    PROPOSALFOR FUNDING

    INTEGRATED ISLAMIC BOARDING COLLEGE OF ASSYAFIIYAHTASIKMALAYA CITY

    INDONESIA2 13

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    2/26

    INTEGRATED ISLAMIC BOARDING COLLEGE

    ASSYAFIIYAHSyeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya City

    West Java, Indonesia Postal Code 46182E-mail: [email protected]

    Tasikmalaya, October 15th

    , 2013No : 01/PPT/X/2013

    Attachment : 1 Bundle

    Subject : Proposal for Funding

    To : All Muslims in Any Places

    May Allah gives His blessing and mercy for us in conducting all activities and creativities in

    order to uphold His great name and greatDienul Islamin the world. Amen!

    Furthemore, by this letter, we would like to submit a proposal for funding for the

    construction and development of Integrated Islamic Boarding College of Assyafiiyah located at

    Sukapala Village, Gununggede, Kawalu, Tasikmalaya City, West Java, Indonesia.

    Since the limited funds that we have as well as the low economic and social conditions of the

    people, we hope the generous people or God servant would like to give their contribution and

    assistance in constructing and developing this Integrated Islamic Boarding College of Assyafiiyah.

    The following are the infrastructures of Integrated Islamic Boarding College of Assyafiiyah

    that will be built:

    1. Mosque (Masjid)2. Male Dormitory3. Female Dormitory4. Islamic Elementary School (Madrasah Ibtidaiyah)5. Multipurpose Hall

    The budget required to realize our plan is Rp. 6,856,970,000.00 (Six Billions Eight Hundred and

    Fifty Six Millions Nine Hundred and Seventy Thousand Rupiahs)orUS$. 606,382.47 (Six Hundredand Six Thousand Three Hundred and Eighty Two Point Fourty Seven Dollars).Help and support

    given will be the power for us to realize this holy plan of constructing and developing Integrated

    Islamic Boarding College of Assyafiiyah in order to upholdDienul Islam.

    Finally, we would like to express our gratitude for them who give their help, support and

    contribution in succeeding this program.

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    3/26

    PREFACE

    All expressions of thank will be praised to Allah for His blessing to the committee, so that

    we can finish composing and submitting this proposal for funding as a real effort to increase and

    improve people education, to increase people knowledge and skill, and to produce educated people

    both in general and religion knowledge.

    Islamic religious education is very important in producing high quality and noble character

    of young generation in this globalization era. The only formal education with little time allocation

    for Islamic education given by the government in curriculum to the young generation is not enough

    to produce high quality and noble character of young generation without being supported by the

    proper and strong basic knowledge of religion. The proper and strong knowledge of religion for

    young generation is not as an additional knowledge of their education, but it is a basic knowledge

    that must be obtained by them to be the generation that have high intellect and noble character.

    Based on the condition above, it is very important to build an Integrated Islamic Boarding

    College supported by complete facility and good system. This Integrated Islamic Boarding College

    is expected to meet the needs of the public to get proper Islamic education. Therefore, we would like

    to submit this proposal for funding to construct and develop an Integrated Islamic Boarding College

    of Assyafiiyah located at Sukapala Village, Tasikmalaya City, West Java, Indonesia.

    Finally, we would like to express our gratitude for them who give support and help of this

    program. May Allah opens His way for us to realize this holy plan and gives reward for all our

    efforts. Amen.

    Sincerely,

    Committee

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    4/26

    INTEGRATED ISLAMIC BOARDING COLLEGE

    ASSYAFIIYAHSyeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya City, West

    Java, Indonesia. Postal Code 46182Email: [email protected]

    A. RATIONALEIslam is revealed by Allah to all people in the world through His messenger, Muhammad,

    as a mercy for the world. Islam is the religion that brings guidance for safety of human life in the

    world and the hereafter. Under any situations and conditions, humans must be able to appreciate

    and practice the entire guidance of life revealed by Allah in order to be independent and

    powerful people through general knowledge and strong religious knowledge.

    Based on the condition above, with a burning passion and commitment to achieve the

    pleasure of Allah, we as the committee plans to construct and develop the Integrated Islamic

    Boarding College of Assyafiiyah which is expected to be the place for obtaining knowledge

    especially Islamic knowledge, place for worshipping, place of establishing relationship, place for

    developing talents, and many kinds of goodness under the pleasure of Allah.

    The construction and development of the Integrated Islamic Boarding College of

    Assyafiiyah is the process of producing the high intellect and noble character of young

    generation which is supported by the strong basic Islamic knowledge so that the output of this

    college is not only good in general knowledge but also understand and mastery in religious

    knowledge.

    The construction and development of the Integrated Islamic Boarding College of

    Assyafiiyah is also a part of the process of improving services in answering the needs of high

    quality education for public so that it will create the good and beneficial educational

    environment.

    B. BASIC OF LAW(As for) those who spend their property by night and by day, secretly and openly, they shall

    have their reward from their Lord and they shall have no fear, nor shall they grieve.

    (Al-Baqara, 2:274)

    C. PURPOSES AND GOALS1. Purposes

    The purposes of composing and submitting this proposal are:

    a. To inform and ask the donors to provide the financial assistance in order to alleviate thefinancing of the construction and development of Integrated Islamic Boarding College of

    Assyafiiyah.

    b. As a means to distribute any donations such asInfaq, Shodaqoh,and other donations forreligious purposes.

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    5/26

    2. GoalsThe goals of constructing and developing the Integrated Islamic Boarding College of

    Assyafiiyah are:

    a. To create the means for learning, discussing, worshipping, rest area, developing talentsand establishing relationship.

    b. To increase and improve the educational services for public.D. TIME AND PLACE

    The construction of Integrated Islamic Boarding College of Assyafiiyah will be carried

    out in 2014 at Sukapala village, Gununggede, Kawalu, Tasikmala City, West Java, Indonesia.

    E. BUDGETThe budget of constructing and developing Integrated Islamic Boarding College of

    Assyafiiyah is Rp. 6,856,970,000.00 (Six Billions Eight Hundred and Fifty Six Millions Nine

    Hundred and Seventy Thousand Rupiahs)orUS$. 606,382.47 (Six Hundred and Six Thousand

    Three Hundred and Eighty Two Point Fourty Seven Dollars). The usage detail of funds is

    attached.

    F. BUDGET SOURCESThe budget source of this program is obtained from public funds by 25 % from total

    budget required and the rest is obtained from the generous donors.

    G. COMMITTEE STRUCTUREThe committee of construction and development of Integrated Islamic Boarding College

    of Assyafiiyah consists of community leaders and community members that are ready to help

    this program.

    H. CLOSINGThat is all the proposal for funding of construction and development of Integrated

    Islamic Boarding College of Assyafiiyah. We hope it becomes the consideration for them who

    want to achieve the pleasure and reward from Allah.

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    6/26

    COMMITTEE STRUCTURE

    INTEGRATED ISLAMIC BOARDING COLLEGE OF ASSYAFIIYAH

    Syeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya CityWest Java, Indonesia Postal Code 46182

    E-mail: [email protected]

    Protection Committee : Sub-District Head of Kawalu

    Village Head of Gununggede

    Head of Resident

    Advisory Committee : Head of Muslim Scholars Assembly of Tasikmalaya

    Head of Religious Ministry of Kawalu

    Drs.Utang Mubarok

    Chairman :KH.Supyan Jaelani

    Secretary :Hj. Evi Sofiati

    Treasurer :Hj.Noneng

    Construction Committee :BapakEman

    Funding Committee :BapakYaya

    Accommodation Committee :BapakAgus

    Public Relationship Committee :BapakAyi

    Consumption Committee :Hj.Noneng

    Security Committee :BapakIim

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    7/26

    CONSTRUCTION PLAN OF MOSQUE (MASJID)

    INTEGRATED ISLAMIC BOARDING COLLEGE OF ASSYAFIIYAH

    Syeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya City

    West Java, Indonesia Postal Code 46182E-mail: [email protected]

    No Budget Use Cost

    1 Preparatory Work Rp 8,697,920.00

    2 Land and Sand Work Rp 5,615,206.65

    3 Installation Work Rp 1,277,535,120.41

    4 Timber Work Rp 86,326,582.15

    5 Roof Installation Work Rp 4,400,000.00

    6 Painting Work Rp 2,886,191.62

    7 Iron and Glass Work Rp 18,330,061.48

    8 Electric Installation Work Rp 5,788,000.00

    9 Water Sanitation Work Rp 84,310,100.00

    10 Setting Outdoor Yard Work Rp 5,000,000.00

    Total Rp 1,498,889,182.30

    Value Added Tax (PPN)10% Rp 149,888,918.23

    Building Permit (IMB) Rp 25,000,000.00

    Total Cost Rp 1,673,778,100.53

    Rounded Rp 1,673,778,000.00

    Read

    One Billion Six Hundred and Seventy Three

    Million Seven Hundred and Seventy Eight

    Thousand Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    8/26

    ENGINEER ESTIMATE (EE)

    PROGRAM : DEVELOPING INFRASTRUCTURES

    JOB : CONSTRUCTING MOSQUE (MASJID)

    No Job Description Unit Volume Cost Total Cost

    1 2 3 4 5 6

    A PREPARATORY WORK

    Demolition of Old Building Ls 2.00 Rp 2,500,000.00 Rp 5,000,000.00

    Procurement of Direksiket Ls 2.00 Rp 750,000.00 Rp 1,500,000.00

    Bamboo Esteger Ls 2.00 Rp 800,000.00 Rp 1,600,000.00

    Measurement and Bawplank M 14.80 Rp 40,400.00 Rp 597,920.00

    Total Rp 8,697,920.00

    B LAND AND SAND WORK

    Soil Excavation M3 15.98 Rp 12,600.00 Rp 201,348.00

    Urugan Former Excavation Land M3 39.94 Rp 6,040.00 Rp 241,237.60

    Floor Elevation of the Former Excavation M2 11.98 Rp 6,040.00 Rp 72,359.20

    Elevation of the Land Bring M3 14.39 Rp 55,015.00 Rp 791,665.85

    UruganSand Under the Floor M3 26.92 Rp 117,850.00 Rp 3,172,522.00

    Urugan Sand Under the Foundation M2 9.64 Rp 117,850.00 Rp 1,136,074.00

    Total Rp 5,615,206.65

    C INSTALLATION WORK

    Inst of Split Rock Foundation M3 91.06 Rp 443,734.00 Rp 40,406,418.04

    Inst ofAnstampengSplit Rock M3 27.00 Rp 260,895.00 Rp 7,044,165.00

    Pas Lt Kerja Bawah Pondasi Beton M3 2.92 Rp 46,662.20 Rp 136,253.62

    Inst of Bony Concrete Foundation M3 91.06 Rp 3,238,880.52 Rp 294,932,460.15

    Inst of Column Sloop of Bony Conctere adk 1:2:3 M3 11.02 Rp 4,181,333.02 Rp 46,078,289.88

    Inst of Column of Bony Concrete adk1:2:3 M3 26.34 Rp 4,863,093.02 Rp 128,093,870.15

    Inst of Balk of Bony Concrete adk 1:2:3 M3 21.12 Rp 4,593,838.02 Rp 97,021,858.98

    Inst of Concrete Roof adk1:2:3 M3 41.26 Rp 2,441,977.00 Rp 100,755,971.02

    Inst of Concrete Dome adk 1:2:3 M3 53.96 Rp 2,441,977.00 Rp 131,769,078.92

    Inst of concrete Listplangadk 1:2:3 + Appearance M3 6.32 Rp 4,868,602.50 Rp 30,769,567.80

    Inst of Brick Wall adk 1:5 M2 56.61 Rp 59,662.20 Rp 3,377,477.14

    Inst of Plestering adk 1:5 M2 11.32 Rp 18,839.80 Rp 213,266.54

    Inst of Concrete Rabat 1:2:3 M3 5.50 Rp 356,941.83 Rp 1,963,180.07

    Inst of Ceramic Floor 30 x 30 M2 56.20 Rp 91,559.60 Rp 5,145,649.52

    Inst of Ceramic Floor 20 x 20 Antislip M2 44.00 Rp 95,442.40 Rp 4,199,465.60

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    9/26

    Inst of Ceramic Wall 20 x 20 M2 9.86 Rp 123,443.00 Rp 1,217,147.98

    Inst of Plastic Door of PVE Pcs 60.00 Rp 275,000.00 Rp 16,500,000.00

    Inst of Ceramic Roaster 20 x 20 Pcs 17.80 Rp 25,000.00 Rp 445,000.00

    Inst of Listband M 92.80 Rp 29,000.00 Rp 2,691,200.00

    Inst of Decorative Glass and Frame Unit 600.00 Rp 600,000.00 Rp 360,000,000.00

    Inst of Window with Dec Glass at Dome Unit 17.80 Rp 250,000.00 Rp 4,450,000.00

    Inst of Concrete Neutunder Door Frame Pcs 92.80 Rp 3,500.00 Rp 324,800.00

    Total Rp 1,277,535,120.41

    D TIMBER WORK

    Inst of Door/Window Frame of Kamper Wood M3 3.92 Rp 11,732,000.00 Rp 45,989,440.00

    Inst of Glass Window Skeleton of Kam Wood M2 25.92 Rp 421,600.00 Rp 10,927,872.00

    Inst of Glass Door Skeleton of Kam Wood M2 35.40 Rp 493,250.00 Rp 17,461,050.00

    Inst of Wood Panel of Kamper Wood M2 13.44 Rp 493,250.00 Rp 6,629,280.00

    Inst of Ceiling Skeleton of Local Wood M2 70.77 Rp 39,500.00 Rp 2,795,415.00

    Inst of Gypsum for Ceiling M2 70.77 Rp 26,695.00 Rp 1,889,205.15

    Inst of Gypsum Appearance (List) M1 79.29 Rp 8,000.00 Rp 634,320.00

    Total Rp 86,326,582.15

    E ROOF INSTALLATION WORK

    Inst of Dome Ornament M 2.00 Rp 450,000.00 Rp 900,000.00

    Inst of Rain Plumbing Unit 2.00 Rp 1,750,000.00 Rp 3,500,000.00

    Total Rp 4,400,000.00

    F PAINTING WORK

    Painting of Wall M2 113.23 Rp 12,264.50 Rp 1,388,709.34

    Painting of Ceiling M2 70.74 Rp 12,572.00 Rp 889,343.28

    Polishing the Frame M2 19.70 Rp 30,870.00 Rp 608,139.00

    Total Rp 2,886,191.62

    G IRON AND GLASS WORK

    Inst of Locker Pcs 12.00 Rp 84,625.00 Rp 1,015,500.00

    Inst of Door Hinges Pcs 88.00 Rp 68,312.50 Rp 6,011,500.00

    Inst of Window Hinges Pcs 14.40 Rp 16,945.00 Rp 244,008.00

    Inst of Door and Window Latch Pcs 72.00 Rp 26,390.00 Rp 1,900,080.00

    Inst of Sliding Hook Pcs 72.00 Rp 15,167.50 Rp 1,092,060.00

    Inst ofAngkur of Concrete Window Dia 10 mm Pcs 180.00 Rp 2,000.00 Rp 360,000.00

    Inst of Concrete hanging for Ceiling Dia 8 mm Pcs 60.00 Rp 3,500.00 Rp 210,000.00

    Inst of Espanyolet Pcs 24.00 Rp 76,000.00 Rp 1,824,000.00

    Inst of Block Glass M2 20.00 Rp 13,500.00 Rp 270,000.00

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    10/26

    Inst of Plain Glass 5 mm 80.44 Rp 67,167.00 Rp 5,402,913.48

    Total Rp 18,330,061.48

    H ELECTRIC INSTALLATION WORK

    Inst of Lamps Ttk 20.00 Rp 65,000.00 Rp 1,300,000.00

    Inst of Switch Pcs 1.00 Rp 16,000.00 Rp 16,000.00

    Inst of Singel Switch Pcs 1.00 Rp 16,000.00 Rp 16,000.00

    Inst of Double Switch Pcs 6.00 Rp 18,000.00 Rp 108,000.00

    Inst of Lamp 25 watt Pcs 8.00 Rp 6,000.00 Rp 48,000.00

    Inst of Economic Lamp 15 watt Pcs 30.00 Rp 30,000.00 Rp 900,000.00

    Inst of hanging decorative lamp Unit 2.00 Rp 675,000.00 Rp 1,350,000.00

    Inst of Box Zekering Pcs 2.00 Rp 75,000.00 Rp 150,000.00

    Electricity Cost Pkt 2.00 Rp 950,000.00 Rp 1,900,000.00

    Total Rp 5,788,000.00

    I WATER SANITATION WORK

    Inst of Closet Pcs 5.00 Rp 229,960.00 Rp 1,149,800.00

    Inst of Tub Pcs 5.00 Rp 252,375.00 Rp 1,261,875.00

    Inst of Disposal Water Filter Pcs 10.00 Rp 19,312.50 Rp 193,125.00

    Inst of Water Tap Dia 1/2 " Pcs 24.00 Rp 29,387.50 Rp 705,300.00

    Pas Saluran Air Bersih Inst of clean Waterway Unit 20.00 Rp 500,000.00 Rp 10,000,000.00

    Inst of Disposal Water Unit 20.00 Rp 500,000.00 Rp 10,000,000.00

    Inst of Water Turn Fiber Unit 20.00 Rp 550,000.00 Rp 11,000,000.00

    Inst of Saptick Tank Unit 20.00 Rp 2,500,000.00 Rp 50,000,000.00

    Total Rp 84,310,100.00

    J SETTING OUTDOOR YARD WORK

    Setting the Garden Pkt 2.00 Rp 2,500,000.00 Rp 5,000,000.00

    Total Rp 5,000,000.00

    Total Rp 1,498,889,182.30

    Value Added Tax (PPN)10% Rp 149,888,918.23

    Total + Value Added Tax (PPN) Rp 1,648,778,100.53

    Building Permit (IMB) Rp 25,000,000.00

    Grand Total Rp 1,673,778,100.53

    Rounded Rp 1,673,778,000.00

    Read

    One Billion Six Hundred and Seventy Three Million

    Seven Hundred and Seventy Eight Thousand Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    11/26

    CONSTRUCTION PLAN OF ISLAMIC ELEMENTARY SCHOOL

    INTEGRATED ISLAMIC BOARDING COLLEGE OF ASSYAFIIYAH

    Syeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya City

    West Java, Indonesia Postal Code 46182E-mail: [email protected]

    No Budget Use Cost

    1 Preparatory Work Rp 8,697,920.00

    2 Land and Sand Work Rp 5,615,206.65

    3 Installation Work Rp 1,277,535,120.41

    4 Timber Work Rp 86,326,582.15

    5 Roof Installation Work Rp 4,400,000.00

    6 Painting Work Rp 2,886,191.62

    7 Iron and Glass Work Rp 18,330,061.48

    8 Electric Installation Work Rp 5,788,000.00

    9 Water Sanitation Work Rp 84,310,100.00

    10 Setting Outdoor Yard Work Rp 5,000,000.00

    Total Rp 1,498,889,182.30

    Value Added Tax (PPN)10% Rp 149,888,918.23

    Building Permit (IMB) Rp 25,000,000.00

    Total Cost Rp 1,673,778,100.53

    Rounded Rp 1,673,778,000.00

    Read

    One Billion Six Hundred and Seventy Three

    Million Seven Hundred and Seventy Eight

    Thousand Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    12/26

    ENGINEER ESTIMATE (EE)

    PROGRAM : DEVELOPING INFRASTRUCTURES

    JOB : CONSTRUCTING ISLAMIC ELEMENTARY SCHOOL

    No Job Description Unit Volume Cost Total Cost

    1 2 3 4 5 6

    A PREPARATORY WORK

    Demolition of Old Building Ls 2.00 Rp 2,500,000.00 Rp 5,000,000.00

    Procurement of Direksiket Ls 2.00 Rp 750,000.00 Rp 1,500,000.00

    Bamboo Esteger Ls 2.00 Rp 800,000.00 Rp 1,600,000.00

    Measurement and Bawplank M 14.80 Rp 40,400.00 Rp 597,920.00

    Total Rp 8,697,920.00

    B LAND AND SAND WORK

    Soil Excavation M3 15.98 Rp 12,600.00 Rp 201,348.00

    Urugan Former Excavation Land M3 39.94 Rp 6,040.00 Rp 241,237.60

    Floor Elevation of the Former Excavation M2 11.98 Rp 6,040.00 Rp 72,359.20

    Elevation of the Land Bring M3 14.39 Rp 55,015.00 Rp 791,665.85

    UruganSand Under the Floor M3 26.92 Rp 117,850.00 Rp 3,172,522.00

    Urugan Sand Under the Foundation M2 9.64 Rp 117,850.00 Rp 1,136,074.00

    Total Rp 5,615,206.65

    C INSTALLATION WORK

    Inst of Split Rock Foundation M3 91.06 Rp 443,734.00 Rp 40,406,418.04

    Inst ofAnstampengSplit Rock M3 27.00 Rp 260,895.00 Rp 7,044,165.00

    Pas Lt Kerja Bawah Pondasi Beton M3 2.92 Rp 46,662.20 Rp 136,253.62

    Inst of Bony Concrete Foundation M3 91.06 Rp 3,238,880.52 Rp 294,932,460.15

    Inst of Column Sloop of Bony Conctere adk 1:2:3 M3 11.02 Rp 4,181,333.02 Rp 46,078,289.88

    Inst of Column of Bony Concrete adk1:2:3 M3 26.34 Rp 4,863,093.02 Rp 128,093,870.15

    Inst of Balk of Bony Concrete adk 1:2:3 M3 21.12 Rp 4,593,838.02 Rp 97,021,858.98

    Inst of Concrete Roof adk1:2:3 M3 41.26 Rp 2,441,977.00 Rp 100,755,971.02

    Inst of Concrete Dome adk 1:2:3 M3 53.96 Rp 2,441,977.00 Rp 131,769,078.92

    Inst of concrete Listplangadk 1:2:3 + Appearance M3 6.32 Rp 4,868,602.50 Rp 30,769,567.80

    Inst of Brick Wall adk 1:5 M2 56.61 Rp 59,662.20 Rp 3,377,477.14

    Inst of Plestering adk 1:5 M2 11.32 Rp 18,839.80 Rp 213,266.54

    Inst of Concrete Rabat 1:2:3 M3 5.50 Rp 356,941.83 Rp 1,963,180.07

    Inst of Ceramic Floor 30 x 30 M2 56.20 Rp 91,559.60 Rp 5,145,649.52

    Inst of Ceramic Floor 20 x 20 Antislip M2 44.00 Rp 95,442.40 Rp 4,199,465.60

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    13/26

    Inst of Ceramic Wall 20 x 20 M2 9.86 Rp 123,443.00 Rp 1,217,147.98

    Inst of Plastic Door of PVE Pcs 60.00 Rp 275,000.00 Rp 16,500,000.00

    Inst of Ceramic Roaster 20 x 20 Pcs 17.80 Rp 25,000.00 Rp 445,000.00

    Inst of Listband M 92.80 Rp 29,000.00 Rp 2,691,200.00

    Inst of Decorative Glass and Frame Unit 600.00 Rp 600,000.00 Rp 360,000,000.00

    Inst of Window with Dec Glass at Dome Unit 17.80 Rp 250,000.00 Rp 4,450,000.00

    Inst of Concrete Neutunder Door Frame Pcs 92.80 Rp 3,500.00 Rp 324,800.00

    Total Rp 1,277,535,120.41

    D TIMBER WORK

    Inst of Door/Window Frame of Kamper Wood M3 3.92 Rp 11,732,000.00 Rp 45,989,440.00

    Inst of Glass Window Skeleton of Kam Wood M2 25.92 Rp 421,600.00 Rp 10,927,872.00

    Inst of Glass Door Skeleton of Kam Wood M2 35.40 Rp 493,250.00 Rp 17,461,050.00

    Inst of Wood Panel of Kamper Wood M2 13.44 Rp 493,250.00 Rp 6,629,280.00

    Inst of Ceiling Skeleton of Local Wood M2 70.77 Rp 39,500.00 Rp 2,795,415.00

    Inst of Gypsum for Ceiling M2 70.77 Rp 26,695.00 Rp 1,889,205.15

    Inst of Gypsum Appearance (List) M1 79.29 Rp 8,000.00 Rp 634,320.00

    Total Rp 86,326,582.15

    E ROOF INSTALLATION WORK

    Inst of Dome Ornament M 2.00 Rp 450,000.00 Rp 900,000.00

    Inst of Rain Plumbing Unit 2.00 Rp 1,750,000.00 Rp 3,500,000.00

    Total Rp 4,400,000.00

    F PAINTING WORK

    Painting of Wall M2 113.23 Rp 12,264.50 Rp 1,388,709.34

    Painting of Ceiling M2 70.74 Rp 12,572.00 Rp 889,343.28

    Polishing the Frame M2 19.70 Rp 30,870.00 Rp 608,139.00

    Total Rp 2,886,191.62

    G IRON AND GLASS WORK

    Inst of Locker Pcs 12.00 Rp 84,625.00 Rp 1,015,500.00

    Inst of Door Hinges Pcs 88.00 Rp 68,312.50 Rp 6,011,500.00

    Inst of Window Hinges Pcs 14.40 Rp 16,945.00 Rp 244,008.00

    Inst of Door and Window Latch Pcs 72.00 Rp 26,390.00 Rp 1,900,080.00

    Inst of Sliding Hook Pcs 72.00 Rp 15,167.50 Rp 1,092,060.00

    Inst ofAngkur of Concrete Window Dia 10 mm Pcs 180.00 Rp 2,000.00 Rp 360,000.00

    Inst of Concrete hanging for Ceiling Dia 8 mm Pcs 60.00 Rp 3,500.00 Rp 210,000.00

    Inst of Espanyolet Pcs 24.00 Rp 76,000.00 Rp 1,824,000.00

    Inst of Block Glass M2 20.00 Rp 13,500.00 Rp 270,000.00

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    14/26

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    15/26

    CONSTRUCTION PLAN OF MALE DORMITORY

    INTEGRATED ISLAMIC BOARDING COLLEGE OF ASSYAFIIYAH

    Syeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya City

    West Java, Indonesia Postal Code 46182E-mail: [email protected]

    No Budget Use Cost

    1 Preparatory Work Rp 81,597,920.00

    2 Land and Sand Work Rp 15,892,090.30

    3 Installation Work Rp 542,603,320.49

    4 Timber Work Rp 467,563,468.30

    5 Roof Installation Work Rp 4,400,000.00

    6 Painting Work Rp 2,883,008.32

    7 Iron and Glass Work Rp 18,788,061.48

    8 Electric Installation Work Rp 5,788,000.00

    9 Water Sanitation Work Rp 94,658,300.00

    10 Setting Outdoor Yard Work Rp 5,000,000.00

    Total Rp 1,239,174,168.89

    Value Added Tax (PPN)10% Rp 123,917,416.89

    Building Permit (IMB) Rp 25,000,000.00

    Total Cost Rp 1,388,091,585.78

    Rounded Rp 1,388,091,000.00

    ReadOne Billion Three Hundred and Eighty Eight

    Million Ninety One Thousand Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    16/26

    ENGINEER ESTIMATE (EE)

    PROGRAM : DEVELOPING INFRASTRUCTURES

    JOB : CONSTRUCTING MALE DORMITORY

    No Job Description Unit Volume Cost Total Cost

    1 2 3 4 5 6

    A PREPARATORY WORK

    Demolition of Old Building Ls 20.00 Rp 2,500,000.00 Rp 50,000,000.00

    Procurement of Direksiket Ls 20.00 Rp 750,000.00 Rp 15,000,000.00

    Bamboo Esteger Ls 20.00 Rp 800,000.00 Rp 16,000,000.00

    Measurement and Bawplank M 14.80 Rp 40,400.00 Rp 597,920.00

    Total Rp 81,597,920.00

    B LAND AND SAND WORK

    Soil Excavation M3 15.98 Rp 12,600.00 Rp 201,348.00

    Urugan Former Excavation Land M3 39.94 Rp 6,040.00 Rp 241,237.60

    Floor Elevation of the Former Excavation M2 15.98 Rp 6,040.00 Rp 96,519.20

    Elevation of the Land Bring M3 14.90 Rp 55,015.00 Rp 819,723.50

    UruganSand Under the Floor M3 26.92 Rp 117,850.00 Rp 3,172,522.00

    Urugan Sand Under the Foundation M2 96.40 Rp 117,850.00 Rp 11,360,740.00

    Total Rp 15,892,090.30

    C INSTALLATION WORK

    Inst of Split Rock Foundation M3 91.00 Rp 443,734.00 Rp 40,379,794.00

    Inst ofAnstampengSplit Rock M3 27.00 Rp 260,895.00 Rp 7,044,165.00

    Pas Lt Kerja Bawah Pondasi Beton M3 29.20 Rp 46,662.20 Rp 1,362,536.24

    Inst of Bony Concrete Foundation M3 9.11 Rp 3,238,880.52 Rp 29,506,201.54

    Inst of Column Sloop of Bony Conctere adk 1:2:3 M3 11.00 Rp 4,181,333.02 Rp 45,994,663.22

    Inst of Column of Bony Concrete adk1:2:3 M3 26.34 Rp 4,863,093.02 Rp 128,093,870.15

    Inst of Balk of Bony Concrete adk 1:2:3 M3 21.12 Rp 4,593,838.02 Rp 97,021,858.98

    Inst of Concrete Roof adk1:2:3 M3 41.26 Rp 2,441,977.00 Rp 100,755,971.02

    Inst of Concrete Dome adk 1:2:3 M3 5.40 Rp 2,441,977.00 Rp 13,186,675.80

    Inst of concrete Listplangadk 1:2:3 + Appearance M3 6.32 Rp 4,868,602.50 Rp 30,769,567.80

    Inst of Brick Wall adk 1:5 M2 5.66 Rp 59,662.20 Rp 337,688.05

    Inst of Plestering adk 1:5 M2 1.13 Rp 18,839.80 Rp 21,288.97

    Inst of Concrete Rabat 1:2:3 M3 5.50 Rp 356,941.83 Rp 1,963,180.07

    Inst of Ceramic Floor 30 x 30 M2 56.21 Rp 91,559.60 Rp 5,146,565.12

    Inst of Ceramic Floor 20 x 20 Antislip M2 4.40 Rp 95,442.40 Rp 419,946.56

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    17/26

    Inst of Ceramic Wall 20 x 20 M2 9.86 Rp 123,443.00 Rp 1,217,147.98

    Inst of Plastic Door of PVE Pcs 6.00 Rp 275,000.00 Rp 1,650,000.00

    Inst of Ceramic Roaster 20 x 20 Pcs 17.80 Rp 25,000.00 Rp 445,000.00

    Inst of Listband M 92.80 Rp 29,000.00 Rp 2,691,200.00

    Inst of Decorative Glass and Frame Unit 44.00 Rp 600,000.00 Rp 26,400,000.00

    Inst of Window with Dec Glass at Dome Unit 32.00 Rp 250,000.00 Rp 8,000,000.00

    Inst of Concrete Neutunder Door Frame Pcs 56.00 Rp 3,500.00 Rp 196,000.00

    Total Rp 542,603,320.49

    D TIMBER WORK

    Inst of Door/Window Frame of Kamper Wood M3 39.00 Rp 11,732,000.00 Rp 457,548,000.00

    Inst of Glass Window Skeleton of Kam Wood M2 2.59 Rp 421,600.00 Rp 1,091,944.00

    Inst of Glass Door Skeleton of Kam Wood M2 3.54 Rp 493,250.00 Rp 1,746,105.00

    Inst of Wood Panel of Kamper Wood M2 13.44 Rp 493,250.00 Rp 6,629,280.00

    Inst of Ceiling Skeleton of Local Wood M2 7.04 Rp 39,500.00 Rp 278,080.00

    Inst of Gypsum for Ceiling M2 7.74 Rp 26,695.00 Rp 206,619.30

    Inst of Gypsum Appearance (List) M1 7.93 Rp 8,000.00 Rp 63,440.00

    Total Rp 467,563,468.30

    E ROOF INSTALLATION WORK

    Inst of Dome Ornament M 2.00 Rp 450,000.00 Rp 900,000.00

    Inst of Rain Plumbing Unit 2.00 Rp 1,750,000.00 Rp 3,500,000.00

    Total Rp 4,400,000.00

    F PAINTING WORK

    Painting of Wall M2 113.23 Rp 12,264.50 Rp 1,388,709.34

    Painting of Ceiling M2 70.74 Rp 12,527.00 Rp 886,159.98

    Polishing the Frame M2 19.70 Rp 30,870.00 Rp 608,139.00

    Total Rp 2,883,008.32

    G IRON AND GLASS WORK

    Inst of Locker Pcs 20.00 Rp 84,625.00 Rp 1,692,500.00

    Inst of Door Hinges Pcs 88.00 Rp 68,312.50 Rp 6,011,500.00

    Inst of Window Hinges Pcs 14.40 Rp 16,945.00 Rp 244,008.00

    Inst of Door and Window Latch Pcs 72.00 Rp 26,390.00 Rp 1,900,080.00

    Inst of Sliding Hook Pcs 72.00 Rp 15,167.50 Rp 1,092,060.00

    Inst ofAngkur of Concrete Window Dia 10 mm Pcs 18.00 Rp 2,000.00 Rp 36,000.00

    Inst of Concrete hanging for Ceiling Dia 8 mm Pcs 90.00 Rp 3,500.00 Rp 315,000.00

    Inst of Espanyolet Pcs 24.00 Rp 76,000.00 Rp 1,824,000.00

    Inst of Block Glass M2 20.00 Rp 13,500.00 Rp 270,000.00

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    18/26

    Inst of Plain Glass 5 mm 80.44 Rp 67,167.00 Rp 5,402,913.48

    Total Rp 18,788,061.48

    H ELECTRIC INSTALLATION WORK

    Inst of Lamps Ttk 20.00 Rp 65,000.00 Rp 1,300,000.00

    Inst of Switch Pcs 1.00 Rp 16,000.00 Rp 16,000.00

    Inst of Singel Switch Pcs 1.00 Rp 16,000.00 Rp 16,000.00

    Inst of Double Switch Pcs 6.00 Rp 18,000.00 Rp 108,000.00

    Inst of Lamp 25 watt Pcs 8.00 Rp 6,000.00 Rp 48,000.00

    Inst of Economic Lamp 15 watt Pcs 30.00 Rp 30,000.00 Rp 900,000.00

    Inst of hanging decorative lamp Unit 2.00 Rp 675,000.00 Rp 1,350,000.00

    Inst of Box Zekering Pcs 2.00 Rp 75,000.00 Rp 150,000.00

    Electricity Cost Pkt 2.00 Rp 950,000.00 Rp 1,900,000.00

    Total Rp 5,788,000.00

    I WATER SANITATION WORK

    Inst of Closet Pcs 50.00 Rp 229,960.00 Rp 11,498,000.00

    Inst of Tub Pcs 5.00 Rp 252,375.00 Rp 1,261,875.00

    Inst of Disposal Water Filter Pcs 10.00 Rp 19,312.50 Rp 193,125.00

    Inst of Water Tap Dia 1/2 " Pcs 24.00 Rp 29,387.50 Rp 705,300.00

    Pas Saluran Air Bersih Inst of clean Waterway Unit 20.00 Rp 500,000.00 Rp 10,000,000.00

    Inst of Disposal Water Unit 20.00 Rp 500,000.00 Rp 10,000,000.00

    Inst of Water Turn Fiber Unit 20.00 Rp 550,000.00 Rp 11,000,000.00

    Inst of Saptick Tank Unit 20.00 Rp 2,500,000.00 Rp 50,000,000.00

    Total Rp 94,658,300.00

    Jj SETTING OUTDOOR YARD WORK

    Setting the Garden Pkt 2.00 Rp 2,500,000.00 Rp 5,000,000.00

    Total Rp 5,000,000.00

    Total Rp 1,239,174,168.89

    Value Added Tax (PPN)10% Rp 123,917,416.89

    Total + Value Added Tax (PPN) Rp 1,363,091,585.78

    Building Permit (IMB) Rp 25,000,000.00

    Grand Total Rp 1,388,091,585.78

    Rounded Rp 1,388,091,000.00

    Read

    One Billion Three Hundred and Eighty Eight Million

    Ninety One Thousand Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    19/26

    CONSTRUCTION PLAN OF FEMALE DORMITORY

    INTEGRATED ISLAMIC BOARDING COLLEGE OF ASSYAFIIYAH

    Syeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya City

    West Java, Indonesia Postal Code 46182E-mail: [email protected]

    No Budget Use Cost

    1 Preparatory Work Rp 81,597,920.00

    2 Land and Sand Work Rp 15,892,090.30

    3 Installation Work Rp 542,603,320.49

    4 Timber Work Rp 467,563,468.30

    5 Roof Installation Work Rp 4,400,000.00

    6 Painting Work Rp 2,883,008.32

    7 Iron and Glass Work Rp 18,788,061.48

    8 Electric Installation Work Rp 5,788,000.00

    9 Water Sanitation Work Rp 94,658,300.00

    10 Setting Outdoor Yard Work Rp 5,000,000.00

    Total Rp 1,239,174,168.89

    Value Added Tax (PPN)10% Rp 123,917,416.89

    Building Permit (IMB) Rp 25,000,000.00

    Total Cost Rp 1,388,091,585.78

    Rounded Rp 1,388,091,000.00

    ReadOne Billion Three Hundred and Eighty Eight

    Million Ninety One Thousand Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    20/26

    ENGINEER ESTIMATE (EE)

    PROGRAM : DEVELOPING INFRASTRUCTURES

    JOB : CONSTRUCTING FEMALE DORMITORY

    No Job Description Unit Volume Cost Total Cost

    1 2 3 4 5 6

    A PREPARATORY WORK

    Demolition of Old Building Ls 20.00 Rp 2,500,000.00 Rp 50,000,000.00

    Procurement of Direksiket Ls 20.00 Rp 750,000.00 Rp 15,000,000.00

    Bamboo Esteger Ls 20.00 Rp 800,000.00 Rp 16,000,000.00

    Measurement and Bawplank M 14.80 Rp 40,400.00 Rp 597,920.00

    Total Rp 81,597,920.00

    B LAND AND SAND WORK

    Soil Excavation M3 15.98 Rp 12,600.00 Rp 201,348.00

    Urugan Former Excavation Land M3 39.94 Rp 6,040.00 Rp 241,237.60

    Floor Elevation of the Former Excavation M2 15.98 Rp 6,040.00 Rp 96,519.20

    Elevation of the Land Bring M3 14.90 Rp 55,015.00 Rp 819,723.50

    UruganSand Under the Floor M3 26.92 Rp 117,850.00 Rp 3,172,522.00

    Urugan Sand Under the Foundation M2 96.40 Rp 117,850.00 Rp 11,360,740.00

    Total Rp 15,892,090.30

    C INSTALLATION WORK

    Inst of Split Rock Foundation M3 91.00 Rp 443,734.00 Rp 40,379,794.00

    Inst ofAnstampengSplit Rock M3 27.00 Rp 260,895.00 Rp 7,044,165.00

    Pas Lt Kerja Bawah Pondasi Beton M3 29.20 Rp 46,662.20 Rp 1,362,536.24

    Inst of Bony Concrete Foundation M3 9.11 Rp 3,238,880.52 Rp 29,506,201.54

    Inst of Column Sloop of Bony Conctere adk 1:2:3 M3 11.00 Rp 4,181,333.02 Rp 45,994,663.22

    Inst of Column of Bony Concrete adk1:2:3 M3 26.34 Rp 4,863,093.02 Rp 128,093,870.15

    Inst of Balk of Bony Concrete adk 1:2:3 M3 21.12 Rp 4,593,838.02 Rp 97,021,858.98

    Inst of Concrete Roof adk1:2:3 M3 41.26 Rp 2,441,977.00 Rp 100,755,971.02

    Inst of Concrete Dome adk 1:2:3 M3 5.40 Rp 2,441,977.00 Rp 13,186,675.80

    Inst of concrete Listplangadk 1:2:3 + Appearance M3 6.32 Rp 4,868,602.50 Rp 30,769,567.80

    Inst of Brick Wall adk 1:5 M2 5.66 Rp 59,662.20 Rp 337,688.05

    Inst of Plestering adk 1:5 M2 1.13 Rp 18,839.80 Rp 21,288.97

    Inst of Concrete Rabat 1:2:3 M3 5.50 Rp 356,941.83 Rp 1,963,180.07

    Inst of Ceramic Floor 30 x 30 M2 56.21 Rp 91,559.60 Rp 5,146,565.12

    Inst of Ceramic Floor 20 x 20 Antislip M2 4.40 Rp 95,442.40 Rp 419,946.56

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    21/26

    Inst of Ceramic Wall 20 x 20 M2 9.86 Rp 123,443.00 Rp 1,217,147.98

    Inst of Plastic Door of PVE Pcs 6.00 Rp 275,000.00 Rp 1,650,000.00

    Inst of Ceramic Roaster 20 x 20 Pcs 17.80 Rp 25,000.00 Rp 445,000.00

    Inst of Listband M 92.80 Rp 29,000.00 Rp 2,691,200.00

    Inst of Decorative Glass and Frame Unit 44.00 Rp 600,000.00 Rp 26,400,000.00

    Inst of Window with Dec Glass at Dome Unit 32.00 Rp 250,000.00 Rp 8,000,000.00

    Inst of Concrete Neutunder Door Frame Pcs 56.00 Rp 3,500.00 Rp 196,000.00

    Total Rp 542,603,320.49

    D TIMBER WORK

    Inst of Door/Window Frame of Kamper Wood M3 39.00 Rp 11,732,000.00 Rp 457,548,000.00

    Inst of Glass Window Skeleton of Kam Wood M2 2.59 Rp 421,600.00 Rp 1,091,944.00

    Inst of Glass Door Skeleton of Kam Wood M2 3.54 Rp 493,250.00 Rp 1,746,105.00

    Inst of Wood Panel of Kamper Wood M2 13.44 Rp 493,250.00 Rp 6,629,280.00

    Inst of Ceiling Skeleton of Local Wood M2 7.04 Rp 39,500.00 Rp 278,080.00

    Inst of Gypsum for Ceiling M2 7.74 Rp 26,695.00 Rp 206,619.30

    Inst of Gypsum Appearance (List) M1 7.93 Rp 8,000.00 Rp 63,440.00

    Total Rp 467,563,468.30

    E ROOF INSTALLATION WORK

    Inst of Dome Ornament M 2.00 Rp 450,000.00 Rp 900,000.00

    Inst of Rain Plumbing Unit 2.00 Rp 1,750,000.00 Rp 3,500,000.00

    Total Rp 4,400,000.00

    F PAINTING WORK

    Painting of Wall M2 113.23 Rp 12,264.50 Rp 1,388,709.34

    Painting of Ceiling M2 70.74 Rp 12,527.00 Rp 886,159.98

    Polishing the Frame M2 19.70 Rp 30,870.00 Rp 608,139.00

    Total Rp 2,883,008.32

    G IRON AND GLASS WORK

    Inst of Locker Pcs 20.00 Rp 84,625.00 Rp 1,692,500.00

    Inst of Door Hinges Pcs 88.00 Rp 68,312.50 Rp 6,011,500.00

    Inst of Window Hinges Pcs 14.40 Rp 16,945.00 Rp 244,008.00

    Inst of Door and Window Latch Pcs 72.00 Rp 26,390.00 Rp 1,900,080.00

    Inst of Sliding Hook Pcs 72.00 Rp 15,167.50 Rp 1,092,060.00

    Inst ofAngkur of Concrete Window Dia 10 mm Pcs 18.00 Rp 2,000.00 Rp 36,000.00

    Inst of Concrete hanging for Ceiling Dia 8 mm Pcs 90.00 Rp 3,500.00 Rp 315,000.00

    Inst of Espanyolet Pcs 24.00 Rp 76,000.00 Rp 1,824,000.00

    Inst of Block Glass M2 20.00 Rp 13,500.00 Rp 270,000.00

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    22/26

    Inst of Plain Glass 5 mm 80.44 Rp 67,167.00 Rp 5,402,913.48

    Total Rp 18,788,061.48

    H ELECTRIC INSTALLATION WORK

    Inst of Lamps Ttk 20.00 Rp 65,000.00 Rp 1,300,000.00

    Inst of Switch Pcs 1.00 Rp 16,000.00 Rp 16,000.00

    Inst of Singel Switch Pcs 1.00 Rp 16,000.00 Rp 16,000.00

    Inst of Double Switch Pcs 6.00 Rp 18,000.00 Rp 108,000.00

    Inst of Lamp 25 watt Pcs 8.00 Rp 6,000.00 Rp 48,000.00

    Inst of Economic Lamp 15 watt Pcs 30.00 Rp 30,000.00 Rp 900,000.00

    Inst of hanging decorative lamp Unit 2.00 Rp 675,000.00 Rp 1,350,000.00

    Inst of Box Zekering Pcs 2.00 Rp 75,000.00 Rp 150,000.00

    Electricity Cost Pkt 2.00 Rp 950,000.00 Rp 1,900,000.00

    Total Rp 5,788,000.00

    I WATER SANITATION WORK

    Inst of Closet Pcs 50.00 Rp 229,960.00 Rp 11,498,000.00

    Inst of Tub Pcs 5.00 Rp 252,375.00 Rp 1,261,875.00

    Inst of Disposal Water Filter Pcs 10.00 Rp 19,312.50 Rp 193,125.00

    Inst of Water Tap Dia 1/2 " Pcs 24.00 Rp 29,387.50 Rp 705,300.00

    Pas Saluran Air Bersih Inst of clean Waterway Unit 20.00 Rp 500,000.00 Rp 10,000,000.00

    Inst of Disposal Water Unit 20.00 Rp 500,000.00 Rp 10,000,000.00

    Inst of Water Turn Fiber Unit 20.00 Rp 550,000.00 Rp 11,000,000.00

    Inst of Saptick Tank Unit 20.00 Rp 2,500,000.00 Rp 50,000,000.00

    Total Rp 94,658,300.00

    Jj SETTING OUTDOOR YARD WORK

    Setting the Garden Pkt 2.00 Rp 2,500,000.00 Rp 5,000,000.00

    Total Rp 5,000,000.00

    Total Rp 1,239,174,168.89

    Value Added Tax (PPN)10% Rp 123,917,416.89

    Total + Value Added Tax (PPN) Rp 1,363,091,585.78

    Building Permit (IMB) Rp 25,000,000.00

    Grand Total Rp 1,388,091,585.78

    Rounded Rp 1,388,091,000.00

    Read

    One Billion Three Hundred and Eighty Eight Million

    Ninety One Thousand Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    23/26

    CONSTRUCTION PLAN OF MULTIPURPOSES HALL

    INTEGRATED ISLAMIC BOARDING COLLEGE OF ASSYAFIIYAH

    Syeikh Abdul Muhyi St., Sukapala, Gununggede, Kawalu, Tasikmalaya City

    West Java, Indonesia Postal Code 46182E-mail: [email protected]

    No Budget Use Cost

    1 Preparatory Work Rp 7,039,600.00

    2 Land and Sand Work Rp 7,601,776.85

    3 Installation Work Rp 552,651140.65

    4 Timber Work Rp 67,100,085.65

    5 Roof Installation Work Rp 2,200,000.00

    6 Painting Work Rp 14,417,602.51

    7 Iron and Glass Work Rp 10,323,566.74

    8 Electric Installation Work Rp 4,068,000.00

    9 Water Sanitation Work Rp 5,946,217.50

    10 Setting Outdoor Yard Work Rp 2,500,000.00

    Total Rp 643,847,989.90

    Value Added Tax (PPN)10% Rp 64,384,798.99

    Building Permit (IMB) Rp 25,000,000.00

    Total Cost Rp 733,232,788.89

    Rounded Rp 733,232,000.00

    Read

    Seven Hundred And Thirty Three Million

    Two Hundred and Thirty Two Thousand

    Rupiahs

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    24/26

    ENGINEER ESTIMATE (EE)

    PROGRAM : DEVELOPING INFRASTRUCTURES

    JOB : CONSTRUCTING MULTIPURPOSES HALL

    No Job Description Unit Volume Cost Total Cost

    1 2 3 4 5 6

    A PREPARATORY WORK

    Demolition of Old Building Ls 1.00 Rp 2,500,000.00 Rp 2,500,000.00

    Procurement of Direksiket Ls 1.00 Rp 750,000.00 Rp 750,000.00

    Bamboo Esteger Ls 1.00 Rp 800,000.00 Rp 800,000.00

    Measurement and Bawplank M 74.00 Rp 40,400.00 Rp 2,989,600.00

    Total Rp 7,039,600.00

    B LAND AND SAND WORK

    Soil Excavation M3 79.89 Rp 12,600.00 Rp 1,006,614.00

    Urugan Former Excavation Land M3 19.97 Rp 6,040.00 Rp 120,618.80

    Floor Elevation of the Former Excavation M2 59.92 Rp 6,040.00 Rp 361,916.80

    Elevation of the Land Bring M3 71.95 Rp 55,015.00 Rp 3,958,329.25

    UruganSand Under the Floor M3 13.46 Rp 117,850.00 Rp 1,586,261.00

    Urugan Sand Under the Foundation M2 4.82 Rp 117,850.00 Rp 568,037.00

    Total Rp 7,601,776.85

    C INSTALLATION WORK

    Inst of Split Rock Foundation M3 45.53 Rp 443,734.00 Rp 20,203,209.02

    Inst ofAnstampengSplit Rock M3 13.50 Rp 260,895.00 Rp 3,522,082.50

    Pas Lt Kerja Bawah Pondasi Beton M3 1.46 Rp 46,662.20 Rp 68,126.81

    Inst of Bony Concrete Foundation M3 45.53 Rp 3,238,880.52 Rp 147,466,230.08

    Inst of Column Sloop of Bony Conctere adk 1:2:3 M3 5.51 Rp 4,181,333.02 Rp 23,039,144.94

    Inst of Column of Bony Concrete adk1:2:3 M3 13.17 Rp 4,863,093.02 Rp 64,046,935.07

    Inst of Balk of Bony Concrete adk 1:2:3 M3 10.56 Rp 4,593,838.02 Rp 48,510,929.49

    Inst of Concrete Roof adk1:2:3 M3 20.63 Rp 2,441,977.00 Rp 50,377,985.51

    Inst of Concrete Dome adk 1:2:3 M3 26.98 Rp 2,441,977.00 Rp 65,884,539.46

    Inst of concrete Listplangadk 1:2:3 + Appearance M3 3.16 Rp 4,868,602.50 Rp 15,384,783.90

    Inst of Brick Wall adk 1:5 M2 283.08 Rp 59,662.20 Rp 16,889,175.58

    Inst of Plestering adk 1:5 M2 566.16 Rp 18,839.80 Rp 10,666,341.17

    Inst of Concrete Rabat 1:2:3 M3 2.75 Rp 356,941.83 Rp 981,590.03

    Inst of Ceramic Floor 30 x 30 M2 281.03 Rp 91,559.60 Rp 25,730,994.39

    Inst of Ceramic Floor 20 x 20 Antislip M2 22.00 Rp 95,442.40 Rp 2,099,732.80

    Inst of Ceramic Wall 20 x 20 M2 49.30 Rp 123,443.00 Rp 6,085,739.90

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    25/26

    Inst of Plastic Door of PVE Pcs 3.00 Rp 275,000.00 Rp 825,000.00

    Inst of Ceramic Roaster 20 x 20 Pcs 89.00 Rp 25,000.00 Rp 2,225,000.00

    Inst of Listband M 46.40 Rp 29,000.00 Rp 1,345,600.00

    Inst of Decorative Glass and Frame Unit 22.00 Rp 600,000.00 Rp 13,200,000.00

    Inst of Window with Dec Glass at Dome Unit 16.00 Rp 250,000.00 Rp 4,000,000.00

    Inst of Concrete Neutunder Door Frame Pcs 28.00 Rp 3,500.00 Rp 98,000.00

    Total Rp 522,651,140.65

    D TIMBER WORK

    Inst of Door/Window Frame of Kamper Wood M3 1.96 Rp 11,732,000.00 Rp 22,994,720.00

    Inst of Glass Window Skeleton of Kam Wood M2 12.96 Rp 421,600.00 Rp 5,463,936.00

    Inst of Glass Door Skeleton of Kam Wood M2 17.70 Rp 493,250.00 Rp 8,730,525.00

    Inst of Wood Panel of Kamper Wood M2 6.72 Rp 493,250.00 Rp 3,314,640.00

    Inst of Ceiling Skeleton of Local Wood M2 353.87 Rp 39,500.00 Rp 13,977,865.00

    Inst of Gypsum for Ceiling M2 353.87 Rp 26,695.00 Rp 9,446,559.65

    Inst of Gypsum Appearance (List) M1 396.48 Rp 8,000.00 Rp 3,171,840.00

    Total Rp 67,100,085.65

    E ROOF INSTALLATION WORK

    Inst of Dome Ornament M 1.00 Rp 450,000.00 Rp 450,000.00

    Inst of Rain Plumbing Unit 1.00 Rp 1,750,000.00 Rp 1,750,000.00

    Total Rp 2,200,000.00

    F PAINTING WORK

    Painting of Wall M2 566.16 Rp 12,264.50 Rp 6,943,669.32

    Painting of Ceiling M2 353.87 Rp 12,527.00 Rp 4,432,929.49

    Polishing the Frame M2 98.51 Rp 30,870.00 Rp 3,041,003.70

    Total Rp 14,417,602.51

    G IRON AND GLASS WORK

    Inst of Locker Pcs 6.00 Rp 84,625.00 Rp 507,750.00

    Inst of Door Hinges Pcs 44.00 Rp 68,312.50 Rp 3,005,750.00

    Inst of Window Hinges Pcs 72.00 Rp 16,945.00 Rp 1,220,040.00

    Inst of Door and Window Latch Pcs 36.00 Rp 26,390.00 Rp 950,040.00

    Inst of Sliding Hook Pcs 36.00 Rp 15,167.50 Rp 546,030.00

    Inst ofAngkur of Concrete Window Dia 10 mm Pcs 94.00 Rp 2,000.00 Rp 188,000.00

    Inst of Concrete hanging for Ceiling Dia 8 mm Pcs 45.00 Rp 3,500.00 Rp 157,500.00

    Inst of Espanyolet Pcs 12.00 Rp 76,000.00 Rp 912,000.00

    Inst of Block Glass M2 10.00 Rp 13,500.00 Rp 135,000.00

    Inst of Plain Glass 5 mm 40.22 Rp 67,167.00 Rp 2,701,456.74

  • 8/13/2019 Proposal of Assyafiiyah Integrated Islamic Boarding College

    26/26

    Total Rp 10,323,566.74

    H ELECTRIC INSTALLATION WORK

    Inst of Lamps Ttk 24.00 Rp 65,000.00 Rp 1,560,000.00

    Inst of Switch Pcs 5.00 Rp 16,000.00 Rp 80,000.00

    Inst of Singel Switch Pcs 5.00 Rp 16,000.00 Rp 80,000.00

    Inst of Double Switch Pcs 3.00 Rp 18,000.00 Rp 54,000.00

    Inst of Lamp 25 watt Pcs 4.00 Rp 6,000.00 Rp 24,000.00

    Inst of Economic Lamp 15 watt Pcs 19.00 Rp 30,000.00 Rp 570,000.00

    Inst of hanging decorative lamp Unit 1.00 Rp 675,000.00 Rp 675,000.00

    Inst of Box Zekering Pcs 1.00 Rp 75,000.00 Rp 75,000.00

    Electricity Cost Pkt 1.00 Rp 950,000.00 Rp 950,000.00

    Total Rp 4,068,000.00

    I WATER SANITATION WORK

    Inst of Closet Pcs 3.00 Rp 229,960.00 Rp 689,880.00

    Inst of Tub Pcs 3.00 Rp 252,375.00 Rp 757,125.00

    Inst of Disposal Water Filter Pcs 5.00 Rp 19,312.50 Rp 96,562.50

    Inst of Water Tap Dia 1/2 " Pcs 12.00 Rp 29,387.50 Rp 352,650.00

    Pas Saluran Air Bersih Inst of clean Waterway Unit 1.00 Rp 500,000.00 Rp 500,000.00

    Inst of Disposal Water Unit 1.00 Rp 500,000.00 Rp 500,000.00

    Inst of Water Turn Fiber Unit 1.00 Rp 550,000.00 Rp 550,000.00

    Inst of Saptick Tank Unit 1.00 Rp 2,500,000.00 Rp 2,500,000.00

    Total Rp 5,946,217.50

    Jj SETTING OUTDOOR YARD WORK

    Setting the Garden Pkt 1.00 Rp 2,500,000.00 Rp 2,500,000.00

    Total Rp 2,500,000.00

    Total Rp 643,847,989.90

    Value Added Tax (PPN)10% Rp 64,384,798.99

    Total + Value Added Tax (PPN) Rp 708,232,788.89

    Building Permit (IMB) Rp 25,000,000.00

    Grand Total Rp 733,232,788.89

    Rounded Rp 733,232,000.00

    Read

    Seven Hundred And Thirty Three Million Two Hundred

    and Thirty Two Thousand Rupiahs