proposed additions and alterations to an existing...

170
THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA MINISTRY OF SKILL DEVELOPMENT VOCATIONAL EDUCATION, RESERCH & ENOVATION PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING BUILDING FOR OCEAN UNIVERSITY OF SRI LANKA AT BOOSSA PHASE I OF STAGE III BIDDING DOCUMENT VOLUME 01 Section 1 - Instructions to Bidders Section 2 - Standard Forms (Contract) Section 3 - Conditions of Contract VOLUME 02 Invitation for Bids Section 4 - Form of Bid & Qualification Information Section 5 - Bidding Data and Contract Data Section 6 - Specifications Section 7 - Bills of Quantities Section 8 - Drawings Section 9 Standard Forms (Bid) May 2021 Employer: Engineer: Vice Chancellor, State Engineering Corporation of Sri Lanka Ocean University of Sri Lanka, (Consultancy) Crow Island, Mattakkuliya, 130, W.A.D. Ramanayaka Mawatha, Colombo 15. Colombo 02. Page 1 of 170

Upload: others

Post on 07-Aug-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA

MINISTRY OF SKILL DEVELOPMENT

VOCATIONAL EDUCATION, RESERCH & ENOVATION

PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING BUILDING FOR OCEAN UNIVERSITY OF SRI

LANKA AT BOOSSA PHASE I OF STAGE III

BIDDING DOCUMENT

VOLUME 01

Section 1 - Instructions to Bidders

Section 2 - Standard Forms (Contract)

Section 3 - Conditions of Contract

VOLUME 02

Invitation for Bids

Section 4 - Form of Bid & Qualification Information

Section 5 - Bidding Data and Contract Data

Section 6 - Specifications

Section 7 - Bills of Quantities

Section 8 - Drawings

Section 9 – Standard Forms (Bid)

May 2021

Employer: Engineer: Vice Chancellor, State Engineering Corporation of Sri Lanka Ocean University of Sri Lanka, (Consultancy) Crow Island, Mattakkuliya, 130, W.A.D. Ramanayaka Mawatha,

Colombo 15. Colombo 02.

Page 1 of 170

Page 2: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

CONTENTS

DOCUMENTS PAGE

Volume 1

Section 1 - Instruction To Bidders

Section 2 - Standard Forms (Contract)

Section 3 - Conditions of Contract

Volume 2

Invitation For Bids 06 - 08

Section 4 – Forms of Bid and Qualification Information

09 – 11

Section 5 – Bidding Data and Contract Data 12 – 18

Section 6 – Specifications

Section 7 – Bills of Quantities 79 – 150

Section 8 – Drawings

Section 9 – Standard Forms (Bid)

Check List

169

19 – 78

151 – 168

Page 2 of 170

Page 3: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

MINISTRY OF SKILL DEVELOPMENT VOCATIONAL EDUCATION, RESERCH & ENOVATION

PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING BUILDING FOR OCEAN

UNIVERSITY OF SRI LANKA AT BOOSSA PHASE I OF STAGE III

BIDDING DOCUMENT

VOLUME 1

Section 1- Instructions to Bidders

Section 2- Standard Forms (Contract)

Section 3- Conditions of Contract

May 2021

Engineer: State Engineering Corporation of Sri Lanka (Consultancy Group) 130, W.A.D. Ramanayaka Mawatha Colombo 2.

Page 3 of 170

Page 4: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Section 1 – Instructions to Bidders (ITB)

Section 2 – Standard Forms (Contract)

- Bid Security

- Letter of Acceptance

- Agreement

- Performance Security

- Advance Payment Security

Section 3 – Condition of Contract

Please refer CIDA Publication No. ICTAD/SBD/01 Standard Bidding

Document, Procurement of Works, Second Edition – January 2007 for

Volume I.

Page 4 of 170

Page 5: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

MINISTRY OF SKILL DEVELOPMENT VOCATIONAL EDUCATION, RESERCH & ENOVATION

PROPOSED ADDITIONS AND ALTERATIONS TO

AN EXISTING BUILDING FOR OCEAN UNIVERSITY OF SRI LANKA AT BOOSSA

PHASE I OF STAGE III

BIDDING DOCUMENT

Volume II

Invitation For Bids

Section 4- Form of Bid and Qualification Information

Section 5- Bidding Data and Contract Data

Section 6- Specifications

Section 7- Bills of Quantities

Section 8- Drawings

Section 9- Standard Forms (Bid)

May 2021

Engineer: State Engineering Corporation of Sri Lanka (Consultancy Group) 130, W.A.D. Ramanayaka Mawatha Colombo 2.

Page 5 of 170

Page 6: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Invitation for Bids (IFB)

Page 6 of 170

Page 7: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Invitation for Bids (IFB)

State Ministry of Skills Development, Vocational Education, Research & Innovations

Proposed Additions and Alterations to an Existing Building for Ocean University of Sri Lanka at Boossa Phase I of Stage III

1. The Chairman, Department Procurement Committee on behalf of thethe Vice Chancellor, Ocean University of Sri Lanka, Crow Island, Mattakkuliya,Colombo 15 now invites sealed bids from eligible & qualified bidders for Constructionof Proposed Additions and Alterations to an Existing Building for Ocean Universityof Sri Lanka at Boossa Phase I of Stage III.

The Work consists of removing of existing roof (lower and upper roof), demolition works, construction of new slab (approx area 445m2), roof work to cover the newly constructed slab and finishes of Ground floor including electrical works.

Location of Project : Premises of Regional Centre of Ocean University of Sri Lanka at Boossa (Near to the Timber Corporation)

The construction period is 170 days. Total estimate amount for works is Rs. 50.2 Million.

2. Bidding will be conducted through National Competitive Bidding Procedure.

3. To be eligible for contract award, the successful bidder shall not have been blacklistedand shall meet the following requirements.

CIDA registration required.

Specialty : Buildings Grade : C4 & C3

4. Qualification requirements to qualify for contract award include.

Average of the annual volume of construction work performed in the last five yearsshall be at least Rs. 75 million

Experience in the construction of at least one contract of a similar nature and thecomplexity equivalent to the value of Rs.35.0 million or above, over the last 5 years(to comply with this requirement, works should be at least 70 percent completed)

The minimum amount of Liquid Assets and or/credit facilities shall be not less thanRs. 19.0million

Page 7 of 170

Page 8: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Interested bidders may obtain further information from Engineer(workshop), Ocean University of Sri Lanka, Crow Island, Mattakkuliya (Tel: .0773511918.)

5. Interested bidders can download the bid documents from the website of the OceanUniversity of Sri Lanka,i.e,www.ocu.ac.lk from 09th July 2021 to 28th July 2021.

6. Non-refundable bid document fee Rupees 12,500/= should be credited to OceanUniversity of Sri Lanka Account No.214-1-001-4-3629868,People`s BankMattakkuliya Branch, from 09.07.2021 to 29.07.2021. Bank slip should be attachedwith the bid documents. Otherwise bid will be rejected. .

7. Bids shall be delivered to the Chairman, Department Procurement Committee,Ocean University of Sri Lanka, Crow Island, Mattakkuliya, Colombo 15 to reachon or before 11.00 a.m on 29.07.2021. Late bids will be rejected. Bids will be openedsoon after closing in the presence of the bidders’ representatives who choose to attend.Project title should be written in left hand site of the envelop.

8. Bids shall be valid up to 91 days from bid opening date.

9. All bids shall be accompanied by a Bid Security of Rs. 500,000.00 in favour of ViceChancellor Ocean University of Sri Lanka. Bid security shall be valid up to24.11.2021

10. A pre-bid meeting will be held on 20.07.2021 at 11.00 a.m at Boossa site.

Chairman, Department Procurement Committee, Ocean University of Sri Lanka, Crow Island, Mattakkuliya, Colombo 15.

Page 8 of 170

Page 9: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Section - 4

Form of Bid and Qualification Information

Page 9 of 170

Page 10: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Form of Bid

NAME OF CONTRACT: Proposed Additions and Alterations to an Existing Building for Ocean University of Sri Lanka at Boossa Phase I of Stage III

CONTRACT NO :OCU/Eng/CO/Boossa/2021/12.

To: Vice Chancellor, Ocean University of Sri Lanka, Crow Island, Mattakkuliya, Colombo 15.

Gentleman,

1. Having examined the Standard Bidding Document – Procurement of Works [ICTAD/SBD/01 –Second Edition, January 2007], Specifications, Drawings and Bills of Quantities and Addendafor the execution of the above-named Works, we the undersigned, offer to execute andcomplete such Works and remedy any defect therein in conformity with the aforesaidConditions of Contract, Specifications, Drawings, Bills of Quantities and Addenda for the sumof Sri Lankan Rupees ……………………………………………….………………………………………… (LKR ……………….………..) (excluding VAT) or suchother sums as may be ascertained in accordance with the said Conditions.

2. We acknowledge that the Contract Data will forms part of our Bid.

3. We undertake, if our Bid is accepted, to commence the Works as stipulated in the contractdata, and to complete the whole of the Works comprised in the Contract within the time statedin the Contract Data.

4. We agree to abide by this Bid for the period of 91 Days from the date fixed for receiving orany extended period and it shall remain binding upon us and may be accepted at any timebefore the expiration of that period.

5. Unless and until a formal Agreement is prepared and executed this Bid, together with yourwritten acceptance thereof, shall constitute a binding Contract between us.

6. We accept / we do not accept the Adjudicator.

7. We understand that you are not bound to accept the lowest or any Bid you may receive.

8. We certify/conform that we comply with the eligibility requirements as per ITB Clause 4 of the

ICTAD publication SBD/01(Second Edition January 2007).

Dated this ………………….…………..day of ...................................................... 2021

in the capacity of ………………………Name ..................................................... duly

authorized to sign tenders for and on behalf of……………………………………………..

[in block capitals or typed]

Signature :………………………………

Address : ……………………………………………………………………………….

Witness : 1. ……………………………………………………………………………

2. ……………………………………………………………………………

Page 10 of 170

Page 11: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Qualification Information

Section 4 - Form of Bid & Qualification Information

(to be completed by the Bidder and submitted with the Bid; Provide only the information requested under ITB Clause 4.3)

CIDA Registration

Registration number (attached certified copies of relevant pages from the registration book)

Grade Main Contractors – C4 & C3

Specialty Buildings

Expiry Date

Black listed Contractors

Have you been declared as a defaulted contractor by NPA or any other agency? (Yes/No)

IF yes provide details

VAT Registration Number

Construction Program (attach as annex)

Legal Status (attach certified copies of relevant status certificates as annex)

Value of Construction works performed in last 5 years

(attach certified copies of certificate of completion etc. and profit-loss and income expenditure statement (Audited report) for last 5 years)

Year 2020

Year 2019

Year 2018

Year 2017

Year 2016

Value of similar works completed in last 5 years (indicate only the three largest projects)

1. Value Year 2. Value Year 3. Value Year (attach certified copies of certificate of completion etc., as annex)

Major items of construction equipment proposed

1. Type Capacity 2. Type Capacity 3. Type Capacity 4. Type Capacity 5. Type Capacity

Qualification and experience of key – staff & Head Office (Permanent, Contract basis & Consultants?)

1. Civil Engineer (B.Sc. or equivalent) with 03 yearconstruction experience

2. NCT (QS) with minimum 3 year construction experience

Other information requested under ITB Clause 4

Average annual value of construction work performedin last five years shall be at least Rs. 75 million.

The minimum amount of Liquid Assets and/or creditfacilities required is Rs. 19.0 million.

Experience in the construction of at least one contractof a similar nature and complexity equivalent to thevalue of Rs. 35.0 million or above over the last 5 years

Page 11 of 170

Page 12: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Section - 5

Bidding Data & Contract Data

Page 12 of 170

Page 13: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Bidding Data

Instructions to Bidders Clause Reference

1.1 Employer’s Name and Address Name : Vice Chancellor Address: Ocean University of Sri Lanka,

No. 15, Crow Island, Mattakkuliya, Colombo 15.

1.2 The Work consists of removing of existing roof (lower and upper roof), demolition works, construction of new slab (approx area 445m2), roof work to cover the newly constructed slab and finishes of Ground floor including electrical works.

Located at the Premises of the Regional Centre of Ocean University of Sri Lanka at Boossa

1.3 Intended Completion Date is 170 Days from the start date.

1.4 The office for collection of bid forms is office of the Engineer(Workshop),, Ocean University of Sri Lanka, Crow Island, Mattakkuliya, Colombo 15

The non-refundable fee is Rupees 12,500.00.

The Bid forms will be issued until ………………………

2.1 The source of funds is Government of Sri Lanka (GOSL)

4.2 The registration required

Specialty : Building Grade : C4 & C3

4.3 The following information (certified copies) shall be provided in Section 4 –

CIDA Registration

Registration number

Grade

Specialty

Expiry Date

VAT Registration number

Construction Program

Legal Status (Sole proprietor, Partnership, Company etc.)

Page 13 of 170

Page 14: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Total monetary value of construction work performed for each of the

last five years (Audited Financial Reports shall be attached)

Experience in works of a similar nature and size for each of the last

five years(Completion Certificates should be attached)

Major Items of Construction equipment proposed to carry out the

Contract (Own/lease/hire)

Qualifications and experience of key site management and technical

personnel proposed for the contract (permanent, contract basis,

casual) curriculum vitae should be submitted.

Authentication for Signatory (power of attorney or documentary

evidence to prove that the signatory to the Bid is authorized to

commit the Bidder)

4.4(a) Average annual volume of construction work performed in last 5 years

Average annual volume of construction work performed in last five years shall be at least Rs. 75 million.

Experience in the construction of at least one contract of a similar nature and complexity with the value of Rs. 35.0 million or above over the last 5 years.

4.4(c) Following technical and managerial staff:

1. 1 nr. BSc (Civil) Engineer with minimum 3 years experience in buildingconstruction 2. 1 nr. NCT (QS) with minimum 3 year experience in building construction

4.4(d) Liquid assets and /or credit facilities required The minimum amount of liquid assets and/ or credit facilities net of other contractual commitments and exclusive of any advance payments which may be made under the Contract shall be not less than Rs. 19.0 Million.

9.1

11.1

Employer’s address for the purpose of clarification is;

Name : Engineer (workshop) Address: Ocean University of Sri Lanka, No 15, Crow Island, Mattakkuliya

The Language of the bidding document shall be English

13.3 VAT component shall not be included in the rates. The amount written in the Form of Bid shall be without VAT. However VAT components shall be shown separately at the end of the BOQ.

Page 14 of 170

Page 15: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

13.4 The Contract is subjected to price adjustment accordance with Clause 47 of Conditions of Contract.

15.1

16.1

The Bid shall be valid up to 24.11.2021.[91 Days from bid opening]

Bid shall include a Bid security using the form included in section 9.

16.2 Bid Security shall be:

The amount of Bid Security is Sri Lanka Rupees Five Hundred Thousand only (SLR. 500,000.00)

The Bid Security shall be valid up to 24.11.2021[28 Days beyond the bid validity period]

The Bid Security should be addressed to The Vice Chancellor, Ocean University of Sri Lanka, Crow Island, Mattakkuliya, Colombo 15 who is the Beneficiary and Issued by a bank operating in Sri Lanka approved by the Central Bank acceptable to Employer using form for bid security (unconditional guarantee) included in Section 9, Standard Forms.

17.0 Pre-Bid meeting

Pre-Bid meeting will be held

Date : 20.07.2021

Time: 11.00 am

Venue: Boossa site

(Prior to the meeting prospective bidders can visit the site)

19.2(a) The Employer’s address for the purpose of Bid submission is Chairman, Department Procurement Committee., Ocean University of Sri Lanka, No. 15, Crow Island, Mattakkuliya, Colombo 15.

19.2(b) Contract name: Proposed Additions and Alterations to an Existing Building for Ocean University of Sri Lanka at Boossa Phase I of Stage III Contract no:

20.1 Deadline for submission of Bids shall be at 11.00 a.m on 29.07.2021.

34 The amount of Performance Security is 5% of the Initial Contract Price.

36 The Adjudicator proposed by the Employer from three names nominated by the CIDA and agreed by the both parties.

Fees and types of reimbursable expenses to be paid to the Adjudicator shall be on a case to case basis and shall be shared by the Contractor and the Employer.

Page 15 of 170

Page 16: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Contract Data (Please note that the Clause nos. given hereunder are that of Conditions of Contract)

(1.1) The Employer is

Name : Vice Chancellor Address: Ocean University of Sri Lanka,

Crow Island, Mattakkuliya, Colombo 15.

Name of Authorized Representative:

(1.1) The Engineer is

Name : Deputy General Manager (Consultancy)

Address : State Engineering Corporation of Sri Lanka No. 130, W.AD. Ramanayake Mawatha, Colombo 02.

Name of Engineer’s Representative: - Chief Engineer (Designs)

Chief Engineer (Electrical) Chief Architect Chief Quantity Surveyor

The Work consists of removing of existing roof (lower and upper roof), demolition works, construction of new slab (approx area 445m2), roof work to cover the newly constructed slab and finishes of Ground floor including electrical works.

Located at the Premises of the Regional Centre of the Ocean University of Sri Lanka at Boossa

(1.1) The Start Date shall be 14 Days from the issue of the Letter of Acceptance.

(8.1) Schedule of other contractors: None

(9.1) Schedule of Key Personnel:

Minimum persons with qualifications and experience to be defined,

1. 1 nr. BSc (Civil) Engineer with minimum 3 years experience in building construction 2. 1 nr. NCT (QS) with minimum 3 year experience in building construction

Page 16 of 170

Page 17: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

(13.1) The minimum insurance covers shall be :

(a) The minimum cover for insurance of the Works and Plant and Materials is 110% of initial contract price.

The maximum deductible for insurance of the works and of Plant and Materials is 5%.

(b) The minimum cover for loss or damaged to Equipment is to cover the replacement cost.

The maximum deductible for insurance of Equipment is 5%.

(c) The minimum cover for insurance of other property (other than the site) is Rupees 300,000.00

(d) The minimum cover for personal injury or death, for third party and

employees of the Employer and other persons engaged by the Employer in the Works is Rupees 500,000.00 per event.

(13.2) (a) The minimum cover for personal injury or death,

For the Contractor’s workmen is Rs 500,000.00 per event

For the Contractor’s employees other than workmen is Rs.500,000.00 per event

(17.1) The Intended Completion date for the whole of Works shall be 170 Days from the Start Date.

(21.1) The Site Possession Date shall be 7 Days from Letter of Acceptance.

(27.1) The Contractor shall submit a Program for the Works within 14 Days of delivery of the Letter of Acceptance.

(27.3) The period between Program update is quarterly

The amount to be withheld for late submission of an updated program is 2% of initial contract price

(35.1) The Defects Liability Period is 365 Days

(39.2) Engineer may order variations up to a total cumulative value of not exceeding 10% of initial contract price

(47.1) The Contract Price is subjected to price adjustment.

Page 17 of 170

Page 18: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

(48.1) The retention from each payment shall be 10 % of the Certified Work Done.

The limit of retention shall be 5 % of the Initial Contract Price.

(49.1) The liquidated damages for the whole of the Works shall be 0.05% of the

Initial Contract Price per Day.

(50.1) The maximum amount of liquidated damages for the whole of the Works shall be

5 % of the Initial Contract Price.

(51.0) 20% of the Initial Contract Price obtain from a bank operating in Sri Lanka

approved by the Central Bank excluding provisional sums and Contingencies,

against an unconditional Bank Guarantee (on-demand) acceptable to the

Employer for the full value (20%) of the advance payment.

(52.1) The performance security shall be 5 % of the Initial Contract Price obtain

from a bank operating in Sri Lanka approved by the Central Bank.

(58.1) The date by which “as built” drawings and / or operating and maintenance

manuals are required is Date of Completion of the Works.

(60.1) The percentage to apply to the value of the work not complete, representing the

Employer’s additional cost for completing the Works, is 25%.

Page 18 of 170

Page 19: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Section – 6

Specifications

Page 19 of 170

Page 20: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

GENERAL SPECIFICATIONS 1. Specifications for Building works - Volume I - ICTAD Publication No. SCA/4 /I

3rd Edition (Revised ) – 2004 July

2. Specifications for Building works - Volume II Sanitary Installations.

ICTAD Publication No. SCA/4/II

2nd Edition ( Revised) – 2001 October

3. Specifications for Water Supply & Sewerage and Storm Water Drainage works

ICTAD Publication No. SCA/3/2.

2nd Edition ( Revised) – 2002 April

4. Specification for Electrical and Mechanical Works associated with Building & Civil

Engineering -. ICTAD Publication No. SCA/8. 2nd Edition (Revised) – 2000 August

Page 20 of 170

Page 21: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PARTICULAR SPECIFICATIONS

The Particular Specification shall be read in conjunction with the General Specification where applicable. In the event the Particular Specification is in conflict with the General Specification, the Particular Specification shall prevail.

Note:

In the specifications if any materials/fittings are described by using a

trade name, it is only for the purpose of indicating the minimum level of

quality and standard required. The Bidder may use any other

material/fitting, which are considered as equivalent in quality and

standard to those specified therein subject to the approval of the

“Engineer”.

Page 21 of 170

Page 22: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR EXCAVATION AND EARTHWORK

The Contractor shall be solely responsible for any damages caused to existing work

during the Construction

EXCAVATING

If existing sewer lines, water mains, power or telephone cables which are not indicated in

Drawings or other records obtained by the Contractor from relevant Authorities, are

encountered, the Contractor shall notify same to the Engineer. The Contractor shall also

furnish to the Engineer for his approval the Methods of protecting such service lines during

the construction works.

All work in connection with protecting and maintaining the said service lines, cables etc.

shall be to the entire satisfaction of the relevant Authorities concerned. The Contractor

shall be solely responsible for any damages caused to such existing work.

EARTH FILLING

Stripping of Top Soil;

Where the existing ground surface is covered with vegetation top soil or other

unsuitable material, it shall be removed together with roots, rubbish or objectionable

materials etc. Vegetation or other unsuitable material so removed shall be disposed

within 5.0 kms of the site.

Borrow Material

Borrow material shall comply with the following specifications:

a) It shall be tested for its suitability by a recognized testing organization acceptable to

the Engineer. It shall be well graded soil mixture with gravel and sand (not less than

70%) silt and clay (not more than 30%).

b) The Contractor shall forward from each borrow pit at different levels, the test results of

particle size distribution and Proctor compaction tests by a recognized testing

organization to the Engineer for approval.

c) It shall be free of vegetation, roots and such other deleterious material.

d) Maximum dry density at optimum moisture content (Standard Proctor Density) shall

not be less than 1.6 gm/cm3.

e) Maximum size of particles shall not exceed 120 mm.

Placing of Fill Material

The distribution and gradation of the material throughout the fill shall be carried out as

directed by the Engineer, so as to ensure that the fill will be free from lenses, pockets,

streaks, or layers of material differing substantially in texture or gradation from the

Page 22 of 170

Page 23: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

surrounding material. The borrow excavation and placing operation shall be such that the

materials when compacted will blend sufficiently to secure the best practicable degree of

compaction and stability. Successive loads of material shall be dumped and spread so as to

produce the best practicable distribution of material and for this purpose the Engineer may

designate the locations in the fill areas where individual loads shall be deposited.

The fill material shall be placed in layers not exceeding 225-mm thickness in loose state. The

fill shall be compacted at each lift to not less than 90% of the Standard Proctor Density for the

building area. For the earth filling along the road way and access roads, the fill shall be

compacted at each lift to not less than 100% of the standard Proctor density. The thickness of

the 1st layer may be increased to facilitate compaction with the approval of the Engineer.

The method of compaction shall be approved by the Engineer.

Moisture Control

The moisture content of the fill material prior to and during compaction shall be maintained

and distributed uniformly through each layer. The allowable placement moisture content will

be determined by the Contractor on Engineer’s approval so that fill placement can be made

under optimum moisture content of the fill material.

Density Control

To determine the dry density requirements of the compacted fill, field and laboratory tests

shall be made on samples of compacted material taken on a 10-m grid.

Method of Measurement

The quantity of fill material shall be determined by measuring the depth by auguring and

multiplying by the area each auger hole represents. All such quantities shall be added to

determine the total quantity. Interim payments shall be made on quantities estimated by the

Engineer.

General Construction Methods

The Engineer shall have complete control over the excavation, moving, filling and disposition

of all material and shall determine the suitability of material to be placed in fill areas. All

material determined unsuitable shall be placed in spoil area and / or removed from site as

directed by the Engineer.

The Contractor shall inform and satisfy as to the character, quality and distribution of all

materials to be excavated filled, spoiled and borrowed.

Should the Contractor through negligence or other fault excavate or fill beyond the

designated lines, he shall replace/remove such excavation/fill in an approved manner and

conditioned at his own expense.

Page 23 of 170

Page 24: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR CONCRETE

CONCRETE

Concrete shall be a designed mix (designed by the Contractor) approved by the

Engineer.

The various grades of concrete to be used in the works shall be as shown on the

drawings or as described in Bill of Quantities.

The characteristic strength, aggregate size, cement content and usage of concrete shall

be as given below.

Grade Characteristic

Strength

(N/mm2)

Max. Aggregate

Size (mm)

Min.Cement

Content

Kg/m3

Max Water: Cement

Ratio

15 15 20 280 0.55

25 25 20 325 0.50

30 30 20 400 0.50

Grade 15 - Concrete in blinding layer (screed concrete)

Grade 25 - All reinforced concrete work unless otherwise specified.

Grade 30 - Reinforced concrete in piles and pile caps and tie beams.

Grade of concrete used in the construction and the suggested mixes are follows:

Grade 30 - 20mm aggr. (suggested mix 1:1:2)

Grade 25 - 20mm aggr. (suggested mix 1:1 1/2:3)

Grade 20 - 20mm aggr. (suggested mix 1:2:4)

Grade 15 - 25mm aggr. (suggested mix 1:2.5:5)

Grade 10 - 25mm aggr. (suggested mix 1:3:6)

Any other information which is indicated on the Drawings or Bill of Quantities, which may

be at variance with the above, shall be brought to the notice of the Engineer.

Minimum free fall of concrete should be limited to 1.5 m during the placement of concrete.

In the event Lift height is greater than 1.5 m Trimy pipe or similar arrangement should be

used. In any circumstances, casting of columns together with slab and beams will not be

allowed.

Page 24 of 170

Page 25: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

WORKABILITY

The concrete shall be of such consistency that it can be readily worked into the corners

and angles of the formwork and around reinforcement without segregation of the

materials or bleeding of free water at the surface. On striking the formwork the concrete

shall present a uniform face, free from honey combing, surface crazing or subsequent

excessive dusting.

The Contractor shall carry out a series of workability tests on samples obtained from the

batches of the trial mixes used for the preliminary test cubes. These tests shall be

carried in accordance with BS 1881.

No additives or admixtures ie. Material other than cement, aggregate or water shall be

added to the concrete without the written approval of the Engineer.

TESTING

CONCRETE QUALITY CONTROL ENGINEER

The Contractor shall employ a competent and experienced concrete quality control Engineer

who shall be responsible for all concreting carried out for the work. He shall be available in

site at all times when concreting works are being carried out. The name, together with

details of training and experience shall be submitted to the Engineer for approval before the

concrete quality control engineer is appointed.

TESTING ARRANGEMENTS

Prior to the commencement of concreting, the Contractor shall submit for approval of the

Engineer details of his proposed arrangements for carrying out tests. The results of all tests

shall be communicated to the Engineer as soon as possible. The Engineer may require to be

present at any test.

COST OF TESTING

Unless specifically provided otherwise in this Contract the cost of all sampling and testing

and the employment of the above mentioned concrete quality control engineer shall be

deemed to be included in the Bid.

SLUMP TESTS

A slump test in accordance with BS 1881, shall be performed and recorded for each batch of

concrete mixed. The records shall show in which section of the work the concrete has been

placed.

WORK CUBE TESTS

a) The cubes shall be prepared, cured, stored, transported and tested in compression in the

Laboratory and in accordance with the requirements of BS 1881.

Page 25 of 170

Page 26: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

b) Reports of all tests shall be supplied to the Engineer within 24 hours of the testing being

carried out.

c) During early stages of the work, or at other times as he may deem necessary, the

Engineer may instruct the Contractor to increase or decrease the frequency of testing.

RATE OF SAMPLING FOR STRENGTH TESTING

Foundations and Columns : 1 sample for each 10 M3 or 10 batches

whichever represents the lesser volume.

Beams, Slabs, Walls, Stairs : 1 sample for each 20 M3 or 20 batches

Whichever represents the lesser volume.

At least one sample should be taken of each Grade of concrete on each day that concrete is

placed.

From each sample, 6 Test Cubes shall be made, using standard cast steel moulds.

3 Cubes shall be tested for compressive strength at 7 days and 3 Cubes at 28 days.

Sampling, Casting, Curing and Testing shall comply with BS 1881.

The Contractor is to provide a water bath of adequate volume and ensure sufficient stocks of

standard 150 mm cube moulds and slump cones on site, for regular and frequent testing.

The Contractor should carry out tests and submit the following graphical representation of

results to the Engineer, before using the retarders in the works:

{a} Initial set delay in “hours” at ambient temperature Vs dosage in ml/100kg cement, the

hours ranging from 1 to 8

and

{b} compressive strength in N/mm2 of 150 mm standard cubes Vs 3 days, 7 days,14

days and 28 days ages, one curve each for the dosage required for 03hour retardation, 04

hour retardation and 5 hour retardation, respectively.

Testing shall be done in an approved Laboratory.

The casting, curing and testing of cubes should comply with BS 1881 (1970) and

interpretation of results for compliance should comply with BS 5328:Part 4 (1990).

Page 26 of 170

Page 27: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

CONCRETE CORES

a) If the concrete cube results fail to meet the specified requirements the Engineer may

instruct the Contractor to cut a minimum of four cores of 150 mm nominal diameter from

the hardened concrete affected.

b) Cores shall be available for inspection by the Engineer prior to preparation and testing

which shall be in accordance with BS 1881.

c) The Contractor shall provide a coring machine with a diamond bit of at least 150 mm

dia.and all further equipment required.

TRIAL MIXES

a) A set of 6 test cubes shall be taken from proposed trial mixes. Three shall be tested at

an age of 7 days and three at 28 days.

b) At each age of test, no cubes strength should fall below one and one third times (ie.1-1/3

times) the specified works test cube’s strength.

c) Before beginning the works the contractor shall submit to the Engineer for his approval

full details of these tests together with grading analysis and mix design calculations.

d) The Contractor shall not place any concrete on site until the Engineer has approved the

Mix Design.

e) The Engineer may require the Contractor to submit test results at regular intervals from

the concrete cast in the work. The Contractor shall allow for this in his Bid.

LIMITS OF ACCEPTABILITY

The concrete shall be deemed to be in accordance with the specified requirements if the

following conditions are met.

a) Work Cube Tests

Compliance with the specified characteristic strength may be assumed if:

The average strength determined from any group of four (4) Consecutive test cubes

exceeds the specified characteristic strength by not less than 0.5 times the current

margin of 15 N/mm2.

Each individual test result is greater than 85% of the specified Characteristic strength.

b) Cement

The cement content of any batch shall be within 5% of the approved cement content for the particular grade of concrete.

c) Workability

Page 27 of 170

Page 28: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The slump for each batch of concrete shall be within either 25 mm or ¼ of the required value

whichever is greater. The required value for each Grade shall be agreed on the basis of the

trial mixes/type of construction.

d) Water / Cement Ratio

The water / cement value of any batch of concrete shall be within –5% of the value approved

for the particular Grade of concrete.

FAILURE TO COMPLY

If any concrete fails to comply with the requirements of Para3.4.1 above, the Engineer may

order additional testing as he deems necessary and/or may condemn such concrete and

order it to be broken out and made good as directed by the Engineer at contractor’s cost.

MIXING OF CONCRETE

Ready-mix Concrete from a Central Mixing Plant is only permitted. All the details of the

Mixing Plant and relevant Test Results should be submitted to the Engineer for approval.

The Contractor will maintain on site a cellular telephone link between site and the Concrete

Mixing Plant and record times of Truck Mixer leaving Plant, arriving at site and the Truck

Mixer number. Copies of all records are to be delivered to the Engineer’s Representative

daily or more frequently, if requested.

PLACING OF CONCRETE

At least 24 hours before the Contractor proposes to place concrete in any section of the

works, he shall notify the Engineer as to his proposed time of commencing. When the

Contractor has completed all preparatory work such as surface preparation, form work,

reinforcement, built-in parts etc. he shall request the Engineer for written approval to

commence concreting at a particular time not less than 3 hours after until all preliminary work

has been checked and written approval given by the Engineer.

CURING CONCRETE

Concrete shall be protected against harmful effects of weather, running water and

drying out by one of the following methods appropriated to the particular situation.

A liquid curing compound shall be applied to the concrete surface by a low pressure

spray until a continuous visible covering is achieved.

The concrete surface shall be covered with hessian, sacking, canvas or other

absorbent material agreed by the Engineer.

The concrete surface shall be covered with polyethylene sheets; concrete surfaces

which have become dry shall be thoroughly wetted before the sheeting is placed.

The minimum curing period shall be seven (07) days.

Page 28 of 170

Page 29: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

DOCUMENTS TO BE SUBMITTED FOR APPROVAL OF THE ENGINEER

Contractor shall be responsible to prepare and submit to the Engineer for approval following

documents at least six weeks before the commencement of the work.

a. Shop Drawings (for form work, masonry work including the Stiffener

column/beam arrangements, roof steel work).

b. Bar bending schedules.

c. Construction drawings for all temporary works (including shoring/cut-off wall

construction, dewatering system, etc.)

d. Drawings for pouring patterns, casting sequence construction joints.

Formwork

CONSTRUCTION OF FORMWORK

The Contractor shall be totally responsible for designing the Formwork and

supporting props required to construct the structure in accordance with the Contract.

The Contractor shall submit detailed calculations and drawings of the proposed

Formwork system to the Engineer for his approval well in advance of the actual

commencement of the work at site.

The Formwork shall be of sufficient strength and stability to safely support the wet

Concrete and any incidental loads which may be applied to the concrete surface

before it has attained sufficient strength to enable it to safely carry such loads

unsupported.

The maximum elastic deflection of any Formwork component shall not exceed

1/500th of its span.

The Formwork shall be constructed with sufficient camber to ensure that the finished

soffits and top surfaces are plain and true.

The Contractor shall ensure that those part of the structure supporting Formwork for

other parts have attained sufficient strength to carry the loads thus imposed without

causing structural distress and any elastic deflection greater than 1/300th of the

minimum span of such a part.

In all water tight walls, Formwork ties shall be left embedded and shall consist of

steel pins with steel discs welded all round (watertight) to them. The disc shall be

located centrally in the wall.

Page 29 of 170

Page 30: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

CLASSES OF FINISH

All concrete surfaces in the superstructure that will be subsequently plastered shall have

“Basic formed finish” (Section5.4.8.1.1 ICTAD).

Soffit of slabs and beams that will be covered by a ceiling underneath and hence will not be

plastered shall be “Plain finish” (Section 5.4.8.1.2 ICTAD).

SOFFIT FORMWORK

The final top surface level of the slab should be correct to a tolerance of +3mm in 3m.

COLUMN FORMWORK

Plan dimension tolerance permitted is +3 mm for 350 and 530 columns. Deviation in

verticality of column should be within +10 mm in a storey height.

DEFLECTION LIMIT

Deflection should be limited to under 1/270 of the span.

Striking of Formwork`

Minimum period before striking Formwork.

Vertical Formwork to columns, walls and large beams 03 days

Soffit Formwork to slabs 14 days

Soffit Formwork to beams 21 days

Care should be exercised to avoid damage to the concrete, especially to arises and features.

LOCATION OF JOINTS

Location and design of construction joints, if not shown shall be proposed for the Engineer’s

approval. The use of construction joints shall be kept to a minimum.

MOVEMENT JOINTS

Movement joints in basement structure shall be made water tight using styrene – butadiene

rubber (SBR) water stop or PVC water stop of approved manufacture and shall have a minimum tensile strength of 15 N/mm , a minimum elongation of 300%, and a tear resistance greater than 3 N/mm .

CONSTRUCTION JOINTS – IN PERIMETER CONCRETE BELOW GROUND LEVEL

All construction joints in this part of the structure shall be provided with black steel water

bars of minimum dimensions 200 x 2 which shall be butt welded throughout their width at all

joints.

Page 30 of 170

Page 31: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

WATER TIGHTNESS OF BASEMENT

The complete water tightness of the complete basement construction shall be proved before

either wall finishing to the inside faces of external walls in the basement are applied or the

floor slab of the basement in cast.

REMOVAL OF FORMWORK

The approval of the Engineer shall be required before the removal of any Formwork.

Before soffit forms or supports are removed, the concrete shall be exposed by removal

of side forms, or as otherwise required by the Engineer, for the purpose of verifying that

concrete is sufficiently hardened.

REINFORCING STEEL

Reinforcement bars should comply with specifications in BS 4449:1988 and mesh

reinforcement with BS 4483:1985. Steel reinforcing bars considered in the design are

highly yield strength bars for diameters 10, 12, 16, 20, 25,32 the characteristic strength

should be 460 N/mm .

Detailing is prepared on the assumption of the use of 12 m bar lengths.

6mm diameter bars shown in reinforcement details are mild steel (fy = 250 N/ mm ).

Reinforcement bending schedules shall be prepared and produced for Engineer’s

approval by the Contractor. Bending and fixing of bars shall start only after the

Contractor has convinced himself that no changes will be made to the concrete structure.

Mill certificates of composition and strengths of steel, and certificates of strength tests on

samples of steel purchased for use on this project and tested in an independent

approved local Laboratory should be furnished.

Spacer for achieving cover to reinforcement:

Specified concrete cover to reinforcement bars should be provided using cover blocks.

Chairs should be used to support top horizontal reinforcement and to separate vertical

reinforcement in walls.

READY MIXED CONCRETE

1. Reinforced Cement Concrete

2. Requirements Of Ready Mixed Concrete

Page 31 of 170

Page 32: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Specification of Concrete Mix

The concrete used shall be ready mixed concrete in accordance with the requirements of BS

5328 and also conform to the following:-

It shall be a designed mix.

Cement used shall be ordinary Portland cement conforming to

BS 12:1989

Coarse and fine aggregates used shall conform to BS 882:1983.

Nominal maximum size of aggregate shall be 20mm.

Concrete shall be of grade 25 or grade 30 as specified.

Minimum cement content 275 kg/m3.

The rate of sampling shall be such that on an average a sample for strength testing

shall be taken for every 50m3 of concrete placed.

Slump shall be not less than 100mm and not to exceed 160mm.

Maximum free water / cement ratio 0.60.

Maximum cement content 450 kg/m3.

Any admixture used shall be with prior approval.

The Contractor shall submit the designed mix specification to the Engineer for prior approval.

Covering Screed – Concrete

Concrete Covering Screed

50mm thick, grade 20 reinforced concrete covering screed shall be laid over the separation

sheet as shown on the drawing. A 50 x 50mm (3mm dia.) galvanize steel wire mesh shall be

provided in covering screed to limit the concrete screed panel size approximately to 12-16

square meters.

Expansion Joints

Expansion joints shall be coincided with the joints of the tile layer above (if any).

Expansion joint shall be filled with a UV resistant joint sealant made from two part

polysulphide sealant (pouring grade).

Page 32 of 170

Page 33: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR MASONRY WORK

1.0 Brick Work

Refer SLS 39/1978 as amended in amendment No. 1 of 1981 and Chapter 6 of

specifications for full descriptions of material and workmanship. Bricks used in this

construction shall be moulded burnt clay bricks conforming to Type II Grade II.

One brick thick walls shall be laid in English Bond and set in 1:6 cement sand mortar one

brick thick wall in contact with ground shall be built in 1:5 cement sand mortar.

The Contractor shall furnish to the Engineer for his approval samples of clay bricks prior to

the delivery of bricks to the site. Bricks used in the construction shall conform to the

approved Standard.

Chasing in Brick Work should be carried out by an experienced mason. Chasing to pipes

exceeding 25 mm shall be carried out only after the written approval of Engineer.

Put log scaffold shall not be used in wall construction, plastering etc.

All Brick Work will be plastered with cement sand mortar, hence bed joints in Brick Work

shall be tooled to form key to plaster work. The faces of the finished brick work shall be

even, and shall not have staggered courses of Brick Work.

Ensure that the maximum finished thickness of plaster does not exceed 20 mm.

2.0 Cement Sand Block Work

Cement blocks shall be 390 x 200 x 190 mm strictly conforming to “Specification for Cement

Blocks” SLS 855 of 1989 Part I and II. The blocks shall be cellular closed cavity or hollow

blocks uniform in size and having an even surface. Blocks shall not be broken to reduce

lengths of blocks. For this purpose, corner column blocks or special cellular/cavity blocks

designed to be cut into two (such as “Amtrad Type AC & ALC respectively) shall be used.

Jambs at opening for doors or windows shall be built with corner column blocks.

Cellular/cavity blocks shall not be chased for pipe or conduits without specific written

approval of the Engineer.

3.0 Anchoring / Pinning

3.1 General

Block work, abutting R.C. structures or M.S. structures shall be anchored to them by

means of galvanized M.S. rod anchors dia. 4 mm or M.S. strip anchors 2 x 20 x 300 laid

at approx. 600 C/C.

Perimeter block/brick walls shall be well anchored to the slabs/structures on which they

are to be erected, in a manner as outlined in Clause 4.3.1.1.

Page 33 of 170

Page 34: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

3.2 Pinning and Wedging

Tops of block/brick walls below non-deflecting structures shall be anchored to all soffits by

means of galvanized m.s. rod anchors, as shown on the drawings.

At deflecting structure, movement shall be assured by means of 30 minutes fire rated

compressible filler 20 thick, as shown on the drawings. Block and brick work should be

anchored to the deflecting structure by means of stainless steel anchors which can transfer

the lateral loads applying on block/brick work while allowing the vertical deflection of the

structure.

4.0 Reinforcement of Block / Brick Walls

4.1 General

Block / Brick walls, whether solid or hollow, shall, when greater than approx. 12 m in

one area and when unsupported laterally by block/brick walls, concrete walls or columns,

be provided with a reinforcing system of R.C. columns and tie beams of a section of 200

by a thickness, depending on the relevant wall thickness.

Where used, expanded metal reinforcement shall be totally embedded in the mortar

joints and kept back 10 mm from both faces.

4.2 Columns and Tie-Beams

R.C. columns shall be formed flush with the faces of the block work / brick work and

reinforced with vertical rebars dia.10 mm lapping with starter bars/anchors, tied into the

concrete structure.

RC Tie-Beams shall be formed flush with the faces of the block work/brick work and

reinforced with rebars dia.10mm tied into the columns and anchored to surrounding R.C.

Structures.

Block work/brick work shall be fixed into columns and Tie-Beams with anchors as

specified in Clause 4.3.1.1. This applies to any method which will be used to work up

block walls.

Reinforcement of columns and Tie-Beams shall be reinforcement bars lapping with

spacer bars cast into the R.C. structures. Block/brick shall be fixed with anchors to such

columns. The surface of the joints (between concrete and block work/brick work) shall

be sealed with flexible sealant of appropriate colour as approved by the Engineer.

If block/brick walls are longer than 6000, then regardless of height, expansion joints shall

be introduced, composed of polystyrene packing, 10 thick and sealed as illustrated in

drawing with the block work/brick work connected with m.s. anchors between every 3rd

course (approx. 600 c/c).

The plaster work at expansion joints should be filled with a flexible sealant. If the surface

is faced with granite or tiles then the joints should be as illustrated in drawing and the

sealant should be of a matching colour approved by the Engineer.

Page 34 of 170

Page 35: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR STRUCTURAL STEEL WORK

1.0 Standards

For the structural steelwork, the following Codes and Standards will be applicable:

BS 5950 – Specification for the use of structural steel in building.

BS 4360:1986 – Specification for weld able structural steels.

Unless otherwise specified the structural steel to be used shall be mild steel Grade

43.

All weld metal shall be suitable steel relative to the parent metal of the structure and

all electrodes used for manual welding shall conform with BS 639. Continuous

electrodes for machine welding shall be to the approval of the Engineer. All welding

must conform to BS 5135.

Site-bolted joints will normally be made using general grade high strength friction grip

Grade 8.8 bolts conform with BS4395, and conform with BS 4190.

2.0 General

In general, shop joints shall be made by welding and site joints by bolting. Site

welding will not be permitted without the express approval of the Engineer.

Contact between galvanized steel members and aluminium surfaces are to be

prevented by means of a layer of P.V.C. self-adhesive plastic tape “Densochrome”

tape or similar approved material.

Steel members for purlins, side and sheeting rails shall be of hot-rolled steel

sections. The use of cold formed steel sections for structural purposes is not

allowed.

3.0 Drawings and Calculations

3.1 Contractor’s Obligations, etc.

The Contractor shall check dimensions on all Shop Drawings with the dimensions on

the Contract Drawings before start of manufacturing of the relevant items.

Should any discrepancies occur between the Contract Drawings and the

Specification, the matter is to be referred immediately to the Engineer for a decision.

Page 35 of 170

Page 36: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

All steel members shown on the Contract Drawings are based on West European

Standards, dimensions, weights and strengths. In case the specified sizes should

not be available, the Contractor shall submit alternatives which shall be to the

approval of the Engineer in all respects.

The Contractor shall prepare and submit for the Engineer’s approval detailed working

drawings for the structural steelwork if an alternative is to be offered to the Architect’s

design.

Detailed design, fabrication, erection, etc.shall comply with all requirements of BS

5950 including amendments.

The Contractor shall prepare and submit for the Engineer’s approval before

manufacturing, all calculations and Shop Drawings, for all parts of the steel structures

and all detailed drawings of all connections in welded, bolted or riveted constructions.

The Engineer’s approval does not release the Contractor from his responsibilities for

the structure and the dimensions on such Shop Drawings.

The Contractor shall prepare assembly drawings showing the location, position and

reference numbers of all components including fixing materials and sequences of

erection and installation to the approval of the Engineer.

Any damage to materials on the site or other storage areas due to inadequate

precautions being taken during the erection of steelwork shall be made good as

required by the Engineer at the Contractor’s expense.

4.0 Scope of Work

4.1 General

The steel works to be supplied and delivered according to drawings and

specifications comprises all structural steel work including the necessary anchors,

base plates, head plates, connecting plates, stiffening plates, bolts, nuts, washers,

temporary bracings and any additional rails required for the fixing of the roofing and

cladding, etc.

The Contractor shall supply and fix all mild steel profiles such as mild steel angles, to

be welded to various structural steel frame members to receive block work, mild steel

plates at columns at corners, etc. all according to the structural (ST) and architectural

(AR) drawings.

To be included in the supply and delivery are the holding down bolts as Indicated on

the Drawings.

Page 36 of 170

Page 37: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The Contractor shall supply the Architect with test certificates obtained from the

rolling mills with each delivery of structural steel and reinforcement steel. The

Architect may order additional tests to be carried out, as may be required, the costs

of which shall be borne by the Contractor.

5.0 Welding

5.1 Materials and Workmanship, etc

Machine welding shall be carried out using approved machines sufficiently supervised

by qualified operators and hand welding shall be executed in an efficient manner by

fully qualified workmen equipped with plant suitable for the purpose. All welding tests

shall comply with BS 4870 and 4871 so far as applicable and except as modified in

this specification.

The manipulators and the sequence of welding shall be suitable for the work, and

shall be subject to the Engineer’s approval before welding is commenced.

Welding procedure shall be such that distortion is reduced to a minimum and local

distortion is rendered negligible in the final structure.

Surfaces to be welded shall be properly prepared in accordance with accepted

Standards and during welding shall be kept clean and free from all extraneous

matter.

All welds shall be finished full and made with the proper number of runs, the welds

being kept free of slag intrusions and all adhering slag being carefully removed from

the exposed surfaces immediately after each run.

Approval of any welding procedure shall not relieve the Contractor of his

responsibility for correct welding and for the minimizing of distortion in the finished

structure.

Only skilled welding operators who satisfy the appropriate welding tests specified in

the relevant Standards shall be employed on welding.

Notwithstanding any routine testing of operators by the Contractor, the Engineer

reserves the right to have any welding operator re-tested at any time.

In addition to the Contractor’s normal supervision and testing procedure, radiographic

and other non-destructive examination shall be carried out, as an when required by

the Engineer, on butt or fillet welded joints and/or on test specimens. Prepared

etched sections of welds may be required for examination. The Contractor shall at

his own cost, provide all equipment necessary for such tests and shall cut out and

remove any portion of the steelwork which the Engineer shall decide is defective.

Page 37 of 170

Page 38: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The acceptance of the welded work shall depend upon correct dimensions and

alignment, absence of distortion in the structure, satisfactory results from the

examination and testing of the joints and the test specimens, soundness of the

welds, and upon general good workmanship.

Welding other than in properly equipped fabricating shops will normally be limited to

non-structural members except where specifically permitted by the Engineer and

designated beam seating and cleats to be welded to the structural steelwork for

receiving the small steelwork.

6.0 Bolted Fixings

6.1 General

All bolts and nuts shall be complete with washers and shall be galvanized where

specified. If washers are not shown on the drawings, they shall be provided in

accordance with best current practice to the approval of the Engineer.

Where H.S.F.G. bolts are used, the holes shall be drilled full size to a diameter not

more than 2 mm greater than the shank diameter of the bolt and all burrs shall be

removed.

Any type of H.S.F.G. bolts which the Contractor may wish to supply and use shall be

submitted to the Engineer for approval and must comply with BS 4395.

7.0 Corrosion Resistance system

7.1 General

The Contractor shall ensure that all the structural steel elements and components

used in the structures will be cleaned properly (Sand blasted) and apply given paint

systemaccording to the cords ISO/EN12944and the structural drawings.The

contractor shall be obtained the approval after the surface preparation form the

Engineer prior to paint application. All the damages occur during fixing and erections

shall be re painted as instructed by the Engineer.

Page 38 of 170

Page 39: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

8.0 Erection of Steelwork

8.1 General

The Contractor shall ensure that all component parts of the structures will fit correctly

and that the holes of adjoining members correctly register with one another. The

Contractor shall temporarily erect at this works such proportion of the component

parts as is necessary to verify to the satisfaction of the Engineer the accuracy of

fabrication.

The verification will not however relieve the Contractor of his responsibility in

ensuring correct fit, etc.

The Contractor shall include in his rates all costs in respect of temporarily erecting

components, the provision of all necessary scaffolding, flooring, staging, bolts and

everything else necessary for erection. The Contractor shall be responsible for the

stability of the structures at all stages of erection and his attention is drawn to the fact

that high winds may occur at the site

The steelwork shall be lined, leveled and plumbed as the erection proceeds

and not cladding or doors shall be fixed to the framework until the bolting up, lining,

leveling and plumbing is complete and to the satisfaction of the Engineer.

After steelwork has been plumbed, lined and leveled, all bases shall be grouted with

neat non-shrink grout of as dry a consistency as possible compatible with the

requirement as regards pouring, raking and ramming of the grout under and through

the steel bases. The grout shall be from an approved manufacturer and shall be

applied in strict accordance with his instructions.

9.0 Information with the Bidder

9.1 General

Information required to be supplied with the Tender and mentioned in this Chapter is

listed below.

Failure to supply information required may result in rejection of the Tender.

The Contractor should not rely solely on this list, which may be incomplete, but

should ensure himself that all information required by the Contract Documents is

supplied in full.

1. Details of structural steel members, where the Contractor proposes to use

profiles differing from those specified or shown on drawings.

2. A list of manufacturers proposed for the main items mentioned in this Chapter

Page 39 of 170

Page 40: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR ELECTRICAL INSTALLATION

1.0 General Requirements

1.1 Scope of Work

The scope of work shall include the provision of all materials, equipments, plant, labour and

services for the satisfactory installation, testing, commissioning and maintenance, during

the Defects Liability periods of the complete Electrical Installation works as specified here

after and as indicated on the Electrical Drawings, and shall include all minor incidents and

associated works which may not be specified in the in the contract but, which are in the

coursed of the functioning and operation of the completed Electrical Installation, considered

necessary in the sole opinion of the consultant/ supervisor, for the safe and proper

functioning and operation of the completed Electrical Installation.

1.2 Application of the Section

The items specified in this section are applicable to all sections of this specification.

1.3 Quality of Material and Equipment

The Contractor shall supply all equipment to be used under the scope of this contract with a

proven quality. The Contractor shall furnish manuals and operational instructions for each

facility where component items of mechanical and/or electrical are furnished under this

contract in accordance with the following clauses.

1.4 Manufacturer's Literature

The contractor shall submit to the Engineer three (03) copies of manufacturer's descriptive

literature in English for each and every item of equipment furnished complete not later than

2 months prior to the date of provisional hand over.

1.5 Equipment Operation

The Contractor shall furnish manuals and operating instructions for each facility where

component items of mechanical and/or electrical equipment is furnished and/or installed

under this contract within the same time limits as described in Para 1.2 of this section and

in accordance with the following paragraphs.

The draft of each manual shall be submitted to the Engineer for approval before printing.

Page 40 of 170

Page 41: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Each manual shall be printed on good quality paper and be bound in hard covers.

1.6 Operation and Maintenance Charts

The Contractor shall furnish three (03) copies of an operation and maintenance instruction

chart, which will incorporate applicable comprehensive descriptive instructions, layouts,

diagrams or any other information that will be necessary, and/or of value to the operating

and maintenance personnel.

1.7 Operation and Maintenance Manuals

The Contractor shall furnish three (03) copies of an operation and maintenance manual,

which shall contain complete instructions for overall operation, and maintenance of the

facility and its component parts. The manual shall also contain the operating and

maintenance instruction charts as specified in section 1.5.

1.8 Adequacy of information submitted

The Engineer/Consultant reserves the right to determine whether the above specified

information as furnished by the Contractor is adequate and complete and to require such

additional submission by the Contractor as necessary to ensure the satisfactory operation

of the various items of equipment and to fulfil the intent of the specifications.

1.9 Materials, fittings and accessories

Bidders are specifically cautioned to the following minimum considerations, which will be

reviewed by the Engineer/Consultant prior to approving any materials, item of equipment or

assembly of construction.

1. Full conformance with architectural and engineering design criteria, design concepts

and performance requirements.

2. Physical dimension requirements to satisfy the space limitations, indicated on the

drawings.

3. Static and dynamic weight limitations.

4. Audible noise level and vibration generation of equipment or assemblies with moving

parts.

5. Interchangeability of parts and components.

Page 41 of 170

Page 42: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

6. Accessibility for preventive maintenance, possible removal and replacement.

7. Compatibility for preventive maintenance, possible removal and replacement.

8. Compatibility with other materials, assemblies and components.

9. Full compliance with all applicable test requirements.

10. Full compliance with guarantee requirements.

Although these designs are mainly based on British Standards and IEE regulations,

equipment designed according to other internationally recognized standards and satisfying

the design criteria and performance requirements mentioned therein will be acceptable if

proved equal or better.

1.10 Un-named Products

Materials, equipment, fixtures, apparatus, appliances, accessories and similar

manufactured products supplied without a manufacturer's name or without a trade name of

the manufacturer, shall include catalogue numbers or similar descriptive data indicating

clearly that the products comply with all requirements of the specification and the

appropriate drawings.

Products which deviate in minor respects from those specified may be proposed after the

award of contract; providing that the proposal is accompanied by a document and drawings

of deviation clearly stating all deviations. Supplying and installing approved deviations shall

be executed at no additional cost.

1.11 Drawings

1.11.1 General

The Contractor shall carefully investigate the structural and finish conditions affecting all

work and shall arrange such work accordingly. He shall if necessary furnish additional

items, not shown on the drawings but necessary for the works to meet the specifications

and/or conditions, at no additional cost.

1.11.2 Verification of Dimensions

The Contractor shall check all drawings and the site conditions to familiarize himself

thoroughly with all details of the work and working conditions and verily all dimensions in

Page 42 of 170

Page 43: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

the field; and shall advise the Engineer/Consultant on any discrepancy or deviation. If

discrepancies or deviations are submitted to the Engineer/Consultant, the Contractor shall

wait for judgment and explanation in writing from the Engineer/Consultant before

performing any work.

1.12 Cutting and Repairing

The work shall be carefully laid-out in advance and no cutting of the structure will be

permitted. Damage to buildings and technical installations as a result of cutting for

installation shall be repaired by persons skilled in the trade involved at no additional cost to

the satisfaction of the Engineer/Consultant. If inspection or tests show defects, such

defective work or material shall be replaced or repaired as necessary and inspection and

tests shall be repeated at no extra cost. Repairs shall be made with new materials.

1.13 Safeguarding the Fixtures, Materials and Equipment during the Installation

Pipe and Ducts openings shall be closed with caps or plugs during installation for protection

against mechanical damage and the client shall not be responsible for theft damage or loss

of any of the materials. Fixtures and equipment shall be covered and protected against dirt,

water, moisture, sand and chemical or mechanical injury. Upon completion of all works the

fixtures, materials and equipment shall be thoroughly cleaned, adjusted and tested to

demonstrate its proper operation to the Engineer.

All materials and equipment shall be properly and adequately protected by the contractor

before, during, and after installation. Material or Equipment damaged due to inadequate

attention of the Contractor shall not be accepted and the client reserves the right to request

replacements for such equipment at the handing over. Replacement of items damaged due

to unavoidable circumstances during removal shall be paid on measure and pay basis.

It is the responsibility of the Contractor to clean the installation at close of work every day

and also to hand over a clean and neat installation at completion.

1.14 As-Built Drawings

The Contractor shall maintain a complete set of drawings at the site on which details shall

be marked exact locations of all mechanical, electrical and control systems complete with

dimensions taken from column center lines. The crossings of other services, the

termination and equipment layout shall be marked during the installation and the Contractor

shall obtain the approval of such drawing before preparing the final as-built drawings. As

Page 43 of 170

Page 44: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

built drawings shall be turned over to the Engineer in accordance with requirements as

specified with the handing over

1.15 Samples

Samples of all electrical, materials, fittings and accessories should be handed over to the

Engineer/Consultant and approval obtained before commencing the work. The work shall

be carried out using such fittings and accessories. These samples will be returned to the

Contractor on successful completion of the project.

1.16 Access Openings

The contractor shall provide all access, openings required for inspection and maintenance

of the installations.

1.17 Language

All information, communications and correspondence shall be in the English Language.

1.18 Codes and Standards

All equipment, materials and workmanship shall be in conformity with relevant and

applicable British Standards and codes of practice where available and currently valid.

1.19 Inspection and Testing

The Contractor shall perform all tests as directed by the Engineer/Consultant and shall

demonstrate the proper operation of all systems. All labour materials and equipment

required for tests shall be provided by the Contractor at no extra cost. Defective

equipment, materials and workmanship shall be replaced, repaired or corrected by the

Contractor and re-tested and re-demonstrated for proper operation.

An Inspection and Testing certificate of the electrical installation conforming to the 18th

edition of the IEE regulations (BS: 7671) should be obtained form a Charted Engineer

before handing over of the installation for relevant authority for approval. If any defects

were detected at this stage Contractor shall rectify the defect or replace the defected items

and re-test if necessary.

Page 44 of 170

Page 45: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

2.0 L.V. Main Switch Boards and Sub Distribution Boards

2.1 Scope of work

Scope covers the fabrication, supply, erection and commission of the Main Switchboard

and Sub Distribution Boards inclusive of mounting cable connections, site tests and

commissioning.

Design of the switchboard with detailed drawings and the requirements of trenches inside

the power room and where necessary shall be provided by the successful Bidder.

LV Main Switch Boards and Sub Switch Boards specified in this section shall apply to all

sections of these specifications.

APPLICABLE PUBLICATIONS

Refer Section: General Requirements.

2.2 Applicable Standards

BS EN 60439 – 1, 1994 Low voltage switchgear and control assemblies.

IEC 446, 1989 Identification of conductors by colours and numerals

IEC 529, 1989 Degree of protection (IP Code)

IEC 664-1, 1992 Insulation co-ordination of low voltage switchgear and control –

gear

IEE Regulations 18th Edition wiring regulations.

2.3 Operating Parameters and Conditions

Rated continuous voltage: 230 V, 50 Hz, phase to earth and 400V,

50 Hz, phase to phase.

Number of phase: 3 phase, 4 wire system

Type of Earthing: TT system (IEE Regulations)

Installation type: Indoor/Outdoor

Page 45 of 170

Page 46: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Degree of protection of cubicles: (IEC 529) IP 54, Natural ventilation or forced ventilation.

Maximum Ambient Temperature: 40C.

Insulation level: between live parts and earth LI -6 kV PF, 50 Hz- 2.5 kV

Between phases LI –7.5 kV PF, 50 Hz- 4 kV

Fault level at the transformer LT terminals: 18 kA

Pollution category: 1 (IEC 439-1)

2.4 General

Main Switch Board and Sub Distribution Boards in each floor shall be of the wall mounting,

metal clad, flush fronted cubicle type with front access. The cable entries shall be from the

bottom of the switchboard. The switchboards shall be constructed in accordance with B.S.

5486 for operation in a 400 Volts 3 phase, 4-wire 50 Hz system.

Generally, the switchboards shall be capable, as a whole of withstanding without damage

the electrical, mechanical and thermal stresses produced under short circuit conditions.

Special attention shall be given to insulation and finish of all items and no hygroscopic

material shall be used in any position, and all components shall have a good finish and

perform at 40 C and 90% R.H.

2.5 Construction

Each cubicle framework shall be fabricated from rolled steel angle sections and shall be

self-supporting when assembled and of standard size, uniform in height and depth. The

cubicle panels and doors shall be fabricated from minimum 14SWG sheet steel to provide a

clean, flush and rigid construction without welded cross struts. The cubicle shall be

strengthened by horizontal and vertical folded channels and corner gussets.

Full access shall be provided to control equipment inside cubicles by means of suitable

hinged doors secured with an approved locking device. All doors shall be provided with

approved type of gasket. The cubicles framework shall be manufactured from electro-zinc

plated sheet steel, and finished with electro-statically applied epoxy powder paint with a

thickness lot less than 80 microns. The epoxy powder paint shall be grey in colour unless

otherwise specified by the Engineer/Consultant.

Page 46 of 170

Page 47: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

2.6 Bus Bars

The main bus bars shall be arranged horizontally in a ventilated separate compartment.

The bus bars shall be of adequate cross sectional area to given the current ratings as

shown in the drawings, after allowing for all necessary derating factors. The main bus bars

shall comprise four rectangular section bars of equal cross sectional areas (i.e. full size

neutral) fabricated from hard-drawn high conductivity (HDHC) copper, electro-tinned for the

entire length, rigidly mounted on proprietary made non hygroscopic insulators. All

connectors from the bus bars to the circuit breakers, shall be identified by means of colour

PVC sleeving or painting to indicate the phases.

Bus Bar insulators shall be selected for BIL of 6kV, impulse withstand voltage of 1.2/50 s

impulse, and power frequency withstand for 1minute of 2.5kV at 80kPa and in dry condition.

2.7 Switch Board Arrangement

The contractor shall provide the proposed switchboard layout drawings for the

Engineer’s/Consultant’s approval before fabrication of switchboards. Switch Boards shall

be arranged to suit the space available.

2.8 Earthing

A suitable earthing terminal shall be provided on the frame of each section of the

switchboard for connection to earth. An electro tinned HDHC copper earth bar shall be

provided in each switchboard for earthing of all outgoing circuits and equipment frames.

2.9 Labels

All cubicle doors shall be appropriately labelled to indicate the service. Labels shall also be

provided to identify all items of equipment, circuits, cables and where applicable current

ratings of circuit breakers and setting of relays. Details of the labels shall be submitted to

the Engineer/Consultant for approval prior to manufacture.

Page 47 of 170

Page 48: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

3.0 Final distribution board

3.1 Scope of Work

Scope covers the supply, installation and commissioning of the Final Distribution Boards

and Sub Distribution boards as per the BOQ. The location of the distribution board is

indicated in the drawing.

Distribution boards specified in this section shall apply to all sections of these

specifications.

Applicable Publications

Refer to section: General Requirements

Applicable Standards

All MCCB, disconnecting devices shall conform to IEC 947-2, IEC 947-3.

The contact separation shall confirm to table 14 of IEC 439-1

All MCB shall confirm to IEC 898.

All RCCB shall confirm to BSEN 61008.

3.2 Construction

It shall be of a reputed make conforming to BS 5486 or equivalent flush mounted suitable

for 400/230 Volts 3 phase/single phase 50Hz supply. The breakers shall be “DIN” rail

mounted type complete with bus bars, neutral and earth bars.

Distribution boards shall be completely enclose in dust, insect and vermin proof units

housing MCB’s, MCCB's contactors, and all necessary items of equipment whether

specified herein or not.

It shall be suitable for indoor service in ambient temperature of up to 400C with 90% relative

humidity at maximum continuous rating without exceeding the maximum temperature

permitted by the relevant B.S. specifications.

All distribution boards shall be manufactured to withstand as a whole the electrical,

mechanical and thermal stress that could be produced by the prospective fault levels at

their respective points of application.

Page 48 of 170

Page 49: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Special Attention shall be given to insulation and finishes of all items and no hygroscopic

materials shall be used in any position and all components shall have a clean finish.

Each distribution board shall be so arranged that all connections are easily accessible from

the front of board. Adequate space shall be provided for outgoing circuit wiring so that the

cable will not be required to pass between the back of the enclosure and the circuit

breakers.

All cables shall be bundled by means of nylon self-locking cable ties and fixed in a neat and

systematic manner.

Each distribution board shall be provided with a label of laminated plastic black, engraved in

white with the words D.B. followed by the reference designation.

3.3 Residual Current Circuit Breakers (RCCB)

Residual current circuit breakers shall be the current operated type 2 or 4 pole as shown on

the drawings, suitable for operation on 230/400 volts, 50Hz A.C. system and manufactured

to comply with the relevant British standards, BSEN 61008.

The residual current circuit breakers shall be the high sensitivity type with tripping currents

as shown, and shall be so designed that the tripping action is completely independent of the

supply voltage. The rupturing capacity of the earth leakage circuit breakers shall be

adequate to withstand the prospective fault level at the respective points of application.

Page 49 of 170

Page 50: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

4.0 LV Cables

4.1 Scope of Work

Supply, laying, termination, and commissioning of the cables shall be as per the BOQ. All

cables shall be laid, clipped to the walls or slabs, or laid in buried conduit or enclosed in

conduits clipped on to the wall or slab as described in the BOQ.

LV Cabling specified in this section shall apply to all section of these specifications.

4.2 Applicable Publications

Refer to Section: General Requirement

4.3 Applicable Standards

BS 951: 1986 Specification for clamps for earthing and bonding purposes

BS 6346: 1989 Specification for PVC insulated cables for electricity supply.

All multi core cable up to sub distribution boards shall be as indicated in the BOQ and the

drawings. The single core/two core cables running in conduit shall be PVC insulated with or

without PVC sheath. All cables shall be with high conductivity stranded copper conductors

and sizes shall be as indicated in the contract drawings.

4.4 Cable Codes

The following cable codes are used throughout and as called for by this specification and

drawing.

a. PVC Polyvinyl chloride insulated

b. PVC/PVC Polyvinyl chloride insulated and Polyvinyl Chloride sheathed.

c. PVC/SWA/PVC Polyvinyl chloride insulated steel wire armoured and polyvinyl

chloride sheathed.

d. XLPE/PVC Cross linked polyethylene insulated and polyvinyl chloride

sheathed.

Page 50 of 170

Page 51: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PVC, PVC/PVC, PVC/SWA/PVC CABLES

PVC, PVC/PVC, PVC/SWA/PVC Cables shall be of 600/1000 volts grade with high

conductivity stranded copper conductors of sizes as shown in the drawings.

The cables shall be manufactured to B.S. 6004 or B.S. 6376 As appropriate.

Insulation colours can be in accordance with current editions of British IEE wiring

regulations.

XLPE/PVC CABLES

Cross linked polyethylene insulated cables shall be of 600/1000 volts grade

comprising high conductivity stranded copper conductors manufactured to B.S. 5467

and finished with an extruded black PVC over sheath.

4.5 Underground Cable Installation

Underground cables shall be laid in trenches or pulled into cable ducts where indicated in

the drawings. Full safety precautions shall be taken to prevent damage to the cable during

the installation.

All trenches shall be excavated to provide a minimum cover of 750mm in open ground and

under pavement and 1000mm under all roadways. Details of the trench construction shall

be as specified in other clauses of this specification.

Where cable passes through a roadway, pavement or enters a building, it shall be threaded

through steel or PVC pipes of minimum 100mm dia. Pipes under roadways shall be

protected with 100mm thick concrete on both sides and top.

All pipes shall be properly sealed to prevent ingress of water. The cable trench shall have

water drain outlets to prevent collecting water inside the trench.

For work where it is involved in digging or interference with existing roads, car parks,

pavements and other services such as gas, water etc., prior approval shall be first obtained

from relevant authorities before carrying out such work.

Cables shall normally go under all obstructions such as mains, sewers, drains conduits and

the like.

The removal, alteration or diversion of mains, sewers, drains, conduits and the like, shall

normally be avoided.

Page 51 of 170

Page 52: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The contractor shall excavate trial holes as and when required by the Engineer/Consultant

in order to determine the location of existing cables or other utility services and mains.

The contractor is advised to familiarize himself as to the nature of the surfacing materials of

both paved and unpaved surfaces roadways etc., and shall satisfy himself before submitting

his tender as to he nature of the subsoil and in general shall obtain all necessary

information as to the risks contingencies and other circumstances which may influence or

affect his tender price as no claim for additional cost will be allowed.

4.6 Termination

The contractor is to be wholly responsible for the sealing and termination of all cables

erected under this contract.

The contractor shall terminate all cable ends and shall make final connection to all sub

switchboards.

The specified sub main cable cross-sections may have been oversized to minimize voltage

drop over long runs. Where these cables are too large for termination within the distribution

board terminal blocks, isolating switches, etc., suitable reducing terminating tags or lugs

shall be used.

Cable sealing and termination is to be in accordance with the best current practice and of

first class workmanship. Where cable sheaths are used, as earth continuity conductor

glands are to have the necessary contact surfaces or straps to provide a low resistance

path under fault conditions.

Compression type glands shall be used for the termination of underground cables. The

design of compression glands to be such that the cable is not twisted when the gland is

tightened.

Appropriate bending radius depending on the cross sectional area of the cable shall be

provided so that the cable insulation is not subjected to stress or damages due to bending

of the cable.

4.7 Straight Joints

Straight joints in any of the cables installed under this contract will only be permitted in very

exceptional circumstances and only with the Engineer’s/Consultant’s approval in writing.

Page 52 of 170

Page 53: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The cost of such straight joints, if permitted by the Engineer/Consultant shall be born by the

contractor.

All joints, which are buried in the ground, shall be compound filled. The design of the box

and the composition shall provide an effective seal to prevent moisture-gaining access to

the conductor ferrules and Armour clamps.

A suitable contract joint marker to the Engineer’s/Consultant’s approval shall be placed

above each under ground cable joint to mark its position. The depth of burial of the cable

joint shall be indicated on the joint marker.

4.8 Excavation of trenches, backfilling and reinstatement

Excavation of trenches where required, shall include all timbering, pumping and baling

required and the provision of all necessary labour, plant, tools, additional soil, fuel and

motive power for such purposes and the cost of this service and of the supply of the

expendable materials shall be included in the contract price.

The contractor shall include for all materials and labour to reinstate the ground to the same

condition as existed prior to excavation.

All trenches shall be of sufficient width to enable the following minimum spacing between

cables to be maintained.

Between HVC and LV cables: 300 mm

Between LV cables: 75 mm

Between LV and ELV cables: 300 mm

Before the cables are laid, the bottom of the trench shall be lined with sifted soil, which is to

be punched down to a thickness of 50mm to form a bed. After the cables are laid, the first

75mm depth of cover back fill shall consist of sifted soil over which shall be placed

protective cable slabs of an approved design.

After all cables and protective cable slabs have been laid, the trenches shall be backfilled in

150mm layers, each layer being well rammed and consolidated.

The surfaces of the re-filled trenches shall be temporarily reinstated and maintained in a

thoroughly safe condition until complete consolidation of the soil is achieved.

Page 53 of 170

Page 54: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The contractor shall supply backfill material necessary for the replacement of unsuitable

excavation material together with the backfilling reinstatement and removal of surplus

material, which shall be included in the contract price.

4.9 Cable Slabs

Protective cable slabs shall be of reinforced concrete and unless otherwise approved, shall

be 750mm long, 230mm wide and 50mm thick. Samples of the cable slab shall be

submitted to the engineer or the engineer for approval before production and installation.

The supply and laying of cable protective slabs shall be included in the rate for cable laying.

4.10 Cable Ladders

Cable ladders shall be of the sizes shown on the drawing. All ladder systems shall be built

up from components from a matching range of straights, bends, tees, reducers, supports

etc.,

The ladder system shall be capable of supporting a load of 75-kg/linear meter over a span

of 6.1 meter with a vertical deflection (sag) of less than 50 mm at mid span.

The ladder system shall be of an approved proprietary manufacture of welded or site

fabricated construction using either aluminium or steel components or both. All steel

components shall be hot dip galvanized. Electro galvanizing will not be accepted.

Unless shown otherwise on the drawings, ladder runs shall be parallel to walls, ceilings

floors, etc., Supports shall be installed at center-line distances not greater than that shown

on the drawings or, where not directed at distances not greater than those recommended

by the manufacturer for the loading concerned.

The Contractor shall co-operate with other trades so as to ensure that the completed ladder

installation does not interfere with other services in the same area.

4.11 Cable Tray

Cable trays shall be of sizes shown on the drawings. All tray systems shall he built up from

a matching range of straights, bends, reducers, tees, supports etc., They shall be of an

approved proprietary manufacture fabricated from minimum 1.2 mm mild steel perforated to

between 25% and 50% of the total area. After fabrication the trays shall be hot dip

galvanized.

Page 54 of 170

Page 55: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Trays shall have upturned edges and be of a width as indicated in the drawing, suitable for

the number of cable to be supported and shall be supplied with purpose-made galvanized

steel bracket suitable for mounting from the building stricture.

Support brackets for cable trays shall be fabricated and finished as for the tray and

provided at intervals not exceeding 1200 mm with 2 bolts to each bracket. Bracket shall he

fixed with not lees than 2 bolts to the wall/slab or other available and approved supports.

Cable shall be supported by a cable tray inside the cable trench. The contractor shall

submit the detailed drawing of the cable trays for the approval of the Engineer/Consultant

4.12 Test During Laying

Where required by this specification and as required from time to time by the engineer, the

contractor shall subject completed portions of the cable installation to voltage tests to prove

the soundness of the conductor insulation and the soundness of the protective sheathing.

4.13 Cable Record Drawings

Cable record drawings of “As Installed” drawings showing the exact route of cables and

positions of all joints etc. shall be submitted for the Engineer’s/Consultant’s review.

Page 55 of 170

Page 56: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

5.0 Conduit Installation

5.1 Scope of Work

All the non-armoured cables and cable bunches shall be installed in GI conduits. Contractor

shall submit the drawings of the conduits where it unavoidable to break the structure to

place the conduits. The conduit runs shall be installed in the way that minimum damage

and necessity of re plastering etc. is applicable.

Conduit installation specified in this section shall apply to all sections of these

specifications.

5.2 Applicable Publications

Refer Section: General Requirements

5.3 Applicable Standards

BS 6053: 1991 Specification for outside diameter of conduits for electrical installations

and threads for conduits and fittings

BS 6099: Conduits for electrical installations

5.4 General

All conduits, fittings and accessories shall be galvanized iron and shall comply with British

standards. Conduits shall be surface in walls, columns and roof unless otherwise shown or

called for in this specification and drawings.

5.5 Installation

All concealed conduits shall be arranged with an adequate number of boxes accessible for

the life of the installation so as to allow easy draw in or draw out of any cables at any time.

Conduits size shall not in any circumstances be less than 20mm dia and cables drawn in

shall not be greater than appropriate number permitted in IEE wiring regulation 18th edition.

Cables for low voltage circuits shall not be drawn into the same conduit for extra low

voltage systems. A number of final sub circuits may be grouped together in large conduits

provided that all sub circuits in one conduit are of the same phase. In the case of three

phase circuits all 3 phases and neutral of any circuit should be drawn into the same conduit.

Wiring lighting shall be run exclusively in separate conduits.

Page 56 of 170

Page 57: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Where a large group of cables run, those may be put in a metal conduit trunking, in which a

false ceiling or a false wall covering shall be used to cover such trunking or surface

conduits.

Where condensation is likely to occur in surface conduits they shall be laid with falls so as

to drain off condensed moisture without entry into termination.

Immediately on completion of installation of conduits during building construction, all

exposed conduits and boxes shall be plugged effectively against the ingress of water and

dirt particularly where concrete will be poured.

Such seals shall be maintained in good order for such time as is necessary to complete

wiring and connection of fittings and switches.

On completion of erection, the Engineer/Consultant will inspect the conduits before any wire

is drawn in. All conduits shall be swabbed out and free from moisture to the

Engineer’s/Consultant’s satisfaction, before wiring is commenced.

5.6 Conduit Fittings

At every lighting outlet points the conduit shall terminate into a GI junction box either one

way or multiway as required. These boxes shall be suitable for surface mounting. At every

switch position, conduits shall terminate in a 86mm x 86mm or 186mm x 148mm injection

moulded GI box. At every socket outlet conduits shall terminate similar to switch position

shall be attached to the boxes using the clip-in adaptors and suitably glued.

Conduits shall be installed with junction boxes, end boxes, draw wires etc., such that the

cables can be drawn in after the installation has been completed without damage to cables

and their installation.

Page 57 of 170

Page 58: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

6.0 General Lightning and Power Installation

6.1 Scope of Work

Scope covers the Supply, install, wire and commission of all light fittings, wall switches,

socket outlets and isolators as per the BOQ. The locations of each point are given in the

drawing. However exact locations shall be verified from the Engineer.

General lightning and power installation specified in this section shall apply to all sections of

these specifications.

6.2 Applicable Publications

Refer to section: General Requirements

6.3 Applicable Standards

Each light fitting for interior use shall be design, manufacture and tested in accordance with

the appropriate section of BS 4533:102.1/EN 605982.1 and together with all components

shall be suitable for service and operation in the local climatic conditions. Louvers shall

comply with CIBSE LG3 VDT recommendations. The luminaries shall be class 1 electrical.

All lighting fittings shall be earthed.

6.4 General

The contractor shall supply, install, wire and connect all lighting fittings as shown on the

drawings. The exact location of all lighting fittings must be checked on the architectural

detailed drawings before installation is commenced. The contractor will be expected to

examine the architectural floor plans and ceiling details in order to fully familiarize with the

type of ceilings and surfaces into and upon which lighting fittings are to be installed.

The contractor shall supply all fixing, brackets angles etc., necessary to fix the lighting

fittings in the locations shown.

The numbers of lighting fittings for the different areas of the building have been calculated

using the photometric data equivalent to Phillips, Thorn, Thorlux or Fitzgerald Lighting

Fittings and GE, Osram and Phillips lamps. If the contractor is offering fitting/lamps different

to the above, he shall provide the calculations to prove the required numbers of lighting

fitting using the photometric data of the lamp offered to the satisfaction of the

Engineer/Consultant.

Page 58 of 170

Page 59: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Care must be taken to ensure that other services such as air conditioning, water piping etc.,

are properly coordinated and the contractor will be required to maintain close liaison with

other contractors in this respect.

6.5 Lighting Fittings

6.5.1 General

The types of lighting fittings to be provided are shown on the drawings and described in the

accompanied schedule of lighting fittings.

All lighting fittings shall be supply complete with lamp and control gears. Luminous efficacy

of lamps shall be greater than 100 lm/W, power factor of lamps shall be 0.9 and colour

rendering index (CRI) shall be greater than 80.

At every lighting fitting, an approved type-earthing terminal shall be provided for connection

to the earth continuity conductor of the final sub-circuit.

Plastic diffusers where used, shall be of non-deteriorating and ultra-violet stabilized material

and shall not change in shape with time or due to handling. Plastic diffusers shall be

washed with a detergent solution and drip-dried immediately prior to installation to restrict

electrostatic dust adhesion.

Fittings and accessories for external use shall be of weatherproof construction specially

treated for corrosion for use in salt laden atmosphere. Totally enclosed fittings shall have

sealing gaskets and shall be insect-proof.

Cables within the lighting fittings shall be neatly bundled by nylon self-locking cable ties.

Wiring shall be properly routed and secured away from heat-generating accessories

like control gear etc.

Each light fitting for interior use shall be design, manufacture and tested in accordance with

the appropriate section of BS 4533:102.1/EN 605982.1 and together with all components

shall be suitable for service and operation in the local climatic conditions. It is the

Contractor’s responsibility to get the approval from the Engineer/Consultant for all light

fittings before the installation.

Luminous efficacy of lamps should be more than 100 lm/W.

Page 59 of 170

Page 60: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

6.6 Lamp Holders

All lamp holders shall be brass or an approved thermosetting plastic with brass insert.

6.7 Lighting Switches

Sub-circuit switches unless otherwise shown on the drawings shall be single pole, quick

make and slow-break silent switch action type with solid silver alloy contacts the totally

enclosed switch action for flush wall mounting.

They should be housed in injection moulded metal clad boxes completed with conduit

knockouts and made up into single or multi-gang units.

Switches associated with essential supply shall be provided with red toggles.

Switches shall conform to BS 3676 and shall be rated 10 Amps or 15 Amps as determined

as circuit lode suitable for use in A.C. inductive circuits or fluorescent lamp circuits.

Single pole switches shall be connected to break the phase wire of the supply. The neutral

wire shall not be routed through switch boxes.

For group switching, switches of appropriate loading shall be used. In case if the switch

body is metallic, an earthing shall be continued at every switch point. This is not necessary

if insulation of switch body is ensured according to the class-2 insulation.

6.8 Switch Socket Outlets

Switch socket outlets shall be to B.S. 1363 single pole – 13 Amp 3 rectangular pin, switch

shuttered outlets, one or two gang for indoor service except as otherwise shown on the

drawings and either surface or flush mounting according to location.

15 Amp socket outlets shall be 3 pin round type to B.S. 546 shuttered of a finished similar

to 13 Amp. Switch socket outlets and mounted in surface metal clad boxes.

Switch socket outlets for indoor use shall be housed in suitable injection moulded metal

clad boxes to B.S. 4662 with conduit knockouts.

6.9 Standard Heights of Electrical Wiring Accessories

Heights measured from finished floor level.

260mm -Socket outlet, telephone socket outlets at general areas.

Page 60 of 170

Page 61: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

1370mm -Socket outlets, cooker control unit at pantry and kitchen.

1500mm -Switches, dimmer switches, fan regulators and general areas.

1700mm -Main switches, earth leakage circuit breakers.

2000mm -MCB Distribution boards

2250mm -Wall brackets, lamp fittings, fuse distribution board geyser outlets, and power

outlets.

2400mm -Pendant lamp fittings

Note: -

The above heights shall be varied according to the interior design, and installation heights

shall be adjusted accordingly to the Engineer’s/Consultant’s approval.

Page 61 of 170

Page 62: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

7.0 Earthing System

7.1 Scope of Work

Earthing systems, testing L.V. equipment specified in this section shall apply to all sections

of these specifications.

7.2 Applicable Publications

Refer to Section: General Requirements

7.3 General

Earthing system and lighting protection for each building shall include ground rods, cable-

accessories, devices and other items necessary for the complete and satisfactory

installation and operation of all equipment.

7.4 Earthing System

a. Equipment Earthing

All exposed metalwork of all electrically operated equipment, metal cable trays and other

exposed (un-insulated) metal work of all electrical services shall be earthed by cables and

conductors of adequate sizes as given in the regulations. All cables above 6mm2 in size

shall be connected by nuts and bolts as relevant with pressure cable connections of

appropriate size.

b. Conductors

All earthing and earth continuity conductors shall be installed in strict conformity with the

I.E.E. regulations and British standard codes of practice.

Cables and conductors shall be sized in accordance with BS table D2M, with the exception

that the smallest size of conductor is 2.5mm2.

This cable or conductor shall be identified by green/yellow insulation. All earthing bars shall

be identified by green/yellow colour codes.

Earth conductors shall be provided for the following equipment.

Page 62 of 170

Page 63: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

c. Socket Outlets

From each socket outlet-earthing terminal a wire shall be provided. The wire shall be

connected to the earthing terminal in the outlet box, or junction box.

d. Switches

From each switch earthing terminal a wire shall be provided. The wire shall be connected to

the earthing terminal in the outlet box, or junction box.

e. Luminaries

From each luminaire (lighting fixture) earthing terminal wire shall be provided. The wire

shall be connected to the earthing terminal in the outlet box.

f. Distribution Boards

From the earthing bar in the distribution boards earthing wires shall be provided to the

equipment as cable trays, outlet boxes etc., as specified.

7.5 Distribution System

Provide separate green-yellow insulated equipment earthing for each single or three-phase

circuit. The required earthing conductor shall be installed in the common conduit or cable

with the related phase and/or neutral conductors. Single-phase sub circuits required for 230

volts lighting, socket outlets and motors shall consist of phase, neutral and earth

conductors.

7.6 Panel Boards

In addition to the active circuits, provide pressure connectors for all three-phase spare

circuits.

7.7 Earth Electrodes

Earth electrodes shall be of earth pipe, earth rod connected to the ground grid of buried

conductors to the area covering not less than 1m2 at the building close to the sub-stations.

The incoming cable from the main distribution board shall be connected to the earth

electrode. The earth electrode and the conductors shall be sized to the full short circuit

current value of the sub-station or incoming supply cables as relevant. The grounding grid

shall be of soft annealed high conductivity copper strip of area not less than 100sq.mm and

Page 63 of 170

Page 64: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

will be installed at a depth of 2m or more in the ground. The distance between copper strips

shall not less than 100mm. The earth electrode resistance shall be less than 5 ohms tested

on a dry day.

7.8 Conductors

All cables and conductors shall be of copper. Joints in copper tape shall be braced. No

joints are allowed in sub-circuit cables.

7.9 Residual Current Protection

Socket outlets shall have earth leakage protection provided with residual current circuit

breakers (RCCB) 30 mA sensitivity of the current operated type. The breakers shall be

suitable for operation on a 400/230V level at a frequency of 50Hz.

7.10 Earth Loop Impedance and Earth Resistance Tests

The entire installation shall be tested for Ohmic resistance as given in regulation E.3 and

Appendix 6 of the IEE regulations. The installation shall be tested to the requirements of

regulation E.4 of the regulations. The test results shall be submitted to the

Engineer/Consultant for approval. The engineer or his representative shall be present at the

testing.

7.11 Earthing L.V. Equipment

All equipment shall be earthed by connection (via green/yellow covered earth wire) to a

common LV inter connected earthing terminal in the Power Room in accordance with the

following: -

The earth resistance of the complete earthing system including all connections between

equipment and earth shall not exceed 5 ohm.All parts of the earthing system, which may

carry low voltage currents shall be so designed and constructed that damage does not

result from the passage of such currents.

The minimum size of the LV earthing conductor shall be as follows: -

In circuits with live conductors not larger than 16mm2 the minimum size of the earthing

conductor shall be not smaller than the live conductor.

In circuits with live conductors exceeding 16mm2 and less than 35mm2, the minimum size

of the earth conductor shall be not smaller than 16mm2.

Page 64 of 170

Page 65: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

In circuits with live conductor-exceeding 35mm2 and above, the minimum size of the earth

conductor shall be not smaller than half the size of the live conductor.

All earth conductors shall be covered by a green/yellow PVC sheath. Green-Yellow shall

not be used for any active, neutral, switch or control wiring and shall be used solely for

earth connection.

Page 65 of 170

Page 66: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR METAL WORK

1.0 General

Aluminum glazed units shall be supplied with all hardware furniture and fittings.

The Contractor shall submit to the Engineer the shop drawings and technical data and other

relevant information for approval of the Engineer.

The Contractor shall include in his rates the cost of tests generally required for ascertaining

the suitability of aluminum extrusions, anodizing, strength of joints, gaskets and weather

stripping, strength of joints and air and water infiltration.

2.0 Materials

All sections shall be extruded from AA 6063 aluminium alloy and sections shall be designed

to give rebated internal and external faces.

Aluminium sections for mullions, frames, transoms, heads and the sills and the other

members should strictly comply with the requirements laid down in the following British

Standard.

B.S. 1161: 1977 (1991) – Specification for aluminium alloy sections for structural purposes.

B.S. 1470: (1987) – Wrought aluminium and aluminium alloys plate, sheet and strip.

B.S. 1474: (1987) – Wrought aluminium and aluminium alloys for general engineering

purpose and external architectural application bars, extruded

down tubes and sections.

3.0 Powder Coating

Powder coating shall conform to BS 6496: 1984 (1991). The powder coating shall be of

thickness 60-80 microns and of approved colour. The Contractor shall submit a ten (10) year

guarantee for the powder coated finish. The Contractor shall allow for cost of required tests

for checking the coating as directed.

4.0 Wind Loading

The fabricated aluminium doors and windows shall be capable of withstanding a wind

pressure load not less than 1500 Pascals (75 M.P.H.)

5.0 Weather Stripping

The weather stripping shall be vinyl or other plastic materials which are dimensionally stable

and are resistant to ultra violet rays, water absorption and are suitable to be used in marine

atmosphere.

Page 66 of 170

Page 67: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

6.0 Screws Nuts etc.

All screws, nuts, washers, bolts, rivets and other fastening devices should be of stainless

steel. Aluminium alloy fasteners may be used in lieu of stainless steel fasteners with the

written approval of the Engineer.

7.0 Ironmongery

Ironmongery used shall satisfactorily perform the function for which it is intended. They shall

be of aluminium die cast alloy, stainless steel or other non-corrosive materials compatible

with aluminium. The Engineer shall duly approve all items of ironmongery before fixing in

position.

8.0 Glass

Glass shall be 5mm/6mm thick clear glass suitable for single glazing and having a thickness

(minimum 5mm) as specified. Glass shall conform to the relevant British Standard including

following:

B.S. 952 Part 1: 1995 – The classification of glass for glazing and terminology for work and

B.S. 952 Part 2 of 1980.

9.0 Assembly

The design of windows should permit free movement of air from exterior environment to the

immediate spaces between the window frame and ventilator to achieve pressure

equalization. The windows should have snap on reusable extruded aluminium glazing beads

and easily removable bottom rails.

The glazing beads should not extend underneath the glass. The design of windows should

permit re-glazing without disassembly of all ventilator extrusions form the frame.

All openable window sash corners should be mitered angle reinforced or mechanically

staked and Epoxy painted. If frames with incompatible extrusions are used, then these

extrusions should be mortised and tenoned. A permanent watertight joint should be made to

the junctions of the side frame members with all horizontal members. Window panels must

be provided with minimum three weep holes, one at the center and one each between the

jamb and the setting block. Fixing of aluminium units to concrete shall be done with high

quality Rawl Plugs with stainless steel sections and other approved fixing devices. Where

friction stays are used the shop drawings shall clearly indicate the size of such stays. The

joint between window frames, external door frames and concrete or masonry work shall be

adequately caulked with a suitable caulking compound. Polysulphide or Silicon sealant may

be used for this purpose. The Contractor shall furnish all literature and instructions published

by the manufacturer of the sealant along with the Tender. Only caulking compound approved

by the Engineer in writing shall be used.

Page 67 of 170

Page 68: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

10.0 Air and Water Infiltration

The Contractor shall submit test certificates from the manufacturer of aluminium extrusions

guaranteeing that the products comply with standards applicable to the country of origin of

these materials.

Fabrication and installation of aluminium units shall be thoroughly watertight.

The degree of resistance to air leakage shall be Grade A (superior resistance)

recommended for air-conditioned buildings.

11.0 Quality

The items to be supplied and installed completed as required for a workmanlike job and

inclusive of all bolts, nuts, anchors, nails, screws, inserts, hooks, etc.

If the Contractor intends to use sections which deviate from those shown on the

drawings, the Contractor shall prove that the calculated strengths (I and W) at least

match those of the given sections.

All steel items to be straight and smooth. All sharp edges to be removed from parts

which remain visible.

All welds to be straight, smooth and smoothly ground. Site welding to be kept to an

absolute minimum; shop welding and bolted fixings on site being the preferred method of

working. Welding as specified in Chapter 5.

Hot-dip galvanized parts to be re-straightened.

12.0 Shop Drawings

The Contractor has to prepare shop drawings for all steel and non-ferrous metal items

mentioned in this specification.

All such shop drawings shall be approved in writing by the Engineer before the work is

put in hand.

Every drawing shall show the number and sizes of all rivets and bolts, complete

details of welds, type of electrodes, welding procedure including where the welds are to

be made, and any other relevant information.

13.0 Calculations

The Contractor is required to submit to the Engineer in adequate time for checking,

calculations of all steelwork mentioned in this Chapter including all fixings, of all large

metal assemblies including large doors and gates; external windows and internal

partitioning.

The Contractor shall be responsible for supplying and fixing such metal work according

to his calculations, and shall remain responsible for the strength and stability of such

steel work and metal assemblies, notwithstanding the presence on Tender Drawings or

Page 68 of 170

Page 69: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

in these specifications of sections, or dimensions which his calculations may prove to be

inadequate for their purposes.

14.0 Commissioning

The Contractor shall commission the doors upon completion of installation and hand all

keys, manuals, etc. to the Employer.

The Employer reserves the right to refuse to make final payment or to take over the

installation should any part of it fail in test or not meet with their Engineer’s approval.

15.0 Stove Enameled Aluminium, Extruded Sections

15.1 General

The choice of both the alloy for aluminium elements and the enameling process itself

shall be extremely carefully made.

The following is therefore a basic minimum specification for the materials and fabrication,

which the Contractor may adapt to suit the prevailing conditions, his own fabrication

process or his experience, but always to the approval of the Engineer and of a proven

equal or higher standard than the basic specification given below.

15.2 Preparation

Preparation of extruded sections and footplates shall comprise: after suspending and

earthing, etching or pickling, rinsing, activating and again rinsing, the sections shall be

provided with a conversion-layer of chromate-fluoride containing hexavalent (yellow)

chromium; after chromating the sections shall be rinsed, sprayed, rinsed with hot

desalinated water, sprayed again with entirely desalinated water and air dried at 80 to

120 degrees C.

The conversion layer shall be even in colour and not come off on a cloth when rubbed.

After preparation the sections shall be protected from any contamination; it is preferred

that the enameling be applied after drying on the same day.

The preparation shall be in accordance with what is specified in DIN 50939, or BS

6496:1984, which shall also apply to coatings and stoving.

16.0 Metal Doors and Windows.

16.1 Scope of Work

16.1.1 Aluminium

The Contractor shall include in his Bidder the supply and installation of the following

items, all of which must be obtained from an approved manufacturer:

All powder coated external and internal aluminium windows, window frames, doors, door

frames and all fixed internal partitions, complete with sub-frames where so detailed.

Page 69 of 170

Page 70: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

All powder coated aluminium infill panels, corrugated panels and composite panels

required for the above, generally as shown on the drawings.

All glazing for all aluminium powder coated doors and windows to be 5 mm thick clear or

tinted glass including all fixing strips, glazing beads, weather stripping, etc. required to

properly and securely fix the glazing.

All fixings, fixing lugs, extension pieces, etc. required to assemble and fix the frames and

sub-frames.

All waterproof sealing, caulking, backing strips, neoprene gaskets, mastic pointing and

the like all specially prepared or selected for use with aluminium in tropical conditions.

All ironmongery, furniture and fittings for windows, doors and frames.

All incidental windows, panels and hatches, etc.

16.2 Execution of the Works

16.2.1 General

The works shall be executed in a first class workmanlike manner including all work and

materials in accordance with this specification and schedules, the drawings referred to

therein and the Shop Drawings, to be prepared by or on behalf of the Contractor and

approved by the Engineer.

In all cases where a component or part of the installation is referred to in the singular, it

is intended that such reference shall apply to as many such items as are required to

complete the whole installation.

16.2.2 Responsibility of the Contractor

The Drawings, showing aluminium windows and details, have been prepared on the

basis of a type of section from a particular manufacturer and have not been calculated

for their respective strengths; details serve only to show requirements as to dimensioning

water and weatherproofing, etc. It is therefore the responsibility of the Contractor:

To calculate and provide on the basis of approved calculations, sections and glazing of

materials, strengths and thicknesses suitable and adequate for their purposes and

locations in the building;

To check joints and clearances available and, if necessary, to provide extra expansion

joints in composite windows. Details and, consequently, interim dimensions of doors and

windows may therefore be subject to change, all such changes in co-ordination with and

to the approval of the Engineer.

16.2.3 Installation

The Contractor shall be responsible for setting all units straight, plumb and level, and for

their satisfactory operation after fixing is complete.

The Contractor shall ensure that he has sufficient support on site from the manufacturer

and/or supplier to guarantee a first class installation procedure and flawless operation of

the units installed.

Page 70 of 170

Page 71: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

All units shall be fixed into prepared openings. Frames shall not be forced into openings

which are out of square or too small. The openings must show at least 2.5 mm tolerance

all round. The frames shall be secured at head, jambs and sill; care should be taken to

ensure that the frames are not distorted when screwing up lugs or fixing screws, etc.

All external doors, door frames, windows and window frames when installed, shall be

completely watertight.

All opening lights, pivoted or sliding, and all doors shall open as indicated on drawings

and schedules.

All window and door units shall be protected from damage by being wrapped in plastic

film or by other approved means until shortly before handing over of the building.

All glass shall be 5 mm thick clear glass or tinted glass.

All glass shall be sized, cut, finished and fixed in accordance with specifications and

requirements of the manufacturer.

The systems offered should be suited for commercial building and of international repute

such as R C system of Belgium or equivalent and certified by independent professional

bodies to conform to the following tests and Standards.

BS 5368:Part 1 Air Permeability

BS 5368:Part 2 Water tightened under static pressure

BS 5368:Part 3 Wind resistance

The aluminium system should also meet the following criteria:

Air Permeability Test (A3) above 600 p.a

Water Tightness Test (E4) above 500 p.a

Wind resistance (V2) above 100 kg/m2 static wind load and 200 kg/m2 security load.

16.2.4 Warranty

All aluminium doors, windows, frames, hatches, grilles, gates, etc. and all associated

fittings thereof shall be erected by experienced specialized personnel in accordance with

the directions of the manufacturer of these items.

Notwithstanding maintenance requirements of the works, the Contractor shall warrant

the Employer, with the assurance of a reputable local insurance company that all items

specified in 6.2.4.1 above shall perform satisfactorily as intended under the contract, in

respect of workmanship, materials, installation, operation and all other aspects for a

period of five years calculated from the date on the certificate of completion.

The form of guarantee offered shall be submitted for the Engineer’s approval prior to

commencement of such works. This guarantee shall in no way indemnify the Contractor

against improper workmanship or performance of the installed items.

16.3 Drawings Required

16.3.1 At Bidding Stage

The Contractor shall furnish with his Bid the principal details of extrusions and sections to be

used for the preparation of the various items; the materials to be used for waterproofing;

drawings or illustrations of locks, handles, hinges, bolts and such items necessary for the

proper functioning of movable parts.

Page 71 of 170

Page 72: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

16.3.2 After Commencement of the Works

Fully detailed Shop Drawings must be submitted as soon as possible after the

commencement of the Works, showing complete scale elevations and full size details of

all doors, windows, etc. required; the relations of all the sections to the exterior and

interior work, the points to which all dimensions are taken and the locations of all

ventilators and opening lights.

The type and positioning of all fixing devices shall be shown, the work to be done by

other trades shall be indicated, and the size, type and thickness of glass and all infill

panels, doors, hatches, etc. shall be shown.

Shop Drawings must be approved by the Engineer before any of the required units are

manufactured or assembled; in programming the Works, the Contractor shall allow

adequate time for the Engineer to inspect and approve these drawings.

16.4 General Specification: Aluminium

16.4.1 General

The choice of both the alloys for aluminium elements and the powder coating and other

processes shall be extremely carefully made.

However, the powder coating of extrusions as well as of panels and sheets will not

permit too much difference in the alloys used in order to avoid unacceptable colour

differences between the individual elements.

The following is therefore a basic minimum specification for materials and fabrication,

which the Contractor may adapt to suit the prevailing conditions, his own fabrication

process or his experience, but always to the approval of the Engineer and of a proven

equal or higher standard than the basic specification given below.

16.4.2 Alloys

All extrusions shall be of A1MgSi, designation 6060, or 6063, temper T5, heat treatable,

and shall be in accordance with BS 1474:1987.

Panels, if not extruded, and sheets, plate and strip shall conform to BS 1470:1987, shall

be of A1MgSi designation 5005, 5050 or 3003; temper and condition to suit conditions of

environment and use.

The average roughness of the surface shall not exceed Ra = 5 microns. The radius of

corners shall be 1.5 mm minimum.

16.4.3 Conditions

The Contractor shall determine the desired mechanical properties to be obtained by

annealing, solution treatment and precipitation treatment, with the manufacturer and in

concert with Engineer. Such properties shall be determined to suit the purposes for which

extrusions, panels or sheets are to be applied in this building, but always within the

requirements of BS 1474, tables 1 and 2 and BS 1470.

Page 72 of 170

Page 73: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

16.4.4 Testing

The testing of alloy strength and sealing as set out in BS 5411 and BS 6161, shall be carried

out per group of elements, i.e. Window frames (2 series of tests), panels (1 set of tests) sun

breakers (1 set of tests), the cost of which shall be borne by the Contractor. Testing shall be

carried out on randomly chosen elements by an approved independent laboratory, and

certificates are to be submitted to the Engineer, who reserves the right to reject any or all of

the groups of elements, not in accordance with the requirements set out.

16.4.5 Strength, Construction and Assembly

Design for wind load shall be according to the British Standard Code of Practice 3 (BS

CP 3) Chapter V Part 2 of 1972, using a basic wind speed of 38 meters per second.

The Contractor shall be responsible for and shall ensure that:

The extrusions, panels and sheets, forming the elements required, including glazing in

the case of windows/doors, are adequate in individual and overall strength for their

particular purposes and locations in the building. See also para 5.1.3;

Where necessary, extrusions shall be reinforced by means of inserted mild steel or

secondary aluminium plates, tubes, sections, and back plates, for locks, furniture or

fixing positions and the like; or other mild steel columns, etc. as may be necessary to

ensure the stability of the complete assembly;

Joints, edges and specifically corners of extrusions, panels or sheets are carried out in a

satisfactory and workmanlike manner, with regard to strength, expansion/contraction,

water/dust-proof, preservation, as well as appearance.

16.4.6 Doors and Windows

Outer frame shall be not less than 50 mm depth and face width. Members shall be mitre cut

to 45 and joining shall be by means of extruded aluminium corner cleats mechanically

crimped to system supplier specification. Mullions and transom is to be 70 mm minimum

face width mitre square cut ends and firmly fixed to the outer frame with brackets and

stainless steel screws having provision for lateral adjustments.

Joints shall be applied with small gap sealant before assembling to ensure proper seal

against water entry.

Glazing bead either square or sloped type is to be fitted from the inside of the building for

maximum security. Difference of plane of outer frame surface to glazed surface shall be

designed for the prevention of dust and water collection and should not in any case exceed

10 mm.

Door outer frame should have nominal depth not less than 50 mm and face width of 70mm.

Door sash stile, top and bottom members should be of face width 90 mm minimum waist rail

face width shall be equal or more than the stile width. Exterior door units must be provided

with an extruded sill/threshold and so designed for proper drainage.

Page 73 of 170

Page 74: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Weep holes not visible to the outside must be provided for proper drainage. Use of rivets is

totally not accepted and fixing of the frame to the structure should be according to accepted

norms laid down by the system supplier. (All pivoted double swing doors unless otherwise

stated shall be fitted with overhead concealed hydraulic automatic door closures with hold

and open option).

16.4.7 Hardware

Casement windows shall be hung with concealed stainless steel first on stays “tilt and turn”

assembly units should be of reputed make.

Door hinges shall have the facility to adjust door height over a period of time and should

have the added facility to fine adjust the plane of pivot thus making certain that hinges on the

same vertical line will pivot along the plumb line of action.

16.5 Aluminium External Doors, Windows and Frames

16.5.1 Appearance and Detailing

The details of aluminium windows on the Tender drawings show certain types of sections,

which have not been calculated for strength, together with the relevant vertical and

horizontal connections to builders work. The Contractor may submit alternative sections

which he proposes to use with his Tender, for approval by the Engineer, although a box-

section is preferred and the width of 50 mm for external window frames should be adhered

to.

16.5.2 Special requirements and applications: Windows and Frames

The air-infiltration factor of sliding windows in the elevations, as outlined by the ASHRAE

Standards shall be 0.16 or less; performance of windows shall otherwise be in

accordance with BS 4873:1986.

Transoms and mullions, complete with all necessary coupling screws and nuts, etc. shall

be supplied as shown on the drawings, and shall be bedded in mastic on assembly in the

factory or at the site so as to fill completely all interstices between components.

16.5.3 Aluminium Doors and Door Frames

To be formed from extruded aluminium sections of alloy specified in 6.4.2.

To be powder coated to a thickness of 60- 80 microns with approved colour by the

Engineer.

With glazing as shown on Drawings.

To be complete with all hinges, locks, doorstops and other ironmongery and furniture as

shown on drawings, described in door schedules or as the function requires.

External doors to be fully draught proof all round by means of rubber or neoprene strips

contained in a suitable housing or frame detail, and to be complete with a waterproof

threshold detail.

Page 74 of 170

Page 75: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

16.5.4 Aluminium Fittings

These shall be powder coated to a thickness of not less than 60-80 microns. The surface

shall be prepared to a satin finish, polish finish or bright finish as required.

Grades of powder coating shall conform to BS 6496 of 1997 and BS 6496 of 1984 .

16.5.5 Door Closers

Pneumatic door closer (exposed type) shall be made of aluminium alloy. These shall be

powder coated as per BS 6496 of 1997 and BS 6496 of 1984.

16.5.6 Lock Types

6.5.2.1 Type A – For all high security areas

Roller Bolt Mortice Lock with 3 multi-point. This should include 3 locking zones and

reversible and uncopiable key system and high security durable cylinder.

6.5.2.2 Type B – For all medium security areas

Single point Mortise Lock with dead bolt. This should include, 1 locking zone, 1 dead

bolt, saw resistant dead bolt, 1 security hook and high security durable cylinder.

16.6 Glazing

16.6.1 General

Glass shall be single glazed unit. All glass panels for powder coated Aluminium doors and

windows shall not be less than 5 mm thick and shall be either clear float or body tinted, solar

control glass. See detail drawings for type of glass.

All interior glass is clear float. (Unless otherwise specified)

Page 75 of 170

Page 76: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR WOOD WORK

1.0 General

The quality and properties of building timber shall conform to SLS 263 (1974).

Sizes of joinery timber indicated in drawings shall be finished sizes and those of structural

timber are “ex”-size before planning. The allowable tolerances of Joinery and Structural

timber shall conform to Clause 4 of SLS 263 (1974).

All timber shall be kiln seasoned to a moisture content of 12% and shall be free of all

defects such as end splits, surface cracks, warping, seasoning of timber shall conform to

CS (SLS)159. Timber shall be preservative treated by application of two coats of

approved wood preservation to naturally durable timber specimen specified.

If imported timber is used, a Certificate from the exporter giving particulars of preservative

treatment, seasoning, etc. shall be furnished by the Contractor to the Engineer.

All timber surfaces in direct contact with masonry or concrete work shall be quoted with

an approved fungi resistant water-proof paint or primer.

The Contractor shall furnish samples of all types of timber used in construction and also

finished sections showing grooves, rebates, splays, etc. indicated in drawings or as

required by the Engineer.

Timber used shall be sawn square and free from sap, shakes, cracks and edges. It shall

be free from decay and insect attack.

Where a choice of more than one species is allowed only one variety shall be used for

any particular class of work.

2.0 Carpentry

The following species of timber shall be used.

2.1 Roof Timber & Timber Brackets

Balau ,Bitis or other approved.(Bitis and Balau are imported species)

3.0 Joinery

The following species of timber shall be used.

3.1 Valance Board

CCA pressure treated Kempas, BalauBitis or other approved

Unless otherwise specified in the respective Trades/Sections, the timber for all trades shall

be as specified in Wood Work section.

Page 76 of 170

Page 77: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SPECIFICATION FOR FLOOR, WALL AND CEILING FINISHES

Refer schedule of finishes for the exact location of respective floor, wall and ceiling finishes.

1.0 Plastering

Surface to receive plasterwork shall be dry brushed to remove all loose particles, dust

laitance etc., and any projecting fins on concrete surfaces shall be hacked off the maximum

finished thickness of plaster coat shall not exceed 20 mm.

Internal and external plaster work shall be 1 part cement: 1 part lime: 5 parts sand.

Plasticizers may be permitted, if the Engineer approves. Sample panels shall be prepared to

check on shrinkage cracking.

All the plastered walls finished semi rough in internal areas shall be smooth with applying of

two coats of “Skimcoat” or equivalent as per the manufactures instructions and to the

satisfaction of the Engineer.

2.0 Expanded Metal lathing, reinforcement and beading.

Where shown on drawings or required by the Engineer or dictated by good practice to avoid

cracking or spalling of external rendering or internal plaster work, expanded metal lathing,

reinforcing, corner, stop and movement beading shall be used.

Beads should be fixed with plaster daubs at 600 mm intervals. The depth of beads should

correspond with finished plaster thickness.

Metal lathing shall be fixed with 38 mm galvanized steel staples with joints lapped 40 mm

and tied with galvanized steel wire or as the situation demands and on approval.

All expanded metal lathing accessories to be of galvanized M.S. and to be to BS 1369.

3.0 Ceramic Floor Tiles / Wall Tiles

These shall be ceramic fully vitrified tiles of approved size and thickness. Tiling shall be laid

on cement sand bedding and shall conform to recommendations stipulated in British

Standard Code of Practice (BS)202 of 1972. Tiles shall be laid by experienced tilers

generally conforming to the British Ceramic Tile Council.

Total areas – fully vitrified ceramic tiles conforming to the standards stated above. The

Contractor shall furnish samples of tiles and tile accessories to the Engineer for his approval

before making firm orders.

Page 77 of 170

Page 78: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Bedding to floor tiles shall be 1:3 cement sand mortar or as specified by the manufacturer.

Grouting to tiles shall be anti bacterial type strictly as recommended by the manufacturer of

tiles concerned.

4.0 Homogeneous Vitreous

Heavy duty Homogeneous Vitreous Porcelain approved manufacture 300 x 300 x 8.5

mm thick matt finished tiles laid on 20 mm thick 1: 3 cement sand screed prepared to

receive tiles. Grouting material for the joints shall be anti bacterial type and from the

same Manufacturer. Joints shall be neat butt joints and method of fixing shall

conform to Manufacturer’s instructions. Tiles shall conform to BSS 202 of 1972 or

revised Edition of the same.

Page 78 of 170

Page 79: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Section 7 - Bill of Quantities

Section - 7

Bill of Quantities

Page 79 of 170

Page 80: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PRICING PREAMBLES

GENERALLY

Provision has been made for the total of each page to be collected at the end of each bill of

these Bills of Quantities.

The Bidder should price all the items in the Bills of Quantity

Lump sums shall not be given where unit rates are applicable.

Payment against any item in the Bill of Quantities will be made only if such item has actually

been carried out by the contractor. If the Contractor intends to execute any alternative

method of construction, the Engineer's prior approval thereof shall be obtained prior to

execution of such work in order to ensure payment against the relevant item.

Unit rates may be used reciprocally in the settlement of accounts unless conflict between

them occurs. The Contractor is, therefore, to ensure that identical items occurring in separate

bills are not priced at different rates unless this is his deliberate intention.

The Contractor shall check against the summaries that each copy of the Bills of Quantities is

complete in the number of pages and in the reproduction of each page.

The Contractor’s prices and extension shall be entered in waterproof ink.

Unit rates and extensions shall be given in Sri Lankan Rupees to a maximum of two

significant places of decimals.

The various documents collectively referred to herein as the Bills of Quantities jointly

constitute the Bill of Quantities referred to in the Conditions of Contract.

These Bills of Quantities have been measured generally in accordance with the principles

laid down in the Method of Measurement of Building Works and rates shall include for

everything required for complete sections of work in accordance with the specifications and

drawings.

In the Bills of Quantities, if any materials/ fittings are described by using a trade name, it is

only for the purpose of indicating the minimum level of quality and standard required. The

Bidder may use any other material/ fittings, which are considered as equivalent in quality and

standard to those specified therein subject to the approval of the “ Engineer”

Items in the preambles section of these Bills of Quantities are deemed to qualify and to form

part of every description of measured work to which they refer including composite

descriptions.

No amendment which has not been authorized in writing by the Engineer shall be made to

these Bills of Quantities.

Page 80 of 170

Page 81: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The Contractor shall not use these Bills of Quantities as a construction programme or for the

purposes of ordering materials or arranging sub-contracts. The references for these activities

shall be the drawings, specification and instructions issued by the Engineer.

These pricing preambles are a standard and comprehensive set and hence may exceed the

requirements of this particular project.

Format for Descriptions

In addition to common abbreviations the following have been adopted:

M - metre m2 - square metre

m3 - cubic metre mm - milli meter

nr - number t - tonne

kg - kilograms h - hour

CP - Code of Practice BS - British Standard

BOQ - Bills of Quantities

Every description shall read as if the phrase “and the like” were incorporated into it.

Where specific classifications have been given but are deemed to include other categories of

work only the classified item shall be given in descriptions.

“Prices also to include”; items under this heading fall into two categories :

a) Those which are deemed to be included in descriptions and therefore, in prices.

b) Those for which the Contractor shall allow in his prices.

“Approved” , “Directed”, “Selected” and similar expressions shall relate to the Engineer’s

decision.

“Falls”, “Slopes”, “Weathered” : inclined from the horizontal in one plane.

“Cross Falls”, “Cross Slopes”, “Cross weathered” : inclination from the horizontal in more than

one plane.

Prices also deemed to include

Rates shall be comprehensive and include for the following:

All obligations imposed by the Contract.

Complying in every respect with the requirements and the considerations of the

specifications and drawings.

All considerations arising from the definitions incorporated into each preamble section.

Labour for fixing and all associated costs.

Materials and goods and all associated costs.

Fitting and / or fixing materials and goods in any position, hoisting to any height.

Page 81 of 170

Page 82: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Use of scaffolding, plant, equipment and tools.

Allow for protection of finished surfaces/fittings etc. of all work sections.

Any additional labours usually associated with measured items.

All measurements are net and the rates shall include for all laps(except for steel

reinforcement where the quantity of laps is included in the BOQ quantity), waste, working

space and trade or traditional allowances.

The pricing of materials shall take account of the following :

Pricing Preambles, Drawings and Specifications shall apply reciprocally between sections of

the works unless otherwise described.

Materials shall be of the best quality available unless otherwise described.

All materials shall be transported, handled, stored and fixed in accordance with the printed

instructions or recommendations of their manufacture or suppliers.

Protection of completed work, all casings and temporary coverings and making good and

clearing away upon completion.

Building paper, damp proof membrane, quilts and all non-rigid sheet materials shall include

cutting or forming holes and notching and the extra labour of turning up at edges and the

like.

Duct shall include draw wires.

Holes, mortices, pockets, grooves, chases and the like and items described as “built in” and

“cast in” shall include making in its fullest sense and through, around, into over and up to the

items concerned.

Items described as “cut” shall include general making good similarly.

Where the word “allow” is used the cost of the items shall be the responsibility of the

Contractor.

The Contractor shall obtain from all sub-contractors (weather nominated or otherwise) their

requirements for all recesses, chases, holes and the like in order that they may be built in or

formed as the work proceeds. No additional charges shall be allowed for cutting recesses,

chases and holes and the like after the construction of the works.

In the event of their being any discrepancies between details on drawings, descriptions in

specifications and descriptions in the Bills of Quantities then the rates and pricing shall be

deemed to relate to the documents order of precedence set out in the Form of Agreement.

The amounts set against any Provisional Sums for supply of materials shall be the net CIF

amount adjusted for all discounts and customs duties. The amounts set against any items of

Page 82 of 170

Page 83: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

profit shall include for all costs in connection with letters of credit, bank charges, interest

charges and insurance after the materials come under the control of the Contractor.

The Contractor should leave the whole of the works ready for immediate occupation to the

satisfaction of the Engineer including the following:

a) Cleaning and touching the buildings both inside and out, leaving all surfaces free of

cracks, blemishes or splashes.

b) Easing, oiling and adjusting and making good of finishes to all fittings, doors, windows,

ironmongery and the like.

c) Cleaning and polishing all marble glass, anodised aluminium and sanitary ware,

including the removal of all protective coverings, paint splashes and the like.

Replacements of all or any chipped, cracked or broken items.

d) Balancing of air conditioning installations where applicable.

e) Removal of rubbish, debris or excess spoil from the site area and raking over and

cleaning all unused parts of the site area.

Fix only

The expression “fix only” used in these Bills of Quantities means that the Contractor shall

provide the following facilities :

a) Fixing with all necessary accessories and the like.

b) Supplying full size templates, giving and marking dimensions and taking responsibility for

their accuracy.

c) Getting in, protecting, handling, distribution and placing in position and assembling as

required.

d) Casing up and protection, including clearing away protection on completion of the works

including sub-contractor works

e) Full cost of replacement of any items which are damaged, broken, lost or stolen after

the acceptance of the items from the supplier or Employer and until handing over the

complete works.

f) Other necessary and usual facilities and documentation.

Supply only

The expression “supply only” used in these Bills of Quantities means that the Contractor is to

provide for everything in connection with such items except fixing in position.

Page 83 of 170

Page 84: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Sub – Contractors

Sub-contractors, whether nominated or not, are to be let on a current form of sub-contract

designed for use in conjunction with the General Conditions of Contract amended as

necessary to incorporate the appropriate provisions of the main Conditions of Contract.

The Contractor should ascertain from sub-contractors and suppliers before the work is put in

hand particulars of positions in which chases, holes, mortices and the like will be required to

be formed or left. No claim for the extra costs of cutting away work already built due to the

Contractor’s failure to asertain these particulars will be admitted.

Any local sub-contractors which the Contractor proposes to use for the works are subject to

the approval of the Engineer and Employer.

The Contractor shall provide for approval a list of sub-contractors who will be employed on

the works.

If the Contractor is refused permission to use any of his proposed sub-contractors then the

work shall be sub-let at no extra cost to an approved sub-contractor.

Any sub-contractor who has not been approved by the Engineer shall not be used in

connection with the carrying out or the works.

Nominated Sub-Contractors

At the time of every valuation of the works for certificate purposes the Contractor shall

submit to the Engineer a statement from each of the nominated sub-contractors showing:

a) The gross amount (including cash discount and retention) claimed in the current

certificate.

b) The net amount received from the Contractor to date excluding agreed contra charges.

Amounts in respect of nominated sub-contractors will not be included in valuations unless

these statements are received.

These statements will be accepted as reasonable proof of payment to nominated sub-

contractors under the Conditions of the Contract but otherwise the received invoices of

nominated sub-contractors are to be submitted to the Engineer as proof of such payments.

At the time of the settlement of accounts and as one of the documents referred to in the

Conditions of Contract the Contractor is to obtain a statement from each of the nominated

sub-contractors that the sums and / or credits to be included in the settlement of accounts in

respect of such nominated sub-contractors are accepted in full and final settlement of their

sub-contracts.

Page 84 of 170

Page 85: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The word “attendance” means that Contractor shall provide the following attendances and

facilities.

a) Use of Contractor’s administrative arrangements.

b) Use of Contractor’s constructional plant at site.

c) Use of Contractor’s facilities at site.

d) Use of temporary works at site.

e) Clearing away rubbish from the central point of collection.

f) Use of Contractor’s scaffolding at site.

g) Unloading, distributing, hoisting and placing in position items of plant and machinery.

h) Supplying full size setting out templates and giving and marking dimensions and taking

responsibility for their accuracy.

i) Providing working space and stores.

j) Other necessary and usual facilities, documentation, general inter-trades attendance,

labour and assistance.

The Contractor shall allow for any additional costs incurred due to sub-contractors working

different hours from and extended hours to those worked by the Contractor.

Prime Cost Sums in Unit Rates

Certain rates within the Bills of Quantities will include Prime Cost Sums. The material

specification and fixing details will be specified. The Contractor is to include against each

heading the necessary uplifts and additions required to give his final rate. This rate will then

be carried to the relative places within the Bills of Quantities.

These prime cost sums are subject to alteration and no additional claim will be allowed for

the varying of these items.

Page 85 of 170

Page 86: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

SECTION: EXCAVATION AND EARTH WORK

Definitions

Rock is defined as any material met with which is of such size or position that, in the opinion

of the Engineer it can only be removed by means of wedges, special plants or explosives..

Method of Measurement

The method of measurement and re-measurement will be entirely at the discretion of the

Engineer but generally will be as follows :

a) Where there is no reduced level excavation, other excavations will be measured from

natural ground level.

b) In instances where there is excavation to reduce levels other excavations will be

measured from the reduced level.

c) Should the Contractor be able to use any excavated material arising from the works as

general filling then it shall be measured as material back filled in making up levels with a

deduction of items for filling and for material removed from site.

Prices also to include

Rates for excavation shall be deemed to include for the following:

a) Excavating by whatever means are necessary including hand excavation in any kind of

ground, except rock.

b) Over break including filling with mass concrete to the levels required by the Engineer.

c) Trimming or grading ground to produce level surfaces or surfaces to falls or slopes.

d) Ramming and compacting sides and bottoms of excavations.

e) Additional excavation for working space arising out of any cause, as excavation

measured nett unless otherwise specified in item description.

f) Any hand excavation required around existing services or the like.

g) Compliance with relevant acts, by laws and regulations relating to excavations and earth

work supports.

h) Inspection of Site

Hard Rock

The tenderer at the time of preparing the tender shall ascertain the prevailing laws and

regulation as to the legal requirements of blasting rock and shall allow in his prices

accordingly.

Page 86 of 170

Page 87: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Hard rock requiring blasting

Rates for excavation in rock requiring blasting shall include for:

a) Obtaining all necessary permits and taking precautionary measures during blasting

operation.

b) Complying with all regulations and instructions issued by relevant government or local

government authorities.

c) Additional Insurance cover; if necessary.

d) Sledding and stock piling excavated rock etc. as directed by the Engineer. (Maximum

distance of stock pile 100 meter from the point of excavation).

Note:

For the purpose of measurements, percentage of voids in stock pile shall be taken as 20%

the volume considered for payment shall be the gross volume of stock pile X 0.80

Earth work support

Provisional quantities of earth work support (planking and strutting) are given in the BOQ.

Payment for earth work supports will only be considered if physically carried out at the site.

The Contractor shall obtain the prior approval of the Engineer before carrying out any

alternative method of earth work supports than specified in the Contract.

Termite Protection/Applying Insecticides.

The quantity measured in the BOQ is the plinth area of the building in square metres.

The bidder shall assess the actual quantity of area to be treated and shall allow in the unit

rate accordingly.

Rate shall include for providing guarantee as per contract.

SECTION: CONCRETE WORK

Prices also to include

The contractor should ascertain from the Engineer the total number of locations of items to

be formed in and cast into in-situ and precast concrete including those which are not

specifically shown on the drawings. No cutting away of concrete shall be carried out without

the approval of the Engineer. All remedial works shall be carried out at the Contractor’s

expense.

Page 87 of 170

Page 88: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The rates for all In-situ concrete work shall include for the following:

a) Concrete test cubes and testing costs.

b) Mixing, hoisting (local) and placing and compacting on the surfaces of any material or

on formwork.

c) Forming any construction joints or the like.

d) Vibrating, Curing and protecting concrete surfaces from harmful weather conditions.

e) All necessary keys to concrete surfaces to receive in-situ finishes.

f) All costs in construction with the construction of “Kickers”.

The rates for plain concrete foundations and concrete blinding shall include for the

following.

a) All necessary shuttering to edges or extra volume of concrete used in lieu of

shuttering.

b) Forming sloping upper surfaces where required.

The rates for reinforced concrete shall include for working concrete around reinforcement

The rates for bar reinforcement shall include for the following:

a) Positioning and protecting starter bars.

b) Straightening (if required) cutting to length and bending reinforcement to required

shapes.

c) Waste and rolling margin of steel reinforcement.

d) Cleaning and wire brushing.

Supporting in position during concreting:

Provision of supports (excluding links and stirrups) steel binding wire and approved/

proprietary distance pieces.

Additional cutting and bonding in connection with holes, mortices, packets, grooves, chases

and the like.

Preparation of detailed reinforcement drawings and bar bending schedules for all steel work

to be submitted to the Engineer or his representative for approval before starting the work.

Page 88 of 170

Page 89: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The rates for fabric reinforcement shall include for the following:

a) Straight raking curved and circular cutting and waste, bending to profiles laps of one

full square/ rectangular module or as noted.

b) Supporting in position during concreting: provision of supports (excluding special

chairs) steel binding wire and approved/ proprietary distance pieces.

c) Cutting, bending and notching around all obstructions.

The rates for Form work as appropriate shall include for the following.

a) Small quantities

b) All cutting and waste including raking curved or circular cutting and cutting and

notching around pipes, ducting and fittings.

c) Setting up, strutting and supporting at any height above the structure subject to any

limitations imposed by the Employer’s representative including all props, stays struts,

wedges and bolts etc.

d) Carefully coating with shutter oil ensuring that no shutter oil is applied to surfaces of

reinforcement.

e) Easting, striking, removing and cleaning and preparing for re-use and removal when

no longer required.

f) Overlaps and passings at angles and labours at intersections.

g) Shortening struts or shapes and re-strutting or re-shoring where required.

h) Rubbing down, filling and making good the surface of concrete after removal of

shuttering.

i) Cutting or notching shutters or moulds to in-situ or pre-cast concrete around

projecting reinforcement.

j) Sealing of joints to avoid leaking of cement grouting.

k) Rate for plain concrete blinding concrete blinding beds shall include for any

necessary formwork at edges for the extra width of concrete which may be required

in lieu.

Page 89 of 170

Page 90: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The rates for wrought shuttering/ shuttering to produce a special finish shall include

for the followings:

a) Any necessary rubbing down or filling allowed by the specification to produce the

finish required.

b) Cutting out and re-casting unsatisfactory work or work not fulfilling the requirements

of the specification or carrying or remedial or any other work required by the

Engineer as an alternative to cutting out substandard work.

The rates for pre-cast concrete shall include for the following:

a) The provision of moulds.

b) Forming a fair in accordance with the specification to all exposed surfaces.

c) Hacking or forming keys to all other surfaces.

d) Lifting hooks or other devices approved by the Employer’s representative for

positioning.

e) Bedding joining in mortar as specified.

f) All necessary temporary struts or supports.

g) Sills and coping etc., shall include for plain ends and mitred angles where necessary.

h) Complying with requirements of the relevant Preamble clauses.

i) Testing pre-cast units, if required.

Reinforcement to Masonry

The concrete of this section equally applies to reinforcement included within the Masonry

section of the Bills of Quantities, unless otherwise stated.

SECTION: MASONRY WORKS

The rates for masonry walls shall include for the following:

(a) Material testing at a recognized laboratory, provision of certificates

(b) Small quantities and any extra labour in forming kerbs.

(c) Straight, raking, curved and circular rough or fair cutting, plumbing at angles, cutting

and bonding at angles, openings and intersections, building into and / or against

adjacent work, wedging and pinning up to soffits.

(d) All necessary keys for in-situ finishing.

(e) Grouting up at back of walls built against other construction.

(f) All necessary cast in wall ties at any junctions between different types of

constructions such as brickwork + block work, brick work + concrete work, block work

+ concrete work and the like.

(g) All necessary expansion, construction, contraction joints, slip strip or the like.

Page 90 of 170

Page 91: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

The rates for pre cast concrete shall include for the following:

a) The provision of moulds.

b) Forming a fair face in accordance with the specification to all exposed surfaces.

c) Hacking or forming keys to all other surfaces.

d) Lifting hooks or other devices approved by the Employer’s representative for positioning.

e) Bedding joining in mortar as specified.

f) All necessary temporary struts or supports.

g) Sills and copings, etc., shall include for plain ends and mitred angles where necessary.

Reinforcement to Masonry

The concrete of this section equally apply to reinforcement included within the Masonry

section of the Bills of Quantities, unless otherwise stated.

SECTION: WATER PROOFING

Rates for Water Proofing shall include for:-

(a) Cleaning, washing and preparation of surfaces to receive Water Proofing treatment

(b) Construction of mortar fillets at slab/wall and wall/wall intersections

(c) Cost of procurement and submission of certificates and warranties as specified

(d) Testing the effectiveness of the water proofing treatment by ponding as directed

and rectification if required.

(e) Laps, cutting waste etc. of pre-formed membrane

SECTION : STRUCTURAL STEEL WORK

Definitions

“Welding” is deemed to be in accordance with the specification and for the material to which

it is to be used. Gusset plates, shoe plates, ends, caps, cleats, brackets, stiffeners, bolts,

etc., have been included in the weights of the associated steel work in which they occur.

Page 91 of 170

Page 92: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Prices to Include

a) All shop fabrication work, marking, delivery, unloading, hoisting (local), erecting and

fixing.

b) Allowance for rolling margin.

c) The weight of weld metal in welded constructions.

d) Members of any length.

e) Cutting to size and shape and joints in the running length.

f) Notches, holes, slots, mitres, ends and for all drilling and splay cut ends.

g) Grinding to a smooth finish, unless otherwise required.

h) After fabrication wire brushed to clean the surface and spray painted with two coats of

quick drying metal primer Zinc phosphate.

j) Rates for galvanizing or similarly treated work are to include for the treatment of all ends

to the approval of the Engineer.

SECTION: METAL WORK

Generally

Sizes given in the description of items are nominal sizes. The Contractor shall visit the site

and take all necessary spot measurements to determine the actual sizes of opening before

fabricating the units.

Definitions

“Welded” or “welding” unless otherwise stated shall be continuous butt or fillet welding left as

laid.

The rates for metal work shall include for the following:

a) All fabrication work, handling, delivery, unloading, hoisting, (local) fitting and fixing in

position.

b) Joints in the running length.

c) Angles in the running length.

d) Holes, notches, slots and the like.

e) Fixing with appropriate non-corroding countersunk screws including holes unless

otherwise described.

f) Riveted and bolted work shall include rivets, bolts and holes.

Page 92 of 170

Page 93: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

g) Approved protection to cut ends or holes in galvanized work or other applied finish.

h) Metal door frames shall include for assembling, fixing with clamps, filling with mortar,

temporary supports and removal of base ties.

i) Floor plates, duct covers, and the like shall include narrow widths laying in position

and for all holes, slots and the like making good.

j) Cutting and wastage

k) Providing separate strips etc, between dissimilar metals to prevent galvanic action.

l) Submitting shop drawings for the approval of the Engineer.

m) Making good the works disturbed.

n) Cleaning and applying two coats of rust inhibitive paint or the application of spray on

fire proofing as per specifications to the unprotected steel trusses, beams and steel

members to achieve a three-hour fire rating.

o) Supplying samples of materials and composite units to the engineer for the approval.

p) All necessary scaffolding work including supply, erection and dismantling.

q) All preparation works to floor, walls and ceiling for fixing.

SECTION: ROOF COVERING AND ROOF PLUMBING

The rates for Roof covering and roof plumbing shall include for the following:

a) Hoisting (local) and placing roofing materials in position.

b) Laps, straight cutting and waste.

c) Nails, screws, clips, rivets, straps and the like.

d) Fixing nuts, limpets etc..

e) Any Guarantee for finished work as per contract

f) Apply paint to all exposed faces of roof plumbing as directed.

Page 93 of 170

Page 94: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Preliminaries

BILL

NO.

01

SPEC. DIV.

NO.

PAGE NO.

1/1

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

1A/-

BILL NO. 01

PRELIMINARIES

(Refer ICTAD Publication No. ICTAD/ID/04 Second

Edition - June 2009)

Note : Following items to be priced as appropriate.

Insurance and Securities

Allow lump sum for Providing a Performance Security.

Allow lump sum for providing an Advance Payment

Security.

Allow lump sum for insurance of Works, Machinery &

Equipment, Plant, Materials, third party persons &

property and Employer's personnel & property at site

as per the Contract.

Allow lump sum for insurance against accidents and

injury to Contractor's personnel as per the Contract.

Engineer's Facilities

Allow lump sum for constructing, maintaining,

dismantling and removal on completion of the works, a

temporary building for Engineer's office consisting of

office area, meeting room and toilet (Approx. area of

40m2) in conformity with the plans provided for

Engineer's requirements including necessary furniture

and fittings, furnishing, sanitary facilities for

male/female and other facilities as follows.

Toilet (02Nrs) - 2nr LLWC ,2nr wash basin,2nr bidet

sprayer,2nr bib tap and 2nr toilet paper holder

Furniture - 1nr conference table and 5 nr chairs, 3nr

office table and 3 nr chairs, 2nr computer table and 2nr

chairs,4nr visitors chairs

Cupboards - 2nr drawers or racks with clips, 1nr filing

cabinet with 4 nr drawers,1nr steel cupboard

Telephone direct line and fax machine

2nr computers with internet facility

Safty equipments

1nr Display board and 1nr magi board,2nr waste paper

baskets,Electric kettle

1A/01

Item

1A/02

Item

1A/03

Item

1A/04

Item

1A/05

Item

TO BILL NO. 01 SUMMARY

Page 94 of 170

Page 95: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Preliminaries

BILL

NO.

01

SPEC. DIV.

NO.

PAGE NO.

1/2

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

1A/06

Allow lump sum for providing telephone and facsimile

facilities, electricity and water services for the

Engineer's site office for their use in connection with

the Works.

Item

1A/07 Allow lump sum for maintenance, rental, consumption

charges etc. for telephone and facsimile facilities,

electricity and water services for the Engineer's site

office for their use in connection with the Works. Item

Contractor's Facilities

1A/08 Allow lump sum for constructing, maintaining,

dismantling and removal on completion of the works, a

temporary site office of adequate size including staff

rest room and toilets and other facilities for the

Contractor's site management staff in accordance with

the plans prepared by the Contractor and concurred by

the Engineer.

Item

1A/09 Allow lump sum for constructing, maintaining,

dismantling and removal on completion of the works,

buildings to be used as workshops and stores for

materials.

Item

1A/10 Allow lump sum for constructing, maintaining,

dismantling and removal on completion of the Works,

temporary buildings in accordance with the plans

prepared by the Contractor and concurred by the

Engineer to accommodate the following:

1. Workers' rest room, canteen facilities, kitchen

2. Toilet and wash areas

3. Sick / First - Aid room

41. Accommodation for Contractor's staff and

workmen including sanitary facilities on site, if

applicable.

Item

Facilities to workmen shall conform to the latest public

health and industrial regulations.

1A/11 Allow lump sum for providing accommodation including

sanitary facilities for Contractor's staff and workmen. Item

1A/12 Allow lump sum for providing telephone and facsimile

facilities, electricity and water services for the

Contractor's site office for their use in connection with

the Works.

Item

TO BILL NO. 01 SUMMARY

Page 95 of 170

Page 96: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Preliminaries

BILL

NO.

01

SPEC. DIV.

NO.

PAGE NO.

1/3

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

1A/13

Allow lump sum for maintenance, rental, consumption

charges etc. for telephone and facsimile facilities,

electricity and water services for the Contractor's site

office for their use in connection with the Works. Item

1A/14 Allow lump sum for Contractor's transport facilities at

site. Item

Construction Management and Supervision

1A/15

Allow lump sum for employing suitably qualified and

experienced technical personnel on full time basis for

Construction Management Services at the site. Listed

below are the particulars of staff to be engaged. Item (a) for 1 nr. Civil Engineer as specified over contract

period.

(b) for 1 nr. Quantity Surveyor as specified over

contract period.

1A/16

Allow lump sum for employing technical supervisory

staff not listed under item 15 above on full time basis. Item

Setting Out

1A/17 Allow lump sum for employing a licensed land surveyor

to define the building site work etc., check levels and

carry out such other surveys as may be necessary to

establish accurately the placing of forms and pouring of

concrete and all other setting out in both vertical and

horizontal plane. Item

1A/18 Allow lump sum for setting out of Works in accordance

with drawings and other written information given by

the Engineer. Item

Quality, Standards and Progress

1A/19 Allow lump sum for provision of progress reports

including photographic records and other schedules

included in the ICTAD publication - Guidelines for

Effective Construction Management. (ICTAD/CM/01),

relevant to contract administration as directed by the

Engineer. Item

TO BILL NO. 01 SUMMARY

Page 96 of 170

Page 97: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Preliminaries

BILL

NO.

01

SPEC. DIV.

NO.

PAGE NO.

1/4

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

1A/20

Allow lump sum for all cost in connection with preparing

samples for testing, making arrangements for testing of

Materials, Goods etc, as stipulated in the specification,

obtaining test reports and submitting the same to the

Engineer.

Item

1A/21 Allow lump sum for provision of shop drawings, bar

schedules etc. for Engineer's approval.

Item

1A/22 Allow lump sum for provision of 3 sets of (hard copies

and soft copies) as-built drawings of all services, for

Engineer's approval.

Item

Health, Safety and Environment

1A/23 Allow lump sum for engaging the service of an

adequately trained person to attend to first-aid medical

duties including a provision of a first aid box and

regular supply of medicine, linen etc.

Item

1A/24 Allow lump sum for providing and maintaining first aid

box and regular supply of medicine, linen etc.

Item

1A/25 Allow lump sum for the following services throughout

the period of construction for the Engineer's office,

Contractor's site office and worker's rest room and

other facilities;

Item

(a) Employing workmen to clean and maintain all

areas to be in good hygienic conditions including

toilets, wash areas, kitchen etc.

(b) Supplying adequate drinking water, water for

washing purposes, soap, detergent, etc. throughout the

period of construction.

1A/26 Allow lump sum for providing all necessary safety

measures to workmen at site conforming to the latest

industrial safety regulations and as directed by the

Engineer.

Item

1A/27 Allow lump sum for making adequate provision against

air and noise pollution of surrounding areas. Hoarding

and dust screens shall be provided to control dust

escaping to surrounding areas.

Item

TO BILL NO. 01 SUMMARY

Page 97 of 170

Page 98: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Preliminaries

BILL

NO.

01

SPEC. DIV.

NO.

PAGE NO.

1/5

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

1A/28

Allow lump sum for maintaining the site in a clean and

orderly manner at all times and during the entire

contract period.

The Contractor shall take due care to prevent water

Item

stagnation, eliminate mosquito breeding places at the

site and this is to be ensured through internal

monitoring mechanism.

Funding provision to be included to assign part time

basis suitable persons to be engaged in maintaining

documents/ forms and also for site inspections, take

actions to prevent mosquito breeding area and to

ensure the site is free of mosquito breeding places.

The Contractor shall follow the Health and Safety

Guidelines for Sri Lankan Construction sites to be

adopted during COVID 19 outbreak as per the CIDA

publications.

1A/29 Allow lump sum for demobilization, removal of all

rubbish & debris and clearing up site on completion,

leaving all in good order and handing over. Item

Security and Protection

1A/30 Allow lump sum for employing an adequate number of

security personnel and security systems on full time

basis throughout the period of construction, and

provide for necessary security lighting and a warning

system. Item

1A/31 Allow lump sum for providing and maintaining

necessary fencing, hoarding and gates for

safeguarding the Works, Materials and Plant, as

directed by the Engineer. Item

1A/32 Allow lump sum for protection of public and private

services at site. The Contractor shall take due care to

protect, water supply and drainage systems, telephone

and overhead/buried electrical cables etc. whose

locations are identified and made available to the

bidder at the time of bidding, unless earmarked for

demolition, during the execution of the Works. The

Contractor is to make good any damage due to any

cause within his control at his own expenses or pay any

cost and charges in connection therewith. Item

TO BILL NO. 01 SUMMARY

Page 98 of 170

Page 99: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Preliminaries

BILL

NO.

01

SPEC. DIV.

NO.

PAGE NO.

1/6

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE TOTAL PRICE

RUPEES

Services and Facilities

1A/33 Allow lump sum for supply of water for the Works and

paying all charges and other expenses in connection

with the supply from water mains or any other

alternative method of water supply, storage and

reticulation.

Item

1A/34 Allow lump sum for supplying temporary electricity for

the Works including connection, distribution system for

the Works, internal arrangements and all payments to

the authorities for consumption.

Item

1A/35 Allow lump sum for providing hoisting equipment and

other plant for the use of the Works on site (dry

hire).

Item

1A/36 Allow lump sum for providing small machinery and

equipment for the use of the Works at site.

Item

1A/37 Allow lump sum for erecting and maintaining

scaffolding and/or self climbing platforms. Such

scaffolding etc. shall be removed on completion and all

Works disturbed shall be made good.

Item

Miscellaneous

1A/38 Allow lump sum for stamp duty in accordance with the

prevailing regulations of the Government.

Item

Deleted

1A/39 Allow lump sum for providing and maintaining a name

board to the specifications and / or as directed by the

Engineer.

Item

1A/40 Allow lump sum for excavation for trial pits/trial

trenches as specified or as directed by the Engineer as

for locating services etc. and reinstating the ground

and making good disturbed work to the satisfaction of

the Engineer.

Item

TO BILL NO. 01 SUMMARY

Page 99 of 170

Page 100: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Preliminaries

BILL

NO.

01

SPEC. DIV.

NO.

PAGE NO.

1/7

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE TOTAL PRICE

RUPEES

PRELIMINARIES

SUMMARY

Page No. 1/1

Page No. 1/2

Page No. 1/3

Page No. 1/4

Page No. 1/5

Page No. 1/6

CARRIED TO GENERAL SUMMARY

Page 100 of 170

Page 101: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Demolition

BILL NO.

02

SPEC. DIV.

NO.

PAGE NO.

2/1

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

BILL NO. 02

2A/- DEMOLITION WORKS

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

a) All tenderers are advised to visit site and make

careful study of all existing conditions and the nature

and extent of work to be done under this contract, as

no extras will be allowed on the plea of want of

information due to negligence of on their part in this

regard.

b) Demolished materials (Reusable) shall be

property of the Employer. Any materials recovered

from the demolitions to be handed over to the

Employer by inventory.

c) Demolished materials (Debris) should be

immediately carted away from the site.

d) Obtain confirmation from the Employer and

Engineer that all power cables and power lines

within the site have been disconnected and

Demolition

2A/01 Carefully demolish existing steel framed upper roof

and removing debris away from site.

1022

m2

2A/02 Carefully demolish existing timber framed lower roof

and removing debris away from site.

367

m2

2A/03 Carefully demolish existing floor concrete and

removing debris away from site.

127

m2

CARRIED TO GENERAL SUMMARY

Page 101 of 170

Page 102: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Construction of Proposed Additions and Alterations to

an Existing Building for Ocean University of Sri Lanka

at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/1

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3D/-

BILL NO. 03

EXCAVATION AND EARTHWORK

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

SITE PREPERATION

Clearing site vegetation, bushes, shurbs under

growth hedges and trees and stumps <

500mm girth removing all debris from site.

EXCAVATION

Note:

All excavations are measured net.

No allowance made for working space.

Excavations as follows in any materials met

with except in rock requiring blasting.

Excavation for foundation commencing

from formed ground level.

Excavate pits not exceeding 1.0m deep.

Excavate trenches width > 300mm, not

exceeding 1.0m deep.

EARTHWORK SUPPORT

Note:

(a) Provisional quantities of earth work

support are given below.

(b) Payment for earth work support will only

be considered if physically carried out at the

site.

(c) Earth work support shall be carried out

only if specially introduced to do so by the

Engineer.

Earthwork support

Total depth < 1.0m and distance between

opposing faces < 2.0m commencing from

formed ground level.

3D/01

Item

3D/02

44

m3

3D/03 11

m3

3D/04

133 m2

TO COLLECTION

Page 102 of 170

Page 103: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Construction of Proposed Additions and Alterations to

an Existing Building for Ocean University of Sri Lanka

at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/2

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE TOTAL PRICE

RUPEES

3D/05

Total depth < 1.0m and distance between

opposing faces 2.0-4.0m commencing from

formed ground level.

13

m2

Disposal

3D/06 Surface water.

Item

3D/07 Ground water.

Item

3D/08 Excavated materials; off site. 55 m3

Filling

3D/09 Back filling with approved imported earth off

site, to sides of foundation 150mm thick layers

well rammed and consolidated.

29

m3

3D/10 Filling with approved imported earth off site, to

make up levels in 150mm thick layers well

rammed and consolidate.

13

m3

TO COLLECTION

EXCAVATION AND EARTHWORK

COLLECTION

Page No.3/1

Page No.3/2

CARRIED TO BILL NO. 3 SUMMARY

Page 103 of 170

Page 104: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/3

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3F/-

CONCRETE WORKS

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

INSITU - CONCRETE

Work up to the top of structural floor level of

ground floor.

Foundation

Mass concrete (Grade 15 ) ; poured in to

ground.

Screed ; 50mm thick. under footings

Reinforced concrete (Grade 25); poured in to

formwork.

Column base.

Column; sectional area < 0.50m2, isolated.

Plinth beam

Staircase base.

Staircase wall

Beds and slab on ground

Reinforced concrete (grade 20) ; poured in to

ground.

Slab ;Thickness < 150mm.

3F/01

67

m2

3F/02

12

m3

3F/03 2.7 m3

3F/04 5.0 m3

3F/05 0.2 m3

3F/06 0.2 m3

3F/07

14

m3

TO COLLECTION

Page 104 of 170

Page 105: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/4

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

Work above top of structural floor level of

ground floor.

Mass concrete (Grade 20) poured in to floor

slab.

3F/08 In Toilets 12 m3

Reinforced concrete (Grade 30 ) poured in to

form work.

Slabs

3F/09 Thickness < 150mm. 56 m3

Columns

3F/10 Sectional area < 0.10m2; isolated. 29 m3

Beams

3F/11 Sectional area < 0.10m2; attached. 9.0 m3

3F/12 Sectional area > 0.10m2; attached. 44 m3

Lintols

3F/13 Sectional area < 0.10m2; isolated. (40 nrs) 3.1 m3

Stairs

3F/14 Steps waist and the like. 2.2 m3

3F/15 Landing Beams 0.3 m3

3F/16 Landings 0.7 m3

Vanity tops / Work tops

3F/17 Slabs, Thickness < 150mm. 1.2 m3

3F/18 Beams, sectional area < 0.10m2; attached. 2.1 m3

Capping beam

3F/19 225x150mm concrete beam at gable, including

necessary form work and reinforcement as per

detail drawing. 24 m

TO COLLECTION

Page 105 of 170

Page 106: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/5

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

Concrete pocket

3F/20 225x225x300mm concrete pockets, at the

connection of column and eave truss (measured

separately) including necessary form work and

reinforcement as per detail drawing. 16 nr

3F/21 225x250x250mm concrete pockets, at the

connection of gable wall and cross bracing

(measured separately) including necessary form

work and reinforcement as per detail drawing. 24 nr

Expansion joints

3F/22 Form 20mm wide expansion joint in 100mm thick

ground floor slab including 20mm thick soft board

with 12x20mm mastic filler as per detail drawing.

100 m

FORMWORK

floor level of ground floor.

Form work basic finished as per general

specification

3F/23 Column base ,height < 300mm. 149 m

3F/24 Columns; isolated ; square or rectangular. 37 m2

3F/25 Plinth beams, height < 300mm. 134 m

3F/26 Staircase base ,height < 300mm. 4.0 m

3F/27 Staircase wall ,height > 300mm. 2.0 m2

Form work plain finished as per general

specification

Work above top of structural floor level of

ground floor.

Formwork, soffit of slabs, horizontal

Slabs

3F/28 Slab thickness < 150mm, height < 3.5m. 368 m2

3F/29 Edges of floor slabs, height < 300mm. 5.0 m

TO COLLECTION

Page 106 of 170

Page 107: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/6

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

Sides and soffit of beams

3F/30 Attached; square or rectangular. 315 m2

Stairs

3F/31 Soffit of stair flights; slab thickness 150 - 300mm

, sloping > 15o.

12

m2

3F/32 Sides of stair flights; height < 300mm. 9.0 m

3F/33 Sides of risers; height < 300mm. 32 m

3F/34 Horizontal edges of landing; height < 300mm. 4.0 m

3F/35 Soffit of landing slab thickness <150 mm

horizontal.

5.0

m2

3F/36 Sides and soffit of landing beam. 3.0 m2

Form work basic finished as per general

specification

Columns

3F/37 Sides of columns isolated, square or rectangular. 180

m2

Sides and soffit of lintols

3F/38 Isolated; square or rectangular. 42 m2

Vanity tops / Work tops

3F/39 Soffit of slabs, Thickness < 150mm. 17.0 m2

3F/40 Edges of slabs, height < 300mm. 37 m

3F/41 Sides and soffit of beams, attached; square or

rectangular.

24

m2

TO COLLECTION

Page 107 of 170

Page 108: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/7

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

REINFORCEMENT IN INSITU CONCRETE

Mild steel bar reinforcement to BS 4449 and

strength (FY= 250 N/mm2) including bends,

hooks, tying wire, distance blocks and

ordinary spacers.

Work upto the top of structural floor level of

ground floor.

Diameter < 10mm

3F/42 In columns shaft 0.30 t

3F/43 In plinth beams 0.30 t

Work above top of structural floor level of

ground floor.

Diameter < 10mm

3F/44 In columns 1.00 t

3F/45 In lintols. 0.09 t

High yield tor steel bar reinforcement to BS

4449 and strength (FY=460 N/mm2) including

bends, tying wire distance blocks and

ordinary spacers.

Work upto the top of structural floor level of

ground floor.

Diameter < 10mm

3F/46 In staircase base & wall. 0.03 t

Diameter 10 - 16mm

3F/47 In column base 0.90 t

3F/48 In column shaft. 1.00 t

3F/49 In staircase base & wall. 0.10 t

3F/50 In plinth beams 0.40 t

TO COLLECTION

Page 108 of 170

Page 109: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/8

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

Work above top of structural floor level of

ground floor.

Diameter < 10mm

3F/51 In suspended slabs. 5.40 t

3F/52 In beams 1.60 t

3F/53 In stairs and landing and landing beam 0.30 t

3F/54 In lintols 0.30 t

3F/55 In vanity tops / work tops 0.50 t

Diameter 10 - 16mm

3F/56 In columns 3.50 t

3F/57 In beams 1.40 t

3F/58 In vanity tops / work tops 0.20 t

3F/59 In stairs and landing and landing beam 0.40 t

Diameter > 16mm

3F/60 In beams 3.00 t

3F/61 In stairs and landing and landing beam 0.03 t

Special treatments

3F/62 Rectification for existing circular columns, wire

brush the exposed reinforcement, apply zinc rich

primer and fill with micro concrete (non shrinkage

grout) as directed by the Engineer. (Approx. 2 nr

columns) Item

3F/63 Rectification for existing circular columns, wire

brush the exposed reinforcement, remove

corroded bars, 600mm long additional bar to be

welded (200mm welding length, apply zinc rich

primer and fill with micro concrete (non shrinkage

grout) as directed by the Engineer. (Approx. 10 nr

columns) Item

Sundries

3F/64 Costruction of concrete facia at roof level. Rate

shall include necessary form work, reinforcement

and finishes as per detail drawing 50.00 m

TO COLLECTION

Page 109 of 170

Page 110: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/9

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE TOTAL PRICE

RUPEES

CONCRETE WORKS

COLLECTION

Page No. 3/3

Page No. 3/4

Page No. 3/5

Page No. 3/6

Page No. 3/7

Page No. 3/8

CARRIED TO BILL NO. 3 SUMMARY

Page 110 of 170

Page 111: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/10

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3G/- MASONRY WORKS

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

BRICK WORK

In common bricks in cement and sand (1:5).

Vertical solid walls

112.5mm thick.

225mm thick.

STONE WORK

Random rubble stone work in cement and

sand (1:5).

In wall foundations

Thickness; 350mm.

3G/01

189

m2

3G/02 384 m2

3G/03

41

m2

CARRIED TO BILL NO. 3 SUMMARY

Page 111 of 170

Page 112: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC.

DIV. NO.

PAGE NO.

3/11

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT

RATE TOTAL PRICE

RUPEES

3H/- WATER PROOFING

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

Damp Proofing

3H/01 Width > 300mm,horizental, gauge 500 polythene

membrane. (measured nett no allowances made for laps.) 127 m2

CARRIED TO BILL NO. 3 SUMMARY

Page 112 of 170

Page 113: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/12

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3J/-

STRUCTURAL METAL WORK FOR

STEEL IN FRAMED STRUCTURE

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

All welds are 6mm thick fillet weld

Rate shall include for machine drilled, bolt

holes, bolts, nuts and washers, cleats,

shoe and gusset plates and all other

connections and after fabrication all mild

steel components should be sand blast to

clean the surface and applied paint to the

specification ISO 12944 - Category C5

(marine).

Fabricating and erecting framed structure

Trusses and built-up girders all as per

detail drawings

Roof trusses consisting 150x75x17.7kg/m

mild steel "C" channels, 65x65x5mm angle

irons and 50x50x5mm angle irons as per

detail drawing.

3J/01

Steel truss type RT1 (4 nr)

4.50

t

3J/02 Steel truss type ET1 (8 nr) 0.40 t

3J/03 Cross bracing type 01 3.60 t

3J/04 Cross bracing type 02 1.80 t

3J/05 150x75x17.7kg/m mild steel "C" channels

fixed to roof trusses ( trusses measured

separately) as per detail drawing. 535 m

3J/06 12mm diameter tie rods fixed to "C" channels

( "C" channels measured separately) as per

detail drawing. 92 m

TO COLLECTION

Page 113 of 170

Page 114: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/13

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

Angle irons

3J/07 100mm long, 100x150x6mm angle iron, at the

connection of gable wall and cross bracing

(measured separately) as per detail drawing.

24 nr

Plates

3J/08 Mild steel base plate size 350 x 350 x 12mm

thick including forming slots/ holes at the

connection of column and main truss

(measured separately) as per detail drawing. 1.0 m2

3J/09 Mild steel base plate size 250 x 175 x 10mm

thick including forming slots/ holes at the

connection of column and eave truss

(measured separately) as per detail drawing. 0.8 m2

Bolts

3J/10 16mm diameter hot dip galvanized thread bars

(approx. 200mm girth) at the connection of

column and main truss (measured separately)

as per detail drawing. 32 nr

3J/11 16mm diameter hot dip galvanized thread bars

at the connection of column and eave truss

(measured separately) as per detail drawing.

64 nr

3J/12 12mm diameter hot dip galvanized grade 8.8

bolts, at the connection of gable wall and

cross bracing (measured separately) as per

detail drawing. 48 nr

TO COLLECTION

Page 114 of 170

Page 115: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/14

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

STRUCTURAL METAL WORK FOR

STEEL IN FRAMED STRUCTURE

COLLECTION

Page No. 3/12

Page No. 3/13

CARRIED TO BILL NO. 3 SUMMARY

Page 115 of 170

Page 116: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/15

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3K/-

METAL WORK

Note:

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawing".

ALUMINIUM / GLAZED / DOORS, WINDOWS,

FANLIGHTS

Note:

(a) The contractor must submit for the approval of

the Architect complete fully dimensioned, detailed

shop drawings (drawn to suitable scales) and

Hardware schedules for the fabrication and

installation of all aluminium works.

(b) All screws, nut and bolts, washers and other

fastenings including those used for the hardware,

shall be of stainless steel type 304 (internal) , 316

(external) or H30 complying with BS 1449: part 2.

Technical information of forwarded.

(c) All aluminium extrusions to be powder coated to

a thickness of 60 - 80 microns, accordance with EN

ISO 2360- 2003

(d) All glazing to be of 5mm thick clear glass

(e) The contractor shall be responsible for checking

the dimensions of all opening sizes on site prior to

fabrication of the aluminium frames and fabricated

to the best standard of workmanship under

experienced factory supervision and control. The

maximum gap between the frame and the wall to be

2mm.

(f) The contractor may make minor changes in

construction details of the unit in order to facilitate

erection on site such changes shall not be made

without prior approval by the Architect in writing.

(g) Refer specification and conditions given in the

tender document.

Page 116 of 170

Page 117: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/16

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3K/01

3K/02

3K/03

3K/04

3K/05

(h) The tenderer to submit manufacturers

recommendation on extrusion with the tenderer.

(j) Together with all technical information and

catalogues of the aluminium extrusion to be used.

(k) All iron mongary to be forwarded with necessary

technical information together with make and unity

of origin.

( l ) The number and the size of the hinge to be

decide depending on the weight of the door.

(m) All s/s hinges to be with 4nrs. Bearings.

Powder coated approved colour aluminium

framed doors, windows units consisting of

aluminium frames, transoms, mullions,

aluminium framed glazed panels, aluminium

louvered panels plywood door sashes and

including necessary hardware such as hinges,

floor hinges, fasteners, stays, bolts, locks, door

closers, handles and the like all as detail

drawing, iron mongery schedule and

specification.

Doors

Door type D1, size 2000 x 2100mm, powder coated

aluminium framed double sash door with 4mm

cladding sheets as per detail drawing.

Door type D2, size 900 x 2100mm, powder coated

aluminium framed single sash door with 4mm

cladding sheets as per detail drawing.

Door type D3, size 750 x 2100mm, powder coated

aluminium framed single sash door with 4mm

cladding sheets as per detail drawing.

Door type D4, size 2000 x 2100mm, powder coated

aluminium framed double sash door with 4mm

cladding sheets and glazed panel as per detail

drawing.

Door type D5, size 900 x 2100mm, powder coated

aluminium framed single sash door with 4mm

cladding sheets and glazed panel as per detail

drawing.

3

2

7

5

4

nr

nr

nr

nr

nr

TO COLLECTION

Page 117 of 170

Page 118: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/17

ITEM REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3K/06

3K/07

3K/08

3K/09

3K/10

3K/11

Door type D6, size 900 x 2100mm, powder coated

aluminium framed single sash door with 4mm

cladding sheets as per detail drawing.

Door type D7, size 1000 x 2100mm, powder coated

aluminium framed double sash door with 4mm

cladding sheets as per detail drawing.

Windows

Window type W1, size 1800 x 1500mm, powder

coated aluminium framed glazed window with fixed

glass above as per detail drawing.

Window type W2, size 900 x 600mm, powder

coated aluminium framed glazed window with fixed

glass above as per detail drawing.

Window type W1, size 1200 x 1500mm, powder

coated aluminium framed glazed window with fixed

glass above as per detail drawing.

Fanlight

Fanlight type FL, size 900 x 600mm, powder

coated aluminium framed sliding fanlight as per

detail drawing.

2

1

10

1

1

4

nr

nr

nr

nr

nr

nr

TO COLLECTION

METAL WORK

COLLECTION

Page No. 3/16

Page No. 3/17

CARRIED TO BILL NO. 3 SUMMARY

Page 118 of 170

Page 119: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/18

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

3L/- WOOD WORK

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

Note:

(a) All roof timber shall be "CCB" pressure

treated and superior quality timber, or other

stated by Engineers.

(b) All bolt holes should be Machine drilled

( c ) All exposed and un exposed areas of roof

timber, ceiling planks shall be well treated as

directed by the Engineer

(d).Rate shall include for all timber rafters,

ceiling planks and timber are planning and

prepare surface and apply one coat of wood

preservative of an approved quality etc.

(e) All iron mongary to be forwarded with

necessary technical information together with

make and unity of origin.

CARPENTRY

50x50 mm reepers ( finished size)

50x100 mm rafters ( finished size)

75x100 mm wall plate ( finished size)

50x125 mm timber plate ( finished size)

JOINERY

Valance board

25mm thick, 300mm high, timber valance board,

fixed to roof frame (measured seperately),

finished with one coat of primer and two coats of

enamel paint as per detail drawing.

3L/01 535 m

3L/02 365 m

3L/03 50 m

3L/04 50 m

3L/05

98 m

CARRIED TO BILL NO. 3 SUMMARY

Page 119 of 170

Page 120: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/19

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3P/-

ROOF COVERING / ROOF PLUMBING

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

Roof Covering

Upper roof

3P/01 Asbestos sheet roof covering on steel frame work

(framework measured seperatly) including 50mm thick

double sided reinforced aluminium foil insulation

(thermal and sound) and gauge16 GI welded wire mesh

to keep the insulation foil in position as per specification

and detail drawing.

570

m2

Lower roof

3P/02 Asbestos sheet roof covering on timber frame work

(framework measured seperatly) as per specification

and detail drawing.

211

m2

Ridges

3P/03 Clay tile ridge cap match to above roofing. 25 m

Flashing

3P/04 0.47 mm thick Zink Aluminium plain steel sheets

flashings bend to shape; approximately 700mm girth,

one end dressed over lower roof sheet covering and

other end dressed over the brick wall as per detail

drawing.

50

m

Roof plumbing

Eave Gutter

3P/05 PVC eave gutter, fix to valance board (measured

separately) including necessary running heads and

connections etc.

98

m

Down pipes

3P/06 90mm diameter PVC rain water down pipe, type 1000,

fixed to wall / column with standard clips at 450mm

centers.

40

m

CARRIED TO BILL NO. 3 SUMMARY

Page 120 of 170

Page 121: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/20

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3Q/-

PLUMBING / SANITARY INSTALLATIONS

Provisional Quantities

Note:

For the full description of materials and

workmanship refer" Specification of works",

"Pricing Preambles" and "Drawing".

COLD WATER

UPVC PIPE PNT 11 ( TYPE 1000 )

20mm diameter.

3Q/01 In chases 18 m

25mm diameter

3Q/02 In chases 10 m

32mm diameter

3Q/03 Fixed to wall 7.0 m

From main connection to building

40mm diameter

3Q/04 In trenches - Up to building 30 m

Drainage above ground

Waste water

UPVC PIPE PNT 7 ( TYPE 600 )

50mm diameter

3Q/05 In concrete 7.0 m

TO COLLECTION

Page 121 of 170

Page 122: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/21

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

63mm diameter

3Q/06 In concrete 14 m

3Q/07 In trenches 3.0 m

3Q/08 "Extra over" for bends. 2 nr

3Q/09 "Extra over" for tees. 2 nr

Soil

UPVC PIPE PNT 7 ( TYPE 600 )

63mm diameter

3Q/10 In concrete 4.0 m

3Q/11 In trenches 2.0 m

110mm diameter pipe

3Q/12 In concrete 14 m

3Q/13 In trenches 5.0 m

3Q/14 "Extra over" for bends. 2 nr

3Q/15 "Extra over" for tees with cleaning eye. 2 nr

Fixtures, appliances and equipments should

be as per Engineers approval.

3Q/16 Supply and installation of Water closet suit

consisting of pedestal pan with 'P' trap, low level

flushing cistern including all accessories complete

to working order to Engineers approval. (Prime

cost Rs. 40,000.00) 7 nr

TO COLLECTION

Page 122 of 170

Page 123: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/22

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3Q/17

Supply and installation of pedestal type wash

basin including all accessories and heavy quality

brass chromium plated pillar tap, complete to

working order to Engineers approval. (Prime cost

Rs 30,000.00) 6 nr

3Q/18 Supply and installation of Bowl type urinal,

including individual flush valve (chromium plated)

all spreader and flushing pipe, waste outlet, bottle

trap as specification and detail, complete to

working order. (Prime cost Rs 25,000.00 ) 5 nr

3Q/19 Supply and installation of Soap holders to match

above fittings. 6 nr

3Q/20 Supply and installation of Mirror size 600 x

750mm high; beveled edge mirror with 4nr

chrome plated cap screws. 6 nr

3Q/21 Supply and installation of Hand spray to match

above fittings. 7 nr

3Q/22 Supply and installation of chemical resistance

ceramic lab sink single bowl fix to top of work top.

(measured seperatly) including swan neck sink

tap as specification and detail, complete to

working order. (Prime cost Rs 80,000.00 ) 12 nr

Cocks/valves/taps etc.

Refer Specifications

3Q/23 Angle valve to suit 20mm diameter pipe 20 nr

3Q/24 Push valve to suit 20mm diameter pipe 5 nr

3Q/25 Gate valve to suit 32mm diameter pipe. 1 nr

3Q/26 Gate valve to suit 40mm diameter pipe. 2 nr

TO COLLECTION

Page 123 of 170

Page 124: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/23

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3Q/27

BUILDERS WORK

Supply and fix PVC floor trap size

150x150x100mm deep (Internally) in concrete

floor including stainless steel grating on top and

necessary water proofing work. 9 nr

TO COLLECTION

PLUMBING / SANITARY INSTALLATIONS

COLLECTION

Page No. 3/20

Page No. 3/21

Page No. 3/22

Page No. 3/23

CARRIED TO BILL NO. 3 SUMMARY

Page 124 of 170

Page 125: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/24

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3S/- ELECTRICAL INSTALLATION

This is a supply, install and commissioning

contract.

All materials, equipments, wiring and

workmanship shall confirm to local codes of

specifications, B.S Standards, latest I.E.E

regulations (18th Edition, 2018 amendment) and

Ceylon Electricity Board specifications.

Contractor shall investigate the site conditions

before submitting their quote.

Contractor shall obtain sample approvals for all

the items used before fixing, from the

Consultant.

Contractor shall propose shop drawings/conduit

lay out drawings and obtained approval from the

Consultant, before commencing Installation.

Original print catalogues shall be submitted.

Warranties for fittings shall be submitted.

The Rate shall include for supply, installation,

commissioning & comprehensive maintenance

during the defect liability period of one year.

During defect liability period any faulty

fitting/component shall be replaced free of

charge.

The Rate shall include for providing insuarance

during handling, transporting, storing &

Installation untill handover.

General

3S/01 Submittal of As Built drawings c/w set of AutoCAD

2012 drawings in a CD and 3 hard copies. 1 Item Deleted

Inspection and testing

3S/02 Obtaining certification for complete Electrical

Installation by a chartered Electrical Engineer. 1 Item

TO COLLECTION

Page 125 of 170

Page 126: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/25

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

Distribution Boards

All the Distribution Boards shall be surface

mounted type Distribution Boards complete with

Powder Coated Steel enclosures with lockable

doors and Shall be Complied to IEC 61439.

Distribution Boards shall be completed with

necessary protection as per the drawing.

Make of MCCBs and MCBs, RCDs and etc shall

be Schneider / ABB / Terasaki or equivalent

make, approved by the Consultant.

Manufactures shop drawings should be

submitted and aproved by the Consultant before

fabrication

3S/03 Floor DB-Stage III Area 1 Item

01 No. 3P 63A MCB. (Main Incomming, 1 6kA Breaking

capacity)

1 set of LED Phase indicator lamps c/w 3 x 2A fuse

03 Nos. 3P 32A, MCB (10kA Breaking Capacity)

03 Nos. 1P 20A MCB (10kA Breaking capacity )

Surface mounted Steel enclosures Enclosure c/w

bus bars and Accessories.

All incoming power cables and outgoing cables are

from the top of the DB.

3S/04 DB-AC 1 Item

01 No. 4P 32A MCB. (Main Incomming , 10kA Breaking

capacity)

03 Nos. 2P 40A, 100mA RCCB (EL Protection of

General Lighting and Power Circuits)

1 set of LED Phase indicator lamps c/w 3 x 2A fuse

06 Nos. 2P 16A MCB (6kA Breaking capacity)

Surface mounted Steel enclosures Enclosure c/w

bus bars and Accessories.

All incoming power cables and outgoing cables are

from the top of the DB.

TO COLLECTION

Page 126 of 170

Page 127: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/26

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3S/05

3S/06

3S/07

DB-AquaCulture LAB

01 No. 4P 32A MCB. (Main Incomming , 10kA Breaking

capacity)

03 Nos. 2P 40A, 30mA RCCB (EL Protection of General

Lighting and Power Circuits)

01 set of LED Phase indicator lamps c/w 3 x 2A fuse

11 Nos. 2P 16A MCB (6kA Breaking capacity)

05 Nos. 2P 16A MCB (6kA Breaking capacity)

Surface mounted Steel enclosures Enclosure c/w

bus bars and Accessories.

All incoming power cables and outgoing cables are

from the top of the DB.

DB-SCUBA Diving Unit

01 No. 4P 32A MCB. (Main Incomming , 10kA Breaking

capacity)

03 Nos. 2P 40A, 30mA RCCB (EL Protection of General

Lighting and Power Circuits)

03 Nos. 4P 40A, 30mA RCCB (EL Protection of General

Lighting and Power Circuits)

1 set of LED Phase indicator lamps c/w 3 x 2A fuse

06 Nos. 2P 16A MCB (6kA Breaking capacity)

06 Nos. 2P 10A MCB (6kA Breaking capacity)

03 Nos. 4P 16A MCB (6kA Breaking capacity)

Surface mounted Steel enclosures Enclosure c/w

bus bars and Accessories.

All incoming power cables and outgoing cables are

from the top of the DB.

DB-Lecture Room

01 No. 2P 20A MCB. (Main Incomming , 10kA Breaking

capacity)

01 Nos. 2P 40A, 30mA RCCB (EL Protection of General

Lighting and Power Circuits)

1 set of LED Phase indicator lamps c/w 3 x 2A fuse

09 Nos. 2P 16A MCB (6kA Breaking capacity)

06 Nos. 2P 10A MCB (6kA Breaking capacity)

Surface mounted Steel enclosures Enclosure c/w

bus bars and Accessories.

All incoming power cables and outgoing cables are

from the top of the DB.

1

1

1

Item

Item

Item

TO COLLECTION

Page 127 of 170

Page 128: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/27

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3S/08

3S/09

3S/10

DB-Cafeteria

01 No. 2P 20A MCB. (Main Incomming , 10kA Breaking

capacity)

01 Nos. 2P 40A, 30mA RCCB (EL Protection of General

Lighting and Power Circuits)

1 set of LED Phase indicator lamps c/w 3 x 2A fuse

07 Nos. 2P 16A MCB (6kA Breaking capacity)

05 Nos. 2P 10A MCB (6kA Breaking capacity)

Surface mounted Steel enclosures Enclosure c/w

bus bars and Accessories.

All incoming power cables and outgoing cables are

from the top of the DB.

DB-Life Saving Unit and Passage

01 No. 2P 20A MCB. (Main Incomming , 10kA Breaking

capacity)

01 Nos. 2P 40A, 30mA RCCB (EL Protection of General

Lighting and Power Circuits)

1 set of LED Phase indicator lamps c/w 3 x 2A fuse

09 Nos. 2P 16A MCB (6kA Breaking capacity)

07 Nos. 2P 10A MCB (6kA Breaking capacity)

Surface mounted Steel enclosures Enclosure c/w

bus bars and Accessories.

All incoming power cables and outgoing cables are

from the top of the DB.

Main Cables for DBs

All the Cables quoted below shall be on measure

and pay basis. Rate shall include for supply and

installation of following cables including

perforated cable trays and Ladders,

conduits,Underground Installments etc.

including termination.

Supply, installation & termination of 4C, 10mm2

Cu/PVC/PVC cable from incomming from MDB to

Floor DB - Stage III

1

1

35

Item

Item

m

TO COLLECTION

Page 128 of 170

Page 129: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/28

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3S/11

3S/12

3S/13

3S/14

3S/15

3S/16

3S/17

Supply, installation & termination of 2C, 4mm2

Cu/PVC/PVC cables from Floor DB - Stage III to DB-

Lecture Room

Supply, installation & termination of 2C, 4mm2

Cu/PVC/PVC cables from Floor DB - Stage III to DB-

Cafeteria

Supply, installation & termination of 2C, 4mm2

Cu/PVC/PVC cables from Floor DB - Stage III to DB-

Life Saving Unit and Passage

Supply, installation & termination of 4C, 6mm2

Cu/PVC/PVC cables from Floor DB - Stage III to DB-

AC

Supply, installation & termination of 4C, 6mm2

Cu/PVC/PVC cables from Floor DB - Stage III to DB-

SCUBA Diving Room

Supply, installation & termination of 4C, 6mm2

Cu/PVC/PVC cables from Floor DB - Stage III to DB-

AcuaCulture Lab

Wiring for Light Points, Ceiling Fans, socket

outlets

Rate for point wiring shall include for all the

conduits, conduit fittings, casings,surface cable

trunks, fixing material, switches, wiring and

terminations, holders for light fittings and

socket outlets for power points. Contractor shall

obtain approvals from the Consultant for above

items

As a standard of quality for switches and socket

outlets, the contractor may use 'CLIPSAL/Hager

/Orange/Schneider or approved equal'.

Supply and Installation of a light point, from the

respective consumer unit using 2x1Cx1.5mm2

Cu/PVC/PVC + 1x1Cx2.5mm2 Cu/PVC(E) cable

drawn through securely fixed concealed 25mm PVC

conduit or casings and controlled by a 10A flush

switch fixed on solid / soft partition wall as shown in

the drawings.

15

17

24

15

25

25

100

m

m

m

m

m

m

nr

TO COLLECTION

Page 129 of 170

Page 130: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/29

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3S/18

3S/19

3S/20

3S/21

Supply and Installation of a fan point, from the

respective consumer unit using 2x1Cx1.5mm2

Cu/PVC/PVC + 1x1Cx2.5mm2 Cu/PVC(E) cable

drawn through securely fixed concealed 25mm PVC

conduit or casings, accessories & fan hook,

controlled by a regulator fixed on solid / soft partition

wall as shown in the drawings.

Supply and Installation of 13A twin switched Metal

Clad socket outlet (Ring circuit) fixed on solid / soft

partition wall, wired from the respective Consumer

Unit using 2 x1Cx 2.5mm2 Cu/PVC/PVC cable with

1x1Cx2.5mm2 Cu/PVC earth wire in 25mm PVC

conduit or casings with Socket and accessories.

Supply and Installation of 13A single switched

socket outlet fixed (Dedicated Circuit)on solid / soft

partition wall, wired from the respective Consumer

Unit using 2 x1Cx 2.5mm2 Cu/PVC/PVC cable with

1x1Cx2.5mm2 Cu/PVC earth wire in 25mm PVC

conduit or casings with Socket and accessories.

Supply and Installation of 16A 3ph Industrial socket

outlet fixed (Dedicated Circuit)on solid / soft partition

wall, wired from the respective Consumer Unit using

4 x1Cx 2.5mm2 Cu/PVC/PVC cable with

1x1Cx2.5mm2 Cu/PVC earth wire in 25mm PVC

conduit or casings with Socket and accessories.

Wiring for Light Points, Ceiling Fans, socket

outlets

The light fittings supplied and installed under

this contract shall be in every respect suitable

for the intended purpose.

Each fitting shall include bulbs, internal wiring,

hanging and fixing material and be complete

without any additional item / material being

required to make it so.

All the light fittings expected are THORN,

GREEN or equivalent made, approved by the

consultant

28

54

10

2

nr

nr

nr

nr

TO COLLECTION

Page 130 of 170

Page 131: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/30

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3S/22

3S/23

3S/24

3S/25

3S/26

3S/27

3S/28

3S/29

The contractor shall obtain consultants and

clients approval for the samples, technical

conformity as well as for the architectural details

of fittings before fixing them in the site.

35W Surface Mountable LED downlight round fiting made

with powder coated Die cast Aluminium housing. Colour

Temp. 6000K, CRI>80, PF>0.9 Luminous Efficacy - 100

lumens/W

35W Ceiling Recessed LED downlight round fiting made

with powder coated Die cast Aluminium housing. Colour

Temp. 6000K, CRI>80, PF>0.9 Luminous Efficacy - 100

lumens/W

9W indoor recessed LED downlight round fitting

mounting to ceiling made with powder coated Die

cast aluminium housing, Colour temp.6000K,

CRI>80, PF>0.9 Luminous Efficacy - 100 lumens/W

9W Surface Mountable LED downlight round fiting

made with powder coated Die cast Aluminium

housing. Colour Temp. 6000K, CRI>80, PF>0.9.

Luminous Efficacy - 100 lumens/W

14W LED Wall Bracket Lamps , indoor type .Colour

Temp. 6000K, PF>0.9. Luminous Efficacy - 100

lumens/W

7W LED Wall Bracket (Mirror lamp) Lamp, indoor

type made with powder coated Die cast Aluminium

housing. Colour Temp. 6000K, CRI>80, PF>0.9.

Luminous Efficacy - 100 lumens/W

1400mm Sweep Type Ceiling fan complete with 5

Speed fan regulator, brackets and all installation

accessories makes KDK, National.

Supply and Installation of Exhaust Fan

55

11

4

22

2

6

21

2

nr

nr

nr

nr

nr

nr

nr

nr

TO COLLECTION

Page 131 of 170

Page 132: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building

Works

BILL

NO.

3

SPEC. DIV. NO. PAGE NO.

3/31

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

ELECTRICAL INSTALLATION

COLLECTION

Page No. 3/24

Page No. 3/25

Page No. 3/26

Page No. 3/27

Page No. 3/28

Page No. 3/29

Page No. 3/30

CARRIED TO BILL NO. 3 SUMMARY

Page 132 of 170

Page 133: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/32

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

3T/-

FLOOR / WALL / CEILING FINISHES

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawing".

FLOOR FINISHES

Work above top of structural floor level of ground

floor.

IN-SITU FLOOR FINISHES

20mm thick, Cement sand (1:3) screed, finished

smooth with coloured cement rendering.

On rubble plinth.

On pavement

PORCELAIN TILES

To approved design and colour and including

20mm thick cement and sand (1:3) screed

bedding level and to slopes < 15° from horizontal.

300x600mm semi glazed homogeneous porcelain

floor tiles of approved colour laid to design; joints to

be grouted with matching to the colour of the tile.

(Price Rs. 600/= per 1 tile)

100mm high skirting to match above.

300x600mm rough finished homogeneous porcelain

floor tiles of approved colour laid to design; joints to

be grouted with matching to the colour of the tile.

(Price Rs. 600/= per 1 tile)

100mm high skirting to match above.

300x600mm semi rough homogeneous porcelain floor

tiles of approved colour laid to design; joints to be

grouted with matching to the colour of the tile. - At

toilets (Price Rs. 600/= per 1 tile)

3T/01

21

m2

3T/02 50 m2

3T/03

440

m2

3T/04 261 m

3T/05

137

m2

3T/06 40 m

3T/07

41

m2

TO COLLECTION

Page 133 of 170

Page 134: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/33

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

On work tops

300x600mm semi glazed homogeneous porcelain

floor tiles of approved colour laid to design; joints

to be grouted with matching to the colour of the

tile. (Price Rs. 600/= per 1 tile)

3T/08 Width < 300mm 37 m

3T/09 Width > 300mm 17 m2

WALL AND CEILING FINISHES

Plastered / Rendered

16mm thick plastering to wall cement, and sand

(1:5) plaster finished smooth with two coats of

skim coat (Internally).

On brick / concrete surfaces.

3T/10 Walls width < 300mm 50 m

3T/11 Walls width > 300mm 659 m2

3T/12 Isolated columns width < 300mm 31 m

On Internal side of the perimeter wall, internal and

external sides of toilet walls

16mm thick plastering to wall cement, lime or

equalent chemical product and sand (1:1:5)

plaster finished smooth with neat lime putty

(Internally).

3T/13 Walls width < 300mm 147 m

3T/14 Walls width > 300mm 403 m2

TO COLLECTION

Page 134 of 170

Page 135: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/34

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

16mm thick plastering to wall in cement lime or

equalent chemical product and sand (1:1:5)

plaster finished semi rough (Externally).

3T/15 Walls width < 300mm 102 m

3T/16 Walls width > 300mm 133 m2

3T/17 Isolated columns width < 300mm 126 m

CERAMIC WALL TILING.

Approved colour wall tiling joint and point in

water proofing grout to match on and including

12mm thick cement and sand (1:3) screed backing

on walls to specified height with beveled edge

from floor level.

300x600mm semi glazed clay tiles of approved

colour laid to design. (Price Rs. 450/= per 1 tile)

3T/18 Walls width < 300mm 29 m

3T/19 Walls width > 300mm 122 m2

CEILING FINISHES

Grinded and finished 16mm thick cement lime or

equalent chemical product and sand (1:1:5)

plaster (Internally) - Soffits of toilets

3T/20 On ceiling and beams; 3.5 < height < 5.0m above

floor 79 m2

TO COLLECTION

FLOOR / WALL / CEILING FINISHES

COLLECTION

Page No. 3/32

Page No. 3/33

Page No. 3/34

CARRIED TO BILL NO. 3 SUMMARY

Page 135 of 170

Page 136: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC.DIV.

NO.

PAGE NO.

3/35

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

3V/- PAINTING

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawing".

PLASTERED WORK

Plastered work ; general surfaces ; girth

> 300mm, plain surfaces,

Prepare and apply one coat of filler and two

coats of emulsion paint to a design as

directed (internally).

On walls / columns

Prepare and apply two coats of skim coats

(shuttering to give a smooth and even finish

suitable for approved skim coat) , one coat of

filler and two coats of emulsion paint to a

design as directed. (internally) - Other soffits

(except toilet soffits )

Ceiling and beams; height < 3.5m above floor.

Staircase Soffits

Sloping.

Horizontal.

Sides.

Prepare and apply one coat of filler and two

coats of weather shield paint to a design as

directed. (internally).

On walls / columns

Ceiling and beams; height < 3.5m above floor.

Prepare and apply one coat of filler and two

coats of weather shield paint to a design as

directed. (externally)

On walls / columns

3V/01

951

m2

3V/02

472

m2

3V/03

12

m2

3V/04 5.0 m2

3V/05 4.0 m2

3V/06

177

m2

3V/07 79 m2

3V/08

276

m2

CARRIED TO BILL NO. 3 SUMMARY

Page 136 of 170

Page 137: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/36

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

3W/-

DRAINAGE SYSTEMS

Note :

For the full description of materials

and workmanship refer "Specification

of works", "Pricing Preambles" and

"Drawings".

BELOW GROUND DRAINAGE

Excavating trenches; pipes < 100mm nominal

size and average depth of trench < 500mm

commencing from formed ground level

including back filling with selected earth.

Excavating trenches; pipes 100-200mm

nominal size and average depth of trench <

500mm commencing from formed ground level

including back filling with selected earth.

Disposal

Surface water.

Pipes

UPVC pipe type 600

In trenches

63mm diameter pipe.

90mm diameter pipe.

110mm diameter pipe.

3W/01

12

m

3W/02

14

m

3W/03

Item

3W/04

6.0

m

3W/05 6.0 m

3W/06 14 m

TO COLLECTION

Page 137 of 170

Page 138: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/37

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

Manholes and Gulleys

3W/07 Gulley type G.T. size 450x450x600mm deep.

(Internally) consisting of 50mm thick screed (Gr

10), 75mm thick reinforced concrete base (Gr

20), 100mm thick reinforced concrete wall (Gr

20), 50mm thick reinforced concrete cover slab

with concrete pad (Gr 20), mass concrete infill,

20mm thick cement and sand (1:3) smooth

coloured cement rendering on all exposed

faces and including necessary excavation and

earth work as per detail drawing.

1 nr

3W/08 Manhole type WMH size 450x450x600mm

(internally) consisting of 50mm thick (Gr 15)

screed, 75mm thick reinforced concrete base

(Gr 20), 100mm thick reinforced concrete walls

(Gr 20), 75mm thick reinforced concrete cover

slab with concrete pad, 20mm thick cement

and sand (1:3) smooth coloured cement

rendering on all exposed faces and including

necessary excavation and earth work as per

detail drawing.

2 nr

3W/09 Manhole type SMH1 size 600x600x600mm

(internally) consisting of 50mm thick screed

(Gr 10), 75mm thick reinforced concrete base

(Gr 20), 100mm thick reinforced concrete walls

(Gr 20), 75mm thick reinforced concrete cover

slab with concrete pad(Gr 20), mass concrete

infill, 20mm thick cement and sand (1:3)

smooth coloured cement rendering on all

exposed faces and including necessary

excavation and earth work as per detail

drawing.

3 nr

Septic tank

3W/10 Allow for construction of septic tank D type size

5.40x1.50x1.95 m deep (internally) all as per

detail drawing and complete to working order.

1 nr

TO COLLECTION

Page 138 of 170

Page 139: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing

Building for Ocean University of Sri Lanka at Boossa -

Phase I of Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/38

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

3W/11

Soakage pit

Allow for construction of soakage pit type D

size 1.5x1.5x3.575 deep (internally) all as per

detail drawing and complete to working order.

2

nr

TO COLLECTION

DRAINAGE SYSTEMS

COLLECTION

Page No. 3/36

Page No. 3/37

Page No. 3/38

CARRIED TO BILL NO. 3 SUMMARY

Page 139 of 170

Page 140: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

Stage III

BILL OF

QUANTITIES

Building Works

BILL

NO.

3

SPEC. DIV.

NO.

PAGE NO.

3/39

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

BILL NO. 03

3D/- EXCAVATION AND EARTHWORK; PAGE 3/2

3F/- CONCRETE WORKS; PAGE 3/9

3G/- MASONARY WORKS; PAGE 3/10

3H/- WATER PROOFING; PAGE 3/11

3J/- STRUCTURAL METAL WORK FOR STEEL IN

FRAMED STRUCTURE; PAGE 3/14

3K/- METAL WORK; PAGE 3/17

3L/- WOOD WORK; PAGE 3/18

3P/- ROOF COVERING/ ROOF PLUMBING;

PAGE 3/19

3Q/- PLUMBING/ SANITARY

INSTALLATIONS; PAGE 3/23

3S/- ELECTRICAL INSTALLATION; PAGE 3/31

3T/- FLOOR/ WALL/ CEILING FINISHES;

PAGE 3/34

3V/- PAINTING; PAGE 3/35

3W/- DRAINAGE SYSTEM; PAGE 3/38

CARRIED TO GENERAL SUMMARY

Page 140 of 170

Page 141: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Construction of Proposed Additions and Alterations to an

Existing Building for Ocean University of Sri Lanka at

Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Specialized

Works

BILL

NO.

4

SPEC. DIV.

NO.

PAGE NO.

4/1

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

4A/

BILL NO. 04

SPLIT TYPE AIR CONDITIONING SYSTEM

Contractor shall inspect the site conditions

before submitting their quote.

This is supply installtion & commissioning

contract, inclusive of all required accessories &

PVC trunking for power cord & refrigerant

piping.

The rate shall include for supply, installation,

commissioning & comprehensive maintenance

during the defect liability period of one year

The rate shall include for providing insurance

during handling, transporting, storing &

installation until handover

The rate shall include for all temporary works

such as scaffolding and electricity supply etc

The rate shall include for activities related to

builder work (Civil, Mechanical & Electrical) in

order to complete the electrical works

The rate shall include internal wiring in order to

complete the electrical works

Power supply available : 400V AC/230 V AC, 50

Hz

Refrigerent Shall be R410A/R32 and

PANASONIC, DIAKIN or equivalent. (Will be

decided by the consultant.)

EER, Equipment Gurantees, free maintenance

period and post warranty maintenance charges

shall be mentioned for evaluation.

Printed Catalogues of the Equipment and wiring

accessories,highlighing the offered items shall

be submitted for evaluation.Photocopies are not

acceptable.

Page 141 of 170

Page 142: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Construction of Proposed Additions and Alterations to an

Existing Building for Ocean University of Sri Lanka at

Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Specialized

Works

BILL

NO.

4

SPEC. DIV.

NO.

PAGE NO.

4/2

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE TOTAL PRICE

RUPEES

4A/01

4A/02

4A/03

Waranty for Equipment and for the Installation

should be submitted in written form

Ground Floor

Supply & Installation of wall mounted inverter type

single phase split air conditioners having nominal

cooling capacity 24,000 Btu/hr each complete with

refrigerant pipes, insulation, wiring, drain pipes,

mounting brackets and other necessary ancillary

items. (for Class Room).Testing and

commissioning included.

Supply & Installation of wall mounted inverter type

single phase split air conditioners having nominal

cooling capacity 12,000 Btu/hr each complete with

refrigerant pipes, insulation, wiring, drain pipes,

mounting brackets and other necessary ancillary

items. (for Instructors Room).Testing and

commissioning included.

DOL starters for single phase AC units

3

1

4

nr

nr

nr

CARRIED TO BILL NO. 4 SUMMARY

Page 142 of 170

Page 143: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Construction of Proposed Additions and Alterations to an

Existing Building for Ocean University of Sri Lanka at

Boossa - Phase I of Stage III

BILL OF

QUANTITIES

Specialized

Works

BILL

NO.

4

SPEC. DIV.

NO.

PAGE NO.

4/3

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

4B/

4B/01

4B/02

4B/03

4B/04

FIRE PROTECTION SYSTEM

Note:

This is a supply, install and commissioning

contract.

Contractor shall investigate the site conditions

before submitting the Bid.

For the full description of scope, materials and

workmanship refer Technical Specification.

All materials, equipments, wiring and

workmanship shall confirm to local codes of

specifications, B.S Standards, ICTAD and local

authority fire requirements.

Contractor shall obtain sample material

approvals for all the items used before fixing,

from the consultant & Fire service department

Contractor shall propose shop drawings/conduit

layout drawings and obtain approvals from the

consultant, before commencing the installation.

Original print catalogues shall be submitted.

Warranties for fittings shall be submitted.

PORTABLE FIRE EXTINGUISHER

9 liter capacity water fire extinguisher complete

with fixing accessories

Stage 04 Considered area

3 Kg capacity carbon dioxide fire extinguishers

complete with fixing accessories.

Stage 04 Considered area

Fire point plastic indicator plate at the location of fire

extinguisher

Exis signs

3

3

6

2

nr

nr

nr

nr

CARRIED TO BILL NO. 4 SUMMARY

Page 143 of 170

Page 144: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME BILL OF

QUANTITIES

BILL

NO.

SPEC. DIV.

NO.

PAGE NO.

Construction of Proposed Additions and Alterations to

an Existing Building for Ocean University of Sri Lanka

at Boossa - Phase I of Stage III

Specialized

Works 4 4/4

ITEM

REF.

ITEM DESCRIPTION QTY. UNIT UNIT RATE TOTAL PRICE

RUPEES

BILL NO. 04

4A/- SPLIT TYPE AIR CONDITIONING SYSTEM;

PAGE 4/2

4B/- FIRE PROTECTION SYSTEM; PAGE 4/3

CARRIED TO GENERAL SUMMARY

Page 144 of 170

Page 145: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building for

Ocean University of Sri Lanka at Boossa - Phase I of Stage

III

BILL OF

QUANTITIES

Provisional

Sums

BILL

NO.

5

SPEC.

DIV. NO.

PAGE NO.

5/1

ITEM

REF.

ITEM DESCRIPTION

QTY.

UNIT

UNIT RATE

TOTAL PRICE

RUPEES

5A/-

5A/01

BILL NO. 05

PROVISIONAL SUMS

Note:-

The following provisional sums are to be used as

directed by the Engineer and deducted in whole

or part if not ordered to be used.

Allow the provisional sum of Rupees Two Million (Rs.

2,000,000.00) for installation of gas system.

PS

2,000,000.00

CARRIED TO GENERAL SUMMARY

Page 145 of 170

Page 146: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING BUILDING FOR OCEAN

UNIVERSITY OF SRI LANKA AT BOOSSA - PHASE I OF STAGE III

GENERAL SUMMARY

BILL NO. 01 .. PRELIMINARIES .. Rs.

BILL NO. 02 .. DEMOLISION WORKS .. Rs.

BILL NO. 03 .. BUILDING WORKS .. Rs.

BILL NO. 04 .. SPECIALIZED WORKS .. Rs.

SUB TOTAL - 1 .. Rs.

DdT : Discount - if any .. Rs.

SUB TOTAL - 2 .. Rs.

BILL NO. 05 .. PROVISIONAL SUMS .. Rs. 2,000,000.00

BID SUM .. Rs.

Carried to Form of Bid

Bid Sum in Words :

…………..……...………………………………………………………………………………………………………

…………..……...………………………………………………………………………………………………………

…………..……...………………………………………………………………………………………………………

VAT 8% of Rs. .................................................................................................... Rs.

VAT Registration No : ……………………………..

Page 146 of 170

Page 147: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

BILL OF

QUANTITIES

Day Works

BILL

NO.

SPEC. DIV.

NO.

PAGE NO.

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

DAY WORKS

Day work definition

The Day Work is defined as being additional or

extra work not envisaged at the time of

Bidding, which is carried out pursuant to

instructions given by the Engineer under the

Contract and further, in the opinion of the

Engineer, cannot be adequately measured or

valued in any other way. The definition applies

solely to Day Work carried out under and

incidential to the Contractor. It does not cover.

- Any work carried out as a separate contract. - Day Work ordered to be carried out after the

date of commencement of the period of

maintenance.

All day work rates shall be inclusive of profit

margin of 16%.

LABOUR

The Contractor shall state under Item 1 to 9

below, the rate per hour irrespective of Public

Holidays, Week-ends, Poya days etc. required

for work ordered to be executed as Day Works

at the site of the works.

Day Work rates quoted below shall also cover

all the expenses of the Contractor and

particularly his overhead expenses, profits and

supervision, repairing and maintaining the

tools necessary to each class of workman.

Page 147 of 170

Page 148: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

BILL OF

QUANTITIES

Day Works

BILL

NO.

SPEC. DIV.

NO.

PAGE NO.

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

1

2

3

4

5

6

7

8

9

10

11

Carpenters.

Masons.

Plumber.

Painter.

Electrician.

Fabricator (aluminium extrusions)

Barbender

Welder

Steel fixer

Unskilled Worker.

Other skilled worker (general)

hour

hour

hour

hour

hour

hour

hour

hour

hour

hour

hour

Page 148 of 170

Page 149: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

BILL OF

QUANTITIES

Day Works

BILL

NO.

SPEC. DIV.

NO.

PAGE NO.

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

12

13

14

15

16

17

18

19

MATERIALS

The Contractor shall state under Item 10 to 16

below, the rates of materials ordered to be

used for Day Works at the site of the works.

The rates shall cover all the expenses of the

Contractor such as loading, delivery to site,

unloading, storing and protecting and

Contractor's profit overheads.

Portland Cement.

Sand.

Bricks

Aluminium extrusions.

Zink Aluminium Sheet (0.47mm)

Gypsum board

Mild steel or tor steel reinforcement.

Structural steel

bags

m3

nr

kg

m2

m2

t

t

Page 149 of 170

Page 150: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

PROJECT NAME

Proposed Additions and Alterations to an Existing Building

for Ocean University of Sri Lanka at Boossa - Phase I of

BILL OF

QUANTITIES

Day Works

BILL

NO.

SPEC. DIV.

NO.

PAGE NO.

ITEM

REF. ITEM DESCRIPTION QTY. UNIT UNIT RATE

TOTAL PRICE

RUPEES

20

21

22

23

24

25

26

27

28

PLANT AND EQUIPMENT

The Contractor shall state under Item 17 to 25

below, the rate per hour for use of plant in

good working condition and include for the

cost of fuel, lubricants, transport to and from

site, wages and allowances of the operator.

Contractor's overheads and profit and any

other expenses and charges.

Planning set of any type and any drive

Hand Pump

Motor Lorry 5 ton

Hoist 1/2 tons

Loader

Hammer Drill

Oxyacetylene welding set

Electrical welding set

Air compressor

hour

hour

hour

hour

hour

hour

hour

hour

hour

Page 150 of 170

Page 151: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Section – 8

Drawings

Page 151 of 170

Page 152: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

List of Drawings

Architectural Drawings

Structural Drawings

Page 152 of 170

Page 153: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

EXISTING DRAIN

GROUND FLOOR PLAN

WALK WAY

CAFETARIA

10075

STAFF

W1

D6

1615

A

A

W1

D1

LIFESAVING

UNIT

AREA - 518 Sqm

1750

100

1750

UP

REST

CLASS ROOM 01

2520

FEMAIL

TOI

MALE

TOI

D4 D4

SCUBA

DIVING UNIT

110.4 sqm

40. sqm

55.3 sqm

93.3 sqm

16.3 sqm

F1 F1F1 F1

W1W1W1

D4D4

D2

D3

D3

D3

D3

D3

D3

D3

W3

W1 W1

D5

W1

W1W1

W1

INSTRUCTOR

ROOM

W2

D5

3600

D5

D5

STORE

ROOM

D6

2805

1800

1195

1500

1000

1500

10075

8295

2910

2255

2890

8900

11895

1500

4225

1500

5835

8900

900

8900

W1

W1W1

D1D7

D2

8875

2465

3000

SERVERY

STAGE 04

STAGE 01

Concrete

work top

concrete work

top &

ceramic lab

sinks

3030 740

2290 3030 3030 3030

2010

4780

1800

A

B

C

D

G

20602800

1110

4560

E

F

1500

4230

1010

900mm high

work top

900mm high

Al.partition &

cladding sheets

D5

1 23

4 56

7 98

3000

62.4 sqm

600

LS

G

G

G

G

LS

LS

LS

G

G

G

G

Movable

working

Table -1

Movable

working

Table -2

Movable

working

Table -3

Movable

working

Table -4

AQUICULTURE

LAB

5835

concrete

work top &

ceramic

lab sinks

2000

concrete work

top &

ceramic lab

sinks

2000

D1

W1

575

3 NOS OF

TAPS WITH

WASHING

TROUGH

PHASE 01- GROUND FLOOR

PHASE 02- UPPER FLOOR

B

B

6065

6060

6060 6060

3190

21125

5960

3190

2800

EXISTING DRAIN

EXISTING DRAIN

EXISTING SEPTIC

TANK

EXISTING SOAKAGE

PIT

GROUND FLOOR PLAN

6030

6060

UP

2695

UP

WALK WAY

ENTRANCE

CAFETARIA

LABS

ROOM

ROOM

ROOM

2690

8910

2815

2795

2740

6085

10075

3170

STORE

STAFF

D2

D2

D2

D2

D2

D1

D1

2055 1880 2130 1305

1500

1505

1725

2735

3030

W1

D6

FG2

1615

A

A

±0

-400

±0

W1

D1

LIFESAVING

UNIT

RD1

RD2

PROPOSED

ROLLER DOOR

1750

100

1750

UP

REST

CLASS ROOM 01

2520

FEMAIL

TOI

MALE

TOI

D4 D4

SCUBA

DIVING UNIT

110.4 sqm

40. sqm

55.3 sqm

93.3 sqm

16.3 sqm

384 sqm

F1 F1 F1 F1

W1W1W1W1

FG2

FG2

FG2

FG2

D4D4

D2

D3

D3

D3

D3

D3

D3

D3

W3

W1 W1

D5

W1

W1W1

W1W1W1W1

INSTRUCTOR

ROOM

W2

D5

3600

D5

D5

STORE

ROOM

D6

2805

1800

1195

1500

1000

1500

10075

8295

2910

2255

2890

8900

11895

1500

4225

1500

5835

8900

900

8900

3000

W1

W1W1

D1D7

STAGE 03

D2

8875

2465

3000

SERVERY

STAGE 04

STAGE 01

Concrete

work top

concrete work

top &

ceramic lab

sinks

3030 740

2290 3030 3030 3030

2010

4780

1800

A

B

C

D

G

20602800

1110

4560

E

F

1500

4230

1010

900mm high

work top

900mm high

Al.partition &

cladding sheets

D5

1 2 3 4 5 6 7 98

3000

62.4 sqm

600

LS

G

G

G

G

LS

LS

LS

G

G

G

G

Movable

working

Table -1

Movable

working

Table -2

Movable

working

Table -3

Movable

working

Table -4

AQUICULTURE

LAB

5835

concrete

work top &

ceramic

lab sinks

2000

concrete work

top &

ceramic lab

sinks

2000

D1

W1

575

3 NOS OF

TAPS WITH

WASHING

TROUGH

STAGE 01 & 02

STAGE 04

PHASE 01- GROUND FLOOR

PHASE 02- UPPER FLOOR

B

B

TYPESIZE DESCRIPTION

D11200X2100

SCHEDULE OF DOORS & WINDOWS

D2

900X2100

POWDER COATED ALUMINIUM FRAME DOUBLE SASH DOOR WITH 4mm

CLADDING SHEETS

D3

750X2100

D4

D5

D6

D7

W11800X1500

POWDER COATED ALUMINIUM FRAME GLAZED WINDOW WITH FIXED

GLASS ABOVE

POWDER COATED ALUMINIUM FRAME SINGLE SASH DOOR WITH 4mm

CLADDING SHEETS

POWDER COATED ALUMINIUM FRAME SINGLE SASH DOOR WITH 4mm

CLADDING SHEETS

1200X2100

POWDER COATED ALUMINIUM FRAME DOUBLE SASH DOOR WITH 4mm

CLADDING SHEETS & GLAZE PANEL

900X2100

POWDER COATED ALUMINIUM FRAME SINGLE SASH DOOR WITH 4mm

CLADDING SHEETS & GLAZE PANEL

900X2100

POWDER COATED ALUMINIUM FRAME SINGLE SASH DOOR WITH 4mm

CLADDING SHEETS

1000X2100

POWDER COATED ALUMINIUM FRAME DOUBLE SASH DOOR WITH GLAZE

PANELS (partition)

D8750X1350

POWDER COATED ALUMINIUM FRAME SINGLE SASH GATE WITH CLADDING

PANELS(partition)

(3 bays 2 panels sliding -sill height 1050 mm)

W2900X600

POWDER COATED ALUMINIUM FRAME GLAZED WINDOW WITH FIXED

GLASS ABOVE

(2 bays 1 panels sliding -sill height 1050 mm)

W3

POWDER COATED ALUMINIUM FRAME GLAZED WINDOW WITH FIXED

GLASS ABOVE

(2 bays 1 panels sliding -sill height 1050 mm)

1200X1500

FG2 600 X1050

FG3 900 X 600

F1600 X 600

POWDER COATED ALUMINIUM FRAME FIXED GLASS

(sill height 2050-existing beam top)

POWDER COATED ALUMINIUM FRAME FIXED GLASS (sill height 1050mm)

POWDER COATED ALUMINIUM FRAME SLIDING FANLIGHT (sill height 1500mm)

SIZE DESCRIPTION

Floor - Toilets

SCHEDULE OF FINISHES

FLOOR - Workshops

300mmx600mm SEMI ROUGH HOMOGENOUS PORCELAIN FLOOR TILES

POWER TROWEL FLOOR

600mmx600mm PAINTED ASBESTOS CEILING WITH TIMBER FRAMEWORK

FLOOR - Other areas

600mmx600mm SEMI GLAZE HOMOGENOUS PORCELAIN FLOOR TILES

WALLS - Toilets

300mmx600mm SEMI GLAZE CLAY TILES

WALLS - Workshops

NEAT CEMENT RENDERED UP TO 1500mm WITH PRIMER &

WASHABLE GLOSS PAINT

WALLS - Other areas

CEMENT SAND PLASTER FINISH WITH WALL PUTTY & WALL

FILLER ,& TWO COATS OF EMULSION/ENEMAL PAINT

CEILING -

CORRUGATED ASBESTOS CEILING

ROOF -

CLASS 01 TIMBER RAILING

HAND RAILS -

PLUMBER OR EQUIVALENT

BATHROOM Accessories -

ROCELL

BATHROOM FITTINGS -

CIC - EXTERNAL 5 COATS SYSTEM

PAINTS - External -

PAINTS - Internal -

CIC - EMULSION PAINTS

GUTTERS & DOWN PIPES

HEAVY DUTY P.V.C

WORK TOPS

CONCRETE WORK TOPS TO FINISH WITH 600mmX600mm

CHEMICAL RESISTANT PORCELAIN TILES

1.CONCRETE WORK TOPS,SIDES

& SUPPORTING WALLS

TO BE FINISHED WITH 600mm X 600mm

HEAVY DUTY, CHEMICAL RESISTANT

GLAZE FLOOR TILES

2. WALLS ALONG THE CONCRETE WORK

TOPS TO BE FINISHED (600MM ABOVE

THE WORK TOPS) WITH

THE SIMILAR TILES.

3.FOR THE OTHER FINISHES

IN SIDE THE LAB,

REFER SCHEDULE OF FINISHES.

NOTES-

4. REFER ELECTRICAL DRAWINGS FOR

THE SOCKET

OUTLETS ABOVE THE WORK TOPS

5. MOVEABLE TABLES ARE NOT

INCLUDED IN THE PHASE 01-

STAGE 4 BUT GAS LINES WILL

BE PROVIDED TO THE INDICATED

POINTS.

( REF GAS LINE LAYOUT DRAWING

6. LAB SINKS- 19mm X 26mm, CHEMICAL

RESISTANT PORCELAIN LAB SINKS

(REF SPECIFICATIONS

IN THE CONTRACT DOCUMENT)

G - GAS POINT

LS - LAB SINK

CPU NO & PATH :CPU704/G/2019 PROJECTS/OCEAN BOOSSA

GROUND FLOOR PLAN,

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

P.O.BOX 194, COLOMBO - 02

ARCHITECT:

DOA :

CHECKED :

CHIEF ARCHITECT:

PROJECT / SENIOR

ARCHITECT :

PROPOSED ADDITION & ALTERNATIONS TO THE

EXISTING BUILDING

FOR OCEAN UNIVERSITY OF SRI LANKA

AT BOOSSA.- PHASE 01 OF STAGE 03

DRG. NO -[2021-13]/A/01

CAD : E.A.N. SHAMIKA / SUDARSHANA

SCALE : 1:100DATE:03-06-2021

KEY PLAN

Page 153 of 170

Page 154: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

EXISTING DRAIN

W1

20602800

D5

62.4 sqm

600

1800

100

465

1275

2500

1800

1120

745

200

G

LS

4585

G

1200

1110

750

1660

1800

1390

1390

AQUICULTURE LAB

5835

CONCRETE WORK TOP &

CERAMIC LAB SINKS

1110

1580

MOVABLE WORKING TABLE 4

150

PROPOSED COLUMNS

PROPOSED COLUMNS

200

200

200

CONCRETE WORK TOP

TO BE FINISHED WITH 600mm X 600mm

HEAVY DUTY, CHEMICAL RESISTANT

GLAZED FLOOR TILES

10080

LS

MOVABLE WORKING TABLE3

MOVABLE WORKING TABLE 2

MOVABLE WORKING TABLE 1

W1W1

D6

G

LS

G

LS

G

LS

G

LS

G

LS

G

LS

CONCRETE WORK TOP

TO BE FINISHED WITH 600mm X 600mm

HEAVY DUTY, CHEMICAL RESISTANT

GLAZED FLOOR TILES

PLAN

Scale: 1 : 50

'A'

1200

600X600mm SEMI GLAZED

HOMOGENEOUS PORCELAIN

FLOOR TILES

08 09

A

C

TYPICAL SECTION ( Through work top)

Scale: 1 : 20

F.F.L. - GROUND FLOOR

FOUNDATION AS PER STRUCTURAL

ENGINEER'S DETAIL

850

1

1

4

" BOTTLE TRAP EXTENSION PIPE TO WALL

"L" IRON EMBEDDED TO BRICK WALL

REFER ENGINEER DETAIL

75

LAB SINK- Refer specification

650

'X'

SWIVEL SWAN NECK TAP - Refer specification

600

CONCRETE WORK TOP

TO BE FINISHED WITH 600mm X 600mm

HEAVY DUTY, CHEMICAL RESISTANT

GLAZED FLOOR TILES

3000

PROPOSED GAS LINE

ARM FIXED TO THE WALL- TO SUPPORT GAS LINE

GAS OUT LET POINT

600X600mm SEMI GLAZED HOMOGENEOUS PORCELAIN

TILLED FLOOR & SKIRTING

200

100

SUPPORTING WALLS

1.CONCRETE WORK TOPS,SIDES & SUPPORTING WALLS TO BE

FINISHED WITH 600mmX600mm HEAVY DUTY CHEMICAL RESISTANT

GLAZED FLOOR TILES.

2. WALLS ALONG THE CONCRETE WORK TOPS TO BE FINISHED

(600mm ABOVE THE WORK TOPS) WITH THE SIMILAR TILES

3.FOR THE OTHER FINISHES IN SIDE THE LAB - REFER

SCHEDULE OF FINISHES

NOTES-

4. REFER ELECTRICAL DRAWINGS FOR THE SOCKET OUTLETS

ABOVE THE WORK TOPS

5. MOVEABLE TABLES ARE NOT INCLUDED IN THE PHASE 01-

STAGE 4 BUT GAS LINES WILL BE PROVIDED TO THE

INDICATED POINTS.(REFER GAS LINE LAY OUT DRAWING)

6. LAB SINKS-600mmx460mmx260mm

CHEMICAL RESISTANT PORCELAIN LAB SINKS

(REF SPECIFICATIONS IN THE CONTRACT DOCUMENT

G - GAS POINT

LS - LAB SINK

DETAIL AT "X"

Scale: 1 : 10

75

50

Rcc SLAB

CEMENT PLASTER

CONCRETE WORK TOP

TO BE FINISHED WITH 600mm X 600mm

HEAVY DUTY, CHEMICAL RESISTANT

GLAZED FLOOR TILES

F.F.L.

800

600

600

400

600x600mm GLAZED WALL TILES

UP TO 600mm HEIGHT

PLASTERED BRICK WALL

PVC ARM

DETAIL OF WASHING TROUGH

( AT CANTEEN AREA)

4560

03 NOS OF TAPS WITH WASHING TROUGH

FINISHED WITH 600x600mm

GLAZED WALL TILES

600

2700

450

800

800

450

PLAN OF WASHING TROUGH

( AT CANTEEN AREA)

REFER STRUCTURAL DRAWING FOR THE DETAIL

REFER STRUCTURAL DRAWING FOR THE DETAIL

E

F

600

100

18001275 7451580150

CONCRETE WORK TOPS,SIDES

& SUPPORTING WALLS

TO BE FINISHED WITH 600mm X 600mm

HEAVY DUTY, CHEMICAL RESISTANT

GLAZE FLOOR TILES

600

WALLS ALONG THE CONCRETE WORK

TOPS TO BE FINISHED (600mm ABOVE THE WORK TOP)

WITH THE SIMILAR TILES

SWIVEL SWAN NECK TAP - Refer specification

FOUNDATION AS PER

STRUCTURAL

ENGINEER'S DETAIL

F.F.L. - GROUND FLOOR

850

ELEVATION - SIDE 'A'

Scale: 1 : 25

100

600X600mm SEMI GLAZED

HOMOGENEOUS PORCELAIN

TILLED FLOOR & SKIRTING

PROPOSED GAS LINE

SLAB SOFIT

TO GAS SUPPLY POINT

A

C

CPU NO & PATH :CPU705/F/Arc. Sudharshana/ Boossa/lab detail

LAB DETAILS & WASHING TROUGH DETAIL AT CANTEEN AREA

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

P.O.BOX 194, COLOMBO - 02

ARCHITECT:

DOA :

CHECKED :

CHIEF ARCHITECT:

PROJECT / SENIOR

ARCHITECT :

PROPOSED ADDITION & ALTERNATIONS TO THE

EXISTING BUILDING

FOR OCEAN UNIVERSITY OF SRI LANKA

AT BOOSSA.- PHASE 01 OF STAGE 03

DRG. NO -[2021-13]/A/06

CAD : HYACINTH

SCALE : 1:50,1:20DATE:04-06-2021

THIS DRAWING IS TO BE READ IN CONJUNCTION WITH

STRUCTURAL DESIGN DRAWINGS & OTHER RESPECTIVE

ARCHITECTURAL DRAWINGS.

REFERENCE DRGs.

PR

OD

UC

ED

B

Y A

N A

UT

OD

ES

K E

DU

CA

TIO

NA

L P

RO

DU

CT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PR

OD

UC

ED

B

Y A

N A

UT

OD

ES

K E

DU

CA

TIO

NA

L P

RO

DU

CT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

Page 154 of 170

Page 155: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

NOTES:

02.

01.

10.

03.

04.

05.

*

06.

07.

08.

09.

ELEVATION

2000

1000 1000

2100

eq

eq

eq

ELEVATION

900

2100

eq

eq

eq

ELEVATION

750

2100

eq

eq

eq

ELEVATION

2000

1000 1000

2100

ELEVATION

900

ELEVATION

900

PLAN OF D1

2000

1000 1000

PLAN OF D4

2000

1000 1000900

PLAN OF D2

750

PLAN OF D3

900

PLAN OF D5

900

PLAN OF D6

DOOR CLOSER

DC

DOOR CLOSER

DC

ALUMINUM HINGES ALUMINUM HINGES

POWDER COATED

ALU. FRAME

{1.6mm Tk. 100mm

sections}

150mm HIGH

ALU.HANDLE

DOOR LOCK

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

F.F.L.

CD

CD

CD

CD

CD

CD

CD

CD

CD

CD

CD

CD

CG CG

CG

CD

CD

CD

F.F.L. F.F.L. F.F.L.

F.F.L. F.F.L.

DOOR CLOSER DOOR CLOSER

DOOR CLOSER

DOOR CLOSER

150mm HIGH

ALU.HANDLE

150mm HIGH

ALU.HANDLE

DOOR LOCK

DOOR LOCK

DOOR LOCK

ALUMINUM HINGES

5mm Tk. CLEAR GLASS

WITH DEFUSE STICKER

CLEAR STRIPS

150mm HIGH

ALU.HANDLE

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

OUT SIDE

OUT SIDE

5mm Tk. CLEAR GLASS

2100

PLAN OF W1

1800

F.F.L.

1500

2550

2100

1050

FG FG FG

CG CG CG

ELEVATION

POWDER COATED

ALU. FRAME

03 BAY

ALU. SLIDING PANELS

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

5mm Tk. CLEAR GLASS

[CG] [CG] [CG]

PLAN OF W2

900

F.F.L.

ELEVATION

POWDER COATED

ALU. FRAME

5mm Tk. CLEAR GLASS

CG CG

600

1050

1650

EQ EQ

F.F.L.

1500

2550

2100

1050

FG FG

CG CG

ELEVATION

POWDER COATED

ALU. FRAME

[CG] [CG]

PLAN OF W3

1200

EQ EQ

F.F.L.

ELEVATION

PLAN OF FG2

600

1050

1050

2100

FG

[CG]

EQ

EQ

EQ

PLAN OF FL

F.F.L.

ELEVATION

POWDER COATED

ALU. FRAME

5mm Tk. CLEAR GLASS

CG CG

600

1500

2100

EQ EQ

POWDER COATED

ALU. FRAME

5mm Tk.

CLEAR GLASS

ELEVATION

PLAN OF FG3

900

2050

600

FG

[CG]

Existing Beam

POWDER COATED

ALU. FRAME

{ 1.6mm Tk. 100mm

sections}

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

POWDER COATED

ALU. FRAME

{ 1.6mm Tk. 100mm

sections}

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

POWDER COATED

ALU. FRAME

{ 1.6mm Tk. 100mm

sections}

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

POWDER COATED

ALU. FRAME

{1.6mm Tk. 100mm

sections}

DcDc

Dc Dc

OUT SIDE OUT SIDE

1000

CD CD

4mm Tk. DOUBLE

SIDE FINISHED

CLADDING BOARD

OUT SIDE OUT SIDE

OUT SIDE

OUT SIDE

POWDER COATED

ALU. FRAME

{1.6mm Tk. 100mm

sections}

POWDER COATED

ALU. FRAME

{1.6mm Tk. 100mm

sections}

POWDER COATED

ALU. FRAME

{1.6mm Tk. 100mm

sections}

2100

1000

1000

CG

CD

ELEVATION

1000

2100

F.F.L.

DOOR CLOSER

150mm HIGH

ALU.HANDLE

DOOR LOCK

ALUMINUM HINGES

Dc

1000

POWDER COATED

ALU. FRAME

{1.6mm Tk. 100mm

sections}

EQ EQ

eq

eq

eq

eq

eq

eq

CG CG

CG CG

CG CG

5mm Tk.

CLEAR GLASS

02 BAY ALU.

SLIDING PANELS

02 BAY ALU.

SLIDING PANELS

OUT SIDE OUT SIDE OUT SIDE OUT SIDE

POWDER COATED

ALU. FRAME

5mm Tk.

CLEAR GLASS

1000

PLAN OF D7

OUT SIDE

POWDER COATED

ALU. FRAME

{1.6mm Tk. 100mm

sections}

5mm Tk. CLEAR GLASS

5mm Tk. CLEAR GLASS

5mm Tk. CLEAR GLASS

POWDER COATED

ALU. FRAME

5mm Tk. CLEAR GLASS

POWDER COATED

ALU. FRAME

5mm Tk. CLEAR GLASS

POWDER COATED

ALU. FRAME

5mm Tk. CLEAR GLASS

POWDER COATED

ALU. FRAME

5mm Tk.

CLEAR GLASS

5mm Tk.

CLEAR GLASS

750

TYPESIZE DESCRIPTION

D12000X2100

SCHEDULE OF DOORS & WINDOWS

D2 900X2100

POWDER COATED ALUMINIUM FRAME DOUBLE SASH DOOR WITH 4mm CLADDING SHEETS

D3 750x2100

D4

D5

D6

D7

W11800X1500

POWDER COATED ALUMINUM FRAME GLAZED SLIDING (03 BAY SLIDING)

WINDOW WITH FIXED GLASS ABOVE-sill height 1050 mm

POWDER COATED ALUMINIUM FRAME SINGLE SASH DOOR WITH 4mm CLADDING SHEETS

POWDER COATED ALUMINIUM FRAME SINGLE SASH DOOR WITH 4mm CLADDING SHEETS

2000X2100

POWDER COATED ALUMINUM FRAME DOUBLE SASH DOOR WITH

4mm CLADDING & GLAZED PANELS

900X2100

POWDER COATED ALUMINUM FRAME SINGLE SASH DOOR WITH

4mm CLADDING & GLAZED PANELS

900X2100

POWDER COATED ALUMINUM FRAME SINGLE SASH DOOR WITH 4mm CLADDING SHEETS

1000X2100

POWDER COATED ALUMINUM FRAME DOUBLE SASH GLAZED DOOR

D8

750X1350

POWDER COATED ALUMINUM FRAME SINGLE SASH GATE WITH CLADDING PANELS(partition)

W2900X600

POWDER COATED ALUMINUM FRAME GLAZED SLIDING (02 BAY SLIDING) WINDOW

-sill height 1050 mm

W3

POWDER COATED ALUMINUM FRAME GLAZED SLIDING(02 BAY SLIDING) WINDOW

WITH FIXED GLASS ABOVE

- sill height 1050 mm

1200X1500

FG1 -------

ONLY IN STAGE 2

FG2 600 x 1050

FG3 900 X 600

FL750 x 600

POWDER COATED ALUMINUM FRAME FIXED GLASS (sill height 2050-existing beam top)

POWDER COATED ALUMINUM FRAME FIXED GLASS (sill height 1050)

POWDER COATED ALUMINUM FRAME SLIDING (02 BAY SLIDING FANLIGHT (sill height 1500)

THIS DRAWING IS TO BE READ IN CONJUNCTION WITH

STRUCTURAL DESIGN DRAWINGS & OTHER RESPECTIVE

ARCHITECTURAL DRAWINGS.

REFERENCE DRGs.

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

CAD : HYACINTH

ARCHITECT:

DOA :

SCALE : 1:25

CHECKED :

DATE:31-05-2021

CHIEF ARCHITECT:

DETAILS OF DOORS &WINDOWS

SENIOR / PROJECT

ARCHITECT :

PROPOSED ADDITIONS & ALTERATION TO AN

EXISTING BUILDING FOR OCEAN UNIVERSITY OF

SRI LANKA AT BOOSSA - PHASE 1 OF STAGE 03

DRG NO: (2021-13)A/03

PR

OD

UC

ED

B

Y A

N A

UT

OD

ES

K E

DU

CA

TIO

NA

L P

RO

DU

CT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PR

OD

UC

ED

B

Y A

N A

UT

OD

ES

K E

DU

CA

TIO

NA

L P

RO

DU

CT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

Page 155 of 170

Page 156: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

ELEVATION TO GALLED ROAD OF E1

STAGE 01

STAGE 02

STAGE 02

STAG

E 01

STAGE 03

PHASE 02

STAGE 03

PHASE 01

STAGE 04

STAGE 04

REAR ELEVATION OF E2

STAGE 01

STAGE 02

STAGE 02

STAGE 03

PHASE 02

STAGE 03

PHASE 01

STAGE 04

STAGE 04

STAGE 01

ELEVATION TO NORTH OF E3

PROPOSED STEPS

T

O

G

A

L

L

E

R

O

A

D

R

O

A

D

R

O

A

D

T

O

R

A

I

L

W

A

Y

S

T

A

T

I

O

N

F

R

O

M

C

O

L

O

M

B

O

SCALE:-1:2000

SITE PLAN

16975

10255

8795

PROPOSED SEPTIC

TANK 50' AWAY FROM

ALL WELLS

PROPOSED SOAKAGE PIT

50' AWAY FROM ALL

WELLS

NOTE

WATER FROM WATER BOARD MAIN

5000

2

4

0

0

7

2

0

0

6000

MAIN ENTRANCE /EXIT

BUILDING TO

DEMOLISH

NOTE

EXISTING TEMPORARY GUARD ROOM TO DEMOLISH

14Nos PARKING SPACE

1No DESABLE PARKING SPACE

PROPOSED BUILDING

CPU NO & PATH :CPU704/G/2019 PROJECTS/OCEAN BOOSSA

ELEVATIONS

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

P.O.BOX 194, COLOMBO - 02

ARCHITECT:

DOA :

CHECKED :

CHIEF ARCHITECT:

PROJECT / SENIOR

ARCHITECT :

PROPOSED ADDITION & ALTERNATIONS TO THE

EXISTING BUILDING

FOR OCEAN UNIVERSITY OF SRI LANKA

AT BOOSSA.- PHASE 01 OF STAGE 03

DRG. NO -[2021-13]/A]/04

CAD : E.A.N. SHAMIKA

SCALE : 1:100

DATE:15-06-2021

KEY PLAN

E2

E3

E1

Page 156 of 170

Page 157: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

DETAILS AT "Y"

SCALE - 1:20

EXISTING WALL

PROPOSED BEAM

EXISTING BEAM

PROPOSED SLAB

50mmX100mm (FINISH)

TIMBER RAFTERS AT

600mm C/C

50mmX50mm (FINISH) TIMBER

BATTONS AS PER STRUCTURAL

DETAILS

ALUMINIUM "T"

SECTIONS AT 1200 C/C)

1200mm x 600mm PAINTED

ASBESTOS SLOPING CEILING

EXISTING WALL

PROPOSED BEAM

EXISTING BEAM

PROPOSED SLAB

50mmX100mm (FINISH) TIMBER

RAFTERS AT 1200mm C/C

50mmX50mm (FINISH)

TIMBER BATTONS AT

600mm C/C

FLAT ALUMINIUM

BEADING AT JOINTS

(BOTH WAY)

DETAILS AT "X"

SCALE - 1:20

PAINTED ASBESTOS FLAT CEILING

6070

4000

3300

SECTION B-B

300

1000

75mmX100mm TIMBER WALL

PLATE ON CONCRETE BEAM

50mmX125mm TIMBER PLATE

PROPERLY FIXED TO THE 1ST

FLOOR WALLS

50mmX100mm (FINISH)

TIMBER RAFTERS

PVC GUTTER (PROPOSED)

TIMBER VALANCE BOARD

CONCRETE BEAM

ASBESTOS ROOF COVERING

(23° ROOF PITCH)

ASBESTOS ROOF COVERING

(17° ROOF PITCH)

50mm THICK DOUBLE SIDED REINFORCED

ALUMINIUM FOIL INSULATION (THERMAL

AND SOUND) EQUIVALENT TO SISILATION

450 LAID OVER THE WIRE MESH REFER

STRUCTURAL DETAILS

STEEL TRUSS REFER STRUCTURAL DETAILS

1000

-400

3420

4285

4mm TK CLADDING BOARD

FACIA

600

P.V.C GUTTER

1000

EXISTING BEAM

PROPOSED BEAM

PROPOSED SLAB

1500

3570

±0

-400

300

100

75mmX100mm TIMBER

RAFTERS AT 1200mm c/c

50mmX50mm TIMBER

BATTONS

At 600 mm c/c

STAFFINSTRUCTOR

CAFETARIA

SEE DETAIL "X"

75mmX100mm TIMBER WALL

PLATE ON CONCRETE BEAM

1200mm x 600mm PAINTED

ASBESTOS SLOPING CEILING

3000

PAINTED ASBESTOS FLAT

CEILING

REFER STRUCTURAL

DETAILS

REFER FINISHING SCHEDULE

300

NOTE- FINISHES &THE

HANDRAIL TO BE COMPLETED

UNDER THE PHASE 2

REFER STRUCTURAL

DETAILS

NOTE- FLOOR FINISHES ON

THE SLABS TO BE COMPLETED

UNDER THE PHASE 2

NOTE- EXISTING ROOF TO BE REMOVED & NEW ROOF

TO CONSTRUCT UNDER THE PHASE 01

3630

SEE DETAIL "Y"

6070

4000

3000

3300

SECTION A-A

300

1000

75mmX100mm TIMBER WALL

PLATE ON CONCRETE BEAM

50mmX125mm TIMBER PLATE

PROPERLY FIXED TO THE 1ST

FLOOR WALLS

50mmX100mm (FINISH)

TIMBER RAFTERS

PVC GUTTER (PROPOSED)

TIMBER VALANCE BOARD

CONCRETE BEAM

ASBESTOS ROOF COVERING

(23° ROOF PITCH)

ASBESTOS ROOF COVERING

(17° ROOF PITCH)

50mm THICK DOUBLE SIDED REINFORCED

ALUMINIUM FOIL INSULATION (THERMAL

AND SOUND) EQUIVALENT TO SISILATION

450 LAID OVER THE WIRE MESH REFER

STRUCTURAL DETAILS

STEEL TRUSS REFER STRUCTURAL DETAILS

1000

WALK WAY

-400

3420

4285

4mm TK CLADDING BOARD

FACIA

75mmX100mm TIMBER WALL

PLATE ON CONCRETE BEAM

50mmX100mm TIMBER

RAFTERS AT 600mm c/c

50mmX50mm TIMBER

BATTONS

AS PER STRUCTURAL DETAILS

1200mm x 600mm PAINTED

ASBESTOS SLOPING CEILING

600

P.V.C GUTTER

1000

PROPOSED SLAB

1500

3570

±0

-400

300

100

LIFESAVING

UNIT

AQUICULTURE

LAB

SCALE 1:100

SEE DETAIL "X"

PAINTED ASBESTOS FLAT

CEILING

NOTE- EXISTING ROOF TO BE REMOVED & NEW ROOF

TO CONSTRUCT UNDER THE PHASE 01

REFER STRUCTURAL

DETAILS

REFER FINISHING SCHEDULE

EXISTING BEAM

PROPOSED BEAM

SEE DETAIL "Y"

6065 6060

6060 6060

3190

21125

5960

3190

2800

EXISTING DRAIN

EXISTING DRAIN

EXISTING SEPTIC

TANK

EXISTING SOAKAGE

PIT

GROUND FLOOR PLAN

6030

6060

UP

2695

UP

WALK WAY

ENTRANCE

CAFETARIA

LABS

ROOM

ROOM

ROOM

2690

8910

2815

2795

2740

6085

10075

3170

STORE

STAFF

D2

D2

D2

D2

D2

D1

D1

2055 1880 2130 1305

1500

1505

1725

2735

3030

W1

D6

FG2

1615

A

A

±0

-400

±0

W1

D1

LIFESAVING

UNIT

RD1

RD2

PROPOSED

ROLLER DOOR

1750

100

1750

UP

REST

CLASS ROOM 01

2520

FEMAIL

TOI

MALE

TOI

D4 D4

SCUBA

DIVING UNIT

110.4 sqm

40. sqm

55.3 sqm

93.3 sqm

16.3 sqm

384 sqm

F1 F1

F1 F1

W1W1W1W1

FG2

FG2

FG2

FG2

D4D4

D2

D3

D3

D3

D3

D3

D3

D3

W3

W1 W1

D5

W1

W1W1

W1W1W1W1

INSTRUCTOR

ROOM

W2

D5

3600

D5

D5

STORE

ROOM

D6

2805

1800

1195

1500

1000

1500

10075

8295

2910

2255

2890

8900

11895

1500

4225

1500

5835

8900

900

8900

3000

W1

W1W1

D1D7

STAGE 03

D2

8875

2465

3000

SERVERY

STAGE 04

STAGE 01

Concrete

work top

concrete work

top &

ceramic lab

sinks

3030 740 2290 3030 3030 3030

2010

4780

1800

A

B

C

D

G

20602800

1110

4560

E

F

1500

4230

1010

900mm high

work top

900mm high

Al.partition &

cladding sheets

D5

1

2

3 4 5 6 7

98

3000

62.4 sqm

600

LS

G

G

G

G

LS

LS

LS

G

G

G

G

Movable

working

Table -1

Movable

working

Table -2

Movable

working

Table -3

Movable

working

Table -4

AQUICULTURE

LAB

5835

concrete

work top &

ceramic

lab sinks

2000

concrete work

top &

ceramic lab

sinks

2000

D1

W1

575

3 NOS OF

TAPS WITH

WASHING

TROUGH

STAGE 01 & 02

STAGE 04

PHASE 01- GROUND FLOOR

PHASE 02- UPPER FLOOR

B

B

CPU NO & PATH :CPU704/G/2019 PROJECTS/OCEAN BOOSSA

SECTIONS

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

P.O.BOX 194, COLOMBO - 02

ARCHITECT:

DOA :

CHECKED :

CHIEF ARCHITECT:

PROJECT / SENIOR

ARCHITECT :

PROPOSED ADDITION & ALTERNATIONS TO THE

EXISTING BUILDING

FOR OCEAN UNIVERSITY OF SRI LANKA

AT BOOSSA.- PHASE 01 OF STAGE 03

DRG. NO -[2021-13]/A]/02

CAD : E.A.N. SHAMIKA

SCALE : 1:100,50DATE:10-06-2021

KEY PLAN

B

B

A

A

Page 157 of 170

Page 158: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

06 07

A

C

F1 F1 F1F1

D2

50mm

DROP

TILE START

POINT

D2

50mm

DROP

TILE START

POINT

25mm

DROP

D3

TILE START

POINT

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

25mm

DROP

D3

TILE START

POINT

25mm

DROP

D3

TILE START

POINT

25mm

DROP

D3

TILE START

POINT

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

W.C

B.S.

CP.

P.H.

300

300

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

CP.

CP.

SLOPE

S

L

O

P

E

SLOPE

S

L

O

P

E

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

S

L

O

P

E

S

L

O

P

E

S

L

O

P

E

+150

+100

+100

+100

+100

+75

+75

+75

+75

LADIES' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

LADIES' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

CP.

SLOPE

S

L

O

P

E

SLOPE

S

L

O

P

E

25mm

DROP

D3

TILE START

POINT

+75

D3

TILE START

POINT

+75

D3

TILE START

POINT

+75

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

SLOPE

SLOPE

SLOPE

SLOPE

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

CP.

CP.

SLOPE

SLOPE

SLOPE

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

UR.

CCP.

UR.

UR.

UR.

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

+100

GENTS' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

+100

GENTS' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

+150

100mm

DROP

100mm

DROP

100mm

DROP

100mm

DROP

900

450

450

1800

1010

1500

1000

1000

S

L

O

P

E

SLOPE

1000

1000

1610

2520

900

900

360

360

2805

630 600 715 600

265

610

485510600

2805

900

450

900

600

100

1500

1500

500

500

500

500

500

500

500

500

1500

500

500

500

500

500

500

1610

900

450

450

1115

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

6790

3030

DRAIN

DRAIN

DRAIN

DRAIN

PLAN (TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

01 01

02

02

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

03

03

690

750

750

750

690

100

100

S.H.

W.B.

MR.1

S.H.

W.B.

MR.1

UR.

INTERNAL WALLS TO BE SMOOTH FINISH PLASTERED & TO BE PAINTED WITH ONE

COAT OF FILLER & TWO COATS OF WEATHER SHIELD PAINT WITH APPROVED COLOUR

D2 D2

+150

-400

+100

+200

+100

+150

-400

50

600

100

850

200

750

125

50

1475

2100

600x300mm GLAZED

CERAMIC WALL TILES

UP TO 1500mm

HEIGHT WITH P.V.C.

EDGE BEADING

GROUTED WITH

APPROVED COLOUR

GROUT

PEDESTAL TYPE WASH

BASIN AS SPECIFIED BY

THE CONSULTANT

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM

PLATED SCREWS

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

225mm THK.

BRICK WALL

SECTION 01-01 (TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

06 07

3030

50

2250

112.5mm THK. 2250mm

HIGH BRICK WALL

W.B

S.H.

200

750

600

350

TP.

MR.1

125

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

W.B

S.H.

200

750

600

300

TP.

MR.1

125

850

D3 D3 D3 D3

D2

F1

+150

+100 +100

-400

1500

550

INTERNAL WALLS TO BE SMOOTH FINISH PLASTERED & TO

BE PAINTED WITH ONE COAT OF FILLER & TWO COATS OF

WEATHER SHIELD PAINT WITH APPROVED COLOUR

INTERNAL WALLS TO BE SMOOTH FINISH

PLASTERED & TO BE PAINTED WITH ONE

COAT OF FILLER & TWO COATS OF WEATHER

SHIELD PAINT WITH APPROVED COLOUR

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM

PLATED SCREWS

600x300mm GLAZED

CERAMIC WALL TILES

UP TO 1500mm

HEIGHT WITH P.V.C.

EDGE BEADING

GROUTED WITH

APPROVED COLOUR

GROUT

PEDESTAL TYPE WASH

BASIN AS SPECIFIED BY

THE CONSULTANT

112.5mm THK. 2250mm

HIGH BRICK WALL

112.5mm THK. 2250mm

HIGH BRICK WALL

AC

6790

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM PLATED

SCREWS

2100

2250

2100

SECTION 02-02 (TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

W.B

S.H.

200

750

600

350

TP.

MR.1

125

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

F1

+150

+100

1500

550

INTERNAL WALLS TO BE SMOOTH FINISH PLASTERED & TO BE PAINTED WITH ONE COAT

OF FILLER & TWO COATS OF WEATHER SHIELD PAINT WITH APPROVED COLOUR

INTERNAL WALLS TO BE SMOOTH FINISH

PLASTERED & TO BE PAINTED WITH ONE

COAT OF FILLER & TWO COATS OF WEATHER

SHIELD PAINT WITH APPROVED COLOUR

600x300mm GLAZED

CERAMIC WALL TILES

UP TO 1500mm

HEIGHT WITH P.V.C.

EDGE BEADING

GROUTED WITH

APPROVED COLOUR

GROUT

PEDESTAL TYPE WASH

BASIN AS SPECIFIED BY

THE CONSULTANT

A C

6790

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM PLATED

SCREWS

B.S.

W.C

P.H.

B.S.

W.C

P.H.

B.S.

W.C

P.H.

UR. UR. UR. UR.

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

112.5mm THK.

2250mm HIGH

BRICK WALL

112.5mm THK.

2250mm HIGH

BRICK WALL

112.5mm THK.

2250mm HIGH

BRICK WALL

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

100

600

600

600

600

1375

100

600

600

600

1500

1500

1500

2100

600x300mm GLAZED CERAMIC WALL

TILES UP TO 1500mm HEIGHT WITH

P.V.C. EDGE BEADING GROUTED

WITH APPROVED COLOUR GROUT

50

-400

SECTION 03-03

(TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

1. ALL TOILET FLOORS SHOULD BE FINISHED WITH 600x300mm

SEMI ROUGH HOMOGENEOUS PORCELAIN FLOOR TILES.

(COLOUR TO BE SPECIFIED BY ARCHITECT)

2. ALL TOILET WALLS TO BE FINISHED WITH 600x300mm

GLAZED CERAMIC WALL TILES UP TO 1500mm FROM F.F.L.

ABOVE FROM WALL TILE LEVEL TO BE SMOOTH PLASTERED AND

PAINTED WITH 0NE COAT OF FILLER AND TWO COATS OF

WEATHER SHIELD PAINT.

(COLOUR TO BE SPECIFIED BY ARCHITECT)

3. ALL SANITARY FITTINGS SHOULD BE ROCELL OR EQUIVALENT.

[COLOUR - WHITE]

4. APPROVED BEVELED EDGED MIRROR TO BE FIXED ON WALL

200mm ABOVE FROM WASH BASIN.

5. BIDET SHOWERS TO BE FIXED 600mm ABOVE FROM F.F.L.

SCHEDULE OF FINISHES:

6. ALL CATCH PITS COVER TO BE S/S 316 150x150mm CATCH PIT

7. TOP EDGE OF LAST TILE SHOULD BE COMPLETED WITH P.V.C.

EDGE BEADING.

8. EVERY CORNER JOINTS IN THE WALL TILES OF THE VERTICAL

EDGES TO BE WITH 45 < TAPERED EDGES TO EACH OTHER.

W.B. -

W.C. -

B.S. - BIDET SHOWER

CP. - S/S 316 150x150mm CATCH PIT

S.H. -S/S 316 SOAP

HOLDER

LEGEND

WATER

CLOSET

WASH

BASIN

P.H. - TOILET PAPER HOLDER

TP. - WASH BASIN TAP

MR.1 - 600x750mm BEVEL EDGED MIRROR

FIXED TO WALL WITH 04 NO OF

CHROMIUM PLATED SCREWS

UR. - URINAL

CCP. - CONCEALED TYPE CATCH PIT

(AT URINAL DRAIN)

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

P.O.BOX 194, COLOMBO - 02

CAD : CHAMIL MADUSHAN

ARCHITECT:

DOA :

SCALE : 1:25

CHECKED :

DATE: 2021-06-17

CHIEF ARCHITECT:

DRG NO: [2021-13] / A / 05

PROPOSED ADDITIONS & ALTERATION TO THE

EXISTING BUILDING

FOR OCEAN UNIVERSITY OF SRI LANKA

AT BOOSSA - PHASE 1 OF STAGE 03

CPU NO 255

DETAILS OF TOILETS -TOILET TYPE - T1 AT GROUND FLOOR

SENIOR / PROJECT

ARCHITECT :

Page 158 of 170

Page 159: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

ELEVATION TO GALLED ROAD OF E1

STAGE 01

STAGE 02

STAGE 02

STAG

E 01

STAGE 03

PHASE 02

STAGE 03

PHASE 01

STAGE 04

STAGE 04

REAR ELEVATION OF E2

STAGE 01

STAGE 02

STAGE 02

STAGE 03

PHASE 02

STAGE 03

PHASE 01

STAGE 04

STAGE 04

STAGE 01

ELEVATION TO NORTH OF E3

PROPOSED STEPS

T

O

G

A

L

L

E

R

O

A

D

R

O

A

D

R

O

A

D

T

O

R

A

I

L

W

A

Y

S

T

A

T

I

O

N

F

R

O

M

C

O

L

O

M

B

O

SCALE:-1:2000

SITE PLAN

16975

10255

8795

PROPOSED SEPTIC

TANK 50' AWAY FROM

ALL WELLS

PROPOSED SOAKAGE PIT

50' AWAY FROM ALL

WELLS

NOTE

WATER FROM WATER BOARD MAIN

5000

2

4

0

0

7

2

0

0

6000

MAIN ENTRANCE /EXIT

BUILDING TO

DEMOLISH

NOTE

EXISTING TEMPORARY GUARD ROOM TO DEMOLISH

14Nos PARKING SPACE

1No DESABLE PARKING SPACE

PROPOSED BUILDING

CPU NO & PATH :CPU704/G/2019 PROJECTS/OCEAN BOOSSA

ELEVATIONS

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

P.O.BOX 194, COLOMBO - 02

ARCHITECT:

DOA :

CHECKED :

CHIEF ARCHITECT:

PROJECT / SENIOR

ARCHITECT :

PROPOSED ADDITION & ALTERNATIONS TO THE

EXISTING BUILDING

FOR OCEAN UNIVERSITY OF SRI LANKA

AT BOOSSA.- PHASE 01 OF STAGE 03

DRG. NO -[2021-13]/A]/04

CAD : E.A.N. SHAMIKA

SCALE : 1:100DATE:15-06-2021

KEY PLAN

E2

E3

E1

Page 159 of 170

Page 160: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

1.5 m / ( 5 ' - 0 " )( c ) MAIN SWITCHES

( f ) FLUORESCENT FITTINGS

( g ) CEILING FANS

FROM FINISHED FLOOR LEVEL TO THECENTRE OF THE ACCESSORIES.

FROM FINISHED FLOOR LEVEL TO UNDERSIDE OF THE RESPECTIVE ITEM.

2.4 m / ( 8 ' - 0 " )

2.6 m / ( 8 ' - 6 " )

1.6 m / ( 5 ' - 3 " )

( 01 ) ALL CEILING FANS, FAN REGULATORS & ALL LAMPS WITH METAL PARTS SHOULD BE EARTHED.

( 03 ) ALL CABLES SHALL BE PVC / PVC COPPER OR XLPE / PVC EXCEPT EARTH WIRE WHICH COULD BE PVC / COPPER.

( 08 ) SWITCHES, SOCKET OUTLETS & CONSUMER UNITS SHALL BE FLUSH MOUNTING TYPE.

( 09 ) ALL ITEMS USED SHALL BE REPUTED MAKES CONFIRMING TO B. S. S. APPROVED BY THE ENGINEER.

( 10 ) ELECTRICAL INSTALLATION SHALL BE IN ACCORDANCE WITH LATEST EDITION OF IEE WIRING REGULATIONS.

( 12 ) INSTALLATION HEIGHTS

( b ) SOCKET OUTLETS

( a ) SWITCHES

NOTES:-

1.2 m / ( 4 ' - 0 " )

0.3 m / ( 0 " - 9 " )

( 11 ) QUANTITIES SHOWN IN THE TABLES SHALL BE VERIFIED BY THE TENDERER BEFORE SUBMITTING THEIR QUOTATION.

( d ) R. C. C. B. 1.5 m / ( 5 ' - 0 " )

( h) DISTRIBUTION BOARDS FROM FINISHED FLOOR LEVEL TO THETOP OF THE DB.

2.1 m / ( 7 ' - 0 " )

( 05 ) 13 A RING CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

( 06 ) 13 A RADIAL CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

( e ) CONSUMER UNITS

( 02 ) ALL FLUORESCENT FITTINGS TO BE OF ELECTRONIC BALLAST TYPE COMPLETE WITH REFLECTOR & & EUROPEAN ACCSAORIES.

( 04 ) LAMPS & FANS CIRCUITS SHALL BE WIRED WITH 2 x 1.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) FOR 10A MCB IN 25 mmØ PVC CONDUIT PIPE.

( 07 ) 10 A RING CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

Gayana

REVISION

CHIEF ELECTRICAL ENGINEER.

P.O.BOX 194, COLOMBO - 02

C

A

MARK

B

DATE MADE BY

D

SCALE: 1 : 100 DRG. NO:

DESIGNED BY:

CHECKED BY:

DOA:

CAD BY: Eng . Rusiru

OCEAN UNIVERSITY OF SRI LANKA,PROPOSED RENOVATION AND ALTERATION TO THE EXISTING BUILDING FOROCEAN UNIVERSITY OF SRI LANKA AT BOOSSA (STAGE lll)ELECTRICAL LAYOUT - SINGLE LINE DIAGRAMGROUND FLOOR

CONSUMER UNIT

YR

1.

2.

3.

4.

MCB32 A, 4P

From MDB

R Y B3x2A

4C x 6mm² Cu/ PVC / PVC + 6mm² Cu / PVC ( E )

16A

16A

16A

16A

Location: As Shown

EARTH BAR

40 A, 2PRCCB( 30 mA )

CONSUMER UNIT

Y BR

MCB32 A, 4P

From MDB

R Y B3x2A

Location: As ShownDB-01 [ Aquaculture Lab ]

EARTH BAR

Enclosure : Surface mounted powder coated steel lockable

40 A, 2PRCCB( 30 mA )

40 A, 2PRCCB( 30 mA )

6L

1.

2.

3.

4.

16A

16A

16A 5F

1.

2.

3.

4.

Spare

16A

16A

16A

2Kt1Kt [ For Multimedia Projector]

CONSUMER UNIT

Y BR

1.

2.

3.

4.

3Kt

Spare

MCB32 A, 4P

From MDB

R Y B3x2A

4C x 6mm² Cu/ PVC / PVC + 6mm² Cu / PVC ( E )

16A

16A

10A

10A

Location: As Shown

EARTH BAR

40 A, 2PRCCB( 30 mA )

CONSUMER UNIT

Y BR

MCB32 A, 4P

From MDB

R Y B3x2A

Location: As ShownDB-02 [ SCUBA Diving Unit ]

EARTH BAR

Enclosure : Surface mounted powder coated steel lockable

40 A, 2PRCCB( 30 mA )

40 A, 2PRCCB( 30 mA )

MCB16 A, 2P

40 A, 4PRCCB( 30 mA )

MCB16 A, 2P

40 A, 4PRCCB( 30 mA )

Spare

Spare

1.

2.

3.

4.

Spare16A

16A

10A

10A Spare

Spare

1.

2.

3.

4.

Spare16A

16A

10A

10A 3F

8L

2Kt 1Kt [For Multimedia Projector]

IS - 01 IS - 02

Spare

5. 16A 6L 4. 16A Spare 4. 16A Spare

16A

2Kt

3Kt

3Kt

2Kt

3Kt

16A

CONSUMER UNIT

1.

2.

8.

9.

MCB

From MDB

R Y B3x2A

2C x 4mm² Cu/ PVC / PVC + 4mm² Cu / PVC ( E )

16A

16A

10A

Location: As Shown

EARTH BAR

40 A, 2PRCCB( 30 mA )

CONSUMER UNIT

20 A, 2P

From MDB

R Y B3x2A

Location: As ShownDB-03 [ Cafeteria ]

EARTH BAR

Enclosure : Surface mounted powder coated steel lockable

6L

3Kt

10A 6L

Spare

2Kt

3. 16A 3Kt

4. 16A 2Kt

5. 16A

6. 16A

7. 16A

Spare

Spare

10. 10A 4F

11. 10A

12. 10A

Spare

Spare

CONSUMER UNIT

1.

2.

8.

9.

MCB

From MDB

R Y B3x2A

2C x 4mm² Cu/ PVC / PVC + 4mm² Cu / PVC ( E )

16A

16A

16A

Location: As Shown

EARTH BAR

40 A, 2PRCCB( 30 mA )

CONSUMER UNIT

20 A, 2P

From MDB

R Y B3x2A

Location: As ShownDB-04 [ Life saving unit and Passage ]

EARTH BAR

Enclosure : Surface mounted powder coated steel lockable

4F

16A

8L

1Kt

3. 16A

4. 16A

5. 16A

6. 16A

7. 16A

10. 10A

11. 10A

12. 10A

13. 10A

14. 10A

6DL

6DL , 3ML

3Kt

1Kt

2Kt

3Kt

1Kt [ For Multimedia Projector]

1K [ For Exhaust fan ]

5DL

15. 10A

16. 10A 3DL

6DL , 3ML

2Kt

3Kt

CONSUMER UNIT

1.

2.

8.

9.

MCB

From MDB

R Y B3x2A

2C x 4mm² Cu/ PVC / PVC + 4mm² Cu / PVC ( E )

16A

16A

10A

Location: As Shown

EARTH BAR

40 A, 2PRCCB( 30 mA )

CONSUMER UNIT

20 A, 2P

From MDB

R Y B3x2A

Location: As ShownDB-05 [ Lecture room ]

EARTH BAR

Enclosure : Surface mounted powder coated steel lockable

1Kt

3. 16A

4. 16A

5. 16A

6. 16A

7. 16A

10. 10A

11. 10A

12. 10A

13. 10A

14. 10A

4F

3Kt

2F

6L

3Kt

3Kt

16A

Spare

Spare

Spare

Spare

Spare

6L

6L

32 A, 4PMCB

32 A, 4PMCB

A As

E.L.R.

3X2A FUSEB Y RB Y R

V Vs Fuse

3x2ASPD

EARTH BARCLASS 1SPD

600 x 600 x 3mm solid copper earth plates& concrete inspection pit etc. to achieve the earth

resistance less than 10 ohms.

16 mm² Cu /PVC(E)

From MDB

4 C x 16 mm² Cu / PVC / PVC

FLOOR DBLocation: As ShownEnclosure: Surface Mounted Power coated Steel Locable Enclosure With 2b

50kA

MCCB63 A, 4P

DB-01 [ Aquaculture Lab ] DB-02 [ SCUBA Diving Unit ]

32 A, 4PMCB

DB-03 [ Cafeteria ] DB-04 [ Life saving unit and Passage ] DB-05 [ Lecture room ]

DATE: 14 / 06 / 2021 [2021-13] / E / 01

20 A, 2PMCB

20 A, 2PMCB

20 A, 2PMCB

1K [ For Exhaust fan ]

L E G E N DSYM.TYPE

L E G E N DDESCRIPTION QTY.

CEILING FAN F

36W 600mm x 600mm LED PANNEL

13 A, SWITCH TWIN SOCKET OUTLET ( Fixed at Ceiling Level )

L

DL

26

60

27

EXHAUST FAN Ex 02

13 A, TWIN SWITCH SOCKET OUTLET

K

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at 4 FEET Level )

INDUTRIAL SOCKET OUTLET

10 A, FLUSH TYPE SWITCH

FAN REGULATOR

- DO - 2 WAY

DISTRIBUTION CENTER

IS

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at Ceiling Level )

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at Table )

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at 1 FEET Level )

13 A, SWITCH SOCKET OUTLET

Kt

Kt

Kt

Kt

Kt

02

02

04

05

14

15

20

MCB16 A, 2P

40 A, 4PRCCB( 30 mA )

IS - 03

DB - AC ( GROUND FLOOR)

(DC PULSATING TYPE)

(DC PULSATING TYPE)

(DC PULSATING TYPE)

Page 160 of 170

Page 161: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

6065

6060

6060 6060 6060 6060 6060 6060 6060 6060

3190

5960

3190

EXISTING DRAIN

GROUND FLOOR PLAN [ AIR CONDITIONING SYSTEM ]

6030

6060

UP

WALK WAY

ENTRANCELOBBY

CAFETARIA

LABS

CONFERENCE HALL OFFICE

A'DS OFFICE

ROOM

ROOM

STAFF COMMONROOM

STORE

STAFF REST

±0

+150 ±0

AQUACULTURE LAB

LIFESAVING UNIT

PROPOSEDROLLER DOOR

UP

CLASS ROOM 01

FIRST AID

FEMAIL TOIMALE TOI

SCUBA DIVING UNIT

384 sqm

INSTRUCTORROOM

STORE ROOM

Gayana

REVISION

CHIEF ELECTRICAL ENGINEER.

P.O.BOX 194, COLOMBO - 02

C

A

MARK

B

DATE MADE BY

D

SCALE: 1 : 100 DATE: 14 / 06 / 2021 DRG. NO: [2021-13] / E / AC / 01

DESIGNED BY:

CHECKED BY:

DOA:

CAD BY: Eng . Rusiru

DB-A/C-02

A/C -01( IDU - 01)18000Btu

MCB32 A, 4P

CONSUMER UNIT

DB - AC ( GROUND FLOOR)Location: As ShownEnclosure: Flush Mounted Powder Coated Steel Enclosure

From MDB

Earth BarR Y B

4C, 6mm² Cu/ PVC / PVC + 6mm² Cu / PVC ( E )

3x2A

R Y B

RCCB 40 A, 2P

( 100 mA ) RCCB 40 A, 2P

( 100 mA )

16A

MCB40 A, 2P

RCCB 40 A, 2P

( 100 mA )

1K [ A/C -01 ]01.

02.

01.

02.

01.

02.

MCB40 A, 2P

MCB40 A, 2P

16A 16A

16A

1K [ A/C -02 ] 1K [ A/C -03 ]

( ODU - 01)

A/C -02( IDU - 02)24000Btu

A/C -03( IDU - 03)24000Btu

A/C -04( IDU - 04)24000Btu

( ODU - 04) ( ODU - 03) & ( ODU - 04)

LEGEND

OUTDOOR UNIT

INDOOR UNITS

INSULATED REFREGERENT PIPE (LIQUID & GAS)LAID ALONG THE WALL & THE BEAM BOTTOM AS APPROPRIATE(EXACT PATH TO BE VERIFIED AT SITE)

NOTES

URF TYPE AIR CONDITIONING SYSTEM

*

ALL OUT DOOR UNIT BRACKETING SHOULD BE DONE USING PROPERLY DESIGNED HOTDIPPED GALVANIZED BRACKETS AND THE INSTALLATION SHOULD BE FREE FROMANY VIBRATION.

NEOPRENE PADS OR ANY OTHER EQUIVALANT MATERIAL SHOULD BE USED TO AVOIDSUCH VIBRATION & TO THE SATISFACTION OF THE STRUCTURAL ENGINEER FORSTABILITY & STRENGTH.

16A16A 1K [ A/C -03 ] Spare Spare AIR CONDITIONING SYSTEM FORGROUND FLOOR

[STAGE - 03 ]

OCEAN UNIVERSITY OF SRI LANKA,PROPOSED RENOVATION AND ALTERATION TO THE EXISTING BUILDING FOROCEAN UNIVERSITY OF SRI LANKA AT BOOSSA (STAGE lll)

Page 161 of 170

Page 162: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

6065

6060

6060 6060 6060 6060 6060 6060 6060 6060

3190

5960

3190

EXISTING DRAIN

GROUND FLOOR PLAN [ POWER LAYOUT ]

6030

6060

UP

UP

WALK WAY

ENTRANCELOBBY

CAFETARIA

LABS

CONFERENCE HALL OFFICE

A'DS OFFICE

ROOM

ROOM

STAFF COMMONROOM

STORE

STAFF REST

±0

+150 ±0

AQUACULTURE LAB

LIFESAVING UNIT

PROPOSEDROLLER DOOR

UP

CLASS ROOM 01

FIRST AID

FEMAIL TOIMALE TOI

SCUBA DIVING UNIT

384 sqm

INSTRUCTORROOM

STORE ROOM

1.5 m / ( 5 ' - 0 " )( c ) MAIN SWITCHES

( f ) FLUORESCENT FITTINGS

( g ) CEILING FANS

FROM FINISHED FLOOR LEVEL TO THECENTRE OF THE ACCESSORIES.

FROM FINISHED FLOOR LEVEL TO UNDERSIDE OF THE RESPECTIVE ITEM.

2.4 m / ( 8 ' - 0 " )

2.6 m / ( 8 ' - 6 " )

1.6 m / ( 5 ' - 3 " )

( 01 ) ALL CEILING FANS, FAN REGULATORS & ALL LAMPS WITH METAL PARTS SHOULD BE EARTHED.

( 03 ) ALL CABLES SHALL BE PVC / PVC COPPER OR XLPE / PVC EXCEPT EARTH WIRE WHICH COULD BE PVC / COPPER.

( 08 ) SWITCHES, SOCKET OUTLETS & CONSUMER UNITS SHALL BE FLUSH MOUNTING TYPE.

( 09 ) ALL ITEMS USED SHALL BE REPUTED MAKES CONFIRMING TO B. S. S. APPROVED BY THE ENGINEER.

( 10 ) ELECTRICAL INSTALLATION SHALL BE IN ACCORDANCE WITH LATEST EDITION OF IEE WIRING REGULATIONS.

( 12 ) INSTALLATION HEIGHTS

( b ) SOCKET OUTLETS

( a ) SWITCHES

NOTES:-

1.2 m / ( 4 ' - 0 " )

0.3 m / ( 0 " - 9 " )

( 11 ) QUANTITIES SHOWN IN THE TABLES SHALL BE VERIFIED BY THE TENDERER BEFORE SUBMITTING THEIR QUOTATION.

( d ) R. C. C. B. 1.5 m / ( 5 ' - 0 " )

( h) DISTRIBUTION BOARDS FROM FINISHED FLOOR LEVEL TO THETOP OF THE DB.

2.1 m / ( 7 ' - 0 " )

( 05 ) 13 A RING CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

( 06 ) 13 A RADIAL CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

( e ) CONSUMER UNITS

L E G E N DSYM.TYPE

L E G E N DDESCRIPTION

13 A, TWIN SWITCH SOCKET OUTLET

K

QTY.

( 02 ) ALL FLUORESCENT FITTINGS TO BE OF ELECTRONIC BALLAST TYPE COMPLETE WITH REFLECTOR & & EUROPEAN ACCSAORIES.

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at 4 FEET Level )

( 04 ) LAMPS & FANS CIRCUITS SHALL BE WIRED WITH 2 x 1.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) FOR 10A MCB IN 25 mmØ PVC CONDUIT PIPE.

( 07 ) 10 A RING CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

INDUTRIAL SOCKET OUTLET

10 A, FLUSH TYPE SWITCH

FAN REGULATOR

- DO - 2 WAY

DISTRIBUTION CENTER

IS

Gayana

REVISION

CHIEF ELECTRICAL ENGINEER.

P.O.BOX 194, COLOMBO - 02

C

A

MARK

B

DATE MADE BY

D

SCALE: 1 : 100 DATE: 14 / 06 / 2021 DRG. NO: [2021-13] / E / P / 01

DESIGNED BY:

CHECKED BY:

DOA:

CAD BY: Eng . Rusiru

ELECTRICAL LAYOUT - POWER LAYOUTGROUND FLOOR

DB-01DB-04

DB-1

1 C1

T

T

T

14

4

1 1

IS -01

IS -02

DB-02

2.R/12.Y/1

1.R/1

1.Y/1

1.R/2

1.Y/3

1.Y/2

1.B/1

1.B/2

2.B/1

DB-03

3/1

3/2 3/4

3/3

4/3

4/1

4/5

4/4

4/2

4/6

4/94/8

4/7

DB-05

5/1

5/2

5/3

5/4

[STAGE - 03 ]

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at Ceiling Level )

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at Table )

13 A, TWIN SWITCH SOCKET OUTLET ( Fixed at 1 FEET Level )

13 A, SWITCH SOCKET OUTLET

Kt

Kt

Kt

Kt

Kt

1.R/3

02

02

04

05

14

15

20

T

OCEAN UNIVERSITY OF SRI LANKA,PROPOSED RENOVATION AND ALTERATION TO THE EXISTING BUILDING FOROCEAN UNIVERSITY OF SRI LANKA AT BOOSSA (STAGE lll)

Page 162 of 170

Page 163: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

6065

6060

6060 6060 6060 6060 6060 6060 6060 6060

3190

5960

3190

EXISTING DRAIN

6030

6060

UP

WALK WAY

ENTRANCELOBBY

CAFETARIA

LABS

CONFERENCE HALL OFFICE

A'DS OFFICE

ROOM

ROOM

STAFF COMMONROOM

STORE

STAFF REST

±0

+150 ±0AQUACULTURE LAB

LIFESAVING UNIT

PROPOSEDROLLER DOOR

UP

CLASS ROOM 01

FIRST AID

FEMAIL TOIMALE TOI

SCUBA DIVING UNIT

384 sqm

INSTRUCTORROOM

STORE ROOM

1.5 m / ( 5 ' - 0 " )( c ) MAIN SWITCHES

( f ) FLUORESCENT FITTINGS

( g ) CEILING FANS

FROM FINISHED FLOOR LEVEL TO THECENTRE OF THE ACCESSORIES.

FROM FINISHED FLOOR LEVEL TO UNDERSIDE OF THE RESPECTIVE ITEM.

2.4 m / ( 8 ' - 0 " )

2.6 m / ( 8 ' - 6 " )

1.6 m / ( 5 ' - 3 " )

( 01 ) ALL CEILING FANS, FAN REGULATORS & ALL LAMPS WITH METAL PARTS SHOULD BE EARTHED.

( 03 ) ALL CABLES SHALL BE PVC / PVC COPPER OR XLPE / PVC EXCEPT EARTH WIRE WHICH COULD BE PVC / COPPER.

( 08 ) SWITCHES, SOCKET OUTLETS & CONSUMER UNITS SHALL BE FLUSH MOUNTING TYPE.

( 09 ) ALL ITEMS USED SHALL BE REPUTED MAKES CONFIRMING TO B. S. S. APPROVED BY THE ENGINEER.

( 10 ) ELECTRICAL INSTALLATION SHALL BE IN ACCORDANCE WITH LATEST EDITION OF IEE WIRING REGULATIONS.

( 12 ) INSTALLATION HEIGHTS

( b ) SOCKET OUTLETS

( a ) SWITCHES

NOTES:-

1.2 m / ( 4 ' - 0 " )

0.3 m / ( 0 " - 9 " )

( 11 ) QUANTITIES SHOWN IN THE TABLES SHALL BE VERIFIED BY THE TENDERER BEFORE SUBMITTING THEIR QUOTATION.

( d ) R. C. C. B. 1.5 m / ( 5 ' - 0 " )

( h) DISTRIBUTION BOARDS FROM FINISHED FLOOR LEVEL TO THETOP OF THE DB.

2.1 m / ( 7 ' - 0 " )

( 05 ) 13 A RING CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

( 06 ) 13 A RADIAL CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

( e ) CONSUMER UNITS

L E G E N DSYM.TYPE

L E G E N DDESCRIPTION QTY.

( 02 ) ALL FLUORESCENT FITTINGS TO BE OF ELECTRONIC BALLAST TYPE COMPLETE WITH REFLECTOR & & EUROPEAN ACCSAORIES.

( 04 ) LAMPS & FANS CIRCUITS SHALL BE WIRED WITH 2 x 1.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) FOR 10A MCB IN 25 mmØ PVC CONDUIT PIPE.

( 07 ) 10 A RING CIRCUITS SHALL BE WIRED WITH 2 x 2.5 mm² PVC / PVC / Cu + 2.5 mm² PVC / Cu ( E ) IN 25 mmØ PVC CONDUIT PIPE.

5 A, FLUSH TYPE SWITCH

FAN REGULATOR

CEILING FAN F

- DO - 2 WAY

DISTRIBUTION CENTER

36W 600mm x 600mm LED PANNEL

13 A, SWITCH TWIN SOCKET OUTLET ( Fixed at Ceiling Level )

L

DL

Gayana

REVISION

CHIEF ELECTRICAL ENGINEER.

P.O.BOX 194, COLOMBO - 02

C

A

MARK

B

DATE MADE BY

D

SCALE: 1 : 100 DRG. NO:

DESIGNED BY:

CHECKED BY:

DOA:

CAD BY: Eng . Rusiru

3gx4[a,b,c,d,e,f,g,h,j,k,l]

a b

dc

e f

g h

ji

k l

DB-01DB-04

DB-1

aa

aa

a a

aaDB-02

2.B/42.R/1

2.B/3

1.R/3

1.R/4

1.Y/4

DB-03

3/3

3/83/10

4/11

4/10

4/124/13

4/14

4/15

4/16

DB-05

5/135/9

5/10

5/115/12

DATE: 14 / 06 / 2021 [2021-13] / E / L / 01

ELECTRICAL LAYOUT - LIGHTING LAYOUTGROUND FLOOR

GROUND FLOOR PLAN [ LIGHTING LAYOUT ][STAGE - 03 ]

26

60

27

EXHAUST FAN Ex 02

OCEAN UNIVERSITY OF SRI LANKA,PROPOSED RENOVATION AND ALTERATION TO THE EXISTING BUILDING FOROCEAN UNIVERSITY OF SRI LANKA AT BOOSSA (STAGE lll)

Page 163 of 170

Page 164: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

06 07

A

C

F1 F1 F1F1

D2

50mm

DROP

TILE START

POINT

D2

50mm

DROP

TILE START

POINT

25mm

DROP

D3

TILE START

POINT

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

25mm

DROP

D3

TILE START

POINT

25mm

DROP

D3

TILE START

POINT

25mm

DROP

D3

TILE START

POINT

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

W.C

B.S.

CP.

P.H.

300

300

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

CP.

CP.

SLOPE

S

L

O

P

E

SLOPE

S

L

O

P

E

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

S

L

O

P

E

S

L

O

P

E

S

L

O

P

E

+150

+100

+100

+100

+100

+75

+75

+75

+75

LADIES' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

LADIES' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

CP.

SLOPE

S

L

O

P

E

SLOPE

S

L

O

P

E

25mm

DROP

D3

TILE START

POINT

+75

D3

TILE START

POINT

+75

D3

TILE START

POINT

+75

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

SLOPE

SLOPE

SLOPE

SLOPE

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

W.B.

TP.

S.H.

MR.1

CP.

CP.

SLOPE

SLOPE

SLOPE

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

W.C

B.S.

CP.

S

L

O

P

E

SLOPE

P.H.

300

300

UR.

CCP.

UR.

UR.

UR.

SLOPE

SLOPE

SLOPE

SLOPE

SLOPE

+100

GENTS' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

+100

GENTS' TOILET

(TOILET TYPE - T1)

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

+150

100mm

DROP

100mm

DROP

100mm

DROP

100mm

DROP

900

450

450

1800

1010

1500

1000

1000

S

L

O

P

E

SLOPE

1000

1000

1610

2520

900

900

360

360

2805

630 600 715 600

265

610

485510600

2805

900

450

900

600

100

1500

1500

500

500

500

500

500

500

500

500

1500

500

500

500

500

500

500

1610

900

450

450

1115

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

600x300mm

SEMI ROUGH

HOMOGENEOUS

PORCELAIN

FLOOR TILES

6790

3030

DRAIN

DRAIN

DRAIN

DRAIN

PLAN (TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

01 01

02

02

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

INTERNAL

PARTITION WALLS

TO BE 112.5mm

THK. 2250mm HIGH

BRICK WALL

03

03

690

750

750

750

690

100

100

S.H.

W.B.

MR.1

S.H.

W.B.

MR.1

UR.

INTERNAL WALLS TO BE SMOOTH FINISH PLASTERED & TO BE PAINTED WITH ONE

COAT OF FILLER & TWO COATS OF WEATHER SHIELD PAINT WITH APPROVED COLOUR

D2 D2

+150

-400

+100

+200

+100

+150

-400

50

600

100

850

200

750

125

50

1475

2100

600x300mm GLAZED

CERAMIC WALL TILES

UP TO 1500mm

HEIGHT WITH P.V.C.

EDGE BEADING

GROUTED WITH

APPROVED COLOUR

GROUT

PEDESTAL TYPE WASH

BASIN AS SPECIFIED BY

THE CONSULTANT

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM

PLATED SCREWS

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

225mm THK.

BRICK WALL

SECTION 01-01 (TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

06 07

3030

50

2250

112.5mm THK. 2250mm

HIGH BRICK WALL

W.B

S.H.

200

750

600

350

TP.

MR.1

125

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

W.B

S.H.

200

750

600

300

TP.

MR.1

125

850

D3 D3 D3 D3

D2

F1

+150

+100 +100

-400

1500

550

INTERNAL WALLS TO BE SMOOTH FINISH PLASTERED & TO

BE PAINTED WITH ONE COAT OF FILLER & TWO COATS OF

WEATHER SHIELD PAINT WITH APPROVED COLOUR

INTERNAL WALLS TO BE SMOOTH FINISH

PLASTERED & TO BE PAINTED WITH ONE

COAT OF FILLER & TWO COATS OF WEATHER

SHIELD PAINT WITH APPROVED COLOUR

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM

PLATED SCREWS

600x300mm GLAZED

CERAMIC WALL TILES

UP TO 1500mm

HEIGHT WITH P.V.C.

EDGE BEADING

GROUTED WITH

APPROVED COLOUR

GROUT

PEDESTAL TYPE WASH

BASIN AS SPECIFIED BY

THE CONSULTANT

112.5mm THK. 2250mm

HIGH BRICK WALL

112.5mm THK. 2250mm

HIGH BRICK WALL

AC

6790

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM PLATED

SCREWS

2100

2250

2100

SECTION 02-02 (TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

W.B

S.H.

200

750

600

350

TP.

MR.1

125

W.B

S.H.

200

750

600

350

TP.

MR.1

125

850

F1

+150

+100

1500

550

INTERNAL WALLS TO BE SMOOTH FINISH PLASTERED & TO BE PAINTED WITH ONE COAT

OF FILLER & TWO COATS OF WEATHER SHIELD PAINT WITH APPROVED COLOUR

INTERNAL WALLS TO BE SMOOTH FINISH

PLASTERED & TO BE PAINTED WITH ONE

COAT OF FILLER & TWO COATS OF WEATHER

SHIELD PAINT WITH APPROVED COLOUR

600x300mm GLAZED

CERAMIC WALL TILES

UP TO 1500mm

HEIGHT WITH P.V.C.

EDGE BEADING

GROUTED WITH

APPROVED COLOUR

GROUT

PEDESTAL TYPE WASH

BASIN AS SPECIFIED BY

THE CONSULTANT

A C

6790

600x750mm BEVEL

EDGED MIRROR FIXED

TO WALL WITH 04 NO

OF CHROMIUM PLATED

SCREWS

B.S.

W.C

P.H.

B.S.

W.C

P.H.

B.S.

W.C

P.H.

UR. UR. UR. UR.

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

112.5mm THK.

2250mm HIGH

BRICK WALL

112.5mm THK.

2250mm HIGH

BRICK WALL

112.5mm THK.

2250mm HIGH

BRICK WALL

P..V.C. EDGE

BEADING

P..V.C. EDGE

BEADING

100

600

600

600

600

1375

100

600

600

600

1500

1500

1500

2100

600x300mm GLAZED CERAMIC WALL

TILES UP TO 1500mm HEIGHT WITH

P.V.C. EDGE BEADING GROUTED

WITH APPROVED COLOUR GROUT

50

-400

SECTION 03-03

(TOILET TYPE - T1 @ GROUND FLOOR)

SCALE 1:25

1. ALL TOILET FLOORS SHOULD BE FINISHED WITH 600x300mm

SEMI ROUGH HOMOGENEOUS PORCELAIN FLOOR TILES.

(COLOUR TO BE SPECIFIED BY ARCHITECT)

2. ALL TOILET WALLS TO BE FINISHED WITH 600x300mm

GLAZED CERAMIC WALL TILES UP TO 1500mm FROM F.F.L.

ABOVE FROM WALL TILE LEVEL TO BE SMOOTH PLASTERED AND

PAINTED WITH 0NE COAT OF FILLER AND TWO COATS OF

WEATHER SHIELD PAINT.

(COLOUR TO BE SPECIFIED BY ARCHITECT)

3. ALL SANITARY FITTINGS SHOULD BE ROCELL OR EQUIVALENT.

[COLOUR - WHITE]

4. APPROVED BEVELED EDGED MIRROR TO BE FIXED ON WALL

200mm ABOVE FROM WASH BASIN.

5. BIDET SHOWERS TO BE FIXED 600mm ABOVE FROM F.F.L.

SCHEDULE OF FINISHES:

6. ALL CATCH PITS COVER TO BE S/S 316 150x150mm CATCH PIT

7. TOP EDGE OF LAST TILE SHOULD BE COMPLETED WITH P.V.C.

EDGE BEADING.

8. EVERY CORNER JOINTS IN THE WALL TILES OF THE VERTICAL

EDGES TO BE WITH 45 < TAPERED EDGES TO EACH OTHER.

W.B. -

W.C. -

B.S. - BIDET SHOWER

CP. - S/S 316 150x150mm CATCH PIT

S.H. -S/S 316 SOAP

HOLDER

LEGEND

WATER

CLOSET

WASH

BASIN

P.H. - TOILET PAPER HOLDER

TP. - WASH BASIN TAP

MR.1 - 600x750mm BEVEL EDGED MIRROR

FIXED TO WALL WITH 04 NO OF

CHROMIUM PLATED SCREWS

UR. - URINAL

CCP. - CONCEALED TYPE CATCH PIT

(AT URINAL DRAIN)

ARCHITECTS, ENGINEERS AND QUANTITY SURVEYORS

REVISION

D

C

B

A

MARK DATE MADE BY

SEC CONSULTANTS

STATE ENGINEERING CORPORATION OF SRI LANKA

P.O.BOX 194, COLOMBO - 02

CAD : CHAMIL MADUSHAN

ARCHITECT:

DOA :

SCALE : 1:25

CHECKED :

DATE: 2021-06-17

CHIEF ARCHITECT:

DRG NO: [2021-13] / A / 05

PROPOSED ADDITIONS & ALTERATION TO THE

EXISTING BUILDING

FOR OCEAN UNIVERSITY OF SRI LANKA

AT BOOSSA - PHASE 1 OF STAGE 03

CPU NO 255

DETAILS OF TOILETS -TOILET TYPE - T1 AT GROUND FLOOR

SENIOR / PROJECT

ARCHITECT :

Page 164 of 170

Page 165: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Page 165 of 170

Page 166: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Page 166 of 170

Page 167: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Page 167 of 170

Page 168: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Page 168 of 170

Page 169: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Section – 9

Standard Forms (Bid)

Page 169 of 170

Page 170: PROPOSED ADDITIONS AND ALTERATIONS TO AN EXISTING …ocu.ac.lk/wp-content/uploads/2021/07/Boossa-Stage-III... · 2021. 7. 9. · Section 6 - Specifications Section 7 - Bills of Quantities

Please Refer Section 9 In ICTAD Publication No.ICTAD/SBD/01

STANDARD BIDDING DOCUMENT

PROCUREMENT OF WORKS

Second Edition – January 2007

Page 170 of 170