QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)1
1.0) General:
The Quality Trophy is an ANNUAL APPRAISAL on the performance towards excellent
performance in Product quality, cost, timely completion, Safe working practices and Progress
achieved through Quality Management System made towards business excellence.
The applicant shall Study the criteria and make a self-assessment in the original copy either with
a tick mark against "YES" or "No" providing with an objective evidence for "YES" at the time of
assessing.
This trophy intends to increase Quality awareness and motivate all towards
1.1) Product Quality as an increasingly important element for competitiveness.
1.2) Adoption of successful quality strategies and benefits derived from implementation of
Quality Management Systems.
1.3) Effective implementation of Quality Management System at sites.
1.4) Effectiveness of corrective and preventive measures initiated at site.
1.5) Safe working practices implementation
2.0) Scope:
The awards will be given to one project in each BU for Electrical construction (Domestic)
Substation Business Unit
Industrial Electrification Business Unit
Transmission Line Business Unit
Railway Construction Business Unit
Transmission Line Factories
The original self-assessed booklet shall be submitted to QMS - HQ in hard and soft copies.
Applicants are requested to ensure the availability of all the objective evidences at the time
of assessment.
Non-availability of objective evidence / continuity breakdown in the workflow will lead to
counting of "NO during the assessment.
LLAARRSSEENN && TTOOUUBBRROO LLIIMMIITTEEDDELECTRICAL CONSTRUCTION (DOMESTIC)
QUALITY TROPHY APPLICATION
APRIL 2009 TO MARCH 2010
-
8/3/2019 Qt Application for Sites-2009-10
2/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)2
The awards will be distributed to winning job sites during New Year address of President -
Construction. The awardees list would be published in internal magazines. The site team
members of the winning project will be awarded a Trophy along with Certificate of Merit.
3.0) Application submission associated Processes and key dates:
EVP- Electrical Construction (Domestic) releases forms in Portal / e mail
Site would submit the filled up application to QMS - HQ
Evaluation of application and finalization of list of sites in consultation
with BU Head
Completion of Evaluation
Submission of recommendation along with assessment report to
HQ Committee for Winner selection
Declaration of Winner
Distribution of Trophy to Winners
27thOctober10
January11
10th November1
15th December10
20th December10
27th December10
5th November10
-
8/3/2019 Qt Application for Sites-2009-10
3/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)3
4.0) Eligibility:
50% or more Sales on erection achieved as of 31st March10, of the total contract value
and should have achieved / exceeded 90% of the budgeted/MTR Sales, GM for the
Assessment Year.
Sites closing early are to be informed to QMS HQ along with Project completion reports
for immediate assessment.
Site Photos, site-in-charge Photo and list of salient Features of the site shall be handed
over to assessor during the Initial assessment itself.
5.0) Assessment areas and scores:
Max.Score
1. PROJECT MANAGEMENT AND PLANNING - 30
2. SITE EXECUITON - 25
3. QUALITY MANAGEMENT SYSTEM - 104. QA / QC - 10
5. STORES MANAGEMENT - 10
6. EHS - 15
---------
Max. Total: 100
---------
6.0) Incomplete applications are liable to be rejected.
7.0) Site assessment will be carried out by HQ-QMS plus External.
-
8/3/2019 Qt Application for Sites-2009-10
4/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)4
APPLICATION FOR QUALITY TROPHY 2009-10
(To be submitted in electronic form as well as hard copy booklet)
1. Name of Project : __________________________________________
Job No :___________________________________________
Address : ___________________________________________
___________________________________________
Telephone: ____________________Fax: _________________________
Email : __________________________________________________
2. Highest ranking official in the Project:
Name________________________________________ PS No.___________
Address _______________________________________
_______________________________________
Tel. No.: Office _________________Home _____________Cell Ph. ______________
3. Category: Tick () as applicable
Substation Business Industrial Electrification Business
Transmissionline Business Transmissionline Factories
Railway Construction Business
4. No. of employees at peak ________________________
5. No. of workmen at peak__________________________
6. Project Value (original) __________________________________
7. Project Value (Actual / Expected) __________________________________
8. Date of project commencement (as per contract)____________________
Passport
Size of
project
manager to
be pasted
-
8/3/2019 Qt Application for Sites-2009-10
5/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)5
9. Date of project commencement (actual )____________________
10. Date of completion (as per contract)_______________________
11. Date of completion (Expected)___________________
12. Staff List for the Project as on 1st April09 to 31st March10 please attach the list
of staff showing the name, PS Number and duration of the team member in the
project for issuing of the certificate of merit.
13. Site In-charges critical review on strengths and opportunities for improvement
with respect to Quality (Min. 3 areas) Mandatory
-
8/3/2019 Qt Application for Sites-2009-10
6/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)6
ASSESSMENT FOR PROJECT MANAGEMENT AND PLANNING
NAME OF THE PROJECT:
PROJECT MANAGEMENT AND PLANNING APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCESSLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
1Receipt and availabilityof the contractdocuments
Tender documents
Technical Specifications
Techno commercial offers
LOI / LOA / Letter of agreements
Vendor offers / correspondences
Approved L2 Schedules
2
Review of the contract
documents and itsevidences
Kick Off Meeting (KOM) Date
KOM attended as per procedure
KOM Minutes
Contract Variation
PV Clause
Approved BOQ
Approved Drawings
3ACE Preparation andsubmission & approval
ACE Submission on
ACE Approved by
ACE Approved on
4Availability of ApprovedL2 Schedule
Submission on
Approved on
5MPCS duly approvedwithin a month from thedate of LOI
S0 to S10 Preparation
LOI date
S0 to S10 submission
S0 to S10 Approved
6S1- Schedule ofInvoicing
Regular updation
Review
Variation identification
Root cause analysis
Corrective action in line to the aboveto eliminate the root cause
Effectiveness of the corrective action
7S5-Schedule of Labourrequirement
Regular updation
Review
Variation identification
Root cause analysis
Corrective action in line to the aboveto eliminate the root cause
Effectiveness of the corrective action
-
8/3/2019 Qt Application for Sites-2009-10
7/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)7
PROJECT MANAGEMENT AND PLANNING APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCESSLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
8S6-Schedule of Materialrequirement & status
Regular updation
Review
Variation identification
Root cause analysis
Corrective action in line to the aboveto eliminate the root cause
Effectiveness of the corrective action
9S8-Schedule of Directcost
Regular updation
Review
Variation identification
Root cause analysis
Corrective action in line to the aboveto eliminate the root cause
Effectiveness of the corrective action
10S9-Schedule of Indirectcost
Regular updation
Review
Variation identification
Root cause analysis
Corrective action in line to the aboveto eliminate the root cause
Effectiveness of the corrective action
11 Job Cost Report
Regular updation
Review
Variation identification
Root cause analysis
Corrective action in line to the aboveto eliminate the root cause
Effectiveness of the corrective action
12 Daily progress
Preparation
Review
Decision / Direction
Action
Effectiveness
13 Weekly progress
Preparation
Review
Decision / Direction
Action
Effectiveness
14 Monthly progress
Preparation
Review
Root cause analysis & correctiveaction
Effectiveness of corrective action
-
8/3/2019 Qt Application for Sites-2009-10
8/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)8
PROJECT MANAGEMENT AND PLANNING APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCESSLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
15Review of objectives &targets in terms ofquality , cost & time
objectives for Planning
Monitoring of performance
Action plan on adverse performance
16Statutory & regulatoryrequirements
list of Statutory & regulatoryrequirements
Compliances to the requirements
17 Invoicing
Validation to period for invoicingrequired vs invoicing actual
Validation to Submission
Validation to Collection
Effectiveness of the cycle time
18Winding up & Projectcompletion
Timely winding up meeting
Monitoring as per the Demobilizationplan
Final bill clearances from clients
Project completion certificates fromclient
Project completion report submissionto HQ
19Sub-contractorManagement
No of Sub Contractors engaged at Site
Sub-contractor evaluation beforeinduction
Screening of subcontractor workmen
Rating of subcontractor
Objective Remarks:
-
8/3/2019 Qt Application for Sites-2009-10
9/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)9
ASSESSMENT FOR SITE EXECUTION
NAME OF THE PROJECT:
SITE EXECUTION APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCESSLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
1 Process identification
Sequence of Processes identification
List of processes and sub processavailability
Approved Work Instructions /Procedures
Weekly & daily planning for executingthe activities
Record of Approved Drawings
2 Drawings /Deliverables
Receipt and updation of the approveddrawings; issue & control on themovement of the drawings
Preparation or coordination for as builtdrawings
Control of Clients data/Drawings
List of codes & standards for referencewith regular updation to requirements
Coordination for obtaining customerapprovals for materials, drawings orany deliverables in time from theclients
3 Input verification
Validation of materials to therequirements before considering asinput
Competency of People
Condition of Machines
4 Process verification
Control parameters identified forexecuting the activities effectively
Monitoring and controlling of theprocess established
Effectiveness of control
Verification on in process authorization/clearance for erection process
Acceptance criteria specification in theQAP
Verification of output in line with QAP
Authorization or clearance validation
Acceptance by client
5Final verification andApprovals
Final inspection as per approved FQP
Final inspection reports
Client acceptance on final product
client submission
Objective Remarks:
-
8/3/2019 Qt Application for Sites-2009-10
10/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)10
ASSESSMENT FOR QUALITY MANAGEMENT SYSTEMS
NAME OF THE PROJECT:
QUALITY MANAGEMENT SYSTEMS APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCESSLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
1 Documentation
Receipt of QMS documents
Issue of QMS Documents
Control of the QMS documents
2 Implementation
Verification of QMS Implementationthough Audits
Audit plan -Plan Vs Actual
Audit Notification
Audit checklist
Audit summary report
Observations /NCR's
Timely compliances on auditobservation points
3 QMS Orientation
QMS orientation ensured to all newstaff at site
Effectiveness of the Orientation
4 Quality Objectives
Quality objectives for the Project site
Review and analysis on achievementof Quality objectives at regularintervals
Implementing the corrective measuresfor adverse performance
5 Trainings
Availability of Training plan
Training conducted as per plan
Availability of Training records
Effectiveness of Training
6CAPA / MonthlyReview Meetings
Conducting regular CAPA/Monthlyreview meetings
Decision / Direction
Effectiveness
7Control of Nonconformities (NCR)
Identification of NCR's through audits,daily inspections etc
identification of root causes
Implementation of Corrective action
Review of effectiveness of Correctiveaction
Initiating the actions to prevent theoccurrences
-
8/3/2019 Qt Application for Sites-2009-10
11/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)11
QUALITY MANAGEMENT SYSTEMS APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCES
SLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
8
Customer complaints
& feedbackMechanism
Customer Compliant Receipt
Method of updation
Response to the client
Correction initiated
Root cause analysis & CorrectiveAction implementation
Effectiveness of Corrective action
9Customer satisfactionReports (CSR)
Receipt of CSR
Review and Feedback analysis of theCSR
Corrective actions on Customerfeedback on improvements
Feedback to clients on Action taken by
the site for improvements
10 Improvements
Identify area for Improvement
Analyze the process for improvements
identify the Preventive action foreliminating potential non conformity
Objective Remarks:
-
8/3/2019 Qt Application for Sites-2009-10
12/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)12
ASSESSMENT FOR QUALITY ASSURANCE / QUALITY CONTROL
NAME OF THE PROJECT:
QUALITY ASSURANCE / QUALITY CONTROL APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCES
SLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
1 QA/QC functions
Approved work Procedures / Qualityassurance plans / checklists
Work done as per the stated methodstatement and checked at differentstages.
In process inspection as per approvedprocedure
Inspection reports/records forinspection
Updation of Checklists
2 Calibration
List of Measuring equipment
Calibration plan
Calibration schedule
Calibration status-Required vs actual
Issue of calibration certificates
3Control of process andproduct nonconformities
Non conformities identified during theprocess or product verification andvalidation
Correction
Root cause analysis
Corrective action implemented
Effectiveness of Corrective action
4 Best PracticesNumber of best practices identified andimplemented
5 Benefits
Cost
Quality
Time
Implemented in QMS
Objective Remarks:
-
8/3/2019 Qt Application for Sites-2009-10
13/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)13
ASSESSMENT FOR STORES MANAGEMENT
NAME OF THE PROJECT:
STORES MANAGEMENT APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCESSLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
1Storage area as per layout drawing
Semi covered
Closed area
Open yard
2Receipt of thematerials
Storage procedure & Loading andunloading instructions
Designated area for receipt
Purchase order(PO)/LR/DC
Source inspection clearance report
Manufacturer's TC
3Inspection of thematerial at the storeyard
Physical verification for damages
Inward material inspection report
Designated area for accepted &rejected materials
Reporting against shortage or damageof the materials
Action on the damaged materials
Non acceptance report for rejectedmaterials
Inspection clearance by site and client
Regular updation for material receiptnote
4Storage of theMaterials
Storage as per designated areas
All the materials are identified andreadily traceable
5 Issue of the Materials
Indent place by the user shallnecessarily cover cost code, materialcode, Quantity and description
Signature of Authorized person as perauthorization list
Updating of Record/Bin cards
6 Monitoring & Control
Follow of FIFO
Monthly stock statement
list of materials (Own)
List of client supplied materials
Periodic physical verification againststock
updation of Materials/consumablesissued to Sub contractors (free)
updation of Materials/consumablesissued to Sub contractors (Chargeable)
Verification of Shelf life materials
Daily stock position of critical items
Objective Remarks:
-
8/3/2019 Qt Application for Sites-2009-10
14/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)14
ASSESSMENT FOR ENVIRONMENT, HEALTH & SAFETY
NAME OF THE PROJECT:
ENVIRONMENT, HEALTH & SAFETY APPLICANTASSESSMENTBY QMS - HQ OBJECTIVE
EVIDENCES
SLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
1 EHS Plan
Availability of EHS plan
Implementation of EHS procedures
Awareness of EHS practices in all thestaff & workman
2 EHS Audits
EHS audits complying with plannedrequirements
Compliances to EHS requirements
3 Emergency Evacuationplan
Availability of Emergency Evacuationplan
Emergency preparedness andresponse time testing
4EHS Educationprogram
Pep talk before the start of erectionactivities
EHS awareness initiatives
5Awards won by site forEHS
Award certificate
Objective Remarks:
-
8/3/2019 Qt Application for Sites-2009-10
15/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)15
ASSESSMENT FOR FINANCIAL PERFORMANCE
(Assessment Financial Year: 2009-2010)
NAME OF THE PROJECT:
FINANCIAL PERFORMANCEBUDGETED
(ACE)ACTUAL
POSITIVE VARIANCE
OBJECTIVEVIDENCEAPPLICANT
ASSESSMENTBY QMS - HQ
SLNO FUNCTIONS REF DOCUMENTS YES NO YES NO
1Project Financialparameters -Budget Vs Actual
Sales
Gross Margin
PBIT
PBIT % of sales
Average Workingcapital (AWC)
Average Net fixedassets (ANFA)
EVA
ROCE (%)
Staff Man Months
ROTE (PBIT/StaffMan Months)
2 InvoicingSubmission of Clientinvoice as percontract
3CollectionTargets
More than Sixmonths
Less than six months
Deduction of LD
Objective Remarks:
-
8/3/2019 Qt Application for Sites-2009-10
16/16
QUALITY TROPHY APPLICATION 2009 10 ELECTRICAL CONSTRUCTION (DOMESTIC)
MAIN ASSESSMENT SHEET
(For use by Applicant and QMS)
NAME OF THE PROJECT & REGION / TFL: PROJECT MANAGER NAME:
JOB CODE OF THE PROJECT: DATE:
SLNO
FUNCTION/ACTIVITYASSESSMENT
POINTSCOMPLIANCE
FOR "YES"COMPLIANCE
FOR "NO"% WEIGHTAGE
FOR " YES "
WEIGHTAGE OBTAINEDFOR " YES "
APPLICANT QMS - HQ
1PROJECT MANAGEMENTAND PLANNING
90 30%
2 SITE EXECUITON 25 25%
3QUALITY MANAGEMENTSYSTEM
40 10%
4QUALITY ASSURANCE /QUALITY CONTROL
20 10%
5 STORES MANAGEMENT 30 10%
6ENVIRONMENT, HEALTH &SAFETY
10 15%
GRAND TOTAL 100%
APPLICANT NAME: ASSESSOR NAME:
SIGNATURE: SIGNATURE:
DATE: DATE:
Recommendation:
HQ Committee evaluated the above parameters. After review, the site is recommended / not
recommended for Quality Trophy Winners 2009-10.
Reasons for Rejection:
Signature