Presentation to

City of MilfordGreat Creek Outlet Improvements

Silver Sands State ParkNovember 14, 2013

Page 2: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Presentation Outline

• Site Setting• Project Background• Coastal Processes Evaluation Summary• Outlet Structure Alternatives Assessment• Recommended Alternative• Next Steps

Page 3: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

Page 4: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

CHARLES ISLAND

GREAT CREEK TIDE GATEAND OUTLET STRUCTUREGREAT CREEK TIDE GATEAND OUTLET STRUCTURE

PUBLIC BEACHPUBLIC BEACH

GREAT CREEK

PARK ENTRANCEPARK ENTRANCE

LONG ISLAND SOUNDLONG ISLAND SOUNDSILVER SANDSSTATE PARK

SILVER SANDSSTATE PARK

Page 5: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

250 FT x 16 FT x 5 FTCONCRETE BOX CULVERT

180 FT LONG TIMBERTRAINING WALLS

TIDE GATE STRUCTURETIDE GATE STRUCTURE

Page 6: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

Great Creek and Tide Gate Structure InletGreat Creek and Tide Gate Structure Inlet

Page 7: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

Tide Gate Structure (behind tree screen)Tide Gate Structure (behind tree screen)

Page 8: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

Tide GatesTide Gates

Page 9: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

Great Creek Outlet Structure (looking east)Great Creek Outlet Structure (looking east)

Page 10: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

Box Culvert Discharge PointBox Culvert Discharge Point

Page 11: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Site Setting

Great Creek Outlet Structure (looking northwest)Great Creek Outlet Structure (looking northwest)

Page 12: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Project Background

Page 13: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Project Background

• Damage occurred to outlet structure

Page 14: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Project Background

• DEEP temporarily repaired training wall– Tiebacks installed to new sheet pile deadman

Page 15: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Project Background

• Sinkholes continue to form after temporary repairs– Additional repairs made by DEEP

Page 16: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Project Background

• Tide gate structure inspected– Tide gates functioning properly– Minor repairs recommended

• Borings performed adjacent to the training walls– Dense sand and silt layer identified approx. 15’ deep– Makes driving conventional wooden piles difficult

• Coastal Engineering study performed

Page 17: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal ProcessesEvaluation Summary

Page 18: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

• Evaluate site-specific coastal processes• Improve structural stability of updrift

structure• Improve sediment bypassing• Reduce downdrift beach impacts• Minimize potential for flanking of

downdrift structure• Maintain inlet stability and maintenance• Minimize safety concerns

Page 19: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

1. Data Collection• Sediment samples• Beach profiles• Tidal currents and flux• Tide data• Existing wind and wave data

2. Coastal Processes Analysis and Modeling• Wave Transformation Modeling• Sediment Transport Modeling• Inlet Stability Analysis

3. Alternatives Analysis• Alternatives Considered• Sediment Distribution• Beach Nourishment Performance

Page 20: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

Page 21: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

TideGate(s)Close

After the tide gate(s) close, slowrise in water surface elevation

due to freshwater input

Page 22: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

The Bar

GreatCreekOutlet

CharlesIsland

MilfordHarborChannel

Simulation Cases• Annual Wave Conditions

(MHW, MTL, MLW)• Return Period and Historical

Storms (10-, 50-, 100-yearstorms and Hurricanes Irene[2011] and Gloria [1985])

• Sea Level Rise

Page 23: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

Page 24: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

Page 25: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

Nearshore Circulation- Physically-based representation- Driven by breaking waves in the surf zone- Based on Depth-averaged mass and

momentum- Provides stream function and vorticity

Page 26: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Coastal Processes Evaluation Summary

4 5 6 7

Average annual rate = 14,600 cy/yr to the east (near the outlet)*as long as sand is available

Page 27: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

AlternativesAssessment

Page 28: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Alternatives Assessment

• No action• Replacement in kind• Removal of training walls• Shortening of training walls• Tapering the elevation of training walls• Culvert extension• Culvert extension with training wall shortening• New outlet structure

Page 29: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Alternatives Assessment

• Balance of inlet stability and sediment bypassing

• Criteria Evaluated– Inlet stability– Downdrift beach– Cost– Service Life– Maintenance requirements– Safety– Modular design

Page 30: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Training Wall Adjustments

Evaluated a range of reductionsReduce length by 30 feet and/or taper slope over 100 feetAllows an additional 1,500-1,800 yd3/yr to naturally bypassMaintains stability of outlet

Page 31: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Culvert ExtensionExtend culvert and reduce training wallsAllows an additional 3,800 yd3/yr to naturally bypassMaintains stability of outlet

Page 32: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

RecommendedAlternative

Page 33: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Recommended Alternative

• Configuration based on Coastal Study– Shorten training walls by 30 feet– Extend box culvert to increase sediment transport

• Various training wall options explored1. Timber piles and lagging – Piles difficult to drive through

confining layer2. Steel sheet piling – Least aesthetically pleasing and difficult to

modify after installation3. Precast concrete piles and panels – Most expensive option

and difficult to modify after installation4. Steel piles with timber lagging – Deemed best compromise

on pile drivability, flexibility, aesthetics, and cost

Page 34: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Recommended Alternative

Existing Great Creek Outlet StructureExisting Great Creek Outlet Structure

Page 35: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Recommended Alternative

Proposed Great Creek Outlet StructureProposed Great Creek Outlet Structure

Page 36: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Next Steps

Page 37: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Next Steps

• Obtain State permits from the DEEP Office of the LongIsland Sound Programs (OLISP)– Project requires a Certificate of Permission (COP)

• Prepare Construction Documents• Solicit bids for proposed work• Hire a contractor• Begin construction

– May be restricted from working during certain times of year

Page 38: Public Presentation to the City of Milford, November 14, 2013

Presentation to City of Milford

Questions