quarterly business review - bpa.gov · bp-18 rate case q2 forecast. b o n n e v i l l e p o w e r a...
TRANSCRIPT
QUARTERLY
BUSINESS REVIEW MAY 1, 2018
INTRODUCTION Scott Simms, DIRECTOR OF COMMUNICATIONS
S L I D E 2 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | S C O T T S I M M S
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
AGENDA
Time Presentation Speaker
9:00 – 9:02 Introductions Scott Simms Director of Communications
9:02 – 9:20 State of the business: • Grid modernization • Environment, Fish and Wildlife
updates
Elliot Mainzer Administrator
9:20 – 9:30 Finance update Mary Hawken Acting chief financial officer
9:30 – 9:40 Power Services update Joel Cook Senior VP of Power Services
9:40 – 9:50 Transmission Services update Richard Shaheen Senior VP of Transmission Services
9:50 – 9:51 Upcoming involvement opportunities Scott Simms
9:51 – 10:00 Question and answer session
S L I D E 3 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | S C O T T S I M M S
STATE OF THE BUSINESS Elliot Mainzer, ADMINISTRATOR AND CHIEF EXECUTIVE OFFICER
S L I D E 4 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
SAFETY
S L I D E 5 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
0.4
0.9
1 1 1
1.1
1.2
0
0.5
1
1.5
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Incident frequency rate Number of injuries and illnesses per 200,000 hours worked
2018 Ceiling
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
GRID MODERNIZATION
S L I D E 6 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
• Modernizing BPA’s assets and operations is a critical
element of our 2018-23 Strategic Plan and will help
increase competitiveness and customer
responsiveness.
– Increase power and transmission revenues.
– Reduce long-term transmission costs by potentially
decreasing or delaying the need for system expansion.
• We will enhance system operations in three major
ways: automation, accuracy and visibility.
• Sustained investment of $25 million per rate period
through 2021.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
ENERGY IMBALANCE MARKET
S L I D E 7 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
• One outcome of grid modernization – the
potential to join the Western EIM.
• BPA is exploring how and under what conditions
it could participate in the EIM operated by the
CAISO.
• Initial cost-benefit analysis:
– Assumed start-up cost of $35 million.
– Annual benefit to Power Services of $14 million.
• BPA is committed to transparency and customer
engagement in working towards a decision on
whether to join the market.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
OTHER GRID MOD ENGAGEMENTS
S L I D E 8 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
• BPA is engaging in related efforts to protect NW
interests and support developments that could
improve secondary revenues.
– Day-ahead capacity product: CAISO’s proposal for
day-ahead market enhancements includes an
imbalance reserve product.
– Intertie optimization: CAISO and others are studying
ways to increase dynamic transfer capability and
capacity of the AC and DC interties.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
SPILL SURCHARGE
S L I D E 9 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
• On April 2, the 9th U.S. Circuit Court of Appeals
upheld the 2018 spill injunction. BPA will be
implementing a spill surcharge in FY 2018.
• The spill surcharge will adjust power rates to
recover the non-Slice portion of the cost
associated with increased spill and lost
generation relative to the spill assumptions used
when setting rates.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
SPILL SURCHARGE
S L I D E 1 0 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
• Next week BPA will share:
– Preliminary data and assumptions used to calculate
the surcharge.
– Information will include proposed program spending
reductions to help offset the spill surcharge.
• Rates staff will review these materials at a
workshop on May 16 at 1 p.m.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
FISH ACCORDS
S L I D E 1 1 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
• Columbia Basin Fish Accords signed in 2008.
– Signed by action agencies, states and tribes.
– To date, partners have restored more than 8,000
acres of estuary floodplain and reopened nearly 4,000
miles of spawning grounds.
• Fish Accords are set to expire in September
2018.
• BPA actively exploring post-2018 path forward
on Fish Accords.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
FISH ACCORDS
S L I D E 1 2 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | E L L I O T M A I N Z E R
• Consideration for Fish Accords extension is the
2018-2023 Strategic Plan commitment:
– BPA intends to manage its fish and wildlife program
costs at or below the rate of inflation, inclusive of any
new obligations that may emerge from litigation or
subsequent commitments in current or future
biological opinions.
• As BPA further explores potential Fish Accords
extension, additional outreach will occur with
customers and regional stakeholders.
FINANCE Mary Hawken, ACTING CHIEF FINANCIAL OFFICER
S L I D E 1 3 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | M A R Y H A W K E N
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
$26
$361
0
100
200
300
400
FCRPS net revenues In millions of dollars
BP-18 Rate Case Q2 Forecast
AGENCY NET REVENUES
S L I D E 1 4 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | M A R Y H A W K E N
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
AGENCY FINANCIAL HEALTH
S L I D E 1 5 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | M A R Y H A W K E N
$3,627 $3,653
$3,300
$3,661
3100
3250
3400
3550
3700
Total expense Total revenue
Federal Columbia River Power System Total revenue and expense in millions of dollars
BP-18 Rate Case Q2 Forecast
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
Q2 BUDGET TRUE UP
S L I D E 1 6 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | M A R Y H A W K E N
1200
1300
1400
1500
1600
FY 2015 FY 2016 FY 2017 FY 2018
Historical agency underspend Total program expense in millions of dollars
Start-of-year budget Actuals FY 2018 budget true up
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
BUDGET ESCALATION
S L I D E 1 7 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | M A R Y H A W K E N
1450
1500
1550
1600
1650
FY 2017actuals
FY 2018 FY 2019 FY 2020 FY 2021 FY 2022 FY 2023
Cost-management objective escalation alternative Total program expense in millions of dollars
FY Target (BP-20 path) Rate period target
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
• Conducted depreciation study update using data
through FY 2016.
• The largest change is due to increased costs
associated with removing assets.
• New depreciation rates went into effect March
2018.
DEPRECIATION STUDY
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | M A R Y H A W K E N S L I D E 1 8
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
DAYS CASH ON HAND
S L I D E 1 9
BP-18 Rate Case FY 2018 EOY forecast
Power Trans. Agency Power Trans. Agency
EOY Reserves 170 468 638 214 566 780
Reserves not for risk 149 63 212 168 102 270
Reserves available for risk 21 405 426 46 464 510
Days cash on hand 4 237 64 9 275 76
*Reserves in millions of dollars
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | M A R Y H A W K E N
POWER SERVICES Joel Cook, SENIOR VICE PRESIDENT OF POWER SERVICES
S L I D E 2 0 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
166
208 211 213
192 201
0
50
100
150
200
250
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Power total expense Total expenses in millions of dollars
BP-18 Rate Case Actuals
POWER SERVICES EXPENSE
S L I D E 2 1
Total expense (in millions of dollars)
BP-18
Rate Case
Q2 EOY
forecast
BP-18
year-to-date
Expenses
year-to-date
2,629 2,488 1,281 1,190
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
POWER SERVICES REVENUES
S L I D E 2 2 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
211 221
242
286 269
262
0
50
100
150
200
250
300
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Power total revenues Total revenues in millions of dollars
BP-18 Rate Case Actuals
Total revenues (in millions of dollars)
BP-18
Rate Case
Q2 EOY
forecast
BP-18
year-to-date
Revenues
year-to-date
2,827 2,841 1,449 1,491
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
PERCENTAGE OF ANNUAL RUNOFF
S L I D E 2 3 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
Where does the water come from? (as a percent of the annual runoff at The Dalles)
22% 15%
59%
14%
6%
4%
6%
8% 27%
10%
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
SNOWPACK CONDITIONS
S L I D E 2 4
National Weather Service official water
supply forecast as of April 9, 2018
Jan. – July
(million acre feet) Percent average
118.3 117
114% 113%
124%
145%
147%
162% 135%
112%
131% 89%
115%
117%
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
HENRY HUB PRICES
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K S L I D E 2 5
2.87 2.97
2.75
3.69
2.66 2.65
2.0
2.5
3.0
3.5
4.0
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Henry Hub prices In dollars per one million British thermal units
Actuals March 28 NYMEX Average BP-18 Rate Case
(0.40) (0.42)
(0.69)
0.23
(0.71)
(0.53)
(0.19) (0.13) (0.12) (0.10)
(0.05) (0.06)
(0.8)
(0.4)
-
0.4
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Variance from BP-18 Rate Case In dollars per one million British thermal units
Actuals FY 2018 expected
BP-18 avg.: $3.12
3/28 avg.: $2.92
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
MID-C PRICES
S L I D E 2 6 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
26.53 26.06 27.44
22.51 21.42 20.53
10
15
20
25
30
35
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Mid-C heavy load hour prices In dollars per megawatt hour
Actuals Forward market (ICE) BP-18 Rate Case
(1.02) (2.10) (3.32)
(7.29) (7.18)
(3.41) (3.41) (4.68) (3.93)
(3.02)
1.32
5.11
(0.21)
(8)
(4)
-
4
8
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Variance from BP-18 Rate Case In dollars per megawatt hour
Actuals FY 2018 expected
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
POWER SERVICES CAPITAL
S L I D E 2 7 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
14 25
43
60
77 92
200
0
100
200
300
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
$ millions
Capital spend and TBD metric Tracks capital expenditure and work completed to date
Actual $ millions FYTD Remaining Forecast
Note: capital expenditure KPI includes only direct-funded federal hydropower capital.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
FEDERAL HYDROPOWER RELIABILITY
S L I D E 2 8 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
Good
3.6
4.6
5.9
3
4
5
6
7
Q1 Q2 Q3 Q4
Federal hydropower forced outage factor Percentage of hours fed hydro projects are offline due to unplanned outages
FY 2018 Target
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
COLUMBIA GENERATING STATION RELIABILITY
S L I D E 2 9 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | J O E L C O O K
93.5
95.6
94
92
93
94
95
96
Q1 Q2 Q3 Q4
Columbia Generating Station availability factor Percentage of time Columbia is available to serve demand
FY 2018 Target
Good
TRANSMISSION SERVICES Richard Shaheen, SENIOR VICE PRESIDENT OF TRANSMISSION SERVICES
S L I D E 3 0 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | R I C H A R D S H A H E E N
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
TRANSMISSION SERVICES EXPENSE
S L I D E 3 1 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | R I C H A R D S H A H E E N
78 78 77
83 77
91
0
20
40
60
80
100
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Transmission total expense Total expense in millions of dollars
BP-18 Rate Case Actuals
Total expense (in millions of dollars)
BP-18
Rate Case
Q2 EOY
forecast
BP-18
year-to-date
Expenses
year-to-date
1,043 1,050 521 485
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
TRANSMISSION SERVICES REVENUES
S L I D E 3 2 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | R I C H A R D S H A H E E N
85 88 89 91 92
99
0
20
40
60
80
100
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Transmission total revenues Total revenues in millions of dollars
BP-18 Rate Case Actuals
Total revenues (in millions of dollars)
BP-18
Rate Case
Q2 EOY
forecast
BP-18
year-to-date
Revenues
year-to-date
1,052 1,066 526 544
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
TRANSMISSION SERVICES CAPITAL
S L I D E 3 3 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | R I C H A R D S H A H E E N
208
329
35
74 103
122 149
182
424
0
100
200
300
400
500
600
0
100
200
300
400
500
600
Oct. Nov. Dec. Jan. Feb. March April May June July Aug. Sept.
Units $ millions
Capital spend and units installed Tracks capital expenditure and work completed to date
Actual assets FYTD Remaining planned assets Actual $ millions FYTD Remaining Forecast
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
TRANSMISSION RELIABILITY - SAIFI
S L I D E 3 4 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | R I C H A R D S H A H E E N
0.74
0.56
0.27
0.22
0.66
0.68
0
0.2
0.4
0.6
0.8
Q1 Q2 Q3 Q4
System average interruption frequency index Tracks frequency of unplanned outages
Low voltage (< 200kV) High voltage (>= 200kV) Low voltage warning level High voltage warning level
Good
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
TRANSMISSION RELIABILITY - SAIDI
S L I D E 3 5 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | R I C H A R D S H A H E E N
150
99
129
76
430
260
50
150
250
350
450
Q1 Q2 Q3 Q4
System average interruption duration index Tracks duration of unplanned outages
Low voltage (< 200kV) High voltage (>= 200kV) Low voltage warning level High voltage warning level
Good
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
ENGAGE WITH TRANSMISSION
S L I D E 3 6
• Reliability coordination.
• Asset management.
• TC-20 (formerly Transmission tariff engagement
and Pro Forma Gap Assessment).
• Evolving transmission demand.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | R I C H A R D S H A H E E N
PUBLIC PROCESSES Scott Simms, DIRECTOR OF COMMUNICATIONS
S L I D E 3 7 B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | S C O T T S I M M S
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
PUBLIC PROCESSES
S L I D E 3 8
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | S C O T T S I M M S
• May 9 – FY2020-21 Rate Period High Water Mark process workshop.
• May 10 – Resource Program workshop.
• May 15-16 – Efficiency Exchange Northwest 2018.
• May 16 – Spill surcharge workshop.
• May 22 – Strengthening financial health: capital financing workshop.
• May 30 – Columbia River System Operation EIS public update webinar.
• May 31 – TC-20 Tariff customer workshops.
– Additional meetings: June 26, July 23, Aug. 21.
• June 13 – South of Allston Bilateral Redispatch Pilot workshop.
• June 18–22 – Integrated Program Review.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
COMMENT PERIODS
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 | S C O T T S I M M S S L I D E 3 9
• May 11 – Financial Reserves Policy and Leverage
Policy.
• May 24 – Bonneville Environmental Foundation
agreement extension.
QUESTION AND ANSWER
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 S L I D E 4 0
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
The next QBR is scheduled for July 31, 2018.
Strategic plan is available at www.bpa.gov/StrategicPlan.
Didn’t get your question answered? Email [email protected]. Answers will be
posted to www.bpa.gov/goto/QBR.
THANK YOU
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 S L I D E 4 1
This information was publicly available on
April 30, 2018, and contains information not sourced
directly from BPA financial statements.
FINANCIAL DISCLOSURE
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N | Q B R M A Y 2 0 1 8 S L I D E 4 2