public jsc ukrnaftokhimproect - unxp.com.uaunxp.com.ua/2012eng.pdf · vantage pd pdms v 12 design...
TRANSCRIPT
Public JSC
“Ukrnaftokhimproect"
Company history
• 1958 Council of Ministers of the USSR State Planning Commission
orders the "Ukrgiproshaht" Institute to be involved in carrying out design,
survey and research works at oil and gas industry enterprises - the
official date of founding of the institute.
• 1992 Reorganization of the SPA "MASMA" and creation of the separate
design institute "Ukrgiproneftehim" with direct subordination to State
Ministry of Chemical Industry of Ukraine.
• 1994 Corporatization. State Commitee for Oil and Gas order established
OJSC "Ukrnaftokhimproect", which became the legal successor of the
Institute "Ukrgiproneftehim".
• 2011 Open Joint Stock Company "Ukrainian Institute for design of refining
and petrochemical plants "Ukrnaftokhimproect" (OJSC
"Ukrnaftokhimproect") was renamed to Public Joint Stock Company
"Ukrainian Institute for design of refining and petrochemical plants
"Ukrnaftokhimproect" (Public JSC "Ukrnaftokhimproect").
Company management
organization structure
Chairman of the Board
Technical director Director of Engineering
Head project engineers bureau Supervision department
Control department Technological department
Assembly and mechanical
department
Architecture and construction
department
Electrotechnical department Control and automation
department
Water supply and sanitation
department Heating and ventilation department
Thermal engineering department General layout and transport
department
Engineering survey department Calculation department
Designing works automation
department
Design documentation output and
storage department
Technical director department
New technology and CAD
development sector Quality management system
and licensing sector
Informational analytical sector
Accounting
Branches:
Lviv, Severodonetsk,
Kharkiv, Kherson,
Kremenchug
Offices in:
Russian Federation,
Republic of Belarus,
Republic of Kazakhstan
Administration
Human resources
Planning and contract department
Department of material and technical
maintenance and cleaning Autotransport department
Industrial safety sector Designing support sector
Marketing sector
Russian Federation
Certificate of Self-Regulatory Organization Non-profit partnership
"Neftegazservis" for admission to the types of works on preparation of project
documentation, which affect the safety of capital construction, including
the especially dangerous objects from 22.09.2011 № 005-2
Certificate of Self-Regulatory Organization Non-profit partnership of specialized
enterprises of Oil and gas industry "Neftegazstroy“ for admission to the
types activities that affect the safety of capital construction, including a
particularly dangerous objects from 11.08.2011 № 000867-2011-9909152511-C-041
Certificate of self-regulating organization Non-Profit Partnership "Engineering
Geological Surveying in Construction" for admission to a particular activity or
activities that affect the safety of capital construction, including a
particularly dangerous objects from 03.05.2012 № 0094.01-2012-214891026148-I-
014
Ukraine
State Architectural and Building Inspection license
State Department of Fire Safety of the Department of Emergencies of Ukraine license
Permission for commencement of works of increased danger
State Service of Geodesy, Cartography and Cadastre license
Republic of Belarus
Permission no. 05-984-2011 from 21.07.2011, the Department for Supervision on safe
works conduction in industry. Ministry of Emergency Situations of the Republic of
Belarus (Gospromnadzor)
Development of projects of technological processes and industries, which apply highly
toxic, toxic and potent substances, including their storage, as well as processes and
industries, where formation of explosive atmospheres is possible
Calculation of the relative energy potentials for explosive hazardous technological units
Development of the declaration of industrial safety for hazardous industrial facilities for
the enterprises controlled by the Republic of Belarus Gospromnadzor
Republic of Kazakhstan
Department of the State Architectural and Construction Supervision of Astana.
State license for activities in designing and surveying in the field of
architecture, urban planning and construction
Department of the State Architectural and Construction Supervision of Astana.
State license for performing construction and assembly works in the field of
architecture, urban planning and construction
Department of the State Architectural and Construction Supervision of Astana.
State license for performing expertise works and engineering services in the
field of architecture, urban planning and construction
Committee for State inspection of oil and gas industry. Ministry of Oil and Gas of
the Republic of Kazakhstan. State license for activities on designing
petrochemical and oil and gas processing plants
Quality management system
Quality of Public JSC “Ukrnaftokhimproect”
works has been approved by Quality Management
System certificate according to International
Standard ISO 9001:2008 (initial certification - 2003).
Main goals in quality are: :
- meeting the increasing demands of customers
(consumers) to product quality;
- development of new designing programs to
occupy the leading position in the design and
survey market.
CAD software for technological
department
Software name
Functionality
Developer
HYSYS.Process. v 2.4
The program of
constructing flow diagrams,
flows, heat transfer
equipment, pipes, pressure
measurement, the operation of
separation, the column definition
of solids, reactors.
HYSYS
TASK. v 5. 0
The program allows
to simulate the
most complex integrated
circuits. It is possible to
check and analyze the network
performance of heat exchangers
in general, or of any
exchanger separately.
HYSYS
Software name
Functionality
Developer
Predklapan v 2.5 The program is designed to
calculate and select the brand of
safety valves of direct
action, mounted
on vehicles, vessels and
process piping.
Scientific Technical Company
“Truboprovod”
Moscow.
Gidrosistema. v 2.10
Carrying
out hydraulic calculations
for single-
phase flow pumping (liquid or
gas) without heat transfer, as
well as to select and to
determine the diameters of the
bandwidth of a
branched pipeline.
Scientific Technical Company
“Truboprovod”
Moscow.
CAD software for technological
department (continued)
CAD software for technological
department (continued)
Software name
Functionality
Developer
SAFETY v 1.2
The program is applicable to
determine the energy
potential of explosive designed
and existing facilities,
preparation of declarations
of security analysis of the
consequences of emergencies.
IKT Service
Moscow.
TOKSI v 2
The program to quantify the
effects of chemical
accidents on industrial facilities
with emissions of hazardous
chemicals into the atmosphere.
IKT Service
Moscow.
Software name
Functionality
Developer
RPMS 2000
RPMS system which is the
most profound in its
capabilities for modeling
technological features at refining
and petrochemical enterprises
and their economic and market
environment.
JV “Perrakom“
Moscow.
VANTAGE PD P&ID v 6.2
VANTAGE PE P &
ID, version 6.2, provides a
solution for developing
and storing project
data integration and process
flow diagrams (P&ID),
developed based on AutoCAD.
AVEVA UK
CAD software for technological
department (continued)
Software name
Functionality
Developer
PV - security
after decompression of device
Accounting for cooling
overheated spilled liquid phase
(LP) when it evaporates.
Calculation of initial conditions
for the composition,
quantities and temperatures of
PGP and LP.
LLC Tehnosoft-Computer Center
Moscow.
“Ecolog - Noise"
Calculation of the noise
characteristics of the
module "Calculation of the
penetrating noise" machine.
Integral
St. Petersburg, Russia
INTERGRAPH P&ID
Is the solution for development
and storage of design
data integration and process
flow diagrams (P&ID).
Intergraph Corp
USA
CAD software for technological
department (continued)
CAD software for Assembly and
Mechanics department
Software name
Functionality
Developer
“Start" The program is designed to
calculate the strength and
stiffness of the space of
branched piping for various
purposes under static loading.
SPA Truboprovod
Moscow
VANTAGE PD PDMS v 12
Design of pipelines,
modeling stairs, ladders, access
zones, equipment design.
AVEVA
UK
Software name
Functionality
Developer
GazCAD. Pipe3d The main functions - the
creation of three-dimensional
model with detailed piping and
pipe fitting process and then
get the plans and sections,
isometric diagrams and output
documents.
JSC Khimproect
Severodonetsk, Ukraine
Shtucer - FEM
Used to calculate the strength
and stiffness of the junction with
the vessel nozzle(device) using
the finite element method
(FEM).
SPA Truboprovod
Moscow.
Astra-Nova Applied computer-aided design,
"ASTRANEFTEKHIM"
JSC Astra
Moscow
CAD software for Assembly and
Mechanics department (continued)
CAD software for Architecture and
Construction department
Software name
Functionality
Developer
VANTAGE PD PDMS v 12
Design of pipelines,
modeling stairs, ladders, access
zones, equipment design.
AVEVA
UK
«Autodesk Revit Building 11»
System of architectural design,
automating the creation of
project documentation. Building
information
model conveys construction of
the designed object, its size and
quantitative indicators.
AUTODESK
CAD software for Architecture and
Construction department (continued)
Software name
Functionality
Developer
Structure CAD (SCAD)
SCAD for Windows -
Wednesday synthesis design
model and analysis
of simulation provides unlimited
possibilities of design
models from the simplest to the
most complex designs.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
Kometa
Calculation and design
of components of steel
structures of buildings and
structures in industrial and
civil construction.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
Kristall Solution of practical problems of
expertise and design of
steel structures.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
Software name
Functionality
Developer
Forum The program is designed to
perform calculations related to
the formation of enlarged
models of the object.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
Arbat The program is designed to
perform calculations relating to
the selection and testing of the
existing reinforcement
in reinforced
concrete structures, as well
as for the calculation
of deflections in the light of
cracks in the tension zone of
reinforced concrete.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
CAD software for Architecture and
Construction department (continued)
Software name
Functionality
Developer
Kamin The program is designed to
perform calculations relating
to the implementation of
settlements and verifications of
stone and reinforced masonry
structures, as well as
examination of the
damaged structures.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
West The program is designed to
perform calculations relating to
the definition of loads and
impacts on building
structures according
to SNiP 2.01.07-85 *.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
CAD software for Architecture and
Construction department (continued)
Software name
Functionality
Developer
Monolith The program is designed to
perform calculations related to
the design of reinforced
concrete monolithic
ribbed slabs.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
Kross The program is designed to
perform calculations related to
determining the coefficients for
calculating the bed of
foundation structures on an
elastic Winkler foundation.
Sci-tech enterprise at scientific
research institute of
environment and resources
Kyiv.
Lira The simulation program design
models from the simplest to the
most complex designs.
JSC Lira
Kyiv
CAD software for Architecture and
Construction department (continued)
Software name
Functionality
Developer
FOK + LENT - PC 2010
Designing separately
standing foundations under
columns of frame buildings on
the natural, piles and piles
hammer drilled foundation.
GPI Kyiv Promstroyproject
Parus PC
For design (checking) retaining
walls under normal and
seismic conditions of
construction.
GPI Kyiv Promstroyproject
Parus - 3
Program for calculating retaining
walls of the bored piles.
GPI Kyiv Promstroyproject
CAD software for Architecture and
Construction department (continued)
CAD software for General layout
and transport department
Software name
Functionality
Developer
Planicad The complex of design of master
plans and grading industrial
facilities, urban and special
objects in the environment
of AutoCAD
GEOCAD
Kyiv.
Topocad + Planicad
The complex of design of master
plans and grading facilities for
industrial use, urban
development and special projects.
GEOCAD
Kyiv.
CAD software for control and
automation department
Software name
Functionality
Developer
VANTAGE PD PDMS v 12 3-D model of the equipment and
piping drawings of plans,
sections and isometric
piping, equipment specification.
AVEVA
UK
"Inergraph Smart Plant Instrumentation"
Provides 10
standard, integrated
modules for data processing,
calculation, wiring,
loop drawings, as well as
two separate additions: three-
dimensional data for pipelines
and telecommunications.
Intergraph Corp
USA
CAD software for electrotechnical
department
Software name
Functionality
Developer
SAPR-Alpha
Power equipment SAPR-
Alpha-PE
Power one-line electrical diagrams, electrical load calculations, equipment selection and cross-sections of conductors, the setting of protective equipment specification. Drawings of the location of electrical equipment and electrical wiring plans on the premises.
SAPR-Alpha
Moscow
WinELSO 6.2
Placement of equipment and cables on the plans. Formation of electrical circuits Formation of the computational model, and for electrical calculations. Perform lighting calculations. Automated development of design documents
WinELSO
Moscow
CAD software for water supply and
sanitation department
Software name
Functionality
Developer
ARS v 9.1
Calculations of the elements of heating
systems in several modes of operation
(heating stations, pipelines, pumping
stations) with automatic water network
operating costs based on
established controls, with
selection throttling devices, with
automatic generation of the
required calculations for input
data. Getting a table of pressure losses.
Y. Kugel
Kyiv
VANTAGE PD PDMS v 12
3-D model of the equipment and
piping drawings of plans, sections
and isometric piping, equipment
specification.
AVEVA UK
CAD software for water supply and
sanitation department (continued)
Software name
Functionality
Developer
Inzhcad ver 8
Program for calculating rainwater
drainage
design of external engineering networks
Inzhcad
Kharkiv, Ukraine
Gidrosistema
The hydraulic calculations for transfer of
single-phase flows. Getting a table of
selected sizes and pressure losses.
SPA Truboprovod
Moscow
CAD software for thermal
engineering department
Software name
Functionality
Developer
Isolation ver 2.11.03
Calculation and selection
of thermal isolation of equipment and
pipelines.
SPA Truboprovod
Moscow
VANTAGE PD PDMS v 12
3-D model of the equipment and
piping drawings of plans, sections
and isometric piping, equipment
specification.
AVEVA
UK
CAD software for heating and
ventilation department
Software name
Functionality
Developer
“PDV-ECOLOG" v 2.50
Program development and formation of project tables of standards of maximum permissible emissions (MPE) of the company.
Integral
St.Petersburg, Russia
VANTAGE PD PDMS v 12
3-D model of the equipment and
piping drawings of plans, sections
and isometric piping, equipment
specification.
AVEVA UK
UPCVP Ecolog
A unified program for calculating the
values of concentrations of pollutants in
the air.
Integral
St.Petersburg, Russia
ARS v 9.1
The calculations of heat exchangers, heat, and engineering calculations.
Y. Kugel
Kyiv
CAD software for heating and
ventilation department (continued)
Software name
Functionality
Developer
EOL(GAS)-2000
Automated system for calculating the dispersion of emissions into the atmosphere designed to assess the impact of emissions planned and existing (reconstructed) companies to pollute the atmospheric boundary layer.
LLC “Soft fund"
Kyiv
ARM-ECO
Program designed to generate tables of inventory of emission sources of enterprises, development of an action plan to reduce emissions and reduce concentrations of harmful substances in the atmospheric surface layer.
A.Homenko,
E.Gusha
Kyiv
CAD software for engineering survey
department
Software name
Functionality
Developer
TopoGrad 3.22
Automated system for processing the results of geodetic surveys and topographic surveying, performed for large scale mapping.
JV ITES
Kyiv
ТороPlan
Automated system for the formation
of topographic maps from
existing cartographic materials.
JV ITES
Kyiv
TopoMap
Automated system for the formation
of topographic maps from
existing cartographic data
JV ITES
Kyiv
CAD software for engineering survey
department (continued)
Software name
Functionality
Developer
Easy Trace v 8.0
Automated digitizing existing plans for cartographic materials.
Easy Trace Group, Ryazan, Russia
WinGEO
Building engineering and geological sections, characterization of soil deformation.
Giosistema
Kyiv
CAD software for calculation
department
Software name
Functionality
Developer
GRAND-smeta
Compilation of local budgets in any of the existing methods of calculation (basic, index, resource, compensation, resource-index).
GRAND
Moscow
AVK-5 Designed for automated determination of the cost of construction, carried out in Ukraine.
SPA AVK
Kyiv
CAD software for information
and reference systems
Software name
Functionality
Developer
StroyConsultant - Reglament
Regulatory support of the design and construction organizations of the Russian Federation.
StroyConsultant
Moscow
“Normativ-Pro"
Regulatory support of the design and construction organizations in Ukraine.
Information
and Marketing Center
Kyiv
Project Management System based
on Spider Project software
Spider Project is focused on the implementation of corporate management
standards and the creation of projects models.
Libraries of typical project templates allow avoiding mistakes in the description of technological processes and significantly ease the formation of project models.
The use of reference books and libraries of fragments allows to create regulatory framework ensuring the consistency of the initial information on the projects.
A computer model of the project should properly reflect the reality, to be able
to take into account the uncertainties and risks, and to track trends in time to
signal need to apply corrective action.
In our view, a mature project management - is an optimal project resource
management for achieving the goals.
Project Management System based on
Spider Project software (continued)
creating a library of schedule templates in order to create preliminary project
schedules during contract stage;
creating a database of completed projects in order to fixate labor costs
for project implementation and use the accumulated data in future planning;
time management of the project, including the operational development
schedules and their correction during implementation;
project cost management;
project resource management;
projects portfolio management;
resource conflict solving;
current projects performance control;
acquiring statistics and reports of projects performance;
centralized storage of information, timelines, resources and costs;
the ability to quickly analyze the impact of changes in the
schedule on resource maintenance and financing of the planned works.
Results guaranteed by system implementation :
Licensors of process technologies
UOP LLC, a Honeywell company (USA)
ABB Lummus Global (USA)
Axens (France)
Webster Griffin (Great Britain)
Merichem (USA)
WorleyParsons Resources & Energy (Australia)
Pörner Verfahrenstechnik (Austria)
Sandvik AB (Germany)
Technimont (Italy)
Technip (France)
Boato International (Italy)
Foster Wheeler (Great Britain)
Honeywell company (USA)
Shell (Netherlands)
Full scale design of industrial facilities :
Development of technical and commercial proposals, feasibility studies and studying investment in the construction, reconstruction, expansion, modernization of enterprises and separate processing plants of refining and petrochemical industries
Selection the company - developer of technology processes, analysis of
"initial data" or the base project
Performing commissioning works at the ”turnkey” enterprises
Development of technical specifications for designing.
Preparation of site-local estimates, estimated calculation of the cost of
construction, construction management project
Our activities.
Design
A full-scale designing of civilian objects : Development of project sketches on civilian objects;
Development of architectural solutions;
Development of carrying and protecting constructions, roof;
Development of gas supply systems, heating, ventilation, water
supply and sewerage of buildings and structures;
Development of power supply systems and telephony;
Development of fire and security alarms
Our activities.
Design. Engineering geological survey and
topographical geodesical works.
Performing engineering geological and topographic geodesical works at
production platforms of any complexity
Our activities.
Commissioning works,
supervision and engineering support of
projects
Performing supervision and engineering support for construction
of industrial and civil facilities to ensure conformity with the
decisions contained in the project documentation
Performing commissioning works on putting into operation separate technological plants and launching oil, gas, refining and petrochemical industry complexes.
Industrial safety (project stage)
Declaration of security for units, offsite facilities, oil storage tank
farms, standalone oil storages.
Declaration of security for company, several plants, offsite
facilities , tank farms.
Calculation of the energy potential of a technology unit, park,
standalone raw material pumping, emergency barn, etc.
Calculation of the energy potential for plant or offsite facilities,
consisting of several units
Industrial safety: calculation of fire
danger rating
Calculation of fire danger category
Calculation of excess pressure developed by the combustion of gas-air mixtures indoor
Calculation of areas bounded by the lower flammability limits of gases and vapors
Calculation of drainage sizes
Calculation of steam fire-screens and other calculations
Activities on water recycling - for production facilities.
Activities on atmospheric air protection;
Justification of decisions on wastewater treatment and disposal of neutralized elements, to prevent accidental discharges of wastewater;
The results of calculations of ground level concentrations of pollutants, analysis and proposals for limit values and temporarily agreed emissions;
List of activities to prevent and (or) reduce the possible negative effects:
List of activities for the
environmental protection (project
stage)
Activities for minimizing the possible occurrence of emergency situations at the facility of capital construction and the consequences of their impact on the ecosystem of the region.
Activities for the protection of flora and fauna and their habitats;
Activities for conservation of mineral resources - for production facilities;
Activities for the collection, use, disposal, transportation and disposal of hazardous waste;
Activities for the protection and management of land resources and soil, including activities for reclamation or contaminated land and soil;
List of activities to prevent and (or) reduce the possible negative effects:
List of activities for the
environmental protection (project
stage) (continued)
Situational plan (schematic map) of the construction area with indication of its land borders, provided for the placement of objects of capital construction, the boundaries of sanitary protection zones, residential areas, recreational areas, water protection zones, protection zones of drinking water sources, habitats of animals and plants.
The list and costing of the implementation of environmental activities and compensatory payments;
Program of industrial environmental control (monitoring) of the nature of the changes in all ecosystem components during the construction and operation of the facility, as well as in case of accidents;
Activities, technical solutions and constructions to ensure rational use and protection of water bodies;
List of activities to prevent and (or) reduce the possible negative effects:
List of activities for the
environmental protection (project
stage) (continued)
Situational plan (schematic map) of the construction area with indication of its land borders, provided for the placement of objects of capital construction, specifying the control points, stations, wells and other facilities that provide water samples from surface water and groundwater - relating to industrial objects.
Maps, charts and summary tables with calculation results of air pollution under adverse weather conditions and emissions of substances and combinations of substances with harmful influence summing - relating to industrial objects;
Situational plan (schematic map) of the construction area with indication of its land borders, provided for the placement of objects of capital construction, the location of sources of emissions of polluting substances and devices to clean up these emissions;
List of activities to prevent and (or) reduce the possible negative effects:
List of activities for the
environmental protection (project
stage) (continued)
Projects designed by
Public JSC
“Ukrnaftokhimproect”
from 2000 to 2012
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery
Year Description of works
2000 Development of Justification of Investments in construction of integrated refining complex
2000 Development of working project for fraction of NK-75oS isomerization unit
2001 Development of working project to expand the transformer substation for isomerization unit in relation with a connection to its facilities
2002 Execution of design works for electrical system installation AT
2002 Development of working documentation for the design of the central operator at deep oil processing plants
Year Description of works
2002 Working project of distillates hydrotreating unit at deep oil processing set
2002 Working project of sulfur production unit at deep oil processing
2002 Performing development of start-up complex of the reconstructed set of AT-2
2002 Working project base for storage and shipment of liquefied gases
2003 Working project industrial park of hydrotreated diesel
2003 Working project nitrogen station with air compressor
2003 Working project coking unit at deep oil processing
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
2003 Working project (approved part) for delayed coking unit
2003 Working project commodity tank farm of the hydrotreated diesel fuel
2003 Working project water treatment unit (tit. 2503/8)
2003 Working project circulating water supply unit hydrotreater distillate (tit. 2503/10)
2003 Working project circulating water supply unit sulfur granulation (tit. 2503/9)
2003 Working project hydrogen concentration unit (CCA) (tit. 2503/5)
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
2003 Working project high pressure nitrogen unit (tit. 2503/6)
2003 Working project hydrogen sulfide flare (tit. 2503/7)
2003 Working project sour water stripper unit (tit. 2503/11)
2003 Working project modernization of CDU AVT-3 unit
2003 Development of technological regulations for the production of distillate hydrotreating unit and unit of sulfur production
2004 Preparation of tender documentation for the installation of a delayed coking unit with offsite objects
2004 Supervision for the construction and installation of offsite facilities for 1st stage of a delayed coking unit
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
2004 Consideration and approval of projects developed by FFP
2005 Alignment of regulations for the isomerization unit
2005
Development of the project of electrical heating systems and blocks of production sulfur and distillate hydrotreater
2006 Performing strength calculations and the development of baseline data on the configuration of the transfer pipeline from the furnace P-1 to columns K-1 and R-1A with the placement of support and strength calculations for CDU-AVT-3 unit
2006 Development of approved part for CDU-AVT-3 unit
2006 Supervision for the construction and installation of furnace P-1 at CDU-AVT-3 unit
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
2006 Development of working documentation on piping for furnace P-1 at CDU-AVT-3 unit
2006 Development of approved part and documentation on a complex of delayed coking of goudron
2006 Development of project of logical schemes PAZ at CDU-AVT-3 unit
2006 Development of working documentation of the transfer line vacuum column K-3 at CDU-AVT-3 unit
2006-2007 Development of working project "delayed coking of goudron unit"
2007 Adjustment of working documentation for the object of delayed coking unit
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
2007 Supervision for the progress of construction of the complex DCU
2007 Execution of design works on adjusting approved part in the project: Complex DCU. Offsite facilities of a delayed coking
2007 Execution of design works on adjusting the working documents on object: Complex DCU. Offsite facilities of a delayed coking
2007 Working project ”Base for storage and shipment of liquefied gases"
2008 Development of reconstruction of a catalytic reforming unit
2008-2009 Development of modernization of CDU-AVT-2
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
2009 Adjustment of working documents regarding the binding of furnace-101 at DCU
2009-2010 Development of launch production schedules at DCU
2009-2010 Development of modernization of CDU-AVT-3
in work Development of working documents ”Sulfur production unit. 2nd stage"
in work Commissioning of the facility delayed coking complex. Offsite facilities at DCU
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
in work Field supervision during the construction and installation of the project "Reconstruction of the catalytic reformer"
in work Supervision for the progress of construction of the complex DCU.
in work Supervision during the construction and installation of the project Base storage and shipment of liquefied natural gas"
in work Designing of the facility, "Isomerization unit No. 2"
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery (continued)
Year Description of works
2002 Development of Justification of Investments for the major reconstruction
2004
Comprehensive survey of the existing production of Tuapse refinery, energy supply systems and the issuance of offsite facilities findings and determination of the costs of bringing the existing production and the systems to requirements of the standards
2005 Working project of cooling towers installation BVG-600 "MAKSI" overall Mfr.1050 m3 for circulating water supply system
2005 Review and approval of design documentation installation of diesel tanks and cable racks (without modifying the documentation)
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Tuapse Refinery
Year Description of works
2005 Consideration and approval of the working draft of JSC "PMP" "Node of regeneration of gases purification installation L-35-11/300
2005 Development of specifications for electrical equipment and incomplete C&A, providing frequency control of electric motors and fans, coolers of cooling towers included in the supply of BVG-600 "MAKSI"
2006 Performing ER of the 1st stage reconstruction of the refinery
2006 Development of proposals to install a backup pump for pumping fuel from the tanks of the 2nd park fuel oil
2006 Development of working documentation for bringing furnace P-1 installation L-35-11/300 to existing rules and regulations
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Tuapse Refinery (continued)
Year Description of works
2006 Development of working documentation for additional equipment installation L35-11/300 nodes remote reset gas torch and cutter overflow VSG
2009 Development of working documentation "Combined installation of KU-1. Section5000. Delayed Coking"
in work Development of working documentation "Combined unit no.3 (tit.672-10)
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Tuapse Refinery (continued)
Year Description of works
in work Performance of design works "Node for receiving and storage of MTBE"
in work Development of working documentation "Mechanical-repair workshop. Engineering Base"
in work Development of working documentation “Circulating water supply node no.2"
in work Development of working documentation “Circulating water supply node no.3"
Projects designed for
OJSC Rosneft Oil Company -
LLC RN-Tuapse Refinery (continued)
Year Description of works
2004 Development of working project for offsite centralized operator for current and future facilities
2004 Development of 2 TER variants for delayed coking unit
2006 Development of technological control instrumentation schemes and questionnaires , the specifications of the instrumentation for the transfer section 200 LK-6Us-catalytic reforming with preliminary hydrotreating
2006 Field supervision of construction of a centralized operator
Projects designed for
OJSC Rosneft Oil Company -
OJSC Achinsk Refinery
Year Description of works
2007 Development of Working documentation to transfer section 200 LK-6U on DCS
2008 Performance of design works "Construction of offsite centralized operator no 2 on object 'The complex of DCU with a vacuum distillation unit"
in work
Реконструкция комплекса производства нефтяного кокса (в т.ч. установка вакуумной перегонки мазута и установка замедленного коксования)
Projects designed for
OJSC Rosneft Oil Company -
OJSC Achinsk Refinery (continued)
Year Description of works
in work Development of design and working documents of the object ”Sulfur production unit"
in work Development of design and working documentation for facilities of the complex of sulfuric acid alkylation unit.
Projects designed for
OJSC Rosneft Oil Company -
OJSC Angarsk Petrochemical Company
Year Description of works
in work Development of design and working documents of the object Catalytic cracking complex. Gas fractionation plant
Projects designed for
OJSC Rosneft Oil Company -
OJSC Syzran Refinery
Year Description of works
in work Development of design and working documents of the object ”BT unit"
Projects designed for
OJSC Rosneft Oil Company -
LLL Novokuibyshevsk Oils and Additives
Plant
Year Description of works
2006 Replacing furnace P-302 with the installation of the evaporator and the I-302 hydro alkylation plant no.58, heating cogeneration block plant codes ”Monomer"
2006 Supervision in the working project for furnace P-302 replacement, installation of the evaporator I-302
2006-2009 Design, commissioning and supervision of construction of visbreaking unit
2007 Development of working project installation of hydrogen and ammonia evolution from the purge and tank gases
Projects designed for
JSC Gazprom neftehim Salavat
Projects designed for
JSC Gazprom neftehim Salavat
(continued)
Year Description of works
2007 Development of working documentation auxiliary facilities at visbreaking complex
2007-2009 Provision of the support on a complex facilities for the production of visbreaking
2008 Development of technological regulations for visbreaking unit
in work Development of working documentation for construction of CDU-AVT-6 plant
Year Description of works
in work Contract supervision and Supervision for the Installation of Synthesis (block number 6), AM-76 ammonia production
in work Supervision for the construction of CDU-AVT-6 unit
in work Development of working documentation for flare unit at CDU-AVT-6
in work
The complex of catalytic cracking. Installing selective hydrotreating catalytic cracking gasoline. Development of design and working documentation
Projects designed for
JSC Gazprom neftehim Salavat
(continued)
Projects designed for
JSC Gazprom Neft – Omsk Refinery
Year Description of works
2005 Working project replacing the furnace unit at AT-9 facility
2005 Pre-commissioning and commissioning of furnace unit at AT-9 facility
Projects designed for
ТNК-BP
JSC Ryazan Oil Refinery Company
Year Description of works
2005 Feasibility of reconstruction of the isomerization unit
in work Development of design and of working documents phased reconstruction of a CL-24/7 unit to produce diesel fuel.
in work Complex of reconstruction of CL-24/7. Installing the CCA.
in work Complex of reconstruction of CL-24/7. Trails connecting the CCA.
in work Development of working documentation of pipeline construction to install SDT CL 24/7 to ASSB.
Projects designed for
OJSC Moscow Refinery
Year Description of works
2006 Working project furnace P-3 with transfer piping on AVT-3 unit
2007 Supervision of construction of furnace P-3 with a transfer pipeline
2010 Development of the project for bringing furnaces P-101 P-102 P-103 P-104 P-105 at LCH-35/11-1000 unit workshop № 2 to the current regulations
Projects designed for
OJSC NC Russneft -
OJSC Orsknefteorgsintez
Year Description of works
2004 Working project refitting CDU-AVT unit
2004 Field supervision of the reconstruction of furnace unit installation L-35-11/300
Projects designed for
OJSC OGC Slavneft -
JSC YARVAZ
Year Description of works
2003-2004 Working project installation preliminary hydrotreating a catalytic reforming unit of raw materials
2004 Construction field supervision and coordination of design solutions for the installation a catalytic reforming unit hydrotreating of raw materials
Projects designed for
LLC Gazneftedobycha
Year Description of works
2008-2009 Commissioning work on a comprehensive gas unit
2009 Tech support, workflow management, the practical training of operating personnel
2010 Development of working documentation for the modernization of process gas desulfurization
Year Description of works
2000 Designing of reconstruction of the workshop of production the imide additives to obtain MTBE and the necessary facilities and offsite facilities
2000 Calculation of cost-effectiveness of a enterprise of production of MTBE
2000 Development of working documentation for the installation of water recycling MTBE with delivery construction documents
Public JSC "Ukrnaftokhimproect" - general designer Kremenchug
refinery. Design and survey work and supervision for the plant are
performed for 35 years, including in recent years:
Projects designed for
JSC Ukrtatnafta
Year Description of works
2000 Development of technological regulations on of production MTBE
2000-2001 Construction field supervision of MTBE unit
2001 Survey of bearing structures of block of production polybutylene, workshop of production additives such as A-9250 with the purpose of reconstruction for MTBE
2001 Development of working documentation of reconstruction of power supply installed at MTBE
2005 Engineering and geological surveys at the sites of production number 3
2005 Pumping station mixing gasoline and diesel fuels of production № 4
Projects designed for
JSC Ukrtatnafta (continued)
Year Description of works
2005 TER modernization of "Ukrtatnafta" "Improving the quality of gasoline and diesel fuels" on the basis of feasibility study the company LG Engineering
2006 Replacement of electrical equipment TA-31
2007 Working documentation for the redevelopment of the building at CDP Energy Center
2007 Biological treatment of a mixture of effluent pumped on evaporation pond
2007 Development of working project "Unloading the equilibrium catalyst regenerators ofcatalytic cracking"
Projects designed for
JSC Ukrtatnafta (continued)
Year Description of works
2007 Technical and economic calculations of the program "Improving the quality of gasoline and diesel fuel on the basis of having the technological equipment"
2007 Development of working documentation "Production no 2. Reserve collector hydrogen-containing gas"
2007 Performing inventory and development of documents to substantiate emissions to obtain a permit for discharges of pollutants into atmosphere sources on "Ukrtatnafta"
2007 Technical and economic calculations solutions to the problems of exploitation of technological facilities in order to maintain the fuel-oil version of the enterprise
Projects designed for
JSC Ukrtatnafta (continued)
Projects designed for
JSC Ukrtatnafta (continued)
Year Description of works
2008 Project Stage I modernization of Kremenchug refinery
2008 Inventory of sources of harmful pollutants into the atmosphere
2008 Development of working documentation "Node of inputting additives to gasoline and diesel fuel pumping mix of gasoline and diesel fuel"
2008 Development of working documentation "Biological treatment of a mixture of effluent pumped on evaporation pond"
2009 Development of design estimates for the objects I stage of modernization of the Kremenchug refinery "Ukrtatnafta "
2009 Performing engineering-geological surveys for stage I of modernization of the Kremenchug refinery
Projects designed for
JSC Ukrtatnafta (continued)
Year Description of works
2010 Development of project documentation and execution of construction supervision of the object "Replacing the stripper K-1 and the column flow irrigation from the separator-2 of production at the facility L-35-11/300 no 2"
2010 Development of project documentation and execution of erection supervision works on object ’CC-2 CC-3 / 1 № 2 № 1 production facility. Replacing the distillation column K-8 "
2010 Performing the calculation of the enterprise flare system and flare units including construction of new facilities
in work Development of design documentation for the replacement of the distillation column K-1 on the AT-2 SC-3 / 1 no 2 unit
Projects designed for
JSC Ukrtatnafta (continued)
Year Description of works
in work Survey and issuing recommendations on the modernization of the object "Reconstruction of furnace P-1"
in work Replacement of basic equipment (furnace P-601) and implementing of forced circulation circuit block VSG pre-hydrotreating LCH-35-11/600
in work Project documentation and contract supervision of the object ”KK-2 SC-3 / 1 № 2 № 1 production facility. Replacing the distillation column K-8"
in work Working documentation of the 1st stage of modernization of Refinery. CCA node for compression of the fuel gas (tit. 16/1-1)
in work Stage 1 modernization of Refinery. The combined isomerization, hydrotreating gasoline QC (tit. 105).
in work Reconstruction of desulfurization of dry gases
Projects designed for
JSC Ukrtatnafta (continued)
Year Description of works
in work Development of design documentation for the replacement of the distillation column K-1 to install the AT-2 SC-3 / 1 № 2 № 1 of production
in work Calculation of the flare system of the enterprise and flares F1-4
in work Amine regeneration unit (tit. 27/2-1)
in work Interdepartment communication
in work "Industrial Park of raw materials isomerization unit (tit.32/105-1). Industrial Park of gasoline catalytic cracking (tit.32/105-2). Industrial Park isomerate(tit.32/105-3) »
Projects designed for
JSC LINIK
Year Description of works
2006 Biochemical treatment of wastewater sewer systems II
2007 Development of working project "Reconstruction of the loading rack heavy petroleum products"
2007 Development of working project to replace the field instrumentation of CDU-AVT-8 unit no.2
2007 Development of working project on re-piping tanks from the of vacuum gas oil for commercial gasoline
2007 Development of working project re-piping column K-2 reforming unit to separate catalytic cracking gasoline
Public JSC "Ukrnaftokhimproect" - general designer of Lisichansk
refinery. Design and survey work for the plant are performed since the
founding of the plant to date, including in recent years:
Projects designed for
JSC LINIK (continued)
Year Description of works
2007 Working project monitoring and control of column K-2 reforming unit
2007-2009 Development and coordination technological regulations isomerization, catalytic cracking, bitumen production units
2009-2010 Development of working project "Reconstruction of hydrotreating and isomerization of the gasoline fraction of NK-70°C"
in work Development of working project of reconstruction of L-35-11/1000 to selective hydrotreating catalytic cracking gasoline and obtaining MTAE
Year Description of works
2005 Project and working documents of reconstruction of CDU-AVT
2006 Working documentation of electrical lines of vacuum gas oil and fuel oil
2006 Working documentation of conjunction of nitric station to the existing communications
2007 Working documentation on the pump pumping oil, diesel and gasoline fractions
2008 Supervision of construction of the object "conjunction of nitric station to the existing communications"
Projects designed for
JSC Lukoil-Odessa Refinery
Projects designed for
JSC Lukoil-Odessa Refinery
(continued)
Year Description of works
2007-2009 Development of technological regulations to facilities
2009 Performance of design works on the reconstruction of railroad of petroleum products loading rack
2009 Development of working project of reconstruction of the tank farm commodity workshop with the construction of the tank no.129 for the storage of petroleum
2009-2010 Technological calculations to improve the efficiency of the pipes furnace P-1redistillation the gasoline unit (UVPB) TC number 2
in work Field supervision of the reconstruction of railroad of petroleum products loading rack
Projects designed for
JSC Kherson Refinery
Year Description of works
2007 Surveying the industrial site for refinery
2007 Feasibility study "Reconstruction of JSC "Kherson Refinery"
2007-2009 Reconstruction of CDU-AVT-2 JSC "Kherson Refinery"
2008 Development of working documentation of electrical networks cable rack
2009 Performing examination of condition of buildings and structures with the issuance of conclusions and decisions
Public JSC "Ukrnaftokhimproect" - general designer of
Kherson refinery. Design and survey works and supervision for the
plant are performed from 1959 to present, including over the past
5 years:
Projects designed for
JSC CPP Galichina -
Drogobych Refinery
Year Description of works
2007-2009 Feasibility for reconstruction of the plant
2007-2009 Engineering-geological surveys for the modernization
2007-2009 Project for hydrotreating unit of diesel fuel
2007-2009 Project for gasoline hydrotreating unit
2007-2009 Project for objects of offsite facilities
2007-2009 Project isomerisation sections
2007-2009 Development and coordination of technological regulations
2007-2009 Development of required standards of water consumption and sewage
Projects designed for
LLC Karpatneftekhim
Year Description of works
2007-2009 Development of working documentation "Construction of a suspension PVC with capacity of 300 tons / year"
2009-2010 Supervision for Construction of a suspension PVC unit
2009-2010 Development of the project "Single-stage design of the boiler plant of PVC with a capacity of 300 tons / year"
Projects designed for
JSC Montazhspetzstroy Company (Republic of Kazakhstan)
Year Description of works
2007-2008 Carrying out commissioning works and putting into operation of facilities in North Offsite Zone.
2007-2008 Engineering support of works on the installation of equipment and technological facilities in North Offsite Zone.
Projects designed for
JSC Harcon
(Republic of Kazakhstan)
Year Description of works
2007-2009 Development of working documentation of the project Substation number 7 of the northern off-site areas complex "the Pilot Program for the Development of the Kashagan field"
Projects designed for
JSC Ukrnafta
Year Description of works
2001 Working project for furnace reconstruction OFG-132
2002 Supervision for furnace reconstruction OFG-132
2004 Development of working documentation for capital repairs of furnace with flameless combustion PB-6-2 UKNP Gnedintsevo GPP
2005 Supervision of construction of the object Reconstruction of furnace with flameless combustion PB-6-2 UKNP Gnedintsevo GPP
2008 Development of working project "Reconstruction of furnace with flameless combustion PB-9 at USN-1 Gnedintsevo GPP"
2008 Development of working project Construction of the furnace OFG-133 at Glinsk-Rozbyshevsk CPG at Kachanovsk GPP
Projects designed for
SPA Belorusneft
Year Description of works
2006 Field supervision of construction the pilot-industrial underground storage for the disposal of drill slurry to the provision of scientific and technical assistance.
Projects designed for
JSC Naftan -
Novopolotsk Refinery
Year Description of works
2007-2009 Site preparation for construction of a delayed coking of petroleum residues.
Year Description of works
2008 Development of working documentation of pipelines removal from the overpass oiltankers loading area at the tank farm in urban village Borodyanka in Kyiv region.
2009 Working project on dispensing additives node for petroleum products at tank farm in Boryspil
Year Description of works
2009 Pre-reconstruction works on petroleum storage depot in Obukhov district, Kyiv region.
2009 Pre-reconstruction works petroleum storage depot in Vasilkiv (Kyiv region)
FDI Lukoil Ukraine
LLC ТNК-ВР Commerce
Projects designed (continued)
Year Description of works
2007 Surveying, geotechnical engineering and meteorological survey for the expansion and renovation of existing treatment facilities and collector trails
2009 Designing of the fuel filling system of platform "D"
Boryspil Airport (Kyiv)
State Holding Titanium of Ukraine (Crimea)
Year Description of works
2008-2009 Working construction project for the production of sulfuric acid with capacity of 1818.2 tons / day.
JSC “Crimean Titanium"
Year Description of works
2009 Field supervision of construction of a sulfuric acid production with capacity of 1818.2 tons / day
Projects designed (continued)
CDU-AVT-2 plant – primary oil processing in vacuum unit.
Capacity of crude oil - 2 million tones / year.
Put into operation in December 2002.
“Turn-key” projects:
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery
Isomerization unit of NC-750C faction - Production of high-octane
isomerate - a component of gasoline with an octane number of 95.
Capacity of raw materials - 160 thousand tons / year.
Put into operation in April 2002.
“Turn-key” projects:
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery
Hydrotreating unit of diesel fuels, obtaining trade diesel fuels with a low content of sulfur and nitrogen . Capacity of raw materials 800 thousand tons / year. Put into operation in
September 2005.
Sulfur production unit with sour water stripper unit and granulation of sulfur.
Capacity 38 tons / day of solid sulfur. Put into operation in September 2005.
“Turn-key” projects:
OJSC Rosneft Oil Company -
LLC RN-Komsomolsk Refinery
“Turn-key” projects: JSC "Transbunker"
(Vanino port, Khabarovskiy Krai)
Unit for preparation of boiler fuels and bunker oil. fuels for power systems, plants,
Capacity - 500 thousand tons / year. Put into operation in 2001.
“Turn-key” projects:
OJSC OGC Slavneft –
OJSC Yaroslavnefteorgsintez
Hydrotreating unit of diesel fuels. Productivity - 1 million tons / year.
Put into operation in September 2003.
“Turn-key” projects:
PJSC Ukrtatnafta
Plant for the production of methyl tret-butyl ether.
Capacity of initial raw material - 60 thousand tons / year.
Productivity - 14 thousand tons / year.
Put into operation in 2001.
Customers’ testimonials
Customers’ testimonials
Customers’ testimonials
Customers’ testimonials
Honors
The Cabinet of Ministers of Ukraine.
Certificate of Merit for significant
contribution to the development of oil
and gas refining and petrochemical
industries.
Honors
Diploma of the winner of the contest for
the best houses and buildings built and
put into operation in Ukraine in 2004, for
the high quality of design.
Honors
1 degree diploma for Kharkiv branch
of OJSC "Ukrnaftokhimproect" -
winner of the best buildings and
facilities constructed and put into
operation in Ukraine in 2010 in the
category "Industrial plants and
facilities for production purposes”
Company’s development strategy
Development and usage of new technologies
Usage of modern computer software
Upgrading PCs, servers, and copying equipment
Further integration of branch networks
Improving project management system
More than 50 years experience in designing
Using modern technologies
Compliance with safety
regulations and environmental protection
Broad reference of completed projects
Assured quality and reliability
The company focuses on long-term cooperation
Our advantages
Contacts – Head Office (Kyiv)
Address:
Ukraine, 04655, Kyiv, Kudryavskiy uzviz, 5-B
Phone: +38 (044) 417-84-80
Fax: +38 (044) 272-18-03, 272-18-51
E-mail: [email protected]
Site: www.unxp.com.ua
Acting Chairman of the Board - Anatoliy Levandovskiy Acting Director of Engineering - Alla Konoplina
Technical director -
Yuriy Vozniuk
Thank you for attention!