r. psp chris carson, faace, - fplotnick.com · glen r. palmer, psp,. cfcc. owner. gr palmer...
TRANSCRIPT
Glen R. Palmer, PSP,
CFCCOwner
GR Palmer Consulting Services, LLC
Chris Carson, FAACE, PSP, DRMP, CEP, CCM, PMPDirector of Program Controls
ARCADIS U.S., Inc.
2
Owner, GR Palmer Consulting Services, LLC
Certifications:
PSP (Planning & Scheduling Professional ) –
AACE International
CFCC (Certified Forensic Claims Consultant) –
AACE International
University of Maine, BS, 1976
Professional Field: Glen Palmer has over 35 years of experience working on engineering
and construction projects. He spent more than 20 years working for two major
engineering and construction companies where he held positions as Project Controls
Manager and Corporate Head of Planning and Scheduling. More recently, he spent five
years with a major risk management and dispute resolution firm in the role of Vice
President of Power. He has experience in power, commercial, infrastructure, and
process projects throughout the United States and internationally. He has extensive
experience in estimating, cost control, planning & scheduling, and project management
covering all project phases. He has been an expert witness
on disputes
Association Involvement
Active in AACE (Association for the Advancement of Cost Engineering)
3
Director of Program & Project Controls, ARCADIS U.S., Inc.
Certifications:
Fellow RICS (Royal Institution of Chartered Surveyors), 2015
Fellow AACE International, 2013
DRMP (Decision & Risk Management Professional ) –
AACE International
PSP (Planning & Scheduling Professional ) –
AACE International
CEP (Cost Estimating Professional) –
AACE International
CCM (Certified Construction Manager) ‐
CMAA
PMP (Project Management Professional) – PMI
University of Virginia, Mechanical Engineering, 1972
Professional Field: 44 years of experience in CM and CM Services
specializing in
Planning and Scheduling, Cost Management, Risk Management , Forensic Analysis,
Dispute Resolution
Awards
Recipient of the 2011 AACE International “Technical Excellence Award”
Received the award for “Significant Contributions to The Scheduling Industry”
from PMI
(Project Management Association of America) College of Scheduling, 2009
Awarded first CMAA “Chairman’s Award”
for contributions to CMAA and the Construction
Management profession, 2006
Other Associations
Active in CMAA (Construction Management Association of America)
Active in PMI and the PMI College of Scheduling/ Scheduling Community of Practice
Active in AACE (Association for the Advancement of Cost Engineering) International
Active in Planning Planet & International Guild of Project Controls
Active in RICS (Royal Institute of Chartered Surveyors)
• Publications:
PMI book, “CPM Scheduling for
Construction ‐
Best Practices and
Guidelines”
published Oct, 2014
AACE RPs, Journal articles in
Scheduling, Risk, Cost, Forensic
Analysis
The authors, with experience of over 75 years in the
engineering / construction industry
The following presentation is based on the some of
biggest lies we have encountered in Project Controls and how to deal with them. What are some of the
biggest lies you have encountered?
There is no Float buried in the Construction Schedule
There is no Float buried in the Construction Schedule
Important Discussion Points
Level III versus Level IV schedule
Critical and near critical activities
Is having float in the schedule a “bad”
thing?
There is no Float buried in the Construction Schedule
Detailed Discussion Points
Level IV – If the construction schedule is prepared at a level IV and
is resource loaded (driven), it is more difficult to find the buried
float, because the unit rates / man‐hours are inflated to add time
Level III – every critical path schedule activity has a duration equal
to the construction work week or multiple work weeks
There is no Float buried in the Construction Schedule
There is no Float buried in the Construction Schedule
Detailed Discussion Points
Level III – Start‐to‐start lags are high numbers and more than likely
represent a later than necessary successor start date
There is no Float buried in the Construction Schedule
There is no Float buried in the Construction Schedule
Detailed Discussion Points
What is the difference between float and “time contingency?”
Is having float in a construction schedule a “bad”
thing?
There is no Float buried in the Construction Schedule
Advice
Adopt a scheduling approach that allows float but makes it
transparent
Resource loading is too much trouble and doesn’t
provide value to the project
Resource loading is too much trouble and doesn’t
provide value to the project
Important Discussion Points
Understanding of planned resources is vital
Performance monitoring requires resource assessment
A schedule is not a true CPM schedule without taking into account
use of available resources
Inadequate available resources is at the heart of most disputes
Accurate resource count and loading is difficult
Resources are factor in all claims, inefficient at end when stacked
Manpower
Resource loading doesn’t provide value to the project
Resource loading is too much trouble and doesn’t
provide value to the project
Detailed Discussion Points
Production Rate x Quantities = Durations
Production Rate of Resources is based on number and capability
Cannot discuss Durations without assessing Production Rates
Achieved Production Rate x Quantities = Performance
Performance analysis is more than just identifying delays, it’s also
improvement analysis
Getting good individual resource information from subcontractors
is difficult and subject to inaccuracy
Loading individual resources carries risk of a high rate of error
Resource loading is too much trouble and doesn’t
provide value to the project
Detailed Discussion Points
Resources can mean Individual Resources (Mary Smith), Roles
(carpenters), or Crew Resources (Electrical Crew)
Value of resources depends on type of project
Individual Resources –
Engineering, Architecture
Individual Roles –
Engineering, shipbuilding
Crew Resources – construction of all types
Use of Crew Resources is simple, very useful, and limits risks of
inaccuracy and error
Resource loading is too much trouble and doesn’t
provide value to the project
Detailed Discussion Points
Baseline Schedule
Identify crews for each activity, load one crew/day in each activity
Need definition of crew composition
Update Schedules
Monitor planned against actual crew use
Analysis
Performance – resource consumption vs. planned
Inefficiency – resource productivity at activity level vs. planned
Delays – change order resource consumption vs. contract
Control trade & space
stacking risks
Resource loading doesn’t provide value to the project
Resource loading is too much trouble and doesn’t
provide value to the project
Advice
Needed Information/Data
Baseline planned resources
Monthly resource look‐ahead plan & actual resources consumed
Use crew resources with crew composition
Analysis
Load crews into schedule, run crew average and peak loads
Review crews per trade, per location, per phase
Review similar as well as dissimilar concurrent crew use
Review crew usage on location basis, avoid overload of spaces
The Project can achieve 10 % construction progress in
one month
The Project can achieve 10 % construction progress in
one month
Important Discussion Points
Size of the Project
Work Force capabilities
Modularization
Increased “safety”
emphasis
Feeding the machine
The Project can achieve 10 % construction progress in
one month
Detailed Discussion Points
Size of the Project
When you have 500,000 craft workhours or higher it becomes
increasingly difficult in the USA to make 10 % construction progress in a
month
The Project can achieve 10 % construction progress in
one month
Detailed Discussion Points
Work Force capabilities
Our construction force is aging and there is substantially less training
than in there was in the past
The Project can achieve 10 % construction progress in
one month
Detailed Discussion Points
Modularization
Moving workhours offsite is a very valid approach to making 10 % in a
month
The Project can achieve 10 % construction progress in
one month
Detailed Discussion Points
Increased “safety”
emphasis
We put a high emphasis on “safety”
in the USA, which impacts
productivity
The Project can achieve 10 % construction progress in
one month
Detailed Discussion Points
Feeding the machine
On large projects with high numbers of craft, it becomes more difficult to
supply the materials required to the work fronts to keep the work force
productive
The Project can achieve 10 % construction progress in
one month
The Project can achieve 10 % construction progress in
one month
Advice
When someone hands you a percent complete curve with one or
more months with greater than 10 % construction progress – pay
attention
A Detailed Design‐Build Schedule is Impossible until
Design is Complete
A Detailed Design‐Build Schedule is Impossible until
Design is Complete
Important Discussion Points
A promoted advantage for DB is shortened construction time
33% faster than DBB*
23.5% faster than Construction Management*
Yet, DB contractors often take the position that they cannot provide
a detailed schedule until design is complete ~30% into
construction?
*Konchar & Sanvido, “Comparison of US Project Delivery Systems, 1997
A Detailed Design‐Build Schedule is Impossible until
Design is Complete
Detailed Discussion Points
Most DB projects are fixed price – with budget commitments at
~30% design completion or less
DB Contractors typically can provide detailed cost estimates
Conceptual but still reasonable with limited contingency
Cost estimates require similar information as scheduling, so if the
data is sufficient for detailed estimates, it is sufficient for schedule
A Detailed Design‐Build Schedule is Impossible until
Design is Complete
Detailed Discussion Points
Most DB projects are fixed price – with budget commitments at
~30% design completion or less
Project duration is an important part of a project budget
Cannot provide accurate project duration without schedule
Contractor’s scheduler and designer work together, so can
collaborate on schedule
A Detailed Design‐Build Schedule is Impossible until
Design is Complete
Detailed Discussion Points
DB Contractors bear ultimate coordination risk
Schedule is primary coordination tool
Schedule is primary communication tool
Often unforeseen conditions show up early with no schedule
Without early schedule, project is at higher risk of coordination and
success
A Detailed Design‐Build Schedule is Impossible until
Design is Complete
Advice
Require detailed schedule early in process
Do not allow late submission of schedule
No excuses because schedule is needed for early coordination and
analysis
Consider multiple submission of schedules
Preliminary schedule should contain detailed look ahead with summary to
completion
Secondary or tertiary schedules can be produced as further development of
preliminary but the goal is to have as much detail as possible
Do not allow “rolling‐wave”
effort as design is developed; need good overall
schedule in place to manage and analyze
The entire schedule has been analyzed and validated
The entire schedule has been analyzed and validated
Important Discussion Points
Critical path
High Float Values
Manpower curves
The entire schedule has been analyzed and validated
Detailed Discussion Points
Critical path
Does the critical path (longest path) make sense? What about the
near
critical paths?
The entire schedule has been analyzed and validated
The entire schedule has been analyzed and validated
Detailed Discussion Points
High Float Values
This is one of the weakest aspects of scheduling today – lack of evaluating
high float
Float values allow monitoring of Non‐Critical Path work
The entire schedule has been analyzed and validated
The entire schedule has been analyzed and validated
Detailed Discussion Points
Manpower Curves
Does the manpower curve have peaks all over the place or is it reasonably
bell shaped?
The entire schedule has been analyzed and validated
The entire schedule has been analyzed and validated
Advice
Don’t take someone’s word that the schedule has been analyzed and
validated; check it yourself!!
All the Delay is the Responsibility of One Party
All the Delay is the Responsibility of One Party
Important Discussion Points
There are significant challenges to identification of delay
Identification of delay
Recognition of entitlement
Assignment of responsibility
All the Delay is the Responsibility of One Party
Detailed Discussion Points
Identification of delay
Requires strong technical scheduling skills, a well maintained schedule that
models the work, and strong technical forensic analysis knowledge & skills
Recognition of entitlement
Well defined and understood contract documents
Detailed understanding of contractual scope of work
Assignment of responsibility
Detailed knowledge of contemporaneous project
Accurate documentation of daily work
All the Delay is the Responsibility of One Party
All the Delay is the Responsibility of One Party
Detailed Discussion Points
Recognition of entitlement
Without a good understanding of both the contract and the scope,
entitlement disputes will delay the negotiations of time extensions
This can cause predicted delays to become absorbed into the project
Changes the entire analysis methodology from simple analysis to complicated
claims analysis
All the Delay is the Responsibility of One Party
All the Delay is the Responsibility of One Party
Detailed Discussion Points
Industry studies show who has most
influence over change:
The Project Manager, Pinnell‐
Busch, Inc. 2005
(“Global Construction Disputes 2016 –
Don’t Get Left Behind”, ARCADIS)
Risk Assessment and Best Practices, Pinnell‐Busch, Inc. 2005
• Causes of Change• Contractors’
view
• Scope changes
• Errors & omissions
• Differing site conditions
• Owner delay
• Contractor error
• Estimated quantities low
• Causes of Change• Owners’
view
• Scope changes
• Differing site conditions
• Design errors
• Estimated quantities low
• Owner delay
• Contractor error
38%
25%
12%
9%
6%
5%
32%
19%
18%
12%
7%
6%
All the Delay is the Responsibility of One Party
All the Delay is the Responsibility of One Party
Advice
Clear contractual requirements for analyzing delay
Treat absorbed delays differently from predicted delays
Reference AACE RP #52R‐06 “Time Impact Analysis”
Reference AACE RP #29R‐03 “Forensic Schedule Analysis”
Embrace strong technical scheduling; knowledgeable schedulers,
good quality schedules, experts to analyze delay for support of
identification of delay
Include contract specialist; CM, QC, Project Engineer, Procurement
Manager for support of entitlement determination
Ensure high quality documentation for support of assignment of
responsibility
The Schedule Dates / Critical Paths have not been
manipulated
The Schedule Dates / Critical Paths have not been
manipulated
Important Discussion Points
Owner / Client on Critical Path
Strange / Changing lag values
Decreased Activity Durations
Schedule Analyzer, Claim Digger, or Fuse
The Schedule Dates / Critical Paths have not been
manipulated
Detailed Discussion Points
If the Owner’s / Client’s activities appear on the critical path soon
after the Project starts to fall behind schedule, you may want to
check the schedule for manipulation
The Schedule Dates / Critical Paths have not been
manipulated
Detailed Discussion Points
Strange / changing lag values – if a lag has a strange value it
suggests some science was involved in it’s determination
The Schedule Dates / Critical Paths have not been
manipulated
The Schedule Dates / Critical Paths have not been
manipulated
Detailed Discussion Points
Strange / changing lag values – if a lag has a different value in a
subsequent update it suggests manipulation
The Schedule Dates / Critical Paths have not been
manipulated
The Schedule Dates / Critical Paths have not been
manipulated
Detailed Discussion Points
Decreased Activity Durations – If you find that activities that are
future work activities and the durations have changed (especially
important on critical and near critical paths); again suggests
manipulation
The Schedule Dates / Critical Paths have not been
manipulated
The Schedule Dates / Critical Paths have not been
manipulated
The Schedule Dates / Critical Paths have not been
manipulated
Detailed Discussion Points
Schedule Analyzer, Claim Digger, Or Fuse – These programs can
help you more quickly see what has changed
The Schedule Dates / Critical Paths have not been
manipulated
Advice:
Analyze, analyze again, and then challenge the questionable
methodology before it goes too far
Our plan has not changed significantly; we’ve only
made minor adjustments
Our plan has not changed significantly; we’ve only
made minor adjustments
Important Discussion Points
Failure to meet plan is a contributing factor in most claims
The “minor adjustments”
tend to reduce the viability of the future
work
It’s in everyone’s best interests to ensure the original plan is
attainable and is pursued aggressively each month
The schedule is a model of the plan ‐
both must align
Our plan has not changed significantly; we’ve only
made minor adjustments
Contractor’s failed plan requiring re-planning
Planned Resources need increases by 3 Crews in one update
“EOP 10”
–
progress only import to Update 10
Our plan has not changed significantly
Our plan has not changed significantly; we’ve only
made minor adjustments
Contractor’s failed plan requiring re-planning
Note that within one update period, the schedule shifted resources 4 months later!
“EOP 10”
–
progress only import to Update 10
Our plan has not changed significantly
Our plan has not changed significantly; we’ve only
made minor adjustments
Important Discussion Points
The Critical Path of the progress‐only schedule is usually very
different from the mitigation efforts in the updated schedule
Progress only is the plan from the previous period – this is the Critical Path
that the CM team was monitoring
Mitigation logic change schedule Critical Path is usually a complete surprise
to the CM team – it can be responsible for a mid‐period Critical Path shift
Determination of driving activities is very different between actual progress & logic
changes (with mitigation manipulation)
Our plan has not changed significantly
Our plan has not changed significantly; we’ve only
made minor adjustments
Advice
Ensure achievable baseline schedule
Review crew resources for concurrency problems
Provide high quality technical review
Bifurcate the update analysis
Evaluate performance against plan
Evaluate logic changes made to mitigate performance failure
Encourage the contractor to make transparent minor adjustments
to better model the plan; but watch for hidden mitigation
“The Project is on Schedule”
“The Project is on Schedule”
Important Discussion Points
Lack of Schedule Detail
Baseline Schedule Comparison
Questionable Updating Process
Schedule Sequence Deviations
Project Management Issues
“…just a quarter of
construction projects
came within 10 percent
of the original
deadline…”
“The Project is on Schedule”
Detailed Discussion Points
Lack of Schedule Detail – Will impact anyone’s ability to accurately
update schedule progress and bring guessing into play
“The Project is on Schedule”
“The Project is on Schedule”
Detailed Discussion Points
Baseline Schedule Comparison – If the current schedule is not being
compared to the baseline or target schedule, how do you know
where you are supposed to be on the job at any point in time?
“The Project is on Schedule”
“The Project is on Schedule”
“The Project is on Schedule”
Detailed Discussion Points
Questionable Updating Process – A true updating process should be
“Quantitative”
not “Qualitative”
“The Project is on Schedule”
“The Project is on Schedule”
Detailed Discussion Points
Schedule Sequence Deviations – If the project team is not paying
attention to the planned sequence of work, the schedule rapidly
becomes useless in monitoring the project’s schedule progress
“The Project is on Schedule”
Detailed Discussion Points
Project Management Issues – There are PMs who are unqualified,
and some that are dishonest when it comes to overseeing a schedule
update; this can lead to an inaccurate picture of project status
“The Project is on Schedule”
Advice:
Don’t accept the above statement without doing your due
diligence!!
The project has only slipped by four days
The project has only slipped by four days
Important Discussion Points
Single period Critical and Near‐Critical Path Analysis, while vital,
will reveal only immediate delay concerns
Equally vital is the issue of trending; what are the ramifications of
the single period delays to all periods?
Analysis can be time‐consuming, particularly if not directed
The project has only slipped by four days
Detailed Discussion Points
All Critical and Near‐Critical Path delays should be examined to
determine if they will occur in later periods
Non‐Critical Path delays may not cause an immediate delay but
could have huge consequences in future periods
Failure to identify trending delays will allow them to be amplified in
later periods, often beyond the ability to mitigate
The project has only slipped by four days
Detailed Discussion Points
All Critical and Near‐Critical Path delays should be examined to
determine if they will occur in later periods
Does the delay reveal a problem with schedule logic?
Does the delay reveal a problem with resources or productivity?
Does the delay reveal a problem with one trade contractor?
Is there any reason to believe that this delay will never happen
again?
The project has only slipped by four days
Detailed Discussion Points
All Non‐Critical Path delays should be identified and examined by
trending
There are multiple tools for trending analysis
Float dissipation
Missed Starts and Finishes
Time Performance Ratio (duration analysis) – TPR or Tipper
Crew resource over‐allocation (under staffed)
Earned Value
The project has only slipped by four days
The project has only slipped by four days
Missed dates show lack of performance
The project has only slipped by four days
97
The project has only slipped by four days
This project suffered a pattern of delays in A/E review
The project has only slipped by four days
Time Performance Ratio
0.02.0
4.06.08.0
10.012.0
Admin
Sitework
Concre
teMas
onry
Metals
Carpen
tryRoo
fing
Doors/
Wind
ows
Finish
esEqu
ipmen
tFurn
ishing
sElev
ators
Mecha
nical
Electric
al
Type of Work
TPR
The project has only slipped by four days
The project has only slipped by four days
EVMS To Complete Indices
To Complete Performance Index
(TCPI) for BAC
TCPI = (BAC – EV)/(BAC – AC)
If TCPI > 1, need improvement to
reach goal
The Planned Value curve slope in future period is steeper then past performance
May be achievable with additional crews with minor trending slippage
Future Plan
The project has only slipped by four days
The Planned Value curve slope in future period is significantly steeper then past performance
Unlikely to be achievable even with additional crews and cannot accommodate trending slippage
Aggressive Future Plan
The project has only slipped by four days
The project has only slipped by four days
Advice
Embrace trending analysis – just as important as CP analysis
Use all the tools to ensure identification of trending problems
Float dissipation
Missed Starts and Finishes
Time Performance Ratio (duration analysis) – TPR or Tipper
Crew resource over‐allocation (under staffed)
Earned Value
10.
There is no Float buried in the construction schedule9.
Resource loading is too much trouble & doesn’t provide much value to
the project
8.
The project can achieve 10 % of the construction progress in one
month7.
A detailed design‐build schedule is impossible until design is complete6.
The entire schedule has been analyzed and validated5.
All the delay is the responsibility of one party4.
The schedule dates / critical paths have not been manipulated3.
Our plan has not changed significantly; we’ve only made minor
adjustments
2.
The project is on schedule 1.
The project has only slipped by four days
Glen R. Palmer, PSP, CFCCOwner
GR Palmer Consulting Services, LLC7 Caswell Drive
Greenland, NH 03840 Office Ph.: 603‐436‐6604Mobile Ph.: 603‐591‐6754
E‐mail: [email protected]
Chris Carson, FAACE, PSP, DRMP, CEP, CCM, PMP
Director of Program & Project ControlsARCADIS U.S., Inc.
295 Bendix Road, Suite 240Virginia Beach, VA 23452Mobile Ph.: 757‐342‐5524
E‐mail: [email protected]