pseg fossil llc and pseg nuclear llc - scotusblog€¦ · 7/3/2008  · during the summer of 2006,...

26
Nos. 07-588, 07-589 & 07-597 IN THE ~ ENTERGY CORPORATION V. EN VIRONMENTAL PgOTECTiON AGENCY, ET AL. PSEG FOSSIL LLC AND PSEG NUCLEAR LLC V. RIVERKEEPER, INC., ET AL. UTILITY WATER ACT GROUP v. RIVERKEEPER, INC., ET AL. ON PETITIONS FOR A WRIT OF CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT BRIEF FOR THE NUCLEAR ENERGY INSTITUTE AS AMICUS CURIAE SUPPORTING PETITIONERS ELLEN C. GINSBERG MICHAEL A. BAUSER iN UCLEAR ENERGY INSTITUTE 1776 I Street, N.W. Washington, D.C. 20006 (202) 739-8000 SETH P. WAXMAN Counsel of Record " - EDWARD C. DUMONT BRIAN M. BOYNTON WILMER CUTLER PICKERING HALE AND DORR LLP 1875 Pennsylvania Ave., N.W. Washington, D.C. 20006 (202) 663-6000

Upload: others

Post on 26-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

Nos. 07-588, 07-589 & 07-597

IN THE ~

ENTERGY CORPORATION

V.

EN VIRONMENTAL PgOTECTiON AGENCY, ET AL.

PSEG FOSSIL LLC AND PSEG NUCLEAR LLC

V.

RIVERKEEPER, INC., ET AL.

UTILITY WATER ACT GROUP

v.

RIVERKEEPER, INC., ET AL.

ON PETITIONS FOR A WRIT OF CERTIORARI TO THE

UNITED STATES COURT OF APPEALSFOR THE SECOND CIRCUIT

BRIEF FOR THENUCLEAR ENERGY INSTITUTE

AS AMICUS CURIAE SUPPORTING PETITIONERS

ELLEN C. GINSBERGMICHAEL A. BAUSERiN UCLEAR ENERGY

INSTITUTE1776 I Street, N.W.Washington, D.C. 20006(202) 739-8000

SETH P. WAXMAN

Counsel of Record" - EDWARD C. DUMONT

BRIAN M. BOYNTONWILMER CUTLER PICKERING

HALE AND DORR LLP1875 Pennsylvania Ave., N.W.Washington, D.C. 20006(202) 663-6000

Page 2: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

TABLE OF CONTENTS

Page

TABLE OF AUTHORITIES ...........................................ii

INTEREST OF AMICUS CURIAE ...............................1

INTRODUCTION AND SUMMARY OFARGUMENT ............: ...................................................2

ARGUMENT .......................................................................4

I. NUCLEAR POWER PROVIDES A CRITICALPORTION OF THE NATION’S ENERGY SUP-PLY, PARTICULARLY IN LIGHT OF CLIMATECHANGE .........................................................................4

II. THE COURT OF APPEALS’ DECISION COULDFORCE RETROFITTING AT EXISTING NU-CLEAR PLANTS, EVEN IF INDEPENDENTREGULATORS WOULD OTHERWISE CON-CLUDE THAT COSTS WHOLLY OUTWEIGHBENEFITS .......................................................................7

III. MANDATING USE OF CLOSED-CYCLECOOLING AT EXISTING NUCLEAR PLANTSWOULD HAVE SIGNIFICANT ADVERSE EF-FECTS ON THE NATION’S POWER SUPPLY--AND ON THE ENVIRONMENT ....................................11

A. Mandating That Existing Plants BeRetrofitted To Use Closed-Cycle Cool-ing Would Reduce The Nation’s SupplyOf Nuclear Power ................................................11

B. Reducing The Supply Of NuclearPower Will Have Substantial AdverseEffects Both On The Energy SupplyAnd On The Environment .................................17

CONCLUSION .................................................................21

Page 3: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

ii

TABLE OF AUTHORITIES

CASESPage(s)

Chevron U.S.A. Inc. v. Natural Resources De-fense Council, Inc., 467 U.S. 837 (1984) ....................9

Massachusetts v. EPA, 127 S. Ct. 1438 (2007) ................6

Riverkeeper, Inc. v. EPA, 475 F.3d 83 (2d Cir.2007) .....................................................................8, 9, 10

STATUTES AND REGULATIONS

16 U.S.C. § 8240 ...................................................................4

33 U.S.C.§ 1314 ..............................................................................9§ 1316 ..............................................................................9§ 1326 ..............................................................................7

10 C.F.R.§ 50.59 ...........................................................................12§ 50.91 ...........................................................................12

National Pollutant Discharge EliminationSystem--Final Regulations To EstablishRequirements for Cooling Water IntakeStructures at Phase H Existing Facilities,69 Fed. Reg. 41,576 (July 9, 2004) ...................passim

ADMINISTRATIVE AUTHORITIES

Comments of Department of Energy, CommentID 316bEFR.010.028, available at http://www.epa.gov/waterscience/316b/phase2/comments/author-ph2.pdf ................................. 11, 16, 18

Page 4: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

ooo111

TABLE OF AUTHORITIES~Continued

Page(s)Comments of Goodwin Procter (submitted on

behalf of Entergy Corp.), Comment ID316bEFR.029.035, available at http://www.epa.gov/waterscience/316b/phase2/comments/author-ph2.pdf ................................................17, 18

Comments of the Nuclear Energy Institute,Comment ID 316bEFR.020.002, availableat http://www.epa.gov/waterscience/316b/phase2/comments/author-ph2.pdf ..............................5

Comments of UWAG, Comment ID316bEFR.041.351, available at http://www¯epa.gov/waterscience/316b/phase2/comments/author-ph2.pdf ......................................................14

FERC, Order Certifying North AmericanElectric Reliability Corporation as theElectric Reliability Organization and Or-dering Compliance Filing, 116 FERC¶ 61,062 (July 20, 2006) ................................................4

OTHER AUTHORITIES

Climate Change 2007: Mitigation, Contributionof Working Group III to the Fourth As-sessment Report of the IntergovernmentalPanel on Climate Change (CambridgeUniv. Press 2007), available at http://www.mnp.nl/ipcc/pages_media/AR4-chapters.html ............................................................................6

Page 5: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

iv

TABLE OF AUTHORITIES--Continued

Page(s)North American Electric Reliability Corpora-

tion, 2006 Long Term Reliability Assess-ment: The Reliability of Bulk PowerSystems in North America (Oct. 2006),available at http://www.nerc.com/~filez/rasreports.html .............................................................4

North American Electric Reliability Corpora-tion, 2007 Long Term Reliability Assess-merit: The Reliability of Bulk PowerSystems in North America (Oct. 2007),available at http://www.nerc.com/~filez/rasreports.html .......................................................4, 18

Nuclear Energy Institute, Environment:Emissions Prevented (2007), available athttp://www.nei.org/resourcesandstats/nuclear_statistics/environmentemissionsprevent

Status and Outlook for Nuclear Energy in theUnited States (Aug. 2006), available athttp://nei.org/resourcesand-stats/documentlibrary/reliableandaffordableenergy/reports/statusreportoutloolg .................................................5

Summary for Policymakers of the SynthesisReport of the IPCC Fourth AssessmentReport (Nov. 16, 2007 draft), available athttp://www.ipcc.ctd .......................................................6

Water & Sustainability (Volume 3): U.S. Wa-ter Consumption for Power Production--The Next Half Century (Elec. Power Re-search Inst. 2002) ........................................................19

Page 6: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

INTEREST OF AMICUS CURIAE

The Nuclear Energy Institute (NED representsthe commercial nuclear energy industry on regulatorymatters.1 NEI’s members include every entity licensedby the Nuclear Regulatory Commission to generateelectricity at a commercial nuclear power plant in theUnited States. Members also include nuclear plant de-signers, major architecture and engineering firms, fuelfabrication facilities, and other organizations and indi-viduals involved in the nuclear energy industry.

The court of appeals’ interpretation of Section316(b) of the Clean Water Act in this case will have asignificant impact on most, if not all, of the 38 U.S. nu-clear power plants that do not currently use "closed-cycle" cooling water systems. NEI can offer the Courtan informed perspective on the likely practical conse-quences of the court of appeals’ decision.

~ No counsel for a party authored this brief in whole or inpart, and no party or its counsel made a monetary contributionintended to fund the preparation or submission of this brief. Peti-tioners PSEG Nuclear LLC and Entergy Corporation, and certainmembers of petitioner Utility Water Act Group with nuclearplants, are members of NEI and make contributions that supportall of NEI’s activities, including the filing of amicus briefs. Noperson other than NEI, its members, or its counsel made a mone-tary contribution to the preparation or submission of this brief.Counsel of record for all parties received timely notice of NEI’sintent to file this brief, and letters from all parties consenting tothe filing of this brief have been submitted to the Clerk.

Page 7: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

2

INTRODUCTION ANDSUMMARY OF ARGUMENT

The petitions for a writ of certiorari should begranted because the court of appeals has misconstruedthe Clean Water Act in a way that is likely to causesignificant reductions in the nation’s supply of nuclearpower in the near and medium term. The court’s deci-sion thus poses a substantial threat to the sufficiency ofthe nation’s electric power supply, to the stability of theelectric power grid--and, perversely, to the very envi-ronmental values that the Clean Water Act and similarstatutes are designed to protect.

Refusing to defer to the EPA’s longstanding inter-pretation of its statutory mandate, the court of appealshas read Section 316(b) of the Clean Water Act to fore-close the agency from comparing incremental costs andbenefits in determining what is, under particular cir-cumstances, "the best technology available for minimiz-ing [the] adverse environmental impact" caused bycooling water intake structures. The court’s reasoningmay require the EPA to mandate that all of the nation’s38 nuclear power plants that now use "once-through"cooling be retrofitted to use "closed-cycle" systems.Some plants, however, would likely find it either physi-cally or economically impossible to comply with such amandate, and would shut down. Others would incur ex-ceptional costs and be unable to produce power for upto a year as they retrofit their systems. In addition,every facility that switches to a closed-cycle systemwill suffer a significant "energy penalty"--a permanentdecrease in generating capacity.

Already, the supply of energy in the United Statesbarely keeps pace with, and sometimes falls below, de-mand. In the near term, capacity margins will only get

Page 8: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

3

tighter. Because the output of nuclear plants is largeand constant, nuclear power plays a particularly impor-tant role in maintaining the nation’s baseload powersupply. Reducing the supply of nuclear power wouldhave a disproportionately adverse effect on both theadequacy of the amount of power supplied to, and thestability of, the power grid.

Substantial time is required to secure approval forand to construct new nuclear plants. If existing nuclearplants are forced to close, either temporarily or perma-nently, in the near and medium term their power out-put could realistically be replaced only by plants thatburn fossil fuels. Unlike nuclear plants, fossil-fuelplants produce greenhouse gases that are believed bymany to contribute to global climate change. Thatwould be, to say the least, an ironic result of over-reading Section 316(b) to require the retrofitting ofcooling systems even where the EPA or responsiblestate officials--not plant ownersmwould otherwiseconclude that the costs involved are wholly dispropor-tionate to any environmental benefit that might beachieved.

All this might be beside the point if, as the court ofappeals held, Section 316(b) were so clear on its face asto leave no room for construction by the EPA. As peti-tioners demonstrate, however, that is not the case. Tothe contrary, the court of appeals adopted facially un-reasonable limits on the sensible flexibility that Con-gress conferred here, as it typically does, on the expertagency it relies on to interpret and administer a broadstatutory mandate. That error threatens very seriousconsequences, and it merits this Court’s review.

Page 9: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

4

ARGUMENT

I. NUCLEAR POWER PROVIDES A CRITICAL PORTION OF THENATION’S ENERGY SUPPLY, PARTICULARLY IN LIGHT OF CLI-MATE CHANGE

The supply of power in the United States is understrain. At times, supply in some areas can barely meetdemand. During the summer of 2006, for example, aheat wave "required utility system operators, custom-ers, and government agencies to implement emergencyprocedures in some areas." North American ElectricReliability Corporation (NERC), 2006 Long Term Re-liability Assessment: The Reliability of Bulk PowerSystems in North America 5 (Oct. 2006), available athttp://www.nerc.com/-filez/rasreports.html.2 Blackoutswere avoided principally ’%ecause generating capacityperformed extremely well during this period." Id.

The problem is likely to get worse before it getsbetter. Over the next ten years, the utility industryexpects peak demand to increase by over 17%, whilecommitted generating capacity is expected to increaseby only 8.4%. NERC, 2007 Long Term Reliability As-sessment: The Reliability of Bulk Power Systems inNorth America 10 (Oct. 2007) (2007 NERC Assess-ment), available at http://www.nerc.com/-filez/rasreports.html. In a number of regions, capacity marginsare expected to drop well below target levels. Id. at 24.

2 NERC is the entity certified by the Federal Energy Regu-latory Commission as the single "Electric Reliability Organization"for the United States under Section 215 of the Federal Power Act,16 U.S.C. § 824o(c). See Order Certifying North American Elec-tric Reliability Corporation as the Electric Reliability Organiza-tion and Ordering Compliance Filing, 116 FERC ¶ 61,062 (July20, 2006).

Page 10: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

Against this backdrop, nuclear power plants are anexceedingly important source of power. There are cur-rently 104 operating units at more than 60 nuclearplants in the United States. These plants generate ap-proximately 20% of the nation’s electricity.3 Along withcoal and natural gas, nuclear energy is a foundationalpart of the nation’s power supply.

Nuclear power is a particularly important source ofgeneration because of its cost stability and output reli-ability. The supply and cost of nuclear power do notfluctuate significantly based on weather or climate con-ditions, fuel cost variability, or the vagaries of foreignsuppliers. Nuclear plants are able to operate withoutinterruption for extended periods, up to 24 months at atime. Because nuclear power can be so reliably gener-ated, it helps supply the ’%aseload" of electricity that isrequired for the national electric power grid to func-tion. Indeed, the stability of the grid depends on nu-clear power.

Nuclear energy is also comparatively inexpensive.Nuclear plants are currently estimated to be the low-est-cost producers of baseload electricity.4 The consis-tent availability of nuclear power at predictable prices

3 See Comments of the Nuclear Energy Institute, Comment

ID 316bEFR.020.002, at 407. The comments cited in this briefare available at http’J/www.epa.gov/waterscience/316b/phase2/comments/author-ph2.pdf. The page citations provided are to thiscompilation of the comments.

4 See Status and Outlook for Nuclear Energy in the United

States 3-4 (Aug. 2006), available at http’J/nei.org/resourcesandstats/documentlibrary/reliableandaffordableenergy/reports/statusreportoutlook/.

Page 11: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

also has a stabilizing effect on the electricity market asa whole.

Finally, nuclear power is increasingly cited as animportant part of efforts to minimize adverse environ-mental impacts. As this Court has recognized, theworld faces serious threats from global climate change.See Massachusetts v. EPA, 127 S. Ct. 1438, 1455 (2007).Many believe that climate change is caused in signifi-cant part by the emission of greenhouse gases, includ-ing carbon dioxide. Nuclear plants emit no such gases.For that reason, the United Nations Intergovernmen-tal Panel on Climate Change, which recently shared theNobel Peace Prize for its work on global warming,listed "nuclear energy" in its recently released FourthAssessment Report as a "key" technology for mitigat-ing greenhouse gas emissions--a technology, impor-tantly, that is "currently commercially available.’’5

This point has concrete application in the UnitedStates today. Nuclear power plants--not solar or windor other "alternative" energy sources--generate some

~ See Summary for Policymakers of the Synthesis Report ofthe IPCC Fourth Assessment Report 17 (Nov. 16, 200~/ draft),available at http’~/www.ipcc.ch]; see also Climate Change 2007:Mitigation, Contribution of Working Group III to the Fourth As-sessment Report of the Intergavernmental Panel on ClimateChange 269 (Cambridge Univ. Press 2007), availabte athttp’~/www.mnp.nYipcc]pages_media/AR4-chapters.htmi ("Totallife-cycle [greenhouse gas] emissions per unit of electricity pro-duced from nuclear power are.., similar to those for renewableenergy sources. Nuclear power is therefore an effective [green-house gas] mitigation option, especially through license extensionsof existing plants enabling investments in retro-fitting and up-grading." (citations omitted)).

Page 12: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

7

71% of all carbon-free electricity in America.6 In-creased electricity production by nuclear power plantsis responsible for one-third of all reductions of carbonemissions by U.S. industry since 1993 as part of theDepartment of Energy’s Climate Challenge and Cli-mate Vision programs. Using nuclear power instead offossil-fuel-burning power plants prevents almost 700million metric tons of carbon dioxide emissions. Forperspective, the volume of greenhouse gas emissionsprevented by the use of nuclear power in the UnitedStates is equivalent to taking more than 90% of all pas-senger cars off the nation’s roadways.

II. THE COURT OF APPEALS’ DECISION COULD FORCE RETRO-Frl’rING AT EXISTING NUCLEAR PLANTS, EVEN IF INDEPEND-ENT REGUI~TORS WOULD OTHERWISE CONCLUDE THATCOSTS WHOLLY OUTWEIGH BENEFITS

Section 316(b) of the Clean Water Act directs theEPA, in establishing discharge standards under Sec-tions 301 and 306 of the Act, to "require that the loca-tion, design, construction, and capacity of cooling waterintake structures reflect the best technology availablefor minimizing adverse environmental impact." 33U.S.C. § 1326(b). In applying that provision to existingpower plants, the EPA concluded that it could andshould compare the costs of adopting particular tech-nologies to their expected incremental benefits. SeeNational Pollutant Discharge Elimination System--Final Regulations To Establish Requirements forCooling Water Intake Structures at Phase H Existing

6 The factual points in this paragraph are drawn from a more

detailed discussion, Environment: Emissions Prevented, availableon NEI’s website at http://www.nei.org/resourcesandstats/nuclear_statistics/environmentemissionsprevented/.

Page 13: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

8

Facilities, 69 Fed. Reg. 41,576, 41,576, 41,583 (July 9,2004) (Phase II Rulemaking). This conclusion was inkeeping with the EPA’s 30-year history of taking costsand benefits into account in determining under Section316(b) what was the "best technology available" forlarge power plants--including the plants approved andconstructed during that period, which are now "exist-ing facilities" subject to the Phase II regulations.

Accordingly, the EPA decided that existing plantsshould not be required to adopt closed-cycle cooling,even though that was the ’’best technology available"for new plants, because the cost considerations are radi-cally different. See 69 Fed. Reg. at 41,605-41,606. Like-wise, the agency concluded that a facility could seekspecial determination of the "best technology available"at a particular site ’’by demonstrating ... that its costswould be significantly greater than the benefits of com-plying with [the generally applicable] performancestandards at the facility." Id. at 41,603.

The court of appeals held that the text and struc-ture of the Clean Water Act foreclose the EPA’s ap-proach. See Riverkeeper, Inc. v. EPA, 475 F.3d 83, 98-99, 114 (2d Cir. 2007). As petitioners PSEG, UWAG,and Entergy demonstrate, that is incorrect. See PSEGPet. 17-27; UWAG Pet. 16-28; Entergy Pet. 25-35. Wedo not repeat the entire analysis here. We do note,however, that the court of appeals’ reasoning is at wareven with itself.

The court recognized that the word "available" iscapacious enough to permit rejection of a technology soexpensive that its cost could not be "reasonably borne"by "the industry" as a whole. See 475 F.3d at 99. Thecourt never explained exactly what it meant by "theindustry" bearing costs, but the formulation suggests

Page 14: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

that the court would accept that a technology is not"available" if implementing it would be cost-prohibitivefor a sufficient number of individual firms and theircustomers. If the statute can bear that meaning, it canalso bear the interpretation adopted by the EPA--ineffect, that a technology is not the "best technologyavailable" in any particular instance if, under all thecircumstances, the particular plant operator involvedcannot reasonably be asked to bear the costof imple-menting it. While the court of appeals preferred todraw the "availability" line in one place rather than theother, once it conceded that there was a line to bedrawn, the specific placement was not its decision tomake. See Chevron U.S.A. Inc. v. Natural Res. Def.Council, Inc., 467 U.S. 837, 842-843 (1984).

Similarly, the court of appeals purported to drawsupport for its interpretation of Section 316(b) fromother sections of the Clean Water Act. 475 F.3d at 97-98. But the provisions upon which the court relied ex-pressly permit EPA to consider "such other factors as[it] deems appropriate," 33 U.S.C. § 1314(b)(2)(B), aswell as "the cost of achieving [the] effluent reduction,"/d.;/d. § 1316(b)(1)(B). Rather than support the courtof appeals’ decision, these provisions confirm its error.

The court of appeals stopped short of expressly or-dering the EPA to mandate retrofitting of all existingplants to use closed-cycle cooling. Respondents, how-ever, will no doubt argue that the court’s reasoning re-quires that result. See 475 F.3d at 102 (stating that thecourt’s "concern with the EPA’s determination withrespect to section 316(b) is further deepened by theAgency’s rejection of closed-cycle cooling and selectionof a suite of technologies as the basis for BTA");/d. at103 & n.16 (expressing doubt as to whether a suite oftechnologies could "approach[] the performance of

Page 15: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

10

closed-cycle cooling" (internal quotation marks omit-ted)); id. at 105 (remanding "for clarification . . . andpossibly for a new determination of BTA"). The EPAmay feel constrained to agree. Because the court of ap-peals expressly read Section 316(b) to prohibit any useof restoration methods, id. at 108-110, that approachwill no longer be available on remand. In light of thecourt of appeals’ severe limitation on the EPA’s abilityto consider costs, closed-cycle cooling may be the onlytechnological solution left open to the agency.

The EPA has already determined that retrofittingplants to use closed-cycle cooling generally will reduceimpingement and entrainment to a greater degree thanupgrading the design and construction of water intakestructures at once-through plants. See 69 Fed Reg.41,576, 41,606.7 While the reductions achievable usingother technologies "approach[]" those from closed-cyclecooling, respondents will surely argue that they are not"essentially the same" in the only sense that the courtof appeals would recognize as allowing selection of thelower-cost alternative. See 475 F.3d at 100-101. If thatis correct, the court’s decision will require the EPA tomandate retrofitting of all existing plants to use closed-cycle cooling, so long as the billions of dollars that ret-rofitting would cost could theoretically be borne by theindustry as a whole.

7 The EPA determined that "closed-cycle, recirculating cool-ing systems (e.g., cooling towers or ponds) can reduce mortalityfrom impingement by up to 98 percent and entrainment by up to98 percent when compared with conventional once-through sys-tems" in fresh water. Id. at 41,601. In contrast, the EPA’s per-formance standards contemplating adoption of other technologiescalled for reduction of impingement "by 80 to 95 percent" and re-duction of entrainment ’’by 60 to 90 percent." Id. at 41,598.

Page 16: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

11

llI. MANDATING USE OF CLOSED-CYCLE COOLING AT EXISTING

NUCLEAR PLANTS WOULD HAVE SIGNIFICANT ADVERSE EF-FECTS ON THE NATION’S POWER SUPPLY--AND ON THE EN-VIRONMENT

The Phase II regulations struck down by the courtof appeals cover all 104 nuclear power units currently inoperation in the United States. Sixty-one of those unitscurrently use once-through cooling. If all existingplants are required to convert to closed-cycle cooling,some will likely close entirely, and all will be subject totemporary closures of up to a year and suffer perma-nent decreases in net generating capacity. These clo-sures and losses in efficiency would significantly dimin-ish the nation’s supply of nuclear power, contributing toshortfalls in generation, grid instability, and environ-mental harm. In part for these reasons, the Depart-ment of Energy "strongly" recommended to the EPAduring the Phase II rulemaking that it "not include anyrequirement that has the effect of forcing any class offacilities to install wet [closed-cycle] cooling towers."Comments of Department of Energy, Comment ID316bEFR.010.028, at 185.

A. Mandating That Existing Plants Be Retrofitted ToUse Closed-Cycle Cooling Would Reduce The Na-tion’s Supply Of Nuclear Power

Retrofitting existing nuclear plants to use closed-cycle cooling is at best a complicated, costly, and time-consuming process, and may not be possible or eco-nomically feasible at some plants. Closed-cycle coolingrequires the construction of large towers to re-cool thewater between cycles. Just finding the space for thesetowers is a significant challenge for many plants. Inrejecting mandatory closed-cycle retrofits, the EPAnoted that "31 out of 56 plants surveyed said that theywould need to acquire additional property to accommo-

Page 17: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

12

date cooling towers." 69 Fed. Reg. at 41,605. Evenleaving aside cost, the agency recognized that theremay be significant impediments to the acquisition anddevelopment of that additional land. Id.

To begin with, in some locations, especially in urbanareas, it may be difficult or impossible to obtain suffi-cient vacant or clearable land adjacent to the existingplant site. 69 Fed. Reg. at 41,605. Moreover, evenwhere land is nominally available, developing it forcooling-tower use may present daunting challenges.For example, retrofitting the Diablo Canyon plant onthe central California coast, if it could be done at all,would require excavating a 1600-foot by 600-foot sec-tion of the Las Cafiadas coastal hills adjacent to theplant to make room for the construction of 132 60-foot-tall water tower cells.8 Retrofitting the San OnofreNuclear Generating Station, on the coast between SanDiego and Los Angeles, likely would require construc-tion of cooling water tanks at the top of 100-foot bluffsoverlooking the beach adjacent to the plant.

If the land necessary for cooling towers could beobtained, a plant owner would need to acquire federal,state, and possibly local permits to proceed with retro-fitting. For example, some retrofits would require alicense amendment from the Nuclear Regulatory Com-mission, which requires a formal approval process gen-erally involving public hearings. See 10 C.F.R. § 50.91.9

8 Unless otherwise indicated, examples in this brief are drawn

from information provided by plant operators.9 A license amendment is required if a proposed change to a

nuclear plant involves, among other things, a modification to tech-nical specifications. See 10 C.F.R. § 50.59(c)(1)(i). Whether retro-

Page 18: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

13

Obtaining such amendments would consume substantialpublic and private resources. This would occur at atime when the Commission and industry are concen-trating on applications to renew operating licenses atexisting nuclear plants and on licensing and construct-ing new plants that are necessary to meet the expand-ing demand for power.

Ironically, efforts to obtain the permits necessaryto address what the court of appeals viewed as the fish-protection requirements of the Clean Water Act couldwell be hampered by adverse environmental impacts ofother sorts that might result from retrofitting plants touse closed-cycle cooling. For example, salt-water cool-ing towers produce large plumes of salt water vaporthat can contribute to fogging and icing in the sur-rounding area and affect nearby electrical equipment.One may anticipate concern about increased noise. Theprospect of extensive construction in sensitive areas,such as around the coastal Diablo Canyon and San On-ofre plants, would raise substantial concerns that coulddelay or even preclude obtaining necessary approvals.As the EPA noted, for example, expanding some plantsmight require displacement of ecologically valuablewetlands. 69 Fed. Reg. at 41,605. Similarly, the SanOnofre plant is surrounded by federal and state landsthat support species protected by state and federallaws.

Apart from land and permits, retrofitting large ex-isting plants to use closed-cycle cooling would be a sig-nificant engineering challenge. Among other things,closed-cycle cooling requires an extensive network of

fitting to use closed-cycle cooling would require a license amend-ment would be a plant-specific determination.

Page 19: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

14

pipes to circulate water to and from the plant’s con-densers. For example, it is estimated that retrofittingthe Salem Generating Station to use closed-cycle cool-ing would require the demolition or abandonment ofover three miles of existing 7-foot and 10-foot diametercirculating pipe and the installation of over 4 miles ofnew 7-foot pipe. See, e.g., Comments of UWAG, Com-ment ID 316bEFR.041.351, at 1330. Additionally, manyplants would need to reinforce their condensers towithstand the increased pressure resulting from closed-cycle cooling and otherwise modify them for use withthe retrofitted system.

For all these reasons, where retrofitting nuclearplants to use closed-cycle cooling is possible at all, itwould be very--sometimes prohibitively~xpensive.As the EPA concluded:

[A] national requirement to retrofit existingsystems is not the most cost-effective approachand at many existing facilities, retrofits may beimpossible or not economically practicable.EPA estimates that the total capital costs forindividual high-flow plants (i.e., greater than 2billion gallons per day) to convert to wet tow-ers generally ranged from $130 to $200 million,with annual operating costs in the range of $4to $20 million ....

69 Fed. Reg. at 41,605.

Indeed, the EPA recognized that, for a variety ofreasons, its substantial cost estimates "may not fullyreflect the costs of the option." 69 Fed. Reg. at 41,605.Consistent with that recognition, forecasts by individ-ual plant operators run even higher. The Edison Elec-tric Institute, the association of U.S. shareholder-owned electric companies, has estimated that retrofit-

Page 20: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

15

ting the 38 existing once-through nuclear plants withclosed-cycle cooling would cost between $10 billion and$19 billion.’° Estimates of the cost of retrofitting all ex-isting once-through plants with closed-cycle coolingsubmitted to the EPA by petitioner UWAG rangedfrom $40 to $66 billion. See UWAG Pet. 37. Using thehigh end of the EEI range, the average cost per nuclearplant would be $500 million. For each of four plants--Diablo Canyon, Salem Generating Station, San Onofre,and Indian Point---EEI or plant owners estimate thatthe cost of retrofitting could total $1 billion or more. AtDiablo Canyon alone, retrofitting could cost in therange of $2.4 billion.

If retrofitting proceeds at any given plant even inthe face of these geographical, governmental, environ-mental, technical, and financial challenges, it can re-quire shutting the plant down for prolonged periods.The EPA estimated that plants would be unavailablefor as long as 10 months. See 69 Fed. Reg. at 41,605.Private estimates suggest that retrofitting Diablo Can-yon and San Onofre would render the plants unavail-able for 12 months or more, that Indian Point would beclosed for approximately 10 months, and that OysterCreek would have to be shut down for more than fourmonths. Extended outages would also be anticipated atthe Salem facility. See PSEG Pet. 34 (estimating that aclosed-cycle retrofit "would require partially suspend-ing operations for at least 14 months, causing a net lossof 1150 megawatts.., during that period").

10 This range is derived from cost estimates subn~tted to theEPA adjusted with some site-specific cost estimates provided byindividual operators.

Page 21: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

16

Finally, once returned to operation, retrofittedplants would produce less usable power than they didbefore. A steam power plant’s condenser "operates un-der vacuum conditions (i.e. a pressure below normalatmospheric pressure)." Comments of the Departmentof Energy, Comment ID 316bEFR.010.101, at 239. Be-cause cooling water in once-through systems has on av-erage a lower temperature than water in closed-cyclecooling systems, the vacuum created in once-throughsystems is greater than in closed-cycle systems, whichincreases efficiency. Id. In addition, closed-cycle sys-tems require more power to run the cooling system it-self, leaving less for consumers.

In its Phase II rulemaking, the EPA relied on anestimate by the Department of Energy that the "en-ergy penalty" resulting from converting existing once-through plants to closed-cycle cooling would generallyamount to a 2.4% to 4.0% decline in energy productioncapacity. 69 Fed. Reg. at 41,605. The EPA noted a5.3% energy penalty associated with the use of closed-cycle cooling for one nuclear plant that provides 78% ofthe electricity for Vermont. See id. Using the sameDOE figures relied upon by the EPA, it has been esti-mated that retrofitting all existing nuclear plants to useclosed-cycle cooling would reduce overall capacity by2,117 megawatts. As the EPA explained with respectto both nuclear and non-nuclear plants, "on average 20additional 400-MW plants might have to be built to re-place the generating capacity lost by replacing once-through cooling systems with wet cooling towers ifsuch towers were required by all Phase II facilities."Id.

In short, if the court of appeals’ decision stands andrequires the EPA to mandate retrofitting of closed-cycle cooling at all existing nuclear power plants, some

Page 22: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

17

of those plants will likely find it physically or economi-cally impossible to continue operation, and all will facetemporary closures and permanent reductions in gen-erating capacity. Either way, requiring retrofittingwould significantly reduce the nation’s supply of nu-clear energy.

B. Reducing The Supply Of Nuclear Power Will HaveSubstantial Adverse Effects Both On The EnergySupply And On The Environment

The reduction in capacity caused by mandating ret-rofitting of existing nuclear plants will have a numberof significant adverse impacts.

First, even if all plants ultimately remain in opera-tion, the significant energy penalty caused by the use ofclosed-cycle cooling would by itself have a significantadverse impact on the power supply. While the lost ca-pacity could eventually be replaced, in the short termair quality limitations would likely prevent fossil-fuelplants from meeting the entire shortfall, and existingnuclear plants lack additional capacity. In areas of thecountry already facing energy constraints, such as Cali-fornia and the mid-Atlantic/Northeast corridor, thenear-term reduction in capacity would increase the like-lihood of brownouts and blackouts during the summermonths.

Loss of the power generated by nuclear plants thatare forced to close would substantially exacerbate theproblem. For example, in its comments to the EPA,petitioner Entergy estimated that if its Indian Pointnuclear plant were to close, target reserve margins inNew York could not be met and "the calculated numberof days where emergency measures would be taken toprevent blackouts, etc., would rise by 800%." Com-merits of Goodwin Procter (submitted on behalf of En-

Page 23: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

18

tergy Corp.), Comment ID 316bEFR.029.035, at 619.Even temporary plant closures to allow retrofittingwould have a significant impact. Because of theirlength, the anticipated closures would likely overlapwith the winter or summer peak electricity demandseasons, threatening the reliability of the power grid.

NERC has recognized that mandating closed-cyclecooling could adversely affect the nation’s power capac-ity margins In its 2007 reliability report, NERC ex-plained:

While plant specific outcomes will vary, retro-fitting existing power plants with cooling tow-ers can reduce the capacity of those plants,which will exacerbate the supply concernsidentified in ... this assessment. In somecases, retrofits may prove so costly that plantsare retired earlier than projected, with the con-sequent loss of the plant’s entire capacity. At atime when additional electricity generating re-sources are needed, the loss of existing gener-ating capacity would undermine U.S. efforts tomeet the growing demand for electricity.

2007 NERC Assessment at 12. And, as noted above,during the Phase II rnlemaking the Department of En-ergy "strongly" recommended that the EPA not re-quire existing plants to be retrofitted to use closed-cycle cooling. Comments of Department of Energy,Comment ID 316bEFR.010.028, at 185.

Mandating the use of closed-cycle cooling wouldlikely also have significant adverse environmental ef-fects. First, as explained above, at some plant sites aclosed-cycle retrofit would raise its own substantial en-vironmental issues. In addition to possible adverse ef-fects on the land and air surrounding the plant, retrofit-

Page 24: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

19

ting could even adversely affect the water resourcesprotected by the Clean Water Act itself. Although aclosed-cycle cooling system at a nuclear plant does nottake in as much water day-to-day as a once-throughsystem, it actually consumes (that is, permanently re-moves from the source water body) up to 80% more wa-ter overall. See Water & Sustainability (Volume 3):

Consumption for Power Production--TheCentury viii (Elec. Power Research Inst.

U.S. WaterNext Half2002).

Second,where existing plants are forced to close orhave their output cut by retrofitting, new nuclearplants cannot realistically replace the lost power overthe short or medium term. Designing a new nuclearplant, obtaining necessary permits, and building theplant takes years. New nuclear projects already inearlY stages of development are not expected to beginproduction until 2015 to 2020. Thus, as a practical mat-ter, for at least several years any generating capacitylost from existing nuclear plants would have to be re-placed, if at all, by power generated using fossil fuels.

The EPA understood that requiring retrofittingwould result in increased reliance on fossil fuels. See,e.g., 69 Fed. Reg. at 41,605. That, in turn, would in-crease "the emission of sulfur dioxide, NOx, particulatematter, mercury and carbon dioxide." Id. It is esti-mated that using fossil fuels to replace the nuclearpower lost due to the retrofitting energy penalty alonecould add 37,000 tons of sulfur dioxide, 13,000 tons ofnitrogen oxide, and 14 million metric tons of carbon di-oxide to the nation’s atmosphere.11 If capacity lost as a

1~ Carbon dioxide typically is measured in metric tons, whichaxe equivalent to approximately 2205 lbs.

Page 25: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

2O

result of nuclear plant closures were also replaced bypower from fossil-fuel plants, the increase in green-house gas emissions would be even more severe.

Taking into account all of these concerns, the EPAreasonably concluded that, for existing power plants,the tremendous costs of retrofitting for closed-cyclecooling far outweigh the incremental benefits it pro-vides, as compared to the use of other EPA-approvedtechnologies, in reducing impingement and entrainmentat water intake structures. Its judgment rested bothon economic costs and on "non-water quality environ-mental impacts." 69 Fed. Reg. at 41,605.

If Congress had weighed the various competingeconomic and environmental considerations itself andclearly mandated a different approach, then the court ofappeals would have been right to set aside the agency’sjudgment and enforce the congressional command. Aspetitioners have demonstrated, however, nothing in thelanguage, structure, purpose, or previous judicial inter-pretation of the Clean Water Act precludes the EPAfrom taking economic and environmental costs into ac-count, along with potential benefits, in determiningwhat constitutes, under particular circumstances, the"best technology available for minimizing adverse envi-ronmental impact" under Section 316(b). On the con-trary, it is precisely in circumstances such as these, in-volving the balancing of important social goals that in-teract in complex ways, that Congress most typicallydelegates to an agency the responsibility for particular-ized implementation of statutory standards.

Because the Act, unsurprisingly, leaves room forjust the sort of complex agency judgment that the EPA

Page 26: PSEG FOSSIL LLC AND PSEG NUCLEAR LLC - SCOTUSblog€¦ · 7/3/2008  · During the summer of 2006, for example, a heat wave "required utility system operators, custom-ers, and government

21

made here, the court of appeals erred in substituting itsown absolutist analysis for the more balanced approachadopted by the EPA. That error threatens real, imme-diate, and far-reaching harm to the nation’s power sup-ply-and, ironically, to the very environmental valuesthat the court no doubt thought it was protecting. Itwarrants review and correction by this Court.

CONCLUSION

The petitions for a writ of certiorari should begranted.

Respectfully submitted.

ELLEN C. GINSBERGMICHAEL A. BAUSERNUCLEAR ENERGY

INSTITUTE1776 I Street, N.W.Washington, D.C. 20006(202) 739-8000

SETH P. WAXMANCounsel of Record

EDWARD C. DUMONTBRIAN M. BOYNTONWILMER CUTLER PICKERING

HALE AND DORR LLP1875 Pennsylvania Ave., N.W.Washington, D.C. 20006(202) 663-6000

DECEMBER 2007