proportional balancing cpd
TRANSCRIPT
Andy Lucas Technical Development Manager CRANE BS&U
CRANE BS&U supporting the Building Services
Industry
Crane Co founded in 1855 by Richard Teller Crane who made the following resolution -
“I am resolved to conduct my business in the strictest honesty and fairness; to avoid all deception and trickery; to deal fairly with both customers and competitors; to be liberal and just towards employees; and to put my whole mind upon the business”
Crane Limited founded in Ipswich in 1919
Crane Building Services & Utilities created 2009
Building Services
Water UtilitiesGas Utilities
CRANE BS&U 2008 sales £102m
Water Utilities
Gas Utilities Building Services
Written by
Andy Lucas Technical Development Manager CRANE BS&U
CIBSE approved CPD
PROPORTIONAL BALANCING
PROPORTIONAL BALANCING
To give an overview of Proportional Balancing within the commission process
This process applies to both constant & variable flow heating and chilled water systems
Title
Objective
Commissioning
Definition:
The advancement of an installation from the state of static completion to full working order to specified requirements.
CIBSE Commissioning Code W
Why commission?
Requirement L1 of Part L of the Building Regulations in England and Wales requires that “reasonable provision shall be made for the conservation of fuel and power in buildings by
providing and commissioning energy efficient fixed building services with effective controls”
Commissioning
Commissioning
Why Balance?
Waters lazy – will take shortest route!
• nearest terminal hottest
• furthest terminal coldest
Balancing forces design flow rates to all areas
Commissioning
Preparation for Commissioning
• Installed in accordance with specification
• successfully pressure tested
• flushed & cleaned
• filled, treated & vented
• safe & ready to set to work
• all valves fully open
Installation must be
Commissioning
Pump shut-off (closed) head test
Pre
ssur
e
Flow Rate
closed head from manufacturer
• measure closed head
• check against pump curve
• draw parallel curve
• pressure at full flow – check against graph
• if flow and pressure co-inside with graph – pump performance OK
pump curvecorrected pump curve
measured closed head
Commissioning
Preliminary flow rate check
• measure flow - all valves open
• if less than 100% - will result in final balance being less than 100%
variable flow systems may have ‘diversity’ designed in
• set to 110% pump design flow rate
Commissioning
Full system scan
• measure all flow rates
• highlights problems
Proportional Balancing
What is it?
The systematic process of bringing the fluid flow rates throughout a distribution system into balance with one another, in their correct proportions and within
tolerances specified by the designer.
CIBSE Commissioning Code W
Proportional Balancing
• fixed speed pumps – no energy saving for part load
• constant volume of water is pumped around the system
• 3 or 4 port control valve diverts water through by-pass
• commissioned by proportional balancing or by the use of constant flow regulators – ABV (Automatic Balancing Valves)
Constant volume flow systems
Proportional Balancing
• variable speed pumps – energy saving for part load
• variable volume of water to match demand
• 2 port control valve
• commissioned by combination of;
proportional balancing
DPCV – Differential Pressure Control Valves
PICV – Pressure Independent Combination Valve
Variable volume flow systems
Proportional Balancing
Terms
• %DFR – Percentage Design Flow Rate
• Least Favoured/Index Circuit
• Reference Circuit
%DFR – Percentage Design Flow Rate
Proportional Balancing
measured flow
design flow%DFR = x 100
eg
%DFR = 0.07kg/s
0.10kg/sx 100 = 70%
Terms
Least favoured & index circuit are same
the least favoured/index circuit is the circuit, when system is unbalanced, having the highest pressure drop relative to all other circuits – ie lowest %DFR
Proportional Balancing
A ? B ? C ?
Terms - Least Favoured & Index circuit
Proportional Balancing
The reference circuit is the circuit, when system is unbalanced, that all other circuits will be balanced against
For proportional balancing, the furthest circuit or terminal unit must be the reference.
If this is not the same as the least favoured, it must be made into the least favoured by adding resistance, ie closing double regulating valve
A ? B ? C ?
Reference
add resistance
Terms - Reference circuit
Proportional Balancing
HighLow
Regulate
orifice
Δp
Signal - Δp (differential pressure) is measured
water
Net system pressure loss
Flow measurement valve
Proportional Balancing
To allow us to measure Δp generally we use 1 of 2 instruments
• U tube manometer fluorocarbon 0 - 4.6kPa mercury 0 - 65kPa
• electronic equipment up to 250kPa
Proportional Balancing
Δp measurement – U tube manometer
0
• zero Δp (differential pressure)
• measure Δp – ‘signal’
• equate to flow rate
Q = Kvs Δp
from graph
Δp
high low
0 1 2 3 4 5
Δp
Flow rate
1
2
36Kvs
Proportional Balancing
Δp measurement - electronic
Electronic flow measurement meters are pre-programmed with valve data, therefore, directly display
• differential pressure
• flow rate
• %DFR
Proportional Balancing
Procedure follows 4 stages
1. Measure (scan) each unregulated terminal to establish ‘least favoured’ & ‘reference’
2. Proportional Balance
3. Regulate flow
4. Complete test sheet
Proportional balancing
Measure each terminal
Proportional Balancing
STAGE 1 Measure each terminal
Design (kg/s)
Actual (kg/s)
%DFR
0.10 0.10 0.10 0.10
0.16 0.13 0.10 0.04
160% 130% 100% 40%
Identify least favoured/index
0.160 0.13 0.04 0.10
160% 130% 40% 100%
least favoured/index
Adjust to 110%DFR
Proportional balancing
Measure each terminal
Proportional Balancing
Make furthest equal to least favoured
Always remains index
made least favoured by regulating, ie adding resistance
0.04
40%40%
• add resistance to make furthest (the reference)
equal to least favoured
• if total flow rate drops bring back to 110% if furthest is reference/index then
regulating valve always fully open%DFR
Proportional Balancing
STAGE 2 Proportional Balance
Design (kg/s)
Actual (kg/s)
%DFR
0.10 0.10 0.10 0.10
reference
0.09
90%
0.091
91%
0.092
92%
0.092
92%
0.091
91%
0.092
92%
0.092
92%
Each terminal is Proportionally Balanced against each other working towards pump
Proportional Balancing
STAGE 3 Regulate flow
Design (kg/s)
Actual (kg/s)
%DFR
0.10 0.10 0.10 0.10
0.92 0.92 0.92 0.92
92% 92% 92% 92%
0.10 0.10 0.10 0.10
100% 100% 100% 100%
Adjust circuit commissioning valve to obtain 100%
Proportional Balancing
Larger circuit• 2 floors
• each with commissioning valve
• divided into 2 sub-circuits
• each with commissioning valve
• sub-circuit divided into 4 terminal branches
• each with commissioning valve
Proportional Balancing
• proportional balance each sub-circuit to reference, ie same %DFR
• sub-circuits can be balanced in any order
• proportionally balance each sub-circuit to reference sub-circuit,
ie same %DFR
Looking at each floorreference
Proportional Balancing
Having proportionally balanced the floor sub-circuits
• Proportionally Balance floors to reference floor, ie same %DFR
• Regulate flow to 100% at pump
constant flow – by regulation
variable flow – by pump speed
Proportional Balancing
Sample from BSRIA Commissioning Water Systems applications guide
valve datadesign data
initial scan measured results
L001 D931 15 lower 0.110 2.2 3.24 4.4 0.128 116 3.28 0.111 101 3.2
%DFR
Proportional Balancing
Steps to Proportional Balancing
scan - %DFR
identify index
same as reference?add resistance
proportional balance
regulate flow
no
yes
complete test sheet
Variable flow CPD
• understanding variable flow systems
• commissioning variable flow systems
proportional balancing
adjusting DPCV
setting PICV
Andy Lucas Technical Development Manager CRANE BS&U
PROPORTIONAL BALANCING