public meeting presentation, 21 july 2020jul 21, 2020  · chambers street side. chambers street...

72
July 21, 2020 Public Meeting The current proposal is: Preservation Department Item 1, LPC-20-08010 49-51 Chambers Street, Borough of Manhattan Note: this is a Public Meeting item. No public testimony will be received today as the hearing on this item is closed

Upload: others

Post on 22-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

Name of Landmark Building

Type of Presentation Month xx, year July 21, 2020

Public Meeting

The current proposal is:

Preservation Department – Item 1, LPC-20-08010

49-51 Chambers Street, Borough of Manhattan

Note: this is a Public Meeting item. No public testimony will be received today as the hearing

on this item is closed

Page 2: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

Culturespaces + IMG

Hall des Lumieres

Creating a Culturespaces Digital® Art Center in New York with Immersive Exhibitions

51 Chambers Street - Emigrant Savings Bank BuildingPublic Meeting Presentation, 21 July 2020

Page 3: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

200 51 CHAMBERS STREET | HALL DES LUMIERES

01.1 Emigrant Industrial Savings Bank

LOCATION:51 Chambers St

BUILT:1909-1912

ARCHITECT:Raymond F. Almirall

HISTORIC EXISTING MAP OF LOWER MANHATTAN

SITE

CHAMBERS STREET

READE STREET

Page 4: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

300 51 CHAMBERS STREET | HALL DES LUMIERES

01.1 51 Chambers - Interior Historic Images

1913 TELLER WINDOWS - 1913

Page 5: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

400 51 CHAMBERS STREET | HALL DES LUMIERES

01.2 Culturespaces Digital: An Innovative Concept for Digital Exhibitions

Before + After Comparison

Carrieres De LumieresBaux-de-Provence, France

Former Stone Quarry

BEFORE AFTER

Page 6: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

500 51 CHAMBERS STREET | HALL DES LUMIERES

01.2 Culturespaces Digital: An Innovative Concept for Digital Exhibitions

Before + After Comparison

49 ChambersNew York, NY

Former Emigrant Industrial Savings Bank

How it Happens:The Exhibition Loop

1. Teaser reminiscent of the space's past2. Long Exhibition3. Short Exhibiton4. Architectural Lighting

Duration: 1 hour 15 minutes

BEFORE AFTER

Page 7: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

600 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.3 Previous Proposal

VIEW OF PROPOSED EXHIBITION SPACE

Blocking of windows

Treatment of new construction (boxes)

Reuse of historic material

Extent of exterior signage

1

2

3

4

1

2 3

GIFT SHOP/EXIT

COAT ROOM/TICKETING AREA

ENTRANCE

WOMEN'SRESTROOM

MEN'SR.R.

LIFTSTORAGE

OFFICE

EXHIBITPANELS

STORAGE

Commissioner Comments:

Page 8: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

700 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.3 Revised Proposal

VIEW OF PROPOSED EXHIBITION SPACE

2

3

1

2

3

1Responses:

4

Introduce interior curtain system to control light and sound. Chambers Street windows to remain uncovered at all times.

Eliminate new construction within designated areas.

All historic material to be removed will be salvaged and stored on site. No reuse.

Reduce signage on Chambers Street.

Page 9: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

800 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.3 Revised Proposal

VIEW OF PROPOSED EXHIBITION SPACE

32

1

Responses:

2

3

1

4

Introduce interior curtain system to control light and sound. Chambers Street windows to remain uncovered at all times.

Eliminate new construction within designated areas.

All historic material to be removed will be salvaged and stored on site. No reuse.

Reduce signage on Chambers Street.

Page 10: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

WOODS BAGOT 900 51 CHAMBERS STREET | HALL DES LUMIERES

EXISTING GROUND FLOOR PREVIOUS PROPOSED GROUND FLOOR

GIFT SHOP/EXIT

COAT ROOM/TICKETING AREA

ENTRANCE

WOMEN'SRESTROOM

MEN'SR.R.

LIFTSTORAGE

OFFICE

EXHIBITPANELS

STORAGE

01.4 Hall des Lumieres - Exhibit Overview

REVISED PROPOSED GROUND FLOOR

1

LANDMARK DESIGNATED AREA

PROPOSED SCOPE

Page 11: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1000 51 CHAMBERS STREET | HALL DES LUMIERES

01.5 Central Curtain - Roller Structure and Curtain Tracks

KEY PLAN

B

B

C

C

COUPE B-B

COUPE C-C

L'utilisation et la reproduction de ce document ne peut etre faite qu'avec l'autorisation écrite de la société Crystal Group (loi du 11 mars 1957 article 3)The use and reproduction of this document can only be made with the written permission of the Crystal-Group compagny (Act of the 11 march 1957/ section 3)

Qty:Mat.:

Format:

Ech/scale:1Culturespaces Nom /Name:

C:\Users\fabri\Documents\TRAVAIL FC\2020\20 - CULTURE ESPACE\

Chamber street 29-06-20 V6Unit:

Page:

Rev. :A

F.C.A3

mm1:100

1Kg

/ 1

29/06/2020

CENTRAL CURTAINCENTRAL CURTAIN ELEVATION

Roller and Truss1

1Curtain Track2

2

2

1

1 Detail on pg.11

Page 12: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1100 51 CHAMBERS STREET | HALL DES LUMIERES

01.5 Central Curtain - Structural details

KEY PLANCURTAIN REWINDER - METAL STRUCTURE DETAIL @ CORNICE

Curtain roller and truss attached to building structure.

1

Curtain track and enclosure attached to masonry wall at mortar joints only.To be scribed around decorative architectural features.

21

2

EXISTING CORNICE TRENCH/CONDUIT OPENING TO REMAIN

CURTAIN TO BE SCRIBED AROUND DECORATIVE ARCHITECTURE FEATURES

EXISTING CORNICE TO REMAIN

GYP. ENCLOSURE ATTACHED TO TRUSS. MATCH STONE COLORATTACHMENT AT MASONRY JOINTS, VIF

LIGHTING TRUSS

ATTACHMENT AT MASONRY JOINTS, VIF

Page 13: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1200 51 CHAMBERS STREET | HALL DES LUMIERES

01.5 Central Curtain - Detail of Curtain Tracks and Enclosures

CURTAIN TRACK AND ENCLOSURE, WITH BRONZE FINISH. ATTACH TO MASONRY AT MORTAR JOINTS ONLY.

Page 14: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1300 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.3 Central Curtain - Revised Proposal

VIEW OF PROPOSED EXHIBITION SPACE

1 Bronze-finished enclosure for curtain system.

Enclosure to be scribed to follow the architectural details, and attached at mortar joints only with masony anchors.

1

Page 15: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1400 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.5 Curtain System - Revised Proposal

Page 16: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1500 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.5 Curtain System - Revised Proposal

Page 17: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1600 51 CHAMBERS STREET | HALL DES LUMIERES

01.5 Side Curtains - Structural Details

WEIGHT OF THE STRUCTURE - CURTAINS

Weight of the structure = 120 kgWeight of the curtains = 200 kg

Total = 320 kg

WEIGHT OF THE STRUCTURE - CURTAINS

Weight of the structure = 80 kgWeight of the curtains = 350 kg

Total = 430 kg (without the decorative formwork)

PLAN OF THE SIDE CURTAIN STRUCTURE - ABOVE THE CORNICE LEVEL

KEY PLAN

Page 18: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1700 51 CHAMBERS STREET | HALL DES LUMIERES

01.5 51 Chambers - Existing Conditions

Page 19: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1800 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.5 Curtain System - Revised Proposal

Page 20: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

1900 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.5 Curtain System - Revised Proposal

Page 21: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2000 51 CHAMBERS STREET | HALL DES LUMIERES

01.6 Plans - Revised removal of historic fabric and insertion of boxes

EXISTING GROUND FLOOR PREVIOUS PROPOSED GROUND FLOOR

GIFT SHOP/EXIT

COAT ROOM/TICKETING AREA

ENTRANCE

WOMEN'SRESTROOM

MEN'SR.R.

LIFTSTORAGE

OFFICE

EXHIBITPANELS

STORAGE

REVISED PROPOSED GROUND FLOOR

NEW CONSTRUCTION

REMOVAL

GIFT SHOP/EXIT

COAT ROOM/TICKETING AREA

ENTRANCE

WOMEN'SRESTROOM

MEN'SR.R.

LIFTSTORAGE

OFFICE

EXHIBITPANELS

STORAGE

Page 22: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2100 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.7 Mezzanine Viewing Platform - Existing

CURRENT INTERIOR CONDITIONS

Page 23: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2200 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

01.7 Mezzanine Viewing Platform and Elevator - Previous Proposal

PROPOSED MEZZANINE

Page 24: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2300 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN PROPOSED MEZZANINE

01.7 Mezzanine Viewing Platform and Elevator - Revised Proposal

1 Plaster cornice detailing on drywall.

1

Page 25: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3

2400 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

Muntin Grid Metal to match existing window metal.

Gyp. to be painted neutral light grey on inside face.

01.8 Main Exhibit Space - Reade Street Window Cover

1 DETAIL OF ELEVATION @ PROPOSED NORTH WALL 3 MUNTIN DETAIL AT SECTION @ PROPOSED NORTH WALL 3"=1' SCALE

PROPOSED MTL. FRAMED WALL W/ GYP. BD. TO BLOCK LIGHT + SOUND.

OUTSIDE INSIDE

NEW MUNTIN GRID ADDED

2 SECTION

1

1

EXISTING WINDOW

LIGHT GREY PAINTED INTERIOR

BLACK PAINTED EXTERIOR

Page 26: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2500 51 CHAMBERS STREET | HALL DES LUMIERES

02.0 Exterior Alterations - Chambers Street Existing Elevation

EXISTING CHAMBERS STREET FACADE EXISTING CHAMBERS STREET FACADE

Page 27: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2600 51 CHAMBERS STREET | HALL DES LUMIERES

02.0 Exterior Alterations - Chambers Street Previous Elevation

EXISTING CHAMBERS STREET FACADE PROPOSED CHAMBERS STREET FACADE

Page 28: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2700 51 CHAMBERS STREET | HALL DES LUMIERES

02.0 Exterior Alterations - Chambers Street Revised Elevation

EXISTING CHAMBERS STREET FACADE PROPOSED CHAMBERS STREET FACADE

Page 29: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2800 51 CHAMBERS STREET | HALL DES LUMIERES

02.0 Exterior Alterations - Chambers Street Proposed Signage Details

1 PROPOSED CHAMBERS STREET ELEVATION

FABRIC MESH BANNER, VINYL IMAGE

ATTACHMENT AT MASONRY JOINTS (V.I.F.)

MTL. PLATE W/ POST

2

FABRIC MESH BANNER, VINYL IMAGE

ATTACHMENT AT MASONRY JOINTS (V.I.F.)

MTL. PLATE W/ POST

3

2

3 ELEVATION @ PROPOSED BANNER2 SECTION @ PROPOSED BANNER

8"

8" 2"

Page 30: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

2900 51 CHAMBERS STREET | HALL DES LUMIERES

02.0 Exterior Alterations - Chambers Street Proposed Signage Details

We would like to keep this sign. We willuse this type of hook, a pressure systemthat has no impact on the building. Wealready used this type of system in ourlandmarked building in France to preservethe architecture

1 PROPOSED CHAMBERS STREET ELEVATION

22

2 BANNER PRESSURE SYSTEM OF PROPOSED BANNER

3 DETAIL OF THE 2 SUPPORTING PRESSURE BARS

PROVIDE POWER AT MASONY JOINT.

Page 31: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3000 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

03.0 Main Exhibit Space

Page 32: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3100 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

03.0 Main Exhibit Space

Page 33: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3200 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

03.1 Main Exhibit Space

Page 34: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3300 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

03.1 Main Exhibit Space

Page 35: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3400 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

03.2 Main Exhibit Space - Proposed

VIEW OF EXHIBITION SPACE

Page 36: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3500 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

03.2 Main Exhibit Space - Proposed with Digital Art

VIEW OF EXHIBITION SPACE

Page 37: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3600 51 CHAMBERS STREET | HALL DES LUMIERES

THANK YOU

Page 38: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

Name of Landmark Building

Type of Presentation Month xx, year July 21, 2020

Public Meeting

The current proposal is:

Preservation Department – Item 1, LPC-20-08010

49-51 Chambers Street, Borough of Manhattan

Note: this is a Public Meeting item. No public testimony will be received today as the hearing

on this item is closed

Page 39: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3700 51 CHAMBERS STREET | HALL DES LUMIERES

51 ChambersAppendix

04

Page 40: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3800 51 CHAMBERS STREET | HALL DES LUMIERES

04.1 51 Chambers - Existing Conditions

1

1

Page 41: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

3900 51 CHAMBERS STREET | HALL DES LUMIERES

04.1 51 Chambers - Existing Conditions

2

2

Page 42: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4000 51 CHAMBERS STREET | HALL DES LUMIERES

04.1 51 Chambers - Existing Conditions

3

3

Page 43: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4100 51 CHAMBERS STREET | HALL DES LUMIERES

04.1 51 Chambers - Existing Conditions

4

4

Page 44: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4200 51 CHAMBERS STREET | HALL DES LUMIERES

04.1 51 Chambers - Existing Conditions

2

5

5

Page 45: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4300 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.2 Exhibit Entrance / Ticketing Area - Proposed Openings

1 EXISTING ELEVATION @ WEST BANK HALL WALL

2 PROPOSED ELEVATION @ WEST BANK HALL WALL

LINE OF PROPOSED ROOM ENCLOSURE

PROVIDE NEW OPENING FOR ENTRANCE TO EXHIBIT

REMOVE EXISTING ORNAMENTAL PIECE

PROVIDE NEW OPENING FOR STAFF ENTRANCE TO EXHIBIT

PROVIDE NEW OPENING FOR INSTALLATION OF DOOR TO LIFT STORAGE ROOM

PROPOSED

OPENING

PROPOSED

OPENINGPROPOSED

OPENING

1

Page 46: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4400 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.2 Exhibit Entrance / Ticketing Area - Proposed Openings

2 TYPICAL PLAN DETAIL @ PROPOSED OPENING

EXISTING WALL

LINE OF FINISHED CEILING

NEW ROOM ENCLOSURE CEILING ASSEMBLY

LINE OF WALL BEYOND

1

ENTRANCE/TICKETING

ROOM

51 CHAMBERS

EXISTING LOBBY

ENTRANCE/TICKETING ROOM

51 CHAMBERS

EXISTING LOBBY

EXISTING WALL

INSTALL NEW STONE TO COVER NEW OPENING

NEW PARTITION / ROOM ENCLOSURE FOR ENTRANCE/TICKETING ROOM

1 ELEVATION @ PROPOSED OPENING 2 SECTION DETAIL @ PROPOSED OPENING

3

2

51 CHAMBERS

EXISTING LOBBY BEYOND

Page 47: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4500 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

1

1 EXISTING ELEVATION @ FRONT TELLERS

1b PROPOSED ELEVATION @ FRONT TELLERS

2 EXISTING PHOTO @ FRONT TELLERS

2b PROPOSED OPENINGS @ FRONT TELLERS

LINE OF PROPOSED ROOM ENCLOSURE

REMOVE EXISTING ORNAMENTAL SHELL & SAVE FOR FUTURE REINSTALLATION

REMOVE TELLER WINDOW, DOOR, AND STONE KNEE WALL IN THEIR ENTIRETY. SALVAGE & STORE ON SITE. REMOVE EXISTING STONE TRANSOM & SAVE. RE-FINISH SIDES OF OPENING & UNDERSIDE OF TRANSOM WITH NEW STONE TO MATCH EXISTING.

04.2 Exhibit Entrance / Ticketing Area - Proposed Teller Window Openings

1

Page 48: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4600 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.2 Teller Window Openings

1

1 EXISTING ELEVATION @ WEST BANK HALL WALL

1b PROPOSED ELEVATION @ WEST BANK HALL WALL

WHERE SHELL ORNAMENTAL PIECES ARE DAMAGED, REPLACE WITH NEW STONE SHELL ORNAMENTAL PIECES.

REMOVE BANK TELLERS IN THEIR ENTIRETY. SALVAGE & STORE ON SITE.

2 EXISTING PHOTO @ WEST TELLERS

2b PROPOSED PHOTO @ WEST TELLERS

Page 49: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4700 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.2 Teller Window Openings

11

REMOVE TELLER WINDOW, DOOR, AND STONE KNEE WALL IN THEIR ENTIRETY. SALVAGE & STORE ON SITE. EXISTING STONE TRANSOM TO REMAIN. RE-FINISH SIDES OF OPENING & UNDERSIDE OF TRANSOM WITH EXISTING STONE OR NEW STONE TO MATCH EXISTING.

1 EXISTING ELEVATION @ NORTH BANK TELLERS

1b PROPOSED ELEVATION @ NORTH BANK TELLERS

2 EXISTING PHOTO @ NORTH TELLERS

2b EXISTING PHOTO @ NORTH TELLERS

Page 50: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4800 51 CHAMBERS STREET | HALL DES LUMIERES

04.3 Approved Bank Hall Adaptations - One Hanson Place

ONE HANSON PLACE - BANKING FLOOR 1929 ONE HANSON PLACE - BANKING FLOOR 2019

LOCATION:1 Hanson PlaceBrooklyn, NY

LANDMARK INTERIOR - APPROVED MODIFICATIONS

One Hanson PlaceAcheson DoylePartners Architects Page 19January 10th, 2017

PROPOSED CONDITIONS - BANKING HALL

Page 51: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

4900 51 CHAMBERS STREET | HALL DES LUMIERES

04.4 Reference - Williamsburgh Savings

MODIFIED TELLER SCREEN DETAIL AT MODIFIED TELLER SCREEN.

LOCATION:175 BroadwayBrooklyn, NY

Page 52: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5000 51 CHAMBERS STREET | HALL DES LUMIERES

04.5 AudioVisual Equipment - Truss Locations + Attachment Detail

ATTACHMENT DETAIL @ CORNICE

CORNICE PLAN

ATTACHMENT AT MASONRY JOINTS (V.I.F.)

EXISTING CORNICE TRENCH / CONDUIT OPENING TO REMAIN

EXISTING CORNICE TO REMAIN

1

1 ELEVATION @ TYPICAL AV TRUSSWIRE MOULDING

SURFACE MOUNTED SPEAKER+ SUBWOOFER

VIDEO PROJECTOR (EXACT QUANTITY + LOCATIONS TBD)

TRUSS

2a

METAL FASCIA ATTACHED TO TRUSS. COLOR TO MATCH STONE

AV EQUIPMENT

LIGHTING TRUSS

METAL FASCIA

2a 2b

2b

Page 53: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5100 51 CHAMBERS STREET | HALL DES LUMIERES

SPOTLIGHTS HIGHLIGHTING VAULTED CEILING

SPOTLIGHTS HIGHLIGHTING ARCHITECTURAL FEATURES

LIGHT FIXTURE HIGHLIGHTING WINDOWS

LINEAR LED LIGHTING HIGHLIGHTING VAULTED CEILINGS

04.5 AudioVisual Equipment - Typical Truss Equipment Types + Layout

PROPOSED TRUSS EQUIPMENT PLAN

VIDEO PROJECTOR

INDICATES TRUSS LOCATIONS

Page 54: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5200 51 CHAMBERS STREET | HALL DES LUMIERES

PROPOSED LIGHTING PLAN

EXISTING CHANDELIER (LANDMARK DESIGNATED)

RAISE HEIGHTREPLACE EXISTING LIGHT SOURCE WITH LED

EXISTING CHANDELIER (NON-HISTORIC)

TO BE REMOVED

04.5 AudioVisual Equipment - Architectural Lighting

Page 55: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5300 51 CHAMBERS STREET | HALL DES LUMIERES

SPEAKER INSTALLATION WITH FASTENERNOTE: ATTACHMENT POINTS TO BE LOCATED AT MASONRY JOINT LINES

ATTACHMENT PIECE

WIRE MOULDING

VERTICAL SPEAKER MODEL

FIXTURE AT EXISTING HANDRAIL

04.5 AudioVisual Equipment - Architectural Modifications

PROPOSED EQUIPMENT PLAN

Page 56: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5400 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

1

1 SECTION AT BATHROOM / MEZZANINE ENCLOSURE

EXISTING BANK TELLER TO REMAIN.CLEAN & REPAIR AS REQUIRED

04.6 Mezzanine Viewing Platform - Proposed Room Enclosure / Platform Details

2" GAP +/- 8'-0" B.O. FINISHED

CEILING

EXISTING WINDOW TO REMAIN

1" GAP TO BE MAINTAINED BETWEEN EXISTING WALLS AND INSIDE FACE OF NEW PARTITION (TYP.)

+/- 2'-0" CEILING/FLOOR ASSEMBLY

+/- 10'-0"TOP OF ENCLOSURE

RESTROOMS

ALL EXPOSED SURFACES @ NEW ROOM ENCLOSURES TO BE GYP. BD. PAINTED BEIGE TO MATCH EXISTING HISTORIC STONE (TYP.)

MEZZANINE

EXTERIOR BUILDING WALL

TOP OF BUILD OUT TO MEET BOTTOM OF FRIEZE BEYOND

PROPOSED LOUVER TO EXHAUST NEW RESTROOMS

PROPOSED PARTITION WINDOW COVERING

READE STREETLIGHTING

Page 57: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5500 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

1 ELEVATION AT PROPOSED LOUVER

04.6 Mezzanine Viewing Platform - Proposed Louver Details

KBAN

ARCHITECT OF RECORDWoods Bagot30 Broad Street, 7th Floor t.: 646-756-3300New York, NY 10004 f.: 646-756-3301

LANDMARKS CONSULTANTHIGGINS QUASEBARTH & PARTNERS, LLC11 Hanover Square16th Floor t.: 212-274-9468New York, NY 10005 f.: 212-274-9380

STRUCTURAL ENGINEERWSP250 West 34th Street t.: 212-687-9888New York, NY 10119 f.: 646-487-5501

MEP/FP ENGINEERRyan Soames Engineering, PC242 West 30th Street t.:New York, NY 10001 f.:

EXPEDITORCrown80 Maiden Lane t.: 212-888-8334New York, NY 10038 f.:

NOT IN SCOPE

EXISTING TO REMAIN

EXISTING TO BE DEMOLISHED

NEW CONSTRUCTION

- ALL TEMPORARY INSTALLATIONS WILL BE REMOVEDAND ANY RESULTING DAMAGE TO HISTORIC FABRICWILL BE REPAIRED IN KIND.

- HOLES IN MASONRY WILL BE PATCHED WITH ARESTORATION PATCH MIX MATCHING THESURROUNDING MASONRY IN COLOR, TEXTURE,HISTORIC PROFILE AND TOOLING. 

- MISSING OR DAMAGED MASONRY UNITS WILL BEREPLACED IN KIND, WITH NEW MASONRY UNIT TOMATCH THE ADJACENT CLEANED STONE IN COLOR,TEXTURE AND PROFILE.

- HOLES IN DECORATIVE METAL WILL BE PATCHEDUSING AN EPOXY-BASED COMPOSITE REPAIRMATERIAL.

- ADHESIVES AND OTHER COATINGS WILL BEREMOVED FROM MASONRY WITH CHEMICALSTRIPPERS USING BY PROSOCO, DIEDRICH OREQUIVALENT, USING THE GENTLEST MEANS POSSIBLEFOR REMOVAL, WITH WATER PRESSURE RINSELIMITED TO 500 P.S.I.

- ALL HISTORIC MATERIAL WILL BE GIVEN A GENERALCLEANING USING LIGHT-DUTY DETERGENT BYPROSOCO, DIEDRICH OR EQUIVALENT.

1

PROPOSED LOUVER TO BE FLUSH MOUNTED, FINISH TO MATCH EXISTING WINDOW FRAME

EXISTING FACADE TO REMAIN, TYP.

EXISTING WINDOWS TO REMAIN, TYP.

REPAIR & PATCH FRAME AS REQUIRED AFTER LOUVER INSTALLATION IS REMOVED, TYP.

Page 58: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5600 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

CONVENIENCE STAIR

3 ELEVATION OF PROPOSED STAIRS

2 SECTION OF PROPOSED STAIRS

1 EXISTING CONDITION

04.7 Convenience Stair - Proposed

2

Page 59: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5700 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.7 Egress Stair - Existing Condition

EXISTING VIEW

Page 60: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5800 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.7 Egress Stair - Previously Proposed

EXISTING VIEW OF STAIRS

Page 61: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

5900 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.7 Egress Stair - Revised Proposed

EXISTING VIEW OF STAIRS

Page 62: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

HALL DESLUMIERES

6000 51 CHAMBERS STREET | HALL DES LUMIERES

04.8 Exterior Alterations - Chambers Street Proposed Exterior Architectural Lighting LED HIGHLIGHTING FACADE AND BANNERS

PROFILE SPOTLIGHTS HIGHLIGHTING ARCHITECTURAL FEATURES

PROPOSED CHAMBERS STREET FACADE LIGHTING LOCATIONS

ATTACHMENT DETAILS:

EXISTING TO REMAIN

6'-10"

22'-

5"

6'-10"

22'-

5"

6'-10"

6'-0

"

4"

1'-7" 7.5" 6"

7.5"

1.5"

10.5" 4.5"

2"

2.5" 4.5"

5.5"

2"

2

1 3

6'-10"

6'-0

"

3

1

3

Page 63: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6100 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

04.8 Exterior Alterations - Reade Street Proposed Egress Doors

KBAN

INSTALL NEW EGRESS DOOR IN PLACE OFEXISTING WINDOW. NEW DOOR TO MATCHEXISTING WINDOW.

KBAN

REMOVE EXISTING WINDOW.EXISTING BARS TO BE REMOVEDAND STORED ON SITE

REMOVE EXISTING WINDOW FORINSTALLATION OF LOUVER.

ARCHITECT OF RECORDWoods Bagot30 Broad Street, 7th Floor t.: 646-756-3300New York, NY 10004 f.: 646-756-3301

LANDMARKS CONSULTANTHIGGINS QUASEBARTH & PARTNERS, LLC11 Hanover Square16th Floor t.: 212-274-9468New York, NY 10005 f.: 212-274-9380

STRUCTURAL ENGINEERWSP250 West 34th Street t.: 212-687-9888New York, NY 10119 f.: 646-487-5501

MEP/FP ENGINEERRyan Soames Engineering, PC242 West 30th Street t.:New York, NY 10001 f.:

EXPEDITORCrown80 Maiden Lane t.: 212-888-8334New York, NY 10038 f.:

NOT IN SCOPE

EXISTING TO REMAIN

EXISTING TO BE DEMOLISHED

NEW CONSTRUCTION

- ALL TEMPORARY INSTALLATIONS WILL BE REMOVEDAND ANY RESULTING DAMAGE TO HISTORIC FABRICWILL BE REPAIRED IN KIND.

- HOLES IN MASONRY WILL BE PATCHED WITH ARESTORATION PATCH MIX MATCHING THESURROUNDING MASONRY IN COLOR, TEXTURE,HISTORIC PROFILE AND TOOLING. 

- MISSING OR DAMAGED MASONRY UNITS WILL BEREPLACED IN KIND, WITH NEW MASONRY UNIT TOMATCH THE ADJACENT CLEANED STONE IN COLOR,TEXTURE AND PROFILE.

- HOLES IN DECORATIVE METAL WILL BE PATCHEDUSING AN EPOXY-BASED COMPOSITE REPAIRMATERIAL.

- ADHESIVES AND OTHER COATINGS WILL BEREMOVED FROM MASONRY WITH CHEMICALSTRIPPERS USING BY PROSOCO, DIEDRICH OREQUIVALENT, USING THE GENTLEST MEANS POSSIBLEFOR REMOVAL, WITH WATER PRESSURE RINSELIMITED TO 500 P.S.I.

- ALL HISTORIC MATERIAL WILL BE GIVEN A GENERALCLEANING USING LIGHT-DUTY DETERGENT BYPROSOCO, DIEDRICH OR EQUIVALENT.

1 READE STREET ELEVATION

11

2 TYPICAL EXISTING WINDOW

1 EXISTING READE STREET FACADE

Page 64: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6200 51 CHAMBERS STREET | HALL DES LUMIERES

KEY PLAN

3 PROPOSED EGRESS DOOR*Bars to be stored on site

04.8 Exterior Alterations - Reade Street Proposed Egress Doors

KBAN

INSTALL NEW EGRESS DOOR IN PLACE OFEXISTING WINDOW. NEW DOOR TO MATCHEXISTING WINDOW.

KBAN

REMOVE EXISTING WINDOW.EXISTING BARS TO BE REMOVEDAND STORED ON SITE

REMOVE EXISTING WINDOW FORINSTALLATION OF LOUVER.

ARCHITECT OF RECORDWoods Bagot30 Broad Street, 7th Floor t.: 646-756-3300New York, NY 10004 f.: 646-756-3301

LANDMARKS CONSULTANTHIGGINS QUASEBARTH & PARTNERS, LLC11 Hanover Square16th Floor t.: 212-274-9468New York, NY 10005 f.: 212-274-9380

STRUCTURAL ENGINEERWSP250 West 34th Street t.: 212-687-9888New York, NY 10119 f.: 646-487-5501

MEP/FP ENGINEERRyan Soames Engineering, PC242 West 30th Street t.:New York, NY 10001 f.:

EXPEDITORCrown80 Maiden Lane t.: 212-888-8334New York, NY 10038 f.:

NOT IN SCOPE

EXISTING TO REMAIN

EXISTING TO BE DEMOLISHED

NEW CONSTRUCTION

- ALL TEMPORARY INSTALLATIONS WILL BE REMOVEDAND ANY RESULTING DAMAGE TO HISTORIC FABRICWILL BE REPAIRED IN KIND.

- HOLES IN MASONRY WILL BE PATCHED WITH ARESTORATION PATCH MIX MATCHING THESURROUNDING MASONRY IN COLOR, TEXTURE,HISTORIC PROFILE AND TOOLING. 

- MISSING OR DAMAGED MASONRY UNITS WILL BEREPLACED IN KIND, WITH NEW MASONRY UNIT TOMATCH THE ADJACENT CLEANED STONE IN COLOR,TEXTURE AND PROFILE.

- HOLES IN DECORATIVE METAL WILL BE PATCHEDUSING AN EPOXY-BASED COMPOSITE REPAIRMATERIAL.

- ADHESIVES AND OTHER COATINGS WILL BEREMOVED FROM MASONRY WITH CHEMICALSTRIPPERS USING BY PROSOCO, DIEDRICH OREQUIVALENT, USING THE GENTLEST MEANS POSSIBLEFOR REMOVAL, WITH WATER PRESSURE RINSELIMITED TO 500 P.S.I.

- ALL HISTORIC MATERIAL WILL BE GIVEN A GENERALCLEANING USING LIGHT-DUTY DETERGENT BYPROSOCO, DIEDRICH OR EQUIVALENT.

1 READE STREET ELEVATION

12

2 EXISTING WINDOW 4 SECTION @ PROPOSED EGRESS DOOR

5 PLAN @ PROPOSED EGRESS DOOR

4

5

OPAQUE GLASS

METAL DOOR + FRAME

Page 65: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6300 51 CHAMBERS STREET | HALL DES LUMIERES

EXISTING BASEMENT MEZZANINE PLAN

PROPOSED BASEMENT MEZZANINE PLAN

04.8 Exterior Alterations - Reade Street Proposed Egress Doors

Page 66: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6400 51 CHAMBERS STREET | HALL DES LUMIERES

EXISTING BASEMENT PLAN PROPOSED BASEMENT PLAN

04.9 Plans - Basement

Page 67: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6500 51 CHAMBERS STREET | HALL DES LUMIERES

EXISTING BASEMENT MEZZANINE PLAN

04.9 Plans - Basement Mezzanine

PROPOSED BASEMENT MEZZANINE PLAN

Page 68: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6600 51 CHAMBERS STREET | HALL DES LUMIERES

EXISTING GROUND FLOOR PLAN

04.9 Plans - Ground Floor

PROPOSED GROUND FLOOR PLAN

GIFT SHOP/EXIT

COAT ROOM/TICKETING AREA

ENTRANCE

WOMEN'SRESTROOM

MEN'SR.R.

LIFTSTORAGE

OFFICE

EXHIBITPANELS

STORAGE

Page 69: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6700 51 CHAMBERS STREET | HALL DES LUMIERES

04.9 Plans - Mezzanine

EXISTING MEZZANINE PLAN

PROPOSED MEZZANINE PLAN

Page 70: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

6800 51 CHAMBERS STREET | HALL DES LUMIERES

04.9 LED Embedded Handrails - Details

Page 71: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

01.7

69

Page 72: Public Meeting Presentation, 21 July 2020Jul 21, 2020  · Chambers Street side. Chambers Street windows are not blocked.-Banking hall entrance will be the main entrance to the exhibit

Name of Landmark Building

Type of Presentation Month xx, year July 21, 2020

Public Meeting

The current proposal is:

Preservation Department – Item 1, LPC-20-08010

49-51 Chambers Street, Borough of Manhattan

Note: this is a Public Meeting item. No public testimony will be received today as the hearing

on this item is closed