qualification process of a gis 400 kv sf6 high voltage...

9
[email protected] Qualification Process of a GIS 400 kV SF6 High Voltage Circuit Breaker Controlled Switching Solution M. WALDRON 1 F. AÏT-ABDELMALEK 2 , A. FICHEUX 2 , J-L. RAYON 2 1 National Grid, United Kingdom 2 Alstom Grid, Aix-les-Bains, France SUMMARY During the past decades and thanks to major improvement of intelligent electronic devices (IEDs) in terms of reliability and costs, controlled switching solutions applied to high voltage circuit-breakers have offered a relevant electronic alternative to more conventional methods, usually used to reduce the switching transients and electrical constraints on the equipment. These controlled switching solutions are now embedded into so-called point-on-wave (POW) controllers. The success of controlled switching relies on two fundamental principles: Identification of a target moment for connecting or disconnecting loads and sources favourable to transient mitigation; Reliable estimation of the duration of the operation for the device being controlled in order to achieve effective switching operation at the predetermined target. Thus, one of the challenges in controlled switching application lies in the prediction of the duration of the operation, subject to the contingencies of the operating conditions. This paper describes the detailed qualification process conducted for a controlled switching solution at 420 kV level together with the deployment on the field. A focus is made on 2 types of applications for which National Grid in UK requires implementation of controlled switching solution: Controlled de-energization of shunt reactor Controlled closing of capacitive loads at zero voltage which is recognized as the most difficult duty. The first qualification process is related to the POW controller ability to operate accurately according to a pre-set switching sequence under various ambient and severe EMV conditions particularly present in GIS substation. The second one is oriented to the associated high-voltage circuit-breaker and its parametric model is established according to the new IEC technical report TR 62271-302 [1] issued by IEC and based heavily upon the work of Cigré WGA3.07 [2]. The third one consists of associating the POW controller with the said circuit-breaker to operate in power laboratory live synchronized switching operations. Finally, some site live start-up observation and performance evaluation are provided as a conclusion of this process. KEYWORDS Controlled Switching Solution, Qualification Process, Circuit-Breaker Behaviour, Point-on-Wave Controller, Asset Lifetime Extension 21, rue d’Artois, F-75008 PARIS A3-204 CIGRE 2014 http : //www.cigre.org

Upload: dinhdang

Post on 19-Feb-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

[email protected]

Qualification Process of a GIS 400 kV SF6 High Voltage Circuit Breaker Controlled Switching Solution

M. WALDRON

1

F. AÏT-ABDELMALEK2, A. FICHEUX

2, J-L. RAYON

2

1National Grid, United Kingdom

2Alstom Grid, Aix-les-Bains, France

SUMMARY

During the past decades and thanks to major improvement of intelligent electronic devices (IEDs) in

terms of reliability and costs, controlled switching solutions applied to high voltage circuit-breakers

have offered a relevant electronic alternative to more conventional methods, usually used to reduce the

switching transients and electrical constraints on the equipment. These controlled switching solutions

are now embedded into so-called point-on-wave (POW) controllers.

The success of controlled switching relies on two fundamental principles:

Identification of a target moment for connecting or disconnecting loads and sources

favourable to transient mitigation;

Reliable estimation of the duration of the operation for the device being controlled in order to

achieve effective switching operation at the predetermined target.

Thus, one of the challenges in controlled switching application lies in the prediction of the duration of

the operation, subject to the contingencies of the operating conditions.

This paper describes the detailed qualification process conducted for a controlled switching solution at

420 kV level together with the deployment on the field. A focus is made on 2 types of applications for

which National Grid in UK requires implementation of controlled switching solution:

Controlled de-energization of shunt reactor

Controlled closing of capacitive loads at zero voltage which is recognized as the most difficult

duty.

The first qualification process is related to the POW controller ability to operate accurately according

to a pre-set switching sequence under various ambient and severe EMV conditions particularly present

in GIS substation. The second one is oriented to the associated high-voltage circuit-breaker and its

parametric model is established according to the new IEC technical report TR 62271-302 [1] issued by

IEC and based heavily upon the work of Cigré WGA3.07 [2]. The third one consists of associating the

POW controller with the said circuit-breaker to operate in power laboratory live synchronized

switching operations. Finally, some site live start-up observation and performance evaluation are

provided as a conclusion of this process.

KEYWORDS

Controlled Switching Solution, Qualification Process, Circuit-Breaker Behaviour, Point-on-Wave

Controller, Asset Lifetime Extension

21, rue d’Artois, F-75008 PARIS A3-204 CIGRE 2014

http : //www.cigre.org

2

1. INTRODUCTION

The phenomena associated to switching capacitive loads and small inductive loads are well described

in the IEC technical report TR 62271-306 [3] and Cigré TB 050 [4]. Some resultant overvoltage can

be of significant magnitude and can require some form of limitation like use of surge arresters or point

on wave switching. In case of bank arrangement of cables or capacitors, additional phenomena need to

be considered (like inrush currents and associated high frequency transients).

Therefore, when switching capacitive or small inductive loads is of concern, specific requirements for

circuit-breakers intended to be used on such applications are specified by National Grid in their

technical specification related to circuit-breaker TS 3.2.1 [5].

Circuit-breakers intended for shunt reactor switching shall be capable of the addition of a controlled

opening facility to facilitate the minimization of re-ignition transients. Performance requirements

related to controlled switching facility for this application are the following:

- Operation of circuit-breaker applied to shunt reactor circuits shall not produce over voltages in

excess of 2 p.u. at the reactor terminals;

- Controlled opening facilities shall be demonstrated to be of sufficient accuracy to eliminate re-

ignitions.

Circuit-breakers intended for capacitive load switching shall be capable of the addition of a controlled

closing facility to facilitate minimization of closing transients when energizing either an earthed star

connected capacitor bank or parallel cable bank. Especially, it needs to eliminate strong inrush

currents that may occur during back-to-back random energization. Performance Requirements related

to controlled switching facility for this application are the following:

- The controlled switching system shall be capable of controlling the closing operations of the

circuit breaker such that the point of current initiation coincides with system voltage zero in

each phase with a tolerance of +/-1ms around the target voltage zero.

For both applications, the qualifications of the POW controller itself and the qualification of POW

controller associated with its circuit breaker are thus required.

According to National Grid requirement stated in [5], the circuit-breakers for intentionally non-

simultaneous pole operation shall be designed and tested in accordance with [1], which provides a

guideline to perform specific tests that allow characterization of the circuit-breaker intended to be

associated with a POW controller. They shall also be subjected to a series of live switching tests as

part of their final commissioning.

2. QUALIFICATION OF POW CONTROLLER WITH CIRCUIT BREAKER

2.1 POW Controller qualification

There is no specific IEC standard to design and qualify specifically the POW controller. However,

National Grid has issued two detailed specifications that are describing the tests to be performed to

qualify the controller as a stand-alone IED. References are TS3.24.54 [6] and TS 3.24.15 [7]

One of these tests is to check the accuracy of the POW controller to determine the optimum operation

moment and effectively issue command orders for various targeted switching angles.

The Point-on-Wave controller operates with high accuracy better than 0.1ms (<1.8° @50Hz).

Therefore the key issue is not the qualification of the controller itself, but the coupling of the POW

controller with its circuit-breaker.

2.2 POW Controller qualification with the circuit breaker

Controlled switching being considered for a switching application, the selection of the circuit-breaker

to perform its duty has to follow a specific process, out of IEC standard 62271-100 [8]. This is

3

requiring some additional test sequence, as given in next Figure 1 extracted from Cigré Technical

Brochure 264 [9].

To determine the key parameters of the circuit breaker for implementing controlled switching, the

recently issued technical report [1] provides guidelines to perform specific tests. An example of

qualification is described in the following chapters. From these specific tests, a parametric / behaviour

model of the circuit-breaker intended to be used for controlled switching can be established and

integrated into EMTP simulation model to verify adequacy with the transient switching performance

criteria [10]

The table I, extracted from [1], summarizes the tests sequences to perform in order to characterize the

circuit-breaker behaviour. From the results of these tests are derived:

- the operating time compensation laws to set in a POW controller to perform proper duty over

the full range of ambient conditions, assuming that the influence of each parameter is

considered independently.

- the pre-arcing and the arcing times.

Note that the influence of each parameter is considered independently

Table I: specific tests recommended by

IEC TR62271-302

Parameter definition tests

Measurement of mechanical scatter

Impact of control voltage

Impact of low temperature

Impact of high temperature

Impact of stored energy level

Impact of idle time

Impact of gas density on operating time

Determination of the rate of decay of dielectric strength

Determination of the rate of rise of dielectric strength

Figure 1: Flow chart for selection of the circuit-breaker

The qualification of the circuit breaker is performed for a specific application like opening on small

inductive loads or closing on capacitive loads. Therefore, for each application, some specific numbers

of parameters are required. Examples are detailed in next chapters.

3. OPENING OPERATION WITH SHUNT REACTOR APPLICATION

3.1 Characterisation of circuit breaker using shunt reactor type test

In order to verify adequate performance for shunt-reactor application, the circuit-breakers must be

tested according to the requirements of the IEC 62271-110 [11].

These tests are designed to take into account the transients of two kinds that occur during small

inductive current breaking:

Chopping overvoltages initiated with long arcing time and caused by the current interruption

prior natural zero crossing;

Steep front overvoltages initiated with short arcing time and subsequent re-ignition between

arcing contacts due to TRV rate of rise higher than RRDS inside interrupting chamber.

The results of these tests are used as an indication of the general behaviour of the circuit-breaker for

reactor switching application. They are also used to provide information regarding the suitability and

relevant parameters of the circuit-breaker in relation to the application of controlled opening

techniques as stated in [6]. Specifically the minimum arcing time without re-ignition, as well as

maximum arcing time producing eligible chopping overvoltage, have to be determined to set the

optimal effective arcing time window targeted for POW switching.

4

3.2 Characterisation of circuit breaker for shunt-reactor controlled opening operation

3.2.1 Determination of the arcing time window

As summarized in Figure 4

Minimum arcing time without re-ignition is derived from the test sequences performed at both

nominal condition and lock-out condition

Maximum arcing time is determined in line with insulation coordination study to limit the

suppression peak overvoltage at shunt-reactor terminals.

Therefore the arcing contact separation window to consider for POW controller setting

Figure 2 : Short arcing time re-ignition Figure 3 : CB during small inductive current

interruption test

Figure 4 : 400kV CB arcing time Figure 5 : 400kV CB opening time distribution

3.2.2 Determination of the opening time standard deviation

Circuit-breaker opening time scatter and standard deviation are determined by a set of 100 consecutive

opening operations at control voltage rated value (100%) and control voltage minimum value (70%)

and under stable conditions of all other influencing parameters.

During this sequence, operating times of arcing contact and signalling device used by POW controller

for CB timing measurement are measured.

It appears from the measurements performed that the opening time distribution behaves as a normal

(Gaussian) distribution with a standard deviation of less than 0.2 ms / 3.6°@50Hz.

Note: determination of the opening time compensation laws

During each test sequence, all other ambient influencing factors remain under stable conditions.

Compensation laws to program the controller are derived from these measurements, a mean value

from 30 operations being considered for each influencing parameter level.

0.8

0.9

1

1.1

1.2

1.3

1.4

1.5

1.6

1.7

0 30 60 90 120 150 180 210 240

Sup

pre

ssio

n p

eak

volt

age

(p.u

.)

Arcing time (°)

Re-ignition & Suppression peak voltage vs. arcing time

Ir = 270A (Pnom) Ir = 113A (Pnom) Ir = 113A (Pmin)

Re-ignition

0

5

10

15

20

25

30

35

40

-20 -15 -10 -5 0 5 10 15 20

Freq

uen

cy [

%]

Opening time deviation [° - Base 50Hz]

Opening time distribution

Uc=100% Uc=85%

Unwanted

re-ignition window

Unwanted

Overvoltage window Targeted window for

Contact separation

5

3.3 Test combination of POWC with CB

The determination of the minimum arcing time without re-ignition and maximum overvoltage allowed

at the reactor terminal allow setting the optimum window to target the arcing contact separation.

A test in laboratory of CB with associated POW controller to perform controlled opening operation is

not recommended by IEC TR62271-302. Indeed it can be skipped with regards to opening time narrow

scatter and low standard deviation that guarantee contact separation within a sufficiently wide

demonstrated window.

3.4 Field live test for commissioning

Following satisfactory laboratory acceptance tests and successful field commissioning tests during

normal conditions, the latest generation of POW controller was put into service in 2012 for one of the

National Grid project. The application was for controlled opening of shunt reactor in an outdoor GIS

application. The integration of this reactor onto the network was part of the London reinforcement

project and was put into service to meet the target of the 2012 London Olympics. It has now recorded

more than one year field operational experience, featuring successful reactor opening operations

within the targeted arcing window.

Typical results for shunt-reactor opening are shown below.

Figure 6 : 400kV outdoor shunt-

reactor CB

Figure 7 : Shunt-reactor current interruption record

4. CAPACITIVE LOAD CLOSING OPERATION

4.1 Phenomena associated to capacitive load switching with zero voltage making

The objective of controlled closing of a HVAC circuit-breaker is to synchronize the instant of current

flow initiation in the circuit with a targeted switching angle based on a reference synchronizing signal.

Practically it consists of closing at zero voltage across the arcing contacts (used to minimize the

phenomena of pre-strike) in order to get the current flow initiation while the arcing contacts are

closing.

Zero-voltage making is recognized as the most difficult duty since the derivative (d) of applied voltage

at circuit-breaker terminals is maximum when it is getting towards zero value. Refer to formula (1).

( ) p.u/rad (1)

4.1.1 Rate of decay of dielectric strength (RDDS)

Thus, the first principle for a circuit-breaker dedicated to perform controlled closing operations on

capacitive loads with zero voltage objective is to have a sufficient RDDS slope, to prevent from

adverse pre-strike phenomena. Typically, the corresponding slope must be higher than the voltage

derivative at its zero crossing. The closing speed of the circuit-breaker combined with SF6 dielectric

withstand are fundamental to guarantee succesful controlled energizing without prestrike. Figure 8

shows the example of a closing operation with a poor RDDS slope. Pre-strike is happening while the

arcing contacts are still significantly separated, and hence when there is a significant voltage across the

closing contacts. On Figure 10, the RDDS slope is higher, circuit is established when the arcing

contacts are just getting in touch and pre-strike is therefore eliminated in case of ideal closing at zero

voltage.

-0.5

-0.25

0

0.25

0.5

0.75

1

1.25

1.5

-300

-250

-200

-150

-100

-50

0

50

100

340 345 350 355 360 365 370 375 380

Vo

ltag

e [V

]

Time [ms]

Shunt reactor current interruption Usource_L1 Usource_L2 Usource_L3I_L1 I_L2 I_L3

Cu

rren

t [A

]

Arcing contacts Separation

Current Interruption

6

Figure 8 : pre-strike in circuit-breaker with poor

RDDS

Figure 9 : circuit-breaker zero-voltage closing

characteristics Figure 10 : pre-strike eliminated in circuit-

breaker with high RDDS

4.1.2 Closing time standard deviation

High slope RDDS is nevertheless not substantial enough to perform proper operation. Indeed, large

closing time scatter may statistically lead to significant prestrike voltages. The second principle for

circuit-breaker performance is a low closing time scatter. It should be low enough to allow a narrow

making window, as shown on Figure 11. It can be clearly seen in this figure that, by targeting the

voltage zero, the pre-strike voltage at the early & late limits of the RDDS envelope differ significantly.

4.1.3 Optimized controlled closing

From the previous statement and figures, it is clearly understandable that optimal switching

performance cannot be reached without any additional contribution coming from the Point-on-Wave

controller intended to synchronize the circuit-breaker. It has to integrate the switching device

characteristics, the RDDS slope and the closing time standard deviation, and delay the target time for

closing slightly from voltage zero in order to optimize the control of the maximum pre-strike voltage,

thus equilibrating the risk of pre-strike (refer to Figure 12). Shifting delay is defined by formula (2)

with being the closing time standard deviation.

( )

(2)

Figure 11 : impact of CB closing time scatter on pre-

strike characteristics Figure 12 : optimized controlled closing operation

4.2 Characterisation of circuit-breaker for closing operation

4.2.1 Determination of the rate of decay of dielectric strength (RDDS)

The circuit-breaker is tested in high voltage test laboratory with rated operating conditions and

following pre-conditioning at lock-out operating conditions. Test voltage applied is twice the rated

voltage. The preferred methodology recommended by [1] to determine the RDDS is the “around the

clock method” consisting in delaying by 15° the closing order from one operation to the consecutive

one.

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

-90 -80 -70 -60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90

Vo

ltag

e (p

.u.)

Angle [°]

Controlled closing - Zero voltage making

Voltage across CB CB RDDS > (d) CB RDDS < (d)

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

-90 -80 -70 -60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90

Vo

ltag

e [

p.u

.]

Angle [°]

Controlled closing - Zero voltage making

Voltage across CB CB RDDS > (d)

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

-90 -80 -70 -60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60 70 80 90

Vo

ltag

e (

p.u

.)

Angle (°)

Controlled closing - Zero voltage making

Voltage across CB CB RDDS > (d) dispersion

7

During each closing operation, instant of contact touch, instant of pre-strike and pre-strike voltage are

measured. The RDDS is derived from the following measurements (see Figure 13):

- RDDS slope is determined for both positive and negative polarities;

- RDDS at lock-out conditions after pre-conditioning of the circuit breaker still exhibits a slope

higher than the voltage zero derivative (design criteria for CB intended to be used in

controlled switching applications).

Figure 13 : 400kV CB single interrupter RDDS Figure 14 : 400kV CB closing time distribution

4.2.2 Determination of the closing time standard deviation

Circuit-breaker closing time scatter and standard deviation are determined by a set of 100 consecutive

closing operations at control voltage rated value (100%) and control voltage minimum value (85%)

and under stable conditions of all other influencing parameters. During this sequence, operating times

are measured for the arcing contacts and signaling devices used by POW controller for CB timing

measurement. It appears from the measurements performed that the closing time distribution behaves

as a normal (Gaussian) distribution with a standard deviation of around 0.4 ms / 7°@50Hz (Figure 14).

Note: determination of the closing time compensation laws

Compensation laws to program in the controller are derived from various measurement sequences.

During each sequence, all ambient influencing factors other than the one considered to establish the

compensation law, remain under stable conditions. A mean value from 30 operations is considered for

each influencing parameter like control voltage, temperature and SF6 pressure.

4.3 Control closing test at zero voltage

Tests in power laboratory have been carried out to demonstrate the performance of the combination of

POW controller function with the associated circuit-breaker. Controlled closing at voltage zero target,

which is the most difficult duty, was performed at KEMA test laboratory in order to determine the

making window specific to the circuit-breaker. This demonstrated making window remains applicable

for all other target points.

Controlled closing operations were performed using a Point-on-Wave controller. For the first time,

this controller was giving synchronized order to the circuit-breaker (Figure 16) instead of the usual

orders coming from the test laboratory.

The Point-on-Wave controller was set to issue closing command to the circuit-breaker in such a

manner that the current initiation coincides with voltage zero in a making window as narrow as

possible, typically +/-1ms, as required by National Grid specification [6]. Especially RDDS and

closing time standard deviation, determined during specific tests, are feeding the parameters file of

the POW controller to shift (slightly delay) the target for closing and thus limit the risk of significant

pre-strike voltage.

Controlled closing test sequence consists of two series of 20 closing operations, first series performed

on a circuit-breaker in new condition and second series on a pre-conditioned circuit-breaker (with T60

duties). The making window is derived from the measured values of synchronizing voltage zero

crossing time and current ignition time (Figure 15).

y = -0.014x

y = 0.0153x

y = -0.009x

y = 0.0087x

y = 0.0087x

y = -0.0087x

-1.5

-1

-0.5

0

0.5

1

1.5

0 10 20 30 40 50 60 70 80 90

Pre

-str

ive

volt

age

[p.u

.]

Pre-strike angle [°]

400kV CB - Single interrupter RDDS Pre-strike characteristics - CB new - Rated conditions

0

5

10

15

20

-30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30

Freq

uen

cy [

%]

Closing time deviation [° - Base 50Hz]

Closing time distribution Uc=100% Uc=85%

8

Target -1ms (-18°) Target Target +1ms (18°)

Figure 15 : Controlled closing test records – Making window determination

Figure 17 synthesizes the making time distribution obtained from the two closing series. It clearly

highlights how critical is the need of CB parametric model to perform proper controlled closing

operation with accuracy as short as +/-1ms.

Figure 16: RPH3 POW Controller & T155 CB in

KEMA Power Lab Figure 17: Making window

4.4 Field live switching test for commissioning

One year after the live switching of the POW controller with shunt-reactor application, a second

switching application has been implemented on the National Grid system at Hackney GIS substation.

The application is related to a HV cable back-to-back switching. Due to the long length of cables, the

switching application is similar to a back-to-back capacitor bank application, but with lower values of

inrush currents and frequency. As per National Grid specification, field live switching has been

performed and results for HV cable back-to-back energizing – 3 phases zero voltage making - are

shown below.

Figure 18 : 400kV indoor CB & Cable feeders Figure 19 : Capacitive load energization field record

(secondary values)

(a) Source side voltage [V / ms]

(b) Load side voltage [V / ms]

(c) Charging current [A / ms]

ITO 200 A pu

UTO 100kV pu

4014

unit 5 ms

ITO 200 A pu

UTO 100kV pu

4015

unit 5 ms

ITO 200 A pu

UTO 100kV pu

4026

unit 5 ms

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

-0.2

-0.1

0

0.1

0.2

0.3

0.4

0.5

-30 -20 -10 0 10 20 30

Vo

ltag

e (p

.u)

Switching angle (°)

420kV CB - Controlled closing test results Absolute voltage across CB (p.u.) RDDS

Making window (CB new) Making window (pre-conditioned CB)

-100

-50

0

50

100

(a)

-100

-50

0

50

100

(b)

-0.1

-0.05

0

0.05

0.1

380 390 400 410 420 430

(c)

Voltage across CB

CB current

9

5. CONCLUSION

POW controllers have positive impact on switching duties of circuit-breaker for various applications

where transients mitigation is required. Qualification of the circuit-breaker intended to perform

controlled switching operations together with the associated controller is a key issue.

The IEC technical report IEC TR 62271-302 gives good guidance to implement specific tests.

Field test are also needed to prove correct procedure and implementation.

First cases that followed this qualification process and implemented in UK prove that these

requirements are well defined to achieve properly the start-up of the complete solution “POW

controller along with circuit-breaker”.

In perspective, newly created Cigré WGA3.35 will provide “Guidelines and Best Practices for the

Commissioning of Controlled Switching Projects” to lead utilities to successful field operation.

BIBLIOGRAPHY

[1] IEC/TR 62271-302 - High-voltage switchgear and controlgear

Part 302: Alternating current circuit-breakers with intentionally non-simultaneous pole

operation; Edition 1, 2010-06

[2] CIGRE WG 13.07, “Controlled Switching of HVAC Circuit-breakers: Guide for Application”;

Part 1: Electra, No. 183, April 1999. Part 2: Electra, No. 185, August 1999.

[3] IEC/TR 62271-306 - High-voltage switchgear and controlgear

Part 306: Guide to IEC 62271-100, IEC 62271-1 and other IEC standards related to alternating

current circuit-breakers; Edition 1, 2012-12

[4] Cigré TB 050 - Interruption of small inductive currents; WG 13.02; 1995

[5] TS 3.02.01 - National Grid - Internal and Contract Specific Technical Specification - Circuit-

breakers; Issue 4 – July 2011

[6] TS 3.24.54 - National Grid - Technical Specification – Circuit-breaker Point-on-Wave

Switching Control; Issue 1 – March 2001

[7] TS 3.24.15 - National Grid - Technical Specification – Environmental and Test Requirements

for Electronic Equipment; Issue 1 – December 2000

[8] IEC 62271-100 - High-voltage switchgear and controlgear

Part 100: Alternating current circuit-breakers; Edition 2.1, 2012-09

[9] Cigré TB 264 - Controlled Switching of HVAC CBs - Planning Specification Testing; WG

A3.07; 2004

[10] Cigré TB 135 - State of the art of circuit-breaker modeling; WG 13.01; 1998

[11] IEC 62271-110 - High-voltage switchgear and controlgear

Part 110: Inductive load switching; Edition 3.0, 2012-09