rab-gang way dmg v tahap ii value

92
Renc Gang way Dmg V Thp I 26,710,000,000.00 RAB Gang way Dmg V Thp I 26,710,115,639.17 (115,639.17) DAFTAR HARGA SATUAN UPAH No Bahan / Material Satuan Harga Satuan (Rp.) 1 Pekerja Hari 46,200.00 2 Tukang Hari 60,500.00 3 Kepala Tukang Hari 66,000.00 4 Mandor Hari 66,000.00 5 Tukang Las Hari 66,000.00 6 Operator Hari 93,500.00 7 Mekanik Hari 77,000.00 8 Juru Ukur Hari 66,000.00 9 Juru Gambar Hari 66,000.00 10 Surveyor Hari 77,000.00 11 Pembantu Surveyor Hari 55,000.00 12 Tukang Selam Hari 110,000.00

Upload: denny-rachman-bastara

Post on 26-Dec-2015

84 views

Category:

Documents


4 download

DESCRIPTION

rab

TRANSCRIPT

Page 1: RAB-Gang Way Dmg v Tahap II Value

Renc Gang way Dmg V Thp 26,710,000,000.00 RAB Gang way Dmg V Thp 26,710,115,639.17

(115,639.17)

DAFTAR HARGA SATUAN UPAH

No Bahan / Material Satuan Harga Satuan(Rp.)

1 Pekerja Hari 46,200.00 42,000.00 2 Tukang Hari 60,500.00 55,000.00 3 Kepala Tukang Hari 66,000.00 60,000.00 4 Mandor Hari 66,000.00 60,000.00 5 Tukang Las Hari 66,000.00 60,000.00 6 Operator Hari 93,500.00 85,000.00 7 Mekanik Hari 77,000.00 70,000.00 8 Juru Ukur Hari 66,000.00 60,000.00 9 Juru Gambar Hari 66,000.00 60,000.00

10 Surveyor Hari 77,000.00 70,000.00 11 Pembantu Surveyor Hari 55,000.00 50,000.00 12 Tukang Selam Hari 110,000.00 100,000.00

Page 2: RAB-Gang Way Dmg v Tahap II Value

DAFTAR HARGA SATUAN BAHAN00

No Bahan / Material Satuan Harga Satuan(Rp.)

1 Semen PC 50 Kg/zak zak 63,390.00 60,000.00 2 Pasir Beton m3 126,780.00 120,000.00 3 Batu Pecah 2-3 m3 142,628.00 135,000.00 4 Pasir Urug m3 116,215.00 110,000.00 5 Tanah Timbunan m3 52,825.00 50,000.00 6 Sirtu m3 123,611.00 117,000.00 7 Base Course m3 153,193.00 145,000.00 8 Batu Kali m3 126,780.00 120,000.00 9 Batu Belah 150 - 200 kg/unit m3 158,475.00 150,000.00

10 Batu Belah 300 - 500 kg/unit m3 211,300.00 200,000.00 11 Besi Beton kg 7,811.00 7,300.00 12 Kawat Beton kg 15,515.00 14,500.00 13 Pipa Baja Ø 406.12 mm t = 12 mm kg 9,660.00 9,660.00 14 Pipa Baja Ø 812.8 mm t = 14 mm kg 9,660.00 9,660.00 15 Pipa Baja Ø 812.8 mm t = 16 mm kg 9,660.00 9,660.00 16 Pipa Baja Ø 1400 mm t = 19 mm kg 9,660.00 9,660.00 17 Baja Profil dan Plat kg 19,661.00 18,375.00 18 Fender V500, L=2000 mm + angker (Hot dip Galvanized) Unit 21,130,000.00 20,000,000.00 19 Electrode kg 31,695.00 30,000.00 20 Oxigen tabung 126,780.00 120,000.00 21 Acetelyn tabung 158,475.00 150,000.00 22 Pasir Kuarsa kg 291.00 275.00 23 Cat Anti Karat Untuk Baja kg 145,523.00 137,741.00 24 Kayu Kelas I m3 3,169,500.00 3,000,000.00 25 Kayu Kelas II m3 2,641,250.00 2,500,000.00 26 Kayu Perancah m3 2,535,600.00 2,400,000.00 27 Multipleks t = 12 mm lbr 168,512.00 159,500.00 28 Geotextile m2 25,356.00 24,000.00 29 Olie Liter 30,000.00 30,000.00 30 Solar Liter 8,200.00 8,200.00 30 Paku kg 15,848.00 15,000.00 31 Air m3 792.00 750.00 32 Beton Readymix K-300 m3 749,100.00 681,000.00 33 Beton Readymix K-250 m3 721,600.00 656,000.00 34 Beton Readymix K-175 m3 666,600.00 606,000.00 35 Beton Readymix K-Bo m3 635,800.00 578,000.00 36 Beton Material Grout m3 998,800.00 908,000.00 37 Karung lbr 5,283.00 5,000.00 38 Air Kerja m3 5,283.00 5,000.00 39 Minyak Bekisting Liter 5,283.00 5,000.00 40 Paving Block Liter 95,085.00 90,000.00 41 Wiremesh D10 m2 74,210.00 70,241.40

Page 3: RAB-Gang Way Dmg v Tahap II Value

DAFTAR HARGA SATUAN PERALATAN00

No Bahan / Material Satuan Harga Satuan Sewa / Bln (Rp.)

1 Crane Kap. 25 Ton Jam 439,900.00 50,000,000.00 Crane Kap. 35 Ton Jam 510,500.00 60,000,000.00 Crane Kap. 40 Ton Jam 581,900.00 70,000,000.00

2 Crane Kap. 90 Ton Jam 763,900.00 ###3 Crane Kap. 100 Ton Jam 1,057,100.00 ###4 Ponton Service Jam 1,288,900.00 ###5 Hammer Diesel 4.5 Ton + Leader Jam 556,400.00 80,000,000.00 6 Hammer Diesel 7.5 Ton + Leader Jam 661,400.00 ###7 Dump Truck Jam 241,400.00 20,000,000.00 8 Excavator Jam 407,900.00 40,000,000.00

Motor Grader Jam 423,900.00 45,000,000.00 9 Bulldozer Jam 480,900.00 50,000,000.00

10 Mesin Gilas Jam 309,900.00 35,000,000.00 11 Water Tank Truck Jam 220,900.00 20,000,000.00 12 Genset Jam 90,900.00 10,000,000.00 13 Mesin Las Jam 62,600.00 9,000,000.00 14 Concrete Mixer Jam 41,400.00 3,000,000.00 15 Air Compressor Jam 103,800.00 10,000,000.00 16 Concrete Vibrator Jam 28,500.00 2,500,000.00 17 Concrete Pump Jam 374,000.00 40,000,000.00 18 Bar Bender/Bar Cutter Jam 33,600.00 2,500,000.00

Page 4: RAB-Gang Way Dmg v Tahap II Value

Persiapan 1.0500 1.05 Mobilisasi 1.0500 1.05 Upah 1.1000 1.11 Bahan Umum 1.0565 1.10 Tiang Pancang 1.0000 1.12 Besi beton 1.0700 1.11 Beton 1.1000 1.13 Peralatan 1.0500 1.06 Sub Pancang (yg tdk pakai anali 1.0500 Sub Pek Sipil 1.1250 Sub Pek Gedung 1.1250 Indeks INASA (diluar analisa) 1.0300

Page 5: RAB-Gang Way Dmg v Tahap II Value

NFA FAJayamix 747,000.00 681,000.00 Estimasi 717,000.00 656,000.00 Estimasi 667,000.00 606,000.00 Jayamix 614,000.00 578,000.00 6.75

187.5

Page 6: RAB-Gang Way Dmg v Tahap II Value

Sewa/Jam HP BBM/Jam BBM/Jam Operator Total Keterangan(liter) (Rp.)

262,500.00 160.00 20.00 164,000.00 13,357.14 439,857.14 315,000.00 180.00 22.50 184,500.00 11,000.00 510,500.00 367,500.00 200.00 25.00 205,000.00 9,428.57 581,928.57 525,000.00 220.00 27.50 225,500.00 13,357.14 763,857.14 787,500.00 250.00 31.25 256,250.00 13,357.14 ###

### 220.00 27.50 225,500.00 13,357.14 ### 420,000.00 120.00 15.00 123,000.00 13,357.14 556,357.14 525,000.00 120.00 15.00 123,000.00 13,357.14 661,357.14 105,000.00 120.00 15.00 123,000.00 13,357.14 241,357.14 210,000.00 180.00 22.50 184,500.00 13,357.14 407,857.14 236,250.00 170.00 21.25 174,250.00 13,357.14 423,857.14 262,500.00 200.00 25.00 205,000.00 13,357.14 480,857.14 183,750.00 110.00 13.75 112,750.00 13,357.14 309,857.14 105,000.00 100.00 12.50 102,500.00 13,357.14 220,857.14 52,500.00 37.50 4.69 38,437.50 - 90,937.50 47,250.00 15.00 1.88 15,375.00 - 62,625.00 15,750.00 25.00 3.13 25,625.00 - 41,375.00 52,500.00 50.00 6.25 51,250.00 - 103,750.00 13,125.00 15.00 1.88 15,375.00 - 28,500.00 210,000.00 160.00 20.00 164,000.00 - 374,000.00 13,125.00 20.00 2.50 20,500.00 - 33,625.00

Page 7: RAB-Gang Way Dmg v Tahap II Value

Solar Umum 4500Solar Industri 8200Bensin 4500

Page 8: RAB-Gang Way Dmg v Tahap II Value

DAFTAR HARGA SATUAN UPAHPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

No Bahan / Material Satuan Harga Satuan(Rp.)

1 Pekerja Hari 46,200.00 2 Tukang Hari 60,500.00 3 Kepala Tukang Hari 66,000.00 4 Mandor Hari 66,000.00 5 Tukang Las Hari 66,000.00 6 Operator Hari 93,500.00 7 Mekanik Hari 77,000.00 8 Juru Ukur Hari 66,000.00 9 Juru Gambar Hari 66,000.00 10 Surveyor Hari 77,000.00 11 Pembantu Surveyor Hari 55,000.00 12 Tukang Selam Hari 110,000.00

Jakarta, 9 Maret 2012PT. WASKITA KARYA (Persero)

Divisi IV

Ir. Ridwan Darma, MMKepala

Page 9: RAB-Gang Way Dmg v Tahap II Value

DAFTAR HARGA SATUAN BAHANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

No Bahan / Material Satuan Harga Satuan(Rp.)

1 Semen PC 50 Kg/zak zak 63,390.00 2 Pasir Beton m3 126,780.00 3 Batu Pecah 2-3 m3 142,628.00 4 Pasir Urug m3 116,215.00 5 Tanah Timbunan m3 52,825.00 6 Sirtu m3 123,611.00 7 Base Course m3 153,193.00 8 Batu Kali m3 126,780.00 9 Batu Belah 150 - 200 kg/unit m3 158,475.00 10 Batu Belah 300 - 500 kg/unit m3 211,300.00 11 Besi Beton kg 7,811.00 12 Kawat Beton kg 15,515.00 13 Baja Profil dan Plat kg 19,661.00 14 Electrode kg 31,695.00 15 Oxigen tabung 126,780.00 16 Acetelyn tabung 158,475.00 17 Kayu Perancah m3 2,535,600.00 18 Multipleks t = 12 mm lbr 168,512.00 19 Olie Liter 30,000.00 20 Solar Liter 8,200.00 21 Paku kg 15,848.00 22 Air m3 792.00 23 Beton Readymix K-300 m3 749,100.00 24 Beton Readymix K-Bo m3 635,800.00 25 Minyak Bekisting Liter 5,283.00 26 Paving Block Liter 95,085.00 27 Wiremesh D10 m2 74,210.00

Jakarta, 9 Maret 2012PT. WASKITA KARYA (Persero)

Ir. Ridwan Darma, MMKepala

Page 10: RAB-Gang Way Dmg v Tahap II Value

DAFTAR HARGA SATUAN PERALATANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

No Bahan / Material Satuan Harga Satuan(Rp.)

1 Crane Kap. 35 Ton Jam 510,500.00 2 Crane Kap. 40 Ton Jam 581,900.00 3 Ponton Service Jam 1,288,900.00 4 Hammer Diesel 4.5 Ton + Leader Jam 556,400.00 5 Dump Truck Jam 241,400.00 6 Excavator Jam 407,900.00 7 Motor Grader Jam 423,900.00 8 Bulldozer Jam 480,900.00 9 Mesin Gilas Jam 309,900.00 10 Water Tank Truck Jam 220,900.00 11 Genset Jam 90,900.00 12 Mesin Las Jam 62,600.00 13 Concrete Mixer Jam 41,400.00 14 Air Compressor Jam 103,800.00 15 Concrete Vibrator Jam 28,500.00 16 Concrete Pump Jam 374,000.00 17 Bar Bender/Bar Cutter Jam 33,600.00

Jakarta, 9 Maret 2012PT. WASKITA KARYA (Persero)

Ir. Ridwan Darma, MMKepala

Page 11: RAB-Gang Way Dmg v Tahap II Value

Beton bertulang K-300 Pile Cap Tipe - 1 (7 m x 8 m x 1.6 m)

No.

Luar Atas 1

Luar Bawah 2

Luar Atas 1

Luar Bawah 2

Samping 1

Tengah 1

Vertikal di tengah pile cap) 1

Beton bertulang K-300 Pile Cap Tipe - 2 (7 m x 8 m x 1.6 m) ada takika

No.

Luar Atas 1

Luar Bawah 2

Luar Atas 1

Luar Bawah 2

Samping 1

Page 12: RAB-Gang Way Dmg v Tahap II Value

Tengah 1

Vertikal di tengah pile cap) 1

Beton bertulang K-300 Pile Cap Tipe - 3 (3.5 m x 3.5 m x 1.6 m)

No.

Luar Atas 1

Luar Bawah 2

Luar Atas 1

Luar Bawah 2

Samping 1

Tengah 1

Vertikal di tengah pile cap) 1

Page 13: RAB-Gang Way Dmg v Tahap II Value

Beton bertulang K-300 Pile Cap Tipe - 4 (4 m x 8 m x 1.6 m)

No.

Luar Atas (x) 1

Luar Bawah (x) 2

Luar Atas (y) 1

Luar Bawah (y) 2

Samping 1

Tengah 1

Vertikal di tengah pile cap) 1

Beton bertulang K-300 Pile Cap Tipe - 5 (3.5 m x 8 m x 1.6 m)

No.

Luar Atas 1

Luar Bawah 2

Luar Atas 1

Luar Bawah 2

Samping 1

Tengah 1

Vertikal di tengah pile cap) 1

Page 14: RAB-Gang Way Dmg v Tahap II Value

Beton bertulang K-300 Pile Cap Tipe - 1 (7 m x 8 m x 1.6 m) 1.00

Tulangan BJ Panjang Jumlah Total Total

Panjang Berat

D22-150 2.984 11.20 54.00 604.80 1,804.72

D22-150 2.984 10.00 54.00 540.00 1,611.36

D22-150 2.984 10.20 48.00 489.60 1,460.97

D22-150 2.984 9.00 48.00 432.00 1,289.09

D22-150 2.984 30.00 12.00 360.00 1,074.24

D22-150 2.984 9.60 48.00 460.80 1,375.03

D22-150 2.984 2.40 96.00 230.40 687.51

Total Pembesian 9,302.92

Jumlah Pile = 1 9,302.92

Volume Beton 89.60

Rasio Besi/m3 103.83

Dibulatkan 1.05 Rasio Besi/m3 109.02

Bekisting 103.75

Volume Beton 89.60

Rasio Bekisting/m3 1.16

Beton bertulang K-300 Pile Cap Tipe - 2 (7 m x 8 m x 1.6 m) ada takika 1.00

Tulangan BJ Panjang Jumlah Total Total

Panjang Berat

D22-150 2.984 11.20 54.00 604.80 1,804.72

D22-150 2.984 10.00 54.00 540.00 1,611.36

D22-150 2.984 10.20 48.00 489.60 1,460.97

D22-150 2.984 9.00 48.00 432.00 1,289.09

D22-150 2.984 30.00 12.00 360.00 1,074.24

Page 15: RAB-Gang Way Dmg v Tahap II Value

D22-150 2.984 9.60 48.00 460.80 1,375.03

D22-150 2.984 2.40 96.00 230.40 687.51

Total Pembesian 9,302.92

Jumlah Pile = 1 9,302.92

Volume Beton 89.60

Rasio Besi/m3 103.83

Dibulatkan 1.1 Rasio Besi/m3 114.21

Bekisting 103.75

Volume Beton 89.60

Rasio Bekisting/m3 1.16

Beton bertulang K-300 Pile Cap Tipe - 3 (3.5 m x 3.5 m x 1.6 m) 1.00

Tulangan BJ Panjang Jumlah Total Total

Panjang Berat

D22-150 2.984 6.70 24.00 160.80 479.83

D22-150 2.984 5.50 24.00 132.00 393.89

D22-150 2.984 6.70 24.00 160.80 479.83

D22-150 2.984 5.50 24.00 132.00 393.89

D22-150 2.984 14.00 12.00 168.00 501.31

D22-150 2.984 5.10 24.00 122.40 365.24

D22-150 2.984 2.40 48.00 115.20 343.76

Total Pembesian 2,957.74

Jumlah Pile = 1 2,957.74

Volume Beton 19.60

Rasio Besi/m3 150.91

Dibulatkan 1.05 Rasio Besi/m3 158.45

Bekisting 103.75

Volume Beton 19.60

Rasio Bekisting/m3 5.29

Page 16: RAB-Gang Way Dmg v Tahap II Value

Beton bertulang K-300 Pile Cap Tipe - 4 (4 m x 8 m x 1.6 m) 1.00

Tulangan BJ Panjang Jumlah Total Total

Panjang Berat

D22-150 2.984 11.20 28.00 313.60 935.78

D22-150 2.984 10.00 28.00 280.00 835.52

D22-150 2.984 7.20 54.00 388.80 1,160.18

D22-150 2.984 6.00 54.00 324.00 966.82

D22-150 2.984 26.40 12.00 316.80 945.33

D22-150 2.984 9.60 28.00 268.80 802.10

D22-150 2.984 2.40 84.00 201.60 601.57

Total Pembesian 6,247.30

Jumlah Pile = 1 6,247.30

Volume Beton 51.20

Rasio Besi/m3 122.02

Dibulatkan 1.05 Rasio Besi/m3 128.12

Bekisting 103.75

Volume Beton 51.20

Rasio Bekisting/m3 2.03

Beton bertulang K-300 Pile Cap Tipe - 5 (3.5 m x 8 m x 1.6 m) 1.00

Tulangan BJ Panjang Jumlah Total Total

Panjang Berat

D22-150 2.984 11.20 28.00 313.60 935.78

D22-150 2.984 10.00 28.00 280.00 835.52

D22-150 2.984 7.20 54.00 388.80 1,160.18

D22-150 2.984 6.00 54.00 324.00 966.82

D22-150 2.984 26.40 12.00 316.80 945.33

D22-150 2.984 9.60 28.00 268.80 802.10

D22-150 2.984 2.40 84.00 201.60 601.57

Page 17: RAB-Gang Way Dmg v Tahap II Value

Total Pembesian 6,247.30

Jumlah Pile = 1 6,247.30

Volume Beton 51.20

Rasio Besi/m3 122.02

Dibulatkan 1.05 Rasio Besi/m3 128.12

Bekisting 103.75

Volume Beton 51.20

Rasio Bekisting/m3 2.03

Page 18: RAB-Gang Way Dmg v Tahap II Value

kg

kg

m3

kg/m3

kg/m3

m2

m3

m2/m3

Page 19: RAB-Gang Way Dmg v Tahap II Value

kg

kg

m3

kg/m3

kg/m3

m2

m3

m2/m3

kg

kg

m3

kg/m3

kg/m3

m2

m3

m2/m3

Page 20: RAB-Gang Way Dmg v Tahap II Value

kg

kg

m3

kg/m3

kg/m3

m2

m3

m2/m3

Page 21: RAB-Gang Way Dmg v Tahap II Value

kg

kg

m3

kg/m3

kg/m3

m2

m3

m2/m3

Page 22: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Mobilisasi dan DemobilisasiHarga Satuan/Lump Sum = Rp. 519,750,000.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

1 Crane Kap. 40 Ton unit 1.00 52,500,000.00 52,500,000.00 2 Crane Service 35 Ton unit 1.00 52,500,000.00 52,500,000.00 3 Diesel Hammer 4.5 Ton + Leader unit 1.00 78,750,000.00 78,750,000.00 4 Ponton 120 ft unit 2.00 157,500,000.00 315,000,000.00 5 Genset unit 1.00 2,100,000.00 2,100,000.00 6 Mesin las unit 2.00 1,050,000.00 2,100,000.00 7 Excavator unit 1.00 5,250,000.00 5,250,000.00 8 Tandem Roller unit 1.00 4,200,000.00 4,200,000.00 9 Air Compressor unit 1.00 1,050,000.00 1,050,000.00 10 Concrete Vibrator unit 3.00 525,000.00 1,575,000.00 11 Bar bender unit 1.00 525,000.00 525,000.00 12 Bar cutter unit 1.00 525,000.00 525,000.00 13 Concrete Pump unit 1.00 2,625,000.00 2,625,000.00 14 Theodolite unit 1.00 525,000.00 525,000.00 15 Waterpass unit 1.00 525,000.00 525,000.00

TOTAL 519,750,000.00

Jenis Pekerjaan = Pengukuran & PositioningHarga Satuan/Bulan = Rp. 47,107,500.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

I PERALATAN 1 Theodolite Bln 8.00 1,050,000.00 8,400,000.00 2 Waterpass Bln 8.00 787,500.00 6,300,000.00 3 Alat bantu ls 1.00 157,500.00 157,500.00

Sub total 14,857,500.00

II TENAGA KERJA 1 Surveyor org 150.00 77,000.00 11,550,000.00 2 Pembantu surveyor org 300.00 55,000.00 16,500,000.00

Sub total 28,050,000.00

III BAHAN BANGUNAN 1 Kayu dan bambu ls 8.00 367,500.00 2,940,000.00 2 Paku, Cat, Meni ls 8.00 157,500.00 1,260,000.00

Sub total 4,200,000.00

TOTAL 47,107,500.00

Page 23: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Instalasi listrik dan air kerja Harga Satuan/Lump Sum = Rp. 8,400,000.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

1 Instalasi Listrik Ls 1.00 5,250,000.00 5,250,000.00 2 Instalasi Air Kerja Ls 1.00 3,150,000.00 3,150,000.00

Jumlah 8,400,000.00

Jenis Pekerjaan = Biaya pemakaian listrik dan air kerja Harga Satuan/Bulan = Rp. 4,725,000.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

1 Rekening listrik dan air kerja bln 1.00 2,625,000.00 2,625,000.00 2 Keselamatan Kerja bln 1.00 2,100,000.00 2,100,000.00

Jumlah 4,725,000.00

Jenis Pekerjaan = Keselamatan Kerja Harga Satuan/Bulan = Rp. 3,609,375.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

1 Peralatan Keselamatan Kerja bln 1.00 984,375.00 984,375.00 2 Petugas Keselamatan Kerja bln 1.00 2,625,000.00 2,625,000.00

Jumlah 3,609,375.00

Jenis Pekerjaan = Direksi KeetHarga Satuan/Ls = Rp. 787,500.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

1 Direksi Keet m2 1.00 787,500.00 787,500.00

Jumlah 787,500.00

Page 24: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Administrasi, As built drawing dan Dokumentasi Harga Satuan/Lump Sum = Rp. 17,955,000.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

1 Administrasi Ls 1.00 8,400,000.00 8,400,000.00 2 Asbuilt Drawing Ls 1.00 7,875,000.00 7,875,000.00 3 Dokumentasi Bln 8.00 210,000.00 1,680,000.00

Jumlah 17,955,000.00

Jenis Pekerjaan = Pembesian Harga Satuan/Kg = Rp. 9,390.79

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Besi Beton kg 1.03 7,811.00 8,045.33 2 Kawat Beton kg 0.02 15,515.00 310.30

Jumlah Bahan 8,355.63

B UPAH 1 Pekerja Hari 0.0143 46,200.00 660.66 2 Mandor Hari 0.0029 66,000.00 191.40

Jumlah Upah 852.06

C ALAT 1 Bar Bender/Bar Cutter Jam 0.0020 33,600.00 67.20 2 Genset Jam 0.0010 90,900.00 90.90 3 Alat bantu Ls 1.00 25.00 25.00

Jumlah Alat 183.10

Jumlah 9,390.79

Jenis Pekerjaan = Pengecoran Beton K-300 Harga Satuan/m3 = Rp. 870,981.92

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton Readymix K-300 m3 1.03 749,100.00 771,573.00

Jumlah Bahan 771,573.00

B UPAH 1 Pekerja Hari 0.9091 46,200.00 42,000.42 2 Mandor Hari 0.2273 66,000.00 15,001.80

Jumlah Upah 57,002.22

C ALAT 1 Concrete Vibrator Jam 0.1250 28,500.00 3,562.50 2 Air Compressor Jam 0.0500 103,800.00 5,190.00 3 Concrete Pump Jam 0.0833 374,000.00 31,154.20 4 Alat bantu Ls 1.00 2,500.00 2,500.00

Jumlah Alat 42,406.70

Jumlah 870,981.92

Page 25: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Bekisting Pile Cap Harga Satuan/m2 = Rp. 350,999.57

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Kayu Perancah m3 0.0560 2,535,600.00 141,990.17 2 Multipleks t = 12 mm lbr 0.1910 168,512.00 32,181.11 3 Paku kg 0.3500 15,848.00 5,546.80 4 Minyak Bekisting ltr 0.2000 5,283.00 1,056.60 5 Klem Baja, Baut dll Ls 1.0000 25,000.00 25,000.00 6 Baja Profil dan Plat kg 2.58 19,661.00 50,729.54

Jumlah Bahan 256,504.22

B UPAH 1 Pekerja Hari 0.8000 46,200.00 36,960.00 2 Tukang Hari 0.2667 60,500.00 16,135.35 3 Kepala Tukang Hari 0.2667 66,000.00 17,602.20 4 Mandor Hari 0.1333 66,000.00 8,797.80

Jumlah Upah 79,495.35

C ALAT 1 Perahu Kerja Ls 1.0000 10,000.00 10,000.00 2 Alat Bantu Ls 1.0000 5,000.00 5,000.00

Jumlah Alat 15,000.00

Jumlah 350,999.57

Jenis Pekerjaan = Bekisting Plat Lantai Harga Satuan/m2 = Rp. 191,378.46

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Kayu Perancah m3 0.0250 2,535,600.00 63,390.00 2 Multipleks t = 12 mm lbr 0.1910 168,512.00 32,181.11 3 Paku kg 0.6000 15,848.00 9,508.80 4 Minyak Bekisting ltr 0.4000 5,283.00 2,113.20 5 Klem Baja, Baut dll Ls 1.0000 7,500.00 7,500.00

Jumlah Bahan 114,693.11

B UPAH 1 Pekerja Hari 0.5000 46,200.00 23,100.00 2 Tukang Hari 0.1667 60,500.00 10,085.35 3 Kepala Tukang Hari 0.1667 66,000.00 11,002.20 4 Mandor Hari 0.0833 66,000.00 5,497.80

Jumlah Upah 49,685.35

C ALAT 1 Alat Bantu Ls 1.0000 2,000.00 2,000.00 2 Scaffolding m2 1.0000 25,000.00 25,000.00

Jumlah Alat 27,000.00

Jumlah 191,378.46

Page 26: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Pemancangan tiang pancang Ø 406.4 mm Harga Satuan/ton = Rp. 211,623.21 Volume =

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 - 2 - 3 -

Jumlah Bahan -

B UPAH 1 Pekerja Hari 0.2000 46,200.00 9,240.00 2 Pembantu surveyor Hari 0.2000 55,000.00 11,000.00 3 Mandor Hari 0.1000 66,000.00 6,600.00 4 Operator Hari 0.2000 93,500.00 18,700.00

Jumlah Upah 45,540.00

C ALAT 1 Crane Kap. 25 Ton Jam 0.1667 439,900.00 73,331.33 2 Hammer Diesel 4.5 Ton + Leader Jam 0.1667 556,400.00 92,751.88

Jumlah Alat 166,083.21

Jumlah 211,623.21

Jenis Pekerjaan = Pengukuran Harga Satuan/ton = Rp. 542,365.00 Volume =

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 - 2 - 3 -

Jumlah Bahan -

B UPAH 1 Pekerja Hari 0.2500 46,200.00 11,550.00 2 Pembantu surveyor Hari 0.2500 55,000.00 13,750.00 3 Mandor Hari 0.1250 66,000.00 8,250.00 4 Operator Hari 0.2500 93,500.00 23,375.00

Jumlah Upah 56,925.00

C ALAT 1 Crane Kap. 40 Ton Jam 0.2000 581,900.00 116,380.00 2 Hammer Diesel 4.5 Ton + Leader Jam 0.2000 556,400.00 111,280.00 3 Ponton Service Jam 0.2000 1,288,900.00 257,780.00

Jumlah Alat 485,440.00

Jumlah 542,365.00

Page 27: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Pemotongan tiang dia 40 cm di Darat Harga Satuan/buah = Rp. 212,284.33

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Oxigen tabung 0.2000 126,780.00 25,356.00 2 Acetelyn tabung 0.2000 158,475.00 31,695.00

Jumlah Bahan 57,051.00

B UPAH 1 Pekerja Hari 1.0000 46,200.00 46,200.00 2 Mandor Hari 0.2500 66,000.00 16,500.00 3 Tukang Hari 0.2500 60,500.00 15,125.00

Jumlah Upah 77,825.00

C ALAT 1 Mesin Las Jam 0.2500 62,600.00 15,650.00 2 Genset Jam 0.2500 90,900.00 22,725.00 3 Crane Kap. 35 Ton Jam 0.0667 510,500.00 34,033.33 4 Alat Bantu Ls 1.0000 5,000.00 5,000.00

Jumlah Alat 77,408.33

Jumlah 212,284.33

Jenis Pekerjaan = Pemotongan tiang pancang, setting dan penyambungan dia 812.3 mm

Harga Satuan/buah = Rp. 473,164.94

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Oxigen tabung 0.2000 126,780.00 25,356.00 2 Acetelyn tabung 0.2000 158,475.00 31,695.00

Jumlah Bahan 57,051.00

B UPAH 1 Pekerja Hari 1.0000 46,200.00 46,200.00 2 Mandor Hari 0.5000 66,000.00 33,000.00 3 Tukang Hari 0.5000 60,500.00 30,250.00

Jumlah Upah 109,450.00

C ALAT 1 Mesin Las Jam 0.2500 62,600.00 15,650.00 2 Genset Jam 0.2500 90,900.00 22,725.00 3 Crane Kap. 40 Ton Jam 0.0833 581,900.00 48,472.27 4 Ponton Service Jam 0.1667 1,288,900.00 214,816.67 5 Alat Bantu Ls 1.0000 5,000.00 5,000.00

Jumlah Alat 306,663.94

Jumlah 473,164.94

Page 28: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan =

=

Harga Satuan/kg = Rp. 34,596.97

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Baja Profil dan Plat Kg 1.0000 19,661.00 19,661.00 2 Pengecatan Kg 1.0000 3,380.80 3,380.80

Jumlah Bahan 23,041.80

B UPAH 1 Pekerja Hari 0.0640 46,200.00 2,956.80 2 Mandor Hari 0.0080 66,000.00 528.00 3 Tukang Hari 0.0320 60,500.00 1,936.00

Jumlah Upah 5,420.80

C ALAT 1 Mesin Las Jam 0.0150 62,600.00 939.00 2 Genset Jam 0.0100 90,900.00 909.00 3 Crane Kap. 35 Ton Jam 0.0029 510,500.00 1,458.57 4 Ponton Service Jam 0.0020 1,288,900.00 2,577.80 5 Alat Bantu Ls 1.0000 250.00 250.00

Jumlah Alat 6,134.37

Jumlah 34,596.97

Jenis Pekerjaan = Pengecatan dan pemasangan konstruksi gangway Harga Satuan/kg = Rp. 8,755.79

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN

1 Pengecatan Kg 1.0000 3,380.80 3,380.80

Jumlah Bahan 3,380.80

B UPAH 1 Pekerja Hari 0.0267 46,200.00 1,233.54 2 Mandor Hari 0.0033 66,000.00 217.80 3 Tukang Hari 0.0133 60,500.00 804.65

Jumlah Upah 2,255.99

C ALAT 1 Mesin Las Jam 0.0150 62,600.00 939.00 2 Genset Jam 0.0100 90,900.00 909.00 3 Crane Kap. 35 Ton Jam 0.0020 510,500.00 1,021.00 4 Alat Bantu Ls 1.0000 250.00 250.00

Jumlah Alat 3,119.00

Jumlah 8,755.79

Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi gangway Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi apron ESR (±100 m)

Page 29: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan =

Harga Satuan/kg = Rp. 35,944.05

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Baja Profil dan Plat Kg 1.0000 19,661.00 19,661.00 2 Pengecatan Kg 1.0000 3,500.00 3,500.00

Jumlah Bahan 23,161.00

B UPAH 1 Pekerja Hari 0.0640 46,200.00 2,956.80 2 Mandor Hari 0.0080 66,000.00 528.00 3 Tukang Hari 0.0320 60,500.00 1,936.00

Jumlah Upah 5,420.80

C ALAT 1 Mesin Las Jam 0.0150 62,600.00 939.00 2 Genset Jam 0.0100 90,900.00 909.00 3 Crane Kap. 35 Ton Jam 0.0040 510,500.00 2,042.00 4 Ponton Service Jam 0.0025 1,288,900.00 3,222.25 5 Alat Bantu Ls 1.0000 250.00 250.00

Jumlah Alat 7,362.25

Jumlah 35,944.05

Pengadaan, pabrikasi pengecatan dan pemasangan konstruksi kolom penyangga

Page 30: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Beton bertulang (K-300, U32) pondasi gangway 3000x1600x1600

Harga Satuan/m3 = Rp. 2,540,514.15 Volume = 26.87 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 2.0000 256,504.22 513,008.44 3 Pembesian (Bahan) kg 103.0300 8,355.63 860,880.56

Jumlah Bahan 2,145,462.00

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 2.0000 79,495.35 158,990.70 3 Pembesian (Upah) kg 103.0300 852.06 87,787.74

Jumlah Upah 303,780.66

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 2.0000 15,000.00 30,000.00 3 Pembesian (Alat) kg 103.0300 183.10 18,864.79

Jumlah Alat 91,271.49

Jumlah 2,540,514.15

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 4,245,262.59 Volume = 3.01

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00

2 Pembesian (Bahan) kg 285.3600 8,355.63 2,384,362.58 3 Plat Beton kg 35.3250 19,661.00 694,524.83

Jumlah Bahan 3,850,460.41

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22

2 Pembesian (Upah) kg 285.3600 852.06 243,143.84

Jumlah Upah 300,146.06

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70

2 Pembesian (Alat) kg 285.3600 183.10 52,249.42

Jumlah Alat 94,656.12

Jumlah 4,245,262.59

Beton bertulang (K-300, U32) pengisi tiang pancang dia.400mm L=1000 mm

Page 31: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Beton lantai kerja (K-100) t = 100 mm

Harga Satuan/m3 = Rp. 694,243.04

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton Readymix K-Bo m3 1.03 635,800.00 654,874.00

Jumlah Bahan 654,874.00

B UPAH 1 Pekerja Hari 0.5000 46,200.00 23,100.00 2 Mandor Hari 0.1250 66,000.00 8,250.00

Jumlah Upah 31,350.00

C ALAT 1 Concrete Vibrator Jam 0.1250 28,500.00 3,562.50 2 Air Compressor Jam 0.0333 103,800.00 3,456.54 3 Alat bantu Ls 1.00 1,000.00 1,000.00

Jumlah Alat 8,019.04

Jumlah 694,243.04

Jenis Pekerjaan = Lapisan batu kali dipadatkan t = 600 mm

Harga Satuan/m3 = Rp. 219,836.00

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Batu Kali m3 1.20 126,780.00 152,136.00

Jumlah Bahan 152,136.00

B UPAH 1 Pekerja Hari 1.0000 46,200.00 46,200.00 2 Mandor Hari 0.2500 66,000.00 16,500.00

Jumlah Upah 62,700.00

C ALAT 1 Alat bantu Ls 1.00 5,000.00 5,000.00

Jumlah Alat 5,000.00

Jumlah 219,836.00

Page 32: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 2,596,751.61 Volume = 89.60 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 2.0000 256,504.22 513,008.44 3 Pembesian (Bahan) kg 109.0186 8,355.63 910,918.88

Jumlah Bahan 2,195,500.32

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 2.0000 79,495.35 158,990.70 3 Pembesian (Upah) kg 109.0186 852.06 92,890.37

Jumlah Upah 308,883.29

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 2.0000 15,000.00 30,000.00 3 Pembesian (Alat) kg 109.0186 183.10 19,961.30

Jumlah Alat 92,368.00

Jumlah 2,596,751.61

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 2,645,502.59 Volume = 97.28 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 2.0000 256,504.22 513,008.44 3 Pembesian (Bahan) kg 114.2099 8,355.63 954,295.97

Jumlah Bahan 2,238,877.41

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 2.0000 79,495.35 158,990.70 3 Pembesian (Upah) kg 114.2099 852.06 97,313.72

Jumlah Upah 313,306.64

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 2.0000 15,000.00 30,000.00 3 Pembesian (Alat) kg 114.2099 183.10 20,911.84

Jumlah Alat 93,318.54

Jumlah 2,645,502.59

Beton bertulang (K-300, U32) pondasi gangway Type-1, 8000x7000x1600 (1 unit)

Beton bertulang (K-300, U32) pondasi gangway Type-2, 8000x7000x1600 (1 unit)

Page 33: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 3,060,955.50 Volume = 78.40 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 2.0000 256,504.22 513,008.44 3 Pembesian (Bahan) kg 158.4504 8,355.63 1,323,952.92

Jumlah Bahan 2,608,534.36

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 2.0000 79,495.35 158,990.70 3 Pembesian (Upah) kg 158.4504 852.06 135,009.25

Jumlah Upah 351,002.17

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 2.0000 15,000.00 30,000.00 3 Pembesian (Alat) kg 158.4504 183.10 29,012.27

Jumlah Alat 101,418.97

Jumlah 3,060,955.50

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 2,776,115.04 Volume = 102.40 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 2.0000 256,504.22 513,008.44 3 Pembesian (Bahan) kg 128.1185 8,355.63 1,070,510.83

Jumlah Bahan 2,355,092.27

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 2.0000 79,495.35 158,990.70 3 Pembesian (Upah) kg 128.1185 852.06 109,164.65

Jumlah Upah 325,157.57

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 2.0000 15,000.00 30,000.00 3 Pembesian (Alat) kg 128.1185 183.10 23,458.50

Jumlah Alat 95,865.20

Jumlah 2,776,115.04

Beton bertulang (K-300, U32) pondasi gangway Type-3, 3500x35000x1600 (3 unit)

Beton bertulang (K-300, U32) pondasi gangway Type-4, 8000x4000x1600 (2 unit)

Page 34: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 2,776,115.04 Volume = 224.00 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 2.0000 256,504.22 513,008.44 3 Pembesian (Bahan) kg 128.1185 8,355.63 1,070,510.83

Jumlah Bahan 2,355,092.27

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 2.0000 79,495.35 158,990.70 3 Pembesian (Upah) kg 128.1185 852.06 109,164.65

Jumlah Upah 325,157.57

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 2.0000 15,000.00 30,000.00 3 Pembesian (Alat) kg 128.1185 183.10 23,458.50

Jumlah Alat 95,865.20

Jumlah 2,776,115.04

Jenis Pekerjaan = Pengadaan material dan pemadatan lapisan sirtu Harga Satuan/m3 = Rp. 173,691.08

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Sirtu m3 1.20 123,611.00 148,333.20

Jumlah Bahan 148,333.20

B UPAH 1 Pekerja Hari 0.1000 46,200.00 4,620.00 2 Mandor Hari 0.0250 66,000.00 1,650.00

Jumlah Upah 6,270.00

C ALAT 1 Motor Grader Jam 0.0167 423,900.00 7,079.13 2 Mesin Gilas Jam 0.0250 309,900.00 7,747.50 3 Water Tank Truck Jam 0.0125 220,900.00 2,761.25 4 Alat bantu Ls 1.00 1,500.00 1,500.00

Jumlah Alat 19,087.88

Jumlah 173,691.08

Beton bertulang (K-300, U32) pondasi gangway Type-5, 8000x3500x1600 (5 unit)

Page 35: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Pengadaan material dan pemadatan lapisan/tanah urug Harga Satuan/m3 = Rp. 83,547.91

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Tanah Timbunan m3 1.20 52,825.00 63,390.00

Jumlah Bahan 63,390.00

B UPAH 1 Pekerja Hari 0.0800 46,200.00 3,696.00 2 Mandor Hari 0.0200 66,000.00 1,320.00

Jumlah Upah 5,016.00

C ALAT 1 Motor Grader Jam 0.0167 423,900.00 7,079.13 2 Mesin Gilas Jam 0.0125 309,900.00 3,873.75 3 Water Tank Truck Jam 0.0167 220,900.00 3,689.03 4 Alat bantu Ls 1.00 500.00 500.00

Jumlah Alat 15,141.91

Jumlah 83,547.91

Jenis Pekerjaan = Pengadaan material dan pemadatan lapisan basecourse (CBR > 80%)

Harga Satuan/m3 = Rp. 209,189.48

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Base Course m3 1.20 153,193.00 183,831.60

Jumlah Bahan 183,831.60

B UPAH 1 Pekerja Hari 0.1000 46,200.00 4,620.00 2 Mandor Hari 0.0250 66,000.00 1,650.00

Jumlah Upah 6,270.00

C ALAT 1 Motor Grader Jam 0.0167 423,900.00 7,079.13 2 Mesin Gilas Jam 0.0250 309,900.00 7,747.50 3 Water Tank Truck Jam 0.0125 220,900.00 2,761.25 4 Alat bantu Ls 1.00 1,500.00 1,500.00

Jumlah Alat 19,087.88

Jumlah 209,189.48

Page 36: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Pengadaan lapisan pasir t = 50 mm di bawah paving blok Harga Satuan/m3 = Rp. 158,410.53

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Pasir Urug m3 1.20 116,215.00 139,458.00

Jumlah Bahan 139,458.00

B UPAH 1 Pekerja Hari 0.0800 46,200.00 3,696.00 2 Mandor Hari 0.0200 66,000.00 1,320.00

Jumlah Upah 5,016.00

C ALAT

1 Mesin Gilas Jam 0.0250 309,900.00 7,747.50 2 Water Tank Truck Jam 0.0167 220,900.00 3,689.03 3 Alat bantu Ls 1.00 2,500.00 2,500.00

Jumlah Alat 13,936.53

Jumlah 158,410.53

Page 37: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = #REF!Harga Satuan/m3 = Rp. 116,858.59

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Paving Block m3 1.05 95,085.00 99,839.25

Jumlah Bahan 99,839.25

B UPAH 1 Pekerja Hari 0.2667 46,200.00 12,321.54 2 Mandor Hari 0.0333 66,000.00 2,197.80

Jumlah Upah 14,519.34

C ALAT

1 Alat bantu Ls 1.00 2,500.00 2,500.00

Jumlah Alat 2,500.00

Jumlah 116,858.59

Page 38: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan= Pengadaan material dan pemasangan batu armour ukuran 150 - 200 Kg/unit

Harga Satuan/m3 = Rp. 276,489.74

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Batu Belah 150 - 200 kg/unit m3 1.20 158,475.00 190,170.00

Jumlah Bahan 190,170.00

B UPAH 1 Pekerja Hari 0.2667 46,200.00 12,321.54 2 Mandor Hari 0.0667 66,000.00 4,402.20

Jumlah Upah 16,723.74

C ALAT 1 Dump Truck Jam 0.2000 241,400.00 48,280.00 2 Excavator Jam 0.0400 407,900.00 16,316.00 3 Alat bantu Ls 1.00 5,000.00 5,000.00

Jumlah Alat 69,596.00

Jumlah 276,489.74

Page 39: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Pengadaan material dan pemasangan batu armour ukuran 300 - 500 Kg/unit

Harga Satuan/m3 = Rp. 350,770.67

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Batu Belah 300 - 500 kg/unit m3 1.20 211,300.00 253,560.00

Jumlah Bahan 253,560.00

B UPAH 1 Pekerja Hari 0.2667 46,200.00 12,321.54 2 Mandor Hari 0.0667 66,000.00 4,402.20

Jumlah Upah 16,723.74

C ALAT 1 Dump Truck Jam 0.2000 241,400.00 48,280.00 2 Excavator Jam 0.0667 407,900.00 27,206.93 3 Alat bantu Ls 1.00 5,000.00 5,000.00

Jumlah Alat 80,486.93

Jumlah 350,770.67

Page 40: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan = Beton bertulang (K-300, U32) paravet/ dinding penahan Harga Satuan/m3 = Rp. 2,806,099.78 Volume = #REF! m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting (Bahan) m2 1.5000 256,504.22 384,756.33 3 Pembesian (Bahan) kg 150.0000 8,355.63 1,253,344.50

Jumlah Bahan 2,409,673.83

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting (Upah) m2 1.5000 79,495.35 119,243.03 3 Pembesian (Upah) kg 150.0000 852.06 127,809.00

Jumlah Upah 304,054.25

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting (Alat) m2 1.5000 15,000.00 22,500.00 3 Pembesian (Alat) kg 150.0000 183.10 27,465.00

Jumlah Alat 92,371.70

Jumlah 2,806,099.78

Jenis Pekerjaan=

Harga Satuan/m3 = Rp. 2,806,099.78 Volume = #REF! m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting (Bahan) m2 1.5000 256,504.22 384,756.33 3 Pembesian (Bahan) kg 150.0000 8,355.63 1,253,344.50

Jumlah Bahan 2,409,673.83

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting (Upah) m2 1.5000 79,495.35 119,243.03 3 Pembesian (Upah) kg 150.0000 852.06 127,809.00

Jumlah Upah 304,054.25

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting (Alat) m2 1.5000 15,000.00 22,500.00 3 Pembesian (Alat) kg 150.0000 183.10 27,465.00

Jumlah Alat 92,371.70

Jumlah 2,806,099.78

Beton bertulang (K-300, U32) kepala tiang pancang/ pier dan abutment

Page 41: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan= Beton bertulang retaining wall apron dan pelat lantai apron

Harga Satuan/m3 = Rp. 2,571,330.03 Volume = #REF! m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting (Bahan) m2 1.5000 256,504.22 384,756.33 3 Pembesian (Bahan) kg 125.0000 8,355.63 1,044,453.75

Jumlah Bahan 2,200,783.08

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting (Upah) m2 1.5000 79,495.35 119,243.03 3 Pembesian (Upah) kg 125.0000 852.06 106,507.50

Jumlah Upah 282,752.75

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting (Alat) m2 1.5000 15,000.00 22,500.00 3 Pembesian (Alat) kg 125.0000 183.10 22,887.50

Jumlah Alat 87,794.20

Jumlah 2,571,330.03

Jenis Pekerjaan = Beton bertulang (K-300, U32) lantai gangway Harga Satuan/m3 = Rp. 1,698,379.19 Volume = #REF! m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting (Bahan) m2 1.5000 114,693.11 172,039.67 3 Wiremesh D10 m2 7.0000 74,210.00 519,470.00

Jumlah Bahan 1,463,082.67

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting (Upah) m2 1.5000 49,685.35 74,528.03 3 Pembesian (Upah) m2 7.0000 2,128.53 14,899.69

Jumlah Upah 146,429.94

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting (Alat) m2 1.5000 27,000.00 40,500.00 3 Pembesian (Alat) m2 7.0000 851.41 5,959.88

Jumlah Alat 88,866.58

Jumlah 1,698,379.19

Page 42: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan= Beton bertulang (K-300, wiremesh D10) lantai selter

Harga Satuan/m3 = Rp. 1,698,379.19 Volume = 54.00 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting (Bahan) m2 1.5000 114,693.11 172,039.67 3 Wiremesh D10 m2 7.0000 74,210.00 519,470.00

Jumlah Bahan 1,463,082.67

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting (Upah) m2 1.5000 49,685.35 74,528.03 3 Pembesian (Upah) m2 7.0000 2,128.53 14,899.69

Jumlah Upah 146,429.94

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting (Alat) m2 1.5000 27,000.00 40,500.00 3 Pembesian (Alat) m2 7.0000 851.41 5,959.88

Jumlah Alat 88,866.58

Jumlah 1,698,379.19

Jenis Pekerjaan = Konstruksi pasangan batu kali sebagai pondasi pagar precast beton

Harga Satuan/m3 = Rp. 480,375.73 Volume = 82.00 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN

1 Batu Kali m3 1.2000 126,780.00 152,136.00 2 Semen PC 50 Kg/zak zak 3.0000 63,390.00 190,170.00 3 Pasir Beton m3 0.4900 126,780.00 62,122.20

Jumlah Bahan 404,428.20

B UPAH 1 Pekerja Hari 0.6667 46,200.00 30,801.54 2 Tukang Hari 0.3333 60,500.00 20,164.65 3 Mandor kg 0.2500 66,000.00 16,500.00

Jumlah Upah 67,466.19

C ALAT 1 Concrete Mixer Jam 0.2000 42,406.70 8,481.34

Jumlah Alat 8,481.34

Jumlah 480,375.73

Page 43: RAB-Gang Way Dmg v Tahap II Value

ANALISA HARGA SATUANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 2,887,691.66 Volume = 41.00 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 2.0000 256,504.22 513,008.44 3 Pembesian (Bahan) kg 140.0000 8,355.63 1,169,788.20

Jumlah Bahan 2,454,369.64

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 2.0000 79,495.35 158,990.70 3 Pembesian (Upah) kg 140.0000 852.06 119,288.40

Jumlah Upah 335,281.32

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 2.0000 15,000.00 30,000.00 3 Pembesian (Alat) kg 140.0000 183.10 25,634.00

Jumlah Alat 98,040.70

Jumlah 2,887,691.66

Jenis Pekerjaan =

Harga Satuan/m3 = Rp. 3,330,956.63 Volume = 2.00 m3

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN (Rp.) JUMLAH (Rp.)

A BAHAN 1 Beton K-300 (Bahan) m3 1.0000 771,573.00 771,573.00 2 Bekisting Pile Cap (Bahan) m2 3.5000 191,378.46 669,824.61 3 Pembesian (Bahan) kg 128.7875 8,355.63 1,076,100.70 4 Angkur Ls 1.00 250,000.00 250,000.00

Jumlah Bahan 2,767,498.31

B UPAH 1 Beton K-300 (Upah) m3 1.0000 57,002.22 57,002.22 2 Bekisting Pile Cap (Upah) m2 3.5000 79,495.35 278,233.73 3 Pembesian (Upah) kg 128.7875 852.06 109,734.68

Jumlah Upah 444,970.63

C ALAT 1 Beton K-300 (Alat) m3 1.0000 42,406.70 42,406.70 2 Bekisting Pile Cap (Alat) m2 3.5000 15,000.00 52,500.00 3 Pembesian (Alat) kg 128.7875 183.10 23,580.99

Jumlah Alat 118,487.69

Jumlah 3,330,956.63

Beton bertulang (K-300, U32) pile cap dan sbg pondasi kolom penyangga selter, 18 unit, dim.1600x1200x1200

Beton bertulang (K-300, U32) pondasi tangga selter termasuk angkur

Page 44: RAB-Gang Way Dmg v Tahap II Value

RENCANA ANGGARAN BIAYA (RAB)PEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

No URAIAN PEKERJAAN UNIT VOLUME HARGA SATUAN JUMLAH HARGA

(Rp.) (Rp.)

A Pekerjaan Persiapan 1 Mobilisasi dan Demobilsasi Ls 1.00 519,750,000.00 519,750,000.00 2 Pengukuran dan Positioning Ls 1.00 47,107,500.00 47,107,500.00 3 Direksi Keet beserta kelengkapannya m2 36.00 787,500.00 28,350,000.00 4 Pagar Pengaman Proyek m' 160.00 150,000.00 24,000,000.00 5 Instalasi listrik, penerangan dan air kerja

a. Instalasi listrik dan air kerja Ls 1.00 8,400,000.00 8,400,000.00 b. Biaya pemakaian listrik dan air kerja Bln 8.00 4,725,000.00 37,800,000.00

6 Keselamatan Kerja Bln 8.00 3,609,375.00 28,875,000.00 7 Administrasi, As built drawing dan Dokumentasi Ls 1.00 17,955,000.00 17,955,000.00

Sub Total 712,237,500.00

B Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway, darat) 1 Pengadaan Tiang pancang Ø 406.4 mm, t=12 mm ( w = 117 kg/m') (TA. 2011) Kg - - 2 Pemancangan tiang pancang dia. 400 mm m 180.00 211,623.21 38,092,177.80 3 Pemotongan tiang pancang unit 6.00 212,284.33 1,273,705.98 4 Penyambungan tiang pancang setiap 12m unit 12.00 262,500.00 3,150,000.00 5 Ring pelat Dia=700mm, t= 12 mm ( w = ± 24.5 kg/unit) unit 6.00 744,432.50 4,466,595.00 6 Pelat penutup tiang dia. 400 mm, t= 6mm ( w = ± 6 Kg/unit) unit 6.00 182,310.00 1,093,860.00 7 Bracing pengaku tiang pancang H 300 x 200 x 8/12 (w=57Kg/m') Kg 140.00 30,385.00 4,253,900.00

Sub Total 52,330,238.78

C Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway dan ESR, laut) 1 Pengadaan Tiang pancang Ø 812,3 mm, t=14 mm ( w = 276 kg/m') (TA.2011) Kg - - 2 Pemancangan tiang pancang dia. 812,3 mm m 1,650.00 542,365.00 894,902,250.00 3 Pemotongan tiang pancang, setting dan penyambungan unit 55.00 473,164.94 26,024,071.70

Penyambungan tiang pancang setiap 12m unit 110.00 567,000.00 62,370,000.00 4 Ring pelat Dia=1200mm, t= 12 mm ( w = ±59 kg/unit) unit 55.00 1,792,715.00 98,599,325.00 5 Pelat penutup tiang dia. 812,3 mm, t= 6mm ( w = ± 23,6 Kg/unit) unit 55.00 717,086.00 39,439,730.00 6 Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94Kg/m') Kg 18,800.00 30,385.00 571,238,000.00 7 Pengadaan dan Pemasangan Selimut Tiang Pancang (Pelindung Karat, PE Cover) m2 580.00 846,443.58 490,937,275.00

Sub Total 2,183,510,651.70

D Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, darat) 1 Beton bertulang (K-300, U32) pondasi gangway 3000x1600x1600 m3 26.87 2,540,514.15 68,263,615.21 2 Beton bertulang (K-300, U32) pengisi tiang pancang dia.400mm L=1000 mm m3 3.01 4,245,262.59 12,778,240.40 3 Beton lantai kerja (K-100) t = 100 mm m3 3.62 694,243.04 2,513,159.80 4 Lapisan batu kali dipadatkan t = 600 mm m3 27.47 219,836.00 6,038,894.92 5 Pembongkaran dan galian tanah untuk pondasi m3 41.20 45,000.00 1,854,000.00 6 Urug kembali dan pemadatan tanah termasuk pemasangan eksisting paving blok m3 80.71 56,250.00 4,539,937.50 7 Pilar pelindung kolom gangway, besi dia.150 mm, t= 10mm, L = 1300 mm digalvanis unit 28.00 1,931,250.00 54,075,000.00 8 Angkur kolom penyangga konstruksi gangway ( w = ± 900 Kg/unit) unit 3.00 31,981,500.00 95,944,500.00

Sub Total 246,007,347.83

E Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, laut) 1 Beton bertulang (K-300, U32) pondasi gangway Type-1, 8000x7000x1600 (1 unit) m3 89.60 2,596,751.61 232,668,944.26 2 Beton bertulang (K-300, U32) pondasi gangway Type-2, 8000x7000x1600 (1 unit) m3 97.28 2,645,502.59 257,354,491.96 3 Beton bertulang (K-300, U32) pondasi gangway Type-3, 3500x35000x1600 (3 unit) m3 78.40 3,060,955.50 239,978,911.20 4 Beton bertulang (K-300, U32) pondasi gangway Type-4, 8000x4000x1600 (2 unit) m3 102.40 2,776,115.04 284,274,180.10 5 Beton bertulang (K-300, U32) pondasi gangway Type-5, 8000x3500x1600 (5 unit) m3 224.00 2,776,115.04 621,849,768.96 6 Beton bertulang (K-300, U32) beton pengisi tiang pancang dia. 800 mm, L=2000 mm m3 55.26 4,245,262.59 234,593,210.72 7 Angkur dan baseplate kolom penyangga konstruksi gangway ( w = ± 900 Kg/unit) unit 9.00 31,981,500.00 287,833,500.00 8 Angkur dan baseplate kolom penyangga konstruksi Akses Bridge ( w = ± 527 Kg/unit) unit 8.00 18,726,945.00 149,815,560.00

9 unit 2.00 23,950,590.00 47,901,180.00

10 unit 2.00 20,859,045.00 41,718,090.00

11 Angkur dan baseplate konstruksi Apron ESR ( w = ± 41 Kg/unit) unit 22.00 1,456,935.00 32,052,570.00 Sub Total 2,430,040,407.19

Angkur dan baseplate konstruksi Kolom Penggantung Hidraulik ESR, Tipe -1 ( w = ± 674 Kg/unit)

Angkur dan baseplate konstruksi Kolom Penggantung Hidraulik ESR, Tipe -2 ( w = ± 587 Kg/unit)

Page 45: RAB-Gang Way Dmg v Tahap II Value

No URAIAN PEKERJAAN UNIT VOLUME HARGA SATUAN JUMLAH HARGA

(Rp.) (Rp.)

F Pekerjaan reklamasi dan revetment 1 Pengadaan material dan pemadatan lapisan sirtu m3 5,756.00 173,691.08 999,765,856.48 2 Pengadaan material dan pemadatan lapisan/tanah urug m3 1,279.00 83,547.91 106,857,776.89 3 Pengadaan material dan pemadatan lapisan basecourse (CBR > 80%) m3 1,066.00 209,189.48 222,995,985.68 4 Pengadaan lapisan pasir t = 50 mm di bawah paving blok m3 127.50 158,410.53 20,197,342.58 5 Pengadaan material dan pemasangan paving blok t =80 mm ( K-400) m2 2,050.00 116,858.59 239,560,109.50 6 Pengadaan material dan pemasangan lapisan geotekstil m2 525.00 16,102.13 8,453,615.63 7 Beton bertulang (K-300, U32) paravet/ dinding penahan m3 87.75 2,806,099.78 246,235,255.70 8 Pengadaan material dan pemasangan batu armour ukuran 150 - 200 Kg/unit m3 1,409.89 276,489.74 389,820,119.53 9 Pengadaan material dan pemasangan batu armour ukuran 300 - 500 Kg/unit m3 600.00 350,770.67 210,462,402.00

10 Pengadaan material dan pemasangan Pipa PVC (AW) dia. 100 mm pada paravet m 10.00 45,000.00 450,000.00 11 Konstruksi pasangan batu kali sebagai pondasi pagar precast beton m3 82.00 480,375.73 39,390,809.86 12 Pengadaan material dan pemasangan kolom pagar precast 200x200x3000 mm int. 2, unit 30.00 225,000.00 6,750,000.00 13 Pengadaan material dan pemasangan pagar pelat beton precast 2400x500x t = 50 m unit 120.00 309,375.00 37,125,000.00 14 Pembongkaran existing pagar beton precast m 75.00 84,375.00 6,328,125.00

Sub Total 2,534,392,398.83

G Tiang Pancang dan Assesoriesnya (Abutment ESR dan Kolom Penyangga Gangway) 1 Pengadaan Tiang pancang Ø 812,8 mm, t=14 mm ( w = 276 kg/m') (TA. 2011) Kg - - 2 Pemancangan tiang pancang dia. 812.8 mm m 60.00 542,365.00 32,541,900.00 3 Pemotongan tiang, setting unit 2.00 473,164.94 946,329.88 4 Penyambungan tiang pancang setiap 12m unit 4.00 567,000.00 2,268,000.00 5 Ring pelat Dia=1200mm, t= 12 mm ( w = ± 59 kg/unit) unit 2.00 1,792,715.00 3,585,430.00 6 Pelat penutup tiang dia. 812.3 mm, t= 6mm ( w = ± 24 Kg/unit) unit 2.00 729,240.00 1,458,480.00 7 Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94 Kg/m') Kg 348.00 30,385.00 10,573,980.00 8 Base plate dan angkur untuk post guard rail ( w= ± 12Kg/unit ) unit 12.00 364,620.00 4,375,440.00

Sub Total 55,749,559.88

H Pekerjaan beton dan pelengkapnya (Abutment dan Appron ESR) 1 Beton bertulang (K-300, U32) kepala tiang pancang/ pier dan abutment m3 27.00 2,806,099.78 75,764,694.06 2 Beton bertulang (K-300, U32) pengisi tiang pancang dia.812.3 mm L=2000 mm m3 2.00 4,245,262.59 8,490,525.18 3 Angkur dan base plate kolom penyangga konstruksi gangway ( w = ± 900 Kg/unit) unit 1.00 31,981,500.00 31,981,500.00 4 Angkur base plate appron ESR (w = ± 45 Kg/unit) unit 2.00 1,367,325.00 2,734,650.00 5 Pelat sudut di abutment termasuk angkurnya , digalvanis ( w = ± 20 Kg/m') m 15.00 607,700.00 9,115,500.00 6 Pengadaan dan pemasangan guard rail , post dan assesoriesnya (digalvanis) Kg 750.00 35,535.00 26,651,250.00 7 Beton bertulang retaining wall apron dan pelat lantai apron m3 20.00 2,571,330.03 51,426,600.60 8 Beton lantai kerja (K-100) t = 100 mm m3 5.00 694,243.04 3,471,215.20 9 Lapisan basecorse termasuk pekerjaan pemadatan m3 20.00 209,189.48 4,183,789.60

10 Lapisan sirtu termasuk pekerjaan pemadatan m3 15.00 173,691.08 2,605,366.20

Sub Total 216,425,090.84

I Konstruksi Gangway dan Kolom Penyangga ( ±267 m, bagian darat )

1 Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi gangway (TA. 2011) Kg - -

2 Kg - -

3 Kg - -

4 Kg - -

5 Pengecatan dan pemasangan konstruksi gangway Kg ### 8,755.79 1,057,165,328.81 6 Pengecatan dan pemasangan konstruksi kolom penyangga Kg 26,638.000 8,755.79 233,236,734.02 7 Beton bertulang (K-300, U32) lantai gangway m3 38.00 1,698,379.19 64,538,409.22 8 Pengadaan dan pemasangan pelat bondek m2 363.00 178,190.00 64,682,970.00 9 Pengadaan dan pemasangan atap asbes dan assesoriesnya m2 727.00 87,550.00 63,648,850.00

10 m2 220.00 918,760.00 202,127,200.00

11 Elektrikal (titk lampu @ 5 m dan jaringannya) unit 53.00 393,750.00 20,868,750.00 Sub Total 1,706,268,242.05

Pengadaan, pabrikasi pengecatan dan pemasangan konstruksi kolom penyangga (TA. 2011) Pengadaan, pabrikasi konstruksi gangway (tanpa pengecatan dan pemancangan) (TA. 2011) Pengadaan, pabrikasi kontruksi kolom penyangga (tanpa pengecatan dan pemasangan) (TA. 2011)

Pengadaan, fabrikasi dan pemasangan fiber sheet t = 5 mm (handrail) dan asesories.

Page 46: RAB-Gang Way Dmg v Tahap II Value

No URAIAN PEKERJAAN UNIT VOLUME HARGA SATUAN JUMLAH HARGA

(Rp.) (Rp.)

J Konstruksi Gangway dan Kolom Penyangga ( ±200 m, bagian laut ) 1 Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi gangway Kg 37,302.00 34,596.97 1,290,536,174.94 2 Pengadaan, pabrikasi (tanpa pengecatan dan pemasangan) (TA. 2011) Kg - - 3 Pengecatan dan pemasangan baja Kg 146,823.00 8,755.79 1,285,551,355.17 4 Pengadaan, pabrikasi pengecatan dan pemasangan konstruksi kolom penyangga Kg 43,800.00 35,944.05 1,574,349,390.00 5 Beton bertulang (K-300, U32) lantai gangway m3 88.00 1,698,379.19 149,457,368.72 6 Pengadaan dan pemasangan pelat bondek m2 735.00 178,190.00 130,969,650.00 7 Pengadaan dan pemasangan atap asbes dan assesoriesnya m2 1,593.00 87,550.00 139,467,150.00 8 Pengadaan, fabrikasi dan pemasangan fiber sheet t = 5 mm (handrail) dan asesories m2 245.00 918,760.00 225,096,200.00 9 Elektrikal (titk lampu @ 5 m dan jaringannya) unit 50.00 393,750.00 19,687,500.00

Sub Total 4,815,114,788.83

K Konstruksi Baja Apron ESR 1 Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi apron ESR (±100 m) Kg 150,000.00 34,596.97 5,189,545,500.00

Sub Total 5,189,545,500.00

L Movable Gangway 1 Konstruksi Movable Gangway ( 1set, 2unit)

a. Fixed Flatform Kg 3,600.00 36,050.00 129,780,000.00 b. Turning Flatform Kg 1,169.00 56,135.00 65,621,815.00 c. Rear Bridge Kg - - d. Movable Frame Kg - - e. Tilting Bridge Kg - - f. Base Frame Kg 3,600.00 36,050.00 129,780,000.00

2 Mekanikal dan Elektrikal ( 1 set, 2 unit ) a. Hidraulik Silinder ( 1 @ 4 unit) unit - - b. Power Pack Hidraulik Unit unit - - c. Elektrikal dan Piping set - -

Sub Total 325,181,815.00

M Elevated Side Ramp 1 Konstruksi Baja Side Ramp

a. Approach Bridge Kg - - b. Moving Bridge Kg 22,000.00 56,135.00 1,234,970,000.00 c. Ramp Bridge Kg 5,500.00 45,835.00 252,092,500.00 d. Rangka Kolom , Operating Room dan Walkway Kg 25,000.00 34,505.00 862,625,000.00 e. Base Plate , Plate 300x300xt=20, Angkur Dia.40mm, L = 500mm Kg 610.00 29,458.00 17,969,380.00 f. Bearing Plate 300 x 300 x t = 50 mm Kg 1,130.00 34,505.00 38,990,650.00

2 Mekanikal dan Elektrikal a. Hidraulik Silinder Moving Bridge ( 2 unit) unit - - b. Hidraulik Silinder Ramp Bridge ( 2 unit) unit - - c. Power Pack Hidraulik Unit unit - -

d. unit - -

e. set -

f. m -

g. Pengadaan dan pemasangan tiang lampu, lampu dan kabel jaringannya titik - 3 Pekerjaan Sipil Lainnya

a. Pelat Lantai kendaraan t = 250 mm (beton bertulang, K500) m3 - - b. Rumah mesin (4 m x 4 m) m2 - -

Sub Total 2,406,647,530.00

Elektrikal, Control Desk, panel dan Oil Piping (sus 304, sch 160) termasuk assesories dan rubber hose Unit 0.00

Pengadaan dan pemasangan lampu red flash, kabel dan assesoriesnya (1 set@ 2 unit)

Pengadaan dan pemasangan kabel listrik (power supply) termasul konduit dan assesoriesnya

Page 47: RAB-Gang Way Dmg v Tahap II Value

No URAIAN PEKERJAAN UNIT VOLUME HARGA SATUAN JUMLAH HARGA

(Rp.) (Rp.)

N Shelter 1 Pengadaan dan pemasangan konstruksi baja termasuk pengecatan Kg - - 2 Pemancangan tiang pancang dia. 400 mm pondasi selter, 18 titik @ 30 m m 540.00 125,000.00 67,500,000.00 3 Pemotongan tiang pancang Unit 18.00 150,000.00 2,700,000.00 4 Penyambungan tiang pancang Unit 36.00 250,000.00 9,000,000.00

Ring pelat Dia=700mm, t= 12 mm ( w = ± 24.5 kg/unit) Unit 18.00 744,432.50 13,399,785.00 Pelat penutup tiang dia. 400 mm, t= 6mm ( w = ± 6 Kg/unit) Unit 18.00 182,310.00 3,281,580.00 Bracing pengaku tiang pancang H 300 x 200 x 8/12 (w=57Kg/m') Kg 897.75 30,385.00 27,278,133.75

5 m3 41.00 2,887,691.66 118,395,358.06

6 Beton bertulang (K-300, U32) pondasi tangga selter termasuk angkur m3 2.00 3,330,956.63 6,661,913.26 7 Angkur dan baseplate kolom penyangga bangunan selter unit 18.00 618,750.00 11,137,500.00 8 Beton bertulang (K-300, wiremesh D10) lantai selter m3 54.00 1,698,379.19 91,712,476.26 9 Pengadaan dan pemasangan lantai keramik 60x60 cm m2 419.00 85,000.00 35,615,000.00

10 Pengadaan dan pemasangan bondek m2 450.00 178,190.00 80,185,500.00

11 unit 11.00 9,290,250.00 102,192,750.00

12 unit 9.00 9,290,250.00 83,612,250.00

13 unit 10.00 6,423,750.00 64,237,500.00

14 unit 2.00 3,177,000.00 6,354,000.00

15 unit 2.00 2,420,156.25 4,840,312.50

16 unit 2.00 1,085,625.00 2,171,250.00

17 unit 2.00 9,802,125.00 19,604,250.00

18 m2 500.00 618,750.00 309,375,000.00

19 Pengadaan dan pemasangan kalsiboard termasuk finishing dan pengecatan m2 500.00 120,937.50 60,468,750.00 20 Pengadaan dan pemasangan atap corrugated metal roof termasuk perlengkapannya m2 540.00 163,928.57 88,521,428.57 21 Pengadaan dan pemasangan pintu PVC untuk toilet termasuk perlengkapannya unit 6.00 393,750.00 2,362,500.00 22 Pekerjaan dinding pasangan bata merah termasuk plesteran, acian dan pengecatan m2 132.00 106,875.00 14,107,500.00 23 Pengadaan dan pemasangan dinding keramik 20X20 cm di toilet m2 122.00 106,875.00 13,038,750.00 24 Pekerjaan plumbing dan sanitari, termasuk kloset duduk, keran dan perelngkapan lain set 1.00 1,968,750.00 1,968,750.00 25 Pekerjaan elektrikal termasuk jaringan listrik, lampu dan perlengkapan lainnya set 1.00 151,875,000.00 151,875,000.00

26 unit 1.00 16,875,000.00 16,875,000.00

Sub Total 1,408,472,237.40

Beton bertulang (K-300, U32) pile cap dan sbg pondasi kolom penyangga selter, 18 unit, dim.1600x1200x1200

Pengadaan dan pemasangan jendela Tipe-1 dim.2800x2200mm (rangka alumunium + Kaca dan assesoriesnyau)

Pengadaan dan pemasangan jendela Tipe-2 dim. 2800x2200mm (rangka alumunium + Kaca dan assesoriesnyuan)

Pengadaan dan pemasangan jendela Tipe-3 dim. 2800x1500mm(rangka alumunium + Kaca dan assesoriesnyau)

Pengadaan dan pemasangan jendela Tipe-4 dim.2200x900mm (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan jendela Tipe-5 dim.1625x900mm (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan jendela Tipe-6 dim. 1100x500mm (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan pintu double dim.3100x2100 (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan Aluminium Komposit Panel PVDF (tebal 4 mm, Al.koil 0,3 mm ) termasuk rangkam dan sealant

Pekerjaan bangunan septic tank (beton bertulang) dim. 2000x2000x3000mm termasuk kelengkapannya

Page 48: RAB-Gang Way Dmg v Tahap II Value

R E K A P I T U L A S IRENCANA ANGGARAN BIAYA (RAB)

PEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA VPELABUHAN PENYEBERANGAN MERAK - TAHAP II

TA. 2012

No URAIAN PEKERJAAN BIAYA (Rp.)

A Pekerjaan Persiapan 712,237,500.00 B Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway, darat) 52,330,238.78 C Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway dan ESR, laut 2,183,510,651.70 D Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, darat) 246,007,347.83 E Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, laut) 2,430,040,407.19 F Pekerjaan reklamasi dan revetmen 2,534,392,398.83 G Tiang Pancang dan Assesoriesnya (Abutment ESR dan Kolom Penyangga Gangway) 55,749,559.88 H Pekerjaan beton dan pelengkapnya (Abutment dan Appron ESR) 216,425,090.84 I Konstruksi Gangway dan Kolom Penyangga ( ±267 m, bagian darat ) 1,706,268,242.05 J Konstruksi Gangway dan Kolom Penyangga ( ±200 m, bagian laut ) 4,815,114,788.83 K Konstruksi Baja Apron ESR (Elevated Side Ramp) 5,189,545,500.00 L Movable Gangway 325,181,815.00 M Elevated Side Ramp 2,406,647,530.00 N Shelter 1,408,472,237.40

Sub Total I 24,281,923,308.34 PPN 10% 2,428,192,330.83 TOTAL 26,710,115,639.17 PEMBULATAN 26,710,115,639.00

Terbilang :

Jakarta, 9 Maret 2012

Kepala

Dua Puluh Enam Milyar Tujuh Ratus Sepuluh Juta Seratus Lima Belas Ribu Enam Ratus Tiga Puluh Sembilan Rupiah

Page 49: RAB-Gang Way Dmg v Tahap II Value

BAGIAN PEKERJAAN YANG DISUBKONTRAKKANPEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA V

PELABUHAN PENYEBERANGAN MERAK - TAHAP II

No URAIAN PEKERJAAN

Bab B2 Pemancangan tiang pancang dia. 400 mm 0.16%3 Pemotongan tiang pancang 0.01%4 Penyambungan tiang pancang setiap 12m 0.01%

Bab C2 Pemancangan tiang pancang dia. 812,3 mm 3.69%3 Pemotongan tiang pancang, setting dan penyambungan 0.11%

Penyambungan tiang pancang setiap 12m 0.26%

Bab D3 Beton lantai kerja (K-100) t = 100 mm 0.01%

Bab H8 Beton lantai kerja (K-100) t = 100 mm 0.01%

4.25%

Jakarta, 9 Maret 2012

Kepala

PROSENTASE DARI HARGA TOTAL

PENAWARAN ( % )

Page 50: RAB-Gang Way Dmg v Tahap II Value

FORMULIR REKAPITULASI PERHITUNGANTINGKAT KOMPONEN DALAM NEGERI (TKDN) GABUNGAN BARANG DAN JASA

PEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA VPELABUHAN PENYEBERANGAN MERAK - TAHAP II

Nilai Gabungan Barang / Jasa (Rp.) TKDN

URAIAN PEKERJAAN DN LN TOTAL Barang / Jasa Rp Gabungan %

Rp % KDN

(01) (2) (3) (4) (5) (7) (8)

BarangI Material Langsung (Bahan Baku) 22,703,598,293.29 - 22,703,598,293.29 100.00% 22,703,598,293.29 85.00%

II Peralatan (Barang Jadi) - - - #DIV/0! - 0.00%

A. Sub Total Barang 22,703,598,293.29 - 22,703,598,293.29 100.00% 22,703,598,293.29 85.00%

JasaIII Manajemen Proyek dan 667,752,890.98 - 667,752,890.98 100.00% 667,752,890.98 2.50%

PrekayasaanIV Alat Kerja / Fasilitas Kerja 934,854,047.37 - 934,854,047.37 100.00% 934,854,047.37 3.50%

V Konstruksi dan Fabrikasi 1,736,157,516.55 - 1,736,157,516.55 100.00% 1,736,157,516.55 6.50%

VI Jasa Umum 667,752,890.98 - 667,752,890.98 100.00% 667,752,890.98 2.50%

B. Sub Total Jasa 4,006,517,345.88 - 4,006,517,345.88 100.00% 4,006,517,345.88 15.00%

C. Total Biaya (A+B) 26,710,115,639.17 - 26,710,115,639.17 100.00% 26,710,115,639.17 100.00%

Jakarta, 9 Maret 2012

Kepala

Page 51: RAB-Gang Way Dmg v Tahap II Value

Terbilang : RUPIAH rupiah

0 1 Satu0 2 Dua

0 0 3 Tiga0 4 Empat0 5 Lima0 6 Enam

0 0 7 Tujuh0 8 Delapan0 9 Sembilan

0 0 10 Sepuluh0 11 Sebelas

12 Dua Belas0 13 Tiga Belas

14 Empat Belas15 Lima Belas16 Enam Belas

512050716870 17 Tujuh Belas18 Delapan Belas19 Sembilan Belas20 Dua Puluh21 Dua Puluh Satu22 Dua Puluh Dua23 Dua Puluh Tiga24 Dua Puluh Empat25 Dua Puluh Lima26 Dua Puluh Enam27 Dua Puluh Tujuh28 Dua Puluh Delapan

RUPIAH 29 Dua Puluh Sembilan30 Tiga Puluh

26,710,115,639 31 Tiga Puluh Satu 26,710,115,639 32 Tiga Puluh Dua 26,710,115 33 Tiga Puluh Tiga 26,710 34 Tiga Puluh Empat 26 0 35 Tiga Puluh Lima

26 36 Tiga Puluh Enam 710 7 37 Tiga Puluh Tujuh

10 38 Tiga Puluh Delapan 115 1 39 Tiga Puluh Sembilan

15 40 Empat Puluh 639 6 41 Empat Puluh Satu

39 42 Empat Puluh Dua43 Empat Puluh Tiga

44 Empat Puluh EmpatDua Puluh Enam 45 Empat Puluh LimaMilyar 46 Empat Puluh EnamTujuh Ratus 47 Empat Puluh TujuhSepuluh 48 Empat Puluh DelapanJuta 49 Empat Puluh SembilanSeratus 50 Lima PuluhLima Belas 51 Lima Puluh Satu

Page 52: RAB-Gang Way Dmg v Tahap II Value

Ribu 52 Lima Puluh DuaEnam Ratus 53 Lima Puluh TigaTiga Puluh Sembilan 54 Lima Puluh EmpatRupiah 55 Lima Puluh Lima

56 Lima Puluh Enam57 Lima Puluh Tujuh58 Lima Puluh Delapan59 Lima Puluh Sembilan60 Enam Puluh61 Enam Puluh Satu62 Enam Puluh Dua63 Enam Puluh Tiga64 Enam Puluh Empat65 Enam Puluh Lima66 Enam Puluh Enam67 Enam Puluh Tujuh68 Enam Puluh Delapan69 Enam Puluh Sembilan70 Tujuh Puluh71 Tujuh Puluh Satu72 Tujuh Puluh Dua73 Tujuh Puluh Tiga74 Tujuh Puluh Empat75 Tujuh Puluh Lima76 Tujuh Puluh Enam77 Tujuh Puluh Tujuh78 Tujuh Puluh Delapan79 Tujuh Puluh Sembilan80 Delapan Puluh81 Delapan Puluh Satu82 Delapan Puluh Dua83 Delapan Puluh Tiga84 Delapan Puluh Empat85 Delapan Puluh Lima86 Delapan Puluh Enam87 Delapan Puluh Tujuh88 Delapan Puluh Delapan89 Delapan Puluh Sembilan90 Sembilan Puluh91 Sembilan Puluh Satu92 Sembilan Puluh Dua93 Sembilan Puluh Tiga94 Sembilan Puluh Empat95 Sembilan Puluh Lima96 Sembilan Puluh Enam97 Sembilan Puluh Tujuh98 Sembilan Puluh Delapan99 Sembilan Puluh Sembilan

12

Page 53: RAB-Gang Way Dmg v Tahap II Value

Empat Puluh DelapanEmpat Puluh Sembilan

Page 54: RAB-Gang Way Dmg v Tahap II Value

26,710,115,639.00 26,710,115,639 Dua Puluh Enam Milyar Tujuh Ratus Sepuluh Juta Seratus Lima Belas Ribu Enam Ratus Tiga Puluh Sembilan Rupiah

Enam Puluh Sembilan

Tujuh Puluh Sembilan

Delapan Puluh Empat

Delapan Puluh DelapanDelapan Puluh Sembilan

Sembilan Puluh Empat

Sembilan Puluh EnamSembilan Puluh TujuhSembilan Puluh DelapanSembilan Puluh Sembilan

Page 55: RAB-Gang Way Dmg v Tahap II Value

2.67E+10 Dua Puluh Enam Milyar Tujuh Ratus Sepuluh Juta Seratus Lima Belas Ribu Enam Ratus Tiga Puluh Sembilan Rupiah

Page 56: RAB-Gang Way Dmg v Tahap II Value

RENCANA ANGGARAN BIAYA (RAB)PEMBANGUNAN GANGWAY DAN ELEVATED SIDE RAMP DI DERMAGA VPELABUHAN PENYEBERANGAN MERAK - TAHAP II

No URAIAN PEKERJAAN UNITESTIMASI HARGA SATUAN JUMLAH HARGA

KUANTITAS (Rp.) (Rp.)

A Pekerjaan Persiapan 1 Mobilisasi dan Demobilsasi Ls 1.00 519,750,000.00 2 Pengukuran dan Positioning Ls 1.00 47,107,500.00 3 Direksi Keet beserta kelengkapannya m2 36.00 787,500.00 4 Pagar Pengaman Proyek m' 160.00 150,000.00 5 Instalasi listrik, penerangan dan air kerja

a. Instalasi listrik dan air kerja Ls 1.00 8,400,000.00 b. Biaya pemakaian listrik dan air kerja Bln 8.00 4,725,000.00

6 Keselamatan Kerja Bln 8.00 3,609,375.00 7 Administrasi, As built drawing dan Dokumentasi Ls 1.00 17,955,000.00

Sub Total -

B Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway, darat) 1 Pengadaan Tiang pancang Ø 406.4 mm, t=12 mm ( w = 117 kg/m') (TA. 2011) Kg - 2 Pemancangan tiang pancang dia. 400 mm m 180.00 100,000.00 3 Pemotongan tiang pancang unit 6.00 100,000.00 4 Penyambungan tiang pancang setiap 12m unit 12.00 250,000.00 5 Ring pelat Dia=700mm, t= 12 mm ( w = ± 24.5 kg/unit) unit 6.00 669,989.25 4,019,935.50 6 Pelat penutup tiang dia. 400 mm, t= 6mm ( w = ± 6 Kg/unit) unit 6.00 164,079.00 984,474.00 7 Bracing pengaku tiang pancang H 300 x 200 x 8/12 (w=57Kg/m') Kg 140.00 27,346.50 3,828,510.00

Sub Total 8,832,919.50

C Tiang Pancang dan Assesoriesnya (Pondasi kolom penyangga gangway dan ESR, laut) 1 Pengadaan Tiang pancang Ø 812,3 mm, t=14 mm ( w = 276 kg/m') (TA.2011) Kg - - 2 Pemancangan tiang pancang dia. 812,3 mm m 1,650.00 350,000.00 3 Pemotongan tiang pancang, setting dan penyambungan unit 55.00 100,000.00

Penyambungan tiang pancang setiap 12m unit 110.00 275,000.00 4 Ring pelat Dia=1200mm, t= 12 mm ( w = ±59 kg/unit) unit 55.00 1,613,443.50 88,739,392.50 5 Pelat penutup tiang dia. 812,3 mm, t= 6mm ( w = ± 23,6 Kg/unit) unit 55.00 645,377.40 35,495,757.00 6 Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94Kg/m') Kg 18,800.00 27,346.50 514,114,200.00 7 Pengadaan dan Pemasangan Selimut Tiang Pancang (Pelindung Karat, PE Cover) m2 580.00 550,000.00

Sub Total 638,349,349.50

D Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, darat) 1 Beton bertulang (K-300, U32) pondasi gangway 3000x1600x1600 m3 26.87 2,540,514.15 2 Beton bertulang (K-300, U32) pengisi tiang pancang dia.400mm L=1000 mm m3 3.01 4,245,262.59 3 Beton lantai kerja (K-100) t = 100 mm m3 3.62 694,243.04 4 Lapisan batu kali dipadatkan t = 600 mm m3 27.47 219,836.00 5 Pembongkaran dan galian tanah untuk pondasi m3 41.20 40,000.00 6 Urug kembali dan pemadatan tanah termasuk pemasangan eksisting paving blok m3 80.71 35,000.00 7 Pilar pelindung kolom gangway, besi dia.150 mm, t= 10mm, L = 1300 mm digalvanis unit 28.00 1,738,125.00 48,667,500.00 8 Angkur kolom penyangga konstruksi gangway ( w = ± 900 Kg/unit) unit 3.00 28,783,350.00 86,350,050.00

Sub Total 135,017,550.00

E Pekerjaan beton dan pelengkapnya (Pondasi kolom penyangga gangway, laut) 1 Beton bertulang (K-300, U32) pondasi gangway Type-1, 8000x7000x1600 (1 unit) m3 89.60 2,596,751.61 2 Beton bertulang (K-300, U32) pondasi gangway Type-2, 8000x7000x1600 (1 unit) m3 97.28 2,645,502.59 3 Beton bertulang (K-300, U32) pondasi gangway Type-3, 3500x35000x1600 (3 unit) m3 78.40 3,060,955.50 4 Beton bertulang (K-300, U32) pondasi gangway Type-4, 8000x4000x1600 (2 unit) m3 102.40 2,776,115.04 5 Beton bertulang (K-300, U32) pondasi gangway Type-5, 8000x3500x1600 (5 unit) m3 224.00 2,776,115.04 6 Beton bertulang (K-300, U32) beton pengisi tiang pancang dia. 800 mm, L=2000 mm m3 55.26 4,245,262.59 7 Angkur dan baseplate kolom penyangga konstruksi gangway ( w = ± 900 Kg/unit) unit 9.00 28,783,350.00 259,050,150.00 8 Angkur dan baseplate kolom penyangga konstruksi Akses Bridge ( w = ± 527 Kg/unit) unit 8.00 16,854,250.50 134,834,004.00

9 unit 2.00 21,555,531.00 43,111,062.00

10 unit 2.00 18,773,140.50 37,546,281.00

11 Angkur dan baseplate konstruksi Apron ESR ( w = ± 41 Kg/unit) unit 22.00 1,311,241.50 28,847,313.00 Sub Total 503,388,810.00

Angkur dan baseplate konstruksi Kolom Penggantung Hidraulik ESR, Tipe -1 ( w = ± 674 Kg/unit)

Angkur dan baseplate konstruksi Kolom Penggantung Hidraulik ESR, Tipe -2 ( w = ± 587 Kg/unit)

Page 57: RAB-Gang Way Dmg v Tahap II Value

No URAIAN PEKERJAAN UNITESTIMASI HARGA SATUAN JUMLAH HARGA

KUANTITAS (Rp.) (Rp.)

F Pekerjaan reklamasi dan revetment 1 Pengadaan material dan pemadatan lapisan sirtu m3 5,756.00 173,691.08 2 Pengadaan material dan pemadatan lapisan/tanah urug m3 1,279.00 83,547.91 3 Pengadaan material dan pemadatan lapisan basecourse (CBR > 80%) m3 1,066.00 209,189.48 4 Pengadaan lapisan pasir t = 50 mm di bawah paving blok m3 127.50 158,410.53 5 Pengadaan material dan pemasangan paving blok t =80 mm ( K-400) m3 2,050.00 116,858.59 6 Pengadaan material dan pemasangan lapisan geotekstil m3 525.00 12,500.00 7 Beton bertulang (K-300, U32) paravet/ dinding penahan m3 87.75 2,806,099.78 8 Pengadaan material dan pemasangan batu armour ukuran 150 - 200 Kg/unit m3 1,409.89 276,489.74 9 Pengadaan material dan pemasangan batu armour ukuran 300 - 500 Kg/unit m3 600.00 350,770.67

10 Pengadaan material dan pemasangan Pipa PVC (AW) dia. 100 mm pada paravet m 10.00 40,000.00 11 Konstruksi pasangan batu kali sebagai pondasi pagar precast beton m3 82.00 450,000.00 12 Pengadaan material dan pemasangan kolom pagar precast 200x200x3000 mm int. 2, unit 30.00 200,000.00 13 Pengadaan material dan pemasangan pagar pelat beton precast 2400x500x t = 50 unit 120.00 275,000.00 14 Pembongkaran existing pagar beton precast m 75.00 75,000.00

Sub Total -

G Tiang Pancang dan Assesoriesnya (Abutment ESR dan Kolom Penyangga Gangway) 1 Pengadaan Tiang pancang Ø 812,8 mm, t=14 mm ( w = 276 kg/m') (TA. 2011) Kg - - 2 Pemancangan tiang pancang dia. 812.8 mm m 60.00 150,000.00 3 Pemotongan tiang, setting unit 2.00 100,000.00 4 Penyambungan tiang pancang setiap 12m unit 4.00 250,000.00 5 Ring pelat Dia=1200mm, t= 12 mm ( w = ± 59 kg/unit) unit 2.00 1,613,443.50 3,226,887.00 6 Pelat penutup tiang dia. 812.3 mm, t= 6mm ( w = ± 24 Kg/unit) unit 2.00 656,316.00 1,312,632.00 7 Bracing pengaku tiang pancang H 300 x 300 x 10/15 (w=94 Kg/m') Kg 348.00 27,346.50 9,516,582.00 8 Base plate dan angkur untuk post guard rail ( w= ± 12Kg/unit ) unit 12.00 328,158.00 3,937,896.00

Sub Total 17,993,997.00

H Pekerjaan beton dan pelengkapnya (Abutment dan Appron ESR) 1 Beton bertulang (K-300, U32) kepala tiang pancang/ pier dan abutment m3 27.00 2,806,099.78 2 Beton bertulang (K-300, U32) pengisi tiang pancang dia.812.3 mm L=2000 mm m3 2.00 4,245,262.59 3 Angkur dan base plate kolom penyangga konstruksi gangway ( w = ± 900 Kg/unit) unit 1.00 28,783,350.00 28,783,350.00 4 Angkur base plate appron ESR (w = ± 45 Kg/unit) unit 2.00 1,230,592.50 2,461,185.00 5 Pelat sudut di abutment termasuk angkurnya , digalvanis ( w = ± 20 Kg/m') m 15.00 546,930.00 8,203,950.00 6 Pengadaan dan pemasangan guard rail , post dan assesoriesnya (digalvanis) Kg 750.00 31,981.50 23,986,125.00 7 Beton bertulang retaining wall apron dan pelat lantai apron m3 20.00 2,571,330.03 8 Beton lantai kerja (K-100) t = 100 mm m3 5.00 694,243.04 9 Lapisan basecorse termasuk pekerjaan pemadatan m3 20.00 209,189.48

10 Lapisan sirtu termasuk pekerjaan pemadatan m3 15.00 173,691.08

Sub Total 63,434,610.00

I Konstruksi Gangway dan Kolom Penyangga ( ±267 m, bagian darat )

1 Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi gangway (TA. 2011)

Kg - -

2 Kg - -

3 Kg - -

4 Kg - -

5 Pengecatan dan pemasangan konstruksi gangway Kg ### 8,806.50 1,063,288,003.50 6 Pengecatan dan pemasangan konstruksi kolom penyangga Kg 26,638.000 8,806.50 234,587,547.00 7 Beton bertulang (K-300, U32) lantai gangway m3 38.00 1,698,379.19 8 Pengadaan dan pemasangan pelat bondek m2 363.00 160,371.00 58,214,673.00 9 Pengadaan dan pemasangan atap asbes dan assesoriesnya m2 727.00 78,795.00 57,283,965.00

10 m2 220.00 826,884.00 181,914,480.00

11 Elektrikal (titk lampu @ 5 m dan jaringannya) unit 53.00 350,000.00 Sub Total 1,595,288,668.50

Pengadaan, pabrikasi pengecatan dan pemasangan konstruksi kolom penyangga (TA. 2011)

Pengadaan, pabrikasi konstruksi gangway (tanpa pengecatan dan pemancangan) (TA. 2011)

Pengadaan, pabrikasi kontruksi kolom penyangga (tanpa pengecatan dan pemasangan) (TA. 2011)

Pengadaan, fabrikasi dan pemasangan fiber sheet t = 5 mm (handrail) dan asesories.

Page 58: RAB-Gang Way Dmg v Tahap II Value

No URAIAN PEKERJAAN UNITESTIMASI HARGA SATUAN JUMLAH HARGA

KUANTITAS (Rp.) (Rp.)

J Konstruksi Gangway dan Kolom Penyangga ( ±200 m, bagian laut ) 1 Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi gangway Kg 37,302.00 29,200.50 1,089,237,051.00 2 Pengadaan, pabrikasi (tanpa pengecatan dan pemasangan) (TA. 2011) Kg - - 3 Pengecatan dan pemasangan baja Kg 146,823.00 8,806.50 1,292,996,749.50 4 Pengadaan, pabrikasi pengecatan dan pemasangan konstruksi kolom penyangga Kg 43,800.00 29,200.50 1,278,981,900.00 5 Beton bertulang (K-300, U32) lantai gangway m3 88.00 3,000,000.00 6 Pengadaan dan pemasangan pelat bondek m2 735.00 160,371.00 117,872,685.00 7 Pengadaan dan pemasangan atap asbes dan assesoriesnya m2 1,593.00 78,795.00 125,520,435.00 8 Pengadaan, fabrikasi dan pemasangan fiber sheet t = 5 mm (handrail) dan asesories m2 245.00 826,884.00 202,586,580.00 9 Elektrikal (titk lampu @ 5 m dan jaringannya) unit 50.00 350,000.00

Sub Total 4,107,195,400.50

K Konstruksi Baja Apron ESR 1 Pengadaan, pabrikasi,pengecatan dan pemasangan konstruksi apron ESR (±100 m) Kg 150,000.00 29,200.50 4,380,075,000.00

Sub Total 4,380,075,000.00

L Movable Gangway 1 Konstruksi Movable Gangway ( 1set, 2unit)

a. Fixed Flatform Kg 3,600.00 Kg 3,600.00 32,445.00 116,802,000.00 b. Turning Flatform Kg 3,600.00 Kg 1,169.00 50,521.50 59,059,633.50 c. Rear Bridge Kg 1,680.00 Kg - - d. Movable Frame Kg 10,800.00 Kg - - e. Tilting Bridge Kg 6,000.00 Kg - - f. Base Frame Kg 3,600.00 Kg 3,600.00 32,445.00 116,802,000.00

2 Mekanikal dan Elektrikal ( 1 set, 2 unit ) a. Hidraulik Silinder ( 1 @ 4 unit) unit - - b. Power Pack Hidraulik Unit unit - - c. Elektrikal dan Piping set - -

Sub Total 292,663,633.50

M Elevated Side Ramp 1 Konstruksi Baja Side Ramp

a. Approach Bridge Kg - - b. Moving Bridge Kg 22,000.00 50,521.50 1,111,473,000.00 c. Ramp Bridge Kg 5,500.00 41,251.50 226,883,250.00 d. Rangka Kolom , Operating Room dan Walkway Kg 25,000.00 31,054.50 776,362,500.00 e. Base Plate , Plate 300x300xt=20, Angkur Dia.40mm, L = 500mm Kg 610.00 26,512.20 16,172,442.00 f. Bearing Plate 300 x 300 x t = 50 mm Kg 1,130.00 31,054.50 35,091,585.00

2 Mekanikal dan Elektrikal a. Hidraulik Silinder Moving Bridge ( 2 unit) unit - - b. Hidraulik Silinder Ramp Bridge ( 2 unit) unit - - c. Power Pack Hidraulik Unit unit - -

d. unit - -

e. set -

f. m -

g. Pengadaan dan pemasangan tiang lampu, lampu dan kabel jaringannya titik - 3 Pekerjaan Sipil Lainnya

a. Pelat Lantai kendaraan t = 250 mm (beton bertulang, K500) m3 - - b. Rumah mesin (4 m x 4 m) m2 - -

Sub Total 2,165,982,777.00

Elektrikal, Control Desk, panel dan Oil Piping (sus 304, sch 160) termasuk assesories dan rubber hose Unit 0.00

Pengadaan dan pemasangan lampu red flash, kabel dan assesoriesnya (1 set@ 2 unit)

Pengadaan dan pemasangan kabel listrik (power supply) termasul konduit dan assesoriesnya

Page 59: RAB-Gang Way Dmg v Tahap II Value

No URAIAN PEKERJAAN UNITESTIMASI HARGA SATUAN JUMLAH HARGA

KUANTITAS (Rp.) (Rp.)

N Shelter 1 Pengadaan dan pemasangan konstruksi baja termasuk pengecatan Kg - - 2 Pemancangan tiang pancang dia. 400 mm pondasi selter, 18 titik @ 30 m m 540.00 475,000.00 3 Pemotongan tiang pancang Unit 18.00 100,000.00 4 Penyambungan tiang pancang Unit 36.00 250,000.00

Ring pelat Dia=700mm, t= 12 mm ( w = ± 24.5 kg/unit) Unit 18.00 669,989.25 12,059,806.50 Pelat penutup tiang dia. 400 mm, t= 6mm ( w = ± 6 Kg/unit) Unit 18.00 164,079.00 2,953,422.00 Bracing pengaku tiang pancang H 300 x 200 x 8/12 (w=57Kg/m') Kg 897.75 27,346.50 24,550,320.38

5 m3 41.00 2,500,000.00

6 Beton bertulang (K-300, U32) pondasi tangga selter termasuk angkur m3 2.00 2,500,000.00 7 Angkur dan baseplate kolom penyangga bangunan selter unit 18.00 550,000.00 8 Beton bertulang (K-300, wiremesh D10) lantai selter m3 54.00 3,500,000.00 9 Pengadaan dan pemasangan lantai keramik 60x60 cm m2 419.00 85,000.00

10 Pengadaan dan pemasangan bondek m2 450.00 160,371.00 72,166,950.00

11 unit 11.00 3,388,000.00

12 unit 9.00 3,388,000.00

13 unit 10.00 2,310,000.00

14 unit 2.00 1,089,000.00

15 unit 2.00 804,375.00

16 unit 2.00 302,500.00

17 unit 2.00 3,580,500.00

18 m2 500.00 350,000.00

19 Pengadaan dan pemasangan kalsiboard termasuk finishing dan pengecatan m2 500.00 150,000.00 20 Pengadaan dan pemasangan atap corrugated metal roof termasuk perlengkapannya m2 540.00 175,000.00 21 Pengadaan dan pemasangan pintu PVC untuk toilet termasuk perlengkapannya unit 6.00 350,000.00 22 Pekerjaan dinding pasangan bata merah termasuk plesteran, acian dan pengecatan m2 132.00 95,000.00 23 Pengadaan dan pemasangan dinding keramik 20X20 cm di toilet m2 122.00 95,000.00 24 Pekerjaan plumbing dan sanitari, termasuk kloset duduk, keran dan perelngkapan lai set 1.00 1,750,000.00 25 Pekerjaan elektrikal termasuk jaringan listrik, lampu dan perlengkapan lainnya set 1.00 35,000,000.00

26 unit 1.00 15,000,000.00

Sub Total 111,730,498.88

Beton bertulang (K-300, U32) pile cap dan sbg pondasi kolom penyangga selter, 18 unit, dim.1600x1200x1200

Pengadaan dan pemasangan jendela Tipe-1 dim.2800x2200mm (rangka alumunium + Kaca dan assesoriesnyau)

Pengadaan dan pemasangan jendela Tipe-2 dim. 2800x2200mm (rangka alumunium + Kaca dan assesoriesnyuan)

Pengadaan dan pemasangan jendela Tipe-3 dim. 2800x1500mm(rangka alumunium + Kaca dan assesoriesnyau)

Pengadaan dan pemasangan jendela Tipe-4 dim.2200x900mm (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan jendela Tipe-5 dim.1625x900mm (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan jendela Tipe-6 dim. 1100x500mm (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan pintu double dim.3100x2100 (rangka alumunium + Kaca dan assesoriesnya)

Pengadaan dan pemasangan Aluminium Komposit Panel PVDF (tebal 4 mm, Al.koil 0,3 mm ) termasuk rangkam dan sealant

Pekerjaan bangunan septic tank (beton bertulang) dim. 2000x2000x3000mm termasuk kelengkapannya

Page 60: RAB-Gang Way Dmg v Tahap II Value

PERHITUNGAN PEMBESIAN

Beton Pengisi Ujung Tiang Pancang Baja K.300

Beton bertulang (K-300) pengisi tiang pancang (panjang 2.0 m / pile)No. Tulangan

18 buah tiap pile 1 18-D 25Spiral 2 D13 - 75

3 Plat t = 9 mm

Beton bertulang selimut tiang pancang

Beton bertulang (K-300) pengisi tiang pancang (panjang 2.5 m / pile)No. Tulangan

18 buah tiap pile 1 16-Ø 13Spiral 2 Ø 10 - 100

II.2 PILE CAP

SEGMEN INo. Tulangan

Luar 1 D19-200

Dalam 2 D19-200

Page 61: RAB-Gang Way Dmg v Tahap II Value

Samping 3 D19-200

Begel tengah 4 D19-200

Penahan FenderTrapesium 1 D19-200

Horizontal (mengelilingi) 2 D19-200

Horizontal Atas 3 D19-200

SEGMEN I'

SEGMEN IINo. Tulangan

Luar 1 D19-200

Dalam Atas 2 D19-200

Samping depan & belakang 3 D19-200

Bawah 4 D19-200

Begel tengah 5 D19-200

SEGMEN II'

SEGMEN IIINo. Tulangan

Luar 1 D19-200

Dalam 2 D19-200

Samping 3 D19-200

Begel tengah 4 D19-200

Penahan FenderTrapesium 1 D19-200

Horizontal (mengelilingi) 2 D19-200

Horizontal Atas 3 D19-200

Page 62: RAB-Gang Way Dmg v Tahap II Value

Multipleks Samping V = (17.5+3.5+3.5+2+4.5+2+1.5+2+4.5+2+3.5+3.5)*1.5Fender V = ((1.5*1.5)+(1.1*1.5*2)+(1.5*2))*3Bawah V = (3.5*3.5)*2+(1.5*4.5*2)+(1.5*3.5)

Kayu Bekisting 5/7 , 6/12

No Kayu

1

2

3456789

10

Total Volume Kayu Pile Cap

Page 63: RAB-Gang Way Dmg v Tahap II Value

1.00

Beton bertulang (K-300) pengisi tiang pancang (panjang 2.0 m / pile)BJ Panjang Jumlah Total Total

Panjang Berat

3.980 3.05 18.00 54.90 218.50 1.042 2.24 29.33 65.61 68.37

terpisah

Total Pembesian 286.87 kgJumlah Pile = 1 286.87 kgVolume Beton Isi Tiang 1.01 m3Rasio Besi/m3 285.36 kg/m3

Dibulatkan 1 Rasio Besi/m3 285.36 kg/m3

1.00

Beton bertulang (K-300) pengisi tiang pancang (panjang 2.5 m / pile)BJ Panjang Jumlah Total Total

Panjang Berat

1.578 3.00 16.00 48.00 75.74 0.617 2.71 25.00 67.70 41.77

Total Pembesian 117.52 kgJumlah Pile = 1 117.52 kgVolume Beton Selimut Tiang 0.72 m3Rasio Besi/m3 164.06 kg/m3

Dibulatkan 1.05 Rasio Besi/m3 172.27 kg/m3

Bekisting 7.95 m2Volume Beton Selimut Tiang 0.72 m3Rasio Bekisting/m3 11.10 m2/m3

-

BJ Panjang Jumlah Total TotalPanjang Berat

2.250 10.00 19.00 190.00 427.50

2.250 10.00 19.00 190.00 427.50

Page 64: RAB-Gang Way Dmg v Tahap II Value

2.250 14.00 9.00 126.00 283.50

2.250 1.90 57.00 108.30 243.67

2.250 7.40 9.00 66.60 149.85

2.250 5.20 9.00 46.80 105.30

2.250 4.50 3.00 13.50 30.38

Total Pembesian 1,667.70 kg

Total Pembesian 1,667.70 kg

BJ Panjang Jumlah Total TotalPanjang Berat

2.250 6.00 24.00 144.00 324.00

2.250 10.00 9.00 90.00 202.50

2.250 4.50 18.00 81.00 182.25

2.250 4.50 9.00 40.50 91.13

2.250 1.90 24.00 45.60 102.60

Total Pembesian 902.48 kg

Total Pembesian 902.48 kg

BJ Panjang Jumlah Total TotalPanjang Berat

2.250 10.00 9.00 90.00 202.50

2.250 6.00 19.00 114.00 256.50

2.250 10.00 9.00 90.00 202.50

2.250 1.90 19.00 36.10 81.23

2.250 7.40 9.00 66.60 149.85

2.250 5.20 9.00 46.80 105.30

2.250 4.50 3.00 13.50 30.38

Total Pembesian 1,028.25 kg

Page 65: RAB-Gang Way Dmg v Tahap II Value

TOTAL BESI + Wise 6,168.60 KgVolume I 39.38 m3Volume II 21.00 m3Volume III 4.50 m3Volume IV 7.09 m3

Pengurang Volume V (3.11) m3Volume Beton Pile Cap 68.86 m3Rasio Besi/m3 89.59 kg/m3 -

Dibulatkan 1.15 Rasio Besi/m3 103.03 kg/m3

(17.5+3.5+3.5+2+4.5+2+1.5+2+4.5+2+3.5+3.5)*1.5 75.00 ((1.5*1.5)+(1.1*1.5*2)+(1.5*2))*3 25.65 (3.5*3.5)*2+(1.5*4.5*2)+(1.5*3.5) 43.25

= 143.90 m2 sudah termasuk bekisting dalamRasio Multipleks/m3 2.09 m2/m3

Type Jumlah Luas Panjang Volume Pot (m3)

5/7 20.00 0.0035 1.40 0.10 5/7 16.00 0.0035 1.00 Kayu dalam utk precast5/7 16.00 0.0035 1.10 0.06 5/7 12.00 0.0035 0.80 Kayu dalam utk precast5/7 20.00 0.0035 0.70 0.05 5/7 4.00 0.0035 1.20 0.02

5/10 6.00 0.0050 1.80 0.05 6/12 2.00 0.0072 1.80 0.03 5/7 8.00 0.0035 0.90 0.03 5/7 4.00 0.0035 0.75 0.01 5/7 4.00 0.0035 1.10 0.02

6/12 2.00 0.0072 0.75 0.01

Total Volume Kayu Pile Cap 7.712

Rasio Kayu Bekisting/m3 0.112 m3/m3

Page 66: RAB-Gang Way Dmg v Tahap II Value

sudah termasuk bekisting dalam

Kayu dalam utk precast

Kayu dalam utk precast

Page 67: RAB-Gang Way Dmg v Tahap II Value

PERHITUNGAN PEMBESIAN

Beton Pengisi Ujung Tiang Pancang Baja K.300

Beton bertulang (K-300) pengisi tiang pancang (panjang 2.0 m / pile)No. Tulangan

328 buah tiap pile 1 32-D 25Spiral 2 D12 - 200

3 Plat t = 9 mm

Beton bertulang K-300 precast (2 m x 2 m x 0.15 m)

No. Tulangan

Luar 1 D13-200

Vertikal 2 D16-200

Samping 3 D16-200

Vertikal (pada 1 m atas) 4 D16-200

Beton bertulang K-300 pengisi beton precast

No. Tulangan

Luar 1 D13-200

Vertikal 2 12-D25

Luar 1 D13-200

Page 68: RAB-Gang Way Dmg v Tahap II Value

Vertikal 2 12-D25

#REF!

SEGMEN INo. Tulangan

Luar 1 D16-150

Atas 2 10-D25

Samping 3 D16-150

Bawah 4 10-D25

Begel Horizontal 5 D13-400

Begel Vertical 5 D13-25

Multipleks Samping V = (1.5+1.5)*6.2Bawah V = 2.8*6.2

Kayu Bekisting 5/7 , 6/12

No Kayu

1

Page 69: RAB-Gang Way Dmg v Tahap II Value

2

3456789

10

Total Volume Kayu Pile Cap

#REF!

No. Tulangan

Luar 1 D13-100

Atas 2 10-D25

Samping 3 D16-150

Bawah 4 10-D25

Tulanagn Penguat Tengah 4 8-D25

Begel Horizontal 5 D13-250

Begel Vertical 5 D13-25

WF dudukan bekisting 1 WF 200x100x5,5x8 mmPlat Klem 2 Plat Clamp Cincin t = 12 mm

lebar 25 cm

Multipleks Samping V = (2*2.8)+(3*2)+(2.8*2)+(3*2)

Page 70: RAB-Gang Way Dmg v Tahap II Value

Bawah V = 2.8*5.8

Kayu Bekisting 5/7 , 6/12

No Kayu

1

2

3456789

10

Total Volume Kayu Pile Cap

#REF!

No. Besi Plat

1 Plat Clamp Cincin t = 12 mmlebar 25 cm

2 Plat Dudukan

3 Pengurang Lingkaran

Page 71: RAB-Gang Way Dmg v Tahap II Value

1.00

BJ Panjang Jumlah Total TotalPanjang Berat

3.980 4.05 32.00 129.60 515.81 0.888 4.24 14.75 62.56 55.55

terpisah

Total Pembesian 571.36 kgJumlah Pile = 1 571.36 kgVolume Beton Isi Tiang 4.54 m3Rasio Besi/m3 125.82 kg/m3

Dibulatkan 1.05 Rasio Besi/m3 132.11 kg/m3

1.00

BJ Panjang Jumlah Total TotalPanjang Berat

1.042 9.80 32.00 313.60 326.77

1.560 7.45 41.00 305.45 476.50

1.560 7.45 4.00 29.80 46.49

1.560 2.50 15.00 37.50 58.50

Total Pembesian 908.26 kgJumlah Pile = 1 908.26 kgVolume Beton Precast 8.03 m3Rasio Besi/m3 113.09 kg/m3

Dibulatkan 1.05 Rasio Besi/m3 118.75 kg/m3

Bekisting 103.75 m2Volume Beton Precast 8.03 m3Rasio Bekisting/m3 12.92 m2/m3

1.00

BJ Panjang Jumlah Total TotalPanjang Berat

1.042 2.60 32.00 83.20 86.69

3.980 8.05 12.00 96.60 384.47

1.042 2.60 32.00 83.20 86.69

Page 72: RAB-Gang Way Dmg v Tahap II Value

3.980 8.05 12.00 96.60 384.47

Total Pembesian 942.32 kgJumlah Pile = 1 942.32 kgVolume Beton Pengisi Precast 8.44 m3Rasio Besi/m3 111.63 kg/m3

Dibulatkan 1.05 Rasio Besi/m3 117.21 kg/m3

Bekisting 4.00 m2Volume Beton Pengisi Precast 8.44 m3Rasio Bekisting/m3 0.47 m2/m3

-

BJ Panjang Jumlah Total TotalPanjang Berat

1.578 9.00 42.00 378.00 596.48

3.980 6.82 10.00 68.20 271.44

1.578 6.82 20.00 136.40 215.24

3.980 6.82 10.00 68.20 271.44

1.042 3.20 32.00 102.40 106.70

1.042 1.80 32.00 57.60 60.02

Total Pembesian 1,521.32 kg

TOTAL BESI + Wise 1,521.32 KgVolume Beton Cap Beam 26.04 m3Rasio Besi/m3 58.42 kg/m3 -

Dibulatkan 1.15 Rasio Besi/m3 67.19 kg/m3

18.60 17.36

= 35.96 m2 sudah termasuk bekisting dalamRasio Multipleks/m3 1.38 m2/m3

Dibulatkan 2.5 Rasio Multipleks/m3 3.45 m2/m3

Type Jumlah Luas Panjang Volume Pot (m3)

5/7 20.00 0.0035 1.40 0.10 5/7 16.00 0.0035 1.00 Kayu dalam utk precast

Page 73: RAB-Gang Way Dmg v Tahap II Value

5/7 16.00 0.0035 1.10 0.06 5/7 12.00 0.0035 0.80 Kayu dalam utk precast5/7 20.00 0.0035 0.70 0.05 5/7 4.00 0.0035 1.20 0.02

5/10 6.00 0.0050 1.80 0.05 6/12 2.00 0.0072 1.80 0.03 5/7 8.00 0.0035 0.90 0.03 5/7 4.00 0.0035 0.75 0.01 5/7 4.00 0.0035 1.10 0.02

6/12 2.00 0.0072 0.75 0.01

3.213

Rasio Kayu Bekisting/m3 0.123 m3/m3

BJ Panjang Jumlah Total TotalPanjang Berat

1.042 10.10 59.00 595.90 620.93

3.980 8.80 10.00 88.00 350.24

1.578 17.60 28.00 492.80 777.64

3.980 8.80 10.00 88.00 350.24

3.980 6.95 8.00 55.60 221.29

1.042 3.20 24.00 76.80 80.03

1.042 2.30 42.00 96.60 100.66

Total Pembesian 2,501.02 kg

TOTAL BESI + Wise 2,501.02 KgVolume Beton Pile cap 31.50 m3Rasio Besi/m3 79.40 kg/m3 -

Dibulatkan 1.2 Rasio Besi/m3 95.28 kg/m3

21.33 6 2 12 256.00 kg 7,850.00 5.60 0.10 0.01 39.55 kg

295.55 kgVolume Beton Pile cap 31.50 m3Rasio WF & Plat/m3 9.38 kg/m3

Dibulatkan 1.1 Rasio WF & Plat/m3 10.32 kg/m3Pemakaian 2.00 Rasio WF & Plat/m3 5.16 kg/m3

23.2

Page 74: RAB-Gang Way Dmg v Tahap II Value

16.24

= 39.44 m2 sudah termasuk bekisting dalamRasio Multipleks/m3 1.25 m2/m3

Dibulatkan 2.5 Rasio Multipleks/m3 3.13 m2/m3

Type Jumlah Luas Panjang Volume Pot (m3)

5/7 20.00 0.0035 1.40 0.10 5/7 16.00 0.0035 1.00 Kayu dalam utk precast5/7 16.00 0.0035 1.10 0.06 5/7 12.00 0.0035 0.80 Kayu dalam utk precast5/7 20.00 0.0035 0.70 0.05 5/7 4.00 0.0035 1.20 0.02

5/10 6.00 0.0050 1.80 0.05 6/12 2.00 0.0072 1.80 0.03 5/7 8.00 0.0035 0.90 0.03 5/7 4.00 0.0035 0.75 0.01 5/7 4.00 0.0035 1.10 0.02

6/12 2.00 0.0072 0.75 0.01

3.213

Rasio Kayu Bekisting/m3 0.102 m3/m3

1.00

BJ Panjang Lebar Volume Totalm m3 Berat

7,850.00 5.60 0.25 0.02 131.84

7,850.00 2.00 2.00 0.05 376.80

7,850.00 (0.02) (145.01)

Total Pembesian 363.63 kg

4,545,358.45

Page 75: RAB-Gang Way Dmg v Tahap II Value

sudah termasuk bekisting dalam

Kayu dalam utk precast

Page 76: RAB-Gang Way Dmg v Tahap II Value

Kayu dalam utk precast

Page 77: RAB-Gang Way Dmg v Tahap II Value

sudah termasuk bekisting dalam

Kayu dalam utk precast

Kayu dalam utk precast

Page 78: RAB-Gang Way Dmg v Tahap II Value

Rasio BekistingSelimut Tiang Ø 609 mm Keliling Luar 2.542 m'

Panjang (coba) 1.000 m'Luas 2.542 m2

VolumeLuas Luar 0.514 m2Luas Dalam 0.291 m2Selisih 0.223 m2Panjang (coba) 1.000 m'

Volume / 1 m' 0.223 m3

Rasio Bekisting 11.410 m2/m3

Misal P = 1.5 m 3.812 m2Klem 2.000 BuahRasio Klem 0.525 Buah / m2

Selimut Tiang Ø 809 mm Keliling Luar 3.170 m'Panjang (coba) 1.000 m'Luas 3.170 m2

VolumeLuas Luar 0.800 m2Luas Dalam 0.514 m2Selisih 0.286 m2Panjang (coba) 1.000 m'

Volume / 1 m' 0.286 m3

Rasio Bekisting 11.100 m2/m3