quality assurance plan sparco for sulemanki.pdf

Upload: muhammad-irfan

Post on 02-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    1/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    TABLE OF CONTENTS

    Sr. No. Description

    PREFACE

    ABBREVIATIONS

    Section-1. QUALITY ASSURANCE ACTIVITIES

    1.1. Contractors Submittals

    1.2. Earthwork

    1.3. Concrete Work

    1.4. Bored Cast-In-Situ R.C.C. Piles

    1.5. Pile Load Test

    1.6. Stone Pitching & Stone Apron1.7. Brickwork

    1.8. R.C.C. Pipes & Laying

    1.9. Steel Sheet Piles

    Section-2. QUALITY CONTROL/QUALITY ASSURANCE TESTING

    2.1 Types of Material Tests

    2.2 Testing Arrangements/Equipment

    2.3 Testing Requirements

    Section-3. RECORD/REPORTING DOCUMENTS

    3.1 Laboratory Record/Reporting Documents

    3.2 Field Record/Reporting Documents (Field Inspection/Testing)

    Section-4. SAFETY REQUIREMENTS

    Section-5. STANDARDS & PROCEDURES

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    2/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    PREFACE

    This Quality Assurance Plan (QAP) is an effort to outline the activities of the Contractor

    in adequate details for the guidance of its staff and other relevant Personnel, during the

    construction activities of the project to satisfy the requirements of Contract. It requires

    that individuals have clearly defined responsibilities and lines of communication to enable

    all aspects of the work activities to be assessed and accepted and if a problem is discovered,

    the solution is quickly found. QAP cannot replace the experience of reasonable and

    responsible staff; however it can help them in selection of timely and sequential line of

    various activities and in keeping and maintaining retrievable record documentation. This

    QAP is specially designed for Rehabilitation and Upgrading of Sulemanki Barrage

    Project

    The Contractor is, in particular, responsible for the Quality Control of the Works as per

    Contract Specification . Consultants supervision and surveillance does not relieve the

    Contractor of his contractual obligations. The basic purpose of QAP is to ensure that the

    Quality Control System is in place and performing to the requirements of Contract

    documents, during the construction period.

    The quality requirements are based on provisions for technical specifications as per

    contract documents for R&U of Sulemanki Barrage. Maximum efforts have been exerted in

    making QAP an acceptable and tangible document for all levels of execution and supervisory

    staff and novice to experience. Technical notes are provided at places to develop field staffs

    approach and insight for a useful and effective supervision, without undermining adherence

    to the contract specification.

    The Contract Documents are the basis for this QAP, therefore, where an ambiguity is

    detected between the procedures and requirements of QAP and content of Contract

    Documents then the latter takes the precedence.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    3/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    The following are the objectives while formulating QAP.

    To define and adopt a sequential and systematic quality assurance line of action with

    participation of the other stake holders for ensuring of all submittals, procurement,

    execution of works and other on and off site construction activities. These activities mayalso include material supply, testing and reporting envisaged in the specification of the

    project.

    To maintain auditable record of all tests, inspections, procedures and corrective

    measures and any other information considered helpful.

    To define the assignment and responsibilities of the Contractors field staff and other

    relevant personnel at site with respect to Quality Assurance of the project viz a the

    Contractors Quality Control Programme and their interaction with the client and the

    Consultant.

    To prevent non-conformities through proactive Quality Assurance.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    4/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    ABBREVIATIONS

    A.C.I. American Concrete Institute

    A.R.E. Assistant Resident Engineer

    AASHTO American Association for State Highway and Transportation

    Officials

    ASTM American Society for Testing Material

    B.S. British Standards

    C.M.E. Construction Management Engineer

    C.R.E Chief Resident Engineer

    E.R. Engineers Representative (Consultants)

    FR Field Record Document (Inspection Note/Testing etc.)

    Geotech. Engr. Geotech Engineer

    Insp. Inspector

    The Engineer Consultants

    LOA Letter of Acceptance

    LR Laboratory Record (Testing etc.)

    M.E Material Engineer

    NSL Natural Surface Level

    P.M Project Manager

    PD PMU Project Director (Clients Representative)

    PIDA Punjab Irrigation & Drainage Authority

    PMU Project Management Unit

    Q.C.S. Quality Control Section

    (Geotech/Mat. Engr. + Field Lab.)

    R.E Resident Engineer

    SOP Survey of Pakistan

    TBM Temporary Bench Mark

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    5/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.1 CONTRACTORS SUBMITTALS

    1.1.1 Objective

    The objective of this Section is to guide the field staff of the Contractor regarding different

    submissions to be made in the form of check requests, test requests, approval requests and

    authorization requests for execution of work. These submissions will be made by for

    methodological construction execution works.

    1.1.2 Applicability

    The Contract Documents for R&U of Sulemanki Barragerequire the Contractor to submit

    certain documents to the Consultants, i.e. before, during and after the execution of the

    works. These documents / write-ups may include;

    Work Programmes (As per Contract specifications)

    Quality Control Test Results (As per Contract specifications)

    Drawings and data for Equipment (As per Contract specifications)

    Installation Instructions for Equipment (As per Contract specifications)

    Operation and Maintenance Manual for mechanical equipment (As per Contract

    specifications)

    Manufacturers Certificates for various Construction Materials like water stops,

    bearing pads, expansion joint fillers and sealants.

    The submittals for various items of Project Works are provided in the checklist CKL-1.1

    Checklist for Contractors Submittals for the guidance of the Contractorsfield staff.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    6/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.1 (1) CHECKLIST FOR CONTRACTORS SUBMITTALS

    General

    Sr. No. Submittal Document Format Time For Submission

    1.1 Contractors workProgramme including

    arrangements, order and

    timings

    Contractors Format

    As per Specification

    Within 28 days of delivery

    of LOA and updates when

    required

    1.2 Details of the

    Programme andResource Schedule

    Contractors Format

    As per Specification

    Within 28 days of delivery

    of LOA

    1.3 Request for Survey

    check by the Contractor

    Contractors Format Prior to commencement ofworks

    1.4 Contractors Quality

    Control Programme

    Contractors Format Prior to commencement of

    works

    These submissions shall be made by the Contractor to The Engineer for prior review,who shall forward these to the Consultants for detailed review and agreement/advice.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    7/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.1 (2) CHECKLIST FOR CONTRACTORS SUBMITTALS

    Earthworks and Caring & Handling of Water

    Sr. No. Submittal Document Format Time For Submission

    2.1 Plan for Protection and

    Diversion Works*

    Contractors Format Prior to Construction of

    protection and diversion

    works

    2.2 Plan for Dewatering of

    foundations to be

    submitted direct to The

    Engineer

    Contractors Format Prior to Commencement

    of dewatering operations

    2.3 Materials SourceApproval*

    Contractors Format Prior to commencement

    of component of work

    2.4 Quality Control/

    Assurance Tests to be

    submitted direct to The

    Engineer

    Consultants QAPSpecified Formats

    As per requirements of

    specifications and QAP

    2.5 Job Safety Analysis as

    per HSE requirements

    Contractors Format Prior to start

    Construction

    *These submissions shall be made by the Contractor to The Engineer for detailed review

    and agreement/advice.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    8/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.1 (3) CHECKLIST FOR CONTRACTORS SUBMITTALS

    Concrete Works

    Sr. No. Submittal Document Format Time For Submission

    3.1 Method Statement ContractorsFormat Prior to Construction

    3.2 Mill test Certificates for

    Steel Reinforcement

    ManufacturersFormat

    Along with delivery of steel

    at site

    3.3 Bar Bending Schedule FR-06 3 days Prior to

    Commencement of

    fabrication of Re-Steel

    3.4 Quality Control Tests for

    Concrete works

    Consultants QAP

    Specified Formats.

    As per requirements of

    specifications and QAP

    3.5 Manufacturers

    Certificate for Rubber

    water stops, bearing

    pads joint filler and

    sealants

    Manufacturers

    Format

    Prior to procurement

    3.6 Job Safety Analysis as

    per HSE requirements

    Contractors Format Prior to start Construction

    These submissions shall be made by the Contractor to The Engineer for detailed review

    and agreement/advice.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    9/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.1 (4) CHECKLIST FOR CONTRACTORS SUBMITTALS

    Bored Cast-in-Situ R.C.C. Piles

    Sr. No. Submittal Document Format Time For Submission

    5.1 Method Statement Contractors Format

    As per Specifications

    Prior to commencement

    of work

    5.2 Date of Survey and

    Location

    Contractors Format Prior to commencement

    of work

    5.3 Protective Measures Contractors Format Prior tocommencement of

    work

    5.4 Placement Schedule Contractors Format Prior to commencement

    of work

    5.5 Approval for Source of

    Material

    Contractors Format Prior to commencementof work

    5.6 Pile Construction Record QAP Format Within 24 hours of

    completion

    5.7 Quality Control Tests QAP Specified Format Within 24 hours of the

    completion of Tests

    5.8 Job Safety Analysis Contractors Format Prior to commencement

    of work

    These submissions shall be made by the Contractor to The Engineer detailed review and

    agreement/advice.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    10/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.1 (5) CHECKLIST FOR CONTRACTORS SUBMITTALS

    Pile Load Test

    Sr. No. Submittal Document Format Time For Submission

    6.1 Method Statement Contractors Format Prior to commencement of

    Test

    6.2 Calibration Certificate

    for Test Apparatus

    Contractors Format Prior to commencement of

    Test

    6.3 Pile Construction

    Record

    QAP Format Within 48 hours of

    completion of pile

    construction

    6.4 Pile Load Test Record

    and Report

    Contractors Format As soon as possible after

    completion of the Test.

    6.5 Job Safety Analysis Contractors Format Prior to commencement ofwork

    These submissions shall be made by the Contractor to The Engineer for detailed review

    and agreement/advice.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    11/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.1 (6) CHECKLIST FOR CONTRACTORS SUBMITTALS

    Mechanical Equipment

    Sr. No. Submittal Document Format Time For Submission

    7.1 QAP Contractors Format After 28 days of

    Commencement of Works

    7.2 Work Schedule, Method

    Statements & List of

    Contractors submittals

    Contractors Format After 28 days ofCommencement of Works

    7.3 Request for Approval ofSub-contractor for M & E

    Works

    Contractors Format Prior to procurement ofGates and Hoists

    7.4 Design calculations &

    Shop Drawings for

    Mechanical & Electrical

    Plants

    Contractors Format Prior to start of

    fabrication of each

    component of work

    7.5 Manufacturers Schedule& Method Statements

    Contractors Format Prior to start offabrication of each

    component of work

    7.6 Installation Schedule and

    Detailed Procedure

    Contractors Format At start of each

    component of work

    7.7 Operation and

    Maintenance Manual

    Contractors Format When gates and gearings

    have been installed

    7.8 As Built Drawings Construction

    Drawings

    45 days after Certificate of

    Completion

    7.9 Job Safety Analysis Contractors Format Prior to commencement

    of work

    These submissions shall be made by the Contractor to The Engineer for detailed review

    and agreement/advice.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    12/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.2 EARTHWORK

    1.2.1 Objective

    Objective of this Section is to provide the recommended guidelines to the Contractors field

    staff for their guidance in performing quality assurance of earthwork for structures and for

    the canal embankments etc. pertaining to the Permanent Works

    This Section covers the open cut/foundation excavations, foundation backfills for the

    structures and earthwork for irrigation canal embankments. The recommended guidelines

    can also be used for other similar works and earthwork required for diversion

    arrangements.

    1.2.2 Construction Equipment

    Selection of type of excavation and compaction equipment must be done wisely keeping in

    view the bulk of work and efficiency of the equipment and that the selected equipment is

    capable and adequate to perform the required earthwork. The following may be deployed as

    per the nature of work involved;

    Excavators

    Dozer and Rippers

    Tractors with implements

    Front End Loaders

    Dragline Excavators / Cranes

    Dump Trucks

    Motor Graders

    Water Bowser

    Dewatering Arrangements Compactors(Rollers)

    Flood Light Arrangements

    1.2.3 Inspection

    Setting out details on site as per design will be the responsibility of the field staff.

    The Consultants through their own field staff shall check the setting-out accuracy,

    survey control for NSL and design levels by joint survey with Contractor. These

    surveys shall be carried out by Contractors surveyors in the presence of

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    13/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    Consultants Inspectors. The site inspector .shall monitor the excavation slopes for

    stability and compaction of the sub grade and fills, etc.

    If the Contractor encounters wet or slush, he is required to report to the Consultants

    Site Engineer who will jointly inspect the site, evaluate according to Earthwork SubClause of Technical Specifications of Contract Documents and submit their

    recommendations for approval by the Engineer.

    The Control of moisture and compaction of soils in the embankment of canals and

    compacted earth consists of inspection of the material used, checking the amount

    and uniformity of the soil moisture, maintaining the thickness of layer, and finally

    determining the percentage of relative Dry Density of the compacted fill.

    The relative Dry Density of the compacted fill is determined on the basis of FieldDensity Tests and the Reference Laboratory Compaction Tests. The Field Density

    Tests shall be performed by the Contractors staff as and when directed by the

    Engineer In-charge or Site Inspectors.

    Tests at critical areas shall be carrying out by Consultants staff and verified in

    Consultants Field Laboratory.

    The Standard/Modified Proctor Compaction Tests are used as Reference Laboratory

    Tests for fine grained clayey soils. These tests shall be performed at the ContractorsField Laboratory.

    The Maximum and Minimum Dry Density Test results (from external laboratory) are

    used as Reference Laboratory Tests for cohesion less sandy soils.

    The soils having less than 12% passing No. 200 sieve are defined as sandy or non-

    cohesive soils.

    The Site Inspector should see that all perishable matter and any soil which may

    become unstable upon saturation, such as highly organic soils, loose silts, very fine

    sands/silts and expansive clays etc. are not present in the foundations. These soils

    either need to be removed or improved to the extent necessary to provide a safe,

    stable foundation or sub-grade under operating conditions.

    A good bond between the foundation and first layer of fill is achieved by moistening

    the foundation rather than using a very wet embankment layer.

    For Quality Assurance (QA) of earthwork operations the Staff shall proceed in

    accordance with CKL-1.2(1) Checklist for Structural Excavations and CKL-1.2(2) Checklist for Canal Earthworks.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    14/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    An important function of inspection is to determine when and where to make Field

    Density Tests. These tests should be made in areas where degree of compaction is

    doubtful.

    Areas of doubtful density are sometimes detected by observation. Possible locations

    of insufficient compaction include:

    The junction between areas of mechanical tamping and rolled earth fill

    embankment along abutments or cut-off walls.

    Areas where rollers turn during rolling operations.

    Areas where too thick a layer is being compacted.

    Areas where improper moisture content exists in the soil.

    Areas where less than specified number of roller passes were made.

    Areas where oversized rock which has been overlooked, is contained in the

    fill.

    Areas containing material differing substantially from the average.

    1.2.4 Specified Limits for Degree of Compaction

    While performing control over compaction the limits given below from specifications should

    be observed.

    Compaction Requirements

    Description Cohesive Soils Cohesionless Soils

    Backfill around Structures

    above foundation level90% Modified Proctor Dry Density 70% Relative Density

    Special Backfill and Fill

    beneath Structures

    (Foundations)

    95% Modified Proctor Dry Density 80% Relative Density

    Foundation under Canal

    Embankment / Sub-grade

    for Lining

    90% Modified Proctor Dry Density 70% Relative Density

    Canal Embankments

    (Main or Branch)90% Modified Proctor Dry Density 70% Relative Density

    Disty/Minor

    embankments90% Modified Proctor Dry Density 70% Relative Density

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    15/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.2.5 Frequency of Control Tests

    The recommended tests, their procedures, frequency and the required facilities for an

    effective quality control/assurance of earthwork are presented in Section 2.3 Testing

    Requirements. The contractors field staff is required to ensure that these tests are

    performed as per specified frequencies in the recommended laboratories or at site. The field

    tests should be performed in the presence of the Engineers site Inspector and the results

    recorded immediately on completion of the test, duly signed by the authorized

    representative of the Contractor and Consultants. An independent record of the tests

    should also be maintained by consultants field staff, in addition to the submittals of the

    Contractor.

    1.2.6 Safety

    The Contractor is to ensure and monitor compliance of the requirements of the Law of

    Pakistan for safety, health and environment impact, in the domain of the construction

    contract. For safety check proceed in accordance with CKL-5.1 Safety.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    16/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.2 (1) CHECKLIST FOR STRUCTURAL EXCAVATIONS

    Sr.

    No.Issues Action by

    Record/Reporting

    Document

    1. Level of TBMs established by theContractor, Confirm by Survey Control.

    Engineers Rep.

    Contractors

    Surveyor

    Survey & Level

    Book and FR-02

    2. NSL by checking of the survey data andrecord entries. Check and approve by

    Survey Control.

    3. Complete setting out/layout. Check by

    Survey Control and Dimensional

    Inspection.

    4. Location and level of level pegs, Checkby visual inspection and Survey

    Control.

    5. Location of spoil or dump for excavatedmaterial. Optional Check by Visual

    Inspection.

    Lab TechnicianFR-02

    6. Deployment of proper Equipment.Discuss with Contractor and Ensure.

    Lab TechnicianFR-02

    7. Adequate dewatering to desired levels,before start of excavation below water

    table. Water level to be maintained 3 ft.

    below the lowest foundation level.

    Ensure by physical inspection

    Lab Technician

    FR-02

    8. Complete information about conditionof soil i.e. dry, wet or slush. Check by

    physical inspection and record

    observations.

    Lab Technician

    FR-02

    9. Stability of excavated slopes. Ensure byphysical inspection.

    Lab TechnicianFR-02

    10. Final levels of excavated surfaces andrecord entries. Check by Survey Control

    and make record entries.

    Engineers Rep.

    Contractors

    Surveyor

    Survey & Level

    Book and FR-02

    All actions should be taken in accordance with the Contract Specifications and Contractors

    Work Methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    17/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.2 (2) CHECKLIST FOR CANAL EARTHWORKS

    Sr.

    No.Issues Action by

    Record/Reporting

    Document

    1. Level of TBMs established by theContractor to be checked jointly.

    -Engineers Rep.

    -ContractorsSurveyor

    Survey & LevelBook and FR-02

    for comments

    2. NSL by checking of the survey data andmake record entries by Joint Survey.

    3. Complete setting out/layout. Check bySurvey Control and Dimensional

    Inspection.

    4. Location and level of level pegs, Checkby spot visual inspection and Survey

    Control.5. Final levels of excavated surfaces.

    Check by Survey Control.

    6. Deployment of proper equipment.Discuss with Contractor and Ensure

    Lab Technician FR-02 for

    comments

    7. Clearing, Grubbing and Stripping.

    Ensure by physical inspection.

    Lab TechnicianFR-02

    8. Approval of backfill material(excavated or borrowed). Check by

    physical Inspection or Test Procedures.

    Lab Technician Field

    Lab. FR-02/Letter

    LR-01, 03

    9. Compaction control during executionCheck by physical Inspection and Test

    Procedures.

    Lab Technician FR-03/A, FR-

    03/B, FR-03C,FR-

    02, LR-05

    10. Records of all Tests made during timeperiod. Update periodically.

    Lab Technician FR-04

    FR-05

    LR-05

    All actions should be taken in accordance with the Contract Specifications and Contractors

    Work Methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    18/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.3 CONCRETE WORK

    1.3.1 Objective

    Objective of this section is to provide the recommended guidelines, sequential

    inspection procedures and other relevant information to the field staff of the

    Contractor for their guidance in quality assurance of reinforced concrete and pre-

    stressed concrete pertaining to the permanent works being executed at site.

    1.3.2 Applicability

    This section covers Plain Cement Concrete (P.C.C.) the Reinforced Cement Concrete

    (R.C.C.) and pre-stressed concrete works for permanent structures as well as pre-

    cast works as shown on the drawings and as directed by the Project Manager.

    1.3.3 Construction Equipment

    The Contractor must ensure that the equipment is adequate to perform the concrete

    work.

    1.3.4 Inspection

    1) For quality assurance of construction activities the Consultants Supervisory

    Staff shall proceed in accordance with CKL-1.3 (1) Checklist for concrete

    work.

    2) For effective Quality Control, the Contractor is required to perform certain tests

    at different stages of the concreting process. These tests include tests to be

    performed on concrete ingredients, before start of the concreting works, tests to

    be performed during construction stages and the tests to be performed

    subsequently in the Contractors Field Lab. or in any other approved externallaboratory.

    3) A list of tests, the test procedures, test frequencies and the proposed testing

    arrangements are provided inSection 2.3 Testing Requirements.

    4) The required Record/Reporting Documents for the Consultants Field Staff are

    also listed in Section 2.3 Testing Requirements.

    5) To maintain an auditable and retrievable record of all Inspection Tests, Non-

    compliance and Corrective Actions etc. the provided proformas must be used by

    the Consultants Supervisory Staff.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    19/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    6) The Engineer is to ensure that the required tests are performed by the

    Contractor in accordance with the specified procedures and in the presence of

    his representative. He is required to maintain a complete record of these test

    results independently.

    1.3.5 Classes of Concrete

    Concrete for several structures and part thereof shall have 28-day compressive

    strength of 6 12 cylinders at least equal to the minimum allowable strength

    shown in the following Table:

    Class Nominal Mix*Compressive Strength at 28-days

    Cylinder Strength

    A 1:1:2 5000 Psi

    A 1:1 :3 4000 Psi

    B 1:2:4 3000 Psi

    C 1:2.5:5 2500 Psi

    D 1:3:6 2000 Psi

    E 1:4:8 1200 Psi

    * Actual Mix Ratio will be determined after Concrete Mix Design carried out in accordance

    with relevant Sub-Clauses of Technical Specifications of Contract Documents.

    1.3.6 Concrete Slump

    For various structural components the concrete shall have the following slump:

    Class Structural Component Slump

    A Pre-cast concrete 2 to 4

    B Concrete Piles 5 to 7

    C Canal Lining 1 to 3

    C Cut-off Walls 2 to 4

    B and CGeneral Reinforced Concrete for Bridge & other

    Structures2 to 4

    C Plain Concrete 2 to 4

    D Fill Concrete 2 to 4

    E Blinding/Lean Concrete 2 to 4

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    20/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.3.7 Nominal Maximum Aggregate Size

    The nominal maximum aggregate size to be used in various structural components

    shall be as follows: (Technical Specifications 5.2)

    General Use Nominal MaximumAggregate Size

    Blinding/Lean Concrete and Canal Lining "

    Maximum dimension of Structure less than 12 "

    Maximum dimension of Structure more than 12 1

    1.3.8 Concrete Mix Design

    The mix proportions for class of concrete mentioned in the specifications are

    nominal. The concrete mix design is required to be carried-out by the contractor

    under supervision of Engineers representative at field laboratory using cement,

    sand and aggregates from the approved source of supply.

    Required average strength fcr used as the basis of selection of concrete proportion,

    shall be in accordance with ACI 318 and provided in the under mentioned Table.

    Specified Compressive Strength fc(PSI) Required Compressive Strength f cr

    (PSI)

    Less than 3000 f c +10003000 to 5000 f c +1200

    Over 5000 f c +1400

    The concrete mix design for each class of concrete in addition to mix proportion will

    also provide water-cement ratio by weight (exclusive of water absorbed by the

    aggregate) which will be determined on the basis of producing concrete having

    suitable workability, density, impermeability, durability and the required strength.

    1.3.9 Concrete Pour Authorization

    The contractor is required to submit two copies in two different colours (white and

    pink) of Concrete Pour Authorization (CPA) Request Form FR-07 before starting

    concrete for any component of a structure. The Engineer should check all the items,

    before allowing pouring of concrete. In case of deficiency, that would be marked on

    the CPA slip and returned to the Contractor for rectification. The same CPA slip will

    be finally signed on satisfactory rectification. Pink copy will be

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    21/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    retained by the Engineer for reference and record. Contractors copy (white) should

    be kept at site by the Contractor.

    1.3.10 Safety

    Proceed in accordance with CKL-5.1 Safety.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    22/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.3 (1) CHECKLIST FOR CONCRETE WORKS

    Sr.

    No.Issue Action by

    Record/Reporting

    Document

    1. Physically inspect all theReinforcement Steel procured by the

    contractor and confirm adherence to

    the Specifications by Test Procedures.

    Lab Technician ManufacturersCertificate and/or

    External Lab.

    Format.

    2. Physically inspect, cement procured by

    the contractor and confirm adherence

    to the Specifications by Test

    Procedures.

    Lab Technician Manufacturers

    Certificate and/or

    External Lab.

    Format.

    3. Physically inspect, fine and coarse

    aggregates and confirm adherence to

    the Specifications by Test Procedures.

    Lab Technician Ref. Section 2

    4. Deployment of proper equipment.Discuss with Contractor and Ensure

    Lab Technician FR-02 forcomments.

    5. Receive Concrete Pour Authorization

    C.P.A. Request from the contractor.

    Lab Technician FR-07

    6. Check all items of C.P.A. as per

    requirements of specifications and

    Drawings and approve.

    Lab Technician FR-08

    7. Mixing, Transportation and Pouring of

    Concrete. Check by Physical Inspection

    and Test Procedure.

    Lab Technician FR-02

    8. Compressive Strength of ConcreteCylinders. Check by Test Procedures.

    Lab Technician. Ref. Section 2FR-09, LR-07

    9. Record of all Tests made during the

    period. Update Periodically.

    Lab Technician. Ref. Section

    FR-10

    All actions should be taken in accordance with Contract Specifications and Contractors work

    methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    23/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.4 BORED CAST-IN-SITU R.C.C. PILES

    1.4.1 Objective

    Objective of this Section is to provide the recommended guidelines, sequential inspection

    procedures and other relevant information to the field staff of the contractor, for their

    guidance in performing Quality Assurance of Bored Cast-in Situ R.C.C. Piles for Structures

    pertaining to the Permanent Works, being executed.

    1.4.2 Applicability

    This Section covers the construction of bored Cast-in-Situ R.C.C. Piles for Pile Load Tests,

    and Working Piles for various Structures, pertaining to the Permanent Works being

    executed by the Contractor.

    1.4.3 Construction Equipment

    The Contractor must ensure the adequacy of the deployed equipment for performing

    the job.

    1.4.4 Inspection

    The field staff is required to ensure setting-out accuracy, perform survey control for

    NSL and design levels. The required surveys are carried out by the Contractors

    Surveyors along with the Engineers representative.

    Each Pile shall be placed with its top being within 2 inches (50.8 mm) of the correct

    position as shown on the Drawings.

    Pile shall be cast as accurately as possible to the vertical. The maximum allowable

    deviation from the vertical shall not exceed 0.5 degrees (1:114).

    Pile heads shall be cut to the levels shown on the Drawings and the cut shall be level,

    smooth and horizontal.

    No pile boring shall take place within 48 hours of the concreting of any pile which is

    within a radius of 10 ft.

    Drilling of holes shall be done by straight or reverse rotary rig or any other suitable

    method.

    After completion of drilling operations the borehole length shall be checked andrecorded.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    24/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    The contractor may use Bentonite Slurry for stabilizing the hole.

    A manufacturers certificate showing the properties of the bentonite powder must

    be submitted by the Contractor.

    Concrete shall be placed within thirty minutes after it has been mixed.

    The concrete temperature should be maintained within 900F (320C) and

    410F (50C).

    Pouring of concrete shall be done by efficient tremie technique.

    The rate of placing concrete in the bentonite stabilized Hole shall not be less than 30

    ft. per hour or more than 50 ft. per hour.

    The discharge end of the tremie shall be kept submerged continuously in the

    concrete and it shall be kept full of concrete to a point well above the water surface.

    The tremine shall not be moved horizontally during a placing operation.

    Anchorage arrangements for lowering of re-steel cage and tremmie shall be

    sufficiently strong to avert slipping down/free fall of cage or tremmie pipe.

    The contractor shall not be permitted to place concrete while it is raining. Should it

    rain while the concrete placement is already in progress, the contractor shall carry

    on, with proper and sufficient precautions, the concrete placement operations until

    the pile is completed. The contractor shall cover the already placed concrete, while

    under settling conditions with polythene or similar impervious sheets.

    The Engineer must maintain an independent record of Pile Construction as per FR-

    11in addition to the submissions by the Contractor.

    1.4.5 Safety

    The Contractor should monitor compliance of the works with requirements of the Law of

    Pakistan for safety, health and environment impact, in the domain of the construction

    contract. For safety check proceed in accordance with CKL-5.1 Safety.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    25/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.4 CHECKLIST FOR BORED CAST-IN-SITU R.C.C. PILES

    Sr.

    No.Issues Action by

    Record/Reporting

    Document

    1. Location and rating of SOP or CanalBench Marks. Confirm handing over by

    the client.

    Lab Technician FR-01

    2. Receive request for Survey check by theContractor.

    Lab TechnicianContractors

    Format3. Contractors Method Statement ofConstruction of Piles. Study, Analyse and

    approve.

    4. Levels of TBM established by theContractor. Confirm by Joint Survey.

    A.R.E./Site

    Inspector

    Contractors

    Surveyor

    FR-02

    for comments

    5. Location of Piles as per approveddrawings. Check by Survey Control and

    Dimensional Inspection.

    6. Excavated ground Elevations for eachpile location by checking of the survey

    data and make record entries by joint

    survey.

    7. Deployment of proper equipment asdescribed in the Work Methodology

    submitted by the Contractor. Discuss

    with Contractor and Ensure.Lab Technician FR-02for comments8. Ensure presence of Contractors

    qualified experienced and competent

    persons to conduct and supervise,

    drilling and pile construction.

    9. Check by physical Inspection and TestProcedures, all materials to be used in

    piling work.

    Lab Technician. Ref. Concretework Section 4

    Item 1.3.

    10. Check by physical Inspection and TestProcedure. The execution of drilling of

    pile bore.

    Lab Technician FR-11

    11. Receive concrete Pour Authorization.Check all items and approve.

    Lab Technician FR-07

    12. The execution of concreting of pile.Check by physical Inspection and Test

    Procedures.

    Lab Technician FR-11

    LR-07

    13. Update Periodically records of all Tests

    made during time period.

    Lab Technician. FR-10

    LR-07

    All actions should be taken in accordance with Contract Specifications and Contractors Work

    Methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    26/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.5 PILE LOAD TEST

    1.5.1 Objective

    Objective of this Section is to provide the recommended guidelines, sequential inspection

    procedures and other relevant information to the field staff of the consultants, for their

    guidance in performing Quality Assurance of Pile Load Tests, being executed by the

    Contractor.

    1.5.2 Applicability

    This Section covers the Pile Load Test on single vertical Piles for the design confirmation

    and for the Proof Load Tests for Quality Assurance of working Piles.

    1.5.3 Apparatus for Applying Loads

    The apparatus for applying compressive Loads to the Test Pile shall be

    constructed so that the Loads are applied to the central longitudinal axis of the

    Pile, with minimum possible eccentric loading.

    A steel Test Plate of at least 2 in. (50 mm) thickness shall be centred on the

    Pile and set perpendicular to the longitudinal axis of the Pile.

    The size of Test Plate shall not be less than size of the Pile.

    The Test Plate shall be set in high-strength quick-setting grout. The hydraulic jack shall be centred on the Test Plate with a steel Bearing

    Plate of adequate thickness between the top of the jack ram and the bottom of

    the Test Beam.

    The complete jacking system including the hydraulic jack, hydraulic pump and

    pressure gauge shall be calibrated as a unit before each test to an accuracy of

    not less than 5% of the applied Load.

    The hydraulic jack shall be calibrated over its complete range of ram travel for

    increasing or decreasing applied loads.

    If it is not feasible to calibrate the complete jacking system as a unit, the

    pressure gauge may be calibrated independently in which case the jack piston

    should be measured to verify the area.

    If the hydraulic jack pump is to be left unattended at any time during the test, it

    shall be equipped with an automatic regulator to hold the Load constant as pile

    settlement occurs.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    27/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    Calibration report shall be furnished by the contractor for all testing equipment

    for which calibration is required which shall also show the temperature at

    which the calibration was done.

    1.5.4 Apparatus for Measuring Movements

    All reference beams shall be independently supported with supports embedded

    in the ground at a clear distance of not less than 8.0 ft. from the Test Pile.

    If steel reference beams are used, one end of each beam shall be free to move

    horizontally as the beam length changes with temperature variations.

    Dial gauges shall have at least a 2-in (50 mm) travel.

    The dial gauges shall have a precision of at least 0.01 in (0.2 mm).

    Smooth bearing surfaces such as glass shall be provided for the gauge stems. All the dial gauges, scales and reference points shall be clearly marked with a

    reference number or letter to assist in recording data accurately.

    1.5.5 Load Application by Hydraulic Jack acting against a Weighed Platform

    Schematic setup for applying loads to Pile using Hydraulic Jack acting against

    weighted Platform is shown in Fig. 1.6.

    Centre over the Test Pile a Test Beam of sufficient size and strength to avoid

    excessive deflection under Load. The clearance between the top of the Test Pile

    and the bottom of the beam after deflection should be enough to accommodate

    the necessary bearing plates and hydraulic jack.

    Centre a Platform on the Test Beam with the edges of the Platform parallel to

    the Test Beam supported by cribbing as far from the Test Pile as practicable but

    in no case less than a clear distance of 5.0 ft.

    Load the Platform with any suitable material such as soil with a total weight of

    at least 10% greater than the anticipated maximum Test Load.

    1.5.6 Test Loads

    The Test Pile for Pile Load Test for confirmation of Pile design shall be loaded

    up to 300%(or a max. of 200 Tons) of the Design Load or failure whichever

    occurs first.

    Cyclic loading sequence shall be used.

    The Test Pile for Proof Load Test shall be loaded up to 150% of the Design

    Load, by Standard Loading Sequence.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    28/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.5.7 Standard Loading Sequence

    Apply the Load in Increments of 25% of the Test Load (150% of Design Load).

    Maintain each Load Increment until the settlement is not greater than 0.01 in

    (0.25mm) per hour but not more then 2.0 hours.

    After application of the total Test Load, if the Pile has not failed and the

    settlement is not greater than 0.01 in (0.25 mm) per hour maintain the Load for

    12.0 hours otherwise allow the Total Load to remain on the Pile for 24 hours.

    After the required holding time, remove the Test Load in decrements of 25% of

    the Total Test Load with 1.0 hour between the decrements.

    If the Pile failure occurs continue jacking the Pile until the settlement equals

    15% of the Pile diameter.

    Pile is considered to have failed if settlement is more than 0.5 in(12.7mm).

    1.5.8 Cyclic Loading Sequence

    1stCycle

    Loading ( up to 100% of Design Load):

    Load Increments of 25% of Design Load (i.e. 0%, 25%, 50%, 75% and 100%).

    Each Load Increment to be maintained till the settlement rate is not more than

    0.25 mm/hour or for a maximum of 2.0 hours.

    Maintain 100% Load for one hour before unloading.

    Unloading:

    Unload with decrements of 25% of design Load (i.e. 100%, 75%, 50%, 25% and

    0%).

    Maintain each step for 20 minutes.

    2ndCycle

    Loading:

    1stStage (up to 100 % of Design Load)

    Up to 100% design Load use three steps 0%, 50% and 100%.

    Each step to be maintained for 20 minutes.

    2ndStage (From 100% to 300% or a max. of 200 Tons)

    Load increments of 25% each (i.e. 100%, 125%, 150%, 175%, 200%, 225%,

    250%, 275% and 300% or a max. of 200 Tons).

    Each Load increment to be maintained till settlement rate is not more than 0.25

    mm/hour or for a maximum of 2 hours.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    29/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    Maintain 300% (or a max. of 200 Tons) Load for 12 hours if settlement is not

    more than 0.25 mm per hour otherwise for 24 hours.

    Unloading:

    Unload in 25% of design Load decrements (i.e.300%, 275%, 250%, 225%,

    200%, 175%, 150%, 125%, 100%, 75%, 50%, 25% and 0%).

    Maintain each step for one hour.

    If the Pile fails, continue jacking the Pile till the settlement equals 15% of Pile dia.

    Pile is considered to have failed if settlement is more than 0.5 in. (12.7 mm).

    1.5.9 Safety

    The Contractor is to ensure compliance with requirements of the Law of Pakistan

    for safety, Health and Environment Impact, in the domain of the construction

    contract. For safety check proceed in accordance with CKL-5.1 Safety.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    30/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.5 CHECKLIST FOR PILE LOAD TEST

    Sr.

    No.Issues Action by

    Record/Reporting

    Document

    1. Details regarding Type of Load Test andLoading Sequence

    Geotech Engr./

    Cont. site engineer

    Letter/

    Memorandum

    2. The location of the Load Test Pile oridentification of Proof Load Test Pile.

    Check by Visual Inspection and Survey

    Control.

    Geotech Engr./

    Cont. site engineer

    FR-02

    3. Study and Analyse, contractors MethodStatement for Pile Test.

    Geotech Engr./

    Cont. site engineer

    ContractorsFormat

    4. Check by Physical Inspection and Test

    Procedures, construction of the Test Pilefor Load Test.

    A.R.E./Geotech

    Engr Cont. siteengineer

    Ref. Section-5

    LR-07FR-11

    5. Check by Physical Inspection and Test

    Procedure. All Materials, Equipment and

    arrangements for Loading Specification.

    Cont. site engineer FR-02

    6. Monitor/Inspect all stages of loading andunloading of Test Pile and keep

    independent records.

    Cont. site engineer FR-02

    7. Submit Pile Load Test Record andReport.

    Contractor Contractors

    Format

    8. Submit Pile Load Test Report toGeotech/Material Engineer.

    Lab Technician ContractorsFormat & Letter

    9. Recommendations for further PilingWork.

    Geotech Engr. Letter/

    Memorandum

    10. Recommendations A.R.E. FR-02or through

    a letter

    All actions should be taken in accordance with Part Two, Contract Specifications and

    Contractors work methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    31/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.6 STONE PITCHING & STONE APRON

    1.6.1 Objective

    Objective of this Section is to provide the scope of applicability of the recommended

    guidelines, sequential inspection procedures and other relevant information to the

    Contractors field staff , for their guidance in performing quality assurance of stone

    pitching and stone apron to the Permanent Work, being executed by the Contractor.

    1.6.2 Applicability

    This Section covers the placing of stone pitching and stone apron at the specified

    locations as shown on the drawings. The recommended guidelines can also be used

    for similar works elsewhere in the project, as directed by the Engineer.

    1.6.3 Construction Equipment

    The equipment specified in the contract Specifications are only to provide guideline

    to assist the Contractor in the selection of proper equipment. The Resident Engineer

    must leave the final selection to the contractor. The Contractor may deploy the

    following equipment.

    Excavators

    Dozer and Rippers

    Front End Loaders

    Dump Trucks

    Water Bowser

    Dewatering arrangements

    1.6.4 Inspection

    For Quality Assurance (QA) of Construction activities the Contractors Staff

    shall proceed in accordance with CKL-1.6 Checklist for Stone Pitching &

    Stone Apron.

    Base Filter Layer under Stone Pitching shall consist of well graded material

    as specified in BOQ and shown on the Drawings.

    The Stones individually shall weigh between 40-120 lbs with 80% shall be

    80 lbs or larger and not more than 5% shall weigh less than 40 lbs.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    32/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    All interstices in Stone Pitching/Apron shall be well filled with rock Spalls.

    The rock Spall shall be rock fragments size between 2 inches and 4 inches.

    The surface over which the base filter is to be placed shall be trimmed to the

    proper lines and grades and shall be moistened with water and tamped or

    rolled with suitable tools or equipment for the purpose of forming a firm

    foundation. Wherever over-excavation occurs it shall be backfilled with

    specially compacted fill.

    The base filter layer shall be placed to a uniform thickness and finished to

    reasonably smooth and even surface.

    Stone used in the Stone Pitching/Apron shall be clean rough quarry stone

    and shall be essentially free from dust, clay, vegetative matter and other

    deleterious materials. The stone shall be hard, tough, durable, dense,

    resistant to the action of water and air, and suitable in all respects for the

    purpose intended. The stones shall be hand packed and placed and bedded

    in such a manner that the completed stone pitching is stable and without

    tendency to slide.

    Construction of stone pitching shall commence at the lowest part of each

    structure or section of a structure or canal and continue progressively

    upward. The stones, largest of which shall be used at the bottob, shall be wellbedded on a layer of graded Graded Granular Material. In general the size of

    the stone used shall have its major dimension the depth of the specified

    pitching.

    Large open spaces between the stone shall be avoided.

    Stone shall be placed so as not to project above neat lines shown on the

    drawings.

    1.6.5 Quality of Stone

    While performing control over procurement and placement of stone and filter

    material, the following characteristics of stone and filter material from the

    specifications must be observed.

    Stone for pitching/Apron should be dense, sound, angular and resistant to

    abrasion.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    33/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    The loss in Los Angles Abrasion Test for large size Aggregates

    (ASTM-C535-96) should not exceed 10% by weight at 200 revolutions or

    40% by weight at 1000 revolutions.

    The loss in Los Angles Test for small size Aggregates (ASTM-C131-96)

    should not exceed 10% by weight at 100 revolutions or 40% by weight at

    500 revolutions.

    The Specific Gravity of stone (Saturated Surface Dry basis) shall be more

    than 2.60.

    1.6.6 Test Procedures Frequency and Facilities

    The recommended test procedures their frequency and required facilities for an

    effective quality control of stone pitching and stone apron are presented in

    QAP/Stone/Test Procedures.

    1.6.7 Safety

    The Resident Engineer must from time to time check the listed item in CKL-5.1

    Safety.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    34/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.6 CHECKLIST FOR STONE PITCHING AND STONE APRON

    Sr.

    No. Issue Action byRecord/Reporting

    Document

    1. Study and Analyse Contractors MethodStatement.

    -A. R.E. Rep.

    - ContractorsSurveyor

    FR-02

    2. Confirm by Survey Control Levels of

    TBMs established by the Contractor.

    3. Check by Survey Control and

    Dimensional Inspection Complete

    setting out/layout as per drawings and

    specifications.

    4. Check by visual Inspection and Survey

    Control location and level of level pegs.

    These should be clear of working area.

    FR-02 for comments

    5. Check by Physical Inspection and Test

    Procedures. The Quality of Base Filter

    Material, Pitching/Apron Stone and

    Rock Spalls.

    Cont. site engineer Test Results on

    External Lab. Format

    or Field Lab.

    6. The material of Base Filter, Stone and

    Rock Spall should be obtained from

    approved source.

    Cont. site engineer FR-02 for comments

    7. Ensure by Physical Inspection

    Placement of stone pitching and Stone

    Apron.

    Cont. site engineer FR-02

    8. Update Periodically Records of all Testsmade during the time period. Cont. site engineer Test Record File

    All actions should be taken in accordance with Part Two, Contract Specifications and

    Contractors work methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    35/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.7 BRICKWORK

    1.7.1 Objective

    Objective of this Section is to provide the recommended guidelines, sequential inspection

    procedures and other relevant information to the field staff of the consultants, for their

    guidance in performing Quality Assurance of Brickworks for Structures pertaining to the

    Permanent Works, being executed by the Contractor.

    1.7.2 Applicability

    This Section covers the construction of Brickworks for brick masonry and brick lining for

    various Structures, being executed by the Contractor.

    1.7.3 Construction Equipment

    The Resident Engineer must leave the selection of construction equipment to the

    Contractor.

    1.7.4 The Consultants Action

    The Consultants field staff will take appropriate action as recommended in the checklist

    CKL-1.7 Checklist for Brickwork.

    1.7.5 Quality of Bricks

    The bricks should be regular, uniform in shape and size.

    Bricks over-burnt, under burnt and irregular should not be used.

    All bricks in oven-dried condition should not absorb more than one sixth ofits weight when soaked for one hour in water at 70 0 F to 800 F and should

    show no efflorescence on subsequent drying.

    The average compressive strength of five (5) representative bricks should

    not be less than 2,000 lbs/in2when tested in accordance with ASTM.C-67.

    Each finished brick should be of standard size (9 x 4.5 x 3) first class and

    weigh between seven (7) and nine (9) pounds.

    All bricks should have a frog. 0.25deep on upper face.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    36/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    Each brick for lining should have standard size (9 x 4.5 x 3) first class.

    1.7.6 Mortar Composition

    Mortar for all brickwork should have mix ratio as specified in BOQ and sufficient water to

    produce the proper consistency.

    1.7.7 Mortar Sand

    Mortar Sand should be as per specifications of sand for concrete works.

    1.7.8 Water

    The water used for preparation of mortar should be free from objectionable quantities of

    silt, organic matter alkali, salts and other impurities.

    1.7.9 Safety

    The Resident Engineer should monitor compliance of the contractor with requirements of

    the Law of Pakistan for safety, health and environment impact, in the domain of the

    construction contract. For safety check proceed in accordance with CKL-5.1 Safety.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    37/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.7 CHECKLIST FOR BRICKWORK

    Sr.

    No.Issues Action by

    Record/Reporting

    Document

    1. Study and Analyse. Contractors Method

    Statement.

    - A.R.E. Rep.

    - ContractorsSurveyor

    FR-02

    2. Check by Survey Control and Dimensional

    Inspection, complete setting out/layout

    as per drawings. FR-02 for

    comments3. Check by Physical Inspection and Survey

    Control, location and level of level pegs.

    These should be clear of working area.

    4. Physically inspect Sand, Cement and

    Bricks and confirm adherence to the

    specifications by Test Procedure.

    External Lab or

    Field Lab Format

    and FR-02 for

    comments

    5. Discuss with and Ensure, deployment of

    proper equipment as described in the

    Work Methodology submitted by the

    Contractor.

    A.R.E./Site

    Inspector/ Cont.

    site engineerFR-02 for

    comments6. Check all items as per requirements of

    specifications and drawings.

    A.R.E./Site

    Inspector/ Cont.

    site engineer

    7. Update Periodically, records of all Tests

    made during the period.

    A.R.E./Field Lab. Test Record Files

    All actions should be taken in accordance with Contract Specifications and Contractors Work

    Methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    38/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.8 R.C.C. PIPES & LAYING

    1.8.1 Objective

    Objective of this Section is to provide the recommended guidelines, sequential inspection

    procedures and other relevant information to the field staff of the consultants, for their

    guidance in performing Quality Assurance of providing and laying R.C.C. Pipes, being

    executed by the Contractor.

    1.8.2 Applicability

    This Section covers the Reinforced Concrete spun pipes and includes all pipe formed

    culverts, inlets, conduits, underpasses etc.

    1.8.3 Construction Equipment

    The Resident Engineer must leave the selection of equipment to the Contractor.

    1.8.4 Inspection

    1.8.4.1 Quality of R.C.C. Pipes

    Consultants field staff will take appropriate action as recommended in

    Checklist CKL-1.8 Checklist for R.C.C. Pipes & Laying.

    All materials, methods of manufacture strength requirements for concrete pipes

    should conform to the requirements of ASTM C-76. Wall B. Class II.

    The inspector must read the relevant sections of ASTM C-76, BS.5911 and

    BS.2494 and thoroughly understand the requirements related to the R.C.C Pipes

    specified on the Drawings.

    The Manufacturers Certificate provided by the contractor should be studied

    carefully, to check conformance to the ASTM C-76 requirements.

    The joints for concrete pipes, bends and junctions shall be of spigot and socket

    type as per clause 17 of BS.5911 and BS.2494.

    The supplied R.C.C. Pipes should be inspected carefully and the rejection may be

    made on account of any of the following:

    Fractures or cracks passing through the shell, except for a single end crack

    that does not exceed the depth of the joint.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    39/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    Defects that indicate imperfect proportioning, mixing and moulding.

    Surface defects indicating honeycombed or open texture.

    Damaged ends, where such damage would prevent the making of a

    satisfactory joint.

    Failure to give a clear ringing sound when tapped with a light hammer.

    Exposure of the reinforcement when such exposure indicates that the

    reinforcement was misplaced.

    1.8.4.2 Excavation and Laying

    The excavation for pipeline should follow the lines and grades on the Drawings.

    The maximum distance from sides of the trench and the barrel of the pipes

    should be as shown on the Drawings.

    1.8.4.3 Joints for Reinforced Concrete Pipes & Fittings

    Joints for concrete pipes, bends and junctions shall be of the flexible spigot and

    socket type as specified in clause 17 of BS 5911 incorporating rubber gasket

    complying with BS 2494.

    1.8.4.4 Bends in Pipelines

    Where it is required to form a bend in a pipeline of more than 11 degrees, either

    a precast pipe bend which meets the requirements of ASTM C76 shall be placed

    or a manhole be installed to lessen the head loss.

    Except where pipes are to be laid in a concrete or gravel bed, pipes including

    bends shall be laid in a trench with the trench bed hand-shaped to support the

    pipe throughout the length of its barrel. Sockets or collars along the pipeline

    shall be accommodated by jointing holes formed in the bottom of the trench.

    1.8.5 Safety

    The Resident Engineer should monitor compliance of the contractor with requirements of

    the Law of Pakistan for safety, health and environment impact, in the domain of the

    construction contract. For safety check proceed in accordance with CKL-5.1 Safety.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    40/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.8 CHECKLIST FOR R.C.C. PIPES AND LAYING

    Sr.

    No.Issues Action by

    Record/Reporting

    Document

    1. Submit Method Statement. Cont. site engineer FR-02 forcomments or

    through letter

    2. Study and Analyse, contractors Source(Manufacturer) approval.

    A.R.E./Site

    Inspector / Cont.

    site engineer

    FR-02 and

    Contractors

    Format

    3. Physically inspect the pipes suppliedand check, the Manufacturers Certificate

    A.R.E./Site

    Inspector/ Cont.

    site engineer

    FR-02

    ManufacturersFormat

    4. Check by Physical Inspection and SurveyControl, the line, grade and depth of

    excavation etc. for Laying Pipes.

    Site Inspector

    Survey (Contr.)/

    Cont. site engineer

    FR-02

    5. Physically Inspect, excavation Backfill. A.R.E./SiteInspector

    FR-02

    6. Update Periodically, records of Tests orManufacturers Certificates during the

    period.

    A.R.E./Site

    Inspector/ Cont.

    site engineerRecord Files

    All actions should be taken in accordance with Contract Specifications, Contractors Work

    Methodology and other Contractors Submittals, as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    41/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    1.9 STEEL SHEET PILES

    1.9.1 Objective

    Objective of this Section is to provide the recommended guidelines, sequential inspection

    procedures and other relevant information to the field staff of the contractor, for their

    guidance in performing quality assurance of Steel Sheet Piling required for the construction

    of canal structures.

    1.9.2 Applicability

    This Section covers the furnishing, handling, transporting, cutting and driving Steel Sheet

    Piles as shown on the drawings or directed by the Engineer in accordance with the Contract

    Specifications.

    1.9.3 Construction Plant

    The Resident Engineer must leave the choice of the construction plant and temporary works

    for the sheet piling to the contractor. The pile-driving and extracting equipment may be

    either percussive or vibratory type. However, the method and the equipment proposed

    should not result in ground resonance which might adversely affect neighbouring existing

    structures or work under construction.

    1.9.4 Inspection

    For Quality Assurance of steel sheet piling construction activities, the

    Consultants Supervisory Staff shall proceed in accordance with CKL-1.10

    Checklist for Steel Sheet Piles.

    Steel Sheet Piles section shall be AU-14 made by ARCELOR or equivalent section

    approved by the Engineer.

    Steel Sheet Piles shall be capable of being interlocked one with another, to form

    a continuous wall or diaphragm.

    Polystyrene sheets to be fixed at the top of sheet piles shall conform to ASTM D-

    4. 549.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    42/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    The Bituminous material for sealing steel sheet piling interlocks shall be

    equivalent of the Noahs Pitch as manufactured by the Philip Carey

    Manufacturing Company of USA.

    Steel Sheet Piles which are of different types, cross-section, weight or lengthshall be stored in separate stacks.

    Piles during storage shall be supported clear from the ground on suitable

    bearers.

    The Piles shall be lifted and transported with adequate supports so that piles

    are not distorted or damaged in transit.

    The Piles shall be driven to lines, levels and dimensions shown on the Drawings.

    The line of piles shall not vary from the true line by more than 2.0 inches.

    The inclination of the plane of piles shall not vary from the true inclination by

    more than 1 in 100.

    The inclination of any pile in that plane shall not vary from the line of greatest

    slope in that plane by more than 1 in 200.

    The finished level of the tip of any pile shall not vary from the true level by more

    than one inch.

    The finished level of the bottom of any pile shall not vary from the true level by

    more than 1% of the specified length of pile.

    Piles shall be prevented from being driven below the true level during the

    driving of neighbouring piles.

    Pile driving shall not be assisted by jets of water or air directed into the ground

    except with the approval of the Engineer.

    Until the driving of a pile is completed, the Contractor shall not excavate below

    existing ground surface adjacent to the pile unless such excavation is either

    approved or ordered by the Engineer.

    The Contractor with the approval of the Engineer may excavate a trench in

    which the steel sheet piling is subsequently pitched and driven.

    If such a trench is allowed to be excavated the void between the piles and

    undisturbed ground shall be backfilled with reinforced cement concrete (1:2:4)

    immediately after driving of the piles is completed.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    43/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    Steel reinforcement to be provided for this concrete shall meet the minimum

    steel reinforcement requirements set forth in the ACI code 318-05 or as

    directed by the Engineer.

    Steel Sheet Piles in the permanent works shall be free from holes, other thanthose specified on the drawing or small holes less than inch diameter and not

    more than 8.0 inches from the top of the Piles to assist in pitching the piles prior

    to driving.

    All welding of piles shall be in accordance with the requirements of B.S. 5135 or

    an approved equivalent and splicing piles shall be full strength butt welds.

    Steel Sheet Piling against which concrete is to be cast shall be clean and

    watertight.

    All such steel sheet piling shall be free from loose rust, loose-mill-scale, oil,

    grease and earth or any other substance which is likely to prevent bonding

    between the concrete and the piles.

    The surface of steel piles, which shall not be buried in ground on completion of

    work, shall be blast cleaned and painted with black bituminous paint applied in

    two coats.

    The first coat shall be applied within 2.0 hours of blast cleaning and the second

    within 24 hours of application of the first coat.

    Concrete capping beam shall be formed of reinforced cement concrete, as

    specified and Cast-in-situ.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    44/59

    Rehabilitation & Upgradation of Sulemanki Barrage Quality Assurance Plan

    CKL 1.9 CHECKLIST FOR STEEL SHEET PILES

    Sr.

    No.Issues Action by

    Record/Reporting

    Document

    1. Confirm by Survey Control, level ofTBMs established by the Contractor.

    -A.R.E. Rep.

    - Contractors

    Surveyor

    Survey & Level

    Book andFR-02

    2. Check and approve by Survey Control,

    NSL by checking of the survey data and

    make record entries by Joint Survey.

    3. Check by Survey Control andDimensional Inspection, complete

    setting out/layout.

    4. Check by visual inspection and SurveyControl, location and level of level pegs,

    these should be clear of working area.

    5. Discuss and Ensure, deployment of

    proper Equipment/ Plant for Sheet PileDriving.

    A.R.E./ Site

    Inspector/ Cont. siteengineer

    FR-02

    6. Ensure by physical inspection, Size,Section and Quality of Steel Sheet Piles.

    A.R.E./ Site

    Inspector / Cont.

    site engineer

    FR-02

    7. Check by visual inspection and TestResults. Quality of Bituminous Material

    for sealing steel piling interlocks.

    A.R.E./ Site

    Inspector Ext. Lab.

    FR-02 and

    Manufacturers

    Certificate

    8. Study and Comment, contractorsproposal for storing, handling and

    transporting piles.

    A.R.E./ Site

    Inspector / Cont.

    site engineer

    Contractors Formatand FR-02

    9. Study and Comment, contractorsproposal for weld procedures.

    A.R.E./ SiteInspector./ Cont. site

    engineer

    FR-02

    10. Update periodically. Piling Record A.R.E./ SiteInspector/ Cont. site

    engineer

    Contractors Format

    All actions should be taken in accordance with the Contract Specifications and Contractors

    Work Methodology as approved by the Engineer.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    45/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    2.1 TYPES OF MATERIAL TESTS

    The Quality Control/Quality Assurance tests are of three type i.e.

    Tests to be performed at site

    These tests are field specific and include the following:

    Field Density Tests for compaction control.

    Slump test for concrete.

    Casting of concrete cylinders for compressive Strength Tests.

    Gradation Analysis of concrete aggregates i.e. sand and coarse aggregates.

    Los Angeles Abrasion Test for Stone.

    Moisture Content of soil.

    Temperature of concrete.

    Testing of concrete cylinders is required to be done at the Engineers Field Laboratory. The

    testing machine at site should be checked and approved by Geotech/Material Engineer of

    the consultants.

    Tests to be performed at Contractors Field Laboratory

    The tests to be performed at Contractors Field Laboratory include the following:

    Soil classification Tests

    Compaction Tests

    Gradation Analysis of Aggregates as required by R.E.

    7 and 28 days compressive Strength Tests on concrete cylinders.

    Unit Weight of aggregates.

    Fresh Density of concrete.

    Absorption and Compressive Strength of bricks.

    Specific Gravity and Absorption of coarse and fine aggregates.

    Los Angeles Abrasion Test for Coarse Aggregate

    Soundness of Aggregate

    Test to be performed at external laboratories/ Consultants laboratory

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    46/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    These tests can only be performed in specified off-site laboratories and include tests on

    reinforcing steel, cement, abrasion, petrography, soundness of concrete aggregates, water

    stop and any other tests required during any problem or dispute.

    2.2 TESTING ARRANGEMENTS/EQUIPMENTS

    2.2.1 Testing at Construction Site

    The Contractor for an individual contract package shall be responsible for providing the

    equipment and carrying out these tests in accordance with the Clause 4.3 under the direct

    supervision and guidance of the Consultants supervision staff.

    The contractor is required to provide and readily make available at construction site the

    following equipment,

    Earthwork:

    Sand - Cone Density Apparatus, complete with base plate and sand bottle.

    Density Core Cutter 4 dia, complete with collar and hammer.

    Speedy Moisture Tester capacity 20.0 gm. Moisture range 0 20% complete with

    electronic balance and plastic carrying case.

    Balance Triple Beam 2610 gm capacity with readability of 0.10 gm.

    Balance 30 Kgs capacity with readability 1.0 gm.

    Drying Oven capacity 108 Litres.

    Concrete Work:

    Cylinder moulds for concrete 6 dia. Complete with tamping rod (5/8 in dia 20

    long) and mallet.

    Slump Test Equipment complete with tamping rod 5/8 dia and 24 long.

    Curing Tanks These shall be constructed close to the construction site for storing

    concrete cylinders till their transportation to the Laboratory for testing.

    A reliable compression machine approved by the Consultants Material Engineer.

    Thermometers to check fresh concrete temperature.

    Note:

    The Contractor shall ensure that sufficient No. of the above equipment is available at

    site to satisfy the testing requirements of the quantum of work.

    Computers with printers should be provided in laboratory.

    2.2.2 Testing in the Engineers Field Laboratory

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    47/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    A material testing laboratory established at site should be equipped and adequately

    staffed to carry out the field laboratory tests as per requirements defined in Section

    2.1.

    This Field Laboratory, established by the contractor and supervised by the

    Consultants Quality Control / Assurance staff is to carry out the required tests

    and maintain a systematic and retrievable record. Test record should be

    computerized.

    All Quality Control/Quality Assurance tests specified to be performed in the field

    laboratory shall be carried at the designated Field Laboratory at site. (Individual

    arrangements by the contractors for this category of tests shall not be acceptable.

    The Contractors shall be responsible for providing and transporting the test

    specimens to the laboratory under the guidance and supervision of the

    Consultants Resident Engineer.

    The contractors shall bear the cost of these tests as per rate list available at any

    Field or external Laboratory specified by the Engineer.

    2.2.3 Testing from External Laboratory

    The Quality Control/Quality Assurance tests to be carried out from an external laboratory

    defined in Section 2.1 are recommended to be carried out at laboratories mentionedbelow or as directed by the Engineer. The cost of transportation and testing charges shall be

    the Contractors responsibility.

    Specified Laboratory.

    Third Party verification

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    48/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    2.3 TESTING REQUIREMENTS

    The test procedures and the test frequencies for the various construction works have been

    summarized in the following tables.

    Earthworks Table 2.3 (1)

    Concrete works Table 2.3 (2)

    Brickworks Table 2.3 (3)

    Stone Pitching and Stone Apron Table 2.3 (4)

    These tables are intended to provide comprehensive guidelines to the supervision staff as

    well as Engineers Field Laboratory personnel.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    49/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    Laboratory Record/Reporting Documents

    3.1 Laboratory Record/Reporting Documents

    ( Field Laboratory )Document No. Document Description

    SOILS

    LR-01 Particle Size Analysis of Soil

    LR-02 Moisture Content of Soils

    LR-03 Liquid Limit, Plastic Limit and Plasticity Index of Soils

    LR-04 Specific Gravity of Fine Grained Soil Particles

    LR-05 Laboratory Compaction characteristics of soils

    CONCRETE

    LR-06 Particle Size Distribution of Concrete Aggregates

    LR-07 Concrete Compressive Strength

    LR-08 Bricks Tests Report

    LR-09 Specific Gravity of Coarse Aggregates

    LR-10 Specific Gravity of Fine Aggregates

    LR-11 Concrete Batching Plant Calibration

    LR-12A Concrete Batching/ Pouring Record Summary

    LR-12B Concrete Aggregate Moisture Content at Batching Plant

    LR-13 Concrete Mix Design

    Note:LR = Laboratory Record

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    50/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    Field Record/Reporting Documents

    3.2 Field Record/Reporting Documents (for Field Inspection/Testing)

    Document No. Document Description

    FR-01 Field Note for Handing over Survey Reference Points/Bench Marks

    FR-02 Field Note (General)

    FR-03/A Field Density & Degree of Compaction of Non-Cohesive Soils.

    FR-03/B Field Density & Degree of Compaction of Cohesive Soils by Sand Cone

    Method

    FR-03/C Field Density & Degree of Compaction of Cohesive Soils by Core Cutter

    Method.

    FR-04 Summary of Compaction Control Tests for Cohesive soils

    FR-05 Summary of Compaction Control Tests for Cohesion less soils

    FR-06 Format for Bar Bending Schedule

    FR-07 Request for Concrete Pour Authorization

    FR-08 Concrete Pour Authorization

    FR-09 Concrete Cylinders/Cubes Casting and Delivery Report

    FR-10 Summary of Cylinder/Cubes Test Results

    FR-11 Bored-Cast-in-Situ Pile Construction Record

    Note:FR = Field Record

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    51/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    4. SAFETY REQUIREMENTS

    High Standards of safety for men/women and machine must be observed at all times. The

    Contractor shall take reasonable measures to prevent members of the public from entering

    areas in which maintenance/construction activities are being carried out by the Contractors

    Equipment and personnel.

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    52/59

    R&U of Sulemanki Barrage Quality Assurance Plan

    CKL 4.1 SAFETY REQUIREMENTS CHECKLIST

    Sr.

    No.Issues Action

    Record/Reporting

    Document

    1. Presence of underground utilities Visual Inspection

    FR-02

    2. Protective barrier on edge of excavationline and Warning Signs

    Visual Inspection

    3. Showing where soft materials areencountered, during excavation.

    Visual Inspection

    4. Employers property is properly protected Visual Inspection

    5. - All work areas, walkways, platformetc. are clear of scrap, small tools,

    accumulation of mud, grease, oil orslippery substances.

    Ensure

    6. - All Test Beams, Reaction Frames andPlatform for the pile load tests are

    adequately supported at all times.

    Ensure

    7. - Only authorized personnel arepermitted within the immediate Test

    area during Pile Tests.

    Ensure

    8. - All Reaction Loads are stable andbalanced, during pile load tests.

    Ensure

    9. - The Equipment in use by contractor isin compliance with HSE regulations.

    Ensure

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    53/59

    5. STANDARDS & PROCEDURES

    A list of ASTM and British Standards and Procedures, applicable to types of construction

    works involved inR&U of Sulemanki Barrage project are presented in the following tables:

    Table-5.1

    Table-5.2

    A copy of all these ASTM and British Standards can be made available to the Site Staff as and

    when required.

    LIST OF ASTM STANDARDS & PROCEDURES

    Sr.

    No.ASTM Designation Title

    Page

    No.

    PART 1

    A FERROUS METALS

    1 A 29/A 29 M-99Std. Spec. for Steel Bars, Carbon & Alloy, Hot-Wrought &

    Finished, General Requirements for1

    2 A 53-98Std. Spec. for Pipe steel, Black & Hot Dipped, Zinc-Coated,

    Welded and Seamless

    23

    3 A 416/A 416M-99Sts. Spec. for Steel Strand, Un-Coated Seven-Wire for Pre-

    Stressed Concrete44

    4 A 421/A 421M-98aStd. Spec. for Uncoated Stress-Relieved steel Wire for Pre-

    Stressed Concrete49

    5 A 501-98Std. Spec. for Hot-Formed Welded & Seamless Carbon

    Steel Structure Tubing52

    6 A 615/A 615M-96aStd. Spec. for Deformed & Plain Billet Steel for Concrete

    Reinforcement58

    7 A 980-97Std. Spec. for Steel, Sheet, Carbon, Ultra High Strength

    Cold Rolled63

    8 A 981-97

    Std. Test Method for Evaluating Bond Strength for

    15.2mm (0.6") Diameter Pre-Stressing Steel Strand Grade

    270, Uncoated, Used in Pre-Stressed Ground Anchors.

    65

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    54/59

    LIST OF ASTM STANDARDS & PROCEDURES

    Sr.

    No.ASTM Designation Title

    Page

    No.

    PART 2

    C CEMENTATIONS, CERAMIC, CONCRETE & MASONRY MATERIALS

    9 C 29/C 29M-97Std. Test Method for Bulk Density (Unit Weight) & Voids

    in Aggregates68

    10 C 31/C 31M-98Std. Practice for Making and Curing Concrete Test

    Specimens in the Field72

    11 C 33-99 Std. Spec. for Concrete Aggregates 77

    12 C 39-96Test Method for Compressive Strength of Cylindrical

    Concrete Specimens85

    13 C 40-99Test Method for Organic Impurities Test in Fine

    Aggregates for Concrete90

    14 C 42/C 42M-03Std. Test Method for Obtaining and Testing Drilled Cores

    and Sawed Beams of Concrete92

    15 C 67-02CStd. Test Methods for Sampling & Testing Brick and

    Structural Clay Tile97

    16 C 76-98aStd. Spec. for Reinforced Concrete Culvert, Storm Drain

    and Sewer Pipe109

    17 C 78-94Std. Test Method for Flexural Strength of Concrete (Using

    Simple Beam with Third-Point Loading)120

    18 C 88-99aTest Method for Soundness of Aggregates by Use of

    Sodium Sulphate or Magnesium Sulphate123

    19 C 97-96Std. Test Method for Absorption and Bulk Specific Gravity

    of Dimension Stone128

    20 C 109/C 109M-02 Std. Test Method for Compressive Strength of HydraulicCement Mortars (Using 2-in/50-mm Cube Specimens)

    130

    21 C 117-95Std. Test Method for Materials Finer than 75-m

    (No. 200) Sieve in Mineral Aggregates by Washing136

    22 C 123-98 Std. Test Method for Light Weight Particles in Aggregate 140

    23 C 127-01Std. Test Method for Density, Relative Density (Specific

    Gravity), And Absorption of (Coarse Aggregate)143

    24 C 128-01

    Std. Test Method for Density, Relative Density (Specific

    Gravity) and Absorption of Fine Aggregate 149

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    55/59

    Sr.

    No.ASTM Designation Title

    Page

    No.

    25 C 131-03

    Std. Test Method for Resistance to Degradation of Small-

    Size Coarse Aggregates by the Abrasion and Impact in the

    Los Angeles Machine

    155

    26 C 136-01Std. Test Method for Sieve Analysis of Fine and Coarse

    Aggregates159

    27 C-138/C 138M-01aStd. Test Method for Density(Unit Weight), Yield, and Air

    Content (Gravimetric) of Concrete.164

    28 C 142-97Std. Test Method for Clay Lumps and Friable Particles in

    Aggregates168

    29 C 143/C 43M-98 Std. Test Method for Slump of Hydraulic Cement Concrete 170

    30 C 144-93 Std. Spec. for Aggregate for Masonry Mortar 173

    31 C 150-98 Std. Spec. for Portland Cement 175

    32 C 171-97a Std. Spec. for Sheet Materials for Curing Concrete 180

    33 C - 172 - 99 Std. Practice for Sampling Freshly Mixed Concrete. 182

    34 C 191-01a Std. Test Method for Time of Setting of Hydraulic Cementby Vicat Meedle

    185

    35 C - 227 - 97aStd. Test Method for Potential Alkali Reactivity of

    Cement-Aggregate Combinations (Mortar-Bar Method).191

    36 C 231-97Std. Test Method for Air Content of Freshly Mixed

    Concrete by the Pressure Method195

    37 C 260-01 Std. Spec. for Air Entraining Admixtures for Concrete 203

    38 C - 289 - 02

    Std. Test Method for Potential Alkali -Silica Reactivity of

    Aggregates (Chemical Method). 206

    39 C 295-03Std. Guide for Petrographic Examination of Aggregates for

    Concrete213

    40 C - 309 - 98aStd. Specification for Liquid Membrane-Forming

    Compounds for Curing Concrete.221

    41 C 494/C 494M-99a Spec. for Chemical Admixtures for Concrete 224

    42 C - 535 - 03

    Std. Test Method for Resistance to Degradation of Large-

    Size Coarse Aggregate by Abrasion and Impact in the Los

    Angeles Machine.

    233

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    56/59

    Sr.

    No.ASTM Designation Title

    Page

    No.

    43 C 566-97 Std. Test Method for Total Evaporable Moisture Contentof Aggregate by Drying

    236

    44 C 597-83 Std. Test Method for Pulse Velocity Through Concrete 239

    45 C 881-99Std. Spec. for Epoxy-Resin Base Bonding Systems for

    Concrete242

    46 C 920-02 Std. Spec. for Elastomeric Joint Sealants 247

  • 8/11/2019 Quality Assurance Plan Sparco for Sulemanki.pdf

    57/59

    LIST OF ASTM STANDARDS & PROCEDURES

    Sr.

    No. ASTM Designation Title

    Page

    No.

    PART 3

    D MISCELLANEOUS MATERIALS

    47D 422-63 (Re-

    approved 1998)Std. Test Method for Particles Size Analysis of Soils 250

    48 D 427-98Std. Test Method for Shrinkage Factors of Soils by

    the Mercury Method258

    49 D - 572 - 88Std. Test Method for Rubber Deterioration by Heat

    and Oxygen.

    262

    50 D 698-00a

    Std. Test Methods for Lab Compaction

    Characteristics of Soil Using Std. Effort (12,400 ft-

    lbf/ft3[600 KN-m/m3])

    265

    51 D 854-02Std. Test Method for Specific Gravity of Soil Solids by

    Water Pycnometer276

    52D 1143-81 (Re-

    approved 1994)

    Std. Test Method for Piles Under Static Axial

    Compressive Load283

    53 D 1556-00Std. Test Method for Density and Unit Weight of Soil

    in Place b