    PURCHASE POLICY

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    2/20

    4

    Table of Contents

    Policy

    Authorized Department For Purchase

    Selection Of Supplier

    Basis Of Purchase

    Forms

    Minor Purchases

    Verbal Quotations

    Written Quotations

    Exceptions

    Responsibilities Of Various Departments Involved In Procurement Procedure

    User Department

    Budget Department

    Purchase Department

    Finance Department

    Guideline And Procedures For Making A Purchase

    Purchase Requisition

    Purchase Order

    Acceptance Of Goods & Services

    Policy For Specific Areas Of Procurement

    IT Procurement

    Travel

    International Travel

    Local Travel

    Stationery

    Consultancy Service Procurement

    Administrative Purchases (Car Maintenance)

    C&F Agent

    Media Buying And Agency Fixation

    Packaging Materials

    Appendices

    PURCHASING POLICY AND GUIDELINE

    POLICY

    Authorized Department for Purchase:

    Procurement of Goods and Services (Excluding Raw Materials for Milk Powder) for the Company will be conducted

    through the Procurement Department. Such Procurement shall be made in conjunction with the Department

    requesting the Goods or Service (User Department), Procurement Department and if required, any other person

    Technically Competent for the purchase of the required item.

    Selection of Supplier:

    Wherever possible, Companys Policy is to purchase directly from manufacturers or officially accredited dealers / main

    suppliers in order to ensure that the goods purchased are of the desired quality at a competitive price and where

    appropriate, the after sales service meets the company standards.

    Basis of Purchase:

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    3/20

    4

    The Procurement Department shall proceed with the procurement process only once they receive a Completed and

    Approved Purchase Requisition Form in a prescribed format.

    Authority to approve the Purchase Requisitions to process for Purchase Order is attached in Appendix A, which may

    be subject to periodic review and change by the Managing Director.

    There are some circumstances where the raising of a Purchase Requisition is irrelevant or impractical. These items

    are detailed in Appendix D of this document, which may be also subject to periodic review and change by the

    Managing Director.

    Forms:

    For any purchase / services, the types of forms are as follows:

    a. Purchase Requisition Form.

    b. Comparative Statement Form.

    c. Purchase Order Form.

    d. Car Maintenance Requisition Form.

    e. Travel Authority Form.

    f. Capital Item Requisit ion Form.

    Minor Purchases:

    To ensure smooth operation of business, when time is crucial than money, in this cases the following mentioned

    departments are allowed to purchases in cash without having to go through the formal Purchasing Procedure (Pre-

    Approval of PR) and Procurement Department.

    But Post Approval through raising PR should be made in this connection to the Minor Purchase (within 15 days of the

    purchase).

    The authorized departments and authority limit are as follows:

    1. Head of Finance - BDT 50,000.00

    2. Head of Production - BDT 25,000.00

    3. Head of Procurement - BDT 25,000.00

    4. Head of Marketing - BDT 10,000.00

    5. Head of Sales - BDT 10,000.00

    6. Head of Administration - BDT 10,000.00

    7. Head of Product Planning - BDT 10,000.00

    Verbal Quotations:

    Purchases with a total value up to BDT 50,000.00 (BDT Fifty thousand only) may be processed through obtaining

    verbal quotation from three reputable and reliable suppliers, evidenced in writing by the Procurement Department.

    Such offers must be evaluated by the Head of Procurement on the basis of price, quality, specification and other

    criteria before selection of the final supplier.

    Written Quotations:

    a. All purchases with a total value in between BDT 50,000.00 to BDT 150,000.00 (BDT One Hundred Fifty

    Thousand only) must be processed through the Procurement Department by obtaining at least one written

    quotation from reputable & reliable suppliers.

    All purchases with a total value in excess of BDT 150,000.00 (BDT One hundred fifty thousand only) must be

    processed through the Procurement Department by obtaining at least three written quotations from reputable &reliable suppliers. Such offers must be evaluated on the basis of price, quality, specification and other criteria

    before a final supplier selection.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    4/20

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    5/20

    4

    b. Where the products is available only from a monopoly/sole supplier. In this circumstance, it is incumbent upon

    the Procurement Department to make all out effort to find an alternative source of supply to reduce the

    companys reliance on one supplier.

    c. For procurement of certain goods and services, special arrangements will be put in place as detailed later in this

    document. These are detailed form section 5 to 11 of this document under the head Policy for Specific areas ofProcurement. This listing may be subject to periodic review by the Managing Director & Procurement Team.

    d. In certain circumstances, it may be necessary to issue a Letter of Intent in order to provide an element of

    conform whilst details are being finalized prior to the issue of Purchase Order. A Letter of Intent may only be

    approved by the Managing Director, or his authorized person in his absence.

    e. In the event of an emergency situation, i.e where time is more critical than cost, mainly related to factory safety

    or loss of production, or to ensure timely distribution, the procedure of obtaining quotes might be waived only

    with the approval of the Assistant Financial Controller or Managing Director or his nominated person at his

    absence.

    f. For RSOs any purchase exceeding BDT 5,000.00, (BDT Five thousand only) which is extremely critical and

    where it is not economically fruitful to purchase from HO, could be procured through RSOs with written/ e-mail

    approval from Head of Finance & Head of Sales in other cases where the value is higher than BDT 5,000.00

    (BDT Five thousand only) by the Managing Director.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    6/20

    4

    Responsibilities of Various Departments Involved in Procurement Procedure:

    For ensuring systematic purchase the related departments have to fulfill some duties which are detailed below:

    User Department:

    User department will raise the PR Form and will be liable for the followings:

    a. Fill up Purchase Requisition Form as per Company Procedure.

    - Put full description / specification of item, if available, provide sample of the product to

    Procurement Department along with the PR Form.

    - Write full justification for purchase including current stock levels, annual usage etc (if

    required)

    - Provide name of recommended suppliers (if any)

    - Put estimated value of the product in PR Form.

    - Put latest acceptable delivery date in PR Form.

    - Put Budget Code, Cost Centre in PR Form.

    b. Acceptance of Goods or Services after delivery / completion.

    c. Checking and Approving bills.

    (For service oriented procurements)

    Budget Department

    Budget Department will be liable for the following:-

    a. Checking Purchase Requisition form against Budget & Budget code, Items, Justification for Purchase,

    Estimated Value of the Product and match against Companys annual budget / specific program budget.

    b. Take Approval from authorized persons (Appendix - A) and forward to purchase department.

    Purchase Department:

    Purchase Department is responsible for commercial aspects of the purchase. i.e:-

    a. Identifying suitable suppliers for the required item.

    b. Obtaining quotations and agreeing final supplier selection in conjunction with the Requisitioning

    Department.

    c. Agreeing delivery terms & date with the suppliers.

    d. Agreeing Payment Terms & date with the suppliers.

    e. Raise PO with compliance with the Purchase Policy.

    f. Receiving Goods from Suppliers and handover to warehouse / user. (Except Factory Items & Services)

    g. Receive bills from suppliers and after initial checking process the bill in accordance with Companys

    Purchase Policy and submit to Finance.

    h. Should maintain & update a suppliers database with all details like name, address, correspondence

    number, products available etc.

    Finance Department

    Finance Department will be liable for the following:-

    a. Check whether the PO value is within 15% variance of the PRs approved value. (To be checked against individual

    items)b. Checking the accuracy of all documentation and matching of the invoice to the Purchase Requisition, Purchase Order

    and Material Received note, suppliers quotation etc.

    c. Ensuring the documents are appropriately authorized prior to presentation to Cheque signatories for payment.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    7/20

    4

    Level of Authority:

    Authority to process the various forms of Related to Procurement are defined hereunder:

    Authorization to process Purchase Requisition:

    Purchase Requisitions are approved Preliminary by the Departments Heads afterwards if the expenditure requested is

    a budgeted revenue expenditure, than Budget Department will forward the PR Form either to AFC or to Managing

    Director depending upon the total amount of the PR Form. A detailed flowchart is appended in Appexdix - A

    Authorization to process Comparative Statement:

    Comparative Statement is mandatory for any purchase over BDT 50,000.00, even if 3 quotations are not received.

    The authority level are of Signatories are attached in Appendix A.

    Authorization to process Purchase Orders:

    a) Purchase Orders with a total value up to BDT 500,000.00 (BDT Fifty thousand only) equivalent will be approved

    and signed by the Head of Procurement. Regarding factory purchase, if PO is required to be raised, the factory

    manager has the sole authority to sign the PO upto BDT 25,000.00 (BDT Twenty five thousand) maintaining the

    company norms & payment terms mentioned hereunder

    Purchase Orders Exceeding limit BDT 500,000.00 (BDT Five lakhs) up to BDT 10,00,000.00 (BDT Ten lacs)

    should be jointly signed by Assistant Financial Controller and any value over BDT 10,00,000.00 (Ten Lakhs)

    should be approved by the Managing Director or his authorized person in his absence.

    a) In absence of the Managing Director any purchase exceeding BDT 10,00,000.00 (BDT Two lacs) should be

    countered signed by both the Head of Procurement & nominated person of the Managing Director.

    b) In the rare case of absence Managing Director and any one of the procurement team alternative signatories

    might be assigned for the duration of absence, in written circular or mail to the related persons by the Managing

    Director.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    8/20

    4

    GUIDELINE AND PROCEDURES FOR MAKING A PURCHASE

    1. Purchase Requisition:

    Where there is a requirement to purchase goods or services, the user department shall complete the Purchase Requisition Form (Form

    on Appendix B) and submit it to the budget holder for initial approval.

    It should be noted that a full justification for the need to purchase should be given in the appropriate box. A list of budget holders is

    provided in Appendix C.

    After initial approval of the budget holder, the Purchase Requisition should be forwarded to the Budget Department for checking the

    budgetary allocation & availability.

    The Purchase Requisition for stock items such as packing foils for different SKUs, cartoon requirements & other packing materials

    should be raised at least two months before requirement from the department involved in supply & demand projection. A detailed

    procedure is elaborated in Section 12 of this manual.

    In case of adequate / surplus budget in the appropriate head, the authorization of processing the Purchase Requisition will be issued by

    the Budget Department by having signature as per the authority level detailed in Appendix A.

    Once appropriate approvals have been obtained, as evidenced in Section 1 of the Purchase Requisition, it should be forwarded to the

    Procurement Department for purchasing.

    Based on the nature and value of the proposed purchase request, the Procurement Department shall determine the mode and therefore

    the appropriate steps to be taken to proceed with the purchase as outlined in Section 1 of this document.

    Minor Purchases: As stated in Section 1.5 of this document, certain items which are not available in the warehouse /

    stores and the value of which does is up to BDT 10,000.00 (BDT Ten thousand) (User authorities are detailed in 1.5

    above)may be purchased directly by the user department in cash. It should be noted that, if desired the purchase

    might be made using Purchasing Department. For cash purchases, a purchase requisition form shall be completed by

    the individual making the request and approved by the Budget Holder against whose budget the item will be charged.

    Once approval is obtained the concerned official or purchasing department may buy from any shop/supplier obtaining

    a receipt as evidence. Re-imbursement of the sums expended will be made through the submission of an expenses

    statement, along with the approved Purchase Requisition form with initial from budget holder, to finance department.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    9/20

    4

    Procurement department should go for purchase if the initial PR value and the proposed PO value of the selected supplier is within

    10% variance of the proposed PR value. Otherwise the PR should be turned back to the Budget department for reallocating the

    budget with coordination with the user department.

    The Priority Rating in the PR should be mentioned following the criterias hereunder:

    1. High - From 3 - 7 working days2. Medium - From 8 15 working days

    3. Low - From 16-45 working days

    3 Purchase Order

    3.1 Once Purchase Requisition Form and Comparative Statement Form has been completed and authorized, (with the

    possible exception of Minor Purchases) Procurement Department will obtain quotations as dictated in paragraphs 1.6

    and 1.7 of this document to fulfill the purchase.

    3.2 Prices stated by the suppliers in their quotations must always be treated as the final price. Further negotiations should

    be entertained, if Hoed of Purchase feels so after written quote has been received.

    3.3 These quotes will be entered in the Comparative Statement Form and then approval will be obtained as per the

    authority level detailed in Annexure G.

    3.4 Every Purchase, with the exception of Minor Purchases as defined above, wil l be made through issue of a pre

    numbered Purchase Order. The number registrar of the purchase order should be maintained by the Procurement

    Department.

    3.5 The Purchase Order is an important document and should be issued with the utmost care. The Purchase Order is a

    legal document that, once signed by authorized official, constitutes a contract between the company and the Supplier

    or Service Provider. It creates a liability for the company and an obligation to pay. For this reason, it is paramount that

    the purchase order is clear and precise. It should detail exactly what is required by the by way, of description,

    manufacturers parts numbers, technical specifications, quantity, goods or service delivery date and price as agreed in

    the quotation. This list is not exhaustive. All relevant information, including technical drawings, where appropriate,

    should be provided.

    In addition, the full terms and conditions of supply should be stipulated on the purchase order.

    3.6 Payment terms are restricted to:-

    - Advance Payment (Limited Situations only) with approval from Managing Director.

    -Payment upon delivery. (limited situations only)

    - 15 days net. (small suppliers only)

    - 30 days net or longer (preferred terms)

    - Against Letter of Credit (overseas only)

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    10/20

    4

    - Progress payments (Restricted to projects)

    All the payments over BDT 10,000.00 (BDT Ten Thousand) are preferred to be made by Cheque with relaxation in few

    occasions subject to approval of the Head of Finance / Managing Director. But under no circumstances, payment over

    BDT 10,000.00 (BDT Ten thousand) will not be made in cash.

    3.7 Once the purchase order has been approved in accordance with paragraph 1.10 of this document, 3 copies should be

    distributes by purchasing department as follows:

    - Original to the supplier / Service Provider.

    - 1st Copy to the supplier / Service Provider for signature and acceptance and returned to the

    Procurement Department.

    - 2nd Copy to Finance Department.

    - 3rd Copy to User Department.

    - In case of involvement of the factory warehouse, a copy should be given to the warehouse.

    3.8 Procurement Department / Department engaged that specific purchase should ensure that the duplicate copy of the

    order is accepted and returned by the supplier without any changes.

    3.9 In the event that the suppliers request any changes to the Purchase Order, such changes will be only and only valid

    with the acceptance of the MD or authorized person in his absence.

    A sample Purchase Order format is presented in Appendix F.

    4 Acceptance of Goods & Services:

    4.1 Where it is possible & practicable, purchases should be inspected by the person requisitioning the item or the

    nominated person of the Budget Holder. Inspection by other departments may also be considered if appropriate.

    4.2 In case of delivery of sub-standard, defective, or non specified items, the company has the right to refuse delivery or

    return the goods, in whole or in part, at the suppliers expense. Considerations needed to be given whether purchase

    order remains valid for replacement or not.

    4.3 For work not done in accordance with specifications or sub-standard quality or poor workmanship, the same will not

    be certified for acceptance and the supplier will be required to rectify the defects within a certain period failing which

    the same will either be rectified by another supplier and costs deducted from the original suppliers invoice. If a

    decision is taken to accept the work/ supply of goods in defective condition, a pro-rata amount will be deducted from

    the suppliers invoice.

    4.4 Where contracted work requires technical or engineering adjustment prior and/ or subsequent to installation, the

    person in charge of the purchase or work should finalize the work prior to final payment.

    4.5 Purchases must be accompanied by instructions, operating and maintenance manuals where applicable. Users

    training & service contracts in appropriate cases should also be considered.

    Policy for Specific Areas of Procurement:

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    11/20

    4

    For various commercial and logistics reasons, purchase of certain goods and services that are best carried out by preferred

    suppliers basis. These types of procurement are detailed below along with the procedures and guideline governing the

    process of selection.

    5. IT Procurement:In order to ensure compatibility of IT equipments and or softwares a preferred supplier might be assigned and in this type of

    case relaxation for three quotations might be waived but with proper justification to Head of Finance & Head of Procurement.

    6. Travel:

    International Travel:

    All international travel on company business must to be approved by the Managing Director.

    A Purchase Requisition Form should be submitted to the Managing Director well advance of the expected travel date. The

    PR should be raised mentioning all the expenditures of the journey and approved in the above mentioned process.

    Once approval has been given a copy of the Purchase Requisition should be passed to the Corporate Office HR

    Department for processing flight booking, visa processing and other related travel documents through the company

    approved travel agent and also the Hotel Booking.

    Local travel:

    A travel authority form must be completed for all local travel prior to the journey commencing. The travel authority form must

    be approved by the appropriate Functional Head before submitting to the HR Department. A Purchase Requisition should be

    raised mentioning all the expenditures of the journey and approved in the above mentioned process.

    8 Stationery

    8.1 In order to provide a consistent and uniform high quality printed stationery, commensurate with the desired image the

    company wished to portray, one supplier who meets the required standards will be selected on value for money basis.

    8.2 An annual supply contract will be negotiated by the Procurement Department to provide the Companys total requirements

    both for Corporate Office, Factory, and Regional Sales Office.

    8.3 For non printed items, different number of suppliers might be utilized from time to time.

    8.4 Procurement of all the stationeries should be requested by the Administrative Department to the Procurement Department.

    9 Consultancy Service Procurement:

    9.1 Consultancy service procurement should be made in presence of the procurement team. The budget holders are authorized

    to give priority to any individual supplier/ consultant based on their quality of service and market reputation. But the

    procurement will be done after approval of all the members of the procurement team. The final approval of procuring such

    service is subject to approval of the Managing Director in the Consultancy Service Contract.

    9.2 Procurement of service related to HR for head hunting or other consultancy related to HR should also be finalized with

    approval of all the members of the procurement team. The final approval of procuring such service is subject to approval of

    the Managing Director in the service contract.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    12/20

    4

    10. Car Maintenance:

    Objective

    To facilitate repair and maintenance of Company Vehicles in order to ensure proper transportation service.

    Scope

    This procedure applies to all vehicles registered under company name, either used by Individuals or Company Pool Car / Microand Delivery Vans.

    Procedure

    Functions of repair and maintenance of Company vehicles will be done in coordination with the Vehicle users, Administration

    Department and Procurement Department. In case of Company Pool Car & Delivery Vans, Administration Department is

    considered as the user of those vehicles.

    The summarized roles of above three departments are mentioned hereunder:

    Vehicle Users:

    i. To fill Vehicle Maintenance Form (VMF) in case of regular maintenance and forward to Administration Department for

    database up-gradation and judge the necessity of the repair work.

    ii. To ensure proper service is availed from vendor.

    Administration Department:

    i . To receive VMF from var ious users and update the database.

    ii. Justify the maintenance and take necessary actions. (if accepted, and then send to vendor. If rejected then send back

    to user)

    iii. To follow up with enlisted suppliers to ensure repairmen of car in due time.

    iv. To ensure Quality Checking and provide report within 7 days from the date of receiving the service.

    Procurement Department:

    i. To select Appropriate Supplier / Vendor and appoint on a yearlong basis both for regular maintenance and also for

    repairmen of vehicle.

    ii. To procure parts required for repairing the car valued over BDT 5,000.00

    iii. To negotiate price with suppliers.

    iv. To raise Purchase Order (PO) in favour of appropriate suppliers.

    v. To submit bills and invoices along with relevant documents to the Finance Department for Payment.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    13/20

    4

    11. C&F Agent, Transport Service Provider, Insurance:

    Procurement for Service from C&F Agent, Transport Service Provider & Insurance will be done based on annual service

    contracts.

    However the rates of the service providers will be reviewed after every four months. The user of the C&F Agent, Transport

    Service Provider will be the Product Planning and Sales Coordination Department and selection of the supplier from time to

    time will be done jointly by Procurement Department & Product Planning and Sales Coordination Department.

    11. Media buying and Agency Fixation:

    Guideline of Procurement of Media and Other marketing agency will be circulated soon.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    14/20

    4

    12. Packaging Materials:

    Objective

    To facilitate forecasted production by ensuring availability of all required packaging materials in a timely and accurate manner.

    Scope

    This procedure applies to all local purchase of packaging materials Inners and Outer Cartons, foils, tape, glue and other misc

    items required for production process.

    Procedure

    Functions of procurement of packaging materials are to be performed in coordination with Product Planning, Procurement and

    Manufacturing Department.

    The summarized roles of above three departments are mentioned hereunder:

    Product Planning Department:

    iii. To prepare 3 months rolling forecast mentioning monthly consumption of each item of packaging materials with the view

    to obtain approval from the Managing Director and to raise Purchase Requisition as per forecasts.

    iv. To ascertain Minimum Order Quantity (MOQ) Level and re-order level of each item of packaging materials in

    consultation with Manufacturing Department.

    v. To provide with delivery schedule of each item of packaging materials at Factory end, either on monthly or quarterlybasis, in consultation with Manufacturing and Procurement Department, considering MOQ and re-order level.

    vi. To follow up with Suppliers for any emergency situations.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    15/20

    4

    vii. To notify Procurement and Manufacturing Department any special issue / special circumstance, which needs to be

    brought to their notice, immediately.

    Procurement Department:vi. To select Appropriate Supplier in compliance with Companys Procurement Policy.

    vii. To negotiate price with suppl iers.

    viii. To raise Purchase Order (PO) in favour appropriate suppliers.

    ix. To follow up with suppliers to ensure supply of packaging materials in a timely manner to fulfil the requirements of

    Product Planning Department.

    x. To notify Product Planning and Manufacturing Department any special issue / special circumstance, which needs to

    be brought to their notice, immediately.

    xi. To submit bills and invoices along with relevant documents to the Finance Department for Payment after completion

    of required formalities.

    Manufacturing Department:

    v. To receive packaging materials and store in appropriate place.

    vi. To ensure Quality Checking and provide report within 7 days from the date of receiving goods.

    vii. To provide daily stock and consumption report to concerned personnel of Product Planning and Procurement

    Department.

    viii. To monitor the Minimum Order Quantity (MOQ) Level and re-order level of each item of packaging materials on

    continuous basis and update Product Planning Department for its appropriate planning.

    ix. To bring to the notice of Product Planning and Procurement Department any other important issue which needs to be

    brought to their notice.

    x. To carry out test of packaging materials, in case of new or existing design and report back to purchase department.

    Appendix - A

    Approval Authority of Purchase Requisitions

    Financial Authority for Approval of Revenue Expenditure Budgeted

    Position Amount

    1. Budget Holder As mentioned in Sec 1.5.

    2. Head of Finance Upto BDT 100,000.00

    3. Managing Director Any Value

    Financial Authority for Approval of Revenue Expenditure Unbudgeted

    Position Amount

    1. Budget Holder Less than BDT 10,000.00

    2. Managing Director Any Value

    Financial Authority for Approval Capital Expenditure Budgeted & Unbudgeted

    Position Amount

    1. Managing Director Any amount.

    Approval Authority of Comparative Statement

    Financial Authority for Approval of Revenue Expenditure Budgeted

    Position Amount

    1. Head of Procurement Up to BDT 150,000.00

    2. Head of Finance & Head of Procurement Up to BDT 500,000.00

    2. Managing Director & Head of Procurement / Head of Finance Any Value

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    16/20

    4

    Approval Authority for Purchase Orders

    Financial Authority for Approval of Purchase Order

    Position Amount

    1. Head of Procurement Up to BDT 500,000.00

    2. Head of Finance & Head of Procurement Up to BDT 10,00,000.00

    3.Managing Director & Head of Procurement / Head of Finance Any Value

    Appendix - B

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    17/20

    4

    Appendix - C

    Appendix - D

    Goods & Services not requiring a Purchase Requisition

    1. Raw Materials Import.

    2. Utilities Bill

    3. Port Clearance Charge.

    4. Customs Duty.

    5. Insurance.

    6. Post & Courier Services.

    7. Property rental charges

    8. Audit & rental fees.9. Salary related Costs

    10. Personal Expenses.

    11. Taxation Payments.

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    18/20

    4

    Appendix - E

    Procurement Team

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    19/20

    4

    Appendix F

  • 7/27/2019 Purchasing Policy and Guideline_final_oct2012v1

    20/20

    4

    Abbreviation:

    Company : New Zealand Dairy Products Bangladesh Ltd

    PR : Purchase RequisitionPO : Purchase Order