r. giles, s. golbek, a. sullivan, j. wood 2 1 ecology and ... · r. giles, s. golbek, a. sullivan,...

15
R. Giles, S. Golbek, A. Sullivan, J. Wood 2 Ecology and Transportation: The I-90 Snoqualmie Pass East Project’s Design Engineering 1 Challenges of Integrating Transportation Needs with Landscape-Level Connectivity and 2 Transportation Corridor Crossing Objectives 3 4 5 6 7 8 9 10 11 12 Randy Giles 13 I-90 Project Director 14 509-577-1879 15 [email protected] 16 17 Scott Golbek 18 I-90 Project Engineering Manager 19 509-577-1880 20 [email protected] 21 22 Amanda Sullivan, corresponding author 23 I-90 Project Communications 24 509-577-1942 25 [email protected] 26 27 Jerry Wood 28 I-90 Project Assistant Engineering Manager 29 509-577-1882 30 [email protected] 31 32 1710 S. 24 th Ave., Ste. 100 33 Yakima, WA 98902 34 Fax: 509-577-1869 35 36 37 38 39 40 41 42 43 Submission Date: July 30, 2009 44 Re-submission Date: Nov. 12, 2009 45 Word Count: 7,286, including 5 figures 46 TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Upload: others

Post on 20-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

2

Ecology and Transportation: The I-90 Snoqualmie Pass East Project’s Design Engineering 1 Challenges of Integrating Transportation Needs with Landscape-Level Connectivity and 2

Transportation Corridor Crossing Objectives 3 4 5 6 7 8 9 10 11 12

Randy Giles 13 I-90 Project Director 14

509-577-1879 15 [email protected] 16

17 Scott Golbek 18

I-90 Project Engineering Manager 19 509-577-1880 20

[email protected] 21 22

Amanda Sullivan, corresponding author 23 I-90 Project Communications 24

509-577-1942 25 [email protected] 26

27 Jerry Wood 28

I-90 Project Assistant Engineering Manager 29 509-577-1882 30

[email protected] 31 32

1710 S. 24th Ave., Ste. 100 33 Yakima, WA 98902 34 Fax: 509-577-1869 35

36 37 38 39 40 41 42

43 Submission Date: July 30, 2009 44

Re-submission Date: Nov. 12, 2009 45 Word Count: 7,286, including 5 figures 46

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 2: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

3

1 ABSTRACT 2 3 ECOLOGY AND TRANSPORTATION: THE I-90 SNOQUALMIE PASS EAST 4 PROJECT’S DESIGN ENGINEERING CHALLENGES OF INTEGRATING 5 TRANSPORTATON NEEDS WITH LANDSCAPE-LEVEL CONNECTIVITY AND 6 TRANSPORTATION CORRIDOR CROSSING OBJECTIVES 7

8 The Washington State Department of Transportation’s I-90 Snoqualmie Pass East Project (I-90 Project) 9 has presented WSDOT engineers with many unique design challenges when integrating the ecological 10 needs of the area with the transportation objectives of the project. 11

In addition to addressing issues regarding capacity, deteriorating concrete pavement, unstable 12 rock slopes, and road closures associated with avalanches, a significant project need is to improve 13 ecological connectivity of the area. I-90 is a physical barrier to the north-south movement of fish and 14 wildlife. Wildlife attempting to cross over the interstate present a safety concern to motorists, and the 15 barrier I-90 forms between upstream and downstream aquatic habitats affects fish passage and hydrologic 16 processes. 17

To identify areas where investments in ecological connectivity should be made, WSDOT worked 18 with dozens of agencies that manage land resources in the project area to design bridges and culverts that 19 improve wildlife and aquatic connections. Integrating ecological objectives presented many design 20 engineering challenges due to the project area’s unfavorable construction conditions. Trade-offs and 21 compromises between WSDOT and land resource managers were needed to find suitable solutions to 22 problems. Issues that required compromises included: eliminating scour issues while maximizing 23 restoration areas; improving ground conditions for foundations without impacts to wetlands, endangered 24 species, and footprint; creating habitat connections while treating stormwater; and designing bridges for 25 clearance and connecting habitat. 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 3: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

4

ECOLOGY AND TRANSPORTATION: THE I-90 SNOQUALMIE PASS EAST 1 PROJECT’S DESIGN ENGINEERING CHALLENGES OF INTEGRATING 2 TRANSPORTATON NEEDS WITH LANDSCAPE-LEVEL CONNECTIVITY AND 3 TRANSPORTATION CORRIDOR CROSSING OBJECTIVES 4 5 The Washington State Department of Transportation’s (WSDOT) I-90 Snoqualmie Pass East Project (I-90 6 Project) is a 15-mile highway improvement project that will ensure the continued availability of Interstate 7 90 as a primary statewide corridor. Through the I-90 Project, WSDOT will improve the safety and 8 reliability of this corridor by reducing avalanche risks to the traveling public, minimizing road closures 9 required for avalanche control work, and reducing the risk of rock and debris falling onto the interstate 10 from unstable slopes. WSDOT will also fix structural deficiencies and provide for the recent and 11 predicted increases in traffic volume. Ecological connectivity is another important project component. 12 WSDOT will work to reduce wildlife / vehicle collisions by re-connecting habitat across I-90 and 13 improving mobility of aquatic species and wildlife. 14

Plans for the project include widening the existing four lane interstate to six lanes, replacing 15 deteriorated concrete pavement, straightening sharp roadway curves, stabilizing unstable rock slopes, 16 building a new, more efficient snowshed (a concrete shed covering the roadway to provide permanent 17 protection from avalanches and other falling debris to travelers passing through Snoqualmie Pass), and 18 constructing wildlife crossings structures. 19 The first five miles of the I-90 Project from Hyak to Keechelus Dam received funding in 2005 20 from the Washington State Legislature through the Transportation Partnership Account – a 9.5 cent 21 increase in the gas tax – in the amount of $595 million. The remaining 10 project miles from Keechelus 22 Dam to Easton remain unfunded. 23

The I-90 Project corridor is located high along a mountain pass in the Central Cascades. The 24 area’s extreme weather conditions and inherent geographical and geotechnical complexities has presented 25 WSDOT I-90 Project engineers with many challenges when designing this improvement project. 26 Integrating ecological connectivity objectives with transportation objectives has also presented 27 challenges. Conflicts in objectives regarding crossing structure designs often surfaced that required the I-28 90 Project design team and partnering resource agencies to compromise and accept trade-offs in order to 29 move the project forward. Finding the right designs to optimize benefits required a great deal of 30 collaboration, technical investigation, and engineering review. 31

In the following paper, several case studies will be provided depicting how conflicts in design 32 between WSDOT engineers and various resource agencies, inter-disciplinary teams, and technical 33 committees were managed to resolve issues and reach compromises with satisfactory outcomes. 34

In order to understand how WSDOT and project stakeholders integrated transportation and 35 ecological connectivity objectives into the I-90 Project, it’s first necessary to understand the environment 36 in which WSDOT is working and the process for developing the project’s purpose and need. 37 38 I-90 PROJECT CORRIDOR ATTRIBUTES 39 I-90 spans 300 miles in Washington state from the Port of Seattle to the Idaho state line, and then 40 continues east across the United States to Boston, MA. I-90 is the major east-west transportation corridor 41 across Washington and is vital to the state’s economy (see figure 1) (1). 42 43 44 45 46 47 48 49 50

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 4: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

5

1 FIGURE 1 State of Washington map with I-90 Project corridor 2 Figure 1 shows Interstate 90, the I-90 Project location, and typical topography. 3

4 The I-90 Project improves a 15-mile portion of I-90, beginning on the eastern side of Snoqualmie 5

Pass at milepost 55.1, just east of the Hyak Interchange, where the existing highway narrows from six 6 lanes to four lanes. The project end point is at milepost 70.3 at the West Easton Interchange, where the 7 terrain becomes flatter and the highway is straighter. This 15-mile stretch of I-90 is in Kittitas County, 8 WA, and is predominately located on federal land within the Okanogan-Wenatchee National Forest. 9

The project corridor is located along a high mountain pass in the Central Cascades. The general 10 topography is one of mountainous peaks and valleys. For the first six miles of the project area, I-90 runs 11 along a narrow corridor between the shores of Keechelus Lake, a deep-water agricultural reservoir, and 12 steep mountain slopes (see figure 2). These steep mountain slopes contain volcanic bedrock at varying 13 depths that are subject to deep fissures and stress cracks with weakened slip planes, which when 14 combined with high annual precipitation and freeze-thaw conditions, makes them susceptible to 15 landslides, debris flow, and avalanches. 16

I-90 is built primarily within an easement on National Forest land. The large areas of protected 17 state, federal, and conservation lands north and south of I-90 support a broad range of habitats and a 18 diverse array of plants and wildlife. Since the late 1990s, the area has been managed according to the 19 Snoqualmie Pass Adaptive Management Area Plan. This plan requires protection of old-growth habitat, 20 removal of portions of existing Forest Service roads, and management of recreation to facilitate species 21 movement. In recent years, there have been substantial private and public land conservation efforts to 22 protect old-growth forest, provide larger contiguous blocks of forested habitat, and facilitate habitat 23 connectivity across the I-90 corridor through the acquisition of private land. The Cascades Conservation 24 Partnership, the Mountains-to-Sound Greenway Trust, the U.S. Fish and Wildlife Service (USFWS), and 25 the U.S. Forest Service (USFS) have invested over $100 million in these efforts during the last five years. 26 These land purchases, along with the I-90 Land Exchange, have added 75,000 acres (approximately 117 27 square miles) of land to the National Forest system adjacent to and within the I-90 Project area (2). 28

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 5: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

6

Even with conservation efforts, I-90’s presence limits wildlife movement and forms a physical 1 barrier between upstream and downstream aquatic environments. Existing culverts and narrow bridges 2 limit aquatic species movement, and in many cases, the highway embankment has filled in habitat that 3 once made up channels, floodplains, and associated wetlands (1). Adequate connections between habitats 4 and hydrologic features on either side of I-90 are necessary for the continued health of the project area’s 5 diverse ecosystems. 6

The last major road construction on I-90 Snoqualmie Pass began in the 1950s when President 7 Dwight D. Eisenhower signed the Federal-Aid Highway Act of 1956, which started the construction of 8 Interstate Highways; construction was completed in the 1970s. Since the 1970s, the state’s transportation 9 needs for I-90 over Snoqualmie Pass have changed, and the existing roadway has deteriorated. 10

Today, daily traffic on Snoqualmie Pass averages about 27,000 vehicles, typically 22,400 11 passenger vehicles and 4,600 freight vehicles. Traffic volumes can rise to more than 59,000 vehicles on 12 weekends and holidays. According to WSDOT traffic studies, travel across Snoqualmie Pass is growing 13 at an annual rate of 2.1 percent, with 51,000 vehicles projected to use I-90 daily by 2028. 14 15 IDENTIFYING A PROJECT PURPOSE AND NEED 16 Seeing a need for additional highway capacity and safety improvements, WSDOT began the public 17 scoping process for the I-90 Project in 1999. By 2000, an Interdisciplinary Team (IDT) was formed 18 consisting of representatives from WSDOT, the Federal Highways Administration (FHWA), USFS, 19 Environmental Protection Agency (EPA), USFWS, and Washington Department of Fish and Wildlife 20 (WDFW); advisory agencies included Washington State Parks, U.S. Army Corps of Engineers, and 21 Washington Department of Ecology (Ecology). The IDT was formed to begin preliminary engineering 22 and environmental analysis of the project area. Additional teams were formed, including a Mitigation 23 Development Team consisting of biologists and hydrologists from WSDOT, USFS, USFW, and WDFW, 24 and a Wetlands Mitigation Technical Committee consisting of a GIS specialist, biologist, and 25 environmental planner, to conduct further environmental analyses and provide design recommendations. 26

After five years of corridor analysis, WSDOT published the I-90 Snoqualmie Pass East Project Draft 27 Environmental Impact Statement (Draft EIS) for public review and comment in 2005. The Draft EIS 28 highlighted six build alternatives that could potentially meet the project’s identified purpose and need for: 29

Reducing the risks of avalanche to the traveling public and eliminating road closures required for 30 avalanche control work, 31

Reducing the risk of rock and debris falling onto the roadway from unstable slopes, 32 Fixing roadway structural deficiencies by replacing damaged pavement, 33 Providing for the growth-related increases in traffic volume, and 34 Connecting habitat across I-90 for fish and wildlife (3). 35 Over the next two years, WSDOT continued using existing partnerships and formed new teams, 36

including a Stormwater Technical Committee and Wildlife Monitoring Technical Committee to help 37 advance technical investigations and identify a preferred design alternative for the I-90 Project. These 38 collaborative efforts culminated with the release of the Final EIS in August 2008 that identified 39 WSDOT’s preferred design alternative for the I-90 Project. FHWA issued its Record of Decision 40 concurring with WSDOT’s preferred alternative in October 2008, which paved the way to complete final 41 design and for construction to begin. 42 43 DEVELOPING I-90 PROJECT DESIGN CONCEPTS 44 After identifying the I-90 Project Preferred Alternative, project engineers began working with the IDT, 45 Mitigation Team, and Wetlands Committee to develop conceptual design plans for ecological 46 connectivity structures. 47

The Mitigation Team presented design engineers with scientific information and site-specific 48 technical report data that determined the existing ecological conditions within the project area. This data 49 identified 14 north-south ecological linkage areas, or Connectivity Emphasis Areas (CEAs), within the 50

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 6: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

7

project area that provided the highest benefit-to-cost ratio and long-term solutions to the issue of 1 ecological connectivity (see figure 2). 2

3 FIGURE 2 15-mile project corridor north-south ecological linkages 4 Figure 2 shows identified CEAs and the bridges and culverts (in yellow) that will be placed at each CEA to 5 improve connectivity. 6

7 Each CEA provided an opportunity to improve connectivity for a unique assemblage of species. 8

CEAs ranged in complexity from single stream crossings to multiple stream crossings with associated 9 wetlands and areas of diffused surface flow, to upland areas that were important travel corridors for 10 wildlife (2). The Mitigation Team found that crossing structures would be more effective for some species 11 if they contained habitat, rather than simply being physical connections between habitats on opposite 12 sides of the highway. For instance, lower mobility animals would feel more secure crossing a structure if 13 it contained hiding cover. Different animals show different preferences for crossing structures, whether 14 the structures are small, medium, or large (2). 15

After analyzing all of the Mitigation Team’s recommendations, WSDOT engineers and the 16 Mitigation Team collaborated to develop conceptual designs for the highway alignment, drainage plans, 17 staging and construction requirements, traffic control strategies, and initial bridge plans at each CEA. The 18 design team also continued to develop designs independently. 19

While working with the Mitigation Team and technical committee, WSDOT and consultant 20 engineers were also gathering geotechnical data from extensive drilling operations on the mountain 21 slopes, in the lakebed of Keechelus Lake, and along the existing roadway to determine geological 22 conditions. This data was essential to progressing conceptual CEA designs. 23

Geotechnical findings indicated that certain portions of the project area contained stable rock and 24 favorable sediment, while other areas contained soft frangible rock and liquefiable soil conditions. Since 25 liquefiable soil conditions result in global instability of structure foundations, WSDOT engineers had to 26 rethink how to construct certain CEA concepts (bridges and culverts). Engineers worked to improve 27 conditions and meet seismic regulations while still aligning with Mitigation Team and Wetlands 28 Committee recommendations. In addition to seismic issues, WSDOT engineers had to reformat other 29 CEA designs to address other unforeseen issues pertaining to erosion, stormwater treatment, clearance, 30 and constructability. These design changes had to be made in a way that minimized footprint impacts, 31 prevented wetland impacts, considered endangered species in the area, and preserved archeological, 32 cultural, and recreational resources. 33

In the following sections, case studies will explain how WSDOT I-90 Project engineers modified 34 original design concepts to resolve conflicts between ecological connectivity recommendations and 35 objectives and the unforeseen seismic, erosion, stormwater treatment, clearance, constructability, and 36 other resource issues. 37

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 7: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

8

1 IMPROVING GROUND CONDITIONS AT GOLD CREEK CEA WITHOUT IMPACTS TO 2 WETLANDS, ENDANGERED SPECIES, AND FOOTPRINT 3 An important CEA identified by the Mitigation Team is located near the Gold Creek Valley. The Gold 4 Creek CEA is located between milepost 55.2 and milepost 55.8, near the starting point of the I-90 Project. 5 Gold Creek crosses I-90 under 138- and 126-foot bridges and empties into Keechelus Lake at the 6 northwest tip of the lake. This CEA connects old growth stands in mountain hemlock-subalpine fir forests 7 and provides important hydrologic functions for Gold Creek. Gold Creek represents a critical area for 8 linking the Alpine Lakes Wilderness to the Norse Peak Wilderness, which, in turn, links to other 9 wilderness areas and national parks throughout the Washington Cascade Mountains (2). 10

To be successful at meeting objectives, WSDOT and the Mitigation Team determined a high 11 level of connectivity for the high- and low-mobility species associated with the mountain hemlock-12 subalpine fir forests, riparian habitats, wetlands, and floodplains must be provided year-round. Other 13 objectives for this CEA include: 14

Providing a high level of connectivity across the reservoir bed for approximately nine to 10 15 months of the year. (The Keechelus Lake reservoir inundates the lakebed at high pool during late 16 spring.) 17

Significantly reducing wildlife / vehicle accidents in this high road-kill zone for deer and elk. 18 This will require wildlife fencing around the crossing structures. 19

Restoring natural channel migration processes and reducing floodplain confinement, particularly 20 upstream of I-90 where floodplains and associated wetlands are not inundated by Keechelus 21 Lake; restoring capacity to convey flood flows, sediment, and debris through the Gold Creek 22 crossing structure. 23

Providing fish passage and habitat improvements for threatened bull trout for the full range of 24 lake elevations. 25

Improving water quality by properly treating stormwater and highway runoff, and minimizing de-26 icer chemical use. 27 The initial Gold Creek CEA concept recommended by the IDT and accepted by WSDOT was to 28

replace the existing 138- and 126-foot bridges with a 1,200-foot eastbound bridge and a 1,000-foot 29 westbound bridge (2). This would provide a connection through the highway for approximately nine 30 to 10 months a year. Additional clearance for winter snowpack was also recommended. 31

After identifying objectives and conceptual Gold Creek CEA bridge designs, WSDOT conducted 32 geotechnical drilling at the Gold Creek area. Geotechnical findings indicated areas of liquefiable soil 33 conditions at the Gold Creek CEA site. Liquefiable soils (typically saturated sand) are a concern because 34 during an earthquake, the soil looses shear strength and can flow like a liquid. This results in global 35 foundation stability issues with bridge designs. To construct the bridges and meet seismic code 36 requirements, WSDOT engineers would need to stabilize ground conditions. 37

Engineers originally proposed to improve liquefiable soils with a technique known as bottom-fed 38 vibro-replacement stone columns. The stone columns were to range in diameter from 2.5 feet to 3.5 feet 39 and would be constructed on a grid pattern designed to suit the load, soil, and performance types. 40 Column holes were to be bored at varying design depths of approximately 50 feet deep in places, then 41 dense, angular crushed or shot rock backfill would be introduced in discrete lifts from the ground surface. 42 Re-penetration of each lift would compact the stone in the surrounding soil. Once complete, the 43 replacement stone columns would have effectively reduced foundation settlement, mitigated liquefaction 44 potential, improved shear resistance, and increased bearing capacity. 45

The ecological impacts of the vibro-replacement ground stabilization technique, however, raised 46 red flags among partnering resource agencies. Partners were concerned that construction of the stone 47 columns would temporarily and permanently impact wetlands and expand the footprint of the roadway 48 prism. This technique would require a pattern of stone columns roughly 50 feet beyond the toe of the 49 highway embankment, necessitating construction within adjacent wetlands. 50

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 8: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

9

Understanding the importance of addressing resource agency concerns, WSDOT design engineers 1 developed a list of plausible alternatives for improving the soil conditions at Gold Creek. WSDOT 2 presented these alternatives to its partners, and together, determined an acceptable method of improving 3 ground conditions that met both transportation and ecological connectivity objectives. 4

The new, agreed-upon method of improving the liquefiable soils is compaction grouting. A very 5 viscous (low-mobility), aggregate grout will be pumped in stages, starting up to 50 feet deep in places and 6 working toward the ground surface. The grout will form a column of bulbs, which densifies and displaces 7 the surrounding soils. WSDOT will construct the grout columns on a grid pattern designed to suit load, 8 soil, and seismic performance. Once complete, the grout columns will reduce foundation settlement, 9 mitigate liquefaction potential, improve shear resistance, and increase bearing capacity. This technique 10 uses a much smaller pattern (20-feet by 30-feet in total), localizes impacts to directly beneath the 11 embankment fill area next to the bridge abutment, and allows minimization of the highway footprint. 12 13 ELIMINATING SCOUR ISSUES AT GOLD CREEK BRIDGES WHILE MAXIMIZING THE 14 RESTORATION AREA 15 The Gold Creek CEA serves as a wildlife crossing structure, restores natural channel migration processes, 16 and reduces floodplain confinement. Because of high spring flows within the creek, WSDOT engineers 17 had to plan for scour in their bridge designs. Original bridge designs called for optimizing costs by 18 keeping the foundations shallow - above ground water level - and using “launching toe” revetments 19 consisting of large rip-rap to protect the foundation embankments (see figure 3). 20

The height and width of the planned revetments, however, resulted in a conflict with CEA 21 objectives. Partnering resource agencies were concerned revetments would reduce clearance and 22 openness, limit the amount of re-vegetation that could occur, and reduce the amount of available wetland 23 credit for the restoration area under the bridges. 24

WSDOT design engineers and the resource agencies collaborated on finding a new design that 25 would satisfy CEA objectives and scour mitigation costs. The resulting compromise in design called for 26 lowering the armament to just below ground level, thereby enabling re-vegetation and openness of the 27 area. Bridge foundations will be accompanied by large rocks inserted under ground, near the scour level 28 at the toe of the bridge (see figure 3). 29

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 9: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

10

1 FIGURE 3 Gold Creek bridge foundations 2 Figure 3 show the original and modified designs for the Gold Creek Bridge foundations. 3 4 CREATING A HABITAT CONNECTION AT GOLD CREEK CEA/UPPER KEECHELUS 5 LAKE, WHILE TREATING STORMWATER AND REDUCING WETLAND IMPACTS 6 The I-90 Project corridor passes through the Wenatchee National Forest and runs adjacent to the north 7 eastern shore of Keechelus Lake for the first six miles, then parallels the Yakima River for the remaining 8 nine miles. The project crosses five tributaries to Keechelus Lake and nine significant tributaries to the 9 Yakima River, including the Kachess River. The project also crosses or is adjacent to numerous wetlands 10 (4). Therefore, incorporating stormwater management systems into I-90 Project is essential for 11 minimizing contamination of terrestrial and aquatic habitats. Stormwater treatment facilities also present 12 WSDOT with the opportunity to repair water quality problems caused by the existing highway. For 13 example, in certain creeks located within the project area, water quality has been effected due in part, to 14 sediment (traction sand from both I-90 and the adjacent WSDOT Maintenance facility sandpile), and the 15 presence of metals (lead and arsenic) in stormwater runoff. 16

The selection, design, and mitigation process for this stormwater system is complex. Portions of 17 the project are located on steep slopes (rock cliffs) where construction of Stormwater Best Management 18 Practices (BMPs) would be very difficult and require extensive structural support. Other typical freeway 19 BMPs such as infiltration swales and ditches are infeasible because portions of the project are located in 20 narrow corridors where cliffs are on one side of the freeway, and a lake or river is on the other side, with 21 no room for a median. And while not exactly a physical constraint, snow management and snow 22 hydrology plays a large role in how space is utilized and what BMPs are most suitable, with open areas in 23 the median or adjacent to the freeway likely doubling as both snow storage areas as well as stormwater 24 BMP locations (4). 25

To help identify issues and find the best solutions to solve stormwater treatment challenges, 26 WSDOT created a multi-agency Stormwater Technical Committee to review stormwater technical and 27

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 10: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

11

permitting issues; evaluate mitigation approaches developed by WSDOT; and recommend appropriate, 1 effective, and efficient mitigation methods to the design team. Committee members included WSDOT 2 and consultants, USFS, and EPA staff that have permitting approval roles or are partner agencies with a 3 strong interest in helping solve stormwater problems. 4

WSDOT and the Stormwater Committee conducted several in-depth studies and determined that a 5 stormwater treatment and snow storage facility was needed near the Gold Creek CEA. The identified 6 preferred location for the facility was at the WSDOT Maintenance facility, just west of the Gold Creek 7 CEA, where additional upland habitat was being created to enhance the effectiveness of a planned 8 undercrossing. WSDOT engineers believed they could further enhance the Gold Creek CEA’s 9 effectiveness by reducing visibility and noise of the stormwater treatment facility and reducing noise from 10 the maintenance facility by building a separation between the two areas. 11

Plans originally called for using a wide grassy swale to treat stormwater from the maintenance 12 facility and building of a tall berm at the upland below the undercrossing to reduce light and noise. 13 Engineers also planned for snow storage within the grassy swale. 14

As designs progressed, however, resource agencies expressed concerns over the footprint of the 15 Keechelus Lake bench design and its impact to the wetland. But because so many transportation facility 16 design objectives and ecological objectives needed to be met at this one location, all parties had to 17 compromise on design. To reach compromises, several organized meetings were held among engineers, 18 technical committees, and resource agencies. In the end, WSDOT compromised for less snow storage 19 space and a more compact stormwater BMP with higher maintenance requirements. The resource 20 agencies compromised by allowing minor wetland and footprint impacts through a shorter, vegetated 21 berm and reduced upland area, versus the previous taller bench design. WSDOT will add vegetation - tall 22 trees - to the shorter and smaller berm design to make up the reduced structure height (see figure 4). 23

24 FIGURE 4 Near shore habitat 25

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 11: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

12

Figure 4 shows the conceptual plans for lowering the berm and vegetating it with 1 tall trees to reduce noise and visibility of the stormwater treatment facility. 2 3 Other Stormwater Treatment Design Challenges 4 Further challenges arose when designing other stormwater treatment facilities for the I-90 Project. Since 5 the project corridor is constrained for most treatment options, Media Filter Drains (MFDs) were selected 6 and approved by Ecology as the most viable treatment option for use along the corridor. MFD’s are linear 7 flow-through stormwater treatment BMPs that can be placed along a highway shoulder for the treatment 8 of sheet flow runoff generated from the highway pavement. MFD’s remove suspended solids, 9 phosphorus, and metals from highway runoff through physical straining, ion exchange, carbonate 10 precipitation, and biofiltration. 11

MFDs as approved by Ecology, however, are not inline with USFS invasive species guidelines 12 since they do not allow for vegetated plantings. While WSDOT has engaged in a pilot program to test 13 growing vegetation on MFDs elsewhere in the state, the pilot program is still underway and vegetated 14 MFDs are still considered experimental. WSDOT sought and obtained approval for use of a vegetated 15 MFD on Snoqualmie Pass in order to meet USFS objectives. 16 17 ELIMINATING SCOUR ISSUES AT WOLFE CREEK CEA WHILE ENHANCHING 18 WILDLIFE AND AQUATIC MOBILITY 19 The Wolfe Creek CEA is located between milepost 57.1 and milepost 57.3. The forest habitat adjacent to 20 this CEA is the Western Hemlock Series, grading into the Pacific Silver Fir Series at higher elevations. 21 The creek has a very steep gradient and provides limited fish habitat, although Pacific giant salamanders 22 and tailed frogs are relatively common (2). 23

Currently, Wolfe Creek passes under I-90 in a 6-foot box culvert and empties into the east side of 24 Keechelus Lake. The Mitigation Team recommended that WSDOT construct a 25-foot by 8-foot 25 bottomless culvert westbound and a 20-foot by 10-foot bottomless culvert eastbound to meet the 26 connectivity needs of wildlife and aquatic organisms, while passing flood flows and debris. This 27 conceptual bridge would need to meet WDFW stream requirements for fish bearing streams. 28

As engineering designs progressed at this CEA, hydrologic analysis identified scour issues from 29 the high-velocity, steep gradient stream that could undermine the culvert foundations and walls. WSDOT 30 engineers considered using larger foundations for the bottomless culvert design, but the larger, deeper 31 foundations were costlier and generated additional construction impacts to the creek banks and / or 32 wetlands. Engineers also explored bridge options, versus a culvert, but again, foundation and cost issues 33 proved formidable challenges. 34

Design engineers, working with WDFW, developed an alternative that included a four-sided box 35 culvert with a stream-simulated bottom. The stream-simulated bottom, a standard WSDOT practice, was 36 designed deep enough to hold four feet of stream-simulation material and maintain the eight feet of 37 clearance needed to meet Mitigation Team recommendations. WSDOT presented this design option to 38 resource agencies, and after thorough review, the agencies agreed that the four-sided box culvert design 39 would provide a high-level of protection for the roadway against scour and still meet the connectivity 40 objectives of restoring capacity for flood and debris flow, providing fish passage for the full range of lake 41 elevations, and providing aquatic organism connectivity. 42 43 DESIGNING ROCKY RUN BRIDGES FOR CLEARANCE AND CONNECTING HABITAT 44 The Rocky Run Creek CEA is located between milepost 56.7 and milepost 56.9, with the creek 45 originating above 4,800 feet elevation at Lake Lillian. The forest habitat adjacent to this CEA is the 46 Western Hemlock Series, grading into the Pacific Silver Fir Series at higher elevations. The creek flows 47 into the east side of Keechelus Lake and has a fairly steep gradient, although several fish species use this 48 system. 49

The existing I-90 crossing over Rocky Run Creek is a 40-foot-long bridge eastbound and two 6-50 foot pipe culverts westbound. The Mitigation Team recommended that WSDOT improve connectivity in 51

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 12: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

13

this area by building twin 120-foot bridges to meet the needs of wildlife and aquatic organisms, while 1 passing flood flows and debris (2). 2

The challenge for WSDOT engineers was to design the Mitigation Team-recommended bridges 3 to optimize clearance beneath the bridges for openness of habitat while keeping the footprint of the 4 highway small to avoid impacts to Keechelus Lake. WSDOT engineers wanted to achieve clearance of at 5 least 16-feet for each Rocky Run bridge to account for snow pack. Varying topography and road profiles 6 between the separated eastbound and westbound lanes at Rocky Run Creek however, would not allow 7 engineers to achieve the clearance needed without further elevating the road profile and increasing the 8 highway footprint. Elevating the profile, however, would not meet design standards for design speeds and 9 also presented safety considerations. To elevate the road profile, engineers would have to create a large 10 crest in the road, creating visibility issues and impacting other resources by enlarging the footprint. 11

WSDOT engineers decided to go back to the drawing board for the Rocky Run Creek bridge 12 designs. Engineers first determined that the new I-90 road profile at Rocky Run Creek needed to be built 13 at the same elevation for both eastbound and westbound lanes across the separated highway to minimize 14 footprint. Engineers also determined that the only way to keep the consistent elevation levels across the 15 bridges, while adding habitat benches under the bridges for connectivity purposes, was to compromise 16 bridge clearance on the westbound structure. The resulting design called for a westbound bridge with 17 reduced clearance and an eastbound bridge with greater clearance (see figure 5). The eastbound bridge 18 was also lengthened to accommodate longer fill slopes and keep some habitat along the creek. 19

20 FIGURE 5 Rocky Run bridges 21 Figure 5 shows a design visualization for the Rocky Run CEA. 22

23 WSDOT engineers successfully overcame design challenges at Rocky Run Creek with new 24

designs that achieved the connectivity objectives of providing moderate level connectivity for high- and 25 low-mobility species associated with the mountain hemlock / subalpine fir species assemblage zone, 26 restoring capacity for flood and debris flow at the crossing structure, and providing fish passage for the 27 full range of lake elevations. 28 29 Subsequent Rocky Run Issue Regarding Profile Adjustment 30 After determining the best profile for the highway to meet clearance and footprint objectives at Rocky 31 Run Creek, archeological and cultural conflicts arose with a USFS Service Road. By elevating the 32 highway profile to create clearance at the creek bridges, the USFS Service Road adjacent to I-90 would 33 become lower than the adjacent interstate, resulting in possible embankment encroachment. WSDOT 34 proposed to raise the profile of the USFS Service Road to remedy the problem, but this would require 35

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 13: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

14

WSDOT to disturb an adjacent property containing old growth trees and a structure eligible for the 1 National Historic Register and State Historic Preservation Office resources. 2

Since not many compromises were available to reduce the primary and secondary impacts of the 3 situation, WSDOT engineers accepted that designing around this issue would require additional cost. 4 WSDOT moved forward with plans to raise the profile of the USFS Service Road and reduce impacts to 5 the historic property by adding a small system of precast concrete barrier to retain the existing slope. 6 WSDOT also re-routed planned drainage systems in the area to lessen the impact near the historic site. 7 8 CONSTRUCTABILITY AND FLOODPLAIN ISSUES OF RESORT CREEK CEA 9 The Resort Creek CEA is located between milepost 59.3 and milepost 59.7. The forest habitat adjacent to 10 this CEA is the Western Hemlock Series, grading into Pacific Silver Fir Series at higher elevations. 11 Currently, Resort Creek flows under I-90 in a 6-foot pipe culvert that is a barrier to fish passage, and 12 drains into Keechelus Lake (2). 13

The Mitigation Team recommended that WSDOT install a series of bottomless culverts 14 throughout the active channel-migration zone of Resort Creek. At least one of these culverts would have a 15 minimum width of 30 feet and a minimum vertical clearance of 12 feet; the combined widths would span 16 about 100 feet. These culverts would extend under both eastbound and westbound lanes, resulting in 17 culvert lengths of about 150 feet. The series of culverts would allow the creek channel to shift location 18 across the alluvial fan in response to sediment deposition and debris blockage. Culverts would be sized to 19 meet WDFW stream simulation requirements for fish passage. 20

As WSDOT engineers advanced this design, uncertainty emerged about Resort Creek actually 21 meandering across the alluvial fan. Additionally, the costs to install a temporary shoring system in order 22 to construct the bottomless culverts and maintain traffic through the construction zone were exorbitant. 23 WSDOT engineers reformulated designs by replacing the culverts with a 180-foot-long bridge that not 24 only provided a large opening across the floodplain for natural creek function, but also created a better 25 wildlife crossing structure for aquatic and terrestrial species. 26

WSDOT engineers presented this modified design to the IDT and Mitigation Team. The agencies 27 agreed that this option achieved connectivity objectives – reducing wildlife / vehicle collisions, restoring 28 capacity for flood and debris flow, providing fish passage, and restoring habitat / aquatic connectivity and 29 channel migration – while meeting the additional objective of providing connectivity for large and small 30 species. 31 32 MOVING DESIGN PLANS FORWARD AND PREPARING FOR CONSTRUCTION 33 After years of working with project partners and resource agencies to find viable solutions to competing 34 objectives between transportation facility design and ecological connectivity, WSDOT engineers are 35 finalizing the remaining design plans and preparing for construction of the second and third construction 36 contracts. 37

The funded five-mile portion of the I-90 Project from Hyak to Keechelus Dam has been broken 38 into three construction contracts. Design and construction of the first construction contract – Phase 1A - 39 are complete. Construction of Phase 1A began in July 2009 and was complete November 2009. WSDOT 40 built a long-term detour bridge at Gold Creek for use in the second construction contract of the project 41 and mitigated for future lake storage impacts to Keechelus Lake – an irrigation reservoir – by excavating 42 approximately 260,000 cubic yards of material from the lakebed. WSDOT has committed to a no-net-loss 43 agreement with U.S. Bureau of Reclamation to not affect lake storage capacity during construction of the 44 I-90 Project. 45

WSDOT completed designs and permits for the second construction contract – Phase 1B – in fall 46 2009, with a Nov. 2, 2009 contract advertisement date. This contract calls for replacing the deteriorated 47 concrete pavement of the existing four lanes, adding a new lane in each direction, rebuilding bridges and 48 culverts, stabilizing rock slopes, and extending chain up / off areas along the first three miles of the 49 project. WSDOT expects to begin construction of Phase 1B in spring 2010. 50

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 14: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

15

Engineering designs and permitting actions are still underway for the third construction contract – 1 Phase 1C – that will cover the remaining two project miles. Phase 1C calls for replacing deteriorated 2 concrete pavement, adding a new lane in each direction, replacing the existing snowshed, addressing 3 unstable slopes, and building new bridges. Phase 1C is expected to advertise to contractors in fall 2010, 4 with construction scheduled to begin in spring 2011. All I-90 Hyak to Keechelus Dam Project 5 improvements are scheduled for completion in 2015. 6

To move the remaining Phase 1 design plans forward, engineers are finishing geotechnical 7 drilling on the rock cliffs and lakebed along the I-90 Project corridor. Drilling core samples will help 8 identify structural needs for the snowshed and the potentially unstable slopes along the corridor that will 9 require stabilization measures as the rock cuts are excavated. WSDOT will stabilize slopes with grouted 10 steel bars that are designed in accordance with the structural geology and height of each rock cut. 11 WSDOT and a consultant team of geologists are also conducting geophysical studies using downhole 12 surveys for bedrock mapping to identify terrain conditions and design the highway realignment. 13

Other work includes completing the structural designs for the remaining three CEAs, roadway 14 drainage, and the new snowshed, which also includes mechanical system designs for illumination, 15 ventilation, back-up electrical generation, and Intelligent Transportation Systems (ITS). Engineers are 16 also finalizing construction schedules and other logistics for traffic control and staging. 17

Pre-construction wildlife monitoring activities continue to move forward as well. As part of the I-18 90 Project Wildlife Monitoring Plan, WSDOT and its partners are evaluating the locations and rate of 19 wildlife / vehicle collisions; assessing the use and effectiveness of wildlife crossing structures – both 20 existing and planned; characterizing the locations and rate of at-grade highway crossings by wildlife; 21 estimating species occurrence and distribution in the project area; assessing the effectiveness of fencing; 22 and appraising the effectiveness of jump-outs (5). Methods being used to meet pre-construction objectives 23 include assessing wildlife use of existing culverts and underpasses via remote cameras; documenting 24 crossing rates via snow tracking; evaluating the distribution of various target species via both noninvasive 25 survey methods and live-capture; and documenting wildlife-vehicle collisions. In addition, specific 26 projects to monitor low-mobility species such as fish, amphibians, and pikas have been initiated. 27

Wildlife monitoring efforts will continue during and after construction of the I-90 Project. The 28 engineering team is working to ensure successful post-construction monitoring efforts by integrating 29 communication systems into the infrastructure of the highway. Engineers plan to install fiber-optic 30 communication cables at each CEA that will instantly transmit wildlife usage data, including images, to 31 WSDOT for more efficient collection of information. Engineers would also like to make the live feeds 32 available for public viewing on the WSDOT Web site. 33

The engineering team continues to test various prototypes of wildlife exclusionary fencing to find 34 a design that will withstand winter weather conditions, maintenance operations, and redirect wildlife 35 away from the interstate and to crossing structures. Several prototypes have been tested over the last two 36 winter seasons; engineers are hopeful to finalize fencing plans this year. 37 38 CONTINUING COLLABORATION TO RESOLVE FUTURE ISSUES 39 Open and honest communication, and the desire to establish and engage in partnerships early on, is what 40 inevitably allowed WSDOT to develop consensus for a long-term vision for the I-90 corridor. By sharing 41 ideas, being adaptive in designs, and receptive to compromises, WSDOT and its partners have designed a 42 project that will not only improve the safety and reliability of a vital cross-state corridor, but will also 43 promote the continued health of the delicate ecosystems of the Central Cascades for generations to come. 44

WSDOT will continue to collaborate with project partners, stakeholders, and resource agencies to 45 overcome challenges as they arise during construction and in future designs. While the remaining 10 46 project miles from Keechelus Dam to Easton remain unfunded at this time, WSDOT, along with its 47 project partners, stand ready to deliver. 48 49 50 51

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.

Page 15: R. Giles, S. Golbek, A. Sullivan, J. Wood 2 1 Ecology and ... · R. Giles, S. Golbek, A. Sullivan, J. Wood 6 1 Even with conservation efforts, I-90’s presence limits wildlife movement

R. Giles, S. Golbek, A. Sullivan, J. Wood

16

REFERENCES 1 2 1 Washington State Department of Transportation. August 2008. I-90 Snoqualmie Pass East Project 3 Final Environmental Impact Statement. FHWA-WA-EIS-05-01-F. PP. 1-1; 1-8. 4 5 2 Mitigation Development Team. July 2006. Interstate 90 Snoqualmie Pass East Mitigation Development 6 Team Recommendation Package. PP. ES-7; ES-8; ES-15; ES-16; ES-17; 1-4. 7 8 3 Washington State Department of Transportation. June 2005. I-90 Snoqualmie Pass East Project Draft 9 Environmental Impact Statement. FHWA-WA-EIS-05-01-D. PP. ES-1. 10 11 4 Washington State Department of Transportation and Otak, Inc. August 2007. Stormwater 12 Treatment and BMP Report. PP. 1-2. 13 14 5 Washington State Department of Transportation and Western Transportation Institute. 15 February 2008. I-90 Wildlife Monitoring Plan. PP. ix. 16 17 18 19 20 21 22

23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

48

TRB 2010 Annual Meeting CD-ROM Paper revised from original submittal.