PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE

DELIVERY

September November 06, 2010

Page 2: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Background

• New Policy and Strategy for Public-Private Partnership (PPP) was approved by the Cabinet and the gazette was published on August 02, 2010 and replaced BPSIG

• The Guidelines for large, medium and small projects have also been approved

Page 3: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Approach

• Definition: providing public goods and services using private

investment

• Office of the PPP: A strong and independent lead agency for

PPP under PMO, CEO directly reporting to the PM

• Streamlined and simplified process

– Formulation, appraisal, approval

• Empowered line Ministries/implementing agencies

• Flexibility: Generic Policy and Strategy has been proposed

and guidelines may be updated time to time based on the

needs and experience of implementation

• CCEA can specify guidelines

Page 4: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Policy and Strategy

• Sectoral coverage (SIC codes)– BOTH infrastructure and service delivery

• Investment size– Small (BDT <500 mil.), Med (BDT 500-2500 mil.), Large

(BDT >2500 mil.)

• Financial participation by government– 1. TA; 2. VGF; 3. Infrastructure Financing

• Linked components– Implemented by government– Financed by public and/or private funds

• Incentives to Private Investor– Fiscal and Special incentives, particularly for pro-poor

projects

Page 5: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Institutional Framework

Entity Chair ToR

PPPAC Prime Minister • Guide Office of PPP, line Ministries to expedite• Break down bottlenecks• Review progress at national level

CCEA Finance Minister

• Approve guidelines, procedures, model docs• Review contingent liability for Large projects• Approve incentives• Approve ‘In Principle’ for Med and Large; Approve Large• Approve org. structure of PPP Cell• Recommend PPP-related laws

Office of PPP

CEO • Prepare model docs and guidelines for approval• Promote PPP projects to investors• To select a panel of experts and transaction projects• Support line Ministries/impl. Agencies in formulation, pre-feasibility, feasibility, technical and contractual parameters• Build capacity of line Ministries/impl. Agencies on PPP• Monitor PPP projects• Prepare and manage budget of PPP Cell

Page 6: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Institutional Framework (cont.)

Entity ToR

Line Ministry/impl. agency

• Initiate, develop, pre-qualify, tender and award PPP projects• Oversee implementation based on concession agreements• Recommend incentives• Proactively involve Office of PPP for own capacity building

Finance Division • Issue procedures and guidelines for financial participation by the government• Approve funds for TA for proposed and VGF for selected projects based on concession agreements• Channelize funds for infrastructure financing

Planning Commission

• Fast-track Linked Components (part of ADP)• Review ADP to prevent duplication

Page 7: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Process by Size of Projects

L

M

OPPP

OPPP

OPPP

Page 8: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Process by Size of Projects

OPPP

Page 9: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Process by Size of Projects

OPPP

Page 10: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

OPPP

Page 11: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

• The government has taken a two-pronged strategy for building public-private partnership: – one is to attract investment for projects,

where building new infrastructure and expanding existing infrastructure is the major component; the

– second is to attract innovation and sustainability of public service delivery to the citizens.

PPP and e-Service Delivery

Page 12: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

PPP and e-Service Delivery

• Service Delivery was focused – Objective 2.a.: Spell out principles of partnership

with private sector for undertaking various projects related to infrastructure as well as public service delivery;

• Dominant role of private party is recognized– Concept of PPP 3.d: In the PPP projects, the

private sector is the active party who undertakes activities, depending on the model, starting from the stage of conception and up to the stage of operation and maintenance

Page 13: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Applicability of PPP

• Any project that generates public goods and services may be considered under the public-private partnership, if at least one of the following circumstances exist for the project :

1. The implementation of the project is difficult with the financial resources or expertise of the government alone;

2. Private investment would increase the quality or level of service or reduce the time to implement compared to what the government could accomplish on its own;

3. There is an opportunity for competition, where possible, among prospective private investors, which may reduce the cost of providing a public service;

4. Private investment in public service provides an opportunity for innovation; and

5. There are no regulatory or legislative restrictions in taking private investment in the delivery of public service.

Page 14: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Sectoral Coverage

• Any project fulfilling one or more of above-mentioned applicability criteria in any economic sector, according to the International Standard Industrial Classification (ISIC) of all Economic Activities, Revision 4, specified by the United Nations, is eligible for PPP.– 5.k: Telecommunication systems, networks and services

including information and communication technology (ICT) (ISIC 60-63)

– 5. n: IT park (ISIC 81-82)– 5.o: social infrastructure e.g. health, education, human

resource development, research and development, and cultural facilities, (ISIC 85-88)

– 5.p: e-service delivery to citizens (ISIC 85)– 5. q.iii: Rural Internet projects (ISIC 61)

Page 15: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Eligibility Criteria

• Any for-profit or not-for-profit entity legally registered in Bangladesh or abroad at the time of submission of proposals in response to Request for Qualification or unsolicited proposals is eligible for participation in PPP projects.

• However, at the time of contract awarding, the foreign entity is required to be registered as a legal entity in Bangladesh

Page 16: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Investment Size and Ease of Processing

• Small: ICT Projects fit mostly in this category– BDT <500 million– Approval Authority: Line Minister– No RFQ Stage– Maximum 7 months for approval

Proactive role of a Ministry will be key

Page 17: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Financial participation of the Government

• Technical Assistance– Pre-feasibility and Feasibility study for projects– Preparation of RFQ and REP documents for

projects– Preparation of concession contracts for projects– PPP related capacity building in the line

Ministries/implementing agencies and other relevant agencies

– PPP related awareness building such as road show, exhibition etc

Page 18: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Financial participation of the Government

• Viability Gap Financing– Viability Gap Financing (VGF) is meant for

projects where financial viability is not ensured but their economic and social viability is high.

– VGF could be in the form of capital grant or annuity payment or in both forms

– VGF in the form of capital grant shall be disbursed only after the private sector company has subscribed and expended the equity contribution required for the project.

Rural Internet, ICT Education, Public Access to ICT, Poverty Alleviation Projects

Page 19: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Fiscal Incentives

• Reduced import tax on capital items under PPP projects

• Tax exemption or reduced tax on profit from operating/managing for a specific time period

• Others specified by LM/ IA

Page 20: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Special Incentives

• Any specific project may get special unique incentives with the approval of the CCEA which shall be declared in the RFP documents.

• Special incentives may be extended to PPP projects targeted for rural or/and underprivileged population

• Special incentives may be given to non-resident Bangladeshis (NRBs) to invest in PPP projects.

Page 21: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Financial participation of the Government

• Infrastructure Financing – The infrastructure financing is an

arrangement for extending financing facilities for the PPP projects in the form of debt or equity through specialized financial institutions

Page 22: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Suitable Models for ICT

• Swiss Challenge: Protecting IPR

Page 23: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Procurement Parameters of ICT Projects under PPP

Revenue Generation Potential

Selection Criteria

Services with full cost recovery

Highest Composite Index on KPI

Lowest cost Highest revenue sharing

Services with partial cost recovery ( in many cases, fixed cost recovery is not possible)

Highest Composite Index on KPI

Highest fixed cost investment by private sector

Public good ( citizens' entitlement)

Total lowest recurring cost

Page 24: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Business Models for PPP in ICT

E-service domain Project financing mechanism Returns to the private partner

Tax and CustomsUser charges as fees for service enhancement

from citizens and businesses% Share of the fees,

per transaction

% share of additional revenues made possible by improved audit and collection programs

e-Procurement

User charges as fees for service enhancement from participating government agencies, subscription fees from prospective suppliers

% share of the amount of bid (with an

upper cap on the total amount)

% share of the subscription amount

Certification and Licensing

User charges as fees for service enhancement from citizens and businesses (in addition to the usual fees charged for issuing certificates and licenses)

% share of the service enhancement fees

--

Social Benefits Related

Viability gap fundingUser charges as fees for service enhancement

from the government

% share of the service enhancement fees, per distribution

--

Health and Education

Viability gap fundingUser charges as fees for service enhancement

from the government

% share of the service enhancement fees,

per distribution--

Source: Evalueserve Research

Page 25: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010

Priority in PPP [WB, 2007]ICT Projects BCS BASIS

Interested in PPP Priority Interested in PPP Priority

G2C

Tax related ▲▲ ▲▲▲

Social Benefits related ▲▲ ▲▲▲

Property related ▲▲ ▲▲▲

Agriculture related ▲▲▲ ▲▲▲

Education based ▲▲▲ ▲▲▲

Health based ▲▲▲ ▲▲▲

Tourism related ▲▲ x --

G2B

Tax related ▲▲▲ ▲▲▲

Corporate Compliance related ▲▲▲ ▲▲▲

e-Procurement ▲▲▲ ▲▲▲

Auctions ▲▲ ▲▲

Treasury Automation ▲▲ ▲▲

Page 26: PUBLIC PRIVATE PARTNERSHIP FRAMEWORK FOR E-SERVICE DELIVERY September November 06, 2010