![Page 1: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/1.jpg)
PTEPotential to Emit
![Page 2: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/2.jpg)
What is PTE?
K.A.R. 28-19-200 General provisions; definitions.
(yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under its physical and operational design. Any physical or operational limitation on the capacity of the source to emit a pollutant, including air pollution control equipment and restrictions on hours of operation or on the type or amount of material combusted, stored, or processed, shall be treated as part of its design if the limitation or the effect it would have on emissions is federally enforceable. Secondary emissions shall not be considered in determining the potential-to-emit of a stationary source.
![Page 3: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/3.jpg)
What is PTE?
• 24-hour operation, 365 days per year
• Operate at maximum capacity
• No pollution control devices or practices
![Page 4: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/4.jpg)
Reasons for evaluating
•It’s required by your permit
•Determine if you need a permit
•Demonstrate your facility is below certain thresholds
•Determine if permit needs have changed
•Determine if adding new equipment will require a construction permit
![Page 5: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/5.jpg)
PTE for what?
• Volatile organic compounds (VOCs)
• Nitrous oxides (NOX)
• Sulfur dioxide (SO2)
• Carbon monoxide (CO)
• Particulate matter (PM)
• Lead (Pb)
• 187 hazardous air pollutants• (e.g., xylene, toluene, chromium, methylene chloride,
manganese, styrene, etc.)
NAAQS
NESHAP
![Page 6: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/6.jpg)
100 tons
25 tons
10 tons
Major sources – above the lineMinor source – below the line
Primary thresholds
![Page 7: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/7.jpg)
Various thresholds
Operating permitClass I (Title V)Class IIPermit by rule
Construction permitApprovalPermit
NESHAPMACTNSPSRACT
![Page 8: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/8.jpg)
Operating permit (Class I)
• Required if your PTE exceeds these thresholds:• 100 tons per year NOx, SOx, PM10, VOC, CO
• 10 tons per year of any single hazardous air pollutant (HAP)
• 25 tons per year of combined HAPs
• Also referred to as Title V permits (EPA version)
![Page 9: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/9.jpg)
Operating permit (Class II)
• Actual emissions are below Class I thresholds but PTE is above—limit PTE and apply for Class II operating permit
• Class II permit requires minimal record keeping and is simpler (and cheaper) than maintaining a Class I permit
• Class II permit-by-rule (KAR 28-19-561 through 564)
![Page 10: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/10.jpg)
Operating permit (Class II)
• Limit PTE by• Implementing pollution prevention
• Change the material
• Change the process
• Change the technology
• Limiting your process rate
• Limiting hours of operation
• Limiting amount of material processed
• Installing a pollution control device
![Page 11: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/11.jpg)
Construction permit/approval
• Evaluate PTE for new activities/equipment
• Evaluate PTE for modified activities/ equipment• Change in method of operation
• Modification of existing emission unit
• If PTE exceeds construction approval or permit thresholds, contact KDHE• Thresholds: www.sbeap.org (helpful resource- Five steps to determine whether your
facility needs an air permit)
• Forms: www.kdheks.gov/air-permit/download.html
![Page 12: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/12.jpg)
Construction permit
If your PTE exceeds these thresholds, then you’ll need a construction permit:
Source: Step 3 of SBEAP fact sheet,Five steps to determine whether your facility needs an air permit -www.sbeap.org/
![Page 13: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/13.jpg)
Construction approval
If your PTE exceeds these thresholds, then you’ll need a construction approval:
Source: Step 3 of SBEAP fact sheet,Five steps to determine whether your facility needs an air permit -www.sbeap.org/
![Page 14: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/14.jpg)
How to evaluate
•Based primarily on potential to emit (PTE)•24 hrs/day, 365 days/year•No control equipment
•Depending on regulation, evaluate on a facility-wide or process/equipment-specific basis
![Page 15: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/15.jpg)
SBEAP’s air emissions toolswww.sbeap.org
![Page 16: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/16.jpg)
Potential to emit (PTE) calculators
• Painting and coating
• Boilers and furnaces
• Engines
•Welding
• Grain elevator (being revised)
• Blasting (not yet posted)
• Plasma cutting (not yet posted)
![Page 17: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/17.jpg)
PTE calculator typical contents
• Typical spreadsheet tabs• Instructions
• Product information and usage amounts
• Summary• PTE
• Actual
• Rolling total
• Other tabs• List of HAPs
• Facility information
![Page 18: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/18.jpg)
PTE calculators input needed
PTE calculator Possible info needed for PTE calculation (spreadsheet inputs)
Painting/coating Density, VOC wt%, each HAP wt% (SDS); monthly usage amts; annual hrs operated; spray gun transfer efficiency; JO or WY county?
Boilers/furnace Heat input capacity or HP, fuel burned, JO or WY county?
Engines Fuel burned; HP or power output/fuel heat input; emergency or non-e
Welding Welding process, electrode type, amt. wire/rod consumed
Grain elevator (being revised) Annual throughput, elevator type,
Blasting (not yet posted) Amt. blasting material, wind speed
Plasma cutting (not yet posted) Steel type, steel thickness; cut dry, semidry, or wet; HAP in steel
![Page 19: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/19.jpg)
Calculation methods (most to least preferred)
• CEMS (continuous emission monitoring systems)
• Stack tests
• Material balance (emissions from painting/coating)
• Emission factors (emissions from engines, boilers, metal fabrication processes, grain elevators, and many more sources)
• Engineering judgement
• Other approved method
![Page 20: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/20.jpg)
Material balance calculations – painting/coating emissionshttp://www.sbeap.org/tools/potential-to-emit-calculators
![Page 21: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/21.jpg)
(www.epa.gov/air-emissions-factors-and-quantification/ap-42-compilation-air-emission-factors)
![Page 22: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/22.jpg)
![Page 23: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/23.jpg)
So you want to build/expand your facility/process
![Page 24: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/24.jpg)
Step 1: Identify emissions
• What are possible emission sources from equipment performed at your facility?
![Page 25: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/25.jpg)
Step 1: Identify emissions
• What are possible emission sources from equipment performed at your facility?• Paint booth
• Curing ovens
• Engines (emergency and non-emergency)
• Boilers
• Compressors
• Heaters
• Grain conveyor, unloading leg
![Page 26: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/26.jpg)
Step 1: Identify emissions
• What are possible emission sources from activities performed at your facility?
![Page 27: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/27.jpg)
Step 1: Identify emissions
• What are possible emission sources from activities performed at your facility?• Spraying paint, gel coat/resin
• Spray gun cleaning
• Paint stripping
• Parts cleaning
• Welding
• Metal blasting
• Plating
• Moving grain
![Page 28: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/28.jpg)
Step 2: Calculate PTE
• Select method(s) to use
• Gather needed information to perform calculations
• Calculate PTE for each criteria pollutant and HAP generated at your facility
• Contact SBEAP or KDHE Permitting Section for assistance
![Page 29: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/29.jpg)
Step 3: Compare PTE results with thresholds
• Refer to SBEAP fact sheet, Five Steps to Determine Whether Your Facility Needs an Air Permit, Step 3, for tables with thresholds
• Determine which permit to apply for• Are you an existing Class II that needs to be a Class I?
• Are you an existing Class I that could be a Class II?
• Have you added a piece of equipment?• Do you need a construction approval?
• Do you need a construction permit?
![Page 30: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/30.jpg)
Step 4: Apply for the appropriate permit
• To be discussed in the next few sessions
![Page 31: PTE - SBEAPWhat is PTE? K.A.R. 28-19-200 General provisions; definitions. (yy) ‘‘Potential-to-emit’’ means the maximum capacity of a stationary source to emit a pollutant under](https://reader030.vdocument.in/reader030/viewer/2022040818/5e63ffeb9144b7270220c9df/html5/thumbnails/31.jpg)
Conclusion
• PTE is fundamental to determining your permitting requirements
• If PTEs are below regulatory thresholds and no permit is needed for any other reason—• File calculations should they be requested later by an inspector
• Continue to track emissions, especially if product usage or product type changes