question: i (1 point) · question: 6 (1 point) given the following unit 2 conditions: rcs cooldown...
TRANSCRIPT
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: I
(1 point)
Given the following Unit 2 conditions:Initial conditions:
• Reactor power = 100%• Both MFDW Pumps tripped• 2RC-66 (PORV) has failed OPEN• Subcooling margin monitors indicate as follows:
o 2A Loop SCM = 18°F decreasingo 2B Loop SCM = 0°F stableo BOTH Core SCM = 12°F decreasing
1) Performing Rule 2 (Loss of SCM) _(1) required.
2) A reason RCPs are secured per Rule 2 is to _(2)_.
Which ONE of the following completes the statements above?
A. 1. is2. prevent pump damage that occurs from pumping a steam/water mixture
B. 1, is2. ensure RCP’s are secured before the RCS can evolve to a void fraction of>
70%
C. 1. is NOT2. prevent pump damage that occurs from pumping a steam/water mixture
D. 1, is NOT2. ensure RCP’s are secured before the RCS can evolve to a void fraction of>
70%
Page 1 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 2
(1 point)
Given the following Unit 1 conditions:Time = 1200:00
• Reactor Power = 100%• RCS Pressure = 2100 psig decreasing• RBNS level increasing• Reactor Building RI/Vs are in alarm
Time = 1202:00• Rule 2 directs tripping ALL RCP’s due to SCM indications
Time = 1204:30• IAI RCP remains operating• 1A1 RCP Amps = 520 amps stable
1) In accordance with Rule 2 (Loss of SCM), at Time 1204:30 the 1A1 RCP shouldbe(1).
2) If ANY RCP cannot be secured by the associated RCP Breaker switch on 1 UB2,Rule 2 directs de-energizing _(2) 6900V bus(es).
Which ONE of the following completes the statements above?
A. 1. left running2. ONLY the associated
B. 1. left running2. BOTH
C. 1. secured2. ONLY the associated
D. 1. secured2. BOTH
Page 2 of 100
Oconee Nuclear Station
Question:(1 point)
3IL T46 ONS SRO NRC Examination
Given the following Unit 1 conditions:Initial conditions:
• Time = 0400:00• Reactor Power 100%• RCS pressure 2100 psig rapidly decreasing• RB Pressure 0.3 psig rapidly increasing• Multiple RB RIA alarms
Current conditions:• Time = 0402:30• RCS pressure = 104 psig slowly decreasing• RB pressure = 16.2 psig slowly increasing• Operators have NOT adjusted the IA RBCU alignment
Which ONE of the following describes the lights that will be ILLUMINATED at Time0402:30 in the picture below?
..A CU
0
A. Damper RED light and RBCU GREEN light
B. Damper RED light and RBCU AMBER light
C. Damper GREEN light and RBCU GREEN light
D. Damper GREEN light and RBCU RED light
Page 3 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 4(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power = 80%• 1A Feedwater Flow 4.4 x 106 LB/HR• lB Feedwater Flow = 4.4 x 106 LB/HR
Current conditions:• 1B1 RCP trips
1) Reactor powerwill AUTOMATICALLY be reduced to a MAXIMUM of_ (1) _%
Core Thermal Power.
2) When the MAXIMUM power level is reached, a MFDW flow of approximately(2)_106 LB/HR will be established to the 1A Steam Generator.
Which ONE of the following completes the statements above?
A. 1.652. 5.4
B. 1.742. 5.4
C. 1.652, 6.1
D. 1.742. 6.1
Page4oflOO
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 5
(1 point)
1) When re-establishing seal injection flow to a RCP, the major concern with thermal shock tothe RCP seals is seal failure resulting in _(1)_.
2) The MINIMUM condition that would require entry into AP/14 (Loss Of Normal HPI Makeupand/or RCP Seal Injection) is loss of seal injection to _(2)_ RCP(s).
Which ONE of the following completes the statements above?
A. 1 excessive RCS leakage2. ANY
B. 1. excessive RCS leakage2. ALL
C. 1. RCP shaft binding2. ANY
D. 1. RCP shaft binding2. ALL
Page 5 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaininationQuestion: 6
(1 point)
Given the following Unit 2 conditions:• RCS cooldown in progress• LPI aligned in the Series Mode
1) The reason Series Mode was developed for Unit 2 was to provide _(1)_.
2) A loss of the _(2)_ LPI Pumps would result in a total loss of Decay HeatRe mova
A. 1 a backup to the Switchover mode of LPI2. 2A and 2C
B. 1. a backup to the Switchover mode of LPI2. 2B and 20
0. 1. additional cooling capacity during 2/0 pump ops2. 2A and 20
D. 1 additional cooling capacity during 2/0 pump ops2. 2B and 20
1age 6 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 7
(1 point)
Given the following plant conditions:Time 1200:00
• Unit 1 100%• Unit2= MODE 5• A and B LPSW Pumps are operating
Time = 1205:00• A LPSW pump trips and will NOT restart• 1SA-91A9 (LPSW HEADER A PRESS LOW) actuates
1) At Time = 1205:05 the C LPSW Pump _(1 )_ received a signal to start.
2) At Time 1206:00 Unit 1 _(2)_ meet the LCO requirements of Tech Spec 3.7.7(LPSW).
Which ONE of the following completes the statement above?
ASSUME NO OPERATOR ACTIONS
A. 1. has2. does
B. 1. has2. does NOT
C. 1. has NOT2. does
D. 1. has NOT2. does NOT
Page 7 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 8
(1 point)
Given the following Unit 1 conditions:• Reactor power 62% stable• RCS pressure = 2185 psig slowly decreasing• Pressurizer level = 229 inches slowly decreasing• Pressurizer temperature = 648.0°F slowly increasing• Pressurizer Heater Bank 1 switch is ON• Pressurizer Heater Bank 2 (Groups B & D) are in AUTO and OFF• Pressurizer Heater Banks 3 and 4 are in AUTO and OFF
1) The pressurizer is(1).
2) The pressurizer saturation circuit (2) — responding as expected.
Which ONE of the following completes the statements above?
A. 1. subcooled2. is
B. 1. subcooled2. is NOT
C. 1. saturated2. is
D. 1. saturated2. is NOT
Page 8 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 9
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power = 100%• BOTH MFDW pumps trip
Current conditions:• Reactor power = 57% slowly decreasing
1) In accordance with Rule 1 (ATWS), the CRD breakers are opened _(1) aligningHPI injection from the BWST.
2) The direction given to the operator opening the CRD breaker is to (2) ArcFlash PPE.
Which ONE of the following completes the statements above?
A. 1. prior to2. wear
B. 1. priorto2. NOT wear
C. 1. after2. wear
D. 1, after2. NOT wear
Page 9 of 100
Oconee Nuclear Station• 1LT46 ONSSRO NRCExarnination
Question: 10(1 point)
Given the following Unit 1 conditions:• Loss of Heat Transfer has occurred• Unit 1 TDEFWP is now available to feed the Steam Generators• 1A SG level = 8” XSUR slowly decreasing• IA SG pressure = 412 psig slowly decreasing• I B SG level = 5” XSUR slowly decreasing• I B SG pressure = 385 psig slowly decreasing
In accordance with Rule 7 (Steam Generator Feed Control), the MAXIMUM initial feedrate allowed to EACH Steam Generator is limited to _(1 )_ gpm in order to prevent_(2)_.
Which ONE of the following completes the statement above?
A. 1. 1002. damage to the Steam Generators
B. 1. 1002. an RCS overcooling event
C 1.502. damage to the Steam Generators
D. 1502. an RCS overcooling event
Page 10 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 11(1 point)
Oconee plant conditions:• Station blackout has occurred• The EOP Blackout tab has been in progress for three hours• 1CA voltage 104 VDC
Which ONE of the following describes why the Blackout tab directs the crew to FAIL100-8 (CC RETURN PENT (54) OUTSIDE BLOCK) closed?
A. 100-8 will fail open if IA pressure decreases to <35 psig.
B. Prevents auto restart of CC pumps once AC power is restored.
C. CC will not be needed in the Reactor Building during the shutdown followingthe blackout.
D. 1CC-8 will fail open if DC power is lost to the solenoid.
Page 11 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 12
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor trip from 100% power due to a loss of offsite power (SwitchyardIsolation)
• CT-i lockout
Current conditions:• AP!1 1 (Recovery from Loss of Power) initiated• Si1 (STBY BUS ito MFB1) Breaker will NOT close• LOAD SHED COMPLETE is NOT lit on the ES Component Status Panel
In accordance with AP/1 i, electrical loads are secured to
_______
Which ONE of the following completes the statement above?
A. prevent exceeding CT-4 Overload Limits
B. prevent exceeding CT-5 Overload Limits
C. ensure Si2 (STBY BUS 2 to MFB2) Breaker is operated within limits
D. ensure adequate voltage to ES equipment during a subsequent LOCA
Page 12 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 13
(1 point)
Given the following Unit 1 conditions:Time = 1200
• Reactor Power = 100%• OAC INOPERABLE
Time = 1300• 1 KVIA is de-energized
1) At Time = 1300 Backup Incore Instrumentation (1) preferred to be used forQuadrant Power Tilt indications in accordance with OP/i /A/1105/014 (ControlRoom Instrumentation Operation And Information) Enclosure 4.13 (ReactorParameter Information).
2) The MINIMUM power level at which the Tech Spec Quadrant Power Tilt limits in theCOLR apply is _(2).
Which ONE of the following completes the statements above?
A. 1. is2. 20%
B. 1. is2. 40%
C. 1. is NOT2. 20%
D. 1. is NOT2. 40%
Page 13 of 100
Oconee Nuclear Station• 1LT46 ONS SRO NRC ExaminationQuestion: 14
(1 point)
Given the following plant conditions:• KHU-1 generating to grid• 1 DA input breaker (K1 -DA-1 A, Batt #1 Ckt Bkr) fails OPEN• 2SA-171A3 (Unit 1 Alarm Lockout) actuates
1) KHU#1 _(1)5trip.
2) The reason DC power is used for Keowee control power is that it will be availablefor a MINIMUM of approximately (2) — hour(s) following a loss of ALL ACpower.
Which ONE of the following completes the statements above?
A. 1.will NOT2. one
B. 1.will NOT2. four
C. 1.will2. one
D. 1.will2. four
Page 14 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 15
(1 point)
Given the following Unit I conditions:e Reactor Power 100%• AP/22 (Loss of Instrument Air) in progress
1) Auxiliary Instrument Air (AlA) (1)_ provide a backup source of air to 1 HP-31.
2) With ALL motive force lost, the operator sent to manually operate 1 HP-31 willINITIALLY be required to throttle 1 HP-31 in the _(2)_ direction.
Which ONE of the following completes the statements above?
A. 1. does2. closed
B. 1. does2. open
C. 1,does NOT2. closed
D. I.does NOT2. open
Page 15 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 16
(1 point)
Given the following Unit 1 conditions:• A loss of ALL sources of Steam Generator feed has occurred• HPI Forced Cooling in progress• RCS pressure = 2210 psig slowly decreasing• Pzr Level = 380 inches increasing• Core SCM 56°F increasing
In accordance with Rule 6 (HPI), HPI flow (1 )_ be throttled because _(2)_.
Which ONE of the following completes the statement above?
A. 1. may NOT2. RCS pressure is decreasing
B. 1. may NOT2. CETCs are increasing
C. 1. may2. Pzr Level is increasing
D. 1. may2. CETCs are decreasing
Page 16 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 17
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power = 100%• 1A Main Steam Line Break occurs
Current conditions:• Reactor has tripped• RCS Tave = 544°F slowly increasing• 1A SG Pressure = 0 psig• 1 B SG Pressure = 990 psig slowly increasing• Turbine bypass valves in Auto• Reactor Building pressure = 0.2 psig stable
Which ONE of the following describes:
1) the status of the TDEFWP?
2) how subsequent operation of the TDEFWP would be performed?
A. 1. Operating2. Can be secured with TDEFWP control switch before AFIS is reset
B. 1. Operating2. Can be secured with TDEFWP control switch ONLY after AFIS is reset
C. 1. NOT operating2. Can be started with TDEFWP control switch before AFIS is reset
D. 1. NOT operating2. Can be started with TDEFWP control switch ONLY after AFIS is reset
Page 17 of 100
Oconee Nuclear Station• 1LT46 ONS SRO NRC ExaminationQuestion: 18
(1 point)
Given the following Unit 1 conditions:• Reactor tripped from 100% power• ALL Control Rods fully inserted• IMS-lO (Main Steam Relief Valve) is stuck open• Main Steam pressure is being reduced in an attempt to reseat 1 MS-i 0
In accordance with Subsequent Actions of the EOP,
1) Main Steam pressure will be reduced in (1) psig increments.
2) the MINIMUM RCS temperature allowed while reseating a MSRV is (2) °F.
Which ONE of the following completes the statements above?
A. 1. 102. 532
B. 1.202. 532
C. 1.102. 525
D. 1.202. 525
Page 18 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 19
(1 point)
Given the following Unit 1 conditions:• Reactor Power = 98% decreasing• Control Rod 4 in Group 6 = 0% withdrawn
1) ICS will automatically reduce Reactor power to _(1)_% Core Thermal Power.
2) The basis for decreasing reactor power to the above level is to ensure _(2).
Which ONE of the following completes the statements above?
A. 1.652. Local Linear Heat Rate limits are not exceeded
B. 1.652. adequate margin in preparation for resetting RPS trip set points
C. 1.552. Local Linear Heat Rate limits are not exceeded
D. 1.552. adequate margin in preparation for resetting RPS trip set points
Page 19 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 20
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor in MODE 3
Current conditions:• 1 DIB inverter DC Input breaker trips
The associated source range power will be restored using the
Which ONE of the following completes the statement above?
A. ASCO Switch
B. Static Transfer Switch
C. Manual Bypass Switch
D. Inverter Bypass Switches
Page 20 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 21
(1 point>
Which ONE of the following is the condenser vacuum (inches Hg) SETPOINT stated inAP/27 (Loss Of Condenser Vacuum) that will require manually tripping the Reactorwhen in MODE 1?
A. 25
B. 24
C. 22
D. 19
Page 21 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExarninationQuestion: 22
(1 point)
1RIA-3, (Refueling Canal Wall Area Monitor)..
1) HIGH alarm (1)_ cause a Reactor Building Evacuation alarm.
2) is NOT in HIGH alarm during Power Operations because the (2)_.
Which ONE of the following completes the statements above?
A. 1. will2. setpoint is raised to provide for indication of RCS leakage
B. 1. will2. detector is removed from the Reactor Building
C. 1. will NOT2. setpoint is raised to provide for indication of RCS leakage
D. 1. will NOT2. detector is removed from the Reactor Building
Page 22 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 23(1 point)
Given the following plant conditions:• An Active Fire is taking place in Unit 2 Equipment Room• The SRO dispatches you to the Unit I Equipment Room to determine Control
Room Ventilation and Fire Damper positions
1) Control Room Ventilation system damper positions _(1 )_ be determined byobserving the linkage pointing to either the “OPEN” or “CLOSED” tag.
2) Observing that all damper blades are aligned in either the open or closed position(2)_ the ONLY way to determine Fire Damper positions between Unit 1 and
Unit 2 Equipment Rooms.
Which ONE of the following completes the statements above?
A. 1. can2. is
B. 1. can2. is NOT
C. 1. can NOT2. is
D. 1. can NOT2. is NOT
Page 23 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 24
(1 point)
Given the following Unit 2 conditions:Initial conditions:
• Reactor power = 90%• Loop ‘A’ Controlling Thot fails HIGH• 2SA21B4 (RC AVERAGE TEMP HIGH/LOW) actuated
Current conditions:• The Diamond and BOTH FDW Masters taken to HAND
Which ONE of the following describes the INITIAL action taken by an RO, and thereason for the action, in accordance with OMP 1-18 (Implementation Standard DuringAbnormal And Emergency Events)?
A. Decrease Feedwater to stabilize reactor power
B. Decrease Feedwater to stabilize RCS pressure
C. Insert control rods to stabilize RCS pressure
D. Insert control rods to stabilize reactor power
Page 24 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExarninationQuestion: 25
(1 point)
Given the following Unit 2 conditions:• Reactor power = 100%• 2SA-18/A-11, TURBINE BSMT WATER EMERGENCY HIGH LEVEL, is in
alarm• Turbine Building flooding is confirmed
In accordance with the Turbine Building Flood tab of the EOP...
1) Emergency Feedwater pumps (1) required to be utilized to fill the SteamGenerators in addition to the Main Feedwater pumps.
2) While maximizing feed to the SGs, the MAXIMUM feed rate limits of Rule 7 (SGFeed Control) (2) apply while maintaining Tave> 532 °F.
Which ONE of the following completes the statements above?
A. 1. are2. do
B. 1. are2. do NOT
C. 1. are NOT2. do
D. 1. are NOT2. do NOT
Page 25 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 26
(1 point)
Given the foNowing Unit 1 conditions:Time = 1200
• Reactor trips from 100% power due to a 1A Main Steam Line Break• BOTH 1A and 1 B SG pressures rapidly decreasing• CoreSCM=0°F
Time = 1204• Tcold reaches lowest value of 416°F
Time = 1215• Tcold = 498°F stable• Core SCM = 78°F stable• Rule 2 (Loss of SCM) is complete
1) — (1) — was the EOP tab that was required to be entered first from SubsequentActions.
2) Rule 8 (Pressurized Thermal Shock) — (2) — required to be invoked.
Which ONE of the following completes the statements above?
A. 1. Loss of SCM2. is
B. 1. Loss of SCM2. is NOT
C. 1, Excessive Heat Transfer2. is
D. 1. Excessive Heat Transfer2. is NOT
Page 26 of 100
Oconee Nuclear Station* 1LT46 ONSSRONRCExaminationQuestion: 27
(1 point)
Given the following Unit 1 conditions:Time = 1200
• EOL Unit shutdown in progress• RCS Thot = 439°F stable
Time 1205• Electrical disturbance occurs• The following statalarms actuate
o iSA-i 5/E6 (EL Swyd Isolation Confirmed Chnl A Logic)o ISA-i 4/E6 (EL Swyd Isolation Confirmed Chnl B Logic)o 1 SA-21A3 (RC Loop A Flow Low)o 1 SA-2/A4 (RC Loop B Flow Low)o 1 SA-2/A5 (RC Total Flow Low)
1) Assuming no additional operator actions, at Time = 1230, Thot will be (i)_439°F.
2) Entry into the EOP _(2) required.
Which ONE of the following completes the statements above?
A. 1. greaterthan2. is NOT
B. 1. greaterthan2. is
C. 1. approximately2. is NOT
D. 1. approximately2. is
Page 27 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 28
(1 point)
Given the following Unit 1 conditions:• Reactor power 100% stable• Delta Tc ICS station in HAND• 1A1 RCP shaft shears
When RCP 1A1 shears, the plant will automatically run back at (1) and whenpower stabilizes, 1 A loop Tc will be (2) 1 B loop Tc.
Which ONE of the following completes the statement above?
ASSUME NO OPERATOR ACTIONS
A. 1. 20% per minute2. less than
B. 1. 20% per minute2. approximately the same as
C. 1. 25%perminute2. less than
D. 1. 25% per minute2. approximately the same as
Page 28 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 29
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• 1A1 RCP start in progress• AC oil lift pump is started
Current conditions:• Oil lift pump low discharge pressure does NOT clear
1) The AC oil lift pump (1)_automatically stop after a time delay.
2) The bypass position on the RCP start/stop switch — (2) — bypass ALL RCPstarting interlocks.
Which ONE of the following completes the statements above?
A. 1. will2. will
B. 1. will2. will NOT
C. 1. will NOT2. will
D. 1. will NOT2. will NOT
Page 29 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 30
(1 point)
Given the following Unit 3 conditions:Reactor Power = 100% for previous 7 months
• lOS in automatic• 3A Purification IX was taken out of service 6 months ago• 3A Purification IX was just placed back in service without being saturated to
current RCS boron concentration
1) Group 7 control rods will be _(l)_
2) Assuming no other operator actions, taking the lOS Reactor Bailey station ONLY toHAND _(2)_ stop the rod motion.
Which ONE of the following completes the statements above?
A. 1. inserting2. will
B. 1. inserting2. will NOT
C. 1. withdrawing2. will
D. 1. withdrawing2. will NOT
Page 30 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 31
(1 point)
Whch ONE of the following consists of ONLY components powered from 2TD?
A. 20 LPI pump and 2B HP) pump
B. 20 LPI pump and 2C HP) pump
C. 2B LPI pump and 2B HP) pump
D. 2B LPI pump and 20 HP) pump
Page 31 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 32
(1 point)
Given the following Unit 3 conditions:• Reactor power 100%• 3A Core Flood Tank
o Pressure = 587 psig stableo Level = 12.87 ft stable
• 3B Core Flood Tanko Pressure = 629 psig stableo Level = 13.36 ft stable
Which ONE of the following describes the potential adverse effect and its cause thatcould occur during a design basis large break LOCA?
A. 3A CFT will discharge an inadequate volume of water into the core due to theCFT level.
B. 3A CFT will discharge an inadequate volume of water into the core due to theCFT pressure.
0. 3B CFT wiN discharge too much inventory during the blow down phase and notcover the hotspot during re-flood due to OFT level.
D. 3B OFT will discharge too much inventory during the blow down phase and notcover the hotspot during re-flood due to OFT pressure.
Page 32 of 100
Oconee Nuclear Station• 1LT46 ONS SRO NRC ExaminationQuestion: 33
(1 point)
Given the following Unit I conditions:• Large Break LOCA has occurred
In accordance with EOP End, 5.12 (ECCS Suction Swap to RBES), which ONE of thefollowing describes:
1) the range of BWST levels (ft) where LPI pump suction would be aligned to both theRB Emergency Sump and the BWST simultaneously?
2) the action(s) that would be required if 1 LP-22 failed to close when isolating theBWST?
A. 1. 15—92. stop the 1 B LPI pump AND 1 B RBS pump
B. 1. 15—92. Maximize total LPI flow < 3100 gpm
C. 1. 9—62. stop the 1 B LPI pump AND 1 B RBS pump
D. 1. 9—62. Maximize total LPI flow < 3100 gpm
Page 33 of 100
Oconee Nuclear Station• IL T46 ONS SRO NRC ExaminationQuestion: 34
(1 point)
Given the following Unit 1 conditions:• Reactor in MODE 1• Quench Tank is being pumped to 1A BHUT using the Quench Tank Pump AND
the Component Drain Pump
1) In accordance with OP!1IA/1104/017 (Quench Tank Operations), Quench TankLevel shall be maintained at a MAXIMUM of _(1)_ inches.
2) The Component Drain Pump _(2)_ automatically trip once Quench Tank levelreaches 80 inches
Which ONE of the following completes the statements above?
A. t902. will
B. 1.902. will NOT
C. 1. 1002. will
D. 1. 1002. will NOT
Page 34 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 35(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power= 100%• 1A and lB Letdown Coolers in service• Letdown flow = 78 gpm
Current conditions:• 1A Letdown Cooler is removed from service by the RO in the Control Room
1) CC flow to the 1 B Letdown Cooler will — (1)
2) In accordance with OP/i/All 104/002 (HPI System), once the IA Letdown Cooler sisolated the MAXIMUM letdown flow is (2) gpm.
Which ONE of the following completes the statements above?
A. 1. stay the same2.88
B. 1. stay the same2. 125
C. 1. increase2.88
D. 1. increase2. 125
Page 35 of 100
Oconee Nuclear Station1LT46 ONS SRO NRC ExaminationQuestion: 36
(1 point)
Which ONE of the following sets of components are BOTH cooled by the ComponentCooling system.
A. RCP Seal Return Coolers AND Quench Tank Coolers
B. RCP Seal Return Coolers AND RCP Motor Coolers
C. RCP Seal Coolers AND Quench Tank Coolers
D. RCP Seal Coolers AND RCP Motor Coolers
Page 36 of 100
Oconee Nuclear Station• 1LT46 ONS SRO NRC ExaminationQuestion: 37
(1 point)
Given the following Unit 3 conditions:• Time=1200• Reactor power = 100%• Channel A AND Channel B narrow range RCS pressure fail HIGH
1) At Time = 1200 an AUTOMATIC reactor trip _(1 )_ occur,
2) At Time 1205 a low RCS pressure ES actuation _(2)_ occurred.
Which ONE of the following completes the statements above?
ASSUME NO OPERATOR ACTIONS
A. 1. will2. has
B. 1. will2. has NOT
C. 1. will NOT2. has
D. 1. will NOT2. has NOT
Page 37 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 38
(1 point)
Given the following Unit 1 conditions:• Reactor power = 100%• I Bi Reactor coolant pump trips
Based on the above conditions, which ONE of the following RPS trips will preventexceeding the Departure from Nucleate Boiling Ratio (DNBR) safety !imit?
A. Flux/Pump
B. L0wRCS Pressure
C. Flux/Flow/Imbalance
D. High RCS Temperature
Page 38 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 39(1 point)
Given the following Unit 1 conditions:• Reactor Power = 100%• 1 KVIB panelboard is de-energized
1) The (1)_ Voters will NOT actuate their associated safeguards equipment.
2) Engineered Safeguards System Instrument Channels are in a (2)_ out of twotrip condition.
Which ONE of the following completes the statements above?
A. 1. ODD2. one
B. 1. ODD2, two
C. 1. EVEN2. one
D. 1. EVEN2. two
Page 39 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 40
(1 point)
Given the following Unit 1 conditions:• Reactor power = 100%• 1A Main Steam Line Break inside containment occurs• Reactor Building Pressure peaks at 22.4 psig
1) The pump whose switch is pictured below _(1) received an ES signal to start.
2) The valve whose switch is pictured below _(2)_ received an ES signal toOPEN.
OPEN CLOSED
Which ONE of the following completes the statements above?
1. has NOT2. has NOT
1. has NOT2. has ,Wt111
t2. 1. has2. has NOT
1. has2. has
Page 40 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 41
(1 point)
Given the following Unit 1 conditions:• Reactor in MODE 1
1) The LOWER Reactor Building Pressure that will result in an automatic start of theReactor Building Spray pumps is _(1 )_ psig.
2) The BWST to RBS pump suction valve 1 LP-22 _(2)_ receive a signal to OPENon ECCS actuation.
Which ONE of the following completes the statements above?
A. 1. 4.22. does NOT
B. 1. 4.22. does
C. 1. 11.52. does NOT
D. 1. 11.52. does
Page-fl of 100
Oconee Nuclear StationIL T46 ONS SRO NRC ExaminationQuestion: 42
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power = 100%1 TC locked out
• 1 BS-2 breaker is open and will not close
Current conditions:• ES 1 * 8 actuates due to a Large Break LOCA
1) Based on the above conditions, the RBS system (1) be able to perform itssafety function.
2) When in recirculation mode, one of the RBS system purposes is to (2)
Which ONE of the following completes the statements above?
A. 1. will2. entrain Iodine thus reducing offsite dose
B. 1. will NOT2. entrain Iodine thus reducing offsite dose
C. 1. will2. minimize hydrogen production
D. 1. will NOT2. minimize hydrogen production
Page 42 of 100
Oconee Nuclear StationIL T46 ONS SRO NRC ExaminationQuestion: 43
(1 point)
Given the following Unit 3 conditions:Initial conditions:
• Reactor power = 100%• 3MS-112 & 3MS-173 (SSRH 3A13B Controls) are OPEN in MANUAL• 3MS-77, 78, 80, 81 (MS to SSR[fs) control switches in OPEN
Current conditions:• Main Turbine trips
1) 3MS-112&3M5-l73will(1).
2) 3MS-77, 78, 80, 81 will — (2) —.
Which ONE of the following completes the statements above?
A. 1 close2. close
B. 1. close2. remain open
C. 1. remain open2. close
D. 1, remain open2. remain open
Page 43 of 100
Oconee Nuclear Station• IL T46 ONS SRO NRC ExaminationQuestion: 44
(1 point)
Given the following Unit 1 conditionsInitial conditions:
• Reactor power = 70% stable
Current conditions:• 1HPE-6 (Heater 1A1 Bleed Inlet) closed
Which ONE of the following predicts the:
1) impact of the malfunction on Feedwater flow assuming no operator action?
2) procedure which can be used to reopen 1 HPE-6?
A. 1. higher2. OP/i /A11106/23 (High and Low Pressure Extraction)
B. 1. higher2. OP/1/A/1106/002 (Condensate and FDWsystem)
C. 1. lower2. OP/iIAIllO6/23 (High and Low Pressure Extraction)
D. 1. lower2. OP!i/A/1106/002 (Condensate and FDWsystem)
Page 44 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 45
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power 100%
Current conditions:• Condenser vacuum = 18.5 inches Hg stable• 1TA and 1TB de-energized
SG levels will be automatically controlled at
_______
Which ONE of the following completes the statement above?
A. 25 inches Startup Range
B. 30 inches XSUR
C. 50% Operating Range
D. 240 inchesXSUR
Page 45 of 100
Oconee Nuclear Station1LT46 ONS SRO NRC ExaminationQuestion: 46
(1 point)
Which ONE of the following utilizes the 1TE ES Power String as its source of electricalpower?
A. C LPSW pump
B. 1CRBCU
C. 1BMDEFWP
D. 1BRBS pump
Page 46 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 47
(1 point)
Given the following plant conditions:• The Standby Buses are being powered from the 100 kV line• The SL Breakers Auto/Manual Selector switches are in AUTO• The TRIP INTERLOCK DEFEAT SWITCH is in the LEE position
Which ONE of the following conditions will cause the SL Breakers to open?
A. An undervoltage condition occurs on Standby Bus 1 ONLY.
B. An undervoltage condition would have to occur on BOTH Standby Bus 1 ANDStandby Bus 2.
C. The 1st level 100KV Degraded Voltage Relay has been satisfied for 9 secondsAND the 2nd level 100KV Degraded Voltage Relay is now satisfied.
D. The 1st level 100KV Degraded Voltage Relay is satisfied now AND the 2ndlevel 100KV Degraded Voltage Relay has been satisfied for 9 seconds.
Page 47 of 100
Oconee Nuclear Station• IL T46 ONS SRO NRC ExaminationQuestion: 48
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power = 100%• 1 PA Battery is inoperable
In accordance with SLC 16.8.3 (Power Battery Parameters):
1) The MAXIMUM Completion time allowed to declare the Unit 1 TDEFDW pumpinoperable is (1)
2) Cross connecting — (2) — buses is required.
Which ONE of the following completes the statements above?
A. 1. immediately2. IPA and IPB
B. 1. immediately2. 1PA,2PAand3PA
C. 1. within one hour2. 1PA and 1PB
D. 1. within one hour2. 1 PA, 2PA and 3PA
Page 48 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 49
(1 point)
Given the following Unit 1 conditions:Time = 1200
• Reactor power = 100%• ACB-4 Closed• Large LOCA occurs coincident with a total loss of offsite power
Time = 1205• Keowee Hydro Unit (KHU)-2 Emergency Lockout occurs
Which ONE of the following describes how ECCS systems are being powered at Time= 1210?
ASSUME NO OPERATOR ACTIONS
A. KHU-1 through the Overhead power path
B. KHU-1 through the underground power path
C. CT-5 powered from Lee combustion turbine
D. CT-5 powered from Central Switchyard
Page 49 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExamination
Question: 50(1 point)
Which ONE of the following describes the operation of the Unit Vent RadiationMonitors RIA-45 and R—46 when the switchover acceptance range setpoint isreached?
RL-45 (1) read ZERO and RIA-46 will provide (2)
A. twill2. only alarm and unit vent radiation level indication
B. twill2. the same interlock functions that R-45 performs
C. twill NOT2. only alarm and unit vent radiation level indication
D. 1.willNOT2. the same interlock functions that RU-45 performs
Page 50 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 51
(1 point)
Given the following Unit 1 conditions:• Reactor power 100%• A and B LPSW pumps are turned OFF and cannot be restarted• IAP/24 (Loss of LPSW) initiated
1) The LOWEST CRD temperature that will require a Reactor trip is (1)_ °F inaccordance with 1API2O (Loss of Component Cooling).
2) PRIOR to the reactor trip, the ROW heat exchanger outlet temperatures would beexpected to (2).
Which ONE of the following completes the statements above?
A. 1. 1402. increase
B. 1. 1402. remain unchanged
0. 1. 1802. increase
D. 1. 1802. remain unchanged
Page 51 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 52
(1 point)
Given the following Unit I conditions:• Reactor Power = 25% stable• Instrument Air pressure = 63 psig slowly decreasing
AP/22 (Loss of Instrument Air) will direct the operator to trip the
Which ONE of the following completes the statement above?
A. Reactor ONLY
B. Main Turbine ONLY
C. Main Feedwater Pumps ONLY
D. Reactor and Main Feedwater Pumps ONLY
Page 52 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 53(1 point>
Given the following Unit 1 conditions:• Reactor trip from 100% due to loss of all Main Feedwater• 1FDW-316 pneumatic supply line has ruptured and the valve cannot be
operated from Control Room• Enclosure 5.27 (Alternate Methods of Feeding the Steam Generator) in
progress• SRO notified that the startup path to the 1 B SG CANNOT be used
Which ONE of the following is the NEXT method specified in Enclosure 5.27 to controlRCS temperature?
A. Using ONLY the 1A SG
B. Use 1A SG AND feed lB SG with Alternate Units EFDW
C. Use 1A SG AND feed 18 SG by manually throttling 1FDW-316
D. Use 1A SG AND feed 18 SG with TDEFWP using 1MS-94 spindle to throttleTDEFWP speed
Page 53 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExamination
Question: 54(1 point>
Given the following Unit 1 conditions:Time 1200
• Reactor in MODE 5• RCSLoopsdropped• Pressurizer level = 340” stable• RB Cavity washdown in progress• RB Purge in progress• Reactor Building Sump is being pumped
Time = 1205• Pressurizer level 322” decreasing• 1RIA-49 (Reactor Building High Gas) in HIGH alarm
1) The Containment Evacuation alarm (1) AUTOMATICALLY actuate as a resultof the I RL’-49 HIGH alarm.
2) _(2)_ is the procedure that is required to be entered FIRST.
Which ONE of the following completes the statements above?
A. 1. will2. AP/26 (Loss of Decay Heat Removal)
B. 1. will2. AP/2 (Excessive RCS Leakage)
C. 1. will NOT2. AP/26 (Loss of Decay Heat Removal)
D. 1. will NOT2. AP/2 (Excessive RCS Leakage)
Page 54 of 100
Oconee Nuclear StationIL T46 ONS SRO NRC Examination
Question: 55(1 point)
Given the following Unit 1 conditions:• Reactor in MODE 5• RB Main Purge in operation
Which ONE of the following will cause the RB Main Purge Fan to AUTOMATICALLYtrip OFF?
A. Suction pressure = 5” of water vacuum
B. 1 RIA—45, UNIT VENT GAS NORM, reaches its ALERT setpoint
C. Statalarm ISA9IB-3, RBV PURGE INLET TEMPERATURE LOW, alarms
D. 1 PR-3 (RB PURGE CONTROL) green CLOSED light is lit and red OPEN lightis off on 1VB2
Page 55 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExamination
Question: 56(1 point)
Given the following Unit 1 conditions• Reactor startup in progress• ALL Control Rods = 0% withdrawn
In accordance with AD-OP-ALL0203 (Reactivity Management), which ONE of thefollowing is the EARLIEST condition during a reactor startup where criticality should beexpected?
When operators begin withdrawing
________
A. CRD Safety Groups
B. CRD Regulating Groups
C. rods after the -.75% delta K/K ECP position is reached
D. rods after the -1% delta K/K ECP position is reached
Page 56 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 57
(1 point)
Given the following Unit 1 conditions:Time 1200
• Reactor has tripped from 100%
Time = 1205• ALL Condensate, Feedwater, AND Emergency Feedwater pumps are
unavailable• BOTH lAand 1BSG’s are dry• RCS temperature = 584°F slowly increasing• RCS pressure 2044 psig slowly increasing
1) Assuming NO operator actions, RCS (1)_ will stop increasing FIRST.
2) The NEXT method of decay heat removal required by the EOP will be _(2).
Which ONE of the following completes the statements above?
A. 1. pressure2. HPI Forced Cooling
B. 1. pressure2. SSFASW
C. ttemperature2. HPI Forced Cooling
D. 1.temperature2. 5SF ASW
Page 57 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 58
(1 point>
Given the foNowing Unit I conditions:Initial Conditions:
• Reactor Power 100%• 1 B RPS channel in Manual Bypass due to failed RB pressure transmitter
Current Conditions:• iNl-7 fails HIGH
The 1C RPS channel:
1) _(i )_ AUTOMATICALLY trip.
2) (2) required to be placed in Manual Bypass in accordance withOP/i IA/i 105/014 (Control Room Instrumentation).
Which ONE of the following completes the statements above?
A. 1. did2. is
B. 1. did2. is NOT
C. 1. did NOT2. is
D. 1. did NOT2. is NOT
Page 58 of 100
Oconee Nuclear Station• IL T46 ONS SRO NRC ExaminationQuestion: 59
(1 point)
Given the following Unit 1 conditions:• Reactor power = 90% stable• 1A and 1 B Main FDW Control valves are in HAND• Controlhng Feedwater valve tP fails LOW
1) The initial response to the above failure is that Steam Generator levels _(1)increase
2) IF the conditions above result in a Reactor trip, the FDW Control Valve lOSHand/Auto stations will _(2).
Which ONE of the following completes the statements above?
ASSUME NO OPERATOR ACTIONS
A. 1. will2. remain in HAND
B. 1. will2. revert to AUTO
C. 1. will NOT2. remain in HAND
D. 1. will NOT2. revert to AUTO
Page 59 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 60
(1 point)
Given the following plant conditions:Time 1200
• Fuel Handling activities in progress in Unit 1&2 Spent Fuel Pool• Fuel Cask is dropped damaging the Spent Fuel Pool liner
Time = 1205• Spent Fuel Pool level = -2.9 feet decreasing• Spent Fuel Pool Ventilation system is in operation
At TIME 1205:
1) The Unit 1 &2 Spent Fuel Cooling Pumps _(1) tripped off on low Spent FuelPool level.
2) Spent Fuel Pool Ventilation system is using the Unit _(2)_ Main Purge Filters.
Which ONE of the following competes the statements above?
A. 1. have2. One
B. 1. have2. Two
C. 1. have NOT2. One
D. 1. have NOT2. Two
Page 60 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 61(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor power = 100%• Turbine Bypass Valves (TBV5) in HAND
Current Conditions• 1KU is de-energized
1) The TBVs are _(1).
2) The TBVs _(2)_ manually operable from the Control Room.
Which ONE of the following completes the statements above?
A. 1. closed2. are
B. 1. 50% open2. are
C. 1. closed2. are NOT
D. 1. 50% open2. are NOT
Page 61 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 62
(1 point)
Given the fouowing Unit 1 conditions:
0359:45• Reactor power 70% stable• 18 CBP trips
0400:00• Main FDW Pump suction pressure = 235 psig decreasing
0401:00• Main FDW Pump suction pressure = 230 psig decreasing
0401:30• Main FDW Pump suction pressure = 225 psig stable
Based on the above conditions, complete the following statements:
1) Of the times listed above, 1 C-61 (Cond Cooler Bypass Control) will first open at
2) At 0401 :35, the entry conditions for the EOP — (2) — met.
Which ONE of the following completes the statements above?
A. 1. 0400:002. are
B. 1. 0400:002. are NOT
C. 1. 0401:302. are
D. 1, 0401:302. are NOT
Page 62 of 100
Oconee Nuclear Station• 1LT46 ONS SRO NRC ExaminationQuestion: 63
(1 point)
Given the following Unit 1 conditions:• 1A GWD tank release in progress• 1 RIA-37 HIGH alarm actuates• 1SA-8/B9 (Process Monitor Radiation High) actuates
1) Which ONE of the following describes the impact on the Gaseous Waste Disposal(GWD) system?
2) AP/1 8 (Abnormal Release of Radioactivity) _(2)_ required to be performed priorto re-initiating the release?
A. 1. Closes 1A GWD tank inlet AND outlet valves2. is
B. 1. Closes 1A GWD tank inlet AND outlet valves2. is NOT
C. 1. Closes 1A GWD tank outlet valves but does NOT close the 1A GWD tankinlet valves
2. is
D. 1. Closes 1A GWD tank outlet valves but does NOT close the 1A GWD tankinlet valves
2. is NOT
Page 63 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 64
(1 point)
Given the following Unit 1 conditions:• PTIOIAIO23OIOO1, Radiation Monitor Check completed on Unit 1• 1RL’\-57 .75 R/HR
Which ONE of the following is an indication of a satisfactory source check?
A. Alert Alarm Actuation ONLY
B. Alert AND High Alarm Actuation ONLY
C. Area Monitor Fault Alarm Actuation ONLY
D. NO alarms actuate during the source check
Page 64 of 100
Oconee Nuclear StationQuestion: 65(1 point>
1LT46 ONS SRO NRC Examination
LU
DCl)Cl)LU
U
IA Pressure vs. Time
Based on the graph above, which ONE of the following describes the EARLIEST timeat which SA-141 (SA to IA Controller) will automatically open?
A. 1207
B. 1210
C. 1212
D. 1215
100
TIME
1200 1210 1220 1230
Page 65 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExamination
Question: 66(1 point>
Given the following Unit 1 plant conditions:• Reactor Power = 100%• An evolution is about to begin in the Control room in which an annunciator alarm has
been deemed “expected”
In accordance with AD-OP-ALL-bOO (Conduct of Operations)..
1) The CR8 _(1)_ suspend the requirement to verbally announce the alarm.
2) Once the annunciator response procedure has been referenced for an Expected alarm, it_(2)_ required to be reviewed for subsequent alarms received during that shift.
Which ONE of the following completes the statements above?
A. 1. may2. is
B. 1. may2. is NOT
C. 1. may NOT2. is
D. 1. may NOT2. is NOT
Page 66 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExamination
Question: 67(1 point)
( (., ‘.. •. C
N,J
Note: Drawing not representative of actual plant conditions.
Given the following Unit 1 conditions:Initial conditions:
• Time = 0400• Reactor power = 100% decreasing• Control Rod Group 1 Rod 3 = 0% withdrawn
Current conditions:• Time 0430• Reactor power 68% decreasing• 1B1 RCP trips
1) At 0400, the power to which the ICS is running the plant back is displayed in the— (1) — window. (refer to the drawing above)
2) The unit — (2) — automatically stabilize at the required reactor power for plantconditions.
Which ONE of the following completes the statements above?
A. 1. upper2. will
B. 1. upper2. will NOT
C. 1. lower2. will
D. 1. lower2. will NOT
Page 67 of 100
Oconee Nuclear Station1LT46 ONS SRO NRC Examination
Question: 68(1 point)
Given the following plant conditions:• Unit I Reactor power = 100%• Unit 2 Reactor in MODE 3• No events in progress that would require activation of the SSF
In accordance with OMP 2-01 Attachment D (SSF Staffing Requirements)...
1) for the given conditions, a minimum of _(1 )_ Reactor Operators is maintainedwithin the Unit I & 2 Control Room (inside the CAD doors), with the followingpotential exception:
2) if one BOP/SSF operator leaves the Unit I & 2 Control Room for a short period oftime, it is required that _(2)_.
NOTE: Consider the two statements separately; i.e., if it is permissible for theBOP/SSF operator to leave the Control Room for a short time, include thatindividual in the minimum number of the first statement.
Which ONE of the following completes the statements above?
A. 1. three2. a method of communication is established to ensure the BOP/SSF operator
outside the Control Room can be informed if the SSF needs to be activated
B. 1. three2. another qualified licensed operator with no other concurrent duties relieves
the BOP/SSF operator and stays within the Unit 1 & 2 Control Room (insidethe CAD doors) until the first individual returns (if SSF activation notrequired)
C, 1. four2. a method of communication is established to ensure the BOP/SSF operator
outside the Control Room can be informed if the SSF needs to be activated
D. 1. four2. another qualified licensed operator with no other concurrent duties relieves
the BOP/SSF operator and stays within the Unit I & 2 Control Room (insidethe CAD doors) until the first individual returns (if SSF activation notrequired)
Page 68 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 69(1 point)
Given the following Unit 1 conditions:• Startup in progress with extra licensed operators in Control Room• An SRO has been assigned oversight of the startup as the Reactivity Manager• The OATC is training an individual on OJT from License Class
In accordance with AD-OP-ALL-0203 (Reactivity Management)...
1) _(1)_ withdrawal(s) of Safety Rods is/are required to be announced to theReactivity Manger PRIOR to Rod withdrawal.
2) the OATC _(2)_ allowed to peer-check the withdrawal of Safety Rods being doneby the trainee.
Which ONE of the following completes the statements above?
A. 1. ALL2. is
B. 1. ALL2. is NOT
C. 1. ONLY the first2. is
D. 1. ONLYthefirst2. is NOT
Page 69 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 70
(1 point)
Given the following Unit 1 conditions:• Reactor in MODE 5• An electric valve is being tagged closed with its breaker open
In accordance with OMP 1-02 (Rules of Practice)..,
1) When closing the electric valve from the Control Room for the tagout, a peer check_(1) required.
2) Diverse verification of the breaker position in the OPEN position 2) requiredirect observation of the breaker position by opening the breaker cubicle door.
Which ONE of the following completes the statements above?
A. 1.is2. does
B. 1. is2. does NOT
C. 1. is NOT2. does
D. 1. is NOT2. does NOT
Page 70 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 71
(1 point)
Given the following Unit 1 conditions:• Reactor power = 35% stable• RCS Pressure = 2150 psig stable
1) The low Pressurizer level cutoff of Pressurizer heaters occurs when Control Roomindication of Pressurizer level reaches _(1).
2) Based on the above conditions, if Pressurizer level is above the low level cutoffsetpoint and all Pressurizer heaters Manually energized, an RPS trip on high RCSpressure (2) occur.
Which ONE of the following completes the statements above?
ASSUME NO ADDITIONAL OPERATOR ACTIONS
A. 1. 80”2. will
B. 1. 85”2. will
C. 1. 80”2. will NOT
D. 1. 85”2. will NOT
Page 71 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 72
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor in MODE 6• RB Purge in progress
Current conditions:• lRlA-47 (RB Particulate) in HIGH alarm• AP/1 8, Abnormal Release of Radioactivity is initiated
1) RB Purge _(1) automatically terminate.
2) AP/18 (2)_ ensure the evacuation of non-essential personnel from the RB
A. 1. will2. does
B. 1. will2. does NOT
C. 1. will NOT2. does
D. 1. will NOT2. does NOT
Page 72 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 73
(1 point)
Given the following Unit 3 conditions:• 3A GWD gas tank release in progress• Release is at 2/3 Station Limit
1) 1 REA-45 (Norm Vent Gas) High and Alert setpoints will be set at — (1) — thenormal 1/3 Station Limit as listed in PT/O/A/230/OO1 (Radiation Monitor Check).
2) if 3RIA-45 High alarm setpoint is reached, the 3A GWD gas tank release _(2)_AUTOMATICALLY terminate.
Which ONE of the following completes the statements above?
A. 1. double2. will
B. 1. double2. will NOT
C. 1. half2. will
D. 1. half2. will NOT
Page 73 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 74
(1 point)
Given the following Plant conditions:• UnitllOO%• Unit 2 has an event in progress that requires SSF ASW activation
1) In accordance with OMP 2-1 (Duties and Responsibilities of On-Shift OperationsPersonnel), the j1)_ BOP will be dispatched to perform AP/25 (SSFActivation).
2) Prior to leaving the Control Room for the 8SF, AP/25 directs tripping _(2)_RCP(s),
Which ONE of the following completes the statements abàve?
A. 1. Unit 12. ALL
B. 1. Unit 12. all but ONE
C. 1. Unit 22. ALL
D. 1. Unit 22. all but ONE
Page 74 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 75
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor in MODE 6• LPI aligned in NORMAL Mode• RCS level = 75” on LT-5 stable• lB LPI Pump tagged out
Current conditions:• RCS level = 72” on LT-5 decreasing
1) In accordance with OP/11A111041004 (LPI System), the _(1)_ LPI pump will be inoperation?
2) In accordance with AP/26 (Loss of Decay Heat Removal), ALL LPI pumps (2)required to be secured in an effort to identify the leak location?
A. 1.102. are
B. 1.1A2. are
C. 1.1C2. are NOT
D. 1.1A2. are NOT
Page 75 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 76
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• RCS cooldown in progress• RCS temperature = 310 °F slowly decreasing
Current conditions:• Both the IA and lB HPI pumps have failed• AP/14 (Loss of HPI Normal Makeup and/or RCP Seal Injection) in progress• IC HPI pump has been aligned to provide RCS makeup
1) In accordance with OP/1/A/1104/002 (HPI System), aligning the 1C HPI pump asthe ROS Makeup pump _(1)_ require the 1HP-120 Travel Stop to be re-adjustedbefore considering it OPERABLE for LTOP?
2) In accordance with the basis of Tech Spec 3.412 (LTOP), opening the breakers for1HP-409 and 1HP-410 _(2)_ required to “deactivate” the 1A HPI train.
Which ONE of the following completes the statements above?
A. 1. does2. is
B. 1. does2. is NOT
C. 1. does NOT2. is
D, 1. does NOT2. is NOT
Page 76 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 77
(1 point)
Given the following Unit 1 conditions:• Reactor Power = 100%• I RC-4 (PORV Block Valve) is Closed due to minor seat leakage past 1 RC-66• Neither 1 RC-4 nor 1 RC-66 have been Red tagged
1) The RCS pressure setpoint atwhich 1RC-66 will Open is_(1)_psig.
2) In accordance with SLC 16.5.1 (Reactor Coolant System Vents), IRC-4 beingclosed _(2)_ make I RC-66 INOPERABLE.
Which ONE of the following completes the statements above?
A. 1. 24502. does
B. 1. 24502. does NOT
C. 1. 25002. does
D. 1. 25002. does NOT
Page 77 of 100
Oconee Nuclear Station• IL T46 ONS SRO NRC ExaminationQuestion: 78
(1 point)
Given the following Unit I conditions:Time 1200
• SGTR tab in progress• Natural Circulation cooldown approved by management and in progress
o Core SCM = 0°F stableo Both loop SCM = 14°F slowly increasing
Time 1230• RVLIS indicates:
o 1A Hot Leg level = 600” stableo 1 B Hot Leg level = 585” stable
1) Based on the conditions at 1200, EOP Enclosure 5.6 (RCP Restart) (1) beutilized to restart a RCP.
2) If EOP Enclosure 5.6 is being used at 1230, pressurizer level must be at least> _(2)_ inches.
Which ONE of the following completes the statements above?
A. 1. can2. 100
B. 1. can NOT2. 100
C. 1. can2. 200
D. 1,canNOT2. 200
Page 78 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaininationQuestion: 79
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor Power = 100%• 1 KVIC power supply is transferred to 1 KRB in support of Maintenance on 1 DIC
inverter
Current conditions:• 1 DIC inverter work is completed and it is ready to be aligned to 1 KVIC, but NO
electrical alignments have been made
1) In accordance with the basis of Tech Spec 3&.6(1rwooro Oporating),- 1 KVICPanelboard is (1) . Vj
.8.2) In accordance with the basis of Tech Spec ,-&.S-(Dist4bution Sys ems-Operating)----- 12/iT?’
the 1 DIC Inverter is _(2)_.
Which ONE of the following completes the statements above?
A. 1. OPERABLE2. OPERABLE
B. 1. OPERABLE2. INOPERABLE
C. 1. INOPERABLE2. OPERABLE
D. 1. INOPERABLE2. INOPERABLE
Page 79 of 100
Oconee Nuclear Station• IL T46 ONS SRO NRC ExaminationQuestion: 80
(1 point)
Given the following Unit 1 conditions:• Reactor power = 100%• SOP and OATC are only RO’s available• Degrading instrument air pressure results in a manual Reactor Trip in
accordance with AP/22 (Loss of Instrument Air)• During the transient, indications of a Main Steam Line Break (MSLB) were
observed• RCS pressure decreased to 1400 psig and then began to increase
1) In accordance with OMP 1-18 (Implementation Standard During Abnormal andEmergency Events) the Procedure Director can direct that AP122 be performed inparallel with the EOP _(1 )_.
2) In accordance with Rule 5 (Main Steam Line Break) HPI can be throttled oncePressurizer level has returned to — (2)
Which ONE of the following completes the statements above?
A. 1 immediately after Immediate Manual Actions and Symptoms Check arecompleted
2. on scale and increasing
B. 1. immediately after Immediate Manual Actions and Symptoms Check arecompleted
2. >lO0inches
C. 1. ONLY after RuleS (Main Steam Line Break) and EOP Enclosure 5.1 (ESActuation) have been completed
2. on scale and increasing
D. 1. ONLY after Rule 5 (Main Steam Line Break) and EOP Enclosure 5.1 (ESActuation) have been completed
2. >100 inches
Page 80 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 81
(1 point)
Given the following Unit I conditions:• Reactor Power 45% stable• AP/34 (Generator Grid Disturbance) in progress• Generator Output = 350 MWe• Hydrogen pressure = 60 psig
In accordance with AP/34,
1) The MAXIMUM limit on MVARs is approximately (1).
2) if operation in the acceptable region of the Generator Capability Curve cannot bemaintained, following required actions in AP134, the next required proceduretransition is to initiate _(2)_.
Which ONE of the following completes the statements above?
REFERENCE PROVIDED
A. 1. 7252. Unit 1 EOP
B. 1. 7252. AP/1 (Unit Runback)
C. 1. 4252. Unit 1 EOP
D. 1. 4252. AP/1 (Unit Runback)
Page 81 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExamination
Question: 82(1 point)
Given the following Unit 1 conditions:Time = 1200:
• Reactor power = 85% stable• DeftaTcinHAND
Time 1210:• ICS runback in progress• Reactor power as indicated below
— .A A A A
125 126+60
125+60
125
100 +40 100 *40 100 .40 100 +40
80 +20 80 +20 80 +20 80 +20
60 0 60 0 60 0 60 0
40 20 40 -20E 40 -20 40 -20k
20-40 20-40 20-40 20-40
0 .60 60 0 60 0 60V V V V
/ MB / IBM / 1MM / MM
POWER RANGE NI’S
1) Which ONE of the following describes the reason for the lOS runback?
2> At Time = 1210 the MINIMUM value of QPT that will result in exceeding the limitsprovided by Tech Spec 3.2.3 (Quadrant Power Tilt> is j2)_?
REFERENCE PROVIDED
A. 1. Dropped Control Rod2. >3.50
B. 1. Dropped Control Rod2. >7.11
C. 1.RCPtrip2. >3.50
D. 1.RCPtrip2. >7.11
Page 82 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExarnination
Question: 83(1 point)
Given the following Unit 1 conditions:Time = 0400
• Reactor has been tripped due to SGTR in the 1A SG
Time 0430• Feedwater to the 1A SG is isolated• 1A SG level = 273 inches XSUR increasing• 1 B SG level = 30 inches XSUR stable
Time = 0500• 1A SG level = 293 inches XSUR increasing
Time = 0530• IA SG reaches the Water in Steam Line Level
In accordance with the SGTR tab:
1) At 0500, operators (1) required to perform EOP Enclosure 5.22 (SGB lowdown).
2) At 0530, operators are required to _(2) steaming the 1A SG.
Which ONE of the following completes the statements above?
A. 1. are NOT2. continue
B. 1. are NOT2, stop
C. 1. are2. continue
D. 1. are2. stop
Page 83 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExamination
Question: 84(1 point)
Given the following Unit I conditions:Initial conditions:
• Time = 0400• Reactor power = 80% stable• Control Rods Group 7 = 83% withdrawn• Group 7 Rod 3 will not move and is declared INOPERABLE
Current conditions:• Time = 0500• Reactor power = 80% stable• Group 7 Control Rods = 61% withdrawn
In accordance with Tech Spec 3.2.1 (Regulating Rod Position Limits>, if the aboveconditions do not change the reactor is required to be in MODE 3 not later than
___?
REFERENCE PROVIDED
A. 1600
B. 1700
C. 1800
D. 1900
Page 84 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 85
(1 point>
Given the following Unit 1 conditions:• Reactor power = 100%• Breaker Status
o ACB 4 Closedo PCB8-Openo PCB9-Open
• SA-2, C-i KEOWEE PCB 9 is in alarm• SA-2, B-i DACUS BL. KEOWEE TIE PCB 8 is in alarm
1) Keowee Hydro Unit-2 _(1) be started in AUTOMATIC (NOT Emergency start)from the Control Room.
2) In accordance with the basis of Tech Spec 3.8.1 (AC Systems-Operating), KeoweeHydro Unit-i is currently _(2).
Which ONE of the following completes the statements above?
A. 1. can2. OPERABLE
B. 1. can2. INOPERABLE
C. 1. can NOT2. OPERABLE
D. 1. can NOT2. INOPERABLE
Page 85 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExarninationQuestion: 86
(1 point)
Given the following Unit 1 plant conditions:• RCS temperature = 240°F• RCS pressure = 260 psig• No RCS Vent Paths are open• HPI has been deactivated• 1A and 1 B OFT pressure = 500 psig• 1CF-1 and 1CF-2 Closed and Breakers White Tagged Opened• Pressurizer level 235 inches stable• 000ldown to Mode 5 in progress at 20°F/Hr
Which ONE of the following describes the impact of this condition, and the actionrequired?
REFERENCE PROVIDED
A. RCS pressure and temperature exceed the limits that ensure brittle fractureprevention in accordance with TS 3.4.3 RCS Pressure and Temperature (PT)Limits;Establish an RCS Vent Path or dedicated LTOP Operator.
B. RCS pressure and temperature exceed the limits that ensure brittle fractureprevention in accordance with TS 3.4.3 RCS Pressure and Temperature (PT)Limits;Restore RCS Pressure and Temperature to within limits in 30 minutes or less
C. Administrative controls (Train 2) for an LTOP event are lost;Establish an RCS Vent Path or dedicated LTOP Operator in accordance withTS 3.4.12 Low Temperature Over Pressure Protection
D. Administrative controls (Train 2) for an LTOP event are lost;Depressurize CFTs to less than RCS pressure within 1 hour in accordancewith TS 3.4.12 Low Temperature Over Pressure Protection.
Page 86 of 100
Oconee Nuclear Station* 1LT46 ONSSRONRCExaminatjonQuestion: 87
(1 point)
Given the following Unit 1 conditions:Time = 0600
• Reactor power = 90%• RPS Channel B High RB pressure fails HIGH• RPS Channel B is Placed in Manual Bypass
Time = 0800• RPS Channel C High RB pressure fails LOW
Time = 0815• RPS Channel C placed in TRIP
Time = 0830• RPS Channel A High RB pressure fails LOW
At 0830 the plant operators are
Which ONE of the following completes the statement above?
REFERENCE PROVIDED
A. NOT required to enter a CONDITION of Tech Spec 3.3.1 (RPSInstrumentation>; the reactor has automatically tripped and TS 13.1 no longerapplies
B. Required to enter/have entered CONDITION A of Tech Spec 3.3.1 ONLY
C. Required to enter/have entered CONDITIONs B and C of Tech Spec 3.3.1ONLY
D. Required to enter/have entered CONDITIONs A, B, and C of Tech Spec 3.3.1
Page 87 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 88
(1 point)
Given the following Unit I conditions:• Reactor Power= 100%• While performing SR 3352, Manual ES Setpoint Verification, SPOC
determines that Reactor Building Pressure High “as found” setpoints to be asfollows:A=353 psigB = 404 psigC 409 psig
1) The Actual Setpoint for ES RB Pressure High is (1)_ psig.
2) Operators (2) required to enter Tech Spec 3.3.5 (ESPS Input Instrumentation)CONDON B.
Which ONE of the following completes the statement above?
REFERENCE PROVIDED
A. 1. 3.02. are
B. 1. 3.02. are NOT
C. 1. 3.52. are
D. 1. 3,52. are NOT
Page 88 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 89
(1 point)
Given the following Unit 2 conditions:• Startup in progress• Reactor in MODE 3• 2A RBS pump inoperable
1) Tech Spec 36.5 (Reactor Building Spray and Cooling Systems) LCO (1) met.
2) When Tech Spec 365 LCO is NOT met, Unit 2 entry into MODE 2 _(2)_ allowedonce ALL additional requirements specified in the associated basis are satisfied.
Which ONE of the following completes the above statement?
A. 1. is2. is
B. 1. is2. is NOT
C. 1. is NOT2is
D. 1. is NOT2. is NOT
Page 89 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 90
(1 point)
Given the following Unit I conditions:Time 0700
• Reactor power = 75% stable• 1A RBCU INOPERABLE
Time = 0800• 1SAI9 A-6 REACTOR BUILDING NORMAL SUMP LEVEL HIGH/LOW in alarm• 10 RBCU flow indications
o A Flow 270 gpmo Inlet Flow = 560 gpm
Time = 0810• 1LPSW-22 (IC RBCU INLET) and 1LPSW-24 (RBCU 10 OUTLET) are closed• RB Sump level has stopped increasing
1) At 0800, 1SAI9 D-9 RBCU C COOLER RUPTURE _(1)_ be in alarm.
2) At 0810, Containment is (2) in accordance with Tech Spec 3.6.1(Containment).
Which ONE of the following completes the statements above?
A. 1. should2. OPERABLE
B. 1. should2. INOPERABLE
C. 1. should NOT2. OPERABLE
D. 1. should NOT2. INOPERABLE
Page 90 of 100
Oconee Nuclear Station• 1LT46 ONS SRO NRC ExaminationQuestion: 91
(1 point)
Given the following Unit 1 conditions:Time 1200:
• Reactor startup in progress• Reactor power = 6E-3% stable on all WR Ni’s• 1 Nl1 and 1 NI-3 Source Range Channels are unavailable
Time = 1205:• 1 Nl-2 Source Range power supply fails
1) 1NI-3 is located in RPS channel _(1)_.
2) At Time = 1205, Tech Specs (2) allow the power increase to continue togreater than 5% power.
Which ONE of the following completes the statements above?
A. 1.B2. does
B. 1.B2. does NOT
C. 1.C2. does
D. 1.C2. does NOT
Page 91 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 92
(1 point)
Given the following Unit 3 conditions:• ReactorinMODE6• Core offload in progress• Main Fuel Bridge is withdrawing a fuel assembly
1) A loss of the _(1)_ interlock would increase the risk of fuel assembly damageduring withdrawal.
2) In accordance with MP/01A115001009 (Reactor Bridge Operation), _(2) mustauthorize bypassing the above interlock.
Which ONE of the following completes the statement above?
A. 1. Fuel Overload (TS-1)2. BOTH the Fuel Handling Supervisor AND the Refueling SRO
B. 1. Fuel Overload (TS-1)2. EITHER the Fuel Handling Supervisor OR the Refueling SRO
C. 1. Fuel Hoist Up/Down (TS-2)2. BOTH the Fuel Handling Supervisor AND the Refueling SRO
D. 1. Fuel Hoist Up/Down (TS-2)2. EITHER the Fuel Handling Supervisor OR the Refueling SRO
Page 92 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 93
(1 point)
Given the following Unit 1 conditions:Time = 1200
• ALL Main And Emergency feedwater pumps have been lost• LOHT tab has been initiated
Time = 1205• Condensate Booster Pump Feed is being aligned in accordance with Rule 3• Increasing RCS temperature results in 1A Core SCM = 0°F
At Time = 1205:
1) Performance of Rule 4 _(1)_ required.
2) Transfer to the LOSCM tab (2)_ required.
Which ONE of the following completes the statements above?
A. 1. is2. is
B. 1. is2. is NOT
C. 1. isNOT2. is
D. 1. is NOT2. is NOT
Page 93 of 100
Oconee Nuclear StationILT46 ONSSRONRCExaminationQuest,on: 94
(1 point)
Given the following Unit 1 conditions:• Maintenance is being performed on Unit 1 condensate system• The clearance for the section of piping connected to the component is such that
the piping can be vented but not drained.
In accordance with SOMP 2-1 (Safety Tagging And Configuration Control)...
1) An SRO with an “Inactive” license _(1)_ allowed to sign the Work Order TaskAssignment (WOTA) Ready for Work.
2) Zero Energy Comments (2)_ have to be entered into ST-2 prior to setting theWOTA Ready for Work.
Which ONE of the following completes the statements above?
A. 1. is2. do
B. 1.is2. do NOT
C. 1. is NOT2. do
D. 1. is NOT2. do NOT
Page 94 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 95
(1 point)
Given the following Unit I conditions:• SGTR tab in progress• RCS temperature = 530°F stable• 1A SG isolated• 3 RCP’s operating• HPI pump suction aligned to BWST• Group 3 Rod 2 100% withdrawn
1) _(1) _tab of the EOP will be utilized to cooldown to LPI,
2) The EOP tab above states that the cooldown plateau allowed prior to performing aShutdown Margin verification is _(2) °F.
Which ONE of the following completes the statements above?
A. 1.SGTR2. 240
B. 1.SGTR2. 450
C. 1.FCD2. 240
D. 1.FCD2. 450
Page 95 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 96
(1 point>
Given the following Unit 1 conditions:• Unit is stable in MODE 3 following an unexpected plant trip one hour ago• Operators have just entered a CONDITION of Tech Spec 3.1.1 (Shutdown
Margin (SDM)) that requires boration be initiated in a short time
1) The basis document for Tech Spec 3.1.1 specifies that operators should use the_(1)_ or the Borated Water Storage Tank (BWST) as the source of boration.
2) The Unit 1 COLR states that BWST boron concentration shall be greater than_(2) ppm.
Which ONE of the following completes the above statements?
A. 1. A Bleed Holdup Tank (BHUT)2. 2220
B. 1. ABleedHoldupTank(BHUT)2. 2500
C. 1. Concentrated Boric Acid Storage Tank (CBAST)2. 2220
0. 1. Concentrated Boric Acid Storage Tank (CBAST)2. 2500
Page 96 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 97
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Defueling in progress• 1 RIA-3 (Fuel Transfer Canal Monitor) = 4 mr/hr stable• Main Fuel Bridge Area Monitor = 6 mr/hr stable
Current conditions:• iRL-3 local reading = 0 mr/hr• 1 RIA-3 View Node indication is magenta
The Refueling SRO will determine that Fuel Handling activities in the Reactor Buildingmay
_______
in accordance with OP/i /AI1 502/007 (Operations Defueli ng/Refueli ngResponsibilities)?
Which ONE of the following completes the statement above?
A. NOT continue until a portable area monitor with local alarm capability is inplace.
B. continue because only the Main Fuel Bridge Area Monitor is required.
C. NOT continue until continuous RP coverage is present on the Main FuelBridge.
D. continue provided 1 RLA-49 (RB Normal Gas) is OPERABLE.
Page 97 of 100
Oconee Nuclear Station• 1LT46 ONS SRO NRC ExaminationQuestion: 98
(1 point)
Given the following plant conditions:• Shift is preparing for ONE (1) GWR release of the 1A Gaseous Waste Disposal
(GWD) tank at the 1/3 Station Limit• The release will be through the P/A/C filter• 1A GWD tank holdup time is 41 days
1) The Shift Manager/OSM _(1)_ the MINIMUM level of authority for approval of theabove release in accordance with OPI1-2/A111041018 (GWD System).
2) The SLC basis for limiting the Curie content of the GWD Tanks limits Whole Bodyexposure of an individual at the nearest exclusion boundary to (2).
Which ONE of the following completes the statements above?
A. 1.is2. 0.5 Rem in the event of a GWD tank rupture.
B. 1. is2. 100 mrem during a planned GWD tank release.
C. 1. is NOT2. 0.5 Rem in the event of a GWD tank rupture.
D. 1. is NOT2. 100 mrem during a planned GWD tank release.
Page 98 of 100
Oconee Nuclear Station1LT46 ONSSRONRCExaminationQuestion: 99
(1 point)
Given the following Unit 1 conditions:Initial conditions:
• Reactor Power = 100%
Current conditions:• Station Blackout occurs• A large RCS leak that is greater than normal makeup capability has occurred
While waiting on power to be restored to the Unit 1 4160v buses...
1) the actions performed by the operators dispatched to the SSF_(1)_ be able tomitigate the RCS leak.
2) Rule 2 (Loss of SCM) _(2) required to be performed in parallel with theBlackout tab if ALL subcooling margins indicate 0°F.
Which ONE of the following completes the statements above?
A. 1. will2. is
B. 1. will2. is NOT
C. 1. will NOT2. is
D. 1. will NOT2. is NOT
Page 99 of 100
Oconee Nuclear Station• 1LT46 ONSSRONRCExaminationQuestion: 100
(1 point)
Given the following Unit I conditions:Time 1200
• Unit shutting down due to a 30 gpm tube leak in 1A SG
Time = 1203• Unit trips due to a loss of Main Feedwater• Emergency Feedwater is NOT available
Time 1207• AO reports one Main Steam Relief Valve on the 1 B SG stuck open• Unit 2 TDEFWP aligned and feeding Unit 1 Steam Generators• 1A SG tube leak = 200 gpm stable
1) The conditions present at 1200 (1) require an emergency classificationwithin 15 minutes.
2) At time = 1207 the emergency classification is — (2)
Assume no additional failures occur AND that Emergency CoordinatorJudgment is NOT used as a reason for classification.
Which ONE of the following completes the statements above?
REFERENCE PROVIDED
A. 1. would2. ALERT
B. 1. would2. SITE AREA EMERGENCY
C. 1. would NOT2. ALERT
D. 1. would NOT2. SITE AREA EMERGENCY
Page 100 of 100
Examination KEYfor: 1LT46 ONS SRO NRC Examin
Question AnswerNumber
1 B
2 B
3 C
4 B
5 B
6 C
7 D
8 B
9 D
10 A
11 D
12 A
13 A
14 A
15 A
16 D
17 C
18 A
19 C
20 C
21 C
22 D
23 A
24 A
25 A
Printed 12/18/2014 10:51:07 AM Page 1 of4
Examination KEYfor: 1LT46 ONS SRO NRC Examin
Question AnswerNumber
26 A
27 B
28 B
29 B
30 D
31 D
32 D
33 C
34 C
35 D
36 C
37 A
38 C V
39 D
40 C
41 C
42 BV
43 BV
44 C
45 DV
46 C
47 B V
48 B
49 A
50 B
Printed 12/18/2014 10:51:0 7 AM Page 2 of 4
Examination KEYfor: 1LT46 ONS SRO NRC Examin
Question AnswerNumber
51 D
52 D
53 C
54 B
55 D
56 A
57 A
58 D
59 B
60 B
61 A
62 A
63 D
64 D
65 D
66 B
67 D
68 C
69 B
70 D
71 C
72 C
73 D
74 C
75 B
Printed 12/18/2014 10:51:07 AM Page 3 of4
Examination KEYfor: 1LT46 ONS SRO NRC Examin
Question AnswerNumber
76 B
77 B
78 D
79 B
80 C
81 B
82 A
83 D
84 D
85 C
86 C
87 D
88 A
89 A
90 A
91 A
92 A
93 B
94 A
95 B
96 D
97 A
98 C
99 C
100 A
Printed 12/18/2014 10:51:07 AM Page 4 of4
IO
conee
IC
ycle
28j
Pag
e25
of33
ON
EI
0400
-50
Rev
34
105
______
______
_
:10
5
I00
_______
_____
Con
trol
Rod
Posi
tion
Set
po
nts
,
100
95
__
__
__
11In
oper
able
Rod
s4
Pum
DF
low
95
90
________
:•
80
_________
.R
stri
cted
90
85
_______
I
75
__
__
__
__
_
Op
erat
ior
__________
85
80 75 70
__
__
__
:U
nac
cep
tab
le70
_______
Oper
atio
n65
_______________
65
U-
60i
H’
60
c
____
____
____
____
____
____
55a
__
__
__
__
___________
50
__
__
__
__
_____________
Acc
epta
ble
________
500
__
__
__
__
__
________
Oner
atio
n
________
-45
__
__
__
__
_____________
45
4040
351
35
3030
2525
!
20‘
Iii
w:
:20
II
15[i
.I.
15I
10:_
_:
:10
5G
roup
6:
::,
5I
rII5
1-
2535
4555
b575
8595
ij0
Hil
LI
,
o0
1020
3040
5060
7080
9010
00
1020
3040
5060
7080
9010
0
Gro
up5
IGro
up7
Con
trol
Rod
Posi
tion,
%W
D
CO>ci)
CDIc)
cDCD
9wz0
It) 0C) 0 10 0 10 CD 10 0 Ic) 0 IC) C) Ic) CD 10 CD IC) CD If) 0
(3) 0) CO Co N- N- (0 (0 If) It) ct CO CO (N (N IC)
C,)CO‘4-
0
IL) 0 IC) C) IC) C) IC) CD IC) 0 10 C) If) C) IL) C) If) C) 10 C) IC) C)CD C) 0) 0) CL) Cc) N- N- CL) (0 10 10 - CO C’) (N (N — ‘-‘- -
ad % ‘JOM0 -‘°Pèi
D
C0
U)0
•t30
0
C00
ON
EI-
0400
-50
Rev
34
LO
conee
IC
ycle
28P
age
27of
33•10
5
_____
__
__
__
__
__
_______
::IIt
t1t
____________
105
10
0
__
__
__
_
100
Con
trol
RodP
os
tion
Set
poin
ts
_____
951
Inoper
able
Rod
,4
Pum
pF
low
_____
95
90
______
90
8585
8080
75
______
75
70
__
__
__
70
6565
Un
acce
pta
ble
0
60O
pera
tion
60
i55
5500
50
_____
50A
ccep
table
_____
0
_____
-45
Oper
atio
n
______
45
4040
0
35
__
__
__
35
30
______
30
15
2525
2020
15 1010 5
Gro
up6
__
__
__
__
__
__
55
1525
3545
5565
7585
95
______
0
__
__
__
__
__
_______
0
r1
02030
4050
6070
8090
100
jI0
1020
3040
5060
7080
9010
0
-IG
roup
5C
ontr
olR
odPo
sitio
n,%
WD
IGro
up7
105
100 95 90 85 80 75 70 65
U I 50 0 C)
Ct a) a::
40 35 30 25 20 15 10 5 0
Oco
nee
IC
ycle
28
1010
2030
405
06
070
8090
100
Gro
up5
Con
trol
Rod
Posi
tion,
%W
D
ON
EI-
0400
-50
Rev
34P
age
28of
3310
5
100
95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 S 010
1020
3040
5060
7080
901001
Gro
up7
3.2 POWER DISTRIBUTION LIMITS
3.2.1 Regulating Rod Position Limits
Regulating Rod Position Limits3.2.1
LCO 3.2.1 Regulating rod groups shall be within the physical position, sequence, andoverlap limits specified in the COLR.
NOTENot required for any regulating rod positioned to perform SR 3.1.4.2.
APPLICABILITY: MODES 1 and 2.
ACTIONS
CONDITION REQUIRED ACTION COMPLETION TIME
A. Regulating rod groups A.1 Restore regulating rod 2 hourssequence or overlap groups to within limits.requirements not met.
(continued)
OCONEE UNITS 1, 2, & 3 3.2.1-1 Amendment Nos. 300, 300, & 300
Regulating Rod Position Limits3.2.1
ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
B. Regulating rod groups B.1 -NOTE-positioned in restricted Not applicable toor unacceptable region. regulating rod groups
positioned in therestricted region.
Initiate boration to 15 minutesrestore SDM to withinthe limits specified inthe COLR.
AND
B.2.1 Restore regulating 2 hoursrod groups to withinacceptable region.
OR
B.2.2 Reduce THERMAL 2 hoursPOWER to less than orequal to THERMALPOWER allowed byregulating rod groupposition limits.
C. Required Action and C.1 Be in MODE 3. 12 hoursassociated CompletionTime of Condition Aor B not met.
OCONEE UNITS 1, 2, & 3 3.2.1-2 Amendment Nos. 300, 300, & 300
Regulating Rod Position Limits3.2.1
SURVEILLANCE REQUIREMENTS
SURVEILLANCE FREQUENCY
SR 3.2.1.1 Verify regulating rod groups are within the In accordance with thesequence and overlap limits as specified in Surveillance Frequencythe COLR. Control Program
SR 3.2.1.2 Verify regulating rod groups meet the position In accordance with thelimits as specified in the COLR. Surveillance Frequency
Control Program
SR 3.2.1.3 Verify SDM to be within the limit as specified Within 4 hours prior toin the COLR. achieving criticality
OCONEE UNITS 1, 2, & 3 3.2.1-3 Amendment Nos. 372, 374, 373 I
Enclosure 4.31 oP/O/A/1 108/00 1Unit 1 RCS Heatup/Cooldown Curves Page 1 of 9
NOTE: If changes are required to curves in this enclosure, the OAC curves must be updated at thesame time or the OAC curves must be considered not valid. { I }
Enclosure 4.31 oP/O/A/1 108/00!Unit 1 RCS Heatup/Cooldown Curves Page 2 of 9
Notes For Unit 1 Wide Range Cooldown Curve
1. Maintain RCS PIT below and to the right of the 300°F, 250°F, and 200°F Subcooled curves.
2. Maintain RCS PIT above and to the left of the 20°F Subcooled curve.
3. When any number of RCPs are running, maintain RCS PIT above and to the left of the 4 RCPNPSH curve. (See EOP curves for abnormal containment conditions).
4. When a single RCP in a loop is operating, minimize operating time below the <4 RC Pump NPSHcurve. This limits cumulative damage to the single operating pump caused by cavitation due torequired NPSH at high flows.
5. RCS is considered depressurized when all of the following conditions exist:
• RCS temperature <200°F
• RCS pressure < 50 psig
• All RCPs off
6. Use Low Range Curves when either of the following exist:
• RCS pressure is <550 psig
• RCS temperature is <350°F
Heatup/Cooldown Limits
RCS Temp Max Cooldown Rate
T> 270°F 45°F in any 1/2 hour period
140°F < T < 270°F < 20°F in any 1/2 hour period
T < 140°F 45°F in any 1 hour periodRCS depressurized < 45°F in any 1 hour period
Note: PT/1/A/0600/001 (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
RCS Temp Max Heatup Rate {22}
T < 270°F <25°F in any 1/2 hour period
T 270°F <45°F in any 1/2 hour period
Enclosure 4.31
Unit 1 RCS Heatup/Cooldown CurvesOP/O/A/I 108/001Page 3 of 9
Unit 1 Wide Range Cooldown Curve
i-f
p NPSHF
1
0 100 200 300 400 500 600 700
Tcold REACTOR COOLANT TEMPERATURE (°F) UIWRCI) 54 FFPY, Rev. 0
Note: PT/1/A/0600/001 (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
Tcold REACTOR COOLANT TEMPERATURE (°F)0 100 200 300 400 500 600 700
2200
2100
2000
1900
1800
1700
1600
1500
1400
1300
1200
2200
2100
2000
190020°FSUBCOOLD, -
-4-t
I
CC
cj
-I
(ID(ID
z
CC
C
LI I
hop
Ei1000
— 1800
• 1700
T 1300
_____
1000
-w
CC-
(ID
(ID
z
CC
C
ff1-900
800
700
600
500
400
300
200k1t •CPun
900
800
700
600
500
400
300
200
100
0
______
F
___
3OO°FLh I • SUBCOOLEII
100
0-r -
I-- I r ii n
Enclosure 4.31 0PIO/A/1 108/001Unit 1 RCS Heatup/Cooldown Curves Page 4 of 9
Notes For Unit 1 Wide Range Heatup Curve
1. Maintain RCS PIT below and to the right of the 300°F, 250°F, and 200°F Subcooled curves.
2. Maintain RCS PIT above and to the left of the 20°F Subcooled curve.
3. When any number of RCPs are running, maintain RCS PIT above and to the left of the 4 RCPNPSH curve. (See EOP curves for abnormal containment conditions).
4. When a single RCP in a loop is operating, minimize operating time below the <4 RC Pump NPSHcurve. This limits cumulative damage to operating pump caused by cavitation due to requiredNPSH needed at high flows.
5. Use Low Range Curves when either of the following exist:
• RCS pressure is < 550 psig
• RCS temperature is <350°F
Heatup/Cooldown Limits
RCS Temp Max Cooldown Rate {22} RCS Temp Max 1-leatup Rate
T> 270°F <45°F in any 1/2 hour period T < 270°F <25°F in any 1/2 hour period
140°F <T <270°F <20°F in any 112 hour period T> 270°F <45°F in any 1/2 hour period
T < 140°F 45°F in any 1 hour periodRCS depressurized 45°F in any 1 hour period
Note: PT/1/A/0600/001 (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
Enclosure 4.31
Unit 1 RCS Heatup/Cooldown CurvesOP/O/A/1 108/00 1Page 5 of 9
Unit 1 Wide Range Heatup Curve
Tcold REACTOR COOLANT TEMPERATURE (°F)
0 100 200 300 400 500 600 700
Teold REACTOR COOLANT TEMPERATURE (°F)UIWRI-IU 54 EFPV, Rev. 0
Note: PT/1/A/0600/O0l (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
0 100 200 300 400 500 6002200
700
ii hiii:-
2100
2000
1900
1800
1300
1200
1100
CC
c,D
z
CCc-)
p
z
liii ETh1T1 ±
2200
2100
_______
2000
1900C
I1400
++— 1300 <C
______
1200
1100
- _—1000
700
::iE:tE:t:1: I
it
:X
1000 __1_4_!rf.j__I_I iiiii• I
lifi900
800
700
600
500
400
300
200
-1
I—:3;:ii-
-j- 4RCPump NPS1I
•TH IIrJT42
100
0
/-3O0F
HI :rt__
h1 _LII_I’ I •II — —J
i
_____
I
_____
600
500
400
300
200
100
0
__1iIi:: zztLLIf
F
Enclosure 4.31
Unit 1 RCS Heatup/Cooldown CurvesOP/O/A/1 108/00 1Page 6 of 9
[Notes For Unit 1 Low Range Cooldown Curve
1. Curve #1- RCS cooldown limitations.
2. Curve #2- Minimum RCS pressure for RCP operation.
3. Curve #3- Minimum RCS pressure for continuous operation of single RCP in a loop. Minimizeoperating time below this line with single RCP in a loop operating to limit cumulative damage tooperating pump caused by cavitation.
4. Curve #4- Max RCS pressure and temperature for LPI pump initiation.
5. RCS is considered depressurized when all of the following conditions exist:
• RCS temperature <200°F
• RCS pressure < 50 psig
• AIIRCPs off
6. Briefly operating above the LPE pressure curve (#4) or below the RCP NPSH curve (#2) by<40 psig is acceptable while swapping RCPs.
Heatup/Cooldown Limits
f RCS Temp Max Cooldown Rate
T> 270°F < 45°F in any 1/2 hour period
140°F < T < 270°F < 20°F in any 1/2 hour period
T < 140°F < 45°F in any 1 hour periodRCS depressurized < 45°F in any 1 hour period
RCS Temp Max Heatup Rate {22}
T < 270°F <25°F in any 1/2 hour period
T> 270°F <45°F in any 1/2 hour period
Note: PT/1/A/0600/001 (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
Enclosure 4.31
Unit 1 RCS Heatup/Cooldown CurvesOP/O/A/I 108/001Page 7 of 9
Unit 1 Low Range Cookiown Curve
TCOId Reactor Coolant Temperature, °F
TCOd Reactor Coolant Temperature, °F UII.RCD 54 EFPV, Res’. 0
*PZR level restricted to <380 inches when RCS temperature is < 160°F. AND NO HPIPs operating.
Note: PT/I/A/0600/001 (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
1
H±-Hi
0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400
-
—
550
adtubcoc
ZE +
525
500
475
450
425
600
575
550
525
500
475
450
425
0)ci) 4000
a)0) 375C
350
325
300a)
275Cct:
250C-)
2250
200
175
150
125
100
75
50
25
0
0)400
0
a)375 0)
C
350
325 a)D
300a)
275CCa
250 00
C-)225
C.)
200
itF\ 24
I Subcoole - .t—H_._—- -
-
LTOP LIMIT HNHF-t Ii I j rF H- Maintain \f,J__QTrJ. JL_ i!T ‘1 FF PZRLev& LT1Pr1T
iJ’- <22Oinches r—
-
in this area -.. ii..
--— H—’’ —. 2z’ :N:
. ±: . ;..--
.
‘kfH - ‘1-TR-b--’-- ---rI .
-‘:-
-
LTOP LIMIT WE - --
._ Maintain — --
I.PZRLeveI - .
,,., ,-1 . --—. <3lOpnches
.,in this area .
-
175
150
125
100
75
50
I .00 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400
25
Enclosure 4.31
Unit 1 RCS Heatup/Cooldown CurvesOP/O/A/l 108/001Page 8 of 9
Notes For Unit 1 Low Range Heatup Curve
1. Curve #1- RCS heatup limitations.
2. Curve #2- Minimum required RCS pressure for RCP operation.
3. Curve #3- Minimum RCS pressure for continuous operation of single RCP in a loop. Minimizeoperating time below this line with single RCP in a loop operating to limit cumulative damage tooperating pump caused by cavitation.
4. Curve #4- Max RCS pressure and temperature for LPI pump initiation.
5. Briefly operating above the LPI pressure curve (#4) or below the RCP NPSH curve (#2) by<40 psig is acceptable while swapping RCPs.
Heatup/Cooldown Limits
RCS Temp
T>270°F
140°F<T <270°F
T< 140°FRCS depressurized
Max Cooldown Rate {22}
45°F in any 1/2 hour period
<20°F in any 1/2 hour period
45°F in any 1 hour period<45°F in any 1 hour period
RCS Temp Max Fleatup Rate
T < 270°F <25°F in any 1/2 hour period
T270°F <45°F in any 1/2 hour period
Note: PT/1/A/0600/001 (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
Enclosure 4.31
Unit 1 RCS Heatup/Cooldown CurvesOP/O/A/l 108/001Page 9 of 9
C)(I)C.
0)C)C(‘3
C-J0)
DC,)C,)0)
0
C(‘300
C-)
00(‘30)
Unit I Low Range Heatup Curve
TCOld Reactor Coolant Temperature, 5F
200
175
150
125
100
75
50
25
0
TCOId Reactor Coolant Temperature, °F UILRHU 54 EFPY, Rev. 0
*PZR level restricted to <380 inches when RCS temperature is < 160°F, AND NO HPIPs operating.
Note: PT/1/A/0600/001 (Periodic Instrument Surveillance) contains Enclosure (RCS Pressure, Temperature, Heatupand Cooldown Surveillance Sheet) for conditions when RCS pressure/temperature are changing.
600
575
0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400
__
600
575
550
525
500
475
450
425
C)
400
ci)375
350
325
300ci)
275C(‘3
250 oC
C-)225
C)(‘30)
550r
uucieaf
525 - . - . .. —i I - —
—4,. -I-
500 - —-.
..t..i. fjl475 . - -
.3 -i Ii_
—.- .
.
450 - - , —
425--
. 250°F—
: Subcooled400 — - .
— - —
375 —rft--.
H- i2-
350-‘
-- - --
325-— - - . —
:- L4’ -J -
300 350F — ,.- . -
Subcooled- - . . . . . — . -
275 - rf —
r -
it! -- . .
250 .E -f225 —
. LTOP Limit . - . -
,. i- . —
. Maintain- lEE
200 I 300 F — PZR Level-
. Subcooled v 220 inches -.
. I . -, in this area — — —175I-
lI . -
150 .:
ioo’:1
+
] : -. ‘Top Limit- I
,
- Maintain—
50 t-’- 4-t — - — PZR Level _
. . . --. <3l0inches —
25 - — -
- is this area -
-:.ZL . *- .,. .
0 E.Z L_ --
0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400
LTOP System3.4.12
3.4 REACTOR COOLANT SYSTEM (RCS)
3.4.12 Low Temperature Overpressure Protection (LTOP) System
LCO 3.4.12 An LTOP System shall be OPERABLE with high pressure injection (HPI)deactivated, and the core flood tanks (CFTs) isolated and:
a. An OPERABLE power operated relief valve (PORV) with a liftsetpoint of 535 psig; and
b. Administrative controls implemented that assure 10 minutes areavailable for operator action to mitigate an LTOP event.
APPLICABILITY: MODE 3 when any RCS cold leg temperature is 325°F,MODES 4, 5, and 6 when an RCS vent path capable of mitigating themost limiting LTOP event is not open.
NOTES1. CFT isolation is only required when CFT pressure is greater than
or equal to the maximum RCS pressure for the existing RCStemperature allowed by the pressure and temperature limit curvesprovided in Specification 3.4.3.
2. The PORV is not required to be OPERABLE when no HPI pumpsare running and RCS pressure < 100 psig.
OCONEE UNITS 1,2, & 3 3.4.12-1 Amendment Nos. 307, 307, & 307
ACTIONS
LTOP System3.4.12
(continued)
CONDITION REQUIRED ACTION COMPLETION TIME
A. HPI activated. A.1 Initiate action to Immediatelydeactivate HPI.
B. A CFT not isolated B.1 Isolate affected OFT. 1 hourwhen OFT pressure isgreater than or equal tothe maximum ROSpressure for existingtemperature allowed bySpecification 3.4.3.
C. Required Action and 0.1 Be in MODE 4 with 12 hoursassociated Completion RCS temperatureTime of Condition B not > 200°F.met.
OR
0.2 Depressurize affected 12 hoursOFT to < 373 psig.
D. PORV inoperable. D.1 Restore PORV to 1 hourOPERABLE status.
E. Required Action and E.1 Be in MODE 3 with 23 hoursassociated Completion RCS averageTime of Condition D not temperaturemet. > 325° F.
OR
E.2 Depressurize RCS to 35 hours< 100 psig.
OCONEE UNITS 1, 2, & 3 3.4.12-2 Amendment Nos. 307, 307, & 307 I
LTOP System3.4.12
SURVEILLANCE REQUIREMENTS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
F. Administrative Controls F.1 Provide compensatory 4 hoursthat assure measures to monitor
10 minutes are for initiation of anavailable to mitigate LTOP event.consequences of anLTOP event notimplemented.
G. Required Action and G.1 Depressurize the RCS 12 hoursassociated Completion and establish an RCSTime of Condition F not vent path capable ofmet. mitigating the most
limiting LTOP event.
H. Administrative Controls H.1 Restore system to 1 hourthat assure OPERABLE status.
10 minutes areavailable to mitigate the Q!consequences of anLTOP event not H.2 Depressurize RCS and 12 hoursimplemented and establish RCS ventPORV inoperable, path capable of
mitigating the mostOR limiting LTOP event.
LTOP Systeminoperable for anyreason other thanCondition A throughCondition G.
SURVEILLANCE REQUIREMENTS
OCONEE UNITS 1,2, &3 3.4.12-3 Amendment Nos. 372, 374, 373
RPS Instrumentation3.3.1
3.3 INSTRUMENTATION
3.3.1 Reactor Protective System (RPS) Instrumentation
LCO 3.3.1 Three channels of RPS instrumentation for each Function in Table 3.3.1-1shall be OPERABLE.
APPLICABILITY: According to Table 3.3.1-1
ACTIONS
CONDITION REQUIRED ACTION COMPLETION TIME
A. One required channel A.1 Place channel in trip. 1 hour for Unit(s) withinoperable. RPS digital upgrade not
complete
OR
4 hours for Unit(s) withRPS digital upgradecomplete
B. Two or more required B.1 Enter the Condition Immediatelychannels inoperable, referenced in
Table 3.3.1-1 for theOR Function.
Required Action andassociated CompletionTime of Condition A notmet.
(continued)
OCONEE UNITS 1, 2, & 3 3.3.1-1 Amendment Nos. 366, 368 & 367
RPS Instrumentation3.3.1
ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
C. As required by Ci Be in MODE 3. 12 hoursRequired Action B.1and referenced in ANDTable 3.3.1-1.
C.2 Open all control rod 12 hoursdrive (CRD) tripbreakers.
D. As required by D.1 Open all CRD trip 6 hoursRequired Action B.1 breakers.and referenced inTable 3.3.1-1.
E. As required by El Reduce THERMAL 6 hoursRequired Action B.1 POWER < 30% RTP.and referenced inTable 3.3.1-1.
F. As required by F.1 Reduce THERMAL 12 hoursRequired Action B.1 POWER < 2% RTP.and referenced inTable 3.3.1-1.
OCONEE UNITS 1, 2, & 3 3.3.1-2 Amendment Nos. 366, 368 & 367
RPS Instrumentation3.3.1
SURVEILLANCE REQUIREMENTS
NOTERefer to Table 3.3.1-1 to determine which SRs apply to each RPS Function.
SURVEILLANCE FREQUENCY
SR 3.3.1.1 Perform CHANNEL CHECK. In accordance with theSurveillance FrequencyControl Program
SR 3.3.1.2 NOTENot required to be performed until 24 hoursafter THERMAL POWER is 15% RTP.
Compare results of calorimetric heat balance In accordance with thecalculation to the power range channel output Surveillance Frequencyand adjust power range channel output if Control Programcalorimetric exceeds power range channeloutput by 2% RTP.
SR 3.3.1.3 NOTENot required to be performed until 24 hoursafter THERMAL POWER is 15% RTP.
Compare out of core measured AXIAL In accordance with thePOWER IMBALANCE (API0) to incore Surveillance Frequencymeasured AXIAL POWER IMBALANCE (API1) Control Programas follows:
(RTP!TP)(API0— (CS X API1)) = imbalanceerror
where CS is CORRELATION SLOPE
Adjust power range channel output if theabsolute value of imbalance error is
2% RTP.
(continued)
OCONEE UNITS 1, 2, & 3 3.3.1-3 Amendment Nos. 372, 374, 373
RPS Instrumentation3.3.1
SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY
SR 3.3.1.4 NOTENot applicable to Unit(s) with RPS digitalupgrade complete.
Perform CHANNEL FUNCTIONAL TEST. In accordance with theSurveillance FrequencyControl Program
SR 3.3.1.5 NOTEOnly applicable to Unit(s) with RPS digitalupgrade complete.
Manually verify the setpoints are correct. In accordance with theSurveillance FrequencyControl Program
SR 3.3.1.6 NOTEOnly applicable to Unit(s) with RPS digitalupgrade complete.
Manually actuate the output channel In accordance with theinterposing relays. Surveillance Frequency
Control Program
SR 3.3.1.7 NOTENeutron detectors are excluded fromCHANNEL CALIBRATION.
Perform CHANNEL CALIBRATION. In accordance with theSurveillance FrequencyControl Program
OCONEE UNITS 1,2, &3 3.3.1-4 Amendment Nos. 372, 374, 373
RPS Instrumentation3.3.1
Table 331-1 (page 1 of 2)Reactor Protective System Instrumentation
APPLICABLE CONDITIONSMODES OR REFERENCED
OTHER FROMSPECIFIED REQUIRED SURVEILLANCE ALLOWABLE
FUNCTION CONDITIONS ACTION B.1 REQUIREMENTS VALUE
6. Reactor Building High Pressure 1,2,3 C SR 3.3.1.1 4 psigSR 3.3.1.4SR 3.3.1.5SR 3.3.1.6SR 3.3.1.7
OCONEE UNITS 1,2, & 3 3.3.1-5 Amendment Nos. 366, 368 & 367
Table 3.3.1-1 (page 2 of 2)Reactor Protective System Instrumentation
APPLICABLE CONDITIONSMODES OR REFERENCED
OTHER FROMSPECIFIED REQUIRED
CONDITIONS ACTION B.1
(a) When not in shutdown bypass operation.
(b) During shutdown bypass operation with any CRD trip breakers in the closed position and the CRD System capable of rodwithdrawal.
(c) With any CRD trip breaker in the closed position and the CRD System capable of rod withdrawal.
FUNCTION
RPS Instrumentation3.31
SURVEILLANCE ALLOWABLEREQUIREMENTS VALUE
OCONEE UNITS 1,2, &3 3.3.1-6 Amendment Nos. 366, 368 & 367
ESPS Input Instrumentation3.3.5
3.3 INSTRUMENTATION
3.3.5 Engineered Safeguards Protective System (ESPS) Input Instrumentation
LCO 3.3.5 Three channels of ESPS input instrumentation for each Parameter inTable 3.3.5-1 shall be OPERABLE.
APPLICABILITY: According to Table 3.3.5-1.
ACTIONS
NOTESeparate Condition entry is allowed for each Parameter.
CONDITION REQUIRED ACTION COMPLETION TIME
A. One or more A.1 Place channel in trip. 1 hour for Unit(s) withParameters with one ESPS digital upgrade notchannel inoperable, complete
OR
4 hours for Unit(s) withESPS digital upgradecomplete
B. One or more B.1 Be in MODE 3. 12 hoursParameters with two ormore channels ANDinoperable.
B.2.1 NOTEQE Only required for RCS
Pressure — Low.Required Action andassociated CompletionTime not met. Reduce RCS pressure 36 hours
< 1750 psig.
AND
(continued)
OCONEE UNITS 1, 2, & 3 3.3.5-1 Amendment Nos. 366, 368 & 367
ESPS Input Instrumentation3.3.5
CONDITION REQUIRED ACTION COMPLETION TIME
B. (continued) B.2.2 NOTEOnly required for RCSPressure — Low Low.
Reduce RCS pressure 36 hours< 900 psig.
AND
B.2.3 NOTEOnly required forReactor BuildingPressure — High andHigh High.
Be in MODE 5. 36 hours
SURVEILLANCE REQUIREMENTS
SURVEILLANCE FREQUENCY
SR 3.3.5.1 Perform CHANNEL CHECK. In accordance with theSurveillance FrequencyControl Program
(continued)
OCONEE UNITS 1, 2, & 3 3.3.5-2 Amendment Nos. 372, 374, 373
ACTIONS
ESPS Input Instrumentationa3.5
SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY
SR 3.3.5.2 NOTEOnly applicable to Unit(s) with ESPS digitalupgrade complete.
Manually verify that the setpoints are correct. In accordance with theSurveillance FrequencyControl Program
SR 3.3.5.3 NOTENot applicable to Unit(s) with ESPS digitalupgrade complete.
Perform CHANNEL FUNCTIONAL TEST. In accordance with theSurveillance FrequencyControl Program
SR 3.3.5.4 Perform CHANNEL CALIBRATION. In accordance with theSurveillance FrequencyControl Program
OCONEE UNITS 1, 2, & 3 3.3.5-3 Amendment Nos. 372, 374, 373 I
ESPS Input Instrumentation I3.3.5
Table 3.3.5-1 (page 1 of 1)Engineered Safeguards Protective System Input Instrumentation I
APPLICABLEMODES OR OTHER SPECIFIED ALLOWABLE
PARAMETER CONDITIONS VALUE
1. Reactor Coolant System Pressure — Low 1750 psig 1590 psig
2. Reactor Coolant System Pressure — Low Low 900 psig 500 psig
3. Reactor Building (RB) Pressure — High 12,3,4 4 psig
4. Reactor Building Pressure — High High 12,3,4 S 15 psig
OCONEE UNITS 1, 2, & 3 3.3.5-4 Amendment Nos. 366, 368 & 367
Duke Energy -- - -
- Procedure No. --
Oconee Nuclear Station RP/O/A/1 000/001
Emergency Classification Revision No.
001
Electronic Reference No.
Reference Use 0p009A63
PERFORMANCE I* * * * * * * * * * UNCONTROLLED FORPRTNT* * * * * * * * * *
(ISSUED) - PDF Format
RP/O/A/1000/001Page 2 of 6
Emergency Classification
NOTE: This procedure is an implementing procedure to the Oconee Nuclear Site Emergency plan and must be forwarded toEmergency Planning within seven (7) working days of approval.
1. Symptoms
1 .1 This procedure describes the immediate actions to be taken to recognize and classify anemergency condition.
1.2 This procedure identifies the four emergency classifications and their correspondingEmergency Action Levels (EAL5).
1.3 This procedure provides reporting requirements for non-emergency abnormal events.
1.4 The following guidance is to be used by the Emergency Coordinator/EOF Director inassessing emergency conditions:
1.4.1 Definitions and Acronyms are italicized throughout procedure for easyrecognition. The definitions are in Enclosure 4.10 (Definitions/Acronyms).
1.4.2 The Emergency Coordinator/EOF Director shall review all applicableinitiating events to ensure proper classification.
1.4.3 The BASIS Document (Volume A, Section D of the Emergency Plan) isavailable for review if any questions arise over proper classification.
1.4.4 IF An event occurs on more than one unit concurrently,
THEN The event with the higher classification will be classified on theEmergency Notification Form.
A. Information relating to the problem(s) on the other unit(s) will becaptured on the Emergency Notification Form as shown inRP/0/A/1000/015A, (Offsite Communications From The Control Room),RP/0/A/1000/015B, (Offsite Communications From The TechnicalSupport Center) or SR/0/B/2000/004, (Notification to States and Countiesfrom the Emergency Operations Facility).
1.4.5 IF An event occurs,
AND A lower or higher plant operating mode is reached before theclassification can be made,
THEN The classification shall be based on the mode that existed at thetime the event occurred.
2
RP/O/A/l000/OOlPage 3 of6
1.4.6 The Fission Product Barrier Matrix is applicable only to those events thatoccur at Mode 4 (Hot Shutdown) or higher.
A. An event that is recognized at Mode 5 (Cold Shutdown) or lower shall notbe classified using the Fission Product Barrier Matrix.
1. Reference should be made to the additional enclosures that provideEmergency Action Levels for specific events (e.g., Severe Weather,Fire, Security).
1.5 IF A transient event should occur,
THEN Review the following guidance:
1.5.1 An Emergency Action Level (EAL) identifies a specific duration
AND The Emergency Coordinator/EOF Director assessment concludesthat the specified duration is exceeded or will be exceeded, (i.e.;condition cannot be reasonably corrected before the durationelapses),
THEN Classify the event.
1.5.2 IF A plant condition exceeding EAL criteria is corrected before thespecified duration time is exceeded,
THEN The event is NOT classified by that EAL.
A. Review lower severity EALs for possible applicability in these cases.
NOTE: Reporting under 1OCFR5O.72 may be required for the following step. Such a conditioncould occur, for example, if a follow up evaluation of an abnormal condition uncoversevidence that the condition was more severe than earlier believed.
1.5.3 IF A plant condition exceeding EAL criteria is not recognized at thetime of occurrence, but is identified well after the condition hasoccurred (e.g.; as a result of routine log or record review)
AND The condition no longer exists,
THEN An emergency shall NOT be declared.
• Refer to NSD 202 for reportability
3
RP/O/A/1000/OO1Page 4 of 6
1.5.4 IF An emergency classification was warranted, but the plant conditionhas been corrected prior to declaration and notification
THEN The Emergency Coordinator must consider the potential that theinitiating condition (e.g.; Failure of Reactor Protection System) mayhave caused plant damage that warrants augmenting the on shiftpersonnel through activation of the Emergency ResponseOrganization.
A. IF An Unusual Event condition exists,
THEN Make the classification as required.
1. The event may be terminated in the same notification or as a separatetermiiation notification.
B. IF An Alert, Site Area Emergency, or General Emergencycondition exists,
THEN Make the classification as required,
AND Activate the Emergency Response Organization.
1.6 Emergency conditions shall be classified as soon as the Emergency Coordinator/EOFDirector assessment determines that the Emergency Action Levels for the InitiatingCondition have been exceeded.
4
RP/O/A/l000/OOlPage 5 of 6
2. Immediate Actions
2.1 Assessment, classification and declaration of any applicable emergency condition shouldbe completed within 15 minutes after the availability of indications or information tocognizant facility staff that an EAL threshold has been exceeded.
2.2 Determine the operating mode that existed at the time the event occurred prior to anyprotection system or operator action initiated in response to the event.
2.3 fl The unit is at Mode 4 (Hot Shutdown) or higher
AND The condition/event affects fission product barriers,
THEN GO TO Enclosure 4.1, (Fission Product Barrier Matrix).
2.3.1 Review the criteria listed in Enclosure 4.1, (Fission Product Barrier Matrix)and make the determination if the event should be classified).
2.4 Review the listing of enclosures to determine if the event is applicable to one of thecategories shown.
2.4.1 IF One or more categories are applicable to the event,
THEN Refer to the associated enclosures.
2.4.2 Review the EALs and determine if the event should be classified.
A. IF An EAL is applicable to the event,
THEN Classify the event as required.
2.5 IF The condition requires an emergency classification,
THEN Initiate the following:• for Control Room - RP/O/B/1000/002, (Control Room
Emergency Coordinator Procedure)• for TSC - RP/O/A/1000/019, (Technical Support Center
Emergency Coordinator Procedure)• for EOF - SR!O/A/2000/003, (Activation of the Emergency
Operations Facility)
2.6 Continue to review the emergency conditions to assure the current classificationcontinues to be applicable.
5
RP/O/A/1000/00 1Page 6 of 6
3. Subsequent Actions
3.1 Continue to review the emergency conditions to assure the current classificationcontinues to be applicable.
4. Enclosures
Enclosures Page Number
4.1 Fission Product Barrier Matrix 7
4.2 System Malfunctions 8
4.3 Abnormal Rad Levels/Radiological Effluents 10
4.4 Loss Of Shutdown Functions 12
4.5 Loss of Power 14
4.6 Fires/Explosions And Security Actions 15
4.7 Natural Disasters, Hazards, And Other Conditions Affecting Plant Safety 17
4.8 Radiation Monitor Readings For Emergency Classification 20
4.9 Unexpected/Unplanned Increase In Area Monitor Readings 21
4.10 Definitions 22
4.11 Operating Modes Defmed In Improved Technical Specifications 27
4.12 Instructions For Using Enclosure 4.1 28
4.13 References 30
6
Encl
osu
re4.
1F
issi
onP
rod
uct
Bar
rier
Mat
rix
DE
TE
RM
INE
TH
EA
PP
RO
PR
IAT
EC
LA
SS
IFIC
AT
ION
US
ING
TH
ET
AB
LE
BE
LO
W:
RP
/0/A
/100
0/00
1Pa
ge1
of1
AD
DP
OIN
TS
TO
CL
AS
SIF
Y.
SE
EN
OT
EB
EL
OW
NO
TE
:•
An
even
tw
ithm
ulti
ple
even
tsco
uld
occu
rw
hich
wou
ldre
sult
inth
eco
nclu
sion
that
exce
edin
gth
elo
ssor
pote
ntia
llo
ssth
resh
old
isIM
MIN
EN
T(i
.e.,
with
in1-
3ho
urs)
.In
this
IMM
INE
NT
LO
SSsi
tuat
ion,
usej
udgm
ent
and
clas
sify
asif
the
thre
shol
dsar
eex
ceed
ed.
•R
efer
enci
ngth
ism
atri
xfr
eque
ntly
will
aid
inde
term
inin
ga
fiss
ion
barr
ier
failu
reor
othe
rup
grad
ecr
iteri
a.
RC
SB
AR
RIE
RS
(lID
5-7)
FU
EL
CL
AD
BA
RR
IER
S(l
ID8
-9)
CO
NT
AIN
ME
NT
BA
RR
IER
S(B
D1
0-1
3)
Pot
enti
alL
oss
(4P
oint
s)L
oss
(5P
oint
s)P
oten
tial
Los
s(4
Poi
nts)
Los
s(5
Poi
nts)
Pot
enti
alL
oss
(1P
oint
)L
oss
(3P
oint
s)
RC
SL
eakr
ate?
160
gpm
RC
SL
eak
rate
that
resu
ltsin
alo
ssA
vera
geof
the
5hi
ghes
tA
vera
geof
the
5hi
ghes
tC
ET
CC
ET
C12
00°
F15
min
utes
Rap
idun
expl
aine
dco
ntai
nmen
tof
subc
oolin
g.C
ET
C12
00°
FO
Rpr
essu
rede
crea
seaf
ter
incr
ease
700°
FC
ET
C70
0°F
15m
inut
esw
itha
vali
dR
VL
Sre
adin
g0”
cont
ainm
ent
pres
sure
orsu
mp
leve
lno
tco
nsis
tent
with
LO
CA
SGT
R?
160
gpm
Val
idR
VL
Sre
adin
gof
0”C
oola
ntac
tivi
ty30
0llC
i/ml
DE
lR
Bp
ress
ure
?59
psig
Fai
lure
ofse
cond
ary
side
of
SGO
Rre
sult
sin
adi
rect
open
ing
toth
eR
Bp
ress
ure
?10
psig
and
noen
viro
nmen
tw
ithSG
Tub
eL
eak
RB
CU
orR
BS
lOgpm
inth
eSA
ME
SG
NO
TE
:R
VL
Sis
NO
Tva
lidif
one
orm
ore
RC
Psar
eru
nnin
gO
Rif
Ent
iyin
toth
ePT
S(P
ress
uriz
edIR
IA57
or58
read
ing?
1.0
RJh
rL
PIpu
mp(
s)ar
eH
ours
RIA
57O
RR
IA58
Hou
rsR
IA57
OR
RIA
58SG
Tub
eL
eak?
10gp
mex
ists
inT
herm
alSh
ock)
Ope
ratio
nS
ince
SDR
Ihr
RJh
rS
ince
SDR
/hr
R/h
ron
eSG
.ru
nnin
gA
ND
taki
ng
NO
TE
:PT
Sis
ente
red
unde
r2
RIA
57re
adin
g1.
6R
lhr
auct
ion
from
the
LPI
the
othe
rSO
has
seco
ndar
ysi
deei
ther
ofth
efo
llow
ing:
2R
IA58
read
ing?
1.0
RJh
rdr
oplin
e.0
-<0
.5?
300
?15
00
-<
0.5
?18
00?
860
failu
reth
atre
sults
ina
dire
ct.
Aco
oldo
wn
belo
w40
0°F
@op
enin
gto
the
envi
ronm
entJj
>10
0°F/
hr.
has
occu
rred
.3R
IA57
or58
read
ing
1.0
R/h
r0.
5-
<2.
0?
80?
400.
5-<
2.0
?40
0?
195
isbe
ing
fed
from
the
affe
cted
unit
.H
PIha
sop
erat
edin
the
2.0
-8.
0?
32?
162.
0-8.
0?
280
?13
0in
ject
ion
mod
ew
hile
NO
RC
Ps
wer
eop
erat
ing.
HPI
Forc
edC
ooli
ngR
CS
pres
sure
spik
e?27
50ps
igH
ydro
gen
conc
entr
atio
n?
9%C
onta
inm
ent
isol
atio
nis
inco
mpl
ete
and
are
leas
epa
thto
the
envi
ronm
ent
exis
ts
Em
erge
ncy
Coo
rdin
ator
fEO
FE
mer
genc
yC
oord
inat
or/E
OF
Em
erge
ncy
Coo
rdin
ator
/EO
FE
mer
genc
yC
oord
inat
or/E
OF
Dir
ecto
rE
mer
genc
yC
oord
inat
or/E
OF
Em
erge
ncy
Coo
rdin
ator
lEO
FD
irec
torj
udgm
ent
Dir
ecto
rjud
gmen
tD
irec
torj
udgm
ent
judg
men
tD
irec
torj
udgm
ent
Dir
eeto
rjud
gmen
t
UN
US
UA
LE
VE
NT
(1-3
Tot
alP
oin
ts)
AL
ER
T(4
-6T
otal
Poi
nts)
SIT
EA
RE
AE
ME
RG
EN
CY
(7-1
0T
otal
Poi
nts)
GE
NE
RA
LE
ME
RG
EN
CY
(11
-13
Tot
alP
oint
s)
OP
ER
AT
ING
MO
DE
:1,2
,3,4
OP
ER
AT
ING
MO
DE
:1
,2,3
,4O
PE
RA
TIN
GM
OD
E:
1,2
,3,4
OP
ER
AT
ING
MO
DE
:1
,2,3
,4
4.1
.U.I
Any
pote
ntia
llo
ssof
Con
tain
men
t4.
1.A
.IA
nypo
tent
ial
loss
orlo
ssof
the
RC
S4
1S
1L
oss
ofan
ytw
oba
rrie
rs4.
1.G
.IL
oss
ofan
yIw
oba
rrie
rsan
dpo
tent
ial
loss
of
the
thir
dba
rrie
r4.
1.U
.2A
nylo
ssof
cont
ainm
ent
4.1
.A.2
Any
pote
ntia
llo
ssor
loss
ofth
eFu
el4.
1.S
.2L
oss
ofon
eba
rrie
ran
dpo
tent
ial
loss
ofei
ther
4.1.
0.2
Los
sof
all
thre
eba
rrie
rsC
lad
RC
Sor
Fuel
Cla
dB
arri
ers
4.1.
S.3
Pote
ntia
llo
ssof
both
the
RC
San
dFu
elC
lad
Bar
rier
s
7
Encl
osu
re4.
2R
P/O
/AJ1
000/
OO
1S
yste
mM
alfu
nct
ions
Pag
e1
of
2
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YG
EN
ER
AL
EM
ER
GE
NC
Y
RC
SL
EA
KA
GE
(BD
15)
OP
ER
AT
ING
MO
DE
:1,2
,3,4
A.
Uni
dent
ifie
dle
akage
10gp
m
B.
Pre
ssur
ebo
unda
ryle
akag
e10
gpm
C.
Iden
tifi
edle
akag
e25
gpm
Incl
udes
SOtu
bele
akag
e
2.U
NP
LA
NN
ED
LO
SS
OF
MO
ST
OR
AL
L1.
UN
PL
AN
NE
DL
OS
SO
FM
OS
TO
RA
LL
SA
FE
TY
SY
ST
EM
AN
NU
NC
IAT
ION
!S
AF
ET
YS
YS
TE
MA
NN
UN
CIA
TIO
N!
1.IN
AB
ILIT
YT
OM
ON
ITO
RA
IND
ICA
TIO
NIN
CO
NT
RO
LR
OO
MIN
DIC
AT
ION
INC
ON
TR
OL
RO
OM
SIG
NIF
ICA
NT
TR
AN
SIE
NT
IN
FO
R>
15M
INU
TE
S(B
D16
)
OP
ER
AT
ING
MO
DE
:1,
2,3
,4O
PE
RA
TIN
GM
OD
E:
1,2,
3,4
OP
ER
AT
ING
MO
DE
:1,
2,3,4
A.
Unp
lann
edlo
sso
f>50
%of
the
foll
owin
gA
.U
npla
nned
loss
of>
50%
ofth
efo
llow
ing
A.
Unp
lann
edlo
ssof>
50%
ofth
efo
llow
ing
annu
ncia
tors
onon
eun
itfo
r>15
min
utes
:an
nunc
iato
rson
one
unit
for>
15m
inut
es:
annu
ncia
tors
onon
eun
itfo
r>15
min
utes
:
Uni
ts1
&3
_________
Unit
sl&
3U
nit
sl&
31
SA
l,2,3
,4,5
,6,7
,8,9
,14
,15
,16
,&
18IS
A1,2
,3,4
,5,6
,7,8
,9,1
4,1
5,1
6,&
18
1S
A1,2
,3,4
,5,6
,7,8
,9,1
4,1
5,1
6,&
18
3S
Al,
2,3
,4,5
,6,7
,8,9
,14
,15
,16
,&
183S
A1
,2,3
,4,5
,6,7
,8,9
,14
,15,
16,&
18S
A1,2
,3,4
,5,6
,7,8
,9,
14,
15,
16,&
18
t2
Um
t2U
mt2
2S
Al,
2,3
,4,5
,6,7
,8,9
,14
,15
,&
162
SA
l,2,3
,4,
5,6
,7,
8,9
,14
,15
,&
162
SA
l,2,3
,4,
5,6
,7,8
,9,
14,
15,
&16
AN
D
__
AN
D
Los
sof
annu
ncia
tors
orin
dica
tors
requ
ires
Los
sof
annu
ncia
tors
orin
dica
tors
requ
ires
Asi
gnif
ican
ttr
ansi
ent
isin
prog
ress
addi
tion
alpe
rson
nel
(bey
ond
norm
alsh
ift
addi
tion
alpe
rson
nel
(bey
ond
norm
alsh
ift
com
plem
ent)
tosa
fely
oper
ate
the
unit
com
plem
ent)
tosa
fely
oper
ate
the
unit
AN
DL
oss
ofth
eO
AC
and
AL
LPA
Min
dica
tion
s(C
ON
TIN
UE
D)
—
Sig
nifi
cant
pla
nt
tran
sien
tin
prog
ress
OR
Inab
ilit
yto
dire
ctly
mon
itor
any
one
ofth
efo
llow
ing
func
tions
:
Los
sof
the
OA
Can
dA
LL
PAM
indi
cati
ons
1.S
ubcr
itic
alit
y(E
ND
)2.
Cor
eC
ooli
ng3.
Hea
tSi
nk4.
RC
SIn
tegr
ity5.
Con
tain
men
tIn
tegr
ity6.
RC
SIn
vent
oiy
=(E
ND
)
8
Encl
osu
re4.
2R
P/0
/A/1
000/
001
Sys
tem
Mal
funct
ions
Pag
e2
of
2
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YG
EN
ER
AL
EM
ER
GE
NC
Y
3.IN
AB
ILIT
YT
OR
EA
CH
RE
QU
IRE
DS
HU
TD
OW
NW
ITH
INL
IMIT
S(B
D17
)
OP
ER
AT
ING
MO
DE
:1,2
,3,4
A.
Req
uire
dop
erat
ing
mod
eno
tre
ache
dw
ithin
TS
LC
Oac
tion
stat
emen
ttim
e
4.U
NP
LA
NN
ED
LO
SS
OF
AL
LO
NS
ITE
OR
OF
FS
ITE
CO
MM
UN
ICA
TIO
NS
(BD
18)
OP
ER
AT
ING
MO
DE
:A
ll
A,
Los
sof
all
onsi
teco
mm
unic
atio
nsca
pabi
lity
(Pla
ntph
one
syst
em,
PAsy
stem
,P
ager
syst
em,
Ons
ite
Rad
iosy
stem
)af
fect
ing
abili
tyto
perf
orm
Rou
tine
oper
atio
ns
13.
Los
sof
all
onsi
teco
mm
unic
atio
nsca
pabi
lity
(Sel
ecti
veSi
gnal
ing,
NR
CE
TS
lines
,O
ffsi
teR
adio
Syst
em,
AT
&T
line)
affe
ctin
gab
ility
toco
mm
unic
ate
with
offs
iteau
thoi
itie
s.
5.F
UE
LC
LA
DD
EG
RA
DA
TIO
N(B
D19
)
OP
ER
AT
ING
MO
DE
:A
ll:
A.
DE
I->
5lIC
i/m
l
(EN
D)
9
Encl
osu
re4.
3R
P/0
/A!1
000/
001
AN
YU
NP
LA
NN
ED
RE
LE
AS
EO
FG
AS
EO
US
OR
LIQ
UID
RA
DIO
AC
TIV
ITY
TO
TH
EE
NV
IRO
NM
EN
TT
HA
TE
XC
EE
DS
TW
OT
IME
ST
HE
SE
CL
IMIT
SF
OR
60M
INU
TE
SO
RL
ON
GE
R(B
D25
)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Val
idin
dica
tion
onra
diat
ion
mon
itor
RTA
33of
4.06
E+
06cp
mfo
r>60
min
utes
(See
Not
e1)
B.
Val
idin
dica
tion
onra
diat
ion
mon
itor
RIA
-45
of>
9.35
E+
05cp
mor
RP
sam
ple
read
ingo
f6.
62E
-2uC
i/m
lX
e13
3eq
for>
60m
inut
es(S
eeN
ote
I)
C.
Liq
uid
effl
uent
bein
gre
leas
edex
ceed
stw
otim
esSL
C16
.11.
1fo
r>60
min
utes
asde
term
ined
byC
hem
istr
yP
roce
dure
D.
Gas
eous
effl
uent
bein
gre
leas
edex
ceed
stw
otim
esSL
C16
.11.
2fo
r>60
min
utes
asde
term
ined
byR
PP
roce
dure
1.A
NY
UN
PL
AN
NE
DR
EL
EA
SE
OF
GA
SE
OU
SO
RL
IQU
IDR
AD
IOA
CT
IVIT
YT
OT
HE
EN
VIR
ON
ME
NT
TH
AT
EX
CE
ED
S20
0T
IME
SR
AD
IOL
OG
ICA
LT
EC
HN
ICA
LS
PE
CIF
ICA
TIO
NS
FO
R15
MIN
UT
ES
OR
LO
NG
ER
(BD
30)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Val
idin
dica
tion
ofR
IA-4
6of>
2.09
E+
04cp
mor
RP
sam
ple
read
ingof
6.62
uCi/m
iX
e13
3eq
for>
15m
inut
es.
(See
Not
eI)
BR
1A33
HIG
HA
larm
AN
D
Liq
uid
effl
uent
bein
gre
leas
edex
ceed
s20
0tim
esth
ele
vel
ofSL
C16
.11.
1fo
r>15
min
utes
asde
term
ined
byC
hem
istr
yPr
oced
ure
C.
Gas
eous
effl
uent
bein
gre
leas
edex
ceed
s20
0tim
esth
ele
vel
ofSL
C16
.11.
2fo
r>1
5m
inut
esas
dete
rmin
edby
RP
Pro
cedu
re
BO
UN
DA
RY
DO
SE
RE
SU
LT
ING
FR
OM
AC
TU
AL
/IM
MIN
EN
TR
EL
EA
SE
OF
GA
SE
OU
SA
CT
IVIT
Y(B
D35
)
OP
ER
AT
ING
MO
DE
:A
ll
Val
idre
adin
gon
RIA
46of>
2.09
E+
05cp
mor
RIA
56re
adin
gof
17.5
R/h
ror
RP
sam
ple
read
ing
of6.
62E
+01
uCi/m
IX
e13
3eq
for>
15m
inut
es(S
eeN
ote
2)
B.
Val
idre
adin
gon
RJA
57or
58as
show
non
Enc
losu
re4.
8(S
eeN
ote
2)
C.
Dos
eca
lcul
atio
nsre
sult
ina
dose
proj
ecti
onat
the
Sit
ebo
unda
ryof
:
100
mR
emT
ED
Eor
500
mR
emC
DE
adul
tth
yroi
d
D.
Fiel
dsu
rvey
resu
ltsin
dica
tesi
tebo
unda
rydo
sera
tes
exce
edin
gl0
0m
Rad
/hr
expe
cted
toco
ntin
uefo
rm
ore
than
one
hour
OR
Ana
lyse
sof
fiel
dsu
rvey
sam
ples
indi
cate
adul
tth
yroi
ddo
seco
mm
itm
ent
of50
0m
Rem
CD
E(3
.84F7
pCi/m
I)fo
ron
eho
urof
inha
lati
on
NO
TE
2:If
actu
alD
ose
Ass
essm
ent
cann
otbe
com
plet
edw
ithin
15m
inut
es,
then
the
vali
dra
diat
ion
mon
itor
read
ing
shou
ldbe
used
for
emer
genc
ycl
assi
fica
tion
.
(CO
NT
INU
ED
)
1.B
OU
ND
AR
YD
OS
ER
ES
UL
TIN
GF
RO
MA
CtU
AL
/IM
MIN
EN
TR
EL
EA
SE
OF
GA
SE
OU
SA
CT
IV1T
Y(B
D39
)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Val
idre
adin
gon
RIA
46of>
2.09
E+
06cp
mor
RIA
56re
adin
gof
175
RIh
ror
RP
sam
ple
read
ing
of6.
62E
+O
2uC
i/ml
Xe
133
eqfo
rk15
min
utes
(See
Not
e3)
B.
Val
idre
adin
gon
RIA
57or
58as
show
non
Enc
losu
re4.
8(S
eeN
ote
3)
C.
Dos
eca
lcul
atio
nsre
sult
ina
dose
proj
ecti
onat
the
site
boun
dary
of:
1000
mR
emT
ED
E
OR 50
00m
Rem
CD
Ead
ult
thyr
oid
D.
Fiel
dsu
rvey
resu
ltsin
dica
tesi
tebo
unda
rydo
sera
tes
exce
edin
gl
000
mR
ad/h
rex
pect
edto
cont
inue
for
mor
eth
anon
eho
ur
OR
Ana
lyse
sof
fiel
dsu
rvey
sam
ples
indi
cate
adul
tth
yroi
ddo
seco
mm
itm
ento
f50
00m
Rem
CD
Efo
ron
eho
urof
inha
lati
on
NO
TE
3:If
actu
alD
ose
Ass
essm
ent
cann
otbe
com
plet
edw
ithin
15m
inut
es,t
hen
the
vali
dra
diat
ion
mon
itor
read
ing
shou
ldbe
used
for
emer
genc
ycl
assi
fica
tion
.
Ab
no
rmal
Rad
Lev
els/
Rad
iolo
gica
lE
fflu
ent
UN
US
UA
LE
VE
NT
AL
ER
Tj
SIT
EA
RE
AE
ME
RG
EN
CY
GE
NE
RA
LE
ME
RG
EN
CY
Pag
e1
of2
A.
(CO
NT
INU
ED
)
NO
TE
1:If
mon
itor
read
ing
issu
stai
ned
for
the
time
peri
odin
dica
ted
inth
eE
AL
AN
Dth
ere
quir
edas
sess
men
ts(p
roce
dure
calc
ulat
ions
)ca
nnot
beco
mpl
eted
with
inth
ispe
riod
,de
clar
atio
nm
ust
bem
ade
onth
eva
lid
Rad
iati
onM
onit
orre
adin
g.
(CO
NT
INU
ED
)
(EN
D1
10
Encl
osu
re4.
3A
bn
orm
alR
adL
evel
sfR
adio
logi
cal
Eff
luen
tR
P/0/
A/1
000/
001
Pag
e2
of
2
2U
NE
XP
EC
TE
DIN
CR
EA
SE
INP
LA
NT
RA
DIA
TIO
NO
RA
IRB
OR
NE
CO
NC
EN
TR
AT
ION
(BD
27)
OP
ER
AT
ING
MO
DE
:A
ll
A.
LT
5re
adin
g14
”an
dde
crea
sing
with
mak
eup
not
keep
ing
upw
ithle
akag
eW
ITH
fuel
inth
eco
re
B.
Val
idin
dica
tion
ofun
cont
roll
edw
ater
decr
ease
inth
eSF
Por
fuel
tran
sfer
cana
lw
ithal
lfu
elas
sem
blie
sre
mai
ning
cove
red
byw
ater
AN
D
Unp
lann
edV
alid
NA
3,6
orP
orta
ble
Are
aM
onit
orre
adin
gsin
crea
se.
C.
1R
Ihr
radi
atio
nre
adin
gat
one
foot
away
from
ada
mag
edst
orag
eca
sklo
cate
dat
the
ISFS
I
D.
Val
idar
eam
onit
orre
adin
gsex
ceed
sli
mit
sst
ated
inE
nclo
sure
4.9.
NO
TE
:T
his
Init
iati
ngC
ondi
tion
isal
solo
cate
din
Enc
losu
re4.
4.,
(Los
sof
Shut
dow
nFu
nctio
ns).
Hig
hra
diat
ion
leve
lsw
illal
sobe
seen
with
this
cond
ition
.
2.R
EL
EA
SE
OF
RA
DIO
AC
TIV
EM
AT
ER
IAL
OR
INC
RE
AS
ES
INR
AD
IAT
ION
LE
VE
LS
TH
AT
IMP
ED
ES
OP
ER
AT
ION
OF
SY
ST
EM
SR
EQ
UIR
ED
TO
MA
INT
AIN
SA
FE
OP
ER
AT
ION
OR
TO
ES
TA
BL
ISH
OR
MA
INT
AIN
CO
LD
SH
UT
DO
WN
(BD
32)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Val
idra
diat
ion
read
ing
15rn
Rad
/hr
inC
R,
CA
S,or
Rad
was
teC
R
B.
Unp
lann
ed/u
nexp
ecte
dva
lid
area
mon
itor
read
ings
exce
edlim
itsst
ated
inE
nclo
sure
4.9
NO
TE
:T
hese
read
ings
may
also
bein
dica
tive
ofFi
ssio
nP
rodu
ctB
arri
erco
ncer
nsw
hich
mak
esa
revi
ewof
the
Fiss
ion
Pro
duct
Bar
rier
Mat
rix
nece
ssar
y. MA
JOR
DA
MA
GE
TO
IRR
AD
IAT
ED
FU
EL
OR
LO
SS
OF
WA
TE
RL
EV
EL
TH
AT
HA
SO
RW
ILL
RE
SU
LT
INT
HE
UN
CO
VE
RIN
GO
FIR
RA
DIA
TE
DF
UE
LO
UT
SID
ET
HE
RE
AC
TO
RV
ES
SE
L(B
D33
)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Val
idN
A3*
,6
,41
,O
R49
*H
IGH
Ala
rm
*-
App
lies
toM
ode
6an
dN
oM
ode
Onl
y
B.
HIG
HA
larm
for
port
able
area
mon
itors
onth
em
ain
bndg
eor
SFP
brid
ge
C.
Rep
ort
ofvi
sual
obse
rvat
ion
ofir
radi
ated
fuel
unco
vere
d
D.
Ope
rato
rsde
term
ine
wat
erle
vel
drop
inei
ther
the
SFP
orfu
eltr
ansf
erca
nal
will
exce
edm
akeu
pca
paci
tysu
chth
atir
radi
ated
fuel
will
beun
cove
red
NO
TE
:T
his
Init
iati
ngC
ondi
tion
isal
solo
cate
din
Enc
losu
re4.
4.,
(Los
so
fSh
utdo
wn
Fun
ctio
ns).
Hig
hra
diat
ion
leve
lsw
illal
sobe
seen
with
this
cond
itio
n.
(EN
D)
2.L
OS
SO
FW
AT
ER
LE
VE
LIN
TH
ER
EA
CT
OR
VE
SS
EL
TH
AT
HA
SO
RW
ILL
UN
CO
VE
RF
UE
LIN
TH
ER
EA
CT
OR
VE
SS
EL
(BD
38)
OP
ER
AT
ING
MO
DE
:5
,6
A.
Los
so
fal
lde
cay
heat
rem
oval
asin
dica
ted
byth
ein
abil
ity
tom
aint
ain
RC
Ste
mpe
ratu
rebe
low
200°
F
AN
D
LT
5in
dica
tes
0in
ches
afte
rin
itia
tion
ofR
CS
mak
eup
B.
Los
sof
all
deca
yhe
atre
mov
alas
indi
cate
dby
the
inab
ilit
yto
mai
ntai
nR
CS
tem
pera
ture
belo
w20
0°F
AN
D
Eit
her
trai
nul
tras
onic
leve
lin
dica
tion
less
than
0in
ches
and
decr
easi
ngaf
ter
init
iati
ono
fR
CS
mak
eup
NO
TE
:T
his
Init
iati
ngC
ondi
tion
isal
solo
cate
din
Enc
losu
re4.
4.,
(Los
sof
Shu
tdow
nF
unct
ions
).H
igh
radi
atio
nle
vels
will
also
bese
enw
ithth
isco
nditi
on.
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YG
EN
ER
AL
EM
ER
GE
NC
Y
3.
(EN
D)
(EN
D))
11
Encl
osu
re4.
4R
P/O
/A!l
000/
OO
lL
oss
ofS
hutd
ow
nF
unct
ions
Pag
e1
of
2
UN
US
UA
LE
VE
NT
IA
LE
RT
SIT
EA
RE
AE
ME
RG
EN
CY
GE
NE
RA
LE
ME
RG
EN
CY
FA
ILU
RE
OF
RP
ST
OC
OM
PL
ET
EO
R1.
FA
ILU
RE
OF
RP
ST
OC
OM
PL
ET
EO
R1.
FA
ILU
RE
OF
RP
ST
OC
OM
PL
ET
EIN
ITIA
TE
AR
xS
CR
AM
(BD
44)
INIT
IAT
EA
Rx
SC
RA
M(B
D50
)
OP
ER
AT
ING
MO
DE
:1,
2O
PE
RA
TIN
GM
OD
E1,2
,3O
PE
RA
TIN
GM
OD
E:
1,2
(CO
NT
INU
ET
ON
EX
TP
AG
E)
A.
Val
idR
xtr
ipsi
gnal
rece
ived
orre
quir
edA
.V
alid
reac
tor
trip
sign
alre
ceiv
edor
requ
ired
A.
Val
idre
acto
rtr
ipsi
gnal
rece
ived
orre
quir
edW
ITH
OU
Tau
tom
atic
scra
mW
ITH
OU
Tau
tom
atic
scra
mW
ITH
OU
Tau
tom
atic
scra
m
AN
D—
AN
DD
SSha
sin
sert
edC
ontr
olR
ods
Man
ual
trip
from
the
Con
trol
Roo
mw
as
OR
DSS
has
NO
Tin
sert
edC
ontr
olR
ods
QI
—su
cces
sful
inre
duci
ngre
acto
rpo
wer
to<
Man
ual
trip
from
the
Con
trol
Roo
mis
5%su
cces
sful
and
reac
tor
pow
eris
less
AN
Dan
dde
crea
sing
than
5%an
dde
crea
sing
Man
ual
trip
from
the
Con
trol
Roo
mw
asN
OT
AN
Isu
cces
sful
inre
duci
ngre
acto
rpo
wer
tole
ssth
an5%
and
decr
easi
ngA
vera
geo
fth
e5
high
est
CE
TC
s1
20
00
Fon
ICC
M
2.IN
AB
ILIT
YT
OM
AIN
TA
INP
LA
NT
IN2.
CO
MP
LE
TE
LO
SS
OF
FU
NC
TIO
N(E
ND
)M
OD
ES
(CO
LD
SH
UT
DO
WN
)(B
D46
)N
EE
DE
DT
OA
CH
IEV
EO
RM
AIN
TA
INM
OD
E4
(HO
TS
HU
TD
OW
N)
(BD
51)
OP
ER
AT
ING
MO
DE
:5
,6O
PE
RA
TIN
GM
OD
E:
1,2
,3,4
A.
Los
sof
LPI
and/
orL
PSW
AN
DA
.A
vera
geo
fth
e5
high
est
CE
TC
sl2
000
F—
show
non
ICC
M
Inab
ility
tom
aint
ain
RC
Ste
mpe
ratu
reB
.U
nabl
eto
mai
ntai
nre
acto
rsu
bcri
tica
lbe
low
2000
Fas
indi
cate
dby
eith
ero
fthe
follo
win
g:C
.E
OP
dire
cts
feed
ing
SOfr
omSS
FA
SWP
orst
atio
nA
SWP
RC
Ste
mpe
ratu
reat
the
LPI
Pum
pS
ucti
on
(CO
NT
INU
ED
)
Ave
rage
ofth
e5
high
est
CE
TC
sas
indi
cate
dby
ICC
Mdi
spla
y
OR
Vis
ual
obse
rvat
ion
(CO
NT
INU
ED
)
_____________________________
12
Encl
osu
re4.
4L
oss
of
Sh
utd
ow
nF
unct
ions
RP
/0/A
/100
0/00
1P
age
2o
f2
1.U
NE
XP
EC
TE
DIN
CR
EA
SE
INP
LA
NT
RA
DIA
TIO
NO
RA
IRB
OR
NE
CO
NC
EN
TR
AT
ION
(BD
42)
OP
ER
AT
ING
MO
DE
:A
ll
A.
LT
5re
adin
g14
”an
dde
crea
sing
with
mak
eup
not
keep
ing
upw
ithle
akag
e31
11i1
fuel
inth
eco
re
B.
Val
idin
dica
tion
ofun
cono
-oll
edw
ater
decr
ease
inth
eSF
Por
fuel
tran
sfer
cana
lw
ithal
lfu
elas
sem
blie
sre
mai
ning
cove
red
byw
ater
AN
D
(Inp
lann
edV
alid
RIA
3,6or
Port
able
Are
aM
onit
orre
adin
gsin
crea
se.
C.
IR
/hr
radi
atio
nre
adin
gat
one
foot
away
from
ada
mag
edst
orag
eca
sklo
cate
dat
the
ISFS
I
D.
Val
idar
eam
onito
rre
adin
gsex
ceed
slim
itsst
ated
inE
nclo
sure
4.9.
NO
TE
:T
his
Init
iati
ngC
ondi
tion
isal
solo
cate
din
Enc
losu
re4.
3.,
(Abn
orm
alR
adL
evel
s/R
adio
logi
cal
Eff
luen
t).
Hig
hra
diat
ion
leve
lsw
illal
sobe
seen
with
this
cond
ition
.
MA
JOR
DA
MA
GE
TO
IRR
AD
IAT
ED
FU
EL
OR
LO
SS
OF
WA
TE
RL
EV
EL
TH
AT
HA
SO
RW
ILL
RE
SU
LT
INT
HE
UN
CO
VE
RIN
GO
FIR
RA
DIA
TE
DF
UE
LO
UT
SID
ET
HE
RE
AC
TO
RV
ES
SE
L(B
D48
)
OP
ER
AT
ING
MO
DE
:A
ll
A.V
alid
RIA
3*,
6,4
1,
OR
49*
HIG
HA
larm
*App
lies
toM
ode
6an
dN
oM
ode
Onl
y
B.
HIG
HA
larm
for
port
able
area
mon
itors
onth
em
ain
brid
geor
SFP
brid
ge
CR
epor
tof
visu
alob
serv
atio
nof
irra
diat
edfu
elun
cove
red
D.
Ope
rato
rsde
term
ine
wat
erle
vel
drop
inei
ther
the
SFP
orfu
eltr
ansf
erca
nal
will
exce
edm
akeu
pca
paci
tysu
chth
atir
radi
ated
fuel
will
beun
cove
red
NO
TE
:T
his
Init
iati
ngC
ondi
tion
isal
solo
cate
din
Enc
losu
re4.
3,(A
bnor
mal
Rad
Lev
els/
Rad
iolo
gica
lE
fflu
ent)
.H
igh
radi
atio
nle
vels
will
also
bese
enw
ithth
isco
nditi
on.
3.L
OS
SO
FW
AT
ER
LE
VE
LIN
TH
ER
EA
CT
OR
VE
SS
EL
TH
AT
HA
SO
RW
ILL
UN
CO
VE
RF
UE
LIN
TH
ER
EA
CT
OR
VE
SS
EL
(BD
52)
OP
ER
AT
ING
MO
DE
:5
,6
A.
Los
so
fal
lde
cay
heat
rem
oval
asin
dica
ted
byth
ein
abili
tyto
mai
ntai
nR
CS
tem
pera
ture
belo
w20
00F
AN
D
LT
-5in
dica
tes
0in
ches
afte
rin
itia
tion
ofR
CS
Mak
eup
B.
Los
sof
all
deca
yhe
atre
mov
alas
indi
cate
dby
the
inab
ilit
yto
mai
ntai
nR
CS
tem
pera
ture
belo
w20
0°F
AN
D
Eit
her
trai
nul
tras
onic
leve
lin
dica
tion
less
than
0in
ches
and
decr
easi
ngaf
ter
init
iati
onof
RC
Sm
akeu
p
NO
TE
:T
his
Init
iati
ngC
ondi
tion
isal
solo
cate
din
Enc
losu
re4.
3,(A
bnor
mal
Rad
Lev
els/
Rad
iolo
gica
lE
fflu
ent)
,H
igh
radi
atio
nle
vels
will
also
bese
enw
ithth
isco
nditi
on.
3.
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YG
EN
ER
AL
EM
ER
GE
NC
Y
(EN
D)
(EN
D)
(EN
D)
13
Encl
osu
re4.
5L
oss
of
Po
wer
{4}
RP
/0/A
tl00
0/00
1Pa
ge1
of
I
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YG
EN
ER
AL
EM
ER
GE
NC
Y
1.L
OS
SO
FA
LL
OF
FS
ITE
PO
WE
RT
OE
SS
EN
TIA
LB
US
SE
SF
OR
GR
EA
TE
RT
HA
N15
MIN
UT
ES
(BD
55)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Uni
tau
xili
arie
sar
ebe
ing
supp
lied
from
Keo
wee
orC
T5
AN
D
Inab
ility
toen
ergi
zeei
ther
MFB
from
anof
fsite
sour
ce(e
ithe
rsw
itch
yard
)w
ithin
15m
inut
es.
1.L
OS
SO
FA
LL
OF
FS
ITE
AC
PO
WE
RA
ND
LO
SS
OF
AL
LO
NS
ITE
AC
PO
WE
RT
OE
SS
EN
TIA
LB
US
SE
S(B
D57
)
OP
ER
AT
ING
MO
DE
:5,6
Def
uele
d
A.
MFB
1an
d2
dc-e
nerg
ized
AN
D
Fai
lure
tore
stor
epo
wer
toat
leas
ton
eM
FBw
ithin
15m
inut
esfr
omth
elim
eo
flo
ssof
both
offs
itean
don
site
AC
pow
er
LO
SS
OF
AL
LO
FF
SIT
EA
CP
OW
ER
AN
DL
OS
SO
FA
LL
ON
SIT
EA
CP
OW
ER
TO
ES
SE
NT
IAL
BU
SS
ES
(BD
59)
OP
ER
AT
ING
MO
DE
:1
,2,3
,4
Failu
reto
rest
ore
pow
erto
atle
ast
one
MFB
with
in15
min
utes
from
the
lime
oflo
ssof
both
offs
itean
don
site
AC
pow
er
1.P
RO
LO
NG
ED
LO
SS
OF
AL
LO
FF
SIT
EP
OW
ER
AN
DO
NS
ITE
AC
PO
WE
R(B
D62
)
OP
ER
AT
ING
MO
DE
:1
,2,3
,4
A.
IvIF
B1
and
2dc
-ene
rgiz
ed
AN
D
SSF
fails
tom
aint
ain
Mod
e3
(Hot
Stan
dby)
{I
2.U
NP
LA
NV
ED
LO
SS
OF
RE
QU
IRE
DD
CP
OW
ER
FO
RG
RE
AT
ER
TH
AN
15M
INU
TE
S(B
D56
)
OP
ER
AT
ING
MO
DE
:5,6
A.
Unp
lann
edba
aof
vita
lD
Cpo
wer
tore
quir
edD
Cbu
sses
asin
dica
ted
bybu
svo
ltage
less
than
110
VD
C
AN
D
Failu
reto
rest
ore
pow
erto
atle
ast
one
requ
ired
DC
bus
wit
hin
15m
inut
esfr
omth
etim
eof
loss
(EN
D)
2.A
CP
OW
ER
CA
PA
BIL
ITY
TO
ES
SE
NT
IAL
BU
SS
ES
RE
DU
CE
DT
OA
SIN
GL
ES
OU
RC
EF
OR
GR
EA
TE
RT
HA
N15
MIN
UT
ES
(BD
58)
OP
ER
AT
ING
MO
DE
:1,2
,3,4
A,
AC
pow
erca
pabi
lity
has
been
degr
aded
toa
sing
lepo
wer
sour
cefo
r>15
min
utes
due
toth
elo
ssof
all
but
one
ofth
efo
llow
ing:
Uni
tN
orm
alT
rans
form
er(b
ackc
harg
ed)
Uni
tSU
Tra
nsfo
rmer
Ano
ther
Uni
tSU
Tra
nsfo
rmer
(ali
ed)
CT
4C
T5
(EN
D)
2.L
OS
SO
FA
LL
VIT
AL
DC
PO
WE
R(l
ID60
)
OP
ER
AT
ING
MO
DE
:1
,2,3
,4
A.
Unp
lann
edlo
ssof
vita
lD
Cpo
wer
tore
quir
edD
Cbu
sses
asin
dica
ted
bybu
svo
ltage
less
than
110
VD
C
AN
D
Failu
reto
rest
ore
pow
erto
atle
ast
one
requ
ired
DC
bus
with
in15
min
utes
from
the
time
oflo
ss
(EN
D)
At
leas
t one
ofth
efo
llow
ing
cond
ition
aex
ist:
Res
tora
tion
ofpo
wer
toat
leas
ton
eM
FBw
ithin
4ho
urs
isN
OT
likel
y
Indi
cati
ons
ofco
ntin
uing
degr
adat
ion
ofco
reco
olin
gba
sed
onF
issi
onP
rodu
ctB
arri
erm
onit
onng
(EN
D)
A.
MFB
Ian
d2
dc-e
nerg
ized
AN
D
AN
D
OR
Los
sof
Pow
er-
Em
erge
ncy
Act
ion
Lev
els
(EA
Ls)
appl
yto
the
abili
tyof
elec
tric
alen
ergy
tope
rfor
mits
inte
nded
func
tion,
reac
hits
inte
nded
equi
pmen
t.ex
.-
Ifbo
thM
FBs,
are
ener
gize
dbu
tal
l41
60V
swit
chge
aris
not
avai
labl
e,th
eel
ectr
ical
ener
gyca
nno
tre
ach
the
mot
ors
inte
nded
.T
here
sult
toth
epl
ant
isth
esa
me
asif
both
MF
Bs
wer
ede
-ene
rgiz
ed.
__________
____
__
__
______
{4}
14
Encl
osu
re4.
6R
P/O
IAI1
000I
OO
IF
ire/
Ex
plo
sio
ns
and
Sec
uri
tyA
ctio
ns{2
}{3
}Pa
ge1
of
2
UN
US
UA
LE
VE
NT
AL
ER
T[
SIT
EA
RE
AE
ME
RG
EN
CY
GE
NE
RA
LE
ME
RG
EN
CY
FIR
ES
/EX
PL
OS
ION
SW
ITH
INT
HE
1.F
IRE
/EX
PL
OS
ION
AF
FE
CT
ING
(CO
NT
INU
ET
ON
EX
TP
AG
E)
(CO
NT
INU
ET
ON
EX
TP
AG
E)
PL
AN
T(B
D65
)O
PE
RA
BIL
ITY
OF
PL
AN
TS
AF
ET
Y
____________
__________________
SY
ST
EM
SR
EQ
UIR
ED
TO
ES
TA
BL
ISH
/MA
INT
AIN
SA
FE
OP
ER
AT
ING
MO
DE
:A
llS
HU
TD
OW
N(B
D70
)
NO
TE
:W
ithin
the
plan
tm
eans
:
____
____
____
____
____
____
____
____
____
___
Tur
bine
Bui
ldin
g•
NO
TE
:O
nly
one
trai
nof
asy
stem
need
sto
Aux
iliar
yB
uild
ing
beaf
fect
edor
dam
aged
inor
der
tosa
tisf
yth
isR
eact
orB
uild
ing
cond
itio
n.ke
owee
Hyd
roT
rans
form
erY
ard
B3T
B4T
Serv
ice
Air
Die
sel
Com
pres
sors
A1i
re/e
xplo
sioi
isK
eow
eeH
ydro
&as
soci
ated
Tra
nsfo
i-m
ers
SSF
Aff
ecte
dsa
fety
-rel
ated
syst
empa
ram
eter
indi
cati
ons
show
degr
aded
petf
orm
ance
OR
A.
Fire
wit
hin
the
plan
tno
tex
ting
uish
edw
ithin
15m
inut
esof
Con
trol
Roo
mno
tifi
cati
onor
Pla
ntpe
rson
nel
repo
rtvi
sibl
eda
mag
eto
veri
fica
tion
ofa
Con
trol
Roo
mal
arm
perm
anen
tst
ruct
ures
oreq
uipm
ent
requ
ired
for
safe
shut
dow
nB
.U
nant
icip
ated
expl
osio
nw
ithin
the
plan
tre
sult
ing
invi
sibl
eda
mag
eto
perm
anen
t(C
onti
nued
)st
ruct
ures
/equ
ipm
ent
incl
udes
stea
mlin
ebr
eak
and
FDW
line
brea
k
(Con
tinu
ed)
15
Encl
osu
re4.
6F
ire/
Ex
plo
sio
ns
and
Sec
uri
tyA
ctio
ns{2
}{3
}
RP
/0/A
!l00
0/00
1P
age
2o
f2
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YI
GE
NE
RA
LE
ME
RG
EN
CY
2.C
ON
FIR
ME
DS
EC
UR
ITY
CO
ND
ITIO
NO
RT
HR
EA
TW
HIC
HIN
DIC
AT
ES
AP
OT
EN
TIA
LD
EG
RA
DA
TIO
NiN
TH
EL
EV
EL
OF
SA
FE
TY
OF
TH
EP
LA
NT
(BD
67)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Secu
rity
cond
itio
nth
atdo
esno
tin
volv
ea
HO
STIL
EA
CT
ION
asre
port
edby
the
Secu
rity
Shif
tSu
perv
isio
n.
B.
Acr
edib
lesi
te-s
peci
fic
secu
rity
thre
atno
tifi
cati
on
C.
Ava
lida
ted
noti
fica
tion
from
NR
Cpr
ovid
ing
info
rmat
ion
ofan
airc
raft
thre
at
3.O
TH
ER
CO
ND
ITIO
NS
EX
IST
WH
ICH
INT
HE
JUD
GE
ME
NT
OF
TH
EE
ME
RG
EN
CY
DIR
EC
TO
RW
AR
RA
NT
DE
CL
AR
AT
ION
OF
AN
OU
E.
(BD
69)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Oth
erco
ndit
ions
exis
tw
hich
inth
ejud
gmen
tof
the
Em
erge
ncy
Dir
ecto
rin
dica
teth
atev
ents
are
inpr
ogre
ssor
have
occu
rred
whi
chin
dica
tea
pote
ntia
lde
grad
atio
nof
the
leve
lof
safe
tyof
the
plan
tor
indi
cate
ase
curi
tyth
reat
tofa
cili
typr
otec
tion
has
been
initi
ated
.N
ore
leas
esof
radi
oact
ive
mat
eria
lre
quir
ing
off-
site
resp
onse
orm
onit
orin
gar
eex
pect
edun
less
furt
her
degr
adat
ion
ofsa
fety
syst
ems
occu
rs.
(EN
D)
2H
OS
TIL
EA
CT
ION
WIT
HIN
TH
EO
WN
ER
CO
NT
RO
LL
ED
AR
EA
OR
AIR
BO
RN
EA
TT
AC
KT
HR
EA
T.
(BD
72)
A.
AH
OST
ILE
AC
TIO
Nis
occu
rlin
gor
has
occu
rred
with
inth
eO
WN
ER
CO
NT
RO
LL
ED
AR
EA
asre
port
edby
the
Sec
unty
Shif
tSu
perv
isio
n.
B.
Ava
lida
ted
noti
fica
tion
from
NR
Co
fan
AIR
LIN
ER
atta
ckth
reat
with
in30
min
utes
ofth
esi
te.
3.O
TH
ER
CO
ND
ITIO
NS
EX
IST
WH
ICH
INT
HE
JUD
GE
ME
NT
OF
TH
EE
ME
RG
EN
CY
DIR
EC
TO
RW
AR
RA
NT
DE
CL
AR
AT
ION
OF
AN
AL
ER
T(B
D75
)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Oth
erco
ndit
ions
exis
tw
hich
inth
ejud
gmen
tof
the
Em
erge
ncy
Dir
ecto
rin
dica
teth
atev
ents
are
inpr
ogre
ssor
have
occu
rred
whi
chin
volv
ean
actu
alor
pote
ntia
lsu
bsta
ntia
lde
grad
atio
nof
the
leve
lof
safe
tyof
the
plan
tor
ase
cunt
yev
ent
that
invo
lves
prob
able
life
thre
aten
ing
risk
tosi
tepe
rson
nel
orda
mag
eto
site
equi
pmen
tbe
caus
eof
HO
STIL
EA
CT
ION
.A
nyre
leas
esar
eex
pect
edto
beli
mit
edto
smal
lfr
acti
ons
of
the
EPA
Pro
tect
ive
Act
ion
Gui
deli
neex
posu
rele
vels
.
(EN
D)
HO
ST
ILE
AC
TIO
Nw
ithi
nth
eP
RO
TE
CT
ED
AR
EA
(BD
76)
OP
ER
AT
ING
MO
DE
:A
ll
A.
AH
OST
ILE
AC
TIO
Nis
occu
rrin
gor
has
occu
rred
with
inth
eP
RO
TE
CT
ED
AR
EA
asre
port
edby
the
Secu
rity
Shif
tSu
perv
isio
n.
2.O
TH
ER
CO
ND
ITIO
NS
EX
IST
WH
ICH
INT
HE
JUD
GE
ME
NT
OF
TH
EE
ME
RG
EN
CY
DIR
EC
TO
RW
AR
RA
NT
DE
CL
AR
AT
ION
OF
AS
ITE
AR
EA
EM
ER
GE
NC
Y.
(BD
78)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Oth
erco
ndit
ions
exis
tw
hich
inth
eju
dgm
ent
ofth
eE
mer
genc
yD
irec
tor
indi
cate
that
even
tsar
ein
prog
ress
orha
veoc
curr
edw
hich
invo
lve
actu
alor
likel
ym
ajor
failu
res
ofpl
ant
func
tion
sne
eded
for
prot
ecti
onof
the
publ
icor
HO
STIL
EA
CT
ION
that
resu
ltsin
inte
ntio
nal
dam
age
orm
alic
ious
acts
;(1
)to
war
dsi
tepe
rson
nel
oreq
uipm
ent
that
coul
dle
adto
the
likel
yfa
ilur
eof
or;
(2)
that
prev
ent
effe
ctiv
eac
cess
toeq
uipm
ent
need
edfo
rth
epr
otec
tion
ofth
epu
blic
.A
nyre
leas
esar
eno
tex
pect
edto
resu
ltin
expo
sure
leve
lsw
hich
exce
edE
PAP
rote
ctiv
eA
ctio
nG
uide
line
expo
sure
leve
lsbe
yond
the
site
boun
dary
.
(EN
D)
AH
OS
TIL
EA
CT
ION
RE
SU
LT
ING
INL
OS
SO
FP
HY
SIC
AL
CO
NT
RO
LO
FT
HE
FA
CIL
ITY
(BD
79)
OP
ER
AT
ING
MO
DE
:A
ll
A.
AH
OST
ILE
AC
TIO
Nha
soc
curr
edsu
chth
atpl
ant
pers
onne
lar
eun
able
toop
erat
eeq
uipm
ent
requ
ired
tom
aint
ain
safe
tyfu
ncti
ons
B.
AH
OST
ILE
AC
TIO
Nha
sca
used
failu
reof
Spe
ntFu
elC
ooli
ngSy
stem
san
dII
vIIv
IIN
ENT
fuel
dam
age
islik
ely
for
afr
eshl
yof
f-lo
aded
reac
tor
core
inpo
ol.
2.O
TH
ER
CO
ND
ITIO
NS
EX
IST
WH
ICH
INT
HE
JUD
GM
EN
TO
FT
HE
EM
ER
GE
NC
YD
IRE
CT
OR
WA
RR
AN
TD
EC
LA
RA
TIO
NO
FA
GE
NE
RA
LE
ME
RG
EN
CY
.(B
D81
)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Oth
erco
ndit
ions
exis
tw
hich
inth
eju
dgm
ent
ofth
eE
mer
genc
yD
irec
tor
indi
cate
that
even
tsar
ein
prog
ress
orha
veoc
curr
edw
hich
invo
lve
actu
alor
IMM
INE
NT
subs
tant
ial
core
degr
adat
ion
orm
elti
ngw
ithpo
tent
ial
for
loss
ofco
ntai
nmen
tin
tegr
ityor
HO
STIL
EA
CT
ION
that
resu
ltsin
anac
tual
loss
of
phys
ical
cont
rol
of
the
faci
lity.
Rel
ease
sca
nbe
reas
onab
lyex
pect
edto
exce
edE
PA
Pro
tect
ive
Act
ion
Gui
deli
neex
posu
rele
vels
off-
site
for
mor
eth
anth
eim
med
iate
site
area
.
(EN
D)
16
1.N
AT
UR
AL
AN
DD
ES
TR
UC
TIV
EP
HE
NO
ME
NA
AF
FE
CT
ING
TH
EP
RO
TE
CT
ED
AR
EA
(BD
83)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Tre
mor
felt
and
vali
dal
arm
onth
est
rong
mot
ion
acce
lero
grap
h
BT
orna
dost
okin
gw
ithin
Pro
tect
edA
rea
Bou
ndai
y
C.
Veh
icle
cras
hin
topl
ant
stru
ctur
es/s
yste
ms
wit
hin
the
Pro
tect
edA
rea
Bou
ndai
y
D.
Tur
bine
failu
rere
sult
ing
inca
sing
pene
trat
ion
orda
mag
eto
turb
ine
orge
nera
tor
seal
s
1.N
AT
UR
AL
AN
DD
ES
TR
UC
TIV
EP
HE
NO
ME
NA
AF
FE
CT
ING
TH
EP
LA
NT
VIT
AL
AR
EA
(BD
89)
OP
ER
AT
ING
MO
DE
:A
llA
.T
rem
orfe
ltan
dse
ism
ictr
igger
actu
ate
s(O
.05g
)
NO
TE
:O
nly
one
trai
nof
asa
fety
-rel
ated
syst
emne
eds
tobe
affe
cted
orda
mag
edin
orde
rto
satis
fyth
ese
cond
ition
s.
B.
Tom
ado,
high
win
ds,
mis
sile
sre
sult
ing
from
turb
ine
failu
re,
vehi
cle
cras
hes,
orot
her
cata
stro
phic
even
t.
Vis
ible
dam
age
tope
rman
ent
strn
ctur
esor
equi
pmen
tre
quir
edfo
rsa
fesh
utdo
wn
ofth
eun
it.
OR
Aff
ecte
dsa
fety
syst
empa
ram
eter
indi
cati
ons
show
degr
aded
perf
orm
ance
.
(CO
NT
INU
ED
)
Encl
osu
re4.
7R
P/O
/A!1
000/
OO
1N
atura
lD
isas
ters
,H
azar
ds
and
Oth
erC
ondit
ions
Aff
ecti
ngP
lan
tS
afet
yP
age
1o
f3
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YG
EN
ER
AL
EM
ER
GE
NC
Y
(CO
NT
INU
ET
ON
EX
TP
AG
E)
(CO
NT
INU
ET
ON
EX
TP
AG
E)
(CO
NT
INU
ED
)
AN
D
17
Enc
losu
re4.
7N
atura
lD
isas
ters
,H
azar
ds
and
Oth
erC
ondi
tion
sA
ffec
ting
Pla
nt
Saf
ety
RP
/0/A
/100
0/00
1P
age
2o
f3
2.N
AT
UR
AL
AN
DD
ES
TR
UC
TIV
EP
HE
NO
ME
NA
AF
FE
CT
ING
KE
OW
EE
HY
DR
OC
ON
DIT
ION
B(l
ID85
)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Res
ervo
irel
evat
ion
805.
0fe
etw
ithal
lsp
iliw
ayga
tes
open
and
the
lake
elev
atio
nco
ntin
ues
tous
e
B.
Seep
age
read
ings
incr
ease
orde
crea
segr
eatly
orse
epag
ew
ater
isca
rryi
nga
sign
ific
ant
amou
ntof
soil
part
icle
s
CN
ewar
eaof
seep
age
orw
etne
ss,
with
larg
eam
ount
sof
seep
age
wat
erob
serv
edon
dam
,da
mto
e,or
the
abut
men
ts
D.
Slid
eor
othe
rm
ovem
ent
ofth
eda
mor
abut
men
tsw
hich
coul
dde
velo
pin
toa
fail
ure
E.D
evel
opin
gfa
ilure
invo
lvin
gth
epo
wer
hous
eor
appu
rten
ant
stru
ctur
esan
dth
eop
erat
orbe
lieve
sth
esa
fety
ofth
est
ruct
ure
isqu
esti
onab
le
3.N
AT
UR
AL
AN
DD
ES
TR
UC
TIV
EP
HE
NO
ME
NA
AF
FE
CT
ING
JOC
AS
SE
EH
YD
RO
CO
ND
ITIO
NB
(BD
86)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Con
diti
onB
has
been
decl
ared
for
the
Joca
ssee
Dam
RE
LE
AS
EO
FT
OX
IC/F
LA
MM
AB
LE
GA
SE
SJE
OP
AR
DIZ
ING
SY
ST
EM
SR
EQ
UIR
ED
TO
MA
INT
AIN
SA
FE
OP
ER
AT
ION
OR
ES
TA
BL
ISH
!M
AIN
TA
INM
OD
ES
(CO
LD
SH
UT
DO
WN
)(l
ID91
)
OP
ER
AT
ING
MO
DE
:A
llA
.R
epor
t/de
tect
ion
of
toxi
cga
ses
inco
ncen
trat
ions
that
will
beli
fe-t
hrea
teni
ngto
plan
tpe
rson
nel
B.
Rep
ort/
dete
ctio
nof
flam
mab
lega
ses
inco
ncen
trat
ions
that
will
affe
ctth
esa
feop
erat
ion
ofth
epl
ant:
•R
eact
orB
uild
ing
•A
uxili
ary
Bui
ldin
g•
Tur
bine
Bui
ldin
g•
Con
trol
Roo
m
OP
ER
AT
ING
MO
DE
:A
ll
A.
Tur
bine
Bui
ldin
gfl
ood
requ
irin
gus
eo
fA
P/l
,2,3
/A/l
700/
10,
(Tur
bine
Bui
ldin
gFl
ood)
4.C
ON
TR
OL
RO
OM
EV
AC
UA
TIO
NH
AS
BE
EN
INIT
IAT
ED
(BD
94)
CO
NT
RO
LR
OO
ME
VA
CU
AT
ION
AN
DP
LA
NT
CO
NT
RO
LC
AN
NO
TB
EE
ST
AB
LIS
HE
D(l
ID96
)
Con
trol
ofth
epl
ant
cann
otbe
esta
blis
hed
from
the
Aux
Shu
tdow
nPa
nel
orth
eSS
Fw
ithin
15m
inut
es
2.K
EO
WE
EH
YD
RO
DA
MF
AIL
UR
E(B
D97
)
OP
ER
AT
ING
MO
DE
:A
ll
Imm
inen
t/ac
tual
dam
failu
reex
ists
invo
lvin
gan
yof
the
follo
win
g:•
Keo
wee
Hyd
roD
am•
Litt
leR
iver
Dam
•D
ikes
A,
B,
C,
orD
•In
take
Can
alD
ike
•Jo
cass
eeD
am-
Con
diti
onA
(CO
NT
INU
ED
)
A.
Eva
cuat
ion
ofC
ontr
olR
oom
(CO
NT
INU
ED
)
AN
D
AN
DO
NE
OF
TH
EF
OL
LO
WIN
G:
Pla
ntco
ntro
lIS
esta
blis
hed
from
the
Aux
shut
dow
nPa
nel
orth
eSS
FO
R
Pla
ntco
ntro
lIS
BE
ING
esta
blis
hed
from
the
Aux
Shut
dow
nPa
nel
orSS
F(C
ON
TIN
UE
D)
2.
UN
US
UA
LE
VE
NT
AL
ER
TS
ITE
AR
EA
EM
ER
GE
NC
YG
EN
ER
AL
EM
ER
GE
NC
Y
(CO
NT
INU
ET
ON
EX
TP
AG
E)
OP
ER
AT
ING
MO
DE
:A
ll
A.
Con
trol
Roo
mev
acua
tion
has
been
init
iate
d
AN
D
3.T
UR
BIN
EB
UIL
DIN
GF
LO
OD
(BD
93)
A.
OP
ER
AT
ING
MO
DE
:A
ll
18
Encl
osu
re4.
7R
P/O
/AI1
000/
OO
1N
atura
lD
isas
ters
,H
azar
ds
and
Oth
erC
ondit
ions
Aff
ecti
ngP
lant
Saf
ety
Pag
e3
of
3
UN
US
UA
LE
VE
NT
jA
LE
RT
SIT
EA
RE
AE
ME
RG
EN
CY
[G
EN
ER
AL
EM
ER
GE
NC
Y
4R
EL
EA
SE
OF
TO
XIC
OR
FL
AM
MA
BL
E5.
OT
HE
RC
ON
DIT
ION
SW
AR
RA
NT
3.O
TH
ER
CO
ND
ITIO
NS
WR
RA
NT
1.O
TH
ER
CO
ND
ITIO
NS
WA
RR
AN
TG
AS
ES
DE
EM
ED
DE
TR
IME
NT
AL
TO
SA
FE
CL
AS
SIF
ICA
TIO
NO
FA
NA
LE
RT
DE
CL
AR
AT
ION
OF
SIT
EA
RE
AD
EC
LA
RA
TIO
NO
FG
EN
ER
AL
OP
ER
AT
JON
OF
TH
EP
LA
NT
(BD
87)
(BD
95)
EM
ER
GE
NC
Y(B
D98
)E
ME
RG
EN
CY
(BD
99)
OP
ER
AT
ING
MO
DE
:A
llO
PE
RA
TIN
GM
OD
E:
All
OP
ER
AT
ING
MO
DE
:A
llO
PE
RA
TIN
GM
OD
E:
All
A.
Rep
ort/
dete
ctio
noft
oxic
orfl
amm
able
gase
sA
.E
mer
genc
yC
oord
inat
orju
dgm
ent
indi
cate
sA
Em
erge
ncy
Coo
rdin
ator
/EO
FD
irec
tor
A.
Em
erge
ncy
Coo
rdin
ator
/EO
FD
irec
tor
that
coul
den
ter
with
inth
esi
tear
eabo
unda
iyin
that
:ju
dgm
ent
judg
men
tin
dica
tes:
amou
nts
that
can
affe
ctno
rmal
oper
atio
nof
the
plan
tP
lant
safe
tym
aybe
degr
aded
Act
ual/
imm
inen
tsu
bsta
ntia
lco
re
(EN
D)
degr
adat
ion
with
pote
ntia
lfo
rlo
ssof
B.
Rep
ort
bylo
cal,
coun
ty,
stat
eof
fici
als
for
cont
ainm
ent
pote
ntia
lev
acua
tion
ofsi
tepe
rson
nel
base
don
offs
ite
even
tIn
crea
sed
mon
itor
ing
ofpl
ant
func
tion
sO
Ris
war
rant
ed
Pote
ntia
lfo
run
cont
roll
ed(E
ND
)ra
dion
ucli
dere
leas
esth
atw
ould
5.O
TH
ER
CO
ND
ITIO
NS
EX
IST
WH
ICH
resu
ltin
ado
sepr
ojec
tion
atth
e
WA
RR
AN
TD
EC
LA
RA
TIO
NO
FA
Nsi
tebo
unda
iygr
eate
rth
an10
00m
Rem
UN
USU
AL
EV
EN
T(B
D88
)T
ED
Eor
5000
mR
emC
DE
Adu
ltT
hyro
id
OP
ER
AT
ING
MO
DE
:A
ll(E
ND
)
A.
Em
erge
ncy
Coo
rdin
ator
dete
rmin
espo
tent
ial
degr
adat
ion
ofle
vel
ofsa
fety
has
occu
rred
(EN
D)
19
Encl
osu
re4.
8R
adia
tion
Mo
nit
or
Rea
din
gs
for
Em
erg
ency
Cla
ssif
icat
ion
RP/
O/A
/100
0/00
1Pa
ge1
of
1
All
RIA
valu
esar
eco
nsi
der
edG
RE
AT
ER
TH
AN
or
EO
UA
LT
O
HO
UR
SS
INC
ER
IA57
R/h
rR
IA58
RIh
r*
RE
AC
TO
RT
RIP
PE
DS
ite
Are
aE
mer
gen
cyG
ener
alE
mer
gen
cyS
ite
Are
aE
mer
gen
cyG
ener
alE
mer
gen
cy
0.0
-<
0.5
5.9E
+00
35.
9E+
004
2.6E
+00
32.
6E+
004
0.5
-<
1.0
2.6E
+00
32.
6E+
004
L1E
+00
31.
IE+
004
1.0-
<1.
51.
9E+0
031.
9E+
004
8.6E
+00
28.
6E+
003
1.5
-<2
.01.
9E+0
031.
9E+
004
8.5E
+00
28.
5E+
003
2.0
-<
2.5
1.4E
+003
1.4E
+00
46.
3E+
002
6.3E
+00
32.
5-
<3.
01.
2E+0
031.
2E+
004
5.7E
+00
25.
7E+
003
3.0
-<3.5
1.1E
+003
1.1E
+00
45.
2E+
002
5.2E
+00
33.
5-
<4.
01 .
OE
+003
I.O
E+0
044.
8E+
002
4.8E
+00
34.
0-
<8.
01.
OE
+003
1.O
E+0
044.
4E+
002
4.4E
+00
3
*R
IA58
isp
arti
ally
shie
lded
20
Encl
osu
re4.
9R
P/0/
A/1
000/
001
Unex
pec
ted/U
npla
nned
Incr
ease
InA
rea
Mo
nit
or
Rea
din
gs
Page
1o
f1
NO
TE
:T
his
Init
iati
ngC
ondi
tion
isno
tin
tend
edto
appl
yto
anti
cipa
ted
tem
pora
ryin
crea
ses
due
topl
anne
dev
ents
(e.g
.;in
core
dete
ctor
mov
emen
t,ra
dwas
teco
ntai
ner
mov
emen
t,de
plet
edre
sin
tran
sfer
s,et
c.).
UN
ITS
1,2
,3
MO
NIT
OR
NU
MB
ER
UN
US
UA
LE
VE
NT
l000x
AL
ER
T
NO
RM
AL
LE
VE
LS
mR
AD
/HR
mR
AD
/HR
RIA
7,H
otM
achi
neSh
opE
leva
tion
796
150
5000
RIA
8,H
otC
hem
istr
yL
abE
leva
tion
796
4200
5000
RIA
10,P
rim
ary
Sam
ple
Hoo
dE
leva
tion
796
830
5000
RIA
11,
Cha
nge
Roo
mE
leva
tion
796
210
5000
RIA
12,
Che
mM
ixT
ank
Ele
vati
on78
380
050
00R
IA13
,W
aste
Dis
posa
lSi
nkE
leva
tion
771
650
5000
RIA
15,H
P!R
oom
Ele
vati
on75
8N
OT
E*
5000
NO
TE
:R
IA15
norm
alre
adin
gsar
eap
prox
imat
ely
9m
Rad
/hr
ona
daily
basi
s.A
pply
ing
l000
xno
rmal
read
ings
wou
ldpu
tthi
sm
onit
orgr
eate
rth
an50
00m
Rad
/hr j
ust
for
anU
nusu
alE
vent
.F
orth
isre
ason
,an
Unu
sual
Eve
ntw
illN
OT
bede
clar
edfo
ra
read
ing
less
than
5000
mR
ad/h
r.
21
Enclosure 4.10 RP/O/A/l000/OOlDefinitions/Acronyms Page 1 of 5
1. List of Definitions and Acronyms
NOTE: Definitions are italicized throughout procedure for easy recognition.
1.1 ALERT - Events are in process or have occurred which involve an actual or potentialsubstantial degradation of the level of safety of the plant or a security event that involvesprobable life threatening risk to site personnel or damage to site equipment because ofHOSTILE ACTION. Any releases are expected to be limited to small fractions of the EPAProtective Action Guideline exposure levels.
1.2 BOMB — Refers to an explosive device suspected of having sufficient force to damage plantsystems or structures.
1.3 COGNIZANT FACILITY STAFF - any member of facility staff, who by virtue of trainingand experience, is qualified to assess the indications or reports for validity and to compare thesame to the EALs in the licenseetsemergency classification scheme. (Does not include staffwhose positions require they report, rather than assess, abnormal conditions to the facility.)
1.4 CONDITION A - Failure is Imminent or Has Occurred - A failure at the dam has occurred oris about to occur and minutes to days may be allowed to respond dependent upon theproximity to the dam.
1.5 CONDITION B - Potentially Hazardous Situation is Developing - A situation where failuremay develop, but preplanned actions taken during certain events (such as major floods,earthquakes, evidence of piping) may prevent or mitigate failure.
1.6 CIVIL DISTURBANCE - A group of persons violently protesting station operations oractivities at the site.
1.7 EXPLOSION - A rapid, violent, unconfined combustion, or catastrophic failure ofpressurized/energized equipment that imparts energy of sufficient force to potentially damagepermanent structures, systems, or components.
1.7 EXTORTION - An attempt to cause an action at the station by threat of force.
1.8 FIRE - Combustion characterized by heat and light. Sources of smoke, such as slipping drivebelts or overheated electrical equipment, do NOT constitutefires. Observation of flames ispreferred but is NOT required if large quantities of smoke and heat are observed.
1.9 FRESHLY OFF-LOADED CORE - The complete removal and relocation of all fuelassemblies from the reactor core and placed in the spent fuel pool. (Typical of a ‘No Modeoperation during a refuel outage that allows safety system maintenance to occur and results inmaximum decay heat load in the spent fuel pool system).
22
Enclosure 4.10 RP/0/A/1000/001Definitions/Acronyms Page 2 of 5
1.10 GENERAL EMERGENCY - Events are in process or have occurred which involve actual orimminent substantial core degradation or melting with potential for loss of containmentintegrity or HOSTILE ACTION that results in an actual loss of physical control of the facility.Releases can be reasonably expected to exceed EPA Protective Action Guidelines exposurelevels offsite for more than the immediate area.
.11 HOSTAGE - A person(s) held as leverage against the station to ensure demands will be metby the station.
1.12 HOSTILE ACTION - An act toward an NPP or its personnel that includes the use of violentforce to destroy equipment, takes HOSTAGES, and/or intimidates the licensee to achieve anend. This includes attack by air, land, or water using guns, explosives, PROJECTILES,vehicles, or other devices used to deliver destructive force. Other acts that satisfy the overallintent may be included. HOSTILE ACTION should not be construed to include acts of civildisobedience or felonious acts that are not part of a concerted attack on the NPP. Non-terrorism-based EALs should be used to address such activities, (e.g., violent acts betweenindividuals in the owner controlled area.)
1.13 HOSTILE FORCE - One or more individuals who are engaged in a determined assault,overtly or by stealth and deception, equipped with suitable weapons capable of killing,maiming, or causing destruction.
1.14 IMMINENT - Mitigation actions have been ineffective, additional actions are not expected tobe successful, and trended information indicates that the event or condition will occur. WhereIMMINENT timeframes are specified, they shall apply.
1.15 INTRUSION — A person(s) present in a specified area without authorization. Discovery of aBOMB in a specified area is indication of INTRUSION into that area by a HOSTILE FORCE.
1.16 INABILITY TO DIRECTLY MONITOR - Operational Aid Computer data points areunavailable or gauges/panel indications are NOT readily available to the operator.
1.17 LOSS OF POWER — Emergency Action Levels (EAL5) apply to the ability of electricalenergy to perform its intended function, reach its intended equipment. Ex. — If both MFBs,are energized but all 4160v switchgear is not available, the electrical energy can not reach themotors intended. The result to the plant is the same as if both MFBs were de-energized.
1.18 PROJECTILE — An object directed toward a NPP that could cause concern for its continuedoperability, reliability, or personnel safety.
1.19 PROTECTED AREA — Typically the site specific area which normally encompasses allcontrolled areas within the security PROTECTED AREA fence.
23
Enclosure 4.10 RP/0/A/1000/001Definitions/Acronyms Page 3 of 5
1.20 REACTOR COOLANT SYSTEM (RCS) LEAKAGE - RCS Operational Leakage asdefined in the Technical Specification Basis B 3.4.13:
RCS leakage includes leakage from connected systems up to and including the secondnormally closed valve for systems which do not penetrate containment and the outermostisolation valve for systems which penetrate containment.
A. Identified LEAKAGE
LEAKAGE to the containment from specifically known and located sources, but does notinclude pressure boundary LEAKAGE or controlled reactor coolant pump (RCP) sealleakoff (a normal function not considered LEAKAGE).
LEAKAGE, such as that from pump seals, gaskets, or valve packing (except RCP sealwater injection or leakoff), that is captured and conducted to collection systems or a sumpor collecting tank;
LEAKAGE through a steam generator (SG) to the Secondary System (primary tosecondary LEAKAGE): Primary to secondary LEAKAGE must be included in the totalcalculated for identified LEAKAGE.
B. Unidentified LEAKAGE
All LEAKAGE (except RCP seal water injection or leakoff) that is not identifiedLEAKAGE.
C. Pressure Boundary LEAKAGE
LEAKAGE (except primary to secondary LEAKAGE) through a nonisolable fault in anRCS component body, pipe wall or vessel wall.
1.21 RUPTURED (As relates to Steam Generator) - Existence of Primary to Secondary leakage ofa magnitude sufficient to require or cause a reactor trip and safety injection.
1.22 SABOTAGE - Deliberate damage, mis-alignment, or mis-operation of plant equipment withthe intent to render the equipment inoperable. Equipment found tampered with or damageddue to malicious mischief may not meet the definition of SABOTAGE until thisdetermination is made by security supervision.
1.23 SECURITY CONDITION — Any Security Event as listed in the approved securitycontingency plan that constitutes a threat/compromise to site security, threat/risk to sitepersonnel, or a potential degradation to the level of safety of the plant. A SECURITYCONDITION does not involve a HOSTILE ACTION.
1.24 SAFETY-RELATED SYSTEMS AREA - Any area within the Protected area whichcontains equipment, systems, components, or material, the failure, destruction, or release ofwhich could directly or indirectly endanger the public health and safety by exposure toradiation.
24
Enclosure 4.10 RP/0/A/l000/0O1Definitions/Acronyms Page 4 of 5
1.25 SELECTED LICENSEE COMMITMENT (SLC) -Chapter 16 of the FSAR
1.26 SIGNIFICANT PLANT TRANSIENT - An unplanned event involving one or more of thefollowing:
(1) Automatic turbine runback>25% thermal reactor power(2) Electrical load rejection >25% full electrical load(3) Reactor Trip(4) Safety Injection System Activation
1.27 SITE AREA EMERGENCY - Events are in process or have occurred which involve actualor likely major failures of plant functions needed for the protection of the public, orHOSTILE ACTION that results in intentional damage or malicious act; (1) toward sitepersonnel or equipment that could lead to the likely failure of or; (2) that prevents effectiveaccess to equipment needed for the protection of the public. Any releases are NOT expectedto result in exposure levels which exceed EPA Protective Action Guideline exposure levelsbeyond the Site Boundary.
1.28 SITE BOUNDARY - That area, including the ProtectedArea, in which DPC has theauthority to control all activities including exclusion or removal of personnel and property(1 mile radius from the center of Unit 2).\
1.29 TOXIC GAS - A gas that is dangerous to life or health by reason of inhalation or skin contact(e.g.; Chlorine).
1.30 UNCONTROLLED - Event is not the result of planned actions by the plant staff.
1.31 UNPLANNED - An event or action is UNPLANNED if it is not the expected result ofnormal operations, testing, or maintenance. Events that result in corrective or mitigativeactions being taken in accordance with abnormal or emergency procedures areUNPLANNED.
1.32 UNUSUAL EVENT - Events are in process or have occurred which indicate a potentialdegradation of the level of safety of the plant or indicate a security threat to facility protectionhas been initiated. No releases of radioactive material requiring offsite response ormonitoring are expected unless further degradation of safety systems occurs.
1.33 VALID - An indication or report or condition is considered to be VALID when it isconclusively verified by: (I) an instrument channel check; or, (2) indications on related orredundant instrumentation; or, (3) by direct observation by plant personnel such that doubtrelated to the instrument’s operability, the condition’s existence, or the report’s accuracy isremoved. Implicit with this defmition is the need for timely assessment.
25
Enclosure 4.10 RP/O/A/l000/OOlDefinitions/Acronyms Page 5 of 5
1.34 VIOLENT - Force has been used in an attempt to injure site personnel or damage plantproperty.
1.35 VISIBLE DAMAGE - Damage to equipment or structure that is readily observable withoutmeasurements, testing, or analyses. Damage is sufficient to cause concern regarding thecontinued operability or reliability of affected safety structure, system, or component.Example damage: deformation due to heat or impact, denting, penetration, rupture.
I .36 VITAL AREA - An area within the protected area where an individual is required to badge into gain access to the area that houses equipment important for nuclear safety. The failureor destruction of this equipment could directly or indirectly endanger the public health andsafety by exposure to radiation.
26
Enclosure 4.11 /O/A/1000/o0IOperating Modes Defined In Improved Page 1 of 1
Technical Specifications
MODES
REACTIVITY % RATED AVERAGECONDITION THERMAL REACTOR COOLANT
MODE TITLE POWER (a) TEMPERATURE(Keff) (°F)
1 Power Operation >0.99 > 5 NA
2 Startup 0.99 <5 NA
3 Hot Standby <0.99 NA 250
4 Hot Shutdown (b) < 0.99 NA 250 > T> 200
5 Cold Shutdown (b) < 0.99 NA < 200
6 Refueling (c) NA NA NA
(a) Excluding decay heat.
(b) All reactor vessel head closure bolts fully tensioned.
(c) One or more reactor vessel head closure bolts less than fully tensioned
27
Enclosure 4.12 /O/A/1ooo/oolInstructions For Using Enclosure 4.1 Page 1 of 2
1. Instructions For Using Enclosure 4.1 — Fission Product Barrier Matrix
1.1 If the unit was at Hot S/D or above, (Modes 1, 2, 3, or 4) and one or more fissionproduct barriers have been affected, refer to Enclosure 4.1, (Fission Product BarrierMatrix) and review the criteria listed to determine if the event should be classified.
1.1.1 For each Fission Product Barrier, review the associated EALs to determineif there is a Loss or Potential Loss of that barrier.
NOTE: An event with multiple events could occur which would result in the conclusion thatexceeding the loss or potential loss thresholds is imminent (i.e. within 1-3 hours). Inthis situation, use judgement and classif, as if the thresholds are exceeded.
1.2 Three possible outcomes exist for each barrier. No challenge, potential loss, or loss.Use the worst case for each barrier and the classification table at the bottom of thepage to determine appropriate classification.
1.3 The numbers in parentheses out beside the label for each column can be used toassist in determining the classification. If no EAL is met for a given barrier, thatbarrier will have 0 points. The points for the columns are as follows:
Barrier Failure Points
RCS Potential Loss 4
Loss 5
Fuel Clad Potential Loss 4
Loss 5
Containment Potential Loss 1
Loss 3
1.3.1 To determine the classification, add the highest point value for each barrierto determine a total for all barriers. Compare this total point value withthe numbers in parentheses beside each classification to see which oneapplies.
1.3.2 Finally as a verification of your decision, look below the EmergencyClassification you selected. The loss and/or potential loss EALs selectedfor each barrier should be described by one of the bullet statements.
28
Enclosure 4.12
Instructions For Using Enclosure 4.1 Page 2 of 2
EXAMPLE: Failure to properly isolate a ‘B’ MS Line Rupture outside containment, results inextremely severe overcooling.
PTS entry conditions were satisfied.
Stresses on the ‘B’ S/G resulted in failure of multiple S/G tubes.
RCS leakage through the S/G exceeds available makeup capacity as indicated byloss of subcooling margin.
Barrier EAL Failure Points
RCS SGTR> Makeup capacity of one HPT pump in Potential Loss 4normal makeup mode with letdown isolated
Entry into PTS operating range Potential Loss 4
RCS leak rate> available makeup capacity as Loss 5indicated by a loss of subcooling
Fuel Clad No EALs met and no justification for No 0classification on judgment
Challenge
Containment Failure of secondary side of SG results in a Loss 3direct opening to the environment
RCS 5 + Fuel 0 + Containment 3 = Total 8
A. Even though two Potential Loss EALs and one Loss EAL are met forthe RCS barrier, credit is only taken for the worst case (highest pointvalue) EAL, so the points from this barrier equal 5.
B. No EAL is satisfied for the Fuel Clad Barrier so the points for thisbarrier equal 0.
C. One Loss EAL is met for the Containment Barrier so the points forthis barrier equal 3.
D. When the total points are calculated the result is 8, therefore theclassification would be a Site Area Emergency.
E. Look in the box below “Site Area Emergency”. You have identified aloss of two barriers. This agrees with one of the bullet statements.The classification is correct.
29
References:
1. PIP 0-05-02980
2. PIP 0-05-4697
3. PIP 0-06-0404
4. PIP 0-06-03347
5. PIP 0-09-00234
6. PIP 0-10-1055
7. PIP 0-10-01750
8. PIPO-11-02811
9. PIP 0-12-1590
10. PIP 0-10-7809
11. PIPO-12-9201
12. PIP 0-12-9198
13. PIP 0-12-11227
Enclosure 4.13 RP!O/A/l000/oolReferences Page 1 of I