remainder ($1,123,299) for design and administration.
021 - Manasota Basin 206
K269
Sarasota Co. - N. Sarasota Co. Reclaimed Water ASRs
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 2,793,304 747,383 286,743 1,753,753 1,605 3,820
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
189,728 0 24,864 164,864 0 0
Project Funds Not Budgeted by the
District
Sarasota County 3,139,341 1,064,341 0 1,725,000 350,000 0
$6,122,373 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Agreement Executed: 5/10/00 5/10/00
Start Permitting and Design: 5/10/00 5/10/00
Complete Permitting and Design Well #1: 8/1/01 9/17/04
District Recognition/Signage: YES 5/1/02 5/1/02
Start Well # 1 Construction: 5/1/02 9/6/05
Complete Construction Well #1: 12/30/02 4/30/06 4/30/06
Engineering Report Well #1: 7/31/03 7/31/06 7/31/06
Start wellhead & UV construction: 9/30/03 1/31/10
Complete wellhead & UV construction: 12/16/03 9/30/10
Begin Cycle tesing Well # 1: 6/30/04 11/30/10
Start Well # 2 & # 3 Construction: 6/30/04 1/31/11
Complete Construction Well #2 & #3: 12/31/04 6/30/11
Final Invoice: 6/30/05 9/30/12
Project Completion: 12/31/05 12/31/12
Status As Of: February 19, 2010
The first reclaimed water ASR well system has been designed, permitted, and is under construction. The consultant,
PBS&J, is overseeing the construction. Diversified Well Drilling started on the Storage Zone Monitor Well (SZMW) on
September 6, 2005. The SZMW was completed February 28, 2006. The driller has completed the Lower Zone Monitor
Well (LZMW) and the Upper Zone Monitor Well (UZMW). A larger drill rig was mobilized and started drilling the ASR test
well February 2006. Construction of the ASR test was substantially complete by May 31, 2006. PBS&J has prepared a
final engineering report for construction and construction testing of the ASR. Design of the Central County Wastewater
Treatment Facility expansion, and the pumps, piping and UV treatment system for the ASR, is complete. The County
requested to add UV disinfection equipment and additional funding for this project in a FY2006 cooperative funding
initiative proposal. This was approved by the Basin Board and an amendment was executed on October 9, 2006 to
include the changes in scope and funding. The County and the District have agreed to put this project on hold pending a
resolution to the arsenic issue. The District is involved in studies to look for ways to meet the EPA and DEP water quality
requirements for arsenic. Results from these studies have been delayed due to the drought and are now scheduled to be
available in July 2010. To date, the Manasota Basin Board has encumbered $100,000 in FY2000, $550,000 in FY2001,
$390,000 in FY2002, $405,000 in FY2003, $286,743 in FY2006 and $280,000 in FY2007. Water Protection and
Sustainability Trust Fund (WPSTF) provided $164,864 for this project in FY2006/7. The remaining $1,127,598 will be
requested in future fiscal years. The County has spent $972,900 in design and construction costs for this project. To
date, the District has reimbursed the County $449,135 from the Manasota Basin and $74,631 from WPSTF funds.
021 - Manasota Basin 207
K883
North Port WMPlan Big Slough
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Emergency Flood Response
Basin(s) Peace River, Manasota
City of North PortCooperator(s)
Project Manager ARNOLD, DAVE
Task Manager(s)
Status Ongoing
DescriptionThis is a multi-year funded cooperative project with the City of North Port to perform 1) Topographic Information, 2)
Watershed Evaluation, and 3) Watershed Management Plan elements of the District's Watershed Management
Program (WMP) for the portion of the Big Slough watershed area lying within the City of North Port. The project
includes detailed study of 60 square miles within the City, and approximate study of the 135 square mile remainder of
the Big Slough watershed to obtain its influence on conveyance of runoff through the City. Issues in the watershed
include land alterations, flood protection, natural systems preservation, water quality preservation, protection and
enhancement of the City's surface water reservoir, and protection of the downstream Charlotte Harbor estuary.
FY2003-2006 funding is budgeted to complete the Topographic Information, Watershed Evaluation, Watershed
Management Plan elements. Topographic information includes the acquisition of data and development of the terrain
features in the Geodatabase to be used in the Watershed Evaluation. The Watershed Evaluation includes collection of
existing data, GIS processing of the terrain features to establish catchments and connectivity, field reconnaissance,
refinement of the terrain features and development of the hydraulic element point features. The Watershed
Management Plan element includes: development of watershed parameters for a specific use, GIS processing,
computer modeling, floodplain and water quality analysis, surface water resource assessment, establishment of LOS,
and BMP alternative analysis.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain and water quality management.
Costs
The total budgeted amount for this project is $1,280,000, of which the District's share is $640,000 provided by the
Manasota Basin. The City is contributing $640,000. Multi-year funding is over FY2003-2006 is budgeted to complete
the project. When each element is completed the project budget may require refinement based on the information
gathered.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. In accordance with Board approval, a cooperative funding revenue agreement with the City of North Port
was developed as a multi-year funded project contingent on the approval of future funding to complete WMP elements
through the Watershed Management Plan. This required cooperative funding requests each year in FY2003-2006 to
accumulate the project budget. The District is managing the project and entering into purchase orders and
agreements to accomplish project tasks. Future cooperative funding requests and agreements will be required for
Implementation of BMPs, and the Maintenance of Watershed Parameters and Models. The District is cooperating with
FEMA to modernize the flood insurance rate maps (FIRMs) in Sarasota County. Information developed with this
project will be used to update the FIRMs representing this watershed.
021 - Manasota Basin 208
K883
North Port WMPlan Big Slough
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 680,821 0 0 676,173 2,334 2,314
District Budgeted - Outside Revenue
North Port - Watershed Mgmt Program
(K883)
640,000 0 0 640,000 0 0
$1,320,821 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesDraft Agreement to Management Services 12/15/02 1/16/03
Basin Board Approval of Agreement 12/15/02 2/1/03
Draft Agreement Returned from Management Services 1/31/03 2/28/03
Governing Board Approval of Agreement 2/28/03 2/1/03
Cooperator Contract Executed 4/15/03 4/29/03
Consultant Contract Executed 10/1/03 7/29/03
Notice to Proceed to Consultant 10/1/03 8/27/03 8/27/03
Watershed Evaluation Commence 10/1/03 8/27/03 8/27/03
Watershed Evaluation Completion 1/1/05 4/1/05 4/19/05
Watershed Plan Commence 1/1/05 4/1/05 4/20/05
Watershed Plan Completion (project complete) 6/1/06 5/1/09
Project Close-out 6/1/07 7/1/09
Status As Of: February 22, 2010
Status History: The cooperative funding agreement was approved by the Basin and Governing Boards in February 2003.
Since then the agreement has been reviewed and executed by the City and the District. District staff negotiated a
contract with Ardaman and Associates, one of the consultants pre-qualified for performing watershed plans, for services
to be completed with the FY2003-2004 funding. Notice-to-proceed was issued, effective the date of the project kick-off
meeting (08/27/2003). Ardaman Associates submitted the first set of deliverables, consisting of annotated base maps,
GIS coverages, and summary letter of data collection results in December 2003. Since then Ardaman Associates has:
(1) completed the watershed field reconnaissance; (2) is continuing to develop the GIS database and hydrologic and
hydraulic inventories; (3) completed the field survey; (3) completed watershed parameterization and model development.
The late delivery of the Sarasota County LiDAR topographic mapping caused delays in this project, but Ardaman now
has the mapping and is proceeding without delay. Current Status: The project is complete through the Floodplain
Analysis deliverables. Ardaman is working to update the watershed based on toptgraphy and land use changes that
occurred between the 2005 and 2007 Sarasota County LiDAR mapping dates. This includes the process for QA/QC
review, peer review, public review/comments, and Governing Board approval. After the Governing Board approves the
submittal of floodplain results to FEMA for updating the Sarasota County FIS, Ardaman will make any needed revisions
to the the Level of Service and preliminary BMP Analysis deliverables, and proceed with the BMP analysis task.
021 - Manasota Basin 209
L007
Manatee - WMPlan Buffalo Canal/Frog Creek
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Minimum Flows and Level Establishment and Monitoring
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager NGUYEN, NAM
Task Manager(s)
Status Ongoing
DescriptionThis multi-year funded project is to perform the 1) Topographic Information, 2) Watershed Evaluation, and 3)
Watershed Management Plan elements of the District's Watershed Management Program (WMP) for the BUFFALO
CANAL/FROG CREEK Watershed. The watershed occupies approximately 18.8 square miles in northwestern
Manatee County and discharges into Terra Ceia Bay, an Outstanding Florida Water. The watershed is experiencing
rapid development without the benefits of a detailed Watershed Management Plan.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies and 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain management and water quality management.
Costs
The current budget amount for this project is $400,000, of which the District's share is $200,000 funded by the
Manasota Basin. The County is contributing $200,000. In FY2004, each party funded $50,000 for the project. The
remaining funds were funded in FY2005. When each element is completed the project budget and scope may require
refinement based on the information gathered. The District funding amounts shown in the table include staff salaries.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. A cooperative funding revenue
agreement with Manatee County was developed as a multi-year funded project to complete the WMP elements
through the Watershed Management Plan. The District is managing the project and will enter into purchase orders
and agreements to accomplish project tasks. Future cooperative funding requests and agreements will be required for
a BMP alternative analysis, the Implementation of BMPs, and Maintenance of Watershed Parameters and Models.
With prior year funding the Topographic Information and Watershed Evaluation should be completed. With FY2005
funding the work on the Watershed Management Plan element began and should be completed. Work on Watershed
Management Plan element includes the following tasks: survey, data management and development of watershed
parameters, GIS processing, computer modeling, floodplain analysis, and establishment of LOS.
021 - Manasota Basin 210
L007
Manatee - WMPlan Buffalo Canal/Frog Creek
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 250,697 0 0 231,836 8,687 10,174
District Budgeted - Outside Revenue
Manatee - Buffalo Canal/Frog Ck W/S
Stdy (L007)
200,000 0 0 200,000 0 0
$450,697 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesRecognition of District, Basin Board, County on reports 6/4/03
Select Consultant 6/4/03 6/4/03
Draft Coop Agreement to Management Services 7/15/03 7/15/03
Draft Coop Agreement to Management Services 7/28/03 7/28/03
Approval of Cooperative Agreement by Manasota Basin Board 8/12/03 8/12/03
Approval of Cooperative Agreement by Governing Board 8/26/03 8/26/03
Begin Negotiations with Consultant (K&S) 8/26/03 8/26/03
Execution of Cooperative Agreement by Manatee County 10/21/03 10/21/03
Execution of Cooperative Agreement by SWFWMD 11/7/03 11/23/03
Consultant Agreement to Management Services 11/26/03 11/26/03
Execution of Agreement by Consultant 1/9/04 1/20/04
Execution of Agreement by SWFWMD 1/30/04 1/30/04
Issue Notice to Proceed to Consultant/ Work Order #1 2/9/04 2/13/04
Terminate Consultant Agreement (K&S) 7/15/05 7/15/05
Execute New Consultant Agreement (JEA) 9/30/05 11/6/06 9/21/05
Issue Notice to Proceed to JEA for Work Order #1 10/31/05 10/28/05
Issue Notice to Proceed to JEA for Work Order #2 11/30/06 12/8/06
Termination of Consultant Agreement 10/31/10
Termination of Cooperative Agreement 12/31/10
1. Critical Project MilestonesExecute Expired Consultant Agreement w/JEA (05CON000119-A) 11/6/06 11/6/06
Execute Expired Cooperative Agreement (04REV0011-A) 1/25/07 1/25/07
Execute First Amendment to Expired Consultant Agreement w/JEA
(05CON000119-A)
1/14/08 1/14/08
Execute First Amendment to Expired Cooperative Agreement (04REV0011-A) 3/20/08 3/20/08
Execute First Amend. to Consultant Agrmt. (05CON000119-B) 10/1/09 9/17/09
Execute New Coop. Agrmt. (04REV0011-C) 2/26/10
2. Watershed Management Program ElementsCommence Element 1, Digital Topographic Information 2/13/04 10/28/05 2/13/04
Commence Element 2, Watershed Evaluation 2/13/04 10/31/05 10/28/05
Complete Element 1, Digital Topographic Information 11/30/05 12/31/06 10/3/06
Commence Element 3, Watershed Management Plan 3/1/06 11/1/07 11/1/07
Complete Element 2, Watershed Evaluation 4/1/06 11/1/07 11/1/07
Complete Element 3, Watershed Management Plan 12/31/10
Status As Of: February 22, 2010
At their August 2003 meetings, both the Manasota Basin Board and the Governing Board approved the FY2004 budget
for the project, approved the cooperative agreement with Manatee County for $400,000, authorized staff to assign a
consultant and enter into contract negotiations, and authorized the Executive Director to execute the consultant contract
up to the FY2004 budgeted amount ($100,000). The Cooperative Funding Agreement was approved by the BCC on
October 21, 2003, and was executed on November 23, 2003. Keith & Schnars was selected to perform the consultant
021 - Manasota Basin 211
L007
Manatee - WMPlan Buffalo Canal/Frog Creek
services associated with the Buffalo Canal/Frog Creek Watershed Management Program. The agreement and Work
Order #1 with Keith & Schnars were executed on January 30, 2004, and February 11, 2004, respectively. Under the first
work order, Keith and Schnars performed a basic Watershed Evaluation, identified voids in the current topographic
information, and prepared a cost estimate to complete the Topographic Information, Watershed Evaluation, and
Watershed Management Plan elements. Work Order #1 tasks were completed. The consultant services agreement with
Keith & Schnars has been terminated, and staff has negotiated a new agreement with Jones Edmunds & Associates to
complete the project within the original schedule and budget. Agreement with JEA to complete the Watershed Evaluation
and the Watershed Management Plan tasks was executed on September 21, 2005. The first work order with JEA has
been executed to complete the existing watershed feature data evaluation and assembly and 80% of the hydrologic
feature inventory, hydraulic feature inventory, and field reconnaissance. Under this work order JEA will begin tasks that
are not contingent upon the LiDAR deliverables. Additionally, staff executed a work order with one of the District's
approved aerial mapping vendors to develop digital topographic information for the entire watershed using LiDAR. The
watershed was flown in conjunction with the Peace River topographic mapping project (P692). The digital topographic
information has been approved by the District and has been transmitted to JEA to complete this project. Submitted
deliverables for Work Order #1 have been reviewed by staff. An amendment to the JEA agreement has been executed
on November 6, 2006, to revise the project schedule and amend the contract termination date. Additionally, the
cooperative funding agreement has been amended to extend the contract termination date. A second work order with
JEA has been executed to complete the Watershed Evaluation and the Watershed Management Plan. JEA has
submitted the first deliverable, Digital Topographic Information, under Work Order #2 for review. Work Order #2,
Deliverable 1 has been reviewed by District staff. Deliverables 2 & 3, as part of the Watershed Evaluation, are anticipated
to be submitted mid May. Work Order #2, Deliverable 2 has been submitted and is currently under review by District
staff. The remaining tasks under Watershed Evaluation, Work Order #2, Deliverables 3 to 5, were submitted to the
District for review. An update meeting was held with the consultant and Manatee County on November 13, 2007 and
Jones Edmunds showed the project progress thru Watershed Evaluation. Work Order #2, Deliverables 6 and
7-Surveying, has been completed and is currently under review with District staff. The cooperative funding agreement
and the consultant services agreement have been amended to extend the contract termination date from December 31,
2007 to December 31, 2008. District staff has completed the review for Work Order #2, Deliverables 3 thru 7 and
comments have been sent to the consultant to address. Consultant is 90% complete with work pertaining to Work Order
#2, Invoice 8 - Watershed Parameterization. Work Order #2, Invoice 8 - Watershed Parameterization is currently under
review by the District. The District has provided comments to the consultant on Work Order #2, Invoice 8 - Watershed
Parameterization. They are to be addressed in the next submittal. Currently, the consultant is wrapping up the model
development and floodplain delineation tasks. Both tasks are projected to be completed by December 31, 2008. An
extension to the cooperator and consultant agreements is required to complete the Level of Service task, which will
follow the additional tasks of peer review, public notification/meeting, 45-day review and comment period to the project,
as part of a separate agreement. Work Order #2, Invoices 9 & 10 deliverable was submitted on January 10, 2009.
Review comments were discussed with JEA on January 27, 2009. A resubmittal of Work Order #2, Invoices 9 & 10
deliverable was submitted on May 18, 2009. A new cooperator agreement, extending the termination date to December
31, 2009 has been sent to Manatee County for signature. Likewise, a new consultant agreement, extending the
termination date to October 31, 2009 has been sent to JEA and executed on January 29, 2009 by the District. A final
submittal of Work Order #2, Invoice 10 was submitted on August 14, 2009. A discussion of this submittal, along with the
usage of a multi-day storm will be held with the County September 8, 2009. A first amendment to the JEA agreement has
been sent to them for signature, extending the expiration date to October 31, 2010. Likewise, an amendment to the
cooperative agreement will need to be done to extend the expiration date. A purchase order for peer review has been
executed to bring on Engineering & Applied Science, Inc. to conduct peer review of floodplain results. Current Status:
JEA has submitted WO#6, Invoice #4 deliveralbe on 12/08/09. District staff completed the review and comments were
sent back to JEA on 12/21/09. Comments were addressed by JEA on 1/4/10. Peer review presentation to Engineering &
Applied Science, Inc. was completed on 2/11/10. Post-peer review meeting #1 is scheduled for 2/25/10.
021 - Manasota Basin 212
L010
Manatee - WMPlan Gamble Creek
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Minimum Flows and Level Establishment and Monitoring
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager NGUYEN, NAM
Task Manager(s)
Status Ongoing
DescriptionThis multi-year funded project is to perform the 1) Topographic Information, 2) Watershed Evaluation, and 3)
Watershed Management Plan elements of the District's Watershed Management Program (WMP) for the GAMBLE
CREEK Watershed. The watershed occupies approximately 56 square miles in northern Manatee County and
discharges into the Manatee River. The watershed is experiencing rapid development without the benefits of a detailed
Watershed Management Plan.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies and 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain management and water quality management.
Costs
The current budget amount for this project is $900,000, of which the District's share is $450,000 funded by the
Manasota Basin. The County is contributing $450,000. Each party funded $125,000, $200,000, and $125,000 for the
project in FY2004, FY2005, and FY2006 respectively. When each element is completed the project budget and scope
of work may be refined based on the information gathered. The District funding amounts shown in the table include
staff salaries.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. A cooperative funding revenue
agreement with Manatee County was developed as a multi-year funded project to complete the WMP elements
through the Watershed Management Plan. The District is managing the project and will enter into purchase orders
and agreements to accomplish project tasks. Future cooperative funding requests and agreements will be required for
a BMP alternative analysis, the Implementation of BMPs, and Maintenance of Watershed Parameters and Models.
With FY2004 and FY2005 year funding the Topographic Information and Watershed Evaluation should be completed.
With FY2005 funding the work on the Watershed Management Plan element began and should be completed with
FY2006 funds. Work on Watershed Management Plan element will include the following tasks: survey, data
management and development of watershed parameters, GIS processing, computer modeling, floodplain analysis,
and establishment of LOS.
021 - Manasota Basin 213
L010
Manatee - WMPlan Gamble Creek
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 504,286 0 0 485,425 8,687 10,174
District Budgeted - Outside Revenue
Manatee - Gamble Ck W/S Mgmt Plan
(L010)
450,000 0 0 450,000 0 0
$954,286 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesRecognition of District, Basin Board, County on reports 6/4/03 6/4/03
Select Consultant 6/4/03 6/4/03
Draft Coop Agreement to Management Services 7/15/03 7/15/03
Approval of Cooperative Agreement by Manasota Basin Board 8/12/03 8/12/03
Approval of Cooperative Agreement by Governing Board 8/26/03 8/26/03
Begin Negotiations with Consultant 8/26/03 8/26/03
Execution of Cooperative Agreement by Manatee County 10/21/03 10/21/03
Execution of Cooperative Agreement by SWFWMD 11/23/03 11/23/03
Consultant Agreement to Management Services 11/26/03 11/26/03
Execution of Agreement by Consultant 2/6/04 2/2/04 2/2/04
Execution of Agreement by SWFWMD 2/13/04 2/18/04
Issue Notice to Proceed to Consultant/ Work Order #1 2/13/04 2/25/04
Requisition to Encumber FY2006 Funds 10/18/05 10/18/05
First Amendment to Consultant Agreement 10/31/05 10/17/05
Execution of Consultant's Work Order #2 by SWFWMD 11/18/05 5/29/07 5/29/07
Execution of Consultant's Work Order #3 by SWFWMD 7/9/07 7/9/07
Execution of Consultant's Work Order #4 by SWFWMD 3/28/08 5/27/08
Termination of Consultant Agreement 6/30/10
Termination of Cooperative Agreement 10/1/10
1. Critical Project MilestonesExecute Expired Consultant Agreement (04CONC00013-A) 3/20/07 3/20/07
Execute Expired Cooperative Agreement (04REV0010-A) 6/14/07 6/14/07
Execute First Amendment to Expired Consultant Agreement (04CONC00013-A) 9/15/08 9/15/08
Execute First Amendment to Expired Cooperative Agreement (04REV0010-A) 12/29/08 12/29/08
Execute Third Amend. to Consultant Agrmt. (04CONC00013-A) 10/1/09 9/17/09
Execute New Coop. Agrmt. (04REV0010-B) 10/1/09 1/14/10
2. Watershed Management Program ElementsCommence Element 1, Digital Topographic Information 2/25/04 2/25/04
Commence Element 2, Watershed Evaluation 5/25/04 2/25/04
Complete Element 1, Digital Topographic Information 11/30/05 2/25/06 12/1/07
Complete Element 2, Watershed Evaluation 5/1/06 12/25/06 12/1/07
Commence Element 3, Watershed Management Plan 5/1/06 2/25/07 11/1/07
Complete Element 3, Watershed Management Plan 10/1/10
Status As Of: February 22, 2010
At their August 2003 meetings, both the Manasota Basin Board and the Governing Board approved the FY2004 budget
for the project, approved the cooperative agreement with Manatee County for $900,000, authorized staff to assign a
consultant and enter into contract negotiations, and authorized the Executive Director to execute the consultant contract
up to the FY2004 budgeted amount ($250,000). The Cooperative Funding Agreement was approved by the BCC on
October 21, 2003, and was executed on November 23, 2003. PBS&J was selected to perform the consultant services
associated with the Gamble Creek Watershed Management Program. The agreement and Work Order #1 with PBS&J
021 - Manasota Basin 214
L010
Manatee - WMPlan Gamble Creek
were executed on February 18, 2004, and February 25, 2004, respectively. Under the first work order, PBS&J performed
a basic Watershed Evaluation, identified voids in the current topographic information, and prepare a cost to complete the
Topographic Information, Watershed Evaluation, and Watershed Management Plan elements. The consultant has
submitted the report on the preliminary evaluation of the watershed and probable costs to complete the first three
elements of the WMP. The First Amendment to the PBS&J's services agreement was executed on October 17, 2005, to
amend the compensation and budget to included approved FY2005 and FY2006 funds. Work Order #2 will complete the
Watershed Evaluation. Work Order #2 was executed on November 18, 2005. Additionally, a work order to develop digital
topographic information for the entire watershed using LiDAR has been executed with 3001, Inc. The watershed was
flown in conjunction with the Peace River topographic mapping project (P692). By doing so, the project realized a
significant cost savings. Aerial mapping deliverables have been approved by Staff. Work Order #3 to collect all remaining
field measurements has been developed, but staff is waiting on supplementary information to be provided by the
consultant. Completion of the Watershed Evaluation and commencement on the Watershed Management Plan have
been delayed due to delays in the digital topographic information development. Both the consultant services agreement
and cooperative agreement are being amended to extend the contract termination date. The agreement with PBS&J has
been extended to October 8, 2008. A project status meeting was held on April 27, 2007 to assess Work Order #2 and set
up Work Order #3. Consultant's field crews have had difficulties gaining access to farm properties to complete field
measurements and therefore delaying the completion of Work Order #2. Work Order #2 will be amended for the work
that could not be done and Work Order #3 will be developed to wrap up the Watershed Evaluation and commence the
Watershed Management Plan. Work Order #3 was executed on 7/9/07. Deliverable 1 of Work Order #3 is anticipated in
September 2007. Work Order #3, Deliverables 1 thru 3, covering the processing of LiDAR data to generate a TIN/DEM,
wrapping up the work for Watershed Evaluation and surveys as part of the Watershed Management Plan has been
delivered to the District for review. District staff is wrapping up the review for Work Order #3, Deliverables 1 thru 3 and
comments will be send to the consultant thereafter. More time was taken for this review is a result of the implemented
increase level of effort to better QA/QC the submittal. The consultant has been instructed to prepare Work Order #4 and
to arrange a project update meeting with Manatee County. A project status meeting with Manatee County was held on
May 14, 2008. Work Order #4 has been signed by the District and a notice to proceed has been given to the consultant,
May 29,2008. Work Order #4, Deliverables 1 thru 3 was delivered to the District on August 22, 2008. A stakeholders
meeting was held on October 8, 2008 at the Manatee County Public Works Department. The 20 largest property owners
and local engineering consultants in the area were invited. The purpose of the meeting was to present our findings from
the work that PBS&J has done thru the Watershed Evaluation element and to get their input based on their knowledge of
the area. Work Order #4, Deliverable 4 was submitted to the District on November 4, 2008. The District's comments for
deliverables 1 thru 4 of Work Order 4 were sent to PBS&J to address. Work Order #4, Deliverable 5 - Calibrated
computer model was submitted to the District on May 1, 2009. The District is currently reviewing the submittal and a
meeting at Manatee County has been set up for May 20, 2009 for the consultant to discuss the model and present the
preliminary floodplain. District & Manatee County comments to Work Order #4, Deliverable 5 were sent to PBS&J on
7/14/09 to address. The District has selected Royal Consulting Services, Inc. to perform the peer review of floodplain
results produced by PBS&J. PBS&J agreement will be modify to reduce by $33,000, to be used for the peer review. A
second amendment to the cooperative agreement is currently being routed for signatures, extending the expiration date
to October 1, 2010. A third amendment to PBS&J agreement is being routed for signatures, reducing the project budget
by $33,000 to be used to hire Royal Consulting Services, Inc. to peer review the floodplain results. District and Manatee
County has provided comments to PBS&J Work Order #4, Deliverable 5. PBS&J is currently addressing those
comments. Current Status: A new cooperative agreement with Manatee County was executed on 1/14/10, extending the
expiration date to October 1, 2010. A third amendment to PBS&J agreement was executed on 9/17/09. In reviewing
PBS&J's WO#4, Invoice #6 deliverable, District staff has questioned the modeling technique used by PBS&J on certain
part of the watershed. Since then, PBS&J has brought on Streamline Technologies, Inc. to evaluate and give opinion on
the adequacy of the H&H conditions used. A summary report about the findings was completed on January 13, 2010 by
Stremline Technologies, Inc. PBS&J is currently in the process of modifying the data & model to address those
comments.
021 - Manasota Basin 215
L210
Implementation of BMPs - Phillippi Creek/Celery Fields
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Emergency Flood ResponseNatural Systems Minimum Flows and Level Establishment and Monitoring
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
PRESTON, MATTTask Manager(s)
Status Ongoing
DescriptionThis is a multi-year funded project to perform the Implementation of Best Management Practices (BMPs) element of
the District's Watershed Management Program (WMP) for the Phillippi Creek Watershed. The watershed covers an
area of approximately 56 square miles and is located in Sarasota County (County). This BMP will be implemented in
the Celery Fields improvement area and specifically includes construction of additional storage to the existing south
cell of the Celery Fields Regional Stormwater Facility. Implementation of the BMP includes the following tasks:
construction and construction engineering and inspection. The proposed BMP will address level of service
deficiencies. In addition, 120-acres of the southern cell pond of Celery Fields will be excavated to create a wetland
habitat that will provide natural systems benefits.
BenefitsThe project will provide additional storage within the watershed and, thereby, provide an improved level of service.
These improvements will address structure flooding downstream along Phillippi Creek by providing flood protection for
15 homes currently inundated and damaged during a 100-year flood event. Based on an Expected Damages Analysis,
the expected flood damages to be mitigated by the project for a 100-year flood event is approximately $2.17 million.
This project is also expected to improve water quality through increased residence times.
Costs
The current total budget for this project is $16.873 million. The FDEP is providing the County with a grant of
$10,079,880 toward the project. The District's contribution is $2,903,060, which is being funded entirely by the
Manasota Basin. Implementation costs for the project are significantly greater than originally estimated in 2001. The
District funding amounts shown in the table include staff salaries, travel and central garage.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies. A WMP provides a method to evaluate the capacity of a watershed to
protect, enhance, and restore water quality and natural systems, while achieving flood protection. This project involves
the Implementation of BMPs which includes design, development of construction documents, construction permitting,
land acquisition, bidding and contractor selection, construction of the BMPs and construction engineering and
inspection. The original budget for the project was around $2.9 million and was based on a November 2001
preliminary design report prepared by the County. The County is managing the project, and the District project
manager must approve any agreements to accomplish project tasks.
021 - Manasota Basin 216
L210
Implementation of BMPs - Phillippi Creek/Celery Fields
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 2,931,645 0 0 2,917,082 2,182 12,381
Project Funds Not Budgeted by the
District
Florida Department of Environmental
Protection
10,079,880 0 0 10,079,880 0 0
Sarasota County 4,383,560 0 0 4,383,560 0 0
$17,395,085 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development and ExecutionDraft Agreement to Management Services 1/7/04 1/6/05
Negotiate Cooperative Funding Agreement with County 9/27/04 1/3/05
Draft Agreement returned from Management Services 2/1/05 1/14/05
Board of County Commissioners Approval 4/1/05 2/22/05
Notice to Proceed 5/1/05 3/4/05
Requisition to Encumber FY2006 Funds 10/18/05 10/18/05
Draft Amendment to Management Services 12/15/06 5/31/07 7/16/07
Draft Amendment returned from Management Services 1/22/07 6/30/07 8/2/07
Board of County Commissioners Approval 2/28/07 7/30/07 9/25/07
Execute Amendment 3/30/07 8/31/07 10/9/07
Requisition to Encumber FY2008 Funds 10/30/07 10/30/07
2. Critical Project MilestonesAlternatives Analysis Complete 4/30/05 3/4/05
Acquire All Permits, Government Approvals, & Real Property Rights for Project 8/26/05 3/30/09 6/1/09
Complete Design and Permitting 10/11/05 5/30/09 6/10/09
Bidding and Contractor Selection 3/13/06 7/30/09 7/7/09
Commence Construction 3/18/06 9/30/09 9/28/09
Complete Construction 1/12/07 6/30/10
Construction Site Signage will Recognize Funding 12/15/07 9/30/09 12/21/09
3. Project Close OutSubmit As-Builts 2/11/07 7/30/10
Contract Termination 12/31/07 11/30/11
Status As Of: February 19, 2010
Project construction began in early September 2009 with equipment mobilization and establishment of haul routes.
Excavation of the additional stormwater storage areas is ongoing and remains on schedule. Excavated material is
stockpiled in several areas for future use in the construction of containment berms. District staff have been in
discussions with Sarasota Co. staff regarding floodplain storage created by the project, and increases in funding
allocations for construction engineering and inspections. ACTIONS-TO-DATE: On Schedule. Project construction is
ongoing and is scheduled for completion in October 2010.
021 - Manasota Basin 217
L230
Longboat Key Backup Potable Water Supply Interconnect
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Regional Water Supply Planning
Basin(s) Manasota
Longboat KeyCooperator(s)
Project Manager MCBRIDE, TAMERA
Task Manager(s)
Status Ongoing
DescriptionThis project includes the design and construction of a subaqueous crossing of New Pass with approximately 2,400
linear feet of 16-inch diameter potable water pipeline. The original proposal was for a 2,000 linear foot 12-inch pipeline;
however, the pipeline was lengthened and rerouted due to permitting issues. The Town of Longboat Key will connect
to the potable water supply system of the City of Sarasota on City Island from Longboat Key's potable water supply
system on the south side of the key. The project will provide the Town with an unspecified amount of back-up potable
water in the event supplies are not available from the Town's current supplier, Manatee County. It was originally
anticipated that the City would supply the Town in emergency situations only, such as if a natural disaster interrupted
supply from Manatee County. However, the Town now envisions that the City will eventually serve as a back-up
supplier in order to meet the Town's peak demands.
BenefitsThe project will enable the Town of Longboat Key to receive a reliable supply of potable water in the event supplies are
not available from Manatee County.
Costs
The District's share of the project is expected to be $1,000,000. The Manasota Basin Board originally budgeted
$50,000 toward completion of the project in FY2005, and an additional $200,000 was transferred from the Water
Supply and Resource Development fund for a total contribution of $250,000 in FY2005. The basin board budgeted
$250,000 in FY2006, $250,000 in FY2007, and $250,000 in FY2008. A cost benefit cannot be calculated, since no new
water supplies will be developed as a result of the project.
Additional Information
The total eligible cost of the project is $2,000,000, of which design represents $500,000 and construction represents
$1,500,000. The Town will be solely responsible for the upsizing of 3.5 miles of existing 8, 10, and 12-inch water
mains along Gulf of Mexico Drive, and for the pump system and emergency generator upgrades at the south and
mid-key water stations. This $2,200,000 portion of the project is not eligible for funding.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,017,849 0 0 1,012,833 0 5,016
Project Funds Not Budgeted by the
District
Longboat Key 6,156,958 0 0 6,156,958 0 0
$7,174,807 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Draft Agreement to Management Services 3/21/05 3/28/05
Draft Agreement Returned from Management Services 4/8/05 4/28/05
Contract Execution 4/22/05 6/20/05
021 - Manasota Basin 218
L230
Longboat Key Backup Potable Water Supply Interconnect
Notice to Proceed 4/22/05 6/23/05
Commence Design 4/29/05 6/20/05
Basin Board Notification of Agreement Execution 6/15/05 10/12/05 10/12/05
Signage Erected 7/31/06 12/10/07 4/30/08
Commence Construction 7/31/06 11/30/07 12/10/07
Project Complete 12/31/07 12/31/09
Contract Close-out 12/31/08 3/31/10
Status As Of: February 23, 2010
A total of $1,000,000 has been budgeted for the project through FY2008. Construction began (December 10, 2007). The
first invoice was received in January 2009 and was reviewed by the District's project manager. Additional backup was
requested for the invoice on March 18, 2009. The Longboat Key project manager resubmitted the invoice package and
additional information was requested on December 30, 2009. The contract expiration date is March 31, 2010; however,
the Town verified that an extension is not required, because all work under the contrat has been completed.
Pipeline Design, Permitting, and Construction The pipeline design was completed. The Town forwarded the 100 percent
design level plans and technical specifications to the District on July 26, 2007. Staff was notified that the final design of
the pipeline alignment differs slightly from the 60 percent design level because of permitting issues.
A Department of Health permit was received on March 5, 2007 and a Florida Department of Transportation permit was
received on April 23, 2007. The Town submitted a Joint Application Environmental Resource Permit (ERP)/Dredge and
Fill/Submerged Land Lease, which includes permits required by the District, Army Corps of Engineers (ACOE), and the
Florida Department of Environmental Protection (FDEP). The District issued an exemption to the ERP portion of the
permit on December 20, 2006, and the ACOE issued a Regional General Permit on March 8, 2007 for dredge and fill
activities. The Sovereign Submerged Lands Lease was fully executed on August 9, 2007. A copy of the fully executed
and recorded easement was returned to the FDEP Department of State Lands on August 27, 2007. The City of Sarasota
entered an access agreement with the contractor on April 3, 2008. The District's Sarasota Regulation Department
accepted the planned pipe transport alternative on April 10, 2008. The final pipeline alignment did fall outside the
Sovereign Submerged Land Lease easement in a small area. The Town and Engineer adjusted the easement
description and lease language, and SWFWMD forwarded the updated survey to the FDEP on April 22, 2009. The Town
received an updated land lease easement from the FDEP on June 5, 2009. The full execution was recorded at the
Sarasota County Clerk of Court on July 31, 2009.
The District received the bid set plans and technical specifications on August 2, 2007. The bid was awarded to Expertech
Network Installation (US) Inc. and notice to proceed was issued for a December 10, 2007 commencement date. The
contractor mobilized on January 18, 2008 and began drilling on January 30, 2008. Drilling was slower than originally
anticipated by the contractor due to equipment issues and the apparent presence of rock. Drilling of the pipeline hole was
completed May 12, 2008, and the pipeline was pulled under New Pass into place on May 14, 2008. Pressure testing and
chlorination of the pipe was conducted the week of May 26, 2008. The contractor performed confirmation surveying on
August 26-27, 2008 and September 5-6, 2008 and was found to be acceptable on October 13, 2008 by the consulting
engineer, CDM. On November 10, 2008, CDM approved the contractor's first request for payment covering work from
March 1, 2008 to July 30, 2008. On June 23, 2009, the Expertech Florida office was closed and the project data was
transferred to the Expertech Canada office. A final pay request for the construction was received on August 17, 2009.
South Key Station No. 2 Design and Permitting A District Environmental Resource Notice General Permit was approved
on January 16, 2008. An application for a Specific Permit to construct potable water system components was received
from the Department of Health on February 25, 2008. A Site Plan Exemption was received from the Town of Longboat
Key Planning, Zoning, and Building Department on June 10, 2008. The South Key Station No. 2 Improvements project
was advertised for bid on June 24, 2008. The bid opened August 6, 2008, was awarded August 21, 2008, and was
executed October 20, 2008. The preconstruction conference was held on November 4, 2008 and the Notice to Proceed
was issued on November 11, 2008. The contractor mobilized on January 12, 2009. Construction on the meter compound
and chemical equipment is complete.
ACTION-TO-DATE: Delayed. An information request concerning the Accelerate Florida Program was mailed to the
cooperator on October 15, 2008. The District's project manager followed up with an email on January 16, 2009 and a
phone call on February 9, 2009. The Town responded with a letter dated February 12, 2009 that stated the following:
"The project is currently in construction. The drilling portion of the project is completed and final billing should be received
soon. The chemical blending and meter compound portions of the project are on the horizon. The contractor is in shop
drawing submittal phase with those portions of the project. We are working with the contractor to get those last few
pieces of the project completed as soon as practical without hindering portions of the project that are not included in the
L230 project."
021 - Manasota Basin 219
L512
(Completed) Manatee County Shallow Well Rebate Program
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project consists of a shallow well rebate program to provide incentives and assistance to encourage existing
homeowners/businesses of Manatee County who use potable water as a landscape irrigation source to convert to a
shallow well (surficial/intermediate) system. This area includes the western unincorporated service area of Manatee
County and the cities of Anna Maria, Bradenton Beach and Holmes Beach.
BenefitsIt is estimated that there will be 100 wells installed each year, saving 493 gpd per site, within the retail service area of
Manatee County Water System. The estimated water savings from this project is 49,300 gpd.
Costs
The total project cost is $50,000, and the District's share is requested to be $25,000. The Manasota Basin is
requested to fund $25,000 in FY2006. The cost, amortized at 8 percent over 20 years, is $0.28 /1000 gal saved. Any
additional funds are for staff time.
Additional Information
This shallow well rebate program provides a cost share (50% of cost up to $500) to any eligible customer who
converts to a shallow well (surficial/intermediate) system and meets all criteria set forth by the Shallow Well Feasibility
Study, conducted during FY2004 and FY2005. Rebate payments are subject to the recipient's submittal of the
documented cost to the Utility Operations Department, Water Conservation Section and a completed site inspection of
every well installation.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 41,065 0 0 38,784 0 2,281
Project Funds Not Budgeted by the
District
Manatee County 25,000 0 0 25,000 0 0
$66,065 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Begin advertising: 12/1/05 12/1/05
Draft Agreement to Contract Administration: 1/15/06 2/1/06
Start processing rebates: 1/31/06 1/31/06
Agreement Executed / Notice to Proceed: 5/31/06 5/22/06
Complete processing rebates: 1/31/07 10/15/09 10/15/09
Final Report: 7/15/07 11/16/09 11/2/09
Final Invoice: 9/15/07 12/15/09 10/30/09
021 - Manasota Basin 220
L512
(Completed) Manatee County Shallow Well Rebate Program
Status As Of: December 01, 2009
The County began advertising the program in December 2005. In May 2006, a billing insert was mailed describing the
program and fifty applications were received. The County sent out an advertisement with the March 2008 utility bills and
received thirty-three requests for applications. To date, a total of two hundred and twenty applications have been
requested from the County. Fifty rebates have been processed by the County. The County has issued 56 rebates and
has submitted forty-two rebates to the District for reimbursement. The program has proceeded slower than expected.
The County requested an extension to the agreement with the District to allow more applicants to take advantage of the
rebate program. A first amemdment was executed 11/27/2007 that extended the project to July 15, 2009. The final
invoice was submitted October 30, 2009. The District reimbursed the County a total of $12,750. The final report was
submitted November 2, 2009. A total of fifty-one rebates were processed by the District for a savings of 64,697 gpd. This
project is complete.
021 - Manasota Basin 221
L604
Manatee - WMPlan Little Manatee River
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Minimum Flows and Level Establishment and MonitoringFlood Protection Floodplain Management
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager NGUYEN, NAM
Task Manager(s)
Status Not Funded
DescriptionThis multi-year funded project is to perform the 1) Topographic Information, 2) Watershed Evaluation, and 3)
Watershed Management Plan elements of the District's Watershed Management Program (WMP) for the LITTLE
MANATEE RIVER Watershed. The watershed occupies approximately 79.0 square miles within northern Manatee
County and discharges into Tampa Bay, a SWIM waterbody. The watershed is beginning to experience rapid
residential development to the west of Interstate 75 that is expected to expand to the east in the near future.
Topographic information includes the acquisition of data and development of the terrain features in the Geodatabase
to be used in the Watershed Evaluation. The Watershed Evaluation includes collection of existing data, GIS
processing of the terrain features to establish catchments and connectivity, field reconnaissance, refinement of the
terrain features and development of the hydraulic element point features. The Watershed Management Plan element
includes: development of watershed parameters for a specific use, GIS processing, computer modeling, floodplain and
water quality analysis, surface water resource assessment, establishment of LOS, BMP alternative analysis.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain and water quality management.
Costs
The current budget amount for this project is $1 million, of which the District's share is $500,000 to be funded by the
Manasota Basin. The County will contribute $500,000. Previously approved FY2007 funding included $500,000 from
the Basin's budget with a revenue from Manatee County for $250,000. Previously approved FY2008 funding included
$500,000 from the Basin's budget with a revenue from Manatee County for $250,000. Due to the recent tax cuts,
Manatee County has notified us that they are not able to contribute the $250,000 as originally planned for FY2008.
When each element is completed the project budget and scope may require refinement based on the information
gathered. The District funding amounts shown in the table include staff salaries.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. The District has been working
with the County for several years through the Watershed Management Program Coordination to develop a five year
implementation schedule by watershed based on their projected funding levels, and funding available from others for
example FEMA or State appropriations. A cooperative funding revenue agreement with Manatee County has been
developed as a multi-year funded project contingent on the approval of future funding to complete the WMP elements
through the Watershed Management Plan. This is a multi-year funded project that will require a cooperative funding
request each fiscal year until completed. If approved, this project will be ranked as a 1A project in future fiscal years.
The District will manage the project and will enter into work orders and agreements to accomplish project tasks.
Future cooperative funding requests and agreements will be required for a BMP alternative analysis, the
Implementation of BMPs, and the Maintenance of Watershed Parameters and Models.
021 - Manasota Basin 222
L604
Manatee - WMPlan Little Manatee River
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 528,167 0 0 519,610 8,557 0
District Budgeted - Outside Revenue
Manatee - WMPlan Little Manatee River
(L604)
500,000 0 0 500,000 0 0
$1,028,167 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesRecognition of the SWFWMD, Manasota Basin Board and Manatee County will
be included on all reports
9/29/06
Select Consultant 9/29/06 9/29/06
Develop Draft Agreement with Manatee County 11/20/06 11/30/06
Cooperative Funding Agreement to Contract Administration 11/27/06 12/8/06
Execution of Cooperative Agreement by Manatee County 12/29/06 1/23/07
Execution of Cooperative Agreement by SWFWMD 1/19/07 1/25/07
Begin Negotiations with Consultant 1/30/07 2/8/07
Execution of Consultant Agreement by SWFWMD 9/30/07
Issue Notice to Proceed to Consultant/ Work Order #1 9/30/07
Requisition to Encumber FY2008 Funds 10/1/07 10/1/07
Termination of Cooperative Agreement 3/1/10
Termination of Consultant Agreement 3/1/10
Status As Of: February 22, 2010
Notice of anticipated funding has been sent to County's project manager. A meeting has been requested to discuss
scope of work and consultant selection. District and Manatee County staff met on October 12, 2006, to discuss the
proposed scope of work and specific project needs. Hillsborough County had developed a model for the watershed that
the District recently reviewed under Project B126. The model and the results of the District's independent review will
serve as the base for the Watershed Management Plan within the Manatee County portion of the watershed. District staff
are currently negotiating with one of its pre-selected vendors to complete aerial topographic mapping for the portions of
the watershed that currently do not have digital topographic information. Boyle Engineering Corp. has been selected as
the consulting firm to perform this project. The Cooperative Funding Agreement was executed on 1/25/2007. Mapping
and GIS staff is putting together a Work Order with Earth Data to begin aerial topographic mapping for portions of the
watershed that currently do not have digital topographic information. District staff will begin talks with Boyle Engineering
and will be putting together a consultant agreement. A Work Order was executed with Earth Data for the aerial
topographic mapping work. District staff initiated communication with Boyle Engineering on 2/8/07 to begin the consultant
services agreement process. A draft consultant services agreement has been sent to Boyle for review. Boyle
Engineering provided Fee Schedule for their team. A consultant agreement is being routed through our contract, legal
sections for review. County's project manager has indicated that due to recent tax cuts they will not be able to contribute
the $250,000 as originally planned for FY2008. District staff has met with County on 8/21/07 to develop a work plan to
move the project forward using only the FY2007 fundings. Boyle Engineering has submitted a project budget for review.
District staff is finishing the consultant services agreement and will be working with the consultant to develop Work Order
#1. The consultant services agreement has been placed on hold by the Department's Director due to the reprioritization
of projects within the department. The LiDAR data acquisition by Earth Data is in its final phase and will be delivered to
the District mid January 2008. The consultant services agreement is still on hold and the consultant has been notified of
the situation. We're still waiting for the delivery of the LiDAR data acquisition by Earth Data. The LiDAR acquisition has
been completed and the data is available for usage as of 04/29/2008. The consultant services agreement with Boyle
Engineering for the watershed management plan will be delay until further notice to enable Manatee County to shift
FY2007 funding contribution to other higher priority projects. It is anticipated that the project will be terminated and any
left over funds will be balance forward. The District is reviewing the project budget to identify how much has been spent
and what the remaining funds are. The District will notify Manatee County once these figures are completed. Current
Status: The project is terminated. Finance has liquidated $357,402 that was encumbered to the agreement to allow the
021 - Manasota Basin 223
L604
Manatee - WMPlan Little Manatee River
dollars to lapse.
021 - Manasota Basin 224
L608
Palmetto Reclaimed Water ASR
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Reclaimed Water
Basin(s) Manasota
PalmettoCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project consists of the design, construction, permitting, ultraviolet (UV) disinfection, cycle testing, and operational
permitting for a 1.2 mgd reclaimed water Aquifer Storage Recovery (ASR) well for the City of Palmetto. The ASR well
will be located at the City's Wastewater Treatment Facility (WWTF). This ASR well will help reduce the demands on
potable water supplies and eliminate the need for surface water discharge of excess reclaimed water to Terra Ceia
Bay.
BenefitsThis reclaimed water ASR well will store an estimated 144 million gallons of reclaimed water during wet weather
periods to help offset approximately 276,000 gallons per day (gpd) of future groundwater supply. The City is projecting
a new irrigation demand of 2.2 million gallons per day (mpd) from approximately 3,696 additional residential units from
planned developments by 2010. Reclaimed water flows normally discharged from the City's WWTF to Terra Ceia Bay
will be stored in the ASR well.
Costs
The total project cost is $2,340,000 and the District's share is requested to be $1,134,000. The Manasota Basin
contributed $389,000 in FY2007 and $272,000 in FY2008. The WPSTF contributed $72,000 in FY2007 and $136,000
in FY2008. The Manasota Basin will asked to provide $405,000 in additional funds in FY2011. The cost, amortized at
8 percent over 30 years is $2.05 per 1000 gallons offset, assuming the City will require the new developments to fund
the connection to the City's reuse system. The future funds identified for the project are contingent upon approval of
such amounts by the District Governing and Basin Boards in the annual budget(s).
Additional Information
The City of Palmetto completed a reclaimed water ASR feasibility study in October 2005 that recommended the City
develop a reclaimed water ASR to provide wet weather storage at the Palmetto WWTF site. The City is prepared to
move forward with the construction and permitting of a test well. If this ASR well is successful, one additional
reclaimed water ASR well is planned at the WWTF site. The City has been in communication with Manatee County
and the City of Bradenton about the future development of a regional system and, depending on the results of those
communications, this project could ultimately be an integral part of a more regional system. Of the total project cost of
$2,340,000, approximately 79 percent ($1,850,000) is expected to be needed for construction, and the remainder
($490,000) for design and administration.
021 - Manasota Basin 225
L608
Palmetto Reclaimed Water ASR
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 678,404 0 0 672,979 1,605 3,820
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
208,000 0 0 208,000 0 0
Project Funds Not Budgeted by the
District
City of Palmetto 1,066,000 0 0 661,000 405,000 0
$1,952,404 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Draft Agreement to Contract Administration: 9/30/06 9/30/06
Agreement Executed / Notice to Proceed: 11/30/06 1/24/07
Start construction of reclaimed water ASR: 9/1/07 3/5/08
Complete construction of reclaimed water ASR: 8/30/10
Start Cycle Testing: 9/1/10
Complete Cycle Testing & Obtain Operational Permit: 12/31/10
Final Invoice: 4/30/11
Contract Termination: 6/30/11
Status As Of: February 19, 2010
The agreement with the City was executed on January 24, 2007. The public hearing for the draft FDEP ASR construction
permit was held on January 23, 2007. The FDEP ASR Construction Permit was issued in April 2007. The City of
Palmetto has agreed with the District to construct the Storage Zone Monitor Well (SZMW) / Exploratory Well as the first
well. This will allow us to gather information about the target aquifer, a drinking water aquifer, and a lower aquifer to
determine if it's suitable for ASR development. If that lower zone is not a drinking water aquifer, and it's suitable for ASR,
it may allow us to bypass the arsenic requirements for ASRs in the drinking water aquifers. The consultant has prepared
the bid specifications for the exploratory well and the City advertised the project for bidding to select a driller. The bid
opening occurred on January 9, 2008. Hausinger and Associates Inc. was the lowest bidder. The City approved the
contract with Hausinger and Associates Inc. on February 18, 2008. Construction started March 5, 2008 on the
exploratory well. The pilot hole was drilled to 1040 feet in depth. It was determined by the consultant that the lower zone,
a non USDW zone, is not suitable for ASR development. The decision was made to perform all water quality and
geological tests and back plug this well to a depth of about 520 feet bls. This well was completed and will be the Storage
Zone Monitor Well (SZMW) for this ASR. The ASR will need to be constructed in the Swuannee Limestone aquifer which
is between 400 and 520 feet bls. A technical memorandum on the exploratory/SZMW was completed and submitted to
FDEP in December 2008. The project has been placed on hold pending the results of the District's arsenic pretreatment
study at the City of Bradenton ASR project which has been delayed due to the drought and is now scheduled to be
available in July 2010. To date, the District has reimbursed the City $223,809 for it's share of design and construction of
the exploratory/SZMW.
021 - Manasota Basin 226
L610
Sarasota County - Watershed Plan: Lemon Bay
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
GARCIA, LIZANNETask Manager(s)
Status Ongoing
DescriptionThe purpose of this project is to develop a comprehensive watershed plan for Lemon Bay. The plan will focus on water
resource issues such as restoration of historic or more natural hydrologic regimes in the basin, improvements to water
quality and habitat restoration. The plan will attempt to identify ways to reduce excess flows into the bay, and thereby
assist in reducing pollutant loads, improving water quality and habitat conditions. The Lemon Bay watershed includes
several localities of concern with regard to documented declining water quality trends: elevated nutrients for Alligator
Creek and Forked Creek, elevated nutrients and low dissolved oxygen levels for Gottfried Creek, and elevated
nutrients from direct run-off to Lemon Bay. These areas of concern suggest a need to develop and implement ways to
reduce nutrient loading from the watershed. An essential element of the project will be updating and fine-resolution
improvements to the current AdICPR flood model.
BenefitsThis regional initiative promotes and furthers the implementation of the Sarasota Bay CCMP, SWFWMD's Southern
Coastal Watershed CWM Plan, and Sarasota County's Comprehensive Plan. The Lemon Bay Watershed
Management Plan will be developed in cooperation with the District, the DEP Lemon Bay Aquatic Preserve Program,
the Charlotte Harbor National Estuary Program, the Lemon Bay League, the DEP Bureau of Watershed Management,
and all other interested stakeholders.
Costs
The total cost of plan development is $600,000. The District's share is $300,000, and the County's share is $300,000.
The FY2007 budget is $300,000 with the District and County each contributing half ($150,000). For FY2007, the
District's share is split between the Manasota Basin Board ($75,000) and the State's Water Protection and
Sustainability Trust Fund ($75,000). The FY2008 budget is $300,000 with the County and the District each contributing
half ($150,000). The District's FY2008 share is funded entirely by the Manasota Basin Board. The District funding
amounts shown in the table include staff salaries, travel and central garage charges.
Additional Information
The completed plan will be presented to the Board of County Commissioners for adoption, and will include short-term
and long-term projects for improvements that may include wastewater reuse, stormwater reuse, smart growth, revised
land development standards, sediment control, wetland or floodplain restoration, flood level abatement, aquifer
protection, and restoration of natural flow regimes. The northern half of Lemon Bay (WBID 1983A) has been listed as
verified impaired for nutrients based on an exceedance of the 11ug/l chlorophyll-a guideline in the Impaired Waters
Rule (62-303, FAC). Lemon Bay has also been listed as impaired for bacteria based on a downgrading of shellfish
harvesting classification from approved to conditional. Development of the plan will include formation of a watershed
stakeholders group working through the Neighborhood Environmental Stewardship Team (NEST) program to
encourage public participation in the process.
021 - Manasota Basin 227
L610
Sarasota County - Watershed Plan: Lemon Bay
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 260,031 0 0 244,086 10,282 5,663
District Budgeted - Outside Revenue
Water Protection & Sust T.F. (Surface
Wtr Rstr)
75,000 0 0 75,000 0 0
Project Funds Not Budgeted by the
District
Sarasota County 300,000 0 0 300,000 0 0
$635,031 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionDevelop Draft Agreement with Sarasota County 11/30/06 3/15/07 4/15/07
Cooperative Funding Agreement to Contract Administration 12/15/06 4/20/07 4/20/07
Execution of Cooperative Agreement by Sarasota County 4/15/07 5/31/07 6/26/07
Execution of Agreement by SWFWMD 4/30/07 7/15/07 7/20/07
Issue Notice to Proceed 5/5/07 7/30/07 7/20/07
2. Critical Project MilestonesLiterature Search and Review (Draft) 1/30/08 3/30/08 3/30/08
Watershed Characterization (Draft) 3/15/08 5/30/08 6/30/08
Develop / Review Sediment Abatement Projects 6/30/08 6/30/08
Prepare Working Draft of Watershed Plan for Review 7/30/09 8/3/09
Review of Working Draft by Project Team - Completed 9/14/09 4/30/10
Watershed Plan Presented to Sarasota County BOCC 6/30/10
Project Complete 8/31/10
Status As Of: February 19, 2010
The working Draft Watershed Management Plan is complete and is undergoing review by the project team members.
Edits, comments and revisions are being collected and incorporated into a final Draft. Additional water quality issues (i.e.,
newly adopted TMDLs) have required additional work and thereby extended the review period. Draft comments are
anticipated to be complete by late May 2010. In order to accommodate the additional work and review time, a no-cost
time extension to the agreement has been approved to extend the project completion date to August 31, 2010.
021 - Manasota Basin 228
L611
Sarasota County - Watershed Plan: Roberts Bay
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
GARCIA, LIZANNE, HEYL, MIKETask Manager(s)
Status Ongoing
DescriptionThe purpose of this project is to develop a comprehensive Watershed Plan for Roberts Bay. The plan will focus on
water resources issues such as restoration of historic or more natural hydrologic regimes in Roberts Bay, and
improvements to water quality and habitat restoration. The plan will attempt to identify ways to reduce flow volumes
into the Bay, and thereby assist in reducing pollutant loads and improving water quality. The Roberts Bay watershed
includes two localities of concern with regard to documented declining water quality trends: increasing trends of
historic chlorophyll a levels at Roberts Bay, and elevated nutrient levels based on Trophic State Index (TSI) for West
Clark Lake. Conditions at both of these localities indicate a need to reduce nutrient loading from the watershed. An
essential element of the project will be updating and improving the existing AdICPR flood model and pollutant loading
model.
BenefitsDevelopment of the plan will allow the County to consolidate and update goals and objectives from the District's SWIM
Plan and the Sarasota Bay Estuary Program (SBEP) into one strategy that would include comprehensive monitoring of
water quality and pollutant loads, detailed mapping, flood and pollutant load modeling, and prioritized practical project
proposals to improve water quality, restore natural run-off regimes, provide water supply, and protect natural
resources.
Costs
The total cost for plan development is $600,000. The District's share is $300,000, and the County's share is $300,000.
The FY2007 budget is $300,000, with the District and County each contributing half ($150,000). For FY2007, the
District's share is split between the Manasota Basin Board ($75,000) and the State's Water Protection and
Sustainability Trust Fund ($75,000). The FY2008 budget is $300,000 with the County and the District each contributing
half ($150,000). The District's FY2008 share is funded entirely by the Manasota Basin Board. The District funding
amounts shown in the table include staff salaries, travel and central garage charges.
Additional Information
Development of the plan will include formation of a watershed stakeholders group working through the Neighborhood
Environmental Stewardship Team (NEST) program to encourage public participation in the process. The completed
plan will be presented to the Board of County Commissioners for adoption, and will include short-term and long-term
projects for improvements that may include wastewater reuse, stormwater reuse, smart growth, revised land
development standards, sediment control, wetland or floodplain restoration, flood level abatement, aquifer protection,
and restoration of natural flow regimes.
021 - Manasota Basin 229
L611
Sarasota County - Watershed Plan: Roberts Bay
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 260,031 0 0 244,086 10,282 5,663
District Budgeted - Outside Revenue
Water Protection & Sust T.F. (Surface
Wtr Rstr)
75,000 0 0 75,000 0 0
Project Funds Not Budgeted by the
District
Sarasota County 300,000 0 0 300,000 0 0
$635,031 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionDevelop Draft Agreement with Sarasota County 11/30/06 2/28/07 3/30/07
Cooperative Funding Agreement to Contract Administration 12/20/06 5/5/07 5/11/07
Execution of Cooperative Agreement by Sarasota County 1/25/07 5/31/07 6/26/07
Execution of Agreement by SWFWMD 2/25/07 7/15/07 7/20/07
Issue Notice To Proceed 3/1/07 7/30/07 7/22/07
2. Critical Project Milestones Literature Search and Review 11/30/07 12/30/07
Watershed Characterization (Draft) 1/10/08 1/15/08
Develop Plan Goals and Objectives (Draft) 1/28/08 5/30/08 5/30/08
Develop / Review Sediment Abatement Plan 6/30/08 6/30/08
Prepare Working Draft Watershed Plan 8/3/09 8/3/09
Review of Working Draft WMP by Project Team - Completed 9/30/09 5/31/10
Watershed Plan Presented to Sarasota County BOCC 6/30/10
Project Complete 8/31/10
Status As Of: February 19, 2010
The working Draft Watershed Management Plan is complete and is undergoing review by the project team members.
Edits, comments and revisions are being collected and incorporated into a final Draft. Additional water quality issues (i.e.,
newly adopted TMDLs) have required additional work and thereby extended the review period. Draft comments are
anticipated to be complete by late May 2010. In order to accommodate the additional work and review time, a no-cost
time extension to the agreement has been prepared to extend the project completion date to August 31, 2010.
021 - Manasota Basin 230
L613
Sarasota Imp. BMPs South Pelican Drive
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager SMITH, RANDY
Task Manager(s)
Status Ongoing
DescriptionThis project is to perform the Implementation of Best Management Practices (BMPs) element of the District's
Watershed Management Program (WMP) for the Hudson Bayou Watershed in Sarasota County. This project will be
implemented in the South Pelican Drive improvement area which has experienced chronic flooding over the past few
years, especially during hurricane Jeanne in 2004. The project will eliminate structural flooding and improve residential
roadway access by providing additional storage and improving conveyance. This will be accomplished through
construction of an attenuation storage pond downstream of the flooded structures and upsizing conveyance pipes and
channels between the flooded areas. The project is also expected to improve water quality by increasing residence
time in the new storage area. This project includes construction of the BMP's and associated construction engineering
and inspection.
BenefitsThe project is expected to meet level of service criteria during a 25-year storm event, eliminate structural flooding of
four structures and improve residential roadway access by providing additional storage and improving conveyance.
The project is also expected to improve water quality by increasing residence times in the new storage area. The flood
hazard mitigation benefit/cost ratio calculated by the County is 1.03.
Costs
The original FY2007 estimated project cost for construction was $594,000 and the District's share of $200,000 was
funded by the Manasota Basin Board. The County was unable to secure the land necessary for the project, which has
forced design changes and increased costs. The new estimated project cost for construction is $1,577,940. The
District funding amounts shown in the table below include staff salaries, travel and central garage charges.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of BMPs, and 5) Maintenance of Watershed Parameters and Models.
Implementing elements of the WMP with local governments is one of the Comprehensive Watershed Management
(CWM) initiative strategies. The County previously budgeted funds for the project design, development of construction
documents, construction permitting, land acquisition, and bidding and contractor selection. The probable construction
costs for this project were based on the BMP alternative analysis developed by the County in its Hudson Bayou Master
Plan completed in September 1994 and updated in April 1997. The County and the City of Sarasota will be required to
acquire a joint drainage easement to implement the BMP. A cooperative funding expenditure agreement with the
County was developed to complete the Implementation of BMPs. The County will manage the project, where the
District project manager must approve any agreements to accomplish project tasks.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 216,920 0 0 210,022 3,405 3,493
Project Funds Not Budgeted by the
District
Sarasota County 1,535,927 0 0 1,535,927 0 0
$1,752,847 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 231
L613
Sarasota Imp. BMPs South Pelican Drive
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionNegotiate Cooperative Funding Agreement with County 10/31/06 1/5/07
Cooperative Funding Agreement to Contract Administration 1/5/07 2/15/07 2/7/07
Contract sent to County for BOCC Approval 3/14/07 3/14/07
Signed Contract returned from County 4/2/07 4/30/07
Contract Executed 4/16/07 5/3/07
Notice to Proceed sent to County 4/16/07 5/5/07
2. Critical Project MilestonesComplete Design and Permitting 6/5/07 2/28/10
Bidding and Contractor Selection 11/5/07 4/1/10
Commence Construction 11/5/07 6/1/10
Complete Construction 1/5/09 6/1/11
3. Project Close OutSubmit As-Builts 5/5/09 8/1/11
Contract Termination 10/1/10
Status As Of: February 19, 2010
Notice of FY2007 funding approval was sent to the County's project manager. A meeting was held with the County to
discuss the scope of work and schedule. The County submitted a FY2008 funding request in the amount of $150,000 to
cover additional costs associated with design changes that have occurred because the County was unable to secure
land for the proposed stormwater pond. The Manasota Basin Board did not include the requested additional funding
amount of $150,000 in its FY2008 budget because the project was on hold pending design changes. An e-mail was sent
to the cooperator on August 21, 2007 notifying that the additional funding request was not approved. On August 21, 2007
District staff requested information on how the County is going to make-up for the $150,000 shortfall. The Hazard
Mitigation Grant in the amount of $258,375 that the County applied for has been denied. The land originally identified for
the pond site could not be acquired. The County tried to negotiate land acquisition from the railroad company for an
alternative pond site but the railroad company was not interested. The County is considering reducing the original level of
service projection and using an existing downstream pond and shallow street swales to meet the water quality
component. The County appropriated the remainder of the project costs in the FY2008 budget. The County submitted a
revised project schedule on August 26, 2008 which extends beyond the contract termination date. District staff has
advised the County that a no cost time extension will need to be requested to extend the contract. District staff met with
the County on December 29, 2008 to discuss the project status. The project design is currently at 20 percent. The project
is currently on hold because of design and modeling issues.
021 - Manasota Basin 232
L614
Sarasota Imp. BMPs Matheny Creek
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager SMITH, RANDY
Task Manager(s)
Status Ongoing
DescriptionThis is a multi-year funded project to perform the Implementation of Best Management Practices (BMPs) element of
the District's Watershed Management Program (WMP) for the Matheny Creek Watershed in Sarasota County.
This project will be implemented in the Siesta Heights improvement area. Intense rainfall combined with inadequate
drainage facilities and high tides cause frequent flooding within the improvement area. The Siesta Heights culvert
system will be enlarged and include grassed swales above the proposed storm drains and a Nutrient Separating Baffle
Box to provide water quality treatment. This project includes construction of the BMP only. The proposed BMP will
address level of service deficiencies and improve water quality.
BenefitsThe project is expected to meet level of service criteria during a 25-year storm event that eliminates structural flooding
of four structures and improves roadway access by improving conveyance. The project is also expected to improve
water quality with increased grassed swale storage and installation of a baffle box sediment trap. According to the
County, the project will provide approximately $833,000 in present-value flood mitigation benefits assuming a 50-year
useful life.
Costs
The total budget amount for this project is $1,100,000, of which the District's share is $425,000. The District
appropriated $212,500 in their FY2007 and FY2008 budgets. The District's share is being funded entirely by the
Manasota Basin Board. The County will contribute $675,000 and is seeking $568,131 from FEMA through the Hazard
Mitigation Grant Program. If the County receives the FEMA grant, the project budget will be refined according to
Board Policy 130-4. When each task is completed the project budget may require refinement based on the
information gathered. The District funding amounts shown in the table include staff salaries, travel and central
garage charges.
Additional Information
The WMP includes five major elements: 1)Topographic Information, 2)Watershed Evaluation, 3)Watershed
Management Plan, 4)Implementation of BMPs, and 5)Maintenance of Watershed Parameters and Models.
Implementing elements of the WMP with local governments is one of the Comprehensive Watershed Management
(CWM) initiative strategies. The probable construction cost for this project was based on the BMP alternative analysis
developed by the County in its Matheny Creek Basin Master Plan. The County previously budgeted funds for the
project design, development of construction documents, construction permitting, land acquisition, and bidding and
contractor selection. Work will be performed in current County and Florida Department of Transportation rights-of-way.
A cooperative funding expenditure agreement with County was developed as a multi-year funded project contingent on
the approval of future funding to complete the Implementation of BMPs. The County will manage the project, where
the District project manager must approve any agreements to accomplish project tasks.
021 - Manasota Basin 233
L614
Sarasota Imp. BMPs Matheny Creek
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 444,958 0 0 435,361 3,464 6,133
Project Funds Not Budgeted by the
District
Sarasota County 675,000 0 0 675,000 0 0
$1,119,958 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionNegotiate Cooperative Funding Agreement with County 10/31/06 1/5/07
Draft Agreement to Management Services 1/5/07 2/15/07 2/2/07
Agreement returned from Management Services 3/14/07 3/14/07
Contract sent to County for BOCC Approval 3/14/07 3/14/07
Signed Contract returned from County 4/2/07 4/30/07
Contract Execution 4/16/07 5/3/07
Notice to Proceed 4/16/07 5/3/07
2. Critical Project MilestonesComplete Design and Permitting 6/5/07 4/1/09 4/1/09
Bidding and Contractor Selection 11/5/07 10/30/09 11/17/09
Commence Construction 11/5/07 12/31/09 12/15/09
Complete Construction 1/5/09 7/15/10
3. Project Close OutSubmit As-Builts 5/5/09 9/1/10
Contract Termination 11/30/10
Status As Of: February 19, 2010
Notice of FY2007 funding approval was sent to the County's project manager. A meeting was held with the County in
August 2006 to discuss the scope of work and schedule. The County submitted a FY2008 funding request in the amount
of $212,500 to cover second year funding of the multi-year funded project. Notice to Proceed was sent to the cooperator
effective May 3, 2007. The Manasota Basin Board included the second year funding request of $212,500 in its FY2008
budget. The ERP modification for the baffle box is completed. The FDOT utility drainage permit and temporary
construction easements were acquired. The County revised the construction plans to accommodate utility adjustments
along US 41. District staff met with the County on December 29, 2008 to discuss the project status. Design and
Permitting were completed in April 2009. The construction component of the project was advertised for bid on August 22,
2009. A pre-bid meeting was held on September 3, 2009. Sarasota County hired EHC, Inc. to do project construction. A
pre-construction meeting was held on December 11, 2009. Project construction began December 15, 2009.
021 - Manasota Basin 234
L615
Sarasota Imp. BMPs Alligator Creek
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager SMITH, RANDY
Task Manager(s)
Status Ongoing
DescriptionThis is a multi-year funded project to perform an element of the District's Watershed Management Program (WMP) for
the Implementation of Best Management Practices (BMPs) in the Alligator Creek Watershed. The watershed covers
an area of approximately 10.7 square miles and is located in Sarasota County. This project will implement several
improvements in the following areas: 1) Banyan Drive - culverts and pond expansion with wetland plantings, 2)
Briarwood area - upsizing of culverts and outfall pipe, 3) Bal Harbour Drive - stormwater collection system, 4) Venice
East Drive - modify the control structure at Heron Lakes, and 5) Venice East Boulevard - installation of box culvert.
Several of the roadways contiguous to these improvement areas become impassable during the 10, 25, and 100-year
storm events that result in a health and welfare threat to residents by creating changes in traffic flow and emergency
vehicle routing. In addition, the project is expected to improve water quality by installing several Nutrient Separating
Baffle Boxes to reduce non-point source pollutant loads. This project is also expected to improve water quality by
increasing residence time through conversion of the old Briarwood wastewater treatment percolation ponds into
stormwater ponds and by expanding the existing lake system storage capacity. This project includes construction of
the BMP only.
BenefitsThe project is expected to meet level of service criteria during a 25-year storm event, improving roadway access by
increasing conveyance and providing additional storage in the watershed. The project is also expected to improve
water quality by increasing residence times and installing several Nutrient Separating Baffle Boxes to reduce non-point
source pollutant loads. According to the County, the project will provide approximately $2.3 million in present-value
flood mitigation benefits assuming a 50-year useful life.
Costs
The total budget amount for this project is $4,220,000, of which the District's share is $1,500,000. The District
appropriated $750,000 in their FY2007 budget and $375,000 in their FY2008 budget. The County will request the
remaining $375,000 of District funding in the fiscal year that it will be used. The District's share is being funded entirely
by the Manasota Basin Board. The County budgeted $2,720,000 over FY2006, FY2007, FY2008, and FY2009. When
each task is completed the project budget may require refinement based on the information gathered. The District
funding amounts shown in the table include staff salaries, travel and central garage charges.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of BMPs, and 5) Maintenance of Watershed Parameters and Models.
Implementing elements of the WMP with local governments is one of the Comprehensive Watershed Management
(CWM) initiative strategies. The probable construction cost for this project was based on the BMP alternative analysis
developed by the County in its Alligator Creek Basin Master Plan. The County previously budgeted funds for the
project design, development of construction documents, construction permitting, land acquisition, and bidding and
contractor selection. The County will be required to acquire easements in order to implement the BMPs. A cooperative
funding expenditure agreement with County was developed as a multi-year funded project contingent on the approval
of future funding to complete the Implementation of BMP's. The County will manage the project, where the District
project manager must approve any agreements to accomplish project tasks.
021 - Manasota Basin 235
L615
Sarasota Imp. BMPs Alligator Creek
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,145,618 0 0 1,135,361 3,464 6,793
Project Funds Not Budgeted by the
District
Sarasota County 2,720,000 0 0 2,720,000 0 0
$3,865,618 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionNegotiate Cooperative Funding Agreement with County 10/31/06 1/4/07
Draft Agreement to Management Services 1/5/07 2/15/07 2/2/07
Agreement returned from Management Services 3/16/07 3/20/07
Contract sent to County for BOCC approval 3/16/07 3/28/07
Signed Contract returned from County 4/2/07 5/18/07 5/14/07
Contract Execution 4/16/07 5/25/07 5/15/07
Notice to Proceed 4/16/07 5/28/07 5/17/07
2. Critical Project MilestonesComplete Design and Permitting 5/17/07 10/1/10
Bidding and Contractor Selection 10/16/07 2/1/11
Commence Construction 10/16/07 3/1/11
Complete Construction 6/16/09 3/1/12
3. Project Close OutSubmit As-Builts 10/16/09 5/1/12
Contract Termination 11/30/10
Status As Of: February 19, 2010
Notice of FY2007 funding approval has been sent to the County's project manager. A meeting was held in August 2006
with the County to discuss the scope of work and schedule. The County submitted an FY2008 funding request in the
amount of $750,000 to cover second year funding of the multi-year funded project. The contract was sent to the County
for signature on March 28, 2007. Due to budgetary constraints District staff only included $375,000 in the FY2008
funding request. The Manasota Basin Board included the second year funding request of $375,000 in their FY2008
Budget. The County requested the remaining $375,000 in FY2009 to complete the project. The County withdrew its
FY2009 funding request because those funds would not be expended until FY2010. The County submitted a revised
project schedule that extends beyond the contract termination date. District staff has notified the County that a no cost
time extension would be required to extend the contract. District staff met with the County on December 29, 2008 to
discuss the project status. The County requested the remaining $375,000 in FY2010 to complete the project. The County
withdrew its FY2010 funding request because those funds would not be expended until FY2011. The County is currently
trying to resolve unexpected stage rises indicated by the modeling effort. The County is exploring options to move
forward with certain elements of the project that are not affected by the modeling issues. The project design is currently
at 60 percent.
021 - Manasota Basin 236
L624
Venice Imp. BMPs Hatchett Creek-Venice
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Emergency Flood Response
Basin(s) Manasota
City of VeniceCooperator(s)
Project Manager PRATER, CORRINA
NORTON, NANCYTask Manager(s)
Status Ongoing
DescriptionThis project is to perform the Implementation of Best Management Practices (BMPs) element of the District's
Watershed Management Program (WMP) for the Hatchett Creek Watershed in Sarasota County. This BMP will be
implemented in the Venice Avenue improvement area. The existing stormwater system on Venice Avenue, U.S.41
Bypass and Warfield Avenue is undersized and causes flooding of the roadways. Venice Avenue and U.S. 41 Bypass
are evacuation routes and Warfield Avenue is an access road for the City of Venice Utilities Department, water
treatment plant and area businesses. Extensive flooding has caused the closure of the Warfield Avenue and U.S. 41
Bypass intersection 3 to 4 times a year when daily rainfall exceeds 3 inches. The proposed stormwater system will be
designed to a 100-year, 24-hour rainfall event. The existing stormwater system on Warfield Avenue will be enlarged
and replaced with new pipe, curb inlets and outfall pipes. Two additional curb inlets and connector pipes will be added
at the intersection of U.S. 41 Bypass and Venice Avenue. In addition, stormwater will be directed to the retention pond
at East Venice Avenue and Warfield Avenue. The existing pond may require modification due to the added water
volume being treated. The proposed BMP will address level of service deficiencies. With FY2007 funding the work on
the Implementation of BMPs will begin and includes the following tasks: evaluation, design, development of
construction documents, construction permitting, bidding and contractor selection, and construction of the BMPs.
BenefitsThe project will improve level of service deficiencies by improving conveyance and providing additional storage within
the watershed. The project is also expected to improve water quality by increasing residence times in the storage area.
Repairing the damaged stormwater pipes that are seeping sediment into the system and Hatchett Creek outfall will
enhance stormwater quality.
Costs
The total budget amount for this project is $351,670, of which the District's share is $175,835. The District's share was
funded entirely by the Manasota Basin in FY07. The City contributed $175,835 over FY2007 and FY2008. When each
task is completed the project budget may require refinement based on the information gathered. The District funding
amounts shown in the table include staff salaries, travel and central garage charges.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of BMPs, and 5) Maintenance of Watershed Parameters and Models.
Implementing elements of the WMP with local governments is one of the Comprehensive Watershed Management
(CWM) initiative strategies. Future funding to complete the project will be provided by the City that will satisfy its
cooperative funding match requirements. The City will manage the project, where the District project manager must
approve any agreements to accomplish project tasks.
021 - Manasota Basin 237
L624
Venice Imp. BMPs Hatchett Creek-Venice
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 194,724 0 0 186,295 4,482 3,947
Project Funds Not Budgeted by the
District
City of Venice 175,835 0 0 175,835 0 0
$370,559 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionNegotiate Cooperative Funding Agreement with City 10/31/06 9/14/06
Draft Agreement to Management Services 3/19/07 2/28/07
Agreement returned from Management Services 4/9/07 5/1/07
Contract sent to City for Approval 4/16/07 5/3/07
Signed Contract returned from City 5/14/07 6/4/07
Contract Execution 5/28/07 6/6/07
Notice to Proceed 6/4/07 6/7/07
2. Critical Project MilestonesAcquire All Permits, Government Approvals, & Real Property Rights for Project 6/4/08 4/4/08
Complete Design and Permitting 6/4/08 4/4/08
Bidding and Contractor Selection 9/4/08 11/10/09 1/29/10
Commence Construction 11/4/08 12/7/09 3/11/10
Complete Construction 12/31/09 12/31/10
3. Project CloseoutSubmit AsBuilts 2/19/10 2/18/11
Contract Termination 3/19/10 3/31/11
Status As Of: February 15, 2010
The City has selected the contractor. A pre-construction meeting is scheduled for February 23.
021 - Manasota Basin 238
L627
City of North Port Water Conservation and Retrofit Project
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Conservation
Basin(s) Manasota
City of North Port - Public UtilitiesCooperator(s)
Project Manager MUSICARO, MELISSA
Task Manager(s)
Status Ongoing
DescriptionThis project consists of offering financial incentives to single-family customers for replacing conventional toilets with
water-conserving equivalents, and installing rain sensors on automatic irrigation systems. For customers that
participate in the program, the City also provided approximately 412 low-flow (2.5 gallons per minute, or gpm) shower
heads to replace conventional models (5-7 gpm). The project targeted the replacement of approximately 824
conventional toilets with low-flow toilets, which use up to 1.6 gallons per flush (gpf). The project also targeted the
installation of approximately 412 rain sensor devices. The City provided a $100 credit to the customers' water bill upon
low-flow toilet installation and inspection, and a $50 credit for the purchase and installation of a rain sensor.
BenefitsThis project is anticipated to save an estimated 22,145 gallons of water per day. The various devices to be installed for
this project have different life spans. The estimated water savings was calculated using a weighted average based on
the total benefit for the life of the project.
Costs
The total project cost is $117,000, and the Manasota Basin Board approved funding in the amount of $58,500 in
FY2007. The cost amortized at 8 percent over 20 years, is $1.45 per thousand gallons saved (calculated using a
weighted average based on the total benefit for the life of the project).
Additional Information
In addition to providing financial assistance for the installation of low- flow toilets, a goal of this project is to educate all
program participants on methods of indoor water conservation and proper maintenance practices to ensure low flow
toilets remain a water conservative fixture. Educational materials on flapper replacement and other water conservation
techniques will be disseminated to all program particpants. The City plans to hire a consultant to administer the
project.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 77,200 0 0 74,167 0 3,033
Project Funds Not Budgeted by the
District
City of North Port 58,500 0 0 58,500 0 0
$135,700 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Draft Agreement to Contract Administration 1/1/07 1/2/07
Draft Agreement returned from Contract Administration 1/31/07 1/9/07
Contract Executed 3/31/07 3/7/07
Notice to Proceed 4/1/07 3/8/07
Basin Board Notification 6/13/07 6/16/07
021 - Manasota Basin 239
L627
City of North Port Water Conservation and Retrofit Project
Rebates Commence 8/1/07 3/1/07
Rebates Complete 8/1/08 10/31/08
Project Complete 9/1/09
Contract Termination 12/31/09
Status As Of: December 08, 2009
The Agreement was executed on March 7, 2007. Toilet rebates are complete, with a total of 715 toilets installed and 32
showerheads distributed. The city continues to receive customer satisfaction surveys; to date, all participants are
satisfied with the new toilets. The final project report is delayed and will be submitted in January 2010. To date, the
county has been reimbursed a total of $36,710.
021 - Manasota Basin 240
L693
Water Exhibits in the Glazer Children's Museum of Tampa
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality MonitoringFlood Protection Floodplain ManagementWater Supply ConservationNatural Systems Natural Systems Identification and Monitoring
Basin(s) Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers, Pinellas-Anclote River,
Withlacoochee River, Peace River, Manasota
The Children's Museum of TampaCooperator(s)
Project Manager HULL, MARY MARGARET
Task Manager(s)
Status Ongoing
DescriptionThe Glazer Children's Museum of Tampa is relocating to a new museum site in Riverfront Park in downtown Tampa.
This multi-year project is part of the City of Tampa's efforts to revitalize the downtown business district. This is the third
and final phase of a project to develop and install water exhibits in the museum. In FY2007, the District funded the
planning and development phase for interactive water exhibits. FY2008 funds paid for detailed specifications,
structural engineering, fabrication of support structure, construction of entrances, partial platform construction and
other expenses related to fabrication. In the conceptual phase, District staff and BBEC members were included in
several planning sessions for the design of the interactive water exhibits to ensure they incorporate the District's
message. These exhibits include Water's Journey, which is a three-story climbing structure where visitors "become" a
drop of water and make their way across the watershed, down through the aquifer, up to the city, down a storm drain
and into a swamp. Another exhibit is the Water Bank, which is styled to look like an ATM. Here visitors explore some
of the issues of water supply and demand. Sample depositors of water into the ATM are rain, reservoir, desalination
plants, etc. Withdrawals of water are made by wildlife, wetlands, cities, people, industry, agriculture, etc. Interest is
earned by saving water through a variety of water conservation actions, such as turning the water off when brushing
teeth, using Florida-Friendly LandscapingTM principles, etc. The FY2009 funding is for exhibit construction and
installation.The museum is scheduled to open to the public in May/June 2010.
BenefitsThe exhibits are multidisciplinary and designed to engage diverse learning styles. The museum is projected to draw
100,000 people annually. The interactive water exhibits address three elements of the District's AORs -- water supply,
water quality and natural systems -- in simple, easy-to-understand terms. Additionally, this project targets children ages
0-10 years and accompanying adults. This segment of the population was identified in an independent evaluation of
the District's youth education program as one to which the District needed to expand its reach. This project helps
accomplish this goal.
Costs
The total cost of the project (including building construction and all exhibits throughout the museum) is estimated to be
$20 million. The total contribution from the District, including FY2007, FY2008 and FY2009, is $617,442. In FY2007,
the basins shared $112,500 for the planning and development phase for interactive water exhibits. FY2008 funds were
for detailed specifications, structural engineering, fabrication of support structure, construction of entrances, partial
platform construction and other expenses related to fabrication. FY2009 funds are for completion of the exhibit
fabrication, installation and education program development. Phase 3 FY2009 funding request of $252,471 is
allocated as follows:
Alafia River: 12% $29,968;
Hillsborough River: 27% $68,900;
Northwest Hillsborough: 15% $37,340;
Coastal Rivers: 9% $22,249;
Pinellas-Anclote: 14% $35,396;
Withlacoochee River: 5% $12,821;
Peace River: 8% $20,550;
Manasota: 10% $25,247.
The funding splits for this project are based on cooperator-supplied projections of museum attendance. This project
anticipates reaching 100,000 people per year at a cost (for the total project, all phases) to the District of $6.18 per
person. Typical museum exhibits have a 10-year life span. This project, therefore, has the potential to reach 1 million
visitors over a 10-year period at a cost to the District of $0.62 per person. The budget lines below include costs for
staff to manage the project.
021 - Manasota Basin 241
L693
Water Exhibits in the Glazer Children's Museum of Tampa
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 74,786 0 0 74,786 0 0
013 Hillsborough River Basin 171,265 0 0 171,265 0 0
014 Northwest Hillsborough Basin 94,255 0 0 94,255 0 0
015 Coastal Rivers Basin 49,738 0 0 48,961 0 777
016 Pinellas-Anclote River Basin 98,917 0 0 98,917 0 0
019 Withlacoochee River Basin 30,290 0 0 29,513 0 777
020 Peace River Basin 49,534 0 0 48,757 0 777
021 Manasota Basin 58,115 0 0 57,338 0 777
Project Funds Not Budgeted by the
District
Glazer Children's Museum of Tampa 5,522,920 0 0 5,522,920 0 0
Other Funding Sources 19,091,102 0 0 19,091,102 0 0
$25,240,922 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2007 Budgeted FundsFY2007 purchase order opened 4/30/07 4/26/07
Confirmation and layout of exhibits in building 6/30/07 6/30/07
Schematic design and fabrication documents 12/30/07 12/14/07
FY2008 Budgeted FundsFY2008 contract executed 5/15/08 9/15/08 9/10/08
Project meeting with Museum staff and architect 7/6/09 7/6/09
FY2008 components completed 12/31/09 2/26/10
FY2009 Budgeted FundsFY2009 contract executed 9/1/09 10/30/09 11/4/09
Building construction complete 3/1/10 3/26/10
Exhibts installed 7/1/10
FY2009 components completed 8/1/10
Museum grand opening 9/30/10
Status As Of: February 19, 2010
ACTION TO DATE: On time. Construction of the Museum building is underway and expected to be complete by March
2010. Once the building construction is complete; exhibit installation will take an additional 4 to 6 months. The fabrication
of the major exhibit, Water's Journey, is happening concurrently with the building's construction. Cooperator is planning a
fundraising event inside the new Museum on May 22.
021 - Manasota Basin 242
L854
Bradenton/Manatee Co./Palmetto Reuse Interconnect Study
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Alternative Water Supply
Basin(s) Manasota
City of BradentonCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project is to perform a detailed study of the interconnection of the existing reclaimed water reuse systems of the
City of Bradenton with the City of Palmetto and the City of Bradenton with Manatee County (MARS). The study will
determine the amounts of reclaimed water from the City of Bradenton that can be beneficially reused during the next
20 years by the City of Palmetto and Manatee County, and develop preliminary designs for the pumping, transmission
and control facilities required to interconnect the three reuse systems. In addition to a final report, a 20-year agreement
between the two cities and the city and county for implementing and operating the interconnected systems will be a
project deliverable.
BenefitsThis interconnection study will provide the City of Bradenton, Manatee County, the City of Palmetto, and the District
with an implementable plan for interconnection of the three reuse systems.
Costs
The total project cost is estimated to be $120,000 and the District's share is $40,000 in FY2008. The City of Bradenton
will fund $80,000 and plans to receive $20,000 from Manatee County and $20,000 from the City of Palmetto. Any
additional funds are for staff time.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 51,661 0 0 50,882 0 779
Project Funds Not Budgeted by the
District
City of Bradenton 40,000 0 0 40,000 0 0
City of Palmetto 20,000 0 0 20,000 0 0
Manatee County 20,000 0 0 20,000 0 0
$131,661 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Agreement Executed: 1/31/08 2/25/08
Begin Interconnect Study: 3/31/08 3/31/08
Complete Interconnect Study: 5/29/09 5/30/09
Status As Of: February 19, 2010
The agreement was executed on February 25, 2008. The consultant, Jones, Edmunds & Associates, Inc. was given a
notice to proceed on March 31, 2008. A project kick-off meeting was held May 19, 2008. Draft interlocal agreements
between the City of Bradenton and City of Palmetto and between the City of Bradenton and Manatee County have been
prepared and reviewed by the City attorney. Data show that the City of Palmetto will have adequate reclaimed water from
021 - Manasota Basin 243
L854
Bradenton/Manatee Co./Palmetto Reuse Interconnect Study
it's own reuse system to meet there needs for the next twenty years. An agreement between the City of Bradenton and
Manatee County for the City to provide MARS the desired quantities of reclaimed water appears unlikely. The study of
the interconnect between Bradenton and Palmetto was completed May 25, 2009. The study of the interconnect between
Bradenton and Manatee County was completed May 30, 2009. This project is complete. The final invoice is scheduled to
be submitted by the City of Bradenton on March 5, 2010.
021 - Manasota Basin 244
L867
Sarasota County GIS Dataset Development
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) General Fund (District), Manasota
Sarasota CountyCooperator(s)
Project Manager FITOS, EKATERINA
TURNER, DAWN, FITOS, EKATERINA, DICKS, STEVETask Manager(s)
Status Ongoing
DescriptionSarasota County Environmental Services is creating and maintaining a comprehensive Geographic Information
System (GIS) database to support surface water modeling and stormwater asset management functions. This project
enhances the quality of the data supporting modeling activities by gathering accurate locations and characteristics of
key stormwater assets. Among many potential applications, these data will aid in the development and management of
watershed management plans through hydrologic model maintenance/updates and point and non-point pollutant
source identification. The funding will be used to enhance the County's current stormwater infrastructure database that
consists of control structures, inlets, pipes, pipelines, ditches, swales and retention/detention ponds. These data will be
used by the County to generate and maintain a common database that will support water quality, hydrologic and
hydraulic models. This database will also be compatible with the District's GIS database standards.
BenefitsDrainage infrastructure is a critical component in the calibration and verification of hydrologic and hydraulic models.
When fully calibrated, these models generate accurate stage-area relationships, allowing County staff to generate
precise floodplain maps needed to estimate flood risks. When paired with topographic data, Sarasota County will be
able to move ahead with Federal Emergency Management Agency Map Modernization efforts. The improved database
will allow the County to initiate proactive flood protection measures that include the rapid assessment and identification
of potential flooding hot spots, and development of complex what-if scenarios. The database will also support water
quality management efforts and to ensure fishable and swimable waters. County staff will be better equipped to identify
and model key water monitoring locations within coastal watersheds.
Costs
Costs for FY2009 include $100,000 from the Manasota Basin Board and $150,000 from Sarasota County. The cost of
the project through FY2008 is $306,742. The Manasota Basin Board is contributing $100,000 and Sarasota County is
$206,742. For FY2010, $100,000 has been allocated in the Manasota Basin Board budget, and Sarasota County will
provide $200,000. The future funds identified for the project are contingent upon approval of such amounts by the
Manasota Basin Board in the annual budget.
Additional Information
As part of the hydrologic model and for the purposes of this project, horizontal survey data collection refers to
structures such as pump stations, weirs, ponds and wetlands which combine to form part of a drainage infrastructure.
By collecting this information through the means of a horizontal survey the data can be used for more accurate
modeling in the event of severe weather impacts or for planning purposes due to urbanization.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 405,425 100,000 0 202,698 0 102,727
Project Funds Not Budgeted by the
District
Sarasota County 1,206,742 0 0 506,742 500,000 200,000
$1,612,167 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 245
L867
Sarasota County GIS Dataset Development
Critical Project Milestones ActualProjected Amended
Phase 2 - FY 2008Contract Execution 12/19/07 9/15/08 9/5/08
Notice to Proceed 1/3/08 9/15/08 9/5/08
Task 1 - Project Initiation Meeting and Field Collection 2/25/08 5/31/08 4/25/08
Task 2 - Field Data Collection 3/15/08 12/31/08
Task 3 - Establish Connectivity and Office QA/QC 3/15/08 1/31/09
Phase 3 - FY 2009Contract Execution 1/15/09 5/30/09
Notice to Proceed 1/30/09 6/1/09
Task 1 - Project Initiation Meeting and Field Collection 1/31/09 1/21/09
Task 2 - Field Data Collection 2/28/09
Task 3 - Establish Connectivity and Office QA/QC 3/31/09
Phase 4 - FY 2010Contract Execution 9/1/09
Notice to Proceed 10/1/09
Task 1 - Project Initiation Meeting and Field Collection 10/1/09
Task 2 - Field Data Collection 7/30/10
Task 3 - Establish Connectivity and Office QA/QC 9/30/10
Status As Of: February 22, 2010
FY2009 - Phase 3: Data archival is in progress, and final invoicing has been approved for reimbursement. Project is in
the process of being closed out. FY2010 - Phase 4: Corresponding to the discussion at the June 2009, kickoff meeting
between the District and the County. Both parties agreed that the project would reap greater benefits if efforts for the GIS
Dataset collection were coupled with the flood plain mapping and watershed modelling activities. Hence, the project has
been transferred to Engineering Section. Dawn Turner will be the acting project manager overseeing this project. County
staff recently indicated the County may not fund the project in FY2010. District staff has requested confirmation as to
whether the project will be funded by the County in FY2010. Florida Initiative ACTION-TO-DATE comment: FY2009 -
Phase 3 project is completed.
021 - Manasota Basin 246
L874
Aqua Utilities Reuse Transmission - Eastern Lakewood Ranch
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Alternative Water Supply
Basin(s) Manasota
Aqua Utilities Florida, Inc.Cooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project consists of the design and construction of 7,500 feet of 12" reclaimed water transmission line, 16,500 feet
of 20" reclaimed water line, and a pump station to provide reclaimed water to the residential and agricultural areas in
the eastern part of Lakewood Ranch. The reuse transmission main will interconnect the Lakewood Ranch Phase VII-D
Lake, with new residential developments and existing agricultural areas along Loraine Road, south of University
Boulevard, and east along University Boulevard from Loraine Road.
BenefitsThe project will provide approximately 1.15 mgd of reclaimed water to meet the near term residential and agricultural
demands. Residential demand will be 0.57 mgd and agricultural demand 0.58 mgd. At build-out it will provide 1.5 mgd
to meet the irrigation need in this eastern area of Lakewood Ranch. It is projected that 100% of the reuse water will
replace future and existing groundwater demand from the Floridan aquifer.
Costs
The total project cost is estimated to be $3,274,000 and the District's share is $734,800 in FY2008 and $818,500 in
FY2009 for a total of $1,553,300. The WPSTF has budgeted $167,400 in FY2008. The cost, amortized at 8 percent
over 30 years, is $0.53 per 1000 gallon offset. Any additional funds are for staff time.
Additional Information
The agricultural customer is Shreoder Manatee (Water Use Permit 207846.022). Beyond the immediate residential
need, at build-out the project will provide 1.5 mgd of reclaimed water to meet the irrigation need in this eastern area of
Lakewood Ranch. It is projected that 100% of the reclaimed water will replace future and existing groundwater
demand from the Floridan aquifer. Of the $3,274,000 total cost, design is estimated to cost $320,000, and the
remaining $2,954,000 is allocated for construction.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,563,075 0 0 1,560,744 0 2,331
District Budgeted - Outside Revenue
Water Protection & Sust T.F.
(Alternative Wtr)
167,400 0 0 167,400 0 0
Project Funds Not Budgeted by the
District
Aqua Utilities 1,553,300 0 0 1,553,300 0 0
$3,283,775 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Begin Design: 11/30/07 12/14/07
021 - Manasota Basin 247
L874
Aqua Utilities Reuse Transmission - Eastern Lakewood Ranch
Execute Agreement: 1/31/08 3/24/08
Complete Design: 9/30/08 9/19/08
Start Construction: 11/30/08 1/5/09
Complete Construction: 11/1/09 8/31/09
Status As Of: March 01, 2010
Processing the agreement was initially delayed due to funding considerations concerning WPSTF funds and acquisition
of the required insurance documentation. The agreement with Aqua Utilities was executed on March 24, 2008. DMK
Associates was selected to design the project and has completed the field study and design work on the transmission
line and pump station. The construction contract was awarded to the low bidder, Woodruff and Sons, Inc.. Construction
on the transmission line began in January 2009 and all the 12 inch and 20 inch reuse pipeline was installed as of April
16, 2009. The concrete pads, pumps and controls were installed the end of July. The system has been tested and is
complete. As-built drawings are being completed. The first invoice was submitted July 8, 2009. Additional documentation
has been requested before any invoice can be processed for payment. The District's entire funding commitment has
been encumbered, of which to date $0 has been reimbursed. This project is consistent with Governor Crist's Accelerate
Florida Initiative to stimulate Florida's economy. Action-to-date: Completed.
021 - Manasota Basin 248
L949
Manatee County Water Conservation Program
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project consists of offering financial incentives to single-family, multi-family, and commercial customers for
replacing conventional toilets with water-conserving equivalents. This project will target the replacement of
approximately 900 conventional toilets with ultra-low volume (ULV) toilets, which use up to 1.6 gallons per flush (gpf).
In addition, approximately 900 low-flow showerheads will be provided to participating customers to replace
conventional showerheads. The project will provide rebates for toilets at $100 per fixture. This proposed project is the
second phase to the Manatee County Indoor Water Conservation Project (L601) funded in FY2007.
BenefitsThis FY2008 project is anticipated to save an estimated 17,250 gallons of water per day or 6,296,250 gallons per year.
Costs
The total project cost is $126,144. The Manasota Basin Board funding share of 50 percent is $63,072 in FY2008.
Manatee County's 50 percent share is $63,072. The cost amortized at 8 percent over 20 years, is $2.07 per thousand
gallons. The savings is calculated using a weighted average due to the varying life expectancies of the different water
saving equipment.
Additional Information
In addition to providing financial assistance for the installation of low flow toilets, a goal of this project is to educate all
program participants on methods of indoor water conservation and proper maintenance practices to ensure low flow
toilets remain a water conservative fixture. Educational materials on flapper replacement and other water conservation
techniques will be disseminated to all program particpants. The county plans to hire a consultant to administer the
project. In regard to low flow showerheads, the county plans to initiate a showerhead exchange or new showerhead
inspection program to verify the replacement of high volume showerheads.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 87,252 0 0 84,221 754 2,277
Project Funds Not Budgeted by the
District
Manatee County 63,072 0 0 63,072 0 0
$150,324 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Program Implementation 4/1/08 6/30/08
Complete Rebates 6/30/09 3/2/09
Distribution Report 7/30/09 7/9/09
Final Report 9/30/10
Project Closeout 1/31/11
021 - Manasota Basin 249
L949
Manatee County Water Conservation Program
Status As Of: February 19, 2010
From April 2009 to May 2009, Manatee County rebated 266 toilets and 160 showerheads. The District has reimbursed
Manatee County $61,768.50 for this project and has a balance of $1,303.50. Manatee County has completed a total of
1,486 toilet rebates. The Distribution report for this project was received on July 9, 2009. The estimated project savings is
over 8 mg per year. Manatee County has received all the funds allocated by the District for toilet rebates. Manatee
County will continue to gather data for the final report which is due September 30, 2010.
021 - Manasota Basin 250
N084
City of North Port Reuse Storage Tank and High Service Pump
StationProject Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water SupplyWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
City of North Port, City of North Port - Public UtilitiesCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project will construct a 2.5 million gallon ground storage tank and design and expand the high service pump
station by adding a 3.3 mgd pump. The benefits of this project will include improving system pressures, peak demand
storage capacity, expand the customer base of the reuse system, and will provide a higher level of service to the
customers. The Heron Creek Development (531,300 gallons per day [gpd]) has 2350 Equivalent Residential
Connections and a golf course. The reuse supply contract between the City and Heron Creek is for up to 500,000 gpd
of reclaimed water. The City currently provides an average of 200,000 gpd to Heron Creek with the existing system.
With the new tank and high service pump they will be able to provide the additional 300,000 gpd to Heron Creek and
provide reclaimed water to additional future customers.
BenefitsThe City plans to increase reuse flows to the Heron Creek Development by approximately 0.3 mgd to provide an offset
of 0.18 mgd of existing and future groundwater use by residential, commercial, and golf course customers. This project
will also provide the infrastructure that will enable the City to serve four additional customers with approximately 1.6
mgd of reclaimed water when additional lines are constructed. The project supports the City's Reuse Master Plan and
will allow the City to meet the demands of future growth in the City's service area.
Costs
The total project cost is $2,102,500 and the District's share is requested to be fifty percent or $1,051,250. The City
plans to spend $202,500 in FY2009 and the Manasota Basin Board has budgeted $101,250 which is fifty percent. The
Manasota Basin has been requested to provide $950,000 in additional funds in FY2010. The cost, amortized at 8
percent over 30 years is $3.38 per 1000 gallons offset. The future funds identified for the project are contingent upon
approval of such amounts by the District Governing and Basin Boards in the annual budget(s).
Additional Information
This project is to implement one of the recommendations of the City's Reuse Master Plan, supported and funded by
SWFWMD. The City of North Port's existing WWTP is permitted to provide 1.88 mgd of public access reclaimed water
to the customers of the system, which consist primarily of two major golf courses, the new City Complex, the North
Port Skate Park, roadway medians, and several bulk residential users. Growth in North Port has resulted in the need
for two additional WWTPs that will be constructed over the next 5-10 years, the West Villages District (WVID) WWTP
and the Panacea WWTP. Both of these two facilities will be designed to provide public access reclaimed quality water
to the customers in the region. In addition, the existing City's WWTP will be expanded to 7.0 mgd within the next 5
year period; therefore, the permitted capacity will be modified to reflect the new reclaimed water availability. This
project will allow the City to provide future reclaimed water service to the following new customers: *The Primary
School, Middle School and High School along Price Boulevard - 0.6 mgd *The Police Training Center on Price
Boulevard - 0.1 mgd *The Sembler Development and Butler Park - 0.7 mgd *Existing Residential and Commercial
Areas along Pan American Boulevard - 0.2 mgd Demands by these new customers will serve to increase reclaimed
water use by nearly 1.6 million gallons per day (mgd).
021 - Manasota Basin 251
N084
City of North Port Reuse Storage Tank and High Service Pump
Station
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,054,302 0 0 101,250 0 953,052
Project Funds Not Budgeted by the
District
City of North Port 1,051,250 0 0 101,250 0 950,000
$2,105,552 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Start Construction Storage Tank 7/1/08 7/1/08
Complete Construction Storage Tank 3/31/09 4/30/09
Start Pump Station Design 3/31/09 4/10/09
Complete Pump Station Design 7/15/09 8/19/09
Start Construction Pump Station 10/1/09 10/1/09
Complete Construction of Pump Station 12/31/09 5/31/10
Agreement Terminated 6/30/10
Status As Of: February 24, 2010
The District received the project scope of work from the City on December 11, 2008. A draft of the agreement was sent
to the City for review on December 31, 2008. The City's comments have been incorporated into the draft agreement. The
agreement was executed February 19, 2009. The construction of the storage tank started July 1, 2008 and was
completed April 2009. The design of the pump station started April 10, 2009 and was completed August 19, 2009. The
City has the contractor, that is currently upgrading the WWTP, constructing the pump station to reduce costs by
eliminating mobilization and demobilization costs. The pump station was scheduled to start October 1, 2009 and be
complete by December 31, 2009, however, the pump is delayed and won't be delivered until May 2010. The City has
requested the "Complete Construction of the Pump Station" date be changed to May 31, 2010. The District budgeted
$101,250 in FY2009 and budgeted $950,000 in FY2010 for a total funding commitment of $1,051,250. To date, $661,701
has been reimbursed.
021 - Manasota Basin 252
N107
Braden River Soil Moisture Sensor Rebate Program
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Conservation
Basin(s) Manasota
Bradenton River Utilities, Braden River UtilitiesCooperator(s)
Project Manager MUSICARO, MELISSA
Task Manager(s)
Status Ongoing
DescriptionThe project consists of providing rebates for the installation of up to 400 soil moisture sensor (SMS) devices to control
irrigation for existing and new residential and non-residential customers in the Lakewood Ranch Development. The
project objective is to reduce irrigation water use and conserve water resources. Braden River Utilities will monitor the
water use and savings for the participating homes, and compare it to that of non-participating homes as part of the
project evaluation to determine water savings. The project will include rebates of up to $495 for eligible customers for
the installation of SMS systems. The utility will administer the program and implement the following measures: work
with homeowners and businesses to install SMS systems, install master meters on 2 subdivisions irrigation mains to
track water use, and use of the Field Guide to Soil Moisture Sensor Use in Florida. BRU will work with the local
Manatee Extension Service office to conduct follow up inspections for the installed SMS devices. Manatee County
Extension will also monitor and document the condition of the landscapes.
BenefitsThe water savings benefit is to be determined.
Costs
The total project cost is $200,000, and the Manasota Basin Board approved funding in the amount $100,000 in
FY2009. The cost benefit is to be determined.
Additional Information
BRU proposed this project as a means to save water, as well as to evaluate this method of water conservation for
potential implementation in future development in Lakewood Ranch. District and BRU staff have refined project scope
details to ensure information about water use of project participants can be compared to water use of non-participants
to help both BRU and the District make decisions about promoting the use of soil moisture sensors. The number of
project participants may be reduced since the District is solely funding the water meter for monitoring the
non-participating homes.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 105,639 0 0 100,125 2,773 2,741
Project Funds Not Budgeted by the
District
Braden River Utilities 100,000 0 0 100,000 0 0
$205,639 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Draft Agreement to Contracts Administration 8/3/09 8/11/09
Draft Agreement returned from Contracts Administration 9/30/09 9/23/09
Contract Executed 1/15/10
Notice to Proceed 1/15/10
021 - Manasota Basin 253
N107
Braden River Soil Moisture Sensor Rebate Program
Sensor Installation Commence 1/31/10
Sensor Installation Complete 11/30/11
Data Collection Evaluation Complete 11/30/12
Contract Termination 12/31/13
Status As Of: December 08, 2009
The agreement has been drafted and the District project manager and cooperator have finalized the scope of work.
Critical elements with the scope of work have been negotiated and resolved. The draft scope includes customer surveys
at the completion of the project to gauge customer satisfaction with the devices and the overall project. District staff
asked the City to request a letter from Manatee County Extension, with Manatee County Extension accepting the
responsibility of completing certain project tasks. The scope tasks Manatee County Extension Service with the following:
conduct follow-up inspections of landscapes, confirm proper installation of soil moisture sensors, conduct educational
workshop for participants. District staff received the the letter mentioned above. The agreement is anticipated to be
executed by January 31, 2010.
021 - Manasota Basin 254
N115
Manatee County Indoor Water Conservation Project
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
MCGOOKEY, SCOTTTask Manager(s)
Status Ongoing
DescriptionThis project consists of offering financial incentives to single-family, multi-family, and commercial customers for
replacing conventional toilets (3.5 gallons per flush or greater) with water-conserving equivalents. This project will
target the replacement of approximately 900 conventional toilets with ultra-low volume (ULV) toilets, which use up to
1.6 gallons per flush (gpf) or High Efficiency Toilets (HET's) that use up to 1.28 gpf. The project will provide rebates for
toilets at $100 per fixture with a maximum of two toilets per unit. This proposed project is the third phase to the
Manatee County Indoor Water Conservation Project originally funded in FY2007.
BenefitsThis FY2009 project is estimated to save 20,079 gallons per day (gpd), or 7,328,835 gallons per year.
Costs
The total project cost is $126,144. The Manasota Basin Board has funded 50 percent, or $63,072, in FY2009.
Manatee County's share is $63,072. The cost amortized at 8 percent over 20 years, is $1.46 per thousand gallons.
The savings is calculated using a weighted average due to the varying life expectancies of the different water saving
equipment.
Additional Information
Manatee County currently services over 90,000 potable water accounts and anticipates continued growth over the
next 20 years. This program is an indoor conservation component to Manatee County's existing Water Conservation
Incentive Program for the County's retail water customers. The program also addresses the Manatee County Board of
County Commissioner's policies on water conservation and is supported by the Utilities recent development of a
conservation based tiered rate structure for potable water. One year of account-level metered water-use data prior to
and one year of metered water use after the retrofit installation will be collected as the raw data for the final savings
analysis. Manatee County Utilities will provide actual billing data and ensure 100 percent fixture inspection. This
project will also institute an educational program designed to assist customers in long-term maintenance related to
water savings, such as selecting parts for repairs, leak detection and choosing proper replacement flapper models for
their HET or ULV toilets. This effort will ensure the retrofit fixture will remain a water-conserving fixture for its
life-expectancy. Bi-monthly status reports will be provided to the District to update project accomplishments.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 72,467 0 0 64,792 2,309 5,366
Project Funds Not Budgeted by the
District
Manatee County 63,072 0 0 63,072 0 0
$135,539 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Execute Agreement 5/1/09 5/1/09
021 - Manasota Basin 255
N115
Manatee County Indoor Water Conservation Project
Start Rebates 5/18/09 5/15/09
Final Distribution report 8/31/10
Final Report 9/30/11
Final Invoice 9/30/11
Project Complete 1/31/12
Status As Of: February 22, 2010
The agreement was executed May 1, 2009 and the project started May 15, 2009. The County has issued 1,094 toilet
rebates by the end of November 2009. The County has met the agreeded amount of 900 toilet rebates. The County will
continue to process rebates at it's own expense. The County reguested it's first reimbursement September 15, 2009. The
second and final invoice was processed for payment by the District on January 28, 2010. The final distribution report is
under development. To date, the District has reimbursed $62,398.09 of the $63,072 budgeted for this project. The
balance of $673.91 funded program promotion and surveys.
021 - Manasota Basin 256
N139
Low Impact Development Manual
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager ZAJAC, CHRIS
Task Manager(s)
Status Ongoing
DescriptionThis project will expand upon an existing Low Impact Development (LID) manual that was created in 2008 by Sarasota
County. LID is a sustainable stormwater management strategy that is gaining wide acceptance in order to meet
regulatory compliance. The Sarasota County Comprehensive Plan states that the County shall provide design
standards for LID measures to mitigate the effect of impervious surfaces and stormwater pollutants on increased
runoff volumes. LID design measures may include, but are not limited to, bioretention areas, porous pavement, roof
gardens, rainwater/stormwater recycling, etc. To initiate the effort, Sarasota County contracted with the engineering
firm of Jones Edmonds and Associates, Inc. (JEA) to complete an assessment of possible LID techniques that may be
effective in Sarasota County. In September 2007, the assessment was completed and focused on three main
categories (1) practices that promote infiltration, (2) non-structural practices that help minimize or control runoff
generation, and (3) practices that promote reuse. The County has developed a design standards manual specific to
the Sarasota County area. The manual was completed in September 2008 and includes design specifications,
construction requirements, potential pollutants to be removed, and site limitations for four techniques; detention with
biofiltration, pervious pavements, stormwater reuse, and greenroofs. The County is currently expanding the manual by
adding two new sections on bioretention for high water table conditions and cisterns for rainwater harvesting. The
County requested cooperative funding in FY2010 to add three more sections to the manual. The new sections will
include vegetated filter strips, soil amendments and tree box planters.
BenefitsThe technologies promoted in the manual will reduce potable water use needed to support landscapes by using
cisterns, rain barrels and rain gardens. These technologies will also protect natural systems by reducing the load of
non-point source pollutants and reduce runoff entering receiving waterbodies while promoting recharge to the aquifer.
Costs
The total project cost is $130,000. In FY2010 the Manasota Basin Board will fund $65,000 while the cooperator will
match $65,000. The District funding amounts shown in the table include staff salary, travel and central garage
charges.
Additional Information
The District's Strategic Program Office Department has been involved in the development of the LID manual and has
provided training to District and County staff. The first training was held on December 19, 2008 and the second on
January 30, 2009. The District is currently developing a spreadsheet tool to assist with permitting the LID technologies
included in the manual.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 71,937 0 0 0 3,085 68,852
Project Funds Not Budgeted by the
District
Sarasota County 65,000 0 0 0 0 65,000
$136,937 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 257
N139
Low Impact Development Manual
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionDevelop Scope of Work 8/15/09 8/13/09
Draft Agreement to Cooperator 9/1/09 8/13/09
Execute Contract 10/31/09
2. Project TasksSelect Contractor 1/31/10
Draft Final Report 6/15/10
Final Report 7/15/10
Status As Of: February 17, 2010
The cooperator was sent an electronic copy of the draft agreement for review on August 13, 2009. The cooperator
approved the draft agreement. The agreement was sent to the cooperator for execution on December 17, 2009. The
agreement will be presented to the Sarasota Board of County Commissioners at their February meeting for approval.
021 - Manasota Basin 258
N188
City of Bradenton NAVD88 Vertical Control Densification
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality ConservationWater Supply Regional Water Supply PlanningNatural Systems Minimum Flows and Level Establishment and MonitoringFlood Protection Floodplain Management
Basin(s) Manasota
City of BradentonCooperator(s)
Project Manager OWENS, JIM
Task Manager(s)
Status Ongoing
DescriptionThe establishment of an accurate and easily accessible vertical control survey network is an important component in
the development of updated Federal Emergency Management Agency Flood Insurance Rate Maps (FEMA FIRM). The
District, in cooperation with the National Geodetic Survey and the Florida Department of Environmental Protection, has
completed the Distict-wide vertical control densification. This project will further enhance the existing vertical control
network to support FEMA FIRM mapping, topographic data collection and modeling activities. The newly-established
vertical control network will allow the District and local governments to transition from the older and less accurate
vertical control survey network known as the National Geodetic Vertical Datum of 1929 to the more accurate North
American Vertical Datum of 1988 (NAVD88) system. In the City of Bradenton this includes running level loops and
establishing bench marks based on NAVD88 along city roadways. This project will enable the surveying community to
make an orderly transition to NAVD88 and will allow the City of Bradenton to be on the same vertical datum as the
District and to comply with the federal surveying and mapping requirements. This project will densify the NAVD88
vertical control in the City of Bradenton and will compliment the District's NAVD88 migration project. The City of
Bradenton will coordinate all vertical control surveying with Manatee County (N151).
BenefitsDensification of benchmarks will support the development of Watershed Management Plans for Polk County thus
contributing to flood protection, natural systems, water quality and water supply. The City of Bradenton participates in
the National Flood Insurance Program administered by FEMA and requires that all finished floor elevations be above
the 100 year floodplain. This project is a key component in meeting this requirement. Also, the establishment and
implementation of the NAVD 1988 will enable more accurate elevations and mapping throughout the District, and the
conversion to the modern vertical datum will allow the ability to establish accurate and reliable elevations using Global
Positioning System (GPS) technology.
Costs
Total cost for contractual services in FY2010 is $136,600 of which the District's share is $68,300. The City of
Bradenton will contribute $68,300. The District's share of funding for this project is within the Manasota Basin.
Additional costs are associated with staff time required to manage the project.
Additional Information
This project will be administered by the City of Bradenton. The vertical control network survey work will be completed
by qualified professional surveying and mapping consultants. All newly-established vertical control network data
produced by this project will be made available through Internet access via LABINS web site and the Manatee County
web site.
021 - Manasota Basin 259
N188
City of Bradenton NAVD88 Vertical Control Densification
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 70,249 0 0 0 0 70,249
Project Funds Not Budgeted by the
District
City of Bradenton 68,300 0 0 0 0 68,300
$138,549 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
150 daysExecute Cooperative Agreement between the County and the District 12/31/09 2/26/10
180 daysExecute Contract with the Consultants 2/1/10 3/26/10
30 daysInitial Project Planning and Develop the Scope of Work 9/1/09 11/9/09
420 daysFinal deliverables 9/30/10
60 daysSubmit cooperative agreement for approval 10/1/09 10/16/09 11/13/09
Status As Of: March 17, 2010
The District project manager and the City project manager completed the final scope of work and the agreement was
submitted for District review and approval on 11/30/2009, the agreement was sent to the City for approval on 1/12/2010.
The City approved and sign the agreement on 2/24/2010. The District executed the agreement on March 12, 2010.
Florida Initiative ACTION-TO-DATE comment: project is proceeding on time.
021 - Manasota Basin 260
N218
Englewood Reclaimed Water Supply Project
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality ConservationWater Supply Alternative Water Supply
Basin(s) Peace River, Manasota
Englewood Water DistrictCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis project consists of the design and construction of a supplemental reclaimed water supply well and the
modification of the intake structure at the onsite reuse pond at the Englewood WRF to provide additional dry weather
irrigation supplies. Reclaimed water is produced at the Englewood WRF, which serves portions of Charlotte and
Sarasota counties. Current reclaimed water storage includes a 1 MG above ground storage tank, wet weather storage
ponds (onsite and offsite), and a fully permitted ASR system. The ASR well provides 0.5 mgd of reclaimed water
during peak demand periods and has become a critical component of the reuse system. Without previous SWFWMD
funding assistance for the ASR program, EWD reuse would not be as efficient and connection of many current
customers would not have been possible. Installing an additional supply well into the ASR storage zone will increase
the rate at which stored water can be recovered during peak demand. A well approximately 600 feet in depth is
required, along with a pump and appurtenances to produce an additional 0.5 mgd, or about 15 mg of water during
each peak month used. Re-engineering the onsite wet weather pond will more effectively utilize available storage and
freshwater in the surficial aquifer at the WRF. Lowering the pump intake from the existing pond will provide additional
water for irrigation. Reuse demands during dry weather periods often exceed the available supply. This project will
provide additional reuse supply to existing customers during peak demand periods. These customers include Lemon
Bay Golf, Oyster Creek Golf, and Rotunda West Utilities in Charlotte County and Myakka Pines Golf, Englewood
Sports Park, Boca Royale Golf, and Gran Paradiso Subdivision in Sarasota County.
BenefitsThe project will provide approximately 82,192 gpd of additional reuse supply that will be used evenly between the
identified customers in Charlotte and Sarasota Counties. This project will offset approximately 61,644 gpd. The
cost/benefit ratio for the total estimated project cost of $260,000 averaging 61,644 gpd using an 8% annual interest
rate amortized over 30 years is $1.02/1000 gallons.
Costs
The total cost of the project is estimated at $260,000. Since the benefits are evenly split between customers in the
Peace and Manasota Basins, EWD is requesting $65,000 from each Basin Board for a total of $130,000 (50%) in
FY2010 funding. Design costs are estimated at $60,000 and construction at $200,000.
Additional Information
Without previous SWFWMD funding assistance for the ASR program, EWD reuse would not be as efficient and
connection of many current customers would not have been possible. This project will further increase this efficiency
and help EWD meet existing contracted amounts. EWD won the 2008 FWEA David York Award for small facilities (<
5 mgd), another example of the benefits that the previous funding assistance has had. Reuse demands during dry
weather periods often exceed the available supply. Additional reuse customers have been identified but the ability to
serve these users during peak demand periods will be problematic without additional supplemental sources. With the
lack of available fresh groundwater or surface water EWD is faced with developing alternative supplemental sources.
Supplemental sources currently identified include the following: Installing an additional supply well into the ASR
storage zone to increase the rate at which stored water can be recovered. A well approximately 600 feet in depth is
required, along with a pump and appurtenances to produce an additional 0.5 mgd, or about 15 mg of water during
each peak month used. Re-engineering the onsite wet weather pond to more effectively utilize available storage and
freshwater in the surficial aquifer at the WRF. Lowering the pump intake from the existing pond will provide additional
water for golf course irrigation to Lemon Bay Golf Course, and may allow EWD to add other golf course storage ponds
to be supplied from this pond. EWD advertises and helps enforce the District's watering restrictions, aids in
xeriscaping education, and have imposed a steep graduated rate structure to discourage high water usage. The EWD
has a policy requiring any new significant development desiring utilities to include a reclaimed water irrigation system
in its infrastructure. EWD's reuse customers are conservation minded and only use the water deemed necessary to
adequately maintain the irrigated area.
021 - Manasota Basin 261
N218
Englewood Reclaimed Water Supply Project
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 65,000 0 0 0 0 65,000
021 Manasota Basin 70,435 0 0 0 2,358 68,077
Project Funds Not Budgeted by the
District
Englewood Water District 130,000 0 0 0 0 130,000
$265,435 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Execute Agreement 11/30/09 11/9/09
Start Design and Permitting 1/29/10 1/8/10
Complete Design and Permitting 7/1/10
Start Construction of Well & Intake Structure 12/31/10
Complet Well Installation 4/1/11
Complete Re-engineering Onsite Pond 5/1/11
Status As Of: February 18, 2010
The agreement between the District and EWD was executed November 9, 2009. The Task Order with the consultant,
ASRUS was executed on the January 8, 2010 by the EWD Board. The design and permitting kick-off meeting was held
on January 29, 2010. To date, the District has reimbursed the EWD $0 of the $130,000 available.
021 - Manasota Basin 262
N231
Manatee County Toilet Rebate Project - Phase IV
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Supply Alternative Water Supply
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Ongoing
DescriptionThis Ultra Low-Flow Toilet Rebate (ULFT) incentive program is for the County's retail water customers (residential,
multi-family, and commercial). The County currently services over 90,000 potable water accounts and anticipates
continued growth over the next 20 years. The objectives of this retrofit program are to reduce water demand and
provide financial incentives for the replacement of an estimated 900 toilets. This program addresses the Manatee
County Board of County Commissioners policies on water conservation and is supported by the recently increased
Water Conservation Rates for potable water use. Any retail water customer who agrees to replace a 3.5 gal or more
toilet with a ultra-low flush (ULF) that uses 1.6 gallons per flush (gpf) or less and/or High Efficiency Toilets (HET), will
receive a $100.00 rebate for each toilet (maximum of two (2) toilets per unit). This project will also focus on educating
the new low volume toilet users on the proper maintenance, specifically flappers and leak detection, necessary to
ensure that each toilet remains a water conserving fixture. Rebate payments are subject to the recipient's submittal of
the completed application, documented cost, and will be distributed upon inspection of the completed installation and
verification that the old toilet is ready for disposal.
BenefitsThe estimated total water saving for this project is 21,425 gpd.
Costs
The total cost for this project is estimated to be $126,144. The cost/benefit is $1.62 per k/gallons, assuming a 20-year
life. The County has requested $63,072 (fifty percent) from the Manasota Basin Board in FY2010.
Additional Information
This incentive program is an enhancement to the County's existing Water Conservation Program. The program
includes existing metering and loss reduction programs, water conserving rate sturctures, urban and agricultural
reclaimed water irrigation supply (with the metering of all users and consumption based billing for all new users),
public education, Florida Friendly based landscape codes, SWUCA based level of service for water supply at 110
gpfcpd, land development codes requiring non-potable sources for irrigation in new development, water supply
protection ordinances, and the use of aquifer storage and recovery for both potable and reclaimed water.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 68,507 0 0 0 2,358 66,149
Project Funds Not Budgeted by the
District
Manatee County 63,072 0 0 0 0 63,072
$131,579 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Agreement Executed 3/12/10
021 - Manasota Basin 263
N231
Manatee County Toilet Rebate Project - Phase IV
Begin Rebate Program 5/1/10
Complete Rebate Program 5/31/11
Final Report 9/14/12
Status As Of: February 19, 2010
The CFI agreement has been drafted by District staff and Manatee County has reviewed and provided comments. The
processing of the agreement is complete and has been sent to the County for signature.
021 - Manasota Basin 264
L019
Sarasota - Update W. Para. & County maintained models
Project Type Cooperative Funding
AORs Strategic InitiativesFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager TURNER, DAWN
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a High priority. Completing elements of the District's Watershed Management Program is a District Strategic
Priority for managing the water resource, and providing information to local governments to address land use changes
and stormwater management within a specific watershed. A senior administrator has provided confirmation that the
city will budget the project for FY2010 funding.
DescriptionThis is a multi-year funded project to perform Digital Topographic Information, Watershed Evaluation, Watershed
Management Plan, and Maintenance of Watershed Parameters and Models elements of the District's Watershed
Management Program (WMP) for multiple watersheds within Sarasota County. The county's area is approximately 570
square miles and includes 28 watersheds. The Topographic Information, Watershed Evaluation and Management
Plan elements were completed by the cooperator for 18 watersheds before implementation of the District's Watershed
Management Program Guidelines and Specifications (G&S). This project involves the Maintenance of Watershed
Parameters and Models to the District's G&S where the Topographic Information, Watershed Evaluation and Plan will
reflect the changes in the watershed due to land alterations approved through County and District permitting. Tthe
County wishes to perform maintenance of the watershed parameters and model(s) to reflect approved County capital
improvement projects (CIPs) and developments 35 acres or greater in size or with 8 acres or more of proposed
impervious cover.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain management and water quality management. The continuous maintenance of watershed
parameters in the GIS database as land alterations are made and permits are approved will provide the most up to
date information about the watershed.
Costs
The total budget amount for this project varies by year depending on the County's anticipated need for maintenance of
the watershed parameters and models. For FY2005, the District and County each funded $356,666 to perform
updates to the Little Sarasota Bay watershed and Dona Bay watershed models and perform maintenance. For
FY2007, the District share is $356,666 and will be funded entirely by the Manasota Basin. The County will contribute
$766,667. For FY2008, the total maintenance budget is $400,000 with the Manasota Basin and County each
contributing $200,000. $400,000 ($200,00 District's share) was also approved for FY2009. However, in November
2008, the County notified District staff they will not accept the FY2009 funds. Instead, they continued the project with
funds remaining from previous years. For FY2010, the total maintenance budget is $400,000 with the Manasota Basin
and County each contributing $200,000. For FY2011, $400,000 ($200,000 District's share) has been requested.
Annual funding requests and ranking will be required to continue maintenance of watershed parameters and the
models. The District funding amounts shown in the table include staff salaries. The future funds identified for the
project are contingent upon approval of such amounts by the Manasota Basin Board in the annual budget.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan (develop and update), 4) Implementation of Best Management Practices, and 5) Maintenance of
Watershed Parameters and Models. Implementing elements of the WMP with local governments is one of the
District's Strategic Priorities. The County completed Watershed Management Plans for 18 watersheds throughout
1999-2002. The update process began in FY2003 with the update of the Whitaker Bayou Watershed Management
Plan (see K872). Approved funds for both the Whitaker Bayou Watershed Management Plan and the Myakka River
Watershed Management Plan (K487) are reflected in the prior funding below. The FY2004 funding amount includes
021 - Manasota Basin 265
L019
Sarasota - Update W. Para. & County maintained models
the costs to develop digital topographic information for the entire county using LiDAR technology, to update portions of
the existing models to the District's G+S, and to maintain the models. Development of the topographic information and
the model updates will be performed in conjunction with the FEMA Map Modernization project for Sarasota County
(see M115). District FY2004 funds were used to develop the topographic information, approximately $1,079,500 of the
$2,000,000 in FEMA funds from the M115 project are going towards updating the models and flood insurance rate
maps, and Sarasota County's FY2004 funds were used to incorporate recent County CIP and private developments
greater than 35 acres in size or with more than 8 acres of proposed impervious cover. With FY2005 funding the model
updates in association with the FEMA Map Modernization project (M115) are continuing, additional coastal areas are
being added into the models. With FY2007 funds maintenance will continue to update additional watersheds to the
District's G+S. FY2008 fand FY2010 funding will support maintenance activities. A cooperative funding expenditure
agreement with the County, or a contract amendment, as appropriate, will be developed each year contingent on the
approval of funding. A cooperative funding request will be required from the County each fiscal year. The County will
manage the update and maintenance of the models, where the District's project manager must approve any
agreements to accomplish project tasks.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 3,449,524 400,000 0 2,641,795 202,644 205,085
District Budgeted - Outside Revenue
FEMA Coop Tech Partner Agreemnt 1,079,500 0 0 1,079,500 0 0
Project Funds Not Budgeted by the
District
Sarasota County 4,148,333 0 0 3,748,333 200,000 200,000
$8,677,357 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesReference Project M115 for milestones for FY2004 funding 12/31/04
Recognition of District, Basin Board, County on reports 12/31/09
2. FY2005 Cooperative Funding AgreementAgreement to Management Services 1/30/05 1/18/05
Negotiate FY2005 Cooperative Funding Agreement with County 4/1/05 11/7/05
Board of County Commissioners Approval 3/21/06 4/11/06
Contract Execution 5/15/06 5/4/06
Notice to Proceed 5/15/06 5/4/06
Contract Termination 6/30/08 6/30/09
3. FY2007 Cooperative Funding AgreementNegotiate FY2007 Cooperative Funding Agreement 8/1/07 7/30/07
FY2007 Agreement to Management Services 8/1/07 8/1/07
Board of County Commissioners Approval 9/30/07 9/25/07
Contract Execution 10/15/07 10/23/07
Submit Requisition for FY2008 Funding 11/9/07 1/25/08
Contract Termination 12/31/09
3. FY2007 Cooperative Funding AgreementFirst Amendment to Management Services 9/30/08 1/8/09
County Commission Approval of 1st Amendment 12/1/08 2/11/09
Execute First Amendment 12/31/08 2/19/09
4. FY2010 Cooperative Funding Agreement
021 - Manasota Basin 266
L019
Sarasota - Update W. Para. & County maintained models
Agreement to Management Services 12/9/09 12/9/09
County Commission Approval of Agreement 4/15/10
Execute FY2010 Agreement 4/30/10
Status As Of: February 22, 2010
Reference project M115 for status of topographic information and model updates performed by the District with FY2004
funding. Both the Manasota Basin Board and Governing Board approved changing the management of the FY2004
funds from the County to the District, using the $420,000 in Basin Board funds to update Watershed Management Plans
in conjunction with the FEMA Map Modernization project, and using FEMA funds to serve as the match for the Basin
Board's FY2004 funds. Cooperative Funding Agreement 06C00000087 encumbers FY2005 and FY2006 funds
($713,332 total, $356,666 District's share). Under the agreement two coastal areas that were not previously studied will
be incorporated into the appropriate watershed models. Because the County's existing watershed models were
developed prior to the District's WMP G&S, staff has had to negotiate a compromise on how the G&S will be satisfied. In
addition, seventeen recent developments will be incorporated into existing watershed models as routine maintenance
activities. The agreement and associated documents were approved by the Sarasota BOCC on April 11, 2006, and were
executed by the District on May 4, 2006. A Second Agreement, No. 07C00000105 was executed, and encumbers
FY2007 and FY2008 funds ($356,666 and $200,000 respectively). The First Amendment to Agreement #07C00000105
was executed to expand the scope of work to include updates to the Upper Myakka River/Howard Creek and Lower
Myakka River watersheds. In 2007, the Florida Department of Emergency Management (FDEM) obtained LiDAR
topographic data for the coastal portion of the County. Consequently, Agreement 07C00000105 includes the
development of LiDAR topographic data for the rest of the County, which has come to be called the "Buy-Up" area. Both
the FDEM data and the LiDAR data for the Buy-Up area were scheduled to be complete in January 2008. The LiDAR
data for both areas was only recently delivered (August 2008), 8 months after the anticipated delivery date. The LiDAR
data was finally approved for use on October 10, 2008. Please refer to M115 for further information regarding the
resulting impacts to the Sarasota Map Modernization project schedule. Current Status: The maintenance reports
associated with the a number of developments have been submitted related to the cooperative agreement using FY2005
funds. Project status meetings have been held with the County's consultants regarding the updates being performed for
Little Sarasota Bay and Dona Bay. The County's consultants are completing the Watershed Evaluation element for their
respective basin areas. In addition, funding will also be allocated for maintenance activities associated with CIPs and
approved developments and to update the existing models based on comments provided by the District, County, and/or
FEMA during the review of the preliminary FIRMs for Sarasota County. For Agreement #06C00000087, a total of
$345,341 of the $356,000 in District funds has been invoiced and paid. The First Amendment to the Agreement
06C00000087 extended the contract expiration date from June 30, 2008 to June 30, 2009. The second Agreement
(Agreement #07C00000105) encumbers FY2007 funds, ($356,666), & FY2008 funds, ($200,000). The First Amendment
to Agreement 07C00000105 was executed to add the Upper and Lower Myakka River watersheds to the list of County
watershed models that may be updated. County staff notified the District they will not have the matching funds for this
project in FY2009. Therefore, the FY2009 funding ($400,000 total, $200,000 District share) has not been added to the
Agreement. Aerial mapping of the portion of the County not covered by the State of Florida Department of Emergency
Management's LiDAR mapping project has been completed to support maintenance. However, delivery of the final
LiDAR topographic information was delayed over 10 months. For Agreement # 07C00000105, a total of $374,572 of the
$556,666 in District funds has been invoiced and paid.
021 - Manasota Basin 267
L238
SEC Southern Coastal Watershed Education
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementWater Supply ConservationNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Science and Environment Council of SarasotaCooperator(s)
Project Manager STERNBERGER, VIRGINIA
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a high priority. This program educates decision-makers and the general public in Sarasota County about the
health, productivity and vitality of natural systems, stormwater capacity, water supply, wastewater treatment and
land-use patterns. The SEC has more than 20 member organizations with a combined total of 300,000 annual visitors.
It is estimated that 181,700 visitors will benefit from this project. SEC plans to continue leveraging the collaborative
strength of its members to convene policy discussions and enhance public understanding about science-based
watershed issues. This project will produce high quality deliverables and effectively raise the awareness and
knowledge of watershed issues to a large audience. In FY2011, SEC plans to build on previous initiatives created for
the Watershed Community Leadership and Education Program (2005-2010). The Manasota Basin Board prioritized
watershed planning and education with science-based organizations within the basin. The proposed project meets
both of these priorities.
DescriptionThis Cooperative Funding Initiative project is a continuation of the SEC program designed to work collaboratively with
its members to convene policy discussions and enhance public understanding about water and watershed
conservation based on science. The FY2011 program components include two decision-maker and policymaker
workshops on water and low-impact development (LID). The first workshop will identify local water and LID issues. The
second will refine and come to a consensus on solutions. The SEC also plans to enhance the general public's
understanding of watersheds by producing four three-minute videos focusing on outdoor experiences. The videos will
provide ideas for nature-based activities and explain the connection people have to the health of their watershed. The
videos will be shown on the Discover Natural Sarasota and on select SEC member web sites. Adding to mobile phone
messages created in FY2009, SEC plans to create five additional messages to provide up-to-date information
about watershed issues. Lastly, the SEC will again coordinate a Watershed Awareness Week in Sarasota County. The
program was developed by SEC to enhance the general public's understanding of watersheds in Sarasota County and
to show how their actions as stewards can help protect water resources. Evaluation will be conducted by SEC member
organizations and will include surveys, attendance statistics, number of website hits, an assessment of visitor
comments (written and voice), and number of promotional brochures distributed.
BenefitsThis program educates 181,700 residents on how productivity and vitality of natural systems, storm water, water
supply, wastewater and land use impact the watershed. The proposed program will build on previously successful
education components to engage discussion between decision-makers and policymakers on water use and LID and
enhance the public's understanding of how they affect the watershed in Sarasota County.
Costs
The total proposed cost of the FY2011 project is $120,000, with the District requested to contribute $60,000
(Manasota). SEC's match is in-kind services from its member organizations. District funds will pay for implementing a
two-part workshop, creating four three-minute video for web site posting, producing five mobile phone audio
messages and coordinating Watershed Awareness Week in Sarasota County. The program is expected to reach
181,700 residents at a cost to the District of $.33 per person, well below average for public education programs. The
budget lines below include costs for staff to manage the project.
Additional Information
The FY2010 total project cost was $120,000, with the District contributing $60,000 (Manasota). District funding was
used to develop a two-part decision makers workshop, a 20-minute video and Watershed Awareness Week. The
project reached 181,700 residents at a cost to the District of $.33 per resident.
021 - Manasota Basin 268
L238
SEC Southern Coastal Watershed Education
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 3,300 0 0 3,300 0 0
021 Manasota Basin 270,817 0 0 146,563 62,162 62,092
Project Funds Not Budgeted by the
District
Science and Environment Council of
Sarasota County
279,000 0 0 159,000 60,000 60,000
$553,117 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2008 Budgeted FundsInitiate purchase order 10/1/07 1/14/07 1/14/07
Outdoor interpretive signs complete 10/15/08 10/15/08
Indoor educational kiosk panels complete 10/15/08 10/15/08
Educational brochures complete 10/15/08 10/15/08
Watershed Awareness Week talk-back boards 10/31/08 11/28/08 11/7/08
Watershed Awareness Week 10/31/08 11/28/08 11/7/08
FY2009 Budgeted FundsInitiate purchase order 10/1/08 2/27/09 2/27/09
Outdoor interpretive signs installed 9/30/09
Mobile messages complete 9/30/09 7/31/09
Brochure complete 9/30/09
Decision-makers workshop 9/30/09 6/5/09
Watershed Awareness Week talk-back boards 10/30/09
Watershed Awareness Week 10/30/09 10/30/09 10/30/09
Project close 10/30/09 10/30/09
FY2010 Budgeted FundsInitiate purchase order 10/1/09 11/30/09 11/30/09
Decision-makers workshop complete 6/30/10
Video complete 9/30/10
Watershed Awareness Week 10/25/10
Project close 10/31/10
FY2011 Budgeted fundsInitiate purchase order 10/29/10
Decision-makers workshop 6/30/11
Five mobile phone messages complete 9/1/11
Four short videos complete 9/1/11
Project close 11/30/11
Watershed Awareness Week 11/30/11
Status As Of: February 17, 2010
ACTION TO DATE: On time. The script for the 20-minute video is being created and a draft will be submitted to staff
before March. Participating SEC organizations include Sarasota Bay Estuary Program, G. WIZ, Selby Gardens, New
College, Mote, Sarasota County, Myakka River State Park, Historic Spanish Point, Conservation Foundation fo the Gulf
Coast and Oscar Scherer State Park. Topics will include sea grass, water quality indicators, stormwater runoff, habitat
preservation, importance of mangroves, land conservation. Two decision-makers workshops are tentatively scheduled
for spring. In FY2009, a series of mobile phone messages were created to provide watershed messages to callers. A
021 - Manasota Basin 269
L238
SEC Southern Coastal Watershed Education
recent report indicated that from 7/2009 through 2/2010 a total of 668 calls were received lasting an average of 3 minutes
each.
021 - Manasota Basin 270
L520
Around the Bend Nature Tours Manatee/Sarasota
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality ConservationNatural Systems Natural Systems Identification and Monitoring
Basin(s) Peace River, Manasota
Around the Bend Nature ToursCooperator(s)
Project Manager TORRUSIO, MARY
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as high priority. This program successfully educates 2,040 public, private and homeschool students and
teachers in grades kindergarten through 12 about watersheds and natural systems through guided tours in the
Manasota Basin. Education has been named as one of the priorities of the Manasota Basin Board, which makes the
project relevant to District goals and objectives. Cooperator has a long history with the District and is well-versed in
Florida's standards-based education guidelines. Additionally the project complements the District's Get Outside!
campaign by using District lands when possible in field excursions. Pre- and post-vist student activities are also
incorporated into the program. In FY2009, students demonstrated a 37.5% knowledge gain through the program,
which is higher than the average youth education program pre/posttest learning gain.
DescriptionThis Cooperative Funding Initiative (CFI) project proposes to educate students and adults about local environmental
systems. Around the Bend Nature Tours provides more than 2,000 students and teachers with site-specific programs
that focus on watersheds and include various Manatee and Sarasota County Conservation Lands and SWFWMD
lands (including Emerson Point Park, Riverview Pointe, Rye Wilderness Park, Duette Park or any SWFWMD area that
is deemed appropriate). These environmental education programs benefit students, parents, teachers and
homeschool groups and use Around the Bend Nature Tours guides and materials. The program's effectiveness is
measured through student pre/posttest data and a teacher evaluation tool. Most recent data provided demonstrates a
significant 37.5% increase in knowledge gain.
BenefitsThis program adresses watershed education and natural systems through hands-on field study programs for youth and
adults. Additionally, some field trip sites are on District-owned lands, so promotion of the District's land stewardship
efforts and Get Outside! campaign will be included in the programming. Cooperator has a long history with the District
and is well versed in Florida's standards-based education guidelines. This program also works with many homeschool
groups, a target audience with which the District's youth education staff would like a greater reach.
Costs
The total cost of the FY2011 program is $105,315, with the District requested to contribute $27,840 (Manasota). The
project is projected to reach 2,040 people at a cost to the District of $13.65 per person (approximately 20% lower than
the average youth education programming) and $3.41 per participant contact hour. Budget line below includes cost for
staff to manage the project.
Additional Information
The total cost of the FY2010 program is $76,390, with the total cost to the District $27,940, all of which is requested
from the Manasota Basin. Around the Bend Nature Tours anticipates reaching 2,475 people at a cost to the District of
$11.29 per person. The cost reduction in FY2010 reflects a decrease in the number of District-funded field trips from
50 to 46. Budget lines include cost for staff to manage the project. FY2010 Cooperative Funding Initiative (CFI) project
educated students and adults about local environmental systems. Around the Bend Nature Tours provided more than
2,000 students and teachers with site-specific programs that focused on watersheds and included various Manatee
and Sarasota County Conservation Lands and SWFWMD lands (including Emerson Point Park, Riverview Pointe, Rye
Wilderness Park, Duette Park or any SWFWMD area deemed appropriate). These environmental education programs
benefited students, parents, teachers and homeschool groups and utilized Around the Bend Nature Tours guides and
materials. The program's effectiveness was measured through student pre/posttest data and a teacher evaluation
tool. The District has supported this project since FY2006.
021 - Manasota Basin 271
L520
Around the Bend Nature Tours Manatee/Sarasota
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 17,900 0 0 17,900 0 0
021 Manasota Basin 134,883 0 0 75,855 30,142 28,886
Project Funds Not Budgeted by the
District
Around the Bend Nature Tours 7,100 0 0 3,650 0 3,450
Braden River Middle School 2,000 0 0 2,000 0 0
FL Division of Historical Resources 30,500 0 0 0 0 30,500
Manatee County Conservation Lands 4,500 0 0 4,500 0 0
Pinellas County Environmental Fund 48,550 0 0 48,550 0 0
Sarasota Bay Estuary Program 79,350 0 0 43,500 21,350 14,500
$324,783 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2009 Budgeted FundsPurchase order opened 10/27/08 10/31/08
Field trips end 9/1/09 6/2/09
Final report due to District 9/30/09 6/12/09
FY2010 Budgeted FundsInitiate purchase order 10/1/09 11/16/09
Field trips end 9/1/10
Final report and invoice due to District 9/30/10
FY2011 Budgeted FundsInitiate purchase order 10/1/10
Field trips end 9/1/11
Final report and invoice due to District 9/30/11
Status As Of: February 18, 2010
ACTION TO DATE: On time. To date, cooperator has provided 25 field trips impacting 1,196 students in the Manasota
Basin.
021 - Manasota Basin 272
L618
Sarasota - Watershed Management Plan: Coastal Fringe
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain ManagementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
TURNER, DAWNTask Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a High priority. This project was originally approved by the Manasota Basin Board as a multi-year project to
develop a Watershed Management Plan (WMP) for Sarasota County's Coastal Fringe Watersheds. The request for
funding in FY2011 is to continue to perform the elements of the District's Watershed Management Program.
DescriptionThis multi-year funded project is to perform the: 1) Topographic Information, 2) Watershed Evaluation, and 3)
Watershed Management Plan elements of the District's Watershed Management Program (WMP) for several coastal
watersheds in Sarasota County. Watershed Management Plans will be updated for 1) the North Roberts Bay Coastal
Watershed, 2) the Lemon Bay Coastal Watershed, and 3) portions of the Sarasota Bay, Little Sarasota Bay,
Dona/Roberts Bay Coastal Watersheds. Combined, these Coastal Watershed areas cover approximately 25 square
miles within the County. The only areas excluded from Sarasota's Coastal Fringe are a small portion of the Little
Sarasota Bay Coastal (Vamo Road area) Basin and the Lyons Bay portion of the Dona Bay Coastal Basin, which are
currently being developed under a separate contract. The Coastal Fringe Watershed updates include developing
portions of the Watershed Management Program, as defined by the District, beginning with the North Roberts Bay
Coastal Watershed as Phase 1. The North Roberts Bay Coastal Watershed is approximately 5.9 square miles in the
coastal fringe of the Phillippi Creek and Matheny Creek Basins, including Siesta Key from Midnight Pass to Siesta
Drive. Phase 2 includes the Lemon Bay Coastal Watershed, which is approximately 7.2 square miles, excluding the
area outside of the County. Phase 3 includes portions of the Sarasota Bay, Little Sarasota Bay, Dona/Roberts Bay
Coastal Watersheds. The total area in Phase 3 is approximately 9.2 square miles. These areas currently do not have
the benefit of a Watershed Management Plan.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) with their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies and 2) by providing a geodatabase and projected results from watershed model
simulations for floodplain management and water quality management through the Total Maximum Daily Loads
(TMDL) process for their National Pollution Discharge Elimination System (NPDES) permit requirements.
Costs
The estimated total budget amount for this multi-year project is $1,966,632, of which the District's share is $983,316 to
be funded over several fiscal years. For FY2007, the Manasota Basin Board originally budgeted $500,000 with an
equal match from Sarasota County. However, Sarasota County was only able to fund $246,491 of the original
$500,000. Correspondingly, the District only encumbered $246,491 in FY2007 as part of the cooperative funding
agreement. For FY2008, the Manasota Basin Board budgeted and encumbered $200,000 into the cooperative
agreement. However, because of budget shortfalls, Sarasota County was unable to provide any funding in
FY2008. For FY2009 Sarasota County encumbered $34,422 for project work. The District only budgeted staff time for
FY2009. In FY2010 Sarasota County budgeted $200,00 for project work; the District budgeted $39,031 in FY2010 in
order to reach the same level of funding. For FY2011 the Manasota Basin Board is requested to fund $200,000
with Sarasota County providing an equal match of $200,000. Requests for future funding are anticipated in FY2012.
As each project element is completed the project budget may require refinement based on the information gathered.
The future funds identified for the project are contingent upon approval of such amounts by the Manasota Basin Board
in the annual budget. The District funding amounts shown in the table include staff salaries, travel and central garage
charges.
Additional Information
A WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
021 - Manasota Basin 273
L618
Sarasota - Watershed Management Plan: Coastal Fringe
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies. Future funding will be required in future years in order to complete
development the Watershed Management Plan for the Sarasota Bay Coastal watershed including: survey, GIS data
base development, watershed parameterization, computer modeling, floodplain analysis, and floodplain delineation,
Level of Service (LOS) determination, and BMP Alternative Analysis. A cooperative funding expenditure agreement
with Sarasota County was developed as a multi-year funded project contingent on the approval of future funding to
complete the WMP elements through the Watershed Management Plan. Sarasota County is the lead manager on
the project, where the District's project manager must approve any agreements with consultants to accomplish
project tasks. Future cooperative funding requests and agreements will be required for the Implementation of BMPs
and the Maintenance of Watershed Parameters and Models.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,093,493 136,825 0 711,499 206,138 39,031
Project Funds Not Budgeted by the
District
Sarasota County 680,914 0 0 280,914 200,000 200,000
$1,774,407 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Contract Development & ExecutionDevelop Draft Agreement with Sarasota County 12/20/06 5/25/07 7/1/07
Cooperative Agreement to Contract Administration 1/27/07 7/15/07 7/23/07
Execution of Cooperative Agreement by Sarasota County 3/30/07 6/30/07 8/28/07
Execution of Cooperative Agreement by SWFWMD 5/10/07 9/5/07 9/12/07
Issue Notice to Proceed 5/16/07 9/15/07 9/13/07
Phase 1 - North Roberts BayReceive / Review LiDAR Information 2/10/08 8/31/08 10/30/08
Digital Topographic Information - Start 3/10/08 12/31/08 1/7/09
Watershed Evaluation - Begin 5/10/08 2/25/09 2/25/09
Digital Topographic Information - Approved 7/10/08 3/31/10
Watershed Evaluation - Approved 8/10/08 6/30/10
Watershed Management Plan - Begin 9/10/08 6/30/10
Watershed Management Plan - Approved 12/30/08 4/20/11
Status As Of: February 19, 2010
Currently, deliverables for feature inventory, terrain information and other watershed parameters are complete and have
been delivered for review. Minor corrections and other changes have been forwarded and will be incorporated into
revised versions of the deliverables. ERP files (permits) have been requested for review and developing additional
information on features and elevations. Work continues on the watershed evaluation. Staff is evaluating a request to
combine several coastal sub-basins (for modeling purposes). These include areas that are under the primary influence of
storm surge events and drain directly to the bay.
021 - Manasota Basin 274
N014
The Florida Aquarium Watershed Education Initiative
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality MonitoringWater Supply ConservationNatural Systems Natural Systems Identification and Monitoring
Basin(s) Alafia River, Hillsborough River, Coastal Rivers, Pinellas-Anclote River, Withlacoochee River,
Peace River, Manasota
The Florida Aquarium, Inc.Cooperator(s)
Project Manager HULL, MARY MARGARET
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as High priority. The Florida Aquarium's focus on telling Florida's fresh water story makes this science-based
attraction closely aligned to the District's mission. The Florida Aquarium Watershed Education Initiative proposes to
continue programming that enhances the District's watershed education efforts by providing participants with a better
understanding of Florida's ecology through workshops, hands-on field experiences and stewardship activities. This
project is ranked high because of its alignment to the District's mission; its summer camp program for minority and
at-risk students, which is an audience the District has identified for additional outreach; and its incorporation of multiple
learning approaches providing water education for learning new behaviors and incorporating environmental leadership
skills. Costs are the lowest among proposed youth education programs and quality is confirmed through evaluations
and pre and post tests. Knowledge gain for FY2009 summer camps, for instance, was 25%, which falls within the
preferred range of youth education programming. The proposed program is aligned with Basin Board priorities.
DescriptionThis Cooperative Funding Initiative (CFI) project proposes to educate teachers and students about Florida's water
resources and natural environment. The Florida Aquarium requests support of a water resources education initiative
that focuses on three distinct programs for elementary, middle and high school students and teachers. These
programs are outlined below and include: What's in Your Watershed? summer camp, Science Education at Sea
(SEAS) teacher training program and Regional Ocean Conference for Students (ROCS) workshop for teachers and
students. While the proposed initiative primarily reaches students and teachers throughout Hillsborough County, it also
draws schools from Polk, Pinellas, Pasco and Manatee counties. What's in Your Watershed? is a summer camp
program designed to teach low-income, at-risk upper elementary and middle school students from local YMCAs and
Boys and Girls Clubs in Hillsborough County the importance of the Tampa Bay watershed. The camp would provide an
opportunity for youth to engage in interactive role-playing to learn about watersheds, water quality, water conservation
and habitat protection. Throughout the proposed program, each student takes part in three field explorations within the
Tampa Bay watershed. The What's in Your Watershed? program will be evaluated through a portfolio of student work,
student and parent evaluation of the program using a written survey, instructor evaluation of the program and student
pre/post assessements. SEAS is a teacher education program proposing to provide workshops for elementary, middle
and high school teachers, focusing on estuaries and incorporating the learning objectives of the Florida
Comprehensive Assessment Test. It would allow teachers to explore current and future environmental issues and
challenges facing those resources. The SEAS program evaluation will include a combination of pre/post assessments,
workshop surveys and teacher journals. The proposed ROCS workshop component would give middle and high
school students the opportunity to study several major water quality issues associated with local watersheds. Students
will identify the issues and create action plans that are achievable and beneficial for the environment. SWIM staff
participate in this conference.The ROCS workshop will be evaluated through pre/post assessments. Independent
evaluation by Pandion systems for the ROCS component previously found that 86% of the teachers agreed that the
project was a valuable addition to their student's education.
BenefitsThe cooperator estimates that the FY2011 program will reach 231 students and teachers directly and 7,500 students
indirectly. ROCS will provide an intensive workshop experience for high school students, providing opportunities for
them to learn about local issues and related science and then create action plans that will result in positive
environmental changes within their communities. The FY2011 project proposes a "What's in Your Watershed?"
summer camp that addresses the important priority of getting traditionally underserved, inner-city youth outside
exploring the Tampa Bay watershed. The program will give youth opportunities to explore current environmental issues
and to use critical thinking to develop strategies for addressing impacts on their local watersheds.
Costs
The total cost of the FY2011 project is $43,346 with the District contributing $21,401 (Alafia River $5,136; Hillsborough
021 - Manasota Basin 275
N014
The Florida Aquarium Watershed Education Initiative
River $10,700; Coastal Rivers $1,070; Pinellas-Anclote River $1,285; Withlacoochee River $1,070; Peace River
$1,070; Manasota $1,070). The dollar amount allocated per basin is determined by the number of participants
projected to participate in the programming from each basin. District funding is requested for a summer camp, teacher
training programs and a workshop for teachers and students. The program proposes to reach 231 students and
teachers directly and 7,500 students indirectly at a cost to the District of $2.77 per person and $1.20 per contact hour.
Budget lines below includes costs to manage projects.
Additional Information
The total FY2010 project cost was $44,741, with the District contributing $21,402 (Alafia River $5,174; Hillsborough
River $10,686; Coastal Rivers $1,108; Pinellas-Anclote River $1,109; Withlacoochee River $1,109; Peace River
$1,108; Manasota $1,108). The dollar amount allocated per basin was determined by the number of participants
projected to participate in the programming from each basin. District funding supported a summer camp, teacher
training programs and a workshop for teachers and students. This program was projected to reach 147 students and
80 teachers directly and 7,500 students indirectly at a cost to the District of $2.77 per person. The budget line includes
costs for staff to manage the project.
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 17,927 0 0 6,025 5,951 5,951
013 Hillsborough River Basin 29,004 0 0 6,026 11,515 11,463
014 Northwest Hillsborough Basin 6,025 0 0 6,025 0 0
015 Coastal Rivers Basin 5,576 0 0 1,806 1,885 1,885
016 Pinellas-Anclote River Basin 5,794 0 0 1,808 2,100 1,886
019 Withlacoochee River Basin 5,677 0 0 1,906 1,885 1,886
020 Peace River Basin 5,577 0 0 1,807 1,885 1,885
021 Manasota Basin 5,577 0 0 1,807 1,885 1,885
Project Funds Not Budgeted by the
District
The Florida Aquarium, Inc. 57,020 0 0 34,450 0 22,570
$138,177 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2009 Budgeted FundsOpen purchase order 11/3/08 1/5/09
Program components completed 9/15/09 9/30/09 9/30/09
Final report received by the District 9/30/09 10/15/09
FY2010 Budgeted FundsInititate purchase order 10/1/09 12/1/09
Program components completed 12/17/10
Final report and invoice received by the District 1/14/11
FY2011 Budgeted FundsBegin planning for two components 4/1/11
Completion of all programs 11/30/11
Status As Of: February 19, 2010
ACTION TO DATE: On time. Educational programming is underway.
021 - Manasota Basin 276
N151
Manatee County NAVD88 Vertical Control Densification
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality ConservationWater Supply Regional Water Supply PlanningNatural Systems Minimum Flows and Level Establishment and MonitoringFlood Protection Floodplain Management
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager OWENS, JIM
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a high priority. This project supports the NAVD88 Migration Project (B134) and the topographic mapping and
watershed modeling currently underway for Manatee County. This is the second year of this mapping effort and the
County has done an excellent job on this project. The County has been an active partner with the District in
establishing geodetic control since the late 1980s and continues to be a leader in this area.
DescriptionThe establishment of an accurate and easily accessible vertical control survey network is an important component in
the development of updated Federal Emergency Management Agency Flood Insurance Rate Maps (FEMA FIRM). The
District, in cooperation with the National Geodetic Survey and the Florida Department of Environmental Protection, has
completed the Distict-wide vertical control densification. This project will further enhance the existing vertical control
network to support FEMA FIRM mapping, topographic data collection and modeling activities. The newly-established
vertical control network will allow the District and local governments to transition from the older and less accurate
vertical control survey network known as the National Geodetic Vertical Datum of 1929 to the more accurate North
American Vertical Datum of 1988 (NAVD88) system. In Manatee County this includes running level loops and
establishing bench marks based on NAVD88 along state and county roadways. This project will enable the surveying
community to make an orderly transition to NAVD88 and will allow Manatee County to be on the same vertical datum
as the District and to comply with the federal surveying and mapping requirements. This project will densify the
NAVD88 vertical control in Manatee County and will compliment the District's NAVD88 migration project.
BenefitsDensification of benchmarks will support the development of Watershed Management Plans for Polk County thus
contributing to flood protection, natural systems, water quality and water supply. Manatee County participates in the
National Flood Insurance Program administered by FEMA and requires that all finished floor elevations be above the
100 year floodplain. This project is a key component in meeting this requirement. Also, the establishment and
implementation of the NAVD 1988 will enable more accurate elevations and mapping throughout the District, and the
conversion to the modern vertical datum will allow the ability to establish accurate and reliable elevations using Global
Positioning System (GPS) technology. Manatee County is a participant in FEMA's Community Rating System and has
a Class 6 rating. A major emphasis of this project is to help Manatee County move from a Class 6 to a Class 5
Community System Rating with FEMA. Manatee County is also coordinating this project with the City of Bradenton and
the City of Palmetto.
Costs
The total cost for contractual services in the proposed FY2011 Cooperative Funding Initiative is $150,000 of which the
District's share is $75,000. The County will contribute $75,000. The District's share of funding for this project is within
the Manasota Basin. Additional costs are associated with staff time required to manage the project. The total cost for
contractual services in the FY2010 Cooperative Funding Agreement is $150,000 of which the District's share is
$75,000. The County will contribute $75,000. The District's share of funding for this project is within the Manasota
Basin. Additional costs are associated with staff time required to manage the project.
Additional Information
This project will be administered by the County. The vertical control network survey work will be completed by qualified
professional surveying and mapping consultants. All newly-established vertical control network data produced by this
project will be made available through Internet access via LABINS web site and the Manatee County web site. The
original CFI project N264 was merged with N151 being that this is the second year of mapping.
021 - Manasota Basin 277
N151
Manatee County NAVD88 Vertical Control Densification
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 155,901 0 0 0 78,952 76,949
Project Funds Not Budgeted by the
District
Manatee County 150,000 0 0 0 75,000 75,000
$305,901 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
150FY2010; Execute Cooperative Agreement between the County and the District 12/31/09 2/5/10 2/5/10
FY2011; Execute Cooperative Agreement between the County and the District 1/31/11
180FY2010; Execute Contract with the Consultants 2/1/10 2/26/10
FY2011; Execute Contract with the Consultant 2/28/11
30FY2010; Initial project planning and develop Scope of Work 9/1/09 9/30/09 10/5/09
FY2011; Project planning and Scope of Work 9/30/10
480FY2010; Final deliverables 9/30/10 12/31/10
FY2011; Final Deliverables 12/31/11
60FY2010; Cooperative Funding Agreement submitted for approval 10/1/09 10/16/09 10/7/09
FY2011; Cooperative Funding Agreement submitted for approval 10/31/10
Status As Of: March 17, 2010
FY2010 Cooperative Funding Agreement: The District project manager and the Manatee County project manager
completed the final scope of work on 10/5/2009 and the Cooperative Agreement was routed to the District Contracts and
Legal department on 10/7/2009. The Manatee County Board of County Commissioners approved and signed the FY2010
Cooperative Agreement on 01/26/2010. The District executed the final agreement on 2/5/2010. The fully executed
agreement was sent to the County with notice to proceed on 2/18/2010. The District project manager has reviewed and
approved the consultant contracts as submitted by the County. The surveying work is in-progress. Florida Initiative
ACTION-TO-DATE comment: project is proceeding on time. FY2011 Cooperative Funding Initiative: The County has
submitted an application for cooperative funding for FY2011.
021 - Manasota Basin 278
N255
Beach Water Quality Project
Project Type Cooperative Funding
AORs Strategic InitiativesFlood Protection Floodplain ManagementWater Quality Water Quality MonitoringWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
City of VeniceCooperator(s)
Project Manager PRATER, CORRINA
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a High priority. This project will improve water quality and develop a project to reduce human exposure to
Enterococci and Fecal Coliform.
DescriptionThe City of Venice has eleven stormwater outfalls that collect from the Venice Island Basin and discharge directly to
the Gulf of Mexico. After a 2008 spring rain event, Venice Beach had high readings of Enterococci and Fecal Coliform
resulting in the closure of the beach at the fishing pier for several days. The City of Venice would like to research and
take preventative measures to protect the waters, reduce flooding, and improve water quality in this area. Two open
ditch outfalls can be found just north of the pier. These outfalls are one of the first outfalls that drain into the Gulf after
a rainfall. Deertown Gulley collects stormwater from 454 acres, the second largest basin on the island. Flamingo Ditch
collects stormwater from 194 acres on the island. In 2002, Sarasota County completed the Island of Venice
Stormwater Basin Study. Both Deertown Gulley and Flamingo Ditch basins have drainage deficiencies. The city has
taken steps to isolate contaminant sources. The first series of water quality testing shows elevated Enterococci and
Fecal Coliform levels in Flamingo Ditch and Deertown Gulley. Both have levels exceeding acceptable limits with the
highest levels found in Flamingo Ditch. Additional water samples were taken at various points along Flamingo Ditch to
try and isolate a source. The utilities department and stormwater division performed pipe inspection in the area around
the ditch to isolate any infiltration. The city is proceeding to perform DNA microbial analysis, with one upstream and
one downstream sample from Flamingo Ditch and one downstream sample from Deertown Gulley.
This will be a phased project. The first phase, which is proposed in this years application, involves additional source
sampling, research, conclusions regarding the water pollution and stormwater solutions, and design of a project to
resolve the issues. The second phase, which would be implemented in years two and three of the grant, involves
project construction. Possible solutions to the problem include modification of outfall to allow for more attenuation
before it outfalls in the gulf, land acquisition activities, public education on pointless pollution, stormwater retention
modification, deep gulf pumped discharge and storm pipe lining and/or replacement.
BenefitsThis project will improve water quality that discharges into the Gulf of Mexico by locating the source of contamination
and protect human safety.
Costs
The total projected cost for the project is $2,240,000. The District's total contribution in FY2011 will be $60,000 with an
equal match from the County. The remaining funds would be used in future years to implement and construct any
projects necessary. The District funding amounts shown in the table include staff salaries, travel and central garage.
The future funds identified for the project are contingent upon approval of such amounts by the District Governing
Board [and Basin Board(s)] in the annual budget(s).
021 - Manasota Basin 279
N255
Beach Water Quality Project
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,122,285 1,060,000 0 0 62,285 0
Project Funds Not Budgeted by the
District
City of Venice 1,120,000 1,060,000 0 0 60,000 0
$2,242,285 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Execute Funding Contract 11/30/10
Testing, Design and Permitting 2/29/12
Construction 12/31/13
Status As Of:
021 - Manasota Basin 280
N263
Manatee County - Watershed Evaluation
Project Type Cooperative Funding
AORs Strategic InitiativesFlood Protection Floodplain ManagementWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager NGUYEN, NAM
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a high priority. A senior administrator has provided confirmation that the County will budget the project for
FY2011. The application was ranked 4 of 7 submitted for cooperative funding by the cooperator.
DescriptionThis is a multi-year funded project to perform the 1) Topographic information, 2) Watershed Evaluation, 3) Watershed
Management Plan elements of the District's Watershed Management Program (WMP). Topographic information
includes the acquisition of data and development of the terrain features in the Geodatabase to be used in the
Watershed Evaluation. The Watershed Evaluation includes collection of existing data, GIS processing of the terrain
features to establish catchments and connectivity, field reconnaissance, refinement of the terrain features and
development of the hydraulic element point features. The Watershed Management Plan element includes:
development of watershed parameters for a specific use, GIS processing, computer modeling, floodplain and water
quality analysis, peer review, public notification/meeting, surface water resource assessment, establishment of LOS,
and BMP alternative analysis. FY2011 funding is to perform the Watershed Evaluation element starting with the
development of the hydraulic element point features.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain and water quality management.
Costs
The projected cost for this project is $740,000 of which the District's share is $370,000. The District's share is from the
Manasota Basin. The County will contribute $370,000. The FY2011 funding is $370,000 with the Manasota Basin
funding $185,000 and revenue of $185,000 from Manatee County. This is the first year of funding for the project. The
District funding amounts shown in the table include staff salaries. Future funds identified for the project are contingent
upon approval of such amounts by the Basin Board in the annual budget. When each element is completed the
projected cost may require refinement based on information gathered and unforeseen circumstances.
Additional Information
The Watershed Management Program (WMP) includes five major elements: 1) Topographic information, 2)
Watershed Evaluation, 3) Watershed Management Plan, 4) Implementation of Best Management Practices, and 5)
Maintenance of Watershed Parameters and Models. Implementing elements of the WMP with local governments is
one of the District's Strategic Priorities. The District is a cooperating technical partner (CTP) with FEMA. The
floodplain results developed will be used to update the flood insurance rate map (FIRM) panels. The District has been
working with the County for several years through the Watershed Management Program Coordination Document to
develop a five year implementation schedule by watershed based on their projected funding levels, and funding
available from FEMA and State appropriations. A cooperative funding revenue agreement with the County will be
developed as a multi-year funded project contingent on the approval of future funding to complete the project. This
project requires a cooperative funding request and ranking each fiscal year until completed. The District will manage
the project and enter into work orders and agreements to accomplish project tasks. Future cooperative funding
requests and agreements will be required for the Implementation of BMPs and Maintenance of Watershed
Parameters and Models.
021 - Manasota Basin 281
N263
Manatee County - Watershed Evaluation
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 371,039 185,000 0 0 186,039 0
District Budgeted - Outside Revenue
Manatee Co - Countywide GIS SW
(N263)
370,000 185,000 0 0 185,000 0
$741,039 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Agreement Executed 10/1/10
Work Assignment 12/20/10
Final report/ map 12/17/12
Status As Of:
021 - Manasota Basin 282
N275
Sarasota County - Watershed Evaluation
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager TURNER, DAWN
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a High Priority. A senior administrator has provided confirmation that the County will budget the project for
FY2011. The application was ranked 16 of 17 submitted for cooperative funding by the cooperator.
DescriptionThis is a multi-year funded project to perform the Watershed Evaluation element of the District's Watershed
Management Program (WMP) for Sarasota Watersheds.The information will be used to update watershed
management plans that are used to address flood protection and water quality issues. Project tasks include field
reconnaissance and data acquistion including the collection of vertical elevations in NAVD 88. Data collection methods
may include GPS (Global Positioning System), TPS (Terrestrial Position Systems) and/or Leveling for drainage
infrastructure.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments with their land
management responsibilities by establishing a level of service, develops Best Management Practices (BMPs) to
address level of service deficiencies, and provides a geodatabase and projected results from watershed model
simulations for floodplain and water quality management. The collected field data will be used to develop Watershed
Management Plans, and to update watershed parameters and models as part of the Sarasota - Update Watershed
Parameters & Models (L019) project.
Costs
This is a multi-year funded project. The projected costs for this project is anticipated to be $900,000 ($450,000
District's share). For FY2011, the total funding amount is $300,000 ($150,000 District's share). The remaining project
funds will be requested in future fiscal years. Please refer to PIMs entry for the Sarasota County GIS Dataset
Development (L867) project for information on prior funding.
Additional Information
The Watershed Management Program (WMP) includes five major elements: 1) Topographic Information, 2)
Watershed Evaluation, 3) Watershed Management Plan, 4) Implementation of Best Management Practices, and 5)
Maintenance of Watershed Parameters and Models. Implementing elements of the WMP with local governments is
one of the District's Strategic Priorities. Sarasota County is continuing its efforts to update their Infrastructure
database.The information collected will be used to support County and District watershed modeling activities. This
project is a continuation of work initiated with the Sarasota County GIS Dataset Development (L867) project. The
District is a cooperating technical partner (CTP) with FEMA, the floodplain results developed with this project will be
used to update the flood insurance rate map (FIRM) panels associated with this watershed.
021 - Manasota Basin 283
N275
Sarasota County - Watershed Evaluation
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 452,685 300,000 0 0 152,685 0
Project Funds Not Budgeted by the
District
Sarasota County 150,000 0 0 0 150,000 0
$602,685 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
MilestonesDevelop RFQ 7/30/10
Project Kick Off Meeting 10/29/10
Award RFQ 10/29/10
Initiate Field Recon 11/30/10
Complete Field Recon 8/31/11
Status As Of:
021 - Manasota Basin 284
N276
Low Impact Design Implementation at Venice East Blvd.
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementNatural Systems Natural Systems Conservation and Restoration
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager PRATER, CORRINA
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a high priority. This project will improve water quality by treating stormwater entering alligator creek. The
project includes water quality sampling to document the efficiency of bioretention using different pollution control
media or designs. This data will be used by the District's Regulation Department.
DescriptionSarasota County and the District are cooperativley funding the design of the County's Low Impact Design (LID)
Manual. The County has developed plans and specifications for approximately 13 bioretention or detention areas to
retrofit an existing roadway system without any stormwater treatment and begin implementing their LID plans. This
project attempts to demonstrate the effectiveness of Bioretention areas with a focus on: a wide plant palette,
engineered soils/amendments such as "Bold and Gold" with a goal of encouraging denitrification of stormwater
pollutants that infiltrate through the system, developing soil amendments similar to "Bold and Gold" but which are
formulated using Sarasota County waste products such as compost and mulch from the Solid Waste handling facility
and harvested/dried aquatic vegetation which are specifically formulated to assist with the denitrification process,
techniques which can be used to retrofit existing neighborhood streets which currently have no stormwater treatment,
and water quality sampling to document the efficiency of bioretention using different pollution control media or designs.
BenefitsThis project will improve water quality by treating stormwater that is currently untreated and replanting native
vegetation.
Costs
The total projected cost for the project is $920,000, of which the District's total contribution in FY2011 is $230.000. The
County will ask the District for $230,000 in FY2012. The County has spent $316,444 in previous years on consulting
fees for the design. The County will contribute $143,556 in FY2011. The District funding amounts shown in the table
include staff salaries, travel and central garage.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 462,812 230,000 0 0 232,812 0
Project Funds Not Budgeted by the
District
Sarasota County 460,000 0 0 155,444 143,556 161,000
$922,812 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Project MilestonesSurvey and Design Complete 3/31/10
Permitting Complete 9/30/10
Begin Construction 1/28/11
021 - Manasota Basin 285
N276
Low Impact Design Implementation at Venice East Blvd.
Construction Complete 6/30/11
Begin Monitoring 7/29/11
Monitoring Ends 7/30/12
Status As Of:
021 - Manasota Basin 286
N277
City of North Port Reclaimed Water Transmission Expansion Phase I
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Reclaimed WaterWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
City of North PortCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a high priority. This project will provide additional infrastructure to support the City's Reuse Master Plan and
future development of the City's reclaimed water system. The project is consistent with the basin objectives by using
an aternative water source to offset potable water use. This project is located in the Southern Water Use Caution Area
(SWUCA). There was sufficient information provided to evaluate the project and the cooperator has confirmed it will
include the necessary matching funds in its capital budget for FY2011. This project is within the District's statutory
authority to fund and is not the result of a permit requirement or enforcement action.
DescriptionThis project includes the design and construction of approximately 22,000 feet of 16 inch reclaimed water transmission
line to replace over 1.0 mgd of groundwater/potable water used for irrigation. The new reclaimed water customers
include the Gardens of the Five Senses; Glenallen Elementary School and soccer fields; Narramore Sports Park;
Police training course; North Port High School; Heron Creek Middle School; Butler Park; and the future Youth
Community Center.
BenefitsThe City plans to provide over 1.0 mgd of reclaimed water to the Gardens of the Five Senses; Glenallen Elementary
School and soccer fields; Narramore Sports Park; Police training course; North Port High School; Heron Creek Middle
School; Butler Park; and the future Youth Community Center to offset approximately 0.6 mgd of existing and future
groundwater use. The project supports the City's Reuse Master Plan and will allow the City to meet the demands of
future growth in the City's service area.
Costs
The total project cost is $3,890,000 and the District's share is requested to be fifty percent or $1,945,000. The City
plans to spend $389,000 in FY2011 and the Manasota Basin Board is requested to budget fifty percent or $194,500.
The Manasota Basin is being requested to provide $1,750,500 in additional funds in FY2012. The future funds
identified for the project are contingent upon approval of such amounts by the District Basin and Governing Boards in
the annual budget(s). The cost, amortized at 8 percent over 30 years is $1.56 per 1000 gallons offset.
Additional Information
In 2007 the City of North Port and the Southwest Florida Water Management District (SWFWMD) entered into an
agreement to fund the City of North Port Reuse Master Plan Project L629. One of the objectives of the project was to
provide preliminary designs and recommendations for the expansion of the reclaimed system. The City of North Port
adopted this Reuse Master Plan, which set forth a program of capital improvements designed to expand the reclaimed
water transmission system. The City entered into a contract with SWFWMD to fund the construction of a reclaimed
water storage tank in 2009, which will provide the necessary storage capacity to serve future customers. The City of
North Port has one of the lowest per-capita water use rates in the region, approximately 76 gallons per-capita per day
(gpdc). This can be attributed to an extensive conservation program which includes a tiered-rate structure, a reuse
water program, a toilet rebate program, community and educational efforts, irrigation enforcement, and the pursuit of
floodplain management. Reuse water is provided to golf courses, residential developments, the government complex,
commercial businesses and roadway medians. The City is expanding reuse in accdordance with the 2007 Reuse
Master Plan to offset potable water use. Water conservation is enforced by issuing tickets and fines for irrigation
violations. The conservation program offers brochures and literature, conservation classes for children at schools and
several neighborhood associations, and conservation displays at the Business Expo, the North Port Library and public
buildings. The City hosts special events such as a Florida Friendly Landscaping seminar and the Environmental Fair
at the Garden of the Five Senses. The City's website provides specific information on water conservation and the
City's Consumer Confidence Report (CCR) includes a section on water conservation that is sent to all utility
customers. Floodplain management projects include watershed hydraulic modeling to evaluate effective best
management practices and alternatives in the Big Slough, Myakkahatchee and Charlotte Harbor Watersheds,
stormwater management education, evaluation of flood control structure within the City's stormwater canal system, a
021 - Manasota Basin 287
N277
City of North Port Reclaimed Water Transmission Expansion Phase I
stormwater study to assess projects and funding, and continued maintenance programs for debris and vegetation
removal from the City waterways. In addition, in November 2007, the City of North Port passed Ordinance No.
2007-45, Fertilizer and Landscape Management, in an effort to protect the quality of the City's potable water.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 1,948,823 1,750,500 0 0 198,323 0
Project Funds Not Budgeted by the
District
North Port 1,945,000 1,750,500 0 0 194,500 0
$3,893,823 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Begin construction 10/29/10
Design of reclaimed water transmission to be extended 3/1/11
Complete construction 10/29/12
Final completion 1/31/13
Status As Of:
021 - Manasota Basin 288
N306
Sarasota County - Englewood CRA Stormwater Retrofit
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality MonitoringWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager PECK, MICHAEL
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a High priority. When implemented, this stormwater retrofit project will provide stormwater treatment for the
Englewood downtown district, resulting in reduced nutrient and sediment loads to the Lemon Bay Aquatic Preserve (an
Outstanding Florida Water). The project will reduce or eliminate the direct discharge of untreated stormwater from the
Englewood downtown district to the Lemon Bay Aquatic Preserve. The project is consistent with the District's priorities
for water quality improvement. The project is within the District's permitting authority and is not the result of a permit
requirement or enforcement action.
DescriptionThe Englewood Community Redevelopment Area (CRA) commercial district is located along Dearborn Street west of
Indiana Ave (SR 776) in Sarasota County. Untreated stormwater runoff from this commercial district, a 71 acre urban
drainage area, currently discharges 51 acres directly into the Lemon Bay Aquatic Preserve (an Outstanding Florida
Water) and 20 acres to the Gottfried Creek watershed. This project is for the design, permitting, and construction of a
stormwater retrofit system to provide stormwater treatment for both the existing development in the Englewood
commercial district as well as future development/redevelopment. The outlook on future development and
redevelopment within the commercial district is challenged by the prospect of having to provide individual stormwater
systems on each parcel which would inhibit the maximized use of available property. This project will provide the
stormwater treatment, reduce or eliminate the need to provide individual stormwater treatment systems on each
parcel, locate the system within the current public ROW or on publicly owned properties, and most importantly
eliminate or minimize direct runoff into the Lemon Bay Aquatic Preserve. This stormwater retrofit project will utilize LID
technologies as opposed to existing traditional practices to meet the stormwater needs of the Englewood CRA
commercial district. Sarasota County's parallel process of developing an LID Manual led to preliminary discussions
and meetings with District and regulatory staff. These meetings resulted in a conceptual agreement to consider permit
applications using LID technologies in lieu of traditional BMPs. In addition to providing 100% of stormwater treatment
utilizing LID technologies, water quality monitoring and educational outreach components will also be included. The
result will be an innovative, real-world, commercial retrofit project which will implement existing or new LID
technologies where they can subsequently be studied and evaluated on a long term basis. The project will provide the
stormwater treatment and attenuation necessary for full commercial development of individual parcels while providing
a net benefit to the water quality of the Lemon Bay Aquatic Preserve (an OFW). The project is funded through Capital
Improvement Program (CIP) dollars, and this request is for grant funding for FY2011. Grant funds will be used for
design, permitting, and construction. Sarasota County's procurement policy requires good faith efforts to encourage
the participation of minority-and woman-owned business enterprises within any future agreement.
BenefitsUntreated stormwater runoff from the Englewood CRA commercial district currently discharges directly into the Lemon
Bay Aquatic Preserve (an Outstanding Florida Water). This retrofit project will provide stormwater treatment for the
entire Englewood CRA commercial district (including eventual complete build-out and redevelopment), as well as
reduce or eliminate direct discharge of untreated runoff to bay. As a result, the project will improve the water quality of
the Lemon Bay Aquatic Preserve.
Costs
The preliminary estimate of total project cost is $1,500,000. For FY2011, the Manasota Basin is requested to fund
$750,000. Updated cost estimates will be calculated during the final design phase of the project. District funds in the
table below include salary, travel, and central garage charges.
Additional Information
Sarasota County adopted a floodplain management Ordinance (O1992-05) as required to participate in the National
Flood Insurance Program (NFIP) administered through the Federal Emergency Management Agency (FEMA). A Land
Development Regulations Ordinance (O2000-074) to further the objectives of floodplain management requires all
development to receive the proper building and site alteration permits. These regulations require all new stormwater
021 - Manasota Basin 289
N306
Sarasota County - Englewood CRA Stormwater Retrofit
management systems and finished floor elevations to be designed at or above the 100-year flood elevation.
Developments are required to be consistent with the detailed watershed models developed by the county by
demonstrating that they will not result in adverse increases in off-site flood stages within the appropriate watershed
model. As a participant in FEMA's Community Rating System we received a Class 5 rating. The county is a
Community Technical Partner (CTP) with FEMA and has entered into a 3-way Mapping Agreement Statement (MAS)
with FEMA and SWFWMD for the conversion of the county's digital floodplain maps and studies to Digital-Flood
Insurance Rate Maps (D-FIRMs). The county was awarded the James Lee Witt Local Award for Excellence by the
State Floodplain Managers Association and FEMA in 2002 and received the Florida Stormwater Association's 2008
Excellence Award for having the best Stormwater Utility Program in Florida. This prestigious award concentrates on
four major areas of the Stormwater Utility Program: Flood Protection, Water Quality, Operations & Maintenance, and
the Capital Improvement Program. A tiered rate structure, promotes water conservation by penalizing high water
consumption. A toilet rebate program has replaced over 8,000 high flow toilets. Another program provided rebates for
rain shut-off devices to help educate the public about Ordinance 96-021 requiring this device to be installed and
functioning on all automatic sprinkler systems. Our Showerhead Exchange program (10,000 replaced) helps to retrofit
buildings built before adoption of Ordinance 94-001 requiring low-flow fixtures in new construction. The Water-Efficient
Landscape Ordinance 2001-081 won a statewide award for innovation. Irrigation restrictions are enforced by code
enforcement officers, meter readers, and volunteers, that allow for once-a-week irrigation. Every resident suspected of
an irrigation violation is mailed a letter with educational material.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 752,425 0 0 0 752,425 0
Project Funds Not Budgeted by the
District
Sarasota County 750,000 0 0 0 750,000 0
$1,502,425 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Contract Development & ExecutionSubmit Cooperative Funding Application 12/1/09 12/1/09
Draft agreement sent to Management Services 8/9/10
Draft agreement returned from Management Services 8/30/10
Agreement sent to Cooperator 9/6/10
Signed agreement returned from Cooperator 10/4/10
Agreement fully executed 10/18/10
Notice to Proceed 10/22/10
2. Design & PermittingBegin Preliminary Design 1/29/10
Complete Preliminary Design 4/2/10
Application for Permit 4/16/10
Final Design 8/20/10
Permit Approved 11/19/10
Request for Bids 11/26/10
Bid Selection & Award 2/11/11
3. ConstructionCommence Construction 3/25/11
Complete Construction 6/30/11
Status As Of: February 11, 2010
Upon finalization of evaluation/ranking process and subsequent development of preliminary budget for the Manasota
021 - Manasota Basin 290
N306
Sarasota County - Englewood CRA Stormwater Retrofit
Basin Board, District Project Manager will interface with the County's Project Manager to formulate scope of work and
contract documents.
021 - Manasota Basin 291
N325
Manatee County Toilet Rebate Program Phase V
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply ConservationWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
Manatee CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a high priority. This project addresses a basin priority by saving potable water through cost-effective water
conservation measures. There is sufficient data submitted to properly evaluate the project, it is within the basin board's
statutory authority to fund, and it is not the result of a permit requirement or enforcement action.
DescriptionThis project is Phase V of the County's Ultra Low-Flow Toilet Rebate (ULFT) incentive program. The program is
available for Manatee County's retail water customers (residential, multi-family, and commercial). The County currently
services over 90,000 potable water accounts and anticipates continued growth over the next 20 years. The objectives
of this retrofit program are to reduce water demand and provide financial incentives for the replacement of an
estimated 1,500 toilets. This program addresses the Manatee County Board of County Commissioners policies on
water conservation and is supported by the recently increased Water Conservation Rates for potable water use. Any
retail water customer who agrees to replace a 3.5 gal or more toilet with a ultra-low flush (ULF) that uses 1.6 gallons
per flush (gpf) or less and/or High Efficiency Toilets (HET) using 1.38 gpf or less, will receive a $100.00 rebate for
each toilet (maximum of two (2) toilets per unit). This project will also focus on educating the new low volume toilet
users on the proper maintenance, specifically flappers and leak detection, necessary to ensure that each toilet remains
a water conserving fixture. Rebate payments are subject to the recipient's submittal of the completed application,
documented cost, and will be distributed upon inspection of the completed installation and verification that the old toilet
is ready for disposal.
BenefitsThe estimated total water saving value of the project is 33,465 gpd.
Costs
The total cost for this project is estimated to be $217,500. The County has requested $108,750 (fifty percent) from the
Manasota Basin Board in FY2011. The cost/benefit is $1.78 per k/gallons, assuming a 20-year life.
Additional Information
This toilet rebate program is an enhancement to the County's existing Water Conservation Program. The County's
Water Conservation Program includes existing metering and loss reduction programs, water conserving rate
sturctures, urban and agricultural reclaimed water irrigation supply (with the metering of all users and consumption
based billing for all new users), public education, Florida Friendly based landscape codes, SWUCA based level of
service for water supply at 110 gpfcpd, land development codes requiring non-potable sources for irrigation in new
development, water supply protection ordinances, and the use of aquifer storage and recovery for both potable and
reclaimed water. Through Phase III of the County's Toilet Rebate Program and the 47,000 eligible properties in the
county, 3,851 rebates have been issued saving over 65,600 gpd.
021 - Manasota Basin 292
N325
Manatee County Toilet Rebate Program Phase V
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 111,818 0 0 0 111,818 0
Project Funds Not Budgeted by the
District
Manatee County 108,750 0 0 0 108,750 0
$220,568 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Advertise project 1/3/11
Execute agreement with District 5/1/11
Begin Phase V Toilet Rebate Program 5/16/11
Complete Rebate Program FY 2011 1/31/13
Status As Of:
021 - Manasota Basin 293
L015
Sarasota County Surface Water Monitoring Program
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and Improvement
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager PRATER, CORRINA
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a medium priority. Continued collection of rainfall and stream stage data will support several on-going projects
including the development of watershed plans for Lemon Bay and Roberts Bay.
DescriptionThis proposed FY2011 cooperative funding project from Sarasota County is for continued rainfall and stream gauge
data collection and analysis at 13 surface water monitoring sites. The County requested to continue the development
of the stage-discharge curves for the sites. The request also included the continuation of field measurements for one
more year to quantify sites influenced by tidal fluctuations. The data and analyses will be used to improve watershed
model calibration and verification, and to quantify freshwater flows to the bays and estuaries. Data collection results
and analyses will support several ongoing projects including the development of watershed plans for Lemon Bay and
Roberts Bay. The County and SWFWMD cooperatively funded the collection of field measurements in FY2004 and
FY2007. In addition to the rating curves, the project will produce one year of daily discharge measurements for each
site. These monitoring sites are important to establishing the volume and timing of freshwater flows into Sarasota's
bays and estuaries and several of the sites are useful for ongoing District MFL studies.
BenefitsThe project is intended to provide daily watershed discharge at up to 23 sites. The County and SWFWMD have
cooperatively funded the field measurements for 13 sites since August 2004. Continued collection of rainfall and
stream stage data in FY2008, FY2009, and FY2010 will support several ongoing projects including the development of
watershed plans for Lemon Bay and Roberts Bay.
Costs
The total project budget is $1,369,516. For FY2007 Sarasota County requested $100,000 from the Manasota Basin
Board. For FY2008 the Manasota Basin Board budgeted an additional $100,000 with an equal match from Sarasota
County. The Manasota Basin Board budgeted $60,000 for the project in its FY2009 budget. The County will provide an
equal match of $60,000 for FY2009. In FY2010, the District is requested to fund $60,000. The County will provide an
equal match of $60,000 . The District funding amounts shown in the table include staff salaries, travel and central
garage charges.
Additional Information
A final project report of all data collected through the FY2007 scope of work was received in December 2007. FY2005
and FY2006 Cooperative Funding Applications in the amount of $275,000 District match were approved by the
District. Subsequent to approval, the County declined to use the funds which were then forfeited.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 748,156 0 0 624,746 61,640 61,770
Project Funds Not Budgeted by the
District
Sarasota County 743,000 0 0 623,000 60,000 60,000
$1,491,156 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 294
L015
Sarasota County Surface Water Monitoring Program
Critical Project Milestones ActualProjected Amended
Phase 1Forward Cooperative Agreement to Contract Administration 10/31/03 11/21/03
Submit Cooperative Agreement to County 12/31/03 12/11/03
Execution of Agreement by SWFWMD 3/31/04 3/17/04
Issue Notice to Proceed to County 3/31/04 3/17/04
Execution of Agreement by County 3/31/04 3/9/04
County Issue Notice to Proceed to Consultant 4/30/04 7/27/04
Submit Contract Extension to County 7/31/05 8/16/05
Execution of FY2004 Amendment by County 9/30/05 4/30/06
Termination of FY2004 Cooperative Agreement 10/31/05 7/28/04
Execution of FY2004 Amendment by SWFWMD 10/31/05 6/30/06
Termination of FY2004 Cooperative Agreement, Amended 10/31/06 10/31/06
Draft Contract for FY2007 Funding 10/31/06 11/6/06
Submit Cooperative Agreement for County Signature 12/30/06 1/22/07
Board of County Commissioner Approval 2/27/07 3/13/07
Execution of Agreement for FY2007 Funding by SWFWMD 3/21/07 3/21/07
FY2007 Data Collection Completed 9/30/07 9/30/07
FY2007 Data Final Report Completed 12/31/07 12/31/07
Expiration Date for FY2007 Agreement 3/31/08 12/31/07
Phase 2Draft New Agreement for FY2008 Funding 9/30/07 2/28/08 6/15/08
Forward Cooperative Agreement for County Signature 11/15/07 6/30/08 7/30/08
Execution of Agreement by County 12/28/07 8/31/08 9/24/08
Execution of Agreement by SWFWMD 1/31/08 9/10/08 10/1/08
FY 2008 Data Collection Completed 9/30/08 9/30/08
Termination Date for FY 2008 Cooperative Agreement 12/31/08 12/31/08
Phase 3Draft Amendment to Agreement for FY2009 Funding 9/15/08 1/15/09 3/4/09
Draft FY09 Amendment to Contracts Section 9/22/08 1/15/09 3/9/09
Forward FY09 Amendment for County Signature 10/15/08 2/15/09 3/31/09
Execution of FY09 Amendment by County 10/31/08 3/5/09 6/23/09
Execution of FY09 Agreement by District 11/7/08 3/15/09 6/30/09
Phase 4Draft Amendment to Agreement for FY2010 Funding 9/15/09
Draft FY10 Agreement to Contracts Section 3/1/10 3/4/10
Forward FY10 Agreement for County Signature 3/31/10
Execution of FY10 Agreement 5/3/10
Status As Of: February 15, 2010
Data collection efforts for FY2009 began October 1, 2008 and all invoices have been received and paid. The agreement
to continue the project through FY2010 with additional funding was developed and is currently routing. The County has
requested FY2011 funding.
021 - Manasota Basin 295
L200
Bradenton - Wares Creek Bridge Replacement
Project Type Cooperative Funding
AORs Strategic InitiativesFlood Protection Floodplain Management
Basin(s) Manasota
City of BradentonCooperator(s)
Project Manager FRIES, GEORGE
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a medium priority. The project is ranked medium because the City will not have construction of the 20th
Street Stormwater Improvements advanced far enough to require the FY2011 funding prior to September 2011. The
City and their consultant were able to provide information demonstrating that replacing the bridges will have flood
protection benefits and that they can address the permitting issues that have been raised. A senior administrator has
provided confirmation that the City will budget the project for FY2011 funding. The City has ranked this project second
of 3 submitted for cooperative funding.
DescriptionThis is a multi-year funded project to perform the Implementation of Best Management Practices (BMPs) element of
the District's Watershed Management Program (WMP) for the Wares Creek Watershed. Implementation of BMPs
includes the following tasks: design, development of construction documents, construction permitting, land acquisition,
bidding and contractor selection, construction of the BMPs and construction engineering and inspection. The
watershed is highly urbanized and covers an area of approximately 2.41 square miles (1,546 acres) and is located in
the City of Bradenton and Manatee County. The City of Bradenton is proposing to replace 4 bridges over Wares
Creek. They are the 9th Ave. West, 12th Ave. West, 14th Ave. West, and 17th Ave. West bridges. In addition,
improvements to existing stormwater facilities that discharge into Wares Creek at the 20th Street West Stormwater
Management System will be constructed as part of this project. These BMPs were evaluated as part the City of
Bradenton Comprehensive Stormwater Management Study funded by the City, and selected for implementation in the
BMP alternative analysis. The proposed improvements are also included in the City's Five-Year Capital Improvement
Plan. Prior years funding was provided for topographic surveying, geotechnical investigation, hydraulic and hydrologic
modeling, design of the 4 bridges, construction of the 9th Avenue Bridge, construction of the 12th Avenue Bridge,
design of the 20th Street West Stormwater Management System and to begin construction of the 14th Avenue Bridge.
For FY2011 funding is requested to complete construction of the 14th Avenue Bridge and to begin construction of the
20th Street West Stormwater Management System.
BenefitsThese BMPs are in conjunction with the $55,000,000 United States Army Corps of Engineer's (USACE) Cedar
Hammock (Wares Creek) Flood Control Channel improvements project, in which the USACE will dredge and widen
the creek to provide an increased level of flood protection. The District is co-funding the Wares Creek project with
Manatee County (K253) to provide the local sponsor's funding obligation. The USACE did not participate in funding the
replacement of the City's bridges or improvements to the City's existing stormwater systems. The bridge replacements
target flood protection on an intermediate conveyance way, and address the local government's level of service
deficiencies by reducing flood levels where the bridges are over topped, homes damaged, and private property and
streets are flooded.
Costs
The projected cost for this project is $7,800,000 of which the District's multi-year share is $3,900,000 and the City's
share is $3,900,000. Funding for this project was provided in the Manasota Basin Board budgets of FY2005 ($50,000);
FY2006 ($200,000); FY2007 ($500,000); FY2008 ($500,000); FY2009 ($500,000); and FY2010 ($500,000) for a total
funding commitment to date of $2,250,000. For FY2011, the City is requesting $500,000 in cooperative funding and
the City will provide $500,000 in matching funds. The probable construction costs for this project are based on a BMP
alternative analysis developed by the cooperator. When each element is completed the projected may require
refinement based on information gathered and unforeseen circumstances. The District funding amounts shown in the
table includes staff salaries. The future funds identified for the project are contingent upon approval of such amounts
by the District Governing Board and Basin Board in the annual budget(s).
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of BMPs, and 5) Maintenance of Watershed Parameters and Models.
Implementing elements of the WMP with local governments is one of the District's Strategic Priorities. The WMP
021 - Manasota Basin 296
L200
Bradenton - Wares Creek Bridge Replacement
provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality and natural
systems while achieving flood protection. A cooperative funding expenditure agreement with the City has been
developed contingent on the approval of future funding to complete the Implementation of BMPs. With FY2005
funding the work on the Implementation of BMPs began and included the following tasks: topographic surveys,
geo-technical investigations, hydrologic and hydraulic investigation and preparation of a preliminary design report. For
FY2006 funding was requested for development of the construction documents and obtaining permits for the four
bridges. For FY2007 funding was requested to begin construction of the 9th Avenue Bridge, for construction
engineering and inspection and for survey, geotechnical investigation and start of design on the 20th Street West
stormwater management system. In FY2008 funding was requested to complete construction of the 9th Avenue West
Bridge. For FY2009, funding was requested to complete construction of the 12th Avenue West Bridge and begin
construction of the 14th Avenue West bridge and for design and geotechnical investigation at the 20th Street West
Stormwater Management System. This project requires a cooperative funding request and ranking each fiscal year
until completed. The City will manage this project, where the District project manager must approve any agreements
to accomplish project tasks.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 3,668,137 900,000 0 1,763,698 501,197 503,242
Project Funds Not Budgeted by the
District
City of Bradenton 3,900,000 1,150,000 0 1,750,000 500,000 500,000
$7,568,137 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesDistrict logo will be provided on construction signs 12/1/07 5/1/10
2. Cooperator AgreementAgreement to Contracts Administration 8/1/04 10/20/04
Agreement back from Contracts Administration 9/10/04 11/1/04
Contract Executed 10/1/04 12/29/04
Notice to Proceed to City 10/2/04 12/29/04
2A. Consultant Services (FY2005 Funding)Consultant Selected (JEA) 3/1/05 11/30/04 11/22/04
Survey & Geotechnical Complete 8/31/05 4/30/05 8/25/05
Hydraulic & Hydrologic Investigation 12/31/05 6/30/06 3/31/06
3. First Amendment (FY2006 Funding)Amendment Executed 9/21/05 9/21/05
FY2006 Funds Encumbered 10/1/05 1/6/06
3A. Consultant Services (FY2006 Funding)Preliminary Plans (4 bridges) 10/1/05 6/12/06
Final Plans & Specifications (9th Ave W & 17th Ave W bridges) 8/31/06
Permitting (9th Ave W & 17th Ave W bridges) 4/1/07
4. Second Amendment (FY2007 Funding)Amendment Executed 10/1/06 8/14/06
FY2007 Funds Encumbered 10/2/06 1/23/07
4A. Consultant & Construction Services (FY2007 Funding)Hydraulic & Hydrologic Modeling 1/30/07 8/31/08
Final Plans and Specifications for the 9th Ave. Bridge 2/28/07 3/31/09
Permitting for the 9th Ave. Bridge 3/31/07 7/31/09 11/16/09
021 - Manasota Basin 297
L200
Bradenton - Wares Creek Bridge Replacement
Bidding & Contr. Selection for 9th Ave. Bridge 5/31/07 11/30/09
Final Plans & Specs for 12th, 14th & 17th Ave. Bridges 5/31/07 8/31/07
Complete Survey, Borings & 30% Design of 20th St. Stormwater Facility
Improvements
6/30/07 6/30/09
Contract award for 9th Ave. Bridge 6/30/07 3/1/10
Commence Construction of 9th Ave. Bridge 9/1/07 5/1/10
Complete Construction of 9th Ave. Bridge 6/1/10 4/1/11
4B. Third Amendment (FY2008 Funding)Amendment Executed 10/1/07 7/26/08
FY2008 Funds Encumbered 10/2/07 6/4/08
4C. Fourth Amendment (FY2009 Funding)Amendment Executed 1/31/09 3/27/09
FY2009 Funds Encumbered 2/1/09 11/7/08
4D. Consultant & Construction Services (FY2009 Funding)Plans & Profiles for 4bridges sufficient to submit for permits 12/31/08
Bidding & Contr. Selection for 12th Ave. Bridge 11/30/10
Contract Award for 12th Ave. Bridge 3/1/11
Commence Construction of 12th Ave. Bridge 5/1/11
5. Contract CompletionCooperator Agreement Expiration 10/1/07 12/31/11
Status As Of: February 17, 2010
Status History: The Cooperative Funding Agreement was executed on December 29, 2004. The City contracted with
Jones Edmunds & Associates (JEA) to perform the engineering work on the project. Topographic surveying and
geo-technical work were completed and existing hydraulic & hydrologic data were collected. The City requested
additional cooperative funding for FY2006 and a contract amendment to incorporate the FY2006 funds was executed on
September 21, 2006. A preliminary hydrologic and hydraulic report was submitted. The City applied for FY2007 funding
to perform additional field survey work, to perform additional hydraulic and hydrologic studies and to begin construction of
the 9th Avenue Bridge. The Preliminary Design Report was submitted on June 12, 2006 and comments were provided to
the City. The hydraulic modeling of Wares Creek was submitted for review and comments on October 20, 2006. District
staff met with the City's consultant in March 2007 to discuss the results of the hydraulic modeling. A pre-application
meeting with Sarasota Regulatory staff was held on April 25, 2007 to discuss the project. The City requested and
received FY2008 cooperative funding to continue work on the project. The consultant is continuing work on the modeling
of the creek hydraulics and hydrology. A progress meeting was held at District headquarters on April 28, 2008 to discuss
the modeling effort, future cooperative funding, ACOE permitting status and other items. The City's consultant (JEA) met
with the Sarasota Regulatory staff on August 20, 2008 for a second pre-application meeting. District staff has met with
the city project manager and the consultant on several occasions to discuss project status and progress.
ACTION-TO-DATE: Delayed. This project has been delayed partly in response to the delays in the ACOE proceeding
with the Wares Creek Dredging project (K253). The City did work with FDOT to see if Federal stimulus funding was
available for this project and it was not. The Environmental Resource Permit for the construction of the 9th Avenue West
Bridge was issued on November 16, 2009. The Fifth Amendment to the cooperative funding agreement adding the
FY2010 cooperative funding was sent to the City for execution.
021 - Manasota Basin 298
N281
Nokomis Drainage Improvement and Stormwater Treatment
Project Type Cooperative Funding
AORs Strategic InitiativesNatural Systems Natural Systems Identification and MonitoringWater Quality Water Quality Maintenance and ImprovementFlood Protection Emergency Flood Response
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager LOPEZ, MANNY
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a Medium priority. If implemented the project would provide stormwater treatment and flood storage at the
local level. The project is consistent with the District's priorities for water quality improvement. The project is within the
District's statutory authority to fund and is not the result of a permit requirement or enforcement action.
DescriptionThe project involves modifying and upgrading an existing retention area currently located on land owned by Sarasota
County and the Parks Department. A stormwater conveyance ditch which currently discharges directly into tidal waters
will be routed through the modified retention area in order to provide stormwater treatment prior to being discharged
into tidal waters. The ditch currently provides drainage from an industrial area. The modified retention area will be
replanted with native wetland species to enhance the water quality treatment capabilities of the system. The system
when modified is also expected to assist with stormwater management for this portion of the Nokomis neighborhood.
BenefitsIf constructed, the proposed project would direct untreated stormwater drainage through an upgraded retention pond
before it enters nearby tidal waters in Shackett Creek. The retention pond would include plantings of native wetland
vegetation for enhanced treatment and uptake of nutrients.
Costs
The preliminary cost estimate for the proposed project is $600,000. Updated costs estimates will be derived as project
design is developed. For FY2011 the Manasota Basin Board is requested to fund $300,000 of project costs. Sarasota
County will provide an equal match of $300,000.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 303,603 0 0 0 303,603 0
Project Funds Not Budgeted by the
District
Sarasota County 300,000 0 0 0 300,000 0
$603,603 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
MilestonesBegin Design and Permitting 10/1/10
Complete Permitting and Design 10/1/11
Begin Construction 1/2/12
Complete Construction 9/25/12
021 - Manasota Basin 299
N181
Science Curriculum Enhancement Program
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality MonitoringWater Supply ConservationNatural Systems Natural Systems Identification and Monitoring
Basin(s) Manasota
Science and Environment Council of SarasotaCooperator(s)
Project Manager TORRUSIO, MARY
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as low priority. The Science Curriculum Enhancement Program, which is based on research SEC conducted, is
designed to increase knowledge and understanding as well as improve attitudes about science. While the project as
proposed offers a high quality educational program from an excellent cooperator, staff has concerns about the high
cost per participant. The program is designed to educate 390 science students from 8th, 9th and 10th grade in
Sarasota County Schools through a choice of three or six field trips to science-based facilities in Sarasota County.
Although the comprehensive nature of this project justifies some higher costs, because of the limited numbers of
students participating, the cost per participant ($82.88) is four times higher than the average cost of District Youth
Education projects and 62% higher per participant contact hour. The FY2010 project is underway, but the response
from teachers has not met cooperator expectations.
DescriptionThis Cooperative Funding Initiative (CFI) project's goal is to enhance student awareness about local water and
watershed conservation based on science. The components of the proposed project are a teacher workshop to
provide tools for teachers to integrate water-related lessons into their curriculum, in-class instruction and a series of
three or six field trips to SEC member sites. The program would be offered to Sarasota County 8th, 9th and 10th grade
science students and geared for the on-level student. Student participants will engage in inquiry-based activities,
lessons and interaction with science professionals and technicians. In-class instruction will take place several days
before each field trip and serve as an orientation to the field trip site, introduction to the lesson and discussion of
careers in the field. The goal is that students, through participating in the program, will understand the importance of
preserving and managing our watershed. While not all will choose science or water-related careers, they will have a
better understanding of the role scientists and water managers play. Evaluation includes student pre- and post-testing,
and teacher evaluation forms.
BenefitsThe project's goal is to provide comprehensive science education opportunities to Sarasota County students in grades
8 through 10. The basin has prioritized partnering with science-based organizations and the SEC is a group of
non-profit and government organizations that operate or support conservation and science-based facilities. SEC's
mission is to promote science, conservation and environmental issues in Sarasota County for maintaining and
improving quality of life through education, public outreach, demonstration, information gathering and analysis, and
special projects. By collaborating on projects, the SEC can offer services and provide educational materials that no
one organization can do alone. Through collaboration, the collective knowledge and expertise of all the organizations
allows SEC to strengthen science curriculum. Through this initiative, the focus of curriculum enhancement will be
water-related. The program is based on results of a previously funded two-year research study at Booker High School.
Costs
The total proposed cost of the FY2011 program is $66,800, with the District requested to contribute $33,400
(Manasota). District funding is requested for an estimated 54 field trips, transportation, teacher workshop stipends,
promotion materials, program evaluation and administration. The program is projected to reach 390 students and 13
teachers at a cost to the District of $82.88 per participant.
Additional Information
The SEC partners/contributors include Aquarian Quest, Charlotte Harbor Environmental Center, Crowley Museum and
Nature Center, Florida West Coast Resource Conservation and Development Council, Friends of Myakka River,
Friends of Oscar Scherer State Park, G.WIZ, Historic Spanish Point, Lemur Conservation Foundation, Marie Selby
Botanical Gardens, Mote Marine Laboratory, New College, Ringling College of Art and Design, Sarasota Bay Estuary
Program, Sarasota Audubon, Sarasota Conservation Foundation, Sarasota County Extension and Florida House
Learning Center and Sarasota County Government. Research-phase funding was through Sarasota County School
Board, with support from Basin Initiative for youth education (P259) from the District's Manasota Basin Board.
021 - Manasota Basin 300
N181
Science Curriculum Enhancement Program
The total FY2010 project cost is $66,800, with the District contributing $33,400 (Manasota). District funding is used to
fund an estimated 54 field trips, transportation, teacher workshop stipends, promotion materials, program evaluation
and administration. It is offered to Sarasota County 8th, 9th and 10th grade science students and geared for the
on-level student.The program is projected to reach 390 students and 14 teachers at a cost to the District of $82.67 per
participant. Students receive a discount (5 to 15 percent less) for the field trips offered as part of this cooperative
funding project.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 67,615 0 0 0 34,215 33,400
Project Funds Not Budgeted by the
District
Science & Environmental Council of
Sarasota (SEC)
66,800 0 0 0 33,400 33,400
$134,415 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2010 Budgeted FundsInitiate purchase order 10/1/09 12/4/09
Complete lesson plans, activities for pre-visits and field trips 1/29/10 2/28/10
Promote field trip packages to teachers 2/26/10
Schedule field trips 2/26/10
Teacher workshop 3/15/10
Conduct pre-visits and field trips 5/28/10
Student and teacher assessments 5/28/10
Evaluate and refine program 8/16/10
Conduct pre-visits and field trips 10/29/10
Evaluate program 10/29/10
Student and teacher assessments 10/29/10
Final report and invoice due to District 11/20/10
FY2011 Budgeted FundsField trips end 9/1/10
Initiate purchase order 10/1/10
Field trips begin 11/1/10
Field tips end 11/1/11
Final report and invoice due to the District 11/30/11
Status As Of: February 18, 2010
ACTION TO DATE: Delayed. Due to low response, the original teacher workshop date of February 6 was pushed back to
March 26 to give teachers a chance to attend on one of the school district's in-service days.
021 - Manasota Basin 301
N206
G.WIZ Water Wonders Workshop
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality ConservationNatural Systems Natural Systems Identification and Monitoring
Basin(s) Manasota
G.WIZ-The Science MuseumCooperator(s)
Project Manager TORRUSIO, MARY
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as low priority. This half-day field trip project educates 1,430 Sarasota County grades 5-7 students and teachers
about issues related to water quality, stormwater runoff, natural systems and conservation. Education programming
aligns with the Manasota Basin Board's priorities. However, the program lacks strong pre- and post-visit education
components, which are essential for reinforcing learning. Workshops offer participants only one-time, 2 ½ hour
sessions, rather than in-depth, long-term experiences, which might justify a higher cost. Data regarding pre/post
assessments demonstrates a 23% learning gain; this number is slightly lower than the average gain in other youth
education programs (30%). The cost per participant contact hour ($6.40) is more than double the cost of the average
youth education program. The total cost per participant ($25.58) is 55% higher than the average youth education
program.
DescriptionThis Cooperative Funding Initiative (CFI) project seeks to educate students and adults in Sarasota County about
conservation and protection of local environmental resources. The project targets 138 adults and 1,380 students in
grades 5-7 in Sarasota County. The program's purpose is to excite students about science in an informal educational
setting that encourages curiosity and understanding through hands-on activities about water quality, water
conservation and protection of water resources. Overall, the program proposes to increase both their awareness and
knowledge of water resources with the ultimate goal that they become engaged stewards of our natural resources. The
project's success is measured by pre/post student assessments as well as teacher evaluations.
BenefitsThis project proposes to provide students with hands-on experiences with water resources. The District would benefit
from Sarasota County students having a better understanding of conservation and preservation of water resources and
be better prepared for future decision-making.
Costs
The total cost of the FY2011 project is proposed to be $71,124, with the District requested to contribute $38,839
(Manasota). District funding is requested for 30 field trips, transportation and workshop supplies. The proposed
program would reach 1,380 students and 138 adults at a cost to the District of $25.59 per person.
Additional Information
The total cost of the FY2010 project was $71,124, with the District's Manasota Basin Board contributing $38,839.
District funding was used to fund 30 field trips, transportation and workshop supplies. The proposed program reached
1,380 students and 138 adults at a cost to the District of $25.58 per person. The project educated students and adults
in Sarasota County about conservation and protection of local environmental resources. The District has supported
this project through the Cooperative Funding Initiative since FY2010.
021 - Manasota Basin 302
N206
G.WIZ Water Wonders Workshop
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 79,270 0 0 0 39,654 39,616
Project Funds Not Budgeted by the
District
G.WIZ 32,285 0 0 0 0 32,285
WCIND 53,645 0 0 0 53,645 0
$165,200 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
FY2010 Budgeted FundsInitiate purchase order 10/1/09 10/12/09
Educational workshops begin 11/2/09 11/20/09
Educational workshops end 7/30/10
Final report and invoice due to the District 8/31/10
FY2011 Budgeted FundsInitiate purchase order 10/1/10
Educational workshops end 7/29/11
Final report and invoice due to the District 8/31/11
Educational workshops begin 11/2/11
Status As Of: February 18, 2010
ACTION TO DATE: On time. To date, cooperator has provided 16 workshops reaching 762 students and 87 adults.
021 - Manasota Basin 303
N215
Anna Maria Island - Watershed Evaluation
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
Lynn Townsend & Associates, LLC.Cooperator(s)
Project Manager NGUYEN, NAM
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a low priority. A senior administrator from each of the three communities has provided confirmation that the
community will budget the project for FY2011. This is the only application submitted for cooperative funding jointly by
the three communities.
DescriptionThis is a multi-year funded project to perform the 1) Topographic information, 2) Watershed Evaluation, 3) Watershed
Management Plan elements of the District's Watershed Management Program (WMP). Topographic information
includes the acquisition of data and development of the terrain features in the Geodatabase to be used in the
Watershed Evaluation. The Watershed Evaluation includes collection of existing data, GIS processing of the terrain
features to establish catchments and connectivity, field reconnaissance, refinement of the terrain features and
development of the hydraulic element point features. The Watershed Management Plan element includes:
development of watershed parameters for a specific use, GIS processing, computer modeling, floodplain and water
quality analysis, peer review, public notification/meeting, surface water resource assessment, establishment of LOS,
and BMP alternative analysis. FY2011 funding is to perform the Watershed Evaluation element starting with the
development of the hydraulic element point features.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain and water quality management.
Costs
The projected cost for this project is $30,000 of which the District's share is $15,000. The District's share is from the
Manasota Basin. The City of Anna Maria will contribute $5,000, the City of Bradenton Beach will contribute $5,000 and
the City of Holmes Beach will contribute $5,000. The FY2011 funding is $30,000 with the Manasota Basin funding
$15,000 and revenue of $15,000 from the Island ($5,000 from each of the three communities). This is the first year of
funding for the project. The District funding amounts shown in the table include staff salaries. Future funds identified
for the project are contingent upon approval of such amounts by the Basin Board in the annual budget. When each
element is completed the projected cost may require refinement based on information gathered and unforeseen
circumstances.
Additional Information
The Watershed Management Program (WMP) includes five major elements: 1) Topographic information, 2)
Watershed Evaluation, 3) Watershed Management Plan, 4) Implementation of Best Management Practices, and 5)
Maintenance of Watershed Parameters and Models. Implementing elements of the WMP with local governments is
one of the District's Strategic Priorities. The District is a cooperating technical partner (CTP) with FEMA. The
floodplain results developed will be used to update the flood insurance rate map (FIRM) panels. A cooperative funding
revenue agreement with the 3 communities will be developed as a multi-year funded project contingent on the
approval of future funding to complete the project. This project requires a cooperative funding request and ranking
each fiscal year until completed. The District will manage the project and enter into work orders and agreements to
accomplish project tasks. Future cooperative funding requests and agreements will be required for the Implementation
of BMPs and Maintenance of Watershed Parameters and Models.
021 - Manasota Basin 304
N215
Anna Maria Island - Watershed Evaluation
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 15,856 0 0 0 15,856 0
District Budgeted - Outside Revenue
Anna Maria - Anna Maria Island WS
Collab (N215)
5,000 0 0 0 5,000 0
Bradenton Bch - Anna Maria Island WS
Coll (N215)
5,000 0 0 0 5,000 0
Holmes Bch - Anna Maria Island WS
Collab (N215)
5,000 0 0 0 5,000 0
$30,856 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Establish Mission/Vision 3/20/09
Commence Research and Design 5/1/09
Identify Goals and Action Items 7/31/09
Complete Master Watershed Report with Recommendations 1/29/10
Status As Of:
021 - Manasota Basin 305
N268
Watershed Education Classroom
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality MonitoringNatural Systems Natural Systems Conservation and RestorationWater Supply Conservation
Basin(s) Alafia River, Hillsborough River, Coastal Rivers, Pinellas-Anclote River, Peace River, Manasota
The Florida Aquarium, Inc.Cooperator(s)
Project Manager HULL, MARY MARGARET
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as low priority. This new project proposed by The Florida Aquarium is to repurpose existing space to feature one
classroom showcasing the Tampa Bay watershed. Several educational freshwater tanks and a wall mural will be
placed in the classroom as teaching tools for the estimated 3,100 annual classroom visitors. Classroom exhibits would
be used with educational programming and a new curriculum guide would be developed. While the exhibits would be
an enhancement to the Aquarium's existing classroom space, the benefit to the District is limited. This project's low
ranking reflects the high cost and limited use and value of the exhibits. Only those participating in programming, not all
aquarium visitors, would see the exhibits. The District's cost per participant contact hour ($4.65) pro-rated over the
expected 5-year life of the exhibits is 58% higher than the average of youth education projects.
DescriptionThis Cooperative Funding Initiative (CFI) project proposes to educate teachers and students about Florida's water
resources and natural environment through re-design of existing space into a watershed classroom inside The Florida
Aquarium. Currently, there is greater demand for the cooperator's on-site programming than the available classroom
space can meet. To increase capacity for conservation education, the cooperator will repurpose existing space to
create a suite of dedicated classrooms with environmental themes. One classroom will showcase an element of the
Florida water story: the Tampa Bay watershed. The goal of the proposed Watershed Classroom is to create an
educational space that enhances study of the watershed. To bring the stages of the watershed to life, the new
classroom would feature interactives, exhibits of freshwater and estuary habitats, touch tanks and a mural of the
ecosystems that comprise the watershed. The cooperator anticipates that on an annual basis up to 3,000 students
from elementary through high school will participate in age-appropriate watershed education programs in the
classroom, as well as 100 teachers in professional development workshops.The Florida Aquarium has submitted an
RFP for bids to local architecture firms, with a deadline for responses of December 30, 2009. Estimates for the entire
education wing budget total $2 million. Success will be measured by completing the classroom according to planned
milestones, as well as the results of feedback from program participants. The proposed project includes: (1) A bi-level
river tank (including two tanks) spanning the length of one wall. Featuring running water, live animals and plants found
in our rivers, a tall tank that is flush with the wall will function as an exhibit. A second lower tank in front will hold water
and be accessible for children's hands-on activities. This will create opportunities for programs that illustrate
engineering, physics and physical processes. (2) Behind the tanks, an original wall mural will illustrate the different
habitats that make up the watershed. (3) Additional classroom components will connect children to their environment,
such as a "Where Are You in the Watershed?" interactive. (4) Individual tanks will bring other freshwater and estuary
habitats to life, like the bay.
BenefitsThe proposed project aligns well with the District's mission to foster increased environmental stewardship of our
freshwater resources. Over the course of five years, these features will directly benefit an estimated 15,500 teachers
and students in watershed education programs. While the current educational programming primarily reaches students
and teachers throughout Hillsborough County, it also draws schools from Polk, Pinellas, Pasco and Manatee counties.
Costs
The total proposed cost of the new FY2011 program is $216,000, with the District requested to contribute $108,000
(Alafia River $25,920; Hillsborough River $54,000; Coastal Rivers $5,400; Pinellas-Anclote River $6,480;
Withlacoochee River $5,400; Peace River $5,400; Manasota $5,400). The dollar amount allocated per basin is
determined by the number of participants projected to participate in the programming from each basin. District funding
is requested for 3 tanks used as exhibits, interactive software development and a custom wall mural. The program
proposes to reach 3,000 students and 100 teachers during one year and 15,500 pro-rated over 5 years, the typical life
span of an exhibit. The cost to the District $6.97 per person is lower than average; however, the cost per contact hour
($4.65) 58% higher than average.
021 - Manasota Basin 306
N268
Watershed Education Classroom
District Budgeted - Ad Valorem Based
Revenue
011 Alafia River Basin 25,920 0 0 0 25,920 0
013 Hillsborough River Basin 54,000 0 0 0 54,000 0
015 Coastal Rivers Basin 5,400 0 0 0 5,400 0
016 Pinellas-Anclote River Basin 6,480 0 0 0 6,480 0
019 Withlacoochee River Basin 5,400 0 0 0 5,400 0
020 Peace River Basin 5,400 0 0 0 5,400 0
021 Manasota Basin 5,400 0 0 0 5,400 0
Project Funds Not Budgeted by the
District
The Florida Aquarium, Inc. 108,000 0 0 0 108,000 0
$216,000 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of:
021 - Manasota Basin 307
N273
Sarasota County Park Facility Construction
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementWater Quality Water Quality MonitoringWater Supply Alternative Water Supply
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a low priority. The project application requests funding for restroom and concession facilities that do not
directly save water resources and will be used to replace an old facilitywith a new one. The proposed low flow toilets
and plumbing fixtures planned to be installed are required by ordinance. No savings data has bee provided in order to
justify the cost of a planned cistern that will be used for toilet flushing and irrigation. This project is located in the
Southern Water Use Caution Area (SWUCA). There is insufficient information provided to evaluate the project. The
cooperator has confirmed it will include the necessary matching funds in its capital budget for FY2011. This project is
within the District's statutory authority to fund and is not the result of a permit requirement or enforcement action.
DescriptionThis project will construct a new multi-purpose facility at the North Jetty Park in Sarasota County. The facility will
include ADA-compliant restrooms and a family-style concession area with an outdoor plaza and seating areas. The
site and structure design include sustainable design concepts such as: Use of a cistern to harvest rainwater for use in
toilet flushing and irrigation; Durable finishes to decrease the need of ongoing staff maintenance; Climate-appropriate
landscape with irrigation limited to a one-year time frame for establishment; Low-flow fixtures to reduce water usage;
No increase to current impervious calculations by removing existing impervious areas to allow for structure and
ADA-compliant parking calculations; Additional use of bio-swales to add additional stormwater treatment to the site;
And, for the benefit of nearly 345,000 visitors annually, this site will also feature educational signage regarding the
sustainable features of the building such as the use of non-potable water for toilet flushing. Construction is scheduled
to begin in 2011 and will be in phased so that existing restrooms can be used during the construction period.
BenefitsThis new facility plans to use of a cistern to harvest rainwater for use in toilet flushing and irrigation. This practice will
conserve potable water, however, it remains unclear how much, or if, water has been currently used for similar
purposes at the older facility. Insuffient data was provided to calculate the amount of potable water saved.
Costs
The total project construction costs are estimated to be $1,450,000 in FY2011. The District's share is $250,000 from
the Manasota Basin Board in FY2011. The cost benefit cannot be calculated since no quantifiable benefits have been
provided in the application.
Additional Information
The North Jetty Park was acquired by Sarasota County in 1977 and is composed of 19 acres of gulf and bay shoreline
located at the south end of Casey Key. It is bordered by the Gulf of Mexico to the west, Venice Inlet on the south and
the Intracoastal Waterway on the east. The current structure, built in 1981, is not ADA-compliant, nor makes efficient
use of water resources. Funding has been acquired for a new facility as part of the County Local Economic Stimulus
program but is for design only. The design contract was approved on March 17, 2009 by the Sarasota County
Commission with CPH Engineers for the new multi-purpose facility which will include ADA-compliant restrooms, as
well as a family-style concession area with an outdoor plaza and seating areas. The county considers itself a leader in
water conservation. A tiered rate structure, in place since November 1991, promotes water conservation by penalizing
high water consumption. Since 1995 a toilet rebate program has replaced over 8,000 high flow toilets. Another
program provided rebates for rain shut-off devices to help educate the public about Ordinance 96-021 requiring this
device to be installed and functioning on all automatic sprinkler systems. Our Showerhead Exchange program (10,000
replaced) helps to retrofit buildings built before adoption of Ordinance 94-001 requiring low-flow fixtures in new
construction.The Water-Efficient Landscape Ordinance 2001-081 won a statewide award for innovation. Irrigation
restrictions are enforced by code enforcement officers, meter readers, and volunteers, that allow for once-a-week
irrigation. Every resident suspected of an irrigation violation is mailed a letter with educational material.
021 - Manasota Basin 308
N273
Sarasota County Park Facility Construction
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 250,000 0 0 0 250,000 0
Project Funds Not Budgeted by the
District
Sarasota County 250,000 0 0 0 250,000 0
$500,000 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Design Complete 12/30/09
Construction Start 12/30/11
Construction Complete 12/1/12
Status As Of:
021 - Manasota Basin 309
N294
Sarasota County Outdoor Conservation Kits
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply Conservation
Basin(s) Manasota
Sarasota CountyCooperator(s)
Project Manager MCGOOKEY, SCOTT
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a low priority. The project application requests funding to provide outdoor conservation kits to homeowners in
the County's utility service area. The County has not determined a way to estimate the water saved with each kit. This
project is located in the Southern Water Use Caution Area (SWUCA). There is sufficient information provided to
evaluate the project. The cooperator has confirmed it will include the necessary matching funds in its capital budget for
FY2011. This project is within the District's statutory authority to fund and is not the result of a permit requirement or
enforcement action.
DescriptionThis project will purchase and distribute 1,000 Outdoor Water Conservation kits. The outdoor water conservation kits
include a water saving hose nozzle, a hose timer, hose repair kit, soil moisture sensor, rain gauge, and educational
materials on water conservation. The kits will be available to Sarasota County Utility customers on a first come-first
served basis until the supply of 1000 kits has been depleted. The distribution of kits will be followed up with a survey of
those who received the kits to determine if and how the kits were used. Outdoor water use for lawn irrigation accounts
for a large percentage of the total water usage in Sarasota County.
BenefitsThe stated goal for this project is to provide citizens with a kit that will help them reduce their total outdoor water usage
and to educate them about efficiencies and practices that support Water Conservation. The County has not yet
determined a way to estimate the water saved with each kit, and there is no education plan associated with the project.
Costs
The total project costs are estimated to be $25,000. The District's share is $12,500, or fifty percent, which is being
requested from the Manasota Basin Board in FY2011. The cost benefit cannot be calculated since the savings per kit
is not quantifiable.
Additional Information
A tiered rate structure, promotes water conservation by penalizing high water consumption. A toilet rebate program
has replaced over 8,000 high flow toilets. Another program provided rebates for rain shut-off devices to help educate
the public about Ordinance 96-021 requiring this device to be installed and functioning on all automatic sprinkler
systems. Our Showerhead Exchange program (10,000 replaced) helps to retrofit buildings built before adoption of
Ordinance 94-001 requiring low-flow fixtures in new construction. The Water-Efficient Landscape Ordinance 2001-081
won a statewide award for innovation. Irrigation restrictions are enforced by code enforcement officers, meter readers,
and volunteers, that allow for once-a-week irrigation. Every resident suspected of an irrigation violation is mailed a
letter with educational material. Sarasota County has applied to be a Promotional Partner with the EPA's WaterSense
Program as another means of expanding our Water Conservation efforts and the Board of County Commissioners will
be passing a Resolution to support this initiative. In light of the ongoing Water Shortage declarations within the
Southwest Florida Water Management District, Sarasota County recognizes this project as an opportunity to expand
our Water Conservation efforts. We view this project as a pilot for future projects of this nature.
021 - Manasota Basin 310
N294
Sarasota County Outdoor Conservation Kits
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 12,500 0 0 0 12,500 0
Project Funds Not Budgeted by the
District
Sarasota County 12,500 0 0 0 12,500 0
$25,000 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
MilestonesDevelop FY11 Coopertive Funding Agreement 10/1/10
Begin to Advertise kit availability via utility bills and website 10/1/11
Purchase Water Conservation Kits 10/28/11
Start Follow up surveys 11/1/11
Begin Distribution of Kits 11/1/11
End Surveys 9/28/12
End Kit Distribution 9/28/12
End Advertising of kits 9/28/12
Ongoing Distribution of Educational MaterialsStart Distribution of Education Materials 10/3/11
Status As Of:
021 - Manasota Basin 311
N297
PRMRWSA Water Supply Construction & Operations Educational
VideoProject Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water SupplyWater Supply Regional Water Supply Planning
Basin(s) Peace River, Manasota
Peace River/Manasota Regional Water Supply Auth.Cooperator(s)
Project Manager ROE, MELISSA
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a low priority. Although the District recognizes the signficant value of the reservoir, staff ranks this project low
priority for several reasons. While the project's promotional benefit to the cooperator is obvious, the benefit to the
District is less clear. In addition, based on staff's experience, interest in the subject matter may be overestimated by
the cooperator. Although water managers would no doubt find a documentary on the building of a reservoir to be
"interesting and entertaining," members of the general public and students would be less likely to do so. Ideas for
placement of the documentary on various television venues are discussed in the proposal, but there there is no clear
indication that the documentary would be broadcast on those channels. There is also no evidence in the proposal that
schools have agreed or would agree to use use the video in the targeted "50% of local junior high and high schools in
the service area." The last concern is with cost. Staff estimates the costs for the $85,000 project are significantly
higher than would be expected.
DescriptionThis Cooperative Funding Initiative (CFI) project proposes to use existing video and photographs from the recently
completed six billion gallon reservoir and 24 mgd expansion of the Peace River Water Treatment Facilities, and new
video of Peace River water treatment facility operations to develop a 30-minute educational documentary video. The
proposed target audience for the documentary is schools, local community programming including public access
channels throughout the four-county region, as well as venues such as The Learning Channel, etc. The documentary
would show how a large above-ground earthen reservoir and a major expansion at a conventional surface water
treatment facilities are completed from start to finish, including explanations of the function of components of the
reservoir and water treatment facility. New interviews and video would also be taken at the now operating facilities to
supplement existing footage and also to show how this system serves the drinking water needs of the public in an
environmentally sustainable manner.
BenefitsThe project proposes to create a video featuring the construction of the reservoir as a successful model for developing
cost-effective, sustainable water supplies.
Costs
The total proposed cost of the FY2011 project is $85,000, with the District requested to contribute $42,500 (Governing
Board $21,250; Manasota $15,300 and Peace River $5,950).The cooperator estimates the project will reach 100,000
residents at a cost to the District of $0.85 per person.
District Budgeted - Ad Valorem Based
Revenue
020 Peace River Basin 5,950 0 0 0 5,950 0
021 Manasota Basin 15,300 0 0 0 15,300 0
Project Funds Not Budgeted by the
District
PRMRWSA 42,500 0 0 0 42,500 0
$63,750 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
021 - Manasota Basin 312
N310
Venice Greenhouse Rain Harvest System
Project Type Cooperative Funding
AORs Strategic InitiativesWater Supply ConservationWater Supply Alternative Water Supply
Basin(s) Manasota
State College of FloridaCooperator(s)
Project Manager MUSICARO, MELISSA
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Fund as a low priority. The anticipated water savings are very low and the cost benefit is not favorable. In addition, the
project does not offer a regional benefit if evaluated as a demonstration project. Additional information was requested
to evaluate this project, and was provided to District staff. There are a few items that still need to be addressed. The
project is within the basin board's statutory authority to fund and it is not a result of a permit requirement or
enforcement action.
DescriptionThe proposed project is to install a rainwater harvesting system at the State College of Florida, Manatee-Sarasota
(SCF). The rainwater harvesting system will be used to reduce the amount of potable water utilized used in the
greenhouse and to educate staff and students on the benefits of these systems. The college plans to use the rainwater
harvesting system in their curriculum to educate students on water conservation and alternative water soruces. The
greenhouse currently uses tap water in its sinks and irrigation system. The rainwater harvesting system will capture
rain water from the roof of the greenhouse, collect it into one or more above ground storage tanks and then store it in
the storage tanks until it is needed for irrigation and general cleaning in the green house. The system will also include
a water purification system, digital wireless control and monitoring system, and micro-irrigation system.
BenefitsThe project will save 100 gallons per day. The primary benefit from this project is education, in which the audience
would be staff and students. The greenhouse is located on the school campus, where public access is limited.
Costs
The total project cost is $15,860, and the Manasota Basin Board is requested to fund $7,930 in FY2011. The cost
amortized at 8 percent over 10 years, is $63.26 per thousand gallons saved.
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 7,930 0 0 0 7,930 0
$7,930 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
Phase IDesign of Rain Harvesting System 10/29/10
Pre-test survey of students 11/30/10
Construction of Rain Harvest System 11/30/10
Post-test survey of students 4/29/11
Compile and develop project data 6/30/11
Status As Of:
021 - Manasota Basin 313
N082
City of North Port Myakkahatchee Creek Water Treatment Plant
RBF/RO Reliability ProjectProject Type Cooperative Funding
AORs Strategic InitiativesWater Supply Alternative Water Supply
Basin(s) Manasota
City of North Port - Public UtilitiesCooperator(s)
Project Manager FERGUSON, JOHN
GOODWIN, AUDRIE, ARMSTRONG, BRIANTask Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Not Recommended. Although this a viable, ongoing AWS project that has received prior funding in FY2009 and
FY2010, the development of additional supply is not currently considered a high priority due to available, unused
quantities within the region. There is currently a large surplus of regional water supply available for use within the
region for which the District has previously funded. In addition, the District is currently engaged in developing
transmission systems to distribute regional supplies. By District policy, these regional distribution projects must be
ranked higher than local projects. Lastly, as indicated in Policy 130-4, the evaluation of revised project costs recently
provided to the District indicate that the City's unit cost is now below the purchase cost of Distribution Pool water from
the Authority, negating the need for additional funding. District staff still appreciate the innovative approach and the
project's importance for maintaining the reliability of the City's current surface water treatment plant and meeting
required water quality stadards, but recognize the economic climate and the requisite of regional investment.
DescriptionThis project is being designed to treat brackish water using reverse osmosis for the production of 1.5mgd of finished
water. The water will be used for blending with the City's existing surface water treatment facility. The project allows
North Port to operate their existing 2.2 mgd Myakkahatchee Creek facility year round and meet required total dissolved
solids standards. The City is currently operating under a Department of Environmental Protection variance for
exceeding TDS that expires on July 2012. The project also provides an additional 1.3 mgd of supply bringing the total
finished potable water supply capacity of the Myakkahatchee Creek facility will be 3.5 mgd.
BenefitsDevelopment of this project will allow the Myakkahatchee Creek facility to operate year round, meet TDS requirements
and develop additional alternative water supplies within the SWUCA.
Costs
The total project cost of the RBF/RO project is now estimated at $13,100,000. This cost includes pilot studies and
existing facility upgrades paid solely by the City of North Port. The District eligible costs are $12,100,000 for the RBF
and RO facilities, with the requested District share being $6,050,000. District funding is provided entirely by the
Manasota Basin Board. District funding budgeted to date (FY2009 and FY2010) is $1,400,000 from the Manasota
Basin Board. The City's FY2011 funding request is for $2,500,000. This amount will be used for the design and
construction of the RBF system and the RO facility. RO facility construction is scheduled to begin during FY2011. The
City has accrued $9,000,000 funds from previous years in preparation for the project, and is able to match the funding
request.
Additional Information
The objective of this project is to increase the reliability of the MCWTP and meet water quality regulations. The
MCWTP is located at the confluence of Myakkahatchee Creek and the Cocoplum canal and is permitted to withdraw
from both water bodies, but both sources exhibit considerable seasonal variability in flow and water quality. The
MCWTP currently operates under a water quality variance for TDS which expires on July 25, 2012. The City has
stated that without quality water from the RO system for blending, the MCWTP would not meet standards, requiring
them to consider decommissioning the facility and purchasing additional water from the Peace River/Manasota
Regional Water Supply Authority and/or develop brackish groundwater wellfields. In July 2008, the City completed a
Water Treatment Plant Enhancement Study to evaluate treatment alternatives that would increase the reliability and
water quality of the MCWTP. The MCWTP Enhancement Study proposed the improvements for the existing
conventional MCWTP as well as the integration strategy of the new RBF-RO facility. This study included an
assessment of the existing conventional MCWTP, along with preliminary pilot test results evaluating reverse osmosis
(RO) in combination with river bank filtration (RBF) pre-treatment for reducing TDS and sulfate. According to the
study, 1.5 mgd from the RO facility could be blended with finished water from the existing system to meet the
regulatory limit of 500 mg/l TDS. This would allow the MCWTP to operate on a consistent and year-round basis
instead of being limited to seasonal operation. In addition, this project will provide an additional 1.3 mgd of supply.
021 - Manasota Basin 314
N082
City of North Port Myakkahatchee Creek Water Treatment Plant
RBF/RO Reliability Project
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 7,163,527 3,250,000 0 901,943 2,505,630 505,954
Project Funds Not Budgeted by the
District
City of North Port 10,582,000 0 0 4,332,000 3,010,000 3,240,000
$17,745,527 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
RBF facilites permitting complete, construction commence 6/1/10
RBF construction complete 1/31/11
RO facilities construction commence 3/2/12
RO facilities construction complete, start-up 12/31/12
Final Project Complete 6/1/13
Status As Of: March 11, 2010
The City of North Port completed the four-month pilot-scale test of the RBF-RO system and published the pilot study in
October 2008. The City continued the pilot skid operation and data gathering for several additional months through the
sponsorship of a company conducting R&D of system components. District staff met with City staff on January 6, 2009,
to discuss portions of the project eligible for funding and details of the Cooperative Funding agreement. The District
clarified that funding would be for RBF/RO treatment, and the improvements to the existing facility were ineligible. The
Cooperative Funding Agreement between the District and the City was executed on March 17, 2009. On May 28, 2009,
The City selected McKim & Creed as the Consultant for permitting, design, and construction management services of the
RBF/RO project. The Consultant proposed using a series of horizontal wells parallel to the Cocoplum Canal for the RBF
system. The City held the Project kick-off meeting on July 9, 2009. On August 5, 2009, the District sent a letter to the City
of North Port explaining that staff were recommending a budget of $500,000 for FY2010 funding, due to budgetary
restraints. The City's FY2010 cooperative funding request was for $3,240,000. The letter also explained that the District
may not be able to fund a full 50% share of the project, but recognizes the public benefit of the project and its importance
to the City. Future funding is contingent on the annual approval of the Manasota Basin budget. The Consultant submitted
a Well Testing Program to the District for review on October 29, 2009. The test will consist of the installation of a
horizontal well in the upper potion of the intermediate aquifer. An aquifer performance (APT) test will be conducted to
determine the amount of infiltration induced from the Cocoplum Canal by the horizontal well. The City has expressed that
if APT test results are unfavorable, they would consider an alternate pretreatment method such as nanofiltration from a
surface water intake. The Project is ahead of schedule and on budget. The City has commenced construction the
horizontal well and associated monitor wells for the APT test. Testing is tentatively scheduled to begin on March 10,
2010. Due to the unique nature and purpose of the horizontal test well, the Department of Health deferred the test well
construction permit to District Regulatory Staff. The District issued the test well permits on March 17, 2010.
021 - Manasota Basin 315
N266
City of North Port - Como Waterway Water Control Structure
Project Type Cooperative Funding
AORs Strategic InitiativesWater Quality Water Quality Maintenance and ImprovementFlood Protection Floodplain Management
Basin(s) Manasota
City of North PortCooperator(s)
Project Manager FRIES, GEORGE
Task Manager(s)
Status Proposed Coop. Funding Application
Recommendation
Not recommended. There are substantive issues that must be addressed prior to funding the construction of this
project, such as, what is the impact on Charlotte County if the flow in Como Waterway is reduced or eliminated? What
will the impact be on the properties upstream if the water level in Cocoplum Waterway and Como Waterway is raised
by up to 4 feet? Are there any other unforeseen impacts associated with raising the water level in these waterways?
Until these questions are satisfactorily addressed, this project should not be funded.
DescriptionThis is a project to perform the Implementation of Best Management Practices (BMPs) element of the District's
Watershed Management Program (WMP) within the Cocoplum Watershed in the City of Northport. Implementation of
BMPs includes the following tasks: design, development of construction documents, construction permitting, land
acquisition, bidding and contractor selection, construction of the BMPs and construction engineering and inspection.
The Cocoplum Waterway is a major east-west canal as well as a receiving canal for all the other north-south man
made canals within the City. A total of 81 miles of wet canals and 69 water control structures (WCS) are located within
the City's borders. Of these 69 structures, 31 are equipped with gates that can be opened in a stepwise fashion to
release water either to the Creek or Cocoplum Waterway. The Cocoplum Waterway is also connected to several
canals that flow in a southerly direction into Charlotte County. There are control structures at all these connections,
except at the Como Waterway. Due to the lack of a water control structure at this point, approximately 4 feet of water
in the Cocoplum Waterway escapes into the Como Waterway. At periods of high tide and storm surge, the Cocoplum
Waterway is also vulnerable to brackish water back-flowing into the canal and mixing with the fresh water. For
FY2011, the City requested funding for the following tasks: design, development of construction documents,
construction permitting, bidding and contractor selection, construction of the BMPs and construction engineering and
inspection.
BenefitsThe project will improve level of service deficiencies by improving conveyance within the service area. In addition,
construction of the water control structure will improve water quality and will provide some storage of fresh water.
Costs
The estimated cost for this project is $450,000 of which the District's share is $225,000 and the City's share is
$225,000. The probable construction costs are based on a BMP analysis developed by the cooperator. The District
funding amount shown in the table includes staff salaries.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of BMPs, and 5) Maintenance of Watershed Parameters and Models.
Implementing elements of the WMP with local governments is one of the District's Strategic Priorities. The WMP
provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality and natural
systems, while achieving flood protection. This project involves the Implementation of BMPs which includes
construction of the BMPs. Funding is included to complete the implementation of the BMP. A cooperative funding
expenditure agreement with the City will be developed for Implementation of BMPs. The City will manage the project,
where the District project manager must approve any agreements to accomplish project tasks.
021 - Manasota Basin 316
N266
City of North Port - Como Waterway Water Control Structure
District Budgeted - Ad Valorem Based
Revenue
021 Manasota Basin 227,305 0 0 0 227,305 0
Project Funds Not Budgeted by the
District
City of North Port 225,000 0 0 0 225,000 0
$452,305 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
August 2010Design and permit of structure 8/18/10
August 2011Construction 8/18/11
Status As Of:
021 - Manasota Basin 317
M110
Manatee - FEMA Map Modernization
Project Type FEMA/Map Mod.
AORs Strategic InitiativesFlood Protection Floodplain Management
Basin(s) Manasota
Federal Emergency Management AgencyCooperator(s)
Project Manager LETASI, SCOTT
NGUYEN, NAMTask Manager(s)
Status Not Funded
DescriptionThis project is to perform Federal Emergency Management Agency (FEMA) flood insurance rate map (FIRM)
modernization which includes 1) Topographic Information, 2) Watershed Evaluation, and 3) Watershed Management
Plan elements of the District's Watershed Management Program (WMP) for numerous Manatee County watersheds.
The County covers an area of approximately 762 square miles. Under this project the FIRMs will reflect updated flood
hazard risk areas and be modernized to a digital product.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain management and water quality management. The FIRMs are used by local governments for
land management and building permitting to satisfy the minimum requirements of the National Flood Insurance
Program.
Costs
The total budget amount for this project is $900,000. FEMA is expected to contribute all the funds for the project in
FY2008. When each element is completed the project budget will be refined based on the information gathered.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. The District is cooperating with
FEMA to modernize the FIRMs in Manatee county. Information developed with this project will be used to update and
modernize the FIRMs for the entire county. Staff has worked with the FEMA to improve and formalize the District's
relationship with a federal agency that shares flood protection responsibilities. FEMA and the District executed a
Cooperating Technical Partners (CTP) Memorandum of Agreement on September 14, 2001. As a CTP, the District is
eligible for federal grants and matching funds to further efforts to modernize the flood insurance rate maps (FIRMs).
The District executed a Mapping Activity Statement with FEMA that identifies costs, responsibilities, and specific
activities to complete the FEMA Map Modernization effort for watersheds in Manatee county. The District will
coordinate with the local government(s), will manage the project, and will enter into purchase orders and agreements
to accomplish project tasks. With FEMA funding several tasks of the Watershed Evaluation and Watershed
Management Plan elements for priority watersheds within the County will be accomplished. Watersheds will be
prioritized based on the needs of the local governments and the District. Because of funding constraints some
watersheds will not be studied in detail. The risk information from the current FIRMs will be transferred to the
modernized, digital maps. These watersheds will be studied in detail when additional funding is available through the
cooperative funding process. Work on the Watershed Management Plan element for the priority watersheds will
include the following tasks: survey, data management and development of watershed parameters, GIS processing,
computer modeling, and floodplain analysis. Future cooperative funding request(s) will be required to complete
remaining Watershed Evaluation and Watershed Management Plan tasks (e.g. LOS determination, surface water
resource assessment, and BMP alternative analysis).
021 - Manasota Basin 318
M110
Manatee - FEMA Map Modernization
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 1,735 0 0 879 856 0
District Budgeted - Outside Revenue
FEMA Coop Tech Partner Agreemnt 900,000 0 0 900,000 0 0
$901,735 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Status As Of: September 01, 2009
Status Update: This project is currently on hold. The District has not received funding from FEMA; therefore the project
can not be started.
021 - Manasota Basin 319
M115
Sarasota - FEMA Map Modernization
Project Type FEMA/Map Mod.
AORs Strategic InitiativesFlood Protection Floodplain Management
Basin(s) General Fund (District), Manasota
Federal Emergency Management AgencyCooperator(s)
Project Manager TURNER, DAWN
Task Manager(s)
Status Ongoing
DescriptionThis project is to perform Federal Emergency Management Agency (FEMA) flood insurance rate map (FIRM)
modernization which includes 1) Topographic Information, 2) Watershed Evaluation, and 3) Watershed Management
Plan elements of the District's Watershed Management Program (WMP) for numerous Sarasota county watersheds.
The county covers an area of approximately 570 square miles. Under this project the FIRMs will reflect updated flood
hazard risk areas and be modernized to a digital product.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain management and water quality management. The FIRMs are used by local governments for
land management and building permitting to satisfy the minimum requirements of the National Flood Insurance
Program.
Costs
The total budget amount for this project is $2.42 million. FEMA is contributing $2 million for the project. $420,000 in
Manasota Basin Board funds approved in FY2004 for project L019 were used towards updating the digital topographic
information for the entire County in conjunction with this FEMA map modernization effort. When each element is
completed the project budget will be refined based on the information gathered.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. The District is cooperating with
FEMA to modernize the FIRMs in Sarasota County. Information developed with this project will be used to update and
modernize the FIRMs for the entire county. Staff has worked with the FEMA to improve and formalize the District's
relationship with a federal agency that shares flood protection responsibilities. FEMA and the District executed a
Cooperating Technical Partners (CTP) Memorandum of Agreement on September 14, 2001. As a CTP, the District is
eligible for federal grants and matching funds to further efforts to modernize the flood insurance rate maps (FIRMs).
The District executed a Mapping Activity Statement with FEMA that identifies costs, responsibilities, and specific
activities to complete the FEMA Map Modernization effort for watersheds in Sarasota county. The District will
coordinate with the local government(s), will manage the project, and will enter into purchase orders and agreements
to accomplish project tasks. With FEMA funding several tasks of the Watershed Evaluation and Watershed
Management Plan elements for priority watersheds within the county will be accomplished. Watersheds will be
prioritized based on the needs of the local governments and the District. Because of funding constraints some
watersheds will not be studied in detail. The risk information from the current FIRMs will be transferred to the
modernized, digital maps. These watersheds will be studied in detail when additional funding is available through the
cooperative funding process. Work on the Watershed Management Plan element for the priority watersheds will
include the following tasks: survey, data management and development of watershed parameters, GIS processing,
computer modeling, and floodplain analysis. FEMA is responsible for working with the local communities for the
adoption of the DFIRMs. Future cooperative funding request(s) will be required to complete remaining Watershed
Evaluation and Watershed Management Plan tasks (e.g. LOS determination, surface water resource assessment, and
BMP alternative analysis).
021 - Manasota Basin 320
M115
Sarasota - FEMA Map Modernization
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 104,813 0 0 74,055 14,174 16,584
District Budgeted - Outside Revenue
FEMA Coop Tech Partner Agreemnt 2,000,000 0 0 2,000,000 0 0
$2,104,813 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. FEMA Cooperative AgreementCooperating Technical Partners Memorandum of Agreement 9/14/01 9/14/01
Cooperating Technical Partners Agreement Executed 8/12/02 8/12/02
Mapping Activity Statement Executed 9/30/03 9/26/03
01A - Scoping 8/30/04 8/30/04
02 - Digital Topographic Data Development 10/1/04 5/31/08
03 - Independent QA/QC of Topographic Information 11/1/04 5/31/08
01C - Review of Existing Info, Reconnaissance, & Field Surveys 2/1/05 7/31/06
04 - Hydrology 2/1/05 7/31/08
06 - Hydraulics 2/1/05 7/31/08
05 - Independent QA/QC of Hydrology 3/1/05 8/31/08
07 - Independent QA/QC of Hydraulics 3/1/05 8/31/08
08 - Floodplain Mapping (Detailed & Redelineation) 4/1/05 7/31/08
09 - Independent QA/QC of Floodplain Mapping 5/2/05 8/31/08
10 - Base Map Acquisition and Preparation 5/2/05 7/31/08
11 - DFIRM Production 6/1/05 11/30/08
12 - Merge Revised and Effective Flood Hazard Data 6/1/05 11/30/08
12A - Application of DFIRM Graphic and Database Specs 6/1/05 11/30/08
13 - Issue Preliminary DFIRMs and FIS to Communities 9/2/05 11/30/08
01B - Outreach 10/1/05 11/30/09
14 - Post-Preliminary Processing (by FEMA) 12/2/05 11/30/09
2. Watershed Update Consultant (BCI)Execute Consultant Contracts for Watershed Updates 6/18/03 6/11/04
Execute Consultant Contract for Digital Topo Information 1/9/04 1/9/04
Contract Termination for Watershed Updates 1/8/07 1/8/08
3. Watershed Update Consultant (JEA)Execute Consultant Contracts for Watershed Updates 6/1/04 6/10/04
Execute First Amendment 3/31/06 3/13/06
Contract Termination for Watershed Updates 6/26/06 12/31/08
First Amendment to 04CONC0000040-B 5/15/08 10/20/08
4. DFIRM Consultant Agreement (URS)Execute Consultant Contract for DFIRM Production 1/9/04 1/15/04
Contract Termination for DFIRM Production 1/14/07 7/14/08
Execute No Cost, Time Extension 3/16/07
Status As Of: February 18, 2010
1. FEMA: In March 2008, staff submitted a request to FEMA to request additional time to revise and update the
watershed models based on quality assurance reviews performed by the District, the County, local governments, and the
District's consultants. The request was approved, and the performance period was extended to March 31, 2009. Further
revisions, verification, and additions are necessary to appropriately represent the hydrologic and hydraulic characteristics
of the watersheds, and reflect 2007 terrain data. Additional time is also required to complete subsequent reviews, public
outreach on the preliminary floodplain information, and to accommodate a public review and comment period. An
additional time extension request was submitted to FEMA in March 2009 to extend the performance period through May
021 - Manasota Basin 321
M115
Sarasota - FEMA Map Modernization
31, 2010. The time extension has been approved. 2. Watershed Updates (BCI): The agreement with BCI was executed
on January 8, 2004 to conduct the scoping activity, and generate digital topographic information (DTI) via LiDAR for the
entire county. Notice to proceed (NTP) for Work Order (WO) #1 was issued effective January 15, 2004. WO#2 to
perform the scoping activity was executed on February 8, 2004; and NTP was issued effective January 15, 2004.
Delivery of DTI was delayed for well over a year. The delay impacted the schedules of all the other elements and
consultants contributing to this project. Project scoping was completed in August 2004. The First Amendment to BCI's
agreement was executed to include updates to the County's existing Dona/Roberts Bay and Lemon Bay watershed
models to reflect the new DTI, convert models from NAVD29 to NAVD88, and begin updating the Ainger and Forked
Creek models to the District's G&S. BCI completed the conversion for its assigned watersheds and deliverables were
received on January 23, 2006. The BCI Agreement was amended as of February 13, 2007 to extend the contract
termination date to January 8, 2008. BCI WO#4 was executed to allow BCI to complete remaining update tasks. Draft
models and associated GIS data for Curry Creek, Hatchet Creek, Alligator Branch, and the Island of Venice were
received on October 14, 2008. The submittal was reviewed by District staff, and comments were provided to BCI on
December 12, 2008. The $750,400 in FEMA funds encumbered to the agreement with BCI has been expended.
$587,281 in B206 funding is being used to completed the models, and the peer and public review process; of which
$454,919 has been expended to date. 3. Watershed Updates (JEA): Agreement JEA was executed and WO#1 issued
to update the existing Little Sarasota and Sarasota watershed model. JEA completed conversion of these models from
NGVD29 to NAVD88. WO #2 was then executed to begin the update of the Phillippi Creek watershed parameters and
model to the District's G&S. Deliverables were received in March 2007 and reviewed by District, County, and municipal
staff. It was determined that significant revisions were needed to address issues with the original model, and that the
work cannot be completed in time to use for DFIRM generation. Further updates to the Phillippi Creek model were
postponed. The consultant services agreement with JEA was amended to include floodway analyses and ArcHydro tool
development to automate repetitive hydrologic and hydraulic modeling tasks (M118). The First Amendment to JEA's
agreement was executed on March 13, 2006. WO#3 was executed on May 16, 2006 for the conceptual design of
ArcHydro tools. WO#4 was executed on May 8, 2007 to develop the ArcHydro tool for Irregular Weirs. WOr #5 was
executed to perform limited updates to the remaining Sarasota Bay and Little Sarasota Bay models, and convert the
lower Myakka River model to NAVD88. Draft deliverables were submitted for WO #5. WO #6 was issued to update the
Hudson and Whitaker Bayou models to reflect 2007 terrain data and incorporate ERP information. Draft deliverables
were received on November 3, 2008 and December 30, 2008 respectively. District and County review comments were
provided to JEA on December 3, 2008 and February 5, 2009 respectively. $729,550 of the FEMA funds have been
encumbered to the agreement with JEA, of which $673,575 has been expended. $140,291 in B206 funding are being
used to complete the models, and the peer and public review process, of which $119,821 has been expended to date. 4.
DFIRM Production (URS): The agreement with URS Southern was executed on January 15, 2004, to produce the
countywide Digital Flood Insurance Rate Maps (DFIRMs) and Flood Insurance Study (FIS), and to support public
outreach. The URS Agreement was amended twice, ultimately extending the contract expiration date from July 14, 2008
to June 1, 2010. WO #1 was executed on February 16, 2004 to identify the data to be used for DFIRM production, and
prepare a detailed approach and project outline. URS completed these tasks. WO #2 was executed to prepare the base
maps and perform outreach. URS submitted draft base maps and redelineations for review and approval in February
2009. District, FEMA, County, and local government staff reviewed the information and provided comments to URS in
April 2009. Staff executed WO#3 with URS to incorporate the final deliverables from model updates and the Big Slough
WMPlan (K883) to produce the preliminary DFIRMs and FIS. A meeting/conference call was held on June 29, 2007
between all consultants associated with the project to coordinate schedules, review deliverable requirements, and
identify points of contact. URS was asked to stop work on production of the preliminary DFIRMs until model updates are
completed. On March 24, 2008 WO#3 was re-issued to reflect the work completed before the stop work order. NTP for
WO#4 was issued on June 5, 2008 for the preparation of the DFIRMs, DFIRM database, and FIS report using the
watershed models that are currently under development, and watershed models previously developed by the County.
Several of the County models have not been signed and sealed by a professional engineer. The County has retained
professional engineers to review and certify the models. The following County models have now been certified, and have
been provided to the URS to include on the draft maps: Lemon Bay, Cow Pen Slough, Phillippi Creek, Little Sarasota
Bay, Lower Myakka River, Upper Myakka/Howard Creek. $520,000 of the FEMA funds have been encumbered to the
agreement with URS, of which $428,972 has been expended. $110,597 in B206 funding has been added to the
agreement to cover the cost of incuding the County's certified models and participate in public meetings.
021 - Manasota Basin 322
M118
FEMA Map Modernization Management Support
Project Type FEMA/Map Mod.
AORs Strategic InitiativesFlood Protection Floodplain Management
Basin(s) General Fund (District), Alafia River, Hillsborough River, Northwest Hillsborough, Coastal Rivers,
Pinellas-Anclote River, Withlacoochee River, Peace River, Manasota
Federal Emergency Management AgencyCooperator(s)
Project Manager TURNER, DAWN
Task Manager(s)
Status Ongoing
DescriptionThis project is to provide management support for Federal Emergency Management Agency (FEMA) flood insurance
rate map (FIRM) modernization projects throughout the District (please reference projects M101-M116). Under these
Map Modernization projects the FIRMs will reflect updated flood hazard risk areas and be modernized to a digital
product. The updated flood hazard risk areas are being developed by the District through the 1) Topographic
Information, 2) Watershed Evaluation, and 3) Watershed Management Plan elements of the District's Watershed
Management Program (WMP). Map Modernization management support (MMMS) funds supplement the ongoing
activities already being performed by staff including, but not limited to coordination and effort in building partnerships,
information technology systems, program management planning, hydrologic and hydraulic review, and outreach.
BenefitsThe WMP provides a method to evaluate the capacity of a watershed to protect, enhance, and restore water quality
and natural systems, while achieving flood protection. The information developed provides the science for the District's
Resource Management and Environmental Resource Permitting (ERP). It assists local governments: 1) With their land
management responsibilities by establishing a level of service and developing Best Management Practices (BMPs) to
address level of service deficiencies. 2) Provides a Geodatabase and projected results from watershed model
simulations for floodplain management and water quality management. The FIRMs are used by local governments for
land management and building permitting to satisfy the minimum requirements of the National Flood Insurance
Program.
Costs
The total amount for MMMS is $1,013,240 to be funded by FEMA. The District has received a total of $713,240 in
FEMA MMMS to date that has been included in the Governing Board's FY2005, FY2006, and FY2007 budgets as
revenue. District Staff anticipate an additional $150,000 to be funded by FEMA for ongoing MMMS activities in both
FEMA's FY2008 and FY2009 ($300,000 in total). Each year FEMA notifies the District how much funding is available
for MMMS. The District funding amounts shown in the table represents staff salaries.
Additional Information
The WMP includes five major elements: 1) Topographic Information, 2) Watershed Evaluation, 3) Watershed
Management Plan, 4) Implementation of Best Management Practices, and 5) Maintenance of Watershed Parameters
and Models. Implementing elements of the WMP with local governments is one of the Comprehensive Watershed
Management (CWM) initiative strategies and one of the District's Strategic Priorities. The District is cooperating with
FEMA to modernize the FIRMs throughout the District. Staff has worked with the FEMA to improve and formalize the
District's relationship with a federal agency that shares flood protection responsibilities. FEMA and the District
executed a Cooperating Technical Partners (CTP) Memorandum of Agreement on September 14, 2001. As a CTP,
the District is eligible for federal grants and matching funds to further efforts to modernize the FIRMs. Each year the
District enters into a cooperative agreement with FEMA for MMMS funding that defines the activities that will be
performed. $250,000 in funding (grant EMA-2004-CA-5038) for FY2005 is being used to provide a meeting facilitator
for ongoing coordination meetings between the water management districts, FEMA Region 4, and the Florida
Department of Community Affairs; develop a District-wide FIRM paneling scheme; determine the feasibility of
expanding the District's role in distributing digital FIRMs to the public; maintaining the digital FIRMs; and revising the
FIRMs simultaneously with the ERP application review. For FY2005, a total of $300,000 was actually budgeted in the
General Fund with associated revenue. The $50,000 difference between expected funding and actual was rolled into
the FY2006 budget. For FY2006 FEMA has granted (EMA-2005-CA-5244) the five water management districts
$120,000 in MMMS to hire an outreach facilitator and develop design storm rainfall depth criteria for the entire State.
The District will manage the project and contract with consultants on behalf of the other water management districts.
In addition, the District received additional MMMS ($144,000) in FY2006 to support outreach efforts, allow the District
to develop quality control/quality assurance tools, and support staff travel to meetings and conferences related to this
effort. For FY2007, the District has received $129,620 from FEMA (grants EMA-2006-CA-5631 and
EMA-2006-CA-5624) for continued travel support, outreach efforts, management assistance, and an XML-based
021 - Manasota Basin 323
M118
FEMA Map Modernization Management Support
export to for the District's Geographic Watershed Information System to populate FEMA's database. The District has
recently received an additional $69,620 under EMA-2007-CA-5723 for continued travel and programmatic assistance.
For FY2008, the District is proposing to budget $150,000 in revenue for continued MMMS. The District will coordinate
with the local government(s), will manage the project, and will enter into purchase orders and agreements to
accomplish project tasks.
District Budgeted - Ad Valorem Based
Revenue
010 General Fund (Districtwide) 73,515 0 (400) 51,444 8,165 14,306
District Budgeted - Outside Revenue
FEMA Coop Tech Partner Agreemnt 1,320,000 0 0 1,100,000 150,000 70,000
$1,393,515 Total:
Prior
Funding
Cumulative
Transfers Funding Funding
2010 FY 2011 FY Future
FundingTotal
Funding
Critical Project Milestones ActualProjected Amended
1. Critical Project MilestonesFEMA & District Recognition on Reports 3/31/10
2. FY2005Develop Mutually Agreeable Scope of Work for MMMS 9/30/04 9/30/04
Execute FEMA Agreement Articles and Related Forms 11/30/04 11/24/04
Develop Consultant Agreement 11/30/04 11/19/04
Draft Agreement to Management Services 1/7/05 1/7/05
Draft Agreement returned from Management Services 1/21/05 2/4/05
Contract Execution 3/4/05 3/1/05
Notice to Proceed 3/4/05 3/1/05
Develop First Amendment to Consultant Service Agmt 7/7/06 8/2/06
Draft Amendment to Management Services 7/12/06 8/2/06
Contract Termination 7/21/06 9/30/10
Amendment Execution 9/18/06 9/18/06
3. FY2006 - DistrictDevelop Cooperative Agreement for MMMS (District) 6/7/05 6/1/07
Execute FEMA Agreement Articles and Related Forms 10/31/05 12/2/05
District Outreach Facilitator Purchase Order Execution 2/28/06 3/2/06
District Outreach Facilitator Purchase Order Termination 12/31/06 12/31/06
3. FY2006 - FL WMDDevelop Application for competitive MMMS (FL WMD) 6/1/05 5/18/05
Execute FEMA Agreement Articles and Related Forms 10/31/05 12/2/05
Develop State Outreach Facilitator Purchase Order 1/30/06 2/21/06
State Outreach Facilitator Purchase Order Execution 2/28/06 3/2/06
Develop Rainfall Frequency Analysis Purchase Order 6/1/06 6/1/06
Rainfall Frequency Analysis Purchase Order Execution 6/30/06 7/20/06
State Outreach Facilitator Purchase Order Termination 12/31/06 12/31/06
Rainfall Frequency Analysis Purchase Order Termination 6/30/07 9/30/07
4. FY2007Develop Application for competitive MMMS 3/27/06 3/27/06
Develop Cooperative Agreement for MMMS 5/26/06 5/26/06
Execute FEMA Agreement Articles and Related Forms 9/22/06 9/28/06
Execute FEMA Agreement Articles and Related Forms 9/22/06 9/29/06
Develop XML-base Export System Purchase Order 11/30/06
021 - Manasota Basin 324
M118
FEMA Map Modernization Management Support
XML-base Export System Purchase Order Execution 11/30/06
Develop Map Modernization Program Assistance Agreement 7/31/07
Map Modernization Program Assistance Agreement Execution 9/30/07
XML-base Export System Purchase Order Termination 9/30/07
FY2008Develop Mutally Agreeable Scope of Work for MMMS 6/25/08 6/25/08
Execute FEMA Agreement Articles 6/25/08 6/25/08
Execute 76-10A Form 7/3/08 8/12/08
Status As Of: February 18, 2010
FY2005: A fully executed FEMA Form 76-10 to MMMS Grant, EMA-2004-CA-5038 has been returned to the District. The
form awards funds pursuant to the approved Statement of Work. Forms SF424 and FEMA 20-20 have also been
executed by the Executive Director and transmitted to FEMA to support these funds. The consultant agreement with
URS Corporation Southern was executed on March 1, 2005. All FY2005 funds have been encumbered via an
amendment to URS' agreement, which was executed in September 2006. Work Orders #1, #2, and #3 have been
executed. Work Order #1 is to incorporate a Hazard Mitigation Component into the District's Business Plan for Map
Modernization. Work Order #2 is to develop a District-wide flood insurance rate map (FIRM) paneling scheme to support
the District's efforts in modernizing and updating the FIRMs throughout the District. The draft paneling scheme has been
prepared and submitted to surrounding water management districts (South Florida, St. Johns River, and Suwannee
River). Work Orders #3 & #4 supply a moderator for ongoing coordination meetings among staff from the five water
management districts regarding Map Modernization and a Sharepoint site for staff to access minutes and associated
documents. Work Order #5 has been executed as of February 23, 2007, to determine the District's ability and resulting
issues of reviewing Letters of Map Change (LOMC) simultaneously with ERPs. Two meetings have been held with
District staff (MAN, TPA-REG, RPM), FEMA Region 4, and Hillsborough County staff. Work Order #6 directs the
consultant team to present how different types of developments are reviewed and permited by the District, FEMA, and
local government (Hillsborough County). The URS agreement expired on October 31, 2008. After the grant expired, the
remaining project funds were released, and re-encumbered to Agreements with Dewberry and with ESRI for MMMS
tasks. To date, $225,000 of the FY2005 funds have been expended. The remaining FY2005 funds will be used to create
a conversion tool to convert District GIS data into FEMA Data Capture Standards format. FY2006: FEMA provided
$144,000 in FY2006 for MMMS. An additional $120,000 was also provided by FEMA for the five water management
districts. These funds were approved to facilitate Map Modernization outreach for all five districts to support the
development of statewide isopluvial maps for various design storm events. The District will contract with consultants and
manage the projects on behalf of the other four water management districts. A purchase order was issued to UCF for
$60,000 to begin resolving design rainfall depth differences between WMDs. UCF has completed the literature review,
data collection, data quality assurance, statistical analysis of the rainfall data, and an initial spatial analysis of the data.
UCF requested a no-cost time extension to complete the project by December 30, 2007. Final deliverables have been
received and approved, and the final invoice has been paid. The District also received FEMA funidng for outreach
consulting services to support the Map Modernization effort of all the WMDs ($45,000), and for specific needs of the
District ($48,000). These funds were used to retain Bender Consulting to provide outreach planning support to review
completed and ongoing outreach efforts associated with each project and provide messages and direction to enhance
future outreach. Bender Consulting has completed all tasks and the purchase order has been closed out. A total of
$93,000 was expended. $63,000 in FY2006 funds were also provided for the development of quality control and
assurance tools. The funds were encumbered through an amendment to JEA's service agreements for the Sarasota
County Map Modernization (M115) project. The consultant agreement with Dewberry has been amended to include
$20,000 in FY2006 and $15,000 in FY2007 funds for ongoing meeting facilitators services. Remaining funds are to
reimburse the District for video conferencing expenses. Funds that have not been expended have been board
encumbered ($3000). FY2007: The District was granted an additional $60,000 in competitive MMMS for FY2007 to
develop tools to export from the District enhanced ArcHydro database to FEMA's data capture standards. In addition, the
District has been awarded $69,200 in MMMS from FEMA to continue travel associated with Map Modernization,
coordination meeting facilitation, and programmatic assistance. A Purchase Order was executed with ESRI to develop
ArcHydro tools, and a total of $60,000 was expended for this work. Of the remaining FY2007 funds ($53,961), $48,674 is
encumbered to an agreement with Dewberry for progammatic assistance and meeting facilitation, of which $3,209 has
been expended. Of the remaining $6,000 for travel, $1,063 has been expended. The remaining travel funds have been
Board encumberd. FY2008: The District received $69,620 in FY2008 funding for ongoing programmatic assistance
($63,620), and to reimburse the District for travel expenses related to Map Modernization projects ($6,000). FY2009:
FEMA notified the District that $69,000 in FY2009 FEMA funding has been awarded to the District, and this amoung has
been included in the District's FY2010 budget. However, the associated 76-10A form has not yet been received from
FEMA. To date, a total of $782,860 has been provided by FEMA for Map Modernization Management Support, of which
$518,136 has been expended.
021 - Manasota Basin 325
The Southwest Florida Water Management District (District) does not discriminate on the basis of disability. This nondiscrimination policy involves every aspect of the District's functions, including access to and participation in the District's programs and activities. Anyone requiring reasonable accommodation as provided for in the Americans with Disabilities Act should contact the District's Human Resources Director, 2379 Broad Street, Brooksville, Florida, 34604-6899; (352) 796-721 or 1-800-423-1476 (FL only), ext. 4702; TDD (FL only)1-800-231-6103; or email [email protected].