public disclosure authorized sr8 - world bank...provide the basis for piloting in the rural roads...

96
DRAFT Safeguard Diagnostic Review for Piloting the Use of Bhutanese Systems to Address Environmental and Social Safeguard Issues in the Proposed World Bank-Assisted Rural Access II Project Equivalence and Acceptability Report SR8 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 16-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

DRAFT

Safeguard Diagnostic Review

for

Piloting the Use of Bhutanese Systems to Address Environmental and Social Safeguard Issues in the

Proposed World Bank-Assisted Rural Access II Project

Equivalence and Acceptability Report

SR8

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

ii

November 2006

Page 3: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

iii

TABLE OF CONTENTS

ABBREVIATIONS AND ACRONYMS ......................................................................................................IV

EXECUTIVE SUMMARY............................................................................................................................VI

BACKGROUND.........................................................................................................................................VI PROJECT DESCRIPTION...........................................................................................................................VII STRUCTURE OF THE REPORT...................................................................................................................VII RESULTS OF EQUIVALENCE ASSESSMENT.............................................................................................VIII RESULTS OF ACCEPTABILITY ASSESSMENT..............................................................................................X

INTRODUCTION............................................................................................................................................ 1

PROJECT DESCRIPTION............................................................................................................................. 1 DONOR ACTIVITIES AND COORDINATION ........................................ERROR! BOOKMARK NOT DEFINED.BACKGROUND.......................................................................................................................................... 1 RATIONALE FOR PROJECT SELECTION...................................................................................................... 2 STRUCTURE OF THE REPORT.................................................................................................................... 3 METHODOLOGY AND PROCESS FOLLOWED IN DETERMINING EQUIVALENCE AND ACCEPTABILITY........ 3

PART I. EQUIVALENCE ANALYSIS.......................................................................................................... 4

APPLICABLE WORLD BANK SAFEGUARDS AND EA CATEGORY............................................................... 4 LEGAL STRUCTURE FOR APPLICABLE SAFEGUARDS................................................................................ 4 EQUIVALENCE TO OPERATIONAL PRINCIPLES OF OP4.00, TABLE A1: DISCUSSION.............................. 12 RELEVANCE OF DIFFERENCES TO RAP II PROJECT................................................................................. 16 CONCLUSIONS OF EQUIVALENCE ANALYSIS .......................................................................................... 16 MEASURES TO ATTAIN EQUIVALENCE................................................................................................... 17 R MEASURES TO SUSTAIN EQUIVALENCE IN THE RURAL ROADS SECTOR.............................................. 17

PART. II ACCEPTABILITY ASSESSMENT ............................................................................................ 20

ENVIRONMENTAL GOVERNANCE PROCESS IN BHUTAN.......................................................................... 20 INSTITUTIONAL AUTHORITY AND CAPACITY OF AGENCIES WITH ENVIRONMENTAL MANDATES IN

THE ROADS SECTOR............................................................................................................................... 27 PERFORMANCE AND OUTCOMES............................................................................................................. 43 CONCLUSIONS OF ACCEPTABILITY ASSESSMENT................................................................................... 48 MEASURES TO ATTAIN ACCEPTABILITY FOR RAP II ............................................................................. 49 MEASURES TO SUSTAIN ACCEPTABILITY IN THE RURAL ROADS SECTOR............................................... 50

PART III. ROLES AND RESPONSIBILITIES OF RGOB AGENCIES AND OTHER STAKEHOLDERS......................................................................................................................................... 54

RESPONSIBILITIES OF RGOB AGENCIES AND OTHER STAKEHOLDERS................................................... 54 RESPONSIBILITIES OF THE WORLD BANK ............................................................................................... 55

PART IV. PUBLIC CONSULTATION AND DISCLOSURE................................................................... 56

REPORT ON OCTOBER 24, 2006 PUBLIC CONSULTATION AND DISCLOSURE WORKSHOP....................... 56

ANNEXES

ANNEX A. EQUIVALENCE ANALYSIS MATRIX........................................................................................ 60 ANNEX B. REFERENCES.......................................................................................................................... 80 ANNEX C. LIST OF PERSONS MET DURING EQUIVALENCE AND ACCEPTABILITY MISSIONS................... 82

Page 4: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

iv

ABBREVIATIONS AND ACRONYMS

ADB Asian Development Bank AEC Application for Environmental Clearance BoQ Bill of Quantity CA Competent Authority CAB Contractors Association of Bhutan CAS Country Assistance Strategy CSEMP Contractor’s Site Environmental Management Plan DC Development Clearance DANIDA Danish International Development Assistance DANTAK Border Road Engineering Program (Government of India) DCA Department of Cultural Affairs DEC Dzongkhag (District) Environmental Committee DoF Department of Forests DoLG Department of Local Governance DoR Department of Roads DYT Dzongkhag Yarge Tshogdu (District Development Committee) EA Environmental Assessment EAA Environmental Assessment Act EC Environmental Clearance ECoP Environmental Code of Practice ECPHR Environmental Code of Practice for Highways and Roads EMP Environmental Management Plan EFRC Environmentally Friendly Road Construction EFRC-SP Environmentally Friendly Road Construction-Support Program EO Environmental Officers EToR Environmental Terms of Reference EU Environment Unit EUSPS Environment and Urban Sector Programme Support (DANIDA) FMU Forest Management Unit GEF Global Environmental Facility GYT Geog Yarge Tshogchung (Block Development Committee) IBRD International Bank for Reconstruction and Development ICR Implementation Completion Report IDD Investigation and Development Division (DoR) IR Involuntary Resettlement MoA Ministry of Agriculture MoHCA Ministry of Home and Cultural Affairs MoWHS Ministry of Works and Human Settlements MRG Monitoring and Reporting Guideline NA National Assembly NCD Nature Conservation Division NEC National Environment Commission NECS National Environment Commission Secretariat NEPA National Environmental Policy Act NES National Environment Strategy NH Natural Habitats

Page 5: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

v

OP Operational Policy PAP Project Affected People PCP Public Consultation Plan PPAH Pollution Prevention and Abatement Handbook PCR Physical Cultural Resources PPD Policy Planning Division (DoR) PRSP Poverty Reduction Strategy Paper RAP I Rural Access Project RAP II Second Rural Access Project RECP Regulation for the Environmental Clearance of Projects RGoB Royal Government of Bhutan SDR Safeguard Diagnostic Review SNV Netherlands Development Organization TC Tender Contract UCS Use of Country Systems UNDP United Nations Development Programme UNEP United Nations Environment Programme WWF World Wildlife Fund

CURRENCY EQUIVALENTS (Exchange Rate Effective November 1, 2006)

Currency Unit = Bhutanese Ngultrum N45.08 = $1

Vice President:

Country Director: Sector Director:

Acting Sector Manager: Team Leader:

Praful C. Patel Alastair McKecknie Constance Bernard Kseniya Lvovsky

Malcolm Jansen

Page 6: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

vi

EXECUTIVE SUMMARY

BACKGROUND

1. Beginning in March 2005, the World Bank has been supporting a limited number of pilot projects in which lending operations are being prepared using the borrowing country’s systems1

for environmental assessment (EA) and other environmental and social safeguards, rather than the World Bank’s operational policies and procedures on safeguards. The rationale for using country systems is to scale up development impact, increase country ownership, build institutional capacity, facilitate harmonization and increase cost effectiveness. These pilot operations are governed by a new operational policy (OP/BP 4.00) on “Piloting the Use of Borrower Systems to Address Environmental and Social Safeguard Issues in Bank-Supported Projects.”2 OP/BP 4.00 elaborates on the approach, enumerates the criteria for assessing country systems, and specifies documentation and disclosure requirements and respective roles of the Borrower and the World Bank.

2. The World Bank considers a Borrower’s environmental and social safeguard system to be equivalent to the World Bank’s if the Borrower’s system, as determined by the World Bank, is designed to achieve the objectives and adhere to the applicable operational principles set out in Table A1 of OP 4.00. Since equivalence is determined on a policy-by-policy basis in accordance with Table A1, the World Bank may conclude that the Borrower’s system is equivalent to the World Bank’s in specific environmental or social safeguard areas in particular pilot projects, and not in other areas. 3 Before deciding on the use of country systems (UCS), the World Bank also assesses the acceptability of the Borrower’s implementation practices, track record, and institutional capacity. The above approach and criteria for assessment were developed with inputs from external stakeholders such as representatives of governments, bilateral and multilateral development institutions, civil society organizations, and the private sector and is consistent with commitments made by the development community in the Paris Declaration on Aid Effectiveness of March 2005.4

3. The Royal Kingdom of Bhutan (RKoB) is a small country with a limited number of donors and a small public administration where a harmonized approach to environmental and social safeguards can lower transaction costs and enhance local systems and capacity for safeguards implementation. Achieving a harmonized approach requires an assessment of the country’s safeguard systems (policies, laws and regulations) as well as the broad institutional arrangements for environmental and social safeguards management. Such an exercise would in the long term help Bhutan improve its overall environmental and social safeguard management system as well as provide opportunity for Bhutan to understand and better manage environmental and social safeguards in its broader development program. It would also provide a basis for reaching agreement among the main donors for harmonization around Bhutan’s country systems.

1 Country systems is defined as the country’s legal and institutional framework, consisting of its nation, subnational or sectoral implementing institutions and relevant laws, regulations, rules and procedures that are applicable to the proposed pilot project. 2 OP/BO 4.00 can be viewed at this website: http://wbln0018.worldbank.org/Institutional/Manuals/OpManual.nsf/tocall/E49CED1645FB433885256FCD00776B19?OpenDocument 3 The Bank’s environmental and social safeguard policies will apply to the areas which the Bank has determined not to be equivalent to its applicable policy framework and will continue to apply to all projects that are not part of the pilot program. 4 The full text of the Paris Declaration can be viewed at: ttp://www.oecd.org/dataoecd/11/41/34428351.pdf

Page 7: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

vii

4. Two prospective Bank-funded projects were selected for piloting the Use of Country Systems (UCS) as part of a World Bank Board-approved pilot program for addressing environmental and social safeguard issues as governed by the OP 4.00: the Second Rural Access Project II (RAP II) and the second Urban Development Project (UDP II).

5. Bhutan was selected for participation in the pilot program due to the relatively recent and therefore advanced state of its laws and regulations corresponding to World Bank environmental and social safeguards, in particular, Environmental Assessment (EA), Natural Habitats (NH), and Physical Cultural Resources (PCR), all of which are triggered by the RAP II Project. In addition, Bhutan’s satisfactory performance in implementing the environmental and social safeguard requirements applicable to the RAP I project, as noted in the Bank’s draft Implementation Completion Report (ICR) on RAP I, suggests that Bhutan’s system may be sufficiently robust to provide the basis for piloting in the rural roads sector.

6. The application of UCS to Bhutan and to the RAP II project is consistent with other donors’ current priorities and programs that seek to contribute to the enhancement of Bhutan’s environmental and social policies, laws, institutional capacity and performance and to the development of the rural roads sector, in particular, the Asian Development Bank (ADB), the Danish International Development Agency (DANIDA), and the Netherlands Development Organization (SNV).

PROJECT DESCRIPTION

7. The development objective of RAP II is to provide all-season road access to targeted rural communities. The project will focus on three Dzongkhags (districts): Wangdue Phodrang, Dagana, and Pemagatshel, where the average distance and walking time from a beneficiary village to an all-season road ranges from 4 to 54 km, or 1 to 15.5 hours. The proposed RAP II is a follow-up operation and it is designed to replicate the positive lessons and good practices from RAP I in three new districts of the country. Its objective of rural access expansion is also assigned a high priority by the RGoB’s Poverty Reduction Strategy, its Ninth Five-Year Plan (2002-2007) and the IBRD’s Country Assistance Strategy for 2006-2009.

8. Of the eight World Bank safeguard policies included in the UCS pilot program, four are applicable to the project: Environmental Assessment (EA), Natural Habitats (NH), Physical Cultural Property (PCP) and Involuntary Resettlement (IR). The remaining environmental and social safeguards – Forests, Pest Management, Safety of Dams and Indigenous Peoples – are not applicable to the RAP II project.

STRUCTURE OF THE REPORT

9. Part I of this Safeguard Diagnostic Review (SDR) comprises the Equivalence Analysis carried out by World Bank legal and policy staff in collaboration with Bhutan’s National Environment Commission (NEC), its Office of Legal Affairs and officials at other agencies with legal authority over decisions in the rural road construction sector, including the Ministry of Works and Human Settlements (MoWHS) and the Ministry of Agriculture (MoA). Part II comprises the Acceptability Assessment carried out by World Bank policy and technical staff in collaboration with NEC and other Bhutanese agencies charged with the implementation of laws and regulations dealing with the environmental and social impacts of rural road construction. The conclusions of Parts I and II of this report include measures designed to ensure that Bhutan’s systems reach and sustain equivalence and acceptability in connection with the implementation of

Page 8: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

viii

the RAP II project and also contribute to the enhancement of Bhutan’s capacity to implement its environmental safeguards throughout the roads sector and beyond.

RESULTS OF EQUIVALENCE ASSESSMENT

10. A comparative analysis was conducted on the RGoB’s laws and regulations corresponding to the World Bank’s safeguards on EA, NH, PCR and IR per the Operational Principles of OP 4.00 Table AI. The results of this comparison are presented in matrix format in Annex A of this report.

11. Bhutan’s policies, legislation and regulations pertaining to the EA process and EA documentation are relatively recent and reflect international best practice to a significant extent, with the consequence that there is a substantial degree of equivalence between Bhutanese EA systems and the required elements of OP 4.00 Table A1 with respect to EA, NH and PCR.

12. Remaining differences between Bhutan’s systems and the Operational Principles of OP4.00 Table A1 for EA, NH and PCR include:

� EA: Absence of required reference in EA documentation to:

o Transboundary and global concerns;

o Bhutan’s international environmental commitments as reflected in treaties and conventions its has ratified; and

o The World Bank’s Pollution Prevention and Abatement (PPAH) Handbook or equivalent international environmental standards;

� NH: Lack of clear preference for siting projects on previously converted lands; and

� PCR: Lack of standard provision for dealing with “chance finds.”

Relevance of Equivalence Findings to RAP II Project

13. A number of these differences are not relevant to the RAP II project and therefore, the project may not be the most appropriate vehicle for addressing them. The RAP project does not raise issues involving transboundary, global concerns or Bhutan’s international environmental commitments. The PPAH does not include guidelines for rural road construction. Therefore, there is no imperative for the project to adopt measures designed to bridge these differences with respect to Bhutan’s EA system.

14. Differences with respect to NH and PCH are relevant to the RAP II project and need to be addressed within the scope and term of the project.

15. With respect to IR there is some congruence between Bhutanese systems on land acquisition and the Objectives and Operational Principles of OP 4.00, to the extent that the Land Act (LA), the primary legislation applicable to land acquisition in Bhutan, does require that when the government acquires land it shall inform affected people and enter into consultation with them about the content of the compensation scheme prior to any land taking. Affected people are to be compensated through allocation of replacement land or through financial compensation according to the classification of the land taken. People whose land is acquired and who choose replacement

Page 9: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

ix

land as compensation are allowed to identify replacement government owned land of equal size and value in the same district. Although the law does not require this in practice, it appears that compensation is often provided to affected people without formal legal rights or claims to lands to be expropriated.

16. However, substantial differences were found between Bhutanese systems and the following Operational Principles of OP 4.00 Table A1 with regard to IR. In particular, Bhutan’s legislation does not include provisions for:

� Avoidance or minimization of IR to the extent possible;

� Improvement or restoration of livelihoods of project affected peoples;

� Assessment of potential social and economic impacts of involuntary land taking or restriction of access to parks and protected areas;

� Consultation with project affected peoples on issues other than compensation;

� Provision of information and assistance to displaced persons;

� Implementation of resettlement plans and entitlements prior to project implementation; and

� Assessment of results of resettlement action plans.

Environmental and Social Safeguards Chosen for Piloting

17. The above findings indicate that there is substantial equivalence between Bhutan’s systems and the requirements of OP 4.00 Table A1 with respect to EA, NH and PCR. The relevant differences that remain with respect to EA are not relevant to the RAP II project and are best addressed in an alternative context. The differences with respect to NH and PCR are relevant to the RAP II project but can be readily addressed within the scope and duration of the project through the measures proposed below. It is, therefore, proposed that these three environmental safeguards be further considered for piloting under OP 4.00 in the RAP II project, subject to:

� The gap filling measures designed to reach and sustain equivalence as proposed below; and

� The findings and recommendations of the Acceptability Assessment included in Part II of this report.

18. With respect to IR, the differences between Bhutan’s systems for land acquisition and mitigation of impacts on project affected peoples are significant, profound and are clearly relevant to RAP II. Therefore, it is proposed that the Bank continue to apply its traditional safeguard mechanism OP 4.12 rather than Bhutan’s own systems to the assessment and management of the IR impacts associated with RAP II.

Recommended Measures to Attain Equivalence for the RAP II Project

19. The relevant substantive differences between Bhutan’s systems and the Operational Policies of OP 4.00 Table A1 identified in the above Equivalence Analysis could be readily

Page 10: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

x

addressed by revisions to the Code of Environmental Practices for Highways and Roads (CEPHR), which is within the administrative authority of the NEC and is a legally binding requirement in road construction contracts as described in the main section of this report.

20. The following specific changes are to be made in the CEPHR, with respect to NH and PCR:

� NH:

o Preference for siting projects on previously converted lands: a provision stating clear preference for siting projects on previously converted lands.

� PCR:

o “Chance Finds:” provision to ensure that the terms of reference provided by the CA would provide for the protection of unanticipated “chance finds” encountered during road construction implementation as well as PCR previously known and/or surveyed.

Recommended Measures to Sustain Equivalence for the Rural Roads Sector

21. The RGoB has for some years recognized the need for a more holistic approach to environmental law and regulation. Such recognition was expressed at the outset of the current Ninth Five-Year Plan for which the Environmental Sector Plan called for the development of an “umbrella law” (the “National Environmental Policy Act” or NEPA) to facilitate implementation of such an approach. The July 24, 2006 Draft of the NEPA (“NEPA Draft”) provides a longer-term opportunity for addressing the differences identified in the Equivalence Analysis with respect to EA and NH. Bhutan is also in the process of drafting a Conservation of Archeological Heritage Act. Although an English-language draft is not yet available, based on interviews with knowledgeable officials, enactment of provisions contained in the current draft could provide an alternative opportunity to bridge the Equivalence difference that applies to PCR. Accordingly comments on the most recent NEPA draft are proposed in the Equivalence section of this report and in the Equivalence Matrix (see Annex A).

22. Likewise, although it is not proposed to include IR as one of the safeguards to be piloted in the RAP II project, the onging reform of the LA provides the RGoB with an opportunity to address the issues identified above with respect to the legal framework for land acquisition and IR in Bhutan. Issues that are conducive to such an approach are highlighted in the Equivalence Matrix (see Annex A).

RESULTS OF ACCEPTABILITY ASSESSMENT

23. Overall, the Acceptability Assessment demonstrates that the agencies and private contractors responsible for implementing Bhutan’s environmental policies, laws, regulations and guidance have the overall capacity to fulfill their responsibilities. The National Environment NEC, together with its Secretariat (NECS), is reasonably well organized and has sufficient resources to carry out its role of reviewing EAs and conducting overall compliance monitoring. The Department of Roads (DoR) has the authority and resources to implement the national policy of Environmentally Friendly Road Construction (EFRC) on the scale required for the RAP II project. Other agencies responsible for granting consent and monitoring the impacts of the project on NH and PCR, including the Department of Forests (DoF) and its Nature Conservation Division (NCD), under MoA, also appear to have the requisite expertise and resources to

Page 11: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

xi

accomplish their assigned missions under the RAP II project. Based on the record of the recently completed RAP I project, during which EFRC was introduced in Bhutan, additional resources and training are needed both within DoR and among the contractors and subcontractors for the RAP II project if the lessons and full benefits of EFRC are to be successfully applied in the RAP II project. The technical assistance component of RAP II, along with the continued efforts of other donors in the environmental and roads sectors in Bhutan, provide substantial opportunities to attain Acceptability for the RAP II project.

24. Contrasting levels of Acceptability were found with respect to the EA clearance process and the compliance monitoring process.

25. EA Clearance Process. The existing EA clearance process, which is centralized under NECS, has become increasingly robust and efficient since the enactment of the Environmental Assessment Act (EAA) in 2000 and in particular since the Regulation for the Environmental Clearance of Projects (RECP) was issued in 2002 clarifying NECS’ roles and responsibilities for EA review and clearance. NECS has hired qualified specialists for each major sector as circumstances have required and has been able to carry out its internal screening and review processes generally within the time frames set forth in the RECP. By all accounts, and as reflected in EA documents for the RAP I project that have been approved by NECS, it has met its regulatory responsibilities with respect to the procedural and substantive requirements of the EAA and the RECP, including the requirements for public consultation as part of the EA process. However, as documented in this and other reports, NEC’s efforts to decentralize the EA review process to line ministries, departments and to a lesser extent to District Environmental Committees (DECs) has not succeeded due to severe limitations of capacity in the line ministries, in particular DoR and the majority of the DECs.

26. Compliance Monitoring: The capacity limitations at the line ministry and DEC levels have had the effect of limiting the effectiveness of compliance monitoring of Environmental Management Plan (EMP) implementation in the rural roads sector, based on this review and other sources cited in this report. Although NEC carries out periodic site inspections it cannot provide continuous on-site monitoring as is needed in order to identify and implement corrective measures during a road construction project. In any case, responsibility for implementation and compliance of EMPs by road contractors is the responsibility of the DoR. Although EFRC techniques were introduced conceptually to DoR as early as 1999 and into the RAP beginning in 2002, with substantial technical support from SNV, these techniques have yet to be fully integrated into the EMP and Compliance Monitoring Procedures followed by DoR.

Proposed Measures to Attain Acceptability

27. To meet the Acceptability criteria for OP 4.00, a number of capacity building measures would need to be completed within the scope and duration of the RAP II project. At the operational level, the guiding principle for these measures would involve the further implementation of the objectives of the Environmentally-Friendly Road Construction Support Project (EFRC-SP) initiated with substantial support from SNV in the context of the RAP I project.

28. Accordingly, the following measures were discussed and agreed to at the Public Consultation Meeting on this report held in Thimphu on October 24, 2006:

� Coordinated management of the EA process for RAP II. Under NECS guidance designated Environmental Officers (EOs) in DoR and MoWHS are to undertake review

Page 12: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

xii

and approval of EAs for RAP II;

� Contractors are to be held directly accountable for implementation of EMPs and to provide progress reports to field engineers. Specifications regarding EFRC and related monitoring requirements are to be included in contact documents. Reporting requirements are to form part of contract covenants. Field engineers shall submit monthly EMP compliance reports to the Project Coordination Unit;

� EOs, with support from the Assistant Project Coordinator and Project Monitoring Engineer, shall provide regular (no less than quarterly) progress reports to the Project Coordinator. Reporting formats shall be reviewed on a regular (semi-annual) basis and revised as needed to ensure effective communication;

� Contractor payments shall be linked to compliance with EMP requirements;

� DECs are to be empowered to carry out compliance monitoring with independent line reporting to NEC. DECs shall coordinate with field engineers to review compliance at regular intervals, no less than bi-monthly. NEC is to provide regular, on-the-job training to DECs for this purpose;

� Satisfactory Project Completion per EMP requirements shall be certified jointly by EO/DoR and NEC on the basis of site visits to verify compliance with EMP safeguard requirements; and

� NCD, DoF and the Department of Cultural Affairs (DCA)/MoHCA shall be consulted, respectively, on all compliance matters relating to biodiversity, and protected areas and cultural resources.

Proposed Measures to Sustain Acceptability in the Rural Roads Sector

29. Within the context of the RAP II project, but not limited to its scope and term, the RGoB has agreed to a number of additional capacity building measures to be implemented with support from the Bank and other donors, principally, DANIDA, ADB, SNV, and GEF:

� Enhancement of management abilities of key institutions and stakeholders at the District level. This effort, also to be funded by GEF,5 will seek to enhance institutional and individual capacities for EAA implementation, compliance and monitoring at the national and district levels, by focusing on strengthening the linkages between these governance levels. To this end a new position within NECS will be established to function as the key governmental environmental focal point and contact person for the twenty DECs.

� Enhancement of environmental assessment capacity in MoWHS/DoR. It is clear that the progressive delegation of authority and responsibility for EA, EMP and project monitoring to line ministries remains incomplete, particularly in the case of MoWHS. The few environmental positions that are filled in the Ministry are scattered among different units (PPD, DoR, DUDES) with little or no coordination between them. If DoR in particular is to play a substantive role in determining the terms of reference for and reviewing EAs for road construction projects, it will need more dedicated and trained

5 Request for GEF Funding, “Enhancing Global Environmental Management in Bhutan’s Local Governance System,” April 28, 2006.

Page 13: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

xiii

environmental staff in particular staffed trained in understanding and mitigating the ecological impacts of road construction projects in biologically rich areas.

� Enhancement of DoR’s technical resources for EA. As recommended by the EFRC-SP Mid-Term Review, DoR should encourage EFRC-SP to make best use of available and affordable tools and concepts provided by the latest geotechnical resources. DoR needs better aerial and satellite maps and improved GIS based mapping capability to enable it to develop site-specific landslide risk and land susceptibility maps capable of providing better information in road planning, location and alignment, to reduce environmental costs and damages. This would require acquisition of maps (1:10,000 scale in preference to the 1:35,000 to 1:50,000 topographic maps currently utilized), map interpretation facilities, training and skills development for GIS mapping, technical assistance and training support, training of field engineers to use improved mapping facilities to ensure best alignment of roads and identification of appropriate mitigation methods when hazards are inevitable. These measures would enable better design and reduce maintenance costs for future road networks in Bhutan.

� Continued EFRC training in DoR, MoA and Districts. Already over 80 percent of DoR technical staff have been trained in EFRC techniques and their implementation, amounting to approximately 1,400 people. However, about twenty percent of the field engineers and staff still need to be trained. It is necessary that such training be imparted on a regular basis, as well as refresher courses of ERFC implementation. SNV will support one week training workshops/refresher courses for contractors and contractor staff in EFRC implementation. Training will also be extended to MoA and District staff, particularly as these institutions are responsible for participating in monitoring project impacts as well construction of farm and power tiller roads, that are required to incorporate EFRC techniques. At the district level, the GEF project will support the costs of EOs in sixteen of the twenty districts beyond the four pilot districts already supported by NECS, as well as the establishment of designated office space and basic equipment for the DEC members to carry out their tasks. NECS will finalize the terms of reference of the EOs.

� Improved EMP implementation. Improved capacity, training and skills development for field engineers are needed on timely preparation, approval, implementation, monitoring and reporting of EMP implementation, including establishment of monthly progress report formats to monitor and report on EMP implementation, to keep in line with the monthly physical/financial reporting requirements. DoR recognizes that EFRC monitoring needs to capture baseline, compliance monitoring and impact monitoring. Refining/integration of EFRC into the new formats for monitoring and evaluation needs to take place, so as to fully capture the benefits of ERFC implementation.

� Job-specific contractor training. Workshops should be held for two-three days with each contractor, prior to the start of work to determine how the overall EFRC concept will be applied to each particular road segment, so that appropriate resources (manpower and equipment) are allocated to the contract. Compliance with all aspects of contract agreements should be strictly enforced. The contractor must be made aware that non-compliance with any contract clause is a breach of contract which can lead to reworking of contract tasks, penalties, suspension and even termination of contracts.

30. A summary of these capacity building activities, the beneficiaries and proposed schedule is included in Table 2 in the Acceptability section of this report.

Page 14: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

INTRODUCTION

PROJECT DESCRIPTION

1. The RAP II development objective is to provide all-season road access to targeted rural communities. The project will focus on three districts: Wangdue Phodrang, Dagana, and Pemagatshel, where the average distance and walking time from a beneficiary village to an all-season road ranges between 4 and 54 km, or 1 to 15.5 hours. RAP II is a follow-up operation and is accordingly designed to replicate the positive lessons and good practices from RAP I in three new districts of the country.

2. The physical component of the RAP II project will cost an estimated $7.44 million and will involve the construction of three feeder roads of approximately 75 kilometers in length; improvement of 15 kilometers of existing feeder roads; and the privatization of routine maintenance.

3. The institutional development and implementation support element of the project will provide approximately $500,000 towards organizational development of the newly established Investigation and Development Division (IDD) within DoR. RAP II will support IDD in the following areas:

� Monitoring and reporting;

� Data collection for traffic and road condition surveys;

� Quality Assurance;

� Work, procurement and contract management system;

� Technical innovation and engineering; and

� Environmental management.

BACKGROUND

4. Beginning in March 2005, the World Bank has been supporting a limited number of pilot projects in which lending operations are being prepared using the borrowing country’s systems1

for EA and other environmental and social safeguards, rather than the World Bank’s operational policies and procedures on safeguards. The rationale for using country systems is to scale up development impact, increase country ownership, build institutional capacity, facilitate harmonization and increase cost effectiveness. These pilot operations are governed by a new operational policy (OP/BP 4.00) on “Piloting the Use of Borrower Systems to Address Environmental and Social Safeguard Issues in Bank-Supported Projects.” OP/BP 4.00 elaborates on the approach, enumerates the criteria for assessing country systems, and specifies documentation and disclosure requirements and respective roles of the Borrower and the World Bank.

5. The World Bank considers a Borrower’s environmental and social safeguard system to be equivalent to the World Bank’s if the Borrower’s system, as determined by the World Bank, is designed to achieve the objectives and adhere to the applicable operational principles set out in Table A1 of OP 4.00. Since equivalence is determined on a policy-by-policy basis in accordance

Page 15: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

2

with Table A1, the World Bank may conclude that the Borrower’s system is equivalent to the World Bank’s in specific environmental or social safeguard areas in particular pilot projects, and not in other areas. Before deciding on the use of country systems (UCS), the World Bank also assesses the acceptability of the Borrower’s implementation practices, track record, and institutional capacity. The above approach and criteria for assessment were developed with inputs from external stakeholders such as representatives of governments, bilateral and multilateral development institutions, civil society organizations, and the private sector and is consistent with commitments made by the development community in the Paris Declaration on Aid Effectiveness of March 2005.

RATIONALE FOR PROJECT SELECTION

6. Bhutan is one of eight countries being considered thus far for piloting UCS, specifically the proposed World Bank-assisted Rural Access II Project (RAP II). The World Bank has considerable relevant experience in the rural roads sector in Bhutan, having supported the RAP I project which became effective in June 2000 and closed in June 2006. The Bank has also supported projects in related sectors such as sustainable land management, forestry and other sectors with environmental and social impacts similar to those associated with the construction of rural roads.

7. On the basis on this experience, Bhutan was selected for participation in the pilot program due to the relatively recent and therefore advanced state of its laws and regulations corresponding to World Bank environmental and social safeguards, in particular, EA, NH, and PCR, all of which are triggered by the RAP II Project. In addition, Bhutan’s satisfactory performance in implementing the environmental and social safeguard requirements applicable to the RAP I project, as noted in the Bank’s draft Implementation Completion Report on RAP I, suggests that Bhutan’s system may be sufficiently robust to provide the basis for piloting in the rural roads sector. The Bank acknowledges that this performance may be attributed in part to the contribution of other donors, including SVN, in introducing environmentally sound road design and construction practices through the Environmentally Friendly Road Construction Support Project (EFRC-SP).

DONOR ACTIVITIES AND COORDINATION

8. The application of UCS to Bhutan and to the RAP II project is consistent with other donors’ current priorities and programs that seek to contribute to the enhancement of Bhutan’s environmental and social policies, laws, institutional capacity and performance and to the development of the rural roads sector. Of specific relevance to the RAP II project and to this SDR is the support that DANIDA is providing for legislative reform and capacity development through Environmental and Urban Sector Program Support (EUSPS); ADB’s technical assistance for enhancement of environmental capacity within sector ministries, at the local level and in the roads sector,6 and SNV’s EFRC-SP.7 In addition this exercise will benefit from the joint United Nations Development Programme (UNDP)-RGoB assessment of Bhutan’s capacity for global

6 Asian Development Bank, Technical Assistance to the Kingdom of Bhutan for Capacity Building to Implement Environmental Assessment Procedures, August 2005; ADB Loan to Help Improve and Expand Bhutan’s Road Network, ADB press release, October 30, 2005. 7 Netherlands Development Organization (SNV), The Road to Sustainability: Environmentally Friendly Road Construction,: Bhutan;” See also, Hendrik Visser, Reindert Augustijn and S.N. Rai, Environmentally Friendly Road Construction in Bhutan: Providing Access to Rural Communities While Protecting the Environment” Seminar on Sustainable Access and Local Resource Solutions, November 28-30, 2005.

Page 16: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

3

environmental management,8 and the joint work undertaken by Bhutan’s NECS and the United Nations University on environmental governance in Bhutan.9

STRUCTURE OF THE REPORT

9. Part I of this report comprises the Equivalence Analysis carried out by World Bank legal and policy staff in collaboration with NEC, the RGoB’s Office of Legal Affairs and officials at other agencies with legal authority over decisions in the rural road construction sector, including MoWHS, and MoA. Part II comprises the Acceptability Assessment carried out by World Bank policy and technical staff in collaboration with NEC and other Bhutanese agencies charged with the implementation of laws and regulations dealing with the environmental and social impacts of rural road construction. These agencies include the Policy Planning Division (PPD) and the DoR/ MoWHS; DoF and DoF’s NCD/MoA; and the DCA/MoHCA. Annex A to this report contains a matrix summarizing the major equivalence findings relative to the Objectives and Operational Policies of OP 4.00, and the remaining differences and measures designed to bridge these differences.

METHODOLOGY AND PROCESS FOLLOWED IN DETERMINING EQUIVALENCE AND ACCEPTABILITY

10. The methodology used to determine equivalence between Bhutan’s EA systems and the Objectives and Operational Principles of OP 4.00 that are applicable to the proposed project involved: (a) a close analysis of Bhutan’s laws, regulations and the CEPHR as these pertain to four environmental and social safeguards (EA, NH, PCR and IR) that are triggered by the RAP II project; (b) interviews with Bhutanese officials, private consultants and members of civil society who are responsible for or otherwise involved in the implementation of Bhutan’s legal and administrative framework for the rural roads sector; (c) consultation with other donors engaged in projects to support the development of Bhutan’s legal system for EA and EMP and its institutional capacity both in general and in the specific context of the rural roads sector; (d) a critical review of the RAP I project from the perspective of Bhutan’s implementation of its own environmental and social safeguard laws and regulations; (e) a review of EAs under way for projects financed independently of the World Bank or other donors that apply environmental and social safeguard conditions; and (f) a site visit to a rural roads segment under construction that is not being supported by the Bank or similar donors.

11. The SDR process included two dedicated Missions. The first, in May 2006, focused on determining Equivalence of Bhutan’s laws, regulations and mandatory codes of practice with the corresponding environmental and social safeguards of the Bank. The second Mission in September 2006 focused on determining the Acceptability of Bhutan’s implementation practices with respect to the three environmental safeguards for which Equivalence had been determined.

8 RGOB, NECS, UNDP, “National Capacity Self-Assessment for Global Environmental Management and Action Framework,” September 2005, p. xvi. 9 NECS and the United Nations University, “Environmental Governance in Bhutan – National Case Study,” June 2004.

Page 17: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

4

PART I. EQUIVALENCE ANALYSIS

APPLICABLE WORLD BANK SAFEGUARDS AND EA CATEGORY

12. Of the eight World Bank safeguard policies included in the UCS pilot program, four are applicable to the project: EA, NH, PCR and IR. The remaining IBRD environmental and social safeguards – Forests, Pest Management, Safety of Dams and Indigenous Peoples – are not applicable to the RAP II project. The project has been screened as IBRD Category B for purposes of EA.

LEGAL STRUCTURE FOR APPLICABLE SAFEGUARDS

Policy Framework

13. The 2005 Draft Constitution of the Kingdom of Bhutan (Draft 2005). Bhutan is in transition to a constitutional monarchy; the draft Constitution is scheduled to be adopted in early 2008. Although the draft Constitution has no current force of law, it is frequently cited as a source of policy guidance. Should the draft be adopted in its current form Bhutan would become one of the very few countries in the world which has incorporated environmental conservation as a constitutional mandate. The draft Constitution, which was released in March 2005 for public review and comments, provides for environmental conservation in its Article 5. The Article states that:

� Every Bhutanese is a trustee of the Kingdom’s natural resources and environment for the benefit of the present and future generations and it is the fundamental duty of every citizen to contribute to the protection of the natural environment, conservation of the rich biodiversity and prevention of all forms of ecological degradation including noise, visual and physical pollution through the adoption of environmentally friendly practices and ethos;

� The Royal Government shall: (a) protect, conserve and improve the pristine environment and safeguard the biodiversity of the country; (b) prevent pollution and environmental degradation; (c) secure ecologically balanced sustainable development while promoting justifiable economic and social development; and (d) ensure a safe and healthy environment;

� The Government shall ensure that, in order to conserve the country’s natural resources and to prevent degradation of the fragile mountain ecosystem, a minimum of 60 percent of Bhutan’s total land shall be maintained under forest cover for all time;

� Parliament may, in order to ensure sustainable use of natural resources, enact environmental legislation and implement environmental standards and instruments based on the precautionary principle, polluter pays principle, maintenance of intergenerational equity; and reaffirm the sovereign rights of the State over its own biological resources; and

� Parliament may, by law, declare any part of the country to be a National Park, Wildlife Reserve, nature reserve, protected forest, biosphere reserve, critical watershed and such other categories meriting protection.

Page 18: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

5

14. Bhutan 2020. The country’s current development philosophy is articulated in the statement of His Majesty King Jigme Singye Wangchuck that “Gross National Happiness is more important than Gross National Product.” For the last two decades, “Gross National Happiness” – underscoring that economic, spiritual and environmental well-being are all equally important – has remained the guiding principle for the Bhutanese in pursuing national development efforts. Around this main tenet, Bhutan has designed its Vision Statement titled “Bhutan 2020: A Vision for Peace, Prosperity and Happiness,” providing a 20-year perspective of development goals and objectives. The Vision Statement features environmental conservation as one of the five main development objectives and emphasizes the need to “ensure that choices made in response to the many challenges that confront the nation embody the diversity of the natural environment.”

15. National Environment Strategy. The National Environment Strategy (NES) titled “The Middle Path” – launched in 1998 – was derived through an inter-sectoral and consultative process. The NES enshrines the concept of sustainable development and identifies three main avenues for such development: hydropower development based on integrated watershed management; agricultural development based on sustainable practices; and industrial development based on effective pollution control measures and environmental legislation. It also examines a number of areas of special importance for environmentally and culturally responsive economic development. These include tourism, roads, financing mechanisms for sustainable development, public health, urbanization, gender and natural resource management, environmental impact assessments, and population. Finally, it goes on to outline five key cross-sectoral needs that the country must effectively address to integrate environmental considerations into economic development planning and policy-making. These needs pertain to information systems and research; institutional development and popular participation; policies and legislation; training and education; and monitoring, evaluation and enforcement.10

16. National Forest and Renewable Natural Resources Sector Policies: Bhutan’s National Forest Policy places priority on conservation of forests and associated resources for their ecological functions. Economic benefit from forest resources is considered secondary and is to be derived within sustainable limits. Bhutan’s Renewable Natural Resources Policy emphasizes people-centered economic development that has prospects for long-term sustainability, balanced and equitable development of the country’s renewable natural resources and distribution of benefits, and development strategies that are environmentally friendly and ensure the integrity of the country’s fragile ecosystem.

10 RGOB, NECS, UNDP, “National Capacity Self-Assessment for Global Environmental Management and Action Framework,” September 2005, p. 29.

Page 19: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

6

Legal Framework

17. The following table provides an overview of the legal framework for Environmental Assessment and Management that is directly applicable to the Roads Sector in Bhutan:

Table 1- Legislation Applicable to the Roads Sector Legislation Objective

Environmental Assessment Act 2000

Establishes procedures for the assessment of potential effects of strategic plans, policies, programs, and projects on the environment, and for the determination of policies and measures to reduce potential adverse effects and to promote environmental benefits. The Act requires the RGoB to ensure that environmental concerns are fully taken into account when formulating, renewing, modifying and implementing any policy, plan or programs.

Regulations for the Environmental Clearance of Projects and Strategic Environmental Assessment 2002

Includes procedures for the implementation and enforcement of the Environmental Assessment Act 2000 and establishes conditions and methods for the use of Strategic Environmental Assessment where applicable.

Road Act 2004 In relation to environmental management, the Act accords the DoR power and function to adopt and promote environmentally friendly techniques in the implementation of road construction activities. It requires that all road construction and maintenance works conform to environmental considerations, geological stability considerations and preservation of agricultural land.

Forest and Nature Conservation Act 1995

Provides for “the protection and sustainable use of forests, wildlife and related natural resources of Bhutan for the benefit of present and future generations,” and covers forest management, prohibitions and concessions in government reserved forests, forestry leases, social and community forestry, transport and trade of forestry produce, protected areas, wildlife conservation, soil and water conservation, and forest fire prevention.

Forest and Nature Conservation Rules 2000

Promulgated for the enforcement of the Forest and Nature Conservation Act 1995.

Dzongkhag Yargye Tshogdu and Geog Yargye Tshogchung Acts 2002

Contain numerous provisions for environmental management by local community bodies at the district and block levels.

Source: IBRD, Environmental Management Plan, Sustainable Land Management Project

Summary of Applicable Laws: Environmental Assessment

18. Environmental Assessment Act 2000 (EAA). The Environmental Assessment Act of 2000 establishes procedures for the assessment of potential effects of strategic plans, policies, programs, and projects on the environment, and for the determination of policies and measures to reduce potential adverse effects and to promote environmental benefits. It establishes the requirement that an Environmental Clearance (EC) shall be a prerequisite for the issuance of a Development Consent (DC).11 EC is defined under Article 6 of the EAA as “the decision…issued in writing by the [NEC] Secretariat or the Competent Authority (CA) to let a project proceed, which includes terms to ensure that the project is managed in an environmentally sound and

11 Article 6 of The EAA defines “Development Consent” as “the approval issued or renewed by a competent authority in the form of a license, lease or permit for land use or construction.

Page 20: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

7

sustainable way.” The Act also requires the RGoB to ensure that environmental concerns are fully taken into account when formulating, renewing, modifying and implementing any policy, plan or program as per regulations that may be adopted within the appropriate provision of the Act. The Act outlines the steps in EA process; the information required to be publicly disclosed in the EA, as well as during and after the EA process; the functions and powers of agencies charged with implementing the EAA; monitoring and control of offenses and penalties; and appeals and dispute resolution procedures under the Act. These issues are addressed in more detail in Part II (Acceptability) of this report.

19. Regulation for Strategic Environmental Assessment 2002 (RSEA). The RSEA was promulgated with the specific purpose to:

� Ensure that environmental concerns are fully taken into account by all government agencies when formulating, renewing, modifying or implementing any policy, plan or program;

� Ensure that the cumulative and large scale environmental effects are taken into consideration while formulating, renewing, modifying or implementing any policy, plan or program;

� Complement project-specific environmental reviews as per RECP and to encourage early identification of environmental objectives and impacts of all government proposals at appropriate planning levels;

� Promote the design of environmentally sustainable proposals that encourage the use of renewable resources and clean technologies and practices;

� Promote and encourage the development of comprehensive natural resource and land use plans at the local, district and national levels; and

� Outline the duties of government agencies in formulating, renewing, modifying, or implementing any policy, plan, or program, the principles of strategic environmental assessment, and essential contents of the environmental statement.

20. Regulation for Environmental Clearance of Projects (RECP). To implement the Environmental Assessment Act 2000, regulations were promulgated in 2002 for the environmental clearance of projects and for strategic environmental assessment. The RECP define responsibilities and procedures for the implementation of the Environmental Assessment Act 2000 concerning the issuance and enforcement of EC for individual projects and to:

� Provide meaningful opportunities for public review of potential environmental impacts of projects;

� Ensure that all projects are implemented in line with the sustainable development policy of the RGoB;

� Ensure that all foreseeable impacts on the environment, including cumulative effects, are fully considered prior to any irrevocable commitments of resources or funds;

� Ensure that all feasible alternatives are fully considered; ensure that all feasible means to avoid or mitigate damage to the environment are implemented;

Page 21: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

8

� Encourage the use of renewable resources, clean technologies and methods; ensure that concerned people benefit from projects in terms of social facilities;

� Help strengthen local institutions in environmental decision making; and

� Create a uniform, comprehensive data base on the environmental and cultural conditions and assets in the country.

Summary of Applicable Laws: Environmental Management for the Road Sector

21. Road Act 2004. The Road Act, issued in August 2004, establishes powers and responsibilities of various agencies for road planning, design, construction and maintenance at the central, district, block and municipal levels. The Act also provides the framework for setting technical standards and requirements. In relation to environmental management, Section 4(1)(h) gives the DoR the power and function to adopt and promote “Environmentally friendly Road Construction [EFRC] techniques in the implementation of road activities.” Section 7(2) requires that all road construction and maintenance works conform to environmental considerations, geological stability considerations and preservation of agricultural land.

22. Environmental Code of Practice for Highways and Road (ECPHR). Under Article 37 of the EAA, the CA for issuance of a DC is directed to attach environmental terms to the DC “which may contain applicable codes of best practices.” Under these circumstances adherence to the terms of the ECP becomes mandatory when referenced in the EC and/or DC for a project. Such reference is standard operating procedure for ECs provided by NEC for all projects in the rural roads sector. Subsequently, ECPs have been issued by NEC under the authority of the EAA for a number of sectors, including the road sector. Accordingly, the ECPHR, issued by NEC in 2000, is a legally enforceable document for road construction projects, including RAP II.

23. In general ECPs are applied to all stages of a project such as planning, study, survey, design, tendering, contract documentation, project execution and supervision, operation, maintenance, and rehabilitation. The ECPHR is to be used by all parties involved with road construction and maintenance activities. According to NEC, the ECPHR is to be considered as part of the standard operating practices for all DoR road construction, maintenance and rehabilitation activities and must also become part of the project tender documents and contract document packages.

24. An ECP consists of a simple and summarized environmental management plan for every project stage. Each management plan is supplemented with an annex where the required explanations and suggested instructions and/or specifications can be found. The management plan is kept in table form and summarizes the following:

� Sequence of the project activities to be carried out;

� Potential negative environmental impacts for each activity;

� Proposed mitigation measures;

� Need for public participation and co-ordination with other government agencies;

� Socio-economic and cultural considerations;

Page 22: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

9

� Need to budget mitigation measures;

� Supervision requirements; and

� Monitoring and evaluation requirements.

25. The ECPHR requires that all work items concerning environmental issues must be included in the Tender Contract (TC), as quantified work items in the Bill of Quantity (BoQ), and as clauses in the Technical Specifications. This requires the contractor to calculate costs and to execute them in a technically correct manner. To facilitate EFRC implementation, right of way clearance and associated permanent structural works must be tendered as one package so that such support structures are constructed before spoil material deposition or back filling of retaining walls can start. The ECPHR requires that provision for corrective environmental mitigation measures be incorporated into the construction/supervision and operations/maintenance stages of the project and sets forth a checklist of such potential measures for each of these stages.

Page 23: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

10

Environmentally Friendly Road Construction

Since its introduction in 1999 EFRC has become the de facto standard for environmental management in the road construction sector in Bhutan, supplementing, but not supplanting the ECP for the Road Sector.

The Netherlands Development Organization (SNV) introduced the concept of EFRC to the Department of Roads (DoR) in 1999 and until 2002 focused its support on creating an enabling environment for EFRC. It was not until 2002 that SNV began introducing EFRC at the operational level, within the context of the ongoing RAP I project.

EFRC design aims to minimize where possible cuts into mountain slopes. Where slopes are fragile and prone to landslides, part of the road width is made in fill, by constructing retaining walls. Box cut designs are avoided as much as possible in order to reduce the volume and height of cut. The cutting of trees is kept to a minimum and limited to within the road corridor. Excavators are used in place of bulldozers, which allows for the loading of tippers and the transport of excavated surplus material and debris to selected disposal sites. Excavation is undertaken in benches starting from the top batter with a smaller excavator and subsequently excavation to the final level with a medium sized excavator.

Controlled blasting is adopted in order to minimize damage to the surrounding hill environment and to prevent destabilization of the slopes. Marshy areas are drained before excavation is allowed through the construction of gravel drains and other water management structures such as catch drains. Barriers constructed out of logs or boulders are used to catch falling materials and in some cases to allow for controlled dumping of excavated materials. These features are especially important to protect the valley side vegetation from damage and to create spoil disposal areas near the excavation site. The latter is important since transport of excavated materials is relatively expensive. A new design for retaining walls, with gabion boxes, has been introduced. These walls are permeable and are flexible enough to adapt to small slope movements. Bioengineering works are carried out in conjunction with the construction of support structures such as breast- and retaining walls. The use of selected vegetation to stabilize and protect slopes against erosion in the monsoon season has proven to be both successful and cost-effective. Preliminary comparative investment analysis shows that road using EFRC techniquesmay cost up to t 35 percent more than conventionally built road,s but this additional cost can be offset by the eighth year of the road operation due to low maintenance cost. In addition, roads built with EFRC techniques would reduce social and economic costs which would otherwise result from frequent road blocks due to landslides.

source: SNV

Page 24: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

11

Summary of Applicable Laws: Environmental Monitoring

26. Environmental monitoring is referenced in the EAA wherein NEC is given the authority under Article 34.2 to “monitor and control compliance with the terms of environmental clearances.” NECS is directed under Article 35.4 to issue regulations and guidelines concerning “monitoring and controlling compliance.” The CA is authorized under Article 39.3 to “monitor, control and enforce the terms of the environmental clearance attached to development consents, including ordering sanctions and compensation for environmental damage.” This monitoring authority gives the CA and/or NECS the right to enter project sites with or without prior notification in order to ensure compliance with the terms of an EC, the make visual inspections and spot checks, interview employees, occupants or other persons on site, collect samples, inspect and take copies of relevant data or documents and take all other measures necessary to the control of the environment. The respective roles of CAs, NEC and NECS with respect to persistent non-compliance with environmental conditions as well as penalties for non-compliance, appeals and dispute resolution are set forth in Articles 40-43 and Articles 49-62 of the EAA.

27. The allocation of responsibility between NECS and the CA for the conduct of compliance monitoring of projects is delineated in the RECP, along with detailed instructions on compliance orders, appeals, legal challenges, sanctions and compensation.

28. Environment-related provisions of the laws governing the authorities of district (Dzongkhag) and block (Geog) level Development Committees are provided in the DYT and GYT Acts of 2002, respectively, which give the DYT and GYTs the power and function to adopt procedures and rules to implement national laws and enforce national regulations on a broad range of activities relating to the construction of roads, such as extraction and conservation of forests; mining and quarrying; designation and protection of monuments and sites of cultural and historical interest; designation and protection of areas of special scenic beauty or biodiversity; parks and sanctuaries; control of noise pollution; conservation and protection of water resources, lakes, springs, streams, and rivers; community forests; prevention of illegal encroachments on land and forests; prevention of construction of structures, whether on national, communal or private lands within 50 feet of highways falling in local area; and protection and preservation of sacred sites that are not part of custody of a monastic body or central agencies.

Summary of Applicable Laws: Protection of Natural Habitats

29. The Forest and Nature Conservation Act was enacted in 1995 in keeping with evolving conservation needs and to allow for community stewardship of forest resources. The objective of the 1995 Act is to “provide for the protection and sustainable use of forests, wildlife and related natural resources of Bhutan for the benefit of present and future generations.” It covers forest management, prohibitions and concessions in government reserved forests, forestry leases, social and community forestry, transport and trade of forestry produce, protected areas, wildlife conservation, soil and water conservation, and forest fire prevention.

30. To support the implementation of the Forest and Nature Conservation Act 1995 MoA promulgated the Forest and Nature Conservation Rules 2000. The Rules establishe regulations for forest management, private and community forestry, establishment and management of protected areas, wildlife protection, and prevention of forest fires, land clearance, and other activities potentially impacting soil, water and wildlife resources, among other things.

Page 25: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

12

Summary of Applicable Laws: Physical Cultural Resources

31. Bhutan does not have legislation specific to immovable physical cultural property. A draft Conservation of Archeological Heritage Act is in the early stages of preparation (an English-language version is not yet available). There is existing legislation that is applicable to trade in artifacts but it does not apply to most forms of physical cultural property as defined in the Bank’s OP 4.11 on PCR.

32. Bhutan’s National Environmental Strategy addresses the need to promote sustainable development without “compromising the country’s cultural integrity [and] historical heritage.” Likewise, the EAA and the RECP require that EA reports describe and analyze project impacts on “culturally significant sites” and mandate review of EA applications by the Ministry of Home and Cultural Affairs (MoHCA). Legislation authorizing block level administrative bodies (GYT) mandates these local authorities to administer, monitor and review block level plan activities, including maintenance and preservation of monuments not under the custody of central agencies or monastic bodies.

Summary of Applicable Laws: Involuntary Resettlement

33. The social impacts of Involuntary Resettlement in Bhutan are addressed in the Land Act (LA). The Act also incorporates Royal Decrees and resolutions of the National Cabinet and National Assembly both of the past and subsequent years. It stipulates procedures and requirements for registration of land, entitlement to land, right to possession of land, land valuation and taxation, land transaction, allotment of government land, construction or renovation of social infrastructure such as irrigation channels and roads on landed property and sharing of benefits from such infrastructure, use of grazing land, land tenancy, and land conversion and encroachment. At the present, a national task force is reviewing the LA to make it more suitable for evolving development needs. The revised LA is expected to be presented and discussed at the National Assembly in 2007.12

EQUIVALENCE TO OPERATIONAL PRINCIPLES OF OP 4.00, TABLE A1: DISCUSSION

34. A comparative analysis was conducted on the RGoB’s laws and regulations corresponding to the World Bank’s safeguards on EA, NH, PCR and IR as per the Objectives and Operational Principles of OP 4.00 Table A1. The results of this comparison are presented in matrix format in Annex A. The major findings of the analysis are discussed here, with an emphasis on differences between Bhutan’s systems and the required elements of OP 4.00 Table A1 and the relevance of these differences to the RAP II project.

EA

35. Bhutan’s policies, legislation and regulations pertaining to the EA process and EA documentation are relatively recent and reflect international best practice to a significant extent, with the consequence that there is a substantial degree of equivalence between Bhutanese EA systems and the required elements of OP 4.00 Table AI with respect to EA.

36. Remaining differences between Bhutan’s EA system and the Operational Principles for EA contained in OP 4.00 Table A1 include:

12 RGoB, NECS, UNDP, “National Capacity Self-Assessment for Global Environmental Management and Action Framework,” September 2005, p 29.

Page 26: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

13

37. Transboundary and global concerns. One potentially significant difference with respect to EA is the absence of any requirement to assess potential impacts of the project on “transboundary and global concerns.” There is implicit reference to transboundary and global concerns in the EAA Section 18 requirement that the NECS may issue an EC only after finding that a project is “consistent with the environmental commitments of the Kingdom.” A similar implicit reference to transboundary impacts is found in the requirement included in the RECP, Annex C, Section 8 that EA include “cumulative impacts on other projects…work or activity in the immediate surroundings and region.” However, in the absence of a more explicit statement requiring that EA address global and transboundary issues, it is unclear whether these provisions would effectively provide for their inclusion in the EA process.

38. International environmental commitments. Related to the absence of any reference to transboundary issues in Bhutan’s EA system, is the absence of any explicit reference to Bhutan’s international environmental commitments, such as those involving trade in internationally protected species or to domestic legislation enforcing such commitments, such as the Conservation of Biodiversity Act. Although such an intent is evident in the National Environmental Strategy which emphasizes Bhutan’s adherence to commitments it has made through international conventions there is only a general, undefined reference in the EAA (Section 18) to the requirement that an EC may be issued only when the NECS is satisfied that a proposed project meets “the environmental commitments of the Kingdom.”

39. Application of World Bank’s Pollution Prevention and Abatement (PPAH) Handbook: In many countries that have made extensive use of World Bank or other multilateral development bank funding, the PPAH is cited as a benchmark for qualitative and quantitative environmental criteria (inputs, technical processes outputs) with respect to pollution abatement and control. In a Guidance Document issued by the NECS in 1999 as background for the issuance of the 2000 EAA by NEC, there was discussion of “criteria for the selection of parameters for consideration in Bhutan.” The discussion was “based on known waste streams of existing industries [and]….emission standards for selected parameters for a number of countries and for World Bank-funded projects in developing countries….The World Bank standards are based on “best-practical-technology” and on levels of waste quality that are routinely achieved by well-run industrial operations around the world. For this reason it is recommended that the RGoB adopt standards that closely approximate those of the World Bank.”13

40. Although Bhutan’s EA system does not include any references to the PPAH per se, the absence of such references is not a substantial difference with the Operational Principles of OP 4.00 Table A1 for this project for two reasons. To begin with the PPAH does not include any criteria for the construction and operation of rural roads and therefore would not be applicable to the RAP II project. With respect to other sectors, the objective of referencing the PPAH is to ensure that a country’s domestic environmental legislation provides for some international benchmarking with respect to the standards it applies to various pollutants and industries. Although Bhutan’s legislation does not make any reference to the PPAH, many of its Environmental Codes of Practice do reference other international standards, such as those issued by the World Health Organization and the Food and Agriculture Organization.

NH

41. Bhutan, a country with an extraordinarily high level of intact biodiversity and primary forest cover, has some of the most progressive conservation and protected areas management

13 NEC Guidance Document, 2000,

Page 27: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

14

policies among developing countries. Therefore, it is not surprising to find that its legal system incorporates virtually all of the elements of OP 4.00 Table A1 with respect to the protection and conservation of natural habitats, with the following substantial difference:

� Preference for siting projects on previously converted lands. The only difference in Bhutan’s system of conservation and protection of natural habitats with respect to the Operational Principles of OP 4.00 Table A1 is the absence of any requirement that preference be given to development on lands previously converted from wilderness as compared to lands that remain in their natural state. This issue may be addressed implicitly in the requirement in the Forest and Nature Conservation Rules providing that land located within protected areas, water catchments or land containing high forest “may be avoided.” Some Bhutanese officials suggested that the term “may” could be a mistranslation of the Dzongkha term for “must,” which if rectified in the English language version of the Rules, would partially address this difference. In any case, a general policy of avoidance in siting projects is not necessarily the same as a policy requiring a preference for converted lands when alternatives are considered.

PCR

42. As noted above, Bhutan has not enacted specialized legislation designed to protect immovable cultural property, such as archeological, paleontological, historical and sacred sites during the development process. However, the need to protect such sites is strongly referenced in the NES and requirements to do so are included in the EAA, the RECP, and legislation pertaining to the responsibilities of local authorities. Collectively, these laws and regulations address nearly all of the required elements of OP 4.00 Table A1 with respect to PCR. There is one aspect where differences remain:

� “Chance Finds.” OP 4.00 Table A1 requires that for materials that may be discovered during project implementation (“chance finds”) there be provision for “chance find” procedures in the context of the PCR management plan or PCR component of the EMP. Bhutan’s legislation does not address the issue of “chance finds.” References in the EAA to cultural heritage appear to restrict its treatment to the pre-implementation phase and to known sites or those discovered during the EA process, and do not make any provisions for unanticipated discoveries of PCR during project implementation.

LA

43. With respect to IR there is some congruence between Bhutanese systems with respect to land acquisition and the Objectives and Operational Principles of OP 4.00 Table A1 to the extent that the LA does require that when the government acquires land it shall inform affected people and enter into consultation with them about the content of the compensation scheme prior to any land taking. Affected people are to be compensated through allocation of replacement land or through financial compensation according to the classification of the land taken. People whose land is acquired and who choose replacement land as compensation are allowed to identify replacement government owned land of equal size and value in the same district. Although the law does not require this in practice, it appears that compensation is often provided to affected people without formal legal rights or claims to lands to be expropriated

44. However, substantial differences were found between Bhutanese systems and the following operational principles of OP 4.00 Table A1 with regard to IR:

Page 28: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

15

� Avoidance or minimization of IR. Although the LA states that government expropriation of land can only be undertaken for national and public interest purposes, it does not predispose the government to avoid or minimize IR, which is an Operating Principle of OP 4.00 Table A1;

� Improvement or restoration of livelihoods. Although the RECP (Art. 2.7) states as one objective of the RECP “to ensure that concerned people benefit from projects” this does not equate to the objective that the livelihoods and standards of living of displaced persons be improved or at least restored relative to the higher of pre-displacement levels or levels prevailing prior to the beginning of project implementation, as does an Operating Principle of OP 4.00 Table A1;

� Assessment of potential social and economic impacts of involuntary land taking or restriction of access to parks and protected areas. The LA requires only that land surveys be undertaken prior to expropriation but no impact assessment of land taking or access restriction is required by Bhutan laws or regulations. This is inconsistent with OP 4.00 Table A1 which requires that census and socio-economic surveys of the affected population be conducted as well as assessment of the potential social and economic impacts of involuntary land taking or restricted access to parks or protected areas;

� Consultation with project affected peoples (PAPs). OP 4.00 Table A1 requires that legal provision be made for consultation with PAPs with respect to planning and implementation of IR, including compensation, development assistance and the establishment of grievance mechanisms, with particular attention to the needs of vulnerable groups. With the exception of compensation, neither the LA nor the applicable environmental legislation provide for such consultation with PAPs on development assistance or grievance mechanism or make any particular provisions for vulnerable groups;

� Provision of information and assistance to displaced persons. OP 4.00 Table A1 requires that displaced persons be informed of their rights, be consulted on options and provided with feasible resettlement alternatives and needed assistance for loss of assets (at full replacement cost), including relocation assistance, transitional support and development assistance, cash compensation under appropriate conditions and civic infrastructure and community services as required. The EAA and the Codes of Environmental Practice: Highways and Roads provide for extensive consultation with concerned people. The LA requires prior consultation with displaced persons affected by land acquisition, including the content of the proposed compensation schemes, but there is no requirement in Bhutan’s laws or regulations to provide information or assistance other than compensation to displaced persons;

� Timing of implementation of resettlement plans and entitlements. OP 4.00 Table A1 requires that all relevant resettlement plans be implemented prior to project completion and that resettlement entitlements be provided prior to displacement or restriction of access. Under the LA, only land substitution provisions are required to be implemented prior to land acquisition. There is no such requirement applicable to cash compensation or other resettlement requirements; and

� Results Assessment. OP 4.00 Table A1 requires that upon project completion, an assessment be conducted as to whether the results of the resettlement instrument have been achieved taking account of the baseline conditions and the results of resettlement

Page 29: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

16

monitoring. As noted above, Bhutan does not require baseline assessment; nor is there any provision for monitoring of resettlement outcomes.

RELEVANCE OF DIFFERENCES TO RAP II PROJECT

45. Not all of the differences between Bhutan’s systems and the Objectives and Operating Principles of OP 4.00 are relevant to the RAP II project. A rural roads project by nature does not raise transboundary or global issues nor does it implicate any of Bhutan’s international environmental commitments. The PPAH does not include guidelines relating to the construction of rural roads; therefore the lack of reference to the PPAH in Bhutan’s EA legislation is not relevant to the RAP II project. On this basis, it can be concluded that there are no relevant differences with respect to Bhutan’s EA legal system that need to be addressed as a prerequisite to using Bhutan’s EA system as a basis for the RAP II project.

46. With respect to NH, the absence of a requirement in Bhutan’s legal system that preference be given to siting projects on previously converted lands is relevant to the siting and alignment of rural roads. Likewise, with respect to PCH, the absence of a generally applicable provision for dealing with chance finds is also relevant to the construction of rural roads. These two differences would need to be addressed in the context of the RAP II project in order to use Bhutan’s systems for RAP II.

CONCLUSIONS OF EQUIVALENCE ANALYSIS

47. With respect to EA, NH and PCR the above findings indicate that there is substantial equivalence between Bhutan’s systems and the Objectives and Operating Principles of OP 4.00 Table A1. The relevant differences that remain with respect to EA (absence of references to transboundary and global issues and Bhutan’s related international commitments and to the World Bank’s PPAH) are not relevant to the RAP II project to the extent that the project does not raise issues involving transboundary, global concerns or Bhutan’s international environmental commitments. The PPAH does not include guidelines for rural road construction. Therefore, there is no imperative for the project to adopt measures designed to bridge these differences with respect to Bhutan’s EA system.

48. With respect to NH (in particular the requirement of OP 4.00 Table A1 that projects be sited preferably on previously converted lands) and PCR (with respect to provisions relating to “chance finds”) differences are relevant, but can readily addressed within the scope and duration of RAP II through the measures proposed below. It is, therefore, recommended that these three environmental safeguards be further considered for piloting under OP 4.00 in the RAP II project, subject to: (a) the measures designed to attain equivalence as proposed below and (b) the findings and recommendations of the Acceptability Assessment included in Part II of this report.

49. With respect to IR, although there is some congruence between the objectives of Bhutan’s systems and the objectives of OP 4.00, the differences between Bhutan’s systems for land acquisition and mitigation of impacts on project affected peoples and the operational principles of 4.00 are significant, profound and are clearly relevant to a rural road construction project. These differences may be attributed to the fact that the governing legislation of Bhutan regarding land acquisition dates from 1979, well before the institution of current resettlement policies and practices among multilateral development banks and other donors. Given the necessity of a significant revision of the LA in order to address these differences, a process that has only recently begun, and that the RAP II project is nearly at the IBRD Appraisal stage, it is

Page 30: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

17

highly unlikely that the RAP II project would be an appropriate vehicle for addressing these differences.

50. Therefore, it is agreed that the Bank will continue to apply its traditional safeguard mechanism, OP 4.12, rather than Bhutan’s own systems to the assessment and management of the IR impacts associated with the RAP II project. Moreover, Bhutan is currently undertaking a substantial revision of the LA to be presented at the forthcoming session of the National Assembly and has invited the World Bank to participate along with other stakeholders in providing comments in the context of that ongoing review process.

MEASURES TO ATTAIN EQUIVALENCE

51. The following proposal for measures to attain and sustain Equivalence between Bhutanese and World Bank environmental safeguards was discussed with NECS during a meeting at the conclusion of the Acceptability Mission held in Bhutan from September 11-21, 2006. The proposal is limited to two of the three environmental safeguards (NH and PCR) which are under consideration for piloting under OP 4.00 within the RAP II project and for which relevant differences remain between Bhutan’s systems and the Operational Principles of OP 4.00 Table A1. As noted above, no measures are proposed with respect to EA as there are no relevant differences between Bhutan’s systems and OP 4.00 that need to be addressed within the context of the RAP II project. Likewise no measures are proposed with respect to IR, as this safeguard is not being proposed for piloting under the RAP II project.

52. It was agreed that all of the relevant differences identified in the above Equivalence Analysis could be readily addressed by clarifications of existing laws and regulations and/or amendments to the CEPHR. Such amendments to the CEPHR could be accomplished under the administrative authority of NEC.

NH

� Preference for siting projects on previously converted lands: include a provision stating clear preference for siting projects on previously converted lands.

PCR:

� “Chance Finds:” include a provision to ensure that the terms of reference provided by the CA would provide for the protection of unanticipated “chance finds” encountered during road construction implementation as well as PCR previously known and/or surveyed.

MEASURES TO SUSTAIN EQUIVALENCE IN THE RURAL ROADS SECTOR

53. Beyond these administrative measures, the RGoB has for some years recognized the need for a more holistic approach to environmental law and regulation. Such recognition was expressed at the outset of the current Ninth Five-Year Plan (2002-2007) for which the Environmental Sector Plan called for the development of an “umbrella law” (the “National Environmental Policy Act” or NEPA) to facilitate implementation of such an approach. Bhutan is also in the process of drafting a Conservation of Archeological Heritage Act. Although an English-language draft is not yet available, based on interviews with knowledgeable officials, enactment of provisions contained in the current draft could provide an alternative opportunity to bridge the Equivalence difference that applies to PCR.

Page 31: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

18

54. The most recent, July 24, 2006 draft of the NEPA (“NEPA Draft”) that has been shared with the World Bank provides longer-term opportunities for addressing the differences identified in the Equivalence Analysis for two of the three environmental safeguards proposed for piloting: EA and NH. Accordingly, comments on the provisions proposed in the current NEPA draft are included in the Equivalence Matrix (Annex A to this report) and are summarized below.

� EA

o Transboundary and global concerns. Article 10.3 of the NEPA Draft would authorize NEC to ensure that the EA process would include the requirement for transboundary consultation when a plan, program or project may have an impact on a neighboring country. Enactment of this or an equivalent administrative measure in the CEPHR would bridge the difference between the ambiguous references in the EAA and RECP to “the environmental commitments of the Kingdom” and to “cumulative impacts on other projects…work or activity in the immediate surroundings and region” and the Operational Principle of OP 4.00 with respect to the inclusion of transboundary and global concerns in the EA process.

o International environmental commitments. Article 103 of the NEPA Draft would require that international (bilateral and multilateral) environmental agreements ratified by the National Assembly “shall be enforceable as any other domestic laws.” The difference between language of EAA and the Operational Principle of OP 4.00 Table A1 with respect to the need to reference Bhutan’s international environmental commitments in the EA process could be bridged by: (1) enactment of Article 103 of the NEPA Draft; (2) an equivalent administrative measure in the CEPHR under the administrative authority of NEC; or (3) other administrative measures clarifying the responsibility of NECS to ensure that the EA process references all applicable domestic legislation, including legislation implementing Bhutan’s international commitments.

� NH: Preference for siting projects on previously converted lands: the enactment of Articles 5.4 and 5.9 of the NEPA Draft that would require that development activities “shall be strategically planned and executed in harmony with the carrying capacity of the country’s sensitive ecological setting and geographical terrains” and should be planned “to cause the least possible change in the environment” would partially meet the requirement that preference be given to development on lands previously converted from wilderness as compared to lands that remain in their natural state. The difference would be fully addressed were language to be added stating a clear preference for siting projects on previously converted lands.

� PCR: Bhutan is also in the process of drafting a Conservation of Archeological Heritage Act, for which an English-language draft is not yet available. Based on interviews with knowledgeable officials, enactment of provisions contained in the current draft could provide additional opportunities to bridge the Equivalence differences that apply to PCR, in particular with respect to provisions for chance finds.

� IR: Likewise, although it is not proposed to include IR as one of the safeguards to be piloted in the RAP II project, the ongoing reform of the Land Act provides the RGoB with an opportunity to address the issues identified above with respect to the legal framework FOR land acquisition and IR in Bhutan. Issues that are conducive to such an approach include the following, and are noted in the Equivalence Matrix, in Annex A of

Page 32: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

19

this report:

o Avoidance or minimization of IR;

o Improvement or restoration of livelihoods;

o Assessment of potential social and economic impacts of involuntary land taking or restriction of access to parks and protected areas;

o Consultation with project affected peoples (PAPs) with respect to planning and implementation of IR, including compensation, development assistance and the establishment of grievance mechanisms, with particular attention to the needs of vulnerable groups;

o Provision of information and assistance to displaced persons;

o Implementation of resettlement plans and entitlements prior to project completion and that resettlement entitlements be provided prior to displacement or restriction of acces; and

o Assessment: as to whether the results of the resettlement instrument have been achieved.

55. Given the prospect of substantive legislative changes affecting the EA, NH and PCR safeguards during the course of the RAP II project and consistent with its responsibilities under OP 4.00, the Bank will assess the effect of these changes on this Equivalence Analysis and will discuss them with the RGoB.14

14 Per OP 4.00, para. 6. If, during project implementation, there are changes in applicable legislation, regulations, rules or procedures, the Bank assesses the effect of those changes and discusses them with the borrower. If, in the judgment of the Bank, the changes reflect a further improvement in the country systems, and if the borrower so requests, the Bank may agree to revise the legal framework applicable to the operation to reflect these improvements, and to amend the legal agreement as necessary. Management documents, explains, and justifies any changes to such framework, and submits them for Board approval (normally on an absence of objection basis). If the country system is changed in a manner inconsistent with the legal framework agreed with the Bank, the Bank’s contractual remedies apply.

Page 33: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

20

PART. II ACCEPTABILITY ASSESSMENT

ENVIRONMENTAL GOVERNANCE PROCESS IN BHUTAN

Organizations of Government

56. His Majesty the King, the National Assembly, the Royal Advisory Council, the Judiciary, the Council of Ministers and the Sectoral Ministries are organizations that play a crucial role in the governance of the Kingdom of Bhutan. After a reformation of the Government in 1998, the Coordination Committee of the Council of Ministers was given full executive powers. Under this process, the country is governed primarily through the cabinet. The Council of Ministers is headed by the Prime Minister, who also currently serves as Minister of Foreign Affairs. The central government consists of nine other Ministries, five Commissions, the Royal Bhutan Army, Royal Bhutan Police, Royal Body Guards and several autonomous bodies. Ministries include: Foreign Affairs, Planning, Works and Human Settlements, Communications, Trade and Industry, Finance, Health and Education, Agriculture, and Home Affairs. The Five Commissions are: Planning Commission, the Royal Civil Service Commission, the Special Commission for Cultural Affairs, Dzongkha Development Commission and National Environment Commission.

57. A Royal Advisory Council consists of 9 councilors to advise the King and his Ministers. Six councilors are elected by the people, and two come from the monastic body. The chairman to the council is nominated by the King and acts as Government representative in the council.

58. The National Assembly (NA) has 150 members of whom 105 are popularly elected for a term of three years. The monastic body elects 10 monastic representatives who serve for one year terms, while the remaining 35 members are government representatives nominated by the King. The NA normally sits twice a year.

59. Bhutan is divided into 20 Dzongkhags (districts) of which larger Dzongkhags are sub-divided into Dungkhags (sub-districts). Dzongkhags are further sub-divided into 196 Gwogs (blocks). Gups (heads of blocks) assist Dzongdags (district heads), and Dungpas (sub-district heads) with the collection of taxes, mobilization of labor for community services and public construction projects, settlement of disputes, and many other activities including implementation of development programs. Decentralization has been a major thrust of government reform in Bhutan since 1981 when it was adopted an official development strategy with the establishment of the District Development Committees (Dzongkhag Yargye Tshogchung (DYTs) and in 1991 the further delegation of administrative authority to Block Development Committees (Gewog Yargye Tshogchung) or (GYTs). The strategy was significantly accelerated in the Ninth Five Year Plan (2002-2007).15

Environmental Assessment Process

60. The EA process is outlined in the RECP and is closely linked to the issuance of DCs for proposed projects. The issuance of DCs is delegated to the CA, typically line ministries such as

15 Karma Ura and Sonam Kinga,“ Bhutan- Sustainable Development through Good Governance,” Center for Bhutan Studies, Thimphu, May 2004; RGOB, National Environmental Committee Secretariat and United Nations University, “Environmental Governance in Bhutan – National Case Study,” June 2004, p 12.

Page 34: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

21

the MoA, the Ministry of Trade and Industry and MoWHS or a Department within one of these ministries and at the regional level, the DECs. There is also a list of minor activities for which no EC is required.

61. Under the EAA, a CA may not issue a DC for a project unless either: (a) the CA issues an EC for the project; or (b) NECS issues an EC for the project. The determination of whether the EC shall be issued by the CA or by NECS is stipulated in Annex 2 of the RECP which sets forth the specific activities for which each designated CA is authorized to issue an EC. It is explicitly stated that the NECS is the CA for all activities not listed in Annex 2. With respect to rural roads the limited activities delegated to MoWHS in its capacity as CA are road widening/curve improvement; monsoon damage restoration works, permanent works (retaining walls, breast walls, causeways); bridges; and road alignments of less than one kilometer and not falling within protected areas. The DoF is delegated EC authority for road construction within forest management units under its jurisdiction. DECs have EC authority for farm roads of less than 5 kilometers, power tiller roads, mule tracks, private roads of less than 500 meters, and the construction of labor camps. Therefore, essentially all activities to be conducted under the auspices of the RAP II project, with the exception of labor camps, require an EC to be delivered by NECS.

62. Under Article 17 of the RECP, for those activities located within the boundary of a protected area; or within 50 meters of a public park, human dwelling, hospital, school or sacred landscape or site, or any other sensitive area designated by the NECS – whether or not listed in Annex 2- NECS is also the CA. In addition, for these projects, other “concerned agencies” (as specified in NEC’s Application for Environmental Clearance Guideline for Highways and Roads) are required to provide “official clearance” before a CA can submit a request to NECS for an EC. There is also an unspecified category of projects which do not require a DC, but which nonetheless require an EC from NECS. Once the CA has done so, it forwards the application to NECS. NECS then conducts a desk study of the application and may request additional information from the CA. In fully reviewing the application the NECS may conduct a site visit to verify information included in the application.

63. The CA has 15 days to acknowledge receipt of an Application for EC (AEC) during which time it must first assess the EC application for adequacy of information. Applicants are free to consult the CA or NECS prior to submitting an application to determine whether the proposed activity is subject to the RECP as well as the potential scope and duration of the EA process. If the type of activity is listed in Annex 2 of the RECP, the application stays with the CA. If not listed, or listed in Annex 2, but falling within the boundary of a protected area; within 50 meters of a public park, human dwelling, hospital, school or a sacred landscape or site, or any other sensitive area so designated by NECS (per Article 17 of the RECP) the CA still has to confirm whether the application conforms with the CA’s own regulations before forwarding it to NECS. The CA or NECS has up to three months to screen the project to determine the level of EA required and to asses the adequacy of the application to meet criteria specified by law and regulation. NECS or the CA must screen and assess the application using criteria and procedures outlined in Chapter III of the EAA.

64. The full screening process leads to one of three outcomes: 1) rejection of the application; 2) issuance of an EC; or 3) requirement for further studies, including a full EA. If screening determines that a full EA is required, the time frame in which to conduct the EA is negotiated between the applicant and the CA or NECS. The CA/NECS has up to three months to issue or deny the EC based on the findings of the EA report. Within 15 days of decision the CA is required to notify the public of its decision. Based on the EC, the applicant has up to one month

Page 35: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

22

to undertake a legal agreement to comply with the EAA. Any decision by the CA may be appealed for up to 30 days from the date of public notification.

65. ECs are required at a minimum to specify binding mitigation and compliance measures and appropriate monitoring, recording and reporting requirements. All ECs (whether issued by NEC or another CA) may be effective for up to five years and may be renewed with or without changes to environmental terms and conditions.

EA Requirements for Highways and Roads Sector

66. Prior to the enactment of the EAA and RECP, the NEC, with financial and technical support from the ADB, issued sectoral EA guidelines for six sectors, including roads. Following the enactment of the EAA and RECP, NEC undertook, again with ADB financial and technical support, to revise and expand the guidelines to conform them to the new legislative and regulatory framework.16 The revised Application for Environmental Clearance Guideline for Highways and Roads was issued by NEC in August 2004. (EA Application Guideline).17

67. The EA Application Guideline itself does not appear to have any legal or regulatory authority, although it makes references to legal requirements of the EAA and RECP in connection with certain practices. However, the Guideline is intended primarily to “assist the CA or the NEC [to] review the project and determine the level of environmental assessment required.” If used by applicants in combination with the EA requirements in the EAA and the RECP, the Guideline provides a useful template for EA in the roads sector.

68. With respect to EA, the Guideline recommends a detailed project description including project objectives; relevance to overall national planning; funding sources; total estimated project cost; project location, specified in road chainage, with maps at a 1:50,000 topographic scale showing existing roads, rivers, protected area and administrative boundaries; and construction specifications including quantities of materials used, excavated materials and explosives.

69. Recommended baseline data includes topography and geology, water course crossings, an inventory of land use, vegetation, protected areas, forest resources, social parameters (population, houses, services, infrastructure), cultural heritage sites and aesthetics. In connection with consideration of project impacts the Guideline recommends consideration of both project (i.e., non-road) and road alignment alternatives.

16 In addition to the highways and roads sector, the expanded list of guidelines includes forestry, hydropower, new and existing industries, mines and mineral processing, power transmission lines, tourism and urban development. 17 Application for Environmental Clearance Guideline for Highways and Roads, NEC, August 2004.

Page 36: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

23

EMP Requirements for Highways and Roads Sector

70. With respect to EMP, the EA Application Guideline recommends a tabular format that describes projected impacts from each stage of project activities and specifying mitigation measures and their estimated costs. It also recommends a detailed breakdown of environmental

Page 37: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

24

costs related to construction, including materials and supervision. The EA Application Guideline recommends that the applicant be held responsible for ensuring that Environmental Terms (ETs) that are attached to the EC are carried out, including all activities to be implemented by contractors. It recommends use of a mechanism of attaching the ETs to the contract document so that the contractor has a clear understanding of the environmental requirements that are to be adhered to during construction. It is also stipulated in the EA Application Guidelines that at the time of tendering, the contractor will be required to prepare a Contractors’ Site Environmental Management Plan (CSEMP) that shows how the contractor will implement the ETs that are included as part of the tender specifications. The CSEMP is to be included as part of the contract documents and is to be evaluated as part of the overall tender.

71. Although the EA Application Guideline is not a binding document, its substantive recommendations relating to EMP and monitoring have been incorporated into the Code of Environmental Practice for Highways and Roads (ECPHR) issued by DoR in 2000.18 According to DoR “the ECP are to be considered as part of the standard operating practices for all DoR road construction, maintenance and rehabilitation activities and must also become part of the project tender documents and contract documents packages.”19

72. The ECP consists of a detailed EMP template for every project stage from planning, studying and surveying, through design, tender documents, construction and supervision; and operation and maintenance. The EA Application Guideline recommends that monitoring responsibilities should be the responsibility of the EC applicant and are to be detailed as part of the EC.

73. Individual EMPs are required for each project stage summarizing:

� The sequence of activities to be carried out;

� The proposed mitigation measures;

� The need for public participation and coordination with other government agencies;

� Socio-economic and cultural considerations;

� The need to budget mitigation measures;

� Supervision requirements; and

� Monitoring and evaluation requirements.

74. In July 2005, under the auspices of the EFRC-SP, DoR issued the Guideline for the Preparation of an Environmental Management Plan.20 (EMP Guideline) The Guideline is designed to be used by contractors and states that “contractors have a legal obligation [to prepare] the EMP” in accordance with the Application for Environmental Clearance Guideline for Highways and Roads and the “National Standard Bidding Document.” It is further stated that the contractor’s responsibility is to prepare the EMP based on the EA and update the EA in order to make it more site specific and applicable. The EMP Guideline specifies that all contractors are

18 RGOB, Department of Roads, “Environmental Codes of Practice: Highways and Roads,” April 2000 19 Ibid. 20 MoWHS/DOR/EFRC-SP, “Guidelines for the Preparation of an Environmental Management Plan,” Version I, July 2005,

Page 38: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

25

required to submit a general EMP along with other bid documents. After the contract has been awarded the selected contractors is required to submit a further detailed EMP, which has to be updated regularly during implementation. Detailed outlines are provided for the components of a general and detailed EMP.

No-Objection Certification

75. According the EMP Guideline, in order to obtain an EC, a No Objection Certificate (NOC) must be obtained from “all relevant parties.” For a roads project, the following NOCs are specified:

Agency/ people concerned Circumstances Dzongkhag/City Corporation Dzongkhag Administrative approval Department of Forest (DoF) Damage or acquisition of sokshing or tsamdo forest Department of Culture (DoC) Located within 50 m of cultural or religious site Nature Conservation Division/DoF Located within boundary of protected areas Municipal authority Located within 50 m of public park Private owner Located within 50 m of human dwelling Private property owner Need to acquire private property Department of Health Located within 50 m of hospital Department of Education (DoE) Located within 50 m of school Department of Energy Require relocation of power line Telcom Authority Require relocation of telephone line Department of Roads Require access from highways and feeder roads

Public Consultation Process

76. The public consultation process applicable for EA for “significant projects” is specified in detail in Articles 31 and Annex 1of the RECP. The CA is authorized to issue an EC only after local authorities and affected persons are adequately informed and consulted

� Public Notice: Applicants are required to provide written notice to “local people” through newspapers or other media prior to any public hearing.

� Public Disclosure: Local authorities are responsible for making copies of all EA documents and decisions available to the affected community and open for public inspection.

� Public Comments: The public and other agencies are provided with at least three weeks from the notice of public availability of EA documents to submit comments.

� Public Consultation Plan (PCB): The CA or NECS may order the applicant to submit a proposed plan for public consultation, notice and review procedures beyond the minimum requirements outlined above, and may order changes to any such PCB to ensure that concerned people and organizations are adequately informed, have adequate opportunity to express their views and to ensure that such views are adequately taken in to account. Each applicant is required to implement any such PCB at its sole expense.

� Verification of Public Consultation: The CA or NECS is required to review and evaluate the implementation of the public consultation process and to verify the findings of any public consultation.

Page 39: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

26

Public Disclosure Requirements

77. Public disclosure requirements are outlined in detail in Chapter IV of the EAA. Under Article 28, when a decision on an EC has been taken, NECS or the CA is required to make a public announcement of the decision and make the following information available to the public:

� Project description;

� Environmental Terms:

� Measures to avoid or mitigate potential adverse impacts and enhance positive benefits:

� Main reasons and considerations on which the EC decision is based, including the basis for the acceptance or rejection of views and arguments presented by other authorities and concerned people; and

� A non-technical summary of the above information

Monitoring and Compliance

78. Under Article 33 of the RECP, NECS is required to conduct compliance monitoring of project that do not require DC and may also conduct spot checks for listed projects under Article 44 of EAA. Under Article 34 of the RECP, the CA is responsible for monitoring compliance for Projects listed under Annex 2 of the RECP.

79. For the roads sector, DoR issued a Monitoring and Reporting Guideline (MRG) in July 2005 under the auspices of the EFRC-SP21. The MRG introduces three levels of monitoring to be selectively incorporated into each phase of the project cycles as described below:

� Baseline Monitoring,: measurement of environmental parameters prior to project inception;

� Effects Monitoring: measurements of environmental parameters during project implementation that can be attributed to the project; and

� Compliance Monitoring: periodic sampling or measurement to ensure that the regulatory requirements are observed and the standards are met.

80. Construction phase: In this phase of the project, three levels of monitoring are pertinent:. routine monitoring, periodic monitoring and evaluation. Routine monitoring is the responsibility of the construction contractors and occurs as the project advances. Records are required to be maintained for by the contractor. For periodical monitoring an external team (to be recommended in the EA on a case-by-case basis) is recruited as appropriate to carry out this monitoring. The cost of this monitoring is be included in the project budget for. Whenever feasible, biannual periodic monitoring should be carried out, once during monsoon and once during the dry season. Projects may be subjected to evaluations e.g. midterm and final evaluations to meet ecological requirements. The findings of the mission is be used to better manage the project to mitigate some of the adverse impacts.

21 MoWHS/DoR/ SNV-EFRC-SP, “Monitoring and Reporting Guideline for the Department of Roads,” July 2005.

Page 40: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

27

81. Operational phase: For the operational phase. there are two levels of monitoring: routine monitoring and periodic monitoring. The site engineer is responsible for carrying out routine monitoring and is directed to inform the head of the Road Maintenance Cell responsible for that road for timely action. An externally formed team should carry out periodical monitoring, whenever feasible on a biannual basis. The team is normally proposed by the EA team commissioned for the particular project. The budget for this monitoring is included in the maintenance cost.

82. Detailed formats are provided for reporting of project progress and status of outcomes as well as checklists to be used by the project engineer or technical teams when monitoring fieldwork to stipulated design and specification requirements. Under DOR’s EMP Guidelines, agencies other than NECS or DoR as the CA are also assigned monitoring responsibilities for roads projects.22 These include:

� DoF: for any illegal tree felling or pouching, improper riverbed quarrying and impacts on nearby forested areas;

� NCD: whether construction activities are being carried out according to the park rules and regulations if the project falls inside or in the buffer zone of a national park or sanctuary;

� DCA/MoHCA: construction activities if near religious structures; and

� District Administration: construction activities within district boundaries.

Appeals, Sanctions and Compensation

83. Suspected violations of the EAA are subject to warning letters and time-limited remedial measures including compliance agreements that must be approved by the CA or NECS. Disputes under the EAA are initially adjudicated by the NEC with final appeal to a Court of Law within 30 days of NEC decision. Sanctions under the EAA may include suspension or revocation of EC and payment of a fine.

INSTITUTIONAL AUTHORITY AND CAPACITY OF AGENCIES WITH ENVIRONMENTAL MANDATES IN THE ROADS SECTOR

84. Agencies responsible for environmental assessment, environmental clearance, project implementation, monitoring and oversight with respect to the RAP II project NEC, MoWHS, DoR, MoA, DoF; NCD and DCA/MoHCA. District Environmental Committees (DECs) in the four Districts involved in RAP II also have an important and growing role to play in project implementation and monitoring.

The National Environment Commission (NEC) and (National Environment Commission Secretariat (NECS)

85. Mandate of the NEC. The NEC was first established in 1989 by Royal Decree as a National Environment Committee as part of the National Planning Commission. Subsequently, as s result of the Paro Workshop on Environment and Sustainable Development held in 1990 and

22 MOWHS/DOR/EFRC-SP, “Guidelines for Preparation of an Environmental Monitoring Plan,” June 2005

Page 41: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

28

coinciding with the start of the Seventh Five Year Plan (1992-1997), the NEC was given the mandate of “coordinating all environmental activities and monitoring the environmental impact of development.” In September 1992, the NEC was officially delinked from the Planning Commission and began functioning as an independent organization. In September 1998 it was reconstituted under the Chairmanship of the Minister of Agriculture and given inter-ministerial representation for policy decisions and guidance on matters related to environmentally sustainable development and institution of measures to integrate environmental management in overall development process.

86. With respect to EA, The functions and powers of the NEC are established in articles 32 and 33 of the EAA of 2000. Under Article 32 the NEC is directed to:

� Supervise the activities of the competent authorities and Secretariat, provide guidance and ensure the implementation of the EAA;

� Adopt regulations defining requirements for strategic environmental assessment of policies, plans and programs of the Royal Government;

� Adopt regulations specifying the time frame within which existing projects shall achieve compliance with the EAA;

� Adopt regulations and guidelines on public information, consultation, mediation and appeals, and on incentives for persons who may inform authorities about emergency situations under Article 48 of the EAA;

� Adopt regulations concerning decision-making and appeal procedures under this Act, where procedures do not exist under other laws;

� Adopt regulations concerning administrative sanctions, fines, and the payment of compensation for environmental damage resulting from projects that have received an environmental clearance under the EAA;

� Bring complaints to the Department of Legal Affairs for the prosecution of violations of the EAA.

� Adopt fine schedule under Article 52, of the EAA which may be reviewed and revised.

87. Under Article 33. NEC also has the discretion to:

� Adopt a list of projects for which the competent authority shall screen and issue the environmental clearance;

� Adopt emission control limits for projects under the EAA; and.

� Hear and decide disputes under this Act.

88. The role of the NEC has not evolved precisely as anticipated in the EAA. The composition of the Commission has been reorganized several times. Although the Commission has meet 22 times since 1992 including twice during 2006, there was a three-year hiatus (2003-2006) during which the Commission did not meet due largely to a jurisdictional dispute over its Chairmanship With the appointment of the current Prime Minister in 2005 this issue was resolved

Page 42: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

29

and the NEC now includes Ministerial-level representatives from the Ministries of Trade and Industry, Works and Human Settlement, Information and Communications as well as the Bhutan Chamber of Commerce and Industry, currently serving in the capacity as the representative of “civil society.” At its first meeting in 2006 the Chairmanship of the Prime Minister the NEC resolved to resume meeting on a quarterly basis.

89. The mandate of the NEC is to be reinforced in the Draft NEPA which states that the NEC is an “independent, multi-sectoral authority and the highest decision-making body of all matters relating to the environment and its management in the country.” The draft further describes the powers and rules of procedure of the NEC. Notwithstanding its right to delegate its powers and functions to other CAs, including DECs, “nothing shall preclude the NEC from its cardinal responsibility of enforcing and administering the provisions of [NEPA].”

90. Mandate of the NECS with Respect to EA. Implementation of many of the above statutory functions of the NEC is assigned by policy and statute to its Secretariat, the NECS. The broad mandate of the NECS most clearly articulated in the Ninth Five Year Environmental Sector Plan (2002-2007) which set forth several immediate, medium and long-term objectives for the NECS:23

� Strengthened overall environmental management and coordination within the environment sector;

� Establishment of an adequate legal framework for environmental management;

� Strengthened professional environmental management of sector activities;

� Strengthened Dzongkhags, Local Authorities and Line Ministries in basic environmental monitoring of development activities;

� Increased environmental awareness through integration of environmental issues in educational curricula and awareness programs;

� Implementation of pollution control and environmental management initiatives in pilot enterprises within the mining and industrial sector;

� Work towards a dialogue with private sector and financial institutions to support clean environmental activities and promote clean technology where possible; and

� Bring all existing industries and mines under the purview of the EAA.

91. According the Ninth Five Year Environmental Sector Plan, “The EA Section of NECS has the mandate to implement and enforce the EA Act, 2000 and its supporting regulations.” It further specifies that under the EAA and its subsequent regulations, the EA Section of NECS is mandated to review project proposals for both new and existing industries, mines, roads and other development activity that are not listed under Annex 2 of the RECP for issuance or rejection of

23 RGOB, NECS, “Ninth Five Year Environment Sector Plan (2002-2007) p. 3

Page 43: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

30

EC. For projects requiring full EA NECS/EA will approve the Terms of Reference as per the RECP. NECS/EA is also required to report to the NEC on the implementation of the EAA.24

92. Among the tasks assigned to NECS under the EAA and the RECP are: implementation of the EAA and supporting regulations, compliance monitoring; strengthening the capabilities of line ministries and updating the EA Sectoral guidelines. With respect to EA and compliance more specific objectives include:

� Ensure that all foreseeable impacts on the environment, including cumulative impacts are fully considered prior to any irrevocable commitment of resources or funds;

� Provide meaningful opportunities or public review of potential environmental impacts of projects;

� Conduct compliance monitoring of project that do not require development consent and conduct spot checks for listed projects under Article 44 of the EAA; and;

� Monitor and ensure that environmental terms and conditions issued with environmental clearances are implemented.

93. The statutory basis for the role of the NECS with respect to EA is codified in the EAA which requires that for all projects not specifically listed under Article 33.1, the competent authority shall forward the application and all related information regarding to the project to the NECS for screening. The NECS is given the role of identifying potential environmental impacts, issuing terms of reference for environmental assessments where required, issuing environmental clearances when it is satisfied that the requirements of A-18 of the EAA are met. NECS is also authorized to screen applications for projects which any agency seeks to undertake that does not require a development consent, and to issue environmental clearances in accord with Article 18.

� Decide on issuance of environmental clearance to projects under Chapter III;

� Monitor and control compliance with the terms of environmental clearances;

� Inform the competent authority of any violation of the terms of environmental clearance, or of any other potentially dangerous activities of a project under Article 40;

� Report annually to the National Environment Commission on the implementation and enforcement of this Act, and propose necessary amendments to it.

94. Under Article 35 NECS, in consultation with the concerned competent authorities, is authorized to shall issue regulations and guidelines concerning:

� Terms of reference for environmental assessments, environmental management plans, and other environmental assessment documents;

� Information to be included in the application for environmental clearance or development consent;

� Fee schedules to cover the costs of administering this Act;

24 Ninth Five Year Environmental Plan, p. 34

Page 44: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

31

� Monitoring and controlling compliance;

� Emergency response;

� Reporting on the implementation and enforcement of this Act; and

� Any other matters necessary for the implementation and enforcement of the Act.

95. Under Articles 36. NECS is vested with the powers and duties of a CA under Articles 39 for the environmental clearance of all projects not explicitly delegated to other agencies. Furthermore Under Article, 37 when the applicant itself a CA the NECS serves as the CA for purposes of EC with all the has the powers and duties assigned to the CA under the Act. Under Article 38, NECS may appoint an Environmental Assessment Advisory Board to provide technical advice on the environmental assessment and the environmental terms for a project.

96. Mandate of the NECS with respect to Public Notification and Consultation. As per the RECP, the NECS along with the CAs, have the responsibility of reviewing and evaluating the implementation of the public consultation process and verifying the findings of public consultation, publishing decisions on environmental clearance of proposed projects through appropriate media for dissemination of environmental information to the public. In addition to this NECS’ EA Section assisted by its Information, Communication and Outreach Section has the specific responsibility to disseminate information concerning the EA process and associated regulations.25 However, it does not appear that NECS is required to maintain any systematic documentation or archive of its public disclosure process.

97. Mandate of the NECS with respect to Compliance Monitoring. According to the Ninth Five Year Environmental Section Plan, The Technical Division of NECS is charged with conducting compliance monitoring of the environmental terms and conditions of all new and existing mines and industries, including other development projects “such as roads”. Under Article 33 of the RECP NECS is also directed to conduct compliance monitoring of projects that do not require DC and may also conduct spot checks for listed projects, in collaboration with technical experts from other agencies. Based on information collected during such tours, environmental monitoring reports are to be prepared for submission to the NEC, Council of Ministers and National Assembly on an annual basis.26

98. Mandate of NECS with respect to the Roads Sector. In the Ninth Five-Year Environmental Sector Plan NECS identified the expansion and improvement of Bhutan’s road network as “vitally important” to the national goal of promoting rural development and improving the quality of life of all Bhutanese people and as “integral” to the supply of materials, equipment and labor needed for development activities including tourism. At the same time, NECS observed that such roads “must be planned and built in an environmentally friendly and culturally sensitive manner within an integrated framework to promote sustainable development. Specifically, NECS called for the elimination of destructive practices, such as “side casting” and improper disposal of construction material and “the use of environmental surveys for all medium and large projects to be carried out as part of an integrated study involving a team of specialists in

25 Ninth Five Year Environmental Sector Plan, p. 35 26 Ibid.

Page 45: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

32

engineering, agriculture, ecology, geology and sociology who work together throughout the entire planning and construction process.”27

99. In August 2004, NEC published its Guidelines for Environmental Clearance Application for Highways and Roads. The Guidelines include explicit specifications for road construction including those relating to disposal of excavated materials, slope stabilization and mitigation measures, including contractors’ site environmental management plans that reference EFRC practice.

100. Current Capacity. The critical role of the NECS in supporting the NEC was recognized in the Ninth Five Year Sector Environmental Plan. The Plan proposed strengthening the capacity of the NECS through streamlined internal management procedures designed to optimize use of its limited human and financial resources. This was to be achieved by having transparent and operational work plans and budgets, clearly structured lines of authority and management responsibility for key functions and concerns. NECS was also directed to work towards improving its financial and administrative systems, including introduction of an information and data management system and the development of clear Terms of Reference and work plans for each division with a clear division of responsibilities.

101. Internal capacity building of the NECS was to be focused on the following priority areas during the period of the Ninth Five Year Plan:28

� Integration of environmental concerns into the national planning process;

� Preparation of a strategic plan for the Secretariat;

� Formulation of a National Environmental Action Plan;

� Refining and expanding environmental objectives and standards;

� Continued development of a legal framework and enforcement/implementation of the EAA;

� Environmental information and baseline data collections and routine monitoring;

� Implementation of the environmental communications strategy; and

� Staff strengthening in terms of number of further training

102. Budget Support. To meet these objectives, NECS was provided with a total budget support package of 147,417 million Ngultrum (Nu) equivalent to approximately US $3 million over the period of the Ninth Five-Year Plan. It was noted that this total represented a slight decrease from the total amount allocated to NECS as part of the Eighth Nine-Year Plan.. Of this amount 18.330 million Nu was to be allocated to implementation of the EAA and supporting regulations and 70.543 million Nu to strengthening the administration and financial management of NECS. The balance of these resources was devoted to strengthening the national and international policy framework; drafting the NEPA; the development of environmental

27 Ibid., p. 19 28 Ninth Five-year Environmental Sector Plan (2002-07) pp 5-6

Page 46: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

33

information management and environmental quality standards; and promoting social mobilization, environmental advocacy and awareness.

103. Through the Eighth Five Year Plan, the NECS budget was supported through various sources, the largest of which was DANIDA, which provided approximately 50 percent of total budget support. Other major donors included UNEP and GEF which collectively provided just under thirty percent. The RGOB provided 16.14 percent. For the period covered by the Ninth Plan (2002-2007) DANIDA has continued to provide approximately one-half of the total budget with the balance coming from the RGOB and other donors.

104. Organization and Staffing. At the present time the NECS is divided into three divisions: Administrative and Finance Technical Division, and Policy and Coordination. The Technical Division is responsible for environmental assessment, research, monitoring, statistics, information, communication and outreach. The Policy and Coordination Division deals with matters related to environmental policy, legislation and program coordination. Since 2002 the NECS has had a stable contingent of 40 full-time staff, including eight assigned full-time to the EC process. At a recent meeting of the NEC, the Commission endorsed a proposed reorganized structure for the NECS, which is awaiting approval by the Council of Ministers.

105. Level of Activity. As of early 2006 NECS reported to NEC that it had processed 588 applications for environmental clearances since the enactment of the 2000 EAA and supporting regulations in 2002 of which 85 percent resulted in the issuance of environmental clearances. In the most recent 2004-05 fiscal year it processed 180 applications for ECs in the of which 142 resulted in the issuance of an EC and 32 remained pending as of March 31, 2005. The major sectors of activity included power transmission lines (46%), roads (26%) and industries (14%).29 According the NEC, annual compliance monitoring of existing industries and mines also continues to be conducted..

Environmental Capacity in Line Ministries

106. Under Articles 22 of the RECP all agencies are required to establish an Environment Unit (EU) responsible for reporting on implementation, enforcement and monitoring compliance with the EAA. Each such EU is required to report annually to the NEC on its implementation and enforcement of the EAA The report is required to include:30

� A list of applications for ECs and their status, giving reasons and justifications for all decisions;

� How the process of inspection, monitoring and enforcement is carried out; and

� Public comments received by the CA on each project.

107. The Ninth Five-Year Plan recognized that although NEC has overall responsibility for coordinating and initiating activities relevant to sustainable development in Bhutan, “it has a limited role when it comes to enforcement of rules and regulations and program implementation.” Accordingly the Plan directed NECS to take the lead in “institutionalizing and strengthening capabilities” in line ministries, districts and private organizations with respect to requirements

29NEC, “Brief Report on Bhutan’s State of the Environment for FY 2004-05” April 2005 30 RECP Article 15.

Page 47: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

34

under the EAA. Annex 2 of the RECP designates a number of agencies as CA to screen, issue or deny environmental clearances for specified types of projects. NECS was specifically directed to work with selected staff of line Ministries to enable the latter to undertake “basic environmental assessments” of proposed rural roads, thus reducing the workload at the central level. The Plan also directed the EA Section of NECS to facilitate line ministries in setting up EU and to work closely with the units in coordinating environmental activities with the line ministries in implementation of the EAA and its regulations by among other things, conducting basic environmental training for sector heads and extension agents in the districts. The EA Section was charged with facilitating the designation by line ministries of environmental focal points 31

108. NEC has assumed the major responsibility of ensuring coordination and consistency in the EA process, and through the creation of a hierarchy of interagency forums, each with distinct roles and responsibilities.

109. This entails three separate functions:

� Major decision-making and policy formulation and interpretation;

� Regular on-going process administration; and

� Technical advice and assistance to proponents in preparing EA submissions.

110. Pursuant to Article 38 of the EAA the NEC has appointed an Environmental Advisory Board. Current membership includes representatives from the National Assembly, the Bhutan Chamber of Commerce and Industry, the Ministry of Communications, MoA, MoHCA and the Ministry of Trade and Industry.32 These functions are coordinated by the NEC Secretariat. The Secretariat is responsible, in consultation with line ministries, for elevating major policy and process issues to the Commission for decisions.

111. Each year the Secretariat reviews screening procedures with responsible ministries and revises them in light of the previous year’s experience.33 Concurrently the Secretariat and the Ministry review the adequacy of environmental terms and conditions applied in permits and contracts issued by each Ministry. The Planning and Policy Divisions of each Ministry are be responsible for initial environmental scoping and screening decisions, according to the agreed-to procedures. Projects screened into the EA process (as opposed to those that might be dealt with by routine licensing) are be administered by ad hoc working groups chaired by the Secretariat. These working groups are responsible for the preparation of terms of reference for EA reports and impact management/monitoring plans, for reviewing and evaluating the completed reports and plans, and for involving local governments, and public NGOs in the EA process.

112. As work loads increase and ministries and local governments begin to acquire trained environmental staff, it is anticipated that more formal institutional structures will evolve to ensure process consistency with greater decentralization. To further this decentralization process and enhance the capacity of local governments on a continuing basis, the Department of Local Governance (DoLG) was created in MoHCA in 2005. In an effort to harmonize and institutionalize capacity building activities into the overall decentralization process, DoLG proposed an integrated Capacity Development Plan at the district and block levels to be prepared

31 Ninth Five Year Environmental Sector Plan, pp. 10, 30 and 35 32 Source: NECS 33 NEC Guidance Document 2000

Page 48: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

35

in collaboration with all relevant sectors. A joint Decentralization Support Program has been established by UNDP, UNCDF, SNV and DANIDA to assist the RGoB in the areas of decentralization. However, many of the designated CAs have yet to carry out their EA and clearance responsibilities. The EA process remains to a large extent a centrally-driven (NECs) function due to limited capacity within the mandated line ministries and departments.

Ministry of Works and Human Services (MoWHS)

113. The Ministry consists of four Departments responsible for Roads, Urban Development and Engineering, Regulations and Corporations. The activities of the Ministry are coordinated by the Policy Planning Division (PPD).

114. PPD. Each government ministry has a PPD with the role of coordinating the activities of each ministry both internally and with the National Planning Commission. The functions of the PPD in MoWHS are to:

� Formulate policies and develop plans related to physical infrastructure;

� Develop and implement acts, regulations and standards related to infrastructure;

� Set policies to promote the construction industry in the private sector;

� Promote research and development related to infrastructure and human services; and

� Develop plans and policies for human settlements.

115. The EU of the MoWHS is located in the PPD. PPD/EU is currently staffed with one full-time Environmental Officer with an undergraduate degree in Environmental Engineering. Other units of PPD include a road engineer, an infrastructure engineer, an economist, a legal officer and a statistician. Its role is to:

� Review the environmental impacts of infrastructure projects;

� Issue ECs for infrastructure projects based on NEC guidelines (per Annex 2 of the RECP);

� Conduct public consultation of proposed infrastructure projects; and

� Conduct environmental monitoring of infrastructure projects.

Department of Roads (DoR)

116. Under the Road Act of 2004, DoR is mandated to take the role of “lead agency in coordinating all road construction” in Bhutan. DoR has four main divisions: the Survey and Design Division for planning and design of roads; the Bridge Division for planning and design of bridges; the Mechanical Division for provision and maintenance of road construction equipment and machinery; and the Roads Division for construction, operation and maintenance of roads. One of six DoR policy objectives, is to “mitigated damage to the natural environment,” and one of its seven strategic objectives is the “adoption of Environmentally Friendly Road Construction Techniques in road and bridge activities.” With respect to the RAP II and other rural roads development projects, the major divisions of DoR charged with project implementation including

Page 49: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

36

environmental clearances, management and oversight include the Standards and Quality Control Authority (S & QCA) with the responsibility for developing standards and ensuring quality in the public infrastructure projects.

117. Within the S & QCA, the Technical and Environment Monitoring Division has functioned as the EU of MWHS from January 2003 through January 2006. The SQCA is identified as one of the CA for issuance of ECs for certain minor listed projects as per the Annex 2 of the RECP including road widening, bridge constructions, , urban road and drainage construction works. In January 2006 the EU was transferred to the PPD Division of the MoWHS.34

118. DoR Contractual Authority. DoR has incorporated environmental provisions, in particular those associated with EFRC, into standard specifications and BoQ items for all feeder roads constructed under the RAP I project. In addition, the new Standard Bidding Document which applies to all construction works in Bhutan, includes a requirement for all contractors to supply an EMP as part of their bidding documents. Contractual EMPs are required to be monitored by the contractual agency’s site representative. Failure to comply on the part of contractors may result in suspension of works or possible termination of contract, if the contractor fails to follow instructions to remediate contract defaults. The challenge is to ensure that these contractual provisions are fully implemented. 119. Environmental Management. DoR’s Tender Contracts (TCs) for road construction projects explicitly reference the ECPHR. Standard clauses in the TCs oblige each contractor to prepare an EMP that conforms with the requirements stated in the ECPHR. This plan includes specific methods to be employed for: location of work and labor camps, drawings indicating how storage areas and adjacent surface waters will be protected against contamination, methods of spoil disposal, quarry and borrow area site operation, protection and restoration procedures and otherwise incorporate environmental mitigation measures into BoQs such that the contractor can calculate the item price and the total cost for their execution. Review by an EA specialist of the environmental requirements contained in each TC is required.35

120. Monitoring and Supervision. Overall monitoring in DOR is the responsibility of DoR’s PPD/EU, subject to spot checks from NEC. Direct monitoring of project construction impacts is the responsibility of DOR’s Project Engineer and his supervisory staff. Other agencies, as well as Dzongkhag Administration also have specific monitoring obligations in areas that affect them as described below.

121. Compliance. Based on the results of monitoring, the Project Engineer has the authority to immediately stop the works in areas of concern when environmental supervision activities reveals a serious existing or imminent environmental hazard. The Engineer also has the authority to extend the contract duration and increase the cost of the contract for the implementation of remedial actions, provided the environmental problem was not caused due to negligence or non-compliance to the ECP by the contractor. Final acceptance of the completed works will not occur until the environmental clauses have been satisfactorily implemented.

122. DoR Human Capacity Resources. The activities undertaken by EFRC-SP in meeting stipulated its objectives can be broadly divided into three distinct but inter-related set of activities: develop wider awareness and skill base among stakeholders, support preparation of technical

34 National Capacity, p. 41 Communication from Sonam Choki, Engineering Unit, DoR, October 10, 2006 35 Environmental Codes of Practice for Roads Construction, Annex 6

Page 50: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

37

manuals and guidelines to support EFRC, and provide advisory support to DoR for RAP implementation.

123. As part of the RAP I project (described below) technical assistance (TA) for mainstreaming EFRC was provided in partnership with Sustainable Development Secretariat (SDS) of Bhutan ( a multi-donor agency of the RGoB) and SNV. The project included full time temporary staff on contract for EM, whose overall responsibilities included: (a) liaising with NEC and World Bank for EA/EMP related activities; (b) contract management on EM related aspects; (c) implementation coordination of bio-engineering measures; (d) overall coordination of training and capacity building; and (e) EM implementation monitoring. The TA has also supported training programs including post-graduate studies, short-term courses, study tours and local training of DOR and project officials. Four DOR engineers completed their overseas post-graduate studies. In addition, a number of short-term courses, training, and study tours were provided to the DOR officials and other stakeholders.

124. The Investigation and Development Division (IDD) and the Geo-environmental Unit (GEU) have also been established in the DOR to undertake the development of standard specifications, quality assurance requirements, field investigations for the compliance with the standards, geotechnical investigation and supports, and environmental and social safeguard aspects. In addition, an Environmental Unit was established in September 2005 within the IDD to serve as the environmental coordinator for DoR. The IDD will be the focus of capacity enhancement activities in the RAP II project.

125. With respect to oversight and monitoring of construction activities, capacity enhancements are required to improve on-site, real time oversight of contractors and subcontractors. Supervision is limited by inadequate number of site-based staff, insufficient skills of site staff on the technical standards; and lack of clarity on roles and responsibilities of the existing staff and their representative institutions.

126. According to DoR management, approximately 80 percent of DoR operational staff has been trained in EFRC standards; the remaining 20 percent (about 60 staff), primarily in the field, have not been trained. Not everyone who has been trained is convinced that EFRC makes sense from an economic standpoint, given the higher up-front costs associated with implementing EFRC in Bhutan’s challenging terrain. In addition, due to the high turnover of contractors continuing training is needed.

127. DoR Technical Resources. With respect to technical resources DoR appears to have regular access to existing aerial photographs of 1:35,000-1:50,000 scale covering most of the country. The Survey Board can produce topographical maps of 1:25,000 scale and, depending on the ruggedness of the area, 10m or 20m contour lines. These maps are a solid basis for designing of optimal alignments at an early project stage. Aerial photographs also allow a preliminary assessment of the geo-technical situation of the project area. An interpretation of the photographs enables an experienced engineering geologist to indicate potential geological weak spots on the topographical map. In addition, the assessment of all known socio -ecological data, taken from land use maps, property maps and satellite imageries, such as existing infrastructures, location of prime agricultural land, sensitive ecosystems and important cultural and religious sites, and its position on the topographical map further allow engineers to avoid sensitive sites or areas when selecting suitable road alignment options at the pre-feasibility study stage. However, DoR senior engineers believe that better topographic maps at 1:10,000 resolution combined with digital satellite mapping would produce more accurate alignments.

Page 51: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

38

128. Organizational Capacity. A major objective of EFRC-SP was "to further strengthen the institutional and organizational capacity of the Department of Roads and other roadwork implementing agencies in Bhutan to sustain the EFRC concept.”

129. Although as a direct result of the EFRC-SP the organizational capability of DOR to implement EFRC methods and introduce community maintenance contracting has demonstrably improved, these efforts have not, however, been fully converted into capacity building modules to meet the long term objectives of the project to build sustainable EM capacity within DOR There is justifiable concern that with the large turnover of staff from the RAP I to the RAP II project, that many of these capacity enhancements will be lost.

130. As noted in the EFRC-SP Mid-Term Review issued in August 2004, in order to develop DoR as an institution with the capability to lead, sustain and expand EFRC in Bhutan, it needs to demonstrate that it is organizationally and institutionally prepared to undergo a change process that it is yet to fully internalize. EFRC-SP now needs to focus on the change process within DoR, and this will need to be done with strong presence at the field level and sharing the information to make decisions and take actions at the central level.

131. Increased EFRC awareness among stakeholders has undoubtedly contributed to stronger sensitivity at the professional and policy level towards achieving quality of output and reducing environmental damage arising from road construction. These two key areas have been well supported and focused by EFRC through development of appropriate techniques, skills, training, documents and compliance mechanisms. However, while there has been heightened desire for quality, the tools and institutional mechanisms developed to achieve them are not yet fully functional.

.Ministry of Agriculture (MoA)

132. MoA is the overall authority for management of renewable natural resources, which includes agriculture, livestock development and forestry. It is made up of three technical departments: Forests, Agriculture and Livestock. Apart from these technical departments, the Ministry directly operates a number of non-departmental services and facilities. These include the National Biodiversity Centre, Bhutan Agriculture and Food Regulatory Authority and Information and Communication Services. It also has established a Council for RNR Research to oversee, guide and coordinate the implementation of research programs.36

133. Department of Forests (DoF). Established in 1952, the DoF is the oldest government department. It is the overall authority for the management of forest resources and wild biodiversity. In terms of land use and cover, forest is by far the most dominant land cover, with 72.5percent (including 8.1 percent scrub forest) of the country under forest cover – one of the highest in the world. Almost all of the forests are natural, with plantation forest being just about 0.2 per cent. The Forest and Nature Conservation Act requires that at least 60 percent of the Kingdom’s land area remain under forest cover. Outside the protected areas, the DoF has a countrywide network of twelve territorial forestry divisions for implementation of field programs and activities related to protection and management of forests and wildlife resources.

134. At the central level, the Forest Protection and Utilization Division is mainly responsible for matters related to forest land allotment, swapping, leasing, clearance and encroachment, coordination of forest demarcation and coordination and monitoring of supply of forest produce.

36 RGOB, NECS, UNDP, “National Capacity Self-Assessment,” op. cit.

Page 52: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

39

The Forest Resource Development Division identifies forest management units (FMUs), carries out forest inventories in the FMUs, prepares forest management plans for the FMUs, and provides technical backstopping for implementation and monitoring of the forest management plans. The Social Forestry Division provides guidance and coordination for social forestry and extension programs, specifically community forestry, private forestry and school social forestry and also monitors reforestation/ afforestation activities in the field.37

135. The role of the DoF of the MoA in the environmental clearance, implementation and monitoring of the RAP II project consists of providing approval, on a non-objection basis, to applications for EC submitted to CAs and NEC. To accomplish this mission, DoF appears and have substantial human and technical resources at its disposal, including a cadre of highly trained foresters at both the central and district levels, near state-of-the art forest and soils mapping technology and a thorough knowledge of the country’s forest resources and their vulnerabilities.

136. NCD. The NCD has overall responsibility for designation, demarcation and management of Bhutan’s protected areas systems which consists of nine protected areas, and associated buffer zones and biological corridors. NCD’s role is critical for the safeguarding of natural habitats in Bhutan, given that Bhutan’s biological resource is one of the richest and most diverse in the world. It ranks among the top ten percent of the countries with the highest species density (species richness per unit area) and is one of the countries with the highest proportion of forest cover in the world. The country is known to have more than 5,400 species of vascular plants, 600 species of birds and 190 species of mammals in the wild. These include several globally threatened species such as the tiger Panthera tigris, snow leopard Uncia uncia, clouded leopard Neofelis nebulosa, red panda Ailurus fulgens, takin Budorcas taxicolor, golden langur Trachypithecus geei, capped langur Trachypithecus pileatus, Asian elephant Elephas maximus,great onehorned rhinoceros Rhinoceros unicornis, serow Capricornis sumatraensis, black-necked crane Grus nigrocollis, rufous-necked hornbill Aceros nipalensis, and white-bellied heron Ardea insignis.38

Table 2. Globally Threatened Species of Birds and Mammals in Bhutan

37 National Capacity,.p.37. 38 RGOB, NECS, UNDP, “National Capacity Self-Assessment for Global Environmental Management and Action Framework,” September 2005. p. x.

Page 53: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

40

Source: Based on IUCN’s Red List of Threatened Species (www.redlist.org)39

137. Over one-quarter of Bhutan is designated as park or other category of nine protected areas.40 The protected areas system consists of four national parks, four wildlife sanctuaries and a strict nature reserve. The protected areas system was further bolstered in 1999, with a network of biological corridors covering an additional nine percent of the country’s area. Bhutan is among the top ten countries in the world with the highest proportion of area under some sort of legal protection.

138. There are strong demographic, religious and cultural predispositions to natural resource conservation in Bhutan. Overall population is small, with the latest census resulting in a total population of 672,425], a decline from previous estimates. Population density is low, despite the act that the population is concentrated in and around narrow areas of arable land, and increasingly in towns and villages. 41

139. Nevertheless, growing population pressure on the land and the need to construct infrastructure, such as roads in and near protected areas, is beginning to challenge NCD’s capacity to monitor of protect Bhutan’s rich biological legacy. In addition, of the nine protected areas in the country, seven share boundaries with other countries.42

140. At present, NCD has established park management offices in six of the nine operational protected areas, with three offices remaining to be staffed.

Table 3. Protected Areas of Bhutan

Protected Area Area (km2)

Main Habitat Types Key Species

Bumdeling Wildlife Sanctuary

1,487 Alpine meadows, high altitude coniferous forest and temperate broadleaf forest

Tiger, snow leopard, musk deer, blue sheep, capped langur, red panda, black-necked crane, chestnut-breasted partridge, Pallas’ fish eagle.

Jigme Dorji National Park

4,349 Alpine meadows, high altitude coniferous forest, temperate and warm broadleaf forests

Snow leopard, tiger, leopard, takin musk deer, blue sheep, Himalayan black bear, red panda, satyr tragopan,

Jigme Singye Wangchuck National Park

1,400 High altitude coniferous forest, temperate and subtropical broadleaf forests

Himalayan black bear, red panda, giant flying squirrel, leopard, tiger, golden cat, rufous-necked hornbill, black-necked crane, Pallas’ fish eagle

Khaling Wildlife Sanctuary

273 Tropical and subtropical broadleaf forests

Tiger, elephant, pygmy hog

39 Cited in RGOB, NECS, UNDP, “National Capacity Self-Assessment for Global Environmental Management and Action Framework,” September 2005. p. 14 40 Ura and Kinga, p28 41 Average population density is more than 19 people per km2 but is variable across the country. Eastern and southern regions have higher population densities than the western region while the northern part is very sparsely populated. National Capacity Self-Assessment, op. cit., p. 9. 42 There is a need for trans-boundary cooperation between protected area personnel on either sides of the border to protect trans-boundary wildlife habitat as well as to prevent poaching as a consequence of porous borders and a ready market for wildlife parts and products in neighboring countries. However, cooperation with Indian authorities is limited to occasional, ad hoc meetings while cooperation with the Chinese authorities is virtually non-existent. 42 RGOB, NECS, UNDP, “National Capacity Self-Assessment,” op. cit.

Page 54: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

41

Phipsoo Wildlife Sanctuary

278 Tropical and subtropical broadleaf forests

Tiger, spotted deer, elephant, golden langur

Royal Manas National Park

1,023 Tropical and subtropical broadleaf forests, and temperate broadleaf forest.

Tiger, leopard, clouded leopard, golden langur, Assamese macaque, elephant, gaur, pygmy hog, hispid hare, rufous-necked hornbill, great Indian hornbill, Pallas’ fish eagle.

Sakten Wildlife Sanctuary

650 High altitude coniferous forest and temperate broadleaf forest.

Tiger, leopard, musk deer, Himalayan black bear, serow.

Thrumshingla National Park

768 Old growth fir forest, mixed coniferous forest, temperate and subtropical broadleaf forests.

Tiger, snow, leopard, red panda, giant squirrel, satyr tragopan, rufous-necked hornbill, wood snipe.

Torsa Strict Nature Reserve

651 Temperate coniferous forests and alpine meadows.

Snow leopard, leopard, tiger, serow, rufous-throated wren babbler

Source (area): Selected RNR Statistics 2003, MoA; and Sustainable Land Management Project Environmental Management Framework, March 2005

141. The protected areas approach in the country departs from the conventional “exclusionary” approach in that it recognizes human-nature interaction as a part of the ecosystems. Local communities have the right to live in a protected area and subsist on natural resources therein but within the limits of sustainability and in harmony with the environmental conservation objectives for which the protected area was established. Efforts to integrate nature conservation objectives and local community development needs in a mutually reinforcing manner are inherent in the protected area management programs. Irrespective of their classification as a national park or wildlife sanctuary, the protected areas are based on a common management concept of zonation, allowing for varying degrees of human intervention or use in different zones along a continuum (core zone-multiple use zone-buffer zone.

MoHCA/DCA

142. The Department of Cultural Affairs within MoHCA is responsible for the protection of Bhutan’s religious and cultural heritage.43 With respect to the RAP II project DCA has the responsibility to provide environmental clearance on a non-objection basis for proposed road construction segments with respect to proximity and impacts to sites known to have religious or cultural significance, typically monasteries, shrines, etc. However, DCA observed that subsequent changes to proposed road alignments are sometimes made without its knowledge and that it becomes aware of potential or actual project impacts after EC has been given and during project implementation. In such circumstances DCA may be able to intervene to mitigate construction impacts (including through alignment changes) on a case-by-case basis Due to its limited authority (discussed above in the equivalence section) DCA does not have the capacity to intervene with respect to “chance finds” that may be anticipated as part of the EA process or subsequently discovered during project implementation.

43 There is a mutually reinforcing relationship between the objectives of religious and cultural heritage and biological heritage conservation in Bhutan due to the tendency of Mahayana Buddhism, as practiced in Bhutan, to imbue its adherents with a compassion and reverence for life that tends to curb profligate use of natural resources. Buddhist and traditional beliefs about appropriate interactions with animals and plants are codified in Bhutan’s conservation principles and laws. The Biodiversity Action Plan recognizes that ”the mountains, rivers, streams, rocks and soils and Bhutan as believed to be the domain of spirits.” Bhutan 2020, the country’s guiding vision document, begins its section on “environmentally sustainable development,” one of the five development goals, with the recognition that Bhutan’s approach to the environment has traditionally been anchored in Buddhist beliefs and values…” 43 Ura and Kinga p. 29

Page 55: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

42

Environmental Capacity of Local Government Units

143. The Ninth Five-Year Plan acknowledged “an urgent need to develop the capacity of personnel at the district level, especially in terms of conducting environmental assessments for development projects. It charged the EA Section of NECS with carrying out training activities for sector head and extension agents in the Dzongkhags to effectively implement the EAA and its regulations in line with the RGoB’s policy of decentralization up to the geog level.44.

144. Over the past few years, District Administrations and NECS have formed District Environmental Committees (DECs) in all 20 Dzongkhags with the responsibility to ensure integration of environmental concerns in district-level planning plans and to implement environmental assessment and clearance procedures for district and block-level projects and activities that are small-scale and unlikely to have any major adverse environmental impacts. The DECs are chaired by the district administrator (Dzongdag) and are comprised of district level planning, agriculture, forestry, engineering and land records officials. The formation of DECs is in line with the RGoB’s decentralization policy and the requirement of the Environmental Assessment Act 2000. It is also intended to cut down the bureaucracy and time involved in the environmental assessment and clearance of smaller projects and activities.

145. To institutionalize and strengthen EA capabilities at the local level the NEC has conducted consultative workshops and training programs. In December 2004 and January 2005 the NEC conducted an eleven day training program for 90 DEC members from all 20 Dzongkhags. The objectives of the training were to:

� Develop the technical capacity of DEC members to conduct compliance monitoring of developmental activities in their respective Dzongkhags;

� Expedite the environmental clearance process by decentralizing some the NEC functions in the DECs;

� Facilitate the incorporation of environmental concerns in mainstream planning

� Make DECs aware of funding windows for environmental projects in their Dzongkhags, such as the GEF Small Grants Program; and

� Discuss the draft ToR for DECs.

146. Despite these efforts, as yet, there is no assigned technical Environmental Officer (EO) in each of the DECs with cross-sectoral environmental expertise who can address the technical environmental tasks and concerns at the district level. To address these gaps, NECS, with support from DANIDA’s EUSPS is also funding Master’s- level degrees in environmental management for four future DEC EOs. However, the DECs still lack technical capacity and dedicated administrative support. 45

44 Ninth Five Year Environmental Sector Plan, p. 10 45 Request for GEF Funding, “Enhancing Global Environmental Management in Bhutan’s Local Governance System,” April 28, 2006.

Page 56: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

43

Private Sector Capacity

147. The road construction industry is a major partner in the implementation of environmentally sound road construction in Bhutan. Through the EFRC-SP capacity building was provided to prime contractors through the Contractors Association of Bhutan (CAB), a body representing nearly 1,498 contractor industry members. CAB recommends that a larger number of individuals would benefit is training were extended to subcontractors and not limited to prime contractors.46

Role of Civil Society

148. Bhutan has very few non-governmental organizations and none that are effectively independent of government control of other official sanction. This is attributed to the lack of any legislation in Bhutan authorizing NGOs to operate as agents of civil society. Such legislation is under discussion among members of civil society, NEC and the National Assembly and is expected to be taken up by the NA in 2008.

149. The Royal Society for the Protection of Nature was founded in 1987 and legally incorporated as a nonprofit NGO in 1997. The mission of the organization is to “inspire personal responsibility and actively involve the people of Bhutan in the conservation of the Kingdom’s environment through education, applied research and information dissemination, and collaboration with concerned agencies and indigenous institutions”. The RSPN has four units: Environment Education, Conservation and Development, Fundraising and Communications, and Administration and Finance. The focus of the RSPN is environmental education as reflected in the vast network of school nature clubs that they have created and sustained across the country. The staff of RSPN are also actively involved in activities to protect the black-necked crane and, of late, white-bellied heron.

150. World Wildlife Fund (WWF) Bhutan Program is a branch of the WWF-US, and is part of the WWF International Network. WWF began its work in Bhutan in the mid-1070's, by providing training to conservation personnel on an ad hoc basis. Support to various projects in Bhutan continued to grow, and in 1992, a field office was established in Thimphu. WWF signed a three-year supplementary agreement with the Ministry of Agriculture (MOA) in 1993, which outlined a three-year plan for collaboration between MOA and WWF. WWF has been directly involved in efforts to delineate and enhance the management of Bhutan’s protected areas network. However, WWF’s Bhutan office considers itself more of a donor agency rather than an advocacy organization, unlike the role of some of other WWF branch offices.

PERFORMANCE AND OUTCOMES

151. In additional to institutional capacity, the Acceptability of Bhutan’s systems for implementing EA (including environmental management of projects and monitoring of project implementation), along with the applicable safeguards of NH and PCR can also be assessed through a review of Bhutan’s performance and outcomes in implementation of projects similar to RAP II. These include the RAP I project as well as other non-Bank-funded projects in the rural roads sector.

46 EFRC-SP Mid-Term Review, June 2004 draft, p. 4

Page 57: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

44

RAP I Project Implementation

152. The main objective of the first Rural Access Project (RAP I) was to improve the access of rural communities to markets, schools, health centers and other economic and social infrastructure, in order to improve quality of life and productivity of project beneficiaries. The project was approved on December 21, 1999, became effective May 24, 2000 and was completed in June 2006. RAP I covered four the four districts of Zhemgang, Lhuntse, Trashi Yangtse and Trashigang. RAP I was initially supported by the Royal Government of Bhutan (RGOB), the World Bank and the Netherlands Development Agency (NEDA). The technical assistance component of RAP implementation was initially supported by NEDA. Upon its termination on December 31, 2002 after 3 years of implementation, this support was continued through the EFRC-SP by the Sustainable Development Secretariat, a RGOB sponsored multi-donor consortium and SNV

153. SNV provided the major source of TA to RAP I in the form of the Environmental Friendly Road Construction- Support Project (EFRC-SP) described above. The project has achieved its development objective satisfactorily with 129 km of feeder roads constructed against 122 km planned at Appraisal.47

154. RAP I project outcomes have been documented in DoR field reports, World Bank Interim Supervision Reports, and EFRC-SP evaluation reports. The World Bank’s Implementation Completion Report (ICR) for the RAP I project is in preparation and its Mission Report is also available. The EAs, EMPS and environmental monitoring plans for the various segments of the RAP I project were developed in a period of transition from 1997 through 2003 during which time Bhutan’s major environmental legislation and Codes of Environmental Practice were drafted and issued. In addition, the EFRC-SP was also introduced during this period, conceptually in 1999 and operationally with respect to the RAP I project beginning only in 2002. Therefore, it is difficult to evaluate the implementation of RAP I in comparison to no consistent body legislative, regulatory or other environmental practice standards.

155. However, it can be concluded that the RAP I project demonstrated several achievements in improved environmental management (EM) and effective integration of EM measures, which have wider application in road development projects in Bhutan, such as the ECPHR, EFRC guidelines, and standard bidding documents, The project has successfully introduced new concepts of bio-engineering measures for slope stabilization and slope protection as an outcome of detailed Geo-technical studies. The full potential of these measures was however, limited by the fact that they were adopted as mid- course corrective actions to improve sustainability of roads and improve EM effectiveness.

RAP I: EA Process

156. The EA process for the RAP I project was conducted as separate exercises for each of the eight segments of road construction included in the project. This resulted in a variety of approaches to EA rather than an integrated and consistent EA process.. It is clear that the RAP I project would have benefited from Sectoral Environmental Framework, as has been conducted by DoR for the RAP II Project.

47 Draft ICR Mission Report, RAP I, September 22, 2006.

Page 58: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

45

157. Nevertheless, some general comments can be made about the quality of the EA conducted.48 The EAs were generally responsive to the Terms of Reference (ToR) provided by NEC and DoR and were consistent with the major requirements of the 2000 ECPHR The EAs effectively identified areas of critical natural habitat, including protected areas, high-value forest and road alignments in proximity to above-ground sites of religious and cultural significance EAs. However, the EAs were not sufficiently site specific in baseline analysis, impact assessment, alternatives assessment or proposed mitigation measures to be thoroughly integrated into detailed project design.

158. If there is a consistent technical weakness in the EA it is in the geotechnical areas: geologically unstable areas were frequently not identified. Geological hazard mapping covering the proposed road network would have provided a stronger basis for choosing alignments to minimize the environmental impacts. These weaknesses are attributed to the fact the many of the EAs were prepared in response to external donor (i.e., World Bank) requirements rather than the then-nascent EA requirements of the RGoB and that, in many cases, the road alignments had been previously designed. In other cases, EAs were prepared prior to detailed road alignment survey work.

Public Consultation Process

159. Public consultations conducted in connection with the RAP I project were documented in the some, but not all of the EAs. Many of the consultations conducted in connection with the RAP I project were undertaken prior to enactment of the EAA and RECP and appeared to be larger donor- (World Bank) driven exercises.

RAP I EMP Process

160. EMPs prepared by contractors for the RAP I project tended to be very general, formulaic and often repetitive. Although generally in compliance with the ToR for EMP included in the ECPHR, they did not consistently incorporate findings and recommendations from the EA process, nor were they consistently updated to take account of changes in road alignment, or unanticipated geotechnical or ecological conditions as required under the ECP for Highways and Roads. This is attributed to the fact that, in spite of extensive training in EFRC undertaken during the course of the RAP I project, contractor site engineers were frequently inexperienced in EMP, turnover of qualified staff remained high, and to a lack of effective monitoring and compliance enforcement, as noted below. DoR attempted to address this deficiency by issuing EMP Guidelines in July 2005, but these were not sufficiently timely to improve EMP quality during the RAP I project

RAP I Environmental Monitoring and Compliance Enforcement

161. Monitoring and evaluation of EMP implementation was the consistent weak point of RAP I implementation. The deficiencies appear to have been related to: (a) lack of allocated responsibility to coordinate overall environmental performance; (b) lack of clear environmental management mandate to field engineers; and (c) deficiencies in documentation, monitoring and reporting mechanism at sub-project level and at divisional level. DoR documentation of RAP impacts and outcomes appears to have been highly dependent on the initiative and resources of external donors, including the World Bank and SNV (in connection with the EFRC-SP). For

48 DoR/EFRC-SP, Evaluation on Environmental Assessment and Environmental Management Plans of Rural Access Project Roads, [undated report, c. 2005]

Page 59: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

46

example, systematic monitoring and evaluating the progress with the bio-engineering for plant survival rates, effectiveness of implementation mechanism in respect of seed supply, nurseries, was not independently conducted by DoR. Spot checks conducted by NECS in connection with the RAP I project do not appear to be systematically documented. Failures by contractors to comply with EMP and other contract requirements only very occasionally resulted in temporary suspension of work, and even more rarely in fines, other penalties or otherwise considered as breach of contract. DoR attempted to partially address these deficiencies by issuing a Monitoring and Reporting Guideline under the auspices of EFRC-SP in July 2005 but, as in the case the EMP Guideline this was too late to influence the quality of monitoring and compliance enforcement for the RAP I project.

RAP I Project Outcomes: Protection of Natural Habitats and Physical Cultural Property

162. In spite of the lack of systematic and integrated EA, EMP and monitoring, significant adverse physical impacts on NH and PCR appear to have been effectively avoided or minimized or mitigated in the case of the RAP I project. To a large extent, this may be attributed to the fact that globally, the major impacts of road construction in areas of limited access tend to be induced, secondary impacts rather than primary, direct impacts of construction activities. This is much less the case in Bhutan than in other developing countries due to the low population density in limited opportunities for conversion of wilderness into agricultural land (including shifting agriculture) on steeply sloped forest land.

163. An example of the apparently limited risks to NH posed by the RAP I project was intersection of the Dakpai-Buli (36.5 km) road alignment with an areas identified in the EA as Golden Langur habitat. As a direct result of the EA a base line study on the Golden Langur was conducted by the NCD of the DoR in 2001. The study concluded that the habitat area was sufficiently large to sustain any impact from blasting and road construction. Although the study’s recommendation for a systematic 5-7 year monitoring effort was not fully adopted by DoR, the fact that Golden Langur is still sited along the Dakpa-Buli road, is cited by the NCD as evidence that the habitat has not been adversely affected. Likewise, with respect to PCR ten different types of religious monuments were identified and protected as part of the EA and EMP for the Lhuentse-Dungkhar (39.78 lm.) road segment. Adequate measures were also provided to protect two chortens along the Yadi-Shershone (7.22 km) alignment.49

164. The limited direct impacts observed from RAP I construction activities may also be attributed to the partly successful integration of EFRC techniques into design, construction and maintenance procedures. As part of the Mid-Term Review of the EFRC-SP, the segments of the Dakapi-Buli Road constructed using a more traditional approach prior to the introduction of EFRC were compared with later segments constructed using EFRC techniques. Consequences of systematic EFRC application were evident in the newly constructed sections: improved structures, considerable reduction in haphazard earth disposal, sensitivity towards natural vegetation and better drainage system. In addition, bio-engineering for slope protection measures have been well integrated into overall environmental management plan. 50

165. However, as is normally the case in pilot phases, some shortcomings were also observed in the RAP I application of EFRC. In some cases RAP implementation resulted in confusion of

49 DoR/EFRC-SP, Evaluation on Environmental Assessments & Environmental Management Plans of Rural Access Roads 50 RAP I ICR Mission Report, September 22, 2006

Page 60: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

47

the alignments under or overestimated cost estimates or the need for permanent structures that were not foreseen in the design process.51

Gomphu-Panbang Road Project EA and EMP

166. The Gomphu-Panbang Road Project is funded by the Government of India’s Border Road Engineering Program, known as “DANTAK.”52 Although DATAK has recently endorsed EFRC in principle, it does not systematically prescribe standard EA practices for rural roads nor does it provide implementation or monitoring support for EFRC-based design and construction activities. Therefore critical review of the EA prepared for this project under DoR supervision53 provides an objective indication of the RGoB’s commitment and capacity to supervise EA and integrate EFRC EMP and monitoring techniques, NH and PCR protection into the EA process in the absence of environmental conditionalities imposed by the World Bank SNV or other donors.

167. The final draft of the EA for the Gomphu-Panbang road project was submitted to DoR in December 2005. The project involves the construction of a 56 kilometer access road along the right bank of the Mangde Chhu River in the district of Zhemgang in the southern part of central Bhutan. The project is particularly challenging from an ecological perspective because the entire road alignment is located within the boundaries of the Royal Manas National park (RMNP). RMNP is known as the largest, biologically richest, and best protected example of southern, tropical and sub-tropical ecosystem of Bhutan, and is situated in the richest part of the Eastern Himalayan biodiversity “hot spot” and one of the richest sites in Asia.54 The park is also continuous with the Manas Tiger Reserve of India, a UNESCO World Heritage Site. The fauna is extremely rich with several internationally recognized endangered faunal and floral species including the Golden Langur and the Golden Monitor Lizard and contains areas of intact primary forest.

168. Although there are a few deficiencies in the EA, the EC process and the resulting documentation demonstrates that Bhutan has the capacity to address sensitive environmental issues in a manner consistent with its own EA requirements and in a manner that is generally consistent with international best practice as reflected in the EA elements of OP 4.00, Table A1.

169. The methodology used in the EA is fully consistent with the requirements of the EAA and RECP with respect to the project description, presentation of baseline data, potential project impacts, alternatives assessment, public disclosure and consultation and proposed mitigation measures and monitoring measures. The EA references in detail the applicable legislative framework and the roles of central district and local officials in the project review and monitoring process. Information specific to the Zhemgang district rather a generic approach is used.

170. The baseline data used in the EA was developed through an exhaustive review of secondary sources supplemented by a fieldwork including a ground-level survey of the entire right of way and one alternative alignment. There is room for improvement in the EA’s characterization of the habitats of endangered species with respect to range and other elements of potential criticality. It appears that extensive discussions were held with local officials of the

51 EFRC-SP Mid-Term Review, June 2004, p. 12 52Since 1961 DANTAK has constructed more than 1,500 kilometers of roads in Bhutan, including the major east-west and north-south highways, as well as other major infrastructure projects. 53 RGoB, Ministry of Works and Human Settlement, Department of Roads, “Final Report: Environmental Assessment: Gomphu-Panbang Highway, Zhemgang, Kyingkhor Consultancy Services, December 2005 54 J. MacKinnon Birds of Royal Manas National Park, 1993 as cited in Gomphu-Panbang EIA, op. cit.

Page 61: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

48

NCD but the details of those discussions were not presented in the EA. The analysis would have benefited from reference to previous studies of the impacts of road construction on Golden Langur habitat in Bhutan as described in connection with the RAP I project, described above. Given the quality of the baseline data, current and potential population density, existing and potential land uses, the impact assessment is candid and realistic with potentially significant adverse impacts predicted as a result of landslides and soil erosion during the monsoon seasons, loss of forest, and loss and fragmentation of non-critical habitat within and immediately adjacent to the right of way (ROW).

171. The alternatives assessment considered the no-project alternative as well as one alignment that would not pass through the core area of the RMNP. The no-project alternative was rejected for social and economic reasons but was not presented in an ecological context. The alternative alignment was given serious consideration from an ecological, economic and social perspective and was rejected for geotechnical and cost reasons. (It is unclear whether this alternative alignment had been given any significant consideration during the initial design of the road or whether it was simply added to fulfill the EAA requirement) .

172. The EA documents extensive public disclosure and consultation on project impacts all of the villages and human settlements encountered along the ROW. The consultations were held at the village level and were supplemented with household surveys that were conducted in a manner designed to be fully gender-inclusive. Results of the public consultations and surveys appear to have been taken into account in selecting the appropriate alignment and proposing specific mitigation measures.

173. The EMP proposes detailed mitigation measures to address the potential direct and indirect impacts of the road construction through the RMNP. These measures incorporate bioengineering, spoils management and other proven techniques developed and implemented by the EFRC-SP in the RAP I project. The EMP also well detailed and assigns clear responsibilities to officials at various levels of government.

174. Deficiencies acknowledged in the EA process include the fact that the baseline data collection took place in the absence of full detailed field survey work. The alignment was therefore in part deduced from a 1:50,000 scale topographic map. Time allotted for the fieldwork was judged to be less than fully adequate. The EA made no mention of any PCR along the ROW nor any approval or monitoring role for DCA. This may reflect the possibility that no cultural or religious sites are located within the RMNP, or may be an oversight in the EA process.

175. In summary the EA, EMP and monitoring plan for the Gomphu-Panbang road project demonstrates that Bhutan has the capacity to implement its own EA requirements for a complex and challenging project in a manner that is designed to protect natural habitats. Although there remain residual ecological risks in constructing a road through a biologically rich national park, if the recommendations of the EA are integrated into the site specific EMPs required of contractors and monitored as appropriate by DoR and other agencies (NCD, DoF) the project has the potential to be implemented in an exemplary manner.

CONCLUSIONS OF ACCEPTABILITY ASSESSMENT

176. Overall, the Acceptability Assessment demonstrates that the agencies and private contractors responsible for implementing Bhutan’s environmental policies laws, regulations and guidance have the overall capacity to fulfill their responsibilities. The NEC and its Secretariat (NECS) are reasonably well organized and have sufficient resources to carry out its role of

Page 62: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

49

reviewing EAs and conducting overall compliance monitoring. DoR under the authority of MoWHS, has the authority and resources to implement the national policy of EFRC on the scale required for the RAP II project. Other agencies responsible for granting consent and monitoring the impacts of the project on NH and PCR, including DoF and NCD under MoA,, also appear to have the requisite expertise and resources to accomplish their assigned missions under the RAP II project. Based on the record of the recently completed RAP I project, during which EFRC was introduced in Bhutan, additional resources and training are needed both within DoR and among the contractors and subcontractors for the RAP II project if the lessons and full benefits of EFRC are to be successfully applied in the RAP II project. The technical assistance component of RAP II, along with the continued efforts of other donors to the environmental and roads sectors in Bhutan, provide substantial opportunities to attain and sustain Acceptability for the RAP II project.

MEASURES TO ATTAIN ACCEPTABILITY FOR RAP II

177. To meet the Acceptability criteria under OP 4.00, a number of measures must be completed within the scope and duration of the RAP II project necessary to ensure effective implementation and compliance with respect Bhutan’s systems relative to project implementation. At the operational level, the guiding principle for these measures would involve the further implementation of the objectives of the EFRC-SP initiated but not fully consummated during the term of the RAP I project. The full implementation of EFRC has implications at the Ministerial, Departmental, and District levels as well as for contractors engaged in road construction project.

178. EFRC is a pioneering concept that was introduced as part of RAP I. It is strongly supported by all participating agencies of the RGoB, including the NA, and forms the norms for road construction in Bhutan. Strong commitment with RGoB and DoR to implement EFRC and RAP I provided the vehicle for testing and refining the application of EFRC, although it came in too late during the implementation of RAP I to make a full impact on the quality and environmental impact of road construction. RAP II should therefore be the chosen vehicle to firmly embed and consolidate EFRC in Bhutan. Accordingly, RAP II will need to take cognizance of this and build in the requisite skills, monitoring and oversight to make this possible and turn Bhutan into an international model for road construction in ecologically sensitive, challenging terrain.

179. EFRC best practices are on display in Bhutan along with good skills and implementation capacity within DoR and among field engineers and contractors. With the recent issuance of DoR Guidance documents for site-specific EMP, Monitoring and Compliance the framework for full introduction of EFRC is in place in Bhutan but needs to be extended and better integrated with EA and EFRC techniques.

180. The following measures were proposed and agreed to at the Public Consultation Meeting on this report held in Thimphu on October 24, 2006:

� Coordinated management of the EA process for RAP II. Under NECS guidance designated Environmental Officers in DoR and MoWHS are to undertake review and approval of EAs for RAP II.

� Contractors are to be held directly accountable for implementation of EMPs and to provide progress reports to field engineers. Specifications regarding BoQs and monitoring requirements are to be included in contact documents. Reporting

Page 63: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

50

requirements are to form part of contract covenants. Satisfactory Project Completion per EMP requirements shall be certified jointly by EO/DoR and NEC on the basis of site visits to verify compliance with EMP safeguard requirements. Contractor payments shall be linked to compliance with EMP requirements.

� Designated DoR Environmental Officers (EOs) with support from the Assistant Project Coordinator and Project Monitoring Engineer shall provide regular (no less than quarterly) progress reports to the Project Coordinator. Reporting formats shall be reviewed on a regular (semi-annual) basis and revised as needed to ensure effective communication.

� Field engineers shall submit monthly EMP compliance reports to the Project Coordination Unit.

� DECs are to be empowered to carry out compliance monitoring with independent line or reporting to NEC. DECs shall coordinate with field engineers to review compliance at regular intervals, no less than bi-monthly. NEC is to provide regular, on-the-job training to DECs for this purpose.

� NCD, DoF and DCA shall be consulted on all compliance matters relating to biodiversity, and protected areas and cultural resources.

MEASURES TO SUSTAIN ACCEPTABILITY IN THE RURAL ROADS SECTOR

181. Within the context of the RAP II project, but not limited to its scope and term, the RGoB has agreed to a number of capacity building measures to be implemented with support from the Bank and other donors, principally, DANIDA, ADB, SNV, and GEF:

� Enhancement of management abilities of key institutions and stakeholders at the district level. This effort, to be funded by GEF, 55 will seek to enhance institutional and individual capacities for EAA implementation, compliance and monitoring at the national and district levels, by focusing on strengthening the linkages between these governance levels. To this end a new position within NECS will be established to function as the key governmental environmental focal point and contact person for the twenty DECs.

� Enhancement of environmental assessment capacity in MoWHS/DoR: It is clear that the progressive delegation of authority and responsibility for EA, EMP and project monitoring to line ministries remains incomplete, particularly in the case of MoWHS. The few environmental positions that are filled in the Ministry are scattered among different units (PPD, DoR, DUDES) with little or no coordination between them. If DoR in particular is to play a substantive in determining the terms of reference for and reviewing EAs for road construction projects, it will need more dedicated and trained environmental staff in particular staffed trained understanding and mitigating the ecological impacts of road construction projects in biologically rich areas.

� Enhancement of DoR’s technical resources for EA. As recommended by the EFRC-SP Mid-Term Review, DoR should encourage EFRC-SP to avail and make best use of available and affordable tools and concepts provided by the latest geotechnical resources.

55 Request for GEF Funding, “Enhancing Global Environmental Management in Bhutan’s Local Governance System,” April 28, 2006

Page 64: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

51

DoR needs better aerial and satellite maps and improved GIS based mapping capability to enable it to develop site-specific landslide risk and land susceptibility maps capable to provide better information in road planning, location and alignment to reduce environmental costs and damages. This would require acquisition of maps (1:10,000 scale in preference to the 1:35,000 to1:50,000 topographic maps currently utilized), map interpretation facilities, training and skills development for GIS mapping, technical assistance and training support, training of field engineers to use improved mapping facilities to ensure best alignment of roads and identification of appropriate mitigation methods when hazards are inevitable. This would enable the better design and reduce maintenance costs for future road network in Bhutan.

� Continued capacity building in DoR, MoA and Dzongkhags. Already over 80% of DoR technical staff have been trained in EFRC techniques and their implementation, amounting to approximately 1,400 people. However, about twenty percent of the field engineers and staff still need to be trained. Contractor compliance. It is necessary that such training will be imparted on a regular basis, as well as refresher courses of ERFC implementation. RAP II will support one week training workshops/refresher courses for contractors and contractor staff in EFRC implementation. Training will also be extended to MoA and District staff, particularly as these institutions are responsible for participating in monitoring project impacts as well constructing of farm and power tiller roads, that are required to incorporate EFRC techniques. At the district level, the GEF project will support the costs of EOs in sixteen of the 20 districts beyond the four pilot districts which are already supported by NECS as well as the establishment of designated office space and basic equipment for the DEC members to carry out their tasks. NECS will finalize the terms of reference of the EOs.

� Improved EMP implementation: Improved capacity, training and skills development for field engineers is needed on timely preparation, approval, implementation, monitoring and reporting of EMP implementation, including establishment of monthly progress report formats to monitor and report on EMP implementation, to keep in line with the monthly physical/financial reporting requirements. DoR recognizes that EFRC monitoring needs to capture baseline, compliance monitoring and impact monitoring. Refining/integration of EFRC into the new formats for M&E needs to take place, so as to fully capture the benefits of ERFC implementation.

� Job-specific contractor training: Workshops should be held for two-three days with each contractor, prior to the start of work to determine how the overall EFRC concept will be applied to each particular road segment, so that appropriate resources (manpower and equipment) are allocated to the contract. Compliance with all aspects of contract agreements should be strictly enforced. The contractor must be made aware that non-compliance with any contract clause is a breach of contract which can lead to reworking of contract tasks, penalties, suspension and even termination of contracts.

182. A summary of these capacity building activities, the beneficiaries and proposed schedule is included in the following Table.

Table 4 Capacity Building Measures Proposed to Sustain Acceptability for RAP II Project Skill/Training Requirement

Responsible Authority

Trainees Remarks/Training Type/Timing

Procurement and contract related

DOR Project staff including Project Coordinator (PC), Asst. PC, Project

Prior to project launch

Page 65: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

52

safeguard issues Managers, Project Engineers and Contractor’s Engineers

Road Survey and Design –Environmental context

DOR/-EFRC-SP

All design and survey engineers, EOs and DEC officials

To be taken up immediately

Conduct of EA NEC/DOR Environmental Officers (Eos) in MoWHS, PPD and DOR, Design engineers, and DEC officials

Prior to forthcoming EAs under RAP-II

E M P implementation DOR Field level and project engineers, DEC officials, EOs and Contractor’s engineers

On job training at regular intervals

Monitoring and Evaluation and reporting

DOR - Same as above- Prior to RAP II construction

Bio-engineering56 (a) Structures

DOR/EFRC-SP

All engineers from PMU and PCU, EOs and Contractor’s Engineers

Study tours to RAP-I and neighboring counties

(b) Vegetation measures for slope protection

DOR/EFRC-SP

- Same as above- On job training

Social assessment NECS/DOR Social assessment specialist to be recruited or the departmental engineer shall be designated for carrying out such activities. In the later case, the engineer shall be provided with long term training

Prior to RAP II construction

Geo-tech skill development to minimize Environmental Hazards

DGS/DOR Two engineers (currently one of the DoR engineer is undergoing Long Term training)

First year of RAP II implementation

� More systematic on-site environmental compliance monitoring by DoR and NEC. Improved capacity, training and skills development for field engineers on timely preparation, approval, implementation, monitoring and reporting of EMP implementation is needed. Monitoring and Compliance report formats need to be revised to fully incorporate EFRC and other EMP requirements as included in contract terms. Monthly progress report formats to monitor and report on EMP implementation need to be coordinated with the monthly physical/financial reporting requirements. Such reporting will also include identification and reporting of non compliance of EMP implementation, rectification of such shortcomings and reporting of any such actions, enforcement of penalties and suspension of work of contractors for non-compliances and their recording and reporting to the DoR. Project Monitoring Team to ensure that such reporting is mandatory and enforced.

� Systematic and documented local stakeholder consultation. EMPs also require stakeholder consultation, but unlike the case with EAs, there is no requirement to document the process or results of these consultations. The EMP Guidelines need to be revised to require a more systematic and documented consultation process. Public notices

56 The Director MOA referred to the ongoing bio-engineering programs for MOA extension engineers under the ongoing World Bank-funded Sustainable Land and Environmental Management project. It was also suggested that these training programs and training material be integrated with better co-ordination efforts

Page 66: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

53

providing accurate information of the proposed activity are required to be advertised locally and in national press requesting for public comments, reaction and suggestions. This is to be followed by a public consultation of interested and affected persons, groups or whole communities at which information is exchanged and views expressed. During this meeting project related details and public involvement processes would be informed and discussed. Representatives of DYT, GYT and other RGoB agencies as appropriate would be present at the meeting. Such community meetings should be held periodically (in particular during the construction phase of the project). Where involuntary resettlement is to take place, meeting with affected families should be held to discuss options, the type and expected compensations and rehabilitation, and other social, economic and environmental issues arising including new opportunities and options at the new relocation site. Each public hearing/meeting should record views/comments/concerns and how these are being addressed in the project design. The framework for public consultation is largely in place. RAPII will provide capacity training, oversight, reporting formats and technical support to enable such consultation to take place as required by RECP guidelines

� NECS documentation of public disclosure of Ecs. At present, NECS does not appear to maintain any archive of its public disclosure of ECs under Article 28 of the EAA. Such an archive be publicly available and integrated into of NECS’ data management and information system.

� Donor coordination on enhancement of regional and local government environmental capacity. ADB is currently undertaking capacity assessment and training of Ministerial-level Environmental Units. SNV is undertaking similar assessment of Dzongkhag level engineers to identify gaps in the implementation of EFRC, how to make EFRC work better, how to better manage workloads and how they can work better with DoR at the national level. This will form the basis for specific actions, including training and skills development, collaboration and coordination to help implement EFRC at the sectoral and local levels. The RBOB and the Bank need to coordinate these donor activities so as to optimize the implementation for the RAP II project. As is suggested in the EFRC-SP Mid-Term Review DoR should gradually transform current EFRC-SP to amore flexible platform for a longer term support by multiple number of donors and with a focus on strengthening project implementation.

Page 67: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

54

PART III. ROLES AND RESPONSIBILITIES OF RGOB AGENCIES AND OTHER STAKEHOLDERS

RESPONSIBILITIES OF RGOB AGENCIES AND OTHER STAKEHOLDERS

183. The public consultation workshop generated a number of recommendations regarding the roles and responsibilities of government agencies and other stakeholders in implementing the recommendations in this report regarding improved compliance monitoring:

Table 5. Roles and Responsibilities with Respect to Improved Compliance Monitoring to Attain and Sustain Acceptability in the RAP II Project:

Roles Responsibilities Specific Actions Management of Overall EA process

Environmental officers in different departments of MOWHS

Effective coordination to be established with the guidance from NEC

Overall Environmental monitoring at PCU level

Jointly by Environmental Officer (EO), Assistant Project Coordinator and Project monitoring engineer (proposed to be part of IDD). EO to take the lead role

• The EO shall regularly review the progress providing feedback to Project Coordinator

• Improve reporting formats based on implementation effectiveness

Field implementation of EMP

Contractor to implement EMP and provide progress reports to field engineers

• Specific items of BoQ and monitoring aspects to be included in contracts.

• Reporting formats to form part of contract covenants

Monthly progress Reporting

Field Engineers to compile the compliance and progress reports for reporting to PCU

• The contractor’s payments to be linked to the compliance on EMP

Regulatory Compliance monitoring

DECs to coordinate with field engineers to review the compliance at regular intervals (at least bi-monthly)

• DECs to be empowered to carry out post clearance compliance monitoring with independent line of need based reporting to NEC

• DECs capacity to be built by NEC through regular on job refresher trainings

Project Completion/ site demobilization certification

EO of DoR to jointly with NEC to assume the responsibility of certification after site visits for verifying safeguard compliance.

• In order to avoid irreversible violations of compliance at the end of the project, NEC shall carry out intermittent site visits.

• The proposed NEC representatives at Dzongkhag level to complement this function

• Other wild life and nature conservation departments to be involved for compliance monitoring in bio-diversity and sensitive areas

Page 68: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

55

RESPONSIBILITIES OF THE WORLD BANK

184. The World Bank, in addition to providing financing for the physical components of the project, consisting of the construction of new feeder roads and the improvement of existing feeder roads will support the institutional and human resource components of the proposed measures to attain and sustain Acceptability in the RAP II project, through the following measures:

Institutional Development and Implementation Support

185. Organizational Development for the newly established Investigation and Development Division. (IDD). The IDD was established in 2005 with a mandate to promote and mainstream technical innovation and support the professional development of the DOR. The proposed project will support IDD in the following areas:

� Monitoring and Reporting,

� Data collection for traffic and road condition surveys,

� Quality Assurance,

� Work, procurement and Contract Management system,

� Technical innovation and engineering aspects, and

� Environmental Management

Human Resource Development

186. As part of the Human Resource Development strategy for the road sector, the proposed project will provide training to trainers and work with local training institutions or universities to institutionalize training in several areas of road planning, design and construction, environmental management, as well as contract management and procurement. In addition, short-term and long-term training to DOR staff and contractors will be supported under the proposed project.

Monitoring and Reporting

187. As part of its reporting to the World Bank, the PMU will prepare quarterly monitoring reports with a focus on implementation status of the agreed measures to attain Equivalence and Acceptability , and in particular the following key elements:

� Revision of the CEPHR to address issues relating to siting new road segments on previously cleared land and procedural measures for “chance finds” of PCR encountered during construction.;

� Accountability of contractors for compliance with EMPs and linkage of contractor payments to EMP compliance; and

� Submission of monthly EMP compliance reports by field engineers.

Page 69: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

56

PART IV. PUBLIC CONSULTATION AND DISCLOSURE

REPORT ON OCTOBER 24, 2006 PUBLIC CONSULTATION AND DISCLOSURE WORKSHOP

188. A draft of this report was sent to the Ministry of Foreign Affairs, the DoR and NECS on October 13, 2006 and was distributed to diverse stakeholders who were invited to take part in a public consultation on the report and associated capacity building measures. The consultation was conducted at the MoWHS in Thimphu on October 24, 2006. The workshop participants included relevant departments of RGOB, Environmental and Social Assessment consultants, donor agencies, representatives from RAP-II project Dzongkhags and NGOs. Annex 2 to this report presents the workshop agenda and participants profile.

189. The workshop was chaired by the secretary MoWHS, RGoB and the public consultation proceedings were conducted by Director, DOR. The key workshop presentations of the forenoon sessions included: (a) Introduction on Context and Scope of Use of Country Systems for Bhutan by NEC representative; and (b) Summary and Findings of SDR by the Bank Representative. The morning sessions were followed by Question and Answer sessions. The afternoon session focused on working group sessions to get the feedback from the stakeholders on three key aspects of implementing RAP-II implementation, including: (a) Training for Capacity Enhancement for effective implementation EFRC guidelines under RAP-II project; (b) Monitoring and Compliance of RAP-II Safeguards implementation; and (c) feedback on field/technical implementation of EFRC guidelines. The key outcomes of workshop deliberations in different sessions are summarized below:

� Overall SDR Findings on Equivalence and Acceptability Assessment. The workshop deliberations in general concurred with the overall findings of SDR in respect of environmental safeguards. Further detailed comments are expected from DoR and NEC. With regard to social safeguards, in particular, IR, the participants felt that though the SDR presents significant differences between Bhutanese system and OP 4.00, the existing country system should have been given more deference. While the findings of SDR were reiterated by the Bank representative, it was agreed that further discussions in this regard will be taken up by the RGoB with the social safeguard specialist of the RAP-II team during Appraisal mission in mid November, 2006.

� Enhancement of Safeguards Capacity. The deliberations concurred that safeguard capacity needs to be enhanced in relevant government departments at various levels. In this regard, the participants highlighted the current budgetary constraints and the need for resource optimization. The workshop discussions were mainly focused on details of various capacity enhancement mechanisms. With regard to budgetary aspects, donor coordination and rationalization of funds are being sought from DADM. It was also felt that the overall goal of capacity building shall be long term based to sustain the safeguard mechanism at DoR level rather than limiting the efforts to meet RAP-II requirements.

Investigation and Development Division (IDD) of DoR, in coordination with NEC will act as a nodal agency for conduct and coordination of various short term training programs. IDD for this purpose will be staffed with a training coordinator. As part of capacity building efforts, the EFRC good practices implemented under RAP-I will be documented in the form of training material. In addition to the proposed short term training programs, the participants felt the need for long term training programs by deputing the professionals for masters programs. A broad framework of training

Page 70: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

57

requirements proposed by the participants during Working Group sessions and is included in the Acceptability section of the SDR report.

� Roles and Responsibilities. The discussions were mainly focused on compliance monitoring responsibilities and reporting mechanisms. In this regard, the participants felt that currently the overall implementation monitoring and compliance reporting is weak. While it was acknowledged that NEC currently cannot extend detailed clearance compliance monitoring, the need for Dzongkhag level regulatory monitoring is thought necessary. In this regard, the majority of the participants opined that DECs should be effectively used by mainstreaming them in to regulatory compliance monitoring. Further, the NEC representative reported that shortly NEC representatives will be appointed at the Dzongkhag level and they could also play a complementary role in compliance monitoring. The overall deliberations during working group discussions and presentations, and question and answer session discussions led to recommendations on roles and responsibilities of various authorities and other stakeholders These recommendations are summarized in table format in the Acceptability section of this report.

� Field and Technical Aspects of Implementing EFRC guidelines. The working group sessions identified specific issues and options for improving RAP-II implementation:

� Problems and Shortcomings:

o The theoretical and practical aspects of EFRC guidelines leads to tough challenges in the field, especially in steep terrain

o Insufficient BOQ items on spoil disposals are often inadequate. This issue need to be sorted out with adequate allowances backed by sufficient field level information

o Construction supervision/management is seldom effective leading to serious QA issues in implementing EFRC guidelines

o The lack of budget for monsoon restoration/maintenance render the EFRC measures ineffective

� Improving EFRC for Better Implementation of RAP-II:

o Strong/robust terms and conditions of contract

o Clear technical specifications (upfront integration of environmental measures), complementary drawings and other contract documents

o Enhancement of contractor capacity for effective implementation of EMP through training programs

o Plan for emergency and periodic budgets for EFRC measures

o Wider application of EFRC to other road programs (such as farm roads, highways, DANTAK roads, etc.) to establish parity and to mainstream environmental safeguards

Page 71: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

58

o One of the key inputs for Environmental hazard management on steep slopes depends on geo-technical investigations. Specific inputs from DGM should be integrated in this regard

o Improve technical resources within DoR – such as, use of aerial photographs and satellite imaginaries, development of maps on landslide risk prone areas/hazard mapping, use of updated maps, etc.

� Other Recommendations made by participants in the public consultation included the following

o The entire project related public consultation and regulatory compliance documentation will be maintained by NEC.

o The monitoring role of different agencies shall be made effective by developing specific reporting formats, providing necessary equipment and machinery (digital cameras, etc.), necessary guidelines, etc.

o The role of DGM for approval quarry sites shall be taken up early to minimize implementation delays.

o The current role of Bank supervision shall remain. The exact reporting frequency need to be further worked out between various agencies

Consultation Workshop--October 24, 2006 (Participant List) Names of Participants Designation Dzongkhag/Organization

Mr. Tshering Dorji Secretary MoWHS Mr. Phuntsho Wangdi Director DoR Mr. David Stiedl Rural Infrastructural Specialist SNV/DUDES Ms. Lhaden Pema Project Manager DUDES Mr. Chencho Norbu PD SLMP/DoR Ministry of Agriculture Mr. A. Sita Ramakrishna Environmental Specialist World Bank Mr. Pasang Dorji District Engineer Samtse Mr. Tshering Wangdi “A” Chief Engineer S & D, DoR Mr. Sangay Tenzin Planning Officer PPD, MoWHS Mr. S. Dorji District Agricultural Officer Samtse Mr. Sangay Asst. Dzongkhag Extension Forestry

Officer Tsirang

Mr. Sonam Tobgyel Executive Engineer Lobeysa, DoR Mr. Kinzang District Engineer Paro Mr. Penden Norgay District Engineer Bumthang Mr. Tsheten Dorji Executive Engineer Trashigang, DoR Mr. S. N. Rai Project Manager JFPR/DoR Mr. Dorji Dukpa Dzongkhag Forestry Officer Haa Mr. Balaram Acharya Project Manager RAP Mr. Mindruk Kencho Executive Engineer Trongsa, DoR Mr. Dungkar Drukpa Sr. Planning Officer PPD, MoWHS Mr. Dago Kuenly Project Manager, GoI DoR Mr. Karma Tshethar Asstt. Project Coordinator DRDP, MOA Ms. Sonam Choki Assistant Engineer DoR Mr. Chengay Penjore Head, Environment Division Thimphu City Corporation Mr. Lobzang Engineer Thimphu

Page 72: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

59

Names of Participants Designation Dzongkhag/Organization

Mr. Gem Tshering Dzongkhag Forestry Officer Sarpang Mr. Bishnu Dhital Dy. Executive Engineer Zhemgang, DoR Mr. Yonten Gyamtsho District Agriculture Officer Punakha Ms. Sonam Desel Environment Focal person PPD, MoWHS Mr. Nima Gyeltshen Asstt. Project Coordinator, RAP-II DoR Ms. Shiriin Barakzai International Road Engineer SNV/DoR Mr. Ram Chandra Subba Project Manager, RAP-II DoR Mr. Tshering Tenzin Program Officer DADM Mr. Tshering Wangdi “B” Chief Engineer Roads, DoR Mr. Sangay Gyaltshen MoD, Mining DGM

Mr. S. R. Gurung Dzongkhag Forestry Officer Thimphu Mr. Jigme Tashi Civil Engineer Forestry Development

Corporation Limited, Thimphu

Mr. Lungten Tshering Civil Engineer Kyingkhor Consultant Mr. T. R. Gurung Project Engineer Trongsa Mr. B. B. Gurung Executive Engineer (Investigation) I & DD, DoR Ms. Choden Junior Engineer DoR Mr. Aku Dorji Dy. Executive Engineer Punakha Mr. Tashi Dundup Forestry Officer Trongsa Mr. Kaka Daongkhag Forestry Officer Wangdue-phodrang Mr. Karma Chogyel Dy. Managing Director BHUCORE Mr. Tshering Gyelthsen Executive Engineer Phuntsholing, DoR Mr. Jangchub Tenzing Executive Engineer Thimphu, DoR Mr. Sangay Dorji District Engineer Sarpang Mr. Kinga Dorji District Engineer Wangdue-phodrang Mr. Jambay Wangchuk Executive Engineer Sarpang Mr. Suk Bdr. Rai Junior Engineer Zhemgang Mr. Karma Rinzin Project Manager Expressway, DoR Mr. Karma C. Nyedup Deputy Director National Environment

Commission Mr. Tsering Paljore Project Coordinator, RAP-II DoR Ms. Phuntsho Choden - SNV Bhutan Ms. Deki Yonten Planning Officer Ministry of Agriculture Mr. Doley Tshering Program Officer United Nations Development

Program

Page 73: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

60

ANNEX A

EQUIVALENCE ANALYSIS MATRIX

BHUTAN: USE OF COUNTRY SYSTEMS FOR ENVIRONMENTAL AND SOCIAL SAFEGUARDS:RURAL ACCESS II

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

ENVIRONMENTAL ASSESSMENT

Objective: To help ensure the environmental and social soundness and sustainability of investment projects. To support integration of environmental and social aspects of projects into the decision- making process.

Under Bhutan’s policies and laws, the objectives of the EA is to establish procedures for the assessment of strategic plans, policies, programs and projects for the determination of policies and measures to reduce potential adverse impacts and promote environmental benefits.

The National Environment Strategy of Bhutan (NES), 1998 stresses the importance of EA as a major way to ensure a sustainable natural resource base for the country.

The Strategy Paper “Bhutan 2020” places high priority on institutionalizing capacities for EA which must be applied a wide variety of projects and activities in order to evaluate their likely impacts on the environment. It states: EA is “particularly important…for helping ensure that development projects are environmentally and economically sound in the longer term. Adverse environmental, social, economic and cultural impacts of development projects are minimized. Environmental impacts on ecologically fragile systems receive prior evaluation

The Environmental Assessment Act (EAA) 2000 mandates the Government to ensure that environmental concerns are fully incorporated into development activities, and while implementing any policy, plan or program. No development consent can be issued without first seeking environmental clearance.

NESB Bhutan 2020 EA Act, 2000 Article 8: “The issuance of environmental clearance shall be prerequisite to the issuance of a development consent”

None None

Operational Principles: 1. Use a screening process for each proposed project, as early as possible, to determine the appropriate extent and type of environmental assessment (EA) so that

A screening process is in force for projects requiring an Environmental Clearance (EC) from permitting authorities. Project proponents must submit an application in a standard form for all prescribed projects. The Competent Authority (CA) shall determine whether the proposed project requires an EA.

Regulations for Environmental Clearance (EC) for Projects, Chapter II Sections 16 through 28 and Annex 2.

None. None.

57 See Attachment 1 to this Annex

Page 74: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

61

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

appropriate studies are undertaken proportional to potential risks and to direct, and, as relevant, indirect, cumulative, and associated impacts. Use sectoral or regional environmental assessment when appropriate.

Once screening determines the need to undertake an EIA, the level of EA effort is determined.

The NEC has enacted sectoral guidelines to define process, content and level of assessment. Eight such sectoral guidelines are in force. The Project proponent must check whether its project falls under the eight activities for which the National Environment Commission (NEC) has issued sectoral guidelines. If so, the proponent must follow the standard guidelines as to determine what data and information need to be provided to the CA. If the project does not fall under any of the eight sectors, then the NEC and/or CA will issue terms of reference commensurate to the project.

The CA would issue an EC, reject the application or subject the project to a full EA and/or further studies.

2. Assess potential impacts of the proposed project on physical, biological, socio-economic and physical cultural resources, including transboundary and global concerns, and potential impacts on human health and safety.

An EC is issued if the CA is of the opinion that a proposed project : (i) “alone or in connection with other programs or activities” contributes to the sustainable development of the Kingdom and the conservation of its natural and cultural heritage”, (ii) grants adequate attention to the interests of “concerned people” and is (iii) consistent with the environmental commitments of the Kingdom”

The minimum requirements and level of detail for EAs reflect the potential environmental, economic and social impacts of the proposal. The EA report must be prepared in accordance with NEC sectoral guidelines, which list common environmental concerns associated with different development activities. Apart from a project description, the EA is to set out alternatives to the project (including the feasibility of a “no build” alternative), a description of the existing environment, an assessment of impacts (positive and adverse), mitigation measures, and a response to comments received from “concerned people” on the environmental report. “The potential adverse effects of the project…including the direct, indirect and cumulative effects” must be clearly stated in the application.

There is no explicit reference to transboundary impacts; however, there is reference to impacts on the “immediate surroundings and region.”

Environmental Act , Section 18 Regulation for the Environmental Clearance of Projects, Section 28.2 and Annex 3 on the description of the Environmental Assessment Report Format, notably Section 8 0n Assessment of Impacts.

Absence of clear reference to “transboundary and global impacts” may be considered a significant gap but is not relevant to the RAP II project.

None for RAP II. Enactment of

draft NEPA provision or an equivalent measure would bridge the gap on a systems level.

Page 75: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

62

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

The most recent draft of the National Environment Protection Act (NEPA) intended to provide an “umbrella” framework for all environmental legislation in Bhutan would authorize NEC to ensure that the EA process becomes an integral part of the development planning process, through implementation of the EAA, and would include transboundary consultation when a plan, program or project may have an impact on a neighboring country.

NEPA Draft VII of July 24, 2006, Article. 10.3

3. Assess the adequacy of the applicable legal and institutional framework, including applicable international environmental agreements, and confirm that they provide that the cooperating government does not finance project activities that would contravene such international obligations.

The Environmental Codes of Practice issued by the NEC require that the EC shall refer to the legal and regulatory framework for the proposed project, including the provisions of the relevant Code of Practice.

Although policy documents, including the NES, state a strong commitment to environmental protection and commitments made through international conventions there is no explicit legal requirement that EA include the assessment of applicable international conventions to which Bhutan is party. Such conventions and agreements include the Convention on Biological Diversity (CBD), the UN Framework Convention on Climate Change (UNFCCC), the CITES, and the Kyoto Protocol (acceded 2002.

The EA Act makes general reference to “the Kingdom commitments” and states that no project would be granted an EC if it is not “consistent with the environmental commitments of the Kingdom.” However, the term “the Kingdom commitments” is not defined.

The most recent draft of the National Environment Protection Act (NEPA) intended to provide an “umbrella” framework for all environmental legislation in Bhutan, would require that international (multilateral and bilateral) environmental agreements ratified by the National Assembly shall be enforceable as any other domestic laws, retrospectively as well as prospectively.

EA Act, 2000, Section 18 And Environmental Codes of Practice for Hazardous Waste Management, Chapter III, Environmental Code of Practice for Sewage and sanitation Management in Urban Areas, Chapter III NEPA Draft VII, July 24, 2006, Article 103

The absence of any reference in the EA process to laws enforcing Bhutan’s commitments to international environmental agreements constitutes a significant gap but is not relevant to the RAP II project

None for RAP II. Enactment of draft NEPA provision or an equivalent measure would bridge the gap on a systems level

4. Provide for assessment of feasible investment, technical, and sitting alternatives, including the “no action” alternative, potential impacts, feasibility of mitigating these impacts, their capital and recurrent costs, their suitability

Under Bhutan’s system, the EA must provide a detailed analysis of he negative and positive impacts of the proposed project and its alternatives including the “alternative of not undertaking the project”. The treatment of the alternative is quite comprehensive and include: (i) analysis of all feasible alternatives, (ii) analysis of the principal differences among the feasible alternatives under consideration, particularly regarding environmental impacts, and (iii)

Regulation for the EC of Projects (RECP), Annex 3, Sections 6 and 8.

None. None.

Page 76: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

63

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

under local conditions, and their institutional, training and monitoring requirements associated with them.

discussion of any alternative non longer under consideration” .

5. Where applicable to the type of project being supported, normally apply the Pollution Prevention and Abatement Handbook (PPAH). Justify deviations when alternatives to measures set forth in the PPAH are selected.

There is no reference to the PPAH Guidelines in Bhutan’s environmental legislation. However the Sectoral Guidelines and Environmental Codes of Practices for specific activities provides very specific guideline and discharge standards setting out acceptable levels of air, noise and other pollutants applicable to specific industries, some if which are drawn from international organization’s guidelines such as WHO and FAO.

Environmental Discharge Standaard, NEC, August 2004/

No significant gap. Absence of reference to PPAH is partially mitigated by the use of internationally recognized guidelines and standards (WHO, FAO) for the development of discharge standards applicable to specific industries. The PPAH does not include guidelines pertaining to the rural roads sector.

None for RAP II. References to internationally recognized standards should be incorporated into ECPs where appropriate.

6. Prevent and, where not possible to prevent, at least minimize, or compensate for adverse project impacts and enhance positive impacts through environmental management and planning that includes the proposed mitigation measures, monitoring, institutional capacity development and training measures, an implementation schedule, and cost estimates.

The EAA provides for the formulation of environmental management plans (EMPs). The EMPs must identify environmental risks and address means of avoiding or minimizing adverse impacts (including direct, indirect and cumulative effects) and enhancing positive impacts. Applicants must also set out a monitoring program (both baseline and compliance monitoring) and are responsible for all project monitoring (project monitoring is undertaken by CA or NEC). The Code of Environmental Practice for Highways and Roads (CEPHR) requires that EMPs include the proposed mitigation measures, the need to budget mitigation measures, supervision, monitoring and evaluation requirements for the construction, operation and maintenance phases of the project cycle. The RECP provides that: (i) “the CA shall be responsible for monitoring compliance” for projects requiring development consent and EC, and (ii) the Secretariat [of NEC] shall monitor projects “that do not require development consent”. The EA Act states that “compliance monitoring of projects” is undertaken by the Secretariat [of NEC]…on becoming aware of non-compliance with the terms or other activities related to a project that may be dangerous to the environment.” EC for a project must be reviewed every 5 years and may be revised and renewed upon

EAA, Sections 7 through 10, 23, 26 through 31, 40 through 43 and RECP, Sections 30, 31, 33-34 and Annex to the Regulations

None None.

Page 77: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

64

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

review but the Secretariat is empowered to review the EC at any time where there is new information indicating the project creates unacceptable risks to the environment, where improved and cleaner technology becomes available, and where the review is needed to bring the project into compliance with changes to Bhutanese laws.

7. Involve stakeholders, including project-affected groups and local nongovernmental organizations, as early as possible, in the preparation process and ensure that their views and concerns are made known to decision makers and taken into account. Continue consultations throughout project implementation as necessary to address EA-related issues that affect them.

Under the EAA, applicants only have a duty to inform and consult with “concerned people” and organizations before submitting the EA documents to the CA where the project is classified as a “significant project”. ‘Concerned people’ and “organizations” are those “individuals, groups or communities whose interests may be affected by a project or proposal” and “significant project” is defined as a project nominated as a type A or B project by sectoral guidelines issued by the NEC. (Category C and D projects may also be considered significant if the cumulative effects of two or more projects are significant.)

Where it applies, the duty to inform and consult includes, at a minimum, written notice to local people, a newspaper notice, and public hearings. Local authorities are directed to assist people express their views to the applicant; the public and other agencies have three weeks to respond to the application with comments. The applicant is solely responsible for costs associated with public consultation. The Secretariat of NEC or CA may require the applicant to undertake public consultation beyond the minimum standard, including public notice and review procedure.

Public information: The Secretariat of NEC or CA must make a public announcement of the decision to issue an environmental clearance and provide reasons for decision including information to the public describing the project, and its environmental terms, describing measures to avoid or mitigate potential adverse effects and to enhance positive impacts, and a non-technical summary of this information. Public notice must be made within 15 days of a decision by the Secretariat or CA. The Secretariat or competent authority may take comments of the public made during the public consultation stage into account when making a decision.

Sectoral guidelines for applications for environmental clearances detail requirements for public consultation. The applicant must explain the expected impact to affected people, where these impacts will

EA Act, 2000, Sections 16 and 22 The Regulations for Environmental Clearance of projects: Sections 5.4, 28.8, 29, 30 and 31. and Annex 1 to the Regulations (Timing of EA processing including for consultation and disclosure)

None None

Page 78: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

65

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

occur and how they will be mitigated; the applicant must provide a record of the meetings (including a record of names, times and place of meeting and information on issues raised and agreements made). Signatures of consulted parties as proof of consultation are required, as is a description of unresolved issues of discussion.

Public participation is an important and necessary component for road projects. Public involvement is likely to result in a more sustainable project when people feel a sense of local ownership, acceptability and a commitment for maintaining the road. It involves a two-way flow of information. Firstly, the study team has a duty to inform the local population in the road area of all aspects of the project for all the project stages (adverse impacts and benefits). Secondly, the public should be knowledgeable about local conditions and issues that are crucial for a good project design, the project management and the road operation. During the execution of the pre-feasibility study, the local population must be informed about options for providing motorable access to their area. The better they are informed about advantages and disadvantages of alignment options the easier will be the dialogue later on when they are confronted with the disadvantages of the new road during construction, operation and maintenance. At this project stage, all available data concerning physical, socio-economical, cultural and ecological factors must be collected from locals to receive a broad and valid information basis for all the proposed alignment options. The potential stakeholders such as involved government agencies, NGOs and private people have to be approached for their input with regard to potential environmental problems caused by the road pr the assignment of EA Team requires adequate preparation and coordination. The team can be assigned by DoR only when NEC has developed or approved the ToR for the EA. The EA Team must inform local populations which alignment option has been selected for execution and for what reasons. Complete information on the process of alignment selection again helps to secure the full co-operation of the local population for the further project stages. More specific and detailed information on important project issues can now be collected from the local population for the selected alignment option

Environmental Codes of Practice: Highways and Roads, Annex 1, 2000

Page 79: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

66

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

Public Participation and Coordination Whenever and wherever required, the further mutual exchange of information between project staff and locals should be encouraged and supported.

8. Use independent expertise in the preparation of EA where appropriate. Use independent advisory panels during preparation and implementation of projects that are highly risky or contentious or that involve serious and multi-dimensional environmental and/or social concerns.

There is no obligation under Bhutanese laws and regulations for the use of independent expertise in the preparation of EAs.

The Secretariat is authorized to establish an Environmental Assessment Advisory Board to advise him on particular projects. The Board membership includes “qualified or knowledgeable persons” and may include (among others) representatives of ministries, representatives of local administrations/municipalities, representatives of NGOs, and representatives of local communities affected by the project.

The Head of the Secretariat may also nominate up to three experts to advise on particular projects.

The planning, studying and surveying phase is the most important phase of all the project stages. It is in this phase where all the fundamental decisions are made to achieve an alignment, which can be constructed and maintained with least cost, minimum instability and a tolerable environmental impact. Therefore, only a highly experienced and multi-disciplinary team of specialists can adequately handle these tasks

The most important factor to optimally guide the EA is a clear ToR for the EA Team. Development of ToR must be given to experienced specialists in the fields concerned. The team must propose mitigation measures wherever required and come up with improvements when necessary to protect the environment to the extent possible. The team must assess whether the project is environmentally feasible or not.

EAA, Section 38 on the establishment of an Environmental Assessment Advisory Board (EAAB).

The Regulations for Environmental Clearance of projects:

Sections 6 through 13 on the EAAB membership and procedures and more specifically Section 11 on the three members expert panel to advise on specific projects.

Environmental Codes of Practices: Highways and Roads ,Annex 1 2000

None None

9. Provide measures to link the environmental assessment process and findings with studies of economic, financial, institutional, social and technical analyses of a proposed project.

Because project activities require environmental clearance prior to development consent, the environmental assessment process and findings are linked to studies of economic, financial, institutional, social and technical analyses of a particular project contained in the initial application for environmental clearance and where appropriate, an environmental assessment report.

EA Act 2000, Sections 9-10 None. none

10. Provide for application of the principles in this Table

There is no reference to Financial Intermediary and subprojects as such, however, EC are granted to “individual

EA Act, 2000 Chapter III, Sections 11 through 25

None. Bhutan’s laws and regulations make no distinctions

None

Page 80: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

67

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

to subprojects under investment and financial intermediary activities.

projects”. Any individual project is subject to the EA Act and its implementing regulations and subject to screening and EAA as appropriate.

Regulations on Environmental Clearance for Projects, 2002, Section 2 in fine

between projects financed directly and those financed through intermediaries.

11. Disclose draft EA in a timely manner, before appraisal formally begins, in an accessible place and in a form and language understandable to key stakeholders.

Under the EA Act, applicants have an obligation to inform and consult with concerned people and organizations before submitting the EA documents to the CA or NEC. Outcomes of the consultations are described in the EA. With respect to “significant projects” the proponent has the further obligation 58 to provide at a minimum, written notice to local people, a newspaper notice, and public hearings. Local authorities are directed to assist people express their views to the applicant; the public and other agencies have three weeks to respond to the application with comments. NECS or tehCA may require the applicant to undertake public consultation beyond the minimum standard, including public notice and review procedures. NECS or the CA must make a public announcement of the decision to issue an environmental clearance and provide reasons for decision including information to the public describing the project, and its environmental terms, describing measures to avoid or mitigate potential adverse effects and to enhance positive impacts, and a non-technical summary of this information. Public notice must be made within 15 days of a decision by the Secretariat or CA. The Secretariat or competent authority may take comments of the public made during the public consultation stage into account when making a decision. Sectoral guidelines for applications for environmental clearances also detail requirements for public consultation. The applicant must explain the expected impact to affected people, where these impacts will occur and how they will be mitigated; the applicant must provide a record of the meetings (including a record of names, times and place of meeting and information on issues raised and agreements made). Signatures of consulted parties as proof of consultation are required, as is a description of unresolved issues of discussion.

EAA 2000, Sections 16, 28.4 and other provisions cited under Principle 7 above. Regulations for EC for projects, Section 31

None None.

Physical Cultural Resources

Page 81: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

68

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

Objective: To assist in preserving physical cultural resources and avoiding their destruction or damage. PCR includes resources of archaeological, paleontological, historical, architectural, religious (including graveyards and burial sites), aesthetic, or other cultural significance.

The National Environment Strategy of Bhutan (NESB) recognizes that sustainable development seeks to raise the living standards of the present population “without compromising the country’s cultural integrity, historical heritage or the quality of life for future generations.” A Commission for Cultural Affairs was established with the mandate to integrate cultural development into the overall national development policy.

EA Report must always describe and analyze, among other elements: “scenic qualities, open space and recreational resources” , “culturally significant sites and “”rare or unique features…of the project site and its immediate surroundings”

Although currently there is no specific legislation for protection of immovable PCR, provisions for protection and maintenance of various cultural properties are embedded in various laws and regulations, particularly Thrimzhung Chenmo (the mother law) and the GYT and DYT Acts, 2002.

NESB Regulations for the EC of Projects, Sections 17.2 and 17.3 and Annex 3 7 (f), (g) and (i)

None. None.

Operational Principles: 1. Use an environmental assessment (EA) or equivalent process to identify PCR and prevent or minimize or compensate for adverse impacts and enhance positive impacts on PCR through site selection and design.

Once a project has been screened as potentially harmful to a sacred landscape or site or any sensitive area, it must be submitted to a full EA with a view to avoid, minimize or reduce impacts and to enhance benefits. The EA must include analysis of all alternatives, including “feasible alternatives” and “the no-build alternative” and describe mitigation measures. Consent of the Ministry of Home and

Cultural Affairs and the consent of the concerned GYT and DYT are pre-requisite for environmental clearance of any project/ activity that is located within 50 meters of a sacred landscape or site.

Regulations for the EC of Projects Annex 3: Section 6 “Alternatives to Projects”

Section 9 “Mitigation Measures” The DYT Act, 2002, mandates the

DYT to adopt and enforce regulations for designation and protection of monuments of cultural and historical importance in the Dzongkhag. The GYT Act, 2002, mandates the GYT to administer, monitor and review geog plan activities, including maintenance and preservation of religious monuments that are not under the custody of monastic body or central agencies

None. None.

2. As part of the EA, as appropriate, conduct field based surveys, using qualified specialists.

The CA and NECS are mandated by all relevant policies to ensure that impacts on cultural heritage be avoided and that any harm is mitigated and or compensated appropriately. Adequate staffing of environmental unit for the project may be required by the CA and Secretariat of NEC and would include cultural heritage specialist as appropriate.

NESB EA Act 2000 Regulations for EC of projects (Sect 17.2 and 17.3 and Annex 3 (f), (j) and (i)

Environmental Codes of Practice: Highways and Roads Sector Annex 1

None. None.

3. Consult concerned government authorities, relevant non-governmental organizations, relevant experts and local people in documenting the presence and significance of PCR,

Provisions for consultation of “concerned people and organization” are made for all projects subject to EA. The outcome of the consultation may be used by the CA and NECS to impose additional binding “mitigation and compliance measures” to the applicant including follow up actions and time frame

Regulations for EC of Projects: Section 30.2, 31, 32.2

None. None.

Page 82: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

69

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

assessing the nature and extent of potential impacts on these resources, and designing and implementing mitigation plans.

4. For materials that may be discovered during project implementation, provide for the use of “chance find” procedures in the context of the PCR management plan or PCR component of the environmental management plan

For any project involving cultural heritage, sacred site or a sacred landscape, the initial review of the application by the Ministry of Home Affairs is mandatory. Consent An EC is granted to a project when, among other aspects, the CA or the Secretariat of the NEC is “satisfied that:…The project alone or in connection with other programs or activities, contributes to the sustainable development of the Kingdom and the conservation of its natural and cultural heritage” The EC will define the process to be followed to deal with any discovery of findings of cultural heritage.

EAA Sections 18.3 RECP Annex 3, Section 7 (g)

Absence of legislation or regulations to protect “chance finds” is a potentially significant gap, particularly in the road sectors.

For RAP II, revision of CEPHR to include procedure for protection of “chance finds.” Enactment of the proposed Conservation of Archeological Hertitage Act or an equivalent measure to ensure the protection of “chance finds” would bridge the difference on a systems level.

5. Disclose draft mitigation plans as part of the EA or equivalent process, in a timely manner, before appraisal formally begins, in an accessible place and in a form and language that are understandable to key stakeholders

Under the EA Act, applicants have an obligation to inform and consult with concerned people and organizations before submitting the EA documents to the CA or NEC. Outcomes of the consultations are described in the EA. Where it applies, the duty to inform and consult includes, at a minimum, written notice to local people, a newspaper notice, and public hearings. Local authorities are directed to assist people express their views to the applicant; the public and other agencies have three weeks to respond to the application with comments. The Secretariat or CA may require the applicant to undertake public consultation beyond the minimum standard, including public notice and review procedures. Sectoral guidelines for applications for environmental clearances detail requirements for public consultation.

EA Act 2000, Sections 16, 28.4 and other provisions cited under Principle 7 above.

None. None.

Natural Habitats

Objective:

To promote environmentally sustainable development by supporting the protection,

72% of the territory of the Kingdom of Bhutan is forest covered, 35% of the territory of the Kingdom consist on six national parks, two wildlife reserves, and one nature reserve, all linked and served by wildlife corridors. It is the official policy of Bhutan to maintain at all time at least sixty

NESB None. None

Page 83: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

70

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

conservation, maintenance and rehabilitation of natural habitats and their functions

percent (60%) of its territory under forest cover.

Operational Principles:

1. Use a precautionary approach to natural resources management to ensure opportunities for environmentally sustainable development. Determine if project benefits substantially outweigh potential environmental costs

Under Bhutan’s laws and regulations, it is prohibited to undertake any human activities within the core zone of a protected area unless determined necessary by forest/ protected area officials to achieve nature conservation objectives. Outside the core area, no construction is allowed except with a written permit or authorization from the MoA, acting as CA under the EA Act. A permit for land clearance may be granted in private lands under strict conditions but not to alter protected area status, water catchment areas and areas containing high forest.

Any activity that may impact protected area and natural habitats in general can not be undertaken unless it is permitted by the Secretariat of the NEC and the CA including local government. The permitting process shall analyze all alternatives including no-project alternative before any decision is reached.

Forest and Nature Conservation Act, 1995

Forest and nature Conservation Rules, Sections 62, 70

EAA and RECP.

None. None

2. Avoid significant conversion or degradation of critical natural habitats, including those habitats that are (a) legally protected, (b) officially proposed for protection, (c) identified by authoritative sources for their high conservation value, or (d) recognized as protected by traditional communities.

Bhutan has set more than half of its territory as “Reserved Forests”. Under Section 10 of the Forest and Nature Conservation Act, no change to land use can be undertaken in a Reserved Forest which include all Bhutan’s Protected Areas. Protected Areas including national parks, wildlife reserves and wildlife corridors represent more that 30% of the whole territory of Bhutan and their legal status includes the prohibition to convert or degrade them. Activities that have an impact on any protected area must be submitted to prior review by the Secretariat of the NEC. Prohibitions include all activities that may alter, degrade, or convert any part of a “habitat” and those permitted activities are to be undertaken by the Forestry Department for the purpose managing the habitat only including “culling species for sanitation and conservation purpose… [as required by].. a management plan”. In general protected areas comprise: (i) a Core Zone, (ii) a Multi-Use Zone, and (iii) a Buffer Zone. Activities and changes to land uses are strictly regulated and stringent norms apply to Core Zone which, in general is a pure conservation area where only scientific and educational activities may be authorized.

Forest and Nature Conservation Act 1995 Chapters III, Section 10 and Chapter VI, Section 21 and Forest and Nature Conservation Rules of Bhutan, 2000, Chapter VI “Protected Area Management” especially Section 62. 5 on “Specific Provisions in Specified Zones or Conditions”

None.. None

Page 84: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

71

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

3. Where a project adversely affect non-critical natural habitats, proceed only if viable alternatives are not available, and if appropriate conservation and mitigation measures, including those required to maintain ecological services they provide, are in place. Include mitigation measures that minimize habitat loss and establish and maintain an ecologically similar protected area.

Clearing or breaking up of any forest land for cultivation or any other purpose is prohibited except in accordance with the rules and procedures defined in the Forest and Nature Conservation Rules, 2000. These rules define the procedural requirements, technical regulations and criteria for allotment of forest land to a person for a purpose other than conservation. However, it is silent on land exchange/ swapping involving forest land. To address this gap, the MoA has developed Procedure for Exchange (Swapping) of Marginal Farm Lands with Forest Land.

The Procedure outlines legal and geophysical criteria and procedural steps for application, field verification, decision-making, demarcation and registration of land, handing/taking over and procedural monitoring.

Forest and Nature Conservation Act 1995 Chapter III Section 17 of the Forest and Nature Conservation Rules, 2000,

None. None.

4. Whenever feasible, give preference to sitting projects on lands already converted.

EA process provide for analysis of all potential alternatives.

Forest and Nature Conservation Rules provide that “land located within protected area, water catchment and area containing high forest may be avoided.” During discussion, it was mentioned that “may” in this section of the rules should have been translated by “must” which is the meaning it has in the Bhutanese language version of the rules.

EAA and RECP Although the applicable laws provide for alternative assessment and appear to require avoidance of mature forest, this does not necessarily require that preference be given to lands previously converted.

Revision of CEPHR to require preference for siting new roads on previously converted lands. Enactment of NEPA Draft VII article 5.4 stating that developmental activities “shall be strategically planned an executed in harmony with the carrying capacity of the country’s sensitive ecological settings and geographical terrains” and article 5.9 which states that activities should be planned to “cause the least possible change in the environment” or equivalent administrative measures enhanced by stating a

Page 85: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

72

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

preference for siting projects on lands already cleared would bridge the gap on a systems level.

5. Consult key stakeholders, including local nongovernmental organizations and local communities, and involve such people in design, implementation, monitoring and evaluation of projects, including mitigation planning.

All Reserved Forests in Bhutan must be equipped with a Management Plan which is developed and adopted after a participatory process including consultation of stakeholders and participation. Stakeholders include: (i) local residents, local authorities, and other members of the public, (ii) persons operating forest-related businesses and other operations, and (iii) government officials in other agencies (other than the forest department), divisions and ministries.

Committees will be established at local and national levels to oversee and advise the Forest Department on the implementation of management plans for Reserved Forests

Forest and Nature Conservation Rules, Section 9.1 “Participation and Comment/Consultation” and 12 on “Forest management Committees”

None. None

6. Provide for the use of appropriate expertise for the design and implementation of mitigation and monitoring plans.

The Forest Department is in charge of preparing forest management plans and benefits for the NEC and other agencies and ministries for the definition of mitigation measures under management plans as appropriate. Generally, TA is used for the purpose of assisting the Forest Department and NEC to implement their mandates as needed.

Chapter II of the Forest and Nature Conservation Rules 2000, especially Section 47 on TA provision and use.

None. None.

7. Disclose draft mitigation plan in a timely manner, before appraisal formally begins, in an accessible place and in a form and language understandable to key stakeholders.

Mitigation measures as part of management plans are disclosed for the purpose of public consultation early in a project preparation process. It follows rules for EA.

See above on EA requirements on public disclosure.

None. None

Involuntary Resettlement

Objective: To avoid or minimize involuntary resettlement and, where this is not feasible, to assist displaced persons in improving or at least restoring their livelihoods and standards of living in real terms relative to pre-displacement levels or to levels prevailing prior to the beginning of

One of the stated objective of EA in Bhutan is to “ensure that concerned people benefit from projects in terms of social facilities.” The 1979 Land Act states that land acquisition through expropriation by government can be undertaken for national public interest and purposes only. Iindividual households are under an obligation to transfer the ownership of their land in the public interest. The Forest and Nature Conservation Act provides that privately owned or used land

Regulations for EC for Projects, Section 2.7 Land Act, 1979, Section 6.9 b Forest and Nature Conservation Act, 1995, Section 9

The stated objective does not equate to the objective of improving or at least restoring livelihoods of displaced persons relative to pre-displacement levels.

For RAP II, the World Bank will use OP 4.12 t implement the IR safeguard. Reform of Land Act would be necessary to address differences on a systems level.

Page 86: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

73

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

project implementation, whichever is higher.

may be acquired by the Department of Forestry (DoF) for “the benefit of the country.”

Operational Principles: 1. Assess all viable alternative project designs to avoid, where feasible, or minimize involuntary resettlement.

The Land Act provides that whenever a land is needed for public interest and/or purpose, a notification is published and notice served to owners and occupiers. There is no explicit reference to “avoiding, where feasible, or minimize involuntary resettlement” in the Land Act. Bhutan’s EA policy and legal framework clearly states that any applicant must provide information demonstrating : (i) “how the impacts of the project will be avoided, minimized or reduced” and (ii) “…..how the project will benefit Concerned People…” The EC is granted only if the EA has considered “all feasible alternatives” and that “concerned people benefit from projects in terms of social facilities.”

Regulation for the EC of Projects, Sections 2.4 , 2.7. 28.2 (c) and 28.2 (d).

Bhutan’s systems do not predispose the government to avoid or minimize IR

For RAP II, the World Bank will use OP 4.12 t implement the IR safeguard. Reform of Land Act would be necessary to address differences on a systems level.

2. Through census and socio-economic surveys of the affected population, identify, assess, and address the potential economic and social impacts of the project that are caused by involuntary taking of land (e.g. relocation or loss of shelter, loss of assets or access to assets, loss of income sources or means of livelihood, whether or not the affected person must move to another location) or involuntary restriction of access to legally designated parks and protected areas.

The minister is responsible for surveying the land to be expropriated before any land taking.

Land Act The law does not require baseline data on socio-economic conditions and resettlement impacts

For RAP II, the World Bank will use OP 4.12 t implement the IR safeguard. Reform of Land Act would be necessary to address differences on a systems level.

3. Identify and address impacts also if they result from other activities that are (a) directly and significantly related to the proposed project, (b) necessary to achieve its objectives, and (c) carried out or planned to be carried out contemporaneously with the project.

Not considered in Bhutan’s legal and regulatory framework

Not applicable to RAP II.

None.

4. Consult project-affected persons, host communities and local

Information disclosure and consultation are mentioned in the Land Act and in the EAA. The Minister shall inform affected people

Municipal Act, 1999, Section 76 provides for compensation “payable as per the rates determined by the

The Land Act and EA Act do not provide specifically for

For RAP II, the World Bank will use OP 4.12 t

Page 87: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

74

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

nongovernmental organizations, as appropriate. Provide them opportunities to participate in the planning, implementation, and monitoring of the resettlement program, especially in the process of developing and implementing the procedures for determining eligibility for compensation benefits and development assistance (as documented in a resettlement plan), and for establishing appropriate and accessible grievance mechanisms. Pay particular attention to the needs of vulnerable groups among those displaced, especially those below the poverty line, the landless, the elderly, women and children, Indigenous Peoples, ethnic minorities, or other displaced persons who may not be protected through national land compensation legislation.

and enter into consultation with them about the content of the compensation scheme. Affected people will be compensated through allocation of replacement land or through financial (cash) compensation according to the classification of the land taken. The classification (quality of the land and geographical situation) is the basis for the determination of the amount of compensation which is decided by law. Disputes are directed to the competent Court.

Royal Government from time to time.”

Land Act 1979. EA Act 2000.

consultation with affected people on planning and implementation of land taking impacts and mitigation measures. Consultation requirements are limited to compensation.

implement the IR safeguard. Reform of Land Act would be necessary to address differences on a systems level.

5. Inform displaced persons of their rights, consult them on options, and provide them with technically and economically feasible resettlement alternatives and needed assistance, including (a) prompt compensation at full replacement cost for loss of assets attributable to the project; (b) if there is relocation, assistance during relocation, and residual housing, or housing sites, or agricultural sites of equivalent potential, as required; (c) transitional support and development assistance,

Those persons and households whose lands are to be taken over are informed prior to any land taking. The EA process provides for consultation abundantly. However, the content of information to be provided to affected people is restricted to those options referred to in the Land Act (land allocation option and cash option). The second option itself is limited to the amount of cash defined by law without any reference to the notion of “market value” or “replacement value”

Land Act. 1979, Section 6.8 and 6.9 Forest and Nature Conservation Act Rules, 2000, Sections 20 through 21 related to “Compensation and Alternative Land Rights”

The Act does not provide for consultation with affected people regarding planning and implementation of land acquisition impacts and mitigation measures.

For RAP II, the World Bank will use OP 4.12 t implement the IR safeguard. Reform of Land Act would be necessary to address differences on a systems level.

Page 88: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

75

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

such as land preparation, credit facilities, training or job opportunities as required, in addition to compensation measures; (d) cash compensation for land when the impact of land acquisition on livelihoods is minor; and (e) provision of civic infrastructure and community services as required.

6. Give preference to land-based resettlement strategies for displaced persons whose livelihoods are land-based.

Land-based resettlement is provided for under the Land Act. Allotment of substitute land shall be from the same Dzongkhag People whose land is acquired and choose replacement land as compensation are allowed to identify replacement government owned land of equal size and value in the dzongkhag. However the government is not bound to provide replacement land chosen by affected landowners, and can recommend alternate locations. In the event of acquisition of land in rural areas, in case developed land is acquired by the government and is substituted by an undeveloped land, in addition to substitute land, the owner concerned shall be compensated with half the cost of developed land acquired. If a person becomes landless due to the acquisition of land, the government allots, free of cost substitute land. In the event of acquisition of land in rural areas, in case developed land is acquired by the government and is substituted by an undeveloped land, in addition to substitute land, the owner concerned shall be compensated with half the cost of developed land acquired Land for land principle remains difficult to implement in the urban area because of the scarcity of available land due to the specific geographical conditions of the country. Land lased resettlement is more easily implemented in rural areas.

Article 6 of Land Act and Forest and nature Conservation Act, Section 9 and Forest and Nature Conservation Rules, 2000 Sections 20 and 21.

No substantial difference

None.

7. For those without formal legal rights to lands or claims to such land that could be recognized under the laws of the country, provide resettlement assistance in lieu of

The law does not distinguish between those affected people with formal and those without formal rights. Based on discussion, it was learned that compensation is actually provided to affected people without formal legal rights or claims to lands to be expropriated

Land Act and Forest and Nature Conservation Act and Rules.

No significant difference.

None.

Page 89: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

76

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

assistance in lieu of compensation for land to help improve or at least restore their livelihoods.

8. Disclose draft resettlement plans, including documentation of the consultation process, in a timely manner, before appraisal formally begins, in an accessible place and in a form and language that are understandable to key stakeholders.

A notice is served to all potentially affected persons and disclosure of the project concept and resettlement proposal is made in public places accessible to the “concerned people” (i.e; defined as “individuals, groups and communities whose interests may be affected by a project.” .However, there is no provision on consultation under the Land Act and the Forest and Nature Conservation Act. People whose land is affected are consulted through a Committee formed for the land acquisition before any land taking and project implementation starts. Consultation is provided for under the EA Act and its implementing regulations

Land Act, 1979 Forest and Nature Conservation Act, 1995 EA Act, 2000

The Act does not provide for consultation with affected people regarding planning and implementation of land acquisition impacts and mitigation measures or payment of compensation before the land is taken by the Government.

For RAP II, the World Bank will use OP 4.12 t implement the IR safeguard. Reform of Land Act would be necessary to address differences on a systems level.

9. Apply the principles described in the involuntary resettlement section of this Table, as applicable and relevant, to subprojects requiring land acquisition.

Sub projects are treated as self standing projects under Bhutan’s laws and regulations

None None.

10. Design, document, and disclose before appraisal of projects involving involuntary restriction of access to legally designated parks and protected areas, a participatory process for: (a) preparing and implementing project components; (b) establishing eligibility criteria; (c) agreeing on mitigation measures that help improve or restore livelihoods in a manner that maintains the sustainability of the park or protected area; (d) resolving conflicts; and (e) monitoring implementation.

Land law does not make reference to legally designated protected areas and parks. Forest means “reserved Forests” which include the nine categories of protected areas. It allows forest neighboring communities to collect “leaf mould [and] fodder” and grant the Minister in charge of forests the mandate to make rules to allow taking of forest produce without a permit. Under the legislation on protected areas, access to natural resources of protected areas may be restricted or prohibited as the case may be by a Minister’s decision. The Forest and Nature Conservation Act mentions however that if this occurs, a compensation must be provided to affected peoples.

Land Act, sections 3.5 and 8.5 Forest and Nature Conservation Act, Sections 9, 12 (a), 12 (b) (iii), 21 (a) in fine

None None.

11. Implement all relevant resettlement plans before project completion and provide resettlement

The legislation does not provide explicitly and clearly for implementation of resettlement plans before the project is implemented. However, in case of land for land compensation, land acquisition will

Land Act Only land substitution programs provisions are required to be implemented prior to land acquisition.

For RAP II, the World Bank will use OP 4.12 t implement the IR safeguard.

Page 90: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

77

Government of Bhutan’s Equivalent Requirements with Specific Reference to Urban Development and Rural Access II Projects

Bank Policy (OP 4.00) Requirements

(Objective and Operational Principles)

Objectives and Operational Principles as stated in the relevant laws, rules,

regulations, procedures, and policies57

References to the relevant sections of the laws, rules, regulations,

procedures, and policies

Differences between OP 4.00 and

Bhutan’s requirements

Improvements needed before implementing

project activities

entitlements before displacement or restriction of access. For projects involving restriction of access, impose the restrictions in accordance with the timetable in the plan of actions.

take place only after fulfilling the Satshab (substitute land) allotment procedures.

There is no such requirement applicable to compensation or other resettlement requirements.

Reform of Land Act would be necessary to address differences on a systems level.

12. Assess whether the objectives of the resettlement instrument have been achieved, upon completion of the project, taking account of the baseline conditions and the results of resettlement monitoring.

No provision in the legal system of Bhutan for

There is no provision for assessing the results of resettlement.

For RAP II, the World Bank will use OP 4.12 t implement the IR safeguard. Reform of Land Act would be necessary to address differences on a systems level.

Page 91: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

78

Attachment 1

Applicable Policies, Acts, Regulations And

International Agreements

I- Relevant Policy Documents a. Gross National Happiness (GNH) b. The Middle path, National Environment Strategy (NES), 1998 c. Bhutan 2020

II- Relevant Legislation to Overall Environmental Governance in Bhutan a. The Road Act, 2004 b. Mines and Minerals Management Act, 1995 c. Penal Code, 2004 (Section 309, 408 and 409) d. Bhutan Municipal Act, 1999, e. The Seeds, 2000 f. The Live stock Act, 2001 g. The pesticides Act, 2000 h. Water and Sanitation Rules, 1995 i. National Environmental Protection Act, Draft VII, July 24, 2006

III- Environmental Assessment a. The Environmental Assessment Act, 2000 b. Regulations for Environmental Clearance, 2002 c. Regulation on Strategic Environmental Assessment, 2002 d. EA: Sectoral Guidelines for Forestry, 1999 as amended by the Guidelines for

Environmental Clearance for Forestry Activities, 2004 e. EA: Sectoral Guidelines for Hydropower, 1999 f. EA: Sectoral Guidelines for Mining & Minerals Processing, 1999 g. EA: Sectoral Guidelines for New and Existing Industries, 1999, 1999 h. EA: Sectoral Guidelines for Roads and Highways, 1999 i. EA: Sectoral Guidelines for Power Transmission Lines, 1999 j. Environmental Codes of Practice for Sewage and Sanitation Management in

Urban areas, 2000 k. Environmental Codes of Practice for Hazardous Waste management, 2002 l. Environmental Codes of Practice for Highways and Roads, 2000 m. Ambient Discharge Standards and Environmental Sampling Manual, 1999

IV- Management of Cultural Property a. The Antique and Art Treasures Rules and Regulations b. The Movable Cultural Property Act of Bhutan, 2005

V- Involuntary Resettlement a. Urban Areas & Property Regulations, 2003 b. Registration of land in Thram (Land Act), 1979 c. Land Compensation Rates, 1996 as amended to date d. Policy Framework for Land Acquisition and Resettlement, 1999

VI- Natural habitats a. Forest and Nature Conservation Act, 1995

Page 92: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

79

b. Forest and nature Conservation Rules of Bhutan, 2000 c. Biodiversity Act, 2003

VII- International Environmental Treaties, Conventions and Agreements to Which Bhutan is a Party and Which Are Relevant to the Use of Country System for the Greater St Lucia Wetlands National Park Pilot Project a. Convention on Biological Diversity b. Convention on World Natural and Cultural Heritage c. United Nations Framework Convention on Climate Change d. Convention to Combat Drought and Desertification, e. Convention on International Trade in Endangered Species (CITES)

Page 93: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

80

ANNEX BREFERENCES

Asian Development Bank (ADB), Project Performance Audit Report on the East-West Highway Maintenance Project, August 2000

ADB Technical Assistance to the Kingdom of Bhutan for Capacity Building to Implement Environmental Assessment Procedures, August 2005

Department of Planning, Ministry of Finance, Royal Government of Bhutan (RGOB)Poverty Reduction Strategy Paper (Cover Note to the Ninth Plan Main Document), 2004

Department of Roads (DOR), Ministry of Works and Human Settlements, RGoB, Final Report:Environmental Assessment: Gomphu-Panbang Highway, Zhemgang, KyingkhorConsultancy Services, December 2005

DoR, Geotrechnical Assessment of Gomphu-Panbang Highway, Final Report, August 2006, M/s Geo-tech consultancy service,Thimphu, August 2006

DOR/Environmentally Friendly Road Construction Support Project (EFRC-SP), Evaluation on Environmental Assessments & Environmental Management Plans of Rural Access Roads

DoR, EFRC-SP Environmental Management Plan, Bioengineering Training, May 2004

DoR, EFRC-SP, Environmental Policy, May, 2004

DoR, EFRC-SP, Guidelines for the Preparation of Environmental Management Plan, Version 1, July 2005

DoR/ SNV-EFRC-SP, Monitoring and Reporting Guideline for the Department of Roads, July 2005

DoR/SNV, EFRC-SP, Road Sector Support Programme, Mission Report, December 2005

DoR. SNV, EFRC-SP, Strengthening of Monitoring and Reporting Systems, Assessment Report.April 2005

EFRC-SP, Evaluation on Environmental Assessment and Environmental Management Plans of Rural Access Project Roads, 2005

EFRC-SP Mid-Term Review, June 2004

Global Environment Facility, Request for Funding, Enhancing Global Environmental Management in Bhutan’s Local Governance System, April 28, 2006

International Bank for Reconstruction and Development (IBRD), Country Assistance Strategy for Bhutan, 2006

IBRD, Environmental Management Plan, Sustainable Land Management Project, 2005

Page 94: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

81

IBRD, Project Information Report, Rural Access Project, Bhutan March 15, 1999

IBRD, Project Appraisal Document, Rural Access Project, Bhutan November 19, 1999

MacKinnon, J. Birds of Royal Manas National Park, 1993

Ministry of Agriculture, (RGoB), Sustainable Land Management Project; Final Environmental Management Framework, March 2005

Netherlands Development Organization (SNV), The Road to Sustainability: Environmentally Friendly Road Construction,: Bhutan

National Environmental Commission (NEC), Royal Government of Bhutan, Application for Environmental Clearance Guideline for Highways and Roads,, August 2004

NEC, Bhutan, Treading the Middle Path to Sustainable Development, 1998

NEC, Brief Report on Bhutan’s State of the Environment for FY 2004-05, April 2005

NEC, Environmental Assessment Act, 2000

NEC, Environmental Assessment Process Manual, February 1999

NEC, Environmental Codes of Practice: Highways and Roads, April 2000

NEC, Institutionalizing and Strengthening of the Environmental Asseessment Process in Bhutan, Reference Document, February 1999

NEC, Ninth Five Year Environmental Sector Plan, 2001

NEC, Regulation for the Environmental Clearance of Projects, 2002

National Environment Commission Secretariat (NECS) and the United Nations University, Environmental Governance in Bhutan – National Case Study, June 2004

NECS/ United Nations Development Programme (UNDP), National Capacity Self-Assessment for Global Environmental Management and Action Framework, September 2005, p. xvi

RGoB, Forest and Nature Conservation Act of Bhutan 1995

United Nations Environmental Progarm, Norwegian Agency for Development Cooperation (NORAD) State of the Environment, Bhutan, 2001,

Ura, Karma and Kinga, Sonam, Bhutan- Sustainable Development through Good Governance,Center for Bhutan Studies, Thimphu, May 2004;

Visser, Hendrik, Augustijn, Reindert and. Rai, S.N, Environmentally Friendly Road Construction in Bhutan: Providing Access to Rural Communities While Protecting the Environment Seminar on Sustainable Access and Local Resource Solutions, November 28-30, 2005

Page 95: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

82

ANNEX C: LIST OF PERSONS MET DURING EQUIVALENCE AND ACCEPTABILITY MISSIONS

David Annandale, Senior Technical Advisor, NEC Torben Bellers, Minister Counselor, Liaison Office of Denmark R.K. Bhandari, UDPII, TA Team, DUDES Tek B. Chhetri, Deputy Head, Liaison Office of Denmark Choden, Junior Engineer, Environment Unit, DOR, MoWHS Sonam Chodan, Environment Officer, DoR Kezang Deki, Deputy Chief Urban Planner, Thimpu City Corporation Sonam Desel, Environment Officer, MoWHS Damcho Dorji, Director, Department of Legal Affairs Tshewang Dorji, Design Engineer, DoR Dung Kar Drukpa, Senior Planning Officer, Policy and Planning Department, MoWHS Raling Ngawang Drukdra, Joint Director, Nature Conservation Department, Ministry of Forests Seeta Giri, Assistant Resident Representative (Energy and Environment), UNDP B.B. Gurung, Executive Engineer I, DoR Nima Gyeltshen, Asst Project Manager (RAP II), MoA Peter Hansen, Consultant, PPD, Ministry of Agriculture S.P. Jakhanwal, UDPII, TA Team, DUDES Himinder Lal, UDPII, TA Team, DUDES Christine McMahon, Country Director, SNV Kinzang Namgay, Country Representative, WWF Seshey Nidup, Officiating Asst Project Manager, RAPII, Department of Roads, MoWHS Karma C. Nyedrup – Deputy Director, National Environment Commission Kinzang Norbu, Superintending Engineer, Department of Urban Development, Ministry of Works and Human Settlements Ugyen Norbu, Program Officer, DADM, MoF Tsering Paljore, Project Coordinator, RAPII, DoR Ms. Lhedin Pema, Project Manager (RAP I), DUDES Phuntsho, Officiating Director, DUDES N.L. Rai, Executive Engineer D, DoR S.N. Rai, Project Coordinator, EFRC, DoR Sonam Reinchen, Head, PPD, MoWHS Nado Rinchhen, Deputy Minister of Environment, NEC B. Suberi, National Road Engineer, RAPII Dasho Dawa Tshering, Director General, Department of Forests Tshering, Economist, MoWHS Roz Saad, Senior Good Governance Advisor, SNV K.N. Sharma, Engineer (Nobdling), DoR Toshihiro Tanaka, Deputy Resident Representative, UNDP Akiko Ueda, UN Coordination Officer, UNDP Tomo Ueda, ADB, Manila K. Wangdi, Chief Engineer (RAP I), DoR Nima Wangdi, Thrompon, Thimpu City Corporation Phuntsho Wangdi, Director, DoR Tshering Wangdi, Officiating Director, Department of Roads, MoWHS Dr. Sanjay Wangchuk, Director, Nature Conservation Division Hon. Sanjay Wangchuk, Secretary, Ministry of Culture Tshering Yangchen, Kyingkhor Consultancy

Page 96: Public Disclosure Authorized SR8 - World Bank...provide the basis for piloting in the rural roads sector. 6. The application of UCS to Bhutan and to the RAP II project is consistent

83