protection & control challenges with distributed...

48
Protection & Control Challenges with Distributed Generation Pankaj Sharma, P Eng. Grid Operations Manager Operating Effectiveness Networks Operating Division Hydro One Networks Inc. July 2015 © 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Upload: others

Post on 24-Oct-2019

10 views

Category:

Documents


0 download

TRANSCRIPT

Protection & Control Challenges

with

Distributed Generation

Pankaj Sharma, P Eng.

Grid Operations Manager Operating Effectiveness

Networks Operating DivisionHydro One Networks Inc.

July 2015

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

OBJECTIVES

Identify major Protection & Control (P&C) Challenges with

Distributed Generation (DG) Connections

Discuss Mitigation of P&C Challenges

Acknowledge advantages of Transfer-Trip (TT) Application

Foster important role of P&C in enabling DG

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Background

Impacts on P&C assets, Challenges & Solutions

Transmission Side

Distribution Side

Operating issues and mitigations

DG Interconnection Protection Challenges

Utility Protection

Advantages of the Transfer Trip

Example of an Islanding event with UFLS operation

Summary

AGENDA

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

DistributionSystem(Dx)

50kV & Below

1. Transmission Station (feeders, buses, transformers etc) 2. Transmission lines

1. Distribution Station Fuses, Transformers, Re-closers etc)

2. Distribution lines

BACKGROUNDOntario T & D

(P&C) Protection & Control

© 2015 Hydro One. All rights reserved.

TransmissionSystem(Tx)

Above 50kV

Operating Effectiveness Hydro One Networks Inc

© 2015 Hydro One. All rights reserved.

Total DG Connected - mid 2015

Wind 473 MWSolar 1236 MW

Bio/CoGen 185 MW

Gas 362 MW Hydro 383 MW

Other (Steam)

226 MW

Micro 115 MW(Each project <

10 KW)

Total Distributed Generation connected at Distribution: 2865 MW

Wind Solar Bio/CoGen Gas Hydro Other (Steam) Micro

Operating Effectiveness Hydro One Networks Inc

© 2015 Hydro One. All rights reserved.

Total DG Connected - mid 2015

Wind3255 MW

Solar140 MW

Total Distributed Generation connected at Transmission: 3395 MW

Wind Solar

Operating Effectiveness Hydro One Networks Inc

DESN

Transformer

Station (TS)

Transmission & Distribution System

Bus A Bus B

Transmission Line 1

Transmission Line 2

F 1

T1 T 2

© 2015 Hydro One. All rights reserved.

Transformer Station (TS)

Fence

Feeder M 2Feeder M 1

Feeder M 3 Feeder M 4

Transmission System

Distribution SystemT4

F 2

F 3

Re-closer

DS TransformerDS Fence

Circuit Breaker

Current Transformer

Fuse

Distribution Station (DS)

Operating Effectiveness Hydro One Networks Inc

Impacts on P&C assetsTransmission Side

Impacts on the Transformer Station (TS)

Feeder protection

Bus protection, Line back-up

Transformer protection, Automatic Voltage Reg

Ground Potential Rise, Neutralizing

Transformer, Neutral Grounding Reactor

Existing Special Protection Schemes (Load

Rejection and Generation Rejection schemes)

Network Management System

Under Frequency Load Shedding

Impacts on the Transmission Line

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Feeder Protection

Feeder Protection De-Sensitization - Upgrades

Feeder Sympathetic trips - Directioning

Out of Phase Re-closing of the Feeder – Transfer-Trip

(TT), and DG End Open Signal (DGEO)

Protection Mis-operation due to DG Transformer

Magnetizing Currents - Low Set Blocking Signal

Protection coordination with downstream devices

Ensure capacity of feeder breaker CT is not exceeded

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Bus Protection

Low impedance Bus differential protection is

not affected but may no longer prove to be

secure

Bus blocking scheme must be reviewed and

may need directioning

Bus blocking scheme is not affected by DG for

faults occurring on the feeder

Bus blocking scheme is affected by DG for faults occurring on the bus

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Bus Blocking Scheme – Feeder Fault

Transmission System

DESN Transformer Station

Feeder 1 Feeder 2

Bus A Bus B

F1 CB opens

Forced Outage

Fault current flows thru feeder

protection and bus protection

CTs. 50B-Abus 50B-Bbus

F1-21 F2-21

Feeder Fault on Feeder F1

Line 1

Line 2

T1 T2

Bus B Protection

I Bbus relay = ∑ IT2 + -IT2 = 0

- Bus B also remains in service.

Bus A ProtectionI Abus relay = ∑ IT1 + IT2 = IF

- 32 ms coordination delay

- F1 block signal prevents trip

Bus A remains in service.

Feeder protection operates, sends

a bus blocking signal to Bus A.

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Bus Blocking Scheme – Bus Fault

Transmission

System

DESN Transformer Station

Feeder #1 Feeder #2

Bus A Bus BCB’s open to

trip Bus A

Forced outage

I Abus relay = ∑ IT1 + IT2

- 32 ms coordination delay

CTs add fault current for Bus A;

Bus A protection operates

I Bbus relay = ∑ IT2 + -IT2 = 0

- Bus B remains in service.

CTs circulates fault current for Bus

B; Bus B remains in service.

Blocking signal was not sent.

Bus Fault with no DG

50B-Abus 50B-Bbus

F1-21 F2-21

Line 1

Line 2

T1 T 250B-Abus 50B-Bbus

F1-21 F2-21

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Bus Blocking – Bus Fault

Transmission

System

Feeder #1 Feeder #2

Bus A Bus B

PROBLEM:

With DG present, CT at bus tie

measures additional DG fault current

which creates an imbalance causing

the protection for the healthy Bus B to

false operate. Bus forced outage is

more widespread than necessary.

CTs add fault current for Bus A;

Bus A protection operates

Forced outage

SOLUTION:

Directioning of B bus

blocking relays will

prevent false operation for

faults on A bus. This allows

faults to be precisely

isolated.

Feeder 2 protection

does not operate

because directioned

thus blocking signal

is not sent

Bus Fault with DG on feeder F2

50B-Abus 50B-Bbus

F1-21 F2-21

DESN Transformer StationLine 1

Line 2

T1 T2

© 2015 Hydro One. All rights reserved.

No fault current at

Feeders of bus A

thus no operation

and blocking signal

not sent

Operating Effectiveness Hydro One Networks Inc

Tra

ns

fer

Tri

p

Lin

e

Pro

tecti

on

s

Lin

e

Pro

tecti

on

s

DESN Transformer Station

Bus ABus B

Line Back-Up ProtectionStation Supplied by Two Transmission Lines

A fault on one transmission line can be

fed by the other transmission line

because the transformer station creates

a path for electric current between the

two lines

Line Protections detect the fault and

respond by taking the line out of service.

Also, a Transfer Trip Signal is sent to the

TS so that the LV CB will open. This cuts

off the electrical path between the two

lines.

In case the Transfer Trip fails however,

line back-up protection is required. Line

back-up is implemented at the station,

and can also signal the LV CB to open

during a line fault.

All TS’s fed by two lines are equipped with

Line Back-Up Protection.

Forced Outage

Line Back-Up

Protection

Tra

nsfe

r

Tri

p

© 2015 Hydro One. All rights reserved.

Line 1

Line 2

T1 T2

M 1 M 2

M 3 M 4

Operating Effectiveness Hydro One Networks Inc

Tra

nsfe

r

Tri

p

Tra

nsfe

r

Tri

pTransformer Station

Bus ABus B

Line Back-Up ProtectionStation Supplied by One Transmission Line

Transformer Stations (TS) that are supplied

by one line and have no DG’s connected

downstream, do not require Line Back-Up

Protection. This is because there is no

current sourcing from within the TS that

can feed the fault on the transmission line.

The fault is managed by the Line

Protections.

Lin

e

Pro

tecti

on

s

Lin

e

Pro

tecti

on

s

Forced Outage

PROBLEM: Once a DG is connected, the

line fault can be fed through the TS by the

DG. It is therefore necessary to send a

Transfer Trip signal to open the DG CB.

SOLUTION: Line Back-Up Protections

must be installed at TS if DGs are

present. This ensures that line fault will

not be fed by DG’s if there is a failure on

the transfer trip.

Line Back-Up

Protection

However, this station does not have Line

Back-Up protections to safeguard

against a Transfer Trip failure. If the

Transfer Trip had failed, the DG would

have fed the fault.

© 2015 Hydro One. All rights reserved.

T1 T2

Transmission Line

M 1 M 2

Operating Effectiveness Hydro One Networks Inc

Transformer P & C

Transformer Differential protection at stations having three winding transformers; needs to be upgraded to provide separate restraint windings

Transformer LV breaker re-closing scheme may need changes (sync-check may be needed)

Restricted ground fault protection may be required if the NGR impedance is increased

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Transformer P & C

Overload protections, monitoring of reverse flows, total current harmonics and winding temperatures may also be required

ULTC voltage regulation may have to be reviewed/changed for reverse P / forward Q flows

Volts/Hertz relay may need to be considered for over-fluxing

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

GPR, NT, NGR

Increased Ground Fault level

increases Ground Potential Rise (GPR)

requires Neutralizing Transformer (NT) voltage rating and spare communications ports to be reviewed – may be replaced with Optical isolator

requires Neutral Grounding Reactor (NGR) size to be reviewed – ohms may have to be increased to respect TSC limits (Transmission System Code)

Location of communication equipment in relay building may have to be re-assessed

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Existing SPS

Review existing Special Protection System (SPS)

Load Rejection (LR) and Generation Rejection (GR) schemes

Modifications may be required

New Generation Rejection Schemes may be required

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Network Management System (NMS)

Upgrades needed to match the changes due to DG

HMI display changes are required at NMS and LCC

Existing Hub sites capacity issue and new sites

Unbundle IED relay failure alarms for selectivity

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Review existing RTU capacities:

Protection alarm points

Telemetry (Amp / MW) and directioning of quantities

Operator control tripping of DG

RTU may not be adequate; upgrades, expansion or even replacements may be required

Upgrade PCMIS to include DG relay settings(Protection & Control Management Information System)

© 2015 Hydro One. All rights reserved.

Network Management System (NMS)

Operating Effectiveness Hydro One Networks Inc

Under Frequency Load Shedding(UFLS)

Review existing UFLS scheme

Re-configure feeder selection in UFLS

Feeders with DG - to be excluded, or

Real time intelligence in selecting feeder under UFLS (dynamic arming), or

Extending UFLS to DS and re-closer level

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Impacts on Transmission Lines

Transmission line protection issues

Consideration of:

Changes due to on-going protection relay replacement programs and/or Tx connected generations

Telecom changes

Impacts on re-closing circuit

Re-closing schemes & timing

Keying of T/T and receiving of DGEO signal

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Transmission Lines Protection Issues

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Non-Overlapping Zone 1 Protections

Enlarged apparent impedance

Current Out feed (Current Reversal)

Non-Overlapping Zone 1 Protections

If zone 1 elements are required not to trip fault beyond new tapped generation CB, the instantaneous zone 1 protection will not be overlapping. The gap area between the reaches of two zone 1s must be protected by teleprotection scheme.

Terminal

Station 1Terminal

Station 2

New Generator

Zone 1Zone 1

Existing customers

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Enlarged apparent impedance

121221111

IG

IZL

ZIIZIZIVZApp

Terminal

Station 1

Terminal

Station 2

New Generator

IG

I1 I2

Z1 Z2

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Current Out feed (Current Reversal)

When a paralleling path exists, the tappedgeneration may cause current reversal. Thedistance element will sense a fault close to theremote station as a backward fault.

Terminal

Station 1

Terminal

Station 2

Existing Generator

IG_2

I1 I2

Z1 Z2

I3

New Generator

IG_1

Z3

L1

L2

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Impacts on P&C assetsDistribution Side

Feeder re-closer controller settings, protection coordination & fuse saving?

Need for HV side automatic interrupting device at DS?

Incorporate blocking scheme?

Un-cleared low level faults between existing HV fuse and station re-closer section?

Sympathetic Tripping - false tripping of a healthy feeder on adjacent feeder faults?

Need for communications at re-closers?

© 2015 Hydro One. All rights reserved. P & C Planning, Network Development & Regional Panning

Planned Outage

DESN

Transformer

Station (TS)

Operating issues and mitigationsISLANDING

Bus A Bus B

Transmission Line 1

Transmission Line 2

F 1

T1 T 2

© 2015 Hydro One. All rights reserved.

Transformer Station (TS)

Fence

Feeder M 2Feeder M 1

Feeder M 3 Feeder M 4

T4

F 2

F 3

Re-closer

DS TransformerDS Fence

Circuit Breaker

Current Transformer

Fuse

Distribution Station (DS)

DG

DG

DG

DG

DG

Operating Effectiveness Hydro One Networks Inc

Overcurrent Protection difficult to set at DG locations.

Inverters - Maximum current about 1.2 p.u., less if DG running at less than max capacity, so there is not enough difference between load and fault for relay to distinguish using over-current

Rely on undervoltage element to trip DG.

Does not always work!!

Faults far away from PCC not visible to DG.

© 2015 Hydro One. All rights reserved.

DG Interconnection ProtectionChallenges

Operating Effectiveness Hydro One Networks Inc

Challenges …

What about Distance Protection?

Zone 1 = 75-80% of Z1

(Instantaneous fault clearance for overlap zone, and high speed trip for rest).

Zone 2 (P) = 120-125% of Max Apparent Impedance.

(High speed or Fast trip for entire line and backed-up with Time Delay trip, usually 400ms).

By setting Zone 2 to 120% of the Max Apparent Impedance for remote 3 phase fault, the relay reach becomes huge.

With interface transformer HV winding ungrounded the ground distance protection not applicable

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Inverters limit fault current & maintain constant power factor dynamically.

Inverters behaviour during fault is important before determining the suitability of the relaying at the DG.

Inverters modeled as a current limiting source

© 2015 Hydro One. All rights reserved.

Challenges …

Operating Effectiveness Hydro One Networks Inc

DG in-feed to a fault anywhere on the Dx can be virtually identical for inverters.

All Dx/Tx faults are in the same direction. Direction cannot be used to avoid tripping for faults on adjacent feeders.

Current only, voltage only or distance cannot be used to avoid tripping for faults on adjacent feeders.

However, distance offers greater precision compared to overcurrent when reach discrimination is required.

© 2015 Hydro One. All rights reserved.

DG Interconnection Protection Typical shortcomings

Operating Effectiveness Hydro One Networks Inc

DG never is certain of the fault location and whether it needs to trip or ride through. Without TT - DG need to delay tripping (at least 150ms) after the utility trips.

Even with the longer delays it is difficult to avoid DG nuisance trips for adjacent feeder permanent faults that are cleared by timed protection elements.

Delay may be too long – due to declining fault infeeds– risk asynchronous reclosing into DG + feeder island.

© 2015 Hydro One. All rights reserved.

DG Interconnection Protection Typical shortcomings

Operating Effectiveness Hydro One Networks Inc

Utility protection has visibility of entire feeder.

Utility feeder protections are capable of selective detection and isolation of all faults on the feeder.

With fault location discrimination it is determined whether or not the DG needs to be tripped for a feeder fault condition.

© 2015 Hydro One. All rights reserved.

Utility Protection

Operating Effectiveness Hydro One Networks Inc

Where current magnitude alone is not sufficient, utility feeder protection use direction to avoid tripping for DG back-feeds to source-side faults (adjacent feeder)

Transfer Trip (TT) can extend utility protection to the DG for fast clearing.

Sequential delay is unavoidable when DG is not capable of detecting feeder faults & there is no TT

© 2015 Hydro One. All rights reserved.

Utility Protection

Operating Effectiveness Hydro One Networks Inc

Adaptive Relaying

Distribution Generation Control Protection (DGCP)

Real Time Automation Controller (RTAC) can provide the mechanism to reconfigure both the sending and receiving protection signals to/from remote field devices and feeder breakers whenever changes occur in the feeder topologies.

The Distribution Management System (DMS) sends topology changes to the DGCP and the DGCP automatically re-configures the protection signals based on the new topology.

Automatically switching setting groups and summing CTs prior to entering or after exiting back-to-back parallel of feeders.

© 2015 Hydro One. All rights reserved.

Utility Protection

Operating Effectiveness Hydro One Networks Inc

Adaptive Relaying …

Blocking the tripping for 44kV reclosers for a loss-of-protection.

Ground backup protection at the DS to open the 44kV recloser at the station for a 27.6/13.8/8.2 kV station recloser failure condition.

The UFLS infrastructure to allow adaptive relaying by evaluating feeder loading conditions by the DMS and having DMS automatically arm selections in real-time at the TS station, 44kV reclosers and 27.6/13.8/8.2 kV DS station reclosers based on the DG generation and loading to satisfy the target load rejection requirement at the TS.

The 27.6/13.8/8.2 kV capacitor banks and voltage regulators can be provided with new controllers and remote control but still switch automatically based on the voltage but with the added remote control switching capability.

© 2015 Hydro One. All rights reserved.

Utility Protection

Operating Effectiveness Hydro One Networks Inc

Advantages of Transfer Trip

© 2015 Hydro One. All rights reserved.

TRANSFER

TRIP

NO

Non-Detection-Zone

Expedites

Restoration Efforts

Facilitates

DGEO, LSBS

TIMELESS

Operates for

Inadvertent Trips

Deterministic,

Most Reliable &

Safest

Fault Ride-

Through Possible

(LVRT, LFRT)

Provides Rapid

Fault Clearance,

Fuse Saving,

Power Quality

Operating Effectiveness Hydro One Networks Inc

M1 M4

M3 M5

M7 M6

R9S R8S

SC1QSC1 SC2

SC2B

BQT2Q T1B

L6L3 TL3 TL1L6L4

L1L4

Q6S (Tx line)

P3S (Tx line) B1S (Tx line)P4S (Tx line)

T2 T1

© 2015 Hydro One. All rights reserved.

Example of an Islanding Event

Operating Effectiveness Hydro One Networks Inc

Sidney TS Configuration

M1 M4

M3 M5

M7 M6

R9S R8S

SC1QSC1 SC2

SC2B

BQT2Q T1B

L6L3 TL3 TL1L6L4

L1L4

Q6S (Tx line)

P3S (Tx line) B1S (Tx line)P4S (Tx line)

T2 T145MW+j9MVar

j21MVar

40A

111A

253A

179A

33A76A

65A27A

DG: 13MWTotal Station Load:

58MW, 30MVAR

G/L: 0.23

45.5k V

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

Pre-Fault Condition

Planned Outage on T1

Pre-fault Statuses of Generators on LV feeders

M1 M4

SC1QSC1 SC2

SC2B

BQT2Q T1B

T2 T1

M3 M5

M7 M6

R8S R9S

Sidney GS

TT: Yes

0.87/2.8

Frankford

TT: No

0.67/2.4

Glen Miler

TT: Yes

1.6/7.2

Sills Island

TT: No

0.65/2.215

Trent Severn

TT: Yes

0/5

Sonoco NUG

TT: No

6.68/7.2

Hagues Reach

TT: No

0.3/3.3

416 Hwy 33

/0.2

Glenburne Farm

/0.25

Hakkesteegt

/0.2

Meyersburg

TT: No

0.84/6

Ranney Falls

TT: No

1.43/10.9

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

M1 M4

M3 M5

M7 M6

R9S R8S

SC1QSC1 SC2

SC2B

BQT2Q T1B

L6L3 TL3 TL1L6L4

L1L4

Q6S

P3S B1SP4S

T2 T1

© 2015 Hydro One. All rights reserved.

Fault Condition

Operating Effectiveness Hydro One Networks Inc

1 2 3 4 5 6 7

© 2015 Hydro One. All rights reserved.

Time

(ms)

f

(Hz)

U

(p.u.)

P

(MW)Events

1 0 115kV Line Q6S Fault cleared, Islanding started

Time

(ms)

f

(Hz)

U

(p.u.)

P

(MW)Events

1 0 115kV Line Q6S Fault cleared, Islanding started

2 130 59.5 0.85 19.7 OPG Generators 81U Pickup

Time

(ms)

f

(Hz)

U

(p.u.)

P

(MW)Events

1 0 115kV Line Q6S Fault cleared, Islanding started

2 130 59.5 0.85 19.7 OPG Generators 81U Pickup

3 153 59.3 0.82 19.6 UFLS Stage 1 Pickup

Time

(ms)

f

(Hz)

U

(p.u.)

P

(MW)Events

1 0 115kV Line Q6S Fault cleared, Islanding started

2 130 59.5 0.85 19.7 OPG Generators 81U Pickup

3 153 59.3 0.82 19.6 UFLS Stage 1 Pickup

4 213 58.8 0.78 19 UFLS Stage 2 Pickup

Time

(ms)

f

(Hz)

U

(p.u.)

P

(MW)Events

1 0 115kV Line Q6S Fault cleared, Islanding started

2 130 59.5 0.85 19.7 OPG Generators 81U Pickup

3 153 59.3 0.82 19.6 UFLS Stage 1 Pickup

4 213 58.8 0.78 19 UFLS Stage 2 Pickup

5 255 58.4 0.74 16 Glen Miler DG Tripped (81U setting: 58.4Hz, 0s)

Time

(ms)

f

(Hz)

U

(p.u.)

P

(MW)Events

1 0 115kV Line Q6S Fault cleared, Islanding started

2 130 59.5 0.85 19.7 OPG Generators 81U Pickup

3 153 59.3 0.82 19.6 UFLS Stage 1 Pickup

4 213 58.8 0.78 19 UFLS Stage 2 Pickup

5 255 58.4 0.74 16 Glen Miler DG Tripped (81U setting: 58.4Hz, 0s)

6 500 56.9 1.05 1.6•Feeder M4, M3, M5, M6, M7 tripped due to UFLS•All DG tripped except Sills Island

Time

(ms)

f

(Hz) (p.u.)

P

(MW)Events

1 0 115kV Line Q6S Fault cleared, Islanding started

2 130 59.5 0.85 19.7 OPG Generators 81U Pickup

3 153 59.3 0.82 19.6 UFLS Stage 1 Pickup

4 213 58.8 0.78 19 UFLS Stage 2 Pickup

5 255 58.4 0.74 16 Glen Miler DG Tripped (81U setting: 58.4Hz, 0s)

6 500 56.9 1.05 1.6•Feeder M4, M3, M5, M6, M7 tripped due to UFLS•All DG tripped except Sills Island

7 1500 48.8 Island Collapsed

Effect of UFLS on Islanding Event

Operating Effectiveness Hydro One Networks Inc

I (R – Φ), Feeder M1

3 I 0 (System, transformers neutral currents)

V (R – W, Φ - Φ), LV Bus

Frequency

P, Feeder M1

Q, Feeder M1

Identify P&C upgrades at Tx and Dx

Detailed P&C assessment should be carried out

Adequate feeder characteristics must be provided to customer to determine relay settings at DG end

DG inter-tie protection design and relay setting must be reviewed for acceptance

Change controls

Feeder Model & Configuration, Short circuit levels and DG equipment changes etc.

© 2015 Hydro One. All rights reserved. Operating Effectiveness Hydro One Networks Inc

SUMMARY and Important Points

Challenges in DG protections relay settings

Depending upon DG type/locations – feeder faults may not be visible to DG protections, issues with O/C & Distance Protection

DG protections have inherent disadvantages

Difficult trade off between DG protection sensitivity and selective – may suffer high number of nuisance trips

Utility feeder protections have advantages

Sensitive, Selective and Deterministic

Advantages of Transfer Trip and Adaptive Relaying to improve DG availability when not required to trip and ensure effective tripping of DGs when required to trip.

© 2015 Hydro One. All rights reserved.

SUMMARY and Important Points

Operating Effectiveness Hydro One Networks Inc

Thank You

© 2015 Hydro One. All rights reserved.

follow-up questions:[email protected] 345 5159 (Tel)416 587 3792 (Mobile)

Operating Effectiveness Hydro One Networks Inc

© 2015 Hydro One. All rights reserved.

The purpose of this presentation is to provide information about some of the issues that Hydro One Networks Inc. (“Hydro One”) has encountered during the process of connection generation facilities to Hydro One’s distribution system. The particular concerns that must be addressed by a generation proponent in respect of the connection of its generation facility to Hydro One’s distribution system will be set out in the Connection Impact Assessment that Hydro One performs or has performed, as the case may be, for such proposed connections and this presentation is not intended to amend, modify or replace same. Hydro One will not be liable or be responsible for any consequences of the use or reliance on the information contained in this presentation.

DISCLAIMER

Operating Effectiveness Hydro One Networks Inc