Nuclear Development 244 Chestnut Street, Salem, NJ 08079 O PSEG Power LLC ND-2012-0024 March 29, 2012 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Subject: PSEG Early Site Permit Application Docket No. 52-043 Response to Request for Additional Information, RAI No. 59, Population Distribution References: 1) PSEG Power, LLC letter to USNRC, Application for Early Site Permit for the PSEG Site, dated May 25, 2010 2) RAI No. 59, SRP Section: 02.01.03 - Population Distribution, dated March 1, 2012 (eRAI 6255) 3) PSEG Power, LLC letter to USNRC, ND-2011-0039, PSEG Power, LLC, Response to Request for Additional Information, RAI No. 21, Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information (RAI) identified in Reference 2 above. This RAI addresses Population Distribution, as described in Subsection 2.1.3 of the Site Safety Analysis Report (SSAR), as submitted in Part 2 of the PSEG Site Early Site Permit Application, Revision 0. Enclosure 1 provides our response for RAI No. 59, Question No. 02.01.03-7. Enclosure 2 includes the revisions to SSAR Subsection 2.1.3 resulting from our response to RAI No. 59, Question No. 02.01.03-7. Enclosure 3 includes the new regulatory commitments established in this submittal. If any additional information is needed, please contact David Robillard, PSEG Nuclear Development Licensing Engineer, at (856) 339-7914. 9

Upload: others

Post on 13-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

Nuclear Development244 Chestnut Street, Salem, NJ 08079

O PSEGPower LLC

ND-2012-0024March 29, 2012

U.S. Nuclear Regulatory CommissionATTN: Document Control DeskWashington, DC 20555-0001

Subject: PSEG Early Site Permit ApplicationDocket No. 52-043Response to Request for Additional Information, RAI No. 59,Population Distribution

References: 1) PSEG Power, LLC letter to USNRC, Application for Early Site Permitfor the PSEG Site, dated May 25, 2010

2) RAI No. 59, SRP Section: 02.01.03 - Population Distribution, datedMarch 1, 2012 (eRAI 6255)

3) PSEG Power, LLC letter to USNRC, ND-2011-0039, PSEG Power,LLC, Response to Request for Additional Information, RAI No. 21,Population Distribution, dated June 7, 2011

The purpose of this letter is to respond to the request for additional information (RAI)identified in Reference 2 above. This RAI addresses Population Distribution, asdescribed in Subsection 2.1.3 of the Site Safety Analysis Report (SSAR), as submittedin Part 2 of the PSEG Site Early Site Permit Application, Revision 0.

Enclosure 1 provides our response for RAI No. 59, Question No. 02.01.03-7. Enclosure2 includes the revisions to SSAR Subsection 2.1.3 resulting from our response to RAINo. 59, Question No. 02.01.03-7. Enclosure 3 includes the new regulatorycommitments established in this submittal.

If any additional information is needed, please contact David Robillard, PSEG NuclearDevelopment Licensing Engineer, at (856) 339-7914.

Uý 9

Page 2: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

U. S. Nuclear RegulatoryCommission

2 3/29/12

I declare under penalty of perjury that the foregoing is true and correct. Executed onthe 29th day of March, 2012.

Sincerely,

James MallonEarly Site Permit ManagerNuclear DevelopmentPSEG Power, LLC

Enclosure 1:

Enclosure 2:

Enclosure 3:

Response to NRC Request for Additional Information, RAI No. 59,Question No. 02.01.03-7, SRP Section: 02.01.03 - PopulationDistributionProposed Revisions, Part 2 - Site Safety Analysis Report (SSAR),Subsection 2.1.3 - Population DistributionSummary of Regulatory Commitments

cc: USNRC Project Manager, Division of New Reactor Licensing, PSEG Site(w/enclosures)USNRC Environmental Project Manager, Division of Site and EnvironmentalReviews (w/enclosures)USNRC Region I, Regional Administrator (w/enclosures)

Page 3: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

PSEG Letter ND-2012-0024, dated March 29, 2012

ENCLOSURE 1

RESPONSE to RAI No. 59

QUESTION No.02.01.03-7

Page 4: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

Response to RAI No. 59, Question 02.01.03-7:

In Reference 2, the NRC staff asked PSEG for information regarding the PopulationDistribution, as described in Subsection 2.1.3 of the Site Safety Analysis Report. Thespecific request for Question 02.01.03-7 was:

10 CFR 52.17(a)(1)(viii), 10 CFR 100.21(h), NUREG-0800, SRP Section 2.1.3,Subsection Ill (Review Procedures), item 5 (Population Density) establish theneed for an evaluation of the population density in the vicinity of the site.Regulatory Position C. 4 of Regulatory Guide (RG) 4.7 specifies, among otherthings, a threshold population density criterion of 500 persons per square mile(per/sq-mi) averaged over any radial out to 20 miles.

In a June 7, 2011, response to RAI No. 21, Question 02.01.03-1, the applicantprovided information pertaining to item (e) and stated that the 2018 populationdensity at 20 miles is 494 per/sq-mi. This projection approaches the criteriaprovided in RG 4.7 (500 per/sq-mi).

The applicant also stated that an Alternative Site Evaluation was performed insupport of the siting determination for the Early Site Permit effort, and made areference to the Environmental Report (ER), Section 9.3. In addition to thisreference, the staff requests that the applicant also present rationale andjustification in the selection of this high population density site, by providinginformation regarding the Alternative Site Evaluation analysis summary andconclusion in SSAR, Section 2.1.3. of the application.

PSEG Response to NRC RAI:

As requested, a summary of the Alternate Site Evaluation discussed in detail in ERSection 9.3, will be added to SSAR Subsection 2.1.3.6.

Associated PSEG Site ESP Application Revisions:

Enclosure 2 includes a markup of the proposed revisions to SSAR Subsection 2.1.3.6per RAI No. 59, Question 02.01.03-7, which supersedes RAI No. 21, Question02.01.03-1 "Insert 2", as provided in Enclosure 2 of Reference 3.

Enclosure 1 Page 1

Page 5: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

PSEG Letter ND-2012-0024, dated March 29, 2012

ENCLOSURE 2

Proposed Revisions

Part 2 - Site Safety Analysis Report (SSAR)Subsection 2.1.3 - Population Distribution

Marked-up Page2.1-8

Page 6: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

2A1 REFERENCS

2-1-1 The Oelaware Population Consortium (DPC). Annual Populaton Pro"cnson DoaeTables. Version 2008.0 (Encel),hA elo nuar.opatonklec wkiwkxshln-d_ October 31,2008. accessed May 18. 2009.

2.1-2 KLD Engineering, PC, Salem and Hope Creek Nucleer Genera&V Stada,Development of Evacuation Time Eslimalee. Commacd, New York, 2009.

2.1-3, Mania, proftde based on data ptovied by Dun anw Bradstreet accessed on June112009MAir Liquide America LP wAutotypehldin (USA). Inc. Nw~w • c nJ l

Detetar Techialogqekw Inc- httmL&0fJ j fw lw " tMm29dkLelke CapoMralon h -D --/wrmnta.onVeomp&nh*=mwvOMemorial Houital of Salem County. Inc.ftftOIhw mantacoicwis2fQbcmpanyv dvl 1y

21-4 Maryland State Data Center, 2009 Population Projeclons, Projections by Tpe forAll Counlew - Hiasoric Census 1970 to 2000, Projected 2006 to 2030, PopilanProjections; XLS. Poomrplhtm. amassedMay 18, 2009

2,t-6 Nation Paik Servie. Division of Ecoufrcs U.S. Fish and Wildlife Service,8lwnJg oan Na"r 2004.* Septenber 2005. Division of Ecofnlo cs U.S. Fish and

Rev. 02.1-8

Enclosure 2 Page 1

Page 7: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

RAI No. 21. Queston 02.01 03.l(bl. insed 1

w Dub ntiab kui ercm of Ian"* PoouMion betwwnn 10 and 50 mi, fromt9. PSEG Shh kincude COvmna Malla a sftccoe mag Woald in Nowak. D[wre.wt rmrm, anmnxkwmtv 1730.0Q0 amuni yvim: ma Daware Pmk. a casno and

raoeIra* boNd in Wm*uio. De~W~met #mxfta apmxhoev 2,MO,000 WmaW

Repboe RAI No. 21.Qus 02.01.03-7 .:

RAI N, 59. o_',on

-NR Ronft Iud NM J th u h ,kolU"0-10-

ofr a Pae 2tshoudbe Mdtoadewl o00 or s.ertI

y"r 2 w Pag 2~ prmw 00Gosows.m o t ao

Encd

Page 8: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

iiii Ii!t|.'ii

Flll

IIIIII

IIIIiHIiIIiiii0

IIIIiIi0

C%

4

0)

a- 0)

Page 9: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

PSEG Letter ND-2012-0024, dated March 29, 2012

ENCLOSURE 3

Summary of Regulatory Commitments

Page 10: PSEG Early Site Permit Application, Response to Request ... · Population Distribution, dated June 7, 2011 The purpose of this letter is to respond to the request for additional information

ENCLOSURE3

SUMMARY OF REGULATORY COMMITMENTS

The following table identifies commitments made in this document. (Any otheractions discussed in the submittal represent intended or planned actions. Theyare described to the NRC for the NRC's information and are not regulatorycommitments.)

COMMITMENT COMMITTED COMMITMENT TYPEDATE ONE-TIME PROGRAMMATIC

ACTION (YES/NO)(YES/NO)

PSEG will revise This revision will be Yes NoSSAR Subsection included in a future2.1.3 to update of the PSEGincorporate the ESP application.changes inEnclosure 2 inresponse to NRCRAI No. 59,Question No.02.01.03-7.

Enclosure 3 Page 1