queens, new york remedial action report€¦ · qa/qc quality assurance/quality control ... a new...
TRANSCRIPT
51-27 QUEENS BOULEVARD
QUEENS, NEW YORK
Remedial Action Report
NYC VCP Project Number 15CVCP027Q
OER Project Number 14EH-N505Q
Prepared For:
Q52, LLC 37‐99 69th Street, Queens, NY 11377
(516) 902-6332 [email protected]
Prepared By:
Athenica Environmental Services, Inc. &
Ariel Czemerinski, P.E.
AMC Engineering
18-36 42nd Street, Queens, NY 11105
JULY 2017
i
REMEDIAL ACTION REPORT
TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................................ i
LIST OF ACRONYMS ............................................................................................................. vi
CERTIFICATION .................................................................................................................... vii
EXECUTIVE SUMMARY ........................................................................................................ 1
REMEDIAL ACTION REPORT ............................................................................................. 10
1.0 SITE BACKGROUND ................................................................................................... 10
1.1 SITE LOCATION AND BACKGROUND .............................................................. 10
1.2 REDEVELOPMENT PLAN ..................................................................................... 10
1.3 DESCRIPTION OF SURROUNDING PROPERTY ............................................... 11
1.4 SUMMARY OF PAST SITE USES AND AREAS OF CONCERN ....................... 11
1.5 SUMMARY OF WORK PERFORMED UNDER THE REMEDIAL
INVESTIGATION .................................................................................................... 12
1.6 SUMMARY OF FINDINGS OF REMEDIAL INVESTIGATION ......................... 12
2.0 DESCRIPTION OF REMEDIAL ACTIONS ................................................................. 16
3.0 COMPLIANCE WITH REMEDIAL ACTION WORKPLAN ...................................... 20
3.1 HEALTH & SAFETY PLAN ................................................................................... 20
3.2 COMMUNITY AIR MONITORING PLAN ............................................................ 20
3.3 SOIL/MATERIALS MANAGEMENT PLAN ......................................................... 20
3.4 STORM-WATER POLLUTION PREVENTION .................................................... 20
3.5 DEVIATIONS FROM THE REMEDIAL ACTION WORK PLAN ....................... 21
4.0 REMEDIAL PROGRAM ................................................................................................ 23
4.1 PROJECT ORGANIZATION ................................................................................... 23
4.2 SITE CONTROLS ..................................................................................................... 23
4.3 MATERIALS EXCAVATION AND REMOVAL ................................................... 25
4.4 MATERIALS DISPOSAL ........................................................................................ 24
4.5 BACKFILL IMPORT ............................................................................................... 25
5.0 ENGINEERING CONTROLS ........................................................................................ 30
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
ii
5.1 COMPOSITE COVER SYSTEM ............................................................................. 27
5.2 ENGINEERING CONTROLS FOR SOIL VAPOR ................................................. 27
6.0 INSTITUTIONAL CONTROLS ..................................................................................... 33
7.0 SITE MANAGEMENT PLAN ....................................................................................... 34
7.1 ENGINEERING CONTROLS .................................................................................. 34
7.2 INSTITUTIONAL CONTROLS ............................................................................... 35
7.3 INSPECTIONS .......................................................................................................... 36
7.4 INSPECTION AND CERTIFICATION LETTER REPORT ................................... 37
7.5 NOTIFICATIONS ..................................................................................................... 38
8.0 SUSTAINABILITY REPORT ........................................................................................ 40
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
iii
FIGURES
Figure 1: Site Location Map
Figure 2: Site Boundary Map
Figure 3: Development Plan
Figure 4: Map of end-point sample location
Figure 5: Map showing location and approximate depth of excavations
Figure 6: Map of soil source area and backfill placement locations
Figure 7: Map of location of Composite Cover System and Design Detail
Figure 8: Map of location of Vapor Barrier System and Design Detail
Figure 9: Map of location of SSDS System
Figure 10: As-built design detail for SSDS System
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
iv
TABLES
Table 1: Summary of end-point analytical results
Table 2: Disposal quantities and disposal facilities
Table 3: Summary of waste classification analytical results
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
v
APPENDICES
Appendix A: Remedial Investigation Report
Appendix B: Remedial Action Work Plan and Stipulation List
Appendix C: Community Air Monitoring Program Results
Appendix D: SSDS Conversion Letter and OER Approval
Appendix E: Daily and Monthly Reports to OER
Appendix F: Photographs of Remedial Action
Appendix G: End-point Sample Analytical Laboratory Data
Appendix H: Laboratory ELAP Certification
Appendix I: Disposal Facility Requests and Approval Letters
Appendix J: Shipping and Disposal Manifests
Appendix K: Disposal Characterization Sample Laboratory Testing Results
Appendix L: Bluestone Import Documentation
Appendix M: Vapor Barrier Documentation
Appendix N: SSDS Documentation
Appendix O: SSDS Start-up Documentation
Appendix P: SSDS Monthly Inspection Form
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
vi
LIST OF ACRONYMS
Acronym Definition
CAMP Community Air Monitoring Plan
DER-10 NYS DEC Division of Environmental Remediation Technical Guidance Manual 10
EC Engineering Control
HASP Health and Safety Plan
IC Institutional Control
NYC VCP New York City Voluntary Cleanup Program
NYC DEP New York City Department of Environmental Protection
NYC DOHMH New York City Department of Health and Mental Hygiene
NYC OER New York City Office of Environmental Remediation
ORC Oxygen Release Compound
PID Photoionization Detector
QA/QC Quality Assurance/Quality Control
QEP Qualified Environmental Professional
RAR Remedial Action Report
RAWP Remedial Action Work Plan
SCG Standards, Criteria and Guidance
SCO Soil Cleanup Objective
SMMP Soil/Materials Management Plan
SMP Site Management Plan
SVOCs Semi-Volatile Organic Compounds
UST Underground Storage Tank
VOCs Volatile Organic Compounds
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
1
EXECUTIVE SUMMARY
Q52, LLC has enrolled in the New York City Voluntary Cleanup Program (NYC
VCP) to investigate and remediate a property located at 51-27 Queens Boulevard in the
Woodside section of Queens, New York. A Remedial Investigation (RI) was performed
to compile and evaluate data and information necessary to develop a Remedial Action
Work Plan (RAWP). A remedial action was performed pursuant to an OER-approved
RAWP in a manner that has rendered the Site protective of public health and the
environment consistent with the proposed use of the property. This RAR describes the
remedial action performed under the RAWP. The remedial action described in this
document provides for the protection of public health and the environment, complies with
applicable environmental standards, criteria and guidance and applicable laws and
regulations.
Site Location and Background
The Site is located at 51-27 Queens Boulevard in the Woodside section of Queens,
New York and is identified as Block 1320 and Lot 47 on the New York City Tax Map.
The Site is 5,387-square feet and is bounded by an asphalt-capped parking area to the
north, Queens Boulevard to the south, 52nd Street to the east, and a multi-story
residential building to the west. Prior to redevelopment, the Site was vacant as recently as
2014, according to the City Directory Abstract, and contained a 1-story mixed-use
building with office space and a split level, 1- and 2-story, mixed-use building with a
partial cellar and office space.
Summary of Redevelopment Plan
A new 7-story mixed residential and commercial use building with a full cellar has
been constructed at the Site. The new building occupies 4,227-square feet, or
approximately 80 percent of the lot area with the remaining open area consisting of a
1,160-square foot concrete-paved courtyard area located on the northern portion of the
property.
The total gross square footage of the new building is approximately 32,861-square
feet, including 2,789-square feet of retail space, 3,943-square feet of community facility
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
2
space, 1,486-square feet of retail storage space, and the remaining area utilized as 29
Class “A” dwelling units, tenant storage, elevator mechanical rooms, sprinkler and water
meter room, electrical meter room, gas meter room, laundry, and compactor room. The
cellar is utilized for commercial use, utility and meter rooms with accessory uses for the
commercial and residential occupancies. The first floor is used for commercial retail,
residential lobby, and one residential apartment. The second floor is used for community
facility space. Floors 3 through 7 are utilized as residential apartment units.
As part of development, the building footprint was excavated to approximately 11-
feet below grade surface (bgs) for installation of the cellar. An additional 9-feet was
excavated in two locations of the cellar for the installation of elevator pits. The remaining
area (1,160-square feet) on the northern portion of the property was excavated to 2-feet
bgs. The total amount of soil removed off-site for excavation of the cellar is 1,494.45
tons. The current zoning designation is C2-3/R7X, denoting it as a residential and light
commercial district. The current use is consistent with existing zoning for the property.
Summary of Description of Surrounding Properties
The Site is located within a mixed use residential and commercial area of Queens,
New York. The Site is bounded by an asphalt-capped parking area to the north, Queens
Boulevard to the south beyond which is Calvary Cemetery, 52nd Street to the east
beyond which is a twelve-story mixed use building, and a multi-story residential building
to the west. There are no sensitive receptors (such as schools, hospitals, and day-care
facilities) within a 500-foot radius of the Site.
Summary of Past Site Uses and Areas of Concern
Based upon the review of the Phase I Environmental Site Assessment (ESA) Report
prepared by Athenica Environmental Services (Athenica) in April 2014, the Site history
was established. Prior to redevelopment, the Site was developed with a 1-story building
and a 1- and 2-story building with a partial cellar. The 2-story building was occupied by
different restaurants between 1934 and 1962. The 2-story building was then utilized as a
private lounge between 1970 and 1983. It was then occupied by private commercial
businesses until 2005. The 1-story building was occupied by a florist between 1934 and
1983. The 1-story building was most recently utilized as an office space, and the 1- and
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
3
2-story building with a partial cellar was most recently utilized as an office of the US
Veterans of Foreign Wars (VFW).
The AOCs identified for this site include:
1. Adjacent former auto repair facility across 52nd Street.
2. Presence of urban fill from grade to approximately 2 feet bgs.
Summary of the Work Performed under the Remedial Investigation
Athenica performed the following scope of work at the site in between April and
September of 2014:
1. Conducted a Site inspection to identify AOCs and physical obstructions (i.e.
structures, buildings, etc.);
2. Installed five (5) soil borings across the entire project Site, and collected fourteen
(14) soil samples for chemical analysis from the soil borings to evaluate soil
quality;
3. Installed one (1) groundwater monitoring well at the Site and collected one (1)
groundwater sample for chemical analysis to evaluate groundwater quality;
4. Installed two (2) soil vapor probes and two (2) sub-slab vapor probes and
collected four (4) samples for chemical analysis.
Summary of Findings of Remedial Investigation
1. Elevation of the property ranges from 107 to 109 feet.
2. Depth to groundwater is 71.87 feet at the Site.
3. Groundwater flow is generally from east to west in the immediate vicinity of the
Site.
4. Bedrock was not encountered during the RI.
5. The stratigraphy of the site, from the surface down, consists of 2 feet of medium
coarse silty sand with traces of urban fill underlain by 10 feet of medium to coarse
sand with pebbles.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
4
6. Soil/fill samples collected during the RI were compared to 6 NYCRR Part 375-
6.8 Track 2 Restricted Residential Use Soil Cleanup Objectives (SCOs). Soil
sampling results showed no VOCs above detection limits, except for acetone
(max. of 0.069 ppm), a common laboratory contaminant which was found below
its Restricted Residential SCO. Several SVOCs, all Polycyclic Aromatic
Hydrocarbon (PAH)s, including Benzo(a)anthracene (max. of 34.80 ppm),
Benzo(a)pyrene (max. of 13.10 ppm), Benzo(b)fluoranthene (max. of 13.90 ppm),
Benzo(k)fluoranthene (max. of 16.70 ppm), Chrysene (max. of 40.60 ppm),
Dibenzo(a,h)anthracene (0.53 ppm), Indeno(1,2,3-cd)pyrene (max. of 8.36 ppm),
Naphthalene (max. of 12.70 ppm), and Phenanthrene (max. of 107 ppm), were
detected above their Restricted Residential Use SCOs in three shallow soil
samples. Pesticides including 4,4’-DDD (max. of 0.030 ppm) and 4,4’-DDT
(max. of 0.0054 ppm) were identified in shallow soil at concentrations well below
Restricted Residential Use SCOs. Metals including chromium hexavalent (2.71
ppm), copper (max. of 127 ppm), lead (max. of 278 ppm) and mercury (max. of
0.21ppm) were below Restricted Residential Use SCOs. No PCBs were detected
in any of the soil samples. Overall, the findings were consistent with observations
of historic fill sites in areas throughout NYC.
7. Groundwater sample results were compared to NYSDEC Technical &
Operational Guidance Series (TOGS) Class GA Ambient Water Quality
Standards (GQS). Two VOCs, chloroform (17 ug/L) and tetrachloroethylene
(PCE) (15 ug/L), were detected at concentrations exceeding their respective GQS.
Trace concentrations of several VOCs were also detected below GQS, including
bromodichloromethane, carbon disulfide, cis-1,2-Dichloroethylene (3.9 ug/L),
MTBE (2.5 ug/L), toluene, and TCE (0.92 ug/L). SVOCs were not detected above
GQS, and only Bis(2-ethylhexyl)phthalate was detected. Two dissolved metals,
manganese (1,050 ug/L) and sodium (79,800 ug/L) exceeded their respective
GQS. No pesticides or PCBs were detected above their detection limits.
8. Soil vapor samples collected during the RI were compared to the compounds
listed in Table 3.1 Air Guideline Values Derived by the NYSDOH located in the
New York State Department of Health (NYSDOH) Final Guidance for Evaluating
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
5
Soil Vapor Intrusion. Soil vapor results showed a wide range of VOCs at low
concentrations for petroleum related compounds and at elevated levels for
chlorinated compounds. Most compounds were detected at less than 10 μg/m3
except for acetone (max. of 450 μg/m3) and isopropanol (max. of 1600 μg/m3).
Petroleum related BTEX compounds were not detected in any vapor sample.
Chlorinated compounds including trichloroethene (TCE) and carbon tetrachloride
were not detected in any of the soil vapor samples. Tetrachloroethylene (PCE)
was detected in three of the four soil vapor samples, ranging from 14 ug/m3 to
2,500 ug/m3 which is above the mitigation range established by NYSDOH Final
Guidance on Soil Vapor Intrusion (October 2006). 1,1,1-Trichloroethane (TCA)
was detected in one of the four samples, at a concentration of 88 ug/m3, which is
below the monitoring/ mitigation range established by NYSDOH. PCE
concentration is above the mitigation level range established by NYSDOH
Guidance matrix and requires further action.
9. Supplemental soil vapor samples collected in May 2015 were compared to the
compounds listed in Table 3.1 Air Guideline Values Derived by the NYSDOH
located in their Final Guidance for Evaluating Soil Vapor Intrusion. Sample
results showed low to moderate levels of chlorinated VOCs. Chlorinated VOCs
were detected at concentrations ranging from non-detectable above laboratory
MDLs to 172 ug/m3. PCE was detected across the Site at concentrations ranging
from 8 ug/m3 to 172 ug/m3, which exceeds the mitigation range established by the
NYSDOH Final Guidance on Soil Vapor Intrusion (October 2006). No other
VOCs were detected at concentrations exceeding their respective mitigation
range. BTEX compounds were not detected at significant concentrations in any
vapor sample collected at the Site.
10. One supplemental sub-slab soil vapor sample collected in November 2016,
subsequent to Site excavation, was compared to the compounds listed in Table 3.1
Air Guideline Values Derived by the NYSDOH located in their Final Guidance
for Evaluating Soil Vapor Intrusion. Sample results showed no concentrations of
VOCs in sub-slab soil vapor at the Site. One VOC, acetone, a common laboratory
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
6
contaminant, was detected at a concentration above its laboratory MDL. No other
VOCs were detected at concentrations above their respective laboratory MDLs.
Summary of the Remedial Action
The remedial action achieved protection of public health and the environment for the
intended use of the property. The remedial action achieved all of the remedial action
objectives established for the project and addressed applicable standards, criterion, and
guidance; was effective in both the short-term and long-term and reduced mobility,
toxicity and volume of contaminants; was cost effective and implementable; and used
standards methods that are well established in the industry.
A summary of the milestones achieved in the Remedial Action is as follows: A Pre-
Application Meeting was held on April 29, 2014. A Remedial Investigation (RI) was
performed from April 2014 to June 2015. A RI Report was prepared to evaluate data and
information necessary to develop a Remedial Action Work Plan (RAWP). A Site Contact
List was established. A draft RAWP was prepared and released with a Fact Sheet on
October 6, 2014 for a 30-day public comment period. The RAWP and Stipulation List
dated November 19, 2014 were approved by the New York City Office of Environmental
Remediation (OER) and the Notice to Proceed was issued on February 6, 2015. A Pre-
Construction Meeting was held on April 30, 2015. A Fact Sheet providing notice of the
start of the remedial action was issued on May 13, 2015. The remedial action was begun
in May 2015 and completed in March 2017.
The remedial action consisted of the following tasks:
1. Prepared a Community Protection Statement and implemented a Citizen
Participation Plan.
2. Mobilized site security, equipment, utility mark outs and marking & staking
excavation areas.
3. Performed Waste Characterization Study prior to excavation activities. Nine (9)
waste characterization soil samples were collected on March 16, 2015. Waste
characterization samples were collected at a frequency dictated by disposal
facilities.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
7
4. Performed a Community Air Monitoring Program for particulates and volatile
organic carbon compounds.
5. Established Track 4 Site-Specific Soil Cleanup Objectives (SCO’s). The
following Track 4 SCO’s were utilized: Total SVOCs: 250 mg/kg; and lead: 600
mg/kg.
6. The following excavations were performed as part of development: soil was
removed to a depth of 11 feet from grade beneath the area of the new building for
the cellar level, 19 feet from grade for two elevator pits within the building
footprint, and to a depth of 2 feet in the remaining open space areas. Urban fill
identified in the shallow soil as Areas of Concern (AOC) were removed across
the site as part of construction. A total of 1,494.45 tons of soil/fill was excavated
and removed from the property.
7. Excavated 1,494.45 tons of non-hazardous soil/fill and transported to the Clean
Earth facility located at 24 Middlesex Avenue, Carteret, New Jersey.
8. Screened excavated soil/fill during intrusive work for indications of
contamination by visual means, odor, and monitoring with a PID.
9. Conducted materials management of excavated materials including temporarily
stockpiling and segregating in accordance with defined material types and to
prevent co-mingling of contaminated material and non-contaminated materials.
10. Appropriately segregated excavated media onsite prior to disposal. Transported
and disposed all soil/fill material at permitted facilities in accordance with all
applicable laws and regulations for handling, transport, and disposal, and the
RAWP.
11. Collected and analyzed four (4) end-point samples to determine attainment of
SCOs. Track 2 Restricted Residential SCOs were achieved for soil; however due
to the elevated concentrations of vapors in soil, an active sub-slab
depressurization system (SSDS) was installed beneath the new building.
12. As part of development, constructed an engineered Composite Cover System
consisting of two feet of clean soil capped with a 6-inch concrete surface in the
open area on the northern portion of the Site and a 4-inch concrete building slab
underlain by clean compacted soil across the entire new building footprint. The
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
8
contractor for the cover construction was Allstate 12 General Contracting
Corporation.
13. As part of development, installed a Vapor Barrier System that consisted of a 20-
mil vapor barrier beneath the structure’s slab and along foundation sidewalls.
The barrier chosen for this project was manufactured by Raven Industries, Inc.
Vapor Block Plus 20, a seven-layer co-extruded 20 mil vapor barrier made from
polyethylene and EVOH resins. The contractor for the vapor barrier installation
was Allstate 12 General Contracting Corporation.
14. Installed and operating an active Sub-Slab Depressurization System consisting of
one depressurization pit installed beneath the slab and surrounded by a
depressurization area approximately 170-square feet in size that has been
backfilled with ¾-inch clean bluestone to a depth of approximately 6-inches
below the slab. The depressurization pit is approximately 5.5-feet by 3-feet in
area and 1.5-feet in depth and consists of an open void beneath the slab that is
framed with concrete blocks and covered with a diamond steel plate. A 4-inch
diameter schedule 40 PVC perforated pipe was installed in the pit and connected
to an exhaust pipe that penetrates the building slab and extends vertically to the
roof of the elevator bulkhead. A trench filled with 4-inches of crushed bluestone
was placed around the horizontal perforated pipe. The 4-inch PVC vertical
standpipe is connected to a hardwired RadonAway RP265 vacuum blower
installed inline at the roof level. A sample port, vacuum pressure alarm system,
and magnehelic vacuum gauge were installed on the riser pipe in an access panel
in the building’s basement to confirm system operation. The exhaust discharge
point is located a minimum 10-feet away from any operable window or air intake
for any building. The design engineer for the active SSDS system was Ariel
Czemerinksi, P.E. of AMC Engineering. The SSDS piping system was installed
by Neda Development Incorporated and the SSDS fan was installed by United
Electric. The SSDS system installation was observed on behalf of the P.E. by
Athenica and confirmed to be built according to design and equipment
manufacturer specifications.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
9
15. Performed all activities required for the Remedial Action, including permitting
requirements and pretreatment requirements, in compliance with applicable laws
and regulations.
16. Implemented storm-water pollution prevention measures in compliance with
applicable laws and regulations.
17. Submitted daily reports during construction oversight activities. Daily reports
were submitted from May 22, 2015 to March 23, 2017.
18. Soil used for backfill and cover completed in compliance with the Remedial
Action Work Plan and in accordance with applicable laws and regulations.
19. Submitted a Sustainability Report.
20. Submitted a RAR that describes the Remedial Action, certifies that the remedial
requirements defined in the Remedial Action Work Plan have been achieved;
defines the Site boundaries; describes all Engineering and Institutional Controls
applicable to the Site; and describes any changes from the RAWP.
21. Submitted a Site Management Plan (SMP) for long-term management of residual
soil, including plans for operation, maintenance, inspection and certification of
the performance of Engineering Controls and Institutional Controls. Inspections
will be performed annually. Inspection and Certification reports will be
submitted by July 31, 2019 (for the reporting period calendar year 2018), July 31,
2020 (for the reporting period calendar year 2019) and every year thereafter (for
the reporting period consisting of the prior calendar year). Inspection and
Certification Reports will cover all calendar years since the prior reporting
period.
22. The property will continue to be registered with an E-Designation by the NYC
Department of Buildings. Engineering Controls and Institutional Controls will be
managed in compliance with the SMP.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
10
REMEDIAL ACTION REPORT
1.0 SITE BACKGROUND
Q52, LLC has enrolled in the New York City Voluntary Cleanup Program (NYC
VCP) to investigate and remediate a property located at 51-27 Queens Boulevard in the
Woodside section of Queens, New York. The boundary of the property subject to this
Remedial Action is shown in Figure 2 and includes, in its entirety, Queens Block 1320
and Lot 47. The Remedial Action was performed pursuant to the OER-approved RAWP
in a manner that has rendered the property protective of public health and the
environment consistent with its intended use. This RAR describes the Remedial Action
performed under the RAWP. The remedial action described in this document provides for
the protection of public health and the environment and complies with applicable
environmental standards, criteria and guidance (SCGs) and applicable laws and
regulations.
1.1 SITE LOCATION AND BACKGROUND
The Site is located at 51-27 Queens Boulevard in the Woodside section of Queens,
New York and is identified as Block 1320 and Lot 47 on the New York City Tax Map.
Figure 1 shows the Site location. The Site is 5,387-square feet and is bounded by an
asphalt-paved parking lot to the north, Queens Boulevard to the south, 52nd Street to the
east, and a multi-story residential building to the west. A map of the site boundary is
shown in Figure 2.
Prior to redevelopment, the Site was developed with a vacant as of 2014 1-story
commercial building previously utilized as an office and a 1- and 2-story building with
partial cellar utilized as an office.
1.2 REDEVELOPMENT PLAN
A new 7-story mixed residential and commercial use building with a full cellar has
been constructed at the Site. The new building occupies 4,227-square feet, or
approximately 80 percent of the lot area with the remaining open area consisting of a
1,160-square foot concrete-paved courtyard area located on the northern portion of the
property. The layout of the redevelopment is shown in Figures 3A and 3B.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
11
The total gross square footage of the new building is approximately 32,861-square
feet, including 2,789-square feet of retail space, 3,943-square feet of community facility
space, 1,486-square feet of retail storage space, and the remaining area utilized as 29
Class “A” dwelling units, tenant storage, elevator mechanical rooms, sprinkler and water
meter room, electrical meter room, gas meter room, laundry, and compactor room. The
cellar is utilized for commercial use, utility and meter rooms with accessory uses for the
commercial and residential occupancies. The first floor is used for commercial retail,
residential lobby, and one residential apartment. The second floor is used for community
facility space. Floors 3 through 7 are utilized as residential apartment units.
As part of development, the building footprint was excavated to approximately 11-
feet below grade surface (bgs) for installation of the cellar. An additional 9-feet was
excavated in two locations of the cellar for the installation of elevator pits. The remaining
area (1,160-square feet) on the northern portion of the property was excavated to 2-feet
bgs. The total amount of soil removed off-site for excavation of the cellar is 1,494.45
tons. The current zoning designation is C2-3/R7X, denoting it as a residential and light
commercial district. The current use is consistent with existing zoning for the property.
A map showing the building location, basement location and open space location is
shown in the Development Plan in Figures 3A and 3B.
1.3 DESCRIPTION OF SURROUNDING PROPERTY
The Site is located within a mixed use residential and commercial area of Queens,
New York. The Site is bounded by an asphalt-capped parking area to the north, Queens
Boulevard to the south beyond which is Calvary Cemetery, 52nd Street to the east
beyond which is a twelve-story mixed use building, and a multi-story residential building
to the west. There are no sensitive receptors (such as schools, hospitals, and day-care
facilities) within a 500-foot radius of the Site.
1.4 SUMMARY OF PAST SITE USES AND AREAS OF CONCERN
Based upon the review of the Phase I Environmental Site Assessment (ESA) Report
prepared by Athenica Environmental Services (Athenica) in April 2014, the Site history
was established. Prior to redevelopment, the Site was developed with a 1-story building
and a 1- and 2-story building with a partial cellar. The 2-story building was occupied by
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
12
different restaurants between 1934 and 1962. The 2-story building was then utilized as a
private lounge between 1970 and 1983. It was then occupied by private commercial
businesses until 2005. The 1-story building was occupied by a florist between 1934 and
1983. The 1-story building was most recently utilized as an office space, and the 1- and
2-story building with a partial cellar was most recently utilized as an office of the US
Veterans of Foreign Wars (VFW).
The AOCs identified for this site include:
1. Adjacent former auto repair facility across 52nd Street.
2. Presence of urban fill from grade to approximately 2 feet bgs.
1.5 SUMMARY OF WORK PERFORMED UNDER THE REMEDIAL
INVESTIGATION
Athenica performed the following scope of work at the Site between April and September
of 2014:
1. Conducted a Site inspection to identify AOCs and physical obstructions (i.e.
structures, buildings, etc.);
2. Installed five (5) soil borings across the entire project Site, and collected fourteen
(14) soil samples for chemical analysis from the soil borings to evaluate soil
quality;
3. Installed one (1) groundwater monitoring well at the Site and collected one (1)
groundwater sample for chemical analysis to evaluate groundwater quality;
4. Installed two (2) soil vapor probes and two (2) sub-slab vapor probes and
collected four (4) samples for chemical analysis.
1.6 SUMMARY OF FINDINGS OF REMEDIAL INVESTIGATION
1. Elevation of the property ranges from 107 to 109 feet.
2. Depth to groundwater is 71.87 feet at the Site.
3. Groundwater flow is generally from east to west in the immediate vicinity of the
Site.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
13
4. Bedrock was not encountered during the RI.
5. The stratigraphy of the site, from the surface down, consists of 2 feet of medium
coarse silty sand with traces of urban fill underlain by 10 feet of medium to coarse
sand with pebbles.
6. Soil/fill samples collected during the RI were compared to 6 NYCRR Part 375-
6.8 Track 2 Restricted Residential Use Soil Cleanup Objectives (SCOs). Soil
sampling results showed no VOCs above detection limits, except for acetone
(max. of 0.069 ppm), a common laboratory contaminant which was found below
its Restricted Residential SCO. Several SVOCs, all Polycyclic Aromatic
Hydrocarbon (PAH)s, including Benzo(a)anthracene (max. of 34.80 ppm),
Benzo(a)pyrene (max. of 13.10 ppm), Benzo(b)fluoranthene (max. of 13.90 ppm),
Benzo(k)fluoranthene (max. of 16.70 ppm), Chrysene (max. of 40.60 ppm),
Dibenzo(a,h)anthracene (0.53 ppm), Indeno(1,2,3-cd)pyrene (max. of 8.36 ppm),
Naphthalene (max. of 12.70 ppm), and Phenanthrene (max. of 107 ppm), were
detected above their Restricted Residential Use SCOs in three shallow soil
samples. Pesticides including 4,4’-DDD (max. of 0.030 ppm) and 4,4’-DDT
(max. of 0.0054 ppm) were identified in shallow soil at concentrations well below
Restricted Residential Use SCOs. Metals including chromium hexavalent (2.71
ppm), copper (max. of 127 ppm), lead (max. of 278 ppm) and mercury (max. of
0.21ppm) were below Restricted Residential Use SCOs. No PCBs were detected
in any of the soil samples. Overall, the findings are unremarkable and are
consistent with observations of historic fill sites in areas throughout NYC.
7. Groundwater sample results were compared to NYSDEC Technical &
Operational Guidance Series (TOGS) Class GA Ambient Water Quality
Standards (GQS). Two VOCs, chloroform (17 ug/L) and tetrachloroethylene
(PCE) (15 ug/L), were detected at concentrations exceeding their respective GQS.
Trace concentrations of several VOCs were also detected below GQS, including
bromodichloromethane, carbon disulfide, cis-1,2-Dichloroethylene (3.9 ug/L),
MTBE (2.5 ug/L), toluene, and TCE (0.92 ug/L). SVOCs were not detected above
GQS, and only Bis(2-ethylhexyl)phthalate was detected. Two dissolved metals,
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
14
manganese (1,050 ug/L) and sodium (79,800 ug/L) exceeded their respective
GQS. No pesticides or PCBs were detected above their detection limits.
8. Soil vapor samples collected during the RI were compared to the compounds
listed in Table 3.1 Air Guideline Values Derived by the NYSDOH located in the
New York State Department of Health (NYSDOH) Final Guidance for Evaluating
Soil Vapor Intrusion. Soil vapor results showed a wide range of VOCs at low
concentrations for petroleum related compounds and at elevated levels for
chlorinated compounds. Most compounds were detected at less than 10 μg/m3
except for acetone (max. of 450 μg/m3) and isopropanol (max. of 1600 μg/m3).
Petroleum related BTEX compounds were not detected in any vapor sample.
Chlorinated compounds including trichloroethene (TCE) and carbon tetrachloride
were not detected in any of the soil vapor samples. Tetrachloroethylene (PCE)
was detected in three of the four soil vapor samples, ranging from 14 ug/m3 to
2,500 ug/m3 which is above the mitigation range established by NYSDOH Final
Guidance on Soil Vapor Intrusion (October 2006). 1,1,1-Trichloroethane (TCA)
was detected in one of the four samples, at a concentration of 88 ug/m3, which is
below the monitoring/ mitigation range established by NYSDOH. PCE
concentration is above the mitigation level range established by NYSDOH
Guidance matrix and requires further action.
9. Supplemental soil vapor samples collected in May 2015 were compared to the
compounds listed in Table 3.1 Air Guideline Values Derived by the NYSDOH
located in their Final Guidance for Evaluating Soil Vapor Intrusion. Sample
results showed low to moderate levels of chlorinated VOCs. Chlorinated VOCs
were detected at concentrations ranging from non-detectable above laboratory
MDLs to 172 ug/m3. PCE was detected across the Site at concentrations ranging
from 8 ug/m3 to 172 ug/m3, which exceeds the mitigation range established by the
NYSDOH Final Guidance on Soil Vapor Intrusion (October 2006). No other
VOCs were detected at concentrations exceeding their respective mitigation
range. BTEX compounds were not detected at significant concentrations in any
vapor sample collected at the Site.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
15
10. One supplemental sub-slab soil vapor sample collected in November 2016,
subsequent to Site excavation, was compared to the compounds listed in Table 3.1
Air Guideline Values Derived by the NYSDOH located in their Final Guidance
for Evaluating Soil Vapor Intrusion. Sample results showed no concentrations of
VOCs in sub-slab soil vapor at the Site. One VOC, acetone, a common laboratory
contaminant, was detected at a concentration above its laboratory MDL. No other
VOCs were detected at concentrations above their respective laboratory MDLs.
For more detailed results, consult the RIR presented as Appendix A and the
Supplemental Soil Vapor Sampling Letter Report presented as Appendix D.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
16
2.0 DESCRIPTION OF REMEDIAL ACTIONS
The remedial action was performed in accordance with an OER approved Remedial
Action Work Plan and achieved the remedial action objectives established for the project.
The remedial action was evaluated in an alternatives analysis and was determined to be
protective of human health and the environment, compliant with standards, criteria, and
guidelines (SCGs), effective in the short-term, effective in the long-term, capable of
attaining appropriate levels of reduction of toxicity, mobility, or volume of contaminated
material, implementable, cost effective, acceptable to the community, consistent with
land uses, and sustainable.
A summary of the milestones achieved in the Remedial Action is as follows: A Pre-
Application Meeting was held on April 29, 2014. A Remedial Investigation (RI) was
performed from April 2014 to June 2015. A RI Report was prepared to evaluate data and
information necessary to develop a Remedial Action Work Plan (RAWP). A Site Contact
List was established. A draft RAWP was prepared and released with a Fact Sheet on
October 6, 2014 for a 30-day public comment period. The RAWP and Stipulation List
dated November 19, 2014 were approved by the New York City Office of Environmental
Remediation (OER) and the Notice to Proceed was issued on February 6, 2015. A Pre-
Construction Meeting was held on April 30, 2015. A Fact Sheet providing notice of the
start of the remedial action was issued in May 2015. The remedial action was begun in
May 2015 and completed in March 2017. Appendix A includes the Remedial
Investigation Report and Appendix B contains RAWP and Stipulation List.
The remedial action consisted of the following tasks:
1. Prepared a Community Protection Statement and implemented a Citizen
Participation Plan.
2. Mobilized site security, equipment, utility mark outs and marking & staking
excavation areas.
3. Performed Waste Characterization Study prior to excavation activities. Nine (9)
waste characterization soil samples were collected on March 16, 2015. Waste
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
17
characterization samples were collected at a frequency dictated by disposal
facilities.
4. Performed a Community Air Monitoring Program for particulates and volatile
organic carbon compounds.
5. Established Track 4 Site-Specific Soil Cleanup Objectives (SCO’s). The
following Track 4 SCO’s were utilized: Total SVOCs: 250 mg/kg; and lead: 600
mg/kg.
6. The following excavations were performed as part of development: soil was
removed to a depth of 11 feet from grade beneath the area of the new building for
the cellar level, 19 feet from grade for two elevator pits within the building
footprint, and to a depth of 2 feet in the remaining open space areas. Urban fill
identified in the shallow soil as Areas of Concern (AOC) were removed across
the site as part of construction. A total of 1,494.45 tons of soil/fill was excavated
and removed from the property.
7. Excavated 1,494.45 tons of non-hazardous soil/fill and transported to the Clean
Earth facility located at 24 Middlesex Avenue, Carteret, New Jersey.
8. Screened excavated soil/fill during intrusive work for indications of
contamination by visual means, odor, and monitoring with a PID.
9. Conducted materials management of excavated materials including temporarily
stockpiling and segregating in accordance with defined material types and to
prevent co-mingling of contaminated material and non-contaminated materials.
10. Appropriately segregated excavated media onsite prior to disposal. Transported
and disposed all soil/fill material at permitted facilities in accordance with all
applicable laws and regulations for handling, transport, and disposal, and the
RAWP.
11. Collected and analyzed four (4) end-point samples to determine attainment of
SCOs. Track 2 Restricted Residential SCOs were achieved for soil; however due
to the elevated concentrations of vapors in soil, an active sub-slab
depressurization system (SSDS) was installed beneath the new building.
12. As part of development, constructed an engineered Composite Cover System
consisting of two feet of clean soil capped with a 6-inch concrete surface in the
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
18
open area on the northern portion of the Site and a 4-inch concrete building slab
underlain by clean compacted soil across the entire new building footprint. The
contractor for the cover construction was Allstate 12 General Contracting
Corporation.
13. As part of development, installed a Vapor Barrier System that consisted of a 20-
mil vapor barrier beneath the structure’s slab and along foundation sidewalls.
The barrier chosen for this project was manufactured by Raven Industries, Inc.
Vapor Block Plus 20, a seven-layer co-extruded 20 mil vapor barrier made from
polyethylene and EVOH resins. The contractor for the vapor barrier installation
was Allstate 12 General Contracting Corporation.
14. Installed and operating an active Sub-Slab Depressurization System consisting of
one depressurization pit installed beneath the slab and surrounded by a
depressurization area approximately 170-square feet in size that has been
backfilled with ¾-inch clean bluestone to a depth of approximately 6-inches
below the slab. The depressurization pit is approximately 5.5-feet by 3-feet in
area and 1.5-feet in depth and consists of an open void beneath the slab that is
framed with concrete blocks and covered with a diamond steel plate. A 4-inch
diameter schedule 40 PVC perforated pipe was installed in the pit and connected
to an exhaust pipe that penetrates the building slab and extends vertically to the
roof of the elevator bulkhead. A trench filled with 4-inches of crushed bluestone
was placed around the horizontal perforated pipe. The 4-inch PVC vertical
standpipe is connected to a hardwired RadonAway RP265 vacuum blower
installed inline at the roof level. A sample port, vacuum pressure alarm system,
and magnehelic vacuum gauge were installed on the riser pipe in an access panel
in the building’s basement to confirm system operation. The exhaust discharge
point is located a minimum 10-feet away from any operable window or air intake
for any building. The design engineer for the active SSDS system was Ariel
Czemerinksi, P.E. of AMC Engineering. The SSDS piping system was installed
by Neda Development Incorporated and the SSDS fan was installed by United
Electric. The SSDS system installation was observed on behalf of the P.E. by
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
19
Athenica and confirmed to be built according to design and equipment
manufacturer specifications.
15. Performed all activities required for the Remedial Action, including permitting
requirements and pretreatment requirements, in compliance with applicable laws
and regulations.
16. Implemented storm-water pollution prevention measures in compliance with
applicable laws and regulations.
17. Submitted daily reports during construction oversight activities. Daily reports
were submitted from May 22, 2015 to March 23, 2017.
18. Soil used for backfill and cover completed in compliance with the Remedial
Action Work Plan and in accordance with applicable laws and regulations.
19. Submitted a Sustainability Report.
20. Submitted a RAR that describes the Remedial Action, certifies that the remedial
requirements defined in the Remedial Action Work Plan have been achieved;
defines the Site boundaries; describes all Engineering and Institutional Controls
applicable to the Site; and describes any changes from the RAWP.
21. Submitted a Site Management Plan (SMP) for long-term management of residual
soil, including plans for operation, maintenance, inspection and certification of
the performance of Engineering Controls and Institutional Controls. Inspections
will be performed annually. Inspection and Certification reports will be
submitted by July 31, 2019 (for the reporting period calendar year 2018), July 31,
2020 (for the reporting period calendar year 2019) and every year thereafter (for
the reporting period consisting of the prior calendar year). Inspection and
Certification Reports will cover all calendar years since the prior reporting
period.
22. The property will continue to be registered with an E-Designation by the NYC
Department of Buildings. Engineering Controls and Institutional Controls will be
managed in compliance with the SMP.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
20
3.0 COMPLIANCE WITH REMEDIAL ACTION
WORKPLAN
3.1 CONSTRUCTION HEALTH & SAFETY PLAN
The remedial construction activities performed under this program were in
compliance with the Construction Health and Safety Plan and applicable laws and
regulations. The Site Safety Coordinator was Joseph Yahudaii.
3.2 COMMUNITY AIR MONITORING PLAN
The Community Air Monitoring Plan provided guidance for the collection and
analysis of air samples during remedial construction activities to ensure proper
protections were employed to protect workers and the neighboring community.
Monitoring was performed in compliance with the Community Air Monitoring Plan in
the approved RAWP. No exceedances of dust or VOCs were recorded at the Site during
the entirety of remedial action. CAMP data was not recorded during one remedial
construction day, June 17, 2015, due to equipment malfunction. During that time no
excessive visual dust was observed. The results of Community Air Monitoring are shown
in Appendix C.
3.3 SOIL/MATERIALS MANAGEMENT PLAN
The Soil/Materials Management Plan provided detailed plans for managing all
soil/materials that were disturbed at the Site, including excavation, handling, storage,
transport and disposal. It also included a series of controls to assure effective, nuisance
free remedial activity in compliance with applicable laws and regulations. Remedial
construction activities performed under this program were in compliance with the SMMP
in the approved RAWP.
3.4 STORM-WATER POLLUTION PREVENTION
Storm water pollution prevention included physical methods and processes to control
and/or divert surface water flows and to limit the potential for erosion and migration of
Site soils, via wind or water. Remedial construction activities performed under this
program were in full compliance with methods and processes defined in the RAWP for
storm water prevention and applicable laws and regulations.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
21
3.5 DEVIATIONS FROM THE REMEDIAL ACTION WORK PLAN
The PE who certified the Remedial Action Work Plan dated October 2014 was
Reza Sharif. However Ariel Czemerinski, P.E. took over the project prior to
construction. He has reviewed all the plans and remedial design and oversaw the
installation of vapor barrier, composite cover, and sub-slab depressurization
system. Mr. Czemerinski is the PE certifying this Remedial Action Report.
The QEP who certified the Remedial Action Work Plan dated October 2014 was
William Silveri. However the project was taken over by Spiro Dongaris who is
the QEP certifying this Remedial Action Report.
The Remedial Action Work Plan dated October 2014 proposed a Track 4 remedy
based on the installation of an active sub-slab depressurization system. However,
Track 2 SCOs were achieved for soil upon completion of the excavation event. A
total of 1,494.45 tons of non-hazardous soil/fill was removed from the Site.
The Remedial Action Work Plan dated October 2014 described the
depressurization pit as an area 2 by 2 feet and 2 feet in depth with the entire
footprint of the building under the influence of the suction pit. However, the
actual depressurization pit was constructed in an area 5.5 by 3 feet and 1.5 feet in
depth within an area of influence approximately 170-square feet backfilled with
¾-inch clean bluestone. Due to the design of the footings and strap beams,
communication under the entire slab was not possible and the area under the
influence of the suction pit was reduced to the area identified to have elevated
PCE concentration during the RI. One round of supplemental soil vapor sampling
prior to excavation and one round of sub-slab soil vapor sampling subsequent to
excavation were conducted in conjunction with the change in SSDS design. The
change in pit size and area under influence does not alter the operation of the
SSDS system and focuses the system onto the area of concern. The SSDS as built
remains protective of public health and the environment. A letter summarizing the
results of the supplemental sub-slab soil vapor sampling, as well as the proposed
change in SSDS design, and an email confirmation from OER approving the
change in design are provided in Appendix D.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
22
The Remedial Action Work Plan dated October 2014 included plans to cap the
open space located on the northern portion of the Site with 2 feet of clean soil;
however, during the course of development, the open area was redesigned to
include a Composite Cover System consisting of 2 feet of clean soil and 6 inches
of poured concrete. A demarcation barrier was not installed beneath the open
space Composite Cover System.
No other significant deviations from the Remedial Action Work Plan occurred during
implementation of the plan.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
23
4.0 REMEDIAL PROGRAM
4.1 PROJECT ORGANIZATION
Principal personnel who participated in the remedial action include Ezgi Karayel
(Project Manager) and Curtis Breuer (Environmental Scientist/Geologist). The
Professional Engineer (PE) and Qualified Environmental Professionals (QEP) for this
project were Ariel Czemerinski, P.E. and Spiro Dongaris, P.E. respectively. The
developer throughout the remedial action was Joseph Yahudaii of Neda Development,
Inc. and the project architect is Victor Filletti, R.A. of T.F. Cusanelli & Filletti Architects
P.C.
4.2 SITE CONTROLS
Site Preparation
Mobilization was conducted as necessary for each phase of work at the Site.
Mobilization included field personnel orientation, equipment mobilization
(including securing all sampling equipment needed for the field investigation),
marking/staking sampling locations, and utility mark-outs. Each field team
member attended an orientation meeting to become familiar with the general
operation of the Site, health and safety requirements, and field procedures.
Mobilization at the Site occurred in October 2014;
Fencing was installed at the Site by October 2014;
Erosion and sedimentation controls were established by May 2015;
The presence of utilities and easements on the Site was fully investigated prior to
the performance of invasive work such as excavation or drilling under this plan by
using, at a minimum, the One-Call System (811). Underground utilities may pose
an electrocution, explosion, or other hazard during excavation or drilling
activities. All invasive activities were performed in compliance with applicable
laws and regulations to assure safety. Utility companies and other responsible
authorities were contacted to locate and mark the locations. Proper safety and
protective measures pertaining to utilities and easements, and compliance with all
laws and regulations were employed during invasive and other work. The
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
24
integrity and safety of on-Site and off-Site structures were maintained during all
invasive, excavation or other remedial activity performed under the RAWP;
The building department issued a building permit for the Site on March 9, 2015;
A pre-construction meeting was held with all contractors on April 30, 2015; and
An OER Project Notice was erected at the project entrance and was in place
during all phases of the Remedial Action.
Soil Screening
Excavation activities began in May 2015. Intrusive soil excavation activities were
overseen by an Athenica as discussed with OER. In addition to extensive sampling and
chemical testing of soils on the Site, excavated soil was screened continuously using
hand-held instruments, and by sight to ensure proper material handling and management.
No visual or olfactory evidence of a spill was observed during Site excavation. VOC
readings were continuously observed and recorded during excavation as part of the
Community Air Monitoring Plan. No elevated readings were recorded.
Stockpile Management
The excavation of on-Site soils was accomplished by directly loading the materials
onto trucks for off-Site disposal/reuse. Stockpiling was minimized. Recognizable C&D
were stockpiled for off-Site disposal on bare soil adjacent to the excavation and near the
trucking gate located in the northeast corner of the Site. Soils utilized for on-Site reuse
were also briefly staged in the northeast corner of the Site prior to use as backfill in the
same area.
Truck Inspection
Outbound-trucks were inspected and cleaned prior to departing the Site from the
trucking gate located in the northeast corner of the Site to prevent any off-Site migrations
of contamination. Cleaning of the adjacent streets was performed as needed during all
trucking events. No evidence of significant off-Site migration of soil was observed during
remedial construction.
Site Security
Site access was controlled through gated entrance of the construction fence. The
fence was locked with a chain and padlock during non-working hours/days.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
25
Nuisance Controls
There were no complaints of odor at the Site. VOCs and dust levels at the Site were
not detected at concentrations warranting corrective action.
Reporting
Daily reports were prepared and submitted to the OER. All daily and monthly reports
are included in Appendix E. Digital photographs of the Remedial Action are included in
Appendix F.
4.3 MATERIALS EXCAVATION AND REMOVAL
Soil/Fill Excavation and Removal
Demolition
Prior to the start of foundation work, the two former on-Site buildings were
demolished under DOB Job No. 420952570 following the approval notice on February
27, 2014 until the sign off notice on May 5, 2015.
Soil Excavation
Followed by the completion of demolition, as part of development, the entire 4,227-
square foot footprint of the new building was excavated to a depth of 11 feet below grade
surface (bgs). In addition, the remaining 1,160-square foot open area was excavated to a
depth of 2 feet bgs to remove historic fill identified during the RI. Additional excavations
of 9-feet were required in two locations in the cellar for the installation of elevator pits. A
map showing the approximate locations where excavations were performed and
approximate thickness of excavated material is shown in Figure 5.
During remedial excavation, the Site was divided into equal quadrants for reporting
purposes, consisting of Grid 1 located in the southwest corner of the Site, along Queens
Boulevard, and progressing clockwise to Grid 4 located in the southeast corner of the
Site, on the corner of Queens Boulevard and 52nd Street. Excavation activity began on
May 22, 2015 with excavation and off-Site disposal of historical fill material from zero to
2 feet below grade across the entire Site. Excavation further progressed from the southern
boundary of the Site, Grid 1 and Grid 4, to the northern extent of the building footprint to
allow for construction of the basement. Excavation of the building’s footprint and off-
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
26
Site soil disposal was completed on June 22, 2015.
A total of 1,494.45 tons of non-hazardous soil/fill was removed from the Site.
Approximately 153 cubic yards of clean native soil excavated from the deep (4- to 11-
feet) interval of Grid 1 was utilized as backfill for the northern open portion of the Site
that was excavated to 2-feet bgs for disposal of historic fill and as backfill behind
foundation walls along 52nd Street and Queens Boulevard. The material encountered
during excavation consisted of brown silty sand and medium to coarse-grained sand with
cobbles. A map showing the approximate source location of reused soil and the location
of placement of reused soil is shown in Figure 6.
Soil Cleanup Objectives
The SCOs for this Site are listed in the 6NYCRR Part 375, Table 6.8(b) Track 2
Restricted Residential Use SCOs as amended by the following Track 4 Site-Specific
SCOs:
Contaminant Site-Specific SCOs
Total SVOCs 250 mg/kg
Lead 600 mg/kg
The SCOs for this Remedial Action are provided in Table 1.
End Point Sample Results
The SCOs for this project were achieved.
Following the completion of excavation activities at the Site, end-point bottom soil
samples were collected at four (4) locations across the Site as proposed in the Stipulation
List dated November 19, 2014. The end-point soil samples were collected using a
dedicated, disposable sampling scoop from three locations at a depth of 11 feet bgs (base
of final excavation) and one location at a depth of 2 feet bgs (base of excavation in open
portion of the Site). Collected end-point soil samples were containerized in laboratory
provided glassware, labeled and placed in coolers. Samples were picked up by the
laboratory on the same day as the collection date. They were preserved on ice in the
coolers to maintain a temperature of 4ºC. York Analytical Laboratories located at 120
Research Drive, Stratford, CT 06615 (New York ELAP Certification No. 10854) was
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
27
used. All end-point soil samples were analyzed for VOCs via EPA Method 8260, SVOCs
via EPA Method 8270, TAL Metals by EPA Method 6010, PCBs and Pesticides via EPA
Method 8081/8082. Analytical laboratory reports for the end-point soil samples are
included in Appendix G. A copy of the laboratory’s ELAP certification is included in
Appendix H.
A map of end-point sample locations is shown in Figure 4. A tabular summary of
end-point sampling results (and representative RI sampling results) compared to SCOs is
included in Table 1.
The end-point samples were compared to Part 375 Track 2 Restricted Residential Use
SCOs and Track 4 Site-Specific SCOs. Significant findings and results of the end-point
soil sampling are as follows:
The subsurface soils did not exhibit field evidence of petroleum or solvent
contamination (i.e. staining, odor).
End-point soil sampling results indicate that soil conditions achieved Track 2
Restricted Residential Use SCOs. Two VOCs, one SVOC and several metals were
detected at minor concentrations well below Track 2 Restricted Residential SCOs.
There was only one minor detection of the pesticide 4,4,4’-DDT also below Track
2 Restricted Residential SCOs. This pesticide was detected in three out of four
samples and the results are from an analysis that required a dilution.
One RIR soil sample, SB-1 (2’-4’), was collected in northern open space area of
the Site and is also representative of the remaining material left at the base of the
excavation. One metal, mercury, was detected at a concentration of 0.21 mg/kg,
slightly above its Track 1 Unrestricted Use SCO but well below its Track 2
Restricted Residential SCO. No other compounds exceeded any of their Part 375
SCOs in SB-1 (2’-4’). The complete analytical data package for the RIR is
included in Appendix A.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
28
4.4 MATERIALS DISPOSAL
As indicated below, soils and fill were properly characterized for off-site disposal
and/or re-use in accordance with the RAWP and/or specific requirements of the off-site
disposal and/or reuse facilities. For characterization of soils and fill for off-site disposal,
five (5) test pits were excavated, and representative soil samples were collected from
each test pit for laboratory analysis. A brief summary of the classification of soils and fill
are found below:
Results of waste classification sampling for historic fill/soils and native clean
soils were sent to Clean Earth for its review and approval at its disposal facilities.
A letter from Clean Earth dated May 22, 2015 and revised June 17, 2015
indicated its approval to accept non-hazardous soils from the Site for disposal at
its Carteret, New Jersey facility.
Excavated material disposal occurred at the Site on May 22, 2015; and June 17,
18, and 22, 2015.
The material type, quantity and disposal location of material removed and disposed
off-Site is presented below:
Disposal Location/Address Type of Material Quantity
Clean Earth of Carteret 24 Middlesex Avenue
Carteret, NJ 07008
Non-Hazardous Soil 1,494.45 tons
A letter from Athenica to Clean Earth providing materials type, source and data, and
acceptance letters from disposal facility stating it is approved to accept above materials
are attached in Appendix I. Waste disposal manifests are included in Appendix J.
Trucking logs with disposal quantities and facilities is provided in Table 2. The waste
characterization sample laboratory analytical report is presented in Appendix K and a
summary of the sample results are presented in Table 3.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
29
4.5 BACKFILL IMPORT
Approximately 2 yards of ¾-inch clean bluestone was imported to the Site and
utilized as backfill for the SSDS suction pit and horizontal pipe trench. Appendix L
includes the bluestone importation documents from Olsen’s Nursery Inc. located at 386
Lake Avenue South in Nesconset, New York. The material originated from Tilcon New
York Inc.’s Clinton Point Quarry and was certified to meet ASTM #57 Stone and ASTM
#8 standards.
Approximately 153 yards of clean soil was excavated as part of development from the
deep (4- to 11-foot) interval of Grid 1 and re-used on-Site as backfill on the northern
open portion of the Site and behind foundation walls along 52nd Street and Queens
Boulevard. A map showing the approximate source location of reused soil and the
location of placement of reused soil is shown in Figure 6.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
30
5.0 ENGINEERING CONTROLS
5.1 COMPOSITE COVER SYSTEM
Track 2 Restricted Residential SCOs for soil were achieved and Engineering Controls are
not required to address residual soil. However, as part of construction, several protective
systems including a composite cover system and vapor barrier was installed across the
entire property. The composite cover system is comprised of a 4-inch concrete building
slab underlain by a vapor barrier and compacted native soil within the building footprint.
Open areas of the property in the northern portion of the lot are covered with an
approximately 6-inch thick concrete paved surface underlain by 2-feet of clean native
soil. Figure 7 depicts the as-built design for each cover type used on this Site.
Photographs of construction of the Composite Cover System are included in Appendix F.
The composite cover system was installed by Allstate 12 General Contracting
Corporation.
5.2 VAPOR BARRIER SYSTEM
As part of construction, a vapor barrier system was installed beneath the entire
building footprint. The vapor barrier was installed vertically on all exterior sub-grade
foundational walls, beneath structural footings, and beneath the entire building slab and
elevator pits. The vapor barrier system consists of VaporBlock Plus 20-mil vapor barrier
manufactured by Raven Industries. The vapor barrier is composed of seven-layers of co-
extruded polyethylene and ethylene vinyl-alcohol copolymers (EVOH) resins. The vapor
barrier was overlapped 6-inches and then sealed utilizing VaporSeal 4” Seaming Tape as
per the manufacturer specifications. All penetrations were sealed with VaporSeal 4”
Seaming Tape. The professional engineer for the Vapor Barrier System was Ariel
Czemerinski, P.E. of AMC Engineering. The contractor for the Vapor Barrier System
construction was Allstate 12 General Contracting Corporation.
Figure 8 shows the as-built design for the Vapor Barrier System used on this Site.
Photographs of installation of the Vapor Barrier System are included in Appendix F. A
copy of the vapor barrier specifications and documentation is included in Appendix L.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
31
5.3 ENGINEERING CONTROL
5.3.1 Active Sub-Slab Depressurization System
One Engineering Control (EC) was employed in the remedial action to address
residual soil vapor remaining at the Site. The ECs employed at the Site is:
(1) An Active Sub-Slab Depressurization System (SSDS)
Exposure to soil vapor is prevented by an active Sub-Slab Depressurization System
that has been built on the Site. The SSDS is located in the southeastern portion of the
cellar where elevated concentrations of PCE were encountered during the original RI.
The SSDS consists of one depressurization pit installed beneath the slab and surrounded
by a depressurization area approximately 170-square feet in size that has been backfilled
with ¾-inch clean bluestone to a depth of approximately 6-inches below the slab. The
depressurization pit is approximately 5.5-feet by 3-feet in area and 1.5-feet in depth and
consists of an open void beneath the slab that is framed with concrete blocks and covered
with a diamond steel plate. A 4-inch diameter schedule 40 PVC perforated piping was
installed in the pit and connected to a 4-inch diameter schedule 40 PVC riser pipe that
penetrates the building slab and extends vertically to the roof of the elevator bulkhead. A
trench filled with 4-inches of crushed bluestone was placed around the horizontal
perforated pipe. The vertical standpipe is connected to a hardwired RadonAway RP265
vacuum blower installed inline at the roof level. A sample port, vacuum pressure alarm
system, and Dwyer Series 2005 magnehelic vacuum gauge were installed on the riser
pipe in an access panel in the building’s basement to confirm system operation and the
riser pipe is labeled “SSDS Vent: DO NOT TAP”. The exhaust discharge point is located
a minimum 10-feet away from any operable window or air intake for any building. The
design engineer for the active SSDS system was Ariel Czemerinksi, P.E. of AMC
Engineering. The SSDS piping system was installed by Neda Development Incorporated
and the fan and electric elements were installed by United Electric. The SSDS system
installation was observed on behalf of the P.E. by Athenica and confirmed to be built
according to design and equipment manufacturer specifications. Figure 9 shows the
location of the SSDS system and Figure 10 shows as-built design details of the system as
constructed. Material/equipment specifications, RadonAway alarm instructions, and
RadonAway blower manual are included in Appendix M.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
32
System start-up and testing was performed on March 23, 2017 by Ariel Czemerinksi,
P.E. of AMC Engineering and Spiro Dongaris, P.E. of Athenica Environmental Services.
The SSDS was operating in accordance with design requirements. The following
summarizes the observations made during the SSDS start-up testing event:
Standpipe vacuum pressure was measured by a manometer to calibrate
magnehelic gauge; vacuum on the exhaust standpipe was measured at -2.6 inches
of water (WC)
The alarm system was tested and found to be operating correctly
A sub-slab vacuum pressure test point was drilled through the slab and installed
in the cellar slab in the area covered by bluestone; vacuum pressure as measured
by a manometer read -2.57” WC. The temporary sub-slab boring was patched
following testing.
SSDS start-up documentation is included in Appendix N. Figure 9 shows the location
of the SSDS system with sub-slab vacuum pressure test point location. SSDS operation
training and monitoring details are included in the SMP in Section 7.0.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
33
6.0 INSTITUTIONAL CONTROLS
A series of Institutional Controls are required under this Remedial Action to
implement, maintain, inspect and certify the Engineering Controls and prevent exposure
to residual material. Adherence to these Institutional Controls is required under this
remedial action and will be implemented under the Site Management Plan included in
this RAR.
Institutional Controls for this property are:
(1) The property will continue to be registered with an E-Designation by the NYC
Department of Buildings. Property owner and property owner’s successors and
assigns are required to comply with the approved SMP;
(2) Compliance with an OER-approved Site Management Plan including procedures
for appropriate operation, maintenance, inspection, and certification of
performance of EC’s and IC’s. The property owner and property owner’s
successors and assigns will inspect EC’s and IC’s and submit to OER a written
certification that evaluates their performance in a manner and at a frequency to be
determined by OER;
(3) Engineering Controls will not be discontinued without prior OER approval; and
(4) OER has the right to enter the Site upon notice for the purpose of evaluating the
performance of EC’s and IC’s.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
34
7.0 SITE MANAGEMENT PLAN
Site Management is the last phase of the remedial process and begins after the
approval of the Remedial Action Report (RAR) and issuance of the Notice of Completion
(NOC) by the OER. It is the responsibility of the property owner to ensure that all Site
Management responsibilities are performed. The penalty for failure to implement the
SMP includes revocation of the Notice of Completion and all associated certifications
and liability protections. If the building is sold, the new owners will be notified of the
SMP requirements.
Engineering Controls and Institutional Controls have been incorporated into this
Remedial Action to ensure that the site remains protective of public health and the
environment. Generally, EC’s provide physical protective measures and IC’s provide
restrictions on Site usage and establish remedial operation, maintenance, inspection and
certification measures. This Site Management Plan has been established to govern long-
term performance of EC’s and IC’s for this property.
The SMP provides a detailed description of procedures required to manage residual
material at the Site following the completion of remedial construction in accordance with
the NYC Voluntary Cleanup Agreement with OER. This includes: (1) operation and
maintenance of Engineering Controls; (2) inspection of EC’s and IC’s; and (3)
certification of performance of EC’s and IC’s.
7.1 ENGINEERING CONTROLS
Engineering Controls were employed in the remedial action to address residual soil
vapor remaining at the site. The Site has one Engineering Control System. Engineering
Control for this property is:
(1) Active Sub-Slab Depressurization System
Operation and Maintenance of Active Sub-Slab Depressurization System
Chapter 5 describes the Active Sub-Slab Depressurization System utilized in this
Remedial Action and provides as-built design details and the system location. The SSDS
is a permanent Engineering Control for the Site. The system will be inspected and its
performance certified at specified intervals defined in this SMP.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
35
The SSDS will be operated and maintained as prescribed below:
The manometer and alarm installed for the system manifold are located immediately
on the SSDS riser pipe in a control box in the northwestern corner of the retail storage
room in the cellar. The system is designed to establish a vacuum of 1.0 inches of water or
higher. If the blower is found to be non-operational by the inspector during an inspection,
or if the blower is operating, but no vacuum reading is observed on the vacuum gauge,
the blower must be replaced or repaired. The SSDS components to be evaluated and
inspected include:
RadonAway RP265 Radon Fan;
RadonAway Checkpoint Mitigation System Alarm;
Dwyer Magnehelic Manometer Gauge Series 2005; and
Control box for the alarms and gauges.
A complete list of components to be inspected is provided in the Monthly SSDS
Inspection Checklist provided in Appendix O.
7.2 INSTITUTIONAL CONTROLS
A series of Institutional Controls are required under this Remedial Action to assure
permanent protection of public health by elimination of exposure to residual materials.
These IC’s define the program to operate, maintain, inspect and certify the performance
of Engineering Controls and Institutional Controls on this property. These Institutional
Controls will be implemented in accordance with the Site Management Plan included in
this RAR.
Institutional Controls for this property are:
(1) The property will continue to be registered with an E-Designation by the NYC
Department of Buildings. Property owner and property owner’s successors and
assigns are required to comply with the approved SMP;
(2) Compliance with an OER-approved Site Management Plan including procedures
for appropriate operation, maintenance, inspection, and certification of
performance of EC’s and IC’s. The property owner and property owner’s
successors and assigns will inspect EC’s and IC’s and submit to OER a written
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
36
certification that evaluates their performance in a manner and at a frequency to be
determined by OER;
(3) Engineering Controls will not be discontinued without prior OER approval; and
(4) OER has the right to enter the Site upon notice for the purpose of evaluating the
performance of EC’s and IC’s.
7.3 INSPECTIONS
Engineering Controls and Institutional Controls will be inspected by a qualified
environmental professional on an annual basis beginning with the initial startup
inspection of the active SSDS performed on March 23, 2017. In addition to these
inspections, the building superintendent will inspect the active SSDS on a monthly basis.
The inspections will evaluate the following:
If Engineering Controls or Institutional Controls employed at the Site continue to
perform as designed and continue to be protective of human health and the
environment;
If anything has occurred that impairs the ability of the Engineering Controls or
Institutional Controls to protect public health and the environment;
If changes are needed to the remedial systems or controls;
If compliance with this SMP has been maintained;
If site records are complete and up to date; and
General Site conditions at the time of inspection.
In an addition, if an emergency occurs, such as a natural disaster, or if an unforeseen
failure of any of the Engineering Controls occurs, an inspection of the Site will be
performed within 14 days to evaluate the Engineering Controls and a letter report of
findings will be submitted to OER.
Inspection of Active Sub-Slab Depressurization System
Inspections of the active SSDS are to be performed on a monthly basis by the
building superintendent and recorded on the SSDS Inspection Checklist provided in
Appendix O. All completed monthly SSDS Inspection Checklists are to be kept on-Site
for review by the qualified environmental professional during the annual inspection. The
monthly SSDS inspection should include confirmation that the audible/visual alarm has
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
37
not been triggered and that the vacuum gauge depicts a minimum vacuum reading of
approximately 1.0 inches of water.
In addition, the RadonAway RP265 Radon Fan located on the roof must be inspected
to determine if the fan is operating by checking for air flow at the exhaust. If the fan is
found to be non-operational by the building superintendent during a monthly inspection,
or if the fan is operating, but no vacuum reading is observed on the vacuum gauge, the
fan must be replaced or repaired. The Owner’s representative(s) shall immediately
contact the appropriate parties from the contact list provided on the monthly SSDS
Inspection Checklist.
A complete list of components to be checked is provided in the SSDS Inspection
Checklist presented in Appendix O. The components of the Active SSDS will also be
inspected annually by a qualified environmental professional to assure that the Active
SSDS is functioning properly.
7.4 INSPECTION AND CERTIFICATION LETTER REPORT
Results of inspections performed during a reporting period and certification of
performance of all Engineering Controls and Institutional Controls will be included in an
Inspection and Certification Letter Report. Inspections will be performed in 2018, 2019,
and every year thereafter. Inspection and Certification Letter Reports will be submitted
by July 31, 2019 (for the reporting period calendar year 2019), July 31, 2020 (for the
reporting period calendar year 2019) and every year thereafter (for the reporting period
consisting of the prior calendar year). Inspection and Certification Letter Reports will be
submitted to OER in digital format. The letter report will include, at a minimum:
Date of inspections;
Personnel conducting inspections;
Description of the inspection activities performed;
Any observations, conclusions, or recommendations;
Copy of all inspection forms;
A determination as to whether groundwater plume conditions, if any, have
changed since the last reporting event; and
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
38
Certification of the performance of Engineering Controls and Institutional
Controls, as discussed below.
The certification of the performance of EC’s and IC’s will establish:
If Engineering Controls or Institutional Controls employed at the Site continue to
be in place and perform as designed and continue to be protective of human health
and the environment;
If anything has occurred that impairs the ability of Engineering Controls or
Institutional Controls to protect public health and the environment;
If changes are needed to the remedial systems or controls;
If compliance with this Site Management Plan has been maintained;
If site records are complete and up to date;
If the Site continues to be registered as an E-Designated property by the NYC
Department of Buildings;
OER may enter the Site upon notice for the purpose of evaluating the performance of
EC’s and IC’s.
In addition to the Inspection and Certification Letter Reports, during the first year of
function, soil vapor beneath the Site will be sampled to evaluate the function of the active
SSDS. The soil vapor sampling will be conducted to evaluate whether a decrease in
SSDS function to a passive system is applicable. The results of the sampling will be
provided to the OER for their review and no alterations will be made to the system
without their written consent. The sampling will be performed no earlier than 6-months
after active SSDS function.
7.5 NOTIFICATIONS
Notifications will be submitted by the property owner to OER as described below:
60-day advance notice of any proposed changes in Site use, such as an upgrade
from existing use to unrestricted residential use that was not contemplated is the
Remedial Action.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
39
Notice within 30 days of any emergency, such as a fire, flood, or earthquake that
has the potential to reduce the effectiveness of Engineering Controls in place at
the Site.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
40
8.0 SUSTAINABILITY REPORT
This Remedial Action Work Plan provides for sustainable remediation and
redevelopment (if applicable) through a variety of means that are defined in this
Sustainability Report.
Reuse of Clean, Recyclable Materials. Reuse of clean, recyclable materials reduces
consumption of non-renewable virgin resources and can provide energy savings and
greenhouse gas reduction since these materials can be locally-derived.
Approximately 153 yards of clean soil generated as part of construction was reused at
the Site to backfill locations where historic fill was removed and behind foundation walls.
Conservation of Non-Renewable Resources. Reduced consumption of non-
renewable resources such as soil and top-soil lowers the overall environmental impact of
the project on the region by conserving these resources.
Conservation of non-renewable resources was achieved by reusing on-Site soil as
backfill. An estimate of the tonnage of non-renewable resources, the use of which will be
avoided under this plan, is 153 yards.
Conversion to Clean Fuels. Use of clean fuel improves NYC’s air quality by
reducing harmful emissions.
Natural gas is utilized as the principal fuel in the new building.
Recontamination Control. Recontamination after cleanup and redevelopment is
completed undermines the value of work performed, may result in a property that is less
protective of public health or the environment, and may necessitate additional cleanup
work later that could impede future redevelopment. Recontamination can arise from
future releases that occur within the property or by influx of existing contamination from
off-Site.
The composite cover system, consisting of a minimum 4-inches of concrete underlain
by a vapor barrier or 2-feet of clean soil, will prevent underlying soil contamination from
future leaks or spills, and migration of vapors into the structure in the future. The
composite cover system covers the entire property boundary; therefore, the area of the
Site that utilizes recontamination controls under this plan is 5,387 square feet.
Remedial Action Report 51-27 Queens Boulevard, Queens, NY July 2017 NYC VCP No.15CVCP027Q
41
Paperless Voluntary Cleanup Program. Q52, LLC participated in OER’s Paperless
Brownfield Voluntary Program. Under this program, submission of electronic documents
replaced submission of hard copies for the review of project documents, communications
and milestone reports. A best estimate of the mass (pounds) of paper saved under this
plan is 25 pounds.
Low-Energy Project Management Program. Q52, LLC participated in OER’s
low-energy project management program. Under this program, whenever possible,
meetings were held using remote communication technologies, such as
videoconferencing and teleconferencing to reduce energy consumption and traffic
congestion associated with personal transportation. A gross estimate of the number of
miles of personal transportation that was conserved in this process is 35 miles.
Trees and Plantings. Trees and other plantings provide habitat and add to NYC’s
environmental quality in a wide variety of ways. Native plant species and native habitat
provide optimal support to local fauna, promote local biodiversity, and require less
maintenance. The number of trees planted as part of this redevelopment is 3.
SITELOCATION
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:NOT TO SCALE 145-09 GREENPOINT AVENUE
LONG ISLAND CITY, NY 11104TEL: (718) 784 - 7490FAX: (718) 784 - 4085
Title: REMEDIAL ACTION REPORT.SITE LOCATION MAP
LEGEND:
SITE LOCATION
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND:
SITE
- SITE BOUNDARY
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:NOT TO SCALE 2Title: REMEDIAL ACTION REPORT.
SITE BOUNDARY MAP
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
SITE
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND: Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:NOT TO SCALE 3ATitle: REMEDIAL ACTION REPORT.
DEVELOPMENT PLAN
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
FRONT ELEVATION
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND: Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:NOT TO SCALE 3BTitle: REMEDIAL ACTION REPORT.
DEVELOPMENT PLAN
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
CELLAR PLAN FIRST FLOOR PLAN
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:NOT TO SCALE 4Title: REMEDIAL ACTION REPORT.
MAP OF END-POINT SAMPLING LOCATIONS
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
- PROJECT SITE BOUNDARY
- END POINT SAMPLE LOCATION
- 2014 REMEDIAL INVESTIGATION SAMPLE LOCATION
-X
Block 1320Lot 47
QU
EEN
S B
OU
LEV
AR
D
52ND STREET
EP-4 (11' BGS)
EP-3 (11' BGS)
EP-2 (11' BGS)
EP-1 (2' BGS)
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND:
SB-1 (2' BGS)
-X
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND: Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:NOT TO SCALE 5Title: REMEDIAL ACTION REPORT.
MAP OF LOCATION AND APPROXIMATEDEPTH OF EXCAVATIONS
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
- PROPERTY BOUNDARY
- EXCAVATION DEPTH: 2 FEET BGS
- EXCAVATION DEPTH: 11 FEET BGS
- EXCAVATION DEPTH: 19 FEET BGS
QU
EEN
S B
OU
LEV
AR
D
52ND STREET
Block 1320Lot 47
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:NOT TO SCALE 6Title: REMEDIAL ACTION REPORT.
MAP OF SOIL SOURCE AREA ANDBACKFILL PLACEMENT LOCATIONS
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
- PROPERTY BOUNDARY
- AREA OF BACKFILL
- APPROXIMATE SOURCE AREA FORBACKFILL/GRID 1, 4'-11'
QU
EEN
S B
OU
LEV
AR
D
52ND STREET
Block 1320Lot 47
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND:
0-11'
0-2'
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:
NOT TO SCALE
7Title: REMEDIAL ACTION REPORT.
MAP OF LOCATION OF COMPOSITECOVER SYSTEM AND DESIGN DETAIL
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
X X X X X X X X X X X X X X X X X
WELDED WIRE FABRIC (W.W.F.)
20-MIL VAPOR BARRIER
4" CONCRETE SLAB ON GRADE
4"
COMPACTED SUBGRADE
DETAIL OF COMPOSITE COVERFOR BUILDING SLAB
- PROPERTY BOUNDARY
- LOCATION OF COMPOSITE COVER SYSTEM
QUEENS BOULEVARD
52N
D
STR
EET
Block 1320Lot 47
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND:
6" CONCRETE SLAB ON GRADE
6"
CLEAN COMPACTED SOIL
DETAIL OF COMPOSITE COVERFOR OPEN AREAS
2'-0"
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:
NOT TO SCALE
8Title: REMEDIAL ACTION REPORT.
MAP OF LOCATION OF VAPOR BARRIERSYSTEM AND DESIGN DETAIL
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
- PROJECT SITE BOUNDARY
- VAPOR BARRIER SYSTEM LOCATION
CROSS SECTIONPLAN VIEW
QUEENS BOULEVARD
52N
D
STR
EET
20-MIL VAPOR BARRIER
COMPACTED SOIL
T/SLAB CELLAR
T/SLAB 1ST FLOORSIDE WALK
CONCRETE FDN WALL
Block 1320Lot 47
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND:
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:
NOT TO SCALE
9Title: REMEDIAL ACTION REPORT.
MAP OF LOCATION OF SSDS SYSTEM
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND:
- AREA FILLED WITH 34" BLUESTONE
- 4" DIA SCH.40 PVC PERFORATED PIPE
- 4" DIA SCH.40 PVC STAND PIPE
See Figure 10, Detail 2
Date:
Drawn by:
Checked by:
Drawing Scale:
Project No.:
VOLODYMYR PROTSYUKSite:
Figure:
NOT TO SCALE
10Title: REMEDIAL ACTION REPORT.
AS-BUILT DESIGN DETAIL FORSSDS SYSTEM
MARCH 23, 2017
A.J. INFANTE
14-133-0759
51-27 QUEENS BOULEVARDWOODSIDE, NY 11377
AAB
B
CB
3'-0"
5'-6"
SSDS DETAIL FOR SUCTION PIT (PLAN VIEW)NTS
CONCRETE BLOCK16" X 8" X 8"
Fig.102
SSDS DETAIL FOR SUCTION PIT (SECTION A)NTSFig.10
3
TYPICAL SSDS DETAIL FOR SUCTION PIT (SECTION B)NTSFig.10
4
12" MIN
4"
4" MIN
NEW CONCRETE FLOOR SLAB
VAPORBLOCK PLUS 20-MIL VAPOR BARRIER
4" DIA SCH.40 PVC PERFORATED PIPE
EXCAVATE TRENCH TO A DEPTH OF 12" MIN
RISER SECTIONNTSFig.10
1
45-09 GREENPOINT AVENUELONG ISLAND CITY, NY 11104
TEL: (718) 784 - 7490FAX: (718) 784 - 4085
LEGEND:
PRECAST STEEL DIAMOND PLATE
4" DIA SCH.40 PVC PERFORATED PIPE
RAIN CAP
RADONAWAY RP265 BLOWER
DWYER MAGNEHELIC GAUGE SERIES 2005AND RADONAWAY CHECKPOINT ALARM SYSTEMALARM TO BE FED WITH INDEPENDENT CIRCUITFROM ELECTRIC PANEL
TO SSDS SUCTION PIT
4" DIA SCH.40 PVC PERFORATED PIPE
4" DIA SCH.40 PVC RISER
ELEVATOR BULKHEAD
BULKHEAD ROOF
MAIN ROOF
CELLAR
1ST FLOOR
5'-6"
CB
CB
CB CB
CB
34" BLUESTONE, NO FINES
5'-6" x 3' PRECAST STEEL DIAMOND PLATE
CONCRETE SLAB16"x8"x8" CONCRETE BLOCK
34" BLUESTONE, NO FINES
TO SSDS RISER
Table 1
End Point Soil Sampling Results
Volatile Organic Compounds (VOCs) in Soil Samples
51‐27 Queens Boulevard, Queens, New York
Sample IDLaboratory IDSampling Depth (ft)Sampling DateSampling Matrix
Dilution Factor
Units of Measure mg/kg mg/kg1,1,1,2‐Tetrachloroethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,1,1‐Trichloroethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 1001,1,2,2‐Tetrachloroethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,1,2‐Trichloro‐1,2,2‐trifluoroethane (Freon 113) 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,1,2‐Trichloroethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,1‐Dichloroethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 26 261,1‐Dichloroethylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 1001,2,3‐Trichlorobenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,2,3‐Trichloropropane 0.0022 ND NT NT 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,2,4‐Trichlorobenzene 0.0022 ND NT NT 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,2,4‐Trimethylbenzene 0.0030 J 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 52 521,2‐Dibromo‐3‐chloropropane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,2‐Dibromoethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,2‐Dichlorobenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 1001,2‐Dichloroethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 3.1 3.11,2‐Dichloropropane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC1,3,5‐Trimethylbenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 52 521,3‐Dichlorobenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 49 491,4‐Dichlorobenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 13 131,4‐Dioxane 0.045 ND 0.048 ND 0.046 ND 0.041 ND 0.043 ND 13 132‐Butanone 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 1002‐Hexanone 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NC4‐Methyl‐2‐pentanone 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCAcetone 0.0045 ND 0.033 0.0089 J 0.0041 ND 0.0043 ND 100 100Acrolein 0.0045 ND 0.0024 ND 0.0046 ND 0.0041 ND 0.0043 ND NC NCAcrylonitrile 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCBenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 4.8 4.8Bromochloromethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCBromodichloromethane 0.0022 ND NT NT 0.0023 ND 0.0021 ND 0.0021 ND NC NCBromoform 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCBromomethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCCarbon disulfide 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCCarbon tetrachloride 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 2.4 2.4Chlorobenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100Chloroethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCChloroform 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 49 49Chloromethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCcis‐1,2‐Dichloroethylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100cis‐1,3‐Dichloropropylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCCyclohexane 0.0022 ND NT NT 0.0023 ND 0.0021 ND 0.0021 ND NC NCDibromochloromethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCDibromomethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCDichlorodifluoromethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCEthyl Benzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 41 41Hexachlorobutadiene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCIsopropylbenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCMethyl acetate 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCMethyl tert‐butyl ether (MTBE) 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100Methylcyclohexane 0.0022 ND NT NT 0.0023 ND 0.0021 ND 0.0021 ND NC NCMethylene chloride 0.0045 ND 0.0024 ND 0.0046 ND 0.0041 ND 0.0043 ND 100 100n‐Butylbenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100n‐Propylbenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100o‐Xylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCp‐ & m‐ Xylenes 0.0045 ND 0.0048 ND 0.0046 ND 0.0041 ND 0.0043 ND NC NCp‐Isopropyltoluene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCsec‐Butylbenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100Styrene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCtert‐Butyl alcohol (TBA) 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCtert‐Butylbenzene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100Tetrachloroethylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 19 19Toluene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100trans‐1,2‐Dichloroethylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 100 100trans‐1,3‐Dichloropropylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCTrichloroethylene 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 21 21Trichlorofluoromethane 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND NC NCVinyl Chloride 0.0022 ND 0.0024 ND 0.0023 ND 0.0021 ND 0.0021 ND 0.9 0.9Xylenes, Total 0.0067 ND 0.0072 ND 0.0068 ND 0.0062 ND 0.0064 ND 100 100
NOTES:
mg/kg = miligrams per kilogramJ = analyte detected at or above the MDL (method detection limit) but below the RL (Reporting Limit) ‐ data is estimated
D = result is from an analysis that required a dilution
ND = analyte not detected at or above the level indicated
NC = this indicates that no regulatory limit has been established for this analyte
NT =analyte not tested by laboratory
Track 4 Site‐Specific
SCOs
Bolded and Shaded values exceed NYSDEC Part 375 Track 2 Restricted Residential Use Soil Cleanup ObjecBolded and Shaded values exceed Track 4 Site‐Specific Soil Cleanup Objectives (SCOs)
EP‐115F0710‐01
6/18/2015Soil
2
mg/Kg
SB‐114F0888‐02
26/20/2014
Soil
5
mg/Kg
NYSDEC Part 375 Track
2 Restricted Residential
Use SCOs
1
mg/kg
1
mg/Kg
1
mgKg
EP‐415F0710‐04
6/18/2015Soil
1
111111
EP‐215F0710‐02
6/18/2015Soil
EP‐315F0710‐03
6/18/2015Soil
Table 1 (cont'd)
End Point Soil Sampling Results
Semi‐Volatile Organic Compounds (SVOCs) in Soil Samples
51‐27 Queens Boulevard, Queens, New York
Sample ID
Laboratory ID
Sampling Depth (ft)
Sampling Date
Sampling Matrix
Dilution Factor
Units of Measure mg/kg mg/kg
1,1'‐Biphenyl 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
1,2,4,5‐Tetrachlorobenzene 0.089 ND NT NT 0.089 ND 0.088 ND 0.090 ND NC NC
1,2,4‐Trichlorobenzene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
1,2‐Dichlorobenzene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 100 100
1,2‐Diphenylhydrazine (as Azobenzene) 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
1,3‐Dichlorobenzene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 49 49
1,4‐Dichlorobenzene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 13 13
2,3,4,6‐Tetrachlorophenol 0.089 ND NT NT 0.089 ND 0.088 ND 0.090 ND NC NC
2,4,5‐Trichlorophenol 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2,4,6‐Trichlorophenol 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2,4‐Dichlorophenol 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2,4‐Dimethylphenol 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2,4‐Dinitrophenol 0.089 ND 0.18 ND 0.089 ND 0.088 ND 0.090 ND NC NC
2,4‐Dinitrotoluene 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2,6‐Dinitrotoluene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2‐Chloronaphthalene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2‐Chlorophenol 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2‐Methylnaphthalene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
2‐Methylphenol 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND 100 100
2‐Nitroaniline 0.089 ND 0.046 ND 0.089 ND 0.088 ND 0.090 ND NC NC
2‐Nitrophenol 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
3‐ & 4‐Methylphenols 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND NC NC
3,3'‐Dichlorobenzidine 0.045 ND 0.18 ND 0.045 ND 0.044 ND 0.045 ND NC NC
3‐Nitroaniline 0.089 ND 0.092 ND 0.089 ND 0.088 ND 0.090 ND NC NC
4,6‐Dinitro‐2‐methylphenol 0.089 ND 0.092 ND 0.089 ND 0.088 ND 0.090 ND NC NC
4‐Bromophenyl phenyl ether 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
4‐Chloro‐3‐methylphenol 0.045 ND NT NT 0.045 ND 0.044 ND 0.045 ND NC NC
4‐Chloroaniline 0.045 ND NT NT 0.045 ND 0.044 ND 0.045 ND NC NC
4‐Chlorophenyl phenyl ether 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
4‐Nitroaniline 0.089 ND 0.092 ND 0.089 ND 0.088 ND 0.090 ND NC NC
4‐Nitrophenol 0.089 ND 0.092 ND 0.089 ND 0.088 ND 0.090 ND NC NC
Acenaphthene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 100 100
Acenaphthylene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 100 100
Acetophenone 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Aniline 0.18 ND NT NT 0.18 ND 0.18 ND 0.18 ND NC NC
Anthracene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 100 100
Atrazine 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Benzaldehyde 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Benzidine 0.18 ND 0.18 ND 0.18 ND 0.18 ND 0.18 ND NC NC
Benzo(a)anthracene 0.045 ND 0.060 J 0.045 ND 0.044 ND 0.045 ND 1 1
Benzo(a)pyrene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 1 1
Benzo(b)fluoranthene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 1 1
Benzo(g,h,i)perylene 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND 100 100
Benzo(k)fluoranthene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 3.9 3.9
Benzoic acid 0.045 ND 0.12 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Benzyl alcohol 0.045 ND NT NT 0.045 ND 0.044 ND 0.045 ND NC NC
Benzyl butyl phthalate 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Bis(2‐chloroethoxy)methane 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Bis(2‐chloroethyl)ether 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Bis(2‐chloroisopropyl)ether 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Bis(2‐ethylhexyl)phthalate 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Caprolactam 0.089 ND 0.046 ND 0.089 ND 0.088 ND 0.090 ND NC NC
Carbazole 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Chrysene 0.045 ND 0.070 J 0.045 ND 0.044 ND 0.045 ND 3.9 3.9
Dibenzo(a,h)anthracene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 0.33 0.33
Dibenzofuran 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 59 59
Diethyl phthalate 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Dimethyl phthalate 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Di‐n‐butyl phthalate 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Di‐n‐octyl phthalate 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Fluoranthene 0.045 ND 0.093 J 0.055 ND 0.044 ND 0.045 ND 100 100
Fluorene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 100 100
Hexachlorobenzene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 1.2 1.2
Hexachlorobutadiene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Hexachlorocyclopentadiene 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Hexachloroethane 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Indeno(1,2,3‐cd)pyrene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 0.5 0.5
Isophorone 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Naphthalene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 100 100
Nitrobenzene 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
N‐Nitrosodimethylamine 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND NC NC
N‐nitroso‐di‐n‐propylamine 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
N‐Nitrosodiphenylamine 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND NC NC
Pentachlorophenol 0.045 ND 0.092 ND 0.045 ND 0.044 ND 0.045 ND 6.7 6.7
Phenanthrene 0.045 ND 0.052 J 0.045 ND 0.044 ND 0.045 ND 100 100
Phenol 0.045 ND 0.046 ND 0.045 ND 0.044 ND 0.045 ND 100 100
Pyrene 0.045 ND 0.11 J 0.045 ND 0.044 ND 0.045 ND 100 100
Total SVOCs ND 0.38 ND ND ND N/A 250
NOTES:
*Track 4 Site Specific SCO established for Total SVOCs in the Remedial Action Work Plan for the Site
Bolded and Shaded values exceed NYSDEC Part 375 Track 2 Restricted Residential Use Soil Cleanup Objectives (SCOs)
Bolded and Shaded values exceed Track 4 Site‐Specific Soil Cleanup Objectives (SCOs)
mg/kg = miligrams per kilogram
J = analyte detected at or above the MDL (method detection limit) but below the RL (Reporting Limit) ‐ data is estimated
D = result is from an analysis that required a dilution
ND = analyte not detected at or above the level indicated
NC = this indicates that no regulatory limit has been established for this analyte
NT =analyte not tested by laboratory
NYSDEC Part 375
Track 2 Restricted
Residential Use
SCOs
Track 4 Site‐Specific SCOs
mg/Kg mg/kg
2 11 11 11
6/18/2015 6/18/2015 6/18/2015 6/18/2015
Soil Soil
2 2
EP‐1 EP‐2 EP‐3
Soil Soil
2
6/20/2014
Soil
5
mg/Kg
2 2
mg/Kg mgKg
EP‐4
15F0710‐01 15F0710‐02 15F0710‐03 15F0710‐04
SB‐1
14F0888‐02
Table 1 (cont'd)
End Point Soil Sampling Results
Pesticides and Polychlorinated Biphenyls (PCBs) in Soil Samples
51‐27 Queens Boulevard, Queens, New York
Sample ID
Laboratory ID
Sampling Depth (ft)
Sampling Date
Sampling Matrix
Dilution Factor
Units of Measure mg/kg mg/kg
4,4'‐DDD 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 13 13
4,4'‐DDE 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 8.9 8.9
4,4'‐DDT 0.012 D 0.0018 ND 0.0057 D 0.011 D 0.0027 ND 7.9 7.9
Aldrin 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 0.097 0.097
alpha‐BHC 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 0.48 0.48
alpha‐Chlordane 0.0026 ND NT NT 0.0026 ND 0.0026 ND 0.0027 ND 4.2 4.2
beta‐BHC 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 0.36 0.36
Chlordane, total 0.11 ND 0.0072 ND 0.11 ND 0.11 ND 0.11 ND NC NC
delta‐BHC 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 100 100
Dieldrin 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 0.2 0.2
Endosulfan I 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 24 24
Endosulfan II 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 24 24
Endosulfan sulfate 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 24 24
Endrin 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 11 11
Endrin aldehyde 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND NC NC
Endrin ketone 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND NC NC
gamma‐BHC (Lindane) 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 1.3 1.3
gamma‐Chlordane 0.0026 ND NT NT 0.0026 ND 0.0026 ND 0.0027 ND NC NC
Heptachlor 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND 2.1 2.1
Heptachlor epoxide 0.0026 ND 0.0018 ND 0.0026 ND 0.0026 ND 0.0027 ND NC NC
Methoxychlor 0.013 ND 0.0090 ND 0.013 ND 0.013 ND 0.013 ND NC NC
Toxaphene 0.13 ND 0.091 ND 0.13 ND 0.13 ND 0.14 ND NC NC
Dilution Factor
Aroclor 1016 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND NC NC
Aroclor 1221 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND NC NC
Aroclor 1232 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND NC NC
Aroclor 1242 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND NC NC
Aroclor 1248 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND NC NC
Aroclor 1254 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND NC NC
Aroclor 1260 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND NC NC
Total PCBs 0.027 ND 0.019 ND 0.027 ND 0.026 ND 0.027 ND 1 1
NOTES:
mg/kg = miligrams per kilogram
J = analyte detected at or above the MDL (method detection limit) but below the RL (Reporting Limit) ‐ data is estimated
D = result is from an analysis that required a dilution
ND = analyte not detected at or above the level indicated
NC = this indicates that no regulatory limit has been established for this analyte
NT =analyte not tested by laboratory
Bolded and Shaded values exceed Track 4 Site‐Specific Soil Cleanup Objectives (S
NYSDEC Part 375
Track 2 Restricted
Residential Use SCOs
Track 4 Site‐Specific
SCOs
Pesticides
Polychlorinated Biphenyls (PCBs)
15F0710‐02 15F0710‐03 15F0710‐04
2 11 11 11
6/18/2015
Soil Soil Soil Soil
1
EP‐1
6/18/2015
SB‐1
14F0888‐02
2
6/20/2014
Soil
5
mg/Kg
1
6/18/2015 6/18/2015
EP‐2 EP‐3 EP‐4
15F0710‐01
Bolded and Shaded values exceed NYSDEC Part 375 Track 2 Restricted Residenti
5 5 5 5
mg/Kg mgKg mg/Kg mg/kg
111
Table 1 (cont'd)
End Point Soil Sampling Results
TAL Metals in Soil Samples
51‐27 Queens Boulevard, Queens, New York
Sample ID
Laboratory ID
Sampling Depth (ft)
Sampling Date
Sampling Matrix
Dilution Factor
Units of Measure mg/kg mg/kg
Aluminum 4,730 5,400 4,140 5,760 4,850 NC NCAntimony 0.53 ND 0.55 ND 0.53 ND 0.53 ND 0.54 ND NC NCArsenic 1.07 ND 2.35 1.07 ND 1.06 ND 1.08 ND 16 16Barium 33.80 55.10 31.50 46.10 47.30 400 400Beryllium 0.11 ND 0.11 ND 0.11 ND 0.11 ND 0.11 ND 72 72Cadmium 0.32 ND 0.33 ND 0.32 ND 0.32 ND 0.32 ND 4.3 4.3Calcium 1,020 874 1,190 1,870 1,390 NC NCChromium 11.20 10.90 12.30 17.10 14.60 NC NCCobalt 4.35 4.25 4.40 6.01 6.16 NC NCCopper 12.20 30.20 10.50 17.70 19.70 270 270
Iron 9,350 11,400 9,940 12,000 13,000 NC NC
Lead 11 40.20 4.52 15.10 6.85 400 600Magnesium 1,310 2,130 1,550 2,090 1,700 NC NCManganese 218 260 239 265 359 2000 2000Nickel 8.28 9.82 7.98 10.20 10.90 310 310Potassium 662 686 801 1,120 958 NC NCSelenium 2.31 2.31 2.33 3.83 3.08 180 180Silver 0.53 ND 0.55 0.53 ND 0.53 ND 0.54 ND 180 180Sodium 157 104 191 195 175 NC NCThallium 1.07 ND 1.09 ND 1.07 ND 1.06 ND 1.08 ND NC NCVanadium 16.60 15.30 17.60 23.60 21.30 NC NCZinc 21.20 358 ND 19.80 34.60 26 10000 10000Mercury 0.032 ND 0.21 0.032 ND 0.032 ND 0.032 ND 0.81 0.81Chromium, Hexavalent 0.53 ND 0.55 ND 0.53 ND 0.53 ND 0.54 ND 110 110
Chromium, Trivalent 11.20 9.98 12.30 17.10 14.60 180 180
NOTES:
*Track 4 Site Specific SCO established for Lead in the Remedial Action Work Plan for the Site
mg/kg = miligrams per kilogram
J = analyte detected at or above the MDL (method detection limit) but below the RL (Reporting Limit) ‐ data is estimated
D = result is from an analysis that required a dilution
ND = analyte not detected at or above the level indicated
NC = this indicates that no regulatory limit has been established for this analyte
NT =analyte not tested by laboratory
Track 4 Site‐Specific
SCOs
Bolded and Shaded values exceed NYSDEC Part 375 Track 2 Restricted Residential
Bolded and Shaded values exceed Track 4 Site‐Specific Soil Cleanup Objectives (SC
EP‐1 EP‐2 EP‐3 EP‐4
15F0710‐01 15F0710‐02 15F0710‐03 15F0710‐04
Soil Soil Soil Soil
1 1 1
mg/Kg mgKg mg/Kg mg/kg
11
2 11 11 11
6/18/2015 6/18/2015 6/18/2015 6/18/2015
NYSDEC Part 375
Track 2 Restricted
Residential Use SCOs
mg/Kg
SB‐1
14F0888‐02
2
6/20/2014
Soil
Table 2: Disposal Quantities and Disposal Facilities Soil Disposal Trucking Log
51-27 Queens Boulevard
Date Manifest # Trucking CompanyLicense
Plate QuantityTons/Yard Receiving Facility Material Type On-Site Grid
5/22/2015 1135074 RLS Trucking AP207R 34.36 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135075 Shirley Express AR770E 34.21 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135076 Shirley Express AP494Y 32.78 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135078 Shirley Express AS125L 32.71 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135077 RLS Trucking AP993P 34.24 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135079 Shirley Express AS352F 34.5 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135081 Shirley Express AR770E 31.66 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135082 Shirley Express AP494Y 31.64 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135080 RLS Trucking AP207R 34.17 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135083 Shirley Express AS125L 31.32 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135085 Shirley Express AS352F 33.96 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
5/22/2015 1135084 RLS Trucking AP993P 29.73 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 3
6/17/2015 939281 JDC Trucking AS709D 34.92 tons Clean Earth of Carteret Non-Hazardous Soil 3 & 4
6/17/2015 939282 JDC Trucking AS813M 32.5 tons Clean Earth of Carteret Non-Hazardous Soil 3 & 4
6/18/2015 1104994 Shirley Express AP161M 35.09 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1104995 Shirley Express #12 34.42 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105013 RLS Trucking AP207R 35.87 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105012 Shirley Express AP752U 35 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105011 Shirley Express AS836B 32.56 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
Table 2: Disposal Quantities and Disposal Facilities Soil Disposal Trucking Log
51-27 Queens Boulevard
6/18/2015 1104996 Shirley Express AS261B 35.3 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105010 Shirley Express AR770E 31.88 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1104997 JLD AS109D 34.99 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105009 Shirley Express AP160M 35.18 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1104998 RLS Trucking AS252C 35.53 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105000 Shirley Express AS836B 33.17 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105008 Shirley Express #12 29.84 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1104999 Shirley Express AP161M 33.87 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105007 Shirley Express AS261B 29.22 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105006 Shirley Express AR770E 28.86 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/18/2015 1105005 Shirley Express AP160M 34.06 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, 3, & 4
6/22/2015 1105001 Shirley Express AP752U 29.79 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105002 RLS Trucking AS193R 35.6 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105003 Shirley Express AR922F 33.89 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105004 Shirley Express AP645E 33.27 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105106 Shirley Express AS122L 33.43 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105101 RLS Trucking AS252C 31.45 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105105 RLS Trucking AS253C 35.97 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105104 RLS Trucking AS193R 32.24 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105103 Shirley Express AP752U 31.98 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
Table 2: Disposal Quantities and Disposal Facilities Soil Disposal Trucking Log
51-27 Queens Boulevard
6/22/2015 1105102 Shirley Express AR922F 33.53 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105087 Shirley Express AS122L 32.26 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105088 Shirley Express AP645E 32.1 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105089 RLS Trucking AS253C 36.06 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105100 RJT AP297P 32.02 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
6/22/2015 1105098 Hales Trucking #2 33.32 tons Clean Earth of Carteret Non-Hazardous Soil 1, 2, & 4
1494.45
Table 3
Waste Characterization Sampling Summary
51‐27 Queens Boulevard, Queens, New York
Sample IDSample DepthLaboratory IDSampling DateSample Matrix
Compound Result Q Result Q Result Q Result Q Result Q Result Q Result Q Result Q Result Q
Total Petroleum Hydrocarbons‐GRO (C5‐C10) mg/kg mg/kg mg/kg mg/kg mg/kgDilution Factor 100 100 100 100 100
Total Petroleum Hydrocarbons‐GRO 91.50 ND 145 ND 105 ND 123 ND 100 ND
Volatile Organics, NJDEP/TCL/Part 375 List mg/kg mg/kg mg/kg mg/kg mg/kgDilution Factor 1 1 1 1 11,1,1,2‐Tetrachloroethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,1,1‐Trichloroethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,1,2,2‐Tetrachloroethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,1,2‐Trichloro‐1,2,2‐trifluoroethane (Freon 113) 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,1,2‐Trichloroethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,1‐Dichloroethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,1‐Dichloroethylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2,3‐Trichlorobenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2,3‐Trichloropropane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2,4‐Trichlorobenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2,4‐Trimethylbenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2‐Dibromo‐3‐chloropropane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2‐Dibromoethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2‐Dichlorobenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2‐Dichloroethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,2‐Dichloropropane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,3,5‐Trimethylbenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,3‐Dichlorobenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,4‐Dichlorobenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND1,4‐Dioxane 0.047 ND 0.055 ND 0.054 ND 0.049 ND 0.045 ND2‐Butanone 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND2‐Hexanone 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 ND4‐Methyl‐2‐pentanone 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDAcetone 0.0047 ND 0.027 0.078 0.0049 ND 0.0045 NDAcrolein 0.0047 ND 0.0055 ND 0.0054 ND 0.0049 ND 0.0045 NDAcrylonitrile 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDBenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDBromochloromethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDBromodichloromethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDBromoform 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDBromomethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDCarbon disulfide 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDCarbon tetrachloride 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDChlorobenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDChloroethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDChloroform 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDChloromethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDcis‐1,2‐Dichloroethylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDcis‐1,3‐Dichloropropylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDCyclohexane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDDibromochloromethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDDibromomethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDDichlorodifluoromethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDEthyl Benzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDHexachlorobutadiene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDIsopropylbenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDMethyl acetate 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDMethyl tert‐butyl ether (MTBE) 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDMethylcyclohexane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDMethylene chloride 0.0047 ND 0.0096 J 0.0054 ND 0.0077 J 0.0066 Jn‐Butylbenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDn‐Propylbenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDo‐Xylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDp‐ & m‐ Xylenes 0.0047 ND 0.0055 ND 0.0054 ND 0.0049 ND 0.0045 NDp‐Isopropyltoluene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDsec‐Butylbenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDStyrene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDtert‐Butyl alcohol (TBA) 0.0047 ND 0.0055 ND 0.0054 ND 0.0025 ND 0.0023 NDtert‐Butylbenzene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDTetrachloroethylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDToluene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDtrans‐1,2‐Dichloroethylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDtrans‐1,3‐Dichloropropylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDTrichloroethylene 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDTrichlorofluoromethane 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDVinyl Chloride 0.0024 ND 0.0028 ND 0.0027 ND 0.0025 ND 0.0023 NDXylenes, Total 0.0071 D 0.0083 ND 0.0081 ND 0.0074 ND 0.0068 ND
Volatile Organics, Tentatively Identified Cmpds. mg/kg mg/kg mg/kg mg/kgDilution Factor 1 1 1 1Tentatively Identified Compounds 0 ND 0 ND 0 ND NTUnknonw aliphatic isomer NT NT NT 0.0048 J
Semi‐Volatiles, NJDEP/TCL/Part 375 List mg/kg mg/kgDilution Factor 2 11,1'‐Biphenyl 0.046 ND 0.023 ND1,2,4,5‐Tetrachlorobenzene 0.092 ND 0.045 ND1,2,4‐Trichlorobenzene 0.046 ND 0.023 ND1,2‐Dichlorobenzene 0.046 ND 0.023 ND1,2‐Diphenylhydrazine (as Azobenzene) 0.046 ND 0.023 ND1,3‐Dichlorobenzene 0.046 ND 0.023 ND1,4‐Dichlorobenzene 0.046 ND 0.023 ND2,3,4,6‐Tetrachlorophenol 0.092 ND 0.045 ND2,4,5‐Trichlorophenol 0.046 ND 0.023 ND2,4,6‐Trichlorophenol 0.046 ND 0.023 ND2,4‐Dichlorophenol 0.046 ND 0.023 ND2,4‐Dimethylphenol 0.046 ND 0.023 ND2,4‐Dinitrophenol 0.092 ND 0.045 ND2,4‐Dinitrotoluene 0.046 ND 0.023 ND2,6‐Dinitrotoluene 0.046 ND 0.023 ND2‐Chloronaphthalene 0.046 ND 0.023 ND2‐Chlorophenol 0.046 ND 0.023 ND2‐Methylnaphthalene 0.046 ND 0.023 ND2‐Methylphenol 0.046 ND 0.023 ND2‐Nitroaniline 0.092 ND 0.045 ND2‐Nitrophenol 0.046 ND 0.023 ND3‐ & 4‐Methylphenols 0.046 ND 0.023 ND3,3'‐Dichlorobenzidine 0.046 ND 0.023 ND3‐Nitroaniline 0.092 ND 0.045 ND4,6‐Dinitro‐2‐methylphenol 0.092 ND 0.045 ND4‐Bromophenyl phenyl ether 0.046 ND 0.023 ND4‐Chloro‐3‐methylphenol 0.046 ND 0.023 ND4‐Chloroaniline 0.046 ND 0.023 ND4‐Chlorophenyl phenyl ether 0.046 ND 0.023 ND
NTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNTNTNTNTNTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNTNTNTNTNTNTNTNTNTNTNT
NTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNTNT
NTNTNTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNTNTNTNT
NTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNTNTNTNTNTNTNTNTNTNTNT
NTNTNTNTNT
NTNTNT
NTNTNTNTNTNTNTNTNT
NTNT
NTNTNTNTNT
NTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNTNTNTNTNTNTNTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNTNTNTNTNTNTNTNTNTNTNTNT
NTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
C‐1
15C0447‐013/16/2015
Soil
0'‐3' 0'‐3'C‐2
15C0447‐023/16/2015
Soil
C‐3
15C0447‐033/16/2015
Soil
0'‐3'
NTNTNTNTNT
G‐21
15C0447‐083/16/2015
Soil
G‐26
15C0447‐093/16/2015
Soil
7'‐11'3'‐7'C‐4
15C0447‐043/16/2015
Soil
C‐5
15C0447‐053/16/2015
Soil
0'‐3'0'‐3'C‐6
15C0447‐063/16/2015
Soil
C‐7
15C0447‐073/16/2015
Soil
7'‐11'3'‐7'
Table 3
Waste Characterization Sampling Summary
51‐27 Queens Boulevard, Queens, New York
4‐Nitroaniline 0.092 ND 0.045 ND4‐Nitrophenol 0.092 ND 0.045 NDAcenaphthene 0.29 D 0.023 NDAcenaphthylene 0.046 ND 0.023 NDAcetophenone 0.046 ND 0.023 NDAniline 0.18 ND 0.090 NDAnthracene 0.52 D 0.023 NDAtrazine 0.046 ND 0.023 NDBenzaldehyde 0.046 ND 0.023 NDBenzidine 0.18 ND 0.090 NDBenzo(a)anthracene 0.78 D 0.023 NDBenzo(a)pyrene 0.41 D 0.023 NDBenzo(b)fluoranthene 0.35 D 0.023 NDBenzo(g,h,i)perylene 0.15 D 0.023 NDBenzo(k)fluoranthene 0.39 D 0.023 NDBenzoic acid 0.046 ND 0.023 NDBenzyl alcohol 0.046 ND 0.023 NDBenzyl butyl phthalate 0.046 ND 0.023 NDBis(2‐chloroethoxy)methane 0.046 ND 0.023 NDBis(2‐chloroethyl)ether 0.046 ND 0.023 NDBis(2‐chloroisopropyl)ether 0.046 ND 0.023 NDBis(2‐ethylhexyl)phthalate 0.046 ND 0.023 NDCaprolactam 0.092 ND 0.045 NDCarbazole 0.11 D 0.023 NDChrysene 0.76 D 0.023 NDDibenzo(a,h)anthracene 0.077 JD 0.023 NDDibenzofuran 0.046 ND 0.023 NDDiethyl phthalate 0.046 ND 0.023 NDDimethyl phthalate 0.046 ND 0.023 NDDi‐n‐butyl phthalate 0.046 ND 0.023 NDDi‐n‐octyl phthalate 0.046 ND 0.023 NDFluoranthene 1.77 D 0.046Fluorene 0.28 D 0.023 NDHexachlorobenzene 0.046 ND 0.023 NDHexachlorobutadiene 0.046 ND 0.023 NDHexachlorocyclopentadiene 0.046 ND 0.023 NDHexachloroethane 0.046 ND 0.023 NDIndeno(1,2,3‐cd)pyrene 0.16 D 0.023 NDIsophorone 0.046 ND 0.023 NDNaphthalene 0.046 ND 0.023 NDNitrobenzene 0.046 ND 0.023 NDN‐Nitrosodimethylamine 0.046 ND 0.023 NDN‐nitroso‐di‐n‐propylamine 0.046 ND 0.023 NDN‐Nitrosodiphenylamine 0.046 ND 0.023 NDPentachlorophenol 0.046 ND 0.023 NDPhenanthrene 2.12 D 0.037 JPhenol 0.046 ND 0.023 NDPyrene 1.38 D 0.032 J
Semi‐Volatiles, PAH Target List mg/kgDilution Factor 202‐Methylnaphthalene 0.46 DAcenaphthene 1.56 DAcenaphthylene 0.21 DAnthracene 2.28 DBenzo(a)anthracene 5.42 DBenzo(a)pyrene 1.22 DBenzo(b)fluoranthene 1.16 DBenzo(g,h,i)perylene 1.23 DBenzo(k)fluoranthene 1.54 DChrysene 10.40 DDibenzo(a,h)anthracene 0.46 DFluoranthene 17.70 DFluorene 1.66 DIndeno(1,2,3‐cd)pyrene 0.81 DNaphthalene 0.89 DPhenanthrene 17.40 DPyrene 16.30 D
Semi‐Volatiles, Tentatively Identified Cmpds. mg/kg mg/kgDilution Factor 2 1Tentatively Identified Compounds 0 NDunknow aromatic 1.59 JD
unknow aromatic #2 0.84 JD
Total Petroleum Hydrocarbons‐DRO (C10‐C28) mg/kg mg/kg mg/kg mg/kg mg/kgDilution Factor 1 1 1 1 1
Total Petroleum Hydrocarbons‐DRO 446 22.50 265 32.50 50.70
Herbicides, NJDEP/TCL/Part 375 List mg/kg mg/kgDilution Factor 1 12,4,5‐T 0.022 ND 0.022 ND2,4,5‐TP (Silvex) 0.022 ND 0.022 ND2,4‐D 0.022 ND 0.022 ND
Pesticides, NJDEP/TCL/Part 375 List mg/kg mg/kgDilution Factor 54,4'‐DDD 0.0018 ND 0.0018 ND4,4'‐DDE 0.0018 ND 0.0046 D4,4'‐DDT 0.0059 D 0.022 DAldrin 0.0018 ND 0.0018 NDalpha‐BHC 0.0018 ND 0.0018 NDalpha‐Chlordane 0.0018 ND 0.0018 NDbeta‐BHC 0.0018 ND 0.0018 NDChlordane, total 0.0073 ND 0.0071 NDdelta‐BHC 0.0018 ND 0.0018 NDDieldrin 0.0018 ND 0.0018 NDEndosulfan I 0.0018 ND 0.0018 NDEndosulfan II 0.0018 ND 0.0018 NDEndosulfan sulfate 0.0018 ND 0.0018 NDEndrin 0.0018 ND 0.0018 NDEndrin aldehyde 0.0018 ND 0.0018 NDEndrin ketone 0.0018 ND 0.0018 NDgamma‐BHC (Lindane) 0.0018 ND 0.0018 NDgamma‐Chlordane 0.0018 ND 0.0018 NDHeptachlor 0.0018 ND 0.0018 NDHeptachlor epoxide 0.0018 ND 0.0018 NDMethoxychlor 0.0091 ND 0.0089 NDToxaphene 0.092 ND 0.090 ND
Polychlorinated Biphenyls (PCB) mg/kg mg/kg mg/kgDilution Factor 1 1 1Aroclor 1016 0.018 ND 0.018 ND 0.018 NDAroclor 1221 0.018 ND 0.018 ND 0.018 NDAroclor 1232 0.018 ND 0.018 ND 0.018 NDAroclor 1242 0.018 ND 0.018 ND 0.018 NDAroclor 1248 0.018 ND 0.018 ND 0.018 NDAroclor 1254 0.018 ND 0.018 ND 0.018 NDAroclor 1260 0.018 ND 0.018 ND 0.018 ND
NTNTNT
NTNTNTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNTNT
NTNT
NT
NT
NT
NTNTNTNTNT
NTNTNT
NT
NT
NT
NTNTNTNTNTNTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNTNTNTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NT
NT
NT
NTNTNTNTNT
NTNT
NTNTNTNTNTNTNTNTNTNTNTNTNTNT
NTNTNTNTNT
NT
NT
NTNT
NTNTNTNTNTNTNTNTNTNTNTNT
NTNT
NTNTNTNTNTNTNTNTNT
NTNTNT
NTNT
NTNTNTNTNTNTNT
NTNTNTNT
NTNTNT
NT
NTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNT
NT
NTNTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NTNTNTNTNT
NTNTNTNT
NT
NTNTNTNTNT
NT
NT
NTNTNTNTNTNTNTNTNTNTNTNTNT
NT
NTNT
NT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNT
NTNTNT
NTNTNT
NTNTNTNT
NTNTNTNTNT
NT
NTNT
NT
NTNTNTNTNTNTNTNTNTNTNTNTNT
NTNT
NTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNTNTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNT
NTNTNTNTNTNTNTNTNTNTNTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NT
NTNTNT
NTNTNTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNT
NT
NTNTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
Table 3
Waste Characterization Sampling Summary
51‐27 Queens Boulevard, Queens, New York
Total PCBs 0.018 ND 0.018 ND 0.018 ND
NJDEP EPH (Cat. 2 Non‐Fractionated) mg/kg mg/kgDilution Factor 1 1
Total EPH NT 55.10 ND 53.80 ND
Metals, RCRA mg/kgDilution Factor 1Arsenic 2.68Barium 68.10Cadmium 0.33 NDChromium 32Lead 80.60Selenium 2.85Silver 0.55 ND
Metals, Target Analyte mg/kg mg/kgDilution Factor 1 1Aluminum 6,020 4,540Antimony 2.70 0.54 NDArsenic 2.63 1.35Barium 49.70 34.90Beryllium 0.11 ND 0.11 NDCadmium 0.33 ND 0.32 NDCalcium 1,100 921Chromium 14.90 10.70Cobalt 5.83 4.60Copper 35.30 17.60Iron 10,700 10,100Lead 59.50 11.40Magnesium 1,700 1,820Manganese 243 231Nickel 12.20 10.80Potassium 704 572Selenium 1.17 1.32Silver 0.55 ND 0.54 NDSodium 167 134Thallium 1.10 ND 1.08 NDVanadium 20.60 16.40Zinc 147 43.80
Metals, TCLP RCRA mg/L mg/L mg/LDilution Factor 1 1 1Arsenic 0.0040 ND 0.0040 ND 0.0040 NDBarium 0.58 0.51 0.39 NTCadmium 0.0080 0.0030 ND 0.0030 ND NTChromium 0.0050 ND 0.0050 ND 0.0050 ND NTLead 0.19 0.070 0.063 NTSelenium 0.010 ND 0.010 ND 0.010 ND NTSilver 0.0050 ND 0.0050 ND 0.0050 ND NT
Mercury by 7473 mg/kg mg/kg mg/kgDilution Factor 1 1 1
Mercury 0.090 0.081 0.032 ND
Mercury TCLP by 7473 mg/L mg/L mg/LDilution Factor 1 1 1
Mercury 0.0002 ND 0.0002 ND 0.0002 ND
Chromium, Hexavalent mg/kg mg/kgDilution Factor 1 1
Chromium, Hexavalent 0.55 ND 0.54 ND
Corrosivity pH units pH units pH unitsDilution Factor 1 1 1
pH 7.92 8.68 7.69
Cyanide, Total mg/kg mg/kgDilution Factor 1 1
Cyanide, total 0.55 ND 0.54 ND
Ignitability ‐ ‐ ‐Dilution Factor 1 1 1
Ignitability Non‐Ignit. Non‐Ignit. Non‐Ignit.
Reactivity‐Cyanide mg/kg mg/kg mg/kgDilution Factor 1 1 1
Reactivity ‐ Cyanide 0.25 ND 0.25 ND 0.25 ND
Reactivity‐Sulfide mg/kg mg/kg mg/kgDilution Factor 1 1 1
Reactivity ‐ Sulfide 15 ND 15 ND 15 ND
TCLP Extraction for METALS EPA 1311 N/A N/A N/ADilution Factor 1 1 1
TCLP Extraction Completed Completed Completed
Total Solids % % % % % % % % %Dilution Factor 1 1 1 1 1 1 1 1 1% Solids 90.60 91.20 90.90 91 91.40 90.80 93 92.60 95.40
NOTES:Any Regulatory Exceedences are color coded by Regulation
Q is the Qualifier Column with definitions as follows:D=result is from an analysis that required a dilutionJ=analyte detected at or above the MDL (method detection limit) but below the RL (Reporting Limit) ‐ data is estimatedB=analyte found in the analysis batch blankE=result is estimated and cannot be accurately reported due to levels encountered or interferencesNT=this indicates the analyte was not a target for this sampleNC=this indicates that no regulatory limit has been established for this analyteND=non‐detect
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNT
NTNT
NT
NT
NT
NTNT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NTNTNTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNT
NTNTNTNTNTNT
NTNTNTNT
NTNT
NT
NT
NT
NTNTNTNT
NT
NTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NTNTNT
NTNTNTNTNT
NTNTNTNT
NTNTNT
NTNTNTNTNT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NT
NT
NTNTNTNTNTNTNT
NTNTNTNTNTNT
NTNT
NT
NTNTNT
NTNTNTNTNTNTNT
NTNTNTNTNT
NTNT
NTNTNTNTNTNTNTNTNTNTNTNTNTNT
NTNTNTNTNT
NT
NT
NT
NT
NT
NT
NT
NT
NT NT
NT
NT
NT
NT
NT
NT
NT
NT
NTNTNTNTNT
NTNTNT
NTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NT
NTNTNTNT
NTNTNTNTNT
NT
NT
NT
NT
NTNTNTNT
NT
NTNTNTNTNT
NTNTNTNTNT
NTNTNTNTNT
NTNTNT