pwa geo environmental ltd · 2014. 8. 5. · calls wharf 2 the calls leeds west yorkshire ls2 7ju...

26
Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 GeoEnvironmental Assessment Proposed Housing Site, Broadway Garage Site Helmshore, Haslingden Project No. 13186/G/1 December 2013 GeoEnvironmental Ltd ConsulƟng GeoEnvironmental Engineers pwa [email protected] www.pwageo.co.uk FS560612

Upload: others

Post on 24-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701

Phase 1 Geo‐Environmental

Assessment

Proposed Housing Site, Broadway Garage Site

Helmshore, Haslingden

Project No. 13186/G/1 December 2013

Geo‐Environmental Ltd Consul ng Geo‐Environmental Engineers pwa

[email protected] www.pwageo.co.uk

FS560612

Page 2: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

 

 Client 

Barnfield Construction Ltd. 

Kenyon Road, 

Lomeshaye Industrial Estate, 

Nelson, Lancashire. 

BB9 5SP

Documents Revision Status 

REVISION  DATE  COMMENTS

_Rev V1  December 2013 

   

 

Page 3: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013  

This brief summary should not be assumed to represent a complete account of all the potential geo‐environmental 

issues that may exist at the site.  As such it is strongly recommended that the report be read in its entirety. 

Executive Summary  

Background 

The  site  is  located  at  Broadway Garage  Site  off  Broadway, Haslingden.    Barnfield  Construction Limited and Greenvale Homes Limited plan  to construct residential units at  the site.   PWA Geo‐Environmental  Ltd were  commissioned  to provide a geo‐environmental appraisal of  the  site.   A summary of the salient geo‐environmental issues is provided in the table below.  

A summary is provided in the table below.  

Subject  Remarks 

Former uses  The site was developed with garage units some time prior to 1961.   Changes  in the locations and number of units are recorded on historic map records. 

 

Based  upon  an  assessment  of  the  site  topography  it  is  considered  that  initial development  comprised  excavation  into  existing  natural  deposits  to  create  a development platform.  

 

Current use  The  site  is currently occupied by a garages, which are used by  the  surrounding residential housing. 

Adjacent land uses  Predominantly mixed residential and commercial uses.   

Landfill sites  There were no recorded landfill sites within 250m of the site. 

Potential Contamination Sources 

Identified sources include: 

Localised  hydrocarbon  contamination  (fuel,  engine  oil  spillages,  and 

lubrications) associated with sites use as storage garages. 

Made  Ground  associated  with  demolition  of  garage  units  may  be 

impacted by asbestos from roof sheeting. 

Anticipated  Ground Conditions 

BGS records  indicate that the site  is underlain by Glacial Till deposits.   The solid geology comprises Marsden Formation,  interbedded mudstone and siltstones of the Millstone Grit Group. 

Mining   The report states that the site is not within the zone of likely physical influence on the surface from past, current or future underground workings.   

Preliminary Assessment 

No site investigation data has been provided and the presence and extent of any contamination is currently unknown. 

The current and previous uses of the site are considered unlikely to have created site wide contamination, although localised occurrences may be present. 

 

Page 4: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013  

Table of Contents 1. INTRODUCTION .................................................................................................................................... 1

1.1. Proposed Development .......................................................................................................................... 1

1.2. Report Format and Limitations ............................................................................................................... 1

2. SITE PROFILE ....................................................................................................................................... 2

2.1 Site Location ........................................................................................................................................... 2

2.2 Site Reconnaissance .............................................................................................................................. 2

2.3 Site Regulatory and Environmental Data ............................................................................................... 2

2.4 Site History ............................................................................................................................................. 3

2.5 Unexploded Ordnance ............................................................................................................................ 4

2.6 Potential Contamination Sources ........................................................................................................... 4

3. ENVIRONMENTAL SETTING ................................................................................................................ 6

3.1 Geology................................................................................................................................................... 6

3.2 Hydrogeology .......................................................................................................................................... 6

3.3 Hydrology ................................................................................................................................................ 6

3.4 Mining and Quarrying ............................................................................................................................. 7

3.5 Ecology ................................................................................................................................................... 7

3.6 Summary of Site Sensitivity .................................................................................................................... 7

4. PRELIMINARY RISK ASSESSMENT .................................................................................................... 8

4.1 Introduction ............................................................................................................................................. 8

4.2 Preliminary Conceptual Site Model ........................................................................................................ 8

4.3 Geotechnical Hazard Identification ......................................................................................................... 9

4.4 Qualitative Risk Assessment ................................................................................................................ 10

5.0 CONCLUSIONS AND RECOMMENDATIONS .................................................................................... 13

5.1 Environmental Risk Assessment .......................................................................................................... 13

5.2 Ground Engineering .............................................................................................................................. 14

5.3 Further Work ......................................................................................................................................... 14

6 UNCERTAINTIES AND LIMITATIONS ................................................................................................ 15 

6.1  General Comments ......................................................... 15 

7.0 REFERENCES ............................................................... 16 

Page 5: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013  

 

APPENDICES 

Appendix A ‐ General Notes 

01  Environmental Setting 

Appendix B– Drawings 

Drawing No.  Title 

13186/G/150  Site Location Plan 

13186/G/151  Schematic Conceptual Site Model 

Day Architect Drawings 

SP_004  Site Option 3 (Proposed Development Plan) 

Appendix C‐ Site Photographs 

Appendix D – Envirocheck Report 

Appendix E – Historical Ordnance Survey Plans 

 

 

Page 6: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

FOREWORD (Geo‐environmental Investigation Report) 

This  report  has  been  prepared  for  the  sole  use  and  reliance  of  Barnfield  Construction  Ltd  and Greenvale  Homes  Limited  (the  Client)  named  above  and  cannot  be  relied  upon  by  any  other parties  without  the  express  written  authorisation  of  PWA  Geo‐Environmental  Ltd.    Any unauthorized third party relies on this report at their own risk and the authors owe them no duty of care.  

The  report  presents  observations  and  factual  data  obtained  during  desk  based  study  and  our intrusive  investigations, and provides an assessment of geo‐environmental  issues with respect to information provided by the Client regarding the site.   

The report should be read in its entirety, including all associated drawings and appendices.  PWA Geo‐Environmental Ltd cannot be held responsible for any misinterpretations arising from the use of extracts that are taken out of context.  

The  findings and opinions conveyed  in any Desk Study section of the report  (including review of any  third party  reports) are based on  information obtained  from  the sources  listed, which PWA Geo‐Environmental Ltd understands are reliable.  All reasonable skill, care and diligence has been applied in examining the information obtained.  However, PWA Geo‐Environmental Ltd accepts no responsibility  for  inaccuracies  in the data supplied or  for opinions based on any such  inaccurate data. 

Where the report refers to the potential presence of invasive weeds such as Japanese Knotweed, or the presence of asbestos containing materials, it should be noted that the observations are for information only and should be verified by a suitably qualified expert. 

PWA Geo‐Environmental Ltd reserves the right to amend their conclusions and recommendations in the light of further information that may become available. 

 

 

 

 

 

Page 7: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

  1   

1. INTRODUCTION  

PWA Geo‐Environmental Ltd (PWAG), were commissioned by Barnfield Construction Limited to carry out a Phase 1 Desk Study of a parcel of land identified as the Broadway Garage Site off Broadway, Haslingden, BB4 4HL  (the site).   The proposal  is  to  redevelop  the Broadway garage site for 3 x 2 bedroom houses and 4 x 3 bedroom houses. 

The site comprised a parcel of land with garage units. The site is located in a predominantly residential  area  with  commercial  and  civic  uses  noted.    The  purpose  of  the  study  is  to provide an assessment of  the environmental  liabilities associated with purchasing  the site, provide preliminary recommendations for developing the site, determine suitability for the proposed end use and investigate ground conditions for foundation design. 

General  notes  and  limitations  relevant  to  all  PWA  Geo‐Environmental  Ltd  preliminary investigations are described in the Foreword. These should be read in conjunction with this report.    The  text  of  the  report  draws  specific  attention  to  any  modification  to  these procedures and to any other special techniques employed. 

Standard  definitions,  procedures  and  guidance  are  contained  within  Appendix  A,  which includes background, generic information on assessment of the site's environmental setting. 

1.1. Proposed Development 

It  is  understood  that  the  development will  comprise  3  x  2  bedroom  houses  and  4  x  3 bedroom  houses;  an  indicative  design  layout  is  shown  on  Day  Architectural  Limited drawing SP_004 presented in Appendix B.  

1.2. Report Format and Limitations 

Standard  definitions,  procedures  and  guidance  are  contained  within  Appendix  A,  which includes background, generic information on assessment of the site's environmental setting. 

The desk  study part of  this  investigation  relied on published  information and  information provided by the client and other parties,  including anecdotal  information, during the given time period.  Regulatory data from the public register and historical OS maps were obtained from an Envirocheck report prepared by Envirocheck Limited.   

General notes and limitations relevant to all PWA Geo‐Environmental Ltd investigations are described  in the Foreword and should be read  in conjunction with this report.   The text of the report draws specific attention to any modification to these procedures and to any other special techniques employed. 

   

Page 8: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

2

2. SITE PROFILE 

2.1 Site Location 

The  site  location  is  shown  on Drawing No.  13186‐G‐150  presented  in Appendix  B  to  this report.  Site details are summarised in Table 1 below. 

Table 1 – Site Details 

Detail  Remarks 

Location  Broadway Garage Site Off Broadway Haslingden, BB4 4HL 

NGR  NGR 378421,421592 

Area  O.25 Ha 

Known services  Electricity, gas and water all considered likely 

2.2 Site Reconnaissance 

A  site  reconnaissance  was  undertaken  on  11th  December  2013  and  observations  are summarised in Table 2 and below.  In addition site photographs are provided in Appendix C. 

At the time of the reconnaissance the site was accessible from all sides from public rights of way.    It was accessed off Broadway and comprised a road and track that enclosed a set of red brick garage units with a corrugated roof, assumed to comprise asbestos cement/fibre boarding.    Two  separate  garage  units were  present  in  the  north  and west  of  the  site  on rough grassland that occupied the northern half of the site. 

Table 2 – Site Reconnaissance Findings 

 

 

 

 

 

 

2.3 Site Regulatory and Environmental Data 

Information  regarding  environmental  regulatory  controls  and  pollution  incidents  in proximity to the site  is summarised  in Table 3.   This  information  is taken  from the data provided by Groundsure, a copy of which is provided in Appendix D.  

 

 

Feature   Remarks  

Current Access  Public access to entire site.   

Topography  The  site  is  generally  flat  and  surrounded  on  all  sides  by  residential properties. 

Approximate  

Areas 

0.25Ha 

Surrounding land uses  North – Residential 

South – Commercial/residential  

West  – Residential 

East   –  Residential 

Page 9: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

3

Table 3 – Summary of Environmental Data. 

Data Source  On/off site?  Details  Potential for Impact on‐site?  

Landfill  Sites, Waste Management Facilities  &  Waste Transfer Sites 

Off site 

 

 

 

 

No EA  or  operational   Landfill  sites  within   250m of the site.  No non‐operational   landfill sites recorded  within 250m of the site  

N/A 

Historic Landfill sites  Off site 

 

 

No EA  historic   landfill    sites   recorded   within 250m  of   the  site:   

N/A 

IPC,  LAPPC authorisations  and IPPC permits 

Off site 

 

 

No permits identified within 250m of the site. N/A 

Part A(2) and Part B Activities 

Off site  Brooklands Dry Cleaners was recorded 211m east of the site.  All other records greater than 250m from the site. 

Impact  unlikely  in consideration  of  distance  to site and activities concerned. 

Trade  directory entries 

Off site  6 entries within 250m of the site.  Active entries include published  goods, electrical sub stations, and a tank. 

Impact  unlikely  in consideration  of  distance  to site and activities concerned. 

Water abstractions  Off site  None recorded within 250m of the site.  N/A 

Recorded  pollution incidents  to controlled waters 

Off site  None recorded within 500m of the site.   N/A 

IPC =  Integrated Pollution Control;  IPPC =  Integrated Pollution Prevention & Control; LAPPC = Local Authority Pollution Prevention & Controls; APC = Air Pollution Control 

2.4 Site History 

The site history has been determined from a review of OS historical maps.  The text below describes  significant  historical  activities  on  the  site  and  surrounding  area.  The  on‐site history  focuses  on  the  1:1,056  and  1:2,500  scale  maps,  with  the  off‐site  history concentrating on  the 1:10,560 scale maps.   All  the scale maps have been used  in some instances to describe relevant features. Table 4 summarises salient points relating to site history.  The maps are included in Appendix E.   

 Table 4 ‐ Site History Summary 

Date(s)  On –Site  Surrounding Land 

1846  The site is undeveloped.  The  surrounding  land  use  is  generally  open fields.    Helmshore  Road  is  marked approximately 80m west of the site. 

1891 ‐ 1892  The site remains undeveloped.  Brickhouse Farm is marked approximately 100m north of the site.  Residential type properties are noted on Helmshore Rd, west of the site. 

1909‐1910  No significant changes.  No significant changes. 

1911  No significant changes.  No  significant  changes  noted.    Some  limited further  development  seen  on  land  adjacent  to Helmshore Rd. 

Page 10: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

4

1927‐28  No significant changes.  No significant changes. 

1930  No significant changes.  No significant changes. 

1938  A footpath appears to cross the site. 

 

No significant changes. 

1950  No significant changes.  Residential type properties marked to the north east of the site. 

1961  Buildings  marked  on  site  with  a similar  footprint  to  the  present  day garages. 

Residential  type  properties  are  marked  to  the north,  east  of  the  site.    Commercial  type properties marked  south of  the  site.   A  vacant plot is marked west of the site. 

1963  No significant changes.  No significant changes. 

1965  No significant changes.  No significant changes. 

1969‐1970  Several new units marked.  No significant changes. 

1976‐1981  One unit removed.  New residential type developments noted to the west of the site. 

1977  No significant changes.  No significant changes. 

1980  Partial coverage.  Some reworking of Gas Works site indicated. 

1981‐85  Partial coverage.  No significant changes. 

1985‐1987  No significant changes.  No significant changes. 

1988  No significant changes.  No significant changes. 

1987‐1991  Partial coverage.  No significant changes. 

2002  Present day site layout noted.  No significant changes. 

2012  No significant changes.  No significant changes. 

 

2.5 Unexploded Ordnance 

In  general  accordance  with  CIRIA  report  C681  (Stone  et  al  2009)  a  non‐UXO  specialist screening exercise has been carried out for the site. This indicates: 

there is no indication of former military use from the desk study; and

the Zetica UXB map (Lancashire) indicates the site to be in an area where the bomb risk is unverified.

The  site  and  adjoining  land  has  been  developed  through  the  two  world  wars  with  no significant demolition of buildings during these periods.   

 

2.6  Potential Contamination Sources 

Currently  the  site  is occupied by a  set of brick  constructed garage units with an asbestos cement/fibre boarded roof and two standalone units that appeared to be of prefabricated concrete construction.   

Page 11: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

5

The northern part of the site is of rough grass with a track crossing behind the main block of garage units.   

Made Ground may be present from the demolition of past developments may include heavy metals, poly aromatic hydrocarbons, petroleum hydrocarbons and asbestos. 

It is considered that there is potential for localised hydrocarbon contamination (fuel, engine oil spillages, and lubrications) related to the use of the site as garages. 

   

Page 12: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

6

3. ENVIRONMENTAL SETTING 

3.1 Geology 

The 1:50,000 scale geological map indicates that the site is underlain by Glacial Till deposits.  

The  solid geology  comprises Marsden Formation,  interbedded mudstone and  siltstones of 

the Millstone Grit Group. 

Publically available ground  investigation  records  taken  from  the National Geoscience Data 

Centre by the British Geological Survey may be used for commercial purposes providing their 

source  is  identified.    No  records  that  are  considered  to  add  additional  detail  to  the 

conceptual model were noted. 

The nearest fault was an inferred normal fault 184m north of the site. 

3.2 Hydrogeology  

According to Environment Agency data the solid strata beneath the site are indicated to be 

classed as a  Secondary A Aquifer,  this  relates  to  the Marsden  Formation.   The Glacial Till 

deposits are indicated to be unproductive and likely to act as an aquiclude to the aquifer in 

the Marsden Formation. 

According to Environment Agency data the solid strata beneath the site are indicated to be 

classed as Unproductive,  these are rock  layers or drift deposits with  low permeability  that 

have negligible significance for water supply or river base flow.   

There  is  one  recorded  groundwater  abstraction  point  and  one  surface  water  abstraction 

located within 500m of the site, relating to non‐potable extractions and the site is not within 

a Source Protection Zone (SPZ). 

The  Secondary  A  Aquifer  is  likely  to  have  a  low  sensitivity  given  its  productivity  and  the 

presence of low permeability Glacial Till limiting vertical migration. 

3.3 Hydrology 

The nearest surface water feature is the River Odgen located over 500m west of the site.  

Reference  to  the  Environment Agency web  site  shows  there  are no  surface water bodies 

within 500m of the site. 

No pollution incidents to controlled waters have been recorded within 500m of the site.   

The site is further than 250m from a Flood Zone 2 as designated by the Environment Agency.  

The groundwater flooding susceptibility is considered as low.   

No further consideration of flood risk is undertaken in this report.  Specialist flood risk advice 

should be sought with regards to drainage and flooding.  

Page 13: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

7

3.4 Mining and Quarrying 

The  site  is  not  located  in  an  area  where  shallow  coal  mining  has  been  undertaken.  The 

hazard potential of subsidence relating to shallow mining on‐site is assessed to be low. 

The historical maps do not  indicate any historical earthworks or quarrying onsite or within 

the vicinity of the site. 

3.5 Ecology 

There are no recorded ecological sensitive sites within 1 km of the site. 

3.6 Summary of Site Sensitivity 

The  sensitivity  of  each  of  the  identified  receptors  in  the  vicinity  of  the  site  to  potential contamination sources are summarised in Table 7. 

Table 5 ‐ Sensitivity of Environmental Receptors in the Vicinity of the Site 

Receptor Type  Receptor(s)  Sensitivity  Reasoning 

Groundwater  Unproductive 

 

Low   No potable abstractions within the vicinity of the site.  . 

 

Surface Water  River  Ogden  Very Low  

 

Located over 500m from the site. 

 

   

Page 14: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

8

4. PRELIMINARY RISK ASSESSMENT 

4.1 Introduction 

Environmental Risk has been addressed by adopting a site‐specific qualitative approach  to identify the risk of environmental harm.  The guiding principle of this approach is an attempt to  establish  connecting  links  between  a  hazardous  source,  via  an  exposure  pathway  to  a potential  receptor.    This  is  in  accordance  with  the  Department  of  the  Environment, Transport and Regions (DETR) guidance on Contaminated Land (Ref.1) and the Construction Industry Research and Information Association (Ref. 2).   

This  assessment  will  identify  where  pollutant  linkages  may  exist  by  considering  where  a viable pathway may exist which  connects a potential  source with a  receptor.   A pollutant linkage  is  the  term used by  the DETR  in  their  standard procedure on  risk  assessment.    If there  is  no  pollutant  linkage,  then  there  is  no  risk.   Our  risk  assessment  is  based on  the proposed residential end‐use. 

4.2 Preliminary Conceptual Site Model 

Contaminated land risk assessment is based on development of a conceptual model for the site.   This  is  a  representation of  the  relationship between potential  contaminant  sources, pathways  and  receptors.  A  preliminary  conceptual  site  model  is  based  on  the  inferred ground  conditions  and  environmental  data  obtained  from  existing  data  sources.    A conceptual  site model  is  discussed  in  the  following  sections  and  a  schematic  preliminary conceptual site model is shown on Drawing 13186‐G‐151 presented in Appendix B. 

4.2.1 Identified Potential Sources 

The following potential sources of contamination have been identified from historic uses of the site and surrounding area.     

The identified potential contamination sources are summarised below: 

On Site Sources 

Identified sources which require further investigation include: 

 

Localised  hydrocarbon  contamination  (fuel,  engine  oil  spillages,  and  lubrications) 

associated with sites use as storage garages. 

Made Ground associated with possible infilling of site (heavy metals, poly aromatic 

hydrocarbons, petroleum hydrocarbons and asbestos). 

Page 15: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

9

Off Site Sources 

No  potential  sources  of  contamination  have  been  identified  in  the  immediate  site surroundings that are relevant to the site. 

 Receptors 

The following receptors have been identified: 

Future site users; 

Construction workers during redevelopment works; 

Controlled Waters – groundwater, Secondary A aquifer; 

The River Ogden has been assessed as being beyond  the zone of  influence of  the site and therefore is not considered further as a potential receptor. 

The following pathways link the potential contaminants with the sensitive receptors: 

Contact, ingestion and inhalation of contaminated soil and dust. 

Leaching and migration via soil mass and rock discontinuities; 

Humans: Ingestion, skin contact, inhalation of dust and outdoor air. 

Buildings: Direct contact. 

Buildings: Ingress via permeable soils and/or construction gaps. 

Underlying groundwater: Migration of contaminant via direct contact. 

The preliminary risk assessment process has identified potential risks to site demolition and redevelopment workers.  However, consideration of occupational health and safety issues is beyond the scope of this report and need to be considered separately  in the Construction Phase Health and Safety Plan. 

4.3 Geotechnical Hazard Identification 

Potential geotechnical hazards are listed below:

Made Ground ‐ excessive settlement (creep and inundation settlement or differential settlement of foundations, roads and infrastructure elements). 

Attack of buried concrete by aggressive ground conditions –and potentially sulfate bearing soils. 

Page 16: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

10

4.4  Qualitative Risk Assessment 

A  qualitative  risk  assessment  has  been  undertaken  for  these  potential  source‐pathway‐receptor linkages. This is based on consideration of both: 

The likelihood of an event (probability – takes into account both the presence of the hazard and receptor and the integrity of the pathway); 

The  severity of  the potential  consequence  (takes  into account both  the potential severity of the hazard and the sensitivity of the receptor). 

The risk assessment has been based on development of the site with a proposed residential end use (Table 6).  

Page 17: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

  Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

11 

Table 6  Preliminary Environmental Risk Assessment – Proposed Residential End Use 

Source  Pollutant / Hazard  Receptors  Pathways to Receptor Associated Hazard [Potential severity] 

Likelihood of Occurrence  Potential 

Risk 

Historic  spillages 

 

 

 

 

 

 

 

Site  spillages, unauthorised disposal  of  waste oils. 

Petroleum Hydrocarbons  and Poly  Aromatic Hydrocarbons. 

 

 

 

 

 

 

Future  Site Occupiers 

Contact,  ingestion, inhalation 

 

Effect  on  human health [Moderate] 

 

Possible  –  Given  previous  site  use.  No  significant  visual  or  olfactory  evidence  noted during walkover, if spillages have occurred likely to be small and localised and limited to shallow soils. 

No existing site investigation data to confirm absence or presence of contamination. 

Low  to moderate 

Neighbours  Contact,  ingestion, inhalation 

 

Effect  on  human health [Moderate] 

Possible  –  Given  previous  site  use.  No  significant  visual  or  olfactory  evidence  noted during walkover, if spillages have occurred likely to be small and localised and limited to shallow soils. 

No existing site investigation data to confirm absence or presence of contamination. 

Low  to moderate 

New  in ground services  and construction materials. 

Direct contact  Degradation (Slight) 

Possible  –  Given  previous  site  use.  No  significant  visual  or  olfactory  evidence  noted during walkover, if spillages have occurred likely to be small and localised and limited to shallow soils 

No existing site investigation data to confirm absence or presence of contamination. 

The  use  of  oversized  service  trenches  and  appropriately  designed  materials  should reduce the risk to low. 

Low  to moderate 

Plant Life  Contact  Effect  on plant  life [Low] 

Landscaped areas may require use of clean topsoil to limit any potential risk.  Low 

Controlled Waters (Groundwater) 

Leaching  and  lateral migration  of  any leachable contaminants  in  soils and rock mass. 

Pollution  of controlled  waters [Slight] 

The overlying low permeability Glacial Till is likely to limit vertical migration. 

Aquifer likely to have a low sensitivity. 

No existing site investigation data to confirm absence or presence of contamination. 

Moderate 

Made  Ground associated with historic infilling 

 

 

Heavy metals, poly aromatic hydrocarbons, petroleum hydrocarbons. 

Future  Site Occupiers 

Contact,  ingestion, inhalation 

 

Effect  on  human health [Moderate] 

 

Possible – Given  site  setting.   No  significant  visual or olfactory evidence noted during reconnaissance. 

No existing site investigation data to confirm absence or presence of contamination. 

Low  to moderate 

Page 18: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

  Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

12 

Source  Pollutant / Hazard  Receptors  Pathways to Receptor Associated Hazard [Potential severity] 

Likelihood of Occurrence  Potential 

Risk 

 

 

 

 

 

 

 

 

Neighbours  Contact,  ingestion, inhalation 

 

Effect  on  human health [Moderate] 

Possible – Given  site  setting.   No  significant  visual or olfactory evidence noted during reconnaissance. 

The surrounding area is predominantly residential. 

No existing site investigation data to confirm absence or presence of contamination. 

Low  to moderate 

New  in ground services  and construction materials. 

Direct contact  Degradation (Slight) 

Possible – Given  site  setting.   No  significant  visual or olfactory evidence noted during reconnaissance. 

No  existing  site  investigation  data  to  confirm  absence  or  presence  of  contamination. The  use  of  oversized  service  trenches  and  appropriately  designed  materials  should reduce the risk to low. 

Low  to moderate 

Plant Life  Contact  Effect  on plant  life [Low] 

Landscaped areas may require importation of clean topsoil limiting any potential risk.  Low 

Controlled Waters (Groundwater) 

Leaching  and  lateral migration  of  any leachable contaminants  in  soils and rock mass. 

Pollution  of controlled  waters [Slight] 

The overlying low permeability Glacial Till is likely to limit vertical migration. 

Aquifer likely to have a low sensitivity. 

No existing site investigation data to confirm absence or presence of contamination. 

Low 

Asbestos  Future  Site Occupiers 

Ingestion, inhalation  Effect  on  human health [Severe] 

Possible.  

 

No existing site investigation data to confirm absence or presence of contamination. 

Moderate 

Neighbours  Ingestion, inhalation  Effect  on  human health [Severe] 

Moderate 

Ground  Gas from  Made Ground  

Ground Gas  Future  Site Occupiers 

Migration through soils or  groundwater  to indoor air. 

asphyxiation  or explosion(Severe) 

Nature  and  extent of Made Ground not  known  at  this  stage.    Intrusive  investigations required. 

Moderate 

Buildings  Explosion (Severe)  Moderate 

 

Page 19: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

  Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

13 

5.0  CONCLUSIONS AND RECOMMENDATIONS 

5.1  Environmental Risk Assessment 

The geo‐environmental assessment undertaken for the site has identified: 

The site  is  located  in a mixed  residential and urban area.   The site was developed with garage units  some  time prior  to 1961.   Changes  in  the locations and number of units are recorded on historic map records. 

The current land use for the site is with garage units. 

Based upon an assessment of  the  site  topography  it  is  considered  that initial development  comprised excavation  into existing natural deposits to create a development platform.  

No  site  investigation  data  has  been  provided  and  the  presence  and extent of any contamination is currently unknown. 

The current and previous uses of the site are considered unlikely to have created site wide contamination, although  localised occurrences may be present. 

 

Page 20: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

  Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

14 

5.2 GroundEngineering

At  present  no  geotechnical  ground  investigation  data  for  the  site  is  available  and consequently it is only possible to estimate and give an indication of the likely ground conditions.    An  intrusive  ground  investigation  would  be  required  to  provide  firm foundation  recommendations.    However,  tentative  recommendations  are  provided below. 

The  published  geological  data  suggest  that  superficial  deposits  comprise  glacial  till (boulder  clay) beneath  the  site.    Limited made  ground may  also be present  locally.  Solid strata are likely to comprise mudstone siltstone deposits. 

Made ground (if present) is not generally considered a suitable founding material and foundations  should  generally  be  taken  through  it  into  underlying  natural  strata  of adequate bearing capacity. 

It  is  anticipated  that  the  Glacial  Till  will  provide  a  suitable  bearing  strata  for  the proposed  residential  housing,  with  shallow  strip/trench  fill  foundations  likely  to provide the most economical foundation solution. 

It is likely that the Glacial Till will be classified as shrinkable and further deepening of foundations  will  be  required  locally  where  foundations  are  within  the  zone  of influence of existing  trees. These  zones depend on  the  soil  shrinkage potential, and the ratio of the tree mature height (H) and distance from the tree to the foundation (D) in accordance with Chapter 4.2 of NHBC Standards. 

New  foundation  positions  that  conflict  with  relict  foundations  should  be  taken  to greater  depths  than  the  relict  foundations  and  into  natural  ground  of  adequate bearing capacity. 

Where  service  trenches  cross  the  site  foundations  should  be  placed  below  a  line drawn up at 45o from the base of any service excavations. 

5.3 FurtherWork

It  is  recommended  that  intrusive  investigations  are undertaken  to  confirm whether there  are  any  potential  contamination  sources  onsite  and  to  provide  geotechnical information for substructure design.    In  line with NHBC Guidance  it  is recommended that ground gas monitoring standpipes are installed and monitored on a minimum of six visits over a three month period. 

It  is  therefore  recommended  that one days  (up  to 8  locations) window  sampling  is undertaken to provide information on the shallow soils, allow the recovery of samples for geotechnical and chemical  laboratory testing and allow the  installation of ground gas monitoring standpipes.  

   

Page 21: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

  Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

15 

6  UNCERTAINTIES AND LIMITATIONS 

6.1  General Comments 

This  report details  the  findings of work carried out  in December 2013.   The  report has been prepared by PWAG on the basis of available  information obtained during the  study  period.   Although  every  reasonable  effort  has  been made  to  gather  all relevant information, all potential environmental constraints or liabilities associated with the site may not have been revealed. 

The  report  has  been  prepared  for  the  exclusive  benefit  of  Barnfield  Construction Limited,  Greenvale  Homes  Limited  and  those  parties  designated  by  them  for  the purpose of providing geotechnical and geo‐environmental recommendations for the site.  The  report  contents  should  only  be  used  in  that  context.  Furthermore,  new information,  changed  practices  or  new  legislation  may  necessitate  revised interpretation of the report after the date of its submission. 

PWAG has used reasonable skill, care and diligence in the design of the investigation of the site. The inherent variation of ground conditions allows only definition of the actual conditions at the locations and depths of trial pits and boreholes at the time of the  investigation.  At  intermediate  locations,  conditions  can  only  be  inferred  and Groundwater findings described are only representative of the dates on which they were made and levels may vary.   

Information provided by third parties has been used in good faith and is taken at face value; however, PWAG cannot guarantee its accuracy or completeness.  

The work has been carried out  in general accordance with recognised best practice as  detailed  in  guidance  documents  such  as  the  CLR  11  Model  Procedures (Environment Agency 2004), BS5930:1999 +A2:2010 and BS10175:2011.    Important aspects  of  the  risk  assessment  process  are  transparency  and  justification.  Unless otherwise  stated,  no  assessment  has  been  made  for  the  presence  of  radioactive substances or unexploded ordnance.   

Unless  otherwise  stated,  the  chemical  testing  carried  out  for  this  report  was  not scoped to comply with  the requirements of the water supply company and  further work may be required.   

The  preliminary  risk  assessment  process  may  identify  potential  risks  to  site demolition  and  redevelopment  workers.    However,  consideration  of  occupational health and safety issues is beyond the scope of this report. 

Please note that notwithstanding any site observations concerning the presence or otherwise  of  archaeological  sites,  asbestos‐containing materials  or  invasive weeds such as Japanese knotweed, this report does not constitute a formal survey of these potential hazards.  

Any site boundary line depicted on plans does not imply legal ownership of land. 

Page 22: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

  Report No: 13186/G/1 Project Details: Broadway Garage Site, Helmshore, Haslingden, BB4 4HL Date: December 2013 

16 

7.0 REFERENCES 

1. Department of the Environment, Transport and the Regions and Environment Agency,  Model  Procedures  for  the  Management  of  Land  Contamination. Contaminated Land Report 11. 

2. Construction  Industry  Research  and  Information  Association  (CIRIA).  Contaminated Land Risk Assessment.   A Guide to Good Practice.  CIRIA C552 2001. 

 

 

Page 23: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Project No. 13186/G/1 Project Details. Broadway Garage Site, Helmshore, Haslingden, BB4 4HL   Date December 2013 

APPENDIX A Legal Framework 

Page 24: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Project No. 13186/G/1 Project Details. Broadway Garage Site, Helmshore, Haslingden, BB4 4HL   Date December 2013 

Legislative Background 

Environmental  liabilities  and  risks have been evaluated  in  terms of  a  source – pathway  ‐  

target relationship  in accordance with  the approach set out  in  the 1995 Environment Act, 

The  Contaminated  Land  (England)  Regulations  2000  and  the  DETR  circular  02/2000 

Environmental  Protection  Act  1990:  Part  IIA  Contaminated  Land.    Contaminated  land  is 

defined within  the  legislative  framework  as  land which  is  in  such  condition by  reason of 

substance in, on or under the land that: 

a) significant  harm  is  being  caused  or  there  is  a  significant  possibility  of  such  harm being caused; 

b) significant pollution of controlled waters is being or is likely to be caused. 

The potential for harm is based on the presence of three factors: 

Source:  Substances  that  are  potential  contaminants  or  pollutants  that  may  cause harm: 

Pathway: A potential route by which contaminants can move from the source to the receptor; and 

Receptor  or  target:  A  receptor  that  may  be  harmed,  for  example  the  waters environment, humans, water, flora and fauna. 

Where a source, pathways and target are all present a pollutant  linkage exists and there  is 

potential for harm to be caused.  Therefore, the presence of measurable concentrations of 

contaminants within the ground and subsurface environment does not automatically imply 

that  a  contamination  problem  exists,  since  contamination  must  be  defined  in  terms  of 

pollutant linkages and unacceptable risk of harm. 

The  nature  and  importance  of  both  pathways  and  receptors,  which  are  relevant  to  a 

particular site, will vary according to the  intended use of the site,  its characteristics and  its 

surroundings. 

The  key principle which underpins  this  approach  is  the  “suitable  for use”  criterion.    This 

requires  remedial  action  only  where  contamination  is  considered  to  pose  unacceptable 

actual or potential  risks  to health or  the environment and appropriate and  cost effective 

remediation techniques exist, taking into account the actual or intended use of the site. 

   

Page 25: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Project No. 13186/G/1 Project Details. Broadway Garage Site, Helmshore, Haslingden, BB4 4HL   Date December 2013 

Guidance 

PWA Geo‐Environmental Ltd (PWAG)  is part of a registered Engineering Practice which  is a 

member of the Association of Consulting Engineers (ACE). 

This report has been prepared in accordance with: 

CLR11 – Model Procedures 

Contamination  and  Environmental  Matters  –  Their  implications  for  Property Professionals (2nd Edition RICS Nov 2003) 

Brownfields – Managing the development of previously developed  land – A client’s guide, CIRIA 2002 

DEFRA  and  Environment  Agency  (EA)  publications  CLR7  –  10,  (subsequently withdrawn) supported by the TOX guides and SGV guides, dated March 2002 

DETR  Circular  02/2000,  Contaminated  Land:  Implementation  of  Part  IIA  of  the Environmental Protection Act 1990 

Environment  Agency  technical  advice  to  third  parties  on  Pollution  of  Controlled Waters for Part IIA of the EPA1990, May 2002 

And  any  other  protocols  advised  by  DEFRA  and  the  EA  and  guidance’s  prepared  by  BSI, 

CERTA, BURA, and other industry advisory bodies including BS5930 and BS10175. 

 

Judicial Precedents and Legislation 

The  following  non‐exhaustive  list  of  the  legislative  framework  documents  has  been 

considered in the compliance of this document. 

The Environment Act (1995) 

The Environment Protection Act (1990) 

The Water Resources Act (1991) 

The Radioactive Substances Act (1993) 

The Pollution Prevention and Control (England and Wales) Regulations (2007) 

The Contaminated Land (England) Regulations (2006) 

The Environment Act 1995  (Commencement No.16 and Saving Provision)  (England) Order (2000) 

The Contaminated Land (England) Regulations (2006) 

The Landfill Regulations (England and Wales) Regulations (2002) 

The Landfill (England and Wales) (Amendment) Regulations (2004) 

Rylands v Fletcher – Private Nuisance, Escape 

Health and Safety at Work Act 1974 

The Building Regulations 2011, Part C of Schedule 1 

The Controlled Waste Regulations 1992 

Special Waste Regulations 1996 

Page 26: pwa Geo Environmental Ltd · 2014. 8. 5. · Calls Wharf 2 The Calls Leeds West Yorkshire LS2 7JU T.0113 2372929 F.0113 2372701 Phase 1 Geo‐Environmental Assessment Proposed Housing

Project No. 13186/G/1 Project Details. Broadway Garage Site, Helmshore, Haslingden, BB4 4HL   Date December 2013 

Neither  the  list  of  guidance  nor  the  list  of  judicial  precedents  and  legislation  should  be 

considered  exclusive  or  comprehensive.    There  are  approximately  85  individual  items  of 

legislation regulating contaminated land work.  PWAG makes every effort to ensure that all 

are adhered to in the preparation and presentation of this report. 

 

Technical Competence 

PWAG  is  a  leading  specialist  multi‐disciplinary  engineering  practice  working  in  the 

contaminated  land  market.    Most  of  the  workload  undertaken  by  PWAG  is  within  the 

property  development  market  dealing  with  brownfield  re‐development  and  associated 

environmental and geotechnical issues. 

Established in 2009 PWAG is at the forefront of environmental asset management providing 

expertise in environmental risk assessments, environmental site investigations, geotechnical 

site investigations and remediation strategies. 

PWAG’s  staff  come  from  a  wide  variety  of  backgrounds  within  the  geotechnical  and 

environmental  sectors  and  are  all  degree  qualified.    Specialists  include  geotechnical 

engineers, geologists, chartered environmentalists and chartered engineers. 

PWAG’s  technical  protocols  are  described  in  our  reports  and  are  strictly  adhered  to  by 

quality control checks in the field and in the laboratory.  PWAG only uses UKAS and MCERTS 

accredited laboratories for all methods used to derive determinant concentrations. 

PWAG is working towards a quality assurance process under ISO9001:2000 which facilitates 

rigorous  in‐house  administrative  and  technical  protocols.    PWAG  also  initiates  a  robust 

health  and  safety program  for  each  site  and  ensures  the  regular  training of  staff  in new 

guidance’s and techniques.