Purple Line ExtensionSection 1 Construction Community Meeting April 25, 2019
1
AgendaSection 1
2
• Project Overview• MOW Building• Tunneling• Station Updates• Eat Shop Play• Business Interruption Fund• Questions & Answers
Purple Line ExtensionProject Alignment
3
Sections 1, 2 & 3 Status
4
*Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Forecasted Schedule
Section Section 1 Section 2 Section 3
Length 3.92 Miles 2.59 Miles 2.56 Miles
New Stations Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega
Wilshire/Rodeo
Century City/
Constellation
Westwood/UCLA
Westwood/VA
Hospital
Pre-Construction
Activities
2014 – 2015 2016 – 2018 2018 – 2019
Construction 2015 – 2023 2018 – 2025 2019 – 2027
Operations 2023 2025 2027
Purple Line ExtensionSection 1 Alignment
5
Purple Line ExtensionSection 1 Schedule
6
*As of April 2019, subject to change
Purple Line Maintenance Facility
7
Maintenance Facility
• Located in the Arts District, north of 6th St Bridge
• 590 S Santa Fe Av
Current Work
• Parking lot paved and striped
• Sidewalks and landscaping installed
• Furniture being placed and assembled
• Artwork installed on west wall approximately mid-June
Purple Line Maintenance Facility
8
Repairing Santa Fe Av
Purple Line Maintenance Facility
9
Storage room
Wilshire/Western Connection ScheduleSchedule
10
*As of April 2019, subject to change
• Intermittent lane reductions on Wilshire Bl will be in place to support the removal of existing monitoring wells
• Needs to be completed before the TBMs reach each location
• Total of 19 locations, the first 2 are at Wilshire/Manhattan Pl
• Additional details for this work will be available in future construction notices
Well AbandonmentOngoing through 2019
11
Approximate Well Locations on Wilshire Bl between Manhattan Pl and St Andrews Pl
Project-wide Tunneling
12
A journey down one of the tunnels
Project-wide Tunneling
13
Tunnel rings lined up, ready to be placed
Wilshire/La Brea Station
14
Wilshire/La Brea Station Box
15
Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St
Wilshire/La Brea StationSchedule
16
*As of April 2019, subject to change
Wilshire/La Brea Station Station Construction
17
Concourse deck construction progress
Wilshire/La Brea Station Station Construction
Construction the interior walls
Wilshire/La Brea Station Station Construction
Installing TBM rings on the west end
Wilshire/Fairfax Station
20
Wilshire/Fairfax Station Box
21
Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr
Wilshire/Fairfax Station Schedule*As of April 2019, subject to change
22
Wilshire/Fairfax StationStation Construction
Excavation complete, excavator moving onto Wilshire/La Cienega Station
Pouring concrete for the floor of Wilshire/Fairfax Station
Wilshire/Fairfax StationStation Construction
Installing station box liner
Orange Grove Av ClosureStart date TBD
• STS is proposing a full closure of Orange Grove Av just south of Wilshire Bl for the duration of the project
• Closure will support the excavation of appendage structures and successor activities
• Outreach to the community and the relevant city agencies has begun
Wilshire/Fairfax StationConcrete and Rebar – Ongoing 2019
• Concrete and rebar (steel) work anticipated to continue through 2019
• Work will require worksite traffic control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr
• Off-peak work hours (9am –3:30pm; 8pm - 6am)
• More details to be provided in future construction notices and briefings
Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar work will be done at the Wilshire/Fairfax Station.
26
Wilshire/Crescent Heights Tunnel Investigation, Ongoing through May 2019
27
Approximate work locations at Wilshire Bl/Crescent Heights Bl
• Investigative drilling in advance of tunneling anticipated at Wilshire Bl/Crescent Heights Bl continuing through May 2019
• Expected traffic control:
• Weekend directional closures centered around Wilshire Bl/Crescent Heights
• Intermittent sidewalk closureswith pedestrian detours
• Temporary center enclosure on Wilshire Bl
Wilshire/La Cienega Station
28
Wilshire/La Cienega Station Box
29
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
Wilshire/La Cienega Station*As of April 2019, subject to change
30
Wilshire/Gale Intermittent Daily Gale Closure – North of Wilshire Bl
• Gale Dr will be intermittently closed Monday to Saturday, 6am to 6pm
• This closure is a public safety measure due to high volumes of ingress/egress from the property
• Access to N Gale Dr will be maintained from San Vicente Bl
31
Gale Dr from north of Wilshire Bl
Wilshire/La Cienega
32
Installing braces inside Wilshire/La Cienega Station
Wilshire/La Cienega – Upcoming Work Instrumentation Work & Street Maintenance
When: Ongoing through 2019
Instrumentation work on Wilshire Bl and La Cienega Bl• Intermittent lane reductions on
Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour)
Street Maintenance, Dewatering Well Maintenance, and Utility Work on Wilshire Bl• Intermittent lane reductions on Wilshire
Bl and side streets during off-peak hours (non-rush hour)
33Example of instrumentation drilling
34
Document Coffee Bar 3850 Wilshire Blvd
Los Angeles, CA 90010(310)465-8135
35
5115 Wilshire Blvd,Los Angeles, CA 90036
(877) 224-0954
Nail Bar LA Beverly Hills 8318 Wilshire Blvd
Beverly Hills, CA 90211 (323) 852-9515
36
Helping local businesses as we build.Update as of 4/19/19
BIF Information and Eligibility
> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas
> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements
> Grant amount determined by loss of business revenue related to period of construction disruption
> To date, 884 grants have been awarded with a total value of more than $20.8 million along all three project area
BIF Grant Award Update
> Purple Line Extension, Section 1
> BIF Grants Awarded: 190
> BIF Grant Amount Awarded: $4,845,122.98
> Number of small businesses awarded: 74
> BIF Business Advisor: Brian Lazo
> Pacific Coast Regional (PCR)
> 213.739.2999
BIF Grant Award Update
> Purple Line Extension, Section 2
> BIF Grants Awarded: 42
> BIF Grant Amount Awarded: $1,169,739.32
> Number of small businesses awarded: 24
> BIF Business Advisor: Darrell Smith
> Pacific Coast Regional (PCR)
> 213.739.2999
BIF Grant Award Update
> Purple Line Extension, Section 3
> At the February 2019 Board meeting, Metro’s Board of Directors authorized the expansion of the Metro Pilot Business Interruption Fund (BIF) to include small “mom and pop” businesses directly impacted by transit rail construction along Section 3 of Metro’s Purple Line Extension.
> BIF Business Advisor: Darrell Smith
> Pacific Coast Regional Small Business Development Corporation (PCR)
> Phone: 213.739.2999
41
Section 1: Construction Community Meeting
Thursday, April 25, 2019
6:30pm – 7:30pm
SAG-AFTRA 5757 Wilshire Bl
Los Angeles, CA 90036
*On-site parking will be validated
42
Next Community MeetingSection 1
Updates on La Cienega and Rodeo Stations
Wednesday, May 1, 20196:30pm – 8pm
Beverly Hills Public Library2nd Floor Auditorium
444 N Rexford DrBeverly Hills, CA 90210
*On-site parking free after 5pm
43
Next Community MeetingBeverly Hills
• Sunday, June 2
• 11am – 3pm
• Great Lawn, La Brea Tar Pits & Museum
44
Halfway There to La Cienega Celebrate 50% Completion of Section 1