r. v. silpa homesenvironmentclearance.nic.in/.../13072016439nzxhwrvsilpahomescp.pdfr. v. silpa homes...
TRANSCRIPT
R. V. SILPA HOMESSURVEY NO. 198/1(PART) & 206/AA,MADINAGUDA, SERILINGAMPALLY,
RANGA REDDY DISTRICT, TELANGANA
Conceptual PlanResidential Apartments Construction Project
Submitted ByR. V. Silpa Homes8-2-268/1/16/B/1, Sriniketan Colony,Road No.3, Banjara Hills,Hyderabad-500034.
Studies & Documentation byM/s Team Labs and Consultants(An ISO Certified Organization)B-115 -117 & 509, Annapurna Block,Aditya Enclave, Ameerpet,Hyderabad- 500 038Phone: 91-040-23748555/616Fax : 91-040-23748666e-mail: [email protected]
SUBMITTED TOSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY
TELANGANAGOVERNMENT OF INDIA
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 1
2.0 CONCEPTUAL PLAN / PROJECT DESCRIPTION
This chapter details the need for the project, description of the proposed project andalternatives, and identifies the valued ecosystem components. R. V. Silpa Homes,proposes to build residential apartment units to cater to the needs with all amenities asa gated community.
2.1 THE PROJECT LOCATION:The project will be spread over an area of 0.795 Hectares in survey nos. 198/1(Part) &206/AA, Madinaguda, Serilingampally, Ranga Reddy District. The site is surrounded byopen lands in all the directions except in west directions. An existing 18m wide roadproposed to be widen 45 m wide road in west direction connecting Miyapur Bachupallyroad. The nearest railway station is the Hafeezpet railway station located at a distanceof 2.5 km
2.2 PROJECT DESCRIPTION2.2.1 DESIGN STAGEThe project is envisaged as a gated community of residential apartments with variousamenities. The land area available for the project is 0.795 ha and will be allocated forvarious types of apartments and amenities based on the development rules of GHMC.The built up areas and the number of units proposed is presented in table 2.1.
Table 2.1 Built Up Area Statement
Land Use No ofFloors
Total No ofUnits
Total Site Areain m2
Total Builtup area (m2)
WING- A & B 2C+G+14 204 1714.69 19112.3Amenities Block G+2 – 465.35 4088.92Green Area 741.00Road Area 2901.8Open Area 1527.1Road widening area 595.7ParkingCellar - 1 6409.41Cellar - 2 6251.27Total 204 7945.7 35861.90
It is proposed to provide 204 units. The land allocation will be optimized to ensurecompliance with the regulations of GHMC. The water requirement of the project duringoperation will be drawn from HMWSSB. Sewage treatment plant will be provided totreat the sewage. Water conservation measures will be incorporated in the plumbingdesigns. Water recycling/reuse will be adopted by way of using treated sewage forgreen belt development. The rainwater will be let-out into harvesting tank and excessdischarged into storm water drains. The required power will be drawn from theTRANSCO. Solar Energy will be used for fencing, and partially for hot water in the
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 2
apartments. The designs of the apartments will also incorporate Indian Architecturalprinciples of “Vastu” as the market demands the same. Construction material will bedrawn from local sources. The layout of the project site is presented in fig. 2.1 andtypical floor plans are presented in figure 2.2. The parking provision follows theguidelines prescribed by GHMC and Building policy. The number of parking spacesprovided is presented in table 2.2
Circulation Plan: Ground Floor Driveway : 7.0 m No. of Cellar: 2 nos. No. of Ramps : 2 –1 way Width of Ramp : 3.8 m Slope of Ramp : 1 in 8 Cellar Driveway : 5.5 m No. of Lifts : 4 Capacity of each Lift: 10 pax. Connecting Road : 18 m ROW
Volume/Capacity RatioTowards Existing
Volume, PCU/hrMaximum
Capacity, PCU/hrVolume/Capacity
LOS,Performance
Site road 446 1800 0.248 “B” VeryGood
Modified Los & Performance
RoadExistingvolume,PCU/hr
Existingvolume/Capacity
Additionalvolume
ModifiedVolume
ModifiedVolume/Capacity
ModifiedLos &
performance
Site road 446 0.248 67 513 0.285 “B” VeryGood
ParkingIt is proposed to provide 2 Cellar floors for parking. The parking provision exceeds theguidelines prescribed by FAR and Building policy. Parking floor plans is presented in fig2.3. The no. of parking spaces is presented in table 2.2.
Table 2.2 Parking Space Provision of the ProjectFloor 4-Wheeler 2-Wheeler
Cellar - 1 114 49Cellar - 2 116 56Total 230 105
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 3
Fig 2.1 Layout of the project site
TRANSFORMER
YARD
G.B
Proposed 45.72M (150') Wide Road
13.03m
29.87m
ENTRY
66.30m31.30m
19.51m15.65m
4.84m
55.00m
15.65m19.51m
95.64m
1.14m 2.68m 5.69m 2.56m 8.10m 10.58m14.52m 9.27m
7. 0
0m
WI D
E D
RI V
E W
AY
RESID
ENTIA
L APA
RTM
ENTS
WIN
G - A
2 CELLA
RS+GRO
UN
D+14 FLO
ORS
RESID
ENTIA
L APA
RTM
ENTS
WIN
G - B
2 CELLA
RS+GRO
UN
D+14 FLO
ORS
ORGANISEDOPEN SPACE-1
ORG
AN
ISEDO
PEN SPA
CE-2
4.60m
23.78m
4.54m
4.31m
13.94m
18.79m
28.46m
11.59m11.59m
7 . 0 0 m W I D E D R I V E W A Y
3.05m
EXIT
AREA LEFT FOR ROAD
WIDENING 595.69 SQMTS11.11m
37.49m
12.41m 4.62m
7. 0
0m
WI D
E D
RI V
E W
AY
7.00m WIDE DRIVE WAY
RAM
P UPFRO
M C
ELLAR - 1
RAM
P DN
TOC
ELLAR - 1
17.06m
3.80m
17.06m
3.80m
SITE PLAN
13.00m
9.14m
13.26m
13.03m
13.03m
SWIM
MIN
G PO
OL
@ F IRST FLO
OR
3.05m3.05m
11.44m
Existing 18.00M (60') Wide Road
22.86m
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 4
Fig 2.2 Typical floor plan
1st FLOOR
2nd FLOOR
3rd FLOOR
4th FLOOR
5th FLOOR
6th FLOOR
7th FLOOR
8th FLOOR
9th FLOOR
10th FLOOR
11th FLOOR
12th FLOOR
TERRACE FLOOR
SOUTH SIDE ELEVATION
GROUND FLOOR
13th FLOOR
14th FLOOR
BED ROOM3.35X3.05
TOILET2.74X1.37
TOILET2.74X1.52
M.BED ROOM4.27X3.35
TOILET1.73X1.83
KITCHEN3.05X3.00
1.22
M W
IDE
UTI
LITY
DINING3.35X6.15
DRAWING3.76X3.35
MD
D
D
D1
D1
D1 D2
KWV
V
V
WW
W
W3
W3
W3
BED ROOM3.66X3.05 DRAWING
3.35X3.35
TOILET2.13X1.68
TOILET2.44X1.37
TOILET3.05X1.52
DINING4.57X3.30
LIVING3.35X2.95
M.BED ROOM3.66X3.35
KITCHEN3.35X2.74
1.52M WIDEUTILITY
MD
D
D
D1
D1
D1
D2
KW
KW1
V
V
V
W1
W1
W1
W3
2.00 WIDE CORRIDOR
2.0
0 W
IDE
CO
RRID
OR
2.00 WIDE CORRIDOR 2.00 WIDE CORRIDOR
2.0
0 W
IDE
CO
RRID
OR
2.0
0 W
IDE
CO
RRID
OR
Co
mm
.sh
aft
Elec.shaft
LOBBY3.05X3.35
BED ROOM3.35X3.05
TOILET2.74X1.37
TOILET2.74X1.52
M.BED ROOM4.27X3.35
TOILET1.73X1.83
KITCHEN3.05X3.00
1.22
M W
IDE
UTI
LITY
DINING3.35X6.15
DRAWING3.76X3.35
D
D
D1
D1
D1 D2
KWV
V
V
WW
W
W3
W3
W3
BED ROOM3.66X3.05 DRAWING
3.35X3.35
TOILET2.13X1.68
TOILET2.44X1.37
TOILET3.05X1.52
DINING4.57X3.30
LIVING3.35X2.95
M.BED ROOM3.66X3.35
KITCHEN3.35X2.74
1.52M WIDEUTILITY
MD
D
D
D1
D1
D1
D2
KW
KW1
V
V
V
W1
W1
W1
W3
1.52m W. BALCONY
BED ROOM3.96X3.05
TOILET1.52X2.44
TOILET2.74X1.52
M.BED ROOM3.96X3.10
DINING3.05X4.42
DRAWING3.66X3.35
KITCHEN2.13X3.35
0.97m WWASH AREA
MD
D
D
D1
D1
SD
KWV
V
WW1
W1
W3
W2
BED ROOM3.05X3.66
M.BED ROOM3.05X4.11
TOILET1.52X2.44
TOILET1.42X2.44
1.22M WIDE UTILITY
KITCHEN3.05X2.59
DRAWING3.30X3.96DINING
3.05X5.33
W
Co
mm
.sh
aft
Elec.shaft
W
W1
W3
W3
V V
KW
MDD
D
D1
D1
D2
BED ROOM3.51X3.66
TOILET2.90X1.32
TOILET1.52X2.44
DRAWING3.76X3.66
DINING5.13X3.66
M.BED ROOM3.66X4.78
TOILET1.52X2.74
KITCHEN2.29X3.35
1.22
M W
IDE
UTI
LITY
MD
D
D
D1
D1
D1
D2
V
V
V
W
KW
KW1
W1
MDDRAWING4.67X3.35
W
BED ROOM4.11X3.35
W3
W
D
TOILET2.44X1.32
D1
VD
W2
BED ROOM3.35X3.45
V
D1
TOILET2.74X1.52
DINING2.90X5.08
LIVING2.54X3.66
M.BED ROOM4.72X3.66
D
W3
W1
TOILET1.52X3.05
V
D1
KW1
KITCHEN2.44X3.66
KW
3
2
T : 0.30mR : 0.15mW : 1.52m
T : 0.30mR : 0.15mW : 1.52m
3.76
1.52
3.76
1.52
3.05 3.45 3.76
3.76 3.45
3.38
0.5310.77
3.15
8.84
2.28
1.53
14.6
1
10.0
110
.01
3.05
10.97
10.97
2.19
10.41
4.78
3.76
1.52
3.45
1.52
4.72
1.52
3.45
1.52
3.76
1.52
5.49
1.52
4.06
1.52
4.06
1.52
3.45 3.76 3.05 3.15 3.15 3.05 2.29 2.29
5.18
3.45
3.05
4.88
3.76
1.901.91
2.24 3.054.063.05
3.453.76
11.59
3.05
3.75
9.40
10.0
1
3.15
1.98
9.09
9.75
8.08
8.84
14.7
4
1.93 1.93
23.77
10.0
1
10.97
8.28
9.75
9.30
12.7
0
9.30
12.7
0
9.7510.97
AA
B
B
6 4 3
1
2
OPEN TO SKY
FIRST FLOOR PLAN
GLS/W GLS/W GLS/W GLS/W
MD1
GLS/WG
LS/W
GLS/W
GLS/W
GLS/W GLS/W
GLS/W
GLS/W
GLS/W
CELLARVENTILATION
DUCT
BED ROOM3.35X3.05
TOILET2.74X1.37
TOILET2.74X1.52
M.BED ROOM4.27X3.35
TOILET1.73X1.83
KITCHEN3.05X3.00
1.22
M W
IDE
UTI
LITY
DINING3.35X6.15
MD
D
D
D1
D1
D1 D2
KWV
V
V
WW
W
W3
W3
W3
BED ROOM3.66X3.05
TOILET2.13X1.68
TOILET2.44X1.37
TOILET3.05X1.52
DINING4.57X3.30
LIVING3.35X2.95
M.BED ROOM3.66X3.35
KITCHEN3.35X2.74
1.52M WIDEUTILITY
MD
D
D
D1
D1
D1
D2
KW
KW1
V
V
V
W1
W1
W1
W3
DN UP
DN
2.00 WIDE CORRIDOR
2.00 WIDE CORRIDOR
2.0
0 W
IDE
CO
RRID
OR
2.00 WIDE CORRIDOR
2.00 WIDE CORRIDOR 2.00 WIDE CORRIDOR
2.0
0 W
IDE
CO
RRID
OR
2.0
0 W
IDE
CO
RRID
OR
Co
mm
.sh
aft
Elec.shaft
LOBBY3.05X3.35
BED ROOM3.35X3.05
TOILET2.74X1.37
TOILET2.74X1.52
M.BED ROOM4.27X3.35
TOILET1.73X1.83
KITCHEN3.05X3.00
1.22
M W
IDE
UTI
LITY
DINING3.35X6.15
D
D
D1
D1
D1 D2
KWV
V
V
WW
W
W3
W3
W3
BED ROOM3.66X3.05
TOILET2.13X1.68
TOILET2.44X1.37
TOILET3.05X1.52
DINING4.57X3.30
LIVING3.35X2.95
M.BED ROOM3.66X3.35
KITCHEN3.35X2.74
1.52M WIDEUTILITY
MD
D
D
D1
D1
D1
D2
KW
KW1
V
V
V
W1
W1
W1
W3
1.52m W. BALCONY
BED ROOM3.96X3.05
TOILET1.52X2.44
TOILET2.74X1.52
M.BED ROOM3.96X3.10
DINING3.05X4.42
DRAWING3.66X3.35
KITCHEN2.13X3.35
0.97m WWASH AREA
MD
D
D
D1
D1
SD
KWV
V
WW1
W1
W3
W2
BED ROOM3.05X3.66
M.BED ROOM3.05X4.11
TOILET1.52X2.44
TOILET1.42X2.44
1.22M WIDE UTILITY
KITCHEN3.05X2.59
DRAWING3.30X3.96DINING
3.05X5.33
W
Co
mm
.sh
aft
Elec.shaft
W
W1
W3
W3
V V
KW
MDD
D
D1
D1
D2
BED ROOM3.51X3.66
TOILET2.90X1.32
TOILET1.52X2.44
DINING5.13X3.66
M.BED ROOM3.66X4.78
TOILET1.52X2.74 KITCHEN
2.29X3.35
1.22
M W
IDE
UTI
LITY
MD
D
D
D1
D1
D1
D2
V
V
V
W
KW
KW1
W1
MDDRAWING4.67X3.35
W
BED ROOM4.11X3.35
W3
W
D
TOILET2.44X1.32
D1
VD
W2
BED ROOM3.35X3.45
V
D1
TOILET2.74X1.52
DINING2.90X5.08
LIVING2.54X3.66
M.BED ROOM4.72X3.66
D
W3
W1
TOILET1.52X3.05
V
D1
KW1
KITCHEN2.44X3.66
KW
3
2
EXTERNALSTAIRCASE
INTERNALSTAIRCASE
1.52
3.76
1.52
3.76
1.52
3.05 3.45 3.76
3.76 3.45
3.38
0.5310.77
3.15
8.64
2.28
1.53
14.6
1
10.0
110
.01
3.05
10.97
10.97
2.19
10.41
4.78
3.76
1.52
3.45
1.52
4.72
1.52
3.45
1.52
3.76
1.52
5.49
1.52
4.06
1.52
4.06
1.52
3.45 3.76 3.05 3.15 3.15 3.05 2.29 2.29
5.18
3.45
3.05
4.88
3.76
1.911.91
2.24 3.054.063.05
3.453.76
11.59
3.05
3.75
10.0
1
3.15
1.98
9.09
9.75
8.08
8.64
14.7
4
1.93 1.93
23.77
10.0
1
10.97
8.28
9.75
9.30
12.7
0
9.30
12.7
0
9.7510.97
B-ST-2
A
B
B
6 4 3
1
2
OPEN TO SKY
GROUND FLOOR PLAN
GLS/W
ENTRANCE
ENTRANCE
UP
UP
GLS/W GLS/W GLS/W GLS/W
MD1
MD1
MD
1 MD
1
GLS/WG
LS/W
GLS/WGLS/WGLS/W
GLS
/WG
LS/WG
LS/W
GLS/W
GLS/W
GLS/W
0.60m W Arch. Projection
Typical Floor Balcony Line
GLS/W GLS/W
GLS/W
GLS/W
GLS/W
LOUNGE8.23X9.60
GYM10.21X9.60
LIBRARY6.25X9.60
CELLARVENTILATION
DUCT
CELLARVENTILATION
DUCT
CELLARVENTILATION
DUCT
CELLARVENTILATION
DUCT
CELLARVENTILATION
DUCT
CELLARVENTILATION
DUCT
CELLARVENTILATION
DUCT
CELLARVENTILATION
DUCT
0.60m W Planter Box
0.60m W Planter Box 0.60m W Planter Box 0.60m W Planter Box
0.60m W Planter Box 0.60m W Planter Box 0.60m W Planter Box
GLS/W
MD
1
MD
1
WAITING HALL4.27X8.43
MD
1
MD
1
HOME THEATER9.35X8.43
WAITING HALL4.27X8.43
MEDITATION HALL9.35X8.43
CRECHE9.35X8.43
AEROBICS9.35X8.43
SWIMMING POOL17.98X7.62
2.00 WIDE CORRIDOR
DECK
DECKDECK
FRD
FRD
UP UP
WING - B WING - A
5
1.52m W. BALCONY
BED ROOM3.96X3.05
TOILET1.52X2.44
TOILET2.74X1.52
M.BED ROOM3.96X3.10
DINING3.05X4.42
DRAWING3.66X3.35
KITCHEN2.13X3.35
0.97m WWASH AREA
MD
D
D
D1
D1
SD
KWV
V
WW1
W1
W3
W2
BED ROOM3.51X3.66
TOILET1.52X2.44
TOILET2.90X1.32
DINING4.83X3.66
M.BED ROOM4.11X3.35
TOILET1.52X2.74
1.32M WIDE UTILITY
KITCHEN3.05X3.35
D2
DRAWING4.67X3.35
BED ROOM4.11X3.35
TOILET2.44X1.32
BED ROOM3.35X3.45
TOILET2.74X1.52
LIVING2.24X3.66
DINING2.90X5.08
M.BED ROOM4.11X3.66
TOILET1.52X2.44
KITCHEN3.05X3.66
KW
DRAWING3.15X3.66
DINING3.05X5.03
M.BED ROOM3.05X4.11
TOILET1.52X2.74 KITCHEN
3.35X2.74
1.22
M W
IDE
UTI
LITY
BED ROOM3.05X3.66
TOILET1.27X2.44
2.0
0 W
IDE
CO
RRID
OR
Co
mm
.sh
aft
Elec.shaft
MD
MD
MD
D
D
D
D
D
D
D
D1
D1
D1
D1
D1
D1
D1
D1
D2
GLS/W
GLS
/W
KW
KW1
KW
V
V
V
V
V
V
V
V
W W
W
W
W
W
W
W1
W2
W3
W3
W3
W3
6
74
4.72 3.45
4.06
1.52
4.06
1.52
4.72
3.45
1.52
2.29 3.05 3.15 3.152.29
2.29 2.29
4.06 2.24
1.68
5.18
3.45
3.05
4.88
3.76
10.62
4.78
8.08
9.75
8.28
9.09
8.28
3.05
9.30
12.7
012
.70
9.30
9.75
9.75
A
1.52
1.52
0.60m W Arch. Projection
Typical Floor Balcony Line
0.60m W Arch. Projection
Typical Floor Balcony Line
GLS
/W
1.52
0.60m W Arch. Projection
Typical Floor Balcony Line
GLS/W
5
1.52m W. BALCONY
BED ROOM3.96X3.05
TOILET1.52X2.44
TOILET2.74X1.52
M.BED ROOM3.96X3.10
DINING3.05X4.42
DRAWING3.66X3.35
KITCHEN2.13X3.35
0.97m WWASH AREA
MD
D
D
D1
D1
SD
KWV
V
WW1
W1
W3
W2
BED ROOM3.51X3.66
TOILET1.52X2.44
DRAWING3.76X3.66
TOILET2.90X1.32
DINING4.83X3.66
M.BED ROOM4.11X3.35
TOILET1.52X2.74
1.32M WIDE UTILITY
KITCHEN3.05X3.35
D2
DRAWING4.67X3.35
BED ROOM4.11X3.35
TOILET2.44X1.32
BED ROOM3.35X3.45
TOILET2.74X1.52
LIVING2.24X3.66
DINING2.90X5.08
M.BED ROOM4.11X3.66
TOILET1.52X2.44
KITCHEN3.05X3.66
KW
DRAWING3.15X3.66
DINING3.05X5.03
M.BED ROOM3.05X4.11
TOILET1.52X2.74
KITCHEN3.35X2.74
1.22
M W
IDE
UTI
LITY
BED ROOM3.05X3.66
TOILET1.27X2.44
Co
mm
.sh
aft
Elec.shaft
MD
MD
MD
D
D
D
D
D
D
D
D1
D1
D1
D1
D1
D1
D1
D1
D2
GLS/W
GLS
/W
KW
KW1
KW
V
V
V
V
V
V
V
V
W W
W
W
W
W
W
W1
W2
W3
W3
W3
W3
6
74
4.72 3.45
4.06
1.52
4.06
1.52
4.72
3.45
1.52
2.29 3.15 3.152.29
2.29 2.29
4.06 2.24
5.18
3.45
3.05
4.88
3.76
10.62
4.78
8.08
9.75
8.28
9.09
9.30
12.7
012
.70
9.30
9.75
9.75
1.52
1.52
Typical Floor Balcony Line
Typ
ical
Flo
or B
alco
ny L
ine
GLS
/W
Typ
ical
Flo
or B
alco
ny L
ine
1.52
Typical Floor Balcony Line
0.60m W Planter Box0.60m W Planter Box
0.60
m W
Pla
nter
Box
0.60
m W
Pla
nter
Box
0.60m W Planter Box
WING - B WING - A
UP
DN UP
DN
D
W2W2W2W2
T : 0.30mR : 0.15mW : 1.52m
T : 0.30mR : 0.15mW : 1.52m
EXTERNALSTAIRCASE
INTERNALSTAIRCASE
1.52
1.52
22.66
B-ST-1 B-ST-2
FRD
Shaft Shaft
Garbagechute
1.52x3.05
F/P.LIFT2.59X2.00
B-L-2P.LIFT
2.00X2.00
B-L-1
LOBBY3.05X3.05
D3
T : 0.30mR : 0.15mW : 1.52m
T : 0.30mR : 0.15mW : 1.52m9.40
UP
FRD
W2W2
T : 0.30mR : 0.15mW : 1.52m
T : 0.30mR : 0.15mW : 1.52m
1.52
22.66
B-ST-1
FRD
Shaft Shaft
Garbagechute
1.52x3.05
F/P.LIFT2.59X2.00
B-L-2P.LIFT
2.00X2.00
B-L-1
LOBBY3.05X3.05
D3
Gla
ss P
art
itio
n
Glass Partition Glass Partition
Glass PartitionGlass Partition
Gla
ss P
art
itio
n
Gla
ss P
art
itio
n
Glass Partition Glass Partition
Glass PartitionGlass Partition
Gla
ss P
art
itio
n
ROOM3.66X3.66
ROOM3.66X3.50
ROOM3.35X3.35
ROOM3.66X3.50
ROOM3.35X3.35
ROOM3.66X3.66
DRAWING3.76X3.35
DRAWING3.35X3.35
DRAWING3.76X3.35
DRAWING3.35X3.35
DRAWING3.76X3.66
DRAWING3.76X3.66
ROOM3.66X3.66
ROOM3.66X3.50
ROOM3.35X3.35
ROOM3.66X3.50
ROOM3.35X3.35
ROOM3.66X3.66
W2 W2W2W2
W2 W2W2W20.60m W Arch. Projection
Typical Floor Balcony Line
0.60
m W
Arc
h. P
roje
ctio
n
Typ
ical
Flo
or B
alco
ny L
ine
0.60
m W
Arc
h. P
roje
ctio
n
Typ
ical
Flo
or B
alco
ny L
ine
0.60m W Arch. Projection
Typical Floor Balcony Line
0.60m W Arch. Projection
Typical Floor Balcony Line
0.60m W Arch. Projection
Typical Floor Balcony Line
0.60m W Arch. Projection
Typical Floor Balcony Line
0.60m W Arch. Projection
Typical Floor Balcony Line
Typical Floor Balcony LineTypical Floor Balcony LineTypical Floor Balcony Line
Typical Floor Balcony Line Typical Floor Balcony Line Typical Floor Balcony Line Typical Floor Balcony Line Typical Floor Balcony Line
Typ
ical
Flo
or B
alco
ny L
ine
Typ
ical
Flo
or B
alco
ny L
ine
Typ
ical
Flo
or B
alco
ny L
ine
Typ
ical
Flo
or B
alco
ny L
ine
0.60
m W
Arc
h. P
roje
ctio
n0.
60m
W A
rch.
Pro
ject
ion
0.60
m W
Pla
nter
Box
0.60
m W
Pla
nter
Box
MD5
MD5
UP
UP DN
DN
EXTERNALSTAIRCASE
1.52
F/P.LIFT2.59X2.00
shaft
A-L-1
LOBBY3.05X3.05
Shaft
P.LIFT2.00X2.00
A-L-2Garbage
chute1.52x3.05
D3
FRD
A-ST-2
FRD
1.52
A-ST-1INTERNALSTAIRCASE
W2W2
UP
UPDN
DN
EXTERNALSTAIRCASE
1.52
F/P.LIFT2.59X2.00
shaft
A-L-1
LOBBY3.05X3.05
Shaft
P.LIFT2.00X2.00
A-L-2Garbage
chute1.52x3.05
D3
FRD
A-ST-2
1.52
A-ST-1INTERNALSTAIRCASE
FRD
FRD
FRD
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 5
Fig 2.3 Parking floor plan
7.87
m
3.05m
3.45
m
3.05m
1.76
m
2.28
m
1.53m
11.56m
3.05
m
8.52m
12.7
5m
9.70
m
3.05m
3.05m
6.30
m
1.93m 1.93m
4.73
m
3.05m
4.57
m
3.56m
3.05
m
11.59m
3.05
m
9.40m
3.75m
26.82m
3.81
m
5.50m WIDE DRIVE WAY
5.18
m W
IDE
DR
IVE
WA
Y
5.18
m W
IDE
DR
IVE
WA
Y
4.58
m W
IDE
DR
IVE
WA
Y
5.50m WIDE DRIVE WAY
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
26.82m
3.81
m
TWO WHEELER PARKING
TWO WHEELER PARKING
5.50m WIDE DRIVE WAY
5.18
m W
IDE
DR
IVE
WA
Y
5.18
m W
IDE
DR
IVE
WA
Y
4.58
m W
IDE
DR
IVE
WA
Y
5.50m WIDE DRIVE WAY
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
TWO WHEELER PARKING
26.82m
3.81
m
26.82m
3.81
m
2.00 122.14m
10.15m40.39m
123.93m
EN
TR
AN
CE
EN
TR
AN
CE
EN
TR
AN
CE
T : 0.30mR : 0.15mW : 1.52m
1.52
m
1.52
mC A R P A R K I N GC A R P A R K I N G
C A R P A R K I N GC A R P A R K I N GC A R P A R K I N G
CA
R
P
AR
KI
NG
C A R P A R K I N GC A R P A R K I N GC A R P A R K I N G
CA
R
P
AR
KI
NG
CA
R
P
AR
KI
NG
CA
R
P
AR
KI
NG
C A R P A R K I N GC A R P A R K I N G
CA
R
P
AR
KI
NG
CA
R P
AR
KIN
G
5.03
m
2.50m
5.03
m
2.50m 2.50m
5.03m
2.50
m
5.03
m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
5.03m
5.03m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
2.50m
5.03
m
2.50m
5.03
m
2.50m
5.03
m
TWO WHEELER PARKING
TWO WHEELER PARKING
C A R P A R K I N GC A R P A R K I N GC A R P A R K I N G
C A R P A R K I N GC A R P A R K I N G
CA
R
P
AR
KI
NG
C A R P A R K I N GC A R P A R K I N GC A R P A R K I N G
CA
R
P
AR
KI
NG
CA
R
P
AR
KI
NG
C A R P A R K I N G
5.03
m
2.50m
5.03
m
2.50m 2.50m
5.03m
2.50
m
5.03m
2.50
m
5.03
m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
5.03m
5.03m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
5.03m
2.50
m
2.50m
5.03
m
2.50m
5.03
m
2.50m
5.03
m
5.03
m
2.50m
2.50m
4.97
m
STORE ROOM3.78x5.90
4.80
m
2.50m
4.80
m
2.50m
4.80
m
2.50m
4.80
m
2.50m
4.80
m
2.50m
4.80
m
2.50m
5.03
m
2.50m
4.50m
2.50
m
4.50m
2.50
m
4.50m
2.50
m
2.00
2.00
2.00
2.00
2.00
CA
R
P
AR
KI
NG
CA
R
P
AR
KI
NG
4.50m
2.50
m
4.50m
2.50
m
4.50m
2.50
m
4.80
m
2.50m4.
80m
2.50m
4.80
m
2.50m
4.80
m
2.50m
4.80
m
2.50m
4.80
m
2.50m
2.00
2.00
2.00
2.00
2.00
2.00m
10.15m40.39m
D.G ROOM3.56x4.42
LAUNDRY ROOM13.92x3.45
MD
1
W1
W1
MD1
W W
W
W1
MD1
W1W1
PANEL ROOM3.78x5.90
ChillerRoom
3.56x4.42
LUMBER ROOM13.92x3.45
MD
1
W1
W1
MD1
W W
W
MD1
W1W1
MD1
W1
W
ENTRANCEW
1W
ENTRANCE
LOBBY7.52x2.00
LOBBY7.42x2.00 MD1
MD1
W1
W1
LOBBY5.13x2.74
ENTRANCE
SITE BOUNDARY LINE
RCC RETAINING WALL
SITE BOUNDARY LINE
RCC RETAINING WALL
SITE
BO
UN
DA
RY L
INE
SITE
BO
UN
DA
RY L
INE
RC
C R
ETA
ININ
G W
ALL
SITE BOUNDARY LINE
RCC RETAINING WALL
SITE BOUNDARY LINE
RCC RETAINING WALL
SITE
BO
UN
DA
RY L
INE
RC
C R
ETA
ININ
G W
ALL
RC
C R
ETA
ININ
G W
ALL
SITE
BO
UN
DA
RY L
INE
5.18m
5.18m
4.80
m4.
80m
4.80
m4.
80m
5.18m
5.18m
Shaft Shaft
Garbagechute
1.52x3.05
F/P.LIFT2.59X2.00
B-L-2P.LIFT
2.00X2.00
B-L-1 LOBBY3.05X3.05
D3
UP
DN UP
DN
T : 0.30mR : 0.15mW : 1.52m
T : 0.30mR : 0.15mW : 1.52m
EXTERNALSTAIRCASE
INTERNALSTAIRCASE
FRD FRD
T : 0.30mR : 0.15mW : 1.52m
T : 0.30mR : 0.15mW : 1.52m
B-ST-1 B-ST-2
UP
UP
EXTERNALSTAIRCASE
INTERNALSTAIRCASE
FRD FRD
T : 0.30mR : 0.15mW : 1.52m
A-ST-1 A-ST-2
11.56m 9.40m
EN
TR
AN
CE
EN
TR
AN
CE
1.52
m
1.52
m
MD1
W1
W
ENTRANCE
W1
W
ENTRANCE
LOBBY7.52x2.00
LOBBY7.42x2.00 MD1
MD1
W1
W1
LOBBY5.13x2.74
ENTRANCE
Shaft Shaft
Garbagechute
1.52x3.05
F/P.LIFT2.59X2.00
A-L-2P.LIFT
2.00X2.00
A-L-1LOBBY
3.05X3.05
D3
T : 0.30mR : 0.15mW : 1.52m
T : 0.30mR : 0.15mW : 1.52m
50.7
7m
122.14m
123.93m
50.7
7m
R.SELECTRICAL
ROOM4.83x5.06
W
11.46
11.46m
SU
MP
AN
D P
UM
P R
OO
MIN
CE
LLA
R F
LOO
R L
EV
EL
TWO WHEELER PARKING
7.06
A.H.U ROOM4.83x5.45
W
MD
1M
D1
TW
O W
HE
ELE
R P
AR
KIN
G
UP
UP DN
DN
1.52
m
FRD
EXTERNALSTAIRCASE
A-L-1F/P.LIFT2.59x2.0
Shaft
LOBBY2.59x3.05
P.LIFT2.0X2.0
A-L-2
Shaft
Garbagechute
1.52x3.05
A-ST-2
FRD
1.52
m
A-ST-1
INTERNALSTAIRCASE
EN
TR
AN
CE
EN
TR
AN
CE
UP
UP DN
1.52
m
FRD
EXTERNALSTAIRCASE
A-L-1F/P.LIFT2.59x2.0
Shaft
LOBBY2.59x3.05
P.LIFT2.0X2.0
A-L-2
Shaft
Garbagechute
1.52x3.05
A-ST-2
FRD
1.52
m
A-ST-1
INTERNALSTAIRCASE
EN
TR
AN
CE
2.56
7.06
R S
FHS-01
GARBAGE4.83x5.45
W
MD
1M
D1
Cellar Ventilation
Duct9.23 Sqmts
Cellar Ventilation Duct
64.82 Sqmts
Cellar Ventilation Duct
64.82 SqmtsCellar
Ventilation Duct
24.00 Sqmts
VENT.DUCT
ABOVE
VENT.DUCT
ABOVE
VENT.DUCT
ABOVE
VENT.DUCT
ABOVE VENT.DUCT
ABOVE
VENT.DUCT
ABOVE
VENT.DUCTABOVE
VENT.DUCT
ABOVE
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 6
2.2.1.1 Storm water drains:Conservation of water resource is most important aspect of the project duringconstruction and occupation phases. Storm water drainage planning, domestic waterplanning and sewerage transfer and sewage treatment planning are most essential.
Calculation for Storm Water DrainQuantity of storm water(a) Without projectArea of Catchment, ‘A’ : 0.7946 HaRun off Coefficient, ‘C’ : 0.6Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q : 0.053 m3/sec(b) With project :Area for catchment for roof and road : 0.568 HaArea of Catchment, ‘A’ : 0.568 HaRun off Coefficient, ‘C’ : 0.9Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q = : 0.057 m3/sec
Area for catchment for open areas : 0.227 HaRun off Coefficient, ‘C’ : 0.6Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q = : 0.015 m3/secTotal Discharge : 0.072 m3/secBut, Discharge, Q = A/VWhere,A= Area of the Drain,V= Max. Permissible Velocity : 6 m/sec for concrete drain
Area of drain, ‘A’ = Q/V : 0.012 m2
Taking depth of drain as 0.6 m atthe starting point : 0.6Width of drain = Area/depth = : 0.020 m 20 mm
Width of the drain is to taken 20 mm and depth varies according to the slope ofground.
Rainwater Harvesting StructuresStorm water drains are provided with recharge pits which will act as flow dissipatersand also as infiltration trenches to ensure percolation of water and enhance the groundwater table. The roof waters are channeled through storm water drains, which areconnected with water harvesting pits. Rain Water Harvesting Pit shown in fig 2.4andContour plan is shown in fig 2.5
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 7
Fig2.4 Rain Water Harvesting Pit
Table 2.3 Strom Water Runoff
Land UseArea inHectar
es
Vol./hrafter
development C=0.8
Vol./hrbefore
Development C=0.6
Difference inDischarges Remarks
Roof Area 0.22 69.8 52.3 17.4 Harvested in sump witha capacity of 20 m3
Road Area 0.35 111.9 83.9 28.0 14 nos. of RWH pitsare provided of size1.5m X 1.5m X 2.0 mOpen Area 0.23 27.2* 54.4 -27.2
TOTAL 0.79 18.2*C=0.3 after development
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 8
2.2.1.2 Water Availability:Water is required for the construction as well as during occupation stage as the same isan important resource. The water requirement during construction is in the order of40 cum/day with a peak demand of 80 cum/day, and during occupation stage in theorder of 151.7 KLD. The water resource available with the Municipal authorities wasstudied to identify the source and feasibility. The water resource both domestic waterand sewage is dealt by the Hyderabad Metropolitan water supply and Sewerage Board(HMWSSB) in the GHMC area. The HMWSSB has been maintaining the water supplyresources for Hyderabad along with the treatment of wastewater. The resourcesavailable with the HMWSSB are presented in table 2.4.
Table 2.4 Details of present sources of water supply to Hyderabad
Source Name River Year ImpoundmentName
Distance fromcity km
InstalledCapacity MGD
Osmansagar Musi 1920 Osmansagar 15 27Himayatsagar ESI 1927 Himayatsagar 9.6 18Manjira Phase I Manjira 1965 Manjira barrage 58 15Manjira Phase II Manjira 1981 Manjira barrage 59 30Manjira Phase III Manjira 1991 Singur Dam 80 37Manjira Phase IV Manjira 1993 Singur Dam 80 38Krishna Phase I Krishna 2005 NagarjunaSagar 116 90Krishna Phase II Krishna 2008 NagarjunaSagar 116 90Krishna Phase III Krishna 2015 NagarjunaSagar 116 90Godavari Phase I Godavari 2016 Yellampally 186 172
Source: Hyderabad Metropolitan Water Supply & Sewerage Board, www.hyderabadwater.gov.in
It may be noted that the following water supply projectsi.e., Krishna Phase III (Part II)with 45 MGD capacity and Godavari phase – I with 172 MGD capacity is anticipated tobe operational during 2015 and 2016 respectively. It may also be noted that thedependability of Osman sagar and Himiyathsagar is reduced to approximately 60%. 45MGD supply is available.
Domestic Water: It is proposed to draw domestic water from the HyderabadMetropolitan Water Supply and Sewerage Board (HMWSSB), which have beenencouraging the bulk consumers. The water shortage if any during summer season willbe drawn from ground water sources /bulk suppliers/municipal tankers. The waterrequirement of the project during occupation stage is in the order of 151.7 KLD. Thewater requirement during construction will be from ground water sources and therequirement is in the order of 30 m3/day. The water requirement for the project duringthe occupation stage is presented in table 2.5. The water saving is presented in table2.6.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 9
Table 2.5 Water Requirement of the Project
Land Use No. ofUnits
No. ofPersons/
unit
Waterrequirement per
person in l *
Total WaterRequirement in
KLDWING- A & B 204 5 135 137.7Amenities 1 65 45 2.9Swimming pool 1 5.0Visitors 2 15 6.1TOTAL 151.7*Water requirement as per NBC
Table 2.6 Water Saving Measures
Land Use No. ofUnits
No. ofPersons/
unit
WaterRequirement
/ KLD
Treatedwater
reuse/dayKlpcd
EffectiveWater
Requirementin KLD
WING- A & B 204 5 137.7 40.8 96.9Amenities 1 65 2.9 1.3 1.6Swimming pool 5.0 5.0Visitors 2 6.1 3.1 3.1TOTAL 151.7 45.2 106.6
The effective water consumption is reduced by 45.2 KLD and the requirement will be inthe order of 106.6 KLD. The water balance of the project during occupation stage istabulated in table 2.7
Table 2.7 Water BalanceInput KLD Output KLDDomestic water fromHMWSSB 106.6 Excess treated water will be sent to
sewer lines 74.1
Recycled water 45.2 Recycled water 45.2Water requirement for green beltduring non monsoon 2.1Losses approx 20% 30.3
Total 151.7 Total 151.7
The water used in the order of 151.7 KLD would generate 121.4 KLD of wastewater,which has to be treated for reuse and excess will be let in to municipal sewer lines. Theeffluent characteristics of wastewater are presented in table 2.8.
Sewage treatment plant based on Fluidized Aerobic Bio Reactor (FAB) technologyPROCESS DESCRIPTION:The raw sewage will be collected in a collection sump and pumped to mechanical barscreen chamber for removal of large floating matter followed by grit removal in GritChamber. The raw sewage will then be collected in an equalization tank for
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 10
homogenization of hydraulic load. The tank contents will be kept in suspension bymeans of course bubble serration through pipe grid. The equalization tank, with airflow indicator for continuous monitoring of air supply to the tank in order to avoidseptic conditions, will be covered from top (RCC or FRP) to avoid nuisance. Theequalized effluent will then be pumped to two Fluidized Aerobic Bio Reactors (FAB) inseries where BOD/COD reduction can be achieved by virtue of aerobic microbialactivities. The oxygen required will be supplied through coarse air bubble diffusers.The bio-solids formed in the biological process will be separated in the down streamTube Settler. The clear supernatant will gravitate to the chlorine contact tank wheresodium hypochlorite will be dosed for disinfection of treated water prior to disposal.
The biological sludge generated in the FAB and settled in the tube settlers will becollected in a sludge sump and then pumped to sludge drying bed for de watering. Thedried sludge will then be disposed off suitably as manure. The schematics of theprocess are shown. The two main components of the treatment system viz. The FABreactor and tube settler are described in the following sections.
Fluidized Aerobic Bio Reactor (FAB)Conventional effluent treatment plants are large sized, power intensive and require alot of monitoring. Scarcity of open space and rising land a power costs have forced theindustries to look our for space saving, compact and efficient treatment options. Thishas led to the development attached growth processes where the bio mass is retainedwithin the aeration tank obviating the need for recycle. These plants are not onlycompact but also user friendly. The endeavor to have a continuously operating, no-clogging biofilm reactor with no need for back washing, low head-loss and high specificbiofilm surface area culminated in the most advanced technology of aerobic biologicalfluidized bed treatment where the biofilm (biomass) grows on small carrier elementsthat move along with the water in the reactor. The movement is normally caused byaeration in the aerobic version of the reactor.The reactor combines all the advantages and best features of Trickling filters, Rotatingbiological contractors, activated sludge process and submerged fixed film reactorswhile eliminating the drawbacks of these systems. The plants are more compact andmore energy efficient.
The Fluidized Aerobic Bio Reactor (FAB) consists of a tank in any shape filled up withsmall carrier elements. The elements are made up of special grade PVC orpolypropylene of controlled density (shown in plate). For media of specific gravity 0.92-0.96 the overall density could be expected to increase up to 9.5% when full of biomasssuch that they can fluidize using an aeration device. A biofilm develops on theelements, which move along the effluent in the reactor. The movement within thereactor is generated by providing aeration with the help of diffusers placed at thebottom of the reactor. Then thin biofilm on the elements enables the bacteria to actupon the biodegradable matter in the effluent and reduce the BOD/COD content in thepresence of oxygen available from the air that is used for fluidization.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 11
Table 2.8 Characteristics of Waste waterParameter Quantity in mg/l
PH 6 – 7Total Suspended Solids 400 – 600BOD 200 – 300COD 450 – 500
Design of the unitBasic dataFlow : 122 KLDCapacity : 150 m3
Peak factor : 3.5Peak flow Q peak : 525 m3/dayInfluent BOD : 200 mg/litInfluent Suspended Solids : 200 mg/litInfluent COD : 350 mg/litEffluent BOD : 30 mg/litEffluent COD : 200 mg/litEffluent Suspended Solids : 100 mg/lit
1. Bar Screen ChamberAverage flow : 0.0017 m3/secPeak factor : 3.5Peak flow : 0.006 m3/secVelocity at peak flow : 0.75 m/SecEffective area of screen RequiredAt average flow : 0.005 m2
At Peak flow : 0.0075 m2
Provide Effective area of screen : 0.0075 m2
Considering the bar of dia. 10 mm(w) and clear spacing of 20 mm (b)Overall area required : 0.012 m2
Considering screen depth as : 0.024 m Consider 0.5 mNumber of clear spacing : 0.3Number of bars : 1 Consider 3 Nos.Hence Provide 5 barsProvide a screen of 0.5 m X 0.5 m at an inclination of sin 600. In a screen channel of onemeter (1 m) length.
2. Grit Chamber :The flow from the bar screen chamber is let into the Grit Chamber of minimum 2 hourscapacity. This tank is provided to even out the flow variation, and to provide acontinuous feed into the secondary biological treatment units.Peak flow Q : 0.006 m3/secProviding a flow through velocity of 0.30 m/secCross sectional area of Channel (0.006/0.3) : 0.02 m2
Surface area of channel (0.006/0.013) : 0.46 m2
Assuming depth d : 0.2 m
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 12
Width of channel (0.02/0.2) : 0.1 m (say 0.2m)Length of channel (0.46/0.1) : 4. 6 m (say 4.6 m)Provide two channels each of 0.2 m wide and 4.6 m long with depth of waste water 0.2m.
3. Equalization tank:The flow from the bar screen chamber is let into the equalization tank of minimum2hours capacity. This tank is provided to even out the flow variation, and to provide acontinuous feed into the secondary biological treatment units.Average flow : 6.25 m3/hrPeak factor : 3.5Peak flow : 21.87 m3/hrHydraulic retention tank = 2 hrs at Peak flowHence required volume of the tank : 43.75 m3
Provide tank of : 43.75 m3 CapacityAssuming depth : 3 mArea : 14.58 m2
Assuming length to width ratio (1:1) ; l=blength of the tank : 3.8 mwidth of the tank : 3.8 mAir required for agitation : 0.01 m3/ m2 minTotal air required : 26.25 m3/hrAir blower required : 40 m3/hr @ 3.8 mwcEffluent transfer pump : 6.25 m3/hr @ 8 mwc
4. Fluidized Aerobic Bio Reactor (FAB):The polypropylene media have been provided with a specific surface area of 350 – 520m2 /m3. This allows micro-organisms to get attached and biomass concentration can beincreased to four folds as compared to Activated Sludge Process. This enables toconsider higher Organic loading rates.
The micro-organisms attached to media are kept in a fluid state thereby maintainingthe CSTR (continuous Stirrer tank reactor) regime as well as two tanks are provided inseries making the plug – flow system. This will enhance the efficiencies and have themerits of both CSTR and plug-flow regimes.Organic loading rate : 3.2 kg BOD/ m3 dOrganic load : 26 kg/dayVolume of the tank : 9.37 m3
Assume the depth : 3 mNo. of tanks in series : 1Size of the tank : 1.8 m dia. x 3.0 SWDSpecific gravity of media : 0.92 to 0.96Specific surface area of media : 350 – 520 m2 /m3
Media filling : 30 – 50 % of tank volumeOxygen required : 2 kg / kg BODOxygen in air : 23%Specific gravity of air @ 30 deg. : 1.65
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 13
Aeration : Coarse bubbleOxygen transfer efficiency : 12%Air required : 77.7 m3/hrAir blower required : 80 m3/hr @ 6.5 m wc
5.Tube settlerSurface loading rate : 48 m2 /m3 dSurface area required : 3.125 m2
Tank size : 3.0 m x 6.0 m x 2.7 m SWD With 55deg. hopper bottom
Tube Modules : 3.0m x 6.0 m x 0.6 m ht.Tube inclination : 60 deg.Settling area for 60 deg slope : 11 m2 /m3
Cross sectional area of tubes : 120 mm x 44 mm HexagonalHydraulic radius : 1/61 cm (1.5 cm)Shape factor : 0.6 – 0.7 for media settleable solids
6. Pre Filtration tankThe flow from the each individual settling tank i.e., the supernatant liquid is let into therespective Pre-Filtration Tank, which has a minimum 1.5 hours holding capacity. Thistank is provided to hold the treated effluent and give an even flow to the pressure sandfilter.Average flow : 6.25 m3/hrPeak factor : 2 m3/hrPeak flow : 12.5 m3/hrProvide min 1.5 hours holding capacity.Hence required volume of the tank : 18.75 m3
7. Pressure Sand Filter:Vertical down flow type with graded/sand bed under drain plate with polysterenestrains.Flow : 150 m3/dayRate of filtration assumed as : 10 m3/m2/hrRequirement of treated water for usage in 20 hrs : 7.5 m3/hrDia. of filter of 1 nos. : 980 mmProvide pressure sand filter of 980 mm dia. and 1200 mm HOS with sand as medialayer, under drain pipe, laterals face piping etc for each stream.
8. Activated Carbon Filter:Vertical down flow type with graded/sand bed under drain plate with polysterenestrains.Flow : 150 m3/dayRate of filtration assumed as : 10 m3/m2/hrRequirement of treated water for usage in 20 hrs : 7.5 m3/hrDia of filter of 1 nos. : 980 mmProvide Activated Carbon filter of 980 mm dia with granular Activated carbon as mediaand 1200 mm HOS with sand as media layer, under drain pipe, laterals face piping etc
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 14
for each stream.
9.Final Treated Water Holding TankIt is always preferred to provide one final holding tank of minimum one day holdingcapacity, so that the treated effluents can be stored and used back for gardening orother tertiary purposes.Capacity: 150 m3
10. Sludge Filter Press:The biomass in the aeration tank stabilizes BOD in wastewater by consuming theorganic matter in the wastewater. The metabolic activity results in growth of thebiomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank hasbeen provided with filter press for dewatering sludge. The filtrate drains off throughthe media, which is again let into equalization tank.The dewatered sludge is collected in trays, which can be used as manure in the garden.No. of plates : 24Size of plates : 600 mm X 600 mmPlate moc (material of construction) : PP (poly propline)Type of operation : HydraulicPower pack capacity : 2 HPThe biomass in the aeration tank stabilizes BOD in wastewater by consuming theorganic matter in the wastewater. The metabolic activity results in growth of thebiomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank hasbeen provided with filter press for dewatering sludge. The filtrate drains off throughthe media, which is again let into equalization tank. The dewatered sludge is collectedin trays, which can be used as manure in the garden.
Characteristics of Treated Waste waterParameter Quantity in mg/l
pH 7 – 8Total Suspended Solids 100BOD 30COD 100
Disposal of Treated Waste Water: It is proposed to reuse the treated wastewater forgreen belt development and for toilet flushing. Excess treated water shall be let outinto the municipal sewer line. It is proposed to release/dispose the storm water in thestorm water drains.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 15
Fig2.5 Sewage Treatment Plant
SEW
AG
E TR
EATM
ENT
PLA
NT
FLU
IDIZ
ED A
ERO
BIC
BIO
REA
CTO
R T
ECH
NO
LOG
Y (F
AB
)
Slud
ge d
ewat
erin
gsy
stem
EQT
TAN
K
PSF
ACF
Bar S
cree
n/ G
rit
Cham
ber
Raw
Sew
age
Ove
rflo
w
Filt
er F
eed
Pum
p(1
W+1
S)
Slud
geD
ispo
sal
SLU
DG
EH
OLD
ING
TAN
K
CLA
RIFI
EDW
ATER
TAN
K
FAB
REA
CTO
R(P
acka
ge u
nit)
TREA
TED
WAT
ERTA
NK
To R
euse
TUBE
Sett
lers
UV
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 16
2.2.1.3 Solid WasteMunicipal Solid Waste CompositionIn India the biodegradable portion dominates the bulk of Municipal Solid Waste.Generally the biodegradable portion is mainly due to food and yard waste.
Table 2.9 Composition of Municipal Solid WasteType Composition (%) Solid waste in kg
Paper 8 52Plastics 9 59Metals 1 7Glass 1 7others 4 26Biodegradable 48 313Inerts 25 163Rags 4 26Total 100 652
(Source: NSWAI- National Solid Waste Association of India estimate)
Design StageThe total number of people anticipated to stay in the housing project is in the range of1500-2000. The anticipated solid waste/garbage is in the range of 500 g/head, and thetotal garbage will be in the order of 652 kg/day. The present practice is to collect thegarbage from each flat using the services of NGO’s and send it to the segregation pointby cycle-rickshaws. The area of Serilingampally has no solid waste disposal plan,however residents of the surrounding layouts are sending their solid waste through theGHMC appointed NGO for collection. Table 2.10 presents the anticipated garbagequantity after occupation. The responsibility of garbage collection and disposal lieswith municipality, however the project authorities propose to educate the residents tosegregate the waste at source before disposal.
Table: 2.10. Solid Waste Generation
Land Use No. ofUnits
No. of Persons/unit
Total No. ofPersons
Total Solid waste inKgs @ 0.5 kg/head
WING- A & B 204 5 1020 510Amenities 1 65 65 20Visitors 2 408 122
TOTAL 652
2.2.2 CONSTRUCTION STAGEThe sequence of construction operations and the approximate time requirement ispresented in the following table 2.11. The construction sequence is for more number offloors and standard housing flats. The time schedule of the entire project isapproximately 36 months.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 17
Table: 2.11 Construction SequenceS.No. Description of work
1 Clearing and Grubbing2 Leveling by way of cut and fill3 Foundation Excavation.4 Foundation PCC & Concrete & Plinth Beam.5 Column lifting up to GF Roof.6 1st floor slab reinforcement & shuttering & Concreting.7 Stair case slab8 1st floor column lifting up to 1st floor roof.9 1st floor roof shuttering, reinforcement & concreting.
10 Deshuttering of GF Roof & cleaning.11 Deshuttering of 1st Roof & cleaning.12 Brick work in GF floor.13 Brick work in 1st floor.14 Staircase up to terrace.15 Staircase headroom slab.16 Plumbing works (concealed works).
Electrical conduit junction boxes & board fixing.Plastering works.
Internal (GF & FF)External (GF & FF)
17 Fixing of door & window frames.18 Plinth filling & floor PCC.19 Floor Tiling Works, Bath Room, kitchen & platform works.20 Staircase stone works.21 Terrace waterproofing works.22 Parapet wall in terrace & miscellaneous works.23 Fixing of door & window shutters.24 Fixing of sanitary fittings.25 Electrical wiring & fixtures.26 Painting works.27 External development & compound wall.
The clearing and grubbing activity involves clearing of shrubs mainly as the land area isdevoid of any trees due to biogenic pressures. The cut and fill operation for the entirearea is presented in table 2.12.
Table 2.12 Earth Work Quantities
S.No. Area Qty. of fill (m3) Qty. of cut (m3) Surplus fill(m3) Surplus cut (m3)
1 Site area 7628 9535 ---- 1907
The construction of this magnitude would require huge quantities of constructionmaterials. The material requirement for the project is presented in table 2.13.Thusaggregate requirement will be met from within the plant site. The lead distance forvarious construction materials is presented in table 2.14.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 18
Table: 2.13 Material Consumption.
BUAper
unit in(m2)
TotalReady
MixConcrete
(m3)
TotalCement(bags)
TotalSand(m3)
TotalAggregate(m3)
TotalWater(m3)
TotalBricks(Nos)
x1000
TotalReinfo
rcementsteel(MT)
BUA 35862 14703 33352 13986 1542 8679 4160 825Total 35862 14703 33352 13986 1542 8679 4160 825
Table: 2.14Lead Distance for Construction Materials
S.No Material Source Lead Distance(Km)
1 Sand ROBOSAND and or Krishna orGodavari river bed areaspermitted by Govt.
100-150
2 Aggregate Crushers near to the site 10-303 Cement Company Dealers 100-1504 Reinforcement Steel TATA / SAIL godowns 10-505 Bricks Local brick kiln 10-306 Plumbing Material Local Suppliers 2-77 Electrical Material Local Suppliers 2-78 Sanitary Material Local suppliers 2-78 Paints Local Suppliers 10-259 Ready Mix Concrete Local Batching Plants 10-50
2.2.2.1 Water RequirementThe water required for this project is in the order of 8700 m3 for the entire projectimplementation period. The peak demand for water may be 60 m3/day, however typicaldaily consumption will be in the order of 30 m3/day. The required water will be drawnfrom ground water sources/bulk suppliers/municipal tankers. The water supply andplumbing will be optimized and low water consuming faucets and flush tanks will beused to conserve water.
2.2.2.2 Construction DebrisThe construction debris consists of various types of materials. The construction debriswill be in both hazardous and non-hazardous categories. The hazardous debris consistsempty containers of adhesives, thinners, paints, and petroleum products. These emptycontainers will be sold to authorize recycling agencies. The non hazardous wastescontain recyclable debris like iron and other metal, glass, plastics, cartons of paper,wood etc. These wastes will be sent for reuse/recycle. The waste percentage will bein the order of 2%. Construction debris containing bricks, demolished RCC will be usedfor land filling in the place of sub grade.
2.2.2.3 PaintsAll the paints used in the premises will be ensured to have an albedo of at least 0.4 toincrease the reflectivity and reduce the heat dissipation and heat island effects.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 19
2.2.2.4 Work Force:The labor/work force requirement is approximately 10,000 man days of various skilledand unskilled employees. Sufficient labor force and skilled employees are available asHyderabad is a favorite destination of skilled employees and migrating people from therural areas. The peak labor force requirement will be in the order of 200 people andsome of the labor force will be provided with temporary accommodation within thesite. The labor force will be provided with a temporary toilet facilities connected to aseptic tank followed by soak pit. The labor accommodation will provide accommodationto about 20families. The water requirement for the labor force will be approximately2,000 lt/day.
2.2.2.5 Material preparation and transportMost of the construction material including aggregate will be drawn from outside. Thematerial will be transported by trucks and the approximate number of truck tripsare1000. The material transport within the site will be facilitated by required numberof tippers. All grades of concrete will be procured from RMC suppliers. No stone crushershall be installed at site. Aggregate for Road, pavements and floorings shall be procuredthrough the metal suppliers in the required quantities.
2.2.3 OCCUPATION PHASEA number of facilities will be provided by project authorities for the occupants and thefacilities are shown in table 2.15.
Table 2.15 Amenities ProposedAmenity Nos. or description
Garbage segregation point 1STP 1Green Area 741.0 m2
DG Sets 3 Nos. X 250 KVA
The owners/purchasers will form cooperative to run the amenities like sewagetreatment plant, DG sets. The major requirement of resource is for electricity andwater. The electricity will be drawn from TRANSCO. The power requirement duringoperation phase is presented in table 2.16 and energy savings is presented in table2.20.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 20
Table 2.16 Electricity Consumption Statement
S.No DescriptionNo. ofUnits Load in KW
TotalConnected
Load(KW)
TotalConnected
Load(kVA)
Total MaxDemand
(KVA)1 WING- A & B 204 6 1224.0 1530.0 1530.02 Street Lights 45 0.04 1.8 2.3 1.83 Amenities 52.2 65.2 52.24 STP 1 90 90.0 112.5 112.55 Lifts 10 15 150.0 187.5 187.5
TOTAL 1518.0 1898.2 1884.0Maximum demand in kw at 0.6 diversity factor 911.1Consumption of power for 8 hours per day 7289.2Maximum demand in kw at 0.2 diversity factor 303.7Consumption of power for 16 hours per day 4859.5Total consumption of power per day 12148.6 KWTotal consumption of power per year 44.3 Lakh Units
Table 2.17 Energy Saving by using Solar Water Heater
S.No Description No. ofUnits
Powerallocated inwatts / unit
Total powerrequired in
(KW)1 WING- A & B 80 2500 200
TOTAL 200Maximum demand in kw at 1 diversity factor 200Consumption of power for 2 hours per day 400Maximum demand in kw at 0.4 diversity factor 80Consumption of power for 2 hours per day 160Total consumption of power per day 560.0 KWTotal consumption of power per year 2.04 Lakh Units
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 21
Table 2.18 Energy Saving by using Solar Street Lights
S.No Description No. ofUnits
Powerallocated inwatts / unit
Total powerrequired in
(KW)1 Street lights 20 40 0.8
TOTAL 0.8Maximum demand in kw at 0.6 diversity factor 0.5Consumption of power for 8 hours per day 4Maximum demand in kw at full load 1Consumption of power for 4 hours per day 3Total consumption of power per day 7.0 KWTotal consumption of power per year 0.03 Lakh Unitssaving with Solar Heater and Street Lighting 2.07 Lakh Units
Table 2.19 Electrical Power savings using CFL for lighting
S.No Description Area inm2
Powerallocated inwatts / unit
Total powerrequired in
(KW)1 Residential 23201 10 2322 Common & Utilities 12661 1.5 19
TOTAL 251Maximum demand in kw at 0.9 diversity factor 226Consumption of power for 12 hours per day 2711Total consumption of power per day 2710.8 KWTotal consumption of power per year 9.89 Lakh UnitsSavings in power using CFL 2.97 Lakh Units
Table 2.20 Savings in Electrical Power Consumption – SUMMARY
S.No Description WithCFL
With SolarHeater and
StreetLighting
TotalConsumption
lakh unitsTotal Saving
1 Savings in lakhkwh units 2.97 2.07
44.345.04
2 Savings inpercentage (%) 6.69 4.67 11.4
2.2.3.1 Domestic WaterThe domestic water will be drawn from HMWSSB to augment the supplies. Thewastewater will be treated and reused for gardening. The line providing grey water willbe colored blue and ensured that the tank is at least 1 foot below the level of othertanks and a distance of minimum 2 feet from the other water pipelines.
R. V. Silpa Homes Environmental Impact Statement
Team Labs and Consultants2 - 22
2.2.3.2 Solid WasteThe solid wastes anticipated during occupation stage include garbage, sludge from STP,hazardous waste of used oils, and batteries from generators. The quantity of wastes ispresented in table 2.21.
Table: 2.21 Solid Waste Generated during Occupation PhaseS. No. Type of Waste Quantity Collection/storage Disposal
1 Garbage 652kg/day
Stored at each housein green and blue binsfor non-recyclable andrecyclable wastesrespectively. Collectedand transported tosegregation bin byMaintenance dept.
Municipal solidwaste disposal
2SewageTreatmentPlant Sludge
7.5 kg/dayStored in HDPE bags. Used as manure
and or given tofarmers.
3 Used Batteries 4 nos. year
Sent toAuthorizedrecyclers orreturned toseller
4 Used Lubricant 85 l/yearStored in HDPECarbouy
Sold toauthorizedrecyclers
5 TransformerOil 90 l/year
Stored in HDPE Drum Sold to TRANSCOauthorizedcontractors
R. V. SILPA HOMESSURVEY NO. 198/1(PART) & 206/AA,MADINAGUDA, SERILINGAMPALLY,
RANGA REDDY DISTRICT, TELANGANA
Studies and Documentation by:Team Labs and Consultants(An ISO Certified Organization)B-115 - 117 & 509, Annapurna Block,Aditya Enclave, Ameerpet,Hyderabad- 500 038Phone: 91-040-23748555/23748616Fax : 91-040-23748666e-mail: [email protected]