(c) Tomoichi Sato, JGC Corporation, 2006 1 PROMAC 2006 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project value analysis – contributed value and procurement cost Tomoichi Sato JGC Corporation

Upload: clarissa-waters

Post on 28-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 1

PR

OM

AC

2006

3rd International Conference on Project Management

28 September 2006

Sydney, Hilton

Risk-based project value analysis – contributed value and procurement cost

Tomoichi SatoJGC Corporation

Page 2: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 2

PR

OM

AC

2006

Introduction• Conventional approach: different methodologies for different

aspects of evaluation.

• New approach: single theoretical framework “RPV”

DCF method

EVMS

Bid tabulation

Project evaluation

Progress measurement

Procurement cost evaluation

Project evaluation

Progress measurement

Procurement cost evaluation

Risk-based projectValue (RPV)

Page 3: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 3

PR

OM

AC

2006Basic concept of the RPV (risk-based project value)

• Simple “project Z” with two tasks.• Initial cost = –20, sales revenue = 100. Risk factor = 50% and 10%.

Task B(sales)

Risk factor 10%$ -20 $100

Task A(development)

Risk factor 50%

Task B

Contributed value =

$10

Task A

Contributed value =

$45

RPV$70

RPV$25

$ -20

RPV$80

$100

• If 2 tasks complete successfully, obtained value = 100 – 20 = 80.• Expected revenue = 90 before task B, and 45 before task A due to risk

factors. Risk-based project value (RPV) = 70 and 25 respectively.

• Obtained (earned) value by task A = 70 – 25 = 45, for B = 80 – 70 = 10.

Page 4: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 4

PR

OM

AC

2006

RPV calculation method

• Initial RPV for single task project:

where, S=revenue, C=cost, r=risk factor (probability of failure).Risk factor r is subjective probability in Bayesian inference.

• Initial RPV for project with two tasks:

• RPV before task i for a project with multiple serial tasks:

where, Si, Ci, ri are revenue, cost, and risk factor of task i

CrSRPV )1(

1

11

11 i

kk

i

kk

i

N

ik

N

ikkkkk

i SCQ

QSQCRPV

i

jji rQ

1

)1(

11211122 )1()1()1)(1( CrCrSrrSRPV

1 2 i-1 i i+1 n

(1)

(2)

(3)

Page 5: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 5

PR

OM

AC

2006

Projects with parallel tasks

• Calculation of parallel tasks’ risk factors– If parallel tasks exists in a project (normally they do), combine them to make a

single task.

– Risk factor for the combined task (j*k) :

• Value contribution of parallel tasks– First, obtain value contribution of the combined task (j*k) :

– Then, divide it in proportion to the risk factors of task j and task k :

, and

kjkjkjkj rrrrrrr )1)(1(1*

ri rj

rk

rm ri rj*k rm

kjRPV *

kj

jkj rr

rRPV

*

kj

kkj rr

rRPV

*

(4)

(5)

Page 6: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 6

PR

OM

AC

2006

RPV and NPV in DCF method

• Net present value (NPV) of DCF method is based on “time value of money” concept; future cash flow should be discounted by cut-off rate (COR) to the present value. COR (R) is like interest rate and determined by capital costs.

• For a simple project with cost C and revenue S, NPV is calculated as:

• Risk-based approach: future revenue is reduced due to risk factor– Investor to this project may require risk premium R .– R should be determined so that the expected return is not less than loss in

failure.– Hence, as minimum,

• Therefore, two approaches gives the same result

• DCF method assumes flat risk factors throughout the project life cycle.

)1/( rrR

RPVCrSCR

SNPV

)1(1

CR

SNPV

1

rCCrR )1(

(6)

(7)(8)

(9)

Page 7: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 7

PR

OM

AC

2006

Value contributed by the task

• After successful completion of each task, RPV increases. This increment can be regarded as the value contributed, or “earned”, by the task.

• From equation (3), contributed value of task i can be obtained as:

• If we denote

then,

• These equations show that the value contributed by a task is proportional to its risk factor.

• If the task has no risk, there is no value contribution. The higher the risk is, the greater the contributed value to project.

)(1 iiiiii CRPVrRPVRPVRPV

i

N

ik

N

ikkkkk

i Q

QSQCH

1

1

)( 11 iiiiii SHrRPVRPVRPV

(10)

(11)

(12)

Page 8: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 8

PR

OM

AC

2006Progress measured by contributed task values

• Conventional Earned Value Analysis (EVA) has regarded the budgeted cost of each task as its value (BCWS).

• Progress measurement of EVA is defined as:

• In product development project, costs for early “soft tasks” are normally smaller. Successful development of product concept earns only small value.

• RPV approach gives greater values to early soft tasks with higher risks. Progress measurement should base on contributed value, enabling more meaningful progress control.

• Progress (%)

• If Task A successfully completes in “Project Z” in slide 3, project progress = 45 / (80 – 25) = 81.8 %.

BCWS

BCWP

01

1

PRVRPV

RPV

RPV

RPV

EV

EV

N

iN

kk

i

Task B

Contributed value =

$10

Task A

Contributed value =

$45

RPV$70

RPV$25

RPV$80

(13)

(14)

Page 9: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 9

PR

OM

AC

2006

Procurement cost evaluation process

• Typical process in the project procurement management

• Basic principles:– Inquire from multiple sources– Ensure “apple to apple comparison”. Create requisition to define vendor’s

scope of work and technical specification precisely.

• Procedure for the fair competition– bidders should submit technical proposal and commercial proposal

separately.– Technical professionals make technical clarification and evaluation without

looking commercial prices.– Select the vendor with the most commercially competent among

acceptable vendors.

Procure-ment Plan

Procure-ment Plan

Vendor survey

Vendor survey

Spec. &Requisition

Spec. &Requisition

InquiryInquiry Bid Tabulation

Bid Tabulation

Order placement

Order placement

Page 10: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 10

PR

OM

AC

2006

Risk-based cost evaluation

• Purchasing and outsourcing has always risks associated: fail to deliver products or services, fatal schedule delay, quality anomaly, bankruptcy, etc.

• How can we compare vendors: reliable but costly one vs. risky cheap one?

• From equation (10) and (11), we can deliver following formula:

• Note that Hi+1 is not dependent on Ci. Therefore, condition to select vendor A should be;

• Conventional vendor selection is based on price comparison (Ca < Cb). Equation (14) shows risk factors should also be taken into consideration.

i

iii r

CHRPV

1

11

(15)

b

bi

a

ai

r

CH

r

CH

1111 (16)

Page 11: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 11

PR

OM

AC

2006

Concept of the critical cost

• It is not always easy for each buyer to calculate Hi+1 on procurement stage. Much simpler approach is needed.

• Consider C* as the maximum cost payable to the procurement task. Its condition is;

• Comparing two vendors, the following relation can be delivered:

• we can define a new criteria Cr, “Critical Cost”, as follows:

• In comparison of more than one vendors, evaluate each Critical Cost Cr and select the smallest one.

oCHr iii *

1)1(

b

b

a

ai r

C

r

CH

11

**

1

r

CCr

1

(17)

(18)

(19)

Page 12: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 12

PR

OM

AC

2006

Critical cost vs. risk factor

Critical cost vs. risk factor

0

2

4

6

8

10

12

0 0.2 0.4 0.6 0.8 1

Risk factor (probability of failure)

Cri

tica

l co

st C

r(b

ase

: C

=1

)

Page 13: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 13

PR

OM

AC

2006Project portfolio value and

“extended DIPP”• Project portfolio value

– Remaining value of an ongoing project :

where, n = final task, i = current task

– RPV can be calculated at any timing, unlike DCF method which is limited in the planning phase. Enterprise project portfolio value is summation of all projects’ remaining values.

• Extended DIPP index– S. Devaux proposed “Simple DIPP” as an index to evaluate project

profitability; expected revenue divided by cost ETC.

– DIPP can be extended using RPV as follows:

– Extended DIPP normally reaches peak just before the production start.

n

ikk

in

C

RPVRPV

1

in RPVRPV

Page 14: PROMAC 2006 (c) Tomoichi Sato, JGC Corporation, 20061 3 rd International Conference on Project Management 28 September 2006 Sydney, Hilton Risk-based project

(c) Tomoichi Sato, JGC Corporation, 2006 14

PR

OM

AC

2006

Conclusion

• Theoretical framework of risk-based project value (RPV) analysis is proposed.

• RPV equals to NPV of DCF method if all tasks are supposed to have the same risk factors per time.

• RPV calculation method is presented for projects having complex task networks.

• RPV analysis can provide three application fields. – (1) Contributed value of tasks. – (2) Procurement cost analysis. – (3) Portfolio management.

• Further development with real project case studies is essential, and the author is glad to have any collaboration opportunities.