Page 1: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Purple Line ExtensionSection 1 Quarterly Construction Update January 16, 2020

1

Page 2: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Metro News

2

> Metro is growing, and that's great news for LA because we have big plans for new rail and busway lines in the coming years.

> To accommodate Metro’s growth and help everyone have a better journey, we’re updating our line naming convention to now include a letter in addition to color on all rail and busway lines.

> A temporary transitional naming system will help riders connect the letter to the color while we update customer information.

Page 3: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Agenda

3

• Section 1 Update• Section 2 Update• Section 3 Update• Eat Shop Play• Business Interruption Fund• Questions & Answers

Page 4: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Purple Line ExtensionProject Alignment

4

Page 5: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Sections 1, 2 & 3 Status

5

*Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Forecasted Schedule

Section Section 1 Section 2 Section 3

Length 3.92 Miles 2.59 Miles 2.56 Miles

New Stations Wilshire/La Brea

Wilshire/Fairfax

Wilshire/La Cienega

Wilshire/Rodeo

Century City/

Constellation

Westwood/UCLA

Westwood/VA

Hospital

Pre-Construction

Activities

2014 – 2015 2016 – 2018 2018 – 2019

Construction 2015 – 2023 2018 – 2025 2019 – 2027

Operations 2023 2025 2027

Page 6: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Purple Line ExtensionSection 1 Alignment

6

Page 7: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/Western Connection ScheduleSchedule

7

*As of January 2020, subject to change

Page 8: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Brea Station

8

Page 9: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Brea Station Box

9

Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St

Page 10: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Brea StationSchedule

10

*As of January 2020, subject to change

Page 11: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Brea Station Station Construction

Installing wall form

Page 12: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire Center OpeningStation Construction

Design-build contractor will be requesting an extension to the existing Center Opening on Wilshire Bl through Q3 2020

Station construction will need continued support from the deck panel openings on Wilshire Bl

Outreach to the community and relevant city agencies is ongoing

Page 13: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Cross Passage 12Concrete Support

13

> K-Rail work zone (already in place) at Wilshire Bl/Rimpau will support concrete and material delivery into the tunnel; similar zones will be placed at other tunnel locations

> Work zone will be in place 24/7; most work will take place during nighttime> Noisier activities will occur during daytime hours> Details on additional locations will be available in future construction notices

and community meetings

Page 14: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire Bl/Sycamore Av AntennaSpecifications

> Steel pole, slightly more than 62 feet above the concrete base

> Less than 12 inches in diameter

> Radio antenna must be in very close proximity (300 feet maximum) to the underground station’s communications room (at the east end of the Wilshire/La Brea Station) to eliminate loss of signal strength

> Location provides connectivity to the various emergency response agencies’ other local and mountain top radio transmitter/receiver sites

> Location allows the Purple Line radio system to have the coverage it requires for all users:> Metro Operations and Maintenance> Public safety (police, fire, Sheriff, and Transit Security) in the

underground stations and tunnels

Page 15: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire Bl/Sycamore Av AntennaRendering of Antenna

Page 16: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire Bl/Sycamore Av AntennaRendering of Antenna

Page 17: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/Fairfax Station

17

Page 18: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/Fairfax Station Box

18

Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west of Fairfax Av to just west of Ogden Dr

Page 19: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/Fairfax Station Schedule*As of January 2020, subject to change

19

Page 20: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/Fairfax StationStation Construction

Installing wall form

Page 21: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Orange Grove Av ClosureStation Construction

> A full closure of Orange Grove Av just south of Wilshire Bl will be in place through June 2020

> This closure will support the excavation of appendage structures

> Excavation is anticipated to continue into Q1 2020

*As of October 2019, subject to change

Closure area

Page 22: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire Bl/Crescent Heights BlTunnel Investigation, Ongoing through January 2020

22

Approximate work locations at Wilshire Bl and Crescent Heights Bl

> Additional investigation wells will be installed in January 2020

> Existing wells may also be converted or abandoned

> In advance of tunneling activities, additional mitigation measures will be in place on the north and south sides of Wilshire Blvd

> Details on this work and the related traffic control will be available in future construction notices.

Page 23: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Directional Drilling

> Continuing through January 2020, STS will be investigating the locations of two abandoned oil wells

> Work will be done during off-peak hours, 9am to 3:30pm and 8pm to 6am

> Intermittent lane closures along Wilshire Bl will be in place to support this investigation

Approximate work location at Wilshire Bl/La Jolla Av

Page 24: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega Station

24

Page 25: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega Station Box

25

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

Page 26: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega Station*As of January 2020, subject to change

26

Page 27: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/Gale Intermittent Daily Gale Closure – North of Wilshire Bl

Gale Dr will be intermittently closed Monday to Saturday, 6am to 10pm*

Closure is a public safety measure due to high volumes of ingress/egress from the property

Material deliveries to the Wilshire/La Cienega Station Box began in October 2019

Access to N Gale Dr will be maintained from San Vicente Bl

* Work hours may transition to overnight, pending City of Beverly Hills approval

27

Gale Dr from north of Wilshire Bl

Page 28: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

> Work hours are expected to increase at the La Cienega and Gale staging yards

> Daily construction activities are expected to continue within both staging yards 24 hours a day

> The increased hours will support station construction activities within the staging yards and underneath Wilshire Bl

> City Council approved work on Martin Luther King Jr. Day and Presidents Day

Installing HDPE layer

Page 29: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Construction Progress

Page 30: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega – Upcoming Work Concrete and Material Deliveries

When: Continuing in 2020

> Work at La Cienega Bl has transitioned to concrete and material deliveries into the station box

> This will require intermittent traffic control on Wilshire Bl between San Vicente Bl and La Cienega Bl

> These activities will be ongoing throughout the station construction phase of the project, for approximately 30 months

30

Material delivery

Page 31: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega – Upcoming Work Concrete and Material Deliveries

Work Hours and Traffic Control:

> Between 7am and 4pm, Wilshire Bl between San Vicente Bl and La Cienega Bl may be reduced to two lanes in each direction*

> Between 9pm and 7am, Wilshire Bl between San Vicente Bl and La Cienega Bl may be reduced to one lane in each direction. Work activities would begin at 10pm

> Left turns from Wilshire Bl to side streets may be restricted during the lane reductions

31Example of rebar delivery

Page 32: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega – Upcoming Work What We Are Building

32

Page 33: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega – Upcoming Work What We Are Building - Stage 1

Invert Slab Placement

Invert slab is a 5ft tall slab of concrete, rebar, and utilities that makes up the ground floor of the future Wilshire/La Cienega Station. When complete, it will also serve as a stable platform for the tunnel boring machines when they arrive at Wilshire/La Cienega in the spring

Work on the invert slab placement is anticipated to be completed in April 2020

Work will require concrete and material delivery directly into the Wilshire/La Cienega Station Box from the deck panels on Wilshire Bl

33

Page 34: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega – Upcoming Work Concrete and Material Deliveries

Mitigations: Sound blankets will be placed around the pump truck, concrete mixers, cranes, and all

other heavy equipment Nylon straps will be used to pick up rebar and other materials whenever possible Vehicles will be equipped with low impact backup alarms Metro will provide alternate parking while parking meters on Wilshire Bl are affected

by this work

34

Page 35: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La CienegaReplacement Parking Locations

One Hour Free Parking available at the following locations:

8447 Wilshire Bl – Access garage from N Hamilton Dr

8350 Wilshire Bl – Access garage from S Tower Dr

Parking program is available from 10am to 3:30pm, Monday – Friday

Mention “Metro” when entering the garage to receive the 1st hour free of charge

Replacement parking locations

35

Page 36: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Wilshire/La Cienega – Upcoming Work Instrumentation Work & Coring Work

When: Ongoing in 2020

Intermittent lane reductions on Wilshire Bl, La Cienega Bl, and side streets during off-peak hours may be in place to support the installation of geotechnical instruments in the Wilshire/La Cienega area

Intermittent lane reductions may be in place on Wilshire Bl, west of La Cienega Bl, to support coring survey work under Wilshire Bl

Additional details on this work will be available in future construction notices

36Example of instrumentation drilling

Page 37: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Benihana Lot Change of Use

37

> City approved Metro’s Change of Use Request for the former Benihana lot at 38 N La Cienega Bl

> 50 – 60 Purple Line Extension personnel can park in the lot 24 hours a day, 7 days a week

> Only personal vehicles and project trucks will be allowed to park in the lot

> No large equipment or construction materials will be staged in the lot

> The main entrance from La Cienega Bl will be protected by a gate

Page 38: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Benihana Lot Change of Use

38

> Only Purple Line Extension personnel will be able to unlock the gate

> Sound mitigation will be in place on the east side of the lot

> Signage will be in place around the lot to remind workers to be considerate of neighbors

> Entry and exit will primarily occur before shifts begin, and after they end

> A normal workday will consist of 2-3 shifts, depending on overnight work on Wilshire Bl

> In accordance with City of Beverly Hills ordinances, smoking will not be permitted within the parking lot

> Trash cans will be placed within the lot

> Metro signage will be located at the front of the lot, which will include the project hotline phone number

Page 39: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

39

3790 Wilshire BlLos Angeles, CA 90010

213.388.1400

Page 40: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

40

5400 Wilshire Bl,Los Angeles, CA 90036

323.761.1211

Page 41: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

155 N Crescent DrBeverly Hills, CA 90210

310.385.192441

Page 42: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Helping local businesses as we build.Purple Line Extension Update

Page 43: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

BIF Information and Eligibility

> Financial assistance to small “mom & pop” businesses with 25 or fewer full-time employees directly impacted by Metro Rail construction along three project areas

> Crenshaw/LAX Transit Project

> Purple Line Extension, Sections 1, 2 & 3

> Regional Connector Project, Little Tokyo area & 2nd/Broadway Segment*

> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements

> Grant amount determined by business revenue loss directly related to period of Metro construction disruption

*Segment eligibility based on full street closure with duration greater than six continuous months.

Page 44: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Business Interruption Fund

$15,027,278.55

$5,485.204.34

$2,061,053.94$1,996,164.16

$950,164.03

Crenshaw/LAXTransit Project

Purple LineExtension,Section 1

Purple LineExtension,Section 2

RegionalConnector,

Little Tokyo Area

RegionalConnector,

2nd/BroadwaySegment

(*as of 1/10/20)

Value of BIF Grants Awarded:$25,519,865.02

Page 45: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Business Interruption Fund

100% 97% 99% 93%84%

74%

Businessesreferred to

supportservices

Applicationsprocessedwithin 9business

days

Clientssatisfaction

rating

Businessesremaining

open after 6months of

grant award

Businessesremaining

open after 1year of grant

award

Businessesremaining

open after 2years of grant

award

Measures of Effectiveness(as of CY 2019 Q3)

Page 46: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

BIF Grant Award Update

> Purple Line Extension Section 1 (as of 1/10/20)

> BIF Grants Awarded: 212

> BIF Grant Amount Awarded: $5,485,204.34

> Number of small businesses awarded: 79

> City of Beverly Hills only

> BIF Grants Awarded: 40

> BIF Grant Amount Awarded: $1,052,192.98

> Number of small businesses awarded: 17

> BIF Business Advisor: Brian Lazo, PCR, 213.739.2999

Page 47: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

BIF Grant Award Update

> Purple Line Extension Section 2 (as of 1/10/20)

> BIF Grants Awarded: 67

> BIF Grant Amount Awarded: $2,061,053.94

> Number of small businesses awarded: 36

> City of Beverly Hills only

> BIF Grants Awarded: 57

> BIF Grant Amount Awarded: $1,760,844.80

> Number of small businesses awarded: 32

> BIF Business Advisor: Darrell Smith, PCR, 213.739.2999

Page 48: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Updates on La Cienega and Rodeo Stations

Wednesday, February 56:30pm – 8pm

Beverly Hills City Hall2nd Floor Municipal Gallery

445 N Rexford DrBeverly Hills, CA 90210

On-site parking free after 5pm

48

Next Community MeetingBeverly Hills

Page 49: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

La Cienega and Rodeo Stations

Wednesday, February 512pm – 1pm

Link to the online meeting: WebexAccess Code: 809 386 471 | Password: Purple

Join by phone: 1-650-479-3207 (toll-free)

49

Lunch with Us: Public WebinarBeverly Hills

Page 50: Purple Line Extension...The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section Section 1 Section 2 Section 3 Length 3.92 Miles

Section 1: Construction Community Meeting

Thursday, May 146:30pm – 7:30pm

SAG-AFTRA5757 Wilshire Bl

Los Angeles, CA 90036

Parking Validation Available On-site

50

Next Community MeetingSection 1