PUBLIC MEETING December 18, 2013

Page 2: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Hudson Bayou Crossing Tools:

• Advanced Geotechnical Techniques

• Soil Borings/Tests

• Water Level Monitoring

• Geophysical Surveys

• Seismic Surveys

• Sound Engineering Practices

Benefits:

• Constructible Design

• Environmental Protection

• Maintain Integrity of Bridge

Page 3: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Pomelo Avenue / Pomelo Place

Options: • Open Cut

Page 4: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Pomelo Avenue / Pomelo Place

AECOM Design • Open Cut

Page 5: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Pomelo Avenue / Pomelo Place

McKim & Creed Design

Page 6: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Pomelo Avenue / Pomelo Place

McKim & Creed Design

Page 7: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Pomelo Avenue / Pomelo Place

Design Benefits: • Upsize Water Mains – Fire Flow

Protection

• New Reclaimed Water Mains

• Full Road Resurfacing

• Restoration of LS 7 Site

McKim & Creed Design

Page 8: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Alta Vista Street / Osprey Avenue

Options: • Open Cut • Microtunneling

Page 9: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Alta Vista Street / Osprey Avenue

AECOM Design • Open Cut • Microtunnel

Design Concerns: • Limitations of 24 inch MT

Machine

• Full Length Lubrication

• Intermediate Jacking Stations

• Pipe Material (VC Pipe)

Page 10: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Alta Vista Street / Osprey Avenue

Design Benefits: • One-pass Construction

• Replace Water Mains (DI and AC)

• New Reclaimed Water Mains

• Storm Sewer Replacement

• Full Road Resurfacing

McKim & Creed Design

Page 11: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Hudson Bayou Crossing

Options: • Microtunneling • Inverted Siphon

Page 12: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Hudson Bayou Crossing

AECOM Design • Microtunnel

Page 13: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Hudson Bayou Crossing

McKim & Creed Design

Design Benefits: • Constructible

• Environmental Protection

• Maintain Structural Integrity of Bridge

Page 14: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Osprey Avenue

Options: • Microtunneling • Open Cut • Combination

Page 15: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

AECOM Design • Microtunnel

Osprey Avenue

Page 16: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

McKim & Creed Design

Design Benefits: • Minimize Disruption to Luke Wood

Park

• Minimize Traffic Impacts (Osprey and Mound Street)

• Full Street Resurfacing (Mound Street to Bahia Vista)

Osprey Avenue

Page 17: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Inverted Siphon Option Comparable Planning Level Cost Estimates

24 inch Hudson Bayou 36” (MT HB) 36” (HDD HB)

Open MT Combo MT HDD MT (Alt.) Open MT Combo Open MT Combo

$1.7M $3.2M N/A $0.60M $1.7M N/A $1.5M $1.9M $1.7M $1.2M $1.8M $1.4M

$4.6 Million

Pros:

Minimizes Lift Station Modifications

Cons:

Odor Control

Maintenance Costs

Traffic Impacts

Construction Constraints

Page 18: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

$4.6 Million

Inverted Siphon Option Comparable Planning Level Cost Estimates

24 inch Hudson Bayou 36” (MT HB) 36” (HDD HB)

Open MT Combo MT HDD MT (Alt.) Open MT Combo Open MT Combo

$1.7M $3.2M N/A $0.60M $1.7M N/A $1.5M $1.9M $1.7M $1.2M $1.8M $1.4M

$5.2 Million

Pros:

Minimizes Lift Station Modifications

Cons:

Odor Control

Annual Maintenance

Constructability

Page 19: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Microtunneling Option Comparable Planning Level Cost Estimates

24 inch Hudson Bayou 36” (MT HB) 36” (HDD HB)

Open MT Combo MT HDD MT (Alt.) Open MT Combo Open MT Combo

$1.7M $3.2M N/A $0.60

M $1.7M N/A $1.5M $1.9M $1.7M $1.2M $1.8M $1.4M

$4.2 Million

Pros: Cost Effective

Traditional Option

Minimizes Impacts to Luke Wood Park

Addresses Public Concerns

Cons: Lower Influent Wet Well

Page 20: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Microtunnel – What’s Different? • Advanced Geotechnical Investigations

• Soils Borings and Tests (Pipe Alignment) • Bathymetric Survey (Hudson Bayou Depth) • Geophysical Survey (Hudson Bayou Subsurface Mapping) • Seismic Refraction Survey (Hudson Bayou Bridge)

• Adequate Pipe Material • Polymer Concrete

• MT Equipment Selection • Mixed Face Conditions • Specify Lubrication Needs • Intermediate Jacking Stations

• National Microtunneling Specialists

Page 21: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Lift Station 87 - Design

Underground Vault Cannot Support Traffic Load

Full Pipe Flow (Submerged Flow Conditions)

Odor Control Structure Access

Lower Wetwell Elevation

Access Hatch Covers Leak

Page 22: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Lift Station 87 - Safety

Limited Communication Between Underground Structures

Access Hatches Do Not Have Adequate Fall Prevention

No Above Ground Indication of Hydrogen Sulfide Gas

Page 23: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

What is Team Doing Differently?

• Advanced Geotechnical Techniques

• Transparent Process

• Pro-Active Public Outreach

• National Design and Construction Expertise

• Fiscally and Environmentally Responsible Approach

• Listening to the Public

Experience + Teamwork = Risk Management

Page 24: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Schedule

Page 25: PUBLIC MEETING - City of Sarasota Lift Station 87 Projectliftstation87.com/.../12/Public-Meeting-Presentation-12.18.2013-.pdf · PUBLIC MEETING December 18, 2013. Hudson Bayou Crossing

Questions & Answers

• Protect the City’s Investment

• Protect the Environment

• Improve System Reliability