provident kenworth
TRANSCRIPT
Tower 1
TOWER
STATUS
• Door & Window work in
progress.
• Stilt floor column & shaft
plastering in progress.
• MEP work in progress.
• External painting work in
progress.
• Lift gladding work in
progress.
MILESTONES
ACHIEVED
• Door work started.
• External plaster 100%
completed.
UPCOMING
MILESTONES
• 1st coat painting will complete
116 flats.
• External paint 1st coat complete.
• Lift gladding 100%.
• Bison board & false ceiling 100%.
• Stilt 100% columns plaster.
• Terrace OTS covering 100%.
PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Tower 2
TOWER
STATUS
• External plastering in
progress.
• Tile work in progress.
• Water proofing in
progress.
MILESTONES
ACHIEVED
• External plaster completed 45%.
• Toilet waterproof 220 flats completed.
• Lift wall & Duct wall plaster
completed.
• Tile dado 80 flats completed.
• Floor tile 11 flats completed.
UPCOMING
MILESTONES
• External plaster 100% complete.
• Waterproofing 100% complete.
• Toilet dada up to 100 flats
complete.
• Floor tile work up to 40 flats
complete.
• 2nd coat putty 100% complete.PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Tower 3
TOWER
STATUS
• External plastering work
in progress.
• Putty work in progress.
• Tile work in progress.
• Stilt floor material
removing work in
progress.
MILESTONES
ACHIEVED
• External plaster 80% completed.
• Putty work 12 flats completed.
• Tile work 57 flats completed.
• External primer 60% completed.
UPCOMING
MILESTONES
• External plaster 100% complete.
• Putty work complete up to 5th floor.
• Tile work complete 60 flats.
• External primer 100% complete.
PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Tower 4
TOWER
STATUS
• Door fixing work in progress.
• Lift gladding work in
progress.
• Stilt floor columns &
basement columns
plastering in progress.
• Stilt floor material removing
work in progress.
MILESTONES
ACHIEVED
• Putty work completed.
UPCOMING
MILESTONES
• Service lift gladding complete.
• Stilt floor Screed complete.
PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Tower 5
TOWER
STATUS
• Tile work in progress.
• Putty work in progress.
• Internal plaster in progress.
• Stilt floor Block work in
progress.
MILESTONES
ACHIEVED
• Tile work completed 17 flats.
• Internal plaster 118 flats completed.
• 1st coat putty 118 flats completed.
• Lift waterproofing completed.
• External plastering 100% completed.
• External primer 70% completed.
UPCOMING
MILESTONES
• Tile work complete up to 3rd floor.
• Stilt floor columns plaster & wall
plaster complete 100%.
• Putty work complete 100%.
• Lift Plaster complete 100%.
• External primer 100% complete.
PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Tower 6
TOWER
STATUS
• Internal plastering in
progress.
• Tile work in progress.
• Putty work in progress.
• Lift block work in progress.
• Stilt floor columns plastering
in progress.
MILESTONES
ACHIEVED
• Tile work completed 40 flats.
• Putty completed 110 flats.
• Internal plastering 95% completed.
• Lift block work 90% completed.
UPCOMING
MILESTONES
• Tile work complete up to 6th floor.
• Stilt floor columns plaster complete 100%.
• Putty work complete 100%.
• Lift Plaster complete 100%.
PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Tower 12
TOWER
STATUS
• External plastering in
progress 7th series OTS.
• 1st & 2nd floor flat inside
1st coat putty work in
progress.
• Common area internal
plastering in progress.
• Toilet waterproofing &
screed work in progress.
• Toilet tile marking & rough
plastering in progress.
MILESTONES
ACHIEVED
• Toilet wall Rough plastering up to
6th floor.
• Internal putty work completed 5 flats.
• External plastering 8 series
completed.
UPCOMING
MILESTONES
• 1st coat putty complete 2nd to 6th floor.
• Tile work complete 36 flats.
• Toilet rough plaster 100% complete.
• External wall plaster 100% complete.
PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Tower 13
TOWER
STATUS
• Above terrace OHT wall, &
slab work in progress.
• Terrace floor screed
concrete in progress.
• External plastering in
progress.
• Block work in progress in
10th floor.
• Internal Wall & ceiling
plaster in progress.
• Toilet waterproofing &
screed work in progress.
MILESTONES
ACHIEVED
• Toilet waterproofing completed up to
3rd floor.
• Internal wall plaster completed 90 flats.
• Flats ceiling work completed 140 flats.
• External plastering 13 & 14 series
completed.
UPCOMING
MILESTONES
• Flats ceiling plaster complete 100%.
• Toilet waterproofing complete up to 6th floor.
• Toilet screed complete up to 6th floor.
• External plastering complete 30%.
• Internal wall plaster complete up to 8th floor.
• ALL OHT complete.
PROGRESS TIMELINE
Actual site photograph
Construction Updates
April 21 May 21 June 21
Site Office :Provident Kenworth
6-1-33, Inner Ring Rd, Shivrampalli Village, Shivarampally Jagir,
Hyderabad, Telangana 500052
Regional Office :Provident Housing Limited
No.8, Ulsoor Road, Bengaluru- 560 042
Tel: 080-44555544
Email : [email protected] (Subject line – Project name/ unit number)
Call Us : +91 - 80-67724001 / 1 860 208 0000
Web : www.providenthousing.com