protection system for the co-generation of … 3/main... · r2 r1 r1 r2 1226 a 1454 a 680 a 271 a...
TRANSCRIPT
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
PROTECTION SYSTEM FOR THE CO-GENERATION OF METHANE GAS CONNECTED TO COPEL’S
DISTRIBUTION GRID – TESTS AND PROCEDURES
Authors :Eloi Rufato Junior – COPEL- USP- UTFPRJulio Shigeaki Omori – COPELMarcos Koehler - COPELDr. Carlos C. Barioni de Oliveira – USP
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
COPEL
3
Área : 199.600 km2
(2,3% del territorio total de Brasil)Población : 9,5 millones
(5,9% de la población brasileña)Urbana: 80 %Rural: 20 %
PIB : R$ 73.800 millones(6,4% del PIB brasileño)
Renta per capita : R$ 7,774
Área :Área : 199.600 km199.600 km22
(2,3% del territorio total de Brasil)(2,3% del territorio total de Brasil)Población :Población : 9,5 millones9,5 millones
(5,9% de la población brasileña)(5,9% de la población brasileña)Urbana: 80 %Urbana: 80 %Rural: 20 %Rural: 20 %
PIB :PIB : R$ 73.800 millonesR$ 73.800 millones(6,4% del PIB brasileño)(6,4% del PIB brasileño)
Renta per capita : R$ 7,774Renta per capita : R$ 7,774
Composición del PIB
Industrial40%
Agrícola14%
Servicios46%
Estado de Paraná
Fuente: IPARDES
Perú
Océano Pacífico Océano Atlántico
BRASIL
PARANA STATE
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
UUU
UUUU
UUUU
U
34,5 kV
69 kVou
138 kV
13,8 kV
UU UUU UUU U
UU UUU UUU U
SD’s
SD’s
SD’s
SD’s
SD’s
13,8 kV
13,8 kV
34,5 kV34,5 kV
SD’sSD’s
34,5 kV
AREAS OF RESPONSABILITY OF PROTECTION
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
DISTRIBUTION SYSTEM
• Substation : 34,5 kV/13,8 kV• Transformers : Grounded Star at the 34,5 kV
/ Delta with ground transformer in Zig-Zag at the 13,8 kV side.
• Powers of Transformers : 4,2 MVA, 5MVA and 7 MVA.
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
PROTECTION and DISTRIBUTION LINES
• SUBSTATION:• Recloser and Circuit Breaker with Relay• DISTRIBUTION LINES:• Reclosers and Fuses• Reclosers: Hydraulics, Electro-mechanic,
Electronics and Micro processed.
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
TYPES OF RECLOSER CONTROLS
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
PROTECTION CONFIGURATION
0,4 A
v v v v v v
v
v
v
I cc min
v
I cc máx
R
1
2 3
4
Iccmáx Iccmín
R
R1R2
R1R2
1226 A
680 A1454 A
271 A
35 A
35A 1968A
CIRCUITS
UUUUUUUU
TF
TF UU UUUUUU
UU UU
UUUU
TA
34,5KV 13,8KV
0,4A
Ts
R1
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Points of Connection of the Small Generators in the Distribution
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
THE PROJECT• Generate electric power in biodigestors using pig
slurry• Generate power with methane gas yielded by the
decomposition of collected organic matter• To enable the connection of this type of distributed
power to COPEL’s grid there are some special measures that must be taken to protect the electric system and ensure safety
• Low-power operating systems, it was not feasible to equip them with the protection systems in place on larger generators.
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
THE PROJECT• The project has been developed and monitored for a
year in a small rural property in the Foz do Iguaçu-Granja Colombari
• The main environmental problem ensuing from pig-raising is the phosphorus-rich pig slurry that is the main nutrient of what is called “blue algae” contaminates and deteriorates water
• If it touches the skin can cause serious health problems to human beings and animals alike.
• The property where the tests were run, electric capacity for power generation is 50 kilowatts–enough to generate power for 100 homes.
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
THE INSTALATIONS
• PIG INSTALATIONS
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
THE INSTALATIONS
• BIODIGESTOR • GENERATOR
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Problems Ensuing from Small Generators Operating Under Islanding
• Operational safety• Personal safety - Affecting distribution
companies and third parties• Causing Technical and Commercial
problems - Voltage and Frequency• Legal problems (Law)
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Vector Jump Relay - 78• Installed to operate the generator’s circuit-
breaker coupling to the distribution system• Operation Principle:• Angle displacement of the phase between
the generator’s internal voltage “Eg” and the voltage at the generator’s terminals“Vtg”
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
CONFIGURATION UNDER STUDY• The 34.5kV distribution system that was tested is
located in the Foz do Iguaçu – Cacic feeder
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Protection System to Connect Generators to 34.5 kV Feeders
• The interconnection functions protection used in thisPilot Tests were:
Overcurrent inst. and timed – 50/51 – 50/51NOver-voltage (3 phases) – 59Under-voltage (3 phases) - 27Over and Under Frequency – 81 O/UTime Relay - 62 Synchronism Check Relay – 25Vector Jump – 78
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Protection Functions
• The diagram shows the minimum protection and trip points for coupling small-size generators to COPEL’sDistribution System
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
LAB TESTS• Tests were carried out using ATP -
developed cases• Operating conditions and Short-circuit tests
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Case 1-Phase-Ground Short-Circuit• ANTICIPATED RESULT: Generator’s circuit-breaker protections should be triggered• TEST RESULT- Circuit-breaker was opened when the Vector Jump relay was
triggered, with 89 ms
CHANNEL OSCILLOGRAPH
-CHANNEL 1, 2 and 3: Tensions A, B and C of the Generator -CHANNEL 4, 5 and 6: Currents A, B and C of the Generator -CHANNEL 7 and 8:CB - KC (Feeder) and KG (Generator)
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Case 2-Phase-Ground Short-Circuit with Fault Impedance - ZF
• ANTICIPATED RESULT: Generator’s circuit-breaker protections should be triggered• TEST RESULT- Circuit-breaker was opened when the Vector Jump relay was
triggered, with 76 ms
CHANNEL OSCILLOGRAPH
-CHANNEL 1, 2 and 3: Tensions A, B and C of the Generator -CHANNEL 4, 5 and 6: Currents A, B and C of the Generator -CHANNEL 7 and 8:CB - KC (Feeder) and KG (Generator)
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
FIELD TESTS
• After lab test results were approved• Panel with protection equipment was installed • Short-circuit and anomaly tests and real
simulations were run on COPEL’s distribution system
• Nine field tests were scheduled and run
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Phase-Ground short-circuit test performed at the São Vicente Feeder
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Equipment Installation
• Feeder Installation - Generator Installation
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
TEST RESULTS• Test 4 consist in mounting the generating unit in
parallel with COPEL’s distribution grid• ACTION: Cause a single-phase short-circuit on the
34.5 kV distribution grid – source side• ANTICIPATED RESULT– Protections on the
generator’s are triggered before the feeder recloser automatically.
• TEST RESULT – Circuit Breaker was opened when the Vector Jump (78) relay was triggered, with 61 ms operating time, before the recloser time
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Oscillography Result
(78) Tripped
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
Summarized Results• Opening time and which protection was
triggered when field tests were run
Prague, 8-11 June 2009COPEL
ELOI RUFATO JUNIOR-Brazil-Session3-Paper ID 0199
CONCLUSIONS• Based on the study of the oscillograms and
measurement results from field tests, it is shown that 90% of the tests were run under the protection of “Vector Jump”
• Time of operation of protection units were 60-80 milliseconds, this time is before the recloser operation.
• Considering that is a low-cost type of protection (Vetor Jump) compared to a complete protection system for generator connection in parallel with distribution systems, Copel’s use this protection for a motor-generator unit run on methane gas.
• Create a new Standards for this Connections