PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 1/59

PS Project Manager Training

Project Systems - Project Manager Training

Course Purpose

Project Manager Training demonstrates how to plan,

monitor and manage capital project costs.

Page 2: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 2/59

Course Map

Project Manager Training Overview

Page 3: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 3/59

Project Systems Process Flow

1 - The capitalized costs of capital projects during construction, assembly, or customization.

2 - The asset(s) to which the costs in an Asset Under Construction (AUC) are capitalized when a capital

project is completed.

3 - Deliverables, or tangible products, structured in descending levels to provide increasingly detailed

definitions of the top element. Components of the Work Breakdown Structure. Costs and revenues

post to WBS elements.

1 2

3

Page 4: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 4/59

Roles and Responsibilities

Financials - Inputs and Outputs

1 - The capital projects capitalized costs during construction, assembly, or customization.

Page 5: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 5/59

Financials - Inputs

When you buy something, work on project related

tasks, or move inventory for use on a project,

those costs are posted to the related WBS element

within the defined project.

Time Entry (labor) costs post automatically during

the payroll posting process.

The costs then display as an expenditure for the

overall project.

Financials - Posting

Page 6: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 6/59

Financials - Inputs

Inputs may also come from periodic costs incurred through

project planning corrections and any overhead interest charged.

Financials - Outputs

Rendered costs are then capitalized through

settlements to Assets Under Construction (AUCs).

The total of all AUCs represent the balance in the

Construction-in-Progress account at the end of an

accounting period.

At the end of a project, AUCs are capitalized to

Final Depreciating Assets (FDAs). FDAs depreciate

over their useful life for full-accrual accounting

purposes.

Page 7: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 7/59

Capital Project Manager Tasks

Work Breakdown Structure and Elements

Page 8: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 8/59

Work Breakdown Structure Purpose

The Work Breakdown Structure (WBS) is a hierarchy of

tasks and deliverables that must be performed to

complete a project.

Work Breakdown Structure role:

Partition the major project deliverables into smaller

components to improve the accuracy of cost estimates

Provide a mechanism for collecting and organizing actual

costs

Capital Project Structure

1 - The project definition contains dates and organizational information that are binding for the entire

project.

Page 9: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 9/59

Capital Project Structure

Capital Project Structure

Page 10: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 10/59

Display Project Structure Overview - CN41

Work Breakdown Structure

Use transaction CN41 to view the project structure.

This transaction displays the structure and numbering

system in a tree format allowing the display of single

elements as well as the ability to add and subtract

specific details.

Page 11: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 11/59

CN41 - Enter Profile

CN41 - Enter Profile

Page 12: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 12/59

CN41 - Display Structure

CN41 - Enter Project Number

Page 13: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 13/59

CN41 - Execute the Report

CN41 - Structure Overview

Page 14: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 14/59

CN41 - Add Reporting Fields

CN41 - Select Display Fields

Page 15: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 15/59

CN41 - Select Display Fields

CN41 - Select Display Fields

Page 16: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 16/59

CN41 - Select Display Fields

CN41 - Select Display Fields

Page 17: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 17/59

CN41 - Structure Overview

WBS Elements

Individual tasks and deliverables in the Work

Breakdown Structure are called WBS elements.

There are two types of WBS elements:

Parent Nodes - elements that roll-up data

Children Nodes - elements that contain data,

including: budgets, plans, encumbrances and

actual costs

Page 18: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 18/59

CN43N - WBS Element Overview

CN43N - WBS Element Overview

Page 19: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 19/59

CN43N - WBS Element Overview

CN43N - Enter WBS Element(s)

Page 20: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 20/59

CN43N - Enter WBS Element(s)

CN43N - WBS Element Overview Report

Page 21: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 21/59

CN43N - WBS Element Overview Report

CN43N - Report Column Review

Page 22: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 22/59

CN43N - Report Column Review

CN43N - System Status

The Status column displays the current system status for each WBS

element. These status are set only by the Project Accountant:

CRTD = WBS element created, but not released for accounting

REL = WBS element released for accounting

SETC = settlement rule created

Page 23: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 23/59

CN43N - Additional Report Functionality

Page 24: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 24/59

Project Cost Planning and Reporting

Project Cost Planning

Project cost planning allows financial planning at

any level of the work breakdown structure over

any number of years.

Entering project cost planning equal to the total

current year project budget enables the Project

Manager to track the incoming costs against the

allocated project costs. These inputs can be

distributed throughout the entire work

breakdown structure for the life of the project.

Use transaction CJ40 to enter a project cost plan.

Page 25: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 25/59

CJ40 - Initial Screen

CJ40 - Initial Screen

Page 26: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 26/59

CJ40 - WBS Element Overivew

CJ40 - WBS Element Overivew

Page 27: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 27/59

CJ40 - Cost plan

CJ40 - Enter cost plan

Page 28: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 28/59

CJ40 - Enter cost plan

CJ40 - Next Year

Page 29: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 29/59

CJ40 - Enter next year's cost plan

CJ40 - Total Up

Page 30: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 30/59

CJ40 - Total Up

CJ40 - Total Up

Page 31: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 31/59

CJ40 - Total Up

CJ40 - Cost plan 2010 Total Up

Page 32: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 32/59

CJ40 - Column Review: Distributed

1 - The distributed value is the result of the plan values in the subordinate objects. In the cost planning

of projects, the distributed value is the total of structure plan values, cost element plan values and

unit costings in WBS elements directly subordinate to the one displayed.

1

Page 33: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 33/59

CJ40 - Column Review: Distributable

1 - The distributable value is the difference between the plan value and the distributed value.

Page 34: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 34/59

CJ40 - Column Review: Planned Total

1 - Plan total is the annual or overall plan value including existing values from unit costing and

cost element planning. In the cost planning of projects, the plan total also includes the plan total

for all orders and networks assigned to the chosen WBS element and those subordinate to it.

Page 35: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 35/59

CJ40 - Column Review

CJ40 - Column Review: Previous year

Page 36: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 36/59

CJ40 - Column Review: Cumulative

CJ40 - Annual Overview

Page 37: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 37/59

CJ40 - Annual Overview

Project Cost Reporting

An important task for all Project Managers is to

monitor project costs. With SAP, Project Managers

can compare planned costs to actual costs and

commitments in order to ensure that projects are

delivered within budget.

To run a project cost report, use transaction

S_ALR_87013533.

Page 38: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 38/59

S_ALR_87013533 - Run Project Cost Report

S_ALR_87013533 - Run Project Cost Report

Page 39: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 39/59

S_ALR_87013533 - Run Project Cost Report

S_ALR_87013533 - Overview

Page 40: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 40/59

S_ALR_87013533 - Overview

S_ALR_87013533 - Overview

Page 41: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 41/59

S_ALR_87013533 - Year Review

S_ALR_87013533 - Year Review

Page 42: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 42/59

S_ALR_87013533 - Year Review

S_ALR_87013533 - Column Review: Plan

Page 43: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 43/59

S_ALR_87013533 - Column Review: Actual

S_ALR_87013533 - Column Review: Commitment

Page 44: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 44/59

S_ALR_87013533 - Column Review: RemOrd

S_ALR_87013533 - Column Review: Assigned

Page 45: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 45/59

S_ALR_87013533 - Column Review: Available

S_ALR_87013533 - Report Detail: Call Up Report

Page 46: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 46/59

S_ALR_87013533 - Call Up Report: Viewing Actuals

S_ALR_87013533 - Call Up Report: Viewing Actuals

Page 47: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 47/59

S_ALR_87013533 - Call Up Report: Viewing Actuals

S_ALR_87013533 - Call Up Report: Viewing Actuals

Page 48: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 48/59

S_ALR_87013533 - Call Up Report: Viewing Actuals

S_ALR_87013533 - Call Up Report: Viewing Commitments

Page 49: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 49/59

S_ALR_87013533 - Call Up Report: Viewing Commitments

S_ALR_87013533 - Call Up Report: Viewing Commitments

Page 50: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 50/59

S_ALR_87013533 - Call Up Report: Viewing Commitments

S_ALR_87013533 - Call Up Report: Viewing the Plan

Page 51: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 51/59

S_ALR_87013533 - Call Up Report: Viewing the Plan

S_ALR_87013533 - Call Up Report: Viewing the Plan

Page 52: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 52/59

S_ALR_87013533 - Call Up Report: Viewing the Plan

Additional Information

To learn more about Costing reports and how to

manipulate these reports, visit the SAP Learning Center

website:

www.portlandoregon.gov/saplc

Page 53: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 53/59

System Status

Capital project activities and postings are controlled by

system and user status.

System status determines which business transactions

can be performed within the work breakdown structure

and when WBS elements can be used. Only Project

Accountants can set the system status.

Page 54: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 54/59

User Status

Project Managers set the user status which

complements the system status.

User status flags the project for a specific purpose.

Use status CMPL - Project Complete to signal to

the Project Accountant that the project is complete

and ready to transfer assets under construction

(AUC) to final depreciating assets (FDA).

To set the user status, use transaction CJ20N.

CJ20N - Set User Status

Page 55: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 55/59

CJ20N - Enter Project Number

CJ20N - Project Builder

Page 56: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 56/59

CJ20N - Set User Status

CJ20N - Set User Status

Page 57: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 57/59

CJ20N - Set User Status

CJ20N - Set User Status

Page 58: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 58/59

CJ20N - Set User Status

CJ20N - Set User Status

Page 59: PS Project Manager 2013

PS Project Manager Training Work Instruction Guide

November 2013 SAP Project Systems (PS) Module 59/59

CJ20N - Saving User Status